煙突の外壁膜施工方法及び外壁膜構造 Download PDFInfo
- Publication number
- WO2014057545A1 WO2014057545A1 PCT/JP2012/076239 JP2012076239W WO2014057545A1 WO 2014057545 A1 WO2014057545 A1 WO 2014057545A1 JP 2012076239 W JP2012076239 W JP 2012076239W WO 2014057545 A1 WO2014057545 A1 WO 2014057545A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- chimney
- film
- membrane
- outer edge
- wall
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H12/00—Towers; Masts or poles; Chimney stacks; Water-towers; Methods of erecting such structures
- E04H12/28—Chimney stacks, e.g. free-standing, or similar ducts
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/002—Coverings or linings, e.g. for walls or ceilings made of webs, e.g. of fabrics, or wallpaper, used as coverings or linings
- E04F13/005—Stretched foil- or web-like elements attached with edge gripping devices
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04H—BUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
- E04H15/00—Tents or canopies, in general
- E04H15/32—Parts, components, construction details, accessories, interior equipment, specially adapted for tents, e.g. guy-line equipment, skirts, thresholds
- E04H15/64—Tent or canopy cover fastenings
- E04H15/642—Tent or canopy cover fastenings with covers held by elongated fixing members locking in longitudinal recesses of a frame
- E04H15/644—Tent or canopy cover fastenings with covers held by elongated fixing members locking in longitudinal recesses of a frame the fixing members being a beading
Definitions
- the present invention provides an outer wall film construction method in which a decorative outer wall covering the periphery of a chimney is replaced with a conventional concrete film so as not to damage the landscape, and an outer wall constructed by this method. It relates to the film structure.
- the outer wall covering the periphery of the chimney is generally composed of reinforced concrete, lightweight cellular concrete, prestressed concrete panel, or the like.
- the shape of the outer wall is limited to a uniform shape such as a square, a circle, or a polygon. Furthermore, since there is only a method for repairing the outer peripheral portion when the outer wall has deteriorated over time, it is difficult to change the design applied to the outer wall, and the repair period becomes longer.
- the problem to be solved by the present invention is that it is difficult to design the environment in consideration of the surroundings of the chimney with an outer wall made of reinforced concrete or the like, and the construction period is required for about one year. Also, the shape of the outer wall is limited to a uniform shape such as a square, a circle, or a polygon. Furthermore, since there is only a method for repairing the outer peripheral portion when the outer wall has deteriorated over time, it is difficult to change the design applied to the outer wall, and the repair period becomes longer.
- the present invention has been made for the purpose of enabling the outer wall covering the periphery of the chimney to be designed in consideration of the environment, to be constructed in a short period of time, and to have a geometric shape with improved design. Is.
- the design applied to the outer wall can be easily changed and can be repaired in a short period of time.
- the outer wall film construction method of the chimney of the present invention A method of constructing an outer wall film around a chimney, To cover the chimney, cover the outer periphery of the first steel material arranged around the chimney or the second steel material installed on the first steel material with the film material, and then the outer edge of the film material which becomes the outer edge of this film material And it is the most main feature that it fixes in appropriate positions other than the outer edge part of a film
- the outer periphery of the first steel material arranged around the chimney or the second steel material installed on the first steel material is covered with a film material, and the outer edge of the film material which becomes the outer edge of this film material and necessary Accordingly, the outer wall membrane structure of the chimney of the present invention fixed at an appropriate position other than the outer edge portion of the membrane material can be applied in a short period of time.
- the first steel material supporting the chimney or the outer peripheral side of the second steel material installed on the first steel material is covered and fixed with the membrane material, so that the geometry with improved design is improved. It can also be a typical shape.
- the design can be easily changed during repair when the outer wall has deteriorated over time, and the repair can be performed in a short period of time.
- the first steel material that supports the chimney can also be used as a film material support member. Cost can be greatly reduced. Moreover, since it can construct from the inner side of an outer wall membrane structure, an external scaffold becomes unnecessary and the construction period and construction cost can be further reduced. Furthermore, if the second steel material is installed on the first steel material in addition to the first steel material that supports the chimney, it is possible to construct in a shape having a recess, and an outer wall with improved design can be obtained.
- FIG. 1 is a view of the fixing completion state of the fourth example of the fixing means seen from the side
- (b) is a cross-sectional view taken along the line AA in (a)
- (c) is an enlarged view of part B in (b).
