CN100478522C - 大桥钢箱提篮拱施工方法 - Google Patents

大桥钢箱提篮拱施工方法 Download PDF

Info

Publication number
CN100478522C
CN100478522C CNB2007100097312A CN200710009731A CN100478522C CN 100478522 C CN100478522 C CN 100478522C CN B2007100097312 A CNB2007100097312 A CN B2007100097312A CN 200710009731 A CN200710009731 A CN 200710009731A CN 100478522 C CN100478522 C CN 100478522C
Authority
CN
China
Prior art keywords
arch
steel
steel box
case beam
steel case
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CNB2007100097312A
Other languages
English (en)
Other versions
CN101148860A (zh
Inventor
周外男
高兴泽
谢季军
李述宝
彭建萍
张大成
赵则锋
聂锦雄
连居
宋伟俊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Major Bridge Engineering Group Co Ltd MBEC
5th Engineering Co Ltd of MBEC
Original Assignee
China Railway Major Bridge Engineering Co Ltd
5th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Major Bridge Engineering Co Ltd, 5th Engineering Co Ltd of MBEC filed Critical China Railway Major Bridge Engineering Co Ltd
Priority to CNB2007100097312A priority Critical patent/CN100478522C/zh
Publication of CN101148860A publication Critical patent/CN101148860A/zh
Application granted granted Critical
Publication of CN100478522C publication Critical patent/CN100478522C/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种使用500吨吊船和满堂支架的大桥钢箱提篮拱施工方法,它先确定大桥的结构型式、矢跨比、拱肋内倾角度、拱轴线型、拱肋断面形式,再安装钢箱梁支架和中跨钢箱梁,然后吊装边拱及边跨钢箱梁,最后吊装拱架。本发明使用全站仪、水准仪全过程进行测量,利用纵、横、竖三向千斤顶精确定位拱肋及钢箱梁,确保了主体结构线形流畅,对整个施工过程进行结构应力及线形监控,确保了结构及施工安全,并通过ANSYS程序计算控制钢结构安装线形,通过传感器来控制主体结构及临时支架应力,采用钢箱梁支架进行施工使施工操作更加简单,易于控制。通过本发明制造出来的钢箱提篮拱桥具有较强抗台风能力,体现了其高效的特点,并具有显著的经济效益。

