WO2023007754A1 - 同調機能付き共吊り連動クレーン - Google Patents

同調機能付き共吊り連動クレーン Download PDF

Info

Publication number
WO2023007754A1
WO2023007754A1 PCT/JP2021/029316 JP2021029316W WO2023007754A1 WO 2023007754 A1 WO2023007754 A1 WO 2023007754A1 JP 2021029316 W JP2021029316 W JP 2021029316W WO 2023007754 A1 WO2023007754 A1 WO 2023007754A1
Authority
WO
WIPO (PCT)
Prior art keywords
speed
hoisting
load
hooks
crane
Prior art date
Application number
PCT/JP2021/029316
Other languages
English (en)
French (fr)
Inventor
至康 岸本
清忠 本間
Original Assignee
株式会社日立プラントメカニクス
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 株式会社日立プラントメカニクス filed Critical 株式会社日立プラントメカニクス
Priority to KR1020227005231A priority Critical patent/KR102652257B1/ko
Priority to CN202180004975.XA priority patent/CN115884938A/zh
Publication of WO2023007754A1 publication Critical patent/WO2023007754A1/ja

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/06Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for minimising or preventing longitudinal or transverse swinging of loads
    • B66C13/063Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for minimising or preventing longitudinal or transverse swinging of loads electrical
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C1/00Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles
    • B66C1/10Load-engaging elements or devices attached to lifting or lowering gear of cranes or adapted for connection therewith for transmitting lifting forces to articles or groups of articles by mechanical means
    • B66C1/12Slings comprising chains, wires, ropes, or bands; Nets
    • B66C1/14Slings with hooks
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/04Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
    • B66C13/08Auxiliary devices for controlling movements of suspended loads, or preventing cable slack for depositing loads in desired attitudes or positions
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/18Control systems or devices
    • B66C13/22Control systems or devices for electric drives
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/18Control systems or devices
    • B66C13/22Control systems or devices for electric drives
    • B66C13/30Circuits for braking, traversing, or slewing motors
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C13/00Other constructional features or details
    • B66C13/18Control systems or devices
    • B66C13/40Applications of devices for transmitting control pulses; Applications of remote control devices
    • B66C13/44Electrical transmitters
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66DCAPSTANS; WINCHES; TACKLES, e.g. PULLEY BLOCKS; HOISTS
    • B66D1/00Rope, cable, or chain winding mechanisms; Capstans
    • B66D1/28Other constructional details
    • B66D1/40Control devices
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C2700/00Cranes
    • B66C2700/08Electrical assemblies or electrical control devices for cranes, winches, capstans or electrical hoists
    • B66C2700/082Control of the secondary movements, e.g. travelling, slewing, luffing of the jib, changing of the range

