WO2012063409A1 - 運転計画方法、運転計画装置、ヒートポンプ式給湯システムの運転方法、及びヒートポンプ式給湯暖房システムの運転方法 - Google Patents
運転計画方法、運転計画装置、ヒートポンプ式給湯システムの運転方法、及びヒートポンプ式給湯暖房システムの運転方法 Download PDFInfo
- Publication number
- WO2012063409A1 WO2012063409A1 PCT/JP2011/005824 JP2011005824W WO2012063409A1 WO 2012063409 A1 WO2012063409 A1 WO 2012063409A1 JP 2011005824 W JP2011005824 W JP 2011005824W WO 2012063409 A1 WO2012063409 A1 WO 2012063409A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- power
- heat
- hot water
- amount
- water supply
- Prior art date
Links
- 238000000034 method Methods 0.000 title claims abstract description 60
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 title claims description 425
- 238000010438 heat treatment Methods 0.000 title claims description 131
- 238000010248 power generation Methods 0.000 claims description 110
- 238000005338 heat storage Methods 0.000 claims description 70
- 230000005855 radiation Effects 0.000 claims description 39
- 239000011232 storage material Substances 0.000 claims description 20
- 238000003860 storage Methods 0.000 claims description 17
- 230000017525 heat dissipation Effects 0.000 claims description 4
- 230000004044 response Effects 0.000 claims description 4
- 238000009826 distribution Methods 0.000 description 21
- 230000008569 process Effects 0.000 description 20
- 238000010586 diagram Methods 0.000 description 14
- 230000020169 heat generation Effects 0.000 description 13
- 239000003507 refrigerant Substances 0.000 description 13
- 238000004590 computer program Methods 0.000 description 12
- 238000012545 processing Methods 0.000 description 9
- 230000006870 function Effects 0.000 description 7
- 238000009825 accumulation Methods 0.000 description 6
- 238000004364 calculation method Methods 0.000 description 6
- 230000001172 regenerating effect Effects 0.000 description 5
- 238000005259 measurement Methods 0.000 description 4
- 238000006243 chemical reaction Methods 0.000 description 3
- 230000005611 electricity Effects 0.000 description 3
- 238000012986 modification Methods 0.000 description 3
- 230000004048 modification Effects 0.000 description 3
- 238000004891 communication Methods 0.000 description 2
- 239000000470 constituent Substances 0.000 description 2
- 230000003203 everyday effect Effects 0.000 description 2
- 239000007788 liquid Substances 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 238000005406 washing Methods 0.000 description 2
- 238000012935 Averaging Methods 0.000 description 1
- 238000013528 artificial neural network Methods 0.000 description 1
- 230000005540 biological transmission Effects 0.000 description 1
- 238000009835 boiling Methods 0.000 description 1
- 230000008859 change Effects 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 230000007613 environmental effect Effects 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 239000004065 semiconductor Substances 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
- 230000006641 stabilisation Effects 0.000 description 1
- 238000011105 stabilization Methods 0.000 description 1
- 230000001360 synchronised effect Effects 0.000 description 1
Images
Classifications
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D19/00—Details
- F24D19/10—Arrangement or mounting of control or safety devices
- F24D19/1006—Arrangement or mounting of control or safety devices for water heating systems
- F24D19/1009—Arrangement or mounting of control or safety devices for water heating systems for central heating
- F24D19/1045—Arrangement or mounting of control or safety devices for water heating systems for central heating the system uses a heat pump and solar energy
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D18/00—Small-scale combined heat and power [CHP] generation systems specially adapted for domestic heating, space heating or domestic hot-water supply
-
- G—PHYSICS
- G05—CONTROLLING; REGULATING
- G05D—SYSTEMS FOR CONTROLLING OR REGULATING NON-ELECTRIC VARIABLES
- G05D23/00—Control of temperature
- G05D23/19—Control of temperature characterised by the use of electric means
- G05D23/1919—Control of temperature characterised by the use of electric means characterised by the type of controller
- G05D23/1924—Control of temperature characterised by the use of electric means characterised by the type of controller using thermal energy, the availability of which is aleatory
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/06—Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/06—Energy or water supply
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/003—Load forecast, e.g. methods or systems for forecasting future load demand
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/004—Generation forecast, e.g. methods or systems for forecasting future energy generation
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J3/00—Circuit arrangements for ac mains or ac distribution networks
- H02J3/12—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load
- H02J3/14—Circuit arrangements for ac mains or ac distribution networks for adjusting voltage in ac networks by changing a characteristic of the network load by switching loads on to, or off from, network, e.g. progressively balanced loading
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D2101/00—Electric generators of small-scale CHP systems
- F24D2101/40—Photovoltaic [PV] modules
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D2103/00—Thermal aspects of small-scale CHP systems
- F24D2103/10—Small-scale CHP systems characterised by their heat recovery units
- F24D2103/13—Small-scale CHP systems characterised by their heat recovery units characterised by their heat exchangers
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D2103/00—Thermal aspects of small-scale CHP systems
- F24D2103/10—Small-scale CHP systems characterised by their heat recovery units
- F24D2103/17—Storage tanks
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D2200/00—Heat sources or energy sources
- F24D2200/02—Photovoltaic energy
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D2200/00—Heat sources or energy sources
- F24D2200/08—Electric heater
-
- F—MECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
- F24—HEATING; RANGES; VENTILATING
- F24D—DOMESTIC- OR SPACE-HEATING SYSTEMS, e.g. CENTRAL HEATING SYSTEMS; DOMESTIC HOT-WATER SUPPLY SYSTEMS; ELEMENTS OR COMPONENTS THEREFOR
- F24D2200/00—Heat sources or energy sources
- F24D2200/12—Heat pump
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02J—CIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
- H02J2310/00—The network for supplying or distributing electric power characterised by its spatial reach or by the load
- H02J2310/10—The network having a local or delimited stationary reach
- H02J2310/12—The local stationary network supplying a household or a building
- H02J2310/14—The load or loads being home appliances
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B30/00—Energy efficient heating, ventilation or air conditioning [HVAC]
- Y02B30/70—Efficient control or regulation technologies, e.g. for control of refrigerant flow, motor or heating
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02B—CLIMATE CHANGE MITIGATION TECHNOLOGIES RELATED TO BUILDINGS, e.g. HOUSING, HOUSE APPLIANCES OR RELATED END-USER APPLICATIONS
- Y02B70/00—Technologies for an efficient end-user side electric power management and consumption
- Y02B70/30—Systems integrating technologies related to power network operation and communication or information technologies for improving the carbon footprint of the management of residential or tertiary loads, i.e. smart grids as climate change mitigation technology in the buildings sector, including also the last stages of power distribution and the control, monitoring or operating management systems at local level
- Y02B70/3225—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/222—Demand response systems, e.g. load shedding, peak shaving
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S20/00—Management or operation of end-user stationary applications or the last stages of power distribution; Controlling, monitoring or operating thereof
- Y04S20/20—End-user application control systems
- Y04S20/242—Home appliances
- Y04S20/244—Home appliances the home appliances being or involving heating ventilating and air conditioning [HVAC] units
Definitions
- the present invention relates to a system including an apparatus related to power generation such as a solar power generation apparatus and a device that consumes electric power such as a heat pump.
- Power generation devices such as solar power generation and wind power generation are devices aimed at creating energy.
- Photovoltaic power generation is natural energy power generation that converts sunlight energy into electric power and supplies it to a home.
- the generated power constantly fluctuates due to changes in weather and meteorological conditions.
- a heat pump water heater absorbs the heat of the atmosphere, compresses and heats the refrigerant with electricity, and makes hot water from water using a heat exchanger, making it an energy-saving hot water supply system compared to conventional heater-type electric water heaters It is.
- Patent Document 1 discloses a heat pump hot water supply / heating system including a conventional power generation device.
- weather forecast information is acquired from the server by the weather information acquisition means, and when the acquisition information is set, the power for boiling hot water with the CO 2 heat pump water heater is not midnight power of commercial power, Switching control is performed so as to use the power of solar power generation. Since the electric water heater is operated with natural energy, the use of electric power is more efficient and energy saving, and the electricity bill is also cheaper.
- the consumption of the reverse power determined by the constantly changing power of the photovoltaic power generation device and the power load of the consumer is not taken into consideration.
- the voltage of the grid rises and the grid becomes unstable.
- a consumer located on the lower side of the system cannot reverse power when the system voltage is high, and the power generated by the solar power generation device is wasted.
- the reversed power is converted to high voltage by the distribution environment, a large conversion loss occurs in the conversion process, and a transmission loss in the process of transmitting to another customer also occurs. For this reason, it is good also from an environmental viewpoint to consume the generated electric power privately.
- Patent Document 2 an apparatus shown in Patent Document 2 has also been proposed.
- the heat pump unit is operated when the amount of power generation exceeds the amount of power used.
- the heat pump unit is not operated corresponding to the amount of electric power exceeding this, and it is not possible to effectively reduce the reverse tide to the system.
- an object of the present invention is to provide an operation planning method for a system including a power generator that has low reverse power and does not impair energy saving.
- An operation planning method generates heat using a power generation device, a first power load that operates using power generated by the power generation device, and power generated by the power generation device.
- the operation plan for the second power load is drawn up. Specifically, in each time zone divided into unit times, a prediction step of predicting the amount of power generated by the power generation device and the amount of power consumed by the first power load; The operation of the second power load is performed so that the second power load is operated in an operation time period including a time period in which the reverse power amount obtained by subtracting the power consumption amount from the generated power amount is maximum. And an operation planning step for formulating a plan.
- the power generation device may be a solar power generation device.
- the second power load includes a raw heat unit that generates heat using electric power generated by the power generation device, a heat storage unit that stores heat generated by the raw heat unit, and a heat storage unit. You may provide the thermal radiation part which thermally radiates the heat currently stored.
- the predicting step further predicts a heat release amount during reverse tide stop that is dissipated by the heat radiating unit during a reverse tide stop time period in which the power consumption exceeds the generated power amount.
- an operation plan of the raw heat unit in the operation time zone may be drafted so that the amount of heat corresponding to the amount of heat released during reverse tide stop predicted by the prediction unit is stored in the heat storage unit.
- the operation planning step one or more of the time zones in the descending order of the reverse power amount until the amount of heat corresponding to the amount of heat released during reverse power flow stop exceeds the time required for the raw heat unit to generate.
- the operation time zone may be determined by selecting and the operation plan in the determined operation time zone may be drafted.
- a minimum value of the backflow power amount in each of the selected one or more time zones is determined as a backflow power threshold value, and actually measured in the operation time zone.
- the operation plan may be drafted so that the operation of the raw heat unit is started at the timing when the reverse flow power becomes equal to or higher than the reverse flow power threshold.
- the operation plan is drawn up so that the operation of the raw heat unit is stopped at the timing when the amount of heat corresponding to the amount of heat released during the reverse tide stop is generated in the operation time period. Also good.
- the heat storage unit may include a heat storage material whose temperature changes according to the amount of heat stored.
- the raw heat unit includes a heat pump that can raise the temperature of the heat storage material to a first temperature, and a heater that can raise the temperature of the heat storage material to a temperature higher than the first temperature. You may prepare.
- the heat pump generates a heat amount until the heat storage material reaches the first temperature, out of a heat amount corresponding to the heat release amount during the reverse tide stop, and the heat storage material is the first heat storage material.
- the operation plan may be drafted so that the heater generates the amount of heat after reaching this temperature.
- a reverse tide stop time which is a time when the reverse flow power amount changes from a positive value to a value of 0 or less
- a predetermined time at which heat dissipation from the heat radiating unit is considered to stop The amount of heat dissipated by the heat dissipating unit in the reverse tide stop time period, which is a time period between the two, may be predicted as the heat release amount during the reverse tide stop.
- the power consumption amount of each time zone is predicted to correspond to an average value of a plurality of past power consumption amounts measured on the same day and the same time zone, and the reverse of each time zone is calculated. It may be predicted that the heat release amount during tidal stop corresponds to the average value of a plurality of past heat flows during reverse tidal stop measured on the same day of the week and in the same time zone.
- a predicted solar radiation amount of each time zone on the prediction day is acquired, and the generated power amount of each time zone is calculated from the previously measured generated power amount, where the solar radiation amount is the predicted solar radiation amount of the current day. It may be predicted that it corresponds to the amount of generated power in the time zone closest to.
- An operation planning device generates heat using a power generation device, a first power load that operates using the power generated by the power generation device, and the power generated by the power generation device.
- an apparatus for planning an operation plan for the second power load In a system including a second power load, an apparatus for planning an operation plan for the second power load. Specifically, in each time zone divided into unit times, a prediction unit that predicts the amount of power generated by the power generation device and the amount of power consumed by the first power load, and The operation of the second power load is performed so that the second power load is operated in an operation time period including a time period in which the reverse power amount obtained by subtracting the power consumption amount from the generated power amount is maximum. And an operation planning section for formulating a plan.
- the operation method of the heat pump hot water supply system is an operation method of a heat pump hot water supply system including a solar power generation device, a heat pump hot water supply device, and an operation planning device.
- the operation planning device is obtained by predicting a power generation amount generated by the power generation device and a power consumption amount consumed by a power load, and subtracting the power consumption amount from the power generation amount.
- a step of calculating a reverse power amount a step of predicting a heat amount required during a reverse power stop time period in which the reverse power amount is zero (a heat release amount during reverse power stop), and the reverse power amount being the largest
- an operation planning step of planning a plan for operating the heat pump hot water supply apparatus so as to store the predicted amount of heat in an operation time zone including the time zone.
- the minimum value among the target heat storage temperature for storing the predicted heat amount and the reverse power amount in each of the selected one or more time zones is determined as the reverse power threshold value. May be.
- the actually measured reverse power is equal to or greater than the reverse power threshold in the operation time zone.
- the operation of the heat pump hot water supply apparatus may be started at the timing, and the operation of the heat pump hot water supply apparatus may be stopped at the timing when the predicted amount of heat is generated in the operation time period.
- the prediction of the power generation amount, the prediction of the power consumption amount, and the prediction of the heat amount may be performed using history information stored in the storage unit.
- the said operation plan apparatus may be installed in the inside of a heat pump type hot water supply apparatus.
- the operation method of the heat pump hot water supply and heating apparatus is an operation method of a heat pump hot water supply and heating system including a solar power generation device and a heat pump hot water supply and heating apparatus.
- the heat pump hot water supply and heating device includes a hot water supply tank and a heating device.
- the system includes an operation planning device. The operation planning device predicts the amount of power generated by the power generation device and the amount of power consumed by the power load, and subtracts the power consumption from the amount of generated power.
- the minimum value among the target heat storage temperature for storing the predicted heat amount and the reverse power amount in each of the selected one or more time zones is determined as the reverse power threshold value. May be.
- the actually measured reverse power is equal to or greater than the reverse power threshold in the operation time zone.
- the operation of the heat pump hot water supply apparatus may be started at the timing, and the operation of the heat pump hot water supply apparatus may be stopped at the timing when the predicted amount of heat is generated in the operation time period.
- the operation planning step determines a target heat storage temperature for storing the predicted amount of heat in the hot water tank, and heats the heat storage material in the hot water tank to a first temperature by a heat pump of the heat pump hot water heater. Thereafter, the heat storage material may be controlled to be heated to a second temperature higher than the first temperature by a heater installed in the hot water supply tank.
- the heat pump hot water supply and heating device includes a hot water supply and heating control device, and the hot water supply and heating control device receives operation information of the heat pump hot water supply and heating device from the operation planning device, and the heat pump hot water supply and heating device from a remote controller.
- the operation information from the operation planning device is acquired, the operation information from the operation planning device is given priority over the operation information from the remote control. You may control the said heat pump type hot-water supply heater.
- the operation information may be an operation mode of the heat pump hot water supply / room heating device and a set hot water supply temperature of a hot water supply tank.
- the heat pump type hot water supply and heating device may include a heat exchanger, and the heat storage material supplied from the heat exchanger may be controlled to be supplied to the hot water supply tank or the heating device by the switching device.
- the present invention predicts a time zone in which the reverse power flow reaches a peak and operates the system in the predicted time zone, damage to the system can be reduced.
- FIG. 1 is a flowchart showing the points of the present invention.
- FIG. 2 is a configuration diagram of a heat pump hot water supply system including the power generation device according to the first embodiment.
- FIG. 3 is a block diagram of the operation planning apparatus.
- FIG. 4 is a diagram illustrating the predicted load power amount, the predicted PV power generation amount, and the predicted reverse power amount at each time.
- FIG. 5 is a diagram showing the priority order of each time period assigned in descending order of the predicted reverse power flow amount.
- FIG. 6 is a flowchart of the operation plan process.
- FIG. 7 is a flowchart of the load prediction process.
- FIG. 8 is a flowchart of the control parameter calculation process of the operation plan means.
- FIG. 9 is a configuration diagram of a heat pump hot water supply and heating system including the power generation device according to the second embodiment.
- FIG. 10 is a configuration diagram of a heat pump hot water supply / room heating device.
- FIG. 11 is a configuration diagram of a heat pump hot water supply and heating system including the power generation device according to the second embodiment.
- FIG. 12 is a diagram showing remote controller setting items and setting information.
- FIG. 13 is a diagram illustrating an example of power consumption when control is different.
- FIG. 14 is a diagram showing the format of information stored in the storage means.
- FIG. 15 is a configuration diagram of a heat pump hot water supply and heating system including a power generation device according to a modification of the second embodiment.
- FIG. 16 is a flowchart showing an example of the operation of the heat pump hot water supply / room heating system of the second embodiment.
- the backflow power is estimated from the prediction of the load power amount that is the power consumption amount in the home (S101) and the prediction of the PV power generation amount that is the power generation amount by PV (Photovoltaic) (S102).
- the amount is predicted (S103), and the HP (Heat Pump) is operated (S105) in the time zone when the reverse power flow is at a peak.
- the operation period of HP is determined by prediction of hot water supply heat quantity (S104).
- FIG. 2 is a diagram showing a heat pump hot water supply system according to Embodiment 1 of the present invention.
- the energy supplier (electric power supply source) 208 shown in FIG. 2 supplies electric power to the house through the electric power system.
- the power system is a power system to which power is stably supplied.
- the power meter 207 measures the amount of power that is supplied through the power system and consumed in the house. In addition, the power meter 207 can consume the power generated by the solar power generator 211 at home and sell the surplus power to the system.
- an electric power load (first electric power load) 206, a heat pump hot water supply device (second electric power load) 200, an operation planning device 210, a solar power generation device 211, and an electric power distribution A device 205 is installed.
- the heat pump hot water supply apparatus 200 includes at least a heat pump 201, a hot water supply tank 202, and a hot water supply apparatus 203.
- the power load 206 is a device that operates by receiving power supply such as an air conditioner, a washing machine, and a refrigerator.
- the solar power generation device 211 is a device that converts solar energy into electric power, converts solar energy into electric power, and outputs the converted electric power (PV power generation).
- the power distribution device 205 is a device that acquires power from the solar power generation device 211 and the commercial power source supplied by the energy supplier 208 and distributes the power to the heat pump hot water supply device 200 and the power load 206 according to demand. is there. In addition, the amount of power to be distributed can be measured.
- the power distribution device 205 acquires the PV power generation from the solar power generation device 211.
- the power distribution device 205 measures load power that is power consumed by the power load 206 and hot water supply power that is power consumed by the heat pump hot water supply device 200. And when the sum of load electric power and hot-water supply electric power exceeds PV generation
- the power distribution device 205 includes a converter and an inverter, and when outputting the acquired power as described above, performs conversion between voltage and AC / DC according to the type of power to output the acquired power. Further, the power distribution device 205 outputs the load power actually consumed by the power load 206 and the PV generated power actually generated by the solar power generation device 211 to the operation planning device 210.
- the server 209 is a device that transmits the current amount of solar radiation at the consumer's home and the amount of solar radiation predicted in the future via the Internet. In the present embodiment, the server 209 transmits the amount of solar radiation measured in the customer's area via the Internet every predetermined time.
- the server 209 calculates a predicted value of the solar radiation amount for every hour from 0:00 to the next 24 hours using the history of the past solar radiation amount in the customer's area and the weather forecast for the next day, Send once over the internet at 0:00.
- the energy supplier 208 supplies purchased power in accordance with the demand of the power distribution device 205 installed in the consumer, and when reverse power is input from the power distribution device 205, the power is supplied to the other demand via the power system. Output to home.
- the power load 206 is a power load of a consumer, and refers to a device that operates using power supplied from the power distribution device 205 such as a television, an air conditioner, a refrigerator, a washing machine, and lighting. And the sum total of the electric power used by these apparatuses is defined as load electric power.
