WO2009094912A1 - Caisson structure and method of sinking the caisson structure into the ground exactly - Google Patents

Caisson structure and method of sinking the caisson structure into the ground exactly Download PDF

Info

Publication number
WO2009094912A1
WO2009094912A1 PCT/CN2009/070038 CN2009070038W WO2009094912A1 WO 2009094912 A1 WO2009094912 A1 WO 2009094912A1 CN 2009070038 W CN2009070038 W CN 2009070038W WO 2009094912 A1 WO2009094912 A1 WO 2009094912A1
Authority
WO
WIPO (PCT)
Prior art keywords
jacks
jack
sinking
batch
base
Prior art date
Application number
PCT/CN2009/070038
Other languages
French (fr)
Chinese (zh)
Inventor
Cixin Ding
Shudong Ding
Original Assignee
Cixin Ding
Shudong Ding
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cixin Ding, Shudong Ding filed Critical Cixin Ding
Priority to EP09705158A priority Critical patent/EP2246481A1/en
Priority to CN2009801026576A priority patent/CN101918643B/en
Priority to JP2010543364A priority patent/JP2011510195A/en
Priority to US12/864,235 priority patent/US20100296876A1/en
Publication of WO2009094912A1 publication Critical patent/WO2009094912A1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • E02D23/08Lowering or sinking caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons

Definitions

  • the invention relates to a building structure and a construction method, in particular to a sinking structure and a construction method for smoothly sinking the sinking structure into the ground and accurately sinking. Background technique
  • Shenjing As a structure of underground space structures or deep foundation or deep foundation pit support construction, Shenjing has its unique range of engineering application conditions. For example, in the case of better hard soil quality, the sinking technology is not used, and other foundation pit construction techniques are more convenient and economical. However, in soft soil areas, due to the looseness of geology and poor stability, the use of general foundation pit support structures will result in high support costs, and at the same time lead to longer construction period and higher construction risks.
  • the sinking well is widely used in the construction of the soft soil foundation of the alluvial layer of the river and the river.
  • the application of the sinking well under soft soil foundation conditions is prone to sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well if the design and construction operations are improper. Wait for major safety and quality incidents. This is mainly caused by the congenital deficiency of the vertical plane stiffness (or the minimum vertical section torsional stiffness) of some parts of the caisson (such as the diagonal of the rectangular caisson); it is also due to the current caisson structure and the corresponding construction.
  • the method can not guarantee the smooth sinking and accurate final sinking of the sinking well in the engineering sense. Therefore, during the actual construction process, most of the caissons are swaying and swaying down, and the construction danger is very likely to occur. During the sinking process, it is necessary to constantly correct and correct the wells, and try to keep the balance of the caisson as much as possible. The construction difficulty is increased, the construction period is extended, and the cost is continuously rising.
  • the shortcomings of these traditional technologies are the technical problems that need to be solved in the long-term construction of the well, but have not been solved.
  • the construction of the foundation pit support by the caisson construction method is one of the research directions of the engineering community.
  • the largest area of the caisson can only meet the foundation pit construction of small and medium-sized area.
  • the speed of development in more complicated and cost-effective ways has limited the expansion of the use of sinking wells; this is also a long-standing problem in the design and application of sinking wells. Summary of the invention
  • the main object of the present invention is to provide a sinking structure, which is formed by providing uniformly distributed supporting block points on a conventional sinking structure, and by means of a uniform support of the supporting pile and the jack, greatly The rigidity requirement of the caisson structure is reduced, and the caisson structure is not easily deformed or broken, thereby improving the safety of construction and use.
  • Another object of the present invention is to provide a construction method for smoothly sinking a sinking well into the ground and accurately sinking, which can ensure that the caisson gradually sinks and accurately sinks in a controlled manner, thereby avoiding the conventional construction.
  • Major safety and quality accidents such as sudden subsidence, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well occur.
  • a sinking structure includes a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, wherein the inner wall surface is disposed between a plurality of horizontal and vertical planes Frame beams that intersect each other and bottom frame beams near the bottom of the well wall.
  • a plurality of equal height inner support blocks are formed on the inner wall surface
  • a plurality of equal outer outer support blocks are disposed on the outer wall surface
  • the outer support block is higher than the inner support block
  • the bottom frame beam bottom surface is bladeless
  • the plane of the foot, the lowermost end of the well wall forms a beveled foot.
  • the present invention provides a method for accurately sinking a sinking structure into the ground and accurately sinking, comprising the following steps:
  • a sinking structure in the construction area, comprising a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, wherein the inner wall surface is provided with a plurality of horizontal planes a frame beam intersecting the vertical plane and a bottom frame beam near the lowermost end of the well wall, wherein the inner wall surface forms a plurality of equal height inner support blocks, and the outer wall surface is provided with a plurality of equal outer support blocks And the outer support block is higher than the inner support block, the bottom surface of the bottom frame beam is a bladeless plane, and the bottom frame beam and the inner surface of the sinking well
  • the support blocks are respectively supported on the partial support piles in the construction area by means of jacks, and the outer support blocks of the sinking holes are supported by a set of vertically stacked blocks and a jack supported under the lowermost block.
  • a part of the supporting pile body in the construction area, and a plurality of longitudinally laminating blocks are arranged around the spacer block, so that the spacer block can only move in the longitudinal direction, and the bottom frame beam is supported
  • the support pile and the jack of the inner support block respectively constitute an internal support pile body and an internal jack
  • the support pile body and the jack supporting the outer support block respectively constitute an external support pile body and an external jack
  • each of the inner and outer jacks a ram including a pedestal and a telescopic extension within the pedestal, the ejector pins of all jacks are initially in an extended state;
  • the upper ends of the ejector pins of all internal jacks are fixed and suspended from the inner support block and the bottom frame beam Underneath; all internal and external jacks are generally divided into the first batch of jacks and the second batch of jacks;
  • each external jack of the first plurality of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the first plurality of jacks
  • the body is cut to a certain length so that a large gap is formed between the base of the inner jack in the first batch of jacks and the inner support pile remaining after cutting, and then each of the inner jacks of the first batch of jacks is operated.
  • each inner jack is lowered relative to the jack, so that the base of each inner jack of the first batch of jacks and the remaining inner portion after cutting Top support contacts the top of the pile tight, so that the entire load of the caisson while focusing on the first jacks and a second batch;
  • each of the outer jacks of the second batch of jacks is operated, so that the top rod of each of the outer jacks is elongated upward relative to the base, so that the uppermost blocks of the remaining blocks of the set are externally
  • the support blocks are in contact with each other and are tightened to each other, and then the internal support piles disposed under each of the inner jacks of the second batch of jacks are cut to a certain length, so that the bases of the inner jacks in the second batch of jacks are cut and A large gap is formed between the remaining inner support piles, and then each inner jack of the second batch of jacks is operated, so that the base of each inner jack is lowered relative to the jack, thereby making the second batch of jacks
  • the base of each internal jack is in contact with the top of the inner support pile remaining after cutting, so that the entire load of the sinking well is concentrated on the first
  • the invention has the advantages that: since a plurality of support blocks and support points are arranged on the appropriate part of the sinking well, the sinking well is supported uniformly by the support pile body and the jack, thereby greatly reducing the rigidity requirement of the sinking structure.
  • the structure of the caisson is not easily deformed or broken, thereby improving the safety of construction and use.
  • the sinking well can be smoothly and controlled to gradually sink into the depth of the predetermined ground and accurately sink, thereby avoiding It avoids major safety and quality accidents such as sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well.
  • Fig. 1 shows a plan view of a plan view of the sinker 100 of the present invention, showing the distribution of the entire support pile on the plane of the sinking plane and the mutual cooperation between the support pile and the sinking well.
  • Figure 2 shows a front elevational view of the sinking well shown in Figure 1, showing the mating relationship of a plurality of outer support blocks formed on the outer wall surface of the well wall with the blocks and corresponding pipe piles that are driven into the ground.
  • Figure 3 shows the cross-sectional structure of the sinking well shown in Figure 1 along the B-B direction, showing the fit of the blade foot to the ground and the fit between the bottom frame beam in the sinking well and the corresponding pipe pile that is driven into the ground.
  • Figure 4 shows a cross-sectional structural view of the sinking well shown in Figure 3 along the A-A direction.
  • Figure 5 shows a cross-sectional structural view of the sinking well shown in Figure 1 along the C-C direction.
  • Fig. 6 partially shows the mutual positional relationship between a part of the outer support block of the sinking well shown in Fig. 2 and the block and the jack and the pipe pile which is driven into the ground.
  • Fig. 7 is a cross-sectional structural view showing the structure shown in Fig. 6 taken along the E-E direction.
  • Fig. 8 is a cross-sectional structural view showing the structure shown in Fig. 6 taken along the line D-D.
  • Figure 9 shows the façade structure of the guide pad rail shown in Figure 8.
  • Figure 10 shows the planar structure of the spacer shown in Figure 6.
  • Figure 11 shows the façade structure of the limit plate shown in Figure 6.
  • Figures 12a-12d sequentially show the variation of the outer support block, the block, the jack and the corresponding pipe pile in the process of sinking the sinking well shown in Figures 1-11.
  • Figures 13a-13d sequentially show the changes of the outer support blocks, the blocks, the jacks and the corresponding pipe piles in the process of sinking the sinking wells shown in Figures 1-11, and the underside of the frame beams at the bottom of the caisson The change of the jack and the pipe pile supporting the jack.
  • Figure 14 shows an arrangement of a plan for the removal of soil from the sinking well and the sinking well.
  • Figure 15 shows an arranging elevational view of a device and a sinking well for removing soil from a sinking well.
  • the sinking well 100 is generally a rectangular body structure, such as a reinforced concrete structure or a steel structure.
  • the sinking well 100 includes four well walls 102 that are connected to each other to be closed, and any two opposing well walls 102 are parallel to each other such that the four well walls 102 together form a rectangular shape.
  • Each well wall 102 has an inner wall surface 110 and an outer wall surface 108 opposite the inner wall surface 110.
  • a plurality of frame beams parallel to each other in the horizontal and vertical planes are disposed between the inner wall faces 110 of any two opposing well walls 102.
  • frame longitudinal members 104 may be disposed between two laterally disposed well walls 102; and frame beams 106 may be disposed between two longitudinally disposed well walls 102. And the cross beam 106 and the corresponding stringers 104 are orthogonal to one another such that they generally provide the structural strength of the horizontal support for the caisson 100.
  • the frame beam and the longitudinal beam of the bottom end of the sinking well 100 constitute the bottom horizontal frame beam 126 of the caisson (refer to Figure 3), which is in the subsequent construction process. It is mainly used to partially support the sinking well 100.
  • Each frame beam is fixedly coupled to the respective well wall 102 by a frame post 116 disposed on the inner wall surface 110 of the well wall 102.
  • an inner partition wall 124 (refer to Fig. 3) is provided between the necessary frame beams, which further enhances the overall structural strength of the caisson 100.
  • an outer support block 112 of a plurality of equal heights is disposed on the outer wall surface 108 of each well wall 102 adjacent the top end of the caisson 100 (i.e., away from the ground). And the height of the outer support block 112 on all of the well walls 102 is the same.
  • an inner support block 114 of a plurality of equal heights is also disposed on the inner wall surface 110 of each well wall 102. And the height of the inner support block 114 on all of the well walls 102 is the same.
  • the height of all the inner support blocks 114 is much lower than the height of the outer support block 112, due to the presence of these inner and outer support blocks (commonly known as the ox legs), and the support wells are supported uniformly by the support piles and the jacks, thereby The rigidity requirement of the sinking structure is greatly reduced.
