CN103352437A - 基于桥梁同步顶升和整体置换的快速降梁方法 - Google Patents

基于桥梁同步顶升和整体置换的快速降梁方法 Download PDF

Info

Publication number
CN103352437A
CN103352437A CN2013102415796A CN201310241579A CN103352437A CN 103352437 A CN103352437 A CN 103352437A CN 2013102415796 A CN2013102415796 A CN 2013102415796A CN 201310241579 A CN201310241579 A CN 201310241579A CN 103352437 A CN103352437 A CN 103352437A
Authority
CN
China
Prior art keywords
post
bridge
sub
synchronous jacking
female
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013102415796A
Other languages
English (en)
Inventor
卢九章
张毅
勘立军
李建军
王贵春
赵济平
周婧
王志顺
刘鸿洲
王林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd
Original Assignee
BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd filed Critical BEIJING MUNICIPAL BRIDGE MANAGEMENT MAINTENANCE GROUP Co Ltd
Priority to CN2013102415796A priority Critical patent/CN103352437A/zh
Publication of CN103352437A publication Critical patent/CN103352437A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

一种基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法包括:用驮运架一体机将桥梁整体下降承载于子柱和顶部具有同步顶升装置的母柱上,所述子柱和母柱均为多节段钢柱对接结构,子柱和母柱的上部还设置有垫块,通过交替调节子柱和母柱的高度并借助母柱顶部设置的同步顶升装置进行桥梁整体的同步下降。本发明简单有效、快捷安全性高,其采用稳定而简捷的降梁装置,能够快速的实现桥梁整体稳定的逐步降低,减轻施工的劳动强度要求对破碎设备和现场的安全隐患。