Description

大桥钢箱提篮拱施工方法
技术领域
本发明涉及大桥施工方法,尤其是涉及一种使用500吨吊船和满堂支架的大桥钢箱提篮拱施工方法。
背景技术
随着我国的经济的发展,需要修建的大跨度桥梁也越来越多,桥梁的结构形式也越来越新颖。常规钢箱提篮拱安装方法一般采用缆索吊机、大跨度龙门吊机斜拉扣索的施工方案,这几种施工方法均需在多台风、海上日潮差达6米的海上进行高空对位与焊接,这样结构线形、焊缝质量就难以得到控制,施工安全也难以得到保证。
发明内容
本发明的目的在于提供一种可以控制大桥的结构线形和焊缝质量从而提高质量控制能力、保证施工安全、降低施工成本、加快施工进度的大桥钢箱提篮拱施工方法。
本发明的目的是这样实现的:一种大桥钢箱提篮拱施工方法,特征是:
A、先确定大桥的结构型式、矢跨比、拱肋内倾角度、拱轴线型、拱肋断面形式,其中大桥的结构型式为边拱加主拱加边拱,拱轴线型为二次抛物线,拱肋采用矩形钢箱加劲梁断面,边拱、主拱在拱脚处通过拱座相连,与主墩固结,钢箱梁由中跨钢箱梁和边跨钢箱梁组成,采用满堂支架支撑;
B、然后利用打桩船在水上插打钢管桩作为拱架及钢箱梁支架的基础,钢管桩间用角钢连接,拱架是由纵桥向两个龙门架通过横向联接系组成的空间立体结构,拱架及钢箱梁支架都是满堂支架,并且拱架及钢箱梁支架均为万能杆件,满堂支架均布置在钢箱梁或拱肋的节点处;
C、在拱肋的内外侧腹板下方焊接箱型钢支座,以消除由于拱肋纵向倾斜大产生对支架的水平推力,同时调整拱肋的内倾角度;
D、将钢箱梁支架的底部支撑及滑移起顶装置设在钢边主箱内侧腹板的正下方,距两段钢箱梁对接接缝1m位置,滑移起顶装置由分配梁及纵向调节、横向调节、竖向调节三向千斤顶组成,滑移起顶装置可调节钢箱梁精确定位并支撑钢箱梁;每个标准钢箱梁由四点支撑并用三个方向千斤顶调节空间位置,调节空间位置时应同步以减小支架的水平位移;
E、在钢箱梁及拱架设计时已考虑钢箱梁及拱架吊装时容许5~10cm水平偏位,要求施工时首先将满堂支架顶标高预调基本到位再吊装,调节时先进行纵横向对位再进行标高调整以确保滑移起顶装置结构受力及稳定;
F、利用500吨水上吊船先安装钢箱梁支架,在钢箱梁内安装传感器,分段吊装中跨钢箱梁,使用滑移起顶装置在全站仪、水准仪测量控制下调整到位,匹切合龙段中跨钢箱梁,吊装合龙段,与此同时吊装边拱及边跨钢箱梁;
G、吊装拱架,在拱肋内安装传感器,分段吊装主拱节段,使用滑移起顶装置在全站仪、水准仪测量控制下调整到位,匹切合龙段拱肋,安装合龙段拱肋,主拱焊接完毕卸除拱架、分次张拉系杆、安装吊杆、调整吊杆索力,最后卸除钢箱梁支架及拔出钢管桩。
本发明使用全站仪、水准仪全过程进行测量,利用纵、横、竖三向千斤顶精确定位拱肋及钢箱梁,确保了主体结构线形流畅,对整个施工过程进行结构应力及线形监控,确保了结构及施工安全,并通过工程中普遍使用的结构有限元分析软件ANSYS程序来计算控制钢结构安装线形,通过传感器来控制主体结构及临时支架应力,采用钢箱梁支架进行施工使施工操作更加简单,易于控制,因此本发明具有可以控制大桥的结构线形和焊缝质量从而提高质量控制能力、保证施工安全、降低施工成本、加快施工进度的优点,通过本发明制造出来的钢箱提篮拱桥具有较强抗台风能力,体现了其高效的特点,并具有显著的经济效益。
附图说明
图1为本发明的结构示意图;
图2为图1的俯视图;
图3为图1中主拱的右视图;
图4为1/2钢箱梁横断面布置图
图5为滑移起顶装置的纵桥向布置图;
图6为滑移起顶装置的横桥向布置图;
图7为施工支架总体布置图。
具体实施方式
下面结合实施例对本发明作进一步详细说明。
一种大桥钢箱提篮拱施工方法为:
A、先确定大桥的结构型式、矢跨比、拱肋内倾角度、拱轴线型、拱肋断面形式,其中大桥的结构型式为边拱1加主拱6加边拱1,主拱6、边拱1的矢跨比为1/4,主拱6、边拱1均内倾,角度为10.6°,拱轴线型为二次抛物线,拱肋10采用矩形钢箱加劲梁断面,边拱1、主拱6在拱脚7处通过拱座2相连,与主墩8固结,钢箱梁14由中跨钢箱梁5和边跨钢箱梁9组成,每个钢箱梁14的标准节段长15米,由2个钢边主箱11、4根小纵梁12、4根横梁13构成一个钢框架,采用满堂支架15支撑;
B、然后利用打桩船在水上插打钢管桩23作为拱架24及钢箱梁支架25的基础,钢管桩23间用角钢26连接,拱架24是由纵桥向两个龙门架27通过横向联接系组成的空间立体结构,拱架24及钢箱梁支架25都是满堂支架15,并且拱架24及钢箱梁支架25均为万能杆件,满堂支架15均布置在钢箱梁14或拱肋10的节点处;
C、在拱肋10的内外侧腹板下方焊接箱型钢支座,以消除由于拱肋10纵向倾斜大产生对支架的水平推力,同时调整拱肋10使其内倾10.6°;
D、将钢箱梁支架25的底部支撑及滑移起顶装置28设在钢边主箱11内侧腹板的正下方,距两段钢箱梁14的对接接缝1m位置,其中滑移起顶装置28安装在钢箱梁支架25的顶部与钢箱梁14的钢边主箱11之间,滑移起顶装置28由3个分配梁:上分配梁17a、中分配梁17b、下分配梁17c及1个15吨纵向调节千斤顶16、1个15吨横向调节千斤顶21、2个50吨竖向调节千斤顶22(即三向千斤顶)组成,在上分配梁17a和中分配梁17b之间的滑动面18涂有黄油,在钢箱梁14与上分配梁17a之间设置有钢垫块19和纵移抄垫块20,滑移起顶装置28可调节钢箱梁14精确定位并支撑钢箱梁14;每个标准钢箱梁14由四点支撑并用三个方向千斤顶调节空间位置,调节空间位置时应同步以减小支架的水平位移;
E、在钢箱梁14及拱架24设计时已考虑吊装时容许5~10cm水平偏位,要求施工时首先将满堂支架15顶标高预调基本到位再吊装,调节时先进行纵横向对位再进行标高调整以确保滑移起顶装置28结构受力及稳定;
F、利用500吨水上吊船先安装钢箱梁支架25,在钢箱梁14内安装传感器,分段吊装中跨钢箱梁5,使用滑移起顶装置28在全站仪、水准仪测量控制下调整到位,匹切合龙段中跨钢箱梁5,吊装合龙段,与此同时吊装边拱1及边跨钢箱梁9;
G、吊装拱架24,在拱肋10内安装传感器,分段吊装主拱6节段,使用滑移起顶装置28在全站仪、水准仪测量控制下调整到位,匹切合龙段拱肋10,安装合龙段拱肋10,主拱6焊接完毕卸除拱架24,分次张拉系杆3、安装吊杆4、调整吊杆4索力,最后卸除钢箱梁支架25及拔出钢管桩23。