Definitions

  • the present invention relates to an interlocked co-hoisting crane that carries long or heavy objects by co-hoisting with a plurality of hooks, and more particularly to a co-hoisting interlocked crane that has a synchronization function for that purpose. be.
  • two cranes When transporting a long or heavy object, two cranes may be used together.
  • a long vehicle with load points near both ends such as a railroad vehicle, can be rationally transported by two co-hoisting interlocking cranes.
  • two cranes when transporting a huge heavy object, it is better to use two cranes rather than one huge crane to spread the load on the building and foundation over a wider area via each crane. Therefore, the cost of building and foundation can be reduced.
  • the ceiling of the building can be lowered and the crane can be easily moved to the edge of the building.
  • the work can be performed separately for each crane, so there are various merits such as high work efficiency.
  • Patent Documents 1 to 3, for example In order to meet the needs for co-hoisting with two cranes, various techniques have been conventionally proposed (see Patent Documents 1 to 3, for example).
  • a serial communication device using radio or light as a medium can be used to simultaneously give hoisting/lowering commands to a plurality of cranes. It is possible to send signals to cranes, but when serial communication is used, the timing at which each crane receives the signal is slightly different, resulting in a slight difference in the timing of activation, resulting in more than three hooks. load-sharing imbalance.
  • the co-hoisting interlocked crane with a synchronization function of the present invention allows a certain change in position and speed instead of the method of aligning the position and speed adopted in conventional co-hoisting interlocked cranes.
  • Co-suspension interlocking by three or more hooks is made possible by performing control so that the torques generated by the interlocking hoisting motors are equalized.
  • the speed control of the hoisting motor for the plurality of hooks is controlled so that the speed decreases as the motor load increases during hoisting.
  • Control is performed so that the speed increases as the motor load decreases, and that when the motor load increases, the speed increases, and as the motor load decreases, the speed decreases. Therefore, when hoisting and hoisting are interlocked, the speed of the hook with a larger load sharing than the other hooks will be slower than the other hooks, and the speed of the hooks with a smaller load sharing will be faster than the other hooks. At the time of hoisting and co-hoisting interlocking, the speed of the hook with a larger load sharing than the other hooks is faster than the other hooks, and the speed of the hook with a smaller load sharing than the other hooks is slower than the other hooks. It is characterized in that the plurality of hooks share the load with each other when the plurality of hooks are hoisted together.
  • the setting of the plurality of hook hoisting control devices is such that the rate of change in speed with respect to the motor load is the same, and the capacities of the plurality of hook hoisting devices are set to the same value. are different, the rate of change in speed with respect to the motor load is set smaller according to the ratio of the capacities of the hoisting devices of each hook so that the load sharing with respect to the capacity of the hoisting device of each hook becomes equal. can be controlled to
  • the output speed characteristics at the time of starting the motor are set so that the speed does not increase in the overload state during hoisting, and the low speed occurs when the load is reduced.
  • the load When lowering the load, it has a characteristic of not speeding up when the load is zero, and a low speed when the load is applied. By doing so, an overload will be applied to any of the hoisting devices that are interlocked with each other due to a difference in reception timing between cranes for serial communication used as an operation signal and a difference in operation timing due to a difference in brake release characteristics. can be prevented.
  • each crane is once accelerated to the rated speed, and the light load high speed that can be output by the load torque at the rated speed is calculated by each crane,
  • the speed is transmitted to other cranes performing co-hoisting interlocking, the light load high speed transmitted from each crane is received, and the slowest speed among the light load high speed speeds of its own crane is received. is used as the speed command value.
  • the speed increases as the motor load increases, and the speed decreases as the motor load decreases.
  • each hook is accelerated to the rated speed, the torque value generated by the hoisting motor of each hook at that time is sampled, and the speed that can be accelerated is transmitted to the other cranes.
  • each crane's speed that can be accelerated includes its own crane, and the slowest speed among them is set as the speed that can be increased for that crane, and each crane is operated at high speed.
  • the speed decreases as the motor load increases, and when the motor load decreases, the speed increases.
  • the first balance is co-suspended by the first hook of the first crane and the first hook of the adjacent second crane, and the second hook of the first crane and the adjacent second hook are suspended. Co-hanging a second beam with the second hook of the second crane, hanging the first sling wire rope with the first beam and the second beam, and adjoining the first hook of the third crane.
  • three or more hooks can be co-hoisted interlocked so that the respective hooks can appropriately share the load.
  • Three or more hooks (three or more cranes) can safely hoist and lower products without being overloaded.
  • the load on the building can be distributed, and when there are no large products, the cranes can be distributed to perform multiple tasks, improving crane work efficiency.
  • the motor can be operated at a speed exceeding the rated speed if there is a margin in the motor torque. Since the load sharing can be kept unchanged during the light load high speed operation, the efficiency of the light load high speed operation can be improved without overloading any of the motors.
  • FIG. 1 is an explanatory diagram of an overall system of a co-hoisting interlocking crane with a synchronization function of the present invention
  • FIG. FIG. 4 is an explanatory diagram of a communication form of interlocked operation
  • FIG. 2 is a control block diagram of a speed control system of the co-hoisting interlocking crane with a tuning function of the present invention
  • FIG. 4 is an explanatory diagram of motor characteristics of the co-hoisting interlocking crane with a tuning function of the present invention
  • FIG. 5 is an explanatory diagram of tuning control when the brake is released at startup
  • FIG. 4 is an explanatory diagram of light-load high-speed interlocked operation
  • FIG. 3 is an explanatory view showing an example of use of the co-suspended interlocking crane with a synchronization function of the present invention
  • FIG. 3 is an explanatory diagram showing an example of use of the co-suspended interlocking crane with a tuning function of the present invention using a balance.
  • FIG. 1 is an explanatory diagram of the overall system of the co-hoisting interlocking crane with a synchronization function of the present invention.
  • co-suspension interlocking has been performed by two hooks. When it is lifted by three or more hooks (four in this embodiment) as in this embodiment, for example, if one hook is delayed in starting during the hoisting operation, that hook will share the load. Conversely, if one hook is activated quickly, the other two hooks out of the four do not share the load.
  • the present invention provides tuning of the load sharing when hoisting with three or more hooks.
  • FIG. 1 is described as an embodiment in which four cranes are equipped with one hook for each crane, interlocking of three or more hooks is preferred.
  • the scope of application of the invention includes a crane equipped with a plurality of hooks, or a crane or a crane with five or more hooks.
  • the motor IM is controlled by the speed feedback of the detector of the pulse generator PG based on the command from the sequencer PLC to the speed controller INV.
  • the power of the IM is transmitted to the wire drum DR via the brake BR and the speed reducer GR, and the hooks are suspended by the wire rope WR wound around the wire drum DR.
  • the four hooks suspended from each crane are A load W is co-suspended.
  • Each hook is equipped with a load cell LC that detects the load applied to each hook, and detects an overload due to unbalanced load sharing among the hooks.
  • the load cell LC has a slow reaction speed, and even if it can detect an overloaded state after it has become overloaded, it cannot prevent it from becoming overloaded.
  • the control of the motor IM by the speed control device INV prevents the imbalanced state of the load sharing between the hooks, which causes the load meter LC to operate, and synchronizes the load sharing between the hooks. .
  • Fig. 2 shows the communication mode of interlocking operation of this crane.
  • interlocking radio controller TCX In order to operate four cranes, there is one interlocking radio controller TCX, and a corresponding interlocking operation receiver RCX is installed on each crane, and the crane operator OP controls the interlocking radio controller TCX. When operated, each crane receives the same signal. Further, radio controllers TC1 to TC4 and operation receivers RC1 to RC4 are installed for each crane CR1 to CR4.
  • the interlocking wireless controller TCX can select which crane to operate and how many cranes to operate.
  • Cranes not selected by the interlocking wireless controller TCX TC1 to TC4 and operation receivers RC1 to RC4 can secure the operation right, disconnect from interlocking operation, and operate the crane independently. Conversely, for cranes whose operation rights are secured by the wireless controllers TC1 to TC4 and operation receivers RC1 to RC4 of each crane, interlocking cannot be selected with the interlocking wireless controller TCX and the dynamic operation receiver RCX. As shown in the figure, the operation rights are interlocked with each other.
  • inter-crane communication transmitters TM1 to TM4 and inter-crane communication receivers RM1 to RM4 are provided for minimum signal confirmation between the cranes.
  • the wireless configuration makes it easy to switch to interlocked operation and leave interlocked operation.
  • FIG. 3 shows a control block diagram of the speed control system of the crane with the tuning function of the present invention. Interlocking selection is performed by the interlocking wireless controller TCX shown in FIG. Through the converter LAD, the instantaneous velocity setpoint value ⁇ * is produced along with the acceleration or deceleration time. The actual speed detection value ⁇ detected by the pulse generator PG is subtracted from the speed target value ⁇ * to calculate the speed deviation amount. The cut value is used as the torque target value T * to control the current of the motor. As a result, as shown in FIG. 4, the speed decreases as the torque increases, and the speed increases as the torque increases in the negative direction. If the characteristics shown in FIG. 4 are replaced by the hoisting operation of the crane, the plus side of the torque means hoisting, and the minus side of the torque means hoisting down.
  • the control constants of the speed controllers of the hoisting devices are set so that the slopes of the characteristics shown in FIG. 4 are the same. It is possible to equalize the rate of change of the speed with respect to the load of each motor, and equalize the load sharing of the hooks interlocked with each other.
  • the slope of the characteristics shown in FIG. 4 is set small according to the ratio of the capacities of the hoisting devices. set to be large. As a result, control can be performed so that the load sharing with respect to the capacity of each hoisting device is even. For example, when co-hoisting with a device having twice the capacity of a hoisting device, the load sharing of the hoisting device can be doubled by halving the slope of FIG. 4 of the speed control device.
  • the hoisting/lowering command signal sent by the interlocking wireless controller TCX is received by the interlocking operation receiver RCX of each crane.
  • the characteristic of Fig. 5 (2) is used when hoisting, and the speed is zero when the torque limiter value (usually 150%) is reached with the slope characteristic of Fig. 5 (2).
  • the load sharing of the hook that released the brake first begins to decrease, the hoisting speed is generated, and the load is shared evenly with the other hooks at low speed. become. Then, when the time (preset time) until the load is evenly shared, the acceleration AC is performed. In this way, by synchronizing the load sharing in the range from zero speed to low speed at startup and then shifting to acceleration AC, it is possible to prevent the inertial force of the rotating part from being generated, and it is incorporated in the speed control system of FIG.
  • the limiter LM suppresses the torque generated by the motor to a value below the limiter value (usually 150%). Mechanical damage to equipment and the like can be prevented.
  • Patent Document 3 discloses that when a deviation in the positions of two hooks is detected, a difference is added to the speed command value V * of the speed control device for the two hooks, A technique for correcting the positional deviation detected during inching or acceleration by changing the curve of the linear acceleration converter LAD is described. In this technique, high-speed tuning control response cannot be expected because it is dominated by the linear acceleration converter LAD. On the other hand, in the co-hoisting interlocking crane with a synchronization function of the present invention, which synchronizes three or more hooks , unless the control loop is rotated at high speed, the synchronization of the load sharing will be lost.
  • the actual speed detection value .omega is performed by the high-speed calculation loop of the automatic speed setter ASR, correction is applied at high speed, and at the same time, deviations occurring during inching and linear acceleration are also sequentially corrected.
  • the motor output torque is sampled during the load torque detection HC time.
  • Each crane calculates light load high speeds VH1 to VH5 from the sampled torque according to FIG.
  • the reason why the acceleration AC is stopped at the rated speed and the motor output torque is sampled is that the higher the speed, the higher the motor torque detection accuracy, and that the motor torque detection accuracy is higher during constant-speed operation than during acceleration. is high, and stopping the acceleration at a higher speed has less effect on the transfer time than stopping the acceleration at a low speed.
  • each crane When each crane receives the reception result of the light load high speed VH1 to VH5 by each of the inter-crane communication receivers RM1 to RM4, each crane, including the light load high speed VH1 to VH5 of its own crane, selects the highest speed among those results. Each crane writes the low result to the speed command value V * of the hoisting speed control device INV, and speeds up to the light load high speed VHX shown in FIG. This processing is performed independently by each crane, but since it is performed based on the same data, the same result is derived for all cranes.
  • the timing of the acceleration AC transition of each crane from the rated speed to the light load high speed VHX is determined by each crane receiving the reception result of the light load high speed VH1 to VH5 by each of the inter-crane communication receivers RM1 to RM4.
  • the timing when the PLC calculation time is added all the cranes are accelerated to the same light load high speed VHX almost simultaneously, but the timing is slightly different. Since this slight timing deviation appears as a speed difference, it appears as a load torque fluctuation, and appears as a deviation amount between the speed target value ⁇ * and the actual speed detection value ⁇ shown in FIG. is absorbed by the control of each crane, and the balance of torque sharing of each crane is maintained.
  • Equipment equipped with wire drums DR11 to DR42 respectively mounted on the wire drums DR11 to DR42 and hooks H11 to H42 suspended from the wire drums DR11 to DR42 may be used.
  • a balance can be used, as shown in FIG. 8, to increase the reliability of synchronizing between cranes.
  • the positional deviation between the No. 11 hook H11 and the No. 12 hook H12 is mechanically eliminated by the No. 1 balance BL1
  • the No. 21 hook H21 and No. 22 hook H22 The positional deviation of is mechanically eliminated by the No. 2 balance BL2.
  • the No. 3 balance BL3 mechanically eliminates the positional deviation between the No. 31 hook H31 and the No. 41 hook H41, and the positional deviation between the No. 32 hook H32 and the No. 42 hook H42.
  • the tuning function of the present invention by using the tuning function of the present invention, the slipping force between the suspended load W and the slinging wire, the force to twist the suspended load W, and the twisting force of the suspended load W. Since the tuning effect is exhibited in the direction of balancing the load sharing against the force that tends to cause an overload due to the lifting, slip between the suspended load W and the sling wire, twisting of the suspended load W, and overload are prevented. can be prevented.
  • co-hoisting synchronization can be performed even with a plurality of hooks of three or more. For example, as shown in FIGS.
  • the load applied to the building by the loads of the cranes and the suspended load can be dispersed over a wide area of the building.
  • the size of one crane can be reduced, the ceiling of the building can be made smaller, and the hook of the crane can be moved to the edge of the building.
  • the suspended load becomes a large aggregate, it is built up from small objects.
  • the work can be done by dividing the crane. Work efficiency can be improved by distributing work to different locations.
  • the co-hoisting interlocking crane with a synchronizing function of the present invention can be used in the case of two cranes, three cranes, four cranes, or more, while similarly adding the number of cranes. Since it is possible to synchronize the load sharing, it is possible to carry out the work efficiently while increasing the number of cranes to handle the load whose weight increases as the work progresses.
  • the hoisting devices of the co-hoisting interlocking cranes do not synchronize while exchanging signals, but each hoisting device operates independently to match another hoisting device. Since it is closed and controlled inside an independent crane, it can be joined with a co-hoisting interlocking crane, or it can be a crane that operates independently, and the number of co-hoisting interlocking cranes can be changed freely. It is a system that makes it easy to
  • co-hoisting interlocking crane with a synchronization function of the present invention co-hoisting of three or more hooks is made possible by synchronizing load sharing, so that a large number of small cranes can be interlocked to hoist a large load.
  • the load applied to the building can be distributed, the crane's side dimensions can be improved, the ceiling of the building can be lowered, and a large load can be collected.
  • There are various merits such as being able to work by distributing the cranes before it becomes, and the industrial utility value is very high.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Automation & Control Theory (AREA)
  • Control And Safety Of Cranes (AREA)
  • Jib Cranes (AREA)
  • Load-Engaging Elements For Cranes (AREA)

