CN203096697U - Ballast field structure at earth and rockfill dam toe - Google Patents
Ballast field structure at earth and rockfill dam toe Download PDFInfo
- Publication number
- CN203096697U CN203096697U CN 201320095576 CN201320095576U CN203096697U CN 203096697 U CN203096697 U CN 203096697U CN 201320095576 CN201320095576 CN 201320095576 CN 201320095576 U CN201320095576 U CN 201320095576U CN 203096697 U CN203096697 U CN 203096697U
- Authority
- CN
- China
- Prior art keywords
- earth
- dam
- ballast
- field
- slag
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Abstract
The utility model discloses a ballast field structure at an earth and rockfill dam toe. A ballast field is arranged at the dam toe of an earth and rockfill dam. The ballast field comprises ballast piled-up bodies, a ballast piled-up body transition layer, a ballast field foundation drainage layer, ballast field top drainage ditches and earth-up green areas. The gradient of the upper stream of the ballast field is the same as the gradient of the lower stream of a dam body of the earth and rockfill dam. Slopes are cut and grades are formed at the lower stream of the ballast field. The ballast piled-up body transition layer is arranged between the ballast piled-up bodies and filling materials of the earth and rockfill dam. The ballast field foundation drainage layer is connected with a dam foundation drainage layer of the earth and rockfill dam. The ballast field top drainage ditches are arranged at the junction positions of the ballast piled-up bodies, the earth and rockfill dam and mountains, and connected with drainage ditches of the earth and rockfill dam and the mountains. The earth-up green areas are arranged at the top face of the ballast field and the lower stream slope face of the ballast field. Due to the fact that the ballast field is arranged at the dam toe of the earth and rockfill dam, land acquisition and immigrants of the ballast field and connecting roads of the ballast field can be reduced, the engineering protection amount and the waste ballast haul distance of the ballast field are reduced, the stability of the dam body is improved, and environment in the dam area is beautified.
Description
Technical field
The utility model relates to the Hydraulic and Hydro-Power Engineering field, relates in particular to slag field structure after a kind of Earth and Rockfill Dam.
Background technology
The main advantage of earth and rockfill dam construction is that utilization excavation slag charge is built a dam, but not every excavation slag charge can both such as table soil, because of containing plants such as radicula palpus, herbaceous plant and covering grass in the organic soil of top layer, can not be gone up the dam as the dam embankment material; The earthwork or the complete severely-weathered rock mass of part of other excavation may the diseconomy of bringing such as roll and thrown aside because of dam on it must slow down dam slope or reinforcement, and these abandon material all needs the slag field to hold.Engineering can select natural terrain cheuch away from Ba Qu as the slag field usually; expropriation of land immigrant and waste haul distance problem far away with regard to having brought slag field and linking-up road thereof like this; the general sloping high ditch of natural terrain cheuch is steep simultaneously, the charge for remittance amount is big; make that slag field preventive works amount is bigger, not only uneconomical but also not environmental protection.
The utility model content
The purpose of this utility model is to provide a kind of expropriation of land and immigrant who reduces slag field and linking-up road thereof, reduce slag field preventive works amount and waste haul distance, increase dam body and stablize, beautify slag field structure after the Earth and Rockfill Dam of dam district environment, not only economy but also environmental protection, thereby solve the foregoing problems that exists in the prior art.
To achieve these goals, the technical solution adopted in the utility model is as follows:
Slag field structure after a kind of Earth and Rockfill Dam, after the slag field was arranged in the dam of earth and rockfill dam, described slag field comprised slag body, slag body transition zone, slag field foundation drainage layer, gutter, top, slag field and earthing green area.
Preferably, upstream, the described slag field gradient is identical with the dam body downstream gradient of described earth and rockfill dam, and described slag is swum after the match and cut the slope and open level.
Preferably, filling of described slag body and described earth and rockfill dam is provided with described slag body transition zone between the material.
Preferably, described slag field foundation drainage layer links to each other with the drain in dam foundation layer of described earth and rockfill dam, and gutter, top, described slag field is located at slag body and described earth and rockfill dam and massif intersection, links to each other with described earth and rockfill dam and massif gutter.
Preferably, it is domatic that described earthing green area is arranged at the end face and the downstream of described slag field.
The beneficial effects of the utility model are:
(1) after the slag field was arranged in Earth and Rockfill Dam, a slag body part was directly laminated on the dam facing of downstream, can reduce the expropriation of land and the immigrant of slag field and linking-up road thereof; (2) can partly utilize the draining and the safeguard procedures thereof of earth and rockfill dam, reduce slag field engineering protection amount; (3) close on engineering excavation districts such as earth and rockfill dam, reduced the waste haul distance; (4) the slag body can be used as the base of dam ballast, has increased the stability of dam body; (5) the domatic earthing in slag field end face and downstream has been afforested and beautified dam district environment; (6) not only economy but also environmental protection of slag field structure after the Earth and Rockfill Dam can be widely used in Hydraulic and Hydro-Power Engineering slag field structure.