  • the invention makes the structural section of the sinking structure not to be made very large, and the safety of settlement and use of the sinking construction can be realized.
  • the bottom of each well wall 102 (with ground)
  • the face-contacting portion) forms a beveled blade foot 128 which, because of its relatively sharp edge, facilitates the sinker 100 to easily sink below the ground.
  • the tubular pile 118 is preferably driven below the ground 300 with its top end exposed a distance above the ground 300, and the tubular pile 118 is preferably supported by any two bottom frame beams of the sinking well 100 (beams)
  • the distribution position of the pipe pile is represented by a black circle or a white circle.
  • a jack 120 for adjusting the height of the caisson is disposed between the pipe pile 118 that is driven into the ground and the inner support block 114 (refer to FIG. 5); similarly, the pipe pile 118 that penetrates the ground and the bottom support beam 126 are also provided with useful
  • the jack 120 for adjusting the height of the caisson (refer to FIG. 3); and between the pipe pile 118 and the outer support block 112 that are driven into the ground, in addition to the jack 120, the jack 120 is also movable between the jack 120 and the outer support block 112.
  • a plurality of spacers 122 are provided (refer to FIGS. 2 and 5). In order to facilitate the sinking operation, the tops of the jacks in the well are fixed to each other and corresponding to the upper structure, and can be suspended.
  • each outer support block 112 protrudes outwardly from the outer wall surface 108 of the well wall 102.
  • Each outer support block 112 has a base portion 160 that projects outwardly from the outer wall surface 108 and two limit walls 134 that project downwardly from the base portion 160. And the two limiting walls 134 and the base portion 160 and the outer wall surface 108 together form a semi-closed space.
  • a hollow rectangular block-shaped guide pad rail 130 is disposed in the semi-closed space, and a rectangular block-shaped spacer 122 is accommodated between the guide pad rail 130 and the two limiting walls 134.
  • the two limiting walls 134 are connected to each other by the limiting plate 132, thereby limiting the spacer 122 to the space enclosed by the two limiting walls 134, the guiding pad rail 130 and the limiting plate 132.
  • the spacer 122 does not fall off the side. This configuration, which ensures that the spacer 122 does not fall from the side during sinking of the sinking, forms a stop for the spacer 122.
  • each of the jacks 120 can be a conventional jack for adjusting the height of the sinking well.
  • the jack 120 can include a base 504 and can be on the base 504 relative to the base 504 at a handle (not shown).
  • the device that moves down and down the position that is, the elongated or shortened jack 502.
  • the limit wall 134 described above extends longitudinally over the entire height of the caisson 100.
  • the limiting wall 134 is a temporary structure, which is gradually cut off as the block gradually withdraws during the sinking of the sinking hole, and the limiting wall 134 will be completely completed after all the blocks are extracted. The ground was removed.
  • the sinking well of the present invention is limited to such a planar shape.
  • the sinking well can be a sinking well with a circular caisson, a regular polygon, a long rectangular shape, or various asymmetrical shaped planar shapes.
  • FIG. 12a-13d illustrate the operation of the method of the present invention. Referring first to Figures 12a and 13a, the initial states of the exterior and interior of the caisson are shown, respectively. That is, a predetermined number of pipe piles 118 are first driven into the ground so that the caisson 100 is supported on the pipe piles 118.
  • the outer support block 112 is supported on the pipe pile 118 by means of a plurality of blocks 122 and a jack 120 between the lowermost pad 122 and the corresponding pipe pile 118; the bottom frame beam 126 inside the caisson 100 is directly
  • the jacks 120 are supported on the corresponding pipe piles 118; at the same time, the inner support blocks inside the caisson 100 are also supported directly on the corresponding pipe piles 118 by means of the jacks 120 (refer to FIG. 5).
  • the weight (load) of the caisson 100 acts on all (in the well wall and the well wall) pipe pile 118. In other words, all the pipe piles 118 are simultaneously subjected to the weight of the sinking well 100.
  • all of the jacks 120 are in an extended state, that is, the jacks 502 on the base 504 are at the highest positions.
  • the cutting edge 128 of the sinking well 100 is initially inserted into the ground.
  • all the inner and outer jacks are generally divided into the first batch of jacks (such as the jack represented by the black circle in Fig. 1) and the second jacks (such as the jack represented by the white circle in Fig. 1). .
  • the jack 502 of the 120 is shortened.
  • the integral sinking hole 100 is correspondingly lowered due to the shortening of the jack 502.
  • the distance is such that the cutting edge of the caisson 100 is inserted into the ground again, and part of the weight of the whole caisson 100 effectively compresses the soil underneath, thereby increasing the horizontal embedding effect of the foundation soil on the caisson 100, increasing The stability of the sinking well 100.
  • the foundation soil began to share the weight of the 100 parts of the caisson, the load on the jack was immediately lowered.
  • Figures 12c and 13c illustrate the next steps of the present invention.
  • the blocks 122 outside the well wall are sequentially numbered from 1 to 1 from the top to the bottom, and the uppermost block number is No. 1 pad, and the rest are analogous.
  • the first batch of jacks (including the inner and outer jacks) is first shortened by a certain distance, such as 30 ⁇ 50 mm, and the uppermost block (block No. 1) is taken from the outside.
  • the two limiting walls 134 of the support block 112 are drawn out.
  • the external jacks in the first batch are then immediately operated, causing the outer jacks to elongate against the next block 122, i.e., the No. 2 block.
  • the spacer No. 2 becomes a spacer which is in contact with the outer support block 112.
  • the upper end of the inner pipe pile under the inner jack of the first jack i.e., the pipe pile supporting the inner jack, also referred to as the inner support pile
  • the inner support pile i.e., the pipe pile supporting the inner jack, also referred to as the inner support pile
  • the ejector pins of the inner jacks of the first jacks are lifted up again to support between the bottom frame beam (or inner support block) and the inner pipe pile.
  • the entire load of the sinking well is concentrated on the first batch and the second batch of jacks.
  • the limiting wall 134 is cut away from the lowermost end to prevent the lowermost end from obstructing the sinking of the sinking well.
  • the second batch of jacks (including the inner and outer jacks) is shortened by a certain distance, such as 30 to 50 mm, and the uppermost block (block No. 1) is removed from the two limiting walls 134 of the outer support block 112. Pull out.
  • the external jacks in the second batch are then immediately operated such that the outer jacks are extended to close the next block 122, i.e., the No. 2 pad.
  • the No. 2 pad becomes a pad that is in contact with the outer support block 112.
  • the upper end of the inner pipe pile under the inner jack of the first jack ie, the pipe pile supporting the inner jack
  • the ejector pins of the inner jacks of the second batch of jacks are lifted up again to be supported between the bottom frame beam (or the inner support block) and the inner pipe pile. So far, at this time, the entire load of the caisson is again concentrated on the first batch and the second batch of jacks at the same time; and, all the blocks 122 on the outer support block have been removed, and all the internals The length of the support pile has been cut to a certain length. Thereafter, the limiting wall 134 is cut away from the lowermost end to avoid obstruction of the sinking of the sinking hole at its lowermost end.
  • the subsequent construction process is basically the same as that described in connection with Figures 12c and 13c, except that the pad is 2 blocks.
  • the process then proceeds to the steps described in connection with Figures 12d and 13d.
  • the block is gradually withdrawn and the caisson gradually descends until all the blocks are withdrawn and all parts of the limit wall are removed.
  • Operate all the inner and outer jacks so that the jack of each jack gradually retracts toward the base, and the sinking sink gradually sinks to the set level.
  • the jacks are removed in batches, and the concrete of the caps is cast on the top of the supporting piles until the tops of all the supporting piles are supported by the concrete of the platform to achieve accurate final sinking.
  • the internal pipe pile needs to be continuously cut off due to the gradual sinking of the caisson.
  • the soil around ie, the inner bottom of the well
  • the soil around is dug out. This is achieved by means of the composite bridge gantry crane 500 of Figures 14 and 15 and the belt conveyor 600 mated with the composite bridge gantry crane 500. Both are placed on the top of the sinking well 100. Since there is a space between the frame beams of the sinking well 100, the soil can be easily excavated.
  • the compound bridge gantry crane 500 can also hoist the excavator into the well for earthmoving operations.
  • the present invention firstly provides a sinking structure comprising a closed well wall having an inner wall surface and an outer wall surface opposite the inner wall surface, wherein the inner wall surfaces are provided with a plurality of mutually intersecting a frame beam and a bottom frame beam near a lowermost end of the well wall, wherein the inner wall surface forms a plurality of inner support blocks of equal height, the outer wall surface is provided with a plurality of outer support blocks of equal height, and the outer support block is higher than the inner support block
  • the support block, the bottom surface of the bottom frame beam is a bladeless plane, and the lowermost end of the well wall forms a blade having a sloped surface.
  • the outer support block includes a base and a pair of limiting walls extending downward from the base. Also, the base and the limiting wall extend longitudinally over the overall height of the well wall. A rectangular body-shaped guide pad rail is disposed in the limiting wall.
  • the invention also provides a method for accurately sinking the above-mentioned caisson structure into the ground. It includes the following steps:
  • each external jack of the first plurality of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the first plurality of jacks
  • the body is cut to a certain length so that a large gap is formed between the base of the inner jack in the first batch of jacks and the inner support pile remaining after cutting, and then each of the inner jacks of the first batch of jacks is operated.
  • each internal jack causing the base of each internal jack to descend relative to the ejector pin, thereby making the first batch
  • the base of each inner jack of the jack is in contact with the top of the inner support pile remaining after cutting, so that the entire load of the sinking well is concentrated on the first batch and the second batch of jacks at the same time;
  • each external jack of the second batch of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the second plurality of jacks
  • the body is cut to a certain length so that a large gap is formed between the base of the inner jack in the second batch of jacks and the inner support pile remaining after cutting, and then each inner jack of the second batch of jacks is operated, Lowering the base of each inner jack relative to the jack, thereby causing the base of each of the inner jacks of the second batch of jacks and the remaining inner portion after cutting Top support contacts the top of the pile tight, so that the entire load of the caisson while focusing on the first jacks and a second batch;
  • the outer support block of the sinking structure includes a base and a pair of limiting walls extending from the base; the base and the limiting wall extend longitudinally over the overall height of the well wall; the limiting wall is provided with a rectangular body a shape of the guide pad rail; the set of spacers are disposed in a space enclosed between the base portion and the limiting wall and the guiding pad rail, and the limit between the two limiting walls by means of a rectangular body shape
  • the plates are connected to each other such that the spacers are confined in the space defined by the two limiting walls, the guiding pad rails and the limiting plates, and the two limiting walls, the guiding pad rails and the limiting plates are combined
  • the above-mentioned limiting device is such that the spacer can only move longitudinally.
  • the supporting pile body is a prestres
  • the invention has the advantages that: by adopting a construction method in which the support block and the jack and the pipe pile cooperate with each other, the sinking well can be smoothly and controlledly gradually sinked into the depth in the predetermined ground, and the sinking is accurate, thereby avoiding the tradition.
  • Major safety and quality accidents such as sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well occurred in the construction method.
  • the inner and outer support blocks may be reinforced concrete structures or steel structures.
  • the inner and outer support blocks may be a single independent support block or a horizontal continuous truss or crown beam or support block.
  • the jacks can be various types of mechanical lifting mechanisms and are not limited to the particular jack structures disclosed herein.
  • the bottom support structure of the well wall, the inner wall support block, the inner bottom frame beam and other bottom support structures may be used alone or in combination, which may be adopted according to different design requirements of the sinking structure.
  • the present invention can be applied to a sinking project having a larger flat area, a more complicated shape, a larger single-sided size, a softer foundation, and a deeper sinking depth, thereby reducing the cost and obtaining a better economy.

