CN100424298C - 用上支承构架制作叠合楼板的施工方法 - Google Patents
用上支承构架制作叠合楼板的施工方法 Download PDFInfo
- Publication number
- CN100424298C CN100424298C CNB2006100807919A CN200610080791A CN100424298C CN 100424298 C CN100424298 C CN 100424298C CN B2006100807919 A CNB2006100807919 A CN B2006100807919A CN 200610080791 A CN200610080791 A CN 200610080791A CN 100424298 C CN100424298 C CN 100424298C
- Authority
- CN
- China
- Prior art keywords
- base plate
- construction
- connection block
- upper support
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Images
Landscapes
- Working Measures On Existing Buildindgs (AREA)
Abstract
本发明涉及一种用上支承构架支承钢筋混凝土薄底板,再在底板上现浇混凝土叠合层,制成叠合楼板的施工方法。它包括预制底板,圈梁模板的制作或安装支承架,吊装底板,悬吊上支承构架,配筋连接,现浇混凝土,拆卸上支承构架等步骤。本发明用上支承构架制作叠合楼板的施工方法,建造的楼板达到设防裂度8级的住宅建筑工程抗震设计规范,使叠合楼板的施工方便可靠,效率高,从而降低工程造价;适应于墙体承重的多层及高层建筑工程,也可用于各种框架结构及剪力墙结构建筑工程。
Description
技术领域
本发明涉及一种叠合楼板的施工方法,具体说是用上支承构架支承钢筋混凝土薄底板,再在底板上现浇混凝土叠合层,制成叠合楼板的施工方法,属房屋楼板施工技术领域。
背景技术
楼板是房屋建筑工程的基本水平构件,一般均采用钢筋混凝土楼板,其施工方法有预制钢筋混凝土圆孔板、全现浇钢筋混凝土板、预制底板加叠合层的叠合楼板等,在钢结构建筑中还有空腹桁架组合楼板等。由于安全原因,预制钢筋混凝土圆孔板在一些地区已停止使用,而全部现浇楼板又由于模板工程的工作量很大,完工后拆模板工序费时费力。而预制底板加现浇叠合层的叠合楼板,因底板的刚度小,规格较大时运输和支撑都比较困难,底板下的满堂支撑拆卸工作量也很大。上支承构架提供了一种制作预制底板加叠合层的叠合楼板施工时的专用吊装支承工具。
发明内容
本发明为了克服现有技术的缺陷,提供一种采用上支承构架制作叠合楼板的施工方法,使叠合楼板的施工方便可靠,效率高,从而降低工程造价。
本发明用上支承构架制作叠合楼板的施工方法,其中包括下列步骤:
1)预制底板:按设计要求预制厚度为50~70mm的钢筋混凝土结构的薄底板,该底板的纵、横向宽度应比所覆盖的开间尺寸均大40~100mm,且钢筋外露胡子筋长250~350mm;在底板的纵向方向,距边缘200~250mm处,每隔1.2~1.5米处预埋设有连接座;在底板的横向方向,距边缘500~600mm处,每隔1.2~1.5米处预埋设有连接座,且连接座外圆周与底板中钢筋焊接固定:
2)圈梁模板的制作:在墙体施工到设计高度时,沿墙体两面或一面四周安装圈梁模板,且圈梁模板的上端面为底板的支承面;上支承构架包括三个纵向支架和二个横向支架相互正交连接而成,纵、横向支架两端和与其连接的底板内的连接座必须置于圈梁模板上;
3)吊装底板:连接管上涂刷隔离剂后并加纸套与底板上的连接座连接,其上端和上支承构架连接固定,用吊装机械将上支承构架吊起,并将底板置于圈梁模板上;
4)配筋连接:根据设计要求,安放圈梁和叠合层中的钢筋,并与底板上的配筋连接固定成一整体;
5)现浇混凝土:同时浇筑圈梁和叠合层中的混凝土;叠合层厚度为60~190mm,完成该层叠合楼板的施工;
6)拆卸上支承构架:待混凝土固化后,卸掉连接管,吊走上支承构架,待墙体施工到设计高度时,重复步骤2)~步骤5),直至完成多层建筑的全部楼板的施工。
本发明用上支承构架制作叠合楼板的施工方法,其中在步骤2)中,底板面积大于30m2时,底板的边缘支承在圈梁模板上,纵、横向支架两端和与其连接的底板内的连接座不置于圈梁模板上,而是必须通过垫块同时置于安装在墙体上的支承架上。
本发明用上支承构架制作框架结构中的叠合楼板的施工方法,其中包括下列步骤:
1)预制底板:按设计要求预制厚度为50~70mm的钢筋混凝土结构的薄底板,该底板的纵、横向宽度应比所覆盖的开间尺寸均大40~100mm,且钢筋外露胡子筋长250~350mm;在底板的纵向或横向方向,距边缘200~250mm处,每隔1.2~1.5米处预埋设有连接座;在底板的横向方向,距边缘500~600mm处,每隔1.2~1.5米处预埋设有连接座,且连接座外圆周与底板中钢筋焊接固定;
