WO2015129128A1 - ヒートポンプシステムおよびその運転方法 - Google Patents

ヒートポンプシステムおよびその運転方法 Download PDF

Info

Publication number
WO2015129128A1
WO2015129128A1 PCT/JP2014/082849 JP2014082849W WO2015129128A1 WO 2015129128 A1 WO2015129128 A1 WO 2015129128A1 JP 2014082849 W JP2014082849 W JP 2014082849W WO 2015129128 A1 WO2015129128 A1 WO 2015129128A1
Authority
WO
WIPO (PCT)
Prior art keywords
heat pump
heat
load
capacity
output
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Ceased
Application number
PCT/JP2014/082849
Other languages
English (en)
French (fr)
Inventor
智 二階堂
剛 淵本
松尾 実
敏昭 大内
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Mitsubishi Heavy Industries Ltd
Original Assignee
Mitsubishi Heavy Industries Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mitsubishi Heavy Industries Ltd filed Critical Mitsubishi Heavy Industries Ltd
Priority to KR1020167015600A priority Critical patent/KR102030890B1/ko
Priority to KR1020177030188A priority patent/KR20170121310A/ko
Priority to CN201480070615.XA priority patent/CN105849484B/zh
Priority to US15/102,023 priority patent/US10215470B2/en
Publication of WO2015129128A1 publication Critical patent/WO2015129128A1/ja
Anticipated expiration legal-status Critical
Ceased legal-status Critical Current

Links

Images

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25DREFRIGERATORS; COLD ROOMS; ICE-BOXES; COOLING OR FREEZING APPARATUS NOT OTHERWISE PROVIDED FOR
    • F25D21/00Defrosting; Preventing frosting; Removing condensed or defrost water
    • F25D21/002Defroster control
    • F25D21/006Defroster control with electronic control circuits
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B49/00Arrangement or mounting of control or safety devices
    • F25B49/02Arrangement or mounting of control or safety devices for compression type machines, plants or systems
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B13/00Compression machines, plants or systems, with reversible cycle
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B25/00Machines, plants or systems, using a combination of modes of operation covered by two or more of the groups F25B1/00 - F25B23/00
    • F25B25/005Machines, plants or systems, using a combination of modes of operation covered by two or more of the groups F25B1/00 - F25B23/00 using primary and secondary systems
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B30/00Heat pumps
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2400/00Component parts or details not otherwise provided for in this subclass
    • F25B2400/06Several compression cycles arranged in parallel
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2400/00Component parts or details not otherwise provided for in this subclass
    • F25B2400/07Details of compressors or related parts
    • F25B2400/075Details of compressors or related parts with parallel compressors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2600/00Control issues
    • F25B2600/02Compressor control
    • F25B2600/021Inverters therefor
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2700/00Sensing or detecting of parameters; Sensors therefor
    • F25B2700/21Temperatures
    • F25B2700/2117Temperatures of an evaporator
    • F25B2700/21171Temperatures of an evaporator of the fluid cooled by the evaporator
    • F25B2700/21172Temperatures of an evaporator of the fluid cooled by the evaporator at the inlet
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B2700/00Sensing or detecting of parameters; Sensors therefor
    • F25B2700/21Temperatures
    • F25B2700/2117Temperatures of an evaporator
    • F25B2700/21171Temperatures of an evaporator of the fluid cooled by the evaporator
    • F25B2700/21173Temperatures of an evaporator of the fluid cooled by the evaporator at the outlet
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B47/00Arrangements for preventing or removing deposits or corrosion, not provided for in another subclass
    • F25B47/02Defrosting cycles
    • F25B47/022Defrosting cycles hot gas defrosting
    • F25B47/025Defrosting cycles hot gas defrosting by reversing the cycle
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02BCLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
    • Y02B30/00Energy efficient heating, ventilation or air conditioning [HVAC]
    • Y02B30/70Efficient control or regulation technologies, e.g. for control of refrigerant flow, motor or heating