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Revetment (AREA)
  • Foundations (AREA)

Abstract

A caisson structure (100) includes sealed well walls (102) with internal faces (110) and external faces (108) placed opposite to the internal faces (110). Many frame beams (106,104) provided between the internal faces (110) are mutually intersecting within a horizontal plane and a vertical plane. A bottom frame beam (126) is placed close to a lowest end of the well walls (102). The internal faces (110) are provided with many internal support blocks (114) being of same height,and the external faces (108) are provided with many external support blocks (112) being of same height, wherein the external support blocks (112) are higher than the internal support blocks (114). A bottom surface of the bottom frame beam (126) is a plane without a bit angle, and the lowest end of the well walls is provided with a bit angle with an angular inclination (128). A method of sinking the caisson structure into the ground exactly is also provided.

Description

沉井结构及将沉井结构平稳准确沉入地面的方法  Sinking structure and method for smoothly and accurately sinking the sinking structure into the ground
技术领域 Technical field
本发明涉及一种建筑结构及施工方法, 尤其涉及一种沉井结构以及将该沉 井结构平稳沉入地面且准确终沉的施工方法。 背景技术  The invention relates to a building structure and a construction method, in particular to a sinking structure and a construction method for smoothly sinking the sinking structure into the ground and accurately sinking. Background technique
沉井作为地下空间构筑物或高层建筑深基础或深基坑支护施工的一种结构, 有其独特的工程应用条件范围。 比如, 一般在较好的硬土地质条件下, 可不采 用沉井技术,而采用其它基坑施工技术方法则更为便捷经济。然而在软土地区, 由于地质疏松, 稳定性差, 因此采用一般的基坑支护结构则将导致高昂的支护 费用, 同时导致施工的工期变长, 此外, 施工的风险也较大。  As a structure of underground space structures or deep foundation or deep foundation pit support construction, Shenjing has its unique range of engineering application conditions. For example, in the case of better hard soil quality, the sinking technology is not used, and other foundation pit construction techniques are more convenient and economical. However, in soft soil areas, due to the looseness of geology and poor stability, the use of general foundation pit support structures will result in high support costs, and at the same time lead to longer construction period and higher construction risks.
因此, 沉井大量地应用于江河湖海边沖积层软土地基条件下施工。 但沉井 在软土地基条件下施工应用, 若设计与施工操作不当, 极易发生突沉、 超沉、 中心偏移、 平面旋转、 竖向歪沉、 变形断裂、 井内涌土, 井外塌陷等重大安全 与质量事故。 这主要是沉井的某些部位 (如矩形沉井的对角线)的竖向平面刚度 (或最小竖向剖面扭转刚度)先天不足所导致的; 亦是由于目前的沉井结构及相应 的施工方法不能保证沉井在工程意义上的平稳下沉且准确终沉所导致的。 因此, 实际施工过程中, 大多数沉井均是东倒西歪、 摇摇晃晃地往下沉, 施工险情极 易发生, 在下沉过程中, 必须不断地纠偏、 扶正, 尽量保持沉井的平衡, 从而 导致施工难度加大, 施工工期延长, 成本不断攀升。 这些传统技术的缺点是沉 井施工中长期需要解决但一直未能解决的技术难题。  Therefore, the sinking well is widely used in the construction of the soft soil foundation of the alluvial layer of the river and the river. However, the application of the sinking well under soft soil foundation conditions is prone to sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well if the design and construction operations are improper. Wait for major safety and quality incidents. This is mainly caused by the congenital deficiency of the vertical plane stiffness (or the minimum vertical section torsional stiffness) of some parts of the caisson (such as the diagonal of the rectangular caisson); it is also due to the current caisson structure and the corresponding construction. The method can not guarantee the smooth sinking and accurate final sinking of the sinking well in the engineering sense. Therefore, during the actual construction process, most of the caissons are swaying and swaying down, and the construction danger is very likely to occur. During the sinking process, it is necessary to constantly correct and correct the wells, and try to keep the balance of the caisson as much as possible. The construction difficulty is increased, the construction period is extended, and the cost is continuously rising. The shortcomings of these traditional technologies are the technical problems that need to be solved in the long-term construction of the well, but have not been solved.
用沉井施工方法进行沉基坑支护的施工, 是工程界研究的方向之一, 但目 前最大面积的沉井仅能满足中小规模面积的基坑施工。 而要做出更大平面积、 更大圓形直径或更大矩形单边长度、 更大的内分格尺寸、 更复杂的异形不对称 平面形状的沉井则目前在工程界极为困难。 这是沉井的自身刚度不足和不能平 稳下沉且准确终沉的特点所决定的, 从而限制了沉井朝着面积更大型化、 平面 更复杂化、 造价更经济化方向发展的速度, 进而限制了沉井用途的扩展; 这也 是沉井设计与应用中长期未决的难题。 发明内容 The construction of the foundation pit support by the caisson construction method is one of the research directions of the engineering community. However, the largest area of the caisson can only meet the foundation pit construction of small and medium-sized area. It is currently extremely difficult in the engineering world to make a sinking hole with a larger flat area, a larger circular diameter or a larger rectangular one-sided length, a larger inner division size, and a more complicated deformed asymmetrical planar shape. This is determined by the characteristics of the sinking shaft's own rigidity and the inability to sink and accurately sink, thus limiting the size of the sinking hole to a larger area and plane. The speed of development in more complicated and cost-effective ways has limited the expansion of the use of sinking wells; this is also a long-standing problem in the design and application of sinking wells. Summary of the invention
本发明的主要目的在于提供一种沉井结构, 通过在传统沉井结构上设置均 匀分布的支撑块点而形成了本发明的沉井结构, 借助支撑桩体和千斤顶的均布 支撑, 极大地降低了对沉井结构的刚度要求, 使沉井结构不易变形或断裂, 从 而提高了施工与使用的安全性。  The main object of the present invention is to provide a sinking structure, which is formed by providing uniformly distributed supporting block points on a conventional sinking structure, and by means of a uniform support of the supporting pile and the jack, greatly The rigidity requirement of the caisson structure is reduced, and the caisson structure is not easily deformed or broken, thereby improving the safety of construction and use.
本发明的另一个目的在于提供一种将沉井平稳地沉入地面且准确终沉的施 工方法, 该方法能够确保沉井以可控制的方式逐渐下沉且准确终沉, 从而避免 了传统施工方法中出现的突沉、 超沉、 中心偏移、 平面旋转、 竖向歪沉、 变形 断裂、 井内涌土、 井外塌陷等重大安全与质量事故。  Another object of the present invention is to provide a construction method for smoothly sinking a sinking well into the ground and accurately sinking, which can ensure that the caisson gradually sinks and accurately sinks in a controlled manner, thereby avoiding the conventional construction. Major safety and quality accidents such as sudden subsidence, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well occur.
为达到上述目的, 一种沉井结构, 其包括封闭起来的井壁, 该井壁具有内 壁面及与该内壁面相对的外壁面, 所述内壁面之间设置多个在水平面和垂直面 内互相交叉的框架梁及靠近井壁最下端的底框架梁。 所述内壁面上形成多个等 高的内支撑块, 所述外壁面上设置多个等高的外支撑块, 且外支撑块高于内支 撑块, 所述的底框架梁底面为无刃脚的平面, 所述井壁的最下端形成具有斜面 的刃脚。  In order to achieve the above object, a sinking structure includes a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, wherein the inner wall surface is disposed between a plurality of horizontal and vertical planes Frame beams that intersect each other and bottom frame beams near the bottom of the well wall. a plurality of equal height inner support blocks are formed on the inner wall surface, a plurality of equal outer outer support blocks are disposed on the outer wall surface, and the outer support block is higher than the inner support block, and the bottom frame beam bottom surface is bladeless The plane of the foot, the lowermost end of the well wall forms a beveled foot.
为达到上述目的, 本发明提供一种将沉井结构准确沉入地面且准确终沉的 方法, 其包括如下步骤:  In order to achieve the above object, the present invention provides a method for accurately sinking a sinking structure into the ground and accurately sinking, comprising the following steps:
(1) 选定一定施工区域, 并在该施工区域内打入多个支撑桩体且保持支撑桩 体的一部分长度暴露于施工区域的地面以上;  (1) Selecting a certain construction area, and driving a plurality of supporting piles in the construction area and keeping a part of the length of the supporting pile exposed above the ground of the construction area;
(2)在该施工区域内构建一种沉井结构, 其包括封闭起来的井壁, 该井壁具 有内壁面及与该内壁面相对的外壁面, 所述内壁面之间设置多个在水平面和竖 向面内互相交叉的框架梁及靠近井壁最下端的底框架梁, 所述内壁面上形成多 个等高的内支撑块, 所述外壁面上设置多个等高的外支撑块, 且外支撑块高于 内支撑块, 所述的底框架梁底面为无刃脚的平面, 并且使沉井的底框架梁及内 支撑块借助千斤顶而分别支撑于所述施工区域内的部分支撑桩体上, 而沉井的 外支撑块则借助一组纵向叠压起来的垫块及支撑于最下端垫块下方的千斤顶而 支撑于施工区域的部分支撑桩体上, 且纵向叠压的多个垫块的周围设有对垫块 进行限位, 从而使垫块仅可在纵向方向内活动的限位装置, 支撑底框架梁与内 支撑块的支撑桩体及千斤顶分别构成了内部支撑桩体与内部千斤顶, 支撑外支 撑块的支撑桩体及千斤顶分别构成了外部支撑桩体及外部千斤顶, 所有内部及 外部千斤顶中的每一个包括基座及可在该基座内伸缩一定行程的顶杆, 所有千 斤顶的顶杆初始地处于伸长状态; 所有内部千斤顶的顶杆上端都与内支撑块及 底框架梁固定且悬吊于其下; 将所有内外千斤顶总体上划分为互相交错的第一 批千斤顶与第二批千斤顶; (2) constructing a sinking structure in the construction area, comprising a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, wherein the inner wall surface is provided with a plurality of horizontal planes a frame beam intersecting the vertical plane and a bottom frame beam near the lowermost end of the well wall, wherein the inner wall surface forms a plurality of equal height inner support blocks, and the outer wall surface is provided with a plurality of equal outer support blocks And the outer support block is higher than the inner support block, the bottom surface of the bottom frame beam is a bladeless plane, and the bottom frame beam and the inner surface of the sinking well The support blocks are respectively supported on the partial support piles in the construction area by means of jacks, and the outer support blocks of the sinking holes are supported by a set of vertically stacked blocks and a jack supported under the lowermost block. A part of the supporting pile body in the construction area, and a plurality of longitudinally laminating blocks are arranged around the spacer block, so that the spacer block can only move in the longitudinal direction, and the bottom frame beam is supported The support pile and the jack of the inner support block respectively constitute an internal support pile body and an internal jack, and the support pile body and the jack supporting the outer support block respectively constitute an external support pile body and an external jack, and each of the inner and outer jacks a ram including a pedestal and a telescopic extension within the pedestal, the ejector pins of all jacks are initially in an extended state; the upper ends of the ejector pins of all internal jacks are fixed and suspended from the inner support block and the bottom frame beam Underneath; all internal and external jacks are generally divided into the first batch of jacks and the second batch of jacks;
(3)操作所有内外千斤顶, 使每个千斤顶的顶杆均向基座缩回一定距离, 并 使顶杆与基座之间尚留有 30毫米以上的行程间隙, 从而使沉井在施工区域内第 一次下沉一定深度, 并使井壁的刃脚插入到地面下;  (3) Operate all internal and external jacks, so that the jacks of each jack are retracted to the base at a certain distance, and there is still a travel clearance of more than 30 mm between the jack and the base, so that the sinking well is in the construction area. The first time it sinks a certain depth, and the cutting edge of the well wall is inserted under the ground;
(4)操作第一批千斤顶使其缩短 20~50毫米, 从而使得沉井的全部载荷完全 地集中于第二批千斤顶, 而第一批千斤顶则处于无载荷状态, 然后将设置于第 一批千斤顶的每个外支撑块与相应外部千斤顶之间的一组垫块中最高的一块垫 块抽去, 接下来操作第一批千斤顶中的每个外部千斤顶, 使该每个外部千斤顶 的顶杆相对于基座向上伸长, 从而使该组剩余垫块中最上端的垫块与外支撑块 接触并互相顶紧, 再将设置于第一批千斤顶中的每个内部千斤顶之下的内部支 撑桩体切断一定的长度, 从而使第一批千斤顶中的内部千斤顶的基座与切割后 剩余的内部支撑桩体之间形成较大的间隙, 接下来操作第一批千斤顶中的该每 个内部千斤顶, 使每个内部千斤顶的基座相对于顶杆向下降落, 从而使第一批 千斤顶中的每个内部千斤顶的基座与切割后剩余的内部支撑桩体的顶部接触顶 紧, 从而使得沉井的全部载荷同时集中于第一批及第二批千斤顶上;  (4) Operating the first batch of jacks to shorten it by 20 to 50 mm, so that the entire load of the caisson is completely concentrated in the second batch of jacks, while the first batch of jacks are in a no-load state, and then will be set in the first batch. The highest one of the set of blocks between each outer support block of the jack and the corresponding external jack is removed, and then each external jack of the first plurality of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the first plurality of jacks The body is cut to a certain length so that a large gap is formed between the base of the inner jack in the first batch of jacks and the inner support pile remaining after cutting, and then each of the inner jacks of the first batch of jacks is operated. , the base of each inner jack is lowered relative to the jack, so that the base of each inner jack of the first batch of jacks and the remaining inner portion after cutting Top support contacts the top of the pile tight, so that the entire load of the caisson while focusing on the first jacks and a second batch;