2)安装支承架:在钢筋混凝土梁或钢梁上用螺栓固定支承架,上支承构架包括三个纵向支架和二个横向支架相互正交连接而成,该支承架的位置与纵、横向支架两端相对应;
3)吊装底板:连接管上涂刷隔离剂后并加纸套与底板上的连接座连接,其上端和上支承构架连接固定;吊装机械将上支承构架吊起,并将底板搭接在钢筋混凝土梁或钢梁上表面上;
4)悬吊上支承构架:用悬吊装置在纵向或横向支架上方的两端,将上支承构架悬吊固定在框架结构的梁或柱上;
5)配筋连接:根据设计要求,安放底板之间和叠合层中的钢筋,并与底板上的配筋连接固定成一整体;
6)现浇混凝土:同时浇筑连接处和叠合层中的混凝土;叠合层厚度为60~190mm,完成该层叠合楼板的施工;
7)拆卸上支承构架:待混凝土固化后,卸掉悬吊装置和连接管,吊走上支承构架,重复步骤2)~步骤6),直至完成多层建筑的全部楼板的施工。
本发明用上支承构架制作叠合楼板的施工方法,建造的楼板达到设防裂度8级的住宅建筑工程抗震设计规范,使叠合楼板的施工方便可靠,效率高,从而降低工程造价;适应于墙体承重的多层及高层建筑工程,也可用于各种框架结构及剪力墙结构建筑工程。
附图说明
图1为本发明的施工方法中使用的上支承构架结构和与底板连接结构的立体示意图;
图2为图1中上支承构架与底板连接结构的剖面示意图;
图3为本发明施工方法第1实施例的安装连接结构示意图;
图4为本发明施工方法第2实施例的安装连接结构局部示意图;
图5为本发明施工方法第3实施例的安装连接结构示意图;
图6为本发明施工方法第4实施例的安装连接结构示意图。
具体实施方式
由图1、2可见,本发明的施工方法中使用的上支承构架结构包括三个纵向支架2和二个横向支架3相互正交连接而成,其中每个纵向支架2由两个相同结构的桁架用螺栓对称连接(图中未视出)固定构成。而每个桁架包括相互平行的上弦梁5和下弦梁6,以及与上、下弦梁之间斜向连接固定的若干根复杆7,且连接处还设有相互连接为一体的节点板8。在下弦梁6的下部安装若干个连接部件4与底扳1中竖直方向安放的连接座17连接固定。连接件4包括与下弦梁6固定连接的悬挂件18和与悬挂件18连接固定的卡具29,连接管16一端与卡具29固定连接,另一端与连接座17螺纹连接;悬挂件18为中间设有连接筋的角钢。二个横向支架3包括分别与上、下弦梁5、6的上、下部分别通过夹具10固定连接的上、下弦杆11、12,在上、下弦杆11、12之间设有二个与其连为一体的三角形稳定架13;下弦杆12的两端分别通过通用建筑扣件15和一端设有螺纹的连接管16固定连接,连接管16的螺纹端与预制在底板1中竖直方向安放的连接座17连接;上、下弦杆11、12为圆钢管,也可为方钢管。
如图3所示,对于砌块和混凝土结构的承重墙体,叠合楼板的施工方法包括下列步骤:
1)预制底板:按设计要求预制厚度为50~70mm的钢筋混凝土结构的薄底板1,该底板1的纵、横向宽度应比所覆盖的开间尺寸均大40~100mm,且钢筋外露胡子筋19长250~350mm;在底板1的纵向方向,距边缘200~250mm处,每隔1.2~1.5米处预埋设有连接座17;在底板的横向方向,距边缘500~600mm处,每隔1.2~1.5米处预埋设有连接座17,且连接座17外圆周与底板1中钢筋焊接固定:当然,一般底板1均事先已经按设计要求制作好了待用;
2)圈梁模板的制作:在墙体施工到设计高度时,沿墙体两面或一面四周安装圈梁模板14,且圈梁模板14的上端面为底板1的支承面,上支承构架包括三个纵向支架2和二个横向支架3相互正交连接而成,纵向支架2两端与底板1内的连接座17必须置于圈梁模板14上;
3)吊装底板:连接管16上涂刷隔离剂后并加纸套9与底板1上的连接座17螺纹连接,其上端和上支承构架连接固定,用吊装机械将上支承构架吊起,并将底板1置于圈梁模板14上;
4)配筋连接:根据设计要求,安放圈梁和叠合层中的钢筋,并与底板1上外露的胡子筋19连接固定成一整体;
5)现浇混凝土:同时浇筑圈梁和叠合层中的混凝土;叠合层厚度为60~190mm,完成该层叠合楼板的施工;
6)拆卸上支承构架:待混凝土固化后,卸掉连接管17,吊走上支承构架,待墙体施工到设计高度时,重复步骤2)~步骤5),直至完成多层建筑的全部楼板的施工。
当底板面积大于30m2时,即房屋开间大,底板1的边缘支承在圈梁模板14上,且纵、横向支架2或3两端和与其连接的底板1内的连接座17不置于圈梁模板14上,而是必须通过垫块21同时置于安装在墙体上的支承架20上,如图4所示,其它施工步骤与前者相同。增加这样的支承后,使其更加安全地承受施工中的载荷。
对于框架结构的建筑物,楼板建造在框架中的钢梁或混凝土梁上,由于钢梁或混凝土梁的承重负荷有限,这时为了施工的安全性,应在上支承构架上方设计悬吊装置,若叠合楼板的施工层上方的框架已经建成,该悬吊装置包括固定在上一层框架中的钢梁或钢筋混凝土梁22上,且与纵、横向支架2或3相同方向安置的悬吊架23,以及两端通过建筑扣件分别与悬吊架23和纵、横向支架2、3固定连接的若干根不同长度的斜拉管21,其悬吊结构如图5所示,其它施工步骤与前述基本相同。斜拉管21也可用钢丝绳替代。