- the purpose of the present invention is to allow the outer wall covering the chimney to be designed in consideration of the environment, to be constructed in a short period of time, and to have a geometric shape with improved design. Realized by constructing a lighter film material from the inside.
- FIG. 1 shows a case where the outer wall membrane structure of the present invention is applied to a self-supporting chimney built on the ground
- FIG. 2 shows a case where the outer wall membrane structure of the present invention is applied to an integrated chimney connected to the upper end of a building.
- reference numeral 1 denotes a chimney, for example, two arranged at a predetermined interval.
- These two chimneys 1 are a first steel material 2 (three in FIG. 1 and four in FIG. 2) arranged around the chimney 1 and an appropriate number attached to the first steel material 2 at a predetermined height position. It is supported by the flooring 3 of.
- the floor material 3 is supported by a beam 4 for connecting and fixing the first steel material 2.
- the film material 5 is a film
- the film material 5 is provided so as to cover the outer peripheral side of the three first steel materials 2.
- the hexagonal floor material 3 attached to the beam 4 which connects and fixes these first steel materials 2 it installed so that it might become a circumscribed circle of three said 1st steel materials 2 and the said floor materials 3. It is provided so as to cover the outer periphery of the small aggregate 11.
- the film material 5 is provided so as to cover the outer peripheral side of the four first steel materials 2. Moreover, in the installation part of the square flooring 3 attached to the beam 4 which connects and fixes these 1st steel materials 2, the inner side part (FIG. 2 (b) of the 4 1st steel materials 2 and the said flooring 3 ) To (d) are provided so as to cover the outer periphery of the small aggregate 11 installed so that the portion excluding the left side of the paper surface) is a curved surface.
- the top flooring 3 is trapezoidal
- the intermediate and leg flooring 3 is rectangular
- the second steel material is outward from the center of the beams 4 on both sides of the beams 4. 6 is protruded
- a film material 5 is provided so as to cover the tip of the second steel material 6.
- the film material 5 covering the outer periphery of the chimney 1 is fixed by drawing the outer edge portion of the film material 5 inward at the positions of the three first steel materials 2 in the example shown in FIG. Yes. Therefore, in the case of the example shown in FIG. 1, three film members 5 are used in the circumferential direction.
- the outer edge portion of the film material 5 is pulled inwardly and fixed at the position of the second steel material 6 projecting outward from the center of the beams 4 on both sides. Therefore, in the case of the example shown in FIG. 2, two film members 5 are used in the circumferential direction.
- the fixing means of the outer edge portions of the film material 5 drawn inward at the position of the first steel material 2 or the second steel material 6 includes a drawing portion provided at a position where the outer edge portion of the film material 5 is drawn in the inner side, For example, a configuration as shown in FIGS. 3 to 5 is adopted.
- the fixing means 7 shown in FIG. 3 has a configuration in which a sandwiched lever 7a having a bent shape is relatively disposed so that the proximal end side is a fulcrum 7aa and the distal end side is freely swingable. And the locking tool 7b which latches the outer edge part of the film
- a contact / separation rocking and fixing mechanism 7c that attaches / detaches the tip end side of the sandwiching lever 7a to the proximal end side of the center bent portion 7ab of the sandwiching lever 7a is attached.
- this contact / separation rocking and fixing mechanism 7c is shown by tightening a nut 7cb fitted to the screw shaft 7ca passed between the both clamping levers 7a.
- the locking tool 7b includes, for example, a hole 7ba for inserting an outer edge portion of the film material 5 integrated with the edge rope 10 inserted into the end portion formed in a bag shape, and a longitudinal section direction of the hole 7ba.
- a slit 7bb that communicates with the outside so as to allow the membrane material 5 to pass therethrough is provided.
- the locking tool 7 b is fixed to the holding lever 7 a via the tension rod 12.
- a pull-in portion is formed by the clamping lever 7a and the contact / separation swinging and fixing mechanism 7c, and the locking tool 7b is a fixing tool.
- the fixing means 7 shown in FIG. 4 has a configuration in which a tube material 7d is disposed adjacently by providing a gap d1 into which the outer edge of the membrane material 5 can be inserted. Then, the outer edge portions of the film material 5 inserted through the gap d1 between the pipe materials 7d are integrally fixed by the fastening tool 7e.
- this fastening tool 7 e shows a device that integrally fixes the outer edge portions of the membrane material 5 by fastening a pair of membrane fixing plates 7 ea with fixing bolts 7 eb and nuts 7 ec.