(5)操作第二批千斤顶使其缩短 20~50毫米, 从而使沉井的全部载荷完全地 转移到第一批千斤顶, 进而使得第二批千斤顶处于无载荷状态, 然后将设置于 第二批千斤顶的每个外支撑块与相应外部千斤顶之间的一组垫块中最高的一块 垫块抽去, 接下来操作第二批千斤顶中的每个外部千斤顶, 使该每个外部千斤 顶的顶杆相对于基座向上伸长, 从而使该组剩余垫块中最上端的垫块与外支撑 块接触并互相顶紧, 再将设置于第二批千斤顶中的每个内部千斤顶之下的内部 支撑桩体切断一定的长度, 从而使第二批千斤顶中的内部千斤顶的基座与切割 后剩余的内部支撑桩体之间形成较大的间隙, 接下来操作第二批千斤顶中的每 个内部千斤顶, 使每个内部千斤顶的基座相对于顶杆向下降落, 从而使第二批 千斤顶中的每个内部千斤顶的基座与切割后剩余的内部支撑桩体的顶部接触顶 紧, 从而使得沉井的全部载荷同时集中于第一批及第二批千斤顶上; (5) Operating the second batch of jacks to shorten the length of 20 to 50 mm, so that the entire load of the caisson is completely transferred to the first batch of jacks, so that the second batch of jacks are in a no-load state, and then will be set in the second batch. The tallest of the set of pads between each outer support block of the jack and the corresponding external jack The block is removed, and then each of the outer jacks of the second batch of jacks is operated, so that the top rod of each of the outer jacks is elongated upward relative to the base, so that the uppermost blocks of the remaining blocks of the set are externally The support blocks are in contact with each other and are tightened to each other, and then the internal support piles disposed under each of the inner jacks of the second batch of jacks are cut to a certain length, so that the bases of the inner jacks in the second batch of jacks are cut and A large gap is formed between the remaining inner support piles, and then each inner jack of the second batch of jacks is operated, so that the base of each inner jack is lowered relative to the jack, thereby making the second batch of jacks The base of each internal jack is in contact with the top of the inner support pile remaining after cutting, so that the entire load of the sinking well is concentrated on the first batch and the second batch of jacks at the same time;
(6)拆除每个外部千斤顶顶杆周围的限位装置;  (6) Remove the limit device around each external jack ejector;
(7)操作所有内外千斤顶, 使每个千斤顶的顶杆均向基座缩回一定距离, 并 使顶杆与基座之间尚留有 30毫米以上的行程间隙, 从而使沉井在施工区域内再 次下沉一定深度;  (7) Operate all internal and external jacks, so that the jacks of each jack are retracted to the base by a certain distance, and there is still a travel clearance of more than 30 mm between the jack and the base, so that the sinking well is in the construction area. Sinking again within a certain depth;
(8)将沉井内井底的土挖去一层, 从而使每个内部支撑桩体的一部分从土中 暴露出来;  (8) Digging the soil at the bottom of the well in the sinking well, so that a part of each internal supporting pile is exposed from the soil;
(9)依次重复上述步骤 (4)、 (5)、 (6)、 (7)以及 (8), 从而使沉井不断下沉, 直至 每个外部千斤顶上的垫块均被抽走, 且使每个外部千斤顶均已直接顶住对应的 外支撑块;  (9) Repeat steps (4), (5), (6), (7), and (8) above in order to allow the caisson to sink continuously until the blocks on each of the external jacks are removed, and So that each external jack has directly supported the corresponding outer support block;
(10)操作所有的内外千斤顶, 使每个千斤顶的顶杆向基座逐渐缩回, 沉井逐 渐下沉至设定标高;  (10) Operate all the inner and outer jacks, so that the jack of each jack is gradually retracted toward the base, and the sinking sink gradually sinks to the set elevation;
(11)分批次拆除千斤顶, 且在支撑桩体顶部上浇注承台混凝土, 直至全部支 撑桩体顶部上都由 7|台混凝土支撑着沉井, 进而实现准确终沉。 (11) The jacks are removed in batches, and the concrete of the caps is cast on the top of the supporting piles until the top of all supporting piles is supported by 7 | concrete to achieve the final sinking.
本发明的优点在于: 由于在沉井上的适当部位上设置有许多个支撑块及支 撑点, 借助支撑桩体和千斤顶均布地支撑着沉井, 因此极大地降低了对沉井结 构的刚度要求,使沉井结构不易变形或断裂,从而提高了施工与使用的安全性。 此外, 通过采用支撑块及支撑点与千斤顶与管桩的相互配合操作的施工方法, 使得沉井可以平稳地受控制地逐渐沉入预定地面内的深度且准确终沉, 从而避 免了传统施工方法中出现的突沉、 超沉、 中心偏移、 平面旋转、 竖向歪沉、 变 形断裂、 井内涌土、 井外塌陷等重大安全与质量事故。 附图说明 The invention has the advantages that: since a plurality of support blocks and support points are arranged on the appropriate part of the sinking well, the sinking well is supported uniformly by the support pile body and the jack, thereby greatly reducing the rigidity requirement of the sinking structure. The structure of the caisson is not easily deformed or broken, thereby improving the safety of construction and use. In addition, by adopting a construction method in which the support block and the support point and the jack and the pipe pile cooperate with each other, the sinking well can be smoothly and controlled to gradually sink into the depth of the predetermined ground and accurately sink, thereby avoiding It avoids major safety and quality accidents such as sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well. DRAWINGS
图 1展示了本发明沉井 100的俯视平面结构图, 展示了全部支撑桩体在沉 井平面上的分布位置及支撑桩体与沉井的互相配合关系。  Fig. 1 shows a plan view of a plan view of the sinker 100 of the present invention, showing the distribution of the entire support pile on the plane of the sinking plane and the mutual cooperation between the support pile and the sinking well.
图 2展示了图 1所示沉井的主视立面图, 显示了多个形成于井壁外壁面的 外支撑块与垫块及打入地面内的相应管桩的配合关系。  Figure 2 shows a front elevational view of the sinking well shown in Figure 1, showing the mating relationship of a plurality of outer support blocks formed on the outer wall surface of the well wall with the blocks and corresponding pipe piles that are driven into the ground.
图 3展示了图 1所示沉井沿着 B-B方向的剖面结构图, 显示了刃脚与地面 的配合情况, 以及沉井内底部框架梁与打入地面内的相应管桩之间的配合关系。  Figure 3 shows the cross-sectional structure of the sinking well shown in Figure 1 along the B-B direction, showing the fit of the blade foot to the ground and the fit between the bottom frame beam in the sinking well and the corresponding pipe pile that is driven into the ground.
图 4展示了图 3所示沉井沿着 A-A方向的剖视结构图。  Figure 4 shows a cross-sectional structural view of the sinking well shown in Figure 3 along the A-A direction.
图 5展示了图 1所示沉井沿着 C-C方向的剖视结构图。  Figure 5 shows a cross-sectional structural view of the sinking well shown in Figure 1 along the C-C direction.
图 6局部地展示了图 2所示沉井的部分外支撑块与垫块及千斤顶及打入地 面内的管桩之间的相互位置关系。  Fig. 6 partially shows the mutual positional relationship between a part of the outer support block of the sinking well shown in Fig. 2 and the block and the jack and the pipe pile which is driven into the ground.
图 7展示了图 6所示结构沿着 E-E方向的剖视结构图。  Fig. 7 is a cross-sectional structural view showing the structure shown in Fig. 6 taken along the E-E direction.
图 8展示了图 6所示结构沿着 D-D方向的剖视结构图。  Fig. 8 is a cross-sectional structural view showing the structure shown in Fig. 6 taken along the line D-D.
图 9展示了图 8所示导向垫轨的立面结构。  Figure 9 shows the façade structure of the guide pad rail shown in Figure 8.
图 10展示了图 6所示垫块的平面结构。  Figure 10 shows the planar structure of the spacer shown in Figure 6.
图 11展示了图 6所示限位板的立面结构。  Figure 11 shows the façade structure of the limit plate shown in Figure 6.
图 12a-12d依次展示了图 1-图 11所示沉井在沉入地面内的过程中外支撑块、 垫块、 千斤顶及相应的管桩的变化情况。  Figures 12a-12d sequentially show the variation of the outer support block, the block, the jack and the corresponding pipe pile in the process of sinking the sinking well shown in Figures 1-11.
图 13a-13d依次展示了图 1-图 11所示沉井在沉入地面内的过程中外支撑块、 垫块、 千斤顶及相应的管桩的变化情况; 同时展示了沉井底部框架梁下的千斤 顶与支撑千斤顶的管桩的变化情况。  Figures 13a-13d sequentially show the changes of the outer support blocks, the blocks, the jacks and the corresponding pipe piles in the process of sinking the sinking wells shown in Figures 1-11, and the underside of the frame beams at the bottom of the caisson The change of the jack and the pipe pile supporting the jack.
图 14展示了用于将土从沉井内取出的装置与沉井的排列平面图。  Figure 14 shows an arrangement of a plan for the removal of soil from the sinking well and the sinking well.
图 15展示了用于将土从沉井内取出的装置与沉井的排列立面图。 具体实施方式 Figure 15 shows an arranging elevational view of a device and a sinking well for removing soil from a sinking well. detailed description
首先介绍本发明的沉井结构。 参考图 1-图 11 , 沉井 100总体上为矩形体的 结构, 比如可以为钢筋混凝土结构或钢制结构等。 该沉井 100 包括四个互相连 接从而封闭起来的井壁 102, 任意两个相对的井壁 102互相平行, 从而使得四个 井壁 102—起构成矩形形状。 每个井壁 102具有内壁面 110及与该内壁面 110 相对的外壁面 108。任意两个相对的井壁 102的内壁面 110之间设置多个在水平 面和竖向面内互相平行的框架梁。 比如两个横向设置的井壁 102之间可以设置 框架纵梁 104; 而两个纵向设置的井壁 102之间可以设置框架横梁 106。 并且横 梁 106与对应的纵梁 104互相正交, 从而使得它们总体上为沉井 100提供了水 平支撑的结构强度。 First, the sinking structure of the present invention will be described. Referring to Figures 1 to 11, the sinking well 100 is generally a rectangular body structure, such as a reinforced concrete structure or a steel structure. The sinking well 100 includes four well walls 102 that are connected to each other to be closed, and any two opposing well walls 102 are parallel to each other such that the four well walls 102 together form a rectangular shape. Each well wall 102 has an inner wall surface 110 and an outer wall surface 108 opposite the inner wall surface 110. A plurality of frame beams parallel to each other in the horizontal and vertical planes are disposed between the inner wall faces 110 of any two opposing well walls 102. For example, frame longitudinal members 104 may be disposed between two laterally disposed well walls 102; and frame beams 106 may be disposed between two longitudinally disposed well walls 102. And the cross beam 106 and the corresponding stringers 104 are orthogonal to one another such that they generally provide the structural strength of the horizontal support for the caisson 100.
其中, 沉井 100最下端 (即沉井制成后, 其最靠近地面的一端)的框架横梁及 纵梁构成了沉井的底部水平框架梁 126(参考图 3), 其在随后的施工过程中主要 用于部分地支撑沉井 100。  Among them, the frame beam and the longitudinal beam of the bottom end of the sinking well 100 (ie, the end closest to the ground after the sinking well is made) constitute the bottom horizontal frame beam 126 of the caisson (refer to Figure 3), which is in the subsequent construction process. It is mainly used to partially support the sinking well 100.
每个框架梁借助设置在井壁 102的内壁面 110上的框架柱 116而固定连接 到相应的井壁 102上。此外,在必要的框架梁之间设置有内隔墙 124(参考图 3), 其进一步加强了沉井 100的整体结构强度。  Each frame beam is fixedly coupled to the respective well wall 102 by a frame post 116 disposed on the inner wall surface 110 of the well wall 102. In addition, an inner partition wall 124 (refer to Fig. 3) is provided between the necessary frame beams, which further enhances the overall structural strength of the caisson 100.
特别地, 每个井壁 102的外壁面 108上靠近沉井 100的顶端(即远离地面) 上设置有多个等高 (相对于沉井最底端的高度)的外支撑块 112。并且所有井壁 102 上的外支撑块 112的高度都相同。 类似地, 每个井壁 102的内壁面 110上也设 置有多个等高 (相对于沉井最底端的高度)的内支撑块 114。 并且所有井壁 102上 的内支撑块 114的高度都相同。 特别地, 所有的内支撑块 114的高度要远远地 低于外支撑块 112的高度, 由于存在这些内外支撑块 (俗称牛腿), 并且借助支撑 桩体和千斤顶均布地支撑沉井, 从而极大地降低了对沉井结构的刚度要求, 换 句话说, 本发明使得沉井结构的构件断面不必制作成非常庞大, 即可实现沉井 施工沉降与使用的安全性。 请参考图 3与图 5, 所述每个井壁 102的底部 (与地 面接触的部分)形成具有斜面的刃脚 128, 由于其边缘相对锋利, 因此其有利于 整体沉井 100容易地沉入地面以下。 In particular, an outer support block 112 of a plurality of equal heights (relative to the bottommost height of the caisson) is disposed on the outer wall surface 108 of each well wall 102 adjacent the top end of the caisson 100 (i.e., away from the ground). And the height of the outer support block 112 on all of the well walls 102 is the same. Similarly, an inner support block 114 of a plurality of equal heights (relative to the lowest end of the caisson) is also disposed on the inner wall surface 110 of each well wall 102. And the height of the inner support block 114 on all of the well walls 102 is the same. In particular, the height of all the inner support blocks 114 is much lower than the height of the outer support block 112, due to the presence of these inner and outer support blocks (commonly known as the ox legs), and the support wells are supported uniformly by the support piles and the jacks, thereby The rigidity requirement of the sinking structure is greatly reduced. In other words, the invention makes the structural section of the sinking structure not to be made very large, and the safety of settlement and use of the sinking construction can be realized. Please refer to FIG. 3 and FIG. 5, the bottom of each well wall 102 (with ground) The face-contacting portion) forms a beveled blade foot 128 which, because of its relatively sharp edge, facilitates the sinker 100 to easily sink below the ground.
下面介绍本发明沉井 100 准确沉入地面的方法, 即沉井是如何平稳有序地 下沉到地面下的。 首先介绍与该方法有关的支撑构造。 为了稳定地将沉井支撑 于地面上, 参考图 2、 图 3及图 5, 地面 300(参考图 5)之下预先打入了预订数量 的支撑桩体, 比如管桩 118。 并且, 优选地, 管桩 118打入地面直到与地质的基 岩持力层 200接触 (如图 5所示)。管桩的数量与分布取决于沉井的结构及地质情 况。 在本实施例中, 管桩 118优选地打入地面 300之下, 并使其顶端露出地面 300之上一段距离,并且管桩 118最好支撑于沉井 100的任意两个底部框架梁 (横 梁与纵梁)交叉的部位及对应于外支撑块 112及内支撑块 114的部位, 此外, 管 桩 118也支撑于底部框架梁 126下方 (参考图 3)。 在图 1、 图 2中, 用黑圓圏或 白圓圏代表了管桩的分布位置。 这些大量均匀分布的管桩 118将在沉井 100的 平稳下沉并准确终沉过程中起到至关重要的作用。  The following is a description of the method in which the sinking well 100 of the present invention is accurately sunk into the ground, that is, how the sinking well sinks to the ground smoothly and orderly. First, the support structure associated with this method will be described. In order to stably support the caisson on the ground, refer to Figures 2, 3 and 5, and under the ground 300 (refer to Figure 5), a predetermined number of support piles, such as pipe piles 118, are pre-introduced. Also, preferably, the tubular pile 118 is driven into the ground until it contacts the geological basement bearing layer 200 (as shown in Figure 5). The number and distribution of pipe piles depends on the structure and geology of the sinking well. In the present embodiment, the tubular pile 118 is preferably driven below the ground 300 with its top end exposed a distance above the ground 300, and the tubular pile 118 is preferably supported by any two bottom frame beams of the sinking well 100 (beams) The portion intersecting the longitudinal beam and the portion corresponding to the outer support block 112 and the inner support block 114, in addition, the pipe pile 118 is also supported below the bottom frame beam 126 (refer to FIG. 3). In Fig. 1 and Fig. 2, the distribution position of the pipe pile is represented by a black circle or a white circle. These large number of evenly distributed tubular piles 118 will play a vital role in the smooth sinking and accurate final sinking of the sinking well 100.