Description

基于桥梁同步顶升和整体置换的快速降梁方法
技术领域
本发明属于桥梁整体置换中对待处置旧桥梁搬运处置技术,具体的涉及一种基于桥梁同步顶升和整体置换工程中对驮运后的旧桥梁进行降至处理位置的快速降梁方法。
背景技术
随着我国旧桥梁改造的大量事实,对于存在病害或者破损的桥梁进行拆除后的及时重建成为施工的重要研究课题。对于主要通道或者重要道路的桥梁拆除,特别是涉及多种类型交通通道的交叉地带,无法进行现场的破拆或碎化后处理,因为现有环境和场地无法满足长时间施工要求,同时临时搭建或者预制性桥梁的施工也无法满足场地和现场破碎施工。而根据桥梁驮运车的要求进行桥梁的分体切割后,用桥梁驮运车运送至指定地点进行破拆。但驮运架一体机上的桥梁承运高度较高,在破拆现场需要将桥梁进行稳定降低至破拆高度,但具有较大重量的桥梁在降低过程中如不能稳定控制会存在倾斜以及倾覆等安全隐患,需要进行较为稳定的降梁操作。
发明内容
本发明提供了一种简单有效、快捷安全性高的基于桥梁同步顶升和整体置换的快速降梁方法,其采用稳定而简捷的降梁装置,能够快速的实现桥梁整体稳定的逐步降低,减轻施工的劳动强度要求对破碎设备和现场的安全隐患。
本发明所采用的技术方案如下:
一种基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法包括:
用驮运架一体机将桥梁整体下降承载于子柱和顶部具有同步顶升装置的母柱上,所述子柱和母柱均为多节段钢柱对接结构,子柱和母柱的上部还设置有垫块,通过交替调节子柱和母柱的高度并借助母柱顶部设置的同步顶升装置进行桥梁整体的同步下降。
具体实施方式中,所述降梁方法进一步包括:
在子柱和母柱的上端均设置垫块,通过母柱上设置的同步顶升装置进行桥梁的顶推,抽出子柱上的垫块后,驱动同步顶升装置下降,使子柱再次承接桥梁重量;
一实施方式中,所述降梁方法进一步包括:
子柱再次承接桥梁重量后,抽出母柱上的垫块,再次通过同步顶升装置进行桥梁的顶推,并抽出子柱上的垫块或减少子柱的节数,并驱动同步顶升装置下降,使降低的子柱再次承接桥梁重量。
一实施方式中,所述降梁方法进一步包括:
所述子柱和母柱为多个分布设置结构,所述桥梁下的两端分布设置两组对应的子柱和母柱组合。
一实施方式中,所述降梁方法进一步包括:
所述两组对应设置的子柱和母柱组合分别通过托梁顶推所述桥梁,所述每组子柱和母柱组合之间连接设置型钢连接梁。
一实施方式中,所述降梁方法进一步包括:
所述同步顶升装置为液压油缸,该液压油缸与托梁之间连接设置并与母柱顶部对应。
另一实施方式中,所述降梁方法进一步包括:
采用一总控制器控制连接所有同步顶升装置,每一同步顶升装置均设置位移传感器和液压传感器,每一同步顶升装置通过中控制器实现顶升和下降的协同控制。
该基于桥梁同步顶升和整体置换的快速降梁方法采用多阶段钢柱对接的子柱和母柱构成桥梁的承载主体,通过垫块和母柱上设置的同步顶升装置完成子柱和母柱承载高度的交替下降。子柱和母柱和采用分两组设置的方式,分别承接桥梁的左右两端,桥梁左右两端同步下降调整。每一端采用一个托梁实现承重的整体均匀分配。
本发明的有益效果在于,该基于桥梁同步顶升和整体置换的快速降梁方法简单有效、快捷安全性高,其采用稳定而简捷的降梁装置,能够快速的实现桥梁整体稳定的逐步降低,减轻施工的劳动强度要求对破碎设备和现场的安全隐患。
下面结合附图和具体实施方式对本发明做进一步的说明。
附图说明
图1是本发明具体实施方式的一状态示意图;
图2是本发明具体实施方式的另一状态示意图;
图3是本发明具体实施方式的又一状态示意图。
具体实施方式
如图1和图2所示,该基于桥梁同步顶升和整体置换的快速降梁方法先采用驮运架一体机将桥梁10整体下降承载于子柱20和顶部具有同步顶升装置31的母柱30上,所述子柱20和母柱30均为多节段钢柱对接结构,子柱和母柱的上部还设置有垫块21,通过交替调节子柱和母柱的高度并借助母柱顶部设置的同步顶升装置31进行桥梁整体的同步下降。
所述子柱和母柱为多个分布设置结构,所述桥梁下的两端分布设置两组对应的子柱和母柱组合。两组对应设置的子柱和母柱组合分别通过托梁40顶推所述桥梁,所述每组子柱和母柱组合之间连接设置型钢连接梁22。同步顶升装置31为液压油缸,该液压油缸与托梁之间连接设置并与母柱顶部对应。采用一总控制器控制连接所有同步顶升装置,每一同步顶升装置均设置位移传感器和液压传感器,每一同步顶升装置通过中控制器实现顶升和下降的协同控制。
如图1所示,在子柱20和母柱30的上端均设置垫块21,通过母柱上设置的同步顶升装置31进行桥梁的下降,如图2所示,子柱20成为承载支撑点,此时抽出母柱上的垫块21后,驱动同步顶升装置下降,使母柱30再次承接桥梁重量;
如图3所示,再次通过同步顶升装置31进行桥梁10的顶推,并抽出子柱上的垫块21或减少子柱的节数,并驱动同步顶升装置下降,使降低的子柱再次承接桥梁重量。依次逐步可以实现桥梁的整体平稳快速降低。

Claims (7)

