CN102828600A - Method for laying floor artificial stones - Google Patents
Method for laying floor artificial stones Download PDFInfo
- Publication number
- CN102828600A CN102828600A CN2012103280170A CN201210328017A CN102828600A CN 102828600 A CN102828600 A CN 102828600A CN 2012103280170 A CN2012103280170 A CN 2012103280170A CN 201210328017 A CN201210328017 A CN 201210328017A CN 102828600 A CN102828600 A CN 102828600A
- Authority
- CN
- China
- Prior art keywords
- man
- made stone
- paving
- leveling layer
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Landscapes
- Road Paving Structures (AREA)
- Road Repair (AREA)
Abstract
The invention relates to a method for laying floor artificial stones, comprising the following steps of: selecting artificial stones with the same color, storing the artificial stones in a construction field for 7-15 days, arranging a leveling layer on the surface of a base layer, descending the artificial stones at the temperature of 3 DEG C to 35 DEG C to connect the artificial stones and the leveling layer by using an adhesive, remaining a gap between every two adjacent artificial stones, maintaining and caulking since the artificial stones are laid for 5-7 days, wherein the floor can be used since the laying construction is finished for 14 days. The method for laying floor artificial stones, provided by the invention, has the following beneficial effects: the quality problem that the artificial stones are extremely likely to crack and deform after being laid is well solved, and the inner stress of the artificial stones can be released in the laying process; and the method has the following characteristics of high efficiency, excellent operability, high pertinence, significant quality control effect and convenience for a technical worker to disclose and an operator to master.
Description
Technical field
The present invention relates to the laying method of a kind of ground man-made stone.
Background technology
Rare gradually even exhausted along with the natural decorating materials resource; Man-made stone tentatively manifests as a kind of advantage of alternative ornament materials; Especially in recent years in large-scale public spaces such as market, research and development centre, high-grade factory building, subway, office building, be used widely, its appearance efficiently solve lithotome the problem of aspects such as ubiquitous aberration, production capacity.But the laying method of existing artificial stone is prone to cause man-made stone quality problems such as cracking, distortion to occur, after long-time the use, makes ground not attractive in appearance, and reaching when changing wastes time and energy the cost of increasing input.
Summary of the invention
The laying method that the purpose of this invention is to provide a kind of ground man-made stone overcomes problems such as being prone to cracking, distortion in the existing product, influences the deficiency of product quality.
The objective of the invention is to realize through following technical scheme:
The laying method of a kind of ground man-made stone may further comprise the steps:
1) material is prepared: the identical man-made stone that gets colors is placed on man-made stone in the construction plant and preserved 7-15 days;
2) the construction line-putting: eject 1 meter absolute altitude line of building and ground paving finished surface absolute altitude line through level gauge;
3) base treatment: remove dirt, oil stain, floating ash and dregs on the floor slab structure substrate surface; Through level gauge per 2 meters get ready do absolute altitude and step on cake after; Use mortar levelling, press polish to form leveling layer; Cement in the mortar and yellow ground weight ratio are 1:3, and leveling layer is whenever established a flexible lattice at a distance from 6 meters and stitched along the vertical, horizontal direction is the longest, and flexible lattice stitches wide 6mm; The whole gauze wire cloth that overlays in the mortar, the specification of gauze wire cloth is: the 8mm/ hole; In 3 days after construction of leveling blanket finishes, every day is respectively at the 18:00 point maintenance of sprinkling water of morning 6:00, noon 12:00, afternoon; After the leveling layer drying, use 2 meters guiding ruler to detect Base Smoothness, flatness error is ± 3mm;
4) man-made stone is set type: unwrapping wire is measured in the construction plant, draws piecemeal composing figure and perforate location detail drawing;
5) after paving construction: base treatment 18-23 days, fully stiff to leveling layer, man-made stone paving temperature is 3-35 ℃, and clean is carried out on the leveling layer surface; Bullet is put paving lattice control line and center line; The preparation bonding adhesive, the bonding adhesive for preparing used in 3-4 hour; The artificial stone carries out clean; Criticize uniformly at the leveling layer that needs paving earlier and scrape one deck bonding adhesive, bonding adhesive thickness blade coating thickness 2-3mm is coated with at the man-made stone back side and scrapes the thick bonding adhesive of 2-3mm; Paving is aimed at lattice control line or center line, and is fully rubbed pressure to ground after using the even combing of tooth pitch scraper; Be provided with the gap between the adjacent man-made stone, clearance distance is 1-2mm, and whenever establishes a flexible lattice seam that matches with leveling layer at a distance from 6 meters along the vertical, horizontal direction is the longest simultaneously; Flexible lattice stitches wide 6mm, makes real man-made stone;
6) maintenance, filleting: after the man-made stone paving construction is accomplished, to cleaning and clear up in man-made stone surface, lattice seam and the gap, behind the paving construction maintenance 5-7 days; The beginning filleting; During filleting, through spatula at the bottom of the rubber caulking agent is daubed in lattice seam and the gap, caulking agent is cleaned its surface with little wet sponge after receiving and doing at once; Caulking agent is the product of neutrality, mildew-resistant, waterproof, and caulking agent adopts no sand mold, flexible caulking material;
7) finished product protection: after maintenance, filleting are accomplished, the man-made stone surface is cleaned, guaranteed to protect, cover with gypsum plank or density board behind the dustless nothing sand, the construction end can be used after 14 days.