打入地面的管桩 118与内支撑块 114之间设置有用于调整沉井高度的千斤 顶 120(参考图 5); 类似地, 打入地面的管桩 118与底部支撑梁 126之间也设置 有用于调整沉井高度的千斤顶 120(参考图 3); 而打入地面的管桩 118与外支撑 块 112之间则除了设置千斤顶 120之外, 还在千斤顶 120与外支撑块 112之间 活动地设置了多个垫块 122(参考图 2及图 5)。 为了下沉作业方便, 井内千斤顶 的顶部都与上部相应结构互相固定, 并且可悬吊。  A jack 120 for adjusting the height of the caisson is disposed between the pipe pile 118 that is driven into the ground and the inner support block 114 (refer to FIG. 5); similarly, the pipe pile 118 that penetrates the ground and the bottom support beam 126 are also provided with useful The jack 120 for adjusting the height of the caisson (refer to FIG. 3); and between the pipe pile 118 and the outer support block 112 that are driven into the ground, in addition to the jack 120, the jack 120 is also movable between the jack 120 and the outer support block 112. A plurality of spacers 122 are provided (refer to FIGS. 2 and 5). In order to facilitate the sinking operation, the tops of the jacks in the well are fixed to each other and corresponding to the upper structure, and can be suspended.
下面详细介绍外支撑块 112与千斤顶 120、垫块 122及管桩 118之间的位置 关系。 参考图 6-图 11及图 1 , 外支撑块 112自井壁 102的外壁面 108向外突出 形成。 每个外支撑块 112具有从外壁面 108向外伸出的基部 160以及从该基部 160向下伸出的两个限位壁 134。 并且该两个限位壁 134及基部 160以及外壁面 108之间共同围成了半封闭的空间。该半封闭的空间内设置有空心的矩形块状的 导向垫轨 130,而该导向垫轨 130与该两个限位壁 134之间则容纳有矩形块形状 的垫块 122。 此外, 所述两个限位壁 134之间借助限位板 132而互相连接, 从而 将垫块 122限制在两个限位壁 134、导向垫轨 130及限位板 132共同围成的空间 内, 进而在施工过程中, 垫块 122不会从侧面掉落。 这种确保垫块 122在沉井 下沉过程中不会从侧面掉落的结构形成了垫块 122 的限位装置。 此外, 每个千 斤顶 120可以为传统的千斤顶, 用于调整沉井的高度, 比如千斤顶 120可以包 括基座 504及可在该基座 504上相对于该基座 504在手柄(图未示)的操作下而上 下移动位置的装置, 即伸长或缩短的顶杆 502。 应当注意: 上述限位壁 134纵向 地在沉井 100的整个高度上延伸。 并且, 限位壁 134为临时结构, 其在沉井下 沉的整个过程中, 随着垫块的逐渐抽出而逐渐被切断一部分, 直到所有的垫块 都被抽出之后, 该限位壁 134将完全地被除去。 The positional relationship between the outer support block 112 and the jack 120, the spacer 122, and the pipe pile 118 will be described in detail below. Referring to FIGS. 6-11 and 1 , the outer support block 112 protrudes outwardly from the outer wall surface 108 of the well wall 102. Each outer support block 112 has a base portion 160 that projects outwardly from the outer wall surface 108 and two limit walls 134 that project downwardly from the base portion 160. And the two limiting walls 134 and the base portion 160 and the outer wall surface 108 together form a semi-closed space. A hollow rectangular block-shaped guide pad rail 130 is disposed in the semi-closed space, and a rectangular block-shaped spacer 122 is accommodated between the guide pad rail 130 and the two limiting walls 134. In addition, the two limiting walls 134 are connected to each other by the limiting plate 132, thereby limiting the spacer 122 to the space enclosed by the two limiting walls 134, the guiding pad rail 130 and the limiting plate 132. Inside, and in the course of construction, the spacer 122 does not fall off the side. This configuration, which ensures that the spacer 122 does not fall from the side during sinking of the sinking, forms a stop for the spacer 122. In addition, each of the jacks 120 can be a conventional jack for adjusting the height of the sinking well. For example, the jack 120 can include a base 504 and can be on the base 504 relative to the base 504 at a handle (not shown). The device that moves down and down the position, that is, the elongated or shortened jack 502. It should be noted that the limit wall 134 described above extends longitudinally over the entire height of the caisson 100. Moreover, the limiting wall 134 is a temporary structure, which is gradually cut off as the block gradually withdraws during the sinking of the sinking hole, and the limiting wall 134 will be completely completed after all the blocks are extracted. The ground was removed.
虽然上述实施例中, 以矩形体形状的沉井作为举例, 但并不意味着本发明 的沉井局限于此一种平面形状的结构。相反, 沉井可以为圓形沉井,正多边形、 长条矩形或各种不对称的异形平面形状等沉井结构。  Although the cavities in the shape of a rectangular body are exemplified in the above embodiments, it does not mean that the sinking well of the present invention is limited to such a planar shape. Conversely, the sinking well can be a sinking well with a circular caisson, a regular polygon, a long rectangular shape, or various asymmetrical shaped planar shapes.
本发明将沉井平稳地沉入地面的施工方法主要是利用沉井全部载荷在相邻 的支撑桩体之间交替转移变化原理及千斤顶高度可调的原理所实现的。 图 12a-13d展示了本发明方法的工作过程。 首先参考图 12a及 13a, 其分别显示了 沉井外部与内部的初始状态。 即预定数量的管桩 118 首先打入地面内, 从而使 沉井 100支撑于管桩 118上。 具体地讲, 外支撑块 112借助多个垫块 122及最 下端的垫块 122与对应管桩 118之间的千斤顶 120而支撑于管桩 118上; 沉井 100内部的底部框架梁 126则直接借助千斤顶 120支撑于相应的管桩 118上; 同 时,沉井 100内部的内支撑块也直接借助千斤顶 120支撑于相应的管桩 118上 (参 考图 5)。 此时, 沉井 100的重量 (载荷)作用于所有的 (井壁内与井壁夕卜)管桩 118 上, 换句话说, 所有的管桩 118都同时承受沉井 100的重量。 并且此时, 所有 千斤顶 120均处于伸长状态, 即其基座 504上的顶杆 502均位于最高位置。 而 沉井 100的刃脚 128则初始地插入到地面内。 此外, 为了描述方便, 将所有内 外千斤顶总体上划分为互相交错的第一批千斤顶(比如图 1中黑色圓圏表示的千 斤顶)与第二批千斤顶(比如图 1中白色圓圏表示的千斤顶)。  The construction method for the sinking of the sinking well into the ground is mainly realized by the principle that the entire load of the sinking well is alternately transferred between adjacent supporting piles and the principle that the height of the jack is adjustable. Figures 12a-13d illustrate the operation of the method of the present invention. Referring first to Figures 12a and 13a, the initial states of the exterior and interior of the caisson are shown, respectively. That is, a predetermined number of pipe piles 118 are first driven into the ground so that the caisson 100 is supported on the pipe piles 118. Specifically, the outer support block 112 is supported on the pipe pile 118 by means of a plurality of blocks 122 and a jack 120 between the lowermost pad 122 and the corresponding pipe pile 118; the bottom frame beam 126 inside the caisson 100 is directly The jacks 120 are supported on the corresponding pipe piles 118; at the same time, the inner support blocks inside the caisson 100 are also supported directly on the corresponding pipe piles 118 by means of the jacks 120 (refer to FIG. 5). At this time, the weight (load) of the caisson 100 acts on all (in the well wall and the well wall) pipe pile 118. In other words, all the pipe piles 118 are simultaneously subjected to the weight of the sinking well 100. At this time, all of the jacks 120 are in an extended state, that is, the jacks 502 on the base 504 are at the highest positions. The cutting edge 128 of the sinking well 100 is initially inserted into the ground. In addition, for the convenience of description, all the inner and outer jacks are generally divided into the first batch of jacks (such as the jack represented by the black circle in Fig. 1) and the second jacks (such as the jack represented by the white circle in Fig. 1). .
接下来, 如图 12b及 13b所示, 操作所有的千斤顶 120, 使得所有千斤顶 Next, as shown in Figures 12b and 13b, all the jacks 120 are operated, so that all the jacks
120的顶杆 502缩短, 此时, 整体沉井 100因为顶杆 502的缩短而相应下沉一定 距离, 从而使沉井 100的刃脚再次插入到地面内, 并且整体沉井 100的部分重 量将其下面的土质有效地压紧,从而增加了地基土对沉井 100的水平嵌固作用, 增加了沉井 100稳定性。 并且由于地基土开始分担沉井 100部分的重量, 从而 立即降氏了沉井对千斤顶的荷载。 The jack 502 of the 120 is shortened. At this time, the integral sinking hole 100 is correspondingly lowered due to the shortening of the jack 502. The distance is such that the cutting edge of the caisson 100 is inserted into the ground again, and part of the weight of the whole caisson 100 effectively compresses the soil underneath, thereby increasing the horizontal embedding effect of the foundation soil on the caisson 100, increasing The stability of the sinking well 100. And because the foundation soil began to share the weight of the 100 parts of the caisson, the load on the jack was immediately lowered.
图 12c及 13c展示了本发明的下一步操作。为了描述方便,将井壁外的垫块 122自上向下依次从 1开始编号,最上面的垫块编号为 1号垫块,其余依次类推。 同时参考图 6-图 11 ,在该操作中,首先将第一批千斤顶(包括内部与外部千斤顶) 缩短一定距离, 比如 30~50毫米, 将最上面的垫块 (1号垫块)从外支撑块 112的 两个限位壁 134之间抽出。 然后立即操作第一批中的外部千斤顶, 使得外部千 斤顶伸长顶紧下一块垫块 122, 即 2号垫块。此时, 2号垫块变成与外支撑块 112 接触的垫块。  Figures 12c and 13c illustrate the next steps of the present invention. For convenience of description, the blocks 122 outside the well wall are sequentially numbered from 1 to 1 from the top to the bottom, and the uppermost block number is No. 1 pad, and the rest are analogous. Referring also to Figures 6-11, in this operation, the first batch of jacks (including the inner and outer jacks) is first shortened by a certain distance, such as 30~50 mm, and the uppermost block (block No. 1) is taken from the outside. The two limiting walls 134 of the support block 112 are drawn out. The external jacks in the first batch are then immediately operated, causing the outer jacks to elongate against the next block 122, i.e., the No. 2 block. At this time, the spacer No. 2 becomes a spacer which is in contact with the outer support block 112.
接下来, 将第一批千斤顶的内部千斤顶下面的内部管桩 (即支撑内部千斤顶 的管桩, 也称为内部支撑桩体)的最上端切掉一定长度。 然后, 将第一批千斤顶 的内部千斤顶的顶杆再次顶起,从而支撑于底框架梁 (或内支撑块)与内部管桩之 间。 此时, 沉井的全部载荷同时集中于第一批与第二批千斤顶上。 此后, 将限 位壁 134自最下端切掉一部分, 从而避免其最下端对沉井的下沉造成障碍。  Next, the upper end of the inner pipe pile under the inner jack of the first jack (i.e., the pipe pile supporting the inner jack, also referred to as the inner support pile) is cut to a certain length. Then, the ejector pins of the inner jacks of the first jacks are lifted up again to support between the bottom frame beam (or inner support block) and the inner pipe pile. At this time, the entire load of the sinking well is concentrated on the first batch and the second batch of jacks. Thereafter, the limiting wall 134 is cut away from the lowermost end to prevent the lowermost end from obstructing the sinking of the sinking well.
接下来,将第二批千斤顶(包括内部与外部千斤顶)缩短一定距离,比如 30~50 毫米, 将最上面的垫块 (1号垫块)从外支撑块 112的两个限位壁 134之间抽出。 然后立即操作第二批中的外部千斤顶,使得外部千斤顶伸长顶紧下一块垫块 122, 即 2号垫块。 此时, 2号垫块变成与外支撑块 112接触的垫块。 接下来, 将第一 批千斤顶的内部千斤顶下面的内部管桩 (即支撑内部千斤顶的管桩)的最上端切 掉一定长度。 然后, 将第二批千斤顶的内部千斤顶的顶杆再次顶起, 从而支撑 于底框架梁 (或内支撑块)与内部管桩之间。 到目前为止, 此时, 沉井的全部载荷 再次同时集中于第一批与第二批千斤顶上; 并且, 所有的外部支撑块上的 1 号 垫块 122均已经被抽去,且所有的内部支撑桩体的长度都已经被切短一定长度。 此后, 将限位壁 134 自最下端切掉一部分, 从而避免其最下端对沉井的下沉造 成障碍。 此后, 如图 12d及 13d所示, 再次让内部及外部千斤顶 120的顶杆缩回, 从而导致沉井 100再次整体向下沉降一定距离, 即外部千斤顶缩短一个行程。 Next, the second batch of jacks (including the inner and outer jacks) is shortened by a certain distance, such as 30 to 50 mm, and the uppermost block (block No. 1) is removed from the two limiting walls 134 of the outer support block 112. Pull out. The external jacks in the second batch are then immediately operated such that the outer jacks are extended to close the next block 122, i.e., the No. 2 pad. At this time, the No. 2 pad becomes a pad that is in contact with the outer support block 112. Next, the upper end of the inner pipe pile under the inner jack of the first jack (ie, the pipe pile supporting the inner jack) is cut to a certain length. Then, the ejector pins of the inner jacks of the second batch of jacks are lifted up again to be supported between the bottom frame beam (or the inner support block) and the inner pipe pile. So far, at this time, the entire load of the caisson is again concentrated on the first batch and the second batch of jacks at the same time; and, all the blocks 122 on the outer support block have been removed, and all the internals The length of the support pile has been cut to a certain length. Thereafter, the limiting wall 134 is cut away from the lowermost end to avoid obstruction of the sinking of the sinking hole at its lowermost end. Thereafter, as shown in Figures 12d and 13d, the rams of the inner and outer jacks 120 are again retracted, causing the sinker 100 to again settle down a certain distance again, i.e., the outer jacks are shortened by one stroke.
接下来的施工过程基本与结合图 12c及 13c描述的过程一致,只不过抽取的 垫块为 2号垫块。 然后, 过程继续进行到结合图 12d及 13d描述的步骤中。 这 样, 随着操作的不断循环, 垫块逐渐被抽出, 沉井逐渐下降, 直到所有的垫块 被抽出, 限位壁的所有部分均被切除之后。 操作所有的内外千斤顶, 使每个千 斤顶的顶杆向基座逐渐缩回, 沉井逐渐下沉至设定标高。 然后, 分批次拆除千 斤顶, 且在支撑桩体顶部上浇注承台混凝土, 直至全部支撑桩体顶部上都由承 台混凝土支撑着沉井, 进而实现准确终沉。  The subsequent construction process is basically the same as that described in connection with Figures 12c and 13c, except that the pad is 2 blocks. The process then proceeds to the steps described in connection with Figures 12d and 13d. Thus, as the operation continues to circulate, the block is gradually withdrawn and the caisson gradually descends until all the blocks are withdrawn and all parts of the limit wall are removed. Operate all the inner and outer jacks so that the jack of each jack gradually retracts toward the base, and the sinking sink gradually sinks to the set level. Then, the jacks are removed in batches, and the concrete of the caps is cast on the top of the supporting piles until the tops of all the supporting piles are supported by the concrete of the platform to achieve accurate final sinking.