- outer edge portion of the membrane material 5 may be fixed via the tension rod 12 using the locking tool 7b shown in FIG.
- reference numeral 10 in FIG. 4 denotes an edge rope which is inserted and integrated into the bag-like portion joined in a bag shape by folding the end portion of the film material 5 and bonded by heat welding or the like.
- the pipe material 7d is a drawing-in part
- the fastening tool 7e is a fixing tool
- the fixing means 7 shown in FIG. 5 is a film drawn along the outer periphery of a pair of pipe members 7f attached in a protruding manner with a predetermined distance d2 at the tip of the first steel material 2 or the second steel material 6.
- the outer edge portion of the material 5 is locked by a locking tool 7 h attached to the tip of a tension rod 7 g attached to the first steel material 2 or the second steel material 6 on the base end side.
- the fixing means 7 shown in FIG. 5 when the end portion of the film material 5 is pulled and fixed, in order to prevent water from entering the inner side, the first steel material 2 or the second steel material 6 is used.
- One end side of the water draining film 7i is attached to this, and the other end side may be joined to the film material 5 by heat welding or the like so as to cover the tip side of the first steel material 2 or the second steel material 6 with the water draining film 7i.
- the outer wall film structure of the present invention is first a film material so as to be in contact with the outer peripheral portion of the first steel material 2 so as to have a shape with the first steel material 2 supporting the chimney 1 as a vertex. Cover with 5. Further, in the example shown in FIG. 2, the first steel material 2 and the second steel material 6 that support the chimney 1 are in contact with the outer peripheries of the first and second steel materials 2 and 6 so as to have a top shape. Cover with film material 5. This operation can be performed from the inside without separately assembling an external scaffold or the like outside the first and second steel materials 2 and 6.
- the outer edges of the film material 5 are drawn from the outside to the inside of the shape at the positions of the three first steel materials 2, and the drawn-in portions are shown in FIGS.
- the fixing means 7 is used for fixing.
- the outer edge portions of the film material 5 are drawn inward from the outside of the shape at the positions of the two second steel materials 6, and the drawing portions shown in FIGS. Fixing is performed using any of the fixing means 7. This is the chimney outer wall film construction method of the present invention.
- the film material 5 which is lighter than concrete or the like is used, the foundation work can be reduced.
- the first steel material 2 that supports the chimney 1 can also be used as a support member for the film material 5, the construction period can be greatly shortened and the construction cost can be greatly reduced.
- the construction can be performed from the inside of the outer wall membrane structure, an external scaffold is not required, and the construction period can be further shortened and the construction cost can be further reduced.
- the design can be easily changed during the repair, and the repair can also be performed in a short period of time.
- the membrane material 5 used in the present invention is not particularly limited as long as it has the durability and heat resistance necessary for the outer wall of the chimney 1.
- a glass fiber coated with a fluororesin may be used. That's fine.
- outer wall film structure shown in FIGS. 1 and 2 using the fixing means 7 described in FIGS. 3 to 5 has a similar cross section from the proximal end side to the distal end side of the chimney.
- an outer wall membrane structure with improved design characteristics with different cross sections at the proximal end side and the distal end side of the chimney can also be used.
- the fixing means 7 shown in FIG. 7 is used in the case of an outer wall film structure having different cross sections on the proximal end side and the distal end side of the chimney as shown in FIG.
- the fixing means 7 shown in FIG. 7 includes a hole 7ja for inserting an edge portion 10 into a bag-like portion formed at the end of the membrane material 5 and inserting an outer edge portion integrated with the edge rope 10, and a longitudinal section of the hole 7ja.
- a U-shaped plate member 7k is attached with a bolt 7n and a nut 7o to a locking member 7j provided with a slit 7jb communicating with the outside so as to allow the membrane material 5 to pass through when the outer edge portion is inserted from the surface direction. is there.
- the wire 7m is, for example, a support member at the upper part of the chimney (first steel member 2, beam 4 or second steel member 6) to a support member at the lower part of the chimney (in the case of the self-supporting chimney shown in FIG. 1, the basic part of the chimney, shown in FIG. 2). In the case of an integrated chimney, it is stretched on a support member provided at the upper end of the building.
- the outer edge portion of the membrane material 5 can be fixed without using a steel material simply by stretching the wire 7m at a predetermined position. At that time, as shown in FIG. 7, the outer edge portions of the two film materials 5 (or the film material separately welded to the outer edge portions of the two film materials 5) are connected to one locking tool 7j via the angle material 7p. If it is fixed at the attached square member 7q, the fixed part can be blocked from the outside and water can be prevented from entering the inside. Further, according to the fixing means 7 shown in FIG. 7, it is possible to fix an appropriate position other than the outer edge portion of the film material 5.