当叠合楼板的施工层上方的框架没有建成时,悬吊装置包括立杆25,该立杆25的下端与固定在施工层框架中的钢梁上端面上或预埋在钢筋混凝土梁22上端面上的连接件26固定连接;其上端设有吊环27,在吊环27和纵、横向支架2、3之间,通过若干根不同长度的斜拉绳28连接固定,其悬吊结构如图6所示,其它施工步骤与前述基本相同。
上述施工中所用的薄底板1为截角型或柱角型;显然,一般底板均事先已经按设计要求成批生产为待用的产品。
Claims (3)
1. 一种用上支承构架制作叠合楼板的施工方法,其特征是包括下列步骤:
1)预制底板:按设计要求预制厚度为50~70mm的钢筋混凝土结构的薄底板,该底板的纵、横向宽度应比所覆盖的开间尺寸均大40~100mm,且钢筋外露胡子筋长250~350mm;在底板的纵向方向,距边缘200~250mm处,每隔1.2~1.5米处预埋设有连接座;在底板的横向方向,距边缘500~600mm处,每隔1.2~1.5米处预埋设有连接座,且连接座外圆周与底板中钢筋焊接固定;
2)圈梁模板的制作:在墙体施工到设计高度时,沿墙体两面或一面四周安装圈梁模板,且圈梁模板的上端面为底板的支承面;上支承构架包括三个纵向支架和二个横向支架相互正交连接而成,纵、横向支架两端与底板内的连接座必须置于圈梁模板上;
3)吊装底板:连接管上涂刷隔离剂后并加纸套与底板上的连接座连接,其上端和上支承构架连接固定,用吊装机械将上支承构架吊起,并将底板置于圈梁模板上;
4)配筋连接:根据设计要求,安放圈梁和叠合层中的钢筋,并与底板上的配筋连接固定成一整体;
5)现浇混凝土:同时浇筑圈梁和叠合层中的混凝土;叠合层厚度为60~190mm,完成该层叠合楼板的施工;
6)拆卸上支承构架:待混凝土固化后,卸掉连接管,吊走上支承构架;待墙体施工到设计高度时,重复步骤2)~步骤5),直至完成多层建筑的全部楼板的施工。
2. 根据权利要求1所述的用上支承构架制作叠合楼板的施工方法,其特征是在所述步骤2)中,底板面积大于30m2时,底板的边缘支承在圈梁模板上,纵、横向支架两端与底板内的连接座不置于圈梁模板上,而是必须通过垫块同时置于安装在墙体上的支承架上。
3. 一种用上支承构架制作框架结构中的叠合楼板的施工方法,其特征包括下列步骤:
1)预制底板:按设计要求预制厚度为50~70mm的钢筋混凝土结构的薄底板,该底板的纵、横向宽度应比所覆盖的开间尺寸均大40~100mm,且钢筋外露胡子筋长250~350mm;在底板的纵向方向,距边缘200~250mm处,每隔1.2~1.5米处预埋设有连接座;在底板的横向方向,距边缘500~600mm处,每隔1.2~1.5米处预埋设有连接座,且连接座外圆周与底板中钢筋焊接固定;
2)安装支承架:在钢筋混凝土梁或钢梁上用螺栓固定支承架,上支承构架包括三个纵向支架和二个横向支架相互正交连接而成,该支承架的位置与纵、横向支架两端相对应;
3)吊装底板:连接管上涂刷隔离剂后并加纸套与底板上的连接座连接,其上端和上支承构架连接固定,用吊装机械将上支承构架吊起,并将底板搭接在钢筋混凝土梁或钢梁上表面上;
4)悬吊上支承构架:用悬吊装置在纵向或横向支架上方的两端,将上支承构架悬吊固定在框架结构的梁或柱上;
5)配筋连接:根据设计要求,安放底板之间和叠合层中的钢筋,并与底板上的配筋连接固定成一整体;
6)现浇混凝土:同时浇筑连接处和叠合层中的混凝土;叠合层厚度为60~190mm,完成该层叠合楼板的施工;
7)拆卸上支承构架:待混凝土固化后,卸掉悬吊装置和连接管,吊走上支承构架,重复步骤2)~步骤6),直至完成多层建筑的全部楼板的施工。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100807919A CN100424298C (zh) | 2006-05-18 | 2006-05-18 | 用上支承构架制作叠合楼板的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CNB2006100807919A CN100424298C (zh) | 2006-05-18 | 2006-05-18 | 用上支承构架制作叠合楼板的施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1851191A CN1851191A (zh) | 2006-10-25 |
CN100424298C true CN100424298C (zh) | 2008-10-08 |
Family
ID=37132692
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CNB2006100807919A Expired - Fee Related CN100424298C (zh) | 2006-05-18 | 2006-05-18 | 用上支承构架制作叠合楼板的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN100424298C (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102712104A (zh) * | 2009-11-13 | 2012-10-03 | 普拉特弗姆斯股份有限公司 | 预浇铸复合结构地板系统 |
Families Citing this family (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102535851A (zh) * | 2012-03-26 | 2012-07-04 | 郑州大学 | 砌体房屋预制楼板板间一体化施工工艺 |
CN103061518A (zh) * | 2013-01-22 | 2013-04-24 | 中国十七冶集团有限公司 | 多层住宅叠合楼板的施工方法 |
CN104790576A (zh) * | 2015-04-26 | 2015-07-22 | 吴方伯 | 一种叠合楼板及其施工方法 |
CN107630553B (zh) * | 2016-07-18 | 2020-07-31 | 上海奇谋能源技术开发有限公司 | 一种用于大跨度楼板的先张快速施工装置及方法 |
CN107630554B (zh) * | 2016-07-18 | 2021-04-30 | 上海奇谋能源技术开发有限公司 | 一种用于楼板的快速施工装置及方法 |
CN107630559B (zh) * | 2016-07-18 | 2021-04-30 | 上海奇谋能源技术开发有限公司 | 一种用于楼板的先张施工装置及方法 |
CN107476476B (zh) * | 2017-09-12 | 2019-04-23 | 中建五局第三建设有限公司 | 一种大跨钢筋桁架楼承板与钢筋混凝土梁组合施工方法 |
CN110397268B (zh) * | 2019-07-20 | 2021-08-31 | 山东金城建设有限公司 | 装配式剪力墙后浇圈梁模板与板支座一体设计与施工方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2535705A1 (de) * | 1975-08-09 | 1977-02-10 | Robert Giesler | Vorgefertigte schalung zur herstellung von ringankern an bauwerken |
FR2578276A1 (fr) * | 1985-03-01 | 1986-09-05 | Rech Etudes Tech | Element de construction en beton, notamment element de plancher, et procede pour sa fabrication |
CN1032690A (zh) * | 1988-08-29 | 1989-05-03 | 和景义 | 预制-现浇叠合空心楼盖 |
DE4041219A1 (de) * | 1990-12-21 | 1992-07-02 | Safet Vajzovic | Verfahren zur herstellung von zwischendecken und dabei verwendbarer traeger |
DE19544219A1 (de) * | 1995-11-28 | 1997-06-05 | Dennert Kg Veit | Industriell vorfertigbare Leichtbau-Deckentafel |
CN2362927Y (zh) * | 1998-06-19 | 2000-02-09 | 温延风 | 预应力钢筋混凝土叠合楼板 |
-
2006
- 2006-05-18 CN CNB2006100807919A patent/CN100424298C/zh not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE2535705A1 (de) * | 1975-08-09 | 1977-02-10 | Robert Giesler | Vorgefertigte schalung zur herstellung von ringankern an bauwerken |
FR2578276A1 (fr) * | 1985-03-01 | 1986-09-05 | Rech Etudes Tech | Element de construction en beton, notamment element de plancher, et procede pour sa fabrication |
CN1032690A (zh) * | 1988-08-29 | 1989-05-03 | 和景义 | 预制-现浇叠合空心楼盖 |
DE4041219A1 (de) * | 1990-12-21 | 1992-07-02 | Safet Vajzovic | Verfahren zur herstellung von zwischendecken und dabei verwendbarer traeger |
DE19544219A1 (de) * | 1995-11-28 | 1997-06-05 | Dennert Kg Veit | Industriell vorfertigbare Leichtbau-Deckentafel |
CN2362927Y (zh) * | 1998-06-19 | 2000-02-09 | 温延风 | 预应力钢筋混凝土叠合楼板 |
Non-Patent Citations (2)
Title |
---|
钢筋析架叠合板性能试验和设计方法研究. 刘轶,童根树,李文斌,石成林,曹志毅.混凝土与水泥制品,第2期. 2006 |
钢筋析架叠合板性能试验和设计方法研究. 刘轶,童根树,李文斌,石成林,曹志毅.混凝土与水泥制品,第2期. 2006 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102712104A (zh) * | 2009-11-13 | 2012-10-03 | 普拉特弗姆斯股份有限公司 | 预浇铸复合结构地板系统 |
CN102712104B (zh) * | 2009-11-13 | 2014-07-16 | 普拉特弗姆斯股份有限公司 | 预浇铸复合结构地板系统 |
Also Published As
Publication number | Publication date |
---|---|
CN1851191A (zh) | 2006-10-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100424298C (zh) | 用上支承构架制作叠合楼板的施工方法 | |
CN107989227B (zh) | 一种装配式型钢混凝土剪力墙结构及其制备和安装方法 | |
US8499511B2 (en) | Precast composite structural floor system | |
CN2818421Y (zh) | 用于叠合楼板施工的上支承构架 | |
CN101831976A (zh) | 一种预制带钢骨肋底板—混凝土叠合空心楼盖 | |
CN102454239A (zh) | 一种预制板施工构件 | |
CN110670770A (zh) | 实心剪力墙与叠合板式边缘构件组合结构及施工方法 | |
CN100460613C (zh) | 悬浮架施工方法 | |
CN203394027U (zh) | 半装配式框架剪力墙筒体结构施工体系 | |
CN113279582A (zh) | 一种用于悬挑并下挂式现浇板的吊挂施工方法 | |
CN114351855A (zh) | 一种装配式全预制混凝土框架结构体系及施工方法 | |
CN2816164Y (zh) | 现浇钢筋砼空中连廊 | |
CN219622069U (zh) | 一种装配式轻钢带空腹钢筋桁架混凝土条带叠合双向楼板 | |
CN218492809U (zh) | 一种短出筋桁架钢筋混凝土叠合板的支座连接结构 | |
CN214785337U (zh) | 一种预制装配式钢管混凝土叠合柱及其建筑 | |
CN210288825U (zh) | 一种装配式、现浇组合梁板结构 | |
CN212453063U (zh) | 装配浇注一体化剪力墙结构建筑体系 | |
CN212001725U (zh) | 一种全螺栓连接多层预制型钢混凝土剪力墙结构 | |
CN114135037A (zh) | 一种板桁模架结构及施工方法 | |
CN112900949A (zh) | 一种装配式钢筋混凝土单向密肋叠合板楼盖及其施工方法 | |
CN219343709U (zh) | 一种立体空间网架叠合板 | |
CN215977872U (zh) | 叠合整体式预制剪力墙边缘构件 | |
CN115949167B (zh) | 一种装配式轻钢强化型带空腹钢筋桁架混凝土条带叠合双向楼板及作法 | |
CN218714208U (zh) | 预应力混凝土叠合板 | |
CN219952395U (zh) | 结构施工一体化预制装配式建筑结构体系 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
DD01 | Delivery of document by public notice |
Addressee: Liu Jiankang Document name: Notification to Pay the Fees |
|
DD01 | Delivery of document by public notice |
Addressee: Liu Jiankang Document name: Notification of Termination of Patent Right |
|
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20081008 Termination date: 20150518 |
|
EXPY | Termination of patent right or utility model |