KR101960413B1 - Structure construction method - Google Patents

Structure construction method Download PDF

Info

Publication number
KR101960413B1
KR101960413B1 KR1020190001641A KR20190001641A KR101960413B1 KR 101960413 B1 KR101960413 B1 KR 101960413B1 KR 1020190001641 A KR1020190001641 A KR 1020190001641A KR 20190001641 A KR20190001641 A KR 20190001641A KR 101960413 B1 KR101960413 B1 KR 101960413B1
Authority
KR
South Korea
Prior art keywords
underground
underground structure
jack
foundation
constructing
Prior art date
Application number
KR1020190001641A
Other languages
Korean (ko)
Inventor
김준성
변수민
Original Assignee
김준성
변수민
주식회사고려이엔시
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 김준성, 변수민, 주식회사고려이엔시 filed Critical 김준성
Priority to KR1020190001641A priority Critical patent/KR101960413B1/en
Application granted granted Critical
Publication of KR101960413B1 publication Critical patent/KR101960413B1/en
Priority to PCT/KR2019/013075 priority patent/WO2020145483A1/en
Priority to SG11202107482SA priority patent/SG11202107482SA/en
Priority to CN201980088045.XA priority patent/CN113614315A/en
Priority to US17/420,979 priority patent/US20220098817A1/en
Priority to JP2021539593A priority patent/JP2022517333A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1628Shapes rectangular

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to a structure construction method to construct a structure by constructing an underground structure on the upper part of the ground and burying the underground structure in the ground. According to the present invention, the structure construction method comprises: A) a step of constructing a base plate (10) and a pile (20); B) a step of constructing a jack-down device and an underground structure; C) a step of excavating the lower part of the base plate (10) and burying the underground structure; and D) a step of releasing the jack-down device and mounting the pile (20).

Description

구조물 시공방법{Structure construction method} [0001] The present invention relates to a structure construction method,

본 발명은, 구조물 시공방법에 관한 것으로, 특히 구조물 중 지하에 설치되는 지하구조물을 지하에서 시공하는 것이 아니라 지반의 위에서 시공하여 지반 아래로 침하시키는 방법에 의한 시공방법에 관한 것이다. The present invention relates to a method of constructing a structure, and more particularly, to a method of constructing an underground structure to be installed in an underground structure by submerging the underground structure under the ground.

지하수위가 높거나 연약한 지반에 지하층을 시공하는 경우에는 지하수의 유출로 인하여 인접한 터널, 박스구조물, 지하철 등 지하구조물뿐만 아니라 지상구조물에 심각한 손상을 유발할 수 있다.If a groundwater layer is installed on a ground with a high groundwater level or a soft ground, it may cause serious damage to ground structures as well as underground structures such as adjacent tunnels, box structures, and subways due to leakage of groundwater.

일정깊이 이상을 굴착하는 경우에는 굴토심의 등을 통하여 인접 구조물의 안전성 여부를 시공 전에 일부 확인하고 있다. 그러나 실제 시공에 있어서는 흙막이 시설의 붕괴로 인한 인명사고 까지도 빈번히 발생하고 있다. 뿐만 아니라 인접 구조물이나 도로 등에 균열과 부등침하, 싱크홀 등이 발생되고 있다. If excavation is carried out above a certain depth, the safety of the adjacent structure is confirmed before installation by the back of the excavator. However, in actual construction, human accidents due to the collapse of the retaining facilities are frequently occurring. In addition, cracks, uneven settlement, sinkholes, etc. are generated in adjacent structures and roads.

더욱이 최근에는 굴토심의 대상이 아닌 굴착깊이가 비교적 깊지 않은 굴착 현장에서도 흙막이 시설의 붕괴 또는 지하수의 유출로 인해 인접 건축물이 붕괴되는 일이 발생하고 있다. 이렇듯 도심지에서의 지하구조물 시공을 위한 굴착은 매우 어려운 작업이다. 따라서 보다 안전하고 안정적인 지하구조물 시공을 위한 굴착 및 구조물 시공방법이 요구된다.In addition, in recent years, collapse of retaining structures or leakage of groundwater has resulted in collapse of adjacent structures even at excavation sites where excavation depth is not relatively high, which is not the object of excavation. Excavation for the construction of underground structures in urban areas is a very difficult task. Therefore, excavation and structure construction methods are needed for the construction of safer and more stable underground structures.

일반적으로 사용하고 있는 지하 굴착 후 시공하는 지하구조물을 도 1에 나타내었다. 도 1에 나타낸 바와 같이 종래의 시공방법은 지하토사를 굴착한 다음 지하구조물을 시공하는 방법이다. 즉, 대지경계선에 인접하여 토류벽(500)을 설치하고, 굴착 지역에 센터파일(700)을 설치한다. 이후 굴착과 스트럿(600) 설치를 반복하여 지하 굴착을 완료한다. 그리고 기초, 옹벽, 지하층 등을 시공하면서 스트럿(600)과 센터파일(700)을 제거하여 지하구조물을 완성하게 된다.Figure 1 shows an underground structure that is generally used after underground excavation. As shown in FIG. 1, the conventional construction method is a method of constructing an underground structure after excavating underground soil. That is, the earth wall 500 is installed adjacent to the site boundary line, and the center file 700 is installed in the excavation area. Subsequently, excavation and installation of the strut 600 are repeated to complete underground excavation. Then, the strut 600 and the center pile 700 are removed while the basement, retaining wall, and basement are being constructed, thereby completing the underground structure.

굴착하는 방법은 여러 가지 공법이 있다. 지반의 조건에 따라 흙막이 시공법 또한 여러 가지 방법이 적용되고 있으며, 지하수위의 위치에 따라 여러 가지의 차수공법이 적용되고 있다. 굴착이 완료된 다음 지하구조물을 시공하게 된다. 또는 흙막이 가설 구조물을 시공하면서 구조물을 상부에서 하부로 시공하는 탑다운 방법을 사용하기도 한다.There are various methods of excavation. Depending on the ground conditions, various methods are applied to the retaining construction method, and several different methods are applied depending on the location of the groundwater. After the excavation is completed, the underground structure will be constructed. Or a top-down method of constructing the structure from the top to the bottom while constructing the earth retaining structure.

굴착한 후 구조물을 시공하는 종래의 지하구조물 시공방법은 안전성과 경제성 측면에서 다음과 같은 문제점이 있었다. 안전성 측면에서 볼 때, 굴착으로 인한 주변 시설물의 피해와 흙막이 구조물의 붕괴로 인한 인명피해가 있었다. 경제성 측면에서 토지를 충분히 이용하지 못하고 흙막이 공사로 인한 공사비가 낭비되고 있었다. Conventional underground structure construction methods for constructing a structure after excavation have the following problems in terms of safety and economy. From the viewpoint of safety, there were damage to surrounding facilities due to excavation and loss of life due to collapse of retaining structures. In terms of economy, the land was not fully utilized and the construction cost due to earthworks was wasted.

즉, 토류벽으로 인해 대지경계선으로부터 일정 거리 떨어진 곳에 지하구조물을 시공할 수 밖에 없어, 상당량의 지하 면적이 사용할 수 없게 되어 경제적 손실이 매우 큰 문제가 있었다. That is, due to the earth wall, it is necessary to construct an underground structure at a certain distance from the site boundary line, so that a considerable amount of underground area can not be used, resulting in a great economic loss.

특허문헌 0001은, 건축물의 지하층이나 지하철 등 지하구조물을 구축하거나 지중 관을 매설하기 위한 지하구조물 시공방법에 관한 것인데, 특허문헌 0001도 터파기를 하고 흙막이 구조를 사용하는 구조이므로, 위와 같은 문제점을 해소하지 못하였다. Patent Literature 0001 relates to a method of constructing an underground structure such as a basement or a subway of a building or an underground structure for embedding an underground pipe. Patent Literature 0001 also discloses a structure using a terrestrial structure and a retaining structure, I can not.

따라서 안전하고, 경제적이며, 신속한 구조물 시공방법의 개발이 요구되었다. Therefore, the development of a safe, economical and rapid construction method has been required.

공개특허공보 10-2013-0061368Japanese Patent Application Laid-Open No. 10-2013-0061368

본 발명은, 위와 같은 종래기술의 문제점을 개선하기 위해, 공사장 주변의 안전을 보장하고, 공사비용이 절감되며, 공사기간이 단축될 수 있는 효율적인 구조물 시공방법을 제공하는 것을 목적으로 한다.SUMMARY OF THE INVENTION It is an object of the present invention to provide an efficient method of constructing a structure to ensure safety around a construction site, reduce a construction cost, and shorten a construction period.

본 발명에서는, 지하구조물을 지반 상부에서 시공하고, 지반 내부에 침하시켜 시공하는 구조물 시공방법에 있어서, 상기 구조물 시공방법은, A) 기초판(10) 및 파일(20)을 시공하는 단계; B) 잭다운 장치 설치 및 지하층구조물 시공 단계; C) 기초판(10) 하부 굴착 및 지하구조물 침하 단계; D) 잭다운 장치 해체 및 파일(20) 정착 단계를 포함하고, 상기 잭다운 장치는 상기 기초판(10)의 상부에 설치되어, 상기 잭다운 장치의 힘을 조절함으로써 상기 지하구조물의 침하량을 제어할 수 있으며, 상기 기초판(10) 하부의 굴착과 지하구조물의 침하가 병행하여 이루어질 수 있도록 하는 것을 특징으로 하는, 구조물 시공방법을 제공한다.A method of constructing a structure for constructing an underground structure in an upper part of a ground and submerged in the ground, the method comprising: A) constructing a foundation plate (10) and a pile (20); B) Jack-down device installation and basement construction step; C) lower excavation of the foundation plate (10) and subsidence of the underground structure; D) jack-down device disassembly and file (20) settlement, wherein the jack-down device is installed on the top plate (10) to control the settlement amount of the underground structure by controlling the force of the jack- And the excavation of the lower part of the base plate 10 and the settlement of the underground structure can be performed in parallel.

또한 본 발명에서는, 지하구조물을 지반 상부에서 시공하고, 지반 내부에 침하시켜 시공하는 구조물 시공방법에 있어서, 상기 구조물 시공방법은, a) 외곽기초판(50) 및 파일(20)을 시공하는 단계; b) 잭다운 장치를 설치하는 단계; c) 외곽기초판(50) 하부 굴착 및 침하 단계; d) 잭다운 장치 해체 및 파일(20) 정착 단계를 포함하고, 상기 잭다운 장치는 상기 외곽기초판(50)의 상부에 설치되어, 상기 잭다운 장치의 힘을 조절함으로써 상기 지하구조물의 침하량을 제어할 수 있으며, 상기 외곽기초판(50) 하부의 굴착과 지하구조물의 침하가 병행하여 이루어질 수 있도록 하는 것을 특징으로 하는, 구조물 시공방법을 제공한다. According to the present invention, there is also provided a method of constructing a structure for constructing an underground structure in an upper part of a ground and submerged in the ground, the method comprising: a) constructing the outer foundation plate 50 and the pile 20 ; b) installing a jack-down device; c) lower excavation and settlement of the outer foundation plate 50; d) disassembling the jack-down device and fixing the file (20), wherein the jack-down device is installed on the upper part of the outer foundation board (50), and adjusts the force of the jack- And the excavation of the lower part of the outer foundation foundation plate 50 and the settlement of the underground structure can be performed in parallel with each other.

상기 침하는 지하구조물의 자중에 의해 이루어진다. The settlement is caused by the self weight of the underground structure.

상기 침하는 지하구조물의 자중에 더하여, 추가 외력에 의해 이루어진다. The settlement is made by an additional external force in addition to the self weight of the underground structure.

상기 추가 외력은, 상기 지하구조물에 임시 하중을 재하하여 하중을 증가시키는 방법; 지반 속에 설치한 락앵커(rock anchor) 또는 어스앵커(earth anchor)를 사용하는 방법; 지반 속에 설치한 파일의 주면마찰력을 이용하는 방법; 중 어느 하나의 방법에 의해 발생한다.The additional external force includes a method of increasing a load by loading a temporary load on the underground structure; A method of using a rock anchor or an earth anchor installed in the ground; A method of using a frictional force of a surface of a file installed in the ground; . ≪ / RTI >

상기 굴착은, 굴착장비를 사용하는 방법; 워터젯(water jet)을 사용하는 방법; 지반의 토사를 흡입하여 배출하는 방법; 중 어느 하나의 방법에 의해 이루어진다.The excavation may comprise a method of using an excavation equipment; A method using a water jet; A method of sucking and discharging the soil from the ground; . ≪ / RTI >

상기 D)단계 후에 기초판(10) 및 파일(20)의 상부에 추가 기초판을 시공하는 단계를 더 포함한다.Further comprising the step of, after step D), constructing an additional base plate on top of the base plate 10 and the piles 20. [

상기 d)단계 후에 외곽기초판(50) 및 파일(20)의 상부에 추가 기초판을 시공하는 단계를 더 포함한다.Further comprising the step of constructing an additional foundation plate on top of the outer foundation foundation 50 and the piles 20 after step d).

삭제delete

삭제delete

본 발명에 따른 구조물 시공방법은 다음과 같은 효과가 있다.The method of constructing a structure according to the present invention has the following effects.

첫째, 지하구조물의 구조체가 되는 굴착용벽체와 외벽이 구조체의 기능을 하면서, 공사 과정에서는 흙막이 벽체로 사용될 수 있으므로, 신축되는 인근의 토사유출 및 누수가 발생되지 않게 되어 주변 시설물의 안전성이 확보된다. First, since excavation wall and outer wall which are structures of underground structures function as structures, they can be used as an earth retaining wall in the construction process, so that there is no leakage of leachate and leakage of nearby soil, and the safety of surrounding facilities is ensured .

둘째, 종래의 방법에서는, 굴착할 때 지하수가 유입되면 이를 펌핑하여 배출하기 때문에 주변 지하수위의 저하로 인한 씽크홀 및 인접구조물의 안전성 문제가 발생하였다. 반면 본 발명에서는, 지하수를 배출하지 않고, 경우에 따라서는 워터젯(water jet)을 이용하면서 토사를 굴착하기 때문에 주변 지하수위의 저하로 인한 문제가 발생하지 않는다.Secondly, in the conventional method, since groundwater is pumped and discharged when excavated, the safety hole of the sinkhole and the adjacent structure due to the lowering of the surrounding groundwater is generated. On the other hand, in the present invention, since the groundwater is not discharged, and in some cases, water jets are used to excavate the earth, the problem caused by the lowering of the surrounding groundwater does not occur.

셋째, 본 발명에서는, 흙막이 가시설을 포함한 차수공법이 필요없고, 굴착에 따른 붕괴 위험이 없으므로 가설구조물의 불안정으로 인한 문제점이 모두 해결된다. Third, according to the present invention, there is no need for an ordering method including a temporary earthquake, and there is no risk of collapse due to excavation, thereby solving all the problems due to the instability of the temporary structure.

넷째, 흙막이 가시설을 설치하지 않으므로, 흙막이 가시설의 설치와 해체에 드는 시간과 비용을 줄일 수 있어, 공사기간이 단축되고 공사비가 절감된다. Fourth, since the installation site of the retaining walls is not installed, it is possible to reduce the time and cost required for installation and demolition of the retaining walls, thus shortening the construction period and reducing the construction cost.

다섯째, 지반을 굴착하기 전에 굴착용벽체와 외벽에 의해 주변 지반이 견고하게 지지되므로, 주변 지반의 교란이 일어나지 않는다.Fifth, since the surrounding ground is firmly supported by the excavation wall and outer wall before excavating the ground, disturbance of the surrounding ground does not occur.

여섯째, 토류벽을 설치하지 않아 대지경계선까지 지하구조물을 시공할 수 있으므로, 토지의 효용가치를 높이고, 지하공간을 최대한으로 사용할 수 있다.Sixth, it is possible to construct an underground structure to the site boundary without installing a tomb wall, so that the utility value of the land can be increased and the underground space can be used to the maximum extent.

일곱째, 지하구조물 시공을 위한 파일은 공사 중에는 지하구조물의 침하량을 제어할 수 있는 지지대 및 가이드 역할을 하고, 공사가 완료된 후에는 영구구조물이 되어 깊은기초(deep foundation)의 역할을 하게 된다.Seventh, the file for the construction of the underground structure serves as a support and guide for controlling the settlement amount of the underground structure during the construction, and becomes a permanent foundation after the construction is completed to serve as a deep foundation.

여덟째, 유압잭을 사용하여 지하구조물의 침하량을 제어할 수 있으므로 정밀 시공이 가능하다. Eighth, it is possible to control the settlement amount of underground structure by using hydraulic jack, so precision construction is possible.

아홉째, 흙막이 가시설이 필요 없으므로, 흙막이 가시설의 붕괴로 인한 사고가 방지된다. Ninth, since the need for temporary pavement is not necessary, accident caused by collapse of temporary pavement is prevented.

도 1은 종래기술이다.
도 2 내지 7은 본 발명의 제1실시예의 과정을 설명하는 것이다.
도 8, 9는 본 발명의 제2실시예를 설명하는 것이다.
도 10, 11은 본 발명의 제3실시예를 설명하는 것이다.
도 12는 기초판, 파일, 유압잭의 확대도이다.
Figure 1 is a prior art.
2 to 7 illustrate the process of the first embodiment of the present invention.
Figures 8 and 9 illustrate a second embodiment of the present invention.
10 and 11 illustrate a third embodiment of the present invention.
12 is an enlarged view of a base plate, a file, and a hydraulic jack.

아래에서는 첨부한 도면을 참조하여 본 발명이 속하는 기술 분야에서 통상의 지식을 가진 자가 쉽게 실시할 수 있도록 본 발명의 실시예를 상세히 설명한다. 그러나 본 발명은 여러 가지 상이한 형태로 구현될 수 있으며 여기에서 설명하는 실시예에 한정되지 않는다. 그리고 도면에서 본 발명을 명확하게 설명하기 위해서 설명과 관계없는 부분은 생략하였으며, 명세서 전체를 통하여 유사한 부분에 대해서는 유사한 도면 부호를 붙였다. 명세서 전체에서, 어떤 부분이 어떤 구성요소를 "포함"한다고 할 때, 이는 특별히 반대되는 기재가 없는 한 다른 구성요소를 제외하는 것이 아니라 다른 구성요소를 더 포함할 수 있는 것을 의미한다. 이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시예를 상세히 설명하기로 한다. Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings so that those skilled in the art can easily carry out the present invention. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. In order to clearly illustrate the present invention, parts not related to the description are omitted, and similar parts are denoted by like reference characters throughout the specification. Throughout the specification, when an element is referred to as "comprising ", it means that it can include other elements as well, without excluding other elements unless specifically stated otherwise. Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

종래에는, 지반을 굴착한 다음 지하공간에서 지하구조물을 시공하는 방법을 사용하였다. 반면 본 발명은, 지반 위에서 지하구조물을 시공한 다음, 기초판의 하부를 굴착하면서 지하구조물을 지반 내부에 침하시켜 구조물을 시공하는 방법이다. Conventionally, a method of constructing an underground structure in an underground space after excavating the ground is used. On the other hand, the present invention is a method of constructing an underground structure on the ground, then digging the lower portion of the foundation plate while submerging the underground structure in the ground.

본 발명의 지하구조물(100)은, 기초판(10), 파일(20), 지하층구조물을 포함한다. 상기 지하층구조물은 1개의 층일 수 있고, 2개 이상의 복수의 층 일 수도 있는데, 제1, 2실시예에서는 상기 지하층구조물이 지하2층구조물(30)과 지하1층구조물(40)을 포함하는 경우를 설명한다. The underground structure 100 of the present invention includes a foundation plate 10, a pile 20, and a basement structure. In the first and second embodiments, when the underground structure includes the underground two-story structure 30 and the underground one-story structure 40, the underground structure may be one layer or two or more layers. .

도 2 내지 도 7에는 지하구조물(100)을 시공하는 본 발명의 제1실시예가 도시되어 있다. 이하에서는 도 2 내지 도 7을 참조하여 지하2층을 시공하는 경우에 대해 각 시공단계별로 자세히 설명한다.2 to 7 illustrate a first embodiment of the present invention for constructing an underground structure 100. Hereinafter, the construction of the two basement floors will be described in detail for each construction step with reference to FIGS. 2 to 7. FIG.

① 기초판(10) 시공(도 2 참조).① Construction of base plate (10) (see Fig. 2).

지반 위에 철근콘크리트로 된 기초판(10)을 시공한다. 도 2에 나타낸 것과 같이 기초판(10)의 테두리는 대지경계선(400) 바로 옆이거나, 대지경계선(400)과 거의 일치하도록 할 수 있다. A foundation plate (10) made of reinforced concrete on the ground is constructed. As shown in FIG. 2, the rim of the base plate 10 may be located immediately adjacent to the site boundary line 400 or substantially the same as the site boundary line 400.

지하구조물의 외벽이 흙막이로 활용되는 공법이므로 별도의 흙막이벽이 필요 없으며, 기초판 및 지하구조물의 외벽은 최대한 대지경계선과 접하도록 시공하여 지하공간을 최대화 할 수 있도록 한다. Since the outer wall of the underground structure is used as a retaining structure, there is no need for a separate retaining wall, and the outer wall of the foundation plate and the underground structure can be maximally constructed so as to be in contact with the site boundary as much as possible.

먼저 기초판(10)을 시공한 다음 파일(20)을 시공하므로 기초판에는 파일(20)을 시공할 수 있는 구멍을 형성하여야 한다. 따라서 기초판을 시공할 때 파일(20) 시공용 구멍을 형성하기 위한 슬리브를 미리 설치한다. 슬리브로는 강관을 사용할 수 있다. Holes are formed in the base plate so that the piles 20 can be installed, since the piles 20 are first constructed after the base plate 10 is constructed. Therefore, a sleeve for forming a hole for installation of the pile 20 is installed in advance when the base plate is constructed. Steel tubes can be used as sleeves.

지하구조물의 침하가 끝난 후, 파일(20)의 상부를 기초판에 정착시키기 위한 공간을 만들기 위해, 기초판에 일정 두께만큼 홈을 두어 블록아웃(11)(도 12 참조)을 형성한다. 파일을 정착시킨 후 상기 블록아웃(11)에 그라우팅하여 마무리하게 된다. After the subsidence of the underground structure is completed, a block-out 11 (see FIG. 12) is formed by grooving the base plate with a predetermined thickness in order to make space for fixing the upper portion of the pile 20 to the base plate. After the file is fixed, the block-out 11 is grouted and finished.

기초판(10)의 하부 테두리에는 굴착용벽체(12)를 구비할 수 있다. 상기 굴착용벽체(12)는 굴착 작업시 흙막이용 벽체로 활용될 수 있다. 그리고 상기 굴착용벽체(12)의 하단에는 선단이 경사진 선단슈(13)를 구비하여 지하구조물이 지반 내로 쉽게 근입될 수 있도록 한다.The bottom wall of the base plate 10 may be provided with a wall 12 for excavation. The excavation wall 12 can be used as a wall for earthworks in excavation work. The lower end of the excavation wall 12 is provided with a tip end shoe 13 whose tip is inclined so that the underground structure can be easily inserted into the ground.

상기 선단슈(13)는 영구거푸집 형태인 철판을 사용할 수도 있고, 콘크리트 단면을 경사지게 형성할 수도 있다. The end shoe 13 may be formed of a steel plate in the form of a permanent mold, or may be formed so that the cross section of the concrete is inclined.

상기 굴착용벽체(12)를 먼저 시공한 다음, 상기 굴착용벽체(12)와 기초판(10)이 일체가 되도록 기초판 콘크리트를 타설한다.After the excavation wall 12 is first constructed, the excavation wall 12 and the foundation plate 10 are laid together with the foundation plate concrete.

기초판(10)을 시공할 때에는, 지하구조물의 하중을 계산하여 필요한 수 만큼의 잭다운용 앵커(310)를 미리 설치할 수 있다(도 12 참조). 앵커(310)의 수량 및 용량은 지하구조물의 무게 및 침하할 때 발생하는 하중에 따라 적용할 수 있다. When the base plate 10 is to be installed, the required number of jack-down anchors 310 can be provided in advance by calculating the loads of the underground structures (see FIG. 12). The quantity and the capacity of the anchor 310 can be applied according to the weight of the underground structure and the load generated upon settlement.

앵커(310)의 하단 끝에는 앵커를 기초판에 고정시키는 앵커고정구(311)가 구비되는데, 상기 앵커고정구(311)는 기초판(10) 내에 묻히도록 설치되거나, 기초판(10)의 하부에 고정될 수 있도록 한다.An anchor fixing means 311 for fixing the anchor to the base plate is provided at the lower end of the anchor 310. The anchor fixing means 311 may be installed to be embedded in the base plate 10, .

잭다운용 앵커(310)를 미리 설치해 두는 것으로 설명하였는데, 경우에 따라 앵커를 미리 설치하지 않고, 기초판 시공 후 케미컬 앵커를 시공한 후 잭다운 하는 것도 가능하다.Down anchor 310 is previously installed. However, it is also possible to jack-down after installing the chemical anchor after the base plate construction without installing an anchor in advance.

기초판의 두께는 잭다운에 필요한 하중과 지하구조물의 구조적 안정성을 고려하여 결정한다. The thickness of the base plate is determined by considering the load required for jack down and the structural stability of the underground structure.

② 파일(20) 시공(도 2 참조).(2) Construction of file (20) (see FIG. 2).

기초판(10)이 설치되면, 슬리브에 의해 형성된 파일(20) 시공용 구멍으로 파일(20)을 시공한다. 파일(20)은 강관파일, 기성 철근콘크리트 파일, PHC 파일, 복합 파일, 현장타설 콘크리트 말뚝 등을 사용할 수 있다. 파일의 설치는 항타, 굴착 후 매입 등의 방법을 사용할 수 있다. 파일은 선단지지력을 발휘할 수 있는 지하 암반층까지 설치한다.When the base plate 10 is installed, the pile 20 is formed with a hole for installing the pile 20 formed by the sleeve. The file 20 can be a steel pipe file, an existing reinforced concrete file, a PHC file, a composite file, an on-site concrete pile or the like. The installation of the file can be done by using a method such as hunting, digging, etc. The file is installed up to the underground rock layer which can exhibit the end bearing capacity.

지하구조물이 완공된 후 상기 파일(20)을 깊은기초(deep foundation)로 사용하지 않는 경우, 즉, 파일기초가 아닌 직접기초(spread foundation)일 경우에는 지하구조물의 잭 다운에 필요한 최소한의 가설 파일만 시공하는 것이 바람직하다. If the file 20 is not used as a deep foundation after completion of the underground structure, that is, if it is a spread foundation rather than a file basis, the minimum hypothesis file necessary for jackdown of the underground structure It is preferable to apply only.

파일기초로 설계되는 지하구조물인 경우, 모든 파일에 잭다운 장치를 설치하지 않고, 지하구조물을 잭다운(jack down)하는데 필요한 수만큼의 파일에만 설치할 수 있다. 이때 적용되는 하중은 잭다운시 시공된 지하구조물의 자중과 부력으로 인한 감소량을 고려하여 적용한다. In the case of an underground structure designed as a file basis, it is possible to install only as many files as necessary to jack down an underground structure without installing a jack-down device in all files. In this case, the applied load is applied considering the reduction of self weight and buoyancy of underground structures constructed when jack down.

직접기초로 설계되는 지하구조물인 경우, 잭다운에 필요한 최소한의 파일을 시공하여 잭다운에 활용한다. 역시 이때 적용되는 하중은 잭다운시 시공된 지하구조물의 자중과 부력으로 인한 감소량을 고려하여 적용한다.If it is an underground structure that is designed as a direct foundation, use the minimum number of files necessary for jackdown to jack down. Also, the load applied at this time is applied considering the decrease in weight due to self weight and buoyancy of underground structures constructed when jack down.

③ 잭다운 장치 설치 및 지하2층구조물(30) 시공(도 3 참조)③ Jack-down device installation and underground two-story structure (30) construction (see Fig. 3)

지하구조물의 침하량과 침하속도를 제어할 수 있는 잭다운 장치를 설치하고, 지하2층구조물(30)을 시공한다. 이때 작업을 효율적으로 진행하여 공사기간을 단축시키기 위해, 잭다운 장치 설치 작업과 동시에 지하2층구조물(30) 시공 작업을 병행할 수도 있다. A jack-down device capable of controlling settlement and settlement speed of an underground structure is installed, and a two-story underground structure (30) is constructed. At this time, in order to efficiently perform the work and shorten the construction period, the jack-down device installation work and the underground two-story structure (30) construction work can be performed concurrently.

도 12에는 잭다운 장치가 도시되어 있는데, 파일(20)의 상부로 가압대(330)가 고정되어 있고, 상기 가압대(330)의 위에 유압잭(300)이 설치되어 있다. 앵커(310)의 하단은 앵커고정구(311)에 의해 기초판(10)에 고정되어 있고, 앵커(310)의 상단은 가압판(320)에 체결되어 있다. 앵커(310)의 상단과 가압판(320)의 체결은 너트를 사용할 수 있다. 상기 유압잭(300)이 가압판(320)을 미는 힘을 조절함으로써 기초판의 침하량을 정밀하게 제어할 수 있게 된다.12 shows a jack-down device in which a pressure pad 330 is fixed to the upper portion of the pile 20 and a hydraulic jack 300 is provided on the pressure pad 330. [ The lower end of the anchor 310 is fixed to the base plate 10 by an anchor fixing member 311 and the upper end of the anchor 310 is fastened to the pressure plate 320. A nut may be used for fastening the upper end of the anchor 310 and the pressure plate 320. It is possible to precisely control the settling amount of the base plate by adjusting the pressing force of the hydraulic jack 300 to the pressing plate 320. [

도 12에 도시된 잭다운 장치는 일실시예를 보인 것이고, 유압잭, 앵커, 가압판, 가압대는 다른 구조로도 결합될 수 있음은 물론이다.It is needless to say that the jack-down device shown in FIG. 12 is an embodiment, and the hydraulic jack, the anchor, the pressure plate, and the pressure pad can be combined with other structures.

상기 지하2층구조물(30)은 바닥판(31), 외벽(32), 기둥(33)을 포함할 수 있다. 상기 외벽(32)은 지하구조물의 외부 벽체의 기능과 흙막이 벽체로서의 기능을 동시에 할 수 있다. 상기 기둥(33)은 바닥판(31)을 지지하는 기둥, 벽체를 포함한다.The underground two-layer structure 30 may include a bottom plate 31, an outer wall 32, and a column 33. The outer wall 32 can function both as an outer wall of an underground structure and as an earth retaining wall. The column (33) includes a column and a wall supporting the bottom plate (31).

④ 기초판(10) 하부 굴착 및 지하구조물 잭다운(도 3, 4 참조)④ Under drilling of foundation plate (10) and jack-down of underground structures (see Figs. 3 and 4)

잭다운 장치 설치가 완료된 후, 기초판의 하부를 굴착하면 기초판과 지하2층구조물의 자중으로 인하여 자연스럽게 침하하게 된다. After the installation of the jack-down device is completed, if the lower part of the foundation plate is excavated, it will settle down naturally due to the weight of the foundation plate and the underground two-layer structure.

기초판 하부를 굴착하는 방법은 하부의 지반조건에 따라 여러 가지 방법을 사용할 수 있다.Various methods can be used to excavate the foundation plate under the ground conditions.

연약지반인 경우 기초판 하부를 흡입하는 방법으로 하부 토사를 제거할 수 있다. 토사가 제거될 때 구조물이 부등침하 하지 않도록 침하량을 정밀하게 계측하면서 잭다운 장치를 제어한다. 일정량이 굴착된 다음 잭다운 장치를 이용하여 구조물을 침하시키게 된다. 이 공정을 반복하여 시공하고자 하는 위치에 지하구조물을 위치시킨다. 점토의 점성 및 수분함량에 따라 흡입에 용이하도록 워터젯(Water Jet) 및 교반을 실시한다. 흡입된 흙탕물은 탈수 과정을 거쳐 토사와 물로 분리한다. 이때 분리된 토사는 사토장으로 반출하고 분리된 물은 현장에 재사용하는 방법을 선택하여 환경오염을 방지할 수 있다. In the case of soft ground, the bottom soil can be removed by sucking the bottom of the foundation plate. The jack-down device is controlled while precisely measuring the settlement amount so that the structure does not settle evenly when the soil is removed. After a certain amount of excavation, the structure is subdivided using a jack-down device. Repeat this process to locate the underground structure at the location where you want to build it. Depending on the viscosity and moisture content of the clay, a water jet and stirring are carried out to facilitate inhalation. The inhaled muddy water is dehydrated and separated into soil and water. At this time, it is possible to prevent the environmental pollution by selecting the method of removing the separated soil to the subduction site and reusing the separated water on the site.

기초판 하부 지반이 비교적 양호한 경우에는 필요에 따라 워터젯(Water Jet) + 흡입(Suction) 또는 탈수(Dewater) 공법을 추가 적용하거나 굴착을 병행하여 구조물을 침하시킨다.If the underlying foundation is relatively good, additional water jet or suction or dewatering may be applied as required or the structure may be subdivided by excavation.

기초판 하부가 암과 같이 단단한 경우에는 기초판에 장비출입구(14)를 형성하여, 굴착장비 등을 이용하여 기초판 하부를 굴착한 다음 구조물을 다운시킨다.When the bottom of the foundation plate is hard like a rock, an equipment entrance 14 is formed in the foundation plate, and the lower part of the foundation plate is excavated using an excavation equipment or the like, and then the structure is down.

⑤ 지하1층구조물(40) 시공(도 5 참조)⑤ Underground 1 story structure (40) construction (see Figure 5)

기초판 위에 지하2층구조물(30)이 올려진 후 필요한 깊이만큼 침하가 완료되면(도 4), 상기 지하2층구조물(30) 위에 지하1층구조물(40)을 지상에서 시공한다(도 5).After the underground two-layer structure 30 is placed on the foundation board and the settlement is completed by the required depth (FIG. 4), the underground one-story structure 40 is constructed on the ground above the underground two- ).

상기 지하1층구조물(40)은 바닥판(41), 외벽(42), 기둥(43)을 포함할 수 있다. 상기 외벽(42)도 지하구조물의 외부 벽체의 기능과 흙막이 벽체로서의 기능을 동시에 하게 된다. 상기 기둥(43)은 바닥판(41)을 지지하는 기둥, 벽체를 포함한다.The underground one-story structure 40 may include a bottom plate 41, an outer wall 42, and a column 43. The outer wall 42 also functions as an outer wall of an underground structure and a wall as a retaining wall. The column 43 includes columns and walls for supporting the bottom plate 41.

⑥ 기초판(10) 하부 굴착 및 지하구조물 잭다운 반복(도 5, 6 참조)⑥ Lower excavation of base plate (10) and jack-down repetition of underground structures (see Figs. 5 and 6)

상기 지하1층구조물(40) 시공 후, 기초판 하부를 굴착하면서 잭다운 장치를 제어하여 지하구조물을 침하시킨다. 필요로 하는 깊이까지 침하를 진행한다(도 6). After constructing the underground one-story structure (40), the lower part of the foundation plate is excavated to control the jack-down device to settle the underground structure. And sinking is carried out to the required depth (Fig. 6).

⑦ 침하 완료, 잭다운 장치 해체 및 파일 정착(도 7 참조)⑦ Completion of settlement, disassembly of jack-down device and settlement of files (see Fig. 7)

필요로 하는 깊이까지 침하가 완료되면 잭다운 장치를 해체한다. 앵커(310)를 절단하고, 앵커(310)와 파일(20) 상단을 고정시킨 후, 블록아웃(11)에 그라우팅하여 파일을 기초판에 정착시킨다. When the sinking is completed to the required depth, disassemble the jack-down device. The anchor 310 is cut and the anchor 310 and the upper end of the file 20 are fixed and the file is grouted in the blockout 11 to fix the file on the base plate.

상기 ① 내지 ⑦의 과정을 거친 후, 필요에 따라 지하구조물 내부 공사와 지상구조물 공사를 하고 나면 구조물의 시공이 완료된다.After the above steps ① to ⑦, if necessary, the construction of the structure is completed after the construction of the underground structure and the construction of the ground structure.

도 8, 9에는 지하구조물(100)을 시공하는 본 발명의 제2실시예가 도시되어 있다.Figures 8 and 9 show a second embodiment of the present invention for constructing an underground structure 100.

제2실시예에서는, 파일(20)을 먼저 시공한 후, 기초판(10)을 시공하게 된다. 즉 제2실시예에서는 상기 ② 먼저 진행한 후, ①을 진행하게 된다. 그리고 ③ 내지 ⑦과 동일한 과정을 진행한다. In the second embodiment, after the pile 20 is first applied, the base plate 10 is constructed. That is, in the second embodiment, after proceeding to the above (2) first, proceed to (1). Then proceed with the same procedure as ③ to ⑦.

제1, 2실시예에서는, 지하1층구조물과 지하2층구조물을 형성하는 과정을 설명하였는데, 본 발명은 지하1층구조물과 지하2층구조물로 한정되지 않는다. 즉, 지하1층구조물만 형성할 수도 있고, 위에서 설명한 ④, ⑤ 과정을 반복하여 지하2층 이상의 복수의 지하층을 형성할 수도 있다.In the first and second embodiments, the process of forming the underground 1-story structure and the underground 2-story structure has been described. However, the present invention is not limited to the underground 1-story structure and the underground 2-story structure. That is, only the underground one-story structure may be formed, or a plurality of basement stories of two or more underground levels may be formed by repeating the above-described steps 4 and 5.

도 10, 11에는 지하구조물(100)을 시공하는 본 발명의 제3실시예가 도시되어 있다.10 and 11 illustrate a third embodiment of the present invention in which an underground structure 100 is constructed.

제3실시예는, 지하구조물을 시공할 면적이 넓은 경우에 적용할 수 있는 실시예이다. 즉 지하구조물의 평면 면적이 넓은 경우에는 전체 기초판을 하나로 형성하여 침하시키는 작업이 어려울 수 있고, 기초판의 파손이 우려되며, 오히려 비효율적일 수도 있다. The third embodiment is an embodiment that can be applied to a case where an underground structure is to be constructed with a large area. That is, when the flat area of the underground structure is wide, it may be difficult to form the entire base plate and sink it, and the base plate may be damaged, which may be rather inefficient.

이 경우에는 대지경계선(400)에서 일정 폭에 대해 외곽기초판(50)을 시공하고, 앞에서 설명한 것과 동일한 방법으로 외곽기초판(50)을 침하시키는 방법이다. 외곽기초판(50)의 상부에는 외곽지하층구조물(60)을 시공하고 침하시킬 수 있다. 이때 외곽기초판(50) 하부의 토사를 굴착하면서 외곽기초판을 침하시킨다. 외곽기초판의 침하가 완료되면 기초판과 지하층구조물을 시공하게 된다.In this case, the outer base plate 50 is applied to the ground line 400 at a constant width, and the outer base plate 50 is submerged in the same manner as described above. An outer sub-layer structure 60 can be constructed and settled on the upper part of the outer foundation plate 50. At this time, the outer foundation foundation plate is settled while the gravel under the outer foundation foundation plate 50 is excavated. Once the settlement of the outer foundation foundation is completed, the foundation foundation and the underground structure are constructed.

이때 외곽기초판(50)의 내부에 있는 내부 토사는 그대로 둔 다음 지하구조물의 침하가 완료된 후 내부 토사를 굴착할 수 있다. 또한 외곽기초판(50)을 일정량 침하시키면서 내부 토사도 함께 굴착할 수도 있다. At this time, the inner soil in the outer foundation plate 50 is left as it is, and the inner soil can be excavated after the settlement of the underground structure is completed. Also, the inner soil can be excavated together while the outer foundation plate 50 is settled by a certain amount.

제3실시예에서 외곽기초판(50)을 시공한 후, 파일(20)을 설치할 수도 있고, 파일(20)을 먼저 설치한 후, 외곽기초판(50)을 시공할 수도 있다.The file 20 may be installed after the outer foundation foundation 50 is installed in the third embodiment or the outer foundation foundation 50 may be constructed after the installation of the file 20 first.

상기 실시예들에서, 기초판(10) 또는 외곽기초판(50)을 하나의 층으로 시공하는 것으로 설명하였는데, 경우에 따라 침하가 완료된 후에 기초판(10) 또는 외곽기초판(50) 위에 추가 기초판을 더 형성할 수도 있다. In the above embodiments, it is described that the base plate 10 or the outer foundation plate 50 is constructed as one layer. However, after the settlement is completed, it is added to the base plate 10 or the outer foundation plate 50 A base plate may be further formed.

즉, 콘크리트 파일 또는 직경이 큰 파일을 파일기초로 사용하는 경우에는, 파일로 인해 기초판(10)의 철근 배근이 어려울 수 있고, 파일의 상부가 기초판에 견고하게 정착되기 어려우므로, 침하가 완료된 후에 기초판(10) 위에 추가 기초판을 시공하는 것이 바람직하다. 추가 기초판을 시공하는 경우에는, 잭다운용 기초판(10)은 최대한 얇게 시공한다. 지하구조물 침하가 끝나고, 파일과 기초판(10)을 정착시킨 후, 파일 상부와 기초판(10) 상부에 철근 배근 후 매트(추가 기초판)를 타설하여 추가 기초판을 시공한다. That is, when a concrete file or a file having a large diameter is used as a file basis, it may be difficult to arrange the reinforcing bars of the foundation board 10 due to the file, and since the upper portion of the file is hardly fixed firmly to the foundation board, After completion, it is preferable to apply an additional base plate on the base plate 10. When the additional base plate is to be constructed, the jack-down base plate 10 is constructed as thin as possible. After the settlement of the underground structures is completed, the piles and the base plate 10 are fixed. Then, the reinforcing bars are installed on the top of the pile and the base plate 10, and a mat (additional base plate) is laid thereon to construct an additional base plate.

기초판(10) 위에 추가 기초판을 시공할 경우에는, 전체 기초의 배근 및 두께를 고려하여 지하구조물의 층고에 반영한다. 추가 기초판을 시공함으로써 직경이 큰 파일을 시공하더라도 매트의 충분한 강성을 얻을 수 있다. 그리고 추가 기초판을 시공하는 경우에는, 추가 기초판과 기초판(10)의 연결, 추가 기초판과 벽체 및 기둥의 연결부를 미리 고려하며 배근될 위치에 철근을 미리 시공하여야 한다. When an additional base plate is to be installed on the base plate 10, it is reflected in the height of the underground structure in consideration of the foundation and thickness of the whole foundation. By installing the additional base plate, sufficient rigidity of the mat can be obtained even when a large diameter file is constructed. When constructing an additional base plate, reinforcements should be installed in advance at the position to be laid, taking into consideration the connection between the additional base plate and the base plate (10), the connection between the additional base plate and the wall and the column.

반면, 강관파일을 사용하는 경우에는, 파일의 직경이 기초판 철근 배근에 간섭될 정도가 아니기 때문에 추가 기초판을 필요로 하지 않고, 기초판(10)만 사용할 수 있다. On the other hand, in the case of using a steel pipe file, since the diameter of the pile does not interfere with the foundation steel reinforcement, only the foundation plate 10 can be used without requiring an additional base plate.

한편, 지하구조물을 침하시킬 때 지하구조물의 자중만으로는 침하가 어려울 경우가 있을 수 있다. 이러한 경우에는 다음과 같은 방법을 사용하여 침하시킬 수 있다.On the other hand, when the underground structure is submerged, it may be difficult to settle only by the self weight of the underground structure. In this case, it can be settled using the following method.

첫째, 하중을 추가하는 방법을 사용할 수 있다. 기초판 또는 지하구조물의 상부에 임시 하중을 재하하여 하중을 증가시키는 방법을 사용할 수 있다. First, a method of adding loads can be used. A method of increasing the load by placing a temporary load on the foundation plate or an underground structure can be used.

둘째, 지반 속에 락앵커(rock anchor) 또는 어스앵커(earth anchor)를 설치하고, 락앵커 또는 어스앵커를 당겨 침하시키는 방법이다. Second, a rock anchor or an earth anchor is installed in the ground, and a rock anchor or an earth anchor is pulled down to settle.

셋째, 설치된 파일의 주면마찰력을 이용하는 방법이다. 유압잭을 수축하면 파일은 주면마찰력에 의해 지반 속에 고정되어 있으므로 기초판을 아래방향으로 당기는 힘이 발생하게 된다. Third, it is a method of using the friction force of the installed file. When the hydraulic jack is contracted, the pile is fixed in the ground due to frictional force, so that a force to pull the base plate downward is generated.

본 발명은 도면에 도시된 실시예를 참고로 설명되었으나 이는 예시적인 것에 불과하며, 본 기술 분야의 통상의 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 다른 실시예가 가능하다는 점을 이해할 것이다. 따라서 본 발명의 진정한 기술적 보호 범위는 첨부된 특허청구범위의 기술적 사상에 의하여 정해져야 할 것이다.While the present invention has been described with reference to exemplary embodiments, it is to be understood that the invention is not limited to the disclosed exemplary embodiments, but, on the contrary, is intended to cover various modifications and equivalent arrangements included within the spirit and scope of the appended claims. Accordingly, the true scope of the present invention should be determined by the technical idea of the appended claims.

100. 지하구조물
10. 기초판 11. 블록아웃
12. 굴착용벽체 13. 선단슈
14. 장비출입구
20. 파일
30. 지하2층구조물
31. 바닥판 32. 외벽
33. 기둥 34. 지하2층
40. 지하1층구조물
41. 바닥판 42. 외벽
43. 기둥 44. 지하1층
50. 외곽기초판
60. 외곽지하층구조물
300. 유압잭
310. 앵커 311. 앵커고정구
320. 가압판 330. 가압대
400. 대지경계선
500. 토류벽 600. 스트럿
700. 센터파일
100. Underground structures
10. Basics 11. Block Out
12. Excavation wall 13. End shoe
14. Equipment doorway
20. Files
30. Underground two story structure
31. Bottom plate 32. Outer wall
33. Column 34. 2 basement levels
40. Basement 1 story structure
41. Bottom plate 42. Outer wall
43. Column 44. Basement 1 floor
50. Outer base plate
60. Subterranean Structures
300. Hydraulic Jack
310. Anchor 311. Anchor fastener
320. Pressure Plate 330. Pressure Plate
400. Property line
500. Earthwalls 600. Struts
700. Center File

Claims (10)

지하구조물을 지반 상부에서 시공하고, 지반 내부에 침하시켜 시공하는 구조물 시공방법에 있어서,
상기 구조물 시공방법은,
A) 기초판(10) 및 파일(20)을 시공하는 단계;
B) 잭다운 장치 설치 및 지하층구조물 시공 단계;
C) 기초판(10) 하부 굴착 및 지하구조물 침하 단계;
D) 잭다운 장치 해체 및 파일(20) 정착 단계를 포함하고,
상기 잭다운 장치는 상기 기초판(10)의 상부에 설치되어, 상기 잭다운 장치의 힘을 조절함으로써 상기 지하구조물의 침하량을 제어할 수 있으며,
상기 기초판(10) 하부의 굴착과 지하구조물의 침하가 병행하여 이루어질 수 있도록 하는 것을 특징으로 하는,
구조물 시공방법.
A method of constructing an underground structure by applying the underground structure at the upper part of the ground,
In the method of constructing a structure,
A) installing the base plate (10) and the pile (20);
B) Jack-down device installation and basement construction step;
C) lower excavation of the foundation plate (10) and subsidence of the underground structure;
D) jack-down device disassembly and file (20)
The jack-down device is installed on the base plate 10 to control the settlement amount of the underground structure by adjusting the force of the jack-down device,
So that excavation under the foundation plate (10) and settlement of the underground structure can be performed in parallel.
Construction method of structure.
지하구조물을 지반 상부에서 시공하고, 지반 내부에 침하시켜 시공하는 구조물 시공방법에 있어서,
상기 구조물 시공방법은,
a) 외곽기초판(50) 및 파일(20)을 시공하는 단계;
b) 잭다운 장치를 설치하는 단계;
c) 외곽기초판(50) 하부 굴착 및 침하 단계;
d) 잭다운 장치 해체 및 파일(20) 정착 단계를 포함하고,
상기 잭다운 장치는 상기 외곽기초판(50)의 상부에 설치되어, 상기 잭다운 장치의 힘을 조절함으로써 상기 지하구조물의 침하량을 제어할 수 있으며,
상기 외곽기초판(50) 하부의 굴착과 지하구조물의 침하가 병행하여 이루어질 수 있도록 하는 것을 특징으로 하는,
구조물 시공방법.
A method of constructing an underground structure by applying the underground structure at the upper part of the ground,
In the method of constructing a structure,
a) constructing an outer foundation plate (50) and a pile (20);
b) installing a jack-down device;
c) lower excavation and settlement of the outer foundation plate 50;
d) a jack-down device disassembly and file (20) settlement step,
The jack-down device is installed at an upper portion of the outer foundation board 50 to control the settlement amount of the underground structure by adjusting the force of the jack-down device,
So that excavation under the outer foundation foundation plate (50) and settlement of the underground structure can be performed in parallel.
Construction method of structure.
제1항 또는 제2항에 있어서,
상기 침하는 지하구조물의 자중에 의해 이루어지는,
구조물 시공방법.
3. The method according to claim 1 or 2,
Wherein the settlement is caused by the self weight of the underground structure,
Construction method of structure.
제1항 또는 제2항에 있어서,
상기 침하는 지하구조물의 자중에 더하여, 추가 외력에 의해 이루어지는,
구조물 시공방법.
3. The method according to claim 1 or 2,
Wherein the settlement is caused by an additional external force in addition to the self weight of the underground structure,
Construction method of structure.
제4항에 있어서,
상기 추가 외력은,
상기 지하구조물에 임시 하중을 재하하여 하중을 증가시키는 방법;
지반 속에 설치한 락앵커(rock anchor) 또는 어스앵커(earth anchor)를 사용하는 방법;
지반 속에 설치한 파일의 주면마찰력을 이용하는 방법;
중 어느 하나의 방법에 의해 발생하는,
구조물 시공방법.
5. The method of claim 4,
The additional external force,
A method in which a temporary load is loaded on the underground structure to increase the load;
A method of using a rock anchor or an earth anchor installed in the ground;
A method of using a frictional force of a surface of a file installed in the ground;
Lt; RTI ID = 0.0 > 1, < / RTI >
Construction method of structure.
제1항 또는 제2항에 있어서,
상기 굴착은,
굴착장비를 사용하는 방법;
워터젯(water jet)을 사용하는 방법;
지반의 토사를 흡입하여 배출하는 방법; 중 어느 하나의 방법에 의해 이루어지는,
구조물 시공방법.
3. The method according to claim 1 or 2,
The excavation,
Methods of using excavation equipment;
A method using a water jet;
A method of sucking and discharging the soil from the ground; The method comprising the steps of:
Construction method of structure.
제1항에 있어서,
상기 D)단계 후에 기초판(10) 및 파일(20)의 상부에 추가 기초판을 시공하는 단계를 더 포함하는
구조물 시공방법.
The method according to claim 1,
Further comprising the step of constructing an additional base plate on top of the base plate (10) and the piles (20) after said step (D)
Construction method of structure.
제2항에 있어서,
상기 d)단계 후에 외곽기초판(50) 및 파일(20)의 상부에 추가 기초판을 시공하는 단계를 더 포함하는
구조물 시공방법.
3. The method of claim 2,
Further comprising the step of constructing an additional foundation plate on top of the outer foundation foundation 50 and the piles 20 after step d)
Construction method of structure.
삭제delete 삭제delete
KR1020190001641A 2019-01-07 2019-01-07 Structure construction method KR101960413B1 (en)

Priority Applications (6)

Application Number Priority Date Filing Date Title
KR1020190001641A KR101960413B1 (en) 2019-01-07 2019-01-07 Structure construction method
PCT/KR2019/013075 WO2020145483A1 (en) 2019-01-07 2019-10-04 Method for constructing structure
SG11202107482SA SG11202107482SA (en) 2019-01-07 2019-10-04 Method for constructing structure
CN201980088045.XA CN113614315A (en) 2019-01-07 2019-10-04 Method of constructing a structure
US17/420,979 US20220098817A1 (en) 2019-01-07 2019-10-04 Method for constructing structure
JP2021539593A JP2022517333A (en) 2019-01-07 2019-10-04 Structure construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020190001641A KR101960413B1 (en) 2019-01-07 2019-01-07 Structure construction method

Publications (1)

Publication Number Publication Date
KR101960413B1 true KR101960413B1 (en) 2019-03-20

Family

ID=66036173

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020190001641A KR101960413B1 (en) 2019-01-07 2019-01-07 Structure construction method

Country Status (6)

Country Link
US (1) US20220098817A1 (en)
JP (1) JP2022517333A (en)
KR (1) KR101960413B1 (en)
CN (1) CN113614315A (en)
SG (1) SG11202107482SA (en)
WO (1) WO2020145483A1 (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102113117B1 (en) * 2019-10-22 2020-05-20 김준성 Structure construction method using guide wall
WO2020145483A1 (en) * 2019-01-07 2020-07-16 김준성 Method for constructing structure
KR102199641B1 (en) 2019-09-19 2021-01-07 김성수 Construction method of driven pile for newly built structure
KR102215027B1 (en) 2020-08-31 2021-02-10 김상우 Construction method of structure using ground bearing capacity
CN112502464A (en) * 2020-11-23 2021-03-16 上海建工二建集团有限公司 Reverse construction method for extension basement under existing building
CN115467367A (en) * 2022-08-17 2022-12-13 湖北工业大学 Construction method for actively compensating deformation of underpass operation tunnel in upper-layer engineering construction
KR102522619B1 (en) * 2023-01-26 2023-04-17 주식회사 선공 Upward basement structure demolition method
KR102595013B1 (en) * 2023-02-09 2023-10-26 노경범 Construction Method of Underground Road to Minimize Traffic Control

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US11946217B1 (en) * 2023-09-18 2024-04-02 China Railway Tunnel Group Co., Ltd. Top plate jacking device and jacking construction method configured for V-shaped columns

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05247951A (en) * 1992-01-30 1993-09-24 Yuan Hoo Lee Construction method of basement of building and traction device used therefor
JPH07189266A (en) * 1993-06-29 1995-07-28 Toda Constr Co Ltd Method of construction of underground body
KR101034398B1 (en) * 2007-06-28 2011-05-16 (주)바로건설기술 Land-side protection wall that use ground structure
JP2012117209A (en) * 2010-11-29 2012-06-21 Kenji Machisuji Caisson method and equipment for caisson method
KR20130061368A (en) 2011-12-01 2013-06-11 정진덕 Structure of retaining wall and construction method for installing underground structures

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3430376B2 (en) * 1993-12-22 2003-07-28 大成建設株式会社 How to build an underground skeleton
JPH09302683A (en) * 1996-05-11 1997-11-25 Fujikou:Kk Construction method for basement
KR100641960B1 (en) * 2005-02-16 2006-11-06 이성우 Form for Footing Structure using Fiber Reinforced Composites Panel of Tubular Profile And Method for Constructing Footing Structure using such Form
CN101418573B (en) * 2008-01-24 2012-09-05 丁慈鑫 Caisson structure and method for smoothly and accurately sinking caisson structure into earth surface
CN101851930B (en) * 2010-01-15 2012-10-03 丁慈鑫 Sinking device of open caisson and sinking method of open caisson with same
CN107842046A (en) * 2017-11-27 2018-03-27 杨孝 A kind of strengthening of foundation error-correction structure and the method for strengthening of foundation correction
KR101960413B1 (en) * 2019-01-07 2019-03-20 김준성 Structure construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05247951A (en) * 1992-01-30 1993-09-24 Yuan Hoo Lee Construction method of basement of building and traction device used therefor
JPH07189266A (en) * 1993-06-29 1995-07-28 Toda Constr Co Ltd Method of construction of underground body
KR101034398B1 (en) * 2007-06-28 2011-05-16 (주)바로건설기술 Land-side protection wall that use ground structure
JP2012117209A (en) * 2010-11-29 2012-06-21 Kenji Machisuji Caisson method and equipment for caisson method
KR20130061368A (en) 2011-12-01 2013-06-11 정진덕 Structure of retaining wall and construction method for installing underground structures

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020145483A1 (en) * 2019-01-07 2020-07-16 김준성 Method for constructing structure
KR102199641B1 (en) 2019-09-19 2021-01-07 김성수 Construction method of driven pile for newly built structure
KR102113117B1 (en) * 2019-10-22 2020-05-20 김준성 Structure construction method using guide wall
KR102215027B1 (en) 2020-08-31 2021-02-10 김상우 Construction method of structure using ground bearing capacity
CN112502464A (en) * 2020-11-23 2021-03-16 上海建工二建集团有限公司 Reverse construction method for extension basement under existing building
CN112502464B (en) * 2020-11-23 2022-07-05 上海建工二建集团有限公司 Reverse construction method for extension basement under existing building
CN115467367A (en) * 2022-08-17 2022-12-13 湖北工业大学 Construction method for actively compensating deformation of underpass operation tunnel in upper-layer engineering construction
KR102522619B1 (en) * 2023-01-26 2023-04-17 주식회사 선공 Upward basement structure demolition method
KR102595013B1 (en) * 2023-02-09 2023-10-26 노경범 Construction Method of Underground Road to Minimize Traffic Control

Also Published As

Publication number Publication date
JP2022517333A (en) 2022-03-08
US20220098817A1 (en) 2022-03-31
WO2020145483A1 (en) 2020-07-16
CN113614315A (en) 2021-11-05
SG11202107482SA (en) 2021-08-30

Similar Documents

Publication Publication Date Title
KR101960413B1 (en) Structure construction method
KR101070426B1 (en) Improved Underpinning Method Using the micro pile
CN107542108A (en) A kind of reverse construction method of building basement structure
RU2414563C1 (en) Method to erect multistory subsurface structure
Godavarthi et al. Contiguous pile wall as a deep excavation supporting system
CN107035159A (en) A kind of method suitable for frame structure isolated footing building underground increasing layer
CN105839946A (en) Brick-concrete structure building lifting add-layer method
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN104264683A (en) Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building
JP3761323B2 (en) How to rebuild a building
CN106988337B (en) It is a kind of for reducing the reinforcement means of bar shaped shallow foundation house differential settlement
KR100976621B1 (en) Construction method for basement extention
CN115506382A (en) Construction method for pile plate wall of island building platform
CN111827705A (en) Method for expanding well barrel-shaped underground garage in existing underground garage
AU2020100004A4 (en) A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method
KR100663109B1 (en) Method for Constructing an Underground Structure Using Up-down Method
KR102113117B1 (en) Structure construction method using guide wall
Dellaria et al. Combining multiple techniques to complete an urban deep excavation
KR20200088659A (en) Top-down type underground structure construction method using earth support plate
Kordahi Underpinning strategies for buildings with deep foundations
KR100663108B1 (en) Method for Constructing an Underground Structure Using Up-down Method
CN110258621B (en) Assembled retaining wall convenient to quick construction
JPH0886117A (en) Building installation method
Yang Remediating a soil-nailed excavation in Wuhan, China
JPH09125405A (en) Deep foundation for inclined tower leg

Legal Events

Date Code Title Description
E701 Decision to grant or registration of patent right
GRNT Written decision to grant