CH317032A - Construction method, prefabricated wall element for its implementation, and construction obtained by this method - Google Patents

Construction method, prefabricated wall element for its implementation, and construction obtained by this method

Info

Publication number
CH317032A
CH317032A CH317032DA CH317032A CH 317032 A CH317032 A CH 317032A CH 317032D A CH317032D A CH 317032DA CH 317032 A CH317032 A CH 317032A
Authority
CH
Switzerland
Prior art keywords
construction
pillars
panels
prefabricated
wall elements
Prior art date
Application number
Other languages
French (fr)
Inventor
Chatelain Frederic
Chatelain Yolande
Original Assignee
Chatelain Frederic
Chatelain Yolande
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chatelain Frederic, Chatelain Yolande filed Critical Chatelain Frederic
Publication of CH317032A publication Critical patent/CH317032A/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Description

  

  Procédé de     construction,    élément de mur préfabriqué pour sa     mise    en     aeuvre,     et construction obtenue par ce procédé    II existe divers procédés de construction du       gros-oeuvre    d'une maison. Pour réduire le coût  de la construction, on a proposé, par exemple,  de monter des     piliers    en béton armé, puis de  fermer les espaces entre ces piliers au moyen  de panneaux préfabriqués.  



  La présente invention a pour objet un pro  cédé de construction à l'aide d'éléments pré  fabriqués qui se caractérise par le fait qu'on  constitue l'ossature de la construction en cou  lant des piliers en béton au fur et à mesure du  montage des murs au moyen de panneaux pré  fabriqués comportant au moins deux parois  parallèles maintenues par des entretoises, les  extrémités de deux panneaux voisins consti  tuant avec les entretoises des     coffrages    perma  nents pour le coulage des piliers.  



  L'invention a également pour objet un élé  ment de mur préfabriqué pour la mise en     oeu-          vre    du procédé et qui se caractérise par le fait  qu'il est constitué par un panneau présentant  des plaques latérales     solidaires    d'au moins  deux entretoises disposées à proximité des ex  trémités desdites plaques latérales, le tout  agencé de manière que chaque extrémité d'un  panneau constitue une partie d'un coffrage  permanent destiné au coulage des piliers for  mant l'ossature de la construction.  



  Enfin, l'invention a encore pour objet une  construction réalisée selon le procédé qui se    caractérise par le fait qu'elle comporte des  panneaux préfabriqués et des     piliers    coulés  dans des     coffrages    permanents formés par les  parties desdits panneaux, et par le fait que ces  panneaux sont en une matière sur laquelle le  béton fait prise, de sorte que, après la prise du  béton, les panneaux et les piliers forment un  ensemble monolithique.  



  Le dessin annexé montre, à titre d'exemple,  quelques variantes de murs construits selon le  procédé.  



  La     fig.    1 est une coupe partielle d'une pre  mière variante.  



  La     fig.    2 est une vue en élévation d'un .  mur en cours de construction.  



  La     fig.    3 est une vue en perspective d'un  outillage.  



  La     fig.    4 est une vue en coupe partielle  d'une première variante d'exécution d'un  angle.  



  Les     fig.    5 et 6 sont des vues en coupe par  tielle de deux autres variantes.  



  La     fig.    7 est une vue en coupe d'une va  riante d'exécution d'un angle.  



  Selon les     fig.    1 et 2 du dessin annexé, un  mur est constitué par des éléments de mur pré  fabriqués disposés bout à bout. Chaque élé  ment de mur préfabriqué comporte      1) une plaque latérale externe 2 ;  2) une plaque latérale interne 3 ;  3) des entretoises 5 fixées à l'aide de clous  4 sur les plaques 2 et 3.  



  Ces entretoises, de préférence en une ma  tière non hygroscopique, sont disposées à  proximité des extrémités des plaques. Dans  une variante, ces entretoises prévues ici en un  matériau aggloméré, pourraient être prévues  en bois ou autre matériau de ce genre.  



  Lorsque ces éléments de mur préfabriqués  sont placés bout à bout, les extrémités de deux  éléments voisins forment un coffrage perma  nent dans lequel on coule un pilier en béton  après avoir placé les armatures nécessaires.  



  En pratique, on procède au montage pro  gressif du mur, c'est-à-dire qu'après avoir  placé deux éléments de mur bout à bout, on  coule du béton dans le coffrage, puis lorsque  tous les     coffrages        formés    par une première  rangée horizontale d'éléments de mur préfabri  qués mis bout à bout et représentant la lon  gueur du mur désirée sont remplis de béton,  on pose une seconde rangée d'éléments de  mur sur la rangée précédente et on recom  mence l'opération de coulage de béton et ainsi  de suite jusqu'à ce que le mur ait la hauteur  désirée. De cette manière, les piliers 6 sont  montés en même temps que le mur et main  tiennent en position les éléments de mur pré  fabriqués.  



  Afin que l'ensemble piliers-éléments pré  fabriqués forme un tout rigide, il est recom  mandable d'employer dans la construction des  éléments de mur préfabriqués, des plaques la  térales et, éventuellement, des entretoises en  un matériau sur lequel le béton fait prise, tel  que du fibrociment par exemple. On évitera  ainsi la nécessité d'un chaînage entre piliers.  



  Afin de faciliter la mise en place des élé  ments de mur préfabriqués de la seconde ran  gée, on peut, lors du coulage du béton dans  les coffrages formés par les éléments de mur  de la première rangée, placer un cadre amo  vible 8 à cheval sur la jonction des éléments  voisins, et remplir de béton chaque     coffrage       jusqu'à la hauteur du bord supérieur 9 de ce  cadre 8.  



  Après retrait de ces cadres, les piliers émer  gent de leurs coffrages permanents et consti  tuent des guides pour la mise en place des  éléments de mur préfabriqués de la seconde  rangée.  



  Dans le vide intérieur 10 des éléments de  mur préfabriqués, on glisse des plaques 11 en  une matière isolante et hydrophile.  



  Les extrémités des éléments de mur pré  fabriqués destinés à former un angle, compor  tent une plaque externe 2, de plus grande lon  gueur que la plaque interne 3. Par longueur,  on entend la dimension horizontale de l'élé  ment. De cette manière, les éléments de mur  préfabriqués peuvent être disposés, comme  représenté à la     fig.    4, afin de former un cof  frage d'angle permanent qui, après mise en  place d'armatures de fer peut être rempli de  béton de la manière usuelle,     afin    de former  un pilier d'angle 13.  



  La     fig.    5 illustre une variante de construc  tion     dans    laquelle les extrémités des deux élé  ments de mur préfabriqués, disposées à une  distance a l'une de l'autre, sont reliées entre  elles par deux pièces profilées 14 ou élément  de jonction présentant en coupe transversale la  forme d'un U. Ces pièces profilées 14 consti  tuent avec les extrémités des deux éléments de  mur préfabriqués un coffrage permanent pour  un pilier 15. De cette manière, il est possible  de réaliser des piliers de plus grandes dimen  sions.  



  La     fig.    6 illustre une variante d'exécution  dans laquelle les plaques d'un côté 2 des élé  ments de mur préfabriqués sont plus courtes  que les plaques de l'autre côté 3. Les plaques  du côté 3 sont placées bout à bout, tandis que  les plaques du côté 2 sont reliées entre elles  par une pièce profilée 14. Dans ce cas, le pilier  porteur 15 fait saillie seulement sur la face 2  du mur. Il est clair que, dans une variante,  les plaques du côté 3 pourraient être plus cour  tes que les plaques du côté 2 et être reliées  entre elles par une pièce profilée. Dans ce cas,  le pilier porteur ferait saillie seulement sur la  face 3 du mur.      La     fig.    7 illustre une variante d'exécution  d'un angle permettant de réaliser un pilier  d'angle porteur 16.

   Les plaques internes 3  sont coupées à une très petite distance b des  entretoises 5 (par exemple de 1 cm) et sont  reliées entre elles par une plaque 17 disposée  en biais et prenant appui sur les entretoises 5  et sur les extrémités des plaques internes 3.  



  De ce qui précède, on peut se rendre  compte que le procédé de construction décrit  permet la réalisation très rapide du gros     oeuvre     d'une maison, par exemple, puisque l'ossature  de celle-ci, constituée par les piliers, est mon  tée en même temps que les éléments de mur  préfabriqués constituant les murs. De plus, ces  éléments constituent des coffrages permanents,  ce qui évite tout le travail de fabrication et de  démolition de coffrages spéciaux.  



  Enfin, la construction réalisée par ce pro  cédé     comporte    des éléments de mur préfabri  qués et des piliers qui, après la prise du béton  des piliers, forment un ensemble monolithique.  



  Les éléments de jonction peuvent être  constitués par des planches fixées sur les faces  externes des plaques latérales 2 et 3. Ces plan  ches peuvent être prévues en un matériau sur  lequel le béton fait prise, afin de former une  partie du 'coffrage permanent, mais peuvent  également être prévues en bois et être retirées  après la prise du béton. Dans ce dernier cas,  seules les parties du     coffrage        formées    par les  éléments de mur préfabriqués sont perma  nentes.



  Construction method, prefabricated wall element for its implementation, and construction obtained by this method There are various methods of constructing the shell of a house. To reduce the cost of construction, it has been proposed, for example, to mount reinforced concrete pillars, then to close the spaces between these pillars by means of prefabricated panels.



  The present invention relates to a construction process using pre-fabricated elements which is characterized by the fact that the framework of the construction is formed by pouring concrete pillars as assembly progresses. walls by means of pre-fabricated panels comprising at least two parallel walls held by spacers, the ends of two neighboring panels constituting with the spacers permanent formwork for the casting of the pillars.



  The subject of the invention is also a prefabricated wall element for implementing the method and which is characterized by the fact that it consists of a panel having side plates integral with at least two spacers arranged at the same time. near the ends of said side plates, the whole arranged so that each end of a panel constitutes a part of a permanent shuttering intended for the casting of the pillars forming the framework of the construction.



  Finally, a further subject of the invention is a construction produced according to the method which is characterized by the fact that it comprises prefabricated panels and pillars cast in permanent forms formed by the parts of said panels, and by the fact that these panels are made of a material on which the concrete sets, so that, after the concrete sets, the panels and the pillars form a monolithic whole.



  The accompanying drawing shows, by way of example, some variants of walls built according to the process.



  Fig. 1 is a partial section of a first variant.



  Fig. 2 is an elevational view of a. wall under construction.



  Fig. 3 is a perspective view of a tool.



  Fig. 4 is a partial sectional view of a first variant embodiment of a corner.



  Figs. 5 and 6 are partial sectional views of two other variants.



  Fig. 7 is a sectional view of an execution variant from an angle.



  According to fig. 1 and 2 of the accompanying drawing, a wall is formed by pre-fabricated wall elements arranged end to end. Each prefabricated wall element has 1) an external side plate 2; 2) an inner side plate 3; 3) spacers 5 fixed with nails 4 on plates 2 and 3.



  These spacers, preferably of a non-hygroscopic material, are arranged near the ends of the plates. In a variant, these spacers provided here in an agglomerated material, could be provided in wood or other material of this kind.



  When these prefabricated wall elements are placed end to end, the ends of two neighboring elements form a permanent formwork in which a concrete pillar is poured after having placed the necessary reinforcements.



  In practice, we proceed with the progressive assembly of the wall, that is to say that after placing two wall elements end to end, concrete is poured into the formwork, then when all the forms formed by a first row horizontal end-to-end prefabricated wall elements representing the desired length of the wall are filled with concrete, a second row of wall elements is placed on the previous row and the concrete pouring operation is restarted and so on until the wall has the desired height. In this way, the pillars 6 are mounted together with the wall and hand hold the pre-fabricated wall elements in position.



  In order for the assembly of pre-fabricated pillars-elements to form a rigid whole, it is advisable to use in the construction of prefabricated wall elements, lateral plates and, if necessary, spacers made of a material on which the concrete takes hold. , such as fiber cement for example. This will avoid the need for chaining between pillars.



  In order to facilitate the installation of the prefabricated wall elements of the second row, it is possible, when pouring the concrete in the forms formed by the wall elements of the first row, to place a removable frame 8 astride the junction of neighboring elements, and fill each formwork with concrete up to the height of the upper edge 9 of this frame 8.



  After removing these frames, the pillars emerge from their permanent forms and form guides for the placement of the prefabricated wall elements of the second row.



  In the interior void 10 of the prefabricated wall elements, plates 11 of an insulating and hydrophilic material are slid.



  The ends of the pre-fabricated wall elements intended to form an angle comprise an external plate 2, of greater length than the internal plate 3. The term “length” is understood to mean the horizontal dimension of the element. In this way, the prefabricated wall elements can be arranged, as shown in fig. 4, in order to form a permanent corner frame which, after placing the iron reinforcements, can be filled with concrete in the usual way, in order to form a corner pillar 13.



  Fig. 5 illustrates an alternative construction in which the ends of the two prefabricated wall elements, arranged at a distance from each other, are connected to each other by two profiled pieces 14 or connecting element having in cross section the U-shaped. These profiled pieces 14 together with the ends of the two prefabricated wall elements constitute a permanent shuttering for a pillar 15. In this way, it is possible to produce pillars of larger dimensions.



  Fig. 6 illustrates an alternative embodiment in which the plates on one side 2 of the prefabricated wall elements are shorter than the plates on the other side 3. The plates on side 3 are placed end to end, while the plates side 2 are interconnected by a profiled part 14. In this case, the supporting pillar 15 protrudes only on the face 2 of the wall. It is clear that, in a variant, the plates on side 3 could be shorter than the plates on side 2 and be connected to each other by a profiled part. In this case, the supporting pillar would protrude only on face 3 of the wall. Fig. 7 illustrates an alternative embodiment of an angle making it possible to produce a supporting angle pillar 16.

   The internal plates 3 are cut at a very small distance b from the spacers 5 (for example 1 cm) and are interconnected by a plate 17 arranged at an angle and bearing on the spacers 5 and on the ends of the internal plates 3.



  From the foregoing, it can be seen that the construction method described allows very rapid construction of the shell of a house, for example, since the framework of the latter, formed by the pillars, is assembled in at the same time as the prefabricated wall elements constituting the walls. In addition, these elements constitute permanent forms, which avoids all the work of manufacturing and demolishing special forms.



  Finally, the construction carried out by this process comprises prefabricated wall elements and pillars which, after the concrete sets on the pillars, form a monolithic whole.



  The junction elements can be constituted by boards fixed to the external faces of the side plates 2 and 3. These boards can be provided in a material on which the concrete sets, in order to form part of the permanent formwork, but can also be provided in wood and be removed after the concrete has set. In the latter case, only the parts of the formwork formed by the prefabricated wall elements are permanent.

 

Claims (1)

REVENDICATIONS 1. Procédé de construction à l'aide d'élé ments préfabriqués, caractérisé par le fait qu'on constitue l'ossature de la construction en coulant des piliers en béton au fur et à me sure du montage des murs au moyen de pan neaux préfabriqués comportant au moins deux parois parallèles maintenues par des entretoi ses, les extrémités de deux panneaux voisins constituant avec les entretoises des coffrages permanents pour le coulage des piliers. CLAIMS 1. Construction method using prefabricated elements, characterized by the fact that the framework of the construction is formed by pouring concrete pillars as the walls are assembled using panes. Prefabricated panels comprising at least two parallel walls held by its spacers, the ends of two neighboring panels constituting with the spacers permanent formwork for the casting of the pillars. II. Elément de mur préfabriqué pour la mise en oeuvre du procédé, caractérisé par le fait qu'il est constitué par un panneau présen tant des plaques latérales solidaires d'au moins deux entretoises disposées à proximité des extrémités desdites plaques latérales, le tout agencé de manière que chaque extrémité d'un panneau constitue une partie d'un coffrage permanent destiné au coulage des piliers for mant l'ossature de la construction. III. II. Prefabricated wall element for implementing the method, characterized in that it consists of a panel having side plates integral with at least two spacers arranged near the ends of said side plates, the whole arranged so that each end of a panel constitutes a part of a permanent formwork intended for the casting of the pillars forming the framework of the construction. III. Construction réalisée selon le procédé, caractérisée par le fait qu'elle comporte des panneaux préfabriqués et des piliers coulés dans des coffrages permanents formés par les parties desdits panneaux et par le fait que ces panneaux sont en une matière sur laquelle le béton fait prise, de sorte que, après la prise du béton, les panneaux et les piliers forment un ensemble monolithique. SOUS-REVENDICATIONS 1. Procédé selon la revendication I, ca ractérisé par le fait qu'on place un cadre amo vible à cheval sur la jonction de deux éléments de mur voisins dressés, puis, rempli de béton le coffrage ainsi formé jusqu'au bord supérieur du cadre, puis retire ce cadre avant de placer de nouveaux éléments de mur préfabriqués sur les éléments de mur de la rangée inférieure. 2. Construction carried out according to the process, characterized by the fact that it comprises prefabricated panels and pillars cast in permanent shutterings formed by the parts of said panels and by the fact that these panels are made of a material on which the concrete sets, of so that, after the concrete sets, the panels and pillars form a monolithic whole. SUB-CLAIMS 1. Method according to claim I, characterized in that a removable frame is placed straddling the junction of two neighboring upright wall elements, then, filled with concrete, the formwork thus formed to the edge. top of the frame, then remove that frame before placing new pre-fabricated wall elements on top of the wall elements in the bottom row. 2. Procédé selon la revendication I, carac térisé par le fait qu'on relie les extrémités de deux éléments de mur préfabriqués voisins par au moins un élément de jonction formant une partie du coffrage permanent. 3. Elément de mur préfabriqué selon la re vendication II, caractérisé par le fait que les plaques sont de même longueur. 4. Elément de mur préfabriqué selon la revendication II, caractérisé par le fait que l'une des plaques est de plus grande longueur que l'autre. Frédéric Châtelain et Yolande Châtelain Method according to Claim I, characterized in that the ends of two neighboring prefabricated wall elements are connected by at least one connecting element forming part of the permanent shuttering. 3. Prefabricated wall element according to claim II, characterized in that the plates are of the same length. 4. Prefabricated wall element according to claim II, characterized in that one of the plates is of greater length than the other. Frédéric Châtelain and Yolande Châtelain
CH317032D 1954-07-16 1954-07-16 Construction method, prefabricated wall element for its implementation, and construction obtained by this method CH317032A (en)

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CH317032T 1954-07-16

Publications (1)

Publication Number Publication Date
CH317032A true CH317032A (en) 1956-11-15

Family

ID=4496619

Family Applications (1)

Application Number Title Priority Date Filing Date
CH317032D CH317032A (en) 1954-07-16 1954-07-16 Construction method, prefabricated wall element for its implementation, and construction obtained by this method

Country Status (1)

Country Link
CH (1) CH317032A (en)

Similar Documents

Publication Publication Date Title
CA2017930A1 (en) Prefabricated concrete form units and wall building process
FR2487405A1 (en) WALL MODULE FOR THE CONSTRUCTION OF CONCRETE STRUCTURES AND METHOD FOR CONSTRUCTING A CONCRETE CAST CONCRETE STRUCTURE
EP0382649A1 (en) Boarding for the realisation of swimming pools in particular, and method of manufacturing same
FR2664319A1 (en) Shuttering device comprising panels, and connection pieces for assembling these panels
CA2802585C (en) Prefabricated modular construction element for building a wall
CH317032A (en) Construction method, prefabricated wall element for its implementation, and construction obtained by this method
BE1010092A6 (en) Method of manufacturing and assembly of an element construction concrete.
FR2567560A1 (en) Method and prefabricated formwork blocks for the construction of concrete walls, particularly for swimming pools
FR2613407A1 (en) GAME GROUND DISMOUNTABLE FOR THE PRACTICE OF SQUASH OR OTHER SIMILAR SPORT
FR2474569A1 (en) Shutter for concrete column - has two similar vertical segments secured to external tie bolts through posts notched onto ends of half yokes
FR2704253A1 (en) Method of constructing buildings with reinforced-concrete frames
CH289601A (en) Wall in molded elements.
FR2650020A1 (en) Ashlar for the construction of vertical reinforced concrete walls, in particular swimming pool walls and a method for its use
FR2545136A1 (en) Building made of prefabricated elements and more precisely tomb
FR2614052A1 (en) Precast reinforced concrete construction elements, method for manufacturing the latter and walls obtained
BE1000801A7 (en) Prefab. wall construction system - uses two panels with inner reinforcing element joined together to retain wall
FR2746128A1 (en) Coffering for concrete building sections
BE460404A (en)
FR2578278A1 (en) Method for the construction of buildings by mechanically assembling prefabricated construction elements and corresponding elements
FR2519364A1 (en) PREFABRICATED PANELS FOR CONSTRUCTION OF BUILDINGS
CH341303A (en) Process for mounting a formwork and spacer for its implementation
CH346009A (en) Plasterboard or similar material for the construction of thin partitions, method of manufacturing this plate and mold for carrying out this method
FR2519048A2 (en) Reinforcement for building walls - comprises cast concrete formed over strengthening wires contained in cavities cut into wall
CH361111A (en) Wall and method for its manufacture
FR2465847A2 (en) House floor is supported by beams - with intermediate joists, positioned at junction between modular wall panels