Definitions

  • the present invention relates to a heat pump system in which a plurality of heat pumps are connected to a system load and a method of operating the same.
  • the air-cooled heat pump chiller forms frost on the heat source side heat exchanger during heating operation under low ambient temperature conditions, and if it progresses, heat exchange is inhibited and efficiency drops, so frost is removed A frost (defrost) operation is required.
  • frost defrost
  • Patent Documents 1 and 2 disclose that the capacity reduction is backed up by operating the system. Further, Patent Document 3 discloses a technology in which two or more heat pumps connected in a plurality are connected to defrosting operation at the same time as much as possible.
  • heat pumps in recent years are being modularized in units.
  • individual air-cooled heat pump chillers are modularized, a plurality of such modules are connected in series to form a unit, and further external load (system load)
  • system load external load
  • a heat pump system configured by connecting a plurality of units in parallel has been put to practical use.
  • the heat pump in the defrosting operation uses the heat exchanger on the use side to function as an evaporator and takes heat, a spare unit and a shutdown unit are added according to the number of heat pumps that have simply entered the defrosting operation. There is a problem that the operation may be insufficient due to the thermal load of the system load only by operating.
  • the present invention has been made in view of such circumstances, and in a heat pump system in which a plurality of heat pumps are connected to a system load, the number of operating heat pumps can be appropriately controlled even while any heat pump is defrosting. It is an object of the present invention to provide a heat pump system capable of always operating at a capacity corresponding to load and a method of operating the same.
  • the heat pump system of the present invention and its operation method adopt the following means. That is, the heat pump system according to the first aspect of the present invention is a heat pump system in which a plurality of heat pumps are connected to a system load, and sequentially calculates the output capability of the heat pump in operation;
  • the system controller is provided with a system control unit that controls the number of operating heat pumps by comparing the capacity calculation value with a thermal load of the system load as a threshold.
  • the capacity that the heat pump in operation can output is sequentially calculated, and the capacity calculation value Because the system control unit is used to control the number of heat pumps operated by comparing the heat load of the system load with the threshold value as the threshold, even if one of the heat pumps in operation enters defrost operation, the heat pump in operation at that time If a heat pump capable of exhibiting the heating capacity in the operating heat pump exists by setting the calculated value of the capacity that can be output as the threshold value and comparing it with the heat load of the system load to control the number of operating heat pumps.
  • Heat-poon with the ability to handle the heat load of the system load immediately without additional operation of another heat pump It is possible to operate the system. Therefore, even when one of the heat pumps is defrosting, energy saving can be achieved by making the additional operation of another heat pump unnecessary depending on the conditions and operating the heat pump system efficiently with the minimum number of heat pumps. In addition, it is possible to improve the reliability of the system by suppressing the on / off frequency of the heat pump and preventing the occurrence of failure or trouble due to frequent on / off repetition.
  • the calculation of the output capable ability of each heat pump is performed by either the control unit on each heat pump side or the system control unit It may be possible.
  • the control unit on each heat pump side has an operation function of the ability Even if the heat pump does not have an additional function of calculating the capacity of the system control unit, as described above, even if a certain heat pump is defrosting, the minimum heat pump may be operated without additional heat pump operation under some conditions.
  • the heat pump system can be operated efficiently by the number. Therefore, the present invention can be easily applied to an existing heat pump system.
  • the system control unit when the heat pump of any one of the heat pumps starts or finishes defrosting operation, the system control unit
  • the capacity of each of the heat pumps may be increased or decreased to calculate the capacity that can be output by each heat pump.
  • the system control unit increases or decreases the capacity of the heat pump when one of the heat pumps of each heat pump starts or ends the defrost operation, and can calculate the capacity that each heat pump can output. Since each heat pump starts and ends the defrost operation, even if the available output capacity increases or decreases, the available output capacity including that can be calculated at any time. Therefore, regardless of the presence or absence of defrost operation, each heat pump can be operated by accurately setting the number of heat pump operation with respect to the thermal load of the system load, and a situation such as a shortage of capacity can be reliably avoided. .
  • the system control unit is configured to be able to calculate the output that each of the heat pumps can output, with the heat component taken by the heat pump during defrosting being minus capacity. It may be
  • the system control unit is configured to be able to calculate the ability that each heat pump can output with the heat capacity taken by the heat pump in defrost as a minus capacity, so the capacity of the heat pump in defrost is reduced.
  • the capacity that can be more accurately output by calculating the capacity that the heat pump can output as a minus capacity the heat component that the heat exchanger use side heat exchanger in defrost is functioning as an evaporator and deprived as well can do. Therefore, it is possible to operate by setting the number of heat pump operating units correctly with respect to the thermal load of the system load, and it is possible to reliably avoid a situation such as a capacity shortage.
  • the system control unit is preset when one of the heat pumps of the respective heat pumps starts defrosting operation.
  • the capacity that can be output by the heat pump in operation may be calculated by multiplying a certain margin ratio.
  • the system control unit can calculate the ability of the heat pump in operation to be able to output by multiplying the margin set in advance. In this case, by assuming that one heat pump is in a defrost operation and the other heat pumps are also frosted and it is operated in a state where it is easy to enter the defrost, as it is configured.
  • the capacity that can be output is calculated by multiplying the preset margin rate to prevent heat load on the heat pump to suppress frost, and the other heat pumps do not follow and enter the defrost operation Can be Therefore, it is possible to reduce the frequency at which each heat pump enters the defrost operation or to delay the timing at which the heat pump enters the defrost operation, and to improve the efficiency at the time of the heating operation.
  • the system control unit cancels the allocation of the margin rate to the available output capacity for a set time from the end of the defrost operation for the heat pump after the end of the defrost operation. It may be configured as follows.
  • the system control unit is configured to cancel allocation of the allowance rate to the possible output capacity for the set time from the end of the defrost operation to the heat pump after the defrost operation is completed.
  • the capacity that can be output if there is a heat pump immediately after the end of defrost, it is judged that the heat pump is not frosted, so it is judged that there is no need to multiply the margin rate, and only the set time from the end of defrost
  • canceling the allocation of the margin rate it is possible to calculate an output capable ability closer to the actual state. As a result, it is possible to calculate the output capable capability more accurately, and set the heat pump operating number appropriately for the heat load of the system load.
  • the system control unit may be configured to gradually reduce and multiply the margin ratio as the time during which each heat pump continues heating operation is longer.
  • the system control unit is configured to gradually reduce the margin ratio as the time during which each heat pump continues the heating operation is longer, the time during which the heating operation is continued The longer the heat pump is, the easier it is for the frost to occur and the other heat pump can easily follow the defrost operation.
  • calculate the capacity that can be output by multiplying the margin ratio to gradually decrease according to the operation continuation time By setting the heat pump so as not to apply a heat load to suppress the frost, it is possible to suppress the start of the defrost operation of another heat pump. Therefore, the frequency at which each heat pump enters the defrost can be reduced or the timing of entering the defrost operation can be delayed to improve the efficiency at the time of the heating operation.
  • the system control unit counts the number of times of defrosting of the heat pump during operation, and gradually reduces the margin rate as the number increases. It may be configured to be multiplied.
  • the system control unit counts the number of times of heat pump defrosting during operation, and the margin ratio is gradually reduced and multiplied as the number of times increases.
  • the number of defrosting cycles of the heat pump during operation is counted, depending on the number of frosts, since some frost remains due to unmelted and enters the defrost again in a short time and the number of times of defrosting may increase.
  • the capacity that can be output by multiplying the margin rate to be gradually reduced it is possible to suppress frost and prevent the heat pump from entering the defrosting operation without applying a heat load to the heat pump. Therefore, the frequency at which each heat pump enters the defrost can be reduced or the timing of entering the defrost operation can be delayed to improve the efficiency at the time of the heating operation.
  • an operating method of a heat pump system is an operating method of a heat pump system in which a plurality of heat pumps are connected to a system load, and the heat pump in operation can be output
  • the process of calculating the capacity sequentially, the process of comparing the capacity calculation value with the heat load of the system load as a threshold, and the heat load of the system load exceeds the threshold which is the capacity calculation value.
  • a second aspect of the present invention in a method of operating a heat pump system in which a plurality of heat pumps are connected to a system load, the process of sequentially calculating the output capable of outputting the heat pump in operation; In order to have the process of comparing the thermal load of the system load with the capacity calculation value as a threshold and the process of increasing or decreasing the number of operating heat pumps depending on whether the thermal load of the system load exceeds the threshold of the capacity calculation value.
  • the calculated value of the ability that the heat pump in operation can output at that time is used as the threshold value to compare with the heat load of the system load, Heat pump during operation by increasing or decreasing the number of operating heat pumps depending on whether the heat load of the If I heat pump capable of exerting heating capacity exists in immediately without adding operation and another heat pump, it is possible to operate the heat pump system capacity that may correspond to the heat load of the system load. Therefore, even when one of the heat pumps is defrosting, energy saving can be achieved by making the additional operation of another heat pump unnecessary depending on the conditions and operating the system efficiently with the minimum number of heat pumps. In addition, it is possible to improve the reliability of the system by suppressing the on / off frequency of the heat pump and preventing the occurrence of failure or trouble due to frequent on / off repetition.
  • the increase or decrease in the number of operating heat pumps is the threshold value where the thermal load of the system load is the capacity calculation value. It may be determined depending on whether the value exceeds the value obtained by multiplying the step-up load factor or the step-down load factor.
  • the increase or decrease in the number of operating heat pumps is determined based on whether or not the thermal load of the system load is a value obtained by multiplying the step-up load factor or the step-down load factor Therefore, when increasing or decreasing the number of operating heat pumps by comparing the threshold value, which is the capacity calculation value, with the heat load, the value obtained by multiplying the capacity calculation value, which is the threshold value, by the increase load factor or reduction load factor The heat load is compared to determine whether to increase or decrease the number of operating heat pumps or to maintain the number as it is.
  • a load factor range in which the coefficient of performance (COP) of each heat pump is equal to or more than a predetermined value is set in advance, and the load factor defined by the relationship between the heat pump capacity and the required heat load is the upper limit of the load factor range. If the value (increased load factor) is exceeded, the number of operating heat pumps is increased, and if the load factor exceeds the lower limit value of the load factor range (reduced load factor), the number of operated heat pumps is decreased to By increasing or decreasing the number of operating units, each heat pump can always be operated at a COP equal to or higher than a predetermined value. Therefore, regardless of the change in the number of operating units, the heat pump system is always operated efficiently and stably at a high COP. be able to.
  • the calculated value of the ability of the heat pump in operation at that time can be output is used as the threshold. If there is a heat pump capable of exhibiting the heating capacity in the operating heat pump by controlling the number of operating heat pumps by comparing the heat load of the load, the system load without immediately operating another heat pump
  • the heat pump system can be operated with the ability to cope with the heat load of one heat pump, so that even when one heat pump is defrosting, additional heat pump operation is not required depending on conditions, and the heat pump system can be efficiently done with the minimum number of heat pumps. Save energy by operating It is possible.
  • it is possible to improve the reliability of the system by suppressing the on / off frequency of the heat pump and preventing the occurrence of failure or trouble due to frequent on / off repetition.
  • FIG. 1 shows a schematic configuration diagram of a heat pump system according to a first embodiment of the present invention
  • FIG. 2 shows a configuration diagram of each unit thereof.
  • the heat pump system 1 is a heat medium that circulates a heat medium (here, hot water or cold water) with respect to an air conditioner such as a fan coil unit, a water heater, an external load such as factory equipment (hereinafter referred to as system load) 2.
  • the piping 3 is provided.
  • a supply header 4 is provided on the supply side of the heat medium pipe 3 and a return header 5 is provided on the return side.
  • a bypass pipe 7 having a bypass valve 6 is connected between the return header 5 and the supply header 4 so that the heat medium can be bypassed from the supply header 4 to the return header 5 side.
  • a plurality of heat pumps 10A, 10B, 10C are connected in parallel between the return header 5 and the supply header 4 via the heat medium pipes 8A, 8B, 8C and the heat medium pumps 9A, 9B, 9C, respectively.
  • FIG. 10A, 10B and 10C an example in which three heat pumps 10A, 10B and 10C are connected in parallel is shown, but it goes without saying that the number of heat pumps is increased or decreased according to the size of the system load and the like.
  • each unit 10A, 10B, and 10C is configured by a single heat pump, and a plurality of heat pumps are connected in series.
  • each heat pump may be referred to as a "module”, and the heat pump referred to as this module may be modularized. It includes both heat pump and normal heat pump which is not modularized.
  • Each of the units 10A, 10B, 10C is provided with unit-side control units 11A, 11B, 11C that individually control the units 10A, 10B, 10C. Further, each unit 10A, 10B, 10C is configured by connecting a plurality of individual heat pumps (here, heat pump chillers) 12 as modules 13A, 13B, 13C, 13D in series. In this embodiment, one module 10A, 10B, 10C is configured by connecting four modules 13A to 13D in series, but the number of modules connected is as follows. It is not limited and can be increased or decreased as appropriate.