- the heat pump (raw heat unit) 201 is a heat pump of an air heat source, and generates hot hot water by exchanging heat between a refrigerant (for example, CO 2 ) and water via a condenser (not shown). To do.
- the hot water supply tank (heat storage unit) 202 stores hot water generated by the heat pump 201, and is used as a buffer that covers heat necessary for keeping the room temperature constant when the outside air temperature rapidly decreases.
- the hot water supply device (heat radiating unit) 203 supplies hot water supplied from the hot water supply tank 202.
- the heat pump 201, the hot water supply tank 202, and the hot water supply device 203 are collectively referred to as a heat pump hot water supply device 200.
- the operation planning device 210 makes an operation plan for the heat pump hot water supply device 200 so as to reduce the amount of reverse power flow and controls its operation.
- the configuration of the operation planning device 210 will be described in detail with reference to FIG.
- the operation planning apparatus 210 includes an accumulation unit 301, a load prediction unit 302, an operation planning unit 303, and an operation control unit 304.
- the storage unit 301 includes an hourly load electric energy consumed by the electric power load 206, an hourly hot water supply heat consumed by the heat pump hot water supply apparatus 200, and an hourly electric power generated by the solar power generation apparatus 211. And the amount of solar radiation generated every hour, which is the value of the current amount of solar radiation.
- This storage means 301 may be any means capable of recording data such as DRAM (Dynamic random access memory), SDRAM (Synchronous dynamic random access memory), flash memory, or ferroelectric memory. It doesn't matter.
- the load predicting means 302 includes a predicted load power amount per hour predicted to be consumed by the power load 206, a predicted hot water supply heat amount per hour predicted to be consumed by the heat pump hot water supply device 200, and the sun An hourly predicted PV power generation amount that is predicted to be generated by the photovoltaic power generation apparatus 211 is calculated.
- the operation planning means 303 draws up an operation plan for the heat pump hot water supply apparatus 200 so as to minimize the amount of reverse power flow, and calculates control parameters for controlling the operation of the heat pump hot water supply apparatus 200. Finally, the operation control means 304 controls the operation of the heat pump hot water supply apparatus 200 based on the control parameter.
- the accumulation means 301 accumulates each value of the consumer's load power amount, hot water supply heat amount, PV power generation amount, and solar radiation amount. More specifically, as shown in the history table of FIG. 14, the storage unit 301 measures the load power hourly measurement value (load power amount), the hot water supply heat amount hourly measurement value, and PV The measurement value (PV power generation amount) of hourly power generation and the hourly measurement value of solar radiation amount are set as a load power history, hot water supply heat amount history, PV power generation history, and solar radiation amount history for a predetermined period, respectively. (In the example of FIG. 14, only 4 weeks) is held.
- This history table holds the history information (load power, hot water supply heat, PV power generation, solar radiation) for each day of the week for four weeks, but more specifically, history information for each time of each day of the week. is doing.
- the times 0, 1, 2,... Indicate the hours of 0 o'clock, 1 o'clock, 2 o'clock,.
- the history information at that time is integrated information.
- the load power history at time 0 is the accumulated power amount of load power in the midnight range.
- the load prediction unit 302 can acquire desired information from the storage unit 301, for example, the load power amount at 15 to 16:00 one week ago, the hot water supply heat amount at 18 to 22:00 two weeks ago, and the like. It has become. The same applies to the PV power generation amount and solar radiation amount.
- the operation planning device 210 acquires the load power amount and the PV power generation amount from the power distribution device 205, acquires the hot water supply heat amount from the heat pump hot water supply device 200, and acquires the solar radiation amount from the server 209 outside the home via the Internet.
- the amount of solar radiation is the amount of solar radiation in the district where the house is installed.
- the amount of hot water supply refers to the amount of heat consumed per hour by the heat pump hot water supply apparatus 200 (heat radiation).
- the load electric energy refers to the electric energy per hour consumed by the electric power load 206.
- the PV power generation amount refers to the amount of power generated per hour by the solar power generation device.
- the amount of solar radiation refers to the amount of solar radiation per unit area of the amount of solar radiation from the server 209 to the current consumer.
- the operation planning device 210 accumulates each piece of information acquired for one day of the previous day, for example, at 0:00 every day in units of one hour, and accumulates values for the past four weeks (28 days) in the accumulation unit 301. .
- the load predicting means 302 has a predicted value of the hourly load power consumed by the power load 206 (predicted load power amount) and a predicted value of the hourly hot water supply heat consumed by the heat pump hot water supply apparatus 200 ( (Predicted hot water supply heat amount) and a predicted value (predicted PV power generation amount) of the PV power generation amount per hour generated by the solar power generation apparatus 211 are calculated.
- the load prediction unit 302 corresponds to the average value of a plurality of measured values in the same time zone on the same day of the past four weeks, which is stored in the storage unit 301, for the predicted load power amount and the predicted hot water supply heat amount for each time zone. I predict that. For example, when predicting the load power amount and hot water supply heat amount from 19:00 to 20:00 on Tuesday, the measured values from 19:00 to 20:00 on Tuesday of the past four weeks are acquired from the storage means 301, and the acquired measured values are added. The average is the predicted value.
- the load prediction unit 302 acquires the predicted solar radiation amount of each time zone on the prediction day from the server 209 via the Internet, and the predicted PV power generation amount of each time zone is the solar radiation amount of the PV power generation amount measured in the past. It is predicted that it corresponds to the PV power generation amount in the time zone closest to the predicted solar radiation amount on that day. That is, the load prediction unit 302 searches the solar radiation amount history of the storage unit 301 for the same value or the closest value to the solar radiation amount in the predicted time period. Next, the PV power generation amount measured in the found time zone is acquired from the PV power generation history. And let the acquired PV generated electric energy be the predicted PV generated electric energy of the time slot
- the load prediction unit 302 executes the above-described prediction process once a day at 0:00, and calculates a predicted value every hour for 24 hours from the current time.
- the operation planning means 303 makes an operation plan for the heat pump hot water supply apparatus 200 so that the amount of reverse power flow is minimized, and calculates control parameters for the heat pump hot water supply apparatus 200.
- the operation planning unit 303 acquires the predicted load power amount, the predicted hot water supply heat amount, and the predicted PV power generation amount from the load prediction unit 302. Furthermore, the set hot water supply temperature (current set temperature) set in the heat pump hot water supply apparatus 200 is acquired from the heat pump hot water supply apparatus 200.
- the operation planning means 303 executes an operation plan planning process once a day, for example, at 0:00.
- the operation planning means 303 calculates the “predicted load power amount” for each time slot from the “predicted PV power generation amount” for each time slot (0 o'clock, 1 o'clock,. Subtraction is performed to calculate a “predicted reverse power amount” for each hour.
- the lower limit of the predicted reverse power flow is zero.
- the predicted PV power generation amount becomes zero (0) and no reverse tide occurs. Therefore, the time when the predicted reverse power flow amount for each time zone first became zero from the next 24 o'clock, in other words, the time when the predicted reverse power flow amount changed from a positive value to a value less than or equal to 0 is expressed as “reverse. It is defined as “tide stop time”.
- the horizontal axis in FIG. 4 is time, and the vertical axis indicates the amount of power.
- ⁇ is the predicted load power amount
- ⁇ is the predicted PV power generation amount
- ⁇ solid black in the figure, the same applies hereinafter
- the predicted reverse power amount ( ⁇ ) is obtained by subtracting the predicted load power amount from the predicted PV generated power amount.
- Each electric energy at each time indicates an integrated value at that time. For example, if it is 12:00, the power of 12:00 (from 12:00 to 13:00) is integrated.
- the reverse tide stop time is 17:00 when the predicted reverse tide power amount becomes zero.
- the amount of heat (heat loss during reverse tide stop) obtained by integrating each predicted hot water supply amount from 17:00 to 24:00 (reverse tide stop time zone), which is the reverse tide stop time, If the hot water supply tank 202 is used to store heat, heating of the hot water supply tank 202 becomes unnecessary after the reverse tide stop time, and it is not necessary to consume extra power.
- the predicted hot water supply heat amount can be calculated, for example, by acquiring the hot water supply heat amount from 17:00 to 24:00 on the same day of the past four weeks from the hot water supply heat amount history and averaging the acquired past hot water supply heat amounts.
- the temperature calculated by dividing the accumulated predicted hot water supply amount from 17:00 to 24:00 by the tank capacity of the hot water supply tank 202 (for example, 200 liters) is set as the target heat storage temperature. That is, the target heat storage temperature is a target temperature for performing heat generation by the heat pump 201 so that the hot water supply tank 202 becomes this temperature. In other words, when the hot water supply tank 202 reaches this temperature, the heat generated by the heat pump 201 is stopped.
- An upper limit value may be set for the heat storage temperature of the hot water supply tank 202. If the target heat storage temperature exceeds the upper limit value, the target heat storage temperature is replaced with the set temperature.
- the upper limit value of the heat storage temperature of the hot water supply tank 202 is 80 ° C.
- the amount of heat to be stored in the hot water supply tank 202 during reverse tide can be calculated from the target heat storage temperature and the temperature currently set in the heat pump hot water supply apparatus 200 (set hot water supply temperature).
- the following formula (1) is used to calculate the amount of raw heat during reverse tide, which is the amount of heat that is regenerated by the heat pump 201 and stored in the hot water supply tank 202 during reverse tide. This amount of raw heat during reverse tide corresponds to the amount of heat released during reverse tide stop radiated by the hot water supply device 203 during the reverse tide stop time zone (17:00 to 24:00).
- the operation plan means 303 calculates a reverse-tide biothermal time, which is a time necessary for regenerating the reverse-tide raw heat quantity with the heat pump 201, using the following equation (2).
- HP average capacity which is an average biothermal capacity of the heat pump 201, which is a value stored in advance, is 9 kW.
- heat amount (kcal) to electric power (kW) is 0.86.
- Reverse-tidal biothermal time (Reverse-tidal bioheat / 0.86 / 1000) / HP average capacity formula (2)
- the operation planning means 303 calculates the predicted reverse power flow amount in each time zone.
- FIG. 5 is obtained by replacing the graph of FIG. 4 with a table format.
- the predicted reverse power flow amount in each time zone indicates the integrated value in that time zone. For example, if it is 0 o'clock, as described above, it is the integrated value of the predicted reverse power at 0 o'clock from 0:00 to 1:00. Further, the priorities in FIG. 5 are given in descending order of the predicted reverse power flow amount.
- the operation planning means 303 determines an operation time zone that is a time zone in which the heat pump 201 is operated, and a reverse power threshold value for determining the timing at which the heat pump 201 actually starts regenerating heat.
- the operation time zone includes a time zone in which the predicted reverse power amount is maximum.
- the operation planning means 303 selects one or more time zones as the operation time zone in descending order of the predicted reverse tidal power amount (that is, in descending order of priority) until the reverse tidal live heat time is exceeded. To do.
- the reverse flow power threshold value matches the minimum value of the reverse flow power amount in the above operation time zone.
- the 12 o'clock range which is the time zone with the highest priority in FIG. 5, is the operating time zone.
- the heat storage start reverse power at this time is 1.68 kW.
- the reverse tidal biothermal time is 3.2 hours
- the time zone for 4 hours is secured by raising this 3.2.
- the operating time zone is a time zone from 10:00 to 13:00, which is a time zone with a priority of 1 to 4.
- the heat storage start reverse power at this time is 1.00 kW.
- the operation plan unit 303 outputs the target heat storage temperature, the operation time zone, and the reverse power threshold value determined above to the operation control unit 304 as control parameters.
- the operation control unit 304 controls the operation of the heat pump type hot water supply apparatus 200 based on the control parameter generated by the operation plan unit 303.
- the operation control unit 304 acquires the reverse power threshold, the operation time zone, and the target heat storage temperature of the hot water tank 202 from the operation plan unit 303, and the current load power amount and the current PV power generation amount from the power distribution device 205.
- the current temperature of the hot water supply tank 202 (hot water supply tank temperature) is acquired from the heat pump hot water supply apparatus 200.
- the operation control means 304 calculates the reverse power that is a value obtained by subtracting the load power from the PV generated power. These processes are executed every minute, for example.
- the heat pump 201 does not start operation when the calculated current reverse power does not reach the reverse power threshold. Then, the heat pump 201 starts operation at the timing when the calculated current reverse power is equal to or greater than the value of the reverse power threshold. Moreover, since the operation control means 304 acquires the temperature of the hot water supply tank 202 every minute, the operation of the heat pump 201 is ended at the timing when the hot water supply tank 202 reaches the target heat storage temperature.
- the heat pump 201 by operating the heat pump 201 during a time zone in which the reverse power amount reaches a peak according to the operation plan formulated by the operation planning device 210, the reverse power during that time zone can be reduced (peak cut). .
- the influence on the power system can be effectively reduced.
- Embodiment 1 (Description of operation of Embodiment 1)
- movement in this Embodiment of a heat pump type hot-water supply system is demonstrated.
- the current time is 0 o'clock and the heat pump hot water supply / heating system has been operating for four weeks (28 days) or more.
- the set hot water supply temperature is “45 ° C.”.
- the temperature in the hot water supply tank 202 is made uniform at 50 ° C. at 0:00.
- FIG. 6 is a flowchart of an operation plan process that is processed by the operation plan apparatus 210 at 0:00 every day.
- the operation planning device 210 starts “operation plan processing” once a day when the current time reaches 0:00 (S601).
- the operation planning device 210 updates the storage unit 301 (S602). Accumulated values for each hour of the load power amount, hot water supply heat amount, PV power generation amount, and solar radiation amount for the past 24 hours are newly added to the storage unit 301.
- the accumulation means 301 accumulates the load power history, the hot water supply heat history, the PV power generation history, and the solar radiation history for the past 28 days. Therefore, the history data is updated by discarding the data of the oldest one day of each history and adding the latest information for the past 24 hours to each history.
- FIG. 7 is a flowchart of the prediction process (S603) processed by the load prediction unit 302.
- the load prediction unit 302 starts a prediction process (S701).
- the load prediction unit 302 acquires data necessary for load prediction (S702).
- the load prediction unit 302 acquires necessary information from the server 209 based on the predicted solar radiation amount from the load power history, hot water supply heat history, PV power generation history, and solar radiation history for the past 28 days stored in the storage unit 301. .
- the load prediction unit 302 calculates a predicted load power amount for every hour (S703). As described above, the load prediction unit 302 acquires four load power amounts on the same day of the week as the prediction date and the same time zone from the load power history, and uses the average value of these as a predicted value for 24 hours of load power. Calculate the amount.
- the load predicting means 302 calculates a predicted hot water supply heat amount (S704). As described above, the load prediction unit 302 obtains four hot water supply heat amounts on the same day of the week as the predicted date and the same time from the hot water supply heat history, and uses the average value thereof as a predicted value to calculate the predicted hot water supply amount for 24 hours. calculate.
- the load prediction unit 302 calculates the predicted PV power generation amount (S705). As described above, the load prediction unit 302 searches the solar radiation history for a value that is the same as or closest to the predicted solar radiation for each hour. Then, the PV power generation amount corresponding to the found time zone is acquired from the PV power generation history, and the predicted PV power generation amount for 24 hours is calculated using this value as the predicted value in that time zone.
- the load prediction unit 302 ends the load prediction processing (S603) (S706).
- FIG. 8 is a flowchart of the control parameter calculation process (S604) processed by the operation plan unit 303.
- the operation planning means 303 starts control parameter calculation processing (S801).
- the operation planning unit 303 acquires data necessary for the control parameter (S802).
- the operation planning unit 303 acquires a set hot water supply temperature from the heat pump hot water supply apparatus 200, and acquires a predicted load power amount, a predicted hot water supply heat amount, and a predicted PV power generation amount from the load prediction unit 302.
- the operation planning means 303 calculates a reverse tide stop time (S803). As described above, the operation planning unit 303 subtracts the predicted load power amount from the predicted PV generated power amount in each time zone, and calculates a predicted reverse power amount that is a value with the lower limit being 0.
- the value of the predicted reverse tide power amount in each time zone goes back from 24 o'clock the next time and becomes 0 first.
- the time is the reverse tide stop time.
- the reverse tide stop time is 17:00.
- the operation planning means 303 calculates a target heat storage temperature (S804). As described above, the operation planning unit 303 calculates the amount of heat obtained by integrating the predicted amount of hot water supply from the reverse tide stop time to the next 24:00 by 200 L, which is the tank capacity of the hot water tank 202, and the set hot water supply. The lower one of the upper limit value of 80 ° C. is set as the target heat storage temperature.
- the temperature divided by 200 L which is the tank capacity is 75 ° C., which is the upper limit value of the set hot water temperature.
- the target heat storage temperature is 75 ° C. because of a value lower than 80 ° C.
- the operation planning means 303 calculates the amount of raw heat during reverse tide (S805).
- the operation planning means 303 calculates the amount of heat during reverse tide, which is the amount of heat to be generated by the heat pump 201. This amount of heat during reverse tide corresponds to the amount of heat released during reverse tide stop.
- the amount of raw heat during reverse tide 6000 kcal is calculated using the above equation (1).
- the operation planning means 303 calculates a reverse tidal live heat time (S806).
- the operation planning means 303 calculates the reverse tide raw heat time, which is the time required to heat the reverse tide raw heat quantity with the heat pump 201, using the above equation (2).
- the reverse tidal HP biothermal time 0.78 hours is calculated using Equation (2).
- the operation planning means 303 calculates an operation time zone and a reverse power threshold value (S807). As described above, the operation planning means 303 selects one or more time zones as the operation time zone in descending order of the predicted reverse tidal power amount until the reverse tidal live heat time is exceeded. Moreover, the minimum value of the predicted reverse power amount in each of one or more time zones included in the operation time zone is determined as the reverse power threshold value. For example, in the case where the result of rearranging the predicted reverse tidal power amount from the higher value is the example shown in FIG. 5, when the calculated reverse tidal thermal heat time is 0.78 hours, the operation time zone Becomes 12 o'clock, and the reverse power threshold is 1.68 kW.
- the operation planning means 303 ends the control parameter calculation processing (S604) (S808), and the operation planning device 210 ends the operation planning processing (S605).
- the operation plan apparatus 210 performs the operation control process of the heat pump hot water supply apparatus 200 by the operation control means 304 every minute.
- the operation control unit 304 acquires the target heat storage temperature, the operation time zone, and the reverse power threshold value from the operation plan unit 303 after the operation plan process ends, and loads the load power, PV, and PV from the power distribution device 205 every minute.
- the temperature of the hot water supply tank 202 is acquired from the heat pump type hot water supply apparatus 200 for the generated power. Then, every time information is acquired every minute, the operation control unit 304 calculates reverse power that is a value obtained by subtracting load power from PV generated power.
- the operation of the heat pump 201 is not started when the calculated current reverse power does not reach the reverse power threshold. Then, the operation of the heat pump 201 is started at the timing when the calculated current reverse power flow becomes equal to or higher than the reverse power power threshold. Since the operation control unit 304 acquires the temperature of the hot water supply tank 202 every minute, the operation of the heat pump 201 is terminated when the hot water supply tank 202 reaches the target heat storage temperature.
- the operation plan apparatus 210 performs a process of storing various information in the storage unit 301 at predetermined time intervals.
- the storage unit 301 stores the amount of hot water supply obtained from the heat pump type hot water supply apparatus 200, the amount of load power acquired from the power distribution apparatus 205, the amount of PV generated from the solar power generation apparatus 211, and the amount of solar radiation acquired from the server 209.
- the values acquired each time are accumulated every hour, and the accumulated value for the past one hour is accumulated in the accumulating unit 301 in association with the time at the timing when the time of the time information held inside changes. At the same time, the integrated value is reset to zero.
- the operation planning device 210 uses the operation planning unit 303 based on the prediction information of the load prediction unit 302 to calculate the amount of heat corresponding to the predicted amount of hot water supply from the reverse tide stop time to the next 24:00.
- the hot water storage tank 202 stores heat at the reverse tide stop time.
- the heat loss will occur on the day when the predicted hot water supply amount is small.
- 80 ° C. which is the upper limit of the set value
- the generated reverse power can be reduced without impairing the energy saving performance.
- Embodiment 2 Heat pump type hot water supply and heating device
- Embodiment 1 demonstrated the heat pump type hot water supply system
- the system of this embodiment is a heat pump type hot water supply and heating system in which a heating device having a heating function is mounted in addition to the hot water supply device.
- FIG. 9 is a configuration diagram illustrating a heat pump hot water supply / heating system 9000 including a power generation device.