在上述过程中, 由于随着沉井的逐渐下沉, 内部管桩需要不断地被截断, 然而由于内部管桩的大部分部位埋在地面内, 因此, 在施工时需要不断地将内 部管桩周围(即井内底)的土挖出。 这是借助图 14、 15 中的复合桥式龙门吊 500 以及与该复合桥式龙门吊 500配合的皮带机 600共同实现的。 两者设置在沉井 100的顶部上, 由于沉井 100的框架梁之间具有分格空间, 因此可以方便地将土 挖出。 此外, 复合桥式龙门吊 500也可以将挖掘机吊入井内进行挖土作业。  In the above process, the internal pipe pile needs to be continuously cut off due to the gradual sinking of the caisson. However, since most of the internal pipe pile is buried in the ground, it is necessary to continuously carry the internal pipe pile during construction. The soil around (ie, the inner bottom of the well) is dug out. This is achieved by means of the composite bridge gantry crane 500 of Figures 14 and 15 and the belt conveyor 600 mated with the composite bridge gantry crane 500. Both are placed on the top of the sinking well 100. Since there is a space between the frame beams of the sinking well 100, the soil can be easily excavated. In addition, the compound bridge gantry crane 500 can also hoist the excavator into the well for earthmoving operations.
概括地讲, 本发明首先提供一种沉井结构, 其包括封闭起来的井壁, 该井 壁具有内壁面及与该内壁面相对的外壁面, 所述内壁面之间设置多个互相交叉 的框架梁及靠近井壁最下端的底框架梁, 所述内壁面上形成多个等高的内支撑 块, 所述外壁面上设置多个等高的外支撑块, 且外支撑块高于内支撑块, 所述 的底框架梁底面为无刃脚的平面,所述井壁的最下端形成具有斜面的刃脚。  Broadly speaking, the present invention firstly provides a sinking structure comprising a closed well wall having an inner wall surface and an outer wall surface opposite the inner wall surface, wherein the inner wall surfaces are provided with a plurality of mutually intersecting a frame beam and a bottom frame beam near a lowermost end of the well wall, wherein the inner wall surface forms a plurality of inner support blocks of equal height, the outer wall surface is provided with a plurality of outer support blocks of equal height, and the outer support block is higher than the inner support block The support block, the bottom surface of the bottom frame beam is a bladeless plane, and the lowermost end of the well wall forms a blade having a sloped surface.
优选地,所述外支撑块包括基部及从该基部延伸向下的一对限位壁。并且, 基部及限位壁纵向地在井壁的整体高度上延伸。 所述限位壁内设置有矩形体形 状的导向垫轨。  Preferably, the outer support block includes a base and a pair of limiting walls extending downward from the base. Also, the base and the limiting wall extend longitudinally over the overall height of the well wall. A rectangular body-shaped guide pad rail is disposed in the limiting wall.
本发明同时提供一种将上述沉井结构准确沉入地面的方法。 其包括如下步 骤:  The invention also provides a method for accurately sinking the above-mentioned caisson structure into the ground. It includes the following steps:
(1) 选定一定施工区域, 并在该施工区域内打入多个支撑桩体且保持支撑桩 体的一部分长度暴露于施工区域的地面以上; (2)在该施工区域内构建一种沉井结构, 其包括封闭起来的井壁, 该井壁具 有内壁面及与该内壁面相对的外壁面, 所述内壁面之间设置多个在水平面和竖 向面内互相交叉的框架梁及靠近井壁最下端的底框架梁, 所述内壁面上形成多 个等高的内支撑块, 所述外壁面上设置多个等高的外支撑块, 且外支撑块高于 内支撑块, 所述的底框架梁底面为无刃脚的平面, 并且使沉井的底框架梁及内 支撑块借助千斤顶而分别支撑于所述施工区域内的部分支撑桩体上, 而沉井的 外支撑块则借助一组纵向叠压起来的垫块及支撑于最下端垫块下方的千斤顶而 支撑于施工区域的部分支撑桩体上, 且纵向叠压的多个垫块的周围设有对垫块 进行限位, 从而使垫块仅可在纵向方向内活动的限位装置, 支撑底框架梁与内 支撑块的支撑桩体及千斤顶分别构成了内部支撑桩体与内部千斤顶, 支撑外支 撑块的支撑桩体及千斤顶分别构成了外部支撑桩体及外部千斤顶, 所有内部及 外部千斤顶中的每一个包括基座及可在该基座内伸缩一定行程的顶杆, 所有千 斤顶的顶杆初始地处于伸长状态; 所有内部千斤顶的顶杆上端都与内支撑块及 底框架梁固定且悬吊于其下; 将所有内外千斤顶总体上划分为互相交错的第一 批千斤顶与第二批千斤顶; (1) Selecting a certain construction area, and driving a plurality of supporting piles in the construction area and keeping a part of the length of the supporting pile body exposed above the ground of the construction area; (2) constructing a sinking structure in the construction area, comprising a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, wherein the inner wall surface is provided with a plurality of horizontal planes a frame beam intersecting the vertical plane and a bottom frame beam near the lowermost end of the well wall, wherein the inner wall surface forms a plurality of equal height inner support blocks, and the outer wall surface is provided with a plurality of equal outer support blocks And the outer support block is higher than the inner support block, the bottom surface of the bottom frame beam is a bladeless plane, and the bottom frame beam and the inner support block of the sinking well are respectively supported by the jack in the part of the construction area Supporting the pile body, and the outer support block of the sinking well is supported on a part of the support pile body of the construction area by a set of longitudinally stacked blocks and a jack supported under the lowermost block, and longitudinally laminated A plurality of spacers are arranged around the spacers to limit the spacers, so that the spacers can only move in the longitudinal direction, and the support frame and the jack supporting the bottom frame beam and the inner support block respectively constitute an internal support Pile and inside The jack, the support pile and the jack supporting the outer support block respectively constitute an external support pile and an external jack, and each of the inner and outer jacks includes a base and a ram which can telescope a certain stroke in the base, all The jacks of the jacks are initially in an extended state; the upper ends of the jacks of all the inner jacks are fixed to the inner support block and the bottom frame beam and suspended under them; all the inner and outer jacks are generally divided into the first batch of jacks interlaced With the second batch of jacks;
(3)操作所有内外千斤顶, 使每个千斤顶的顶杆均向基座缩回一定距离, 并 使顶杆与基座之间尚留有 30毫米以上的行程间隙, 从而使沉井在施工区域内第 一次下沉一定深度, 并使井壁的刃脚插入到地面下;  (3) Operate all internal and external jacks, so that the jacks of each jack are retracted to the base at a certain distance, and there is still a travel clearance of more than 30 mm between the jack and the base, so that the sinking well is in the construction area. The first time it sinks a certain depth, and the cutting edge of the well wall is inserted under the ground;
(4)操作第一批千斤顶使其缩短 20~50毫米, 从而使得沉井的全部载荷完全 地集中于第二批千斤顶, 而第一批千斤顶则处于无载荷状态, 然后将设置于第 一批千斤顶的每个外支撑块与相应外部千斤顶之间的一组垫块中最高的一块垫 块抽去, 接下来操作第一批千斤顶中的每个外部千斤顶, 使该每个外部千斤顶 的顶杆相对于基座向上伸长, 从而使该组剩余垫块中最上端的垫块与外支撑块 接触并互相顶紧, 再将设置于第一批千斤顶中的每个内部千斤顶之下的内部支 撑桩体切断一定的长度, 从而使第一批千斤顶中的内部千斤顶的基座与切割后 剩余的内部支撑桩体之间形成较大的间隙, 接下来操作第一批千斤顶中的该每 个内部千斤顶, 使每个内部千斤顶的基座相对于顶杆向下降落, 从而使第一批 千斤顶中的每个内部千斤顶的基座与切割后剩余的内部支撑桩体的顶部接触顶 紧, 从而使得沉井的全部载荷同时集中于第一批及第二批千斤顶上; (4) Operating the first batch of jacks to shorten it by 20 to 50 mm, so that the entire load of the caisson is completely concentrated in the second batch of jacks, while the first batch of jacks are in a no-load state, and then will be set in the first batch. The highest one of the set of blocks between each outer support block of the jack and the corresponding external jack is removed, and then each external jack of the first plurality of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the first plurality of jacks The body is cut to a certain length so that a large gap is formed between the base of the inner jack in the first batch of jacks and the inner support pile remaining after cutting, and then each of the inner jacks of the first batch of jacks is operated. , causing the base of each internal jack to descend relative to the ejector pin, thereby making the first batch The base of each inner jack of the jack is in contact with the top of the inner support pile remaining after cutting, so that the entire load of the sinking well is concentrated on the first batch and the second batch of jacks at the same time;
(5)操作第二批千斤顶使其缩短 20~50毫米, 从而使沉井的全部载荷完全地 转移到第一批千斤顶, 进而使得第二批千斤顶处于无载荷状态, 然后将设置于 第二批千斤顶的每个外支撑块与相应外部千斤顶之间的一组垫块中最高的一块 垫块抽去, 接下来操作第二批千斤顶中的每个外部千斤顶, 使该每个外部千斤 顶的顶杆相对于基座向上伸长, 从而使该组剩余垫块中最上端的垫块与外支撑 块接触并互相顶紧, 再将设置于第二批千斤顶中的每个内部千斤顶之下的内部 支撑桩体切断一定的长度, 从而使第二批千斤顶中的内部千斤顶的基座与切割 后剩余的内部支撑桩体之间形成较大的间隙, 接下来操作第二批千斤顶中的每 个内部千斤顶, 使每个内部千斤顶的基座相对于顶杆向下降落, 从而使第二批 千斤顶中的每个内部千斤顶的基座与切割后剩余的内部支撑桩体的顶部接触顶 紧, 从而使得沉井的全部载荷同时集中于第一批及第二批千斤顶上;  (5) Operating the second batch of jacks to shorten the length of 20 to 50 mm, so that the entire load of the caisson is completely transferred to the first batch of jacks, so that the second batch of jacks are in a no-load state, and then will be set in the second batch. The highest one of the set of blocks between each outer support block of the jack and the corresponding external jack is removed, and then each external jack of the second batch of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the second plurality of jacks The body is cut to a certain length so that a large gap is formed between the base of the inner jack in the second batch of jacks and the inner support pile remaining after cutting, and then each inner jack of the second batch of jacks is operated, Lowering the base of each inner jack relative to the jack, thereby causing the base of each of the inner jacks of the second batch of jacks and the remaining inner portion after cutting Top support contacts the top of the pile tight, so that the entire load of the caisson while focusing on the first jacks and a second batch;
(6)拆除每个外部千斤顶顶杆周围的限位装置;  (6) Remove the limit device around each external jack ejector;
(7)操作所有内外千斤顶, 使每个千斤顶的顶杆均向基座缩回一定距离, 并 使顶杆与基座之间尚留有 30毫米以上的行程间隙, 从而使沉井在施工区域内再 次下沉一定深度;  (7) Operate all internal and external jacks, so that the jacks of each jack are retracted to the base by a certain distance, and there is still a travel clearance of more than 30 mm between the jack and the base, so that the sinking well is in the construction area. Sinking again within a certain depth;
(8)将沉井内井底的土挖去一层, 从而使每个内部支撑桩体的一部分从土中 暴露出来;  (8) Digging the soil at the bottom of the well in the sinking well, so that a part of each internal supporting pile is exposed from the soil;
(9)依次重复上述步骤 (4)、 (5)、 (6)、 (7)以及 (8), 从而使沉井不断下沉, 直至 每个外部千斤顶上的垫块均被抽走, 且使每个外部千斤顶均已直接顶住对应的 外支撑块;  (9) Repeat steps (4), (5), (6), (7), and (8) above in order to allow the caisson to sink continuously until the blocks on each of the external jacks are removed, and So that each external jack has directly supported the corresponding outer support block;
(10)操作所有的内外千斤顶, 使每个千斤顶的顶杆向基座逐渐缩回, 沉井逐 渐下沉至设定标高;  (10) Operate all the inner and outer jacks, so that the jack of each jack is gradually retracted toward the base, and the sinking sink gradually sinks to the set elevation;
(11)分批次拆除千斤顶, 且在支撑桩体顶部上浇注承台混凝土, 直至全部支 撑桩体顶部上都由 7|台混凝土支撑着沉井, 进而实现准确终沉。 具体地, 沉井结构的外支撑块包括基部及从该基部延伸的一对限位壁; 基 部及限位壁纵向地在井壁的整体高度上延伸; 所述限位壁内设置有矩形体形状 的导向垫轨; 所述一组垫块设置在基部与限位壁与导向垫轨三者之间围成的空 间内, 并且所述两个限位壁之间借助矩形体形状的限位板而互相连接起来, 从 而使得垫块被限制于两个限位壁、 导向垫轨及限位板所围成的空间内, 所述两 个限位壁、 导向垫轨及限位板共同构成了上述限位装置, 从而使垫块仅可纵向 地活动。 所述支撑桩体为预应力高强混凝土管桩或钢管桩, 且管桩须打入到地 下的基岩土持力层内。 (11) The jacks are removed in batches, and the concrete of the caps is cast on the top of the supporting piles until the top of all supporting piles is supported by 7 | concrete to achieve the final sinking. Specifically, the outer support block of the sinking structure includes a base and a pair of limiting walls extending from the base; the base and the limiting wall extend longitudinally over the overall height of the well wall; the limiting wall is provided with a rectangular body a shape of the guide pad rail; the set of spacers are disposed in a space enclosed between the base portion and the limiting wall and the guiding pad rail, and the limit between the two limiting walls by means of a rectangular body shape The plates are connected to each other such that the spacers are confined in the space defined by the two limiting walls, the guiding pad rails and the limiting plates, and the two limiting walls, the guiding pad rails and the limiting plates are combined The above-mentioned limiting device is such that the spacer can only move longitudinally. The supporting pile body is a prestressed high-strength concrete pipe pile or a steel pipe pile, and the pipe pile has to be driven into the underground bearing soil layer.
本发明的优点在于: 通过采用支撑块与千斤顶与管桩的相互配合操作的施 工方法, 使得沉井可以平稳地受控制地逐渐沉入预定地面内的深度, 且准确终 沉, 从而避免了传统施工方法中出现的突沉、 超沉、 中心偏移、 平面旋转、 竖 向歪沉、 变形断裂、 井内涌土、 井外塌陷等重大安全与质量事故。  The invention has the advantages that: by adopting a construction method in which the support block and the jack and the pipe pile cooperate with each other, the sinking well can be smoothly and controlledly gradually sinked into the depth in the predetermined ground, and the sinking is accurate, thereby avoiding the tradition. Major safety and quality accidents such as sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well occurred in the construction method.
所述内外支撑块可以是钢筋混凝土结构, 亦可以是钢结构。 内外支撑块可 以是单个独立支撑体块, 亦可以是水平连续的圏梁式或冠梁式或支撑体块。 另 外, 所述千斤顶可以为各种类型的机械升降机构, 而并不局限于文中公开的特 定千斤顶结构。 沉井的井壁外支撑块、 井壁内支撑块、 井内底框架梁等底面支 撑结构可以单独使用, 也可以灵活地组合使用, 其可以根据不同的沉井结构设 计需求而采用。 另外, 本发明可用于平面积更大、 形状更复杂、 单边尺寸更大 及地基更加软且下沉深度更深的沉井项目, 从而降低了造价, 获得了更好的经 济性。  The inner and outer support blocks may be reinforced concrete structures or steel structures. The inner and outer support blocks may be a single independent support block or a horizontal continuous truss or crown beam or support block. Additionally, the jacks can be various types of mechanical lifting mechanisms and are not limited to the particular jack structures disclosed herein. The bottom support structure of the well wall, the inner wall support block, the inner bottom frame beam and other bottom support structures may be used alone or in combination, which may be adopted according to different design requirements of the sinking structure. In addition, the present invention can be applied to a sinking project having a larger flat area, a more complicated shape, a larger single-sided size, a softer foundation, and a deeper sinking depth, thereby reducing the cost and obtaining a better economy.