  • each heat pump chiller 12 which comprises each module 13A, 13B, 13C, 13D is demonstrated.
  • the heat pump chiller 12 exchanges heat between a plurality of compressors 14A and 14B connected in parallel, a four-way switching valve 15 for switching the flow direction of the refrigerant, and the refrigerant and water to produce hot water or cold water
  • the refrigeration cycle of the closed circuit comprised by connecting sequentially the refrigerant
  • the heat pump chiller 12 itself may be a known one, and the heat pump chiller 12 having the same configuration is used in each of the modules 13A to 13D. However, they do not necessarily have to have the same configuration.
  • Each heat pump chiller 12 is a module for controlling the number of revolutions and the like of the compressors 14A and 14B based on the detection values of the temperature sensors 19 and 20 provided in the heat medium inlet piping and outlet piping of the water heat exchanger 16, respectively.
  • a control system such as the substrate 21 and the inverter substrates 22A and 22B is provided, and is configured as a module.
  • each of the units 10A, 10B, and 10C described above has a configuration in which four modules 13A to 13D are connected in series to the heat medium pipes 8A, 8B, and 8C.
  • Each module 13A is provided with a control unit 11A, 11B, 11C on each unit side provided with a unit control board 23 for controlling the control of four modules 13A to 13D and an operation unit 24. It is assumed.
  • the unit side control units 11A, 11B and 11C are configured to receive detection values from temperature sensors 25 and 26 provided in the heat medium inlet piping and outlet piping for the units 10A, 10B and 10C. .
  • the heat pump system 1 is provided with a system control unit 27 that controls the number of operating units 10A, 10B, 10C connected in parallel to the system load 2.
  • the system control unit 27 calculates the heat load (flow rate ⁇ return temperature difference ⁇ specific gravity ⁇ specific heat) Q of the system load 2 and the ability C that can be output by the operating units 10A, 10B and 10C as needed. The two are compared based on the result, and the number of operating units 10A, 10B, 10C is controlled to increase or decrease.
  • increase / decrease control of the number of operating units 10A, 10B, 10C by the system control unit 27 will be described in detail with reference to FIGS. 3 and 4.
  • FIG. 3 shows a control flowchart when increasing or decreasing the number of operation
  • FIG. 4 shows an image of the control threshold.
  • the heat load Q of the system load 2 acquires the main pipe flow rate F, the cold water return temperature Ts, the cold water return temperature Tr, etc., which are water supply data to the load side in step S2, and is preset in step S3.
  • Data such as specific gravity Cp, specific heat ⁇ , etc. can be fetched, and can be calculated from the following equation (1) in step S4.
  • Q F (Tr-Ts) Cp ⁇ ((1)
  • the unit 10A during operation, 10B, 10C capable C possible output units 10A in operation at step S12, 10B, the defrost condition monitoring data of each module 13A to 13D of 10C, the heating operation module number M H , obtained as defrost module M D, also by taking the rated capacity Crate of each module which is set in advance in step S13 (heat pump), it is possible in step S14, the calculation from the following equation (2).
  • Crate (M D / M H + M D ) may be replaced by ⁇ ⁇ M D.
  • the capacity C that each unit 10A, 10B, 10C can output during the heating operation is the air heat exchanger 18 of any of the four modules 13A to 13D that constitute each unit 10A, 10B, 10C.
  • the defrosting operation must be performed to melt the frost, and since the heating operation of the module is interrupted, it is necessary to calculate by subtracting its capacity.
  • the thermal load Q of the system load 2 thus calculated is compared with the capability C that the units 10A to 10C can output during the heating operation in step S5, and the number of units 10A to 10C operated is increased or decreased. That is, in the present embodiment, the capability C which can be output by the units 10A to 10C in operation is sequentially calculated, and the calculated value is used as a threshold value when increasing or decreasing the number of operating units. In the above case, as shown in FIG. 4, if the thermal load Q originally exceeds 100 kW, which is the capacity C that can be output, the number of units 10A to 10C operated will be increased, but one module is defrosted Since the possible output capacity C is 75 kW, this value is used as a threshold to increase the number of units 10A to 10C operated.
  • step S5 it is determined whether or not the thermal load Q of the system load 2 exceeds the output capability C. If YES, the process proceeds to step S6 to operate the units 10A to 10C. Instruct to increase the number by one. In the present embodiment, when increasing / decreasing the number of units 10A to 10C operated by comparing the thermal load Q and the available output capacity C, the available output capacity C is multiplied by the increase load factor and the decrease load factor. I use a value.
  • load factor ranges in which the coefficient of performance (COP) of each unit 10A to 10C is equal to or more than a predetermined value are set in advance. If the load factor specified in the relationship with the upper limit value of the load factor range exceeds the operating load factor of units 10A to 10C, the load factor is set as the lower limit value of the load factor range. If the defined step reduction load factor is exceeded, the number of operating units 10A to 10C is decreased to increase or decrease the number of operating units 10A to 10C, so that each unit 10A to 10C always has a COP equal to or greater than a predetermined value. It makes it possible to drive.
  • COP coefficient of performance
  • step S5 "Q> C ⁇ stage increase load factor” is determined, and when the thermal load Q exceeds "C ⁇ stage increase load factor”, "Q ⁇ C ⁇ stage increase load factor” is determined in step S6. The number of units will be calculated and the number of operating units will be instructed to increase. If NO in step S5, the process proceeds to step S7, where "Q> C ⁇ step reduction load factor” is determined, and when the thermal load Q exceeds "C ⁇ step reduction load factor", The process proceeds to step S8 to instruct to decrease the number of operating units 10A to 10C, and when it is determined NO in step S7, the process proceeds to step S9 and nothing is performed (the number of operating units is not increased or decreased). It will return to the position.
  • the system control unit 27 calculates the capability C that the units 10A to 10C in operation can output
  • the capability C that each unit 10A to 10C can output is
  • the control units 11A to 11C on the units 10A to 10C may calculate and send the calculation result to the system control unit 27 to determine increase or decrease in the number of operation.
  • the control units 11A to 11C on the units 10A to 10C side are responsible for the functions shown in steps S11 to S14 in FIG.
  • cold water or hot water is produced by operating the appropriate number of units 10A to 10C, and the cold water or hot water is circulated to the system load 2 for use. it can.
  • the system control unit 27 or the unit side control units 11A to 11C calculate the thermal load Q of the system load 2 and the capability C which can be output by each unit 10A to 10C as needed, and the thermal load Q and the capability capable of outputting
  • the number of operating units 10A to 10C is controlled to be increased or decreased, and the heat pump system 1 is operated with the ability to correspond to the heat load Q of the system load 2.
  • the capacity C which each unit 10A to 10C can output is sequentially calculated, and the capacity calculation value C is used as a threshold value to compare with the thermal load Q of the system load 2 to calculate the number of units 10A to 10C operating. Since the system control unit 27 for controlling is provided, even if any module 13A to 13D in each unit 10A to 10C enters the defrosting operation, calculation of the ability C that each unit 10A to 10C can output at that time. By controlling the number of units 10A to 10C operating by comparing the thermal load Q of the system load 2 with a threshold value and controlling the number of units 10A to 10C operating, modules 13A to 13D capable of exhibiting the heating capacity are present. If there are any other units 10A to 10C immediately without additional operation, It is possible to operate the heat pump system 1 in capacity, which may correspond to the stem load 2.
  • the modules 13A to 13D in the units 10A to 10C are defrosting, depending on the conditions, additional operation of the other units 10A to 10C is not required, and energy saving is achieved by operating the heat pump system 1 efficiently with the minimum number of units.
  • the on / off frequency of the units 10A to 10C can be suppressed, and the occurrence of failure or trouble due to frequent on / off repetition can be prevented, and the reliability of the heat pump system 1 can be improved.
  • the thermal load Q of the system load 2 is compared with the capacity C that the units 10A to 10C in operation can output and the number of units 10A to 10C is increased or decreased, the thermal load Q of the system load 2 is Since it is determined whether it exceeds a value obtained by multiplying the loadable capability C, which is the threshold value, by the step-up load factor or the step-down load factor, each unit 10A to 10C always has a predetermined value or more. It is possible to operate with the coefficient of performance (COP), and therefore, the heat pump system 1 can always be operated efficiently and stably with a high COP regardless of the change in the number of operation.
  • COP coefficient of performance
  • the calculation of the output capability C of the units 10A to 10C in operation can be performed by the module 13A to 13D. Since the calculation is performed by increasing and decreasing the minutes, even if the output capability C increases or decreases, the output can be included including the increase or decrease as the modules 13A to 13D start or end defrosting. The ability can be calculated appropriately at any time. Therefore, regardless of the presence or absence of defrost operation of each of the modules 13A to 13D, the unit operation number can be accurately set with respect to the thermal load Q of the system load 2 and operation can be performed. It can be avoided.
  • the calculation of the output capability C of each unit 10A to 10C can be performed by any of the control units 11A to 11C on each unit side or the system control unit 27, control on each unit side
  • control on each unit side Even when the units 11A to 11C do not have the capability arithmetic function, by adding the capability arithmetic function to the system control unit 27, even if a certain module 13A to 13D is defrosting, some modules may be spared depending on the conditions.
  • the heat pump system 1 can be efficiently operated with the minimum number of units corresponding to the heat load Q of the system load 2 without additionally operating the units 10A to 10 of the above. Thereby, the present invention can be easily applied to an existing heat pump system.
  • Example 1 In the first embodiment described above, when any of the plurality of modules 13A to 13D constituting each unit 10A to 10C enters the defrosting operation or the operation is ended, the modules 13A to 13D are The capacity C is increased or decreased by calculating the capacity C. However, in the heat pump, the water heat exchanger 16 which is the use side heat exchanger functions as an evaporator when the defrost operation is started during heating. In the modules 13A to 13D, heat is taken from the load side.
  • the output capable ability C is calculated in consideration of this point.
  • the modules 13A to 13D that have entered defrost operation not only loses the output capability C to zero, but also consumes heat, acting as a minus capability.
  • 100kW x (1/4)-100kW x (3/4) -50kW Since the units 10A to 10C have a negative capacity, the number of units to be added may be one or two.
  • Example 2 Furthermore, when any module 13A to 13D in the units 10A to 10C enters the defrosting operation, the other modules 13A to 13D are also frosted and are operated in a state where it is easy to enter the defrosting. You can look at it. In such a case, there is a possibility that the other modules 13A to 13D also follow and enter the defrost, and in order to avoid it, the margin ratio (for example, 0.9) is set when calculating the output capability C. By interrupting it and not applying a thermal load to the units 10A to 10C, it is possible to suppress frost and prevent the other modules 13A to 13D from following and entering the defrost operation. it can.
  • the margin ratio for example, 0.9
  • the output capability C is calculated by multiplying the preset margin ratio, and heat is generated to the units 10A to 10C.
  • the allowances rate was set to "for example, 0.9" in the above, it is needless to say that it is not limited to this and it may be changed suitably. Further, the margin rate may be changed according to the number of modules 13A to 13D in the heating operation.
  • Example 3 In the second embodiment, at the time of calculating the output capability C of the units 10A to 10C, the other modules 13A to 13D are made difficult to enter the defrost by multiplying the margin ratio, but after the defrost is completed Modules 13A-13D can generally be considered not to be frosted. Therefore, with regard to the modules 13A to 13D after the end of defrosting, the allowance ratio may be released during the calculation of the output capability C for the set time T from the end of the defrost operation.
  • Example 4 In addition, the longer the time during which each unit 10A to 10C or module 13A to 13D continues the heating operation, the more easily frost is generated, and the other module 13A to 13D becomes easier to follow in the defrosting operation. For this reason, according to the continuation time of heating operation, the said margin ratio can be reduced gradually and it can be made to be so long that time is long. That is, the concept of time is taken into setting the margin rate, and for example, the margin rate is decreased by 10% each time t minutes elapse.
  • the capacity C which can be output is calculated by multiplying the margin rate which is gradually reduced according to the operation duration time, and the frost is suppressed by not applying a thermal load to the units 10A to 10C, Defrosting of the other modules 13A to 13D can be suppressed. Therefore, the frequency at which each module 13A to 13D enters the defrost can be reduced or the timing of entering the defrosting operation can be delayed, and the efficiency at the time of heating operation can be improved.
  • Example 5 Furthermore, even if defrosting is performed, frost may remain unmelted and in such a case, it becomes easy to enter defrost again. Therefore, the number of times of defrosting of the modules 13A to 13D while the units 10A to 10C are in operation may be counted, and the margin rate may be gradually reduced and divided as the number of times of defrosting increases. That is, according to the number of times of defrosting, for example, the margin rate is decreased by 10% at a time of one defrosting and divided, and the output capability C is calculated.
  • the defrosting may be increased again by entering the defrosting again in a short time.
  • the defrosting times of the modules 13A to 13D during unit operation are counted.
  • the frost is suppressed so as not to apply a heat load to the units 10A to 10C, and the other modules 13A to It is possible to suppress the entry of the 13D defrost operation. Therefore, the frequency at which each module 13A to 13D enters the defrost can be reduced or the timing at which the defrost operation starts can be delayed, and the efficiency at the time of the heating operation can be improved.
  • the present invention is not limited to the invention according to the above-described embodiment, and appropriate modifications can be made without departing from the scope of the invention.
  • the amount of heat removed by each of the modules 13A to 13D at the time of defrosting is made equal to the capacity of each of the modules 13A to 13D, but a fixed value may be separately provided.
  • each heat pump is described as a module or one or a plurality of heat pumps connected as a unit for convenience, in the present invention, a plurality of heat pumps are connected to a load.
  • a heat pump system or a plurality of heat pumps can be used as a unit and can be applied to any of a plurality of heat pump systems connected.
  • modules or units may be read as heat pumps in each case, and Each heat pump may be either modularized or not as described above.
  • Heat pump system System load (external load) 10A, 10B, 10C unit (heat pump) 11A, 11B, 11C unit side control part 12 heat pump (heat pump chiller) 13A, 13B, 13C, 13D modules (heat pump) 27 System controller