Claims (1)

1、一种大桥钢箱提篮拱施工方法,其特征在于:
A、先确定大桥的结构型式、矢跨比、拱肋内倾角度、拱轴线型、拱肋断面形式,其中大桥的结构型式为边拱加主拱加边拱,拱轴线型为二次抛物线,拱肋采用矩形钢箱加劲梁断面,边拱、主拱在拱脚处通过拱座相连,与主墩固结,钢箱梁由中跨钢箱梁和边跨钢箱梁组成,采用满堂支架支撑;
B、然后利用打桩船在水上插打钢管桩作为拱架及钢箱梁支架的基础,钢管桩间用角钢连接,拱架是由纵桥向两个龙门架通过横向联接系组成的空间立体结构,拱架及钢箱梁支架都是满堂支架,并且拱架及钢箱梁支架均为万能杆件,满堂支架均布置在钢箱梁或拱肋的节点处;
C、在拱肋的内外侧腹板下方焊接箱型钢支座,以消除由于拱肋纵向倾斜大产生对支架的水平推力,同时调整拱肋的内倾角度;
D、将钢箱梁支架的底部支撑及滑移起顶装置设在钢边主箱内侧腹板的正下方,距两段钢箱梁对接接缝1m位置,滑移起顶装置由分配梁及纵向调节、横向调节、竖向调节三向千斤顶组成,滑移起顶装置可调节钢箱梁精确定位并支撑钢箱梁;每个标准钢箱梁由四点支撑并用三个方向千斤顶调节空间位置,调节空间位置时应同步以减小支架的水平位移;
E、在钢箱梁及拱架设计时已考虑钢箱梁及拱架吊装时容许5~10cm水平偏位,要求施工时首先将满堂支架顶标高预调基本到位再吊装,调节时先进行纵横向对位再进行标高调整以确保滑移起顶装置结构受力及稳定;
F、利用500吨水上吊船先安装钢箱梁支架,在钢箱梁内安装传感器,分段吊装中跨钢箱梁,使用滑移起顶装置在全站仪、水准仪测量控制下调整到位,匹切合龙段中跨钢箱梁,吊装合龙段,与此同时吊装边拱及边跨钢箱梁;
G、吊装拱架,在拱肋内安装传感器,分段吊装主拱节段,使用滑移起顶装置在全站仪、水准仪测量控制下调整到位,匹切合龙段拱肋,安装合龙段拱肋,主拱焊接完毕卸除拱架、分次张拉系杆、安装吊杆、调整吊杆索力,最后卸除钢箱梁支架及拔出钢管桩。
CNB2007100097312A 2007-10-24 2007-10-24 大桥钢箱提篮拱施工方法 Active CN100478522C (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CNB2007100097312A CN100478522C (zh) 2007-10-24 2007-10-24 大桥钢箱提篮拱施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CNB2007100097312A CN100478522C (zh) 2007-10-24 2007-10-24 大桥钢箱提篮拱施工方法

