CN104895335A - 一种吊柱的安装方法 - Google Patents

一种吊柱的安装方法 Download PDF

Info

Publication number
CN104895335A
CN104895335A CN201510249615.2A CN201510249615A CN104895335A CN 104895335 A CN104895335 A CN 104895335A CN 201510249615 A CN201510249615 A CN 201510249615A CN 104895335 A CN104895335 A CN 104895335A
Authority
CN
China
Prior art keywords
davit
pillar
base post
hanging
bolt
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510249615.2A
Other languages
English (en)
Other versions
CN104895335B (zh
Inventor
冯锋
姚钊
冉旭勇
甘霖
严小霞
孟凡帆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Science And Industry Co ltd
Original Assignee
China Construction Steel Structure Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Steel Structure Corp Ltd filed Critical China Construction Steel Structure Corp Ltd
Priority to CN201510249615.2A priority Critical patent/CN104895335B/zh
Publication of CN104895335A publication Critical patent/CN104895335A/zh
Application granted granted Critical
Publication of CN104895335B publication Critical patent/CN104895335B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

本发明适用于建筑施工技术领域,提供了一种吊柱的安装方法,包括以下步骤:A、搭设操作平台;B、在下方底座柱顶面上焊接临时连接耳板;C、在吊柱底部焊接临时连接耳板,开螺栓孔,并焊接上吊耳,在上方底座柱上开螺栓孔;D、将吊柱吊起,将螺栓拧入螺栓孔,使吊柱可以螺栓为中心旋转;E、使吊柱下降,其底面对齐下方底座柱的顶面,用螺栓将吊柱两连接耳板连接;F、用错位调节装置对吊柱的标高以及垂直度校正;G、割除临时连接耳板和吊耳,焊接马板,使吊柱与下方底座柱临时固定连接;H、将吊柱的底面与下方底座柱的顶面焊接,完成一根吊柱的安装。本发明安装过程操作简单、规范。为钢结构的制作,提供了一种简便、合理的吊柱安装方法。