- the heat pump hot water supply and heating system 9000 according to the second embodiment includes a heat pump hot water supply and heating device 900, a power distribution device 905, a power load 906, an operation planning device 910, and a solar power generation device. 911.
- the power distribution device 905 is connected to the energy supplier 908 via the power meter 907, and the operation planning device 910 is connected to the server 909 via the Internet.
- a heat pump hot water supply / room heating device 900 is different from the first embodiment in that it includes a heating device 904 in addition to the hot water supply device 903. That is, the heat pump hot water supply / room heating apparatus 900 includes a heat pump 901, a heat exchanger 902, a hot water supply apparatus 903, and a heating apparatus 904.
- the heat pump 901 is once stored in the hot water supply tank 901t, and heat is supplied from the hot water supply tank 901t to the hot water supply load. Heat may be supplied to the heating load via 904a. That is, a system in which the hot water supply tank 901t covers both the hot water supply load and the heating load may be used.
- switching between hot water supply and heating can be controlled by a remote controller 1101 used by a customer (user).
- the remote controller 1101 has a function of setting the heat generated by the heat pump 901 to “heating” used for heating, “hot water” used for hot water supply, or “stop” for stopping the heat pump 901. ing.
- the remote controller 1101 outputs the set operation mode to the hot water supply / heating control apparatus 1001. The user can also set the hot water supply temperature and the heating temperature.
- the operation mode When the operation mode is “heating”, the temperature of water (hot water) entering a heating circuit 904a described later is a set heating temperature set by the user.
- the operation mode is “hot water supply”, a temperature in a hot water supply tank 903a described later becomes a set hot water supply temperature set by the user.
- FIG. 10 is a block diagram for explaining the details of the heat pump hot water supply / room heating device 900.
- the heat pump hot water supply and heating apparatus 900 is mainly configured by a hot water supply and heating control apparatus 1001, a heat pump 901, a hot water supply apparatus 903, a heating apparatus 904, and a three-way valve (switching apparatus) 1010.
- the heat pump 901 includes a heat pump unit 901a and a heat exchanger 902.
- the heat pump unit 901a is an evaporator that exchanges heat between the outside air and a low-temperature and low-pressure liquid refrigerant to generate a low-temperature and low-pressure vapor refrigerant, and compresses the low-temperature and low-pressure vapor refrigerant into a high-temperature and high-pressure vapor refrigerant
- an expansion valve that generates low-temperature and low-pressure liquid refrigerant, a fan that promotes heat exchange between the refrigerant in the evaporator and the outside air, and the like.
- the hot water supply tank 903a stores the heat that covers the hot water supply load.
- the hot water heater 903h is in the hot water tank 903a and heats the water in the hot water tank 903a.
- the heating circuit 904a is a hot water passage of the heating facility that covers the heating load.
- the heat exchanger 902 performs heat exchange between the refrigerant heated by the heat pump unit 901a and the secondary water cycle filled with water.
- the three-way valve 1010 is a device that switches the flow path in order to guide the water heated by the heat exchanger 902 to either the hot water supply tank 903a or the heating circuit 904a.
- the refrigerant of the heat pump 901 is 410A. Due to the characteristics of this refrigerant, the maximum temperature of the outlet on the water cycle side of the heat exchanger 902 is 55 ° C., and the upper limit value of the set heating temperature is 55 ° C.
- the hot water supply tank 903a has a heat exchange coil inside. This heat exchange coil is a dotted line portion of the hot water supply tank 903a in FIG.
- the three-way valve 1010 When the three-way valve 1010 is set in the flow path of the hot water supply tank 903a, the water heated by the heat exchanger 902 passes through the heat exchange coil and heats the water in the hot water supply tank 903a. Since the maximum temperature at the water cycle side outlet of the heat exchanger 902 is 55 ° C., when the temperature of the hot water supply tank 903a is 50 ° C. or higher, heat exchange by the heat exchange coil is hardly performed.
- the hot water heater 903h is energized and heated.
- the capacity of the hot water supply tank 903a is 200L
- the heating capacity of the hot water heater 903h is 3 kW
- the upper limit value of the set hot water temperature is 80 ° C.
- the heat pump unit 901a can raise the temperature of the water in the hot water supply tank 903a to around 50 ° C. (first temperature), and the hot water heater 903h makes the temperature of the water in the hot water supply tank 903a higher than 50 ° C.
- the temperature can be raised (second temperature).
- water is used as an example of the heat storage material held in the hot water supply tank 903a.
- the present invention is not limited to this, and any heat storage material whose temperature changes according to the amount of heat stored is adopted. can do.
- the hot water supply and heating control device 1001 is a device that controls the entire system of the heat pump hot water supply and heating device 900 based on set information. As shown in FIG. 11, hot water supply and heating control device 1001 acquires operation information from remote controller 1101 and operation planning device 910.
- the hot water supply / heating control apparatus 1001 acquires an operation mode, a set heating temperature, and a set hot water supply temperature as operation information from the remote controller 1101. Moreover, the hot water supply and heating control device 1001 acquires the priority operation mode and the priority set hot water supply temperature as operation information from the operation planning device 910.
- the priority operation mode has priority over the operation mode acquired from the remote controller 1101.
- the priority set hot water supply temperature has priority over the set hot water supply temperature acquired from the remote controller 1101. That is, even when the hot water supply / heating control apparatus 1001 acquires the operation mode from the remote controller 1101, when the priority operation mode is acquired from the operation planning apparatus 910, the priority operation mode from the operation planning apparatus 910 is given priority.
- the hot water supply and heating control device 1001 sends information on the amount of hot water supply and the temperature of the hot water supply tank to the operation planning device 910.
- the operation planning device 910 receives information on the load power amount and the PV power generation amount from the power distribution device 205. In addition, it is set to receive solar radiation information and predicted solar radiation information via the Internet.
- the hot water supply / heating control apparatus 1001 sets the three-way valve 1010 as the flow path of the heating circuit 904a, and when the operation mode is “hot water supply”, the three-way valve 1010 is set as the flow path of the hot water tank 903a. Set. When the operation mode is “stop”, the three-way valve 1010 is not changed.
- the hot water supply / heating control apparatus 1001 operates the heat pump unit 901a, and the rotation speed of the compressor of the heat pump unit 901a so that the outlet temperature of the heat exchanger 902 becomes equal to the set heating temperature. Adjust the opening of the expansion valve.
- the hot water heater 903h When the temperature of the hot water supply tank 903a is 5 degrees or more lower than the set hot water supply temperature ("set hot water supply temperature -5" ° C or less), the hot water heater 903h is energized to heat the water in the hot water supply tank 903a. When the temperature of the hot water supply tank 903a becomes equal to or higher than the set hot water supply temperature, the power supply to the hot water heater 903h is stopped.
- the hot water supply / heating control apparatus 1001 has a temperature in the hot water supply tank 903a of 50 ° C. or lower and lower than the set hot water supply temperature by 5 degrees or more (“set hot water supply temperature ⁇ 5”). And the three-way valve 1010 is set in the flow path of the hot water supply tank 903a, and the heat pump 901 is controlled so that the outlet temperature of the heat exchanger 902 becomes 55 ° C. This is because, as described above, when the temperature in the hot water supply tank 903a is 50 ° C. or higher, heat exchange (heating) in the hot water supply tank 903a is hardly performed.
- the hot water heater 903h is energized, Heat the water inside.
- the temperature of the hot water supply tank 903a becomes equal to or higher than the set hot water supply temperature, the power supply to the hot water heater 903h is stopped.
- the hot water supply and heating control device 1001 acquires the priority operation mode and the priority set hot water supply temperature from the operation planning device 910, the operation plan is given priority over the operation mode and the set hot water supply temperature set by the user with the remote controller 1101. Control is performed using the “priority operation mode” acquired from the device 910 as the operation mode and the “priority set hot water temperature” as the set hot water temperature.
- the operation planning device 910 is almost the same as the operation described in FIG. Unlike the first embodiment, the heat pump hot water supply and heating system 9000 of the second embodiment performs heat exchange with a heat exchanger 902 and then uses a three-way valve 1010 to supply a hot water supply tank 903a and a heating circuit 904a as shown in FIG. The flow path is switched. Further, since the heat exchanger 902 can only heat up to about 50 ° C., when heating to a temperature higher than that, the hot water heater 903h in the hot water tank 903a is used.
- the operation planning device 910 causes the heat pump unit 901a to generate the amount of heat until the water in the hot water supply tank 903a reaches 50 ° C. out of the amount of heat corresponding to the amount of heat released during reverse tide stop, and the water in the hot water supply tank 903a
- An operation plan is made so that the amount of heat after reaching 50 ° C. is generated in the hot water heater 903h. For this reason, the calculation method of the amount of heat required during reverse tide is as follows.
- the operation plan means 303 uses the following equation (3) “Reverse tide HP raw heat amount”, which is the amount of heat generated in 901, is calculated, and “Reverse tide heater heat amount”, which is the amount of heat generated by the hot water heater 903h during reverse tide, is calculated by the following equation (4). calculate.
- the operation planning device 910 When the set hot water supply temperature (current set temperature of the hot water supply tank 903a) is 50 ° C. or higher.
- the operation planning device 910 generates the hot water heater 903h using the following equation (5) when the set hot water supply temperature is 50 ° C. or higher.
- the amount of raw heat generated during reverse tide, which is the amount of heat that is heated, is calculated.
- Heater heat quantity during reverse tide (Target heat storage temperature-Set hot water temperature) * Hot water tank capacity ⁇ Equation (5)
- the operation planning means 303 uses the following equation (6) to calculate “the reverse tidal HP biothermal time t (HP)” which is the time required to regenerate the reverse tidal HP raw heat quantity with the heat pump 901. And the “reverse tide heater heat generation time t (HT)”, which is the time required for regenerating the reverse tide heater raw heat amount with the hot water heater 903h, is calculated by the following equation (7).
- capacitance which is an average raw heat capacity of the heat pump 901 which is a value memorize
- the heater heating capacity which is an average raw heat capacity of the hot water heater 903h, is 3 kW.
- the conversion factor from the amount of heat (kcal) to electric power (kW) is 0.86.
- t (HP) (HP tidal energy during reverse tide / 0.86 / 1000) / HP average capacity formula (6)
- t (HT) (heat amount of heater during reverse tide / 0.86 / 1000) / heater heating capacity / expression (7)
- the operation planning means 303 calculates a value (t (HP) + t (HT)) obtained by adding the reverse-tide HP heat generation time and the reverse-flow heater heat generation time as the reverse-tide heat generation time. .
- the operation planning means 303 makes an operation plan for the heat pump 901 from the calculated reverse tidal live heat time.
- the hot water heater 903h is heated subsequent to the operation of the heat pump 901, but an operation plan is drawn up so that the operation of the hot water heater 903h is also terminated before the reverse tide stop time.
- the operation of the heat pump hot water supply / heating system 9000 according to Embodiment 2 will be described.
- the current time is 0:00 and the heat pump hot water supply / heating system 9000 has been operating for 28 days or more.
- the remote controller 1101 is set such that the operation mode information is “heating”, the set heating temperature is “50 ° C.”, and the set hot water supply temperature is “45 ° C.”. Further, the temperature in the hot water supply tank 903a is made uniform at 50 ° C. at 0:00.
- the operation planning means 303 uses the formula (3) to generate heat in the reverse tide HP, which is the heat generated by the heat pump 901, and the formula (4).
- the amount of regenerative heat during reverse tide which is the amount of heat generated by the heater 903h, is calculated.
- the set hot-water supply temperature is less than 50 ° C., and therefore, using the equations (3) and (4), the amount of HP heat generated during reverse tide Is 1000 [kcal], and the amount of raw heat generated during reverse tide is 5000 [kcal].
- the hot water storage tank capacity is 200 liters.
- the operation planning means 303 calculates the heating time during reverse tide. As described above, the operation planning means 303 calculates the reverse tidal HP heat generation time, which is the time required for regenerating the reverse tidal HP raw heat amount with the heat pump 901, using the equation (6). ) To calculate the heater heat generation time during reverse tide, which is the time required for the amount of heat generated during reverse tide heating by the hot water heater 903h.
- the operation planning means 303 calculates a value (t (HP) + t (HT)) obtained by adding the reverse tidal HP heat generation time and the reverse tidal heater heat generation time as the reverse tidal heating time. For example, 2.07 [hr] is calculated as the heating time during reverse tide for t (HP) and t (HT) calculated as described above.
- the priority order 1 to 3 in FIG. is set as the reverse flow power threshold.
- FIG. 16 is a flowchart showing the operation of the heat pump hot water supply / room heating device 900.
- the hot water supply and heating control device 1001 monitors the reverse power, and starts the operation of the heat pump hot water supply and heating device 900 at a timing (S1601) when the reverse power becomes equal to or higher than the reverse power threshold. At that time, if the temperature of the hot water supply tank (current temperature of the hot water supply tank 903a) is 50 ° C. or higher (S1602), the hot water heater 903h is heated (S1603), and the water in the hot water supply tank 903a reaches the target heat storage temperature. (S1604), the raw heat by the hot water heater 903h is terminated (S1605).
- the heat pump unit 901a is heated. At this time, if the target heat storage temperature is less than 50 ° C. (S1606), only the heat pump unit 901a is heated (S1609). When the water in the hot water supply tank 903a reaches the target heat storage temperature (S1610), the heat generation by the heat pump unit 901a is terminated (S1611).
- the heat pump 901 a is heated until the water in the hot water supply tank 903 a reaches 50 ° C. (S 1607). Furthermore, after the water in the hot water supply tank 903a has reached the upper limit temperature of 50 ° C. (S1608), the hot water supply heater 903h is regenerated until the target heat storage temperature is reached (S1603), and the water in the hot water supply tank 903a becomes the target heat storage. When the temperature is reached (S1604), the heat generation by the hot water heater 903h is terminated (S1605).
- the operation planning device 910 predicts the load power amount, the hot water supply heat amount, and the PV power generation amount in each time zone on the prediction day, and uses the reverse power to make a hot water supply tank based on the prediction information.
- An operation plan for heating 202 is made.
- the operation time zone is selected in order from the time zone in which the backflow power amount is large, and the minimum value of the backflow power amount in each selected time zone is set as the backflow power threshold value.
- the 11:00 platform is 1.44 [kW]
- the 12:00 platform is 1.68 [kW]
- the 13:00 range is 1.38 [kW]
- the reverse power threshold when the 11:00 to 13:00 range is the operating time zone is 1.38, which is the smallest value among these three. [KW] is set.
- the operation planning device 910 uses the control parameters determined as described above for the control of the heat pump hot water supply and heating device 900 in preference to the setting information by the remote controller 1101.
- FIG. 13 shows a comparison of power consumption required for heating the water in the hot water supply tank 903a when the load prediction unit 302 is not used.
- the operation 2 in FIG. 13 is a result of the operation in which the operation planning apparatus 910 is not provided with a load prediction unit and the reverse power threshold is larger than 0, that is, when the occurrence of reverse power is detected, the hot water supply tank 903a is heated. is there.
- the reverse power threshold is set to a large value, the hot water supply tank 903a may not be heated on the day when the reverse flow power is low.
- the operation plan is performed using the prediction result of the load prediction means, so that the problem between the operation 1 and the operation 2 is solved and the reverse power is minimized. I understand.
- the reverse power flow generated can be reduced by the heat pump hot water supply and heating system 9000 including the solar power generation device 911 without impairing energy saving performance.
- the solar power generation device has been described as an example of the power generation device, a power generation device in which a plurality of solar power generation devices are combined may be used.
- the operation planning device is outside the hot water supply and heating device and serves as a gateway, it may be installed inside the hot water supply and heating device or inside the power distribution device. Further, the operation planning function of the operation planning device may be provided to the hot water supply device or the power distribution device.
- the operation plan means calculates the reverse power threshold, and the operation control means controls according to the magnitude of the reverse power, but the timer is set at a predetermined time period calculated to minimize the reverse power.
- the hot water heater may be operated between 11:00 and 13:00.
- the operation planning apparatus performs the operation planning process once a day at 0 o'clock, but it may be performed several times a day, or at any time such as 2 o'clock or 6 o'clock even if it is not 0 o'clock.
- the end of the reverse tide stop time zone (in the embodiment, 24:00) is changed in the same manner. That is, the reverse tide stop time period is a time period from the reverse tide stop time (in the example, 17:00) to a predetermined time when heat dissipation (hot water supply) from the heat radiating unit (hot water supply device) is considered to stop. Therefore, the operation planning device may make an operation plan for the next day after the end of the reverse tide stop time period.
- the unit of 1 hour is used as the unit time of the load information and the prediction information used in the processing of the operation planning device, information in an arbitrary unit such as a unit of 15 minutes or a unit of 1 minute may be used.
- the average value of the same day of the week and the same time is used for the prediction using the load prediction means, but a method such as prediction using a neural network may be used.
- Each of the above devices is specifically a computer system including a microprocessor, ROM, RAM, a hard disk unit, a display unit, a keyboard, a mouse, and the like.
- a computer program is stored in the RAM or the hard disk unit.
- Each device achieves its functions by the microprocessor operating according to the computer program.
- the computer program is configured by combining a plurality of instruction codes indicating instructions for the computer in order to achieve a predetermined function.
- the system LSI is a super multifunctional LSI manufactured by integrating a plurality of components on a single chip, and specifically, a computer system including a microprocessor, a ROM, a RAM, and the like. .
- a computer program is stored in the RAM.
- the system LSI achieves its functions by the microprocessor operating according to the computer program.
- the constituent elements constituting each of the above devices may be constituted by an IC card or a single module that can be attached to and detached from each device.
- the IC card or module is a computer system that includes a microprocessor, ROM, RAM, and the like.
- the IC card or the module may include the super multifunctional LSI described above.
- the IC card or the module achieves its functions by the microprocessor operating according to the computer program. This IC card or this module may have tamper resistance.
- the present invention may be the method described above. Further, the present invention may be a computer program that realizes these methods by a computer, or may be a digital signal composed of a computer program.
- the present invention also relates to a computer-readable recording medium capable of reading a computer program or a digital signal, such as a flexible disk, hard disk, CD-ROM, MO, DVD, DVD-ROM, DVD-RAM, BD (Blu-ray Disc), It may be recorded in a semiconductor memory or the like. Further, it may be a digital signal recorded on these recording media.
- a computer-readable recording medium capable of reading a computer program or a digital signal, such as a flexible disk, hard disk, CD-ROM, MO, DVD, DVD-ROM, DVD-RAM, BD (Blu-ray Disc), It may be recorded in a semiconductor memory or the like. Further, it may be a digital signal recorded on these recording media.
- the present invention may transmit a computer program or a digital signal via an electric communication line, a wireless or wired communication line, a network represented by the Internet, a data broadcast, or the like.
- the present invention may be a computer system including a microprocessor and a memory.
- the memory may store the computer program, and the microprocessor may operate according to the computer program.
- program or digital signal may be recorded on a recording medium and transferred, or the program or digital signal may be transferred via a network or the like, and may be implemented by another independent computer system.
- the operation planning apparatus is useful as an apparatus that contributes to stabilization of the electric power system when operating a hot water supply system or a hot water supply / heating system.