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Tents Or Canopies (AREA)
Abstract
Description
煙突の周囲に外壁膜を施工する方法であって、
煙突を支持すべく、煙突の周囲に配置される第一鋼材、または前記第一鋼材に設置した第二鋼材の外周側を膜材で覆った後、この膜材の外縁となる膜材外縁部及び必要に応じて膜材の外縁部以外の適宜の位置で固定することを最も主要な特徴としている。
煙突を支持すべく、煙突の周囲に配置される第一鋼材、または前記第一鋼材に設置した第二鋼材の外周側を膜材で覆い、この膜材の外縁となる膜材外縁部及び必要に応じて膜材の外縁部以外の適宜の位置で固定した本発明の煙突の外壁膜構造を、短期間で施工することができる。
図1は地上に建てた自立型の煙突に本発明の外壁膜構造を適用した場合の図、図2は建物の上端に連結した一体型の煙突に本発明の外壁膜構造を適用した場合の図である。
この膜材5は、図1に示す例では、3本の前記第一鋼材2の外周側を覆うように設けている。また、これら第一鋼材2を連結固定する梁4に取り付けられた六角形の床材3の設置部では、3本の前記第一鋼材2と前記床材3の外接円となるように設置した小骨材11の外周を覆うように設けている。
2 第一鋼材
3 床材
5 膜材
6 第二鋼材
7 固定手段
7a 挟持レバー
7aa 支点
7b 係止具
7c 接離揺動及び固定機構
7d 管材
7e 締付け具
7f 管材
7g テンションロッド
7h,7j 係止具
7k 板部材
7m ワイヤー
Claims (7)
- 煙突の周囲に外壁膜を施工する方法であって、
煙突を支持すべく、煙突の周囲に配置される第一鋼材、または前記第一鋼材に設置した第二鋼材の外周側を膜材で覆った後、この膜材の外縁となる膜材外縁部及び必要に応じて膜材の外縁部以外の適宜の位置で固定することを特徴とする煙突の外壁膜施工方法。 - 煙突の周囲に設ける外壁膜構造であって、
煙突を支持すべく、煙突の周囲に配置される第一鋼材、または前記第一鋼材に設置した第二鋼材の外周側を膜材で覆い、この膜材の外縁となる膜材外縁部及び必要に応じて膜材の外縁部以外の適宜の位置で固定したことを特徴とする煙突の外壁膜構造。 - 前記膜材の外縁部の固定手段は、
前記外縁部を前記形状の外側から内側に引き込む位置に設けた引き込み部と、この引き込み部に引き込んだ前記外縁部を固定する固定具とを有するものであることを特徴とする請求の範囲第2項に記載の煙突の外壁膜構造。 - 前記固定具は、
基端部を支点として先端が接離揺動自在な対をなす挟持レバーと、これら挟持レバーに取り付けられた前記膜材の外縁部を係止する係止具と、前記挟持レバーの接離揺動及び固定機構を備えたものであることを特徴とする請求の範囲第3項に記載の煙突の外壁膜構造。 - 前記固定具は、
前記膜材を挿入可能な隙間を設けて隣接配置した管材と、これら管材間の前記隙間から挿入された複数の前記膜材の外縁部同士を一体的に固定する締付け具によって固定するものであることを特徴とする請求の範囲第3項に記載の煙突の外壁膜構造。 - 前記固定具は、
前記第一鋼材又は前記第二鋼材の先端部に所定の間隔を存して突出状に取り付けた一対の管材と、これら管材の外周に沿って引き込んだ前記膜材の外縁部を係止する前記係止具を備え、テンションロッドを介して前記係止具を前記膜材固定部材に固定するものであることを特徴とする請求の範囲第3項に記載の煙突の外壁膜構造。 - 前記膜材の固定手段は、
前記膜材の所要位置に形成した係止部を係止する係止具と、この係止具に取り付けた板部材とで構成され、前記板部材を煙突の外周部に張り設けたワイヤーに係合させることで前記係止具に係止した膜材を固定するものであることを特徴とする請求の範囲第2項に記載の煙突の外壁膜構造。
Priority Applications (6)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP12886498.0A EP2918752B1 (en) | 2012-10-10 | 2012-10-10 | Outer wall membrane construction method and outer wall membrane structure for chimney stacks |
MYPI2015701115A MY187911A (en) | 2012-10-10 | 2012-10-10 | Exterior wall membrane construction method and exterior wall membrane structure for stack |
SG11201502173TA SG11201502173TA (en) | 2012-10-10 | 2012-10-10 | Exterior wall membrane construction method and exteriorwall membrane structure for stack |
PCT/JP2012/076239 WO2014057545A1 (ja) | 2012-10-10 | 2012-10-10 | 煙突の外壁膜施工方法及び外壁膜構造 |
KR1020157010681A KR20150068408A (ko) | 2012-10-10 | 2012-10-10 | 굴뚝의 외벽막 시공방법 및 외벽막 구조 |
CN201280076025.9A CN104662240B (zh) | 2012-10-10 | 2012-10-10 | 烟囱的外壁膜施工方法及外壁膜的构造 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
PCT/JP2012/076239 WO2014057545A1 (ja) | 2012-10-10 | 2012-10-10 | 煙突の外壁膜施工方法及び外壁膜構造 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2014057545A1 true WO2014057545A1 (ja) | 2014-04-17 |
