CN101602194B - 一种钢制筒体组对接长法 - Google Patents

一种钢制筒体组对接长法 Download PDF

Info

Publication number
CN101602194B
CN101602194B CN2009101598505A CN200910159850A CN101602194B CN 101602194 B CN101602194 B CN 101602194B CN 2009101598505 A CN2009101598505 A CN 2009101598505A CN 200910159850 A CN200910159850 A CN 200910159850A CN 101602194 B CN101602194 B CN 101602194B
Authority
CN
China
Prior art keywords
group
shell ring
turning rolls
desire
special
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN2009101598505A
Other languages
English (en)
Other versions
CN101602194A (zh
Inventor
者中林
秦明诗
赵智峰
付英杰
王军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China No2 Metallurgical Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China No2 Metallurgical Construction Co Ltd filed Critical China No2 Metallurgical Construction Co Ltd
Priority to CN2009101598505A priority Critical patent/CN101602194B/zh
Publication of CN101602194A publication Critical patent/CN101602194A/zh
Application granted granted Critical
Publication of CN101602194B publication Critical patent/CN101602194B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明解决其技术问题所采用的技术方案是:利用主动滚轮架(5)和被动滚轮架(6)作为已组对好筒段(或首个筒节)(1)的支撑体及转动动力源,组对专用滚轮架(3、4)作为欲组对筒节的支撑体,通过调节组对专用滚轮架滚轮的位置来调节筒节接口之间的错口及母线直线度,当接口的间隙、错边量、平整度等调整到符合要求时进行接口的定位焊,之后完成接口的封底焊便完成了一节筒节的组对过程。