Description of drawings
Fig. 1 is a slag field structure floor map after the Earth and Rockfill Dam of the present utility model;
Fig. 2 is a slag field structure generalized section after the Earth and Rockfill Dam of the present utility model;
Wherein: the 1---earth and rockfill dam; 2---slag field; 3---slag body; 4---slag body transition zone; 5---slag field foundation drainage layer; 6---earth and rockfill dam dam foundation drainage blanket; Gutter, top, 7---slag field; The 8---massif; 9---earth and rockfill dam and massif gutter; 10---earthing green area.
The specific embodiment
In order to make the purpose of this utility model, technical scheme and advantage clearer,, the utility model is further elaborated below in conjunction with accompanying drawing.Should be appreciated that the specific embodiment described herein only in order to explanation the utility model, and be not used in qualification the utility model.
As shown in Figure 1, 2, the utility model discloses slag field structure after a kind of Earth and Rockfill Dam, after the slag field was arranged in the dam of earth and rockfill dam, described slag field comprised slag body, slag body transition zone, slag field foundation drainage layer, gutter, top, slag field and earthing green area.Upstream, the described slag field gradient is identical with the dam body downstream gradient of described earth and rockfill dam, and described slag is swum after the match and cut the slope and open level, to satisfy the homeostasis requirement.Filling of described slag body and described earth and rockfill dam is provided with described slag body transition zone between the material, the slag body can roll also and can not roll according to the impact analysis of slag field sedimentation to dam body.Described slag field foundation drainage layer links to each other with the drain in dam foundation layer of described earth and rockfill dam, gutter, top, described slag field is located at slag body and described earth and rockfill dam and massif intersection, link to each other with described earth and rockfill dam and massif gutter, slag field drainage system must satisfy the draining level of protection of earth and rockfill dam and slag field simultaneously.It is domatic that described earthing green area is arranged at the end face and the downstream of described slag field, is used for solid slag bank protection.
Be that example further specifies in conjunction with the accompanying drawings with certain major works that has adopted technical solutions of the utility model below: bituminous concrete surface sheetpile masonry dam crest elevation 1943m, the maximum height of dam 95.2m in base of dam place, downstream dam slope 1: 1.6 is arranged slag field 2 behind earth and rockfill dam 1 dam.Slag field 2 crest level 1875m, maximum slag height 50.2m, slag capacity 920,000 m
3The slag field 2 upstream gradients 1: 1.6 are identical with the downstream dam slope, and slag field 2 downstream gradients are 1: 2, establish the wide packway of 2m at the 1855m elevation.Slag body 3 and earth and rockfill dam 1 fill establishes slag body transition zone 4 thick 0.6m between the material, slag body 3 does not roll.The 5 suitable bottom of trench setting of slag field foundation drainage layer, wide 45m, high 3m, the upstream links to each other with earth and rockfill dam dam foundation drainage blanket 6; Gutter, top, slag field 7 adopts stone masonry to build by laying bricks or stones, wide 1.2m, and high 0.6m is located at slag body 3 and earth and rockfill dam 1 and massif 8 intersections, links to each other with earth and rockfill dam and massif gutter 9, and slag field drainage system can satisfy the draining level of protection of earth and rockfill dam 1 and slag field 2 simultaneously.The thick 1m of earthing green area 10 organic soils, it is domatic to be arranged at slag field end face and downstream, and the solid slag corrosion protection shelter-forest of grass is irritated in plantation, to irritate grass, plantation part arbor.
By adopting the disclosed technique scheme of the utility model, obtained following useful effect:
(1) after the slag field was arranged in the loose rock dam dam, a slag body part was directly laminated on the dam facing of downstream, had cancelled former design at southern side, dam slag capacity 610,000 m
3A slag field, reduced No. two slag fields, east side, dam capacity 310,000 m simultaneously
3, can reduce slag field and linking-up road thereof and occupy cultivated land and forest land 37hm
2, reduce the immigrant; (2) can partly utilize the draining and the safeguard procedures thereof of earth and rockfill dam, reduce former slag field engineering protection amount; (3) close on engineering excavation districts such as loose rock dam, reduced the about 1km of waste haul distance; (4) the slag body can be used as the base of dam ballast, has increased the stability of dam body, and dangerous slide plane buckling safety factor increases by 21% along the basis to make loose rock dam downstream dam slope buckling safety factor raising 5%, downstream dam slope; (5) the domatic earthing in slag field end face and downstream has been afforested and beautified dam district environment; (6) save about 4,000,000 yuan of slag field fees paid for taking rural land, engineering measure expense and waste freight charges, not only economy but also environmental protection.
The above only is a preferred implementation of the present utility model; should be pointed out that for those skilled in the art, under the prerequisite that does not break away from the utility model principle; can also make some improvements and modifications, these improvements and modifications also should be looked protection domain of the present utility model.
Claims (5)
1. slag field structure after the Earth and Rockfill Dam is characterized in that after the slag field was arranged in the dam of earth and rockfill dam, described slag field comprised slag body, slag body transition zone, slag field foundation drainage layer, gutter, top, slag field and earthing green area.