Publications (2)

Publication Number Publication Date
CN101148860A CN101148860A (zh) 2008-03-26
CN100478522C true CN100478522C (zh) 2009-04-15

Family

ID=39249550

Family Applications (1)

Application Number Title Priority Date Filing Date
CNB2007100097312A Active CN100478522C (zh) 2007-10-24 2007-10-24 大桥钢箱提篮拱施工方法

Country Status (1)

Country Link
CN (1) CN100478522C (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736699B (zh) * 2009-12-15 2011-04-20 中交路桥华北工程有限公司 全支架钢箱梁滑移精确定位方法

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101695984B (zh) * 2009-09-28 2011-11-23 中铁八局集团第一工程有限公司 中承式钢管混凝土拱桥拱下纵横梁的安装方法及吊具
CN101984189B (zh) * 2010-11-10 2012-08-22 中交第二航务工程局有限公司 大型钢混组合多棱台斜面拱座施工方法
CN102418315B (zh) * 2011-09-30 2013-10-23 长沙理工大学 低扣塔架设桥宽较大的钢管混凝土拱桥的施工方法
CN102493347B (zh) * 2011-12-13 2013-08-14 武船重型工程股份有限公司 一种钢管拱节段间法兰盘加工及安装方法
CN103453229A (zh) * 2013-08-28 2013-12-18 中机国能电力工程有限公司 一种大跨度x型空间拱形管道支架
CN103741581A (zh) * 2013-12-25 2014-04-23 广西科技大学 一种矩形箱梁
CN105040570B (zh) * 2015-08-11 2016-08-31 苏州同尚工程设计咨询有限公司 一种拱桥结构及其实施铺设工艺
CN105887686B (zh) * 2016-04-21 2017-10-13 中铁十七局集团第四工程有限公司 内倾式三角拱桥钢拱肋合龙方法
CN107117522A (zh) * 2017-06-20 2017-09-01 中国五冶集团有限公司 钢箱梁吊装系统及吊装方法
CN108035258B (zh) * 2017-11-28 2019-07-12 江苏中铁山桥重工有限公司 一种提篮式钢箱拱肋制作方法
CN108221694B (zh) * 2018-01-19 2019-06-21 中铁大桥局集团有限公司 安装大跨度拱桥系杆的方法
CN109440644B (zh) * 2018-08-28 2024-06-11 浙江中南绿建科技集团有限公司 一种连续钢梁桥安装用临时结构及其对梁段施工方法
CN109763416B (zh) * 2019-01-31 2021-04-06 同济大学建筑设计研究院(集团)有限公司 一种新型双曲拱桥
CN112709153B (zh) * 2020-12-30 2022-04-26 中铁二院工程集团有限责任公司 高铁大跨上承式拱桥运营期桥面线形的调整方法
CN113250067A (zh) * 2021-05-26 2021-08-13 中电建十一局工程有限公司 一种飞燕中承式钢管混凝土系杆拱桥主边拱施工方法
CN113789712B (zh) * 2021-09-17 2023-10-13 上海建工一建集团有限公司 钢拱桥的纵梁和拱肋成型控制方法
CN113737627A (zh) * 2021-09-29 2021-12-03 中铁广州工程局集团有限公司 一种小半径曲线高低箱异形断面钢箱梁的施工方法
CN114482015B (zh) * 2021-12-30 2023-11-10 江苏华滋能源工程有限公司 一种特大型海上风电基础钢管桩的建造方法
CN114674296B (zh) * 2022-02-21 2024-02-20 中交二航局结构工程有限公司 一种钢箱梁拼装精调自动调控系统
CN115787505B (zh) * 2022-12-20 2023-12-12 中铁上海工程局集团有限公司 一种飞燕式拱桥下拱肋的施工方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101736699B (zh) * 2009-12-15 2011-04-20 中交路桥华北工程有限公司 全支架钢箱梁滑移精确定位方法