- Heat pump type hot water supply apparatus 201 901 Heat pump 202, 901t, 903a Hot water supply tank 203, 903 Hot water supply apparatus 205, 905 Electric power distribution apparatus 206, 906 Electric power load 207, 907 Electric power meter 208, 908 Energy supplier 209, 909 Server 210, 910 Operation planning apparatuses 211 and 911 Photovoltaic power generation apparatus 301 Accumulation means 302 Load prediction means 303 Operation planning means 304 Operation control means 900 Heat pump hot water heater / heater 901a Heat pump unit 902 Heat exchanger 903h Hot water heater 904 Heater 904a Heating circuit 1001 Hot water heater Control device 1010 Three-way valve 1101 Remote control 2000 Heat pump hot water supply system 9000 Heat pump hot water supply heating system
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Economics (AREA)
- General Physics & Mathematics (AREA)
- Strategic Management (AREA)
- Human Resources & Organizations (AREA)
- Power Engineering (AREA)
- Marketing (AREA)
- Tourism & Hospitality (AREA)
- Health & Medical Sciences (AREA)
- Theoretical Computer Science (AREA)
- Entrepreneurship & Innovation (AREA)
- General Business, Economics & Management (AREA)
- Thermal Sciences (AREA)
- Mechanical Engineering (AREA)
- Chemical & Material Sciences (AREA)
- General Engineering & Computer Science (AREA)
- Combustion & Propulsion (AREA)
- Automation & Control Theory (AREA)
- Water Supply & Treatment (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Quality & Reliability (AREA)
- Operations Research (AREA)
- Public Health (AREA)
- Game Theory and Decision Science (AREA)
- General Health & Medical Sciences (AREA)
- Primary Health Care (AREA)
- Life Sciences & Earth Sciences (AREA)
- Sustainable Development (AREA)
- Sustainable Energy (AREA)
- Heat-Pump Type And Storage Water Heaters (AREA)
- Supply And Distribution Of Alternating Current (AREA)
Abstract
運転計画方法は、発電装置と、発電装置で発電された電力を用いて動作する第1の電力負荷と、発電装置で発電された電力を用いて熱を生成する第2の電力負荷とを備えるシステムにおいて、第2の電力負荷の運転計画を立案する方法である。具体的には、単位時間に区切られた各時間帯において、発電装置で発電される発電電力量(S102)と、第1の電力負荷で消費される消費電力量とを予測する予測ステップ(S101)と、発電電力量から消費電力量を減算して得られる逆潮電力量が最も多くなる時間帯を含む運転時間帯に第2の電力負荷を動作させるように、第2の電力負荷の運転計画を立案する運転計画ステップ(S103~S105)とを含む。
Description
本発明は、太陽光発電装置などの発電に関する装置と、ヒートポンプなどの電力を消費する機器とを備えたシステムに関するものである。
太陽光発電、風力発電などの発電装置は、創エネルギーを目的とした装置である。太陽光発電は、太陽光のエネルギーを電力に変換し家庭に供給する自然エネルギー発電であり、天候や気象条件の変化によって、常に発電電力が変動する。
ヒートポンプ式給湯器は、大気の熱を吸熱し、電気で冷媒を圧縮して加熱し、熱交換器により水から温水を作るので、従来のヒータ式の電気温水器と比較して省エネな給湯システムである。
発電装置を備えたヒートポンプ式給湯システムは、これらの組合せで構成され、需要家に電気と熱のエネルギーを供給する。従来の発電装置を備えたヒートポンプ式給湯暖房システムとして、例えば特許文献1に示すものがある。
特許文献1の発明では、気象情報取得手段でサーバから気象予測情報を取得し、取得情報が設定した条件であると、CO2ヒートポンプ給湯器でお湯を沸かす電力を商用電力の深夜電力ではなく、太陽光発電の電力を利用するように切り替え制御する。自然エネルギーの電力で電気給湯器を稼動させるので、電力利用がより効率的・省エネルギーになり、電気代も安価になる。
しかしながら、従来の装置によれば、常に変動する太陽光発電装置の電力と需要家の電力負荷とから決定される逆潮電力の消費量を考慮していない。太陽光発電が普及し、多くの家庭で逆潮電力が同時に発生すると、系統の電圧が上がり、系統が不安定になる。また、系統の下位側に位置する需要家では、系統の電圧が高い場合に逆潮できなくなり、太陽光発電装置で発電した電力を無駄にすることになる。
また、逆潮した電力は、配電環境によって高圧に変換され、変換される過程で大きな変換ロスが生じ、また別の需要家に送電する過程での送電ロスも生じる。このため、発電した電力を自家消費することが環境面からも良い。
さらに、特許文献2に示す装置も提案されている。この装置では、発電量が使用電力量を上回った場合にヒートポンプユニットを稼動させている。しかし、この上回った電力量に対応してヒートポンプユニットを稼動させるものではなく、系統への逆潮低減を効果的にできるものではない。
そこで、本発明は上記の課題を解決するためになされたもので、逆潮電力が小さく、省エネルギー性を損なわない、発電装置を備えたシステムの運転計画方法を提供することを目的とする。
本発明の一形態に係る運転計画方法は、発電装置と、前記発電装置で発電された電力を用いて動作する第1の電力負荷と、前記発電装置で発電された電力を用いて熱を生成する第2の電力負荷とを備えるシステムにおいて、前記第2の電力負荷の運転計画を立案する方法である。具体的には、単位時間に区切られた各時間帯において、前記発電装置で発電される発電電力量と、前記第1の電力負荷で消費される消費電力量とを予測する予測ステップと、前記発電電力量から前記消費電力量を減算して得られる逆潮電力量が最も多くなる時間帯を含む運転時間帯に前記第2の電力負荷を動作させるように、前記第2の電力負荷の運転計画を立案する運転計画ステップとを含む。
上記構成のように、逆潮電力量がピークとなる時間帯を予測し、予測した時間帯に第2の電力負荷を運転させることにより、系統へのダメージを小さくすることができる。
一例として、前記発電装置は、太陽光発電装置であってもよい。また、前記第2の電力負荷は、前記発電装置で発電される電力を用いて熱を生成する生熱部と、前記生熱部で生成された熱を蓄熱する蓄熱部と、前記蓄熱部に蓄熱されている熱を放熱する放熱部とを備えてもよい。そして、前記予測ステップでは、さらに、前記消費電力量が前記発電電力量を上回る時間帯である逆潮停止時間帯に前記放熱部で放熱される逆潮停止中放熱量を予測し、前記運転計画ステップでは、前記予測部で予測された逆潮停止中放熱量に相当する熱量が前記蓄熱部に蓄熱されるように、前記運転時間帯における前記生熱部の運転計画を立案してもよい。
また、前記運転計画ステップでは、前記逆潮停止中放熱量に相当する熱量を前記生熱部が生成するのに必要な時間を超えるまで、前記逆潮電力量の大きい順に1以上の前記時間帯を選択することによって前記運転時間帯を決定し、決定した前記運転時間帯における前記運転計画を立案してもよい。
また、前記運転計画ステップでは、選択された前記1以上の時間帯各々における前記逆潮電力量のうちの最小値を、逆潮電力閾値として決定し、前記運転時間帯において、実際に計測された逆潮電力が前記逆潮電力閾値以上になったタイミングで前記生熱部の運転を開始するように、前記運転計画を立案してもよい。
さらに、前記運転計画ステップでは、前記運転時間帯において、前記逆潮停止中放熱量に相当する熱量が生成されたタイミングで前記生熱部の運転を停止するように、前記運転計画を立案してもよい。
また、前記蓄熱部は、蓄熱している熱量に応じて温度が変化する蓄熱材を備えてもよい。さらに、前記生熱部は、前記蓄熱材の温度を第1の温度まで上昇させることのできるヒートポンプと、前記蓄熱材の温度を前記第1の温度より高い温度まで上昇させることのできるヒータとを備えてもよい。そして、前記運転計画ステップでは、前記逆潮停止中放熱量に相当する熱量のうち、前記蓄熱材が前記第1の温度に達するまでの熱量を前記ヒートポンプに生成させ、前記蓄熱材が前記第1の温度に達した後の熱量を前記ヒータに生成させるように、前記運転計画を立案してもよい。
また、前記予測ステップでは、前記逆潮電力量が正の値から0以下の値に変化した時刻である逆潮停止時刻から、前記放熱部からの放熱が停止すると考えられる予め定められた時刻までの間の時間帯である前記逆潮停止時間帯に前記放熱部で放熱される熱量を、前記逆潮停止中放熱量として予測してもよい。
また、前記予測ステップでは、各時間帯の前記消費電力量を、同じ曜日で且つ同じ時間帯に計測された過去の複数の消費電力量の平均値に相当すると予測し、各時間帯の前記逆潮停止中放熱量を、同じ曜日で且つ同じ時間帯に計測された過去の複数の逆潮停止中放熱量の平均値に相当すると予測してもよい。
また、前記予測ステップでは、予測当日の各時間帯の予測日射量を取得し、各時間帯の前記発電電力量を、過去に計測された発電電力量のうち、日射量が当日の予測日射量に最も近い時間帯の発電電力量に相当すると予測してもよい。
本発明の一形態に係る運転計画装置は、発電装置と、前記発電装置で発電された電力を用いて動作する第1の電力負荷と、前記発電装置で発電された電力を用いて熱を生成する第2の電力負荷とを備えるシステムにおいて、前記第2の電力負荷の運転計画を立案する装置である。具体的には、単位時間に区切られた各時間帯において、前記発電装置で発電される発電電力量と、前記第1の電力負荷で消費される消費電力量とを予測する予測部と、前記発電電力量から前記消費電力量を減算して得られる逆潮電力量が最も多くなる時間帯を含む運転時間帯に前記第2の電力負荷を動作させるように、前記第2の電力負荷の運転計画を立案する運転計画部とを備える。
本発明の一形態に係るヒートポンプ式給湯システムの運転方法は、太陽光発電装置と、ヒートポンプ式給湯装置と、運転計画装置とを備えるヒートポンプ式給湯システムの運転方法である。前記運転計画装置は、前記発電装置で発電される発電電力量と、電力負荷で消費される消費電力量とを予測する予測ステップと、前記発電電力量から前記消費電力量を減算して得られる逆潮電力量を算出するステップと、前記逆潮電力量がゼロとなる逆潮停止時間帯に必要な熱量(逆潮停止中放熱量)を予測するステップと、前記逆潮電力量が最も多くなる時間帯を含む運転時間帯に、前記予測した熱量を蓄熱するように、前記ヒートポンプ式給湯装置を動作させる計画を立案する運転計画ステップとを含む制御をする。
また、前記運転計画ステップは、予測した熱量を蓄熱するための目標蓄熱温度と、選択された前記1以上の時間帯各々における前記逆潮電力量のうちの最小値を、逆潮電力閾値として決定してもよい。
また、前記運転計画ステップで決定された前記目標蓄熱温度と、前記逆潮電力閾値とを受けて、前記運転時間帯において、実際に計測された逆潮電力が前記逆潮電力閾値以上になったタイミングで前記ヒートポンプ式給湯装置の運転を開始し、前記運転時間帯において、前記予測した熱量が生成されたタイミングで前記ヒートポンプ式給湯装置の運転を停止してもよい。
また、前記発電電力量の予測、前記消費電力量の予測、及び前記熱量の予測は、蓄積手段に蓄積された履歴情報を用いて行ってもよい。
また、前記運転計画装置は、ヒートポンプ式給湯装置の内部に設置されていてもよい。
本発明の一形態に係るヒートポンプ式給湯暖房装置の運転方法は、太陽光発電装置と、ヒートポンプ式給湯暖房装置とを備えたヒートポンプ式給湯暖房システムの運転方法である。前記ヒートポンプ式給湯暖房装置は、給湯タンクと暖房装置とを備える。前記システムは運転計画装置を備える。そして、前記運転計画装置は、前記発電装置で発電される発電電力量と、電力負荷で消費される消費電力量とを予測する予測ステップと、前記発電電力量から前記消費電力量を減算して得られる逆潮電力量を算出するステップと、前記逆潮電力量がゼロとなる逆潮停止時間帯に必要な熱量(逆潮停止中放熱量)を予測するステップと、前記逆潮電力量が最も多くなる時間帯を含む運転時間帯に、前記予測した熱量を蓄熱するように、前記ヒートポンプ式給湯暖房装置を動作させる計画を立案する運転計画ステップとを含む制御をする。
また、前記運転計画ステップは、予測した熱量を蓄熱するための目標蓄熱温度と、選択された前記1以上の時間帯各々における前記逆潮電力量のうちの最小値を、逆潮電力閾値として決定してもよい。
また、前記運転計画ステップで決定された前記目標蓄熱温度と、前記逆潮電力閾値とを受けて、前記運転時間帯において、実際に計測された逆潮電力が前記逆潮電力閾値以上になったタイミングで前記ヒートポンプ式給湯装置の運転を開始し、前記運転時間帯において、前記予測した熱量が生成されたタイミングで前記ヒートポンプ式給湯装置の運転を停止してもよい。
また、前記運転計画ステップは、予測した熱量を給湯タンクに蓄熱するための目標蓄熱温度を決定し、前記ヒートポンプ式給湯暖房装置のヒートポンプにより第1の温度まで前記給湯タンク内の蓄熱材を加熱し、その後、前記給湯タンク内に設置されたヒータにより第1の温度よりも高い第2の温度まで前記蓄熱材を加熱するよう制御してもよい。
また、前記ヒートポンプ式給湯暖房装置は、給湯暖房制御装置を備え、前記給湯暖房制御装置は、前記運転計画装置から前記ヒートポンプ式給湯暖房装置の運転情報を受けるとともに、リモコンから前記ヒートポンプ式給湯暖房装置の運転情報を受けるように設定されており、前記運転計画装置からの前記運転情報を取得した場合には、前記リモコンからの前記運転情報に優先して、前記運転計画装置からの前記運転情報に基づいて前記ヒートポンプ式給湯暖房装置を制御してもよい。
また、前記運転情報は、前記ヒートポンプ式給湯暖房装置の運転モード及び給湯タンクの設定給湯温度であってもよい。
また、前記ヒートポンプ式給湯暖房装置は熱交換器を備え、熱交換器から供給される蓄熱材は、切替装置により、給湯タンクまたは暖房装置へ供給されるように制御されてもよい。
本発明は、逆潮電力量がピークとなる時間帯を予測し、予測した時間帯にシステムを運転させるため、系統へのダメージを小さくできる。
以下、本発明の実施の形態について、図面を参照しながら説明する。図1に示す通り、本発明では、宅内の消費電力量である負荷電力量の予測(S101)と、PV(Photovoltaic)による発電力量であるPV発電力量の予測(S102)とから、逆潮電力量を予測(S103)し、この逆潮電力量がピークとなる時間帯にHP(Heat Pump)を運転(S105)させるものである。HPの運転期間は、給湯熱量の予測(S104)により決定する。これにより系統へ逆潮する電力量を低減し、電力系統への影響を効果的に少なくすることができる。
(実施の形態1:ヒートポンプ式給湯装置)
図2は、本発明の実施の形態1に係るヒートポンプ式給湯システムを示す図である。図2に示されるエネルギー供給業者(電力供給元)208は、住宅に対して、電力系統を通じて電力を供給している。電力系統は、安定的に電力が供給される電力系統である。電力メーター207は、電力系統を通じて供給され、住宅で消費される電力の消費量を計測する。また、電力メーター207は、太陽光発電装置211で発電された電力を宅内で消費し、余った電力を系統へ売電できるようになっている。
図2は、本発明の実施の形態1に係るヒートポンプ式給湯システムを示す図である。図2に示されるエネルギー供給業者(電力供給元)208は、住宅に対して、電力系統を通じて電力を供給している。電力系統は、安定的に電力が供給される電力系統である。電力メーター207は、電力系統を通じて供給され、住宅で消費される電力の消費量を計測する。また、電力メーター207は、太陽光発電装置211で発電された電力を宅内で消費し、余った電力を系統へ売電できるようになっている。
図2に示される住宅には、電力負荷(第1の電力負荷)206と、ヒートポンプ式給湯装置(第2の電力負荷)200と、運転計画装置210と、太陽光発電装置211と、電力分配装置205とが設置されている。ヒートポンプ式給湯装置200は、ヒートポンプ201と、給湯タンク202と、給湯装置203とを少なくとも備えている。電力負荷206は、例えば、エアコン、洗濯機、冷蔵庫などの電力の供給を受けて動作する機器である。
太陽光発電装置211は、太陽光のエネルギーを電力に変換する装置であり、太陽光のエネルギーを電力に変換し、変換した電力(PV発電力)を出力する。
電力分配装置205は、太陽光発電装置211と、エネルギー供給業者208が供給する商用電源とから電力を取得し、需要に応じてヒートポンプ式給湯装置200と電力負荷206とに電力を分配する装置である。また、分配する電力量を計測することができる。
電力分配装置205は、太陽光発電装置211からPV発電力を取得する。電力分配装置205は、電力負荷206で消費されている電力である負荷電力と、ヒートポンプ式給湯装置200で消費されている電力である給湯電力とを計測する。そして、負荷電力と給湯電力との和がPV発電力を上回る場合には、電力メーター207を通して電力系統から購入した電力である買電力を取得する。すなわち、電力分配装置205は、PV発電力と買電力を取得し、ヒートポンプ式給湯装置200へは給湯電力を、電力負荷206へは負荷電力をそれぞれ供給する。また、PV発電力が給湯電力と負荷電力との和を上回った場合には、余った電力をエネルギー供給業者208に逆潮電力として出力し、電力を売電できる。
また、電力分配装置205は、コンバータ及びインバータを備え、上記の通り取得した電力を出力する場合に、取得した電力を出力する電力の形式に合わせて電圧、及びAC/DC間の変換を行う。また、電力分配装置205は、電力負荷206で実際に消費された負荷電力と、太陽光発電装置211で実際に発電されたPV発電力とを運転計画装置210に出力する。
サーバ209は、需要家の自宅における現在の日射量と、将来に予測される日射量とをインターネット経由で送信する装置である。本実施の形態では、サーバ209は、需要家の地域で計測された日射量を、所定の時間毎にインターネット経由で送信する。
また、サーバ209は、需要家の地域の過去の日射量の履歴と、翌日の天気予報とを用いて0時から翌24時間の1時間毎の日射量の予測値を算出し、1日に1回、0時にインターネット経由で送信する。
エネルギー供給業者208は、需要家に設置された電力分配装置205の需要に従って買電力を供給し、電力分配装置205から逆潮電力が入力された場合は、その電力を電力系統経由で他の需要家へ出力する。
電力負荷206は、需要家の電力負荷であり、例えばテレビ、エアコン、冷蔵庫、洗濯機、照明等の電力分配装置205から供給される電力を用いて動作する機器を指す。そして、これらの機器で使用される電力の総和を負荷電力と定義する。
ヒートポンプ(生熱部)201は、空気熱源のヒートポンプであり、冷媒(例えば、CO2)と水との間で凝縮器(図示せず)を介して熱交換させることにより、高温の温水を生成するものである。給湯タンク(蓄熱部)202は、ヒートポンプ201で生成した温水を蓄え、急激に外気温が低下した際などに、室温を一定に保つために必要な熱をまかなうバッファとして用いるものである。給湯装置(放熱部)203は、給湯タンク202から供給される温水を供給するものである。ここでは、ヒートポンプ201、給湯タンク202、及び給湯装置203を併せて、ヒートポンプ式給湯装置200と呼ぶ。
運転計画装置210は、図1で説明したように、逆潮電力量が小さくなるようにヒートポンプ式給湯装置200の運転計画を立案し、その動作を制御するものである。図3を用いて、運転計画装置210の構成を詳細に説明する。運転計画装置210は、図2に示されるように、蓄積手段301、負荷予測手段302、運転計画手段303および運転制御手段304で構成されている。
蓄積手段301は、電力負荷206で消費された1時間毎の負荷電力量と、ヒートポンプ式給湯装置200で消費された1時間毎の給湯熱量と、太陽光発電装置211で発電された1時間毎のPV発電力量と、現在の日射量の値である1時間毎の日射量とを蓄積する。
この蓄積手段301は、例えば、DRAM(Dynamic random access memory)、SDRAM(Synchronous dynamic random access memory)、フラッシュメモリ、又は強誘電体メモリ等のデータを記録可能な手段であればどのようなものを利用しても構わない。
負荷予測手段302は、電力負荷206で消費されると予測される1時間毎の予測負荷電力量と、ヒートポンプ式給湯装置200で消費されると予測される1時間毎の予測給湯熱量と、太陽光発電装置211で発電されると予測される1時間毎の予測PV発電力量とを算出する。
運転計画手段303は、逆潮電力量が最小となるように、ヒートポンプ式給湯装置200の運転計画を立案し、ヒートポンプ式給湯装置200の動作を制御する制御パラメータを算出する。最後に運転制御手段304は、制御パラメータに基づきヒートポンプ式給湯装置200の運転を制御する。
(蓄積手段)
まず蓄積手段301は、需要家の負荷電力量、給湯熱量、PV発電力量、及び日射量の各値を蓄積する。より具体的には、蓄積手段301は、図14の履歴表に示されるように、負荷電力の1時間毎の計測値(負荷電力量)と、給湯熱量の1時間毎の計測値と、PV発電力の1時間毎の計測値(PV発電力量)と、日射量の1時間毎の計測値とを、それぞれ負荷電力履歴、給湯熱量履歴、PV発電力履歴、及び日射量履歴として所定の期間(図14の例では、4週間分)だけ保持している。この履歴表は、4週間分の各曜日の履歴情報(負荷電力、給湯熱量、PV発電力、日射量)を保持しているが、さらに詳細には、各曜日の各時刻の履歴情報を保持している。時刻が0、1、2、・・・とは、0時台、1時台、2時台、・・・を示している。またその時刻における履歴情報は、積算情報となっている。時刻0の負荷電力履歴は、0時台の負荷電力の積算電力量である。