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Mechanical Engineering (AREA)
  • Thermal Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Air Conditioning Control Device (AREA)

Abstract

 いずれかのヒートポンプがデフロスト中でもその運転台数を適切に制御できるとともに、常に負荷に対応した能力で運転ができるヒートポンプシステムおよびその運転方法を提供する。システム負荷に対して複数台のヒートポンプ(10Aないし10C(13Aないし13D))が接続されているヒートポンプシステム1であって、運転中のヒートポンプ(10Aないし10C(13Aないし13D))が出力可能な能力を逐次演算し、その能力演算値を閾値としてシステム負荷の熱負荷と比較し、ヒートポンプ(10Aないし10C(13Aないし13D))の運転台数を制御するシステム制御部(27)を備えている。

Description

ヒートポンプシステムおよびその運転方法
 本発明は、システム負荷に対して複数台のヒートポンプを接続しているヒートポンプシステムおよびその運転方法に関するものである。
 空冷ヒートポンプチラーは、外気温が低い条件下での暖房運転時に熱源側熱交換器に着霜(フロスト)し、それが進行すると、熱交換を阻害して効率が低下するため、霜を溶かす除霜(デフロスト)運転が必要となる。この場合、ヒートポンプチラーでは、利用側の水熱交換器が蒸発器として機能することにより熱を奪うため、負荷への供給温度が低下してしまうという課題が発生する。
 そこで、負荷に対して複数台のヒートポンプを接続したシステムにおいて、或るヒートポンプがフロストしてデフロスト運転に入ったとき、停止していたヒートポンプを強制的に運転し、あるいは非定常運転の予備のヒートポンプを運転することにより、能力の低下分をバックアップするようにしたものが特許文献1,2に開示されている。また、特許文献3には、複数台接続されたヒートポンプの中の2台以上が同時期にデフロスト運転に入るのを極力回避するようにした技術が開示されている。
 一方、近年のヒートポンプは、ユニット内モジュール化が進んでおり、例えば、個々の空冷ヒートポンプチラーをモジュール化し、そのモジュールを複数台直列に接続してユニットを構成し、更に外部負荷(システム負荷)に対して複数台のユニットを並列に接続した構成のヒートポンプシステムが実用化されている。
特開平6-74531号公報 特許第3221232号公報 特開2013-108732号公報
 しかしながら、負荷に対して複数台のヒートポンプを接続した構成のヒートポンプシステムでは、いずれかのヒートポンプがデフロスト中であっても、中に暖房能力を発揮できるヒートポンプが存在している場合、デフロスト運転に入ったヒートポンプに対応して直ちに予備や停止中のヒートポンプを追加運転する必要はなく、特許文献1,2に示すもののように、或るヒートポンプがデフロストに入ったとき、それに対応して予備機や停止機を追加運転するものでは、予備機や停止機を無駄に運転することになり兼ねず、省エネルギー化に反する等の課題を有していた。
 また、デフロスト運転中のヒートポンプは、利用側熱交換器が蒸発器として機能し、熱を奪うことになるため、単純にデフロスト運転に入ったヒートポンプ台数に対応して、予備機や停止機を追加運転するだけでは、システム負荷の熱負荷に対して能力不足に陥る場合がある等の課題があった。
 本発明は、このような事情に鑑みてなされたものであって、システム負荷に対して複数台のヒートポンプを接続したヒートポンプシステムにおいて、いずれかのヒートポンプがデフロスト中でもその運転台数を適切に制御できるとともに、常に負荷に対応した能力で運転ができるヒートポンプシステムおよびその運転方法を提供することを目的とする。
 上記した課題を解決するために、本発明のヒートポンプシステムおよびその運転方法は以下の手段を採用する。
 すなわち、本発明の第1の態様にかかるヒートポンプシステムは、システム負荷に対して複数台のヒートポンプが接続されているヒートポンプシステムであって、運転中の前記ヒートポンプが出力可能な能力を逐次演算し、その能力演算値を閾値として前記システム負荷の熱負荷と比較し、前記ヒートポンプの運転台数を制御するシステム制御部を備えている。
 本発明の上記第1の態様によれば、システム負荷に対して複数台のヒートポンプを接続しているヒートポンプシステムにあって、運転中のヒートポンプが出力可能な能力を逐次演算し、その能力演算値を閾値としてシステム負荷の熱負荷と比較し、ヒートポンプの運転台数を制御するシステム制御部を備えているため、運転中のヒートポンプのいずれかがデフロスト運転に入ったとしても、その時の運転中のヒートポンプが出力可能な能力の演算値を閾値とし、それとシステム負荷の熱負荷とを比較してヒートポンプの運転台数を制御することによって、運転中のヒートポンプに暖房能力を発揮できるヒートポンプが存在しておれば、直ちに他のヒートポンプを追加運転することなく、システム負荷の熱負荷に対応し得る能力でヒートポンプシステムを運転することができる。従って、いずれかのヒートポンプがデフロスト時でも、条件によっては他のヒートポンプの追加運転を不要とし、最少のヒートポンプ台数で効率よくヒートポンプシステムを運転することにより、省エネルギー化を図ることができる。また、ヒートポンプのオンオフ頻度を抑制し、頻繁なオンオフの繰り返しによる故障やトラブルの発生を防止して、システムの信頼性を向上することができる。
 さらに、本発明の上記第1の態様のヒートポンプシステムは、上記のヒートポンプシステムにおいて、前記各ヒートポンプの出力可能な能力の演算は、前記各ヒートポンプ側の制御部または前記システム制御部のいずれかにより演算可能とされていることとしてもよい。
 上記態様によれば、各ヒートポンプの出力可能な能力の演算が、各ヒートポンプ側の制御部またはシステム制御部のいずれかにより演算可能とされているため、各ヒートポンプ側の制御部が能力の演算機能を有していない場合でも、システム制御部に能力の演算機能を付加することにより、上記の如く、或るヒートポンプがデフロスト時でも、条件によっては予備のヒートポンプを追加運転することなく、最少のヒートポンプ台数で効率よくヒートポンプシステムを運転することができる。従って、既設のヒートポンプシステムに対しても簡易に本発明を適用することができる。
 さらに、本発明の上記第1の態様のヒートポンプシステムは、上述のいずれかのヒートポンプシステムにおいて、前記システム制御部は、前記各ヒートポンプのいずれかのヒートポンプがデフロスト運転を開始または終了したとき、そのヒートポンプの能力分を増減して前記各ヒートポンプが出力可能な能力を演算可能な構成とされていることとしてもよい。
 上記態様によれば、システム制御部が、各ヒートポンプのいずれかのヒートポンプがデフロスト運転を開始または終了したとき、そのヒートポンプの能力分を増減して各ヒートポンプが出力可能な能力を演算可能な構成とされているため、各ヒートポンプがデフロスト運転を開始したり、終了したりすることによって、出力可能な能力が増減しても、それを含めて出力可能な能力を随時的確に演算することができる。従って、各ヒートポンプがデフロスト運転の有無にかかわらず、システム負荷の熱負荷に対してヒートポンプ運転台数を正確に設定して運転することができ、能力不足に陥る事態等を確実に回避することができる。
 さらに、上記構成のヒートポンプシステムは、上記のヒートポンプシステムにおいて、前記システム制御部は、デフロスト中の前記ヒートポンプが奪う熱分をマイナス能力として前記各ヒートポンプが出力可能な能力を演算可能な構成とされていることとしてもよい。
 上記構成によれば、システム制御部が、デフロスト中のヒートポンプが奪う熱分をマイナス能力として各ヒートポンプが出力可能な能力を演算可能な構成とされているため、デフロスト中のヒートポンプの能力分を減ずるだけでなく、デフロスト中のヒートポンプの利用側熱交換器が蒸発器として機能し奪う熱分を、更にマイナス能力としてヒートポンプが出力可能な能力を演算することによって、より正確に出力可能な能力を演算することができる。従って、システム負荷の熱負荷に対してヒートポンプ運転台数を正確に設定して運転することができ、能力不足に陥る事態等を確実に回避することができる。
 さらに、本発明の上記第1の態様のヒートポンプシステムは、上述のいずれかのヒートポンプシステムにおいて、前記システム制御部は、前記各ヒートポンプのいずれかのヒートポンプがデフロスト運転を開始したとき、予め設定されている余裕率を割り掛けして運転中の前記ヒートポンプが出力可能な能力を演算可能な構成とされていることとしてもよい。
 上記態様によれば、システム制御部が、各ヒートポンプのいずれかのヒートポンプがデフロスト運転を開始したとき、予め設定されている余裕率を割り掛けて運転中のヒートポンプが出力可能な能力を演算可能な構成とされているため、或るヒートポンプがデフロスト運転に入ったことを以って他のヒートポンプもフロストしており、デフロストに入り易い状態で運転されていると見做すことにより、この場合、出力可能な能力を予め設定されている余裕率を割り掛けて演算し、そのヒートポンプに熱負荷をかけないようにすることによりフロストを抑制し、他のヒートポンプが追従してデフロスト運転に入らないようにすることができる。従って、各ヒートポンプがデフロスト運転に入る頻度を低減あるいはデフロスト運転に入るタイミングを遅延し、暖房運転時の効率を高めることができる。
 さらに、上記構成のヒートポンプシステムにおいて、前記システム制御部は、前記デフロスト運転終了後の前記ヒートポンプに対して、デフロスト運転終了時点から設定時間だけ、前記出力可能能力への前記余裕率の割り掛けを解除する構成とされていることとしてもよい。
 上記構成によれば、システム制御部が、デフロスト運転終了後のヒートポンプに対して、デフロスト運転終了時点から設定時間だけ、出力可能能力への余裕率の割り掛けを解除する構成とされているため、出力可能な能力の演算時、デフロスト終了直後のヒートポンプが存在した場合、そのヒートポンプはフロストしていないと見做せることから余裕率を割り掛ける必要がないと判断し、デフロスト終了時点から設定時間だけ余裕率の割り掛けを解除することによって、より実態に近い出力可能な能力を演算することができる。これによって、出力可能な能力をより正確に演算し、システム負荷の熱負荷に対してヒートポンプ運転台数を適切に設定して運転することができる。
 さらに、上記構成のヒートポンプシステムにおいて、前記システム制御部は、前記各ヒートポンプが暖房運転を継続している時間が長くなるほど、前記余裕率を漸次低減して割り掛ける構成とされていることとしてもよい。
 上記構成によれば、システム制御部が、各ヒートポンプが暖房運転を継続している時間が長くなるほど、余裕率を漸次低減して割り掛ける構成とされているため、暖房運転を継続している時間が長いヒートポンプほどフロストが発生し易く、他のヒートポンプに追従してデフロスト運転に入り易くなることから、この場合、運転継続時間に応じて漸次低減する余裕率を割り掛けて出力可能な能力を演算し、そのヒートポンプに熱負荷をかけないようにしてフロストを抑制することにより、他のヒートポンプのデフロスト運転入りを抑止することができる。従って、各ヒートポンプがデフロスト入りする頻度を低減あるいはデフロスト運転入りするタイミングを遅延し、暖房運転時の効率を向上することができる。
 さらに、上記構成のヒートポンプシステムは、上述のいずれかのヒートポンプシステムにおいて、前記システム制御部は、運転中の前記ヒートポンプのデフロスト回数をカウントし、その回数が多くなるほど、前記余裕率を漸次低減して割り掛ける構成とされていることとしてもよい。
 上記構成によれば、システム制御部が、運転中のヒートポンプのデフロスト回数をカウントし、その回数が多くなるほど、余裕率を漸次低減して割り掛ける構成とされているため、デフロストを実施しても一部の霜が溶け残しにより残存し、短時間のうちに再度デフロストに入ってデフロスト回数が多くなる場合があることから、この場合、運転中のヒートポンプのデフロスト回数をカウントし、その回数に応じて漸次低減する余裕率を割り掛けて出力可能な能力を演算することにより、当該ヒートポンプに熱負荷をかけないようにしてフロストを抑制し、そのヒートポンプのデフロスト運転入りを抑止することができる。従って、各ヒートポンプがデフロスト入りする頻度を低減あるいはデフロスト運転入りするタイミングを遅延し、暖房運転時の効率を向上することができる。
 さらに、本発明の第2の態様にかかるヒートポンプシステムの運転方法は、システム負荷に対して複数台のヒートポンプが接続されているヒートポンプシステムの運転方法であって、運転中の前記ヒートポンプが出力可能な能力を逐次演算する過程と、前記能力演算値を閾値として前記システム負荷の熱負荷と比較する過程と、前記システム負荷の熱負荷が前記能力演算値である前記閾値を超えているか否かにより前記ヒートポンプの運転台数を増減制御する過程と、を備える。