Abstract

3個以上のフックにより共吊り連動をするのに当たり、各フックの負荷分担が同調する巻上同調機能付きクレーンを提供するため、複数のフックHの巻上げモータIMの速度制御を、巻上げ時においては、モータ負荷が大きくなるとそれにつれて速度が遅くなり、モータ負荷が小さくなるとそれにつれて速度が速くなるように、巻下げ時においては、モータ負荷が大きくなるとそれにつれて速度が速くなり、モータ負荷が小さくなるとそれにつれて速度が遅くなるように、それぞれ制御することにより、巻上げ共吊り連動時においては、他のフックHより荷重分担が大きなフックHは他のフックHより速度が遅くなり、他のフックHより荷重分担が小さなフックHは他のフックHより速度が速くなるように、巻下げ共吊り連動時においては、他のフックHより荷重分担が大きなフックHは他のフックHより速度が速くなり、他のフックHより荷重分担が小さなフックHは他のフックHより速度が遅くなるように、それぞれ動作させるようにして、複数のフックHの共吊り連動時に複数のフックHが互いに荷重を分担し合うようにする。

Description

同調機能付き共吊り連動クレーン
 本発明は、複数のフックで共吊り連動を行うことで、長尺物や重量物を運搬するようにした共吊り連動クレーンに関し、特に、そのための同調機能を備えた共吊り連動クレーンに関するものである。
 長尺物や重量物を運搬する場合、2台のクレーンで共吊りを行う場合がある。例えば、鉄道車両のように、長尺で荷重ポイントが両端部付近にあるものは、2台の共吊り連動クレーンで合理的な運搬ができる。
 また、巨大な重量物を搬送する場合には、巨大なクレーン1台で吊るよりも、2台のクレーンで吊る方が、建屋や基礎に掛かる荷重を各クレーンを介して広い範囲に分散することで、建屋や基礎を低コストにできる。
 また、天井クレーンの場合、建屋天井を低くできたり建屋端部へのクレーンの寄りが良くなる。
 そして、重量物の搬送を行わない場合は、各々のクレーン毎に分割して作業ができるので、作業効率が高い等の様々なメリットがある。
 そして、このような2台のクレーンで共吊りを行うニーズに対応するために、従来から様々な技術が提案されている(例えば、特許文献1~3参照。)。
特開平7―237885号公報 特開平8―217378号公報 特開2016―147726号公報
 ところで、吊り上げる運搬物がさらに長尺で巨大化すると、2台のクレーン(2個のフック)で吊り上げるのではなく、3台以上のクレーン(3個以上のフック)を用いた方がクレーンのコスト的には安価なシステムになる場合があり、そのようなニーズが出てきている。
 しかしながら、上記特許文献1~3に開示された技術で3台以上のクレーン(3個以上のフック)で共吊り連動での吊り上げを行うと、何れかのフックが過荷重になったり、何れかのフックが浮いてしまう等の現象が発生し、3個以上のフックでの共吊り連動は従来技術で実現が困難で、3個以上のフックを共吊り連動させるための新たな技術が必要であった。
 ここで、3個以上のフックを共吊り連動させる場合に、複数台のクレーンに同時に巻上げ/巻下げ指令を与えるのに無線や光などを媒体にしたシリアル通信装置を用いることで合理的に各クレーンへの信号を送信することができるが、シリアル通信を用いた場合、それぞれのクレーンが信号を受け取るタイミングが僅かにズレるため、起動のタイミングに僅かなズレが生じてしまい、3台以上のフックの負荷分担の不均衡が発生する。
 また、巻上げ制御には、吊荷が軽い時に定格速度を超えて増速する軽負荷高速運転制御を採用する場合があるが、定格速度を超えた状態はモータトルクが低下している状態であるため、高速運転中に連動するフックの荷重の分担率が変化してしまうとトルク不足になる危険性があり、共吊り連動運転時の軽負荷高速運転は採用しない場合が多かった。
 本発明は、上記従来の3個以上のフックにより共吊り連動させる場合の問題点に鑑み、3個以上のフックにより共吊り連動させるための同調機能を備えた共吊り連動クレーンを提供することを目的とする。
 上記課題を解決するため本発明の同調機能付き共吊り連動クレーンは、従来の共吊り連動クレーンに採用されている位置や速度を揃える方式ではなく、位置や速度はある一定の変化を許容し、連動するそれぞれの巻上げモータが発生するトルクが均等になるように制御を行うことにより、3個以上のフックによる共吊り連動を可能としたものである。
 具体的には、3個以上の複数のフックで共吊り連動を行うクレーンにおいて、前記複数のフックの巻上げモータの速度制御を、巻上げ時においては、モータ負荷が大きくなるとそれにつれて速度が遅くなり、モータ負荷が小さくなるとそれにつれて速度が速くなるように、巻下げ時においては、モータ負荷が大きくなるとそれにつれて速度が速くなり、モータ負荷が小さくなるとそれにつれて速度が遅くなるように、それぞれ制御することにより、巻上げ共吊り連動時においては、他のフックより荷重分担が大きなフックは他のフックより速度が遅くなり、他のフックより荷重分担が小さなフックは他のフックより速度が速くなるように、巻下げ共吊り連動時においては、他のフックより荷重分担が大きなフックは他のフックより速度が速くなり、他のフックより荷重分担が小さなフックは他のフックより速度が遅くなるように、それぞれ動作させるようにして、複数のフックの共吊り連動時に複数のフックが互いに荷重を分担し合うようにすることを特徴とするものである。
 この場合において、前記複数のフックの巻上げ制御装置の設定を、複数のフックの巻上げ装置の容量が等容量の場合は、モータ負荷に対する速度の変化率を同一にし、複数のフックの巻上げ装置の容量が異なる場合は、各フックの巻上げ装置の容量の大きさの比に応じて、モータ負荷に対する速度の変化率を小さく設定することにより、各フックの巻上げ装置の容量に対する負荷分担が均等になるように制御を行うようにすることができる。
 また、前記巻上げ共吊り連動時又は巻下げ共吊り連動時に、モータ始動時の出力速度特性を、巻上げ時においては、過負荷状態では速度が出ない特性とし、負荷が下がると低速が出る特性とし、巻下げ時においては、負荷がゼロの時には速度が出ない特性とし、負荷が掛かると低速が出る特性とし、ブレーキ解放後のすべてのフックの負荷分担の連動が取れる時間を待ってから加速をするようにすることにより、運転信号として用いるシリアル通信のクレーン間での受信タイミングのズレやブレーキ解放の特性ズレ等による動作タイミングのズレにより、共吊り連動する何れかの巻上げ装置に過負荷が掛かることを防ぐことができる。
 また、前記巻上げ共吊り連動時又は巻下げ共吊り連動時に、各々のクレーンを定格速度まで一旦加速し、定格速度での負荷トルクにより出力可能な軽負荷高速の速度を各々のクレーンで算出し、該速度を共吊り連動を行う他のクレーンに送信し合い、各々のクレーンから送信された軽負荷高速の速度を受信し、それに自身のクレーンの軽負荷高速の速度を含めた中で最も遅い速度を速度指令値として高速運転をさせるに当たり、軽負荷高速運転を行う際に、巻上げ時においては、モータ負荷が大きくなるにつれて速度が遅くなり、モータ負荷が小さくなるとそれにつれて速度が速くなるように、巻下げ時においては、モータ負荷が大きくなるにつれて速度が速くなり、モータ負荷が小さくなるとそれにつれて速度が遅くなるように、それぞれ制御することにより、軽負荷高速運転中に負荷分担がズレないようにする機能を有するようにすることができる。
 すなわち、連動運転時の軽負高速運転を行うのに当たり、前記の制御により、各フックの荷重分担が均等に制御されている。