Further, in step 3), when the thickness of leveling layer surpasses 50mm, use the C20 pea gravel concreten to carry out levelling, press polish, the whole round steel that overlays in the C20 pea gravel concreten.
Beneficial effect of the present invention is: the laying method of a kind of ground provided by the invention man-made stone; The quality problems that very easily ftracture, are out of shape after the man-made stone paving have been solved preferably; This laying method can discharge the inner internal stress of man-made stone in the paving process; This method work efficiency is high, operability is good, with strong points, the quality control effect is obvious, and is convenient to that the technician tells somebody what one's real intentions are, operating personnel grasp.
The specific embodiment
The laying method of the described a kind of ground of embodiment of the invention man-made stone may further comprise the steps:
1) material is prepared: identical man-made stone gets colors; Man-made stone is placed in the construction plant preserved 7-15 days; Letting man-made stone fully adapt to soon temperature, the humidity of the environment of paving construction, and let the internal stress of gathering in the man-made stone process fully discharge;
2) the construction line-putting: eject 1 meter absolute altitude line of building and ground paving finished surface absolute altitude line through level gauge;
3) base treatment: remove dirt, oil stain, floating ash and dregs on the floor slab structure substrate surface; Through level gauge per 2 meters get ready do absolute altitude and step on cake after; Use mortar levelling, press polish to form leveling layer; Cement in the mortar and yellow ground weight ratio are 1:3, the whole gauze wire cloth that overlays in the mortar, and the specification of gauze wire cloth is: the 8mm/ hole; When the thickness of leveling layer surpasses 50mm, use the C20 pea gravel concreten to carry out levelling, press polish, the whole round steel that overlays in the C20 pea gravel concreten, leveling layer is whenever established a flexible lattice at a distance from 6 meters and is stitched along the vertical, horizontal direction is the longest, and flexible lattice stitches wide 6mm; In 3 days after construction of leveling blanket finishes, every day, watering adopted watering can to spray respectively at the 18:00 point maintenance of sprinkling water of morning 6:00, noon 12:00, afternoon; After the leveling layer drying, use 2 meters guiding ruler to detect Base Smoothness, flatness error is ± 3mm;
4) man-made stone is set type: unwrapping wire is measured in the construction plant, draws piecemeal composing figure and perforate location detail drawing;
5) after paving construction: base treatment 18-23 days, fully stiff to leveling layer, man-made stone paving temperature is 3-35 ℃, and clean is carried out on the leveling layer surface, accomplishes not have greasy dirt, foreign material such as dust stratification, dust; Bullet is put paving lattice control line and center line; Adopt the bonding adhesive that matches with man-made stone (when the floor heating construction requirement is arranged; Adopt flexible adhesive during the man-made stone paving); Use electronic stirring tool fully to stir bonding adhesive to paste during the preparation bonding adhesive, and do not have caking, the bonding adhesive for preparing used in 3-4 hour; The artificial stone carries out clean, and touching to palm does not have floating ash; Criticize uniformly at the leveling layer that needs paving earlier and scrape one deck bonding adhesive, bonding adhesive should be used the jagged scraper blade coating of 10 * 10cm, bonding adhesive thickness blade coating thickness 2-3mm; Be coated with at the man-made stone back side and scrape the thick bonding adhesive of 2-3mm, paving is aimed at lattice control line or center line to ground after the even combing of use tooth pitch scraper; And fully rub pressure, and being provided with the gap between the adjacent man-made stone, clearance distance is 1-2mm; When letting man-made stone combine with leveling layer; The inner heat of hydration that produces has the passage of an evacuation in the solidification process, also is convenient to the release of the internal stress of man-made stone accumulated inside simultaneously, and whenever establishes a flexible lattice seam that matches with leveling layer at a distance from 6 meters along the vertical, horizontal direction is the longest simultaneously; Flexible lattice stitches wide 6mm, and flexible lattice stitches gathering for the thermal stresses of clearing up, reduce large tracts of land man-made stone paving formation; When making real man-made stone; For fear of causing inner secretly the splitting of man-made stone; Stiffened wooden bat plate knocks through rubber hammer when making real; Firmly appropriateness (dynamics is can let man-made stone fully combine and be unlikely to bonding adhesive with the ground bonding adhesive to extrude in a large number) makes planeness, absolute altitude, the angle of man-made stone meet the paving purpose;