 本発明の第2の態様によれば、システム負荷に対して複数台のヒートポンプを接続しているヒートポンプシステムの運転方法にあって、運転中のヒートポンプが出力可能な能力を逐次演算する過程と、その能力演算値を閾値としてシステム負荷の熱負荷と比較する過程と、システム負荷の熱負荷が能力演算値である閾値を超えている否かによりヒートポンプの運転台数を増減制御する過程とを備えるため、運転中のヒートポンプのいずれかのヒートポンプがデフロスト運転に入ったとしても、その時の運転中のヒートポンプが出力可能な能力の演算値を閾値に、それとシステム負荷の熱負荷とを比較し、システム負荷の熱負荷が能力演算値である閾値以上か否かによりヒートポンプの運転台数を増減することによって、運転中のヒートポンプに暖房能力を発揮できるヒートポンプが存在しておれば、直ちに他のヒートポンプを追加運転することなく、システム負荷の熱負荷に対応し得る能力でヒートポンプシステムを運転することができる。従って、いずれかのヒートポンプがデフロスト時でも、条件によっては他のヒートポンプの追加運転を不要とし、最少のヒートポンプ台数で効率よくシステムを運転することにより、省エネルギー化を図ることができる。また、ヒートポンプのオンオフ頻度を抑制し、頻繁なオンオフの繰り返しによる故障やトラブルの発生を防止して、システムの信頼性を向上することができる。
 さらに、本発明の第2の態様のヒートポンプシステムの運転方法は、上記のヒートポンプシステムの運転方法において、前記ヒートポンプの運転台数の増減が、前記システム負荷の熱負荷が前記能力演算値である前記閾値に対して増段負荷率または減段負荷率を掛けた値を超えている否かにより決定されることとしてもよい。
 上記態様によれば、ヒートポンプの運転台数の増減が、システム負荷の熱負荷が能力演算値である閾値に対して、増段負荷率または減段負荷率を掛けた値以上か否かにより決定されるため、能力演算値である閾値と熱負荷とを比較してヒートポンプの運転台数を増減する際、閾値である能力演算値に増段負荷率または減段負荷率を掛けた値とシステム負荷の熱負荷とを比較し、ヒートポンプの運転台数を増減するかそのままの台数を維持するかを決定するようにしている。これにより、各ヒートポンプの成績係数(COP)が所定値以上となる負荷率範囲を予め設定しておき、ヒートポンプの能力と要求熱負荷との関係で規定される負荷率がその負荷率範囲の上限値(増段負荷率)を超えた場合、ヒートポンプの運転台数を増加し、負荷率が負荷率範囲の下限値(減段負荷率)を超えた場合、ヒートポンプの運転台数を減少してヒートポンプの運転台数を増減することで、各ヒートポンプを常に所定値以上のCOPで運転可能とすることができ、従って、運転台数の変更にかかわらず、常にヒートポンプシステムを高COPで効率よく安定的に運転することができる。
 本発明のヒートポンプシステムおよびその運転方法によると、運転中のヒートポンプのいずれかのヒートポンプがデフロスト運転に入ったとしても、その時の運転中のヒートポンプが出力可能な能力の演算値を閾値とし、それとシステム負荷の熱負荷とを比較してヒートポンプの運転台数を制御することにより、運転中のヒートポンプに暖房能力を発揮できるヒートポンプが存在しておれば、直ちに他のヒートポンプを追加運転することなく、システム負荷の熱負荷に対応し得る能力でヒートポンプシステムを運転することができるため、或るヒートポンプがデフロスト時でも、条件によっては他のヒートポンプの追加運転を不要とし、最少のヒートポンプ台数で効率よくヒートポンプシステムを運転することにより、省エネルギー化を図ることができる。また、ヒートポンプのオンオフ頻度を抑制し、頻繁なオンオフの繰り返しによる故障やトラブルの発生を防止して、システムの信頼性を向上することができる。
本発明の第1実施形態に係るヒートポンプシステムの概略構成図である。 上記ヒートポンプシステムの各ユニットの構成図である。 上記ヒートポンプシステムの各ユニットの運転台数を制御する際のフローチャート図である。 上記ヒートポンプシステムの各ユニットの運転台数を増減する際の制御閾値のイメージ図である。
 以下に、本発明にかかる実施形態について、図面を参照して説明する。
[第1実施形態]
 以下、本発明の第1実施形態について、図1ないし図4を用いて説明する。
 図1には、本発明の第1実施形態に係るヒートポンプシステムの概略構成図が示され、図2には、その各ユニットの構成図が示されている。
 ヒートポンプシステム1は、ファンコイルユニット等の空調機器、給湯機器、工場設備等の外部負荷(以下、システム負荷という。)2に対して、熱媒体(ここでは、温水または冷水)を循環する熱媒体配管3を備えている。この熱媒体配管3の供給側にはサプライヘッダ4、戻り側にはリターンヘッダ5が設けられている。
 リターンヘッダ5とサプライヘッダ4間には、バイパス弁6を備えたバイパス配管7が接続されており、サプライヘッダ4側からリターンヘッダ5側に対して熱媒体がバイパス可能とされている。また、リターンヘッダ5とサプライヘッダ4間には、それぞれ熱媒体配管8A,8B,8Cおよび熱媒体ポンプ9A,9B,9Cを介して複数台のヒートポンプ10A,10B,10Cが並列に接続されている。ここでは、3台のヒートポンプ10A,10B,10Cを並列に接続した例を示すが、台数は、システム負荷の大きさ等に応じて増減されることは云うまでもない。
 以下、本実施形態では、このヒートポンプ10A,10B,10Cをそれぞれ「ユニット」と称することとし、各ユニット10A,10B,10Cは、それぞれ単独のヒートポンプで構成されるもの、複数台のヒートポンプを直列に接続して構成されるもののいずれであってもよく、また、複数台のヒートポンプで構成されるユニットの場合、それぞれのヒートポンプを「モジュール」と称することとし、このモジュールと称するヒートポンプには、モジュール化したヒートポンプ、モジュール化していない通常ヒートポンプのいずれをも含むものとする。
 各ユニット10A,10B,10Cには、各々のユニット10A,10B,10Cを個別に制御するユニット側制御部11A,11B,11Cが設けられている。また、各ユニット10A,10B,10Cは、個々のヒートポンプ(ここでは、ヒートポンプチラー)12をモジュール13A,13B,13C,13Dとして複数台直列に接続して構成したものである。なお、この実施形態では、4台のモジュール13Aないし13Dを直列に接続することにより、1台のユニット10A,10B,10Cを構成したものを例示しているが、モジュールの接続台数は、これに限られるものではなく、適宜増減することができるものとする。
 以下に、各モジュール13A,13B,13C,13Dを構成する個々のヒートポンプチラー12の構成について説明する。
 ヒートポンプチラー12は、並列に接続される複数台の圧縮機14A,14Bと、冷媒の流れ方向を切換える四方切換弁15と、冷媒と水とを熱交換し、温水または冷水を製造する水熱交換器16と、膨張弁17と、外気と冷媒とを熱交換する空気熱交換器18とを順次冷媒配管を介して接続することにより構成された閉回路の冷凍サイクルを備えたものである。このヒートポンプチラー12自体は、公知のものでよく、各々のモジュール13Aないし13Dとも、同一構成のヒートポンプチラー12が使用されている。但し、必ずしも同一構成である必要はない。
 個々のヒートポンプチラー12は、それぞれ水熱交換器16の熱媒体入口配管および出口配管に設けられている温度センサ19,20の検出値に基づいて圧縮機14A,14Bの回転数等を制御するモジュール基板21、インバータ基板22A,22B等の制御系を備えたものであり、モジュール化された構成とされている。
 本実施形態において、上記した各ユニット10A,10B,10Cは、図2に示されるように、4台のモジュール13Aないし13Dを熱媒体配管8A,8B,8Cに対して直列に接続した構成とされており、そのモジュールの1つ13Aに、4台のモジュール13Aないし13Dの制御を統括するユニット統括基板23および操作部24を備えた各ユニット側の制御部11A,11B,11Cが設けられた構成とされている。このユニット側制御部11A,11B,11Cには、各ユニット10A,10B,10Cに対する熱媒体入口配管および出口配管に設けられた温度センサ25,26からの検出値が入力されるようになっている。
 また、上記ヒートポンプシステム1には、システム負荷2に対して並列に接続されている複数台のユニット10A,10B,10Cの運転台数を制御するシステム制御部27が設けられている。このシステム制御部27は、システム負荷2の熱負荷(流量×往還温度差×比重・比熱)Qと、運転しているユニット10A,10B,10Cが出力可能な能力Cとを随時演算し、その結果に基づいて両者を比較し、ユニット10A,10B,10Cの運転台数を増減制御するものである。
 以下に、システム制御部27によるユニット10A,10B,10Cの運転台数の増減制御を、図3および図4を参照して詳しく説明する。
 図3には、運転台数を増減する際の制御フローチャート図が示され、図4には、その制御閾値のイメージ図が示されている。
 制御が開始されると、ステップS1およびステップS11において、システム負荷2の熱負荷Qおよび運転中のユニット10A,10B,10Cが出力可能な能力Cの計算(演算)が随時実行される。システム負荷2の熱負荷Qは、ステップS2で負荷側への送水データである主管流量F、冷水往温度Ts、冷水還温度Tr等を各センサから取得し、またステップS3で予め設定されている比重Cp、比熱ρ等のデータを取り込み、ステップS4において、下記(1)式から演算することができる。
 Q=F(Tr-Ts)Cp・ρ  (1)
 一方、運転中のユニット10A,10B,10Cが出力可能な能力Cは、ステップS12で運転中のユニット10A,10B,10Cの各モジュール13Aないし13Dのデフロスト状態監視データを、暖房運転モジュール数M、デフロストモジュールMとして取得し、またステップS13で予め設定されている各モジュール(ヒートポンプ)の定格能力Crateを取り込むことにより、ステップS14において、下記(2)式から演算することができる。
 C=Σ{Crate(M/M+M)-Crate(M/M+M)}(2)
 なお、Crate(M/M+M)を、α×Mにより代替してもよい。
 ここで、暖房運転中の各ユニット10A,10B,10Cが出力可能な能力Cは、各ユニット10A,10B,10Cを構成している4台のモジュール13Aないし13Dのいずれかの空気熱交換器18がフロストした場合、その霜を溶かすためにデフロスト運転しなければならず、当該モジュールの暖房運転が中断されることから、その能力を差し引いて演算する必要がある。例えば、各ユニット10A,10B,10Cの能力を各々100kWとしたとき、上記した1ユニット4モジュールの場合、1モジュールがフロストしてデフロスト運転に入ると、各ユニットの出力可能な能力Cは、
 100kW×(3/4)=75kW
となる。
 こうして演算されたシステム負荷2の熱負荷Qと、暖房運転中のユニット10Aないし10Cが出力可能な能力CとをステップS5において比較し、ユニット10Aないし10Cの運転台数を増減するようにしている。つまり、本実施形態においては、運転中のユニット10Aないし10Cが出力可能な能力Cを逐次演算し、その演算値をユニットの運転台数を増減制御する際の閾値として用いる構成としている。上記ケースでは、図4に示すように、本来、熱負荷Qが出力可能な能力Cである100kWを上回った場合、ユニット10Aないし10Cの運転台数が増加されることになるが、1モジュールがデフロスト中であり、出力可能能力Cが75kWとなることから、この値を閾値としてユニット10Aないし10Cの運転台数が増加されることになる。
 このように、ステップS5においては、システム負荷2の熱負荷Qが出力可能な能力Cを上回っているが否かを判断し、YESであれば、ステップS6に移行してユニット10Aないし10Cの運転台数を1台増加指示する。本実施形態では、熱負荷Qと出力可能能力Cとを比較してユニット10Aないし10Cの運転台数を増減制御するに当たり、出力可能能力Cに対して増段負荷率および減段負荷率を掛けた値を用いるようにしている。
 この増段負荷率および減段負荷率は、各ユニット10Aないし10Cの成績係数(COP)が所定値以上となる負荷率範囲を予め設定しておき、ユニット10Aないし10Cの能力と要求熱負荷との関係で規定される負荷率がその負荷率範囲の上限値として定義される増段負荷率を超えた場合、ユニット10Aないし10Cの運転台数を増加し、負荷率が負荷率範囲の下限値として定義される減段負荷率を超えた場合、ユニット10Aないし10Cの運転台数を減少して、ユニット10Aないし10Cの運転台数を増減することによって、各ユニット10Aないし10Cを常に所定値以上のCOPで運転できるようにするものである。
 これによって、ステップS5においては、「Q>C×増段負荷率」が判断され、熱負荷Qが「C×増段負荷率」を超える場合、ステップS6で「Q<C×増段負荷率」となるユニット台数を計算して運転台数を増加指示することになる。また、ステップS5でNOと判断されると、ステップS7に移行し、ここで「Q>C×減段負荷率」が判断され、熱負荷Qが「C×減段負荷率」を超える場合、ステップS8に移行し、ユニット10Aないし10Cの運転台数減少を指示することになり、ステップS7でNOと判定されると、ステップS9に移行し、何もせず(運転台数を増減せず)にスタート位置に戻ることになる。
 なお、上記実施形態では、運転中のユニット10Aないし10Cが出力可能な能力Cをシステム制御部27で演算するようにした例について説明したが、各ユニット10Aないし10Cが出力可能な能力Cは、各ユニット10Aないし10C側の制御部11Aないし11Cで演算し、その演算結果をシステム制御部27に送って運転台数の増減を決定するようなシステムとしてもよい。この場合、図4におけるステップS11ないしステップS14に示す機能を各ユニット10Aないし10C側の制御部11Aないし11Cが担うことになる。
