CN103122691A - 塔吊标准节支承高空支模钢平台结构及施工方法 - Google Patents

塔吊标准节支承高空支模钢平台结构及施工方法 Download PDF

Info

Publication number
CN103122691A
CN103122691A CN2013100417551A CN201310041755A CN103122691A CN 103122691 A CN103122691 A CN 103122691A CN 2013100417551 A CN2013100417551 A CN 2013100417551A CN 201310041755 A CN201310041755 A CN 201310041755A CN 103122691 A CN103122691 A CN 103122691A
Authority
CN
China
Prior art keywords
tower crane
standard section
steel platform
lattice column
formwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013100417551A
Other languages
English (en)
Inventor
华学严
张灵传
崔朝赟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Construction Group Co Ltd filed Critical Zhongtian Construction Group Co Ltd
Priority to CN2013100417551A priority Critical patent/CN103122691A/zh
Publication of CN103122691A publication Critical patent/CN103122691A/zh
Pending legal-status Critical Current

Links

Images

Abstract

本发明公开了一种塔吊标准节支承高空支模钢平台结构,包括塔吊标准节格构柱基础及安装于塔吊标准节格构柱基础上的格构柱结构的塔吊标准节,所述塔吊标准节四周环绕设置有周边支模架,所述塔吊标准节顶部设有口字型或者工字型顶支座,所述顶支座上安装钢平台,所述钢平台上安装钢管支撑架,所述钢管支撑架上设有浇筑混凝土用的木方及模板。本发明支模体系传力明确、受力合理、安全可靠,能满足结构截面尺寸大、搭设高度高的要求;施工便捷、实施可行、定型稳定、且可缩短施工工期。