まず蓄積手段301は、需要家の負荷電力量、給湯熱量、PV発電力量、及び日射量の各値を蓄積する。より具体的には、蓄積手段301は、図14の履歴表に示されるように、負荷電力の1時間毎の計測値(負荷電力量)と、給湯熱量の1時間毎の計測値と、PV発電力の1時間毎の計測値(PV発電力量)と、日射量の1時間毎の計測値とを、それぞれ負荷電力履歴、給湯熱量履歴、PV発電力履歴、及び日射量履歴として所定の期間(図14の例では、4週間分)だけ保持している。この履歴表は、4週間分の各曜日の履歴情報(負荷電力、給湯熱量、PV発電力、日射量)を保持しているが、さらに詳細には、各曜日の各時刻の履歴情報を保持している。時刻が0、1、2、・・・とは、0時台、1時台、2時台、・・・を示している。またその時刻における履歴情報は、積算情報となっている。時刻0の負荷電力履歴は、0時台の負荷電力の積算電力量である。
そして、負荷予測手段302は、この蓄積手段301から所望の情報、例えば、1週間前の15~16時の負荷電力量や、2週間前の18~22時の給湯熱量等を取得できるようになっている。PV発電力量及び日射量についても、同様である。
運転計画装置210は、負荷電力量とPV発電力量とを電力分配装置205から取得し、給湯熱量をヒートポンプ式給湯装置200から取得し、日射量を宅外のサーバ209からインターネットを経由して取得する。ここで日射量とは住宅が設置された地区の日射量である。
給湯熱量とは、ヒートポンプ式給湯装置200で消費(放熱)された1時間当たりの熱量を指す。負荷電力量とは、電力負荷206で消費された1時間当たりの電力量を指す。PV発電力量とは、太陽光発電装置で発電された1時間当たりの電力量を指す。日射量とは、サーバ209から現在の需要家への日射量の単位面積当たりの日射量を指す。
また、運転計画装置210は、例えば、毎日0時に、前日の1日間に取得した各情報を1時間単位で積算し、過去4週間分(28日間)の値を蓄積手段301に蓄積している。
(負荷予測手段)
負荷予測手段302は、電力負荷206で消費される1時間毎の負荷電力量の予測値(予測負荷電力量)と、ヒートポンプ式給湯装置200で消費される1時間毎の給湯熱量の予測値(予測給湯熱量)と、太陽光発電装置211で発電される1時間毎のPV発電力量の予測値(予測PV発電力量)とを算出する。
負荷予測手段302は、電力負荷206で消費される1時間毎の負荷電力量の予測値(予測負荷電力量)と、ヒートポンプ式給湯装置200で消費される1時間毎の給湯熱量の予測値(予測給湯熱量)と、太陽光発電装置211で発電される1時間毎のPV発電力量の予測値(予測PV発電力量)とを算出する。
負荷予測手段302は、各時間帯の予測負荷電力量と予測給湯熱量とを、蓄積手段301に保持されている、過去4週間の同じ曜日の同じ時間帯の複数の計測値の平均値に相当すると予測する。たとえば、火曜日、19時~20時の負荷電力量と給湯熱量とを予測する場合、蓄積手段301から過去4週間の火曜日の19時~20時の計測値を取得し、取得した計測値の加算平均を予測値とする。
負荷予測手段302は、予測当日の各時間帯の予測日射量をインターネット経由でサーバ209から取得し、各時間帯の予測PV発電力量を、過去に計測されたPV発電力量のうち、日射量が当日の予測日射量に最も近い時間帯のPV発電力量に相当すると予測する。すなわち、負荷予測手段302は、予測時間帯の日射量と同値又は最も近い値を、蓄積手段301の日射量履歴内で検索する。次に、見つかった時間帯に計測されたPV発電力量をPV発電力履歴から取得する。そして、取得したPV発電力量をその時間帯の予測PV発電力量とする。
負荷予測手段302は、1日に1回、0時に上記の予測処理を実行し、現在時刻から24時間の1時間毎の予測値を算出する。
(運転計画手段)
運転計画手段303は、逆潮電力量が最小となるように、ヒートポンプ式給湯装置200の運転計画を立案し、ヒートポンプ式給湯装置200に対する制御パラメータを算出する。
運転計画手段303は、逆潮電力量が最小となるように、ヒートポンプ式給湯装置200の運転計画を立案し、ヒートポンプ式給湯装置200に対する制御パラメータを算出する。
本実施の形態では、運転計画手段303は、負荷予測手段302から予測負荷電力量と、予測給湯熱量と、予測PV発電力量とを取得する。さらに、ヒートポンプ式給湯装置200に設定されている設定給湯温度(現在の設定温度)をヒートポンプ式給湯装置200から取得する。運転計画手段303は、1日に1回、例えば、0時に運転計画の立案処理を実行する。
まず、運転計画手段303は、各時間帯(0時台、1時台、・・・22時台、23時台)の「予測PV発電力量」から各時間帯の「予測負荷電力量」を減算して、1時間毎の「予測逆潮電力量」を算出する。予測逆潮電力量の下限はゼロである。夕方以降は予測PV発電力量がゼロ(0)となり逆潮が発生しない。そこで、各時間帯の予測逆潮電力量を翌24時から遡って最初にゼロになった時刻、言い換えれば、予測逆潮電力量が正の値から0以下の値に変化した時刻を「逆潮停止時刻」と定義する。
図4を用いて詳しく説明する。図4の横軸は時刻であり、縦軸は電力量を示している。◆は予測負荷電力量であり、□は予測PV発電力量であり、△(図中の黒塗り△印。以下同じ。)は予測逆潮電力量である。予測逆潮電力量(△)は、予測PV発電力量から、予測負荷電力量を減算したものである。各時刻おける各電力量は、その時刻での積算値を示している。例えば12時であれば、12時台(12:00から13:00まで)の電力を積算したものとなっている。
図4からわかるように、逆潮停止時刻は、予測逆潮電力量がゼロとなる17時である。この逆潮停止時刻である17時から翌24時まで(逆潮停止時間帯)の各予測給湯熱量を積算した熱量(逆潮停止中放熱量)を、逆潮停止時刻までに逆潮電力を用いて給湯タンク202に蓄熱しておけば、逆潮停止時刻以降に給湯タンク202の加熱は不要となり、余分な電力の消費をしなくてすむ。予測給湯熱量は、例えば、過去4週間の同じ曜日の17時から24時までの給湯熱量を給湯熱量履歴から取得し、取得した過去の給湯熱量を加算平均することによって算出することができる。
この17時から24時までの積算した予測給湯熱量を、給湯タンク202のタンク容量(例えば200リッター)で除算して算出された温度を、目標蓄熱温度とする。つまり目標蓄熱温度とは、給湯タンク202がこの温度となるように、ヒートポンプ201で生熱を行うための目標温度である。言い換えれば、給湯タンク202がこの温度になればヒートポンプ201での生熱を停止することになる。
給湯タンク202の蓄熱温度には上限値が設定されている場合がある。もし目標蓄熱温度がこの上限値を越えることになれば、目標蓄熱温度は、この上限値を設定温度に置き換えられる。ここでは、給湯タンク202の蓄熱温度の上限値は80℃とする。
逆潮中に給湯タンク202に蓄熱すべき熱量は、目標蓄熱温度と、現在ヒートポンプ式給湯装置200に設定されている温度(設定給湯温度)とから算出できる。以下の式(1)を用いて、逆潮中にヒートポンプ201で生熱され、給湯タンク202に蓄熱される熱量である逆潮中生熱量を算出する。この逆潮中生熱量は、逆潮停止時間帯(17時から24時)に給湯装置203で放熱される逆潮停止中放熱量に相当する。
逆潮中生熱量=(目標蓄熱温度-設定給湯温度)*給湯タンク容量・・・式(1)
次に、運転計画手段303は、以下の式(2)で、ヒートポンプ201で逆潮中生熱量を生熱するために必要な時間である逆潮中生熱時間を算出する。
また、予め記憶されている値である、ヒートポンプ201の平均的な生熱能力であるHP平均能力は9kWとする。また、熱量(kcal)から電力(kW)への換算係数は0.86である。
逆潮中生熱時間=(逆潮中生熱量/0.86/1000)/HP平均能力・・式(2)
次に、運転計画手段303は、図5に示す通り、各時間帯における予測逆潮電力量を算出する。図5は、図4のグラフを表形式に置き換えたものである。各時間帯における予測逆潮電力量は、その時間帯の積算値を示している。例えば、0時であれば、前述したように0:00から1:00までの0時台の予測逆潮電力の積算値である。また、図5の優先順位は、予測逆潮電力量の高い順に付与されている。
次に、運転計画手段303は、ヒートポンプ201を運転する時間帯である運転時間帯と、ヒートポンプ201が実際に生熱を開始するタイミングを決定するための逆潮電力閾値とを決定する。運転時間帯は、予測逆潮電力量が最大となる時間帯を含む。具体的には、運転計画手段303は、逆潮中生熱時間を超えるまで、予測逆潮電力量の大きい順(すなわち、優先順位の高い順)に1以上の時間帯を運転時間帯として選択する。逆潮電力閾値は、上記の運転時間帯における逆潮電力量の最小値に一致する。
例えば、算出した逆潮中生熱時間が0.5時間の場合には、図5の優先順位が一番高くなる時間帯である12時台が運転時間帯となる。また、このときの蓄熱開始逆潮電力は1.68kWとなる。一方、逆潮中生熱時間が3.2時間の場合には、この3.2を繰り上げて4時間分の時間帯を確保する。つまり、優先順位が1から4の時間帯である10時台~13時台が運転時間帯となる。また、このときの蓄熱開始逆潮電力は1.00kWとなる。
そして、運転計画手段303は、上記で決定された目標蓄熱温度、運転時間帯、及び逆潮電力閾値を、制御パラメータとして運転制御手段304に出力する。
(運転制御手段)
運転制御手段304は、運転計画手段303で生成された制御パラメータに基づきヒートポンプ式給湯装置200の運転を制御する。運転制御手段304は、運転計画手段303から逆潮電力閾値と、運転時間帯と、給湯タンク202の目標蓄熱温度とを取得し、電力分配装置205から現在の負荷電力量と現在のPV発電力量とを取得し、ヒートポンプ式給湯装置200から現在の給湯タンク202の温度(給湯タンク温度)を取得する。運転制御手段304は、PV発電力から負荷電力を減算した値である逆潮電力を算出する。これらの処理は、例えば、1分毎に実行される。
運転制御手段304は、運転計画手段303で生成された制御パラメータに基づきヒートポンプ式給湯装置200の運転を制御する。運転制御手段304は、運転計画手段303から逆潮電力閾値と、運転時間帯と、給湯タンク202の目標蓄熱温度とを取得し、電力分配装置205から現在の負荷電力量と現在のPV発電力量とを取得し、ヒートポンプ式給湯装置200から現在の給湯タンク202の温度(給湯タンク温度)を取得する。運転制御手段304は、PV発電力から負荷電力を減算した値である逆潮電力を算出する。これらの処理は、例えば、1分毎に実行される。
運転時間帯であっても、算出した現在の逆潮電力が逆潮電力閾値に達していない場合は、ヒートポンプ201は運転を開始しない。そして、算出した現在の逆潮電力が逆潮電力閾値の値以上となったタイミングで、ヒートポンプ201が運転を開始する。また、運転制御手段304は、1分毎に給湯タンク202の温度を取得しているため、給湯タンク202が、目標蓄熱温度に達したタイミングで、ヒートポンプ201の運転を終了する。
このように運転計画装置210で立案された運転計画に従って逆潮電力量がピークとなる時間帯にヒートポンプ201を運転することにより、その時間帯の逆潮電力を低減(ピークカット)することができる。その結果、電力系統への影響を効果的に低減することができる。また逆潮停止時刻(図4の例では17時)以降に必要と予測される逆潮停止中放熱量を自然エネルギーで賄うことができるので、エネルギー供給業者208から電力を買電する必要がなくなり、省エネにも寄与することができる。
(実施形態1の動作説明)
以下、ヒートポンプ式給湯システムの本実施の形態における動作の一例について説明する。前提として、現在時刻を0時とし、ヒートポンプ式給湯暖房システムは、4週間(28日間)以上運転を行っているとする。設定は、設定給湯温度が「45℃」となっている。また、給湯タンク202内の温度は0時に50℃で均一とする。
以下、ヒートポンプ式給湯システムの本実施の形態における動作の一例について説明する。前提として、現在時刻を0時とし、ヒートポンプ式給湯暖房システムは、4週間(28日間)以上運転を行っているとする。設定は、設定給湯温度が「45℃」となっている。また、給湯タンク202内の温度は0時に50℃で均一とする。
(運転計画装置の0時におけるデータ更新処理)
図6は、運転計画装置210で毎日0時に処理される運転計画処理のフローチャートである。まず、運転計画装置210は、現在時刻が0時となると、1日に1回の「運転計画処理」を開始する(S601)。
図6は、運転計画装置210で毎日0時に処理される運転計画処理のフローチャートである。まず、運転計画装置210は、現在時刻が0時となると、1日に1回の「運転計画処理」を開始する(S601)。
次に、運転計画装置210は、蓄積手段301を更新する(S602)。蓄積手段301には、過去24時間分の負荷電力量、給湯熱量、PV発電力量、日射量の1時間毎の積算値が新たに追加される。
また、過去28日以上運転しているため、蓄積手段301には、過去28日分の1時間単位の負荷電力履歴、給湯熱量履歴、PV発電力履歴、日射量履歴が蓄積されている。そこで、各履歴の最も古い1日分のデータを破棄し、最新の過去24時間分の情報を各履歴に追加することで各履歴情報を更新する。
次に、運転計画装置210は、負荷予測手段302で予測処理を行う(S603)。図7は、負荷予測手段302で処理される予測処理(S603)のフローチャートである。まず、負荷予測手段302は予測処理を開始する(S701)。
次に、負荷予測手段302は、負荷予測に必要なデータを取得する(S702)。負荷予測手段302は、サーバ209から予測日射量を、蓄積手段301に蓄積されている過去28日分の負荷電力履歴、給湯熱量履歴、PV発電力履歴、日射量履歴から必要な情報を取得する。
次に、負荷予測手段302は、1時間毎の予測負荷電力量を算出する(S703)。負荷予測手段302は、前述の通り、予測日当日と同じ曜日で且つ同じ時間帯の4つの負荷電力量を負荷電力履歴から取得し、これらの平均値を予測値として、24時間分の負荷電力量を算出する。
次に、負荷予測手段302は、予測給湯熱量を算出する(S704)。負荷予測手段302は、前述の通り、予測日当日と同じ曜日で且つ同時刻の4つの給湯熱量を給湯熱量履歴から取得し、これらの平均値を予測値として、24時間分の予測給湯熱量を算出する。
次に、負荷予測手段302は、予測PV発電力量を算出する(S705)。負荷予測手段302は、前述の通り、1時間毎の予測日射量と同値又は最も近い値を日射量履歴内で検索する。そして、見つかった時間帯に対応するPV発電力量をPV発電力履歴から取得し、この値をその時間帯における予測値として、24時間分の予測PV発電力量を算出する。
以上の処理により、負荷予測手段302は負荷予測処理(S603)を終了する(S706)。
(運転計画手段)
次に、運転計画装置210は、運転計画手段303で制御パラメータの算出処理を行う(S604)。図8は、運転計画手段303で処理される制御パラメータの算出処理(S604)のフローチャートである。まず、運転計画手段303は、制御パラメータの算出処理を開始する(S801)。
次に、運転計画装置210は、運転計画手段303で制御パラメータの算出処理を行う(S604)。図8は、運転計画手段303で処理される制御パラメータの算出処理(S604)のフローチャートである。まず、運転計画手段303は、制御パラメータの算出処理を開始する(S801)。
次に、運転計画手段303は、制御パラメータに必要なデータを取得する(S802)。運転計画手段303は、ヒートポンプ式給湯装置200から設定給湯温度を取得し、負荷予測手段302から予測負荷電力量、予測給湯熱量、予測PV発電力量を取得する。
次に、運転計画手段303は、逆潮停止時刻を算出する(S803)。運転計画手段303は、前述の通り、各時間帯における予測PV発電力量から予測負荷電力量を減算し、下限を0とした値である予測逆潮電力量を算出する。
図4の例に示すように、夕方以降は予測PV発電力量が0となり逆潮が発生しないため、各時間帯の予測逆潮電力量の値を翌24時から遡り、最初に0になった時刻を逆潮停止時刻とする。例えば、図4の例では逆潮停止時刻は17時である。
次に、運転計画手段303は、目標蓄熱温度を算出する(S804)。運転計画手段303は、前述の通り、逆潮停止時刻から翌24時までの予測給湯熱量を積算した熱量を、給湯タンク202のタンク容量である200Lで除算して算出された温度と、設定給湯温度の上限値である80℃の低い方を目標蓄熱温度とする。
例えば、逆潮停止時刻(17時)から翌24時までの予測給湯熱量を積算した熱量が15000kcalの場合、タンク容量である200Lで除算した温度は75℃であり、設定給湯温度の上限値である80℃より低い値のため、目標蓄熱温度は75℃となる。
次に、運転計画手段303は、逆潮中生熱量を算出する(S805)。運転計画手段303は、ヒートポンプ201で生熱すべき熱量である逆潮中生熱量を算出する。この逆潮中生熱量は、逆潮停止中放熱量に相当する。
例えば、給湯タンク202の目標蓄熱温度が75℃、設定給湯温度45℃の場合には、上記の式(1)を用いて、逆潮中生熱量=6000kcalが算出される。
次に、運転計画手段303は、逆潮中生熱時間を算出する(S806)。運転計画手段303は、前述の通り、上記式(2)を用いて、逆潮中生熱量をヒートポンプ201で生熱するのに必要な時間である逆潮中生熱時間を算出する。例えば、上記で算出された値(6000kcal)に対しては、式(2)を用いて逆潮中HP生熱時間=0.78時間が算出される。
次に、運転計画手段303は、運転時間帯と、逆潮電力閾値とを算出する(S807)。運転計画手段303は、前述の通り、逆潮中生熱時間を超えるまで、予測逆潮電力量の大きい順に1以上の時間帯を運転時間帯として選択する。また、運転時間帯に含まれる1以上の時間帯各々における予測逆潮電力量の最小値を、逆潮電力閾値と決定する。例えば、予測逆潮電力量を高い方の値から並び替えた結果が図5に示す例のような場合において、算出した逆潮中生熱時間が0.78時間の場合には、運転時間帯は12時台となり、逆潮電力閾値は1.68kWとなる。
以上の処理により、運転計画手段303は、制御パラメータの算出処理(S604)を終了し(S808)、運転計画装置210は、運転計画処理を終了する(S605)。
運転計画処理終了後~翌日の0時までの時間帯には、運転計画装置210は、1分毎に運転制御手段304でヒートポンプ式給湯装置200の運転制御処理を行う。
運転制御手段304は、運転計画処理終了後に、運転計画手段303から目標蓄熱温度と、運転時間帯と、逆潮電力閾値とを取得し、1分毎に電力分配装置205から負荷電力と、PV発電力とを、ヒートポンプ式給湯装置200から給湯タンク202の温度を取得する。そして、1分毎の情報取得の度に、運転制御手段304は、PV発電力から負荷電力を減算した値である逆潮電力を算出する。
運転時間帯であっても、算出した現在の逆潮電力が逆潮電力閾値に達していない場合は、ヒートポンプ201運転を開始しない。そして、算出した現在の逆潮電力が逆潮電力閾値以上となったタイミングで、ヒートポンプ201の運転を開始する。運転制御手段304は、1分毎に給湯タンク202の温度を取得しているため、給湯タンク202が、目標蓄熱温度に達した場合に、ヒートポンプ201の運転を終了する。
また、運転計画処理終了後~翌日の0時までの時間帯には、運転計画装置210は、所定の時間毎に蓄積手段301に各種情報を蓄積する処理を行う。蓄積手段301には、ヒートポンプ式給湯装置200から取得した給湯熱量、電力分配装置205から取得した負荷電力量、太陽光発電装置211から取得したPV発電力量、サーバ209から取得した日射量が蓄積される。
毎回取得された各値が1時間毎に積算され、内部で保持している時刻情報の時が変わった場合タイミングで、過去1時間分の積算値が時刻と結びつけて蓄積手段301に蓄積されると共に、積算した値は0にリセットする。
以上の通り、本実施形態では、運転計画装置210は、負荷予測手段302の予測情報を元に、運転計画手段303で、逆潮停止時刻から翌24時までの予測給湯熱量に相当する熱量を逆潮停止時刻に給湯タンク202に蓄熱する。
一方、必ず逆潮電力を使い切るために給湯タンク202の温度を設定の上限値である80℃まで加熱すると、予測給湯熱量の小さい日などは放熱ロスが発生してしまう。一方、本実施形態では、必要な熱量を予測するため、無駄に生熱することなく、省エネ性を損なわない。
以上から、本発明のかかる構成によれば、太陽光発電装置211とヒートポンプ式給湯装置200とを備えるシステムにおいて、省エネ性を損なうことなく、発生する逆潮電力を小さくすることができる。
(実施の形態2:ヒートポンプ式給湯暖房装置)
実施形態1では、ヒートポンプ式給湯システムについて説明したが、この実施形態のシステムは、給湯装置に加えて、暖房機能をもつ暖房装置を搭載したヒートポンプ式給湯暖房システムである。
実施形態1では、ヒートポンプ式給湯システムについて説明したが、この実施形態のシステムは、給湯装置に加えて、暖房機能をもつ暖房装置を搭載したヒートポンプ式給湯暖房システムである。
図9は、発電装置を備えたヒートポンプ式給湯暖房システム9000を説明する構成図である。実施形態2に係るヒートポンプ式給湯暖房システム9000は、図9に示されるように、ヒートポンプ式給湯暖房装置900と、電力分配装置905と、電力負荷906と、運転計画装置910と、太陽光発電装置911とを備える。そして、電力分配装置905は、電力メーター907を介してエネルギー供給業者908に接続され、運転計画装置910は、インターネットを介してサーバ909に接続されている。
この構成は実施形態1と類似しているが、このシステムに係るヒートポンプ式給湯暖房装置900は、給湯装置903に加え、暖房装置904を備えている点が実施形態1と異なる。すなわち、ヒートポンプ式給湯暖房装置900は、ヒートポンプ901と、熱交換器902と、給湯装置903と、暖房装置904とで構成されている。
また簡略化した構成として、図15に示すヒートポンプ式給湯暖房装置900のように、ヒートポンプ901の加熱をいったん給湯タンク901tに全て蓄熱し、給湯タンク901tから給湯負荷に熱を供給するとともに、暖房回路904aを介して暖房負荷に熱を供給するものでもよい。つまり給湯タンク901tが給湯負荷と暖房負荷との両方の熱を賄うようなシステムでも良い。
また、実施の形態2に係るヒートポンプ式給湯暖房システム9000では、図11に示されるように、需要家(ユーザ)が使用するリモコン1101により、給湯と暖房との切り替え等のコントロールができるようになっている。リモコン1101は、図12に示す通り、ヒートポンプ901で生熱された熱を、暖房に用いる「暖房」、給湯に用いる「給湯」、もしくはヒートポンプ901を停止する「停止」の設定をする機能を備えている。ユーザが運転モードをこのいずれかに設定すると、リモコン1101は、設定された運転モードを給湯暖房制御装置1001に出力する。また給湯温度、暖房温度もユーザが設定できるようになっている。運転モードが「暖房」の場合、後述する暖房回路904aに入る水(湯)の温度が、ユーザから設定された設定暖房温度になる。一方、運転モードが「給湯」の場合、後述する給湯タンク903a内の温度が、ユーザから設定された設定給湯温度になる。