 斯くして、上記のヒートポンプシステム1によると、適宜台数のユニット10Aないし10Cを運転することにより冷水または温水を製造し、その冷水または温水をシステム負荷2に循環することによりその利用に供することができる。この際、システム制御部27またはユニット側制御部11Aないし11Cにおいて、システム負荷2の熱負荷Qおよび各ユニット10Aないし10Cが出力可能な能力Cを随時演算され、その熱負荷Qと出力可能な能力Cとが比較されることにより、ユニット10Aないし10Cの運転台数が増減制御され、システム負荷2の熱負荷Qに対応し得る能力にてヒートポンプシステム1が運転されることになる。
 つまり、本実施形態では、各ユニット10Aないし10Cが出力可能な能力Cを逐次演算し、その能力演算値Cを閾値としてシステム負荷2の熱負荷Qと比較し、ユニット10Aないし10Cの運転台数を制御するシステム制御部27を備えているため、各ユニット10Aないし10C内のいずれかのモジュール13Aないし13Dがデフロスト運転に入ったとしても、その時の各ユニット10Aないし10Cが出力可能な能力Cの演算値を閾値に、それとシステム負荷2の熱負荷Qとを比較してユニット10Aないし10Cの運転台数を制御することにより、当該ユニット10Aないし10C内に暖房能力を発揮できるモジュール13Aないし13Dが存在しておれば、直ちに他のユニット10Aないし10Cを追加運転することなく、システム負荷2に対応し得る能力でヒートポンプシステム1を運転することができる。
 従って、ユニット10Aないし10C内のモジュール13Aないし13Dがデフロスト時でも、条件によっては他のユニット10Aないし10Cの追加運転を不要とし、最少のユニット台数で効率よくヒートポンプシステム1を運転することにより省エネルギー化を図ることができる。また、ユニット10Aないし10Cのオンオフ頻度を抑制し、頻繁なオンオフの繰り返しによる故障やトラブルの発生を防止してヒートポンプシステム1の信頼性を向上することができる。
 また、システム負荷2の熱負荷Qと運転中のユニット10Aないし10Cが出力可能な能力Cとを比較して、ユニット10Aないし10Cの運転台数を増減制御する際、システム負荷2の熱負荷Qが閾値である出力可能な能力Cに対して増段負荷率または減段負荷率を掛けた値を超えている否かで決定するようにしているため、各ユニット10Aないし10Cを常に所定値以上の成績係数(COP)で運転可能とすることができ、従って、運転台数の変更にかかわらず、常にヒートポンプシステム1を高COPで効率よく安定的に運転することができる。
 また、運転中のユニット10Aないし10Cの出力可能な能力Cの演算を、各ユニット10Aないし10C内のいずれかのモジュール13Aないし13Dがデフロスト運転を開始または終了したとき、そのモジュール13Aないし13Dの能力分を増減して演算するようにしているため、各モジュール13Aないし13Dがデフロストを開始したり、終了したりすることにより、出力可能な能力Cが増減しても、それを含めて出力可能な能力を随時的確に演算することができる。従って、各モジュール13Aないし13Dがデフロスト運転の有無にかかわらず、システム負荷2の熱負荷Qに対してユニット運転台数を正確に設定して運転することができ、能力不足に陥る事態等を確実に回避することができる。
 さらに、本実施形態では、各ユニット10Aないし10Cの出力可能な能力Cの演算を各ユニット側の制御部11Aないし11Cまたはシステム制御部27のいずれかで演算可能としているため、各ユニット側の制御部11Aないし11Cが能力の演算機能を有していない場合であっても、システム制御部27に能力の演算機能を付加することにより、或るモジュール13Aないし13Dがデフロスト時でも、条件によっては予備のユニット10Aないし10を追加運転することなく、システム負荷2の熱負荷Qに対応させて最少のユニット台数で効率よくヒートポンプシステム1を運転することができる。これにより、既設のヒートポンプシステムに対しても簡易に本発明を適用することができる。
[他の実施形態]
 次に、本発明の他の実施形態について説明する。
 [実施例1]
 上記した第1実施形態では、各ユニット10Aないし10Cを構成している複数台のモジュール13Aないし13Dのいずれかがデフロスト運転に入ったり、その運転が終了したりした際、そのモジュール13Aないし13Dの能力分を増減して出力可能な能力Cを演算するようにしているが、ヒートポンプでは、暖房時にデフロスト運転に入ると、利用側熱交換器である水熱交換器16が蒸発器として機能するため、当該モジュール13Aないし13Dでは負荷側から熱を奪うことになる。
 本実施例では、この点を考慮して出力可能な能力Cを演算するようにしたものである。
 つまり、デフロスト運転に入ったモジュール13Aないし13Dは、出力可能な能力Cが零になるだけでなく、熱を奪う分がマイナス能力として作用するため、上記した1ユニットが4モジュールの場合、1モジュールがフロストしてデフロスト運転に入ると、各ユニットの出力可能な能力Cは、
 100kW×(3/4)-100kW×(1/4)=50kW
となる。また、3モジュールがフロストしてデフロスト運転に入ると、
 100kW×(1/4)-100kW×(3/4)=-50kW
となり、ユニット10Aないし10Cの能力が、マイナス能力となるため、追加されるユニットの運転台数は、1台もしくは2台になることも考えられる。
 このように、デフロスト中のモジュール13Aないし13Dの能力分を差し引くだけでなく、デフロスト中のモジュール13Aないし13Dの利用側熱交換器が蒸発器として機能し奪う熱分を、マイナス能力としてユニット10Aないし10Cの出力可能能力Cを演算することによって、より正確に出力可能能力Cを演算することができるため、システム負荷2の熱負荷Qに対してユニット運転台数を正確に設定して運転することができ、能力不足に陥る事態等を確実に回避することができる。
 [実施例2]
 さらに、ユニット10Aないし10C内のいずれかのモジュール13Aないし13Dがデフロスト運転に入ったことを以って、他のモジュール13Aないし13Dもフロストしており、デフロストに入り易い状態で運転されていると見做すことができる。このような場合、他のモジュール13Aないし13Dも追従してデフロストに入る虞があり、それを回避するため、出力可能な能力Cを演算する際、余裕率(例えば、0.9)を設定してそれを割り掛けし、ユニット10Aないし10Cに対して熱負荷をかけないようにすることにより、フロストを抑制し、他のモジュール13Aないし13Dが追従してデフロスト運転に入らないようにすることができる。
 この場合の各ユニット10Aないし10Cの出力可能な能力Cは、上記した1ユニット4モジュールの場合で、1モジュールがデフロストのとき、
 100kW×(3/4)×0.9=67.5kW
あるいは、
 100kW×(3/4)×0.9-100kW×(1/4)=42.5kW
として演算することができる。
 このように、デフロストに入り易い状態で運転していると見做すことができる場合、出力可能な能力Cを予め設定されている余裕率を割り掛けて演算し、そのユニット10Aないし10Cに熱負荷をかけないようにすることにより、フロストを抑制し、他のモジュール13Aないし13Dが追従してデフロスト運転に入らないようにすることができ、これによって、各モジュール13Aないし13Dがデフロストに入る頻度を低減あるいはデフロストに入るタイミングを遅延し、暖房運転時の効率を高めることができる。
 なお、余裕率は、上記では「例えば、0.9」としたが、これに限定されるものではないことは云うまでもなく、適宜変更してもよい。また、暖房運転しているモジュール13Aないし13Dの数に応じて、余裕率を変えるようにしてもよい。
 [実施例3]
 上記実施例2では、ユニット10Aないし10Cの出力可能な能力Cの演算時、余裕率を割り掛けすることにより、他のモジュール13Aないし13Dがデフロストに入り難くなるようにしているが、デフロスト終了後のモジュール13Aないし13Dは、通常フロストしていないと見做すことができる。このため、デフロスト終了後のモジュール13Aないし13Dについては、デフロスト運転終了時点から設定時間Tだけ、出力可能な能力Cの演算時において、上記余裕率の割り掛けを解除するようにしてもよい。
 つまり、上記実施例2の後者のケースで、1モジュールがデフロスト中で、1モジュールがデフロスト終了後T時間以内の場合、
 100kW×(2/4)×0.9+100kW×(1/4)-100kW×(1/4)=45kW
として出力可能な能力Cを演算することができる。
 このように、ユニット10Aないし10C内にデフロスト終了直後のモジュール13Aないし13Dが存在した場合、そのモジュール13Aないし13Dに対してデフロスト運転終了時点から設定時間だけ、出力可能な能力Cの演算時、余裕率の割り掛けを解除することにより、より実態に近い出力可能能力Cを演算することができる。従って、出力可能能力Cをより正確に演算し、システム負荷2の熱負荷Qに対してユニット10Aないし10Cの運転台数を適切に設定して運転することができる。
 [実施例4]
 また、各ユニット10Aないし10Cまたはモジュール13Aないし13Dが暖房運転を継続している時間が長くなるほど、フロストが発生し易く、他のモジュール13Aないし13Dに追従してデフロスト運転に入り易くなる。このため、暖房運転の継続時間に応じて、その時間が長くなるほど、上記余裕率を漸次低減して割り掛けるようにすることができる。つまり、余裕率の設定に時間的な概念を取り入れ、例えば、t分経過する度に余裕率を10%ずつ低下するようにする。
 この場合、1ユニット4モジュールで、1モジュールがデフロスト中のとき、ユニット10Aないし10Cとしてのデフロストがt分継続時、出力可能な能力Cは、
 100kW×(3/4)×(1-0.1×t)-100kW×(1/4)=50kW
として演算することができる。
 このように、運転継続時間に応じて漸次低減される余裕率を割り掛けて出力可能な能力Cを演算し、そのユニット10Aないし10Cに熱負荷をかけないようにしてフロストを抑制することにより、他のモジュール13Aないし13Dのデフロスト運転入りを抑止することができる。従って、各モジュール13Aないし13Dがデフロスト入りする頻度を低減あるいはデフロスト運転入りするタイミングを遅延し、暖房運転時の効率を向上することができる。
 [実施例5]
 さらに、デフロストを実施しても霜が溶け残しにより残存することがあり、このような場合、再度デフロスト入りし易くなる。そこで、ユニット10Aないし10Cが運転中のモジュール13Aないし13Dのデフロスト回数をカウントし、デフロスト回数が多くなるほど、余裕率を漸次低減して割り掛けするようにしてもよい。つまり、デフロスト回数に応じて、例えば1回のデフロストにより余裕率を10%ずつ低下させて割り掛け、出力可能な能力Cを演算するようにする。
 この場合、1ユニット4モジュールで、1モジュールがデフロストに入り、運転継続している3モジュールがそれぞれ2回デフロスト済みのとき、出力可能な能力Cは、
 100kW×(3/4)×(1-0.1×2)-100kW×(1/4)=35kW
として演算することができる。
 このように、デフロスト時の霜の溶け残しによって、短時間のうちに再度デフロスト入りしてデフロスト回数が多くなることがあるので、この場合、ユニット運転中のモジュール13Aないし13Dのデフロスト回数をカウントし、その回数に応じて漸次低減された余裕率を割り掛けて出力可能能力Cを演算することにより、当該ユニット10Aないし10Cに熱負荷をかけないようにしてフロストを抑制し、他のモジュール13Aないし13Dのデフロスト運転入りを抑止することができる。このため、各モジュール13Aないし13Dがデフロスト入りする頻度を低減あるいはデフロスト運転入りするタイミングを遅延し、暖房運転時の効率を向上することができる。
 なお、本発明は、上記実施形態にかかる発明に限定されるものではなく、その要旨を逸脱しない範囲において、適宜変形が可能である。例えば、上記実施形態では、各モジュール13Aないし13Dがデフロスト時に奪う熱量を各モジュール13Aないし13Dの能力と同等としたが、別途固定値を与えるようにしてもよい。
 更に、上記実施形態では、便宜上、個々のヒートポンプをモジュールまたはそれを1台または複数台接続したものをユニットと称して説明したが、本発明は、負荷に対して個別のヒートポンプを複数台接続したヒートポンプシステム、または複数台のヒートポンプをユニットとし、それを複数台接続したヒートポンプシステムのいずれにも適用することができるものであり、この場合、それぞれにおいてモジュールあるいはユニットをヒートポンプと読み替えればよく、また、各々のヒートポンプは、上述した通り、モジュール化されたもの、されていないもののいずれであってもよい。
1 ヒートポンプシステム
2 システム負荷(外部負荷)
10A,10B,10C ユニット(ヒートポンプ)
11A,11B,11C ユニット側制御部
12 ヒートポンプ(ヒートポンプチラー)
13A,13B,13C,13D モジュール(ヒートポンプ)
27 システム制御部

