CN106638697A - 钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 - Google Patents
钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 Download PDFInfo
- Publication number
- CN106638697A CN106638697A CN201610976580.7A CN201610976580A CN106638697A CN 106638697 A CN106638697 A CN 106638697A CN 201610976580 A CN201610976580 A CN 201610976580A CN 106638697 A CN106638697 A CN 106638697A
- Authority
- CN
- China
- Prior art keywords
- formwork
- concrete
- internal model
- inspection well
- cast
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/12—Manhole shafts; Other inspection or access chambers; Accessories therefor
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
本发明公开了一种钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法,包括有以下施工步骤:先安装内模:检查井钢筋绑扎完成及底板混凝土浇筑完成,在混凝土底板上正确定出内模边线,沿边线井壁内侧采用电钻钻孔并插入钢筋头,沿中心垂直插入4根钢筋头,用来定位内模位置,内模采用2块半圆轻质木模,在平坦地面拼装成圆形,沿垂直拼缝对撑处采用紧绳器对拉。内模板再外拼装完成后,人工搬运放至井室内固定;本发明采取先订制半圆形轻质木模板再由人工现场搬运安装,使排水检车井施工较为快速,钢筋混凝土现浇圆形排水检查井模板安装采用钢模板或窄条木模拼接。
Description
技术领域
本发明涉及钢筋混凝土现浇排水检查井领域,具体属于钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法。
背景技术
一般市政钢筋混凝土现浇圆形排水检查井采用钢模板或窄条木模拼接,钢模板自重较大,人工无法搬运,需吊装机械配合,拼接安装较为不便;木模切成窄条拼装成圆形模板,拼缝较大,容易造成漏浆,且几何尺寸不易控制。
随着我国城乡建设的步伐加快,环境污染问题也较为严重。为防止市政排水系统污水渗漏,需加大排水检查井的施工防渗要求。钢筋混凝土现浇排水检查井采取一次浇筑成型方法,无二次施工接缝,与排水管道紧密结合,渗水现象能得到有效的控制。
发明内容
本发明的目的是提供一种钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法,采取先订制半圆形轻质木模板再由人工现场搬运安装,使排水检车井施工较为快速,钢筋混凝土现浇圆形排水检查井模板安装采用钢模板或窄条木模拼接。
本发明的技术方案如下:
一种钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法,包括有以下施工步骤:
1、模板安装
(1)先安装内模:检查井钢筋绑扎完成及底板混凝土浇筑完成,在底板混凝土上正确定出内模边线,沿边线井壁内侧采用电钻钻孔并插入钢筋头,沿中心垂直插入4根钢筋头,用来定位内模位置,内模采用2块半圆轻质木模,在平坦地面拼装成圆形,内部采用2*4cm方木十字对撑,十字对撑分别设置在模板拼缝处、垂直于模板拼缝处,沿垂直拼缝对撑处采用紧绳器对拉,内模板再外拼装完成后,人工搬运放至井室内固定;
(2)后安装外模:内模完成后,先用准备好的与井室壁厚度相同的混凝土预制条定位外模与内模的相对位置,外模板人工搬运安装就位后,在外侧采用宽30mm、厚2mm的钢带外抱箍固定,全部安装完成后,模板与管材之间的接缝采用泡沫剂进行封堵,防止漏浆;
2、模板拆除
(1)先拆除外模:混凝土浇筑完成后,拆模龄期不小于24小时,将外抱箍螺丝直接拧松,去除抱箍,外模板人工直接搬至平坦地面;
(2)后拆除内模:内模拆除由上至下将紧绳器、十字撑依次拆除,用撬棍沿模板拼缝一侧由上将模板之间撬错口,用大头楔抵塞,依次至下将2块模板分离,分别人工搬至地面。
本发明的有益技术效果如下:
1、该方法解决常规排水检查井防渗不足的问题。
2、模板质地轻便,搬运安装无需机械配合。
3、安装加固操作方便。
4、保证几何尺寸,无漏浆现象。
具体实施方式
一种钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法,包括有以下施工步骤:
1、模板安装
(1)先安装内模:检查井钢筋绑扎完成及底板混凝土浇筑完成,在底板混凝土上正确定出内模边线,沿边线井壁内侧采用电钻钻孔并插入钢筋头,沿中心垂直插入4根钢筋头,用来定位内模位置,内模采用2块半圆轻质木模,在平坦地面拼装成圆形,内部采用2*4cm方木十字对撑,十字对撑分别设置在模板拼缝处、垂直于模板拼缝处,沿垂直拼缝对撑处采用紧绳器对拉,内模板再外拼装完成后,人工搬运放至井室内固定;
(2)后安装外模:内模完成后,先用准备好的与井室壁厚度相同的混凝土预制条定位外模与内模的相对位置,外模板人工搬运安装就位后,在外侧采用宽30mm、厚2mm的钢带外抱箍固定,全部安装完成后,模板与管材之间的接缝采用泡沫剂进行封堵,防止漏浆;
2、模板拆除
(1)先拆除外模:混凝土浇筑完成后,拆模龄期不小于24小时,将外抱箍螺丝直接拧松,去除抱箍,外模板人工直接搬至平坦地面;
(2)后拆除内模:内模拆除由上至下将紧绳器、十字撑依次拆除,用撬棍沿模板拼缝一侧由上将模板之间撬错口,用大头楔抵塞,依次至下将2块模板分离,分别人工搬至地面。
Claims (1)
1.一种钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法,其特征在于,包括有以下施工步骤:
1、模板安装
(1)先安装内模:检查井钢筋绑扎完成及底板混凝土浇筑完成,在底板混凝土上正确定出内模边线,沿边线井壁内侧采用电钻钻孔并插入钢筋头,沿中心垂直插入4根钢筋头,用来定位内模位置,内模采用2块半圆轻质木模,在平坦地面拼装成圆形,内部采用2*4cm方木十字对撑,十字对撑分别设置在模板拼缝处、垂直于模板拼缝处,沿垂直拼缝对撑处采用紧绳器对拉,内模板再外拼装完成后,人工搬运放至井室内固定;
(2)后安装外模:内模完成后,先用准备好的与井室壁厚度相同的混凝土预制条定位外模与内模的相对位置,外模板人工搬运安装就位后,在外侧采用宽30mm、厚2mm的钢带外抱箍固定,全部安装完成后,模板与管材之间的接缝采用泡沫剂进行封堵,防止漏浆;
2、模板拆除
(1)先拆除外模:混凝土浇筑完成后,拆模龄期不小于24小时,将外抱箍螺丝直接拧松,去除抱箍,外模板人工直接搬至平坦地面;
(2)后拆除内模:内模拆除由上至下将紧绳器、十字撑依次拆除,用撬棍沿模板拼缝一侧由上将模板之间撬错口,用大头楔抵塞,依次至下将2块模板分离,分别人工搬至地面。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610976580.7A CN106638697A (zh) | 2016-11-08 | 2016-11-08 | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610976580.7A CN106638697A (zh) | 2016-11-08 | 2016-11-08 | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106638697A true CN106638697A (zh) | 2017-05-10 |
Family
ID=58805280
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610976580.7A Pending CN106638697A (zh) | 2016-11-08 | 2016-11-08 | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106638697A (zh) |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653252A (zh) * | 2019-01-08 | 2019-04-19 | 湖南省第五工程有限公司 | 一种圆形现浇井室钢模板及施工方法 |
CN109826233A (zh) * | 2019-03-05 | 2019-05-31 | 车明凤 | 一种小直径观测井定型钢模板浇筑施工方法 |
CN111074943A (zh) * | 2020-01-10 | 2020-04-28 | 广西建工集团联合建设有限公司 | 一种检查井定型化钢模整体现浇施工方法 |
CN111894106A (zh) * | 2020-08-11 | 2020-11-06 | 安徽兴浩建设有限公司 | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 |
CN111910684A (zh) * | 2020-08-18 | 2020-11-10 | 安徽铭安建设工程有限公司 | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工系统及方法 |
CN112342998A (zh) * | 2020-10-22 | 2021-02-09 | 湖南柿竹园有色金属有限责任公司 | 一种无砂混凝土管井解决尾矿库堆积坝积水方法 |
CN112878462A (zh) * | 2021-01-13 | 2021-06-01 | 广州市第三市政工程有限公司 | 一种圆形检查井模板的施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101691751A (zh) * | 2009-08-31 | 2010-04-07 | 中建三局第三建设工程有限责任公司 | 超长人工挖孔桩穿越溶洞施工方法及穿越溶洞的超长桩 |
CN202164698U (zh) * | 2011-07-29 | 2012-03-14 | 济南黄河路桥工程公司 | 污水检查井钢模 |
CN103088844A (zh) * | 2013-03-04 | 2013-05-08 | 济南城建集团有限公司 | 钢筋混凝土检查井整体预制吊装施工方法 |
CN203878615U (zh) * | 2014-05-30 | 2014-10-15 | 中国建筑第八工程局有限公司 | 检查井筒轻型组合式定型钢模板 |
-
2016
- 2016-11-08 CN CN201610976580.7A patent/CN106638697A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101691751A (zh) * | 2009-08-31 | 2010-04-07 | 中建三局第三建设工程有限责任公司 | 超长人工挖孔桩穿越溶洞施工方法及穿越溶洞的超长桩 |
CN202164698U (zh) * | 2011-07-29 | 2012-03-14 | 济南黄河路桥工程公司 | 污水检查井钢模 |
CN103088844A (zh) * | 2013-03-04 | 2013-05-08 | 济南城建集团有限公司 | 钢筋混凝土检查井整体预制吊装施工方法 |
CN203878615U (zh) * | 2014-05-30 | 2014-10-15 | 中国建筑第八工程局有限公司 | 检查井筒轻型组合式定型钢模板 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109653252A (zh) * | 2019-01-08 | 2019-04-19 | 湖南省第五工程有限公司 | 一种圆形现浇井室钢模板及施工方法 |
CN109826233A (zh) * | 2019-03-05 | 2019-05-31 | 车明凤 | 一种小直径观测井定型钢模板浇筑施工方法 |
CN111074943A (zh) * | 2020-01-10 | 2020-04-28 | 广西建工集团联合建设有限公司 | 一种检查井定型化钢模整体现浇施工方法 |
CN111894106A (zh) * | 2020-08-11 | 2020-11-06 | 安徽兴浩建设有限公司 | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 |
CN111894106B (zh) * | 2020-08-11 | 2021-07-20 | 安徽兴浩建设有限公司 | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 |
CN111910684A (zh) * | 2020-08-18 | 2020-11-10 | 安徽铭安建设工程有限公司 | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工系统及方法 |
CN112342998A (zh) * | 2020-10-22 | 2021-02-09 | 湖南柿竹园有色金属有限责任公司 | 一种无砂混凝土管井解决尾矿库堆积坝积水方法 |
CN112878462A (zh) * | 2021-01-13 | 2021-06-01 | 广州市第三市政工程有限公司 | 一种圆形检查井模板的施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106638697A (zh) | 钢筋混凝土现浇圆形排水检查井轻质模板快速施工方法 | |
CN102758451B (zh) | 混凝土电缆沟施工工艺 | |
CN107130791A (zh) | 组合铝合金模板用于装配式混凝土预制结构的施工方法 | |
CN103422674A (zh) | 装配式混凝土结构现浇段混凝土施工方法 | |
CN104652815A (zh) | 一种厨卫间止水反梁浇筑的施工方法 | |
CN107893529A (zh) | 适用于深基坑地下室外墙pc模板体系及其施工方法 | |
CN102444285A (zh) | 一种地下室钢筋混凝土外墙的制作方法 | |
CN108755972B (zh) | 预制件用垫脚及其使用方法 | |
CN106113230B (zh) | 用于梯段预制的非定型、可周转模板体系及其施工方法 | |
CN103568109A (zh) | 一种预制混凝土空心构件成孔方法 | |
CN104153573B (zh) | V型圆柱混凝土的浇筑模具及施工方法 | |
CN110952995A (zh) | 一种外接式洞门后浇环梁施工方法 | |
CN207177286U (zh) | 装配式剪力墙预留后加区域模具 | |
CN106337530B (zh) | 一种框架梁施工缝封堵的施工方法 | |
CN105804396A (zh) | 一种非定型、可周转模板体系预制楼梯梯段以及施工工法 | |
CN106930391B (zh) | 无模施工顶板现浇排水渠结构及施工方法 | |
CN205476468U (zh) | 一种非定型、可周转模板体系预制楼梯梯段模板 | |
CN112878462A (zh) | 一种圆形检查井模板的施工方法 | |
CN214220178U (zh) | 楼面挡水条一次成型的预制免拆侧模及可调节支撑系统 | |
CN107060173A (zh) | 清水混凝土华夫板结构孔内早拆模施工方法 | |
CN210552011U (zh) | 一种带混凝土养护功能的预制楼梯模具 | |
CN112814041A (zh) | 一种地下外墙超前止水后浇带免拆模板及施工方法 | |
CN206957201U (zh) | 清水混凝土华夫板结构孔内早拆模 | |
CN204238244U (zh) | 深基坑施工结构 | |
CN111576658A (zh) | 一种装配式地下室外墙后浇带保护墙施工工法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170510 |