図10は、ヒートポンプ式給湯暖房装置900の詳細を説明する構成図である。ヒートポンプ式給湯暖房装置900は、主として、給湯暖房制御装置1001と、ヒートポンプ901と、給湯装置903と、暖房装置904と、三方弁(切替装置)1010とにより構成されている。ヒートポンプ901は、ヒートポンプ部901aと、熱交換器902とにより構成されている。
ヒートポンプ部901aは、図示していないが、外気と低温低圧の液体冷媒との間で熱交換させて低温低圧の蒸気冷媒を生成する蒸発器、低温低圧の蒸気冷媒を高温高圧の蒸気冷媒に圧縮するモーター駆動の圧縮機、高温高圧の蒸気冷媒と循環される水(蓄熱材)との間で熱交換させて低温高圧の液体冷媒を生成する凝縮器、及び低温高圧の蒸気冷媒の圧力を下げて低温低圧の液体冷媒を生成する膨張弁、蒸発器中の冷媒と外気との熱交換を促進させるファン等により構成されている。
給湯タンク903aは、給湯負荷を賄う熱を貯湯する。給湯ヒータ903hは、給湯タンク903a内にあり、給湯タンク903a内の水を加熱する。暖房回路904aは、暖房負荷を賄う暖房設備の湯の流路である。熱交換器902は、ヒートポンプ部901aで加熱された冷媒と、水が充填されている二次側の水サイクルとの間で熱交換を行う。三方弁1010は、熱交換器902により加熱された水を、給湯タンク903aまたは暖房回路904aのいずれかに導くために流路を切り替える装置である。
本実施の形態では、ヒートポンプ901の冷媒は410Aとする。この冷媒の特性により、熱交換器902の水サイクル側の出口の最高温度は55℃となり、設定暖房温度の上限値は55℃とする。
給湯タンク903aは、内部に熱交換コイルを持っている。この熱交換コイルは、図10の給湯タンク903aの点線の部分である。三方弁1010が給湯タンク903aの流路に設定されている場合、熱交換器902で加熱された水が熱交換コイルを通過し、給湯タンク903a内の水を加熱する。熱交換器902の水サイクル側の出口の最高温度が55℃のため、給湯タンク903aの温度が50℃以上の場合には熱交換コイルによる熱交換がほぼ行われなくなる。
このため、給湯タンク202内の水を50℃以上に加熱する場合には、給湯ヒータ903hに通電して加熱する。また、給湯タンク903aの容量は200L、給湯ヒータ903hの加熱能力は3kW、設定給湯温度の上限値は80℃とする。
すなわち、ヒートポンプ部901aは、給湯タンク903a内の水の温度を50℃(第1の温度)前後まで上昇させることができ、給湯ヒータ903hは、給湯タンク903a内の水の温度を50℃より高い温度(第2の温度)まで上昇させることができる。なお、上記の実施の形態では、給湯タンク903aに保持される蓄熱材として水を例に挙げたが、これに限ることなく、蓄熱している熱量に応じて温度が変化するあらゆる蓄熱材を採用することができる。
給湯暖房制御装置1001は、設定された情報に基づき、ヒートポンプ式給湯暖房装置900のシステム全体の制御を行う装置である。図11に示すように、給湯暖房制御装置1001は、リモコン1101および運転計画装置910から運転情報を取得する。
給湯暖房制御装置1001は、リモコン1101から、運転情報として、運転モードと、設定暖房温度と、設定給湯温度とを取得する。また、給湯暖房制御装置1001は、運転計画装置910から、運転情報として、優先運転モードと、優先設定給湯温度とを取得する。優先運転モードは、リモコン1101から取得する運転モードより優先される。同様に、優先設定給湯温度は、リモコン1101から取得する設定給湯温度より優先される。すなわち、給湯暖房制御装置1001は、リモコン1101により運転モードを取得していても、運転計画装置910からの優先運転モードを取得した場合には、運転計画装置910からの優先運転モードを優先させる。
図11に示す通り、給湯暖房制御装置1001は、運転計画装置910に給湯熱量、給湯タンク温度の情報を送る。運転計画装置910は、図3で説明したように、電力分配装置205から負荷電力量、PV発電力量の情報を受ける。またインターネット経由で、日射量情報、予測日射量の情報を受けるように設定されている。
給湯暖房制御装置1001は、運転モードが「暖房」の場合は三方弁1010を暖房回路904aの流路に設定し、運転モードが「給湯」の場合は三方弁1010を給湯タンク903aの流路に設定する。また、運転モードが「停止」の場合は、三方弁1010は変更されない。
また、給湯暖房制御装置1001は、運転モードが「暖房」の場合、ヒートポンプ部901aを運転させ、熱交換器902の出口温度が設定暖房温度と等しくなるよう、ヒートポンプ部901aの圧縮機の回転数、膨張弁の開度等を調整する。
また、給湯タンク903aの温度が、設定給湯温度よりも5度以上低くなった場合(「設定給湯温度-5」℃以下)に、給湯ヒータ903hに通電し、給湯タンク903a内の水の加熱を行い、給湯タンク903aの温度が設定給湯温度以上となった場合に給湯ヒータ903hへの通電を停止する。
また、給湯暖房制御装置1001は、運転モードが「給湯」の場合、給湯タンク903a内の温度が50℃以下、かつ設定給湯温度よりも5度以上低くなった場合(「設定給湯温度-5」℃以下)、三方弁1010を給湯タンク903aの流路に設定し、熱交換器902の出口温度が55℃となるようヒートポンプ901を制御する。これは、前述の通り、給湯タンク903a内の温度が50℃以上の場合には、給湯タンク903aでの熱交換(加熱)がほぼ行われなくなるためである。
また、給湯タンク903a内の温度が50℃以上の場合かつ、設定給湯温度よりも5度以上低くなった場合(「設定給湯温度-5」℃以下)、給湯ヒータ903hに通電し、給湯タンク903a内の水の加熱を行う。給湯タンク903aの温度が設定給湯温度以上となった場合に、給湯ヒータ903hへの通電を停止する。
また、給湯暖房制御装置1001は、運転計画装置910から優先運転モードと優先設定給湯温度とを取得している場合、ユーザがリモコン1101で設定した運転モードと設定給湯温度に優先して、運転計画装置910から取得した、「優先運転モード」を運転モードとし、「優先設定給湯温度」を設定給湯温度として用いて制御を行う。
運転計画装置910については、図3で説明した動作とほぼ同じである。実施形態2のヒートポンプ式給湯暖房システム9000は、実施形態1と異なり、図10で示すように、熱交換器902で熱交換を行った後、三方弁1010により給湯タンク903aと暖房回路904aとに流路を切り替えるようになっている。また、熱交換器902では50℃程度までしか加熱できないため、それ以上の温度に加熱する場合は、給湯タンク903a内の給湯ヒータ903hを用いる。
すなわち、運転計画装置910は、逆潮停止中放熱量に相当する熱量のうち、給湯タンク903a内の水が50℃に達するまでの熱量をヒートポンプ部901aに生成させ、給湯タンク903a内の水が50℃に達した後の熱量を給湯ヒータ903hに生成させるように、運転計画を立案する。このため逆潮中に必要な熱量の算出方法は以下の通りとなる。
(1)設定給湯温度(現在の給湯タンク903aの設定温度)が50℃未満の場合
運転計画手段303は、設定給湯温度が50℃未満の場合、以下の式(3)で逆潮中にヒートポンプ901で生熱される熱量である「逆潮中HP生熱量」を算出し、以下の式(4)で逆潮中に給湯ヒータ903hで生熱される熱量である「逆潮中ヒータ生熱量」を算出する。
運転計画手段303は、設定給湯温度が50℃未満の場合、以下の式(3)で逆潮中にヒートポンプ901で生熱される熱量である「逆潮中HP生熱量」を算出し、以下の式(4)で逆潮中に給湯ヒータ903hで生熱される熱量である「逆潮中ヒータ生熱量」を算出する。
逆潮中HP生熱量=(50-設定給湯温度)*給湯タンク容量 ・・・式(3)
逆潮中ヒータ生熱量=(目標蓄熱温度-50)*給湯タンク容量 ・・式(4)
逆潮中ヒータ生熱量=(目標蓄熱温度-50)*給湯タンク容量 ・・式(4)
(2)設定給湯温度(現在の給湯タンク903aの設定温度)が50℃以上の場合
運転計画装置910は、設定給湯温度が50℃以上の場合、以下の式(5)で給湯ヒータ903hで生熱される熱量である逆潮中ヒータ生熱量を算出する。
運転計画装置910は、設定給湯温度が50℃以上の場合、以下の式(5)で給湯ヒータ903hで生熱される熱量である逆潮中ヒータ生熱量を算出する。
逆潮中ヒータ生熱量=(目標蓄熱温度-設定給湯温度)*給湯タンク容量・・式(5)
次に、運転計画手段303は、以下の式(6)で、逆潮中HP生熱量をヒートポンプ901で生熱するのに必要な時間である「逆潮中HP生熱時間t(HP)」を算出し、以下の式(7)で逆潮中ヒータ生熱量を給湯ヒータ903hで生熱するのに必要な時間である「逆潮中ヒータ生熱時間t(HT)」を算出する。
なお、予め記憶されている値である、ヒートポンプ901の平均的な生熱能力であるHP平均能力は9kWとする。また、給湯ヒータ903hの平均的な生熱能力であるヒータ加熱能力は3kWとする。熱量(kcal)から電力(kW)への換算係数は0.86である。
t(HP)=(逆潮中HP生熱量/0.86/1000)/HP平均能力・・式(6)
t(HT)=(逆潮中ヒータ生熱量/0.86/1000)/ヒータ加熱能力・式(7)
t(HP)=(逆潮中HP生熱量/0.86/1000)/HP平均能力・・式(6)
t(HT)=(逆潮中ヒータ生熱量/0.86/1000)/ヒータ加熱能力・式(7)
次に、運転計画手段303は、逆潮中HP生熱時間と逆潮中ヒータ生熱時間を和算した値(t(HP)+t(HT))を逆潮中生熱時間として算出する。算出した逆潮中生熱時間から、運転計画手段303がヒートポンプ901の運転計画を立案する。また、給湯ヒータ903hの加熱はヒートポンプ901の運転に引き続いて行うが、給湯ヒータ903hの運転も逆潮停止時刻前に終了するように、運転計画が立案される。
(1)逆潮電力が逆潮電力閾値未満の場合
優先運転モード、優先設定給湯温度共に「なし」を算出する。この場合、リモコン1101からの設定でヒートポンプ式給湯暖房システム9000は運転される。
優先運転モード、優先設定給湯温度共に「なし」を算出する。この場合、リモコン1101からの設定でヒートポンプ式給湯暖房システム9000は運転される。
(2)逆潮電力が逆潮電力閾値以上の場合
(i)給湯タンク温度が50℃未満の場合
優先運転モードとして「給湯」を、優先設定給湯温度として「目標蓄熱温度」を算出する。この場合、ヒートポンプ901のみで生熱可能な温度のため、ヒートポンプ式給湯暖房装置900は、運転モードを「給湯」とし、ヒートポンプ901を用いて給湯タンク903a内の水の加熱を行う。
(i)給湯タンク温度が50℃未満の場合
優先運転モードとして「給湯」を、優先設定給湯温度として「目標蓄熱温度」を算出する。この場合、ヒートポンプ901のみで生熱可能な温度のため、ヒートポンプ式給湯暖房装置900は、運転モードを「給湯」とし、ヒートポンプ901を用いて給湯タンク903a内の水の加熱を行う。
(ii)給湯タンク温度が50℃以上の場合
優先運転モードとして「なし」を、優先設定給湯温度として「目標蓄熱温度」を算出する。この場合、ヒートポンプ901で生熱可能な温度(50℃)を超えているため、ヒートポンプ式給湯暖房装置900は、運転モードをリモコン1101のまま変更せず、給湯ヒータ903hを用いて給湯タンク903a内の水の加熱を行う。ユーザのリモコン設定が、「暖房」になっていても「給湯」になっていても、いずれにしても給湯タンク903a内の水は、給湯ヒータ903hを用いて加熱するしかない。
優先運転モードとして「なし」を、優先設定給湯温度として「目標蓄熱温度」を算出する。この場合、ヒートポンプ901で生熱可能な温度(50℃)を超えているため、ヒートポンプ式給湯暖房装置900は、運転モードをリモコン1101のまま変更せず、給湯ヒータ903hを用いて給湯タンク903a内の水の加熱を行う。ユーザのリモコン設定が、「暖房」になっていても「給湯」になっていても、いずれにしても給湯タンク903a内の水は、給湯ヒータ903hを用いて加熱するしかない。
(具体例)
以下、実施の形態2に係るヒートポンプ式給湯暖房システム9000の動作について説明する。前提として、現在時刻を0時とし、ヒートポンプ式給湯暖房システム9000は、28日間以上運転を行っているとする。また、リモコン1101の設定は、運転モード情報が「暖房」、設定暖房温度が「50℃」、設定給湯温度が「45℃」となっているとする。また、給湯タンク903a内の温度は0時に50℃で均一とする。
以下、実施の形態2に係るヒートポンプ式給湯暖房システム9000の動作について説明する。前提として、現在時刻を0時とし、ヒートポンプ式給湯暖房システム9000は、28日間以上運転を行っているとする。また、リモコン1101の設定は、運転モード情報が「暖房」、設定暖房温度が「50℃」、設定給湯温度が「45℃」となっているとする。また、給湯タンク903a内の温度は0時に50℃で均一とする。
まず、運転計画手段303は、設定給湯温度が50℃未満の場合、式(3)を用いてヒートポンプ901で生熱される熱量である逆潮中HP生熱量と、式(4)を用いて給湯ヒータ903hで生熱される熱量である逆潮中ヒータ生熱量とを算出する。
例えば、目標蓄熱温度が75℃、設定給湯温度が45℃の場合には、設定給湯温度が50℃未満のため、式(3)と式(4)とを用いて、逆潮中HP生熱量が1000[kcal]、逆潮中ヒータ生熱量が5000[kcal]と算出される。式(3)及び式(4)において、貯湯タンク容量は200リッターとしている。
次に、運転計画手段303は、逆潮中加熱時間を算出する。運転計画手段303は、前述の通り、式(6)で、逆潮中HP生熱量をヒートポンプ901で生熱するのに必要な時間である逆潮中HP生熱時間を算出し、式(7)で逆潮中ヒータ生熱量を給湯ヒータ903hで生熱するのに必要な時間である逆潮中ヒータ生熱時間を算出する。
例えば、上記のように算出された逆潮中HP生熱量及び逆潮中ヒータ生熱量に対しては、逆潮中HP生熱時間t(HP)=0.13[hr]、逆潮中ヒータ生熱時間t(HT)=1.94[hr]が算出される。
次に、運転計画手段303は、逆潮中HP生熱時間と逆潮中ヒータ生熱時間とを和算した値(t(HP)+t(HT))を逆潮中加熱時間として算出する。例えば、上記のように算出されたt(HP)及びt(HT)に対しては、逆潮中加熱時間として2.07[hr]が算出される。
この場合、図5の優先順位1~3である11時台~13時台を運転時間帯に設定する。そして、選択された運転時間帯における逆潮電力量の最小値である1.38[kW]を逆潮電力閾値とする。
次に、実施の形態2に係るヒートポンプ式給湯暖房装置900の動作を説明する。図16は、ヒートポンプ式給湯暖房装置900の動作を示すフローチャートである。
まず、給湯暖房制御装置1001は、逆潮電力をモニターし、逆潮電力が逆潮電力閾値以上となるタイミング(S1601)で、ヒートポンプ式給湯暖房装置900の運転を開始する。その際、給湯タンク温度(給湯タンク903aの現在の温度)が50℃以上であれば(S1602)、給湯ヒータ903hにより生熱させ(S1603)、給湯タンク903a内の水が目標蓄熱温度に達すると(S1604)、給湯ヒータ903hによる生熱を終了させる(S1605)。
一方、給湯タンク温度が50℃未満であれば(S1602)、まずヒートポンプ部901aに生熱させる。このとき、目標蓄熱温度が50℃未満であれば(S1606)、ヒートポンプ部901aのみに生熱させる(S1609)。そして、給湯タンク903a内の水が目標蓄熱温度に達したときに(S1610)、ヒートポンプ部901aによる生熱を終了させる(S1611)。
一方、目標蓄熱温度が50℃以上であれば(S1606)、給湯タンク903a内の水が50℃に達するまでヒートポンプ部901aに生熱させる(S1607)。さらに、給湯タンク903a内の水が上限温度である50℃に達した後(S1608)から、目標蓄熱温度に達するまで給湯ヒータ903hに生熱させ(S1603)、給湯タンク903a内の水が目標蓄熱温度に達すると(S1604)、給湯ヒータ903hによる生熱を終了させる(S1605)。
以下、実施の形態2に係るヒートポンプ式給湯暖房システム9000の効果について説明する。
本実施の形態に係る運転計画装置910は、予測日当日の各時間帯における負荷電力量、給湯熱量、PV発電力量を予測し、その予測情報を元に、逆潮電力を利用して給湯タンク202の加熱を行うような運転計画を立案する。このとき、逆潮電力量の大きい時間帯から順番に運転時間帯として選択し、選択された各時間帯における逆潮電力量の最小値を逆潮電力閾値とする。
例えば上記の通り、逆潮中生熱時間として2.07[hr]となる場合、図5に示す通り、11時台は1.44[kW]、12時台は1.68[kW]、13時台は1.38[kW]となるため、この11時台~13時台が運転時間帯となる場合の逆潮電力閾値は、この3つの中で一番小さい値である1.38[kW]に設定される。
そして、運転計画装置910は、上記のように決定された制御パラメータは、リモコン1101よる設定情報に優先して、ヒートポンプ式給湯暖房装置900の制御に用いられる。
これにより、ヒートポンプ式給湯暖房装置900で給湯タンク903a内の水を加熱する場合でも、最もエネルギー供給業者908への逆潮電力が少なくなるような運転を行うことができる。
仮に、負荷予測手段302を用いなかった場合の給湯タンク903a内の水の加熱に要する消費電力の比較を図13に示す。
図13の運転1は、ユーザからリモコン1101経由で設定された情報に従い、給湯タンク903a内の水の温度が「設定給湯温度-5」℃未満になった場合に加熱し、給湯タンク903a内の水の温度が設定給湯温度以上となった場合に加熱を停止する運転の結果である。この場合、需要家の給湯熱量にのみ依存して運転を行うため、逆潮電力を全く使用することができない。
図13の運転2は、運転計画装置910に負荷予測手段を設けず、逆潮電力閾値が0より大、つまり、逆潮電力の発生を検知した場合に給湯タンク903aを加熱した運転の結果である。このように、逆潮電力が小さい場合でも加熱を行うと、逆潮電力に対して消費電力が大きくなる時間帯が発生するため、逆潮電力を有効に消費できていない。また、逆に逆潮電力閾値に大きい値に設定すると、逆潮電力が少ない日などに給湯タンク903aの加熱が行われなくなる可能性がある。
図13の本発明の運転では、負荷予測手段の予測結果を用いて運転計画を行うことで、運転1と運転2との問題を解決し、逆潮電力が最小となる運転となっていることが分かる。
以上から、本発明のかかる構成によれば、太陽光発電装置911を備えたヒートポンプ式給湯暖房システム9000により、省エネ性を損なうことなく、発生する逆潮電力を小さくすることができる。
(他の構成)
以上、本発明の発電装置を備えたヒートポンプ式給湯システム、およびヒートポンプ式給湯暖房システムの実施形態について説明したが、以下の形態であってもよい。
以上、本発明の発電装置を備えたヒートポンプ式給湯システム、およびヒートポンプ式給湯暖房システムの実施形態について説明したが、以下の形態であってもよい。
発電装置には、太陽光発電装置を例にして説明したが、複数の太陽光発電装置を組合せた発電装置としてもよい。
また、運転計画装置は、給湯暖房装置の外部にあり、ゲートウェイの位置付けを兼ねているが、給湯暖房装置の内部や、電力分配装置の内部に設置していてもよい。また運転計画装置の運転計画の機能を、給湯装置や電力分配装置に持たせてもよい。
また、運転計画手段で、逆潮電力閾値を算出し、逆潮電力の大きさによって運転制御手段で制御を行っているが、逆潮電力を最小化するよう算出された所定の時間帯にタイマー設定して、例えば11時から13時の間に給湯暖房装置を運転するようにしても良い。
また、運転計画装置は1日に1回、0時に運転計画処理を行っているが、1日に複数回でも、0時でなくても午前2時や6時など任意の時刻でも良い。この場合、逆潮停止時間帯の終期(実施例では24時とした)も同じように変更する。すなわち、逆潮停止時間帯は、逆潮停止時刻(実施例は17時)から、放熱部(給湯装置)からの放熱(給湯)が停止すると考えられる予め定められた時刻までの間の時間帯であり、運転計画装置は、逆潮停止時間帯の終了後に、次の1日分の運転計画を立案すればよい。
また、運転計画装置の処理で用いている負荷情報、予測情報の単位時間として1時間単位を用いているが、15分単位や1分単位など任意の単位の情報でも良い。
また、負荷予測手段を用いた予測に過去の同曜日、同時刻の平均値を用いているが、ニューラルネットを用いて予測するなどの手法を用いて良い。
(その他変形例)
なお、本発明を上記実施の形態に基づいて説明してきたが、本発明は、上記の実施の形態に限定されないのはもちろんである。以下のような場合も本発明に含まれる。
なお、本発明を上記実施の形態に基づいて説明してきたが、本発明は、上記の実施の形態に限定されないのはもちろんである。以下のような場合も本発明に含まれる。
上記の各装置は、具体的には、マイクロプロセッサ、ROM、RAM、ハードディスクユニット、ディスプレイユニット、キーボード、マウスなどから構成されるコンピュータシステムである。RAMまたはハードディスクユニットには、コンピュータプログラムが記憶されている。マイクロプロセッサが、コンピュータプログラムにしたがって動作することにより、各装置は、その機能を達成する。ここでコンピュータプログラムは、所定の機能を達成するために、コンピュータに対する指令を示す命令コードが複数個組み合わされて構成されたものである。
上記の各装置を構成する構成要素の一部または全部は、1個のシステムLSI(Large Scale Integration:大規模集積回路)から構成されているとしてもよい。システムLSIは、複数の構成要素を1個のチップ上に集積して製造された超多機能LSIであり、具体的には、マイクロプロセッサ、ROM、RAMなどを含んで構成されるコンピュータシステムである。RAMには、コンピュータプログラムが記憶さている。マイクロプロセッサが、コンピュータプログラムにしたがって動作することにより、システムLSIは、その機能を達成する。
上記の各装置を構成する構成要素の一部または全部は、各装置に脱着可能なICカードまたは単体のモジュールから構成されているとしてもよい。ICカードまたはモジュールは、マイクロプロセッサ、ROM、RAMなどから構成されるコンピュータシステムである。ICカードまたはモジュールは、上記の超多機能LSIを含むとしてもよい。マイクロプロセッサが、コンピュータプログラムにしたがって動作することにより、ICカードまたはモジュールは、その機能を達成する。このICカードまたはこのモジュールは、耐タンパ性を有するとしてもよい。
本発明は、上記に示す方法であるとしてもよい。また、これらの方法をコンピュータにより実現するコンピュータプログラムであるとしてもよいし、コンピュータプログラムからなるデジタル信号であるとしてもよい。
また、本発明は、コンピュータプログラムまたはデジタル信号をコンピュータ読み取り可能な記録媒体、例えば、フレキシブルディスク、ハードディスク、CD-ROM、MO、DVD、DVD-ROM、DVD-RAM、BD(Blu-ray Disc)、半導体メモリなどに記録したものとしてもよい。また、これらの記録媒体に記録されているデジタル信号であるとしてもよい。