6) maintenance, filleting: after the man-made stone paving construction is accomplished, to cleaning and clear up in man-made stone surface, lattice seam and the gap, behind the paving construction maintenance 5-7 days; The beginning filleting; During filleting, through spatula at the bottom of the rubber caulking agent is daubed in lattice seam and the gap, caulking agent is cleaned its surface with little wet sponge after receiving and doing at once; Caulking agent is the product of neutrality, mildew-resistant, waterproof, and caulking agent adopts no sand mold, flexible caulking material;
7) finished product protection: after maintenance, filleting are accomplished, the man-made stone surface is cleaned, guaranteed to protect, cover with gypsum plank or density board behind the dustless nothing sand, the construction end can be used after 14 days.
Surface quality cleaning, clear patterns, color and luster through the plate surface layer after the paving of this man-made stone laying method are consistent, and seam is even, peripheral straight plate flawless, arrisdefect and scarce stupefied phenomenon.Touch on the man-made stone of having completed with hand hammer, the hollowing rate is in 5%, and monolithic hollowing rate is in 20%.
Its quality-controlling parameters is following:
The present invention is not limited to above-mentioned preferred forms; Anyone can draw other various forms of products under enlightenment of the present invention; No matter but on its shape or structure, do any variation; Every have identical with a application or akin technical scheme, all drops within protection scope of the present invention.
Claims (2)
1. the laying method of a ground man-made stone is characterized in that, may further comprise the steps:
1) material is prepared: the identical man-made stone that gets colors is placed on man-made stone in the construction plant and preserved 7-15 days;
2) the construction line-putting: eject 1 meter absolute altitude line of building and ground paving finished surface absolute altitude line through level gauge;
3) base treatment: remove dirt, oil stain, floating ash and dregs on the floor slab structure substrate surface; Through level gauge per 2 meters get ready do absolute altitude and step on cake after; Use mortar levelling, press polish to form leveling layer; Cement in the mortar and yellow ground weight ratio are 1:3, and leveling layer is whenever established a flexible lattice at a distance from 6 meters and stitched along the vertical, horizontal direction is the longest, and flexible lattice stitches wide 6mm; The whole gauze wire cloth that overlays in the mortar, the specification of gauze wire cloth is: the 8mm/ hole; In 3 days after construction of leveling blanket finishes, every day is respectively at the 18:00 point maintenance of sprinkling water of morning 6:00, noon 12:00, afternoon; After the leveling layer drying, use 2 meters guiding ruler to detect Base Smoothness, flatness error is ± 3mm;
4) man-made stone is set type: unwrapping wire is measured in the construction plant, draws piecemeal composing figure and perforate location detail drawing;
5) after paving construction: base treatment 18-23 days, fully stiff to leveling layer, man-made stone paving temperature is 3-35 ℃, and clean is carried out on the leveling layer surface; Bullet is put paving lattice control line and center line; The preparation bonding adhesive, the bonding adhesive for preparing used in 3-4 hour; The artificial stone carries out clean; Criticize uniformly at the leveling layer that needs paving earlier and scrape one deck bonding adhesive, bonding adhesive thickness blade coating thickness 2-3mm is coated with at the man-made stone back side and scrapes the thick bonding adhesive of 2-3mm; Paving is aimed at lattice control line or center line, and is fully rubbed pressure to ground after using the even combing of tooth pitch scraper; Be provided with the gap between the adjacent man-made stone, clearance distance is 1-2mm, and whenever establishes a flexible lattice seam that matches with leveling layer at a distance from 6 meters along the vertical, horizontal direction is the longest simultaneously; Flexible lattice stitches wide 6mm, makes real man-made stone;
6) maintenance, filleting: after the man-made stone paving construction is accomplished, to cleaning and clear up in man-made stone surface, lattice seam and the gap, behind the paving construction maintenance 5-7 days; The beginning filleting; During filleting, through spatula at the bottom of the rubber caulking agent is daubed in lattice seam and the gap, caulking agent is cleaned its surface with little wet sponge after receiving and doing at once; Caulking agent is the product of neutrality, mildew-resistant, waterproof, and caulking agent adopts no sand mold, flexible caulking material;
7) finished product protection: after maintenance, filleting are accomplished, the man-made stone surface is cleaned, guaranteed to protect, cover with gypsum plank or density board behind the dustless nothing sand, the construction end can be used after 14 days.