Claims (10)

  1.  システム負荷に対して複数台のヒートポンプが接続されているヒートポンプシステムであって、
     運転中の前記ヒートポンプが出力可能な能力を逐次演算し、その能力演算値を閾値として前記システム負荷の熱負荷と比較し、前記ヒートポンプの運転台数を制御するシステム制御部を備えているヒートポンプシステム。
  2.  前記各ヒートポンプの出力可能な能力の演算は、前記各ヒートポンプ側の制御部または前記システム制御部のいずれかにより演算可能とされている請求項1に記載のヒートポンプシステム。
  3.  前記システム制御部は、前記各ヒートポンプのいずれかのヒートポンプがデフロスト運転を開始または終了したとき、そのヒートポンプの能力分を増減して前記各ヒートポンプが出力可能な能力を演算可能な構成とされている請求項1または2に記載のヒートポンプシステム。
  4.  前記システム制御部は、デフロスト中の前記ヒートポンプが奪う熱分をマイナス能力として前記各ヒートポンプが出力可能な能力を演算可能な構成とされている請求項3に記載のヒートポンプシステム。
  5.  前記システム制御部は、前記各ヒートポンプのいずれかのヒートポンプがデフロスト運転を開始したとき、予め設定されている余裕率を割り掛けして運転中の前記ヒートポンプが出力可能な能力を演算可能な構成とされている請求項1ないし4のいずれかに記載のヒートポンプシステム。
  6.  前記システム制御部は、前記デフロスト運転終了後の前記ヒートポンプに対して、デフロスト運転終了時点から設定時間だけ、前記出力可能能力への前記余裕率の割り掛けを解除する構成とされている請求項5に記載のヒートポンプシステム。
  7.  前記システム制御部は、前記各ヒートポンプが暖房運転を継続している時間が長くなるほど、前記余裕率を漸次低減して割り掛ける構成とされている請求項5または6に記載のヒートポンプシステム。
  8.  前記システム制御部は、運転中の前記ヒートポンプのデフロスト回数をカウントし、その回数が多くなるほど、前記余裕率を漸次低減して割り掛ける構成とされている請求項5ないし7のいずれかに記載のヒートポンプシステム。
  9.  システム負荷に対して複数台のヒートポンプが接続されているヒートポンプシステムの運転方法であって、
     運転中の前記ヒートポンプが出力可能な能力を逐次演算する過程と、前記能力演算値を閾値として前記システム負荷の熱負荷と比較する過程と、前記システム負荷の熱負荷が前記能力演算値である前記閾値を超えているか否かにより前記ヒートポンプの運転台数を増減制御する過程と、を備えるヒートポンプシステムの運転方法。
  10.  前記ヒートポンプの運転台数の増減が、前記システム負荷の熱負荷が前記能力演算値である前記閾値に対して増段負荷率または減段負荷率を掛けた値を超えている否かにより決定される請求項9に記載のヒートポンプシステムの運転方法。
PCT/JP2014/082849 2014-02-25 2014-12-11 ヒートポンプシステムおよびその運転方法 Ceased WO2015129128A1 (ja)

Priority Applications (4)