また、本発明は、コンピュータプログラムまたはデジタル信号を、電気通信回線、無線または有線通信回線、インターネットを代表とするネットワーク、データ放送等を経由して伝送するものとしてもよい。
また、本発明は、マイクロプロセッサとメモリを備えたコンピュータシステムであって、メモリは、上記コンピュータプログラムを記憶しており、マイクロプロセッサは、コンピュータプログラムにしたがって動作するとしてもよい。
また、プログラムまたはデジタル信号を記録媒体に記録して移送することにより、またはプログラムまたはデジタル信号をネットワーク等を経由して移送することにより、独立した他のコンピュータシステムにより実施してもよい。
上記実施の形態及び上記変形例をそれぞれ組み合わせてもよい。
以上、図面を参照してこの発明の実施形態を説明したが、この発明は、図示した実施形態のものに限定されない。図示した実施形態に対して、この発明と同一の範囲内において、あるいは均等の範囲内において、種々の修正や変形を加えることが可能である。
本発明にかかる運転計画装置は、給湯システム又は給湯暖房システム等の運転に際して、電力系統の安定化に寄与する装置として有用である。
200 ヒートポンプ式給湯装置
201,901 ヒートポンプ
202,901t,903a 給湯タンク
203,903 給湯装置
205,905 電力分配装置
206,906 電力負荷
207,907 電力メーター
208,908 エネルギー供給業者
209,909 サーバ
210,910 運転計画装置
211,911 太陽光発電装置
301 蓄積手段
302 負荷予測手段
303 運転計画手段
304 運転制御手段
900 ヒートポンプ式給湯暖房装置
901a ヒートポンプ部
902 熱交換器
903h 給湯ヒータ
904 暖房装置
904a 暖房回路
1001 給湯暖房制御装置
1010 三方弁
1101 リモコン
2000 ヒートポンプ式給湯システム
9000 ヒートポンプ式給湯暖房システム
201,901 ヒートポンプ
202,901t,903a 給湯タンク
203,903 給湯装置
205,905 電力分配装置
206,906 電力負荷
207,907 電力メーター
208,908 エネルギー供給業者
209,909 サーバ
210,910 運転計画装置
211,911 太陽光発電装置
301 蓄積手段
302 負荷予測手段
303 運転計画手段
304 運転制御手段
900 ヒートポンプ式給湯暖房装置
901a ヒートポンプ部
902 熱交換器
903h 給湯ヒータ
904 暖房装置
904a 暖房回路
1001 給湯暖房制御装置
1010 三方弁
1101 リモコン
2000 ヒートポンプ式給湯システム
9000 ヒートポンプ式給湯暖房システム
Claims (22)
- 発電装置と、前記発電装置で発電された電力を用いて動作する第1の電力負荷と、前記発電装置で発電された電力を用いて熱を生成する第2の電力負荷とを備えるシステムにおいて、前記第2の電力負荷の運転計画を立案する運転計画方法であって、
単位時間に区切られた各時間帯において、前記発電装置で発電される発電電力量と、前記第1の電力負荷で消費される消費電力量とを予測する予測ステップと、
前記発電電力量から前記消費電力量を減算して得られる逆潮電力量が最も多くなる時間帯を含む運転時間帯に前記第2の電力負荷を動作させるように、前記第2の電力負荷の運転計画を立案する運転計画ステップとを含む
運転計画方法。 - 前記発電装置は、太陽光発電装置であり、
前記第2の電力負荷は、前記発電装置で発電される電力を用いて熱を生成する生熱部と、前記生熱部で生成された熱を蓄熱する蓄熱部と、前記蓄熱部に蓄熱されている熱を放熱する放熱部とを備え、
前記予測ステップでは、さらに、前記消費電力量が前記発電電力量を上回る時間帯である逆潮停止時間帯に前記放熱部で放熱される逆潮停止中放熱量を予測し、
前記運転計画ステップでは、前記予測部で予測された逆潮停止中放熱量に相当する熱量が前記蓄熱部に蓄熱されるように、前記運転時間帯における前記生熱部の運転計画を立案する
請求項1に記載の運転計画方法。 - 前記運転計画ステップでは、前記逆潮停止中放熱量に相当する熱量を前記生熱部が生成するのに必要な時間を超えるまで、前記逆潮電力量の大きい順に1以上の前記時間帯を選択することによって前記運転時間帯を決定し、決定した前記運転時間帯における前記運転計画を立案する
請求項2に記載の運転計画方法。 - 前記運転計画ステップでは、
選択された前記1以上の時間帯各々における前記逆潮電力量のうちの最小値を、逆潮電力閾値として決定し、
前記運転時間帯において、実際に計測された逆潮電力が前記逆潮電力閾値以上になったタイミングで前記生熱部の運転を開始するように、前記運転計画を立案する
請求項3に記載の運転計画方法。 - 前記運転計画ステップでは、さらに、前記運転時間帯において、前記逆潮停止中放熱量に相当する熱量が生成されたタイミングで前記生熱部の運転を停止するように、前記運転計画を立案する
請求項4に記載の運転計画方法。 - 前記蓄熱部は、蓄熱している熱量に応じて温度が変化する蓄熱材を備え、
前記生熱部は、前記蓄熱材の温度を第1の温度まで上昇させることのできるヒートポンプと、前記蓄熱材の温度を前記第1の温度より高い温度まで上昇させることのできるヒータとを備え、
前記運転計画ステップでは、前記逆潮停止中放熱量に相当する熱量のうち、前記蓄熱材が前記第1の温度に達するまでの熱量を前記ヒートポンプに生成させ、前記蓄熱材が前記第1の温度に達した後の熱量を前記ヒータに生成させるように、前記運転計画を立案する
請求項2~5のいずれか1項に記載の運転計画方法。 - 前記予測ステップでは、前記逆潮電力量が正の値から0以下の値に変化した時刻である逆潮停止時刻から、前記放熱部からの放熱が停止すると考えられる予め定められた時刻までの間の時間帯である前記逆潮停止時間帯に前記放熱部で放熱される熱量を、前記逆潮停止中放熱量として予測する
請求項2~6のいずれか1項に記載の運転計画方法。 - 前記予測ステップでは、
各時間帯の前記消費電力量を、同じ曜日で且つ同じ時間帯に計測された過去の複数の消費電力量の平均値に相当すると予測し、
各時間帯の前記逆潮停止中放熱量を、同じ曜日で且つ同じ時間帯に計測された過去の複数の逆潮停止中放熱量の平均値に相当すると予測する
請求項2~7のいずれか1項に記載の運転計画方法。 - 前記予測ステップでは、予測当日の各時間帯の予測日射量を取得し、各時間帯の前記発電電力量を、過去に計測された発電電力量のうち、日射量が当日の予測日射量に最も近い時間帯の発電電力量に相当すると予測する
請求項1~8のいずれか1項に記載の運転計画方法。 - 発電装置と、前記発電装置で発電された電力を用いて動作する第1の電力負荷と、前記発電装置で発電された電力を用いて熱を生成する第2の電力負荷とを備えるシステムにおいて、前記第2の電力負荷の運転計画を立案する運転計画装置であって、
単位時間に区切られた各時間帯において、前記発電装置で発電される発電電力量と、前記第1の電力負荷で消費される消費電力量とを予測する予測部と、
前記発電電力量から前記消費電力量を減算して得られる逆潮電力量が最も多くなる時間帯を含む運転時間帯に前記第2の電力負荷を動作させるように、前記第2の電力負荷の運転計画を立案する運転計画部とを備える
運転計画装置。 - 太陽光発電装置と、ヒートポンプ式給湯装置とを備えたヒートポンプ式給湯システムの運転方法であって、
前記システムは運転計画装置をさらに備え、
前記運転計画装置は、
前記発電装置で発電される発電電力量と、電力負荷で消費される消費電力量とを予測する予測ステップと、
前記発電電力量から前記消費電力量を減算して得られる逆潮電力量を算出するステップと、
前記逆潮電力量がゼロとなる逆潮停止時間帯に必要な熱量を予測するステップと、
前記逆潮電力量が最も多くなる時間帯を含む運転時間帯に、前記予測した熱量を蓄熱するように、前記ヒートポンプ式給湯装置を動作させる計画を立案する運転計画ステップと、を含む制御をする、
ヒートポンプ式給湯システムの運転方法。 - 前記運転計画ステップは、
予測した熱量を蓄熱するための目標蓄熱温度と、選択された前記1以上の時間帯各々における前記逆潮電力量のうちの最小値を、逆潮電力閾値として決定する、
請求項11に記載のヒートポンプ式給湯システムの運転方法。 - 前記運転計画ステップで決定された前記目標蓄熱温度と、前記逆潮電力閾値とを受けて、
前記運転時間帯において、実際に計測された逆潮電力が前記逆潮電力閾値以上になったタイミングで前記ヒートポンプ式給湯装置の運転を開始し、
前記運転時間帯において、前記予測した熱量が生成されたタイミングで前記ヒートポンプ式給湯装置の運転を停止する、
運転制御ステップをさらに備えた、
請求項12に記載のヒートポンプ式給湯システムの運転方法。 - 前記発電電力量の予測、前記消費電力量の予測、及び前記熱量の予測は、蓄積手段に蓄積された履歴情報を用いて行う、
請求項13に記載のヒートポンプ式給湯システムの運転方法。 - 前記運転計画装置は、ヒートポンプ式給湯装置の内部に設置されている、
請求項14に記載のヒートポンプ式給湯システムの運転方法。 - 太陽光発電装置と、ヒートポンプ式給湯暖房装置とを備えたヒートポンプ式給湯暖房システムの運転方法であって、
前記ヒートポンプ式給湯暖房装置は、給湯タンクと暖房装置とを備え、
前記システムは運転計画装置を備え、
前記運転計画装置は、
前記発電装置で発電される発電電力量と、電力負荷で消費される消費電力量とを予測する予測ステップと、
前記発電電力量から前記消費電力量を減算して得られる逆潮電力量を算出するステップと、
前記逆潮電力量がゼロとなる逆潮停止時間帯に必要な熱量を予測するステップと、
前記逆潮電力量が最も多くなる時間帯を含む運転時間帯に、前記予測した熱量を蓄熱するように、前記ヒートポンプ式給湯暖房装置を動作させる計画を立案する運転計画ステップと、を含む制御をする、
ヒートポンプ式給湯暖房システムの運転方法。 - 前記運転計画ステップは、
予測した熱量を蓄熱するための目標蓄熱温度と、選択された前記1以上の時間帯各々における前記逆潮電力量のうちの最小値を、逆潮電力閾値として決定する、
請求項16に記載のヒートポンプ式給湯暖房システムの運転方法。 - 前記運転計画ステップで決定された前記目標蓄熱温度と、前記逆潮電力閾値とを受けて、
前記運転時間帯において、実際に計測された逆潮電力が前記逆潮電力閾値以上になったタイミングで前記ヒートポンプ式給湯装置の運転を開始し、
前記運転時間帯において、前記予測した熱量が生成されたタイミングで前記ヒートポンプ式給湯装置の運転を停止する運転制御ステップをさらに備えた、
請求項17に記載のヒートポンプ式給湯暖房システムの運転方法。 - 前記運転計画ステップは、予測した熱量を給湯タンクに蓄熱するための目標蓄熱温度を決定し、
前記ヒートポンプ式給湯暖房装置のヒートポンプにより第1の温度まで前記給湯タンク内の蓄熱材を加熱し、その後、前記給湯タンク内に設置されたヒータにより第1の温度よりも高い第2の温度まで前記蓄熱材を加熱するよう制御する、
請求項18に記載のヒートポンプ式給湯暖房システムの運転方法。 - 前記ヒートポンプ式給湯暖房装置は、給湯暖房制御装置を備え、
前記給湯暖房制御装置は、
前記運転計画装置から前記ヒートポンプ式給湯暖房装置の運転情報を受けるとともに、リモコンから前記ヒートポンプ式給湯暖房装置の運転情報を受けるように設定されており、
前記運転計画装置からの前記運転情報を取得した場合には、前記リモコンからの前記運転情報に優先して、前記運転計画装置からの前記運転情報に基づいて前記ヒートポンプ式給湯暖房装置を制御する、
請求項18に記載のヒートポンプ式給湯暖房システムの運転方法。 - 前記運転情報は、前記ヒートポンプ式給湯暖房装置の運転モード及び給湯タンクの設定給湯温度である、
請求項20に記載のヒートポンプ式給湯暖房システムの運転方法。 - 前記ヒートポンプ式給湯暖房装置は熱交換器を備え、
熱交換器から供給される蓄熱材は、切替装置により、給湯タンクまたは暖房装置へ供給されるように制御される、
請求項18に記載のヒートポンプ式給湯暖房システムの運転方法。
Priority Applications (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP11839783.5A EP2639922B1 (en) | 2010-11-10 | 2011-10-18 | Operation planning method and operation planning device |
US13/511,289 US8972073B2 (en) | 2010-11-10 | 2011-10-18 | Operation planning method, operation planning device, heat pump hot water supply system operation method, and heat pump hot water supply and heating system operation method |
JP2012507526A JP5025834B2 (ja) | 2010-11-10 | 2011-10-18 | 運転計画方法、運転計画装置、ヒートポンプ式給湯システムの運転方法、及びヒートポンプ式給湯暖房システムの運転方法 |
CN2011800050467A CN102668302A (zh) | 2010-11-10 | 2011-10-18 | 运转计划方法、运转计划装置、热泵式热水供给系统的运转方法、以及热泵式热水供给供暖系统的运转方法 |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2010-252341 | 2010-11-10 | ||
JP2010252341 | 2010-11-10 |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2012063409A1 true WO2012063409A1 (ja) | 2012-05-18 |
Family
ID=46050581
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/JP2011/005824 WO2012063409A1 (ja) | 2010-11-10 | 2011-10-18 | 運転計画方法、運転計画装置、ヒートポンプ式給湯システムの運転方法、及びヒートポンプ式給湯暖房システムの運転方法 |
Country Status (5)
Country | Link |
---|---|
US (1) | US8972073B2 (ja) |
EP (1) | EP2639922B1 (ja) |
JP (1) | JP5025834B2 (ja) |
CN (1) | CN102668302A (ja) |
WO (1) | WO2012063409A1 (ja) |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013245839A (ja) * | 2012-05-23 | 2013-12-09 | Mitsubishi Electric Corp | 電気給湯装置 |
JP2014078127A (ja) * | 2012-10-10 | 2014-05-01 | Sharp Corp | 情報処理装置、情報処理方法及びプログラム |
JP2014078137A (ja) * | 2012-10-10 | 2014-05-01 | Sharp Corp | 情報処理装置、情報処理方法及びプログラム |
JP2014214978A (ja) * | 2013-04-25 | 2014-11-17 | パナソニック株式会社 | ヒートポンプシステム制御装置、ヒートポンプシステム、および、ヒートポンプシステム制御方法 |
JP5823085B1 (ja) * | 2015-01-27 | 2015-11-25 | 三菱電機株式会社 | 給湯機運転管理装置、給湯機運転管理システムおよび給湯機運転管理方法 |
JP2017005851A (ja) * | 2015-06-09 | 2017-01-05 | 東京電力ホールディングス株式会社 | 電力制御方法および電力制御システム |
WO2017090110A1 (ja) * | 2015-11-25 | 2017-06-01 | 三菱電機株式会社 | 給湯器制御システム、制御方法及びプログラム |
WO2017145369A1 (ja) * | 2016-02-26 | 2017-08-31 | 三菱電機株式会社 | 給湯システム及び給湯機の制御方法 |
US20170276406A1 (en) * | 2014-08-27 | 2017-09-28 | Alpiq Intec Ag | Method to heat water in an electrical boiler, corresponding device and electrical boiler |
JP2020170363A (ja) * | 2019-04-03 | 2020-10-15 | 東京瓦斯株式会社 | 需要調整システム、需要調整方法及びプログラム |
EP4113028A4 (en) * | 2020-05-19 | 2023-08-16 | Mitsubishi Heavy Industries Thermal Systems, Ltd. | SYSTEM FOR CREATING A HOT WATER TANK PLAN, METHOD FOR CREATING A HOT WATER TANK PLAN AND PROGRAM |
JP7493444B2 (ja) | 2020-12-22 | 2024-05-31 | 三菱電機株式会社 | 需給管理装置および需給管理プログラム |
Families Citing this family (44)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8204633B2 (en) * | 2008-07-01 | 2012-06-19 | Carina Technology, Inc. | Water heater demand side management system |
CN102668302A (zh) * | 2010-11-10 | 2012-09-12 | 松下电器产业株式会社 | 运转计划方法、运转计划装置、热泵式热水供给系统的运转方法、以及热泵式热水供给供暖系统的运转方法 |
CN102687364A (zh) * | 2010-12-27 | 2012-09-19 | 松下电器产业株式会社 | 运转计划方法以及热泵式热水供给供暖系统的运转方法 |
US9494373B2 (en) | 2011-06-06 | 2016-11-15 | Panasonic Intellectual Property Management Co., Ltd. | Heat pump operation method and heat pump system |
CN102933914A (zh) | 2011-06-06 | 2013-02-13 | 松下电器产业株式会社 | 热泵的运转方法及热泵系统 |
EP2719971B1 (en) | 2011-06-06 | 2017-02-01 | Panasonic Intellectual Property Management Co., Ltd. | Operating method for heat pump, and heat pump system |
JP6024758B2 (ja) * | 2012-10-01 | 2016-11-16 | 富士通株式会社 | 配電管理装置、パターン抽出方法及びパターン抽出プログラム |
JP5857228B2 (ja) * | 2013-04-12 | 2016-02-10 | パナソニックIpマネジメント株式会社 | 周波数制御方法および周波数制御システム |
GB2514128B (en) * | 2013-05-14 | 2015-04-01 | Exergy Devices Ltd | Energy management method and apparatus |
EP2811607A1 (de) * | 2013-06-06 | 2014-12-10 | Diehl AKO Stiftung & Co. KG | Lokales Energiesystem |
EP3039767A4 (en) * | 2013-08-26 | 2017-10-18 | Robert Bosch GmbH | Dispatch controller for an energy system |
CN103530504B (zh) * | 2013-09-27 | 2017-03-29 | 广东电网公司电力科学研究院 | 热电联产机组以热定电下可行运行区间的计算系统及方法 |
CN103544541B (zh) * | 2013-10-15 | 2016-08-24 | 国家电网公司 | 智能配用电系统碳减排评价与测算方法 |
WO2015083207A1 (ja) * | 2013-12-06 | 2015-06-11 | 守満 立花 | 太陽光発電評点化システム |
FR3017941B1 (fr) * | 2014-02-27 | 2018-07-13 | Ergylink | Dispositif pour piloter au moins un sous-ensemble apte a transformer de l'energie electrique et a la stocker sous forme thermique, systeme et procede associes |
JP6129768B2 (ja) * | 2014-03-07 | 2017-05-17 | 株式会社日立製作所 | 需要家機器運用管理システムおよび方法 |
FR3018594B1 (fr) * | 2014-03-11 | 2016-04-01 | Electricite De France | Chauffe-eau joule regulable en puissance |
CN104571050B (zh) * | 2015-01-13 | 2017-09-26 | 国网上海市电力公司 | 基于高频用电数据的工业企业污染物排放监控方法 |
WO2016158028A1 (ja) * | 2015-03-30 | 2016-10-06 | オムロン株式会社 | 管理装置、管理システム、管理装置の制御方法および制御プログラム |
CN105046064A (zh) * | 2015-07-01 | 2015-11-11 | 国网天津市电力公司 | 一种供热期热电联产机组电负荷可调范围的计算方法 |
GB2541246A (en) * | 2015-08-14 | 2017-02-15 | Gordon Laurence Hunter Alastair | The remote control of networks of heat-pump systems, in particular where thermal stores are used, for the purpose of demand side management |
KR101707745B1 (ko) * | 2015-09-02 | 2017-02-16 | 엘에스산전 주식회사 | 전력 모니터링 시스템 및 그의 전력 모니터링 방법 |
