CN106284997A - 钢筋混凝土烟囱的大钢模整体提升施工方法 - Google Patents

钢筋混凝土烟囱的大钢模整体提升施工方法 Download PDF

Info

Publication number
CN106284997A
CN106284997A CN201510279628.4A CN201510279628A CN106284997A CN 106284997 A CN106284997 A CN 106284997A CN 201510279628 A CN201510279628 A CN 201510279628A CN 106284997 A CN106284997 A CN 106284997A
Authority
CN
China
Prior art keywords
steel
chimney
construction
wire rope
template
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510279628.4A
Other languages
English (en)
Other versions
CN106284997B (zh
Inventor
林锡森
王争
凌香宝
袁鹏辉
王欣
张志坤
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Original Assignee
China MCC20 Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201510279628.4A priority Critical patent/CN106284997B/zh
Publication of CN106284997A publication Critical patent/CN106284997A/zh
Application granted granted Critical
Publication of CN106284997B publication Critical patent/CN106284997B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明涉及烟囱施工方法。一种钢筋混凝土烟囱的大钢模整体提升施工方法,它包括:步骤一,根据筒体结构放线定位,在烟囱基础底板上搭设满堂脚手架;在操作平台中间位置留出方孔,作为吊篮或吊桶的上、下料通道;步骤二,安装垂直运输设施;步骤三,冷轧大钢模板安装;步骤四,冷轧大钢模板安装后,在钢丝绳端部安装钢丝绳紧固器,钢丝绳在紧固器上一端做成固定端,一端为活动端;步骤五,冷轧大钢模板整体拆卸提升;步骤六,按照传统施工工艺绑扎筒壁钢筋、埋设件、砌筑耐火砖,安放隔热层,逐层浇筑混凝土,直至完成施工。本发明简化了提升设备,减少高空作业,提高施工效率。