 この状況において、まず、各フックが各々定格速度まで加速させ、その時の各フックの巻上げモータが発生しているトルク値をサンプリングし増速可能な速度を他のクレーンに向けて発信する。そして、各クレーンが発信してきた各クレーンの増速可能な速度に自身のクレーンを含めて、そのうちから最も遅い速度をそのクレーンの増速可能な速度に設定し、各クレーンを高速運転する。この時、巻上げ時においてはモータ負荷が大きくなるにつれて速度が遅くなり、モータ負荷が小さくなるとそれにつれて速度が速くなり、巻下げ時においては、モータ負荷が大きくなるにつれて速度が速くなり、モータ負荷が小さくなるとそれにつれて速度が遅くなるように制御することにより各フック間の荷重分担率がトルクのサンプリング時から変わるのを防ぐことで、軽負荷高速運転中における負荷分担率の変化に伴うモータトルクの不足を防止する。
 また、クレーン間のフック間に天秤を用いることによりクレーン間の連動ズレを機械的に許容する構造とすることで、クレーン内のみの連動を取る構造とし、連動の信頼性を向上し、例えば、長尺物に生じる捻じれを防止することができる。
 具体的には、第1のクレーンの第1のフックと隣接する第2のクレーンの第1のフックとで第1の天秤を共吊りし、第1のクレーンの第2のフックと隣接する第2のクレーンの第2のフックとで第2の天秤を共吊りし、第1の天秤と第2の天秤で第1の玉掛けワイヤロープを吊るし、第3のクレーンの第1のフックと隣接する第4のクレーンの第1のフックとで第3の天秤を共吊りし、第3のクレーンの第2のフックと隣接する第4のクレーンの第2のフックとで第4の天秤を共吊りし、第3の天秤と第4の天秤で第2の玉掛けワイヤロープを吊るし、第1の玉掛けワイヤロープと第2の玉掛けワイヤロープで長尺物の吊荷を吊り下げるようにすることができる。
 本発明の同調機能付き共吊り連動クレーンによれば、3個以上のフックの共吊り連動を行い、それぞれのフックが適切に負荷分担をするようにすることができ、巨大な製品や非常に長い製品等を3個以上のフック(3台以上のクレーン)が、過負荷状態になることなく安全に吊荷の巻上げ下げを行うことができる。
 これにより、建屋に掛かる荷重が分散できたり、巨大な製品がない時は、クレーンを分散して複数の作業ができるようになるので、クレーン作業効率が向上する。
 さらに、3個以上のフックの共吊り連動時、モータトルクに余裕がある時は定格速度を超えて運転することができる。そして軽負荷高速運転中に負荷分担が変化しないようにできるので、何れのモータも過負荷になることなく軽負荷高速運転の効率化が図れる。
本発明の同調機能付き共吊り連動クレーンの全体システムの説明図である。 連動操作運転の通信形態の説明図である。 本発明の同調機能付き共吊り連動クレーンの速度制御系の制御ブロック図である。 本発明の同調機能付き共吊り連動クレーンのモータ特性の説明図である。 起動時ブレーキ解放時の同調制御の説明図である。 軽負荷高速連動運転の説明図である。 本発明の同調機能付き共吊り連動クレーンの使用例を示す説明図である。 本発明の同調機能付き共吊り連動クレーンの天秤を用いた使用例を示す説明図である。
 以下、本発明の同調機能付き共吊り連動クレーンの実施の形態を、図面を用いて説明する。
 図1は、本発明の同調機能付き共吊り連動クレーンの全体システムの説明図である。
 従来より、共吊り連動は、2個のフックにより行われてきた。
 それが本実施例のように3個以上の数(本実施例では4個)のフックで吊り上げた場合において、例えば、巻上げ操作時に1個のフックの起動が遅れると、そのフックは荷重を分担しなくなり、逆に1個のフックの起動が速くなると4個のうちの他の2個のフックが荷重を分担しなくなる。
 本発明は、このような3個以上のフックで吊り上げる場合に、負荷分担の同調を行うものである。
 ここで、図1の構成は4台のクレーンで、各クレーンに1個ずつのフックが装備された構成の実施例で記載しているが、フックが3個以上のものの連動を行うのが本発明の適用範囲であり、1台のクレーンに複数個のフックが装備されるクレーンの場合であったり、或いはクレーンやフックの数量が5個以上であるものも本発明の適用範囲となる。
 1号クレーンCR1から4号クレーンCR4までのそれぞれの4台のクレーンでは、シーケンサPLCから速度制御装置INVへの指令に基づき、パルスジェネレータPGの検出器の速度フィードバックバックによりモータIMを制御し、モータIMの動力はブレーキBR、減速機GRを介してワイヤドラムDRに伝達し、ワイヤドラムDRに巻き付けられたワイヤロープWRでフックが吊り下げられ、それぞれのクレーンから吊り下げられた4個のフックは共に吊荷Wを共吊りしている。各フックには、それぞれのフックに掛かる荷重を検出する荷重計LCが装備されており、それぞれのフックの荷重分担が不均衡になることによる過荷重を検出するようになっている。しかしながら、荷重計LCは反応速度が遅く、過荷重状態になった後にそれを検出することができても、過荷重になることを未然に防止することはできない。
 本実施例では、速度制御装置INVによるモータIMの制御により、荷重計LCが作動するようなフック間の荷重分担の不均衡状態になることを未然に防ぎ、フック間の荷重分担の同調を行う。
 図2に本クレーンの連動操作運転の通信形態について記載する。
 4台のクレーンを操作するために、連動用無線制御器TCXが1台あり、これに相応する連動操作用受信器RCXが各クレーンに設置され、クレーン運転士OPが連動用無線制御器TCXを操作すると、各クレーンで同じ信号を受信できるようになっている。
 そして、各クレーンCR1~CR4には、各クレーン用に対比する各無線制御器TC1~TC4及び各操作受信器RC1~RC4が設置されている。
 連動用無線制御器TCXは、どのクレーンを動かすか、何台のクレーンを動かすかを選択できるようになっており、連動用無線制御器TCXで選択されなかったクレーンは、各クレーンの無線制御器TC1~TC4と操作受信器RC1~RC4が操作権を確保することができ、連動運転から切り離し、単独でクレーンを動かすことができる。また、逆に各クレーンの無線制御器TC1~TC4と操作受信器RC1~RC4が操作権を確保しているクレーンについては、連動用無線制御器TCX及び動操作用受信器RCXで連動を選択できないように相互に操作権のインターロックが掛かっている。
 そして、各クレーン間の通信には、各クレーン間通信送信器TM1~TM4及び各クレーン間通信受信器RM1~RM4が設けられており最低限のクレーン間の信号確認が行われている。
 このシステムの特長としては、無線構成とすることで、連動運転にしたり、連動運転から離脱したりすることが、容易に行える特徴がある。
 図3に本発明の同調機能付きクレーンの速度制御系の制御ブロック図を示す。
 図2に記載の連動用無線制御器TCXにより連動の選択が行われ、運転指令、速度指令を受けると、速度制御装置INV内部の速度制御系部分に速度指令値Vが発せられ、線形加速変換器LADを通り、加速時間或いは減速時間に沿ったその瞬時の速度目標値ωが作られる。速度目標値ωからパルスジェネレータPGで検出した実速度検出値ωを減算し速度偏差量を算出し、その速度偏差量を自動速度設定器ASRで比例制御PCに掛け、リミッタLMを通し上限をカットした値をトルク目標値Tとしてモータの電流制御を行う。
 これにより、図4に示すようにトルクが大きくなると速度が遅くなり、マイナス側にトルクが大きくなると速度が速くなる特性を得ることができる。
 この図4に示す特性をクレーンの巻上げ動作に置き換えると、トルクがプラス側が巻上げを意味し、トルクがマイナス側が巻下げを意味する。
 図4に示す特性を各モータIMに与えることで、巻上げ時においてはモータ負荷が大きくなるとそれにつれて速度が遅くなり、モータ負荷が小さくなるとそれにつれて速度が速くなるように、巻下げ時においては、モータ負荷が大きくなるとそれにつれて速度が速くなり、モータ負荷が小さくなるとそれにつれて速度が遅くなるように、それぞれ制御する。