Description

一种吊柱的安装方法
技术领域
本发明属于建筑施工技术领域,尤其涉及一种吊柱的安装方法。
背景技术
随着我国经济水平的不断发展,人民物质文化生活水平达到了一个新的高度。人们对建筑(特别是公共建筑)的需求观念也发生了根本性变化,在对功能、安全要求日益提高的同时,对建筑美观性能也比以往有着更高的需求。近15年间,国内各类结构形式新颖、造型奇特的钢结构建筑层出不穷。不断追求性能与美观的同时,对钢结构制作、安装以及焊接作业提出了更大的挑战以及更高的要求。
在一些建筑主体的施工过程中,需要吊装垂直的吊柱或者是倾斜的吊柱(转换斜柱),为了简化吊装安装步骤、缩短工期、提高施工效率与质量,需要研发一种简便、合理的吊柱安装方法。
发明内容
本发明所要解决的技术问题在于提供一种简便、合理的吊柱安装方法。
本发明是这样实现的,一种吊柱的安装方法,包括以下步骤:
A、搭设操作平台;
B、在楼面板上的下方底座柱的侧面上焊接临时连接耳板;
C、在待吊装的吊柱底部焊接上临时连接耳板,在其顶部开设螺栓孔,并在其一侧面上焊接上吊耳,在上方底座柱上亦开设螺栓孔;
D、用吊钩勾住吊耳,将吊柱吊起,借助操作平台,将螺栓拧入吊柱顶部的螺栓孔与上方底座柱上的螺栓孔,并使吊柱可以螺栓为中心旋转;
E、使吊柱下降,其底面对齐下方底座柱的顶面,用螺栓将吊柱的临时连接耳板与下方底座柱侧面的临时连接耳板连接;
F、用错位调节装置对吊柱进行标高以及垂直度进行校正;
G、割除下方底座柱的临时连接耳板、吊柱的临时连接耳板以及吊耳,焊接马板,使吊柱与下方底座柱临时固定连接;
H、将吊柱的底面与楼面板上的下方底座柱的顶面焊接,完成一根吊柱的安装。
进一步地,所述的步骤G还包括以下的步骤:
G1、向楼层板上浇筑混凝土,并在吊柱的四周预留出供后续吊柱焊接施工的空间。
进一步地,所述的步骤H还包括以下的步骤:
H1、向所述楼层板混凝土与吊柱四周的空间浇筑混凝土,使吊柱间的焊接处被混凝土覆盖、隐藏。
进一步地,所述的步骤H还包括以下的步骤:
H2、割除马板。
进一步地,所述的步骤H还包括以下的步骤:
H3、再次对吊柱的标高及垂直度进行测量、校正。
进一步地,所述步骤A还包括以下的步骤:
A1、安装爬梯及安全防护措施,并焊好防坠绳绑牢爬梯。
本发明与现有技术相比,有益效果在于:本发明于吊柱上焊接吊耳以及临时连接耳板,通过吊柱的吊装就位、临时固定、测量校正、焊接等操作后,完成了吊柱的安装,整个安装过程操作简单、设备简单,安装准确、规范。为形式新颖、造型奇特的钢结构的制作,提供了一种简便、合理的吊柱安装方法。
附图说明
图1是本发明实施例提供的一种吊柱的主视示意图。
图2是应用吊钩将图1所示吊柱吊起时的示意图。
图3是图1所示吊柱吊装就位后,拧入螺栓时的示意图。
图4是图1所示吊柱被吊钩松开、立正后的示意图。
图5是应用错位调节装置对吊柱进行垂直度及标高校正的示意图。
图6是用马板将图1所示吊柱与下方底座柱初步固定的示意图。
图7是往楼层板浇筑混凝土后的示意图。
图8是图1所示的吊柱割除临时连接板以及吊耳后的示意图。
图9是焊接结束后,往楼层板再次浇筑混凝土,将焊接位置隐藏的示意图。
具体实施方式
为了使本发明所要解决的技术问题、技术方案及有益效果更加清楚明白,以下结合附图及实施例,对本发明进行进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
如图1至图9所示,为本发明的一较佳实施例,一种吊柱的安装方法,具体步骤如下:
1、先根据各根吊柱100的重量及吊耳101的分布情况,准备足够的不同长度、不同规格的钢丝绳和卡环,并准备好倒链、揽风绳、爬梯、工具包、榔头以及扳手等机具。吊柱100统一设置在梁面标高1.3m以上,然后搭设操作平台(图中未示出);因为当吊柱100是转换斜柱时,上下焊缝高差较大,达到1.2m,因此最好把操作平台设置成三级不同高度的平台,并检查其稳定性,安装爬梯及安全防护措施,并焊好防坠绳绑牢爬梯。
2、将底座柱200顶面和吊柱100底面的渣土和浮锈清除干净,以保证焊接道内的清洁,然后,在楼面板300上的下方底座柱200的侧面上焊接临时连接耳板201(请参见图5)。在待吊装的吊柱100底部焊接上临时连接耳板102,在其顶部开设螺栓孔103,并在其一侧面上焊接上吊耳101(如图1所示),在上方底座柱200上亦开设螺栓孔202。
3、请参见图2,用吊钩400勾住吊耳101,将吊柱100吊起,借助操作平台,将螺栓1拧入吊柱100顶部的螺栓孔103与上方底座柱200上的螺栓孔202,初步拧紧,确保吊柱100可以螺栓1为中心旋转(如图3所示)。使吊柱100下降,其底面对齐下方底座柱200的顶面,用螺栓2将吊柱100的临时连接耳板102与下方底座柱200的临时连接耳板201连接,如果吊柱100是转换斜柱,还需配合揽风绳进行临时固定。
4、用错位调节装置400对吊柱100进行标高校正,再进行垂直度的校正(如图5所示);校正时,应对轴线、垂直度、标高、焊缝间隙等因素综合考虑,全面兼顾,每个分项的偏差值都要符合设计及规范要求。
5、割除下方底座柱200的临时连接耳板201、吊柱100的临时连接耳板102以及吊耳101,焊接马板104(如图6所示),使吊柱100与下方底座柱200临时固定连接,向楼层板300上浇筑混凝土301,并在吊柱100的四周预留出供后续吊柱100焊接施工的空间(如图7所示)。
6、将吊柱100的底面与楼面板300上的下方底座柱200的顶面焊接,完成一根吊柱100的安装,割除马板104(如图8所示),再次对吊柱100的标高及垂直度进行测量、校正。然后,向楼层板300的混凝土301与吊柱100四周的空间浇筑混凝土302,使吊柱100间的焊接处被混凝土302覆盖、隐藏(如图9所示)。
上述的安装过程中,还应注意以下的事项:每根吊柱100的定位轴线应从地面控制线直接从基准线向上引,不得引用下节吊柱100的轴线,吊柱100标高可按相对标高进行控制,标高控制需从同一控制网引测,避免累计误差。
吊柱100下降时必须紧固螺栓1,于本实施例中,吊柱100的顶部设置有双夹板105,上述的螺栓孔103开设在双夹板105上。利用双夹板105自平衡双夹板对接技术保证吊柱100连接稳固。为了确保吊柱100吊装成垂直状,吊耳101必须对称,吊柱100起吊时必须平稳,不得使吊柱100在地面上有拖拉现象,离地后立即停留一分钟。起钩、旋转、移动三个动作交替缓慢进行,旋转时需要有一定的高度,就位时缓慢下落,防止吊柱大幅度摆动和震荡。
本实施例于吊柱100上焊接吊耳101以及临时连接耳板102,通过吊柱100的吊装就位、临时固定、测量校正、焊接等操作后,完成了吊柱100的安装,整个安装过程操作简单、设备简单,安装准确、规范。为形式新颖、造型奇特的钢结构的制作,提供了一种简便、合理的吊柱安装方法。
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。