Description

钢筋混凝土烟囱的大钢模整体提升施工方法
技术领域
本发明涉及烟囱,尤其涉及钢筋混凝土烟囱的大钢模施工方法。
背景技术
工业建设中使用的烟囱包括砖烟囱、钢筋混凝土烟囱以及钢烟囱。其中钢筋混凝土烟囱是指多用于高度超过50米的烟囱,具有抗风、抗震性能好,施工简便,维修量小等优点,因此较广泛应用于工业建设中。
目前,钢筋混凝土烟囱的传统施工方法,主要有坚井架移置模板施工法和无井架夜压滑模施工法。这施工工艺需要有较繁杂的提升设施,而操作平台需延伸出筒壁且进行提升,混凝土筒壁施工时还需要悬挂内外施工吊架、倒模施工需投入多套模板,同时筒壁和内衬需分开先后进行施工,施工工期较长等一系列缺点。
发明内容
本发明在解决上述钢筋混凝土烟囱施工方法的缺陷,提供一种钢筋混凝土烟囱的大钢模整体提升施工方法。本发明简化了提升设备,减少高空作业,提高施工效率。
本发明是这样实现的:一种钢筋混凝土烟囱的大钢模整体提升施工方法,它包括:
步骤一,根据筒体结构放线定位,在烟囱基础底板上搭设满堂脚手架;满堂脚手架内施工层位置满铺木跳板作为简易操作平台;在操作平台中间位置留出方孔,作为吊篮或吊桶的上、下料通道;
步骤二,安装垂直运输设施:烟囱内垂直提升设备采用卷扬机,配钢丝绳,通过内吊桶或吊篮上、下料;钢筋由井架上的拔杆进行垂直运输;
步骤三,冷轧大钢模板安装:沿烟囱外径一次组装一套定制冷轧大钢模板作为外模,外模板采用钢丝绳、穿绳耳和紧固器进行收紧固定,模板按烟囱外壁收分度加工成均分的四组,每组均在两面侧边留出收分模板,每组内模板之间焊接牢固;在每组模板的上部焊接钢筋挂钩,作为紧丝器提升挂钩;在每张冷轧钢板模上近连接缝处,焊两列穿钢丝绳的穿绳耳;按拼装顺序将四组预拼装好的模板采用钢丝绳串联就位,每节模板钢丝绳间距为150~170mm,每浇筑层为12道;
步骤四,冷轧大钢模板安装后,在钢丝绳端部安装钢丝绳紧固器,钢丝绳在紧固器上一端做成固定端,一端为活动端;以后每次只对活动端进行紧固或松驰,就可完成模板的固定和拆卸工作;
步骤五,冷轧大钢模板整体拆卸提升:提升采用提升支架配合紧丝器来完成,提升支架和紧丝器沿筒壁周边均匀分布;提升支架采用钢筋焊接成三角形提升支架,将提升支架绑扎在施工层上方的筒壁钢筋上,将紧丝器悬挂固定在提升支架上,利用紧丝器的铁钩钩住钢模上的钢筋挂钩;待新浇筑的混凝土达到拆模条件后,施工人员拧动钢丝绳紧固器松弛钢模板支撑结构,然后通过操作紧丝器来逐步均匀提升钢模;
步骤六,按照传统施工工艺绑扎筒壁钢筋、埋设件、砌筑耐火砖,安放隔热层,逐层浇筑混凝土,直至完成施工。
所述的钢筋混凝土烟囱的大钢模整体提升施工方法,所述步骤一当中的操作平台共分为两层,上层为砌内衬墙、绑扎钢筋、提升模板、支设模板、浇混凝土施工用,下层为安全防护加固层。
所述的钢筋混凝土烟囱的大钢模整体提升施工方法,所述步骤四当中的钢丝绳固定端的钢丝绳与螺杆形成死结,活动端通过紧固器的螺栓拧紧,固定紧箍钢丝绳。
本发明沿烟囱外径一次组装一套1m(宽)*2m(高)定制冷轧大钢模板作为外模,采用耐火砖内衬墙作为内侧模板。外模板采用钢丝绳、穿绳耳和紧固器进行收紧固定,模板按烟囱外壁收分度加工成均分的四组,每组均在两面侧边留出收分模板,每组内模板之间焊接牢固;在每组模板的上部焊接钢筋挂钩,作为紧丝器提升挂钩。通过紧丝器及其简易提升支架进行大钢模整体提升;逐节完成整个烟囱筒壁外模板提升、安装、拆卸以及混凝土浇筑工作。同时烟囱筒身之内搭设满堂脚手架,满堂架内施工层顶部设简易操作平台,作为砌内衬墙、隔热板、钢筋、模板、混凝土施工及垂直运输的平台。材料垂直运输设一个吊篮,由1台3吨卷扬机提升,钢筋由井架上的拔杆进行垂直运输(1吨卷扬机);施工人员通过外爬梯上下施工平台。
与现有的施工方法相比,本发明简化了提升系统:该施工方法无需繁杂的提升设施,提升系统仅对外模进行提升,因此无需投入千斤顶、手动葫芦等大量提升设施;
简化了操作平台:操作平台无需延伸出筒壁,也无需提升系统,降低了操作平台的负荷,只需搭设简易的操作平台即可;
避免了筒壁的内外吊架施工,只采用简易的内操作平台,减少高空作业,大大减少施工过程不安全因素;
外模采用2mm厚冷轧薄板,能有效提高烟囱筒壁观感质量;
该方法主张用采用烟囱内衬耐火砖砌体取代混凝土筒壁内模板,大大减少钢模及架管等周转材料的使用,减少内模板支撑系统工作量,降低施工成本,缩短工程施工周期;
综上,本发明的该施工方法,能实现了筒壁、内衬、隔热层及爬梯钢平台“四同步”施工,大大提高了工效,缩短了施工工期。
具体实施方式
一种钢筋混凝土烟囱的大钢模整体提升施工方法,它包括:
1.根据筒体结构放线定位,在烟囱基础底板上搭设满堂脚手架。
2.满堂架内施工层位置满铺木跳板作为简易操作平台,操作平台共分为两层,上层为砌内衬墙、绑扎钢筋、提升模板、支设模板、浇混凝土等施工用,下层为安全防护加固层。在操作平台中间位置留出0.9m×0.9m的方孔,作为吊篮或吊桶的上、下料通道。
3.安装垂直运输设施:烟囱内垂直提升设备采用3t卷扬机,配直径16mm钢丝绳,通过内吊桶或吊篮上、下料。钢筋由井架上的拔杆进行垂直运输。
4.冷轧大钢模安装:沿烟囱外径一次组装一套1m(宽)*2m(高)定制冷轧大钢模板作为外模,外模板采用钢丝绳、穿绳耳和紧固器进行收紧固定,模板按烟囱外壁收分度加工成均分的四组,每组均在两面侧边留出收分模板,每组内模板之间焊接牢固;在每组模板的上部焊接钢筋挂钩,作为紧丝器提升挂钩。在每张冷轧钢板模上距连接缝100mm处,焊两列穿钢丝绳的穿绳耳。按拼装顺序将四组预拼装好的模板采用钢丝绳串联就位,每节模板钢丝绳间距为150~170mm之间,每浇筑层约为12道,钢丝绳直径为6.5mm。
初次模板安装后,在钢丝绳端部安装钢丝绳紧固器,钢丝绳在紧固器上一端做成固定端,一端为活动端。固定端的钢丝绳与螺杆形成死结,活动端通过紧固器的螺栓拧紧,固定紧箍钢丝绳,以后每次则对活动端进行紧固或松驰,就可完成模板的固定和拆卸工作。
5.冷轧大钢模整体拆卸提升:模板的提升采用提升支架配合紧丝器来完成,提升支架和紧丝器沿筒壁周边均匀分布,间距为2m。提升支架采用Φ22钢筋焊接成三角形提升支架,将提升支架绑扎在施工层上方的筒壁钢筋上,将紧丝器(其起重能力达1.0t)悬挂固定在提升支架上,利用紧丝器的铁钩钩住钢模上的钢筋挂钩。待新浇筑的混凝土达到拆模条件后,施工人员拧动钢丝绳紧固器松弛钢模板支撑结构,然后通过操作紧丝器来逐步均匀提升钢模。
6.按照传统施工工艺绑扎筒壁钢筋、埋设件、砌筑耐火砖,安放隔热层,逐层浇筑混凝土。