 これにより、巻上げ共吊り連動時には、他のフックより荷重分担が大きなフックは他のフックより速度が遅くなり、他のフックより荷重分担が少ないクレーンは他のフックより速度が速くなるように、巻下げ共吊り連動時においては、他のフックより荷重分担が大きなフックは他のフックより速度が速くなり、他のフックより荷重分担が小さなフックは他のフックより速度が遅くなるように、それぞれ動作させることにより、複数のフックの共吊り連動時に、これら複数のフックが互いに荷重を分担し合うように動作する。
 この時、共吊り連動する巻上げ装置の容量が等容量の場合は、各巻上げ装置の速度制御装置の制御定数の設定を、図4に示す特性の傾きが同一になるように設定することで、各モータの負荷に対する速度の変化率を同一にし、共吊り連動する各フックの負荷分担を均等にすることができる。
 また、各巻上げ装置の容量が異なる場合は、各巻上げ装置の容量の大きさの比に応じて、図4に示す特性の傾きを小さく設定することで、モータの速度の変化率に対する負荷分担が大きくなるように設定する。これにより、各巻上げ装置の容量に対する負荷分担が均等になるように制御を行うことができる。
 例えば、巻上げ装置の容量が2倍の装置と共吊り連動する場合、その速度制御装置の図4の傾きを半分にすれば、その巻上げ装置の負荷分担を2倍にすることができる。
 ところで、連動用無線制御器TCXが発信した巻上げ/巻下げ指令信号を、各クレーンの連動操作用受信器RCXが受信する各クレーンでの僅かな受信タイミングのズレや、各クレーンのブレーキの開閉タイミングの僅かなズレによる同期ズレを解消するため、巻上げ時には、図5(2)の特性とし、図5(2)の傾き特性でトルクのリミッタ値(通常は150%)に達した時に速度がゼロになるように速度目標値ωの値を設定する。この状態で、図5(1)に示す巻上げ起動合わせSUの時間だけ待ってから加速に移す。
 これにより、他のフックより速くブレーキの解放をしてしまったフックは、トルクのリミッタ値(通常は150%)に達しゼロ速度で停止する。
 そして、その他のフックもブレーキが開き、巻上げトルクが発生しだすと、最初にブレーキを解放したフックの荷重分担が下がりだし、巻上げ速度を発生し、他のフックと低速で負荷を均等に分担するようになる。そして、その負荷が均等に分担するまでの時間(予め設定した時間)を経過すると加速ACに移行する。
 このように起動時にゼロ速度から低速の範囲で負荷分担を同調させてから加速ACに移行することで、回転部の慣性力等が発生することを防ぎ、図3の速度制御系に組み込まれたリミッタLMにより、モータが発生するトルクはリミッタ値(通常は150%)以下のトルクに抑制し、起動タイミングのズレにより、トルクのリミッタ値を超える負荷が掛かるのを防ぎ、起動タイミングのズレによる巻上げ装置等の機械的損傷を防止することができる。
 一方、巻下げ時には、図5(3)の特性とし、ブレーキが先に解放したものが少し動いた状態で負荷分担がなくなってしまい、トルクゼロの速度ゼロの状態で停止状態になる。そして他のフックのブレーキが解放していった時に負荷分担が均等化し低速の速度が同調をする。そして、図5(1)の巻下げ起動合わせSDの予め設定された時間を経過した後に加速ACする。
 これにより、巻上げ時と同様に巻下げ時の起動タイミングのズレに対しても、モータが発生するトルクのリミッタ値(通常は150%)の範囲以下のトルクに抑えることができるので巻上げ装置等の機械的損傷を防止することができる。
 このような起動時に発生した同調ズレを補正する方法として、特許文献3には、2つのフックの位置のズレを検出すると2つのフックの速度制御装置の速度指令値Vに差を付けたり、インチング時や加速時に検出した位置のズレに対しては線形加速変換器LADのカーブを変更して位置のズレを修正する技術が記載されている。この技術では、線形加速変換器LADに支配されるので高速の同調制御の応答は期待できない。
 これに対して、3フック以上の同調を行う本発明の同調機能付き共吊り連動クレーンにおいては、高速で制御ループを回さないと負荷分担の同調が崩れてしまうので、速度指令値Vや線形加速変換器LADで調節するのではなく、線形加速変換器LADを通過した後の速度目標値ωに対し、逐次負荷変動により変化して入力されるパルスジェネレータPGの実速度検出値ωとの速度偏差量を自動速度設定器ASRの高速の演算ループで行うので、高速で補正が掛かると同時にインチング時や線形加速時に生じるズレも逐次補正がなされることとなる。
 本実施例では、負荷が小さい時にモータの余力を利用して定格速度100%を超えて速度を増速するシステムを装備している。
 定格速度を超えるとモータの出力トルクが低下するので、負荷トルクTと速度Vの関係は式(1)により2乗低減で抑えるようにしている。
   V=(1/T)1/2 ・・・式(1)
 位置や速度の同調をする従来の同調では、定格速度を超えた運転をしている時に、負荷分担が変わると片側のモータが過負荷になるリスクがあったが、本発明の同調機能付き共吊り連動クレーンでは、負荷分担が等しくなるように同調制御を行うので、前記のようなリスクがなく、定格速度を超えて安全に動作させることができる。
 ただし、各クレーンで速度を増速するのに当たり、各々のクレーンが式(1)の計算結果に基づき速度Vを決定すると、負荷トルクTの検出誤差などの影響で各クレーンの速度Vの値がばらばらになってしまう。また、全クレーンの軽負荷高速の速度を統一するため、式(1)の演算結果をそのままクレーン間で通信すると、通信データ量が増えるので、図6に示すように、T1~T5に対するVH1~VH5に段階的に区切り、VH1~VH5の何れの軽負荷高速の速度が出せるか、或いは出せないかを算出する。
 まず、巻上げUP或いは巻下げDWを行うと、図5に示すように、加速ACを行い、定格速度に到達したところで負荷トルク検出HCの時間、モータ出力トルクのサンプリングを行う。各クレーンがそのサンプリングしたトルクから図6により軽負荷高速VH1~VH5を算出し、その結果を図2に示す各クレーン間通信送信器TM1~TM4により送信する。
 ここで、定格速度で加速ACを止めてモータ出力トルクのサンプリングを行うのは、速度が速いほどモータトルクの検出精度が高いことと、加速中より定速運転中の方がモータトルクの検出精度が高いことと、低速で加速を止めるより、より速い速度で加速を止める方が搬送時間に対する負荷トルク検出HCの時間が与える影響が少ないためである。
 各クレーンは、各クレーン間通信受信器RM1~RM4により軽負荷高速VH1~VH5の受信結果を受け取ると、自身のクレーンの軽負荷高速VH1~VH5を含めて、それらの結果の中から最も速度の低かった結果を各クレーンが巻上げの速度制御装置INVの速度指令値Vに書き込み、図5に示す軽負荷高速度VHXまで増速する。この処理は、各クレーンが独立して行うが、同じデータを基に行うので全クレーンとも同じ結果が導き出される。
 この時、定格速度から軽負荷高速度VHXへの加速AC移行する各クレーンのタイミングは、各クレーンが各クレーン間通信受信器RM1~RM4により軽負荷高速VH1~VH5の受信結果を受け取り、それにシーケンサPLCの演算時間が加わったタイミングで、すべてのクレーンがほぼ同時に同じ軽負荷高速度VHXへの加速が行われるが、僅かにタイミングがズレる。この僅かなタイミングのズレは速度差として出るので、それが負荷トルク変動として表れ、図3に示す速度目標値ωと実速度検出値ωの偏差量として表れ自動速度設定器ASRの比例制御PCの制御により吸収され、各クレーンのトルク分担の均衡が保たれる。