Claims (6)

1.一种吊柱的安装方法,包括以下步骤:
A、搭设操作平台;
B、在楼面板上的下方底座柱的侧面上焊接临时连接耳板;
C、在待吊装的吊柱底部焊接上临时连接耳板,在其顶部开设螺栓孔,并在其一侧面上焊接上吊耳,在上方底座柱上亦开设螺栓孔;
D、用吊钩勾住吊耳,将吊柱吊起,借助操作平台,将螺栓拧入吊柱顶部的螺栓孔与上方底座柱上的螺栓孔,并使吊柱可以螺栓为中心旋转;
E、使吊柱下降,其底面对齐下方底座柱的顶面,用螺栓将吊柱的临时连接耳板与下方底座柱侧面的临时连接耳板连接;
F、用错位调节装置对吊柱进行标高以及垂直度进行校正;
G、割除下方底座柱的临时连接耳板、吊柱的临时连接耳板以及吊耳,焊接马板,使吊柱与下方底座柱临时固定连接;
H、将吊柱的底面与楼面板上的下方底座柱的顶面焊接,完成一根吊柱的安装。
2.如权利要求1所述的吊柱的安装方法,所述的步骤G还包括以下的步骤:
G1、向楼层板上浇筑混凝土,并在吊柱的四周预留出供后续吊柱焊接施工的空间。
3.如权利要求2所述的吊柱的安装方法,所述的步骤H还包括以下的步骤:
H1、向所述楼层板混凝土与吊柱四周的空间浇筑混凝土,使吊柱间的焊接处被混凝土覆盖、隐藏。
4.如权利要求1所述的吊柱的安装方法,所述的步骤H还包括以下的步骤:
H2、割除马板。
5.如权利要求1至4任一项所述的吊柱的安装方法,所述的步骤H还包括以下的步骤:
H3、再次对吊柱的标高及垂直度进行测量、校正。
6.如权利要求1所述的吊柱的安装方法,所述步骤A还包括以下的步骤:
A1、安装爬梯及安全防护措施,并焊好防坠绳绑牢爬梯。
CN201510249615.2A 2015-05-15 2015-05-15 一种吊柱的安装方法 Active CN104895335B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510249615.2A CN104895335B (zh) 2015-05-15 2015-05-15 一种吊柱的安装方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510249615.2A CN104895335B (zh) 2015-05-15 2015-05-15 一种吊柱的安装方法

Publications (2)

Publication Number Publication Date
CN104895335A true CN104895335A (zh) 2015-09-09
CN104895335B CN104895335B (zh) 2017-01-18

Family

ID=54028260

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510249615.2A Active CN104895335B (zh) 2015-05-15 2015-05-15 一种吊柱的安装方法

Country Status (1)

Country Link
CN (1) CN104895335B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107190995A (zh) * 2017-07-06 2017-09-22 中建三局集团有限公司 多层弧形吊柱高空无胎架支撑
CN107938858A (zh) * 2017-12-19 2018-04-20 凉山州现代房屋建筑集成制造有限公司 异形柱防错边现场拼接节点
CN109098284A (zh) * 2018-08-31 2018-12-28 中建三局第建设工程有限责任公司 一种钢结构吊柱及其受力状态转换施工方法
JP2019011648A (ja) * 2017-06-30 2019-01-24 大和ハウス工業株式会社 地組架台
CN111519910A (zh) * 2020-05-06 2020-08-11 中建八局第一建设有限公司 多角度大斜率钢柱吊装方法及配合使用的防护架体组件
CN113175222A (zh) * 2021-04-02 2021-07-27 赵东昕 一种内嵌式预制外墙板构件的安装方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0742369A (ja) * 1993-07-29 1995-02-10 Shimizu Corp 鉄骨柱の建て込み方法
JPH11247450A (ja) * 1998-02-26 1999-09-14 Okumura Corp プレキャスト柱ユニットおよびそれを使用する柱の構築工法
CN101858148A (zh) * 2009-04-10 2010-10-13 江苏顺通建设工程有限公司 钢柱对接三维调校方法
CN103195256A (zh) * 2013-04-02 2013-07-10 广东省建筑工程集团有限公司 吊柱式钢结构胎架法施工工法
CN103452326A (zh) * 2013-07-25 2013-12-18 浙江精工钢结构有限公司 超长吊柱顺做法施工方法及其设备