2. the laying method of a kind of ground according to claim 1 man-made stone is characterized in that, in step 3), when the thickness of leveling layer surpasses 50mm, uses the C20 pea gravel concreten to carry out levelling, press polish, the whole round steel that overlays in the C20 pea gravel concreten.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012103280170A CN102828600A (en) | 2012-09-07 | 2012-09-07 | Method for laying floor artificial stones |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012103280170A CN102828600A (en) | 2012-09-07 | 2012-09-07 | Method for laying floor artificial stones |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102828600A true CN102828600A (en) | 2012-12-19 |
Family
ID=47331892
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012103280170A Pending CN102828600A (en) | 2012-09-07 | 2012-09-07 | Method for laying floor artificial stones |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102828600A (en) |
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104131681A (en) * | 2014-07-31 | 2014-11-05 | 华鼎建筑装饰工程有限公司 | Method for laying archaistic gold bricks |
CN105201176A (en) * | 2014-06-13 | 2015-12-30 | 杭州三鹰化工有限公司 | Novel wood floor installation method |
CN105926886A (en) * | 2016-04-20 | 2016-09-07 | 安徽老石人石业有限公司 | Marble laying technological process in building |
CN106223151A (en) * | 2016-07-22 | 2016-12-14 | 南通八建集团有限公司 | Severe cold area large area wing square stone material is mated formation prevention and cure of crack method |
CN106677490A (en) * | 2016-12-15 | 2017-05-17 | 苏州红叶装饰工程有限公司 | Empty-drum-proof paving method through stone wet combining |
CN106836729A (en) * | 2017-04-13 | 2017-06-13 | 上海爱迪技术发展有限公司 | Floor heating artificial stone's wet combining construction method and associated mounting structure |
CN107489255A (en) * | 2017-08-01 | 2017-12-19 | 苏州苏明装饰股份有限公司 | A kind of big specification stone floor paving structure and construction method |
CN108179858A (en) * | 2018-02-10 | 2018-06-19 | 苏州金螳螂建筑装饰股份有限公司 | A kind of artificial stone paving structure and its laying method |
CN109222442A (en) * | 2018-09-03 | 2019-01-18 | 成都生活家网络科技有限公司 | A kind of wardrobe mounting process |
CN109653469A (en) * | 2019-01-31 | 2019-04-19 | 广东爱富兰建设有限公司 | The levelling floor construction method of anti-hollowing essence |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1786363A (en) * | 2005-12-12 | 2006-06-14 | 张建荣 | Method for construction of binding face tile and stone material on external heat preservation system on outside wall |
CN101413326A (en) * | 2008-11-12 | 2009-04-22 | 张建国 | Flat roof structure and construction method thereof |
CN102505831A (en) * | 2011-12-22 | 2012-06-20 | 深圳市深装总装饰工程工业有限公司 | Construction method for paving plasters on ground and manmade stone |
CN102518278A (en) * | 2011-12-12 | 2012-06-27 | 杭州市园林绿化工程有限公司 | Saltpetering preventive stone paving method |
-
2012
- 2012-09-07 CN CN2012103280170A patent/CN102828600A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1786363A (en) * | 2005-12-12 | 2006-06-14 | 张建荣 | Method for construction of binding face tile and stone material on external heat preservation system on outside wall |
CN101413326A (en) * | 2008-11-12 | 2009-04-22 | 张建国 | Flat roof structure and construction method thereof |
CN102518278A (en) * | 2011-12-12 | 2012-06-27 | 杭州市园林绿化工程有限公司 | Saltpetering preventive stone paving method |
CN102505831A (en) * | 2011-12-22 | 2012-06-20 | 深圳市深装总装饰工程工业有限公司 | Construction method for paving plasters on ground and manmade stone |
Non-Patent Citations (2)
Title |
---|
中华人民共和国建设部,国家质量监督检验检疫总局: "《屋面工程施工质量验收规范(GB50207-2002)》", 1 June 2002 * |
滕道社: "《建筑装饰工程施工》", 31 August 2011, 中国水利水电出版社 * |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105201176A (en) * | 2014-06-13 | 2015-12-30 | 杭州三鹰化工有限公司 | Novel wood floor installation method |
CN104131681A (en) * | 2014-07-31 | 2014-11-05 | 华鼎建筑装饰工程有限公司 | Method for laying archaistic gold bricks |
CN105926886A (en) * | 2016-04-20 | 2016-09-07 | 安徽老石人石业有限公司 | Marble laying technological process in building |
CN106223151A (en) * | 2016-07-22 | 2016-12-14 | 南通八建集团有限公司 | Severe cold area large area wing square stone material is mated formation prevention and cure of crack method |
CN106223151B (en) * | 2016-07-22 | 2018-05-15 | 南通八建集团有限公司 | Large area wing square stone material in severe cold area is mated formation prevention and cure of crack method |
CN106677490A (en) * | 2016-12-15 | 2017-05-17 | 苏州红叶装饰工程有限公司 | Empty-drum-proof paving method through stone wet combining |
CN106836729A (en) * | 2017-04-13 | 2017-06-13 | 上海爱迪技术发展有限公司 | Floor heating artificial stone's wet combining construction method and associated mounting structure |
CN106836729B (en) * | 2017-04-13 | 2023-05-12 | 上海爱迪技术发展有限公司 | Floor heating artificial stone wet adhesion construction method and related installation structure |
CN107489255A (en) * | 2017-08-01 | 2017-12-19 | 苏州苏明装饰股份有限公司 | A kind of big specification stone floor paving structure and construction method |
CN108179858A (en) * | 2018-02-10 | 2018-06-19 | 苏州金螳螂建筑装饰股份有限公司 | A kind of artificial stone paving structure and its laying method |
CN109222442A (en) * | 2018-09-03 | 2019-01-18 | 成都生活家网络科技有限公司 | A kind of wardrobe mounting process |
CN109653469A (en) * | 2019-01-31 | 2019-04-19 | 广东爱富兰建设有限公司 | The levelling floor construction method of anti-hollowing essence |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102828600A (en) | Method for laying floor artificial stones | |
CN103470067B (en) | Transformation and construction method used for facing bare concrete of existing building outer wall | |
CN102206066B (en) | Tile glue | |
CN105587102B (en) | A kind of wet construction method to the wet type high abrasion terrace that paves | |
CN107254954A (en) | Ground paving ceramic tile construction technology | |
CN101886460B (en) | Press polishing method of plastered mesh cloth of inner wall | |
CN101565997A (en) | Construction method for large-area irregular floor tile | |
CN103572845B (en) | A kind of insulation clay reflective heat-insulation paint exterior wall heat-preserving system and construction technology thereof | |
CN102518271B (en) | Coating construction method of faux stones | |
CN102400525B (en) | Thin-layer plastering method for autoclaved aerated concrete block wall bodies | |
CN107035103A (en) | A kind of cement floor construction method | |
CN104047410B (en) | Stone material paving construction method | |
CN106284998A (en) | Plastering on inner walls completely spreads fiberglass gridding cloth construction method | |
CN106284929A (en) | A kind of furring tile anti-hollowing edge patch construction method | |
CN103174274A (en) | Stone material seamless polishing construction method | |
CN104712114A (en) | Outer wall clay sculpture construction method and mortar adopted in same | |
CN110616861B (en) | Thermal power plant concrete structure modification construction method | |
CN106088533B (en) | A kind of construction method and constructing device of building decoration gray line | |
CN107574936A (en) | A kind of heat preserving exterior wall construction technology | |
CN101565991A (en) | Construction method for large-area inverse parking and accessible roof layer | |
CN113802844B (en) | Imitative preparation of rammed earth of building wall is with assisting lining curve mould strip | |
CN114876155A (en) | Construction process for polishing ground by using non-ignition fine stone concrete | |
CN205025042U (en) | Big unit pottery sheet metal back of body kiss -coating bonds and constructs | |
CN106193462A (en) | Roofing Splitting Tile construction method modelled after an antique | |
CN107327117A (en) | The preparation method on flat-die color concrete ground |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20121219 |