Family
ID=50477034
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/JP2012/076239 WO2014057545A1 (ja) | 2012-10-10 | 2012-10-10 | 煙突の外壁膜施工方法及び外壁膜構造 |
Country Status (5)
Country | Link |
---|---|
EP (1) | EP2918752B1 (ja) |
KR (1) | KR20150068408A (ja) |
CN (1) | CN104662240B (ja) |
SG (1) | SG11201502173TA (ja) |
WO (1) | WO2014057545A1 (ja) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4593510A (en) * | 1984-10-31 | 1986-06-10 | Newsome R Wayne | Pre-fabricated and modular chimney facade system |
JPH0490434A (ja) * | 1990-08-02 | 1992-03-24 | Mitsui Eng & Shipbuild Co Ltd | 焼却設備の換気方法 |
JPH0666051A (ja) | 1992-08-20 | 1994-03-08 | Tokyo Electric Power Co Inc:The | 煙 突 |
JPH084357A (ja) * | 1994-06-24 | 1996-01-09 | Taiyo Kogyo Kk | 膜体の張力導入構造 |
JP2002047831A (ja) * | 2000-08-04 | 2002-02-15 | Taiyo Kogyo Corp | 膜構造建築物の膜下地兼用構造材 |
JP2003106315A (ja) * | 2001-09-28 | 2003-04-09 | Taiyo Kogyo Corp | 膜材の中間部定着構造 |
JP2005256999A (ja) * | 2004-03-12 | 2005-09-22 | Takenaka Komuten Co Ltd | 膜構造物固定構造 |
Family Cites Families (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DD128358A1 (de) * | 1977-02-17 | 1977-11-16 | Hoetechnika Epitoe Es Szigetel | Ein in der durch decken in mehrere hoehenstufen geteilten lasttragenden konstruktion angeordnetes rauchrohr |
DE2845194A1 (de) * | 1978-10-17 | 1980-04-30 | Leonhardt Fritz | Sattelflaechenfoermiger mantel fuer rohrfoermige bauwerke sowie verfahren zu seiner herstellung |
US5033240A (en) * | 1990-06-01 | 1991-07-23 | Richard Louis J | Method and apparatus to enshroud large vertical structures |
WO1992012309A1 (fr) * | 1991-01-10 | 1992-07-23 | Scs Promotion Company Limited | Dispositif de fixation de feuille, dispositif de reglage du support de celui-ci et feuille a fixer par le dispositif de fixation |
CN1087155A (zh) * | 1993-11-19 | 1994-05-25 | 骆锡耀 | 整圆等扇形分隔式钢烟囱及其气顶倒装施工方法 |
JP3174677B2 (ja) * | 1993-11-30 | 2001-06-11 | 三菱重工業株式会社 | 塔状構造物の架設装置 |
DE4430876C1 (de) * | 1994-08-31 | 1995-07-13 | Philips Patentverwaltung | Kommunikationssystem |
US6021702A (en) * | 1998-02-09 | 2000-02-08 | Rexroad; John | Aesthetic barrier/debris system and material |
CN103883152B (zh) * | 2012-12-21 | 2016-05-25 | 河南省电力勘测设计院 | 一种新型索网膜结构内筒烟塔合一结构体系 |
-
2012
- 2012-10-10 SG SG11201502173TA patent/SG11201502173TA/en unknown
- 2012-10-10 EP EP12886498.0A patent/EP2918752B1/en active Active
- 2012-10-10 CN CN201280076025.9A patent/CN104662240B/zh active Active
- 2012-10-10 WO PCT/JP2012/076239 patent/WO2014057545A1/ja active Application Filing
- 2012-10-10 KR KR1020157010681A patent/KR20150068408A/ko not_active Application Discontinuation
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4593510A (en) * | 1984-10-31 | 1986-06-10 | Newsome R Wayne | Pre-fabricated and modular chimney facade system |