Description

塔吊标准节支承高空支模钢平台结构及施工方法
技术领域
本发明涉及悬空梁板结构支模领域,具体涉及塔吊标准节支承高空支模钢平台体系及施工方法。
背景技术
在大型建筑中,因结构需要或建筑外形美观要求,大截面悬空梁板结构设计形式越来越多。如大型体育馆顶环梁、联系两相邻高楼间的高空连廊、展览中心的大截面悬挑屋盖梁等。大截面悬空梁板结构施工过程中,模板支撑是关键环节。在悬空结构的模板支撑体系中,一般采用满堂落地支模架,但当悬空结构截面特大,或支模架搭设高度超过30m时,满堂支模架不能满足施工要求时,因此需要一种安全可靠的高空支模体系。
发明内容
本发明所要解决的技术问题就是提供一种塔吊标准节支承高空支模钢平台结构及施工方法,支模体系传力明确、受力合理、安全可靠,能满足结构截面尺寸大、搭设高度高的要求。
为解决上述技术问题,本发明采用如下技术方案:塔吊标准节支承高空支模钢平台结构,包括塔吊标准节格构柱基础及安装于塔吊标准节格构柱基础上的格构柱结构的塔吊标准节,其特征在于:所述塔吊标准节四周环绕设置有周边支模架,所述塔吊标准节顶部设有口字型或者工字型顶支座,所述顶支座上安装钢平台,所述钢平台上安装钢管支撑架,所述钢管支撑架上设有浇筑混凝土用的木方及模板。
优选的,所述塔吊标准节格构柱基础内设置有井字形的暗梁,所述塔吊标准节底部与预埋在暗梁内的螺栓紧固。
优选的,所述塔吊标准节的格构柱沿柱高设置抱箍与周边支模架相连接。
优选的,所述钢平台板包括两根竖向主龙骨及焊接固定于竖向主龙骨顶端之间的横向次龙骨,所述竖向主龙骨通过抱箍连接顶支座。
优选的,所述次龙骨上间隔焊接有短钢筋。
优选的,所述顶支座与次龙骨间设置竖向斜撑。
优选的,所述顶支座下部焊接方钢管,所述方钢管插入塔吊标准节的主肢内。
本发明还提供了一种塔吊标准节支承高空支模钢平台施工方法,其特征在于包括以下步骤:
步骤一:塔吊标准节格构柱基础加固,当塔吊标准节格构柱基础坐落于楼层结构时,需采取竖向支撑的加固方式将上部荷载往下传至地下室底板或者自然地坪,竖向支撑随楼层结构施工预设;
步骤二:塔吊标准节格构柱基础施工,施工前按规范进行基础受力计算,使基础配筋满足要求;
步骤三:塔吊标准节格构柱的吊装与安装,利用施工现场塔吊或汽车吊吊装塔吊标准节,上下标准节间采用螺栓连接固定;
步骤四:塔吊标准节安装完成后进行塔吊标准节顶支座处理,在塔吊标准节上设置口字型顶支座,或者采用工字型顶支座;
步骤五:钢平台施工;
步骤六:搭设上部钢管支撑架;
步骤七:按常规支模施工方法铺设木方、模板,绑扎钢筋,浇筑混凝土;
步骤八:待混凝土达到强度要求后拆除支模体系,从一端向另一端、自上而下逐步拆除。
优选的,所述塔吊标准节基础采用满堂扣件式钢管脚手架进行加固。
本发明采用上述技术方案提供的塔吊标准节支承高空支模钢平台体系施工方法,支模体系传力明确、受力合理、安全可靠,能满足结构截面尺寸大、搭设高度高的要求;施工便捷、实施可行、定型稳定、且可缩短施工工期;材料可回收,经济性好;塔吊标准节格构柱柱距较大,方便结构下方车辆及大型机械运输通行。
附图说明
下面结合附图和具体实施方式对本发明作进一步描述:
图1为塔吊标准节格构柱基础结构示意图;
图2为钢管支撑架结构示意图;
图3为暗梁结构示意图;
图4为钢平台结构示意图;
图5为顶支座与塔吊标准节的主肢连接结构示意图。
具体实施方式
如图1至图5的塔吊标准节支承高空支模钢平台结构,其包括塔吊标准节格构柱基础1及安装于塔吊标准节格构柱基础上的格构柱结构的塔吊标准节2,所述塔吊标准节四周环绕设置有周边支模架12,所述塔吊标准节顶部设有口字型或者工字型顶支座3,所述顶支座上安装钢平台,所述钢平台上安装钢管支撑架4。所述塔吊标准节格构柱基础内设置有井字形的暗梁11,所述塔吊标准节底部与预埋在暗梁内的螺栓紧固。所述塔吊标准节的格构柱沿柱高设置抱箍与周边支模架12相连接。
所述钢平台板包括两根竖向主龙骨30及焊接固定于竖向主龙骨顶端之间的横向次龙骨31,所述竖向主龙骨通过抱箍连接顶支座3。所述次龙骨上间隔焊接有短钢筋34固定立杆。所述顶支座与次龙骨间设置竖向斜撑33。所述顶支座下部焊接方钢管35,所述方钢管插入塔吊标准节的主肢20内。
上述塔吊标准节支承高空支模钢平台施工方法,包括以下步骤:
步骤一:塔吊标准节格构柱基础加固,当塔吊标准节格构柱基础坐落于楼层结构时,需采取竖向支撑的加固方式将上部荷载往下传至地下室底板或者自然地坪,竖向支撑随楼层结构施工预设;
步骤二:塔吊标准节格构柱基础施工,施工前按规范进行基础受力计算,使基础配筋满足要求;
步骤三:塔吊标准节格构柱的吊装与安装,利用施工现场塔吊或汽车吊吊装塔吊标准节,上下标准节间采用螺栓连接固定;
步骤四:塔吊标准节安装完成后进行塔吊标准节顶支座处理,在塔吊标准节上设置口字型顶支座,或者采用工字型顶支座等;
步骤五:钢平台施工,主龙骨采用大截面型钢,次龙骨采用小截面型钢,主次龙骨之间采用焊接连接;
步骤六:以次龙骨为立杆基础,搭设上部钢管支撑架,立杆顶部采用可调顶托,顶托梁采用双钢管;
步骤七:按常规支模施工方法铺设木方、模板,绑扎钢筋,浇筑混凝土;
步骤八:待混凝土达到强度要求后拆除支模体系,从一端向另一端、自上而下逐步拆除。
其中所述塔吊标准节基础采用满堂扣件式钢管脚手架进行加固。

Claims (9)