Claims

权利要求 Rights request
1. 一种沉井结构, 其包括封闭起来的井壁, 该井壁具有内壁面 及与该内壁面相对的外壁面,所述内壁面之间设置多个在水平面和竖 向面内互相交叉的框架梁及靠近井壁最下端的底框架梁,其特征在于: 所述内壁面上形成多个等高的内支撑块,所述外壁面上设置多个等高 的外支撑块, 且外支撑块高于内支撑块, 所述底框架梁的底面为无刃 脚的平面, 所述井壁的最下端形成具有斜面的刃脚。 An open well structure comprising a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, the plurality of inner wall surfaces being disposed to intersect each other in a horizontal plane and a vertical plane The frame beam and the bottom frame beam near the lowermost end of the well wall are characterized in that: a plurality of equal height inner support blocks are formed on the inner wall surface, and a plurality of equal height outer support blocks are disposed on the outer wall surface, and The support block is higher than the inner support block, the bottom surface of the bottom frame beam is a bladeless surface, and the lowermost end of the well wall forms a beveled blade.
2. 根据权利要求 1 所述的沉井结构, 其特征在于: 所述外支撑 块包括基部及从该基部向下延伸的一对限位壁。 2. The sinking structure of claim 1 wherein: the outer support block includes a base and a pair of limit walls extending downwardly from the base.
3. 根据权利要求 2所述的沉井结构, 其特征在于: 所述基部及 限位壁纵向地在井壁的整体高度上延伸,且所述限位壁从外壁面突出, 且所述限位壁内设置有矩形体形状的导向垫轨,该导向垫轨固定在井 壁的外壁面上。 3. The sinkhole structure according to claim 2, wherein: the base portion and the limiting wall extend longitudinally over the entire height of the well wall, and the limiting wall protrudes from the outer wall surface, and the limit A guide pad rail having a rectangular body shape is disposed in the wall, and the guide pad rail is fixed on the outer wall surface of the well wall.
4.一种将沉井结构准确沉入地面的方法, 其包括如下步骤: 4. A method of accurately sinking a caisson structure into the ground, comprising the steps of:
(1) 选定一定施工区域, 并在该施工区域内打入多个支撑桩体 且保持支撑桩体的一部分长度暴露于施工区域的地面以上;  (1) Selecting a certain construction area, and driving a plurality of supporting piles in the construction area and keeping a part of the length of the supporting pile body exposed above the ground of the construction area;
(2)在该施工区域内构建一种沉井结构,其包括封闭起来的井壁, 该井壁具有内壁面及与该内壁面相对的外壁面,所述内壁面之间设置 多个在水平面和竖向面内互相交叉的框架梁及靠近井壁最下端的底 框架梁, 所述内壁面上形成多个等高的内支撑块, 所述外壁面上设置 多个等高的外支撑块, 且外支撑块高于内支撑块, 所述的底框架梁底 面为无刃脚的平面,并且使沉井的底框架梁及内支撑块借助千斤顶而 分别支撑于所述施工区域内的部分支撑桩体上,而沉井的外支撑块则 借助一组纵向叠压起来的垫块及支撑于最下端垫块下方的千斤顶而 支撑于施工区域的部分支撑桩体上,且纵向叠压的多个垫块的周围设 有对垫块进行限位, 从而使垫块仅可在纵向方向内活动的限位装置, 支撑底框架梁与内支撑块的支撑桩体及千斤顶分别构成了内部支撑 桩体与内部千斤顶,支撑外支撑块的支撑桩体及千斤顶分别构成了外 部支撑桩体及外部千斤顶,所有内部及外部千斤顶中的每一个包括基 座及可在该基座内伸缩一定行程的顶杆,所有千斤顶的顶杆初始地处 于伸长状态;所有内部千斤顶的顶杆上端都与内支撑块及底框架梁固 定且悬吊于其下;将所有内外千斤顶总体上划分为互相交错的第一批 千斤顶与第二批千斤顶; (2) constructing a sinking structure in the construction area, comprising a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, wherein the inner wall surface is provided with a plurality of horizontal planes a frame beam intersecting the vertical plane and a bottom frame beam near the lowermost end of the well wall, wherein the inner wall surface forms a plurality of equal height inner support blocks, and the outer wall surface is disposed a plurality of equal outer support blocks, wherein the outer support block is higher than the inner support block, the bottom surface of the bottom frame beam is a bladeless plane, and the bottom frame beam and the inner support block of the sinking well are respectively supported by the jack Partially supporting the pile in the construction area, and the outer support block of the sinking well is supported by a set of support piles in the construction area by means of a set of vertically stacked blocks and a jack supported under the lowermost block The support member of the bottom frame beam and the inner support block is supported by a plurality of blocks vertically and vertically stacked around the spacer block for limiting the spacer block so that the spacer block can only move in the longitudinal direction. The body and the jack respectively constitute an internal support pile body and an internal jack, and the support pile body and the jack supporting the outer support block respectively constitute an external support pile body and an external jack, and each of the inner and outer jacks includes a base and can be The ejector rod of the base is telescopically stretched, and the jacks of all the jacks are initially in an extended state; the upper ends of the ejector pins of all the internal jacks are fixed and suspended with the inner support block and the bottom frame beam Under it; all internal and external jack interwoven divided into first and second batch of jack jack on the whole;
(3)操作所有内外千斤顶,使每个千斤顶的顶杆均向基座缩回一定 距离, 并使顶杆与基座之间尚留有 30毫米以上的行程间隙, 从而使 沉井在施工区域内第一次下沉一定深度,并使井壁的刃脚插入到地面 下;  (3) Operate all internal and external jacks so that the jacks of each jack are retracted to the base at a certain distance, and there is still a travel clearance of more than 30 mm between the jack and the base, so that the sinking well is in the construction area. The first time it sinks a certain depth, and the cutting edge of the well wall is inserted under the ground;
(4)操作第一批千斤顶使其缩短 20~50毫米,从而使得沉井的全部 载荷完全地集中于第二批千斤顶,而第一批千斤顶则处于无载荷状态, 然后将设置于第一批千斤顶的每个外支撑块与相应外部千斤顶之间 的一组垫块中最高的一块垫块抽去,接下来操作第一批千斤顶中的每 个外部千斤顶,使该每个外部千斤顶的顶杆相对于基座向上伸长, 从 而使该组剩余垫块中最上端的垫块与外支撑块接触并互相顶紧,再将 设置于第一批千斤顶中的每个内部千斤顶之下的内部支撑桩体切断 一定的长度,从而使第一批千斤顶中的内部千斤顶的基座与切割后剩 余的内部支撑桩体之间形成较大的间隙,接下来操作第一批千斤顶中 的该每个内部千斤顶,使每个内部千斤顶的基座相对于顶杆向下降落, 从而使第一批千斤顶中的每个内部千斤顶的基座与切割后剩余的内 部支撑桩体的顶部接触顶紧,从而使得沉井的全部载荷同时集中于第 一批及第二批千斤顶上; (4) Operate the first batch of jacks to shorten it by 20~50 mm, so that the entire load of the caisson is completely concentrated in the second batch of jacks, while the first batch of jacks are in no-load condition, and then will be set in the first batch. The highest one of the set of blocks between each outer support block of the jack and the corresponding external jack is removed, and then each external jack of the first plurality of jacks is operated to make the ejector of each external jack Extending upward relative to the base, from And the uppermost block of the remaining blocks of the group is in contact with the outer support block and is mutually compacted, and then the inner support piles disposed under each of the inner jacks of the first batch of jacks are cut to a certain length, thereby A large gap is formed between the base of the inner jack in the first batch of jacks and the inner support pile remaining after cutting, and then each of the inner jacks of the first batch of jacks is operated to make the base of each inner jack The seat is lowered relative to the jack, so that the base of each inner jack of the first batch of jacks is in contact with the top of the inner support pile remaining after cutting, so that the entire load of the sinking well is concentrated at the same time One batch and the second batch of jacks;
(5)操作第二批千斤顶使其缩短 20~50毫米,从而使沉井的全部载 荷完全地转移到第一批千斤顶,进而使得第二批千斤顶处于无载荷状 态,然后将设置于第二批千斤顶的每个外支撑块与相应外部千斤顶之 间的一组垫块中最高的一块垫块抽去,接下来操作第二批千斤顶中的 每个外部千斤顶, 使该每个外部千斤顶的顶杆相对于基座向上伸长, 从而使该组剩余垫块中最上端的垫块与外支撑块接触并互相顶紧,再 将设置于第二批千斤顶中的每个内部千斤顶之下的内部支撑桩体切 断一定的长度,从而使第二批千斤顶中的内部千斤顶的基座与切割后 剩余的内部支撑桩体之间形成较大的间隙,接下来操作第二批千斤顶 中的每个内部千斤顶,使每个内部千斤顶的基座相对于顶杆向下降落, 从而使第二批千斤顶中的每个内部千斤顶的基座与切割后剩余的内 部支撑桩体的顶部接触顶紧,从而使得沉井的全部载荷同时集中于第 一批及第二批千斤顶上;  (5) Operating the second batch of jacks to shorten the length of 20 to 50 mm, so that the entire load of the caisson is completely transferred to the first batch of jacks, so that the second batch of jacks are in a no-load state, and then will be set in the second batch. The highest one of the set of blocks between each outer support block of the jack and the corresponding external jack is removed, and then each external jack of the second batch of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the second plurality of jacks The body is cut to a certain length so that a large gap is formed between the base of the inner jack in the second batch of jacks and the inner support pile remaining after cutting, and then each inner jack of the second batch of jacks is operated, The base of each inner jack is lowered relative to the jack, so that the base of each inner jack of the second batch of jacks and the inner support remaining after cutting Top tight contact with the top body, so that the entire load of the caisson while focusing on the first jacks and a second batch;
(6)拆除每个外部千斤顶顶杆周围的限位装置; (6) Remove the limit device around each external jack ejector;
(7)操作所有内外千斤顶,使每个千斤顶的顶杆均向基座缩回一定 距离, 并使顶杆与基座之间尚留有 30毫米以上的行程间隙, 从而使 沉井在施工区域内再次下沉一定深度; (7) Operate all the inner and outer jacks so that the jacks of each jack are retracted to the base a certain distance, and there is still a travel clearance of more than 30 mm between the jack and the base, so that the sinking hole is in the construction area. Sinking again within a certain depth;
(8)将沉井内井底的土挖去一层,从而使每个内部支撑桩体的一部 分从土中暴露出来;  (8) Digging the soil at the bottom of the well in the sinking well so that a part of each internal support pile is exposed from the soil;
(9)依次重复上述步骤 (4)、 (5)、 (6)、 (7)以及 (8), 从而使沉井不断 下沉, 直至每个外部千斤顶上的垫块均被抽走, 且使每个外部千斤顶 均已直接顶住对应的外支撑块;  (9) Repeat steps (4), (5), (6), (7), and (8) above in order to allow the caisson to sink continuously until the blocks on each of the external jacks are removed, and So that each external jack has directly supported the corresponding outer support block;
(10)操作所有的内外千斤顶, 使每个千斤顶的顶杆向基座逐渐缩 回, 沉井逐渐下沉至设定标高;  (10) Operate all the inner and outer jacks, so that the jack of each jack is gradually retracted toward the base, and the sinking hole gradually sinks to the set elevation;
(11)分批次拆除千斤顶, 且在支撑桩体顶部上浇注承台混凝土, 直至全部支撑桩体顶部上都由承台混凝土支撑着沉井,进而实现准确 终沉。  (11) The jacks are removed in batches, and the concrete of the caps is cast on the top of the supporting piles until the top of all the supporting piles is supported by the concrete of the caps to achieve the accurate sinking.
5. 根据权利要求 4 所述的方法, 其特征在于: 沉井结构的外支 撑块包括基部及从该基部延伸的一对限位壁;基部及限位壁纵向地在 井壁的整体高度上延伸; 所述限位壁从外壁面突出, 且其内设置有矩 形体形状的导向垫轨;所述一组垫块设置在基部与限位壁与导向垫轨 之间围成的空间内,并且所述两个限位壁之间借助矩形体形状的限位 板而互相连接起来, 从而使得垫块被限制于两个限位壁、导向垫轨及 限位板所围成的空间内, 所述两个限位壁、导向垫轨及限位板共同构 成了上述限位装置, 从而使垫块仅可纵向地活动。 5. The method according to claim 4, wherein: the outer support block of the sinking structure comprises a base and a pair of limiting walls extending from the base; the base and the limiting wall are longitudinally at an overall height of the well wall Extending; the limiting wall protrudes from the outer wall surface, and is provided with a rectangular body-shaped guiding pad rail; the group of the spacers is disposed in a space enclosed between the base portion and the limiting wall and the guiding pad rail, And the two limiting walls are connected to each other by a rectangular body-shaped limiting plate, so that the spacer is limited to the space surrounded by the two limiting walls, the guiding pad rail and the limiting plate. The two limiting walls, the guiding pad rail and the limiting plate together constitute the above-mentioned limiting device, so that the spacer can only move longitudinally.
6. 根据权利要求 4 所述的方法, 其特征在于: 所述支撑桩体为 预应力高强混凝土管桩或钢管桩,且管桩须打入到地下的基岩土持力 层内。 6. The method according to claim 4, wherein: the supporting pile body is a prestressed high-strength concrete pipe pile or a steel pipe pile, and the pipe pile has to be driven into the underground bearing soil layer.
PCT/CN2009/070038 2008-01-24 2009-01-06 Caisson structure and method of sinking the caisson structure into the ground exactly WO2009094912A1 (en)