JPH0490434A (ja) * | 1990-08-02 | 1992-03-24 | Mitsui Eng & Shipbuild Co Ltd | 焼却設備の換気方法 |
JPH0666051A (ja) | 1992-08-20 | 1994-03-08 | Tokyo Electric Power Co Inc:The | 煙 突 |
JPH084357A (ja) * | 1994-06-24 | 1996-01-09 | Taiyo Kogyo Kk | 膜体の張力導入構造 |
JP2002047831A (ja) * | 2000-08-04 | 2002-02-15 | Taiyo Kogyo Corp | 膜構造建築物の膜下地兼用構造材 |
JP2003106315A (ja) * | 2001-09-28 | 2003-04-09 | Taiyo Kogyo Corp | 膜材の中間部定着構造 |
JP2005256999A (ja) * | 2004-03-12 | 2005-09-22 | Takenaka Komuten Co Ltd | 膜構造物固定構造 |
Non-Patent Citations (1)
Title |
---|
See also references of EP2918752A4 * |
Also Published As
Publication number | Publication date |
---|---|
KR20150068408A (ko) | 2015-06-19 |
EP2918752A4 (en) | 2016-08-24 |
CN104662240B (zh) | 2016-10-12 |
CN104662240A (zh) | 2015-05-27 |
EP2918752B1 (en) | 2019-07-17 |
EP2918752A1 (en) | 2015-09-16 |
SG11201502173TA (en) | 2015-05-28 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102562490A (zh) | 风力涡轮机塔架组件及其组装方法 | |
JP5292441B2 (ja) | 足場/養生ユニットおよびその連結装置 | |
JP5841369B2 (ja) | 貯水槽の補強構造 | |
KR100736254B1 (ko) | 장력식 상판 구조를 갖는 무용접 저수구조물 | |
EP3568593B1 (en) | Hatches of nacelle and helicopter hoisting platform | |
KR101406873B1 (ko) | 경량 골조를 이용한 터널형 방음벽 | |
US20120293881A1 (en) | Segment of a solar collector and solar collector | |
ES2794799T3 (es) | Torre de una instalación de energía eólica | |
JP5702213B2 (ja) | 煙突の外壁膜施工方法及び外壁膜構造 | |
WO2014057545A1 (ja) | 煙突の外壁膜施工方法及び外壁膜構造 | |
JP2005350904A (ja) | 仮締切構造体および仮締切工法 | |
JP6099993B2 (ja) | 塔状体の外壁膜施工方法 | |
JP5701490B2 (ja) | 屋根改修工法及び構造物 | |
EP3580408B1 (en) | A resuable modular building and a method for erecting the same | |
JP2012207379A (ja) | 構造物解体システム | |
ES2693022T3 (es) | Elemento de encofrado de panel de marco | |
JP5972122B2 (ja) | 煙突のユニット構造物及び煙突の施工方法 | |
JP2012209892A (ja) | 支持柱及びその設置方法 | |
JP2008115560A (ja) | 仮設屋根構造 | |
JP5612832B2 (ja) | ユニット建物 | |
JP3158432U (ja) | テント用支柱部材およびテント | |
KR102323154B1 (ko) | 시공성이 우수한 조립식 돔형구조물 및 그 시공방법 | |
US20240128918A1 (en) | Apparatus, system, and method for wind-resilient solar panel racking | |
JP2014224393A (ja) | 塔状物構造、ユニット構造体及び塔状物の施工方法 | |
KR20150070569A (ko) | 공기 주입형 공사용 덮개 구조물 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 12886498 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2012886498 Country of ref document: EP |
|
ENP | Entry into the national phase |
Ref document number: 20157010681 Country of ref document: KR Kind code of ref document: A |
|
WWE | Wipo information: entry into national phase |
Ref document number: IDP00201502784 Country of ref document: ID |
|
NENP | Non-entry into the national phase |
Ref country code: JP |