Description

一种钢制筒体组对接长法
技术领域
本发明涉及一种筒体制作组对的方法,特别是涉及一种钢制筒体的组对方法。
背景技术
通常由于卷制设备能力的限制,筒形压力容器及风力发电机的锥形塔杆都是由长度不大于3米的筒节组对接长的。而传统的接长方法是在由槽钢或工字钢制作的胎具上用千斤顶从外侧将两段筒节顶紧,内侧用千斤顶或采用在筒体上焊“弯尺弯”打楔子的方法对齐而接长成整体。这种方法存在难度大、作业效率低、制作成本高、安全性差、组对完成后需打掉“弯尺弯”磨平焊点等缺点。
发明内容
为了克服上述缺点,本发明提供了一种筒体组对的新方法。该法是利用主动滚轮架和被动滚轮架作为已组对好的筒段(或首个筒节)支撑体及转动动力源,组对专用滚轮架作为欲组对筒节的支撑体,通过调节组对专用滚轮架滚轮的位置来调节筒节接口之间的错口及母线直线度;其特征是:主动滚轮架、被动滚轮架、组对专用滚轮架顺序排列,已组对好的筒段(或首个筒节)置于主动滚轮架、被动滚轮架上方,而欲组对的筒节位于组对专用滚轮架上方;组对滚轮架的滚轮通过支架与床身滑动联结;组对滚轮架的滚轮通过支架经液压缸联结到床身。
本发明解决其技术问题所采用的技术方案是:利用主动滚轮架和被动滚轮架作为已组对好筒段(或首个筒节)的支撑体及转动动力源,组对专用滚轮架作为欲组对筒节的支撑体,通过调节组对专用滚轮架滚轮的位置来调节筒节接口之间的错口及母线直线度,当接口的间隙、错边量、平整度等调整到符合要求时进行接口的定位焊,之后完成接口的封底焊便完成了一节筒节的组对过程。
本发明的有益效果是,提高了筒节的组对质量和工作效率、减小了员工的作业难度。从而使筒体的组对高效安全地进行。
附图说明
下面结合附图和实施例对本发明作进一步说明。
图1是筒节与组对设备位置关系主视图。
图2是图1的府视图。
图3是组对点左右偏移示意图。
图4、图5是组对点上下偏移示意图。
图6是组对点合适位置示意图。
图中1欲组对筒节,2已组对完成或首节筒节,3、4组对滚轮架,5主动滚轮架,6被动滚轮架,7组对滚轮架左滚轮,8组对滚轮架上侧液压缸,9组对滚轮架下侧液压缸,10组对滚轮架右滚轮。
具体实施方式
从图1和图2可以看出,已组对完成或首节筒节2位于主动滚轮架3和被动滚轮架4上,而欲组对的筒节1位于组对专用滚轮架5和6上,组对点位于两筒节接口的最下侧。
下面结合图3到图6将具体的实施方式叙述如下:
1、组对前的准备工作
A、一般来说,欲组对的两筒节的接口处的外圆直径应该是相等的,但由于筒节在卷制、纵缝焊接等过程中往往会产生偏差,因此在组对前必须测量其周长差并算出两节接口处的错边量,以避免组对后出现局部错边超差的质量问题;
B、根据风电塔筒的技术要求,两段相接的筒节的纵焊缝应错开180°,因此要在两筒节的相应位置作出初始组对点的标记;
C、将已组对完成或首节筒节2(首节是带法兰的)放在主动滚轮架5和被动滚轮架6上适当的位置;
D、将欲组对的筒节1位于组对专用滚轮架3和4上适当的位置并使组对点标记位于下侧。
2、筒节的组对
A、转动行走主动滚轮架5使已组对完成或首节筒节2的组对点标记与将欲组对的筒节1的组对点标记对应;
B、此时,如出现图3所示的筒节欲组对的筒节1向右偏差,则通过组对滚轮架上侧液压缸8,组对滚轮架下侧液压缸9,分别驱动组对滚轮架左滚轮7和组对滚轮架右滚轮10向左移动,从而使欲组对的筒节1向左侧移动直到图6所示的位置。反之则向右移动组对滚轮架滚轮7和10来调节;
C、如出现图4所示的筒节欲组对的筒节1向上偏差,则通过组对滚轮架上侧液压缸8,组对滚轮架下侧液压缸9,分别驱动组对滚轮架左滚7轮和组对滚轮架右滚轮10向外移动,从而使欲组对的筒节1向下移动直到图6所示的位置;
D、如出现图5所示的筒节欲组对的筒节1向下偏差,则通过组对滚轮架上侧液压缸8,组对滚轮架下侧液压缸9,分别驱动组对滚轮架左滚7轮和组对滚轮架右滚轮10向内移动,从而使欲组对的筒节1向上移动直到图6所示的位置;
E、向外调节组对滚轮架3上滚轮的位置使欲组对的筒节1与已组对完成或首节筒节2接口上部约有5~10毫米的间隙(如图1所示);
F、若欲组对的筒节1与已组对完成或首节筒节2接口存在如图2所侧面缝隙,则可通过单独调节组对滚轮架3和4的滚轮位置使左右侧的间隙均匀;
G、驱动主动滚轮架5和被动滚轮架6,使已组对完成或首节筒节2与欲组对的筒节1顶紧,调整好错边量便可进行定位焊;
H、转动主动滚轮架5使筒节的弧面转过约150毫米的弧长按上述方法进行下一个组对点的调整直到一周全部组对完毕
I、进行接口内环缝的封底焊;
J、向外驱动节组对滚轮架3和4的滚轮7和10,使其与筒体脱离;
K、驱被动滚轮架6,使已组对完成的筒节2随之右移直到欲组对口位于组对滚轮架4和行走主动滚轮架5之间(此时主动滚轮架5不动)顺序进行下一节的组对直到整段筒体组对完成。
3、组对时应注意的问题
A、当已组对完成的筒节2的重心位置超出主动滚轮架5和被动滚轮架6的支撑范围时,要用起重设备将刚组对的筒节侧吊起使筒体与被动滚轮架6保持接触而与主动滚轮架5脱开,此时向右驱动被动滚轮架6向左驱动主动滚轮架5到合适位置就位筒体,以防筒体的倾翻;
B、组对时要保持筒体的转向一致,并顺序组对。

Claims (1)

1.一种筒节组对的方法,利用主动滚轮架和被动滚轮架作为已组对好的筒节或首个筒节的支撑体及转动动力源,组对专用滚轮架作为欲组对筒节的支撑体;主动滚轮架、被动滚轮架、组对专用滚轮架顺序排列,已组对好的筒节或首个筒节置于主动滚轮架、被动滚轮架上方,而欲组对筒节位于组对专用滚轮架上方,其特征在于,组对专用滚轮架有左右两个滚轮通过支架与床身滑动联结,两个滚轮分别通过支架经上侧和下侧两个液压缸联结到床身,调节筒节接口之间的错口和母线直线度的具体方法如下:
1)如出现欲组对筒节向右偏差,则通过上侧液压缸和下侧液压缸,分别驱动左滚轮和右滚轮向左移动,从而使欲组对筒节向左侧移动,反之则向右移动左滚轮和右滚轮来调节;
2)如出现欲组对筒节向上偏差,则通过上侧液压缸和下侧液压缸,分别驱动左滚轮和右滚轮向外移动,从而使欲组对筒节向下移动,反之则向内移动左滚轮和右滚轮来调节;
3)若欲组对筒节与已组对好的筒节或首节筒节接口存在侧面缝隙,则可通过单独调节组对专用滚轮架的滚轮位置使左右侧的间隙均匀。
CN2009101598505A 2009-07-11 2009-07-11 一种钢制筒体组对接长法 Active CN101602194B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101598505A CN101602194B (zh) 2009-07-11 2009-07-11 一种钢制筒体组对接长法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101598505A CN101602194B (zh) 2009-07-11 2009-07-11 一种钢制筒体组对接长法