2. slag field structure after the Earth and Rockfill Dam according to claim 1 is characterized in that, upstream, the described slag field gradient is identical with the dam body downstream gradient of described earth and rockfill dam, and described slag is swum after the match and cut the slope and open level.
3. slag field structure after the Earth and Rockfill Dam according to claim 1 is characterized in that, filling of described slag body and described earth and rockfill dam is provided with described slag body transition zone between the material.
4. slag field structure after the Earth and Rockfill Dam according to claim 1, it is characterized in that, described slag field foundation drainage layer links to each other with the drain in dam foundation layer of described earth and rockfill dam, gutter, top, described slag field is located at slag body and described earth and rockfill dam and massif intersection, links to each other with described earth and rockfill dam and massif gutter.
5. slag field structure after the Earth and Rockfill Dam according to claim 1 is characterized in that, it is domatic that described earthing green area is arranged at the end face and the downstream of described slag field.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320095576 CN203096697U (en) | 2013-03-01 | 2013-03-01 | Ballast field structure at earth and rockfill dam toe |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201320095576 CN203096697U (en) | 2013-03-01 | 2013-03-01 | Ballast field structure at earth and rockfill dam toe |
Publications (1)
Publication Number | Publication Date |
---|---|
CN203096697U true CN203096697U (en) | 2013-07-31 |
Family
ID=48848114
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201320095576 Expired - Fee Related CN203096697U (en) | 2013-03-01 | 2013-03-01 | Ballast field structure at earth and rockfill dam toe |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN203096697U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103397618A (en) * | 2013-08-21 | 2013-11-20 | 北京华石纳固科技有限公司 | Simple rockfill warehousing construction method based on transportation cage and used transportation cage |
CN104264635A (en) * | 2014-09-23 | 2015-01-07 | 国家电网公司 | Construction technology of slag stacking behind concrete faced rock-fill dam |
CN114481967A (en) * | 2022-02-24 | 2022-05-13 | 中水北方勘测设计研究有限责任公司 | Construction method of hydraulic engineering waste slag yard |
-
2013
- 2013-03-01 CN CN 201320095576 patent/CN203096697U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103397618A (en) * | 2013-08-21 | 2013-11-20 | 北京华石纳固科技有限公司 | Simple rockfill warehousing construction method based on transportation cage and used transportation cage |
CN103397618B (en) * | 2013-08-21 | 2015-08-26 | 北京华石纳固科技有限公司 | A kind of simple and easy enrockment based on transport cage puts in storage the transport cage of construction method and use |
CN104264635A (en) * | 2014-09-23 | 2015-01-07 | 国家电网公司 | Construction technology of slag stacking behind concrete faced rock-fill dam |
CN114481967A (en) * | 2022-02-24 | 2022-05-13 | 中水北方勘测设计研究有限责任公司 | Construction method of hydraulic engineering waste slag yard |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107558480B (en) | The construction method of the reinforced ecological slope protection structure of roadbed three-dimensional water discharge | |
CN203403426U (en) | Supporting structure of expensive earth road cutting side slope | |
CN105927272A (en) | Floor anchoring constraint tunnel lining structure | |
CN113445396B (en) | High-fill road foundation filling construction method for high liquid limit soil road section | |
CN109024458A (en) | A kind of coal mine subsidence land landscape revetment and the construction method of water-bed antiseepage | |
CN207295358U (en) | A kind of platform back of the body for preventing bumping at bridge-head and road surface drainage structure | |
CN103628488B (en) | A kind of damming method of mine tailing embankment dam | |
CN203096697U (en) | Ballast field structure at earth and rockfill dam toe | |
CN103643689A (en) | Pipe type underground water drainage blind ditch and construction technology and application thereof | |
CN206016853U (en) | Base plate anchors restricted type tunnel lining structure | |
CN102817298B (en) | Construction method on permafrost | |
CN102425175B (en) | Reinforcement protective structure of large spoil disposal area in mountainous area | |
CN106703053A (en) | Construction method for reinforced soil drainage composite revetment structure | |
CN206428602U (en) | Prevent mud from blocking the roadbed both sides shallow seated groundwater connectivity structure with soil erosion | |
CN104264635A (en) | Construction technology of slag stacking behind concrete faced rock-fill dam | |
CN208884292U (en) | Soft soil roadbed and normal roadbed intersection anti-settling structure | |
CN102704437A (en) | Coal mining subsidence area cultivation water source reconstruction method suitable for complex mountain area | |
CN207469190U (en) | A kind of infitration galleries structure of efficient draining | |
CN203741852U (en) | Tubular groundwater drainage and seepage blind ditch | |
CN100567649C (en) | The structure of a kind of bottom of the reservior landfill waste residue | |
CN212742576U (en) | Internal drainage structure of loess high fill side slope | |
CN109403356B (en) | Side slope supporting structure | |
CN209482321U (en) | A kind of slope retaining structure | |
CN209010891U (en) | A kind of multi-functional lobby drainage facility | |
CN206352302U (en) | A kind of protective slope structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20130731 |
|
CF01 | Termination of patent right due to non-payment of annual fee |