1.一种基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法包括: 
用驮运架一体机将桥梁整体下降承载于子柱和顶部具有同步顶升装置的母柱上,所述子柱和母柱均为多节段钢柱对接结构,子柱和母柱的上部还设置有垫块,通过交替调节子柱和母柱的高度并借助母柱顶部设置的同步顶升装置进行桥梁整体的同步下降。 
2.根据权利要求1所述的基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法进一步包括: 
在子柱和母柱的上端均设置垫块,通过母柱上设置的同步顶升装置进行桥梁的顶推,抽出子柱上的垫块后,驱动同步顶升装置下降,使子柱再次承接桥梁重量。 
3.根据权利要求2所述的基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法进一步包括: 
子柱再次承接桥梁重量后,抽出母柱上的垫块,再次通过同步顶升装置进行桥梁的顶推,并抽出子柱上的垫块或减少子柱的节数,并驱动同步顶升装置下降,使降低的子柱再次承接桥梁重量。 
4.根据权利要求1所述的基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法进一步包括: 
所述子柱和母柱为多个分布设置结构,所述桥梁下的两端分布设置两组对应的子柱和母柱组合。 
5.根据权利要求4所述的基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法进一步包括: 
所述两组对应设置的子柱和母柱组合分别通过托梁顶推所述桥梁,所述每组子柱和母柱组合之间连接设置型钢连接梁。 
6.根据权利要求5所述的基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法进一步包括: 
所述同步顶升装置为液压油缸,该液压油缸与托梁之间连接设置并与母柱 顶部对应。 
7.根据权利要求1所述的基于桥梁同步顶升和整体置换的快速降梁方法,其特征在于所述降梁方法进一步包括: 
采用一总控制器控制连接所有同步顶升装置,每一同步顶升装置均设置位移传感器和液压传感器,每一同步顶升装置通过中控制器实现顶升和下降的协同控制。 
CN2013102415796A 2013-06-19 2013-06-19 基于桥梁同步顶升和整体置换的快速降梁方法 Pending CN103352437A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013102415796A CN103352437A (zh) 2013-06-19 2013-06-19 基于桥梁同步顶升和整体置换的快速降梁方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013102415796A CN103352437A (zh) 2013-06-19 2013-06-19 基于桥梁同步顶升和整体置换的快速降梁方法

Publications (1)

Publication Number Publication Date
CN103352437A true CN103352437A (zh) 2013-10-16

Family

ID=49308845

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013102415796A Pending CN103352437A (zh) 2013-06-19 2013-06-19 基于桥梁同步顶升和整体置换的快速降梁方法

Country Status (1)

Country Link
CN (1) CN103352437A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284079A (zh) * 2016-08-08 2017-01-04 中交三公局桥梁隧道工程有限公司 一种桥梁断柱交替分级同步整体顶升的施工方法
CN110528405A (zh) * 2019-05-28 2019-12-03 武汉二航路桥特种工程有限责任公司 基于车组的桥梁大高度升降移位装备及其施工方法
CN111021771A (zh) * 2019-12-24 2020-04-17 上海市机械施工集团有限公司 一种钢结构置换原有建筑结构的施工方法
CN111422797A (zh) * 2020-03-25 2020-07-17 中国五冶集团有限公司 一种冷水机组室内垂直运输方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1837485A (zh) * 2006-04-19 2006-09-27 中国建筑第二工程局 空中预制平移就位的桥梁施工方法
JP4134104B2 (ja) * 2005-06-06 2008-08-13 株式会社新井組 橋梁一括撤去工法
CN102092331A (zh) * 2010-12-29 2011-06-15 江阴大桥(北京)工程有限公司 一种带顶升装置的运输车及其运输桥梁的方法
CN102587291A (zh) * 2012-03-27 2012-07-18 中交四航局第一工程有限公司 一种钢箱梁步履式多点顶推施工方法及施工系统
CN102704705A (zh) * 2012-06-06 2012-10-03 河北省建筑科学研究院 建筑物长行程无回降多点同步顶升方法
CN102995571A (zh) * 2012-09-05 2013-03-27 武汉二航路桥特种工程有限责任公司 桥梁梁体拆除时单根大吨位临时钢管支架预压后和梁底顶紧的方法及其装置
CN203346805U (zh) * 2013-06-18 2013-12-18 北京市政路桥管理养护集团有限公司 桥梁同步顶升技术的快速降梁顶撑机构