Publications (2)

Publication Number Publication Date
CN101602194A CN101602194A (zh) 2009-12-16
CN101602194B true CN101602194B (zh) 2011-02-09

Family

ID=41468165

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101598505A Active CN101602194B (zh) 2009-07-11 2009-07-11 一种钢制筒体组对接长法

Country Status (1)

Country Link
CN (1) CN101602194B (zh)

Families Citing this family (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102717223B (zh) * 2012-06-30 2014-12-10 成都阿朗科技有限责任公司 一种可调式滚轮架
CN102990275B (zh) * 2012-11-19 2015-05-20 南京奥特电气股份有限公司 大管径筒节三维调节装置
CN102935575B (zh) * 2012-11-19 2015-05-20 南京奥特电气股份有限公司 大管径筒节组对接长装置
CN102922207B (zh) * 2012-11-21 2015-04-29 无锡三虹重工机械设备有限公司 一种用于筒体焊接接长的装置
CN102922202A (zh) * 2012-11-21 2013-02-13 无锡三虹重工机械设备有限公司 组对焊接滚轮架
CN103331534B (zh) * 2012-12-18 2015-08-12 南通振华重型装备制造有限公司 海上风电用圆筒体鳄式组对工艺
CN103008962A (zh) * 2012-12-24 2013-04-03 滁州永强汽车制造有限公司 阻浪板焊接方法和阻浪板焊接辅助设备
CN103103928B (zh) * 2013-03-08 2015-09-23 中国建筑第六工程局有限公司 用于张拉杆与斜拉索头吻合安装的辅助工具及其使用方法
CN103223658A (zh) * 2013-04-28 2013-07-31 江苏曙光石油钻采设备有限公司 钻杆接头卧姿上扣台架
CN103567695B (zh) * 2013-11-04 2015-05-20 南京奥特电气股份有限公司 一种筒体组对装置
CN105195962A (zh) * 2015-10-22 2015-12-30 南京奥特电气股份有限公司 一种三接一管道组对接长装置
CN105195961A (zh) * 2015-10-22 2015-12-30 南京奥特电气股份有限公司 一种二接一管道组对接长装置
CN105904111A (zh) * 2016-04-05 2016-08-31 福建帆新能源装备制造有限公司 一种大直径风电塔筒用塔段的组对工艺
CN105834622A (zh) * 2016-05-26 2016-08-10 永胜机械工业(昆山)有限公司 一种压力容器筒节组对装置
CN106623515B (zh) * 2016-12-30 2019-04-30 深圳赤湾胜宝旺工程有限公司 重型钢管匹配及组对方法与系统
CN108750910B (zh) * 2017-02-08 2020-02-25 林兵兵 一种风电机架翻转方法
CN110434545A (zh) * 2019-09-02 2019-11-12 湖南万征机械科技有限公司 一种用于大型工程机械设备滚轮结构
CN110539077A (zh) * 2019-09-30 2019-12-06 北京星航机电装备有限公司 一种轻量化结构舱段与支耳的激光焊接变形控制工装及变形控制方法
CN110814617B (zh) * 2019-11-29 2024-08-23 山东中车同力钢构有限公司 一种风电塔筒法兰组对装置及方法
WO2022007872A1 (zh) * 2020-07-09 2022-01-13 中建三局第二建设工程有限责任公司 角度可调管道组对机器人及管道组角度调节方法
CN112570968B (zh) * 2020-12-08 2022-05-06 上海振华重工启东海洋工程股份有限公司 一种桩腿筒节对接方法
CN113909647B (zh) * 2021-09-17 2023-05-12 中信重工机械股份有限公司 一种海上风电基础大型钢管桩的快速制作方法
CN114012372B (zh) * 2022-01-05 2022-04-08 中交三航(南通)海洋工程有限公司 一种超大直径单桩复合筒的建造方法
CN114623045B (zh) * 2022-05-16 2022-07-19 中交三航(南通)海洋工程有限公司 一种超大直径单桩复合筒轴线调整方法