1.塔吊标准节支承高空支模钢平台结构,包括塔吊标准节格构柱基础(1)及安装于塔吊标准节格构柱基础上的格构柱结构的塔吊标准节(2),其特征在于:所述塔吊标准节四周环绕设置有周边支模架(12),所述塔吊标准节顶部设有口字型或者工字型顶支座(3),所述顶支座上安装钢平台,所述钢平台上安装钢管支撑架(4),所述钢管支撑架(4)上设有浇筑混凝土用的木方及模板。
2.根据权利要求1所述的塔吊标准节支承高空支模钢平台结构,其特征在于:所述塔吊标准节格构柱基础(1)内设置有井字形的暗梁(11),所述塔吊标准节(2)底部与预埋在暗梁内的螺栓紧固。
3.根据权利要求1所述的塔吊标准节支承高空支模钢平台结构,其特征在于:所述塔吊标准节的格构柱沿柱高设置抱箍与周边支模架(12)相连接。
4.根据权利要求1所述的塔吊标准节支承高空支模钢平台结构,其特征在于:所述钢平台板包括两根竖向主龙骨(30)及焊接固定于竖向主龙骨顶端之间的横向次龙骨(31),所述竖向主龙骨通过抱箍连接顶支座。
5.根据权利要求4所述的塔吊标准节支承高空支模钢平台结构,其特征在于:所述次龙骨上间隔焊接有短钢筋(34)。
6.根据权利要求4所述的塔吊标准节支承高空支模钢平台结构,其特征在于:所述顶支座(3)与次龙骨间设置竖向斜撑(33)。
7.根据权利要求1所述的塔吊标准节支承高空支模钢平台结构,其特征在于:所述顶支座(3)下部焊接方钢管(35),所述方钢管插入塔吊标准节的主肢(20)内。
8.塔吊标准节支承高空支模钢平台施工方法,其特征在于包括以下步骤:
步骤一:塔吊标准节格构柱基础加固,当塔吊标准节格构柱基础坐落于楼层结构时,需采取竖向支撑的加固方式将上部荷载往下传至地下室底板或者自然地坪,竖向支撑随楼层结构施工预设;
步骤二:塔吊标准节格构柱基础施工,施工前按规范进行基础受力计算,使基础配筋满足要求;
步骤三:塔吊标准节格构柱的吊装与安装,利用施工现场塔吊或汽车吊吊装塔吊标准节,上下标准节间采用螺栓连接固定;
步骤四:塔吊标准节安装完成后进行塔吊标准节顶支座处理,在塔吊标准节上设置口字型顶支座,或者采用工字型顶支座;
步骤五:钢平台施工;
步骤六:搭设上部钢管支撑架;
步骤七:按常规支模施工方法铺设木方、模板,绑扎钢筋,浇筑混凝土;
步骤八:待混凝土达到强度要求后拆除支模体系,从一端向另一端、自上而下逐步拆除。
9.根据权利要求8所述的塔吊标准节支承高空支模钢平台施工方法,其特征在于:所述塔吊标准节基础采用满堂扣件式钢管脚手架进行加固。
CN2013100417551A 2013-02-04 2013-02-04 塔吊标准节支承高空支模钢平台结构及施工方法 Pending CN103122691A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013100417551A CN103122691A (zh) 2013-02-04 2013-02-04 塔吊标准节支承高空支模钢平台结构及施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013100417551A CN103122691A (zh) 2013-02-04 2013-02-04 塔吊标准节支承高空支模钢平台结构及施工方法

Publications (1)

Publication Number Publication Date
CN103122691A true CN103122691A (zh) 2013-05-29

Family

ID=48453812

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013100417551A Pending CN103122691A (zh) 2013-02-04 2013-02-04 塔吊标准节支承高空支模钢平台结构及施工方法

Country Status (1)

Country Link
CN (1) CN103122691A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103791156A (zh) * 2012-10-29 2014-05-14 五冶集团上海有限公司 大直径玻璃钢管道超高空快速安装方法
CN105888242A (zh) * 2014-12-15 2016-08-24 上海电力建筑工程公司 混凝土柱现浇结构移动式模板支撑体系及施工方法
CN107035200A (zh) * 2017-05-10 2017-08-11 南京瑞麒凰电子科技有限公司 一种悬梁吊板建造方法及悬梁吊板结构
CN107794945A (zh) * 2017-11-27 2018-03-13 陕西建工机械施工集团有限公司 一种可移动装配式模板安拆操作系统及其施工方法
CN109610831A (zh) * 2019-01-07 2019-04-12 五冶集团上海有限公司 一种现代物流厂房地坪与高支模综合施工方法
CN110748155A (zh) * 2019-10-30 2020-02-04 中国一冶集团有限公司 大直径筒仓锥斗混凝土施工模板的支撑装置及其施工方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201794317U (zh) * 2010-09-27 2011-04-13 南京道广建筑模板有限公司 一种建筑塔式支撑架
CN201809972U (zh) * 2010-10-19 2011-04-27 苑炳南 建筑水平结构模板支承格构件的早拆体系
CN102108788A (zh) * 2010-12-31 2011-06-29 华煜建设集团有限公司 一种悬空大跨度支架的施工方法
CN102587648A (zh) * 2012-03-17 2012-07-18 浙江城建建设集团有限公司 一种门式钢管与扣件式钢管组合模板支架装置及施工方法
JP3179138U (ja) * 2012-08-03 2012-10-18 川田建設株式会社 脚頭部施工用足場支保工
CN203034799U (zh) * 2013-02-04 2013-07-03 中天建设集团有限公司 塔吊标准节支承高空支模钢平台结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201794317U (zh) * 2010-09-27 2011-04-13 南京道广建筑模板有限公司 一种建筑塔式支撑架
CN201809972U (zh) * 2010-10-19 2011-04-27 苑炳南 建筑水平结构模板支承格构件的早拆体系
CN102108788A (zh) * 2010-12-31 2011-06-29 华煜建设集团有限公司 一种悬空大跨度支架的施工方法
CN102587648A (zh) * 2012-03-17 2012-07-18 浙江城建建设集团有限公司 一种门式钢管与扣件式钢管组合模板支架装置及施工方法
JP3179138U (ja) * 2012-08-03 2012-10-18 川田建設株式会社 脚頭部施工用足場支保工
CN203034799U (zh) * 2013-02-04 2013-07-03 中天建设集团有限公司 塔吊标准节支承高空支模钢平台结构