US20190199128A1 (en) * | 2015-11-24 | 2019-06-27 | New Energy Corporation Inc. | Mobile electric power genera ting and conditioning system |
US20170211829A1 (en) | 2016-01-25 | 2017-07-27 | Sharp Kabushiki Kaisha | Optimised heat pump system |
US20170211862A1 (en) | 2016-01-25 | 2017-07-27 | Sharp Kabushiki Kaisha | Dual temperature heat pump system |
FR3051987B1 (fr) * | 2016-05-30 | 2018-05-18 | Centre National De La Recherche Scientifique (Cnrs) | Procede d'alimentation electrique d'un equipement par une station autonome hybride |
CN106209981A (zh) * | 2016-06-23 | 2016-12-07 | 珠海格力电器股份有限公司 | 热水机及其获取天气信息的方法,装置和系统 |
WO2018003042A1 (ja) * | 2016-06-29 | 2018-01-04 | 三菱電機株式会社 | 給湯システム、給湯機及び給湯機の制御方法 |
CN106052162B (zh) * | 2016-07-01 | 2017-12-08 | 顺德职业技术学院 | 热泵与太阳能热水器组合系统预测控制方法 |
CN106123360B (zh) * | 2016-07-01 | 2017-12-01 | 顺德职业技术学院 | 热泵与太阳能热水器组合系统中太阳能得热量预测控制方法 |
JP6656385B2 (ja) * | 2016-08-30 | 2020-03-04 | 三菱電機株式会社 | 給湯制御システム、サーバ、給湯制御方法及びプログラム |
JP6882973B2 (ja) * | 2017-11-13 | 2021-06-02 | 株式会社日立製作所 | エネルギー管理システム、及びエネルギー管理方法 |
DE102017220414A1 (de) * | 2017-11-16 | 2019-05-16 | Robert Bosch Gmbh | Verfahren zum Betreiben eines eine Wärmepumpe aufweisenden Wärmespeichersystems |
JP7033750B2 (ja) * | 2017-12-15 | 2022-03-11 | パナソニックIpマネジメント株式会社 | 電力管理システム |
JP6513257B2 (ja) * | 2018-04-17 | 2019-05-15 | 三菱電機株式会社 | コントローラ、スケジュール作成方法、及びプログラム |
US10976067B2 (en) * | 2019-06-14 | 2021-04-13 | Albasolar S.R.L. | Exploitation of a photovoltaic system coupled to a joint water boiler-air/air heat pump air conditioning system |
JP7345408B2 (ja) * | 2020-01-29 | 2023-09-15 | 株式会社日立製作所 | エネルギー管理システムおよびエネルギー管理方法 |
JP7108220B2 (ja) * | 2020-06-02 | 2022-07-28 | ダイキン工業株式会社 | 貯湯式給湯装置 |
CN111947206B (zh) * | 2020-08-11 | 2021-09-14 | 天津大学 | 用于建筑物平抑电能供给波动的热泵蓄热-供热优化方法 |
US20220235970A1 (en) * | 2021-01-26 | 2022-07-28 | John Williams | Solar Heat Pump Water Heater |
GB202101678D0 (en) * | 2021-02-07 | 2021-03-24 | Octopus Energy Ltd | Methods and systems and apparatus to support reduced energy and water usage |
EP4288720A1 (en) * | 2021-02-07 | 2023-12-13 | Octopus Energy Heating Limited | Temporary water/energy flow reduction |
US11988412B2 (en) | 2021-02-07 | 2024-05-21 | Octopus Energy Heating Limited | Methods and systems for modulating energy usage |
WO2022168039A1 (en) * | 2021-02-07 | 2022-08-11 | Octopus Energy Group Limited | Methods and systems for modulating energy usage |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004194485A (ja) * | 2002-12-13 | 2004-07-08 | Hitachi Home & Life Solutions Inc | エネルギーシステム |
JP2006158027A (ja) | 2004-11-26 | 2006-06-15 | Hanshin Electric Co Ltd | 家庭内電力システム |
JP2008002702A (ja) | 2006-06-20 | 2008-01-10 | Matsushita Electric Ind Co Ltd | 貯湯式給湯装置、給湯方法およびプログラム |
JP2009268247A (ja) * | 2008-04-24 | 2009-11-12 | Central Res Inst Of Electric Power Ind | 電力需給制御プログラム、電力需給制御装置および電力需給制御システム |
JP2009284586A (ja) * | 2008-05-20 | 2009-12-03 | Nippon Telegr & Teleph Corp <Ntt> | 電力システムおよびその制御方法 |
JP2010249333A (ja) * | 2009-04-10 | 2010-11-04 | Mitsubishi Electric Corp | 運転制御情報生成装置及び運転制御情報生成プログラム及び記録媒体及び運転制御情報生成方法 |
Family Cites Families (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6865450B2 (en) | 2001-05-10 | 2005-03-08 | Siemens Westinghouse Power Corporation | Schedule-based load estimator and method for electric power and other utilities and resources |
WO2003023675A2 (en) * | 2001-09-13 | 2003-03-20 | Abb Ab | Method and system to calculate a demand for energy |
JP2003254161A (ja) * | 2002-02-28 | 2003-09-10 | Osaka Gas Co Ltd | 計画変更方法、計画立案装置、コンピュータプログラム及び記録媒体 |
JP3825020B2 (ja) | 2002-08-01 | 2006-09-20 | 株式会社アイ・ヒッツ研究所 | 分散給電システム |
JP2006295090A (ja) | 2005-04-07 | 2006-10-26 | Shoji Ueda | 逆潮流電力削減型家庭用太陽光発電システム |
WO2007094054A1 (ja) * | 2006-02-15 | 2007-08-23 | Mitsubishi Denki Kabushiki Kaisha | 電力系統安定化システム |
GB2446530B (en) * | 2007-02-08 | 2009-03-11 | Univ Montfort | Apparatus and methods for metering of renewable energy devices |
US8219505B2 (en) * | 2007-08-15 | 2012-07-10 | Constellation Energy Group, Inc. | Energy usage prediction and control system and method |
NL1035008C2 (nl) * | 2007-10-29 | 2009-05-06 | Marc Jan Minnee | Werkwijze en systeem voor het toewijzen van energie aan een aantal energieverbruikers. |
US8204633B2 (en) * | 2008-07-01 | 2012-06-19 | Carina Technology, Inc. | Water heater demand side management system |
GB0815589D0 (en) * | 2008-08-28 | 2008-10-01 | Turbine Services Wind Hydro Ltd | Apparatus and method for the efficient utilisation of renewable energy |
US8494685B2 (en) | 2009-04-27 | 2013-07-23 | Cisco Technology, Inc. | System for utilizing predictive energy consumption |
WO2012004985A1 (ja) | 2010-07-07 | 2012-01-12 | パナソニック株式会社 | 貯湯式給湯システムとその運転方法 |
CN102668302A (zh) * | 2010-11-10 | 2012-09-12 | 松下电器产业株式会社 | 运转计划方法、运转计划装置、热泵式热水供给系统的运转方法、以及热泵式热水供给供暖系统的运转方法 |
KR101141946B1 (ko) * | 2011-06-08 | 2012-05-04 | 삼성에버랜드 주식회사 | 복합 발전 시스템 및 복합 발전 시스템의 온수 공급 방법 |
-
2011
- 2011-10-18 CN CN2011800050467A patent/CN102668302A/zh active Pending
- 2011-10-18 EP EP11839783.5A patent/EP2639922B1/en active Active
- 2011-10-18 WO PCT/JP2011/005824 patent/WO2012063409A1/ja active Application Filing
- 2011-10-18 JP JP2012507526A patent/JP5025834B2/ja active Active
- 2011-10-18 US US13/511,289 patent/US8972073B2/en active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004194485A (ja) * | 2002-12-13 | 2004-07-08 | Hitachi Home & Life Solutions Inc | エネルギーシステム |
JP2006158027A (ja) | 2004-11-26 | 2006-06-15 | Hanshin Electric Co Ltd | 家庭内電力システム |
JP2008002702A (ja) | 2006-06-20 | 2008-01-10 | Matsushita Electric Ind Co Ltd | 貯湯式給湯装置、給湯方法およびプログラム |
JP2009268247A (ja) * | 2008-04-24 | 2009-11-12 | Central Res Inst Of Electric Power Ind | 電力需給制御プログラム、電力需給制御装置および電力需給制御システム |
JP2009284586A (ja) * | 2008-05-20 | 2009-12-03 | Nippon Telegr & Teleph Corp <Ntt> | 電力システムおよびその制御方法 |
JP2010249333A (ja) * | 2009-04-10 | 2010-11-04 | Mitsubishi Electric Corp | 運転制御情報生成装置及び運転制御情報生成プログラム及び記録媒体及び運転制御情報生成方法 |
Non-Patent Citations (1)
Title |
---|
See also references of EP2639922A4 |
Cited By (23)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2013245839A (ja) * | 2012-05-23 | 2013-12-09 | Mitsubishi Electric Corp | 電気給湯装置 |
JP2014078127A (ja) * | 2012-10-10 | 2014-05-01 | Sharp Corp | 情報処理装置、情報処理方法及びプログラム |
JP2014078137A (ja) * | 2012-10-10 | 2014-05-01 | Sharp Corp | 情報処理装置、情報処理方法及びプログラム |
JP2014214978A (ja) * | 2013-04-25 | 2014-11-17 | パナソニック株式会社 | ヒートポンプシステム制御装置、ヒートポンプシステム、および、ヒートポンプシステム制御方法 |
US20170276406A1 (en) * | 2014-08-27 | 2017-09-28 | Alpiq Intec Ag | Method to heat water in an electrical boiler, corresponding device and electrical boiler |
US10161654B2 (en) * | 2014-08-27 | 2018-12-25 | Innosense Ag | Method to heat water in an electrical boiler, corresponding device and electrical boiler |
WO2016120995A1 (ja) * | 2015-01-27 | 2016-08-04 | 三菱電機株式会社 | 給湯機運転管理装置、給湯機運転管理システムおよび給湯機運転管理方法 |
JP5823085B1 (ja) * | 2015-01-27 | 2015-11-25 | 三菱電機株式会社 | 給湯機運転管理装置、給湯機運転管理システムおよび給湯機運転管理方法 |
GB2547398A (en) * | 2015-01-27 | 2017-08-16 | Mitsubishi Electric Corp | Water heater operation management device, water heater operation management system, and water heater operation management method |
GB2547398B (en) * | 2015-01-27 | 2020-06-17 | Mitsubishi Electric Corp | Water heater operation management device, water heater operation management system, and water heater operation management method |
JP2017005851A (ja) * | 2015-06-09 | 2017-01-05 | 東京電力ホールディングス株式会社 | 電力制御方法および電力制御システム |
JPWO2017090110A1 (ja) * | 2015-11-25 | 2018-04-26 | 三菱電機株式会社 | 給湯器制御システム、制御方法及びプログラム |
WO2017090110A1 (ja) * | 2015-11-25 | 2017-06-01 | 三菱電機株式会社 | 給湯器制御システム、制御方法及びプログラム |
JPWO2017145369A1 (ja) * | 2016-02-26 | 2018-10-25 | 三菱電機株式会社 | 給湯システム及び給湯機の制御方法 |
GB2562926A (en) * | 2016-02-26 | 2018-11-28 | Mitsubishi Electric Corp | Hot-water supply system, and control method for water heater |
WO2017145369A1 (ja) * | 2016-02-26 | 2017-08-31 | 三菱電機株式会社 | 給湯システム及び給湯機の制御方法 |
GB2562926B (en) * | 2016-02-26 | 2020-07-15 | Mitsubishi Electric Corp | Hot-water supply system, and control method for water heater |
JP2020170363A (ja) * | 2019-04-03 | 2020-10-15 | 東京瓦斯株式会社 | 需要調整システム、需要調整方法及びプログラム |
JP7274331B2 (ja) | 2019-04-03 | 2023-05-16 | 東京瓦斯株式会社 | 需要調整システム、需要調整方法及びプログラム |
JP7470833B2 (ja) | 2019-04-03 | 2024-04-18 | 東京瓦斯株式会社 | 需要調整システム、需要調整方法及びプログラム |
JP7470832B2 (ja) | 2019-04-03 | 2024-04-18 | 東京瓦斯株式会社 | 需要調整システム、需要調整方法及びプログラム |
EP4113028A4 (en) * | 2020-05-19 | 2023-08-16 | Mitsubishi Heavy Industries Thermal Systems, Ltd. | SYSTEM FOR CREATING A HOT WATER TANK PLAN, METHOD FOR CREATING A HOT WATER TANK PLAN AND PROGRAM |
JP7493444B2 (ja) | 2020-12-22 | 2024-05-31 | 三菱電機株式会社 | 需給管理装置および需給管理プログラム |
Also Published As
Publication number | Publication date |
---|---|
CN102668302A (zh) | 2012-09-12 |
EP2639922B1 (en) | 2017-12-06 |
JPWO2012063409A1 (ja) | 2014-05-12 |
JP5025834B2 (ja) | 2012-09-12 |
US20120232706A1 (en) | 2012-09-13 |
EP2639922A4 (en) | 2014-12-10 |
US8972073B2 (en) | 2015-03-03 |
EP2639922A1 (en) | 2013-09-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP5025834B2 (ja) | 運転計画方法、運転計画装置、ヒートポンプ式給湯システムの運転方法、及びヒートポンプ式給湯暖房システムの運転方法 | |
JP5025835B2 (ja) | 運転計画方法、及びヒートポンプ式給湯暖房システムの運転方法 | |
JP5942196B2 (ja) | ヒートポンプの運転方法及びヒートポンプシステム | |
US9494373B2 (en) | Heat pump operation method and heat pump system | |
JP5927569B2 (ja) | ヒートポンプの運転方法及びヒートポンプシステム | |
WO2016120995A1 (ja) | 給湯機運転管理装置、給湯機運転管理システムおよび給湯機運転管理方法 | |
JP7146035B2 (ja) | 給湯システム、沸き上げスケジュール作成装置、沸き上げスケジュール作成方法及びプログラム | |
WO2017145369A1 (ja) | 給湯システム及び給湯機の制御方法 | |
JP5899482B2 (ja) | 暖房装置の制御方法及び制御装置 | |
WO2011036524A1 (ja) | ヒートポンプ給湯システム | |
JP2016133228A (ja) | 蓄熱管理装置、蓄熱管理方法、及び蓄熱管理システム | |
JP7182431B2 (ja) | 給湯システム | |
JP7378251B2 (ja) | 制御装置、エネルギー管理システム、エネルギー管理方法及びプログラム | |
US20240044550A1 (en) | Improvements in heating systems |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
WWE | Wipo information: entry into national phase |
Ref document number: 2012507526 Country of ref document: JP |
|
WWE | Wipo information: entry into national phase |
Ref document number: 13511289 Country of ref document: US |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2011839783 Country of ref document: EP |
|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 11839783 Country of ref document: EP Kind code of ref document: A1 |
|
NENP | Non-entry into the national phase |
Ref country code: DE |