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3970295A (en) * 1975-02-03 1976-07-20 The Pandjiris Weldment Co. Pipe fitting locator apparatus
DE19961596C1 (de) * 1999-12-21 2001-04-05 Bergrohr Gmbh Siegen Vorrichtung zur Beförderung von längszuschweissenden Rohren
CN2432002Y (zh) * 2000-07-26 2001-05-30 胜利石油管理局工程建设一公司技术发展中心 管道三维对口器
CN2514965Y (zh) * 2001-10-22 2002-10-09 白天海 管道对口器
CN2589146Y (zh) * 2002-12-31 2003-12-03 北京宣武华光焊接工艺成套装备联营公司 多元滚轮架
CN2825214Y (zh) * 2005-09-09 2006-10-11 中国石油天然气管道局 双联管对口装置

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3970295A (en) * 1975-02-03 1976-07-20 The Pandjiris Weldment Co. Pipe fitting locator apparatus
DE19961596C1 (de) * 1999-12-21 2001-04-05 Bergrohr Gmbh Siegen Vorrichtung zur Beförderung von längszuschweissenden Rohren
CN2432002Y (zh) * 2000-07-26 2001-05-30 胜利石油管理局工程建设一公司技术发展中心 管道三维对口器
CN2514965Y (zh) * 2001-10-22 2002-10-09 白天海 管道对口器
CN2589146Y (zh) * 2002-12-31 2003-12-03 北京宣武华光焊接工艺成套装备联营公司 多元滚轮架
CN2825214Y (zh) * 2005-09-09 2006-10-11 中国石油天然气管道局 双联管对口装置

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
JP昭61-14095A 1986.01.22
JP特开平11-197886A 1999.07.27

Also Published As

Publication number Publication date
CN101602194A (zh) 2009-12-16

Similar Documents

Publication Publication Date Title
CN101602194B (zh) 一种钢制筒体组对接长法
CN202317572U (zh) 大型筒体组对装置
CN204053371U (zh) 一种可调节的钢管合缝装置
CN104148873B (zh) 一种可调节的钢管合缝装置
CN104384192B (zh) 拉管机和无缝管轧制方法
CN113732585B (zh) 一种厚壁金属直缝焊管焊缝自动对齐快速焊接装置及方法
CN103331534A (zh) 海上风电用圆筒体鳄式组对工艺
CN102794623B (zh) 用于长皮带运输机的皮带收取装置的使用方法
CN104476192B (zh) 一种罐体自动卷制成型装置及成型方法
CN201376016Y (zh) 大直径钢管卷制支撑装置
CN219818673U (zh) 一种塔筒纵缝焊接辅助支撑
CN211464299U (zh) 一种高效铁碳钢管下料传送装置
CN202527476U (zh) 一种轧机机架辊检修工装
CN104998982A (zh) 一种高精度可调节扩径机
CN104014596A (zh) 一种连退线活套小车转向辊上带钢跑偏的调整方法
CN106996094B (zh) 一种用于拔出防渗墙接头管的全自动拔管机及其应用
CN114012372B (zh) 一种超大直径单桩复合筒的建造方法
CN203197060U (zh) 冷弯成型快换机架的换辊装置
CN201791802U (zh) 弧线下调式卷板机侧托架
CN113458195B (zh) 具有后置卸料板幅度调节结构的数控万能卷板机及方法
CN101653783B (zh) 顶头夹持装置
CN213245207U (zh) 一种连铸坯输送辊道的连铸坯对正装置
CN204248400U (zh) 一种罐体自动卷制成型装置
CN103331343A (zh) 高强度大尺寸板体的锥度卷制工艺
CN103182979A (zh) 一种重型轧辊运输车

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee

Owner name: CHINA SECOND METALLURGY GROUP CORPORATION LIMITED

Free format text: FORMER NAME: CHINA NO.2 METALLURGICAL CONSTRUCTION CO., LTD.

CP01 Change in the name or title of a patent holder

Address after: 014010 the Inner Mongolia Autonomous Region Baotou City Queensland Steel Street No. 122

Patentee after: China Second Metallurgy Group Co., Ltd.

Address before: 014010 the Inner Mongolia Autonomous Region Baotou City Queensland Steel Street No. 122

Patentee before: China No.2 Metallurgical Construction Co., Ltd.