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4134104B2 (ja) * 2005-06-06 2008-08-13 株式会社新井組 橋梁一括撤去工法
CN1837485A (zh) * 2006-04-19 2006-09-27 中国建筑第二工程局 空中预制平移就位的桥梁施工方法
CN102092331A (zh) * 2010-12-29 2011-06-15 江阴大桥(北京)工程有限公司 一种带顶升装置的运输车及其运输桥梁的方法
CN102587291A (zh) * 2012-03-27 2012-07-18 中交四航局第一工程有限公司 一种钢箱梁步履式多点顶推施工方法及施工系统
CN102704705A (zh) * 2012-06-06 2012-10-03 河北省建筑科学研究院 建筑物长行程无回降多点同步顶升方法
CN102995571A (zh) * 2012-09-05 2013-03-27 武汉二航路桥特种工程有限责任公司 桥梁梁体拆除时单根大吨位临时钢管支架预压后和梁底顶紧的方法及其装置
CN203346805U (zh) * 2013-06-18 2013-12-18 北京市政路桥管理养护集团有限公司 桥梁同步顶升技术的快速降梁顶撑机构

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106284079A (zh) * 2016-08-08 2017-01-04 中交三公局桥梁隧道工程有限公司 一种桥梁断柱交替分级同步整体顶升的施工方法
CN110528405A (zh) * 2019-05-28 2019-12-03 武汉二航路桥特种工程有限责任公司 基于车组的桥梁大高度升降移位装备及其施工方法
CN110528405B (zh) * 2019-05-28 2022-01-07 武汉二航路桥特种工程有限责任公司 基于车组的桥梁大高度升降移位装备及其施工方法
CN111021771A (zh) * 2019-12-24 2020-04-17 上海市机械施工集团有限公司 一种钢结构置换原有建筑结构的施工方法
CN111021771B (zh) * 2019-12-24 2021-06-18 上海市机械施工集团有限公司 一种钢结构置换原有建筑结构的施工方法
CN111422797A (zh) * 2020-03-25 2020-07-17 中国五冶集团有限公司 一种冷水机组室内垂直运输方法

Similar Documents

Publication Publication Date Title
CN203411917U (zh) 基于桥梁同步顶升和整体置换技术的快速降梁机构
CN104032678B (zh) H型塔柱内力可调的临时横撑结构及其施工方法
CN103352437A (zh) 基于桥梁同步顶升和整体置换的快速降梁方法
CN101122114A (zh) 无背索斜拉桥钢塔竖向转体施工方法
CN107872129A (zh) 用于核电站卧式高压电机的转子抽穿装置及方法
CN202380732U (zh) 型钢混凝土梁自承重模板支撑装置
CN202936732U (zh) 悬索桥临时散索鞍架体
CN202559236U (zh) 一种拱肋限位固定钢支座
CN203346805U (zh) 桥梁同步顶升技术的快速降梁顶撑机构
CN101967798A (zh) 公路双导梁架桥机及调头方法
CN106223204A (zh) 一种预应力张拉高窄区域辅助施工张拉台车及施工方法
CN205895267U (zh) 一种自动输送行走轨道的隧道衬砌模板台车
CN210888015U (zh) 一种挂篮走行顶推装置
CN211775667U (zh) 一种输电线路跨越塔组立高空施工平台
CN203411916U (zh) 基于桥梁同步顶升技术的快速降梁支撑系统
CN105000498A (zh) 升降装置
CN202803757U (zh) 初轧机衬板更换装置
CN106829750B (zh) 一种重型模块装拆机
CN204532376U (zh) 分体式升降施工台车
CN104514200B (zh) 大吨位架桥机的后辅助支撑装置
CN203270465U (zh) 悬浇挂篮液压预压施工装置
CN204356659U (zh) 新型大吨位架桥机的后辅助支撑装置
CN202746770U (zh) 采煤巷道电缆支架车
CN203350751U (zh) 基于计算机控制的桥梁整体置换液压同步顶升装置
CN206702543U (zh) 立杆碗扣拆卸机

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20131016