 ところで、長尺で巨大な吊荷Wを対象とする場合、図1に示す方式のほか、図7に示すように、4台のクレーンCR1~CR4、各クレーンCR1~CR4上の2台のクラブにそれぞれ搭載されたワイヤドラムDR11~DR42及びワイヤドラムDR11~DR42に吊られたフックH11~H42を備えた設備を用いることがある。
 さらに、クレーン間の同調の信頼性を上げるために、図8に示すように、天秤を用いることができる。
 具体的には、1号クレーンCR1と2号クレーンCR2については、11号フックH11と12号フックH12の位置ズレは1号天秤BL1が機械的に解消し、21号フックH21と22号フックH22の位置ズレは2号天秤BL2が機械的に解消する。
 また、3号クレーンCR3と4号クレーンCR4については、31号フックH31と41号フックH41の位置ズレは3号天秤BL3が機械的に解消し、32号フックH32と42号フックH42の位置ズレは4号天秤BL4が機械的に解消する。
 そして、1号クレーンCR1と2号クレーンCR2のグループと、3号クレーンCR3と4号クレーンCR4のグループと間の位置ズレは、1号天秤BL1と2号天秤BL2で吊られた玉掛けワイヤ1 SL1と、3号天秤BL3と4号天秤BL4で吊られた玉掛けワイヤ2 SL2とにより吊られた吊荷W自身が天秤となり解消するものとなる。
 これにより、連動用無線制御器TCXの運転信号を各クレーン搭載の連動操作用受信器RCXのクレーン間での受信ズレや、各クレーン間通信の送受信器のクレーン間での受信ズレ等に基づくクレーン間のズレ要因を機械的に解消することができる。
 しかしながら、図8に示す天秤によるクレーン間の位置ズレを機械的に解消する方法も、クレーン内部の、例えば、11号フックH11と12号フックH12間の位置ズレは機械的に解消してくれない。例えば、同調がズレて11号フックH11に対し12号フックH12の位置が高くなってしまった場合、吊荷Wが軽い物体の場合は吊荷Wと玉掛けワイヤ1 SL1との間でスリップし、その摩擦で吊荷Wや玉掛けワイヤ1 SL1を傷付けてしまったり、吊荷Wが捻じり耐力がない物体の場合は玉掛けワイヤ1 SL1と玉掛けワイヤ2 SL2の間で吊荷Wが捻じられてしまい吊荷Wが歪んでしまったり、吊荷Wが重くて捻じりにも強い物体の場合は、12号フックH12と22号フックH22と31号フックH31と41号フックH41が過負荷になってしまう。
 この図8の天秤により構成する方式においても、本発明の同調機能を用いることにより、前記の吊荷Wと玉掛けワイヤ間のスリップしようとする力や吊荷Wが捻じられようとする力や捻じりにより過負荷が生じようとする力に対し負荷分担の均衡を取る方向に同調効果が発揮されるので、吊荷Wと玉掛けワイヤ間のスリップや吊荷Wの捻じりや過負荷が生じることを防止することができる。
 このように、本発明の同調機能付き共吊り連動クレーンを用いることで、3個以上の複数のフックでも共吊り同調ができることになり、例えば、図1、図7及び図8に示すように、4台のクレーンで吊荷Wを吊ることで、クレーンと吊荷の荷重が建屋に加える荷重を建屋の広い範囲に分散することができる。
 また、多くの台数のクレーンで吊ることにより、1台のクレーンの寸法が小さくなり、建屋も天井が小さくできたり、クレーンのフックが建屋の端に寄れるようになる。また、吊荷が大きな集合体になる前は小さい物体から組み上げられていくので、最終組み上げ前の小さいブロックの時には、クレーンを分割して作業ができ、図7及び図8の実施例では、4か所に分散して作業ができるので、作業効率が高くできる。
 また、本発明の同調機能付き共吊り連動クレーンは、2台のクレーンの場合でも、3台のクレーンの場合でも、4台でも、或いはそれ以上の台数でも、同様にクレーン台数を足しながらそれぞれが負荷分担の同調をすることが可能となるので、作業の進行状態に伴い重量が増加していく吊荷を、順次クレーンの台数を増やしながら効率よく作業を進めることができる。
 本発明の同調機能付き共吊り連動クレーンは、共吊り連動するクレーンの巻上げ装置同士が信号をやり取りしながら同調するのではなく、それぞれの巻上げ装置が独立して別の巻上げ装置に合わせるように動作するのが特徴で、独立したクレーン内部で閉じられて制御されているので、共吊り連動クレーンに加わったり、或いは単独動作のクレーンになったり、共吊り連動クレーンの台数を変更したり自在に変更するのが容易なシステムになっている。
 以上、本発明の同調機能付き共吊り連動クレーンについて、その実施例に基づいて説明したが、本発明は上記実施例に記載した構成に限定されるものではなく、その趣旨を逸脱しない範囲において適宜その構成を変更することができるものである。
 本発明の同調機能付き共吊り連動クレーンによれば、3個以上のフックの共吊りを負荷分担の同調を行うことにより可能としたことで、小さいクレーンを多数連動して大きな吊荷を吊ることが可能になり、それに伴い2台のクレーンで吊る場合に比較し、建屋に掛かる荷重を分散したり、クレーンの寄り寸法を改善したり、建屋の天井を低くできたり、吊荷が大きな集合体になる前には、クレーンを分散して作業ができる等、様々なメリットがあり、産業上の利用価値が非常に高いものである。
 CR1 1号クレーン
 CR2 2号クレーン
 CR3 3号クレーン
 CR4 4号クレーン
 H11 11号フック
 H12 12号フック
 H21 21号フック
 H22 22号フック
 H31 31号フック
 H32 32号フック
 H41 41号フック
 H42 42号フック
 W 吊荷
 WR ワイヤロープ
 DR ワイヤドラム
 LC 荷重計
 GR 減速機
 BR ブレーキ
 IM モータ
 INV 速度制御装置
 PG パルスジェネレータ
 PLC シーケンサ
 OP クレーン運転士
 TCX 連動用無線制御器
 TC1 1号無線制御器
 TC2 2号無線制御器
 TC3 3号無線制御器
 TC4 4号無線制御器
 RCX 連動操作用受信器
 RC1 1号操作受信器
 RC2 2号操作受信器
 RC3 3号操作受信器
 RC4 4号操作受信器
 TM1 1号クレーン間通信送信器
 TM2 2号クレーン間通信送信器
 TM3 3号クレーン間通信送信器
 TM4 4号クレーン間通信送信器
 RM1 1号クレーン間通信受信器
 RM2 2号クレーン間通信受信器
 RM3 3号クレーン間通信受信器
 RM4 4号クレーン間通信受信器
 V 速度指令値
 LAD 線形加速変換器
 ω 速度目標値
 ω 実速度検出値
 ASR 自動速度設定器
 PC 比例制御
 LM リミッタ
 T トルク目標値
 T 負荷トルク
 BRA ブレーキ開閉
 BRC ブレーキ閉
 BRO ブレーキ開
 SU 巻上げ起動合わせ
 SD 巻下げ起動合わせ
 UP 巻上げ
 DW 巻下げ
 AC 加速
 DC 減速
 HC 負荷トルク検出
 VHX 軽負荷高速度
 V 速度
 T1 トルク値1(25%)
 T2 トルク値2(35%)
 T3 トルク値3(45%)
 T4 トルク値4(60%)
 T5 トルク値5(75%)
 VH1 軽負荷高速1(200%)
 VH2 軽負荷高速2(169%)
 VH3 軽負荷高速3(149%)
 VH4 軽負荷高速4(129%)
 VH5 軽負荷高速5(115%)
 DR11 1号ワイヤドラム1
 DR12 1号ワイヤドラム2
 DR21 2号ワイヤドラム1
 DR22 2号ワイヤドラム2
 DR31 3号ワイヤドラム1
 DR32 3号ワイヤドラム2
 DR41 4号ワイヤドラム1
 DR42 4号ワイヤドラム2
 BL1 1号天秤
 BL2 2号天秤
 BL3 3号天秤
 BL4 4号天秤
 SL1 玉掛けワイヤ1
 SL2 玉掛けワイヤ2
 SL3 玉掛けワイヤ3
 SL4 玉掛けワイヤ4

Claims (5)

  1.  3個以上の複数のフックで共吊り連動を行うクレーンにおいて、
     前記複数のフックの巻上げモータの速度制御を、巻上げ時においては、モータ負荷が大きくなるとそれにつれて速度が遅くなり、モータ負荷が小さくなるとそれにつれて速度が速くなるように、巻下げ時においては、モータ負荷が大きくなるとそれにつれて速度が速くなり、モータ負荷が小さくなるとそれにつれて速度が遅くなるように、それぞれ制御することにより、
     巻上げ共吊り連動時においては、他のフックより荷重分担が大きなフックは他のフックより速度が遅くなり、他のフックより荷重分担が小さなフックは他のフックより速度が速くなるように、巻下げ共吊り連動時においては、他のフックより荷重分担が大きなフックは他のフックより速度が速くなり、他のフックより荷重分担が小さなフックは他のフックより速度が遅くなるように、それぞれ動作させるようにして、
     複数のフックの共吊り連動時に複数のフックが互いに荷重を分担し合うようにする
     ことを特徴とする同調機能付き共吊り連動クレーン。
  2.  前記複数のフックの巻上げ制御装置の設定を、複数のフックの巻上げ装置の容量が等容量の場合は、モータ負荷に対する速度の変化率を同一にし、複数のフックの巻上げ装置の容量が異なる場合は、各フックの巻上げ装置の容量の大きさの比に応じて、モータ負荷に対する速度の変化率を小さく設定することにより、各フックの巻上げ装置の容量に対する負荷分担が均等になるように制御を行うようにすることを特徴とする請求項1に記載の同調機能付き共吊り連動クレーン。
  3.  前記巻上げ共吊り連動時又は巻下げ共吊り連動時に、モータ始動時の出力速度特性を、巻上げ時においては、過負荷状態では速度が出ない特性とし、負荷が下がると低速が出る特性とし、巻下げ時においては、負荷がゼロの時には速度が出ない特性とし、負荷が掛かると低速が出る特性とし、ブレーキ解放後のすべてのフックの負荷分担の連動が取れる時間を待ってから加速をするようにしたことを特徴とする請求項1又は2に記載の同調機能付き共吊り連動クレーン。
  4.  前記巻上げ共吊り連動時又は巻下げ共吊り連動時に、各々のクレーンを定格速度まで一旦加速し、定格速度での負荷トルクにより出力可能な軽負荷高速の速度を各々のクレーンで算出し、該速度を共吊り連動を行う他のクレーンに送信し合い、各々のクレーンから送信された軽負荷高速の速度を受信し、それに自身のクレーンの軽負荷高速の速度を含めた中で最も遅い速度を速度指令値として高速運転をさせるに当たり、軽負荷高速運転を行う際に、巻上げ時においては、モータ負荷が大きくなるにつれて速度が遅くなり、モータ負荷が小さくなるとそれにつれて速度が速くなるように、巻下げ時においては、モータ負荷が大きくなるにつれて速度が速くなり、モータ負荷が小さくなるとそれにつれて速度が遅くなるように、それぞれ制御することにより、軽負荷高速運転中に負荷分担がズレないようにする機能を有するようにしたことを特徴とする請求項1、2又は3に記載の同調機能付き共吊り連動クレーン。
  5.  第1のクレーンの第1のフックと隣接する第2のクレーンの第1のフックとで第1の天秤を共吊りし、第1のクレーンの第2のフックと隣接する第2のクレーンの第2のフックとで第2の天秤を共吊りし、第1の天秤と第2の天秤で第1の玉掛けワイヤロープを吊るし、第3のクレーンの第1のフックと隣接する第4のクレーンの第1のフックとで第3の天秤を共吊りし、第3のクレーンの第2のフックと隣接する第4のクレーンの第2のフックとで第4の天秤を共吊りし、第3の天秤と第4の天秤で第2の玉掛けワイヤロープを吊るし、第1の玉掛けワイヤロープと第2の玉掛けワイヤロープで長尺物の吊荷を吊り下げるようにしたことを特徴とする請求項1、2、3又は4に記載の同調機能付き共吊り連動
    クレーン。
PCT/JP2021/029316 2021-07-26 2021-08-06 同調機能付き共吊り連動クレーン WO2023007754A1 (ja)