Priority Applications (4)

Application Number Priority Date Filing Date Title
EP09705158A EP2246481A1 (en) 2008-01-24 2009-01-06 Caisson structure and method of sinking the caisson structure into the ground exactly
CN2009801026576A CN101918643B (en) 2008-01-24 2009-01-06 Caisson structure and method of sinking the caisson structure into the ground exactly
JP2010543364A JP2011510195A (en) 2008-01-24 2009-01-06 Caisson structure and method of precisely laying caisson structure underground
US12/864,235 US20100296876A1 (en) 2008-01-24 2009-01-06 Caisson structures and methods for precisely and stably sinking the caisson structures into ground

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN200810026012.6 2008-01-24
CN200810026012A CN101418573B (en) 2008-01-24 2008-01-24 Caisson structure and method for smoothly and accurately sinking caisson structure into earth surface

Publications (1)

Publication Number Publication Date
WO2009094912A1 true WO2009094912A1 (en) 2009-08-06

Family

ID=40629560

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2009/070038 WO2009094912A1 (en) 2008-01-24 2009-01-06 Caisson structure and method of sinking the caisson structure into the ground exactly

Country Status (5)

Country Link
US (1) US20100296876A1 (en)
EP (1) EP2246481A1 (en)
JP (1) JP2011510195A (en)
CN (2) CN101418573B (en)
WO (1) WO2009094912A1 (en)

Families Citing this family (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101591915B (en) * 2009-06-25 2014-12-17 丁慈鑫 Outer support system for supporting caisson structure and construction method thereof
CN101851930B (en) * 2010-01-15 2012-10-03 丁慈鑫 Sinking device of open caisson and sinking method of open caisson with same
CN101787703B (en) * 2010-03-17 2011-06-15 中国二十二冶集团有限公司 Sinking construction method of sinking well with geology of gravel and pebble beds under saturated water condition
CN101942839B (en) * 2010-09-10 2012-05-02 丁慈鑫 Construction method for entering inside of open caisson and transporting soil
JP4942230B1 (en) * 2010-11-29 2012-05-30 賢治 町筋 Submersible method and equipment for submerged method
CN102900090A (en) * 2011-07-29 2013-01-30 邹宗煊 Non-inclined dry-operation open caisson capable of preventing water burst and land subsidence and construction method thereof
CN102926395A (en) * 2012-11-22 2013-02-13 天津华悦土木工程质量检测有限公司 Open caisson construction method of flowing muddy mollisol
CN103422508B (en) * 2013-03-08 2015-09-30 中国建筑第四工程局有限公司 Deep foundation ditch inner support platform structure machinery is vexed tears method and structure open
JP6219666B2 (en) * 2013-10-10 2017-10-25 株式会社安藤・間 Pneumatic caisson installation method
CN105201003B (en) * 2015-10-15 2018-04-20 北京中岩大地科技股份有限公司 A kind of open caisson construction method and method for dismounting
CN105696614B (en) * 2016-01-27 2018-02-02 中国十七冶集团有限公司 One kind solves the super heavy resetting means of open caisson using top of above leaving behind
CN108999202A (en) * 2018-08-23 2018-12-14 中铁六局集团广州工程有限公司 Prevent the super heavy method and device of open caisson
CN109098201A (en) * 2018-10-12 2018-12-28 西南交通大学 A kind of super plane area portions prestressed concrete well foundation and its construction method
CN109518691B (en) * 2018-11-27 2020-10-20 张利均 Pile extractor
KR101960413B1 (en) * 2019-01-07 2019-03-20 김준성 Structure construction method
CN109826218A (en) * 2019-03-25 2019-05-31 中国十七冶集团有限公司 A kind of open caisson end heavy stage hydraulic lifting deviation-rectifying system
CN110093942A (en) * 2019-05-30 2019-08-06 安徽省交通控股集团有限公司 A kind of assembled radical well foundation of two-wall hollow
CN110485470B (en) * 2019-08-08 2021-05-04 郑州安源工程技术有限公司 Rectangular working well with pre-arranged jacking pipe door opening and sliding type rear wall in water-rich stratum and construction method of rectangular working well
CN112523243B (en) * 2019-09-19 2024-06-18 派利欧洲公司 Caisson template
CN111677008B (en) * 2020-06-02 2021-11-16 福州市恒坤建设发展有限公司 Construction method of assembled underground garage
CN111622251A (en) * 2020-06-15 2020-09-04 北京中岩智泊科技有限公司 Assembly type open caisson structure and construction method thereof
CN111749258A (en) * 2020-06-30 2020-10-09 中国二十二冶集团有限公司 Construction method of tire mold of edge foot of cyclone well
CN112854296B (en) * 2021-01-13 2022-04-15 河南城建学院 Vertical wall sliding installation supporting device and construction method thereof
CN113737833B (en) * 2021-09-09 2022-09-09 中建七局交通建设有限公司 Open caisson construction formwork and construction method thereof
CN113833001A (en) * 2021-09-22 2021-12-24 济南市市政工程设计研究院(集团)有限责任公司 Detachable rolling sinking type open caisson structure and construction process
CN115262649A (en) * 2022-08-05 2022-11-01 安徽科尼盛机电科技有限责任公司 Composite construction's waterproof theftproof well lid

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1044144A (en) * 1989-01-14 1990-07-25 全球海洋问题研究所 Caisson
JP2003171941A (en) * 2001-12-03 2003-06-20 Ishikawajima Harima Heavy Ind Co Ltd Caisson and its construction method
CN1441127A (en) * 2003-04-09 2003-09-10 王民寿 Caisson structure and fast construction method of opencaisson
KR20050097735A (en) * 2004-04-02 2005-10-10 (주) 선암기술연구소 Caisson installed support means and construction method of underwater structure using it
CN101003974A (en) * 2006-12-22 2007-07-25 中铁大桥局股份有限公司 Method for constructing groundwork for large-scale sinking well in deep water
CN201176597Y (en) * 2008-01-28 2009-01-07 丁慈鑫 Sinking well structure

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU912836A1 (en) * 1980-07-07 1982-03-15 Государственный Институт По Проектированию Горнорудных Предприятий Центральных Районов Рсфср "Центргипроруда" Method of driving a sinkable well into soil
US4938634A (en) * 1989-06-26 1990-07-03 Lee Yuan Ho Process for lowering basement
CN2193891Y (en) * 1993-06-17 1995-04-05 张卡鸣 Double-wall cylindrical open well frame
CN1043483C (en) * 1994-07-30 1999-05-26 海勃湾矿务局基本建设第一工程处 Open caisson method of inclined shaft
CN1053246C (en) * 1994-08-01 2000-06-07 胡泽嘉 Construction method and device using large open caisson lowering water level in high-storied buiding and under ground engineering
CN1884719A (en) * 2006-06-08 2006-12-27 中铁大桥局股份有限公司 High opening, low edge-foot double-wall steel-cofferdams construction process for coffer without back cover concrete

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1044144A (en) * 1989-01-14 1990-07-25 全球海洋问题研究所 Caisson
JP2003171941A (en) * 2001-12-03 2003-06-20 Ishikawajima Harima Heavy Ind Co Ltd Caisson and its construction method
CN1441127A (en) * 2003-04-09 2003-09-10 王民寿 Caisson structure and fast construction method of opencaisson
KR20050097735A (en) * 2004-04-02 2005-10-10 (주) 선암기술연구소 Caisson installed support means and construction method of underwater structure using it
CN101003974A (en) * 2006-12-22 2007-07-25 中铁大桥局股份有限公司 Method for constructing groundwork for large-scale sinking well in deep water
CN201176597Y (en) * 2008-01-28 2009-01-07 丁慈鑫 Sinking well structure

Also Published As

Publication number Publication date
US20100296876A1 (en) 2010-11-25
EP2246481A1 (en) 2010-11-03
JP2011510195A (en) 2011-03-31
CN101918643B (en) 2012-10-10
CN101418573B (en) 2012-09-05
CN101918643A (en) 2010-12-15
CN101418573A (en) 2009-04-29

Similar Documents

Publication Publication Date Title
WO2009094912A1 (en) Caisson structure and method of sinking the caisson structure into the ground exactly
KR101859367B1 (en) Method for constructing vertical structure in vertical tunnel using top down method
CN103912134B (en) Existing building underground space structure and construction method in situ
CN102704705A (en) Building long-stroke redescending-free multi-point synchronous jacking method
CN105804119A (en) Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure
CN1888331A (en) Guide pit type manual pot holing pile reinforing and underpinning method for building foundation and composite supporting pile
CN103526781B (en) A kind of ancient architecture foundation integrated pallet base isolation reinforcement structure and construction method thereof
CN103669385A (en) Method for improving pile group bearing capacity by means of reticular pile foundations
CN112195779A (en) Multifunctional trestle construction method suitable for thick pebble layer
CN201176597Y (en) Sinking well structure
CN112195928B (en) Pile plate composite structure for foundation pit support
CN111677008B (en) Construction method of assembled underground garage
CN205024719U (en) Pile foundation and integrated reverse construction vertical braces system of underground continuous wall
CN210315664U (en) Reverse construction method foundation pit rectangular lattice column positioning and verticality adjusting device
CN203603176U (en) Historic building foundation overall tray shock insulating and reinforcing structure
CN203755173U (en) Formwork device used for hydraulic climbing of bridge high pier
CN210946864U (en) Landscape structure foundation for soft stratum
CN202745081U (en) Large-size rubble concrete settlement joint template system
CN201620419U (en) Steel support structure
CN206319314U (en) A kind of additional cuff back-up sand building stones prefabricated pile
CN206110185U (en) Prestressing force is assembled and is pressed heavy indoor ground of formula storehouse structure
CN219569001U (en) Node structure for avoiding additional overhead layer of primary foundation reinforcement
CN220579971U (en) Special-shaped pile capable of being used as anti-floating roof
CN217630057U (en) Body foundation structure and dry quenching furnace
CN202644566U (en) Foundation bolt box with dense steel mesh

Legal Events

Date Code Title Description
WWE Wipo information: entry into national phase

Ref document number: 200980102657.6

Country of ref document: CN

121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 09705158

Country of ref document: EP

Kind code of ref document: A1

WWE Wipo information: entry into national phase

Ref document number: 2010543364

Country of ref document: JP

WWE Wipo information: entry into national phase

Ref document number: 12864235

Country of ref document: US

NENP Non-entry into the national phase

Ref country code: DE

WWE Wipo information: entry into national phase

Ref document number: 2009705158

Country of ref document: EP