Claims (3)

1.一种钢筋混凝土烟囱的大钢模整体提升施工方法,其特征在于,它包括:
步骤一,根据筒体结构放线定位,在烟囱基础底板上搭设满堂脚手架;满堂脚手架内施工层位置满铺木跳板作为简易操作平台;在操作平台中间位置留出方孔,作为吊篮或吊桶的上、下料通道;
步骤二,安装垂直运输设施:烟囱内垂直提升设备采用卷扬机,配钢丝绳,通过内吊桶或吊篮上、下料;钢筋由井架上的拔杆进行垂直运输;
步骤三,冷轧大钢模板安装:沿烟囱外径一次组装一套定制冷轧大钢模板作为外模,外模板采用钢丝绳、穿绳耳和紧固器进行收紧固定,模板按烟囱外壁收分度加工成均分的四组,每组均在两面侧边留出收分模板,每组内模板之间焊接牢固;在每组模板的上部焊接钢筋挂钩,作为紧丝器提升挂钩;在每张冷轧钢板模上近连接缝处,焊两列穿钢丝绳的穿绳耳;按拼装顺序将四组预拼装好的模板采用钢丝绳串联就位,每节模板钢丝绳间距为150~170mm,每浇筑层为12道;
步骤四,冷轧大钢模板安装后,在钢丝绳端部安装钢丝绳紧固器,钢丝绳在紧固器上一端做成固定端,一端为活动端;以后每次只对活动端进行紧固或松驰,就可完成模板的固定和拆卸工作;
步骤五,冷轧大钢模板整体拆卸提升:提升采用提升支架配合紧丝器来完成,提升支架和紧丝器沿筒壁周边均匀分布;提升支架采用钢筋焊接成三角形提升支架,将提升支架绑扎在施工层上方的筒壁钢筋上,将紧丝器悬挂固定在提升支架上,利用紧丝器的铁钩钩住钢模上的钢筋挂钩;待新浇筑的混凝土达到拆模条件后,施工人员拧动钢丝绳紧固器松弛钢模板支撑结构,然后通过操作紧丝器来逐步均匀提升钢模;
步骤六,按照传统施工工艺绑扎筒壁钢筋、埋设件、砌筑耐火砖,安放隔热层,逐层浇筑混凝土,直至完成施工。
2.根据权利要求1所述的钢筋混凝土烟囱的大钢模整体提升施工方法,其特征在于,所述步骤一当中的操作平台共分为两层,上层为砌内衬墙、绑扎钢筋、提升模板、支设模板、浇混凝土施工用,下层为安全防护加固层。
3.根据权利要求1所述的钢筋混凝土烟囱的大钢模整体提升施工方法,其特征在于,所述步骤四当中的钢丝绳固定端的钢丝绳与螺杆形成死结,活动端通过紧固器的螺栓拧紧,固定紧箍钢丝绳。
CN201510279628.4A 2015-05-28 2015-05-28 钢筋混凝土烟囱的大钢模整体提升施工方法 Active CN106284997B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510279628.4A CN106284997B (zh) 2015-05-28 2015-05-28 钢筋混凝土烟囱的大钢模整体提升施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510279628.4A CN106284997B (zh) 2015-05-28 2015-05-28 钢筋混凝土烟囱的大钢模整体提升施工方法