Priority Applications (2)

Application Number Priority Date Filing Date Title
KR1020227005231A KR102652257B1 (ko) 2021-07-26 2021-08-06 동조 기능 구비 공현수 연동 크레인
CN202180004975.XA CN115884938A (zh) 2021-07-26 2021-08-06 带同步谐调功能的合吊联动起重机

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2021121239A JP7009693B1 (ja) 2021-07-26 2021-07-26 同調機能付き共吊り連動クレーン
JP2021-121239 2021-07-26

Publications (1)

Publication Number Publication Date
WO2023007754A1 true WO2023007754A1 (ja) 2023-02-02

Family

ID=80678842

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2021/029316 WO2023007754A1 (ja) 2021-07-26 2021-08-06 同調機能付き共吊り連動クレーン

Country Status (5)

Country Link
JP (1) JP7009693B1 (ja)
KR (1) KR102652257B1 (ja)
CN (1) CN115884938A (ja)
TW (1) TWI796002B (ja)
WO (1) WO2023007754A1 (ja)

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0683689U (ja) * 1993-05-21 1994-11-29 神鋼電機株式会社 複数の揚降用ワイヤを連動し荷役における荷重値に対応したワイヤの揃速制御機能を備えたクレ−ンの揚降制御装置
JPH0925091A (ja) * 1995-07-10 1997-01-28 Hitachi Ltd 連動型インバータ駆動ホイスト
JPH1087282A (ja) * 1996-09-11 1998-04-07 Hitachi Constr Mach Co Ltd 同調制御装置
WO2006013053A1 (en) * 2004-08-02 2006-02-09 Terex-Demag Gmbh & Co. Kg Hoisting-cable drive comprising a single bottom-hook block and two winches

Family Cites Families (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07237885A (ja) 1994-02-28 1995-09-12 Kawaden Co Ltd 複数台のクレーンの同期運転方法
JPH08217378A (ja) 1995-02-08 1996-08-27 Mitsubishi Electric Corp クレーンの制御装置
KR200368133Y1 (ko) 2004-08-04 2004-11-17 (주)성림엠앤씨 권양기의 밸런스 제어장치
KR20070019470A (ko) * 2005-08-12 2007-02-15 현대자동차주식회사 부품 로딩 장치
KR100849520B1 (ko) 2007-02-27 2008-07-31 김경환 동기식 체인 리프트 장치
CN101139069A (zh) * 2007-06-29 2008-03-12 大连华锐股份有限公司 多吊点起重机电气控制方法
US9567195B2 (en) * 2013-05-13 2017-02-14 Hall David R Load distribution management for groups of motorized lifting devices
JP6352201B2 (ja) 2015-02-10 2018-07-04 住友重機械搬送システム株式会社 クレーン装置
KR20210106242A (ko) * 2020-02-20 2021-08-30 주식회사 부명 지능형 연동방식 리프팅 장치

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0683689U (ja) * 1993-05-21 1994-11-29 神鋼電機株式会社 複数の揚降用ワイヤを連動し荷役における荷重値に対応したワイヤの揃速制御機能を備えたクレ−ンの揚降制御装置
JPH0925091A (ja) * 1995-07-10 1997-01-28 Hitachi Ltd 連動型インバータ駆動ホイスト
JPH1087282A (ja) * 1996-09-11 1998-04-07 Hitachi Constr Mach Co Ltd 同調制御装置
WO2006013053A1 (en) * 2004-08-02 2006-02-09 Terex-Demag Gmbh & Co. Kg Hoisting-cable drive comprising a single bottom-hook block and two winches

Also Published As

Publication number Publication date
KR20230018354A (ko) 2023-02-07
TW202304802A (zh) 2023-02-01
KR102652257B1 (ko) 2024-03-29
JP2023017176A (ja) 2023-02-07
JP7009693B1 (ja) 2022-01-26
TWI796002B (zh) 2023-03-11
CN115884938A (zh) 2023-03-31

Similar Documents

Publication Publication Date Title
RU2445250C2 (ru) Способ электрического управления подъемным краном с множеством точек подвеса
CN101330275B (zh) 感应电动机驱动装置、电动机驱动系统以及升降系统
EP3426592B1 (en) Method of detecting a magnitude of a load applied to a hoisting motor in a material handling system, method of determining a magnitude of a load applied to a matrial handling system when the load is lifted using a plurality of hoisting motors and motor drive
US5625262A (en) System for equalizing the load of a plurality of motors
WO2002070392A1 (en) Method and system for load measurement in a crane hoist
US8669724B2 (en) Method and apparatus for load dependent speed control of a motor
CN103601093B (zh) 塔机及其双起升机构同步控制方法、设备和系统
US5210473A (en) System with delay timer for motor load equalization
CN102730568B (zh) 起重机起升机构调速方法、设备以及包含该设备的起重机
CN102647148B (zh) 用于起升变频电机的设备、方法、系统及工程机械设备
WO1995035254A1 (fr) Procede d'arret d'une machine d'enroulement
WO2023007754A1 (ja) 同調機能付き共吊り連動クレーン
US20230072458A1 (en) Lifting apparatus of crane and method of operation thereof
JP2015073385A (ja) インバータ装置
KR20210023337A (ko) 서보모터와 토크센서를 이용한 호이스트 장치
US10167177B2 (en) Crane, and crane control method
JP5566746B2 (ja) 鍛造クレーン及び鍛造クレーンの制御方法
US2774923A (en) Electric control for alternatingcurrent motor
CN105236226A (zh) 对重与轿厢自动平衡节能电梯
CN104891342B (zh) 起升开闭机构及实现起升开闭机构负载均衡的方法、系统
JPH0683689U (ja) 複数の揚降用ワイヤを連動し荷役における荷重値に対応したワイヤの揃速制御機能を備えたクレ−ンの揚降制御装置
CN107973220A (zh) 永磁直驱式电磁挂梁吊的起升系统及其控制方法
JPH04341494A (ja) 4点吊り同調制御方法
AU2020202801B1 (en) Double-drum linkage winding type hoisting system with permanent magnet outer rotor drive
CN103723633A (zh) 一种起重机及其自由落钩控制设备、系统和方法

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21951949

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE