WO2009094912A1 - Caisson structure and method of sinking the caisson structure into the ground exactly - Google Patents
Caisson structure and method of sinking the caisson structure into the ground exactly Download PDFInfo
- Publication number
- WO2009094912A1 WO2009094912A1 PCT/CN2009/070038 CN2009070038W WO2009094912A1 WO 2009094912 A1 WO2009094912 A1 WO 2009094912A1 CN 2009070038 W CN2009070038 W CN 2009070038W WO 2009094912 A1 WO2009094912 A1 WO 2009094912A1
- Authority
- WO
- WIPO (PCT)
- Prior art keywords
- jacks
- jack
- sinking
- batch
- base
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
- E02D23/08—Lowering or sinking caissons
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D23/00—Caissons; Construction or placing of caissons
Definitions
- the invention relates to a building structure and a construction method, in particular to a sinking structure and a construction method for smoothly sinking the sinking structure into the ground and accurately sinking. Background technique
- Shenjing As a structure of underground space structures or deep foundation or deep foundation pit support construction, Shenjing has its unique range of engineering application conditions. For example, in the case of better hard soil quality, the sinking technology is not used, and other foundation pit construction techniques are more convenient and economical. However, in soft soil areas, due to the looseness of geology and poor stability, the use of general foundation pit support structures will result in high support costs, and at the same time lead to longer construction period and higher construction risks.
- the sinking well is widely used in the construction of the soft soil foundation of the alluvial layer of the river and the river.
- the application of the sinking well under soft soil foundation conditions is prone to sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well if the design and construction operations are improper. Wait for major safety and quality incidents. This is mainly caused by the congenital deficiency of the vertical plane stiffness (or the minimum vertical section torsional stiffness) of some parts of the caisson (such as the diagonal of the rectangular caisson); it is also due to the current caisson structure and the corresponding construction.
- the method can not guarantee the smooth sinking and accurate final sinking of the sinking well in the engineering sense. Therefore, during the actual construction process, most of the caissons are swaying and swaying down, and the construction danger is very likely to occur. During the sinking process, it is necessary to constantly correct and correct the wells, and try to keep the balance of the caisson as much as possible. The construction difficulty is increased, the construction period is extended, and the cost is continuously rising.
- the shortcomings of these traditional technologies are the technical problems that need to be solved in the long-term construction of the well, but have not been solved.
- the construction of the foundation pit support by the caisson construction method is one of the research directions of the engineering community.
- the largest area of the caisson can only meet the foundation pit construction of small and medium-sized area.
- the speed of development in more complicated and cost-effective ways has limited the expansion of the use of sinking wells; this is also a long-standing problem in the design and application of sinking wells. Summary of the invention
- the main object of the present invention is to provide a sinking structure, which is formed by providing uniformly distributed supporting block points on a conventional sinking structure, and by means of a uniform support of the supporting pile and the jack, greatly The rigidity requirement of the caisson structure is reduced, and the caisson structure is not easily deformed or broken, thereby improving the safety of construction and use.
- Another object of the present invention is to provide a construction method for smoothly sinking a sinking well into the ground and accurately sinking, which can ensure that the caisson gradually sinks and accurately sinks in a controlled manner, thereby avoiding the conventional construction.
- Major safety and quality accidents such as sudden subsidence, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well occur.
- a sinking structure includes a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, wherein the inner wall surface is disposed between a plurality of horizontal and vertical planes Frame beams that intersect each other and bottom frame beams near the bottom of the well wall.
- a plurality of equal height inner support blocks are formed on the inner wall surface
- a plurality of equal outer outer support blocks are disposed on the outer wall surface
- the outer support block is higher than the inner support block
- the bottom frame beam bottom surface is bladeless
- the plane of the foot, the lowermost end of the well wall forms a beveled foot.
- the present invention provides a method for accurately sinking a sinking structure into the ground and accurately sinking, comprising the following steps:
- a sinking structure in the construction area, comprising a closed well wall having an inner wall surface and an outer wall surface opposite to the inner wall surface, wherein the inner wall surface is provided with a plurality of horizontal planes a frame beam intersecting the vertical plane and a bottom frame beam near the lowermost end of the well wall, wherein the inner wall surface forms a plurality of equal height inner support blocks, and the outer wall surface is provided with a plurality of equal outer support blocks And the outer support block is higher than the inner support block, the bottom surface of the bottom frame beam is a bladeless plane, and the bottom frame beam and the inner surface of the sinking well
- the support blocks are respectively supported on the partial support piles in the construction area by means of jacks, and the outer support blocks of the sinking holes are supported by a set of vertically stacked blocks and a jack supported under the lowermost block.
- a part of the supporting pile body in the construction area, and a plurality of longitudinally laminating blocks are arranged around the spacer block, so that the spacer block can only move in the longitudinal direction, and the bottom frame beam is supported
- the support pile and the jack of the inner support block respectively constitute an internal support pile body and an internal jack
- the support pile body and the jack supporting the outer support block respectively constitute an external support pile body and an external jack
- each of the inner and outer jacks a ram including a pedestal and a telescopic extension within the pedestal, the ejector pins of all jacks are initially in an extended state;
- the upper ends of the ejector pins of all internal jacks are fixed and suspended from the inner support block and the bottom frame beam Underneath; all internal and external jacks are generally divided into the first batch of jacks and the second batch of jacks;
- each external jack of the first plurality of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the first plurality of jacks
- the body is cut to a certain length so that a large gap is formed between the base of the inner jack in the first batch of jacks and the inner support pile remaining after cutting, and then each of the inner jacks of the first batch of jacks is operated.
- each inner jack is lowered relative to the jack, so that the base of each inner jack of the first batch of jacks and the remaining inner portion after cutting Top support contacts the top of the pile tight, so that the entire load of the caisson while focusing on the first jacks and a second batch;
- each of the outer jacks of the second batch of jacks is operated, so that the top rod of each of the outer jacks is elongated upward relative to the base, so that the uppermost blocks of the remaining blocks of the set are externally
- the support blocks are in contact with each other and are tightened to each other, and then the internal support piles disposed under each of the inner jacks of the second batch of jacks are cut to a certain length, so that the bases of the inner jacks in the second batch of jacks are cut and A large gap is formed between the remaining inner support piles, and then each inner jack of the second batch of jacks is operated, so that the base of each inner jack is lowered relative to the jack, thereby making the second batch of jacks
- the base of each internal jack is in contact with the top of the inner support pile remaining after cutting, so that the entire load of the sinking well is concentrated on the first
- the invention has the advantages that: since a plurality of support blocks and support points are arranged on the appropriate part of the sinking well, the sinking well is supported uniformly by the support pile body and the jack, thereby greatly reducing the rigidity requirement of the sinking structure.
- the structure of the caisson is not easily deformed or broken, thereby improving the safety of construction and use.
- the sinking well can be smoothly and controlled to gradually sink into the depth of the predetermined ground and accurately sink, thereby avoiding It avoids major safety and quality accidents such as sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well.
- Fig. 1 shows a plan view of a plan view of the sinker 100 of the present invention, showing the distribution of the entire support pile on the plane of the sinking plane and the mutual cooperation between the support pile and the sinking well.
- Figure 2 shows a front elevational view of the sinking well shown in Figure 1, showing the mating relationship of a plurality of outer support blocks formed on the outer wall surface of the well wall with the blocks and corresponding pipe piles that are driven into the ground.
- Figure 3 shows the cross-sectional structure of the sinking well shown in Figure 1 along the B-B direction, showing the fit of the blade foot to the ground and the fit between the bottom frame beam in the sinking well and the corresponding pipe pile that is driven into the ground.
- Figure 4 shows a cross-sectional structural view of the sinking well shown in Figure 3 along the A-A direction.
- Figure 5 shows a cross-sectional structural view of the sinking well shown in Figure 1 along the C-C direction.
- Fig. 6 partially shows the mutual positional relationship between a part of the outer support block of the sinking well shown in Fig. 2 and the block and the jack and the pipe pile which is driven into the ground.
- Fig. 7 is a cross-sectional structural view showing the structure shown in Fig. 6 taken along the E-E direction.
- Fig. 8 is a cross-sectional structural view showing the structure shown in Fig. 6 taken along the line D-D.
- Figure 9 shows the façade structure of the guide pad rail shown in Figure 8.
- Figure 10 shows the planar structure of the spacer shown in Figure 6.
- Figure 11 shows the façade structure of the limit plate shown in Figure 6.
- Figures 12a-12d sequentially show the variation of the outer support block, the block, the jack and the corresponding pipe pile in the process of sinking the sinking well shown in Figures 1-11.
- Figures 13a-13d sequentially show the changes of the outer support blocks, the blocks, the jacks and the corresponding pipe piles in the process of sinking the sinking wells shown in Figures 1-11, and the underside of the frame beams at the bottom of the caisson The change of the jack and the pipe pile supporting the jack.
- Figure 14 shows an arrangement of a plan for the removal of soil from the sinking well and the sinking well.
- Figure 15 shows an arranging elevational view of a device and a sinking well for removing soil from a sinking well.
- the sinking well 100 is generally a rectangular body structure, such as a reinforced concrete structure or a steel structure.
- the sinking well 100 includes four well walls 102 that are connected to each other to be closed, and any two opposing well walls 102 are parallel to each other such that the four well walls 102 together form a rectangular shape.
- Each well wall 102 has an inner wall surface 110 and an outer wall surface 108 opposite the inner wall surface 110.
- a plurality of frame beams parallel to each other in the horizontal and vertical planes are disposed between the inner wall faces 110 of any two opposing well walls 102.
- frame longitudinal members 104 may be disposed between two laterally disposed well walls 102; and frame beams 106 may be disposed between two longitudinally disposed well walls 102. And the cross beam 106 and the corresponding stringers 104 are orthogonal to one another such that they generally provide the structural strength of the horizontal support for the caisson 100.
- the frame beam and the longitudinal beam of the bottom end of the sinking well 100 constitute the bottom horizontal frame beam 126 of the caisson (refer to Figure 3), which is in the subsequent construction process. It is mainly used to partially support the sinking well 100.
- Each frame beam is fixedly coupled to the respective well wall 102 by a frame post 116 disposed on the inner wall surface 110 of the well wall 102.
- an inner partition wall 124 (refer to Fig. 3) is provided between the necessary frame beams, which further enhances the overall structural strength of the caisson 100.
- an outer support block 112 of a plurality of equal heights is disposed on the outer wall surface 108 of each well wall 102 adjacent the top end of the caisson 100 (i.e., away from the ground). And the height of the outer support block 112 on all of the well walls 102 is the same.
- an inner support block 114 of a plurality of equal heights is also disposed on the inner wall surface 110 of each well wall 102. And the height of the inner support block 114 on all of the well walls 102 is the same.
- the height of all the inner support blocks 114 is much lower than the height of the outer support block 112, due to the presence of these inner and outer support blocks (commonly known as the ox legs), and the support wells are supported uniformly by the support piles and the jacks, thereby The rigidity requirement of the sinking structure is greatly reduced.
- the invention makes the structural section of the sinking structure not to be made very large, and the safety of settlement and use of the sinking construction can be realized.
- the bottom of each well wall 102 (with ground)
- the face-contacting portion) forms a beveled blade foot 128 which, because of its relatively sharp edge, facilitates the sinker 100 to easily sink below the ground.
- the tubular pile 118 is preferably driven below the ground 300 with its top end exposed a distance above the ground 300, and the tubular pile 118 is preferably supported by any two bottom frame beams of the sinking well 100 (beams)
- the distribution position of the pipe pile is represented by a black circle or a white circle.
- a jack 120 for adjusting the height of the caisson is disposed between the pipe pile 118 that is driven into the ground and the inner support block 114 (refer to FIG. 5); similarly, the pipe pile 118 that penetrates the ground and the bottom support beam 126 are also provided with useful
- the jack 120 for adjusting the height of the caisson (refer to FIG. 3); and between the pipe pile 118 and the outer support block 112 that are driven into the ground, in addition to the jack 120, the jack 120 is also movable between the jack 120 and the outer support block 112.
- a plurality of spacers 122 are provided (refer to FIGS. 2 and 5). In order to facilitate the sinking operation, the tops of the jacks in the well are fixed to each other and corresponding to the upper structure, and can be suspended.
- each outer support block 112 protrudes outwardly from the outer wall surface 108 of the well wall 102.
- Each outer support block 112 has a base portion 160 that projects outwardly from the outer wall surface 108 and two limit walls 134 that project downwardly from the base portion 160. And the two limiting walls 134 and the base portion 160 and the outer wall surface 108 together form a semi-closed space.
- a hollow rectangular block-shaped guide pad rail 130 is disposed in the semi-closed space, and a rectangular block-shaped spacer 122 is accommodated between the guide pad rail 130 and the two limiting walls 134.
- the two limiting walls 134 are connected to each other by the limiting plate 132, thereby limiting the spacer 122 to the space enclosed by the two limiting walls 134, the guiding pad rail 130 and the limiting plate 132.
- the spacer 122 does not fall off the side. This configuration, which ensures that the spacer 122 does not fall from the side during sinking of the sinking, forms a stop for the spacer 122.
- each of the jacks 120 can be a conventional jack for adjusting the height of the sinking well.
- the jack 120 can include a base 504 and can be on the base 504 relative to the base 504 at a handle (not shown).
- the device that moves down and down the position that is, the elongated or shortened jack 502.
- the limit wall 134 described above extends longitudinally over the entire height of the caisson 100.
- the limiting wall 134 is a temporary structure, which is gradually cut off as the block gradually withdraws during the sinking of the sinking hole, and the limiting wall 134 will be completely completed after all the blocks are extracted. The ground was removed.
- the sinking well of the present invention is limited to such a planar shape.
- the sinking well can be a sinking well with a circular caisson, a regular polygon, a long rectangular shape, or various asymmetrical shaped planar shapes.
- FIG. 12a-13d illustrate the operation of the method of the present invention. Referring first to Figures 12a and 13a, the initial states of the exterior and interior of the caisson are shown, respectively. That is, a predetermined number of pipe piles 118 are first driven into the ground so that the caisson 100 is supported on the pipe piles 118.
- the outer support block 112 is supported on the pipe pile 118 by means of a plurality of blocks 122 and a jack 120 between the lowermost pad 122 and the corresponding pipe pile 118; the bottom frame beam 126 inside the caisson 100 is directly
- the jacks 120 are supported on the corresponding pipe piles 118; at the same time, the inner support blocks inside the caisson 100 are also supported directly on the corresponding pipe piles 118 by means of the jacks 120 (refer to FIG. 5).
- the weight (load) of the caisson 100 acts on all (in the well wall and the well wall) pipe pile 118. In other words, all the pipe piles 118 are simultaneously subjected to the weight of the sinking well 100.
- all of the jacks 120 are in an extended state, that is, the jacks 502 on the base 504 are at the highest positions.
- the cutting edge 128 of the sinking well 100 is initially inserted into the ground.
- all the inner and outer jacks are generally divided into the first batch of jacks (such as the jack represented by the black circle in Fig. 1) and the second jacks (such as the jack represented by the white circle in Fig. 1). .
- the jack 502 of the 120 is shortened.
- the integral sinking hole 100 is correspondingly lowered due to the shortening of the jack 502.
- the distance is such that the cutting edge of the caisson 100 is inserted into the ground again, and part of the weight of the whole caisson 100 effectively compresses the soil underneath, thereby increasing the horizontal embedding effect of the foundation soil on the caisson 100, increasing The stability of the sinking well 100.
- the foundation soil began to share the weight of the 100 parts of the caisson, the load on the jack was immediately lowered.
- Figures 12c and 13c illustrate the next steps of the present invention.
- the blocks 122 outside the well wall are sequentially numbered from 1 to 1 from the top to the bottom, and the uppermost block number is No. 1 pad, and the rest are analogous.
- the first batch of jacks (including the inner and outer jacks) is first shortened by a certain distance, such as 30 ⁇ 50 mm, and the uppermost block (block No. 1) is taken from the outside.
- the two limiting walls 134 of the support block 112 are drawn out.
- the external jacks in the first batch are then immediately operated, causing the outer jacks to elongate against the next block 122, i.e., the No. 2 block.
- the spacer No. 2 becomes a spacer which is in contact with the outer support block 112.
- the upper end of the inner pipe pile under the inner jack of the first jack i.e., the pipe pile supporting the inner jack, also referred to as the inner support pile
- the inner support pile i.e., the pipe pile supporting the inner jack, also referred to as the inner support pile
- the ejector pins of the inner jacks of the first jacks are lifted up again to support between the bottom frame beam (or inner support block) and the inner pipe pile.
- the entire load of the sinking well is concentrated on the first batch and the second batch of jacks.
- the limiting wall 134 is cut away from the lowermost end to prevent the lowermost end from obstructing the sinking of the sinking well.
- the second batch of jacks (including the inner and outer jacks) is shortened by a certain distance, such as 30 to 50 mm, and the uppermost block (block No. 1) is removed from the two limiting walls 134 of the outer support block 112. Pull out.
- the external jacks in the second batch are then immediately operated such that the outer jacks are extended to close the next block 122, i.e., the No. 2 pad.
- the No. 2 pad becomes a pad that is in contact with the outer support block 112.
- the upper end of the inner pipe pile under the inner jack of the first jack ie, the pipe pile supporting the inner jack
- the ejector pins of the inner jacks of the second batch of jacks are lifted up again to be supported between the bottom frame beam (or the inner support block) and the inner pipe pile. So far, at this time, the entire load of the caisson is again concentrated on the first batch and the second batch of jacks at the same time; and, all the blocks 122 on the outer support block have been removed, and all the internals The length of the support pile has been cut to a certain length. Thereafter, the limiting wall 134 is cut away from the lowermost end to avoid obstruction of the sinking of the sinking hole at its lowermost end.
- the subsequent construction process is basically the same as that described in connection with Figures 12c and 13c, except that the pad is 2 blocks.
- the process then proceeds to the steps described in connection with Figures 12d and 13d.
- the block is gradually withdrawn and the caisson gradually descends until all the blocks are withdrawn and all parts of the limit wall are removed.
- Operate all the inner and outer jacks so that the jack of each jack gradually retracts toward the base, and the sinking sink gradually sinks to the set level.
- the jacks are removed in batches, and the concrete of the caps is cast on the top of the supporting piles until the tops of all the supporting piles are supported by the concrete of the platform to achieve accurate final sinking.
- the internal pipe pile needs to be continuously cut off due to the gradual sinking of the caisson.
- the soil around ie, the inner bottom of the well
- the soil around is dug out. This is achieved by means of the composite bridge gantry crane 500 of Figures 14 and 15 and the belt conveyor 600 mated with the composite bridge gantry crane 500. Both are placed on the top of the sinking well 100. Since there is a space between the frame beams of the sinking well 100, the soil can be easily excavated.
- the compound bridge gantry crane 500 can also hoist the excavator into the well for earthmoving operations.
- the present invention firstly provides a sinking structure comprising a closed well wall having an inner wall surface and an outer wall surface opposite the inner wall surface, wherein the inner wall surfaces are provided with a plurality of mutually intersecting a frame beam and a bottom frame beam near a lowermost end of the well wall, wherein the inner wall surface forms a plurality of inner support blocks of equal height, the outer wall surface is provided with a plurality of outer support blocks of equal height, and the outer support block is higher than the inner support block
- the support block, the bottom surface of the bottom frame beam is a bladeless plane, and the lowermost end of the well wall forms a blade having a sloped surface.
- the outer support block includes a base and a pair of limiting walls extending downward from the base. Also, the base and the limiting wall extend longitudinally over the overall height of the well wall. A rectangular body-shaped guide pad rail is disposed in the limiting wall.
- the invention also provides a method for accurately sinking the above-mentioned caisson structure into the ground. It includes the following steps:
- each external jack of the first plurality of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the first plurality of jacks
- the body is cut to a certain length so that a large gap is formed between the base of the inner jack in the first batch of jacks and the inner support pile remaining after cutting, and then each of the inner jacks of the first batch of jacks is operated.
- each internal jack causing the base of each internal jack to descend relative to the ejector pin, thereby making the first batch
- the base of each inner jack of the jack is in contact with the top of the inner support pile remaining after cutting, so that the entire load of the sinking well is concentrated on the first batch and the second batch of jacks at the same time;
- each external jack of the second batch of jacks is operated to make the ejector of each external jack Extending upward relative to the base such that the uppermost of the remaining blocks of the set are in contact with the outer support block and are mutually tightened, and the inner support piles disposed under each of the inner jacks of the second plurality of jacks
- the body is cut to a certain length so that a large gap is formed between the base of the inner jack in the second batch of jacks and the inner support pile remaining after cutting, and then each inner jack of the second batch of jacks is operated, Lowering the base of each inner jack relative to the jack, thereby causing the base of each of the inner jacks of the second batch of jacks and the remaining inner portion after cutting Top support contacts the top of the pile tight, so that the entire load of the caisson while focusing on the first jacks and a second batch;
- the outer support block of the sinking structure includes a base and a pair of limiting walls extending from the base; the base and the limiting wall extend longitudinally over the overall height of the well wall; the limiting wall is provided with a rectangular body a shape of the guide pad rail; the set of spacers are disposed in a space enclosed between the base portion and the limiting wall and the guiding pad rail, and the limit between the two limiting walls by means of a rectangular body shape
- the plates are connected to each other such that the spacers are confined in the space defined by the two limiting walls, the guiding pad rails and the limiting plates, and the two limiting walls, the guiding pad rails and the limiting plates are combined
- the above-mentioned limiting device is such that the spacer can only move longitudinally.
- the supporting pile body is a prestres
- the invention has the advantages that: by adopting a construction method in which the support block and the jack and the pipe pile cooperate with each other, the sinking well can be smoothly and controlledly gradually sinked into the depth in the predetermined ground, and the sinking is accurate, thereby avoiding the tradition.
- Major safety and quality accidents such as sudden sinking, over-sinking, center-offset, plane rotation, vertical subsidence, deformation and fracture, wellbore in the well, and collapse outside the well occurred in the construction method.
- the inner and outer support blocks may be reinforced concrete structures or steel structures.
- the inner and outer support blocks may be a single independent support block or a horizontal continuous truss or crown beam or support block.
- the jacks can be various types of mechanical lifting mechanisms and are not limited to the particular jack structures disclosed herein.
- the bottom support structure of the well wall, the inner wall support block, the inner bottom frame beam and other bottom support structures may be used alone or in combination, which may be adopted according to different design requirements of the sinking structure.
- the present invention can be applied to a sinking project having a larger flat area, a more complicated shape, a larger single-sided size, a softer foundation, and a deeper sinking depth, thereby reducing the cost and obtaining a better economy.
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Revetment (AREA)
- Foundations (AREA)
Abstract
Description
Claims
Priority Applications (4)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
EP09705158A EP2246481A1 (en) | 2008-01-24 | 2009-01-06 | Caisson structure and method of sinking the caisson structure into the ground exactly |
CN2009801026576A CN101918643B (en) | 2008-01-24 | 2009-01-06 | Caisson structure and method of sinking the caisson structure into the ground exactly |
JP2010543364A JP2011510195A (en) | 2008-01-24 | 2009-01-06 | Caisson structure and method of precisely laying caisson structure underground |
US12/864,235 US20100296876A1 (en) | 2008-01-24 | 2009-01-06 | Caisson structures and methods for precisely and stably sinking the caisson structures into ground |
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN200810026012.6 | 2008-01-24 | ||
CN200810026012A CN101418573B (en) | 2008-01-24 | 2008-01-24 | Caisson structure and method for smoothly and accurately sinking caisson structure into earth surface |
Publications (1)
Publication Number | Publication Date |
---|---|
WO2009094912A1 true WO2009094912A1 (en) | 2009-08-06 |
Family
ID=40629560
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
PCT/CN2009/070038 WO2009094912A1 (en) | 2008-01-24 | 2009-01-06 | Caisson structure and method of sinking the caisson structure into the ground exactly |
Country Status (5)
Country | Link |
---|---|
US (1) | US20100296876A1 (en) |
EP (1) | EP2246481A1 (en) |
JP (1) | JP2011510195A (en) |
CN (2) | CN101418573B (en) |
WO (1) | WO2009094912A1 (en) |
Families Citing this family (26)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101591915B (en) * | 2009-06-25 | 2014-12-17 | 丁慈鑫 | Outer support system for supporting caisson structure and construction method thereof |
CN101851930B (en) * | 2010-01-15 | 2012-10-03 | 丁慈鑫 | Sinking device of open caisson and sinking method of open caisson with same |
CN101787703B (en) * | 2010-03-17 | 2011-06-15 | 中国二十二冶集团有限公司 | Sinking construction method of sinking well with geology of gravel and pebble beds under saturated water condition |
CN101942839B (en) * | 2010-09-10 | 2012-05-02 | 丁慈鑫 | Construction method for entering inside of open caisson and transporting soil |
JP4942230B1 (en) * | 2010-11-29 | 2012-05-30 | 賢治 町筋 | Submersible method and equipment for submerged method |
CN102900090A (en) * | 2011-07-29 | 2013-01-30 | 邹宗煊 | Non-inclined dry-operation open caisson capable of preventing water burst and land subsidence and construction method thereof |
CN102926395A (en) * | 2012-11-22 | 2013-02-13 | 天津华悦土木工程质量检测有限公司 | Open caisson construction method of flowing muddy mollisol |
CN103422508B (en) * | 2013-03-08 | 2015-09-30 | 中国建筑第四工程局有限公司 | Deep foundation ditch inner support platform structure machinery is vexed tears method and structure open |
JP6219666B2 (en) * | 2013-10-10 | 2017-10-25 | 株式会社安藤・間 | Pneumatic caisson installation method |
CN105201003B (en) * | 2015-10-15 | 2018-04-20 | 北京中岩大地科技股份有限公司 | A kind of open caisson construction method and method for dismounting |
CN105696614B (en) * | 2016-01-27 | 2018-02-02 | 中国十七冶集团有限公司 | One kind solves the super heavy resetting means of open caisson using top of above leaving behind |
CN108999202A (en) * | 2018-08-23 | 2018-12-14 | 中铁六局集团广州工程有限公司 | Prevent the super heavy method and device of open caisson |
CN109098201A (en) * | 2018-10-12 | 2018-12-28 | 西南交通大学 | A kind of super plane area portions prestressed concrete well foundation and its construction method |
CN109518691B (en) * | 2018-11-27 | 2020-10-20 | 张利均 | Pile extractor |
KR101960413B1 (en) * | 2019-01-07 | 2019-03-20 | 김준성 | Structure construction method |
CN109826218A (en) * | 2019-03-25 | 2019-05-31 | 中国十七冶集团有限公司 | A kind of open caisson end heavy stage hydraulic lifting deviation-rectifying system |
CN110093942A (en) * | 2019-05-30 | 2019-08-06 | 安徽省交通控股集团有限公司 | A kind of assembled radical well foundation of two-wall hollow |
CN110485470B (en) * | 2019-08-08 | 2021-05-04 | 郑州安源工程技术有限公司 | Rectangular working well with pre-arranged jacking pipe door opening and sliding type rear wall in water-rich stratum and construction method of rectangular working well |
CN112523243B (en) * | 2019-09-19 | 2024-06-18 | 派利欧洲公司 | Caisson template |
CN111677008B (en) * | 2020-06-02 | 2021-11-16 | 福州市恒坤建设发展有限公司 | Construction method of assembled underground garage |
CN111622251A (en) * | 2020-06-15 | 2020-09-04 | 北京中岩智泊科技有限公司 | Assembly type open caisson structure and construction method thereof |
CN111749258A (en) * | 2020-06-30 | 2020-10-09 | 中国二十二冶集团有限公司 | Construction method of tire mold of edge foot of cyclone well |
CN112854296B (en) * | 2021-01-13 | 2022-04-15 | 河南城建学院 | Vertical wall sliding installation supporting device and construction method thereof |
CN113737833B (en) * | 2021-09-09 | 2022-09-09 | 中建七局交通建设有限公司 | Open caisson construction formwork and construction method thereof |
CN113833001A (en) * | 2021-09-22 | 2021-12-24 | 济南市市政工程设计研究院(集团)有限责任公司 | Detachable rolling sinking type open caisson structure and construction process |
CN115262649A (en) * | 2022-08-05 | 2022-11-01 | 安徽科尼盛机电科技有限责任公司 | Composite construction's waterproof theftproof well lid |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1044144A (en) * | 1989-01-14 | 1990-07-25 | 全球海洋问题研究所 | Caisson |
JP2003171941A (en) * | 2001-12-03 | 2003-06-20 | Ishikawajima Harima Heavy Ind Co Ltd | Caisson and its construction method |
CN1441127A (en) * | 2003-04-09 | 2003-09-10 | 王民寿 | Caisson structure and fast construction method of opencaisson |
KR20050097735A (en) * | 2004-04-02 | 2005-10-10 | (주) 선암기술연구소 | Caisson installed support means and construction method of underwater structure using it |
CN101003974A (en) * | 2006-12-22 | 2007-07-25 | 中铁大桥局股份有限公司 | Method for constructing groundwork for large-scale sinking well in deep water |
CN201176597Y (en) * | 2008-01-28 | 2009-01-07 | 丁慈鑫 | Sinking well structure |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU912836A1 (en) * | 1980-07-07 | 1982-03-15 | Государственный Институт По Проектированию Горнорудных Предприятий Центральных Районов Рсфср "Центргипроруда" | Method of driving a sinkable well into soil |
US4938634A (en) * | 1989-06-26 | 1990-07-03 | Lee Yuan Ho | Process for lowering basement |
CN2193891Y (en) * | 1993-06-17 | 1995-04-05 | 张卡鸣 | Double-wall cylindrical open well frame |
CN1043483C (en) * | 1994-07-30 | 1999-05-26 | 海勃湾矿务局基本建设第一工程处 | Open caisson method of inclined shaft |
CN1053246C (en) * | 1994-08-01 | 2000-06-07 | 胡泽嘉 | Construction method and device using large open caisson lowering water level in high-storied buiding and under ground engineering |
CN1884719A (en) * | 2006-06-08 | 2006-12-27 | 中铁大桥局股份有限公司 | High opening, low edge-foot double-wall steel-cofferdams construction process for coffer without back cover concrete |
-
2008
- 2008-01-24 CN CN200810026012A patent/CN101418573B/en not_active Expired - Fee Related
-
2009
- 2009-01-06 EP EP09705158A patent/EP2246481A1/en not_active Withdrawn
- 2009-01-06 JP JP2010543364A patent/JP2011510195A/en active Pending
- 2009-01-06 WO PCT/CN2009/070038 patent/WO2009094912A1/en active Application Filing
- 2009-01-06 US US12/864,235 patent/US20100296876A1/en not_active Abandoned
- 2009-01-06 CN CN2009801026576A patent/CN101918643B/en not_active Expired - Fee Related
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1044144A (en) * | 1989-01-14 | 1990-07-25 | 全球海洋问题研究所 | Caisson |
JP2003171941A (en) * | 2001-12-03 | 2003-06-20 | Ishikawajima Harima Heavy Ind Co Ltd | Caisson and its construction method |
CN1441127A (en) * | 2003-04-09 | 2003-09-10 | 王民寿 | Caisson structure and fast construction method of opencaisson |
KR20050097735A (en) * | 2004-04-02 | 2005-10-10 | (주) 선암기술연구소 | Caisson installed support means and construction method of underwater structure using it |
CN101003974A (en) * | 2006-12-22 | 2007-07-25 | 中铁大桥局股份有限公司 | Method for constructing groundwork for large-scale sinking well in deep water |
CN201176597Y (en) * | 2008-01-28 | 2009-01-07 | 丁慈鑫 | Sinking well structure |
Also Published As
Publication number | Publication date |
---|---|
US20100296876A1 (en) | 2010-11-25 |
EP2246481A1 (en) | 2010-11-03 |
JP2011510195A (en) | 2011-03-31 |
CN101918643B (en) | 2012-10-10 |
CN101418573B (en) | 2012-09-05 |
CN101918643A (en) | 2010-12-15 |
CN101418573A (en) | 2009-04-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2009094912A1 (en) | Caisson structure and method of sinking the caisson structure into the ground exactly | |
KR101859367B1 (en) | Method for constructing vertical structure in vertical tunnel using top down method | |
CN103912134B (en) | Existing building underground space structure and construction method in situ | |
CN102704705A (en) | Building long-stroke redescending-free multi-point synchronous jacking method | |
CN105804119A (en) | Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure | |
CN1888331A (en) | Guide pit type manual pot holing pile reinforing and underpinning method for building foundation and composite supporting pile | |
CN103526781B (en) | A kind of ancient architecture foundation integrated pallet base isolation reinforcement structure and construction method thereof | |
CN103669385A (en) | Method for improving pile group bearing capacity by means of reticular pile foundations | |
CN112195779A (en) | Multifunctional trestle construction method suitable for thick pebble layer | |
CN201176597Y (en) | Sinking well structure | |
CN112195928B (en) | Pile plate composite structure for foundation pit support | |
CN111677008B (en) | Construction method of assembled underground garage | |
CN205024719U (en) | Pile foundation and integrated reverse construction vertical braces system of underground continuous wall | |
CN210315664U (en) | Reverse construction method foundation pit rectangular lattice column positioning and verticality adjusting device | |
CN203603176U (en) | Historic building foundation overall tray shock insulating and reinforcing structure | |
CN203755173U (en) | Formwork device used for hydraulic climbing of bridge high pier | |
CN210946864U (en) | Landscape structure foundation for soft stratum | |
CN202745081U (en) | Large-size rubble concrete settlement joint template system | |
CN201620419U (en) | Steel support structure | |
CN206319314U (en) | A kind of additional cuff back-up sand building stones prefabricated pile | |
CN206110185U (en) | Prestressing force is assembled and is pressed heavy indoor ground of formula storehouse structure | |
CN219569001U (en) | Node structure for avoiding additional overhead layer of primary foundation reinforcement | |
CN220579971U (en) | Special-shaped pile capable of being used as anti-floating roof | |
CN217630057U (en) | Body foundation structure and dry quenching furnace | |
CN202644566U (en) | Foundation bolt box with dense steel mesh |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
WWE | Wipo information: entry into national phase |
Ref document number: 200980102657.6 Country of ref document: CN |
|
121 | Ep: the epo has been informed by wipo that ep was designated in this application |
Ref document number: 09705158 Country of ref document: EP Kind code of ref document: A1 |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2010543364 Country of ref document: JP |
|
WWE | Wipo information: entry into national phase |
Ref document number: 12864235 Country of ref document: US |
|
NENP | Non-entry into the national phase |
Ref country code: DE |
|
WWE | Wipo information: entry into national phase |
Ref document number: 2009705158 Country of ref document: EP |