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
张立新等: ""深圳会议展览中心45m标高预应力鱼腹悬挑梁高支模施工技术"", 《广东土木与建筑》 *
朱国梁: ""高空大悬挑钢筋混凝土结构的高支模施工工法"", 《深圳土木与建筑》 *
杜耀进等: ""钢管格构柱在钢筋混凝土高支撑承重架中的应用"", 《施工技术》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103791156A (zh) * 2012-10-29 2014-05-14 五冶集团上海有限公司 大直径玻璃钢管道超高空快速安装方法
CN103791156B (zh) * 2012-10-29 2016-01-20 五冶集团上海有限公司 大直径玻璃钢管道超高空快速安装方法
CN105888242A (zh) * 2014-12-15 2016-08-24 上海电力建筑工程公司 混凝土柱现浇结构移动式模板支撑体系及施工方法
CN105888242B (zh) * 2014-12-15 2019-02-12 上海电力建筑工程公司 混凝土柱现浇结构移动式模板支撑体系及施工方法
CN107035200A (zh) * 2017-05-10 2017-08-11 南京瑞麒凰电子科技有限公司 一种悬梁吊板建造方法及悬梁吊板结构
CN107794945A (zh) * 2017-11-27 2018-03-13 陕西建工机械施工集团有限公司 一种可移动装配式模板安拆操作系统及其施工方法
CN109610831A (zh) * 2019-01-07 2019-04-12 五冶集团上海有限公司 一种现代物流厂房地坪与高支模综合施工方法
CN110748155A (zh) * 2019-10-30 2020-02-04 中国一冶集团有限公司 大直径筒仓锥斗混凝土施工模板的支撑装置及其施工方法
CN110748155B (zh) * 2019-10-30 2022-01-25 中国一冶集团有限公司 大直径筒仓锥斗混凝土施工模板的支撑装置及其施工方法

Similar Documents

Publication Publication Date Title
CN101886468B (zh) 高位连体结构悬挂式模板支撑施工方法
CN105649360A (zh) 一种整体装配式建筑系统及安装方法
CN102733606B (zh) 高空大悬挑结构的施工方法
CN106337555A (zh) 建筑外墙悬挑结构三角钢支撑施工方法
CN102535845A (zh) 一种连廊结构承重架的施工方法
CN103422672A (zh) 一种钢筋混凝土预制装配式房屋施工建造方法
CN104480922B (zh) 空间桁架支模系统及其施工方法
CN103122691A (zh) 塔吊标准节支承高空支模钢平台结构及施工方法
CN105442839A (zh) 一种悬挑结构模板排架的搭设方法
CN103046645A (zh) 一种大跨度预制整浇结构及施工方法
CN102071747A (zh) 方钢管混凝土柱与钢筋混凝土楼盖连接的节点及制作方法
CN203034799U (zh) 塔吊标准节支承高空支模钢平台结构
CN204282803U (zh) 悬挑支模平台安装结构
CN212507296U (zh) 高支模体系
CN206956979U (zh) 一种带顶柱的一字型剪力墙
CN212897482U (zh) 一种高层建筑悬挑结构层的施工平台
CN203230165U (zh) 超高悬挑结构模板支撑平台
CN109457814B (zh) 基于贝雷架结构的高耸及大直径建筑物顶盖施工方法
CN102787717B (zh) 自承式组合钢模板施工方法
CN202831219U (zh) 一种大跨度预制整浇结构
CN206769199U (zh) 后穿式后张法竖向预应力现浇混凝土柱结构
CN114134820A (zh) 一种工字组合梁现浇桥面板的模板支撑及施工方法
CN210288825U (zh) 一种装配式、现浇组合梁板结构
CN209874434U (zh) 一种建筑物高空简易外挑脚手架
CN210507094U (zh) 索塔下横梁预埋钢棒支撑系统

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130529