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0742369A (ja) * 1993-07-29 1995-02-10 Shimizu Corp 鉄骨柱の建て込み方法
JPH11247450A (ja) * 1998-02-26 1999-09-14 Okumura Corp プレキャスト柱ユニットおよびそれを使用する柱の構築工法
CN101858148A (zh) * 2009-04-10 2010-10-13 江苏顺通建设工程有限公司 钢柱对接三维调校方法
CN103195256A (zh) * 2013-04-02 2013-07-10 广东省建筑工程集团有限公司 吊柱式钢结构胎架法施工工法
CN103452326A (zh) * 2013-07-25 2013-12-18 浙江精工钢结构有限公司 超长吊柱顺做法施工方法及其设备

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019011648A (ja) * 2017-06-30 2019-01-24 大和ハウス工業株式会社 地組架台
JP7050431B2 (ja) 2017-06-30 2022-04-08 大和ハウス工業株式会社 地組架台
CN107190995A (zh) * 2017-07-06 2017-09-22 中建三局集团有限公司 多层弧形吊柱高空无胎架支撑
CN107938858A (zh) * 2017-12-19 2018-04-20 凉山州现代房屋建筑集成制造有限公司 异形柱防错边现场拼接节点
CN107938858B (zh) * 2017-12-19 2023-10-20 凉山州现代房屋建筑集成制造有限公司 异形柱防错边现场拼接节点
CN109098284A (zh) * 2018-08-31 2018-12-28 中建三局第建设工程有限责任公司 一种钢结构吊柱及其受力状态转换施工方法
CN111519910A (zh) * 2020-05-06 2020-08-11 中建八局第一建设有限公司 多角度大斜率钢柱吊装方法及配合使用的防护架体组件
CN111519910B (zh) * 2020-05-06 2021-11-16 中建八局第一建设有限公司 多角度大斜率钢柱吊装方法及配合使用的防护架体组件
CN113175222A (zh) * 2021-04-02 2021-07-27 赵东昕 一种内嵌式预制外墙板构件的安装方法
CN113175222B (zh) * 2021-04-02 2023-08-15 台州优匠建筑科技有限公司 一种内嵌式预制外墙板构件的安装方法

Also Published As

Publication number Publication date
CN104895335B (zh) 2017-01-18

Similar Documents

Publication Publication Date Title
CN104895335A (zh) 一种吊柱的安装方法
CN101852019B (zh) 一种倾斜钢屋盖的提升安装方法
CN101284628B (zh) 大吨位压力机架的吊装方法
CN109231023B (zh) 门座式起重机臂架系统的安装方法
CN108643584A (zh) 一种钢结构超长悬挑大梁无支撑安装的施工方法
CN109826082B (zh) 一种在斜拉桥多塔柱组合空间内安装装饰结构的施工方法
CN208563968U (zh) 一种矩形烟囱双井架移置式模板整体提升装置
CN108104482B (zh) 斜柱安装方法
CN103991800A (zh) 建筑用屋面吊机
CN105239804B (zh) 一种间接空冷系统展宽平台组合吊装安装方法
CN104404888A (zh) 一种大型空中坡度调整吊装系统及应用
CN208071235U (zh) 一种钢桁架整体提升的支座及提升系统
CN110040632A (zh) 一种大跨度型钢梁的分段吊装施工方法
CN203486787U (zh) 一种维金斯式煤气柜柜顶的整体提升装置
CN204530492U (zh) 一种液压爬模施工平台
CN204040442U (zh) 一种整体提升式电梯井道操作平台
CN211173029U (zh) 用于烟囱加固施工的可升降平台结构
CN210549018U (zh) 偏心弧形环廊段高空提升工装
CN204112692U (zh) 简易提升式井筒操作平台
CN112160608A (zh) 一种高空全通透钢环廊提升安装方法
CN220178462U (zh) 钢制烟囱组对平台结构
Jones et al. Essential Elements
CN207737870U (zh) 一种大型储罐倒装提升装置
CN206376615U (zh) 烟囱钢内筒提升装置
CN108385844A (zh) 高层建筑屋顶钢结构桅杆免塔吊施工工法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Science And Industry Co.,Ltd.

Address before: 518040 Guangdong city of Shenzhen province Futian District Che Kung Temple Binhe Tairan industry tipping 17 storey building No. 17A

Patentee before: China Construction Steel Structure Corp.,Ltd.

CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 3801, 38 / F, Zhongjian science and engineering building, No. 3331, Weilan Coast Community Center Road, Yuehai street, Nanshan District, Shenzhen City, Guangdong Province

Patentee after: China Construction Science And Industry Co.,Ltd.

Address before: 518000 Guangdong city of Shenzhen province Futian District Che Kung Temple Binhe Tairan industry tipping 17 storey building No. 17A

Patentee before: China Construction Steel Structure Corp.,Ltd.