Also Published As

Publication number Publication date
CN101148860A (zh) 2008-03-26

Similar Documents

Publication Publication Date Title
CN100478522C (zh) 大桥钢箱提篮拱施工方法
CN103410322B (zh) 大跨度平行桁架钢连廊施工方法
CN102431626B (zh) 超长双艉鳍结构分段与轴架船坞的安装方法
CN111749145A (zh) 顶推施工方法
CN109629442A (zh) 一种大跨度斜拉桥钢箱桁梁线型控制施工方法
CN201411665Y (zh) 闸墩液压调平内爬式滑升模板
CN105317052B (zh) 一种塔吊基础螺栓固定方法
CN104831632B (zh) 一种桥梁索塔上横梁与下横梁施工方法
CN110106881A (zh) 一种钢管桩施工导向定位架及施工方法
CN110499702A (zh) 一种斜拉桥索塔的索鞍定位加固装置
CN214394730U (zh) 一种用于沉管的平台组件及升降平台装置
CN1472400A (zh) 钢吊箱整体浮运锚墩预施拉力定位、兼作钻孔平台方案
CN204642092U (zh) 海上风力发动机安装专用船舶
CN102358406A (zh) 船坞内船舶二次落墩定位装置
KR101814539B1 (ko) 선박의 평형계측 장치 및 평형계측 방법
CN205675201U (zh) 一种彻底解决晕船的机电一体化系统
CN111979913A (zh) 斜拉桥索梁锚固结构及锚管角度的控制方法
CN205000349U (zh) 钢板桩围堰多层围囹整体下放装置
CN110979595B (zh) 一种海损船修复方法
CN210293232U (zh) 一种用于定位水下建筑物基准点的测量平台
CN203929187U (zh) 适用于悬臂梁总成的称重系统
CN209323394U (zh) 一种拉索桥主塔内斜面修补吊篮施工结构
CN113338167A (zh) 一种桁架拱桥大节段整体合拢施工方法
CN202369932U (zh) 一种桥梁遮板安装车
CN101435180B (zh) 一种钢帽定位方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20090109

Address after: Jiangxi Province, Jiujiang Road No. 20 bridge of Bai Shuihu five post encoding: 332000

Applicant after: China Railway Bridge Group Fifth Engineering Co., Ltd.

Co-applicant after: China Zhongtie Major Bridge Engineering Co., Ltd.

Address before: Jiangxi Province, Jiujiang Road No. 20 bridge of Bai Shuihu five post encoding: 332000

Applicant before: No. 5 Enginering Co., Ltd. Of China Zhongtie Major Bridge Engineering

C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: GROUP CO., LTD., ZHONGTIE DAQIAO BUREAU

Free format text: FORMER OWNER: CHINA ZHONGTIE MAJOR BRIDGE ENGINEERING CO., LTD.

Effective date: 20150225

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150225

Address after: 332000 Jiangxi province Jiujiang Baishui Lake Road No. 20 Bridge five

Patentee after: No. 5 Enginering Co., Ltd. Of China Zhongtie Major Bridge Engineering

Patentee after: Group Co., Ltd., Zhongtie Daqiao Bureau

Address before: 332000 Jiangxi province Jiujiang Baishui Lake Road No. 20 Bridge five

Patentee before: No. 5 Enginering Co., Ltd. Of China Zhongtie Major Bridge Engineering

Patentee before: China Zhongtie Major Bridge Engineering Co., Ltd.