Application Number Priority Date Filing Date Title
KR1020167015600A KR102030890B1 (ko) 2014-02-25 2014-12-11 히트 펌프 시스템 및 그 운전 방법
KR1020177030188A KR20170121310A (ko) 2014-02-25 2014-12-11 히트 펌프 시스템 및 그 운전 방법
CN201480070615.XA CN105849484B (zh) 2014-02-25 2014-12-11 热泵系统及其运行方法
US15/102,023 US10215470B2 (en) 2014-02-25 2014-12-11 Heat pump system and operation method therefor

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
JP2014034150A JP6381927B2 (ja) 2014-02-25 2014-02-25 ヒートポンプシステムおよびその運転方法
JP2014-034150 2014-02-25

Publications (1)

Publication Number Publication Date
WO2015129128A1 true WO2015129128A1 (ja) 2015-09-03

Family

ID=54008468

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/JP2014/082849 Ceased WO2015129128A1 (ja) 2014-02-25 2014-12-11 ヒートポンプシステムおよびその運転方法

Country Status (5)

Country Link
US (1) US10215470B2 (ja)
JP (1) JP6381927B2 (ja)
KR (2) KR102030890B1 (ja)
CN (1) CN105849484B (ja)
WO (1) WO2015129128A1 (ja)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11585578B2 (en) 2017-07-07 2023-02-21 Mitsubishi Electric Corporation Refrigeration cycle apparatus
WO2025154239A1 (ja) * 2024-01-18 2025-07-24 三菱電機株式会社 ヒートポンプシステム

Families Citing this family (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP6290724B2 (ja) * 2014-06-24 2018-03-07 ヤンマー株式会社 チラーシステム
KR101865637B1 (ko) * 2016-07-12 2018-06-11 대림산업 주식회사 구동 히트펌프에 대한 열부하 발휘성능 재평가를 이용한 지중열교환기의 히트펌프 구동 제어방법 및 히트펌프 구동 제어장치
CA3031935A1 (en) * 2016-07-25 2018-02-01 Robert W. Jacobi Modular system for heating and/or cooling requirements
US10352604B2 (en) * 2016-12-06 2019-07-16 Heatcraft Refrigeration Products Llc System for controlling a refrigeration system with a parallel compressor
CN110462300B (zh) * 2017-04-07 2021-09-28 开利公司 用于空气冷却的制冷机的模块化水侧经济器
JP7332274B2 (ja) * 2018-03-29 2023-08-23 三機工業株式会社 熱源システム
CN109268924B (zh) * 2018-08-23 2020-01-10 珠海格力电器股份有限公司 控制热泵机组开停数量的方法及热泵机组系统
DE102018127175A1 (de) * 2018-10-31 2020-04-30 Klaus Scherrieble System und Verfahren zur Regelung und Überwachung der Kälteerzeugung für eine Einheit
CN109916028B (zh) * 2019-03-20 2020-08-14 珠海格力电器股份有限公司 一种控制机组输出能力与负荷匹配的方法、装置及机组
US11326830B2 (en) 2019-03-22 2022-05-10 Robert W. Jacobi Multiple module modular systems for refrigeration
US12066221B2 (en) * 2019-06-07 2024-08-20 Carrier Corporation Modular waterside economizer integrated with air-cooled chillers
CN112082249B (zh) * 2020-08-25 2022-02-18 青岛海信移动通信技术股份有限公司 一种空调外机的防冻预警方法、系统及服务器
CN112303825A (zh) * 2020-09-30 2021-02-02 青岛海尔空调电子有限公司 热源塔的除霜控制方法
US12222144B2 (en) 2021-07-19 2025-02-11 Carrier Corporation Variable capacity defrost
CN114576882B (zh) * 2022-03-07 2023-07-21 广东芬尼克兹节能设备有限公司 热泵除霜控制方法、装置、计算机设备及存储介质
JPWO2024062529A1 (ja) 2022-09-20 2024-03-28
WO2024180660A1 (ja) * 2023-02-28 2024-09-06 三菱電機株式会社 給湯システム
CN120385115B (zh) * 2025-06-30 2025-09-12 中国建筑西南设计研究院有限公司 基于空气源热泵负载率优化的运行控制方法、电子设备
CN120506747B (zh) * 2025-07-21 2025-10-03 中国建筑西南设计研究院有限公司 一种空气源热泵阵列优化控制方法、装置及系统
CN121112534B (zh) * 2025-11-03 2026-02-17 青岛斑科变频技术有限公司 一种空气源变频热泵除霜间隔时间自适应监控系统及方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6217572A (ja) * 1985-07-15 1987-01-26 ダイキン工業株式会社 空冷ヒ−トポンプ式冷凍機の除霜装置
JPH01273947A (ja) * 1988-04-27 1989-11-01 Hitachi Ltd 空気調和機の運転方法
JPH03168554A (ja) * 1989-11-24 1991-07-22 Mitsubishi Electric Corp 空気調和装置
JP2004278884A (ja) * 2003-03-14 2004-10-07 Mitsubishi Jisho Sekkei Inc 制御装置
JP2009127936A (ja) * 2007-11-22 2009-06-11 Yamatake Corp 熱源機の台数制御装置および熱源機の台数制御方法
JP2011106699A (ja) * 2009-11-13 2011-06-02 Mitsubishi Heavy Ind Ltd 熱源システム
JP2013108732A (ja) * 2011-11-24 2013-06-06 Mitsubishi Heavy Ind Ltd ヒートポンプシステムの除霜運転方法及びヒートポンプシステム
JP2013228130A (ja) * 2012-04-25 2013-11-07 Mitsubishi Electric Corp 冷凍装置

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5934256B2 (ja) * 1979-08-06 1984-08-21 ダイキン工業株式会社 空気調和機
JPS594857A (ja) * 1982-06-30 1984-01-11 三菱電機株式会社 冷凍機の運転制御装置
JPH0674531A (ja) 1992-04-10 1994-03-15 Sanyo Electric Co Ltd 空気調和装置
JP3221232B2 (ja) 1994-06-07 2001-10-22 ダイキン工業株式会社 ヒートポンプ式冷凍装置
JP2003050066A (ja) * 2001-08-07 2003-02-21 Fujitsu General Ltd 空気調和機の制御装置
US6874693B2 (en) * 2002-12-20 2005-04-05 Honeywell International Inc. Method and apparatus for controlling a multi-source heating system
CN201429161Y (zh) * 2009-07-08 2010-03-24 郑州中南科莱空调设备有限公司 整体式水源热泵空调
JP5789748B2 (ja) * 2010-12-17 2015-10-07 パナソニックIpマネジメント株式会社 給湯システム
JP5787792B2 (ja) 2012-02-29 2015-09-30 三菱重工業株式会社 熱源システムの台数制御装置及びその方法並びに熱源システム
JP6249932B2 (ja) * 2014-12-04 2017-12-20 三菱電機株式会社 空調システム

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS6217572A (ja) * 1985-07-15 1987-01-26 ダイキン工業株式会社 空冷ヒ−トポンプ式冷凍機の除霜装置
JPH01273947A (ja) * 1988-04-27 1989-11-01 Hitachi Ltd 空気調和機の運転方法
JPH03168554A (ja) * 1989-11-24 1991-07-22 Mitsubishi Electric Corp 空気調和装置
JP2004278884A (ja) * 2003-03-14 2004-10-07 Mitsubishi Jisho Sekkei Inc 制御装置
JP2009127936A (ja) * 2007-11-22 2009-06-11 Yamatake Corp 熱源機の台数制御装置および熱源機の台数制御方法
JP2011106699A (ja) * 2009-11-13 2011-06-02 Mitsubishi Heavy Ind Ltd 熱源システム
JP2013108732A (ja) * 2011-11-24 2013-06-06 Mitsubishi Heavy Ind Ltd ヒートポンプシステムの除霜運転方法及びヒートポンプシステム
JP2013228130A (ja) * 2012-04-25 2013-11-07 Mitsubishi Electric Corp 冷凍装置

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11585578B2 (en) 2017-07-07 2023-02-21 Mitsubishi Electric Corporation Refrigeration cycle apparatus
WO2025154239A1 (ja) * 2024-01-18 2025-07-24 三菱電機株式会社 ヒートポンプシステム

Also Published As

Publication number Publication date
JP2015158337A (ja) 2015-09-03
KR20170121310A (ko) 2017-11-01
KR20160089399A (ko) 2016-07-27
KR102030890B1 (ko) 2019-10-10
CN105849484B (zh) 2018-09-21
US10215470B2 (en) 2019-02-26
CN105849484A (zh) 2016-08-10
US20160305702A1 (en) 2016-10-20
JP6381927B2 (ja) 2018-08-29

Similar Documents

Publication Publication Date Title
JP6381927B2 (ja) ヒートポンプシステムおよびその運転方法
EP3708920B1 (en) Control method and device for air conditioning system and air conditioning system
CN115638528B (zh) 风冷式冷水机组系统及其控制方法、控制器和存储介质
EP2716989B1 (en) Temperature adjusting system, air conditioning system, and control method
CN108518821B (zh) 空调的控制方法和装置
JP5537979B2 (ja) 空気調和機
EP3575712B1 (en) Cooling system
JP2013119954A (ja) ヒートポンプ式温水暖房機
JP5201183B2 (ja) 空調装置および冷凍機の運転方法
JP5227247B2 (ja) 熱源システム運転方法及び熱源システム
CN115046289B (zh) 多联机空调系统的控制方法、控制装置和多联机空调系统
JP3306612B2 (ja) 熱源機の運転台数制御方法
JP6257993B2 (ja) 冷凍システムおよび冷凍システムの台数制御方法
JP5140341B2 (ja) 熱源制御装置および熱源制御方法
CN120008259B (zh) 双复叠式热泵除霜控制方法、系统及双复叠式热泵系统
WO2025232298A1 (zh) 热泵系统控制
JPH09287797A (ja) 氷蓄熱システムの解氷運転制御方法
EP2885588B1 (en) A system and method for improving efficiency of a refrigerant based system
CN117355101A (zh) 一种供冷控制方法、装置及供冷系统
CN118722130A (zh) 一种电动汽车集成热管理系统及方法
JP2015183948A (ja) ソーラー装置
JP5786645B2 (ja) 冷凍空調装置
EP3764022B1 (en) Hot water supply device
CN112161379A (zh) 空调机组控制方法和装置
EP4733690A1 (en) Control system and method for a cooling system

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 14883781

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 15102023

Country of ref document: US

ENP Entry into the national phase

Ref document number: 20167015600

Country of ref document: KR

Kind code of ref document: A

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 14883781

Country of ref document: EP

Kind code of ref document: A1