Publications (2)

Publication Number Publication Date
CN106284997A true CN106284997A (zh) 2017-01-04
CN106284997B CN106284997B (zh) 2019-06-14

Family

ID=57634248

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510279628.4A Active CN106284997B (zh) 2015-05-28 2015-05-28 钢筋混凝土烟囱的大钢模整体提升施工方法

Country Status (1)

Country Link
CN (1) CN106284997B (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812307A (zh) * 2017-03-31 2017-06-09 中国化学工程第七建设有限公司 一种钢筋混凝土结构的施工装置
CN109736625A (zh) * 2019-03-01 2019-05-10 中国二十二冶集团有限公司 高大混凝土烟囱外筒壁的加固装置及加固方法
CN110409803A (zh) * 2019-08-07 2019-11-05 中国电建集团山东电力建设有限公司 拆卸液压提模装置中心鼓圈的吊装方法

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1038330A (zh) * 1988-02-26 1989-12-27 诺尔洛制钢股份有限公司 封闭支架
CN1078286A (zh) * 1993-03-20 1993-11-10 山西省电力公司电力建设三公司 混凝土筒体新型建筑法及设施
CN2212037Y (zh) * 1994-12-20 1995-11-08 中国建筑第三工程局第二建筑安装工程公司 液压自升式多功能高速井架
CN1664273A (zh) * 2005-03-10 2005-09-07 深圳市特辰升降架工程有限公司 一种整体提升爬模平台系统及其操作方法
RU2276244C2 (ru) * 2004-07-08 2006-05-10 Нижегородский государственный архитектурно-строительный университет Подвижная опалубка с механизированным комплексом для возведения междуэтажных перекрытий
CN101225708A (zh) * 2007-01-19 2008-07-23 兖州煤业榆林能化有限公司 一种烟囱的上滑下砌无井架液压滑动模板安装方法
CN101725271A (zh) * 2009-11-17 2010-06-09 江苏南通三建集团有限公司 一种钢筋混凝土烟囱的快速施工方法
CN102677890A (zh) * 2012-04-23 2012-09-19 中化二建集团第三安装工程有限公司 烟囱建筑模板提升装置及施工方法
CN202831617U (zh) * 2012-10-23 2013-03-27 中国葛洲坝集团股份有限公司 一种大型整体式钢模板
US20160083957A1 (en) * 2013-06-27 2016-03-24 Ihi Corporation Method for constructing cylindrical tank

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1038330A (zh) * 1988-02-26 1989-12-27 诺尔洛制钢股份有限公司 封闭支架
CN1078286A (zh) * 1993-03-20 1993-11-10 山西省电力公司电力建设三公司 混凝土筒体新型建筑法及设施
CN2212037Y (zh) * 1994-12-20 1995-11-08 中国建筑第三工程局第二建筑安装工程公司 液压自升式多功能高速井架
RU2276244C2 (ru) * 2004-07-08 2006-05-10 Нижегородский государственный архитектурно-строительный университет Подвижная опалубка с механизированным комплексом для возведения междуэтажных перекрытий
CN1664273A (zh) * 2005-03-10 2005-09-07 深圳市特辰升降架工程有限公司 一种整体提升爬模平台系统及其操作方法
CN101225708A (zh) * 2007-01-19 2008-07-23 兖州煤业榆林能化有限公司 一种烟囱的上滑下砌无井架液压滑动模板安装方法
CN101725271A (zh) * 2009-11-17 2010-06-09 江苏南通三建集团有限公司 一种钢筋混凝土烟囱的快速施工方法
CN102677890A (zh) * 2012-04-23 2012-09-19 中化二建集团第三安装工程有限公司 烟囱建筑模板提升装置及施工方法
CN202831617U (zh) * 2012-10-23 2013-03-27 中国葛洲坝集团股份有限公司 一种大型整体式钢模板
US20160083957A1 (en) * 2013-06-27 2016-03-24 Ihi Corporation Method for constructing cylindrical tank

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106812307A (zh) * 2017-03-31 2017-06-09 中国化学工程第七建设有限公司 一种钢筋混凝土结构的施工装置
CN109736625A (zh) * 2019-03-01 2019-05-10 中国二十二冶集团有限公司 高大混凝土烟囱外筒壁的加固装置及加固方法
CN110409803A (zh) * 2019-08-07 2019-11-05 中国电建集团山东电力建设有限公司 拆卸液压提模装置中心鼓圈的吊装方法
CN110409803B (zh) * 2019-08-07 2022-02-01 中国电建集团山东电力建设有限公司 拆卸液压提模装置中心鼓圈的吊装方法

Also Published As

Publication number Publication date
CN106284997B (zh) 2019-06-14

Similar Documents

Publication Publication Date Title
CN103104091B (zh) 滑模整体提升平台及施工方法
CN101725271B (zh) 一种钢筋混凝土烟囱的快速施工方法
CN106120568A (zh) 跨河大桥主桥墩二次锁定临时固结结构及施工方法
CN104712143A (zh) 一种圆形钢筋混凝土烟囱筒壁倒模施工方法
CN108360380A (zh) 一种桥梁墩柱施工作业平台及其施工方法
CN114150766B (zh) 一种预制钢筋混凝土柱连接节点及其施工方法
CN102661019A (zh) 建筑物外墙保温装饰一体化施工方法
CN102444310A (zh) 一种模板提升法施工砼烟囱筒体的方法
CN107091007B (zh) 钢筋混凝土烟囱内砌外提模板施工工法
CN106284997A (zh) 钢筋混凝土烟囱的大钢模整体提升施工方法
CN112832368A (zh) 一种超高处悬挑梁快速施工工艺
CN108862081A (zh) 一种手拉葫芦起重架及在梁钢筋保护层厚度调节中的应用
CN203654702U (zh) 一种钢筋混凝土烟囱施工操作平台
CN105178503B (zh) 一种预制外挂保温墙板
CN113833263A (zh) 一种用于框架柱的整体灯笼式支架循环吊装施工方法
CN105370027B (zh) 高层悬空结构中整体提升支撑钢平台结构的施工方法
CN106284086B (zh) 一种利用电动爬模装置浇注高墩柱的方法
CN109457814B (zh) 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法
CN102605988B (zh) 烟囱内衬外砼同步施工方法
CN205329640U (zh) 一种“t”支撑对称滑升模板施工结构
CN210597742U (zh) 一种剪力墙
CN112554534A (zh) 一种大型筒仓穹顶砼的施工方法
CN107313591B (zh) 千吨级水塔施工方法
RU2405897C1 (ru) Способ строительства жаропрочных высотных железобетонных труб с малым выходным диаметром с большой толщиной теплоизоляции и футеровки из штучных материалов
KR100973503B1 (ko) 다층 1절 철근 선조립체를 이용한 rc 수직부재 시공방법

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant