Prior art keywords
slope
grade
build
building
soil
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012102144855A
Other languages
Chinese (zh)
Other versions
CN102733401B (en
Inventor
燕建龙
王军
申红军
赵晓光
刘科
谭新平
赵治海
张海峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NORTHWEST RESEARCH INSTITUTE OF ENGINEERING INVESTIGATIONS AND DESIGN
Xian University of Science and Technology
Original Assignee
NORTHWEST RESEARCH INSTITUTE OF ENGINEERING INVESTIGATIONS AND DESIGN
Xian University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NORTHWEST RESEARCH INSTITUTE OF ENGINEERING INVESTIGATIONS AND DESIGN, Xian University of Science and Technology filed Critical NORTHWEST RESEARCH INSTITUTE OF ENGINEERING INVESTIGATIONS AND DESIGN
Priority to CN201210214485.5A priority Critical patent/CN102733401B/en
Publication of CN102733401A publication Critical patent/CN102733401A/en
Application granted granted Critical
Publication of CN102733401B publication Critical patent/CN102733401B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Cultivation Of Plants (AREA)
  • Pit Excavations, Shoring, Fill Or Stabilisation Of Slopes (AREA)

Abstract

The invention discloses a method for treating a dump slope of a surface mine. The method comprises the following steps of: treating to ensure that the side slope grade is (1:1.5)-(1:3), wherein if the slope is cohesive soil, the side slope grade is 1:1.5; if the slope is gravel, the side slope grade is 1:3; if the slope is other soil, the side slope grade is (1:1.5)-(1:3); building platforms (2), namely building a horizontal platform every 6 to 12 meters in the vertical height, wherein the width of the platform is 5 meters; building horizontal a drainage ditches (3), namely building the horizontal drainage ditches in the middles of the platforms; building discharging ditches (4), namely building the discharging ditch perpendicular to the horizontal drainage ditch every 30 meters on the slope surface in the horizontal direction, wherein the slope grade is determined according to the rainfall of the place where the slope is, the slope grade a in the north is 2 to 3 degrees, and the slope grade b in the south is 3 to 5 degrees; if the slope grade on the top of a dump cannot meet the requirement, building a canal and ditch net (6) on the top; and growing plant to protect the slope. The conventional dump is transformed by limited engineering and biological control measures, the potential safety hazard of strip mining dumps can be avoided completely, the water losses and soil erosion can be reduced greatly, ecological environment is improved, and mining areas and the environment around the same can be beautified. Meanwhile, the method has the characteristics of low investment and short construction period; and the structure is simple, so that later-stage maintenance cost is low.

Description

Surface mine refuse dump slope treatment method
Technical field
The invention belongs to mine construction, environmental improvement technical field, be specifically related to a kind of surface mine refuse dump slope treatment method.
Background technology
Mining mainly contains two kinds of different mining modes of surface mining and underground mining, comprises peeling off with excavation during the mine capital construction in the open and opens up; Dumping thing generally has corruption to plant table soil, weathered rock and soil, solid rock and mixing ground, and also comprising sometimes can recoverable unbalanced-ore, lean ore etc.When ore body buries more shallow or there is when appearing on the face of land, it is the most superior to use strip mining transformation (surface mining).Compare with underground mining, the strip mining transformation advantage is that the utilization of resources is abundant, the rate of extraction is high, the rate of dilution is low, is suitable for the big machinery construction, and it is fast to build the ore deposit, and output is big, and labor productivity is high, and cost is low, and condition of labor is good, production safety.But need dump a large amount of rocks, especially darker opencut often takies more farmland.
The refuse dump (dump) claim waste-rock yard again, is meant that mining dumps the place that thing is concentrated discharging.The refuse dump is the loose heap pad of a kind of huge manual work, has serious potential safety hazard.The refuse dump unstability will cause a mine soil disaster and Important Project accident, not only have influence on the ordinary production in mine, also will make the mine suffer enormous economic loss.Simultaneously, the soil erosion of refuse dump and barren hill make ecological environment become bad again.
Summary of the invention
The deficiency that the present invention is directed to prior art provides a kind of surface mine refuse dump slope treatment method.
The present invention adopts following technical scheme:
A kind of surface mine refuse dump slope treatment method is 1 with the grade of side slope arrangement: 1.5-1: 3, and cohesive soil was got 1: 1.5, and grit stone was got 1: 3, and other great soil group is got median; Build platform (2): the every rising 6-12m of vertical height builds levelling bench, and width is 5m; Build horizontal rows ditch (3): build the horizontal rows ditch at the platform middle part, discharge section is trapezoidal, bottom width 1m, and top width 2m, height 1m is with the concrete precast block lining cutting or build; Build drain way (4): horizontal direction is every on domatic builds a drain way perpendicular to the horizontal rows ditch at a distance from 30m, in order to drain the current in the horizontal ditch; The top, refuse dump is trimmed to certain slope, is convenient to rain drainage, and the gradient is looked location precipitation size and decided, and northern α=2-3 °, southern α=3-5 °; If top, the refuse dump gradient does not reach aforementioned requirement, build net of canals and ditches (6) at the top, so that rainfall runoff compiles drainage fast, directly excavation forms, not lining cutting, and be connected to drain way; Vegetation slope pavement: be prevention soil and water loss, stable side slope is planted shrub (7) on side slope, utilize its root system soil and slope protection; The plantation arbor at the top, refuse dump.
Advantage of the present invention is: on original refuse dump through limited engineering and biological control measure transformation, can effect a radical cure the potential safety hazard of surface mining refuse dump, soil erosion is greatly alleviated, improve the ecological environment, beautify mining area and surrounding enviroment.Have small investment simultaneously, the characteristics that the duration is short, because simple in structure, the later maintenance expense is low.
Description of drawings
Fig. 1 is the inventive method sketch map.
The specific embodiment
Below in conjunction with specific embodiment, the present invention is elaborated.
Press with reference to figure 1 regulation side slope 1: with grade of side slope (tangent value of slope angle) arrangement is 1: 1.5-1: 3, and cohesive soil was got 1: 1.5, and grit stone was got 1: 3, and other great soil group is got median.
Build platform 2: the every rising 6-12m of vertical height (cohesive soil is got 12m, and grit stone is got 6m, and other great soil group is got median) and build levelling bench, width is 5m.
Build horizontal rows ditch 3: build the horizontal rows ditch at the platform middle part, discharge section is trapezoidal, bottom width 1m, and top width 2m, height 1m is with the concrete precast block lining cutting or build.
Build drain way 4: horizontal direction is every on domatic builds a drain way perpendicular to the horizontal rows ditch at a distance from 30m, in order to drain the current in the horizontal ditch.Section configuration, size and lining cutting mode are the same.
The top, refuse dump is trimmed to certain slope, is convenient to rain drainage, and the gradient is looked location precipitation size and decided, and northern α=2-3 °, southern α=3-5 °.If top, the refuse dump gradient does not reach aforementioned requirement, build net of canals and ditches 6 at the top, so that rainfall runoff compiles drainage fast, directly excavation forms, not lining cutting, and be connected to drain way.
Vegetation slope pavement: be prevention soil and water loss, stable side slope, plantation shrub 7 utilizes its root system soil and slope protection on side slope; The plantation arbor at the top, refuse dump, density is looked tree characteristics and is decided, and under its normal growth condition, adopts dense planting.Seeds are selected local autochthonal seeds for use, can guarantee survival rate.
Should be understood that, concerning those of ordinary skills, can improve or conversion, and all these improvement and conversion all should belong to the protection domain of accompanying claims of the present invention according to above-mentioned explanation.

Claims (1)

1. a surface mine refuse dump slope treatment method is characterized in that, is 1 with the grade of side slope arrangement: 1.5-1: 3, and cohesive soil was got 1: 1.5, and grit stone was got 1: 3, and other great soil group is got median; Build platform (2): the every rising 6-12m of vertical height builds levelling bench, and width is 5m; Build horizontal rows ditch (3): build the horizontal rows ditch at the platform middle part, discharge section is trapezoidal, bottom width 1m, and top width 2m, height 1m is with the concrete precast block lining cutting or build; Build drain way (4): horizontal direction is every on domatic builds a drain way perpendicular to the horizontal rows ditch at a distance from 30m, in order to drain the current in the horizontal ditch; The top, refuse dump is trimmed to certain slope, is convenient to rain drainage, and the gradient is looked location precipitation size and decided, and northern α=2-3 °, southern α=3-5 °; If top, the refuse dump gradient does not reach aforementioned requirement, build net of canals and ditches (6) at the top, so that rainfall runoff compiles drainage fast, directly excavation forms, not lining cutting, and be connected to drain way; Vegetation slope pavement: be prevention soil and water loss, stable side slope is planted shrub (7) on side slope, utilize its root system soil and slope protection; The plantation arbor at the top, refuse dump.
CN201210214485.5A 2012-06-25 2012-06-25 Method for treating dump slope of surface mine Expired - Fee Related CN102733401B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210214485.5A CN102733401B (en) 2012-06-25 2012-06-25 Method for treating dump slope of surface mine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210214485.5A CN102733401B (en) 2012-06-25 2012-06-25 Method for treating dump slope of surface mine

Publications (2)

Publication Number Publication Date
CN102733401A true CN102733401A (en) 2012-10-17
CN102733401B CN102733401B (en) 2015-05-06

Family

ID=46989658

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210214485.5A Expired - Fee Related CN102733401B (en) 2012-06-25 2012-06-25 Method for treating dump slope of surface mine

Country Status (1)

Country Link
CN (1) CN102733401B (en)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102888832A (en) * 2012-10-22 2013-01-23 金丹越 Construction method of furrow-shaped slow flow ecological purification system
CN102913246A (en) * 2012-10-30 2013-02-06 中国科学院地质与地球物理研究所 Solid potash ore open-pit mining method under condition of tropical monsoon climate
CN103277136A (en) * 2013-04-15 2013-09-04 中国神华能源股份有限公司 Draining system
CN103866774A (en) * 2014-03-31 2014-06-18 张锦宇 Ditch pipe network protection body for slope protection and collapsing hill drainage and soil fixation
CN103999592A (en) * 2014-05-26 2014-08-27 华南农业大学 Method for avoiding vegetation degradation of acid mine waste rock yard
CN104234010A (en) * 2014-08-15 2014-12-24 内蒙古大学 Construction method for ecological draining and accumulating water channel
CN105075551A (en) * 2014-05-07 2015-11-25 黄弘 Method for afforesting terrace planting tank type side slope
CN105155555A (en) * 2015-06-20 2015-12-16 广东安元矿业勘察设计有限公司 Method for preventing water and soil loss in refuse dump
CN106688357A (en) * 2016-12-19 2017-05-24 陈贺铭 Iron mine waste land vegetation recovery method
CN107152030A (en) * 2017-06-30 2017-09-12 西安科技大学 A kind of Slope of Open Pit Coal Mine administering method
CN107724402A (en) * 2017-11-08 2018-02-23 广西南宁胜祺安科技开发有限公司 A kind of spoil ground regulation method
CN109555139A (en) * 2018-12-29 2019-04-02 内蒙古蒙草生态环境(集团)股份有限公司 Extremely frigid zones collapsibility refuse dump abrupt slope means of defence
CN109566290A (en) * 2019-01-10 2019-04-05 辽宁大学 A kind of Mine production side slope vegetation restorative procedure

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0813500A (en) * 1994-07-04 1996-01-16 Studio Kiyabu:Kk Slope surface protection net for drainage channel
JP2009243225A (en) * 2008-03-31 2009-10-22 Railway Technical Res Inst Method for forming mixture of long fiber-hardener-soil
CN102071697A (en) * 2011-02-12 2011-05-25 河海大学 Hard reinforced concrete revetment slope biological repairing method
CN102080381A (en) * 2010-12-31 2011-06-01 佛山市顺德电力设计院有限公司 Method for managing landslip of side slope landslide for transformer substation
CN102418346A (en) * 2011-10-13 2012-04-18 中钢集团马鞍山矿山研究院有限公司 Mine dump horizontal flat plate remediation and ecological restoration method
CN102444134A (en) * 2011-10-09 2012-05-09 东南大学 Slope protecting method based on slope with soil layer as upper part and rock layer as lower part

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0813500A (en) * 1994-07-04 1996-01-16 Studio Kiyabu:Kk Slope surface protection net for drainage channel
JP2009243225A (en) * 2008-03-31 2009-10-22 Railway Technical Res Inst Method for forming mixture of long fiber-hardener-soil
CN102080381A (en) * 2010-12-31 2011-06-01 佛山市顺德电力设计院有限公司 Method for managing landslip of side slope landslide for transformer substation
CN102071697A (en) * 2011-02-12 2011-05-25 河海大学 Hard reinforced concrete revetment slope biological repairing method
CN102444134A (en) * 2011-10-09 2012-05-09 东南大学 Slope protecting method based on slope with soil layer as upper part and rock layer as lower part
CN102418346A (en) * 2011-10-13 2012-04-18 中钢集团马鞍山矿山研究院有限公司 Mine dump horizontal flat plate remediation and ecological restoration method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘陶安等: ""铀矿山废石场边坡稳定化设计"", 《铀矿冶》 *

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102888832A (en) * 2012-10-22 2013-01-23 金丹越 Construction method of furrow-shaped slow flow ecological purification system
CN102913246A (en) * 2012-10-30 2013-02-06 中国科学院地质与地球物理研究所 Solid potash ore open-pit mining method under condition of tropical monsoon climate
CN102913246B (en) * 2012-10-30 2014-10-08 中国科学院地质与地球物理研究所 Solid potash ore open-pit mining method under condition of tropical monsoon climate
CN103277136A (en) * 2013-04-15 2013-09-04 中国神华能源股份有限公司 Draining system
CN103866774A (en) * 2014-03-31 2014-06-18 张锦宇 Ditch pipe network protection body for slope protection and collapsing hill drainage and soil fixation
CN105075551A (en) * 2014-05-07 2015-11-25 黄弘 Method for afforesting terrace planting tank type side slope
CN103999592A (en) * 2014-05-26 2014-08-27 华南农业大学 Method for avoiding vegetation degradation of acid mine waste rock yard
CN103999592B (en) * 2014-05-26 2016-08-24 华南农业大学 A kind of method preventing acid mining area waste-rock yard vegetation degeneration
CN104234010B (en) * 2014-08-15 2017-05-17 内蒙古大学 Construction method for ecological draining and accumulating water channel
CN104234010A (en) * 2014-08-15 2014-12-24 内蒙古大学 Construction method for ecological draining and accumulating water channel
CN105155555A (en) * 2015-06-20 2015-12-16 广东安元矿业勘察设计有限公司 Method for preventing water and soil loss in refuse dump
CN106688357A (en) * 2016-12-19 2017-05-24 陈贺铭 Iron mine waste land vegetation recovery method
CN107152030A (en) * 2017-06-30 2017-09-12 西安科技大学 A kind of Slope of Open Pit Coal Mine administering method
CN107724402A (en) * 2017-11-08 2018-02-23 广西南宁胜祺安科技开发有限公司 A kind of spoil ground regulation method
CN107724402B (en) * 2017-11-08 2019-06-07 广西南宁胜祺安科技开发有限公司 A kind of spoil ground regulation method
CN109555139A (en) * 2018-12-29 2019-04-02 内蒙古蒙草生态环境(集团)股份有限公司 Extremely frigid zones collapsibility refuse dump abrupt slope means of defence
CN109566290A (en) * 2019-01-10 2019-04-05 辽宁大学 A kind of Mine production side slope vegetation restorative procedure

Also Published As

Publication number Publication date
CN102733401B (en) 2015-05-06

Similar Documents

Publication Publication Date Title
CN102733401B (en) Method for treating dump slope of surface mine
CN103039147B (en) Reclamation method for sunk paddy field caused by mining in mountainous regions
CN105230323B (en) A kind of growth-promoting binary stereoscopic configurations pattern against corrosion suitable for feldspathic sandstone small watershed
CN101580305B (en) Wetland governance method for improving ecological environmental in reservoir falling zone
CN106759104B (en) Ecological slope protection structure and construction method
CN102392455A (en) Technique for safe improvement as well as ecological repair and reconstruction of mine soil discharge yard
CN102392454A (en) Adverse-slope flat-plate treating and ecological restorative measure for refuse dump
CN204220612U (en) Repair the green of heavy metals mining area soil and plant structure
CN210827501U (en) Greening structure of stock ground rock slope
CN106368227A (en) Water erosion prevention system and method for ecology of slope of abandoned rear-earth mine land
CN203977363U (en) A kind of ecological slope protection
CN109005722B (en) Comprehensive reclamation method for land reclamation of iron ore waste stone yard
CN102418346A (en) Mine dump horizontal flat plate remediation and ecological restoration method
CN110424421A (en) Abandoned mine raised fields goes along with sb. to guard him ecological restoring method
CN104294830A (en) Side slope ecological protection and recovery method and arrangement structure
CN105672198B (en) Land-building and plowing structure for reservoir inundation and immersion area and construction method thereof
CN114134877B (en) Treatment method for mining ground cracks of shallow coal seam in hilly and hilly areas of peaked landform
CN105340408A (en) Afforestation and soil preparation method for rocky barren mountains in semi-arid regions
CN202509509U (en) Novel slope protection structure
CN211922648U (en) Ecological restoration type rare earth tailings
CN104695379A (en) Ecological river channel revetment structure
CN203096697U (en) Ballast field structure at earth and rockfill dam toe
CN202369883U (en) Road base treatment structure for soft soil region
CN206245319U (en) A kind of anti-rare earth slash side slope water erosion system
CN205546463U (en) Ecological recovery system of slope vegetation

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
DD01 Delivery of document by public notice

Addressee: Northwest Research Institute of Engineering Investigations and Design

Document name: Notification to Pay the Fees

CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20150506

Termination date: 20160625

CF01 Termination of patent right due to non-payment of annual fee