JP3430376B2 - How to build an underground skeleton - Google Patents

How to build an underground skeleton

Info

Publication number
JP3430376B2
JP3430376B2 JP34642193A JP34642193A JP3430376B2 JP 3430376 B2 JP3430376 B2 JP 3430376B2 JP 34642193 A JP34642193 A JP 34642193A JP 34642193 A JP34642193 A JP 34642193A JP 3430376 B2 JP3430376 B2 JP 3430376B2
Authority
JP
Japan
Prior art keywords
underground skeleton
open
open caisson
impermeable wall
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
JP34642193A
Other languages
Japanese (ja)
Other versions
JPH07180164A (en
Inventor
喜志恭博
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Taisei Corp
Original Assignee
Taisei Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Taisei Corp filed Critical Taisei Corp
Priority to JP34642193A priority Critical patent/JP3430376B2/en
Publication of JPH07180164A publication Critical patent/JPH07180164A/en
Application granted granted Critical
Publication of JP3430376B2 publication Critical patent/JP3430376B2/en
Anticipated expiration legal-status Critical
Expired - Fee Related legal-status Critical Current

Links

Description

【発明の詳細な説明】Detailed Description of the Invention

【0001】[0001]

【産業上の利用分野】本発明は、地下躯体の築造方法に
関するものである。
BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method for constructing an underground structure.

【0002】[0002]

【従来の技術】近年、ビルなどの建築構造物あるいは土
木構造物も、平面的に大型化あるいは大深度化が進んで
いる。こうした、大型の地下構造物の建築に対して、安
全かつ効率的で経済性に富む工法が求められている。大
型の地下構造物を築造する場合、一般的には連続地中壁
あるいは鋼管矢板などの山留壁を、予定される構造物外
周に築造し、内部に山留支保工を設置し、掘削を繰り返
す工法が一般的である。
2. Description of the Related Art In recent years, building structures such as buildings and civil engineering structures have been increasing in size and depth in plan view. For such construction of large underground structures, safe, efficient and economical construction methods are required. When constructing a large underground structure, generally, a continuous underground wall or a mountain retaining wall such as a steel pipe sheet pile is built around the planned structure, and a mountain retaining structure is installed inside to excavate. The method of repeating is common.

【0003】[0003]

【発明が解決しようとする問題点】しかし、従来の方法
では、次のような問題点がある。 <イ>掘削に伴う山留支保工の組立の煩雑さ、多段に配
置されている山留支保工間の狭隘な場所での構築作業、
支保工の解体作業等、工種が複雑であり、危険性が高
い。 <ロ>工種が複雑化するため工程が増大し、工費が増加
する。
However, the conventional method has the following problems. <A> Complexity of assembling the mountain shoring support due to excavation, construction work in a narrow space between the mountain shoring supports arranged in multiple stages,
The type of work is complicated, such as the dismantling work of the supporting work, and the risk is high. <B> Since the type of work is complicated, the number of processes is increased and the work cost is increased.

【0004】[0004]

【本発明の目的】本発明は、作業工程が簡略化され、施
工精度が高いオープンケーソンによる地下躯体の築造方
法を提供することにある。
SUMMARY OF THE INVENTION It is an object of the present invention to provide a method of constructing an underground skeleton by an open caisson, which simplifies working steps and has high construction accuracy.

【0005】[0005]

【課題を解決するための手段】本発明は、オープンケー
ソンによる地下躯体の築造方法において、該地下躯体を
築造する範囲の外周で、該地下躯体の築造深度以深まで
遮水壁を設け、複数のオープンケーソンの下方にアース
アンカーを設け、複数のオープンケーソンの刃口近傍に
ジャッキを載置し、気中掘削し、該アースアンカーを該
ジャッキで引張り、引張り反力により複数のオープンケ
ーソンを同時に沈設し、複数のオープンケーソン間を接
続し、一体の地下躯体を築造することを特徴とする、地
下躯体の築造方法にある。
Means for Solving the Problems The present invention provides a method of constructing an underground skeleton by an open caisson, wherein an impermeable wall is provided to the outer periphery of a range where the underground skeleton is constructed to a depth deeper than the construction depth of the underground skeleton , Ground below the open caisson
Anchors are provided near the blades of multiple open caissons.
Place the jack, excavate in the air, and attach the earth anchor.
Pull it with a jack and use the pulling reaction force to
The caisson is simultaneously laid down and the open caisson is connected.
It is a method of constructing an underground skeleton, which is characterized by continuing and constructing an integral underground skeleton.

【0006】[0006]

【実施例】以下、図面を用いて本発明の実施例を説明す
る。 <イ>地下躯体 地下に躯体を構築する場合、躯体の構築予定地の周囲に
地下連続壁などの遮水壁2を構築する。遮水壁2の内部
領域の水位を低下するために、ディープウェル(揚水
井)3を掘る。遮水壁2の内部領域で地下水を低下しな
がら、気中掘削し、オープンケーソン1を沈設して、地
下躯体を構築する。オープンケーソン1の沈下には、刃
口11付近にセンターホールジャッキ41を配置し、ア
ースアンカー4の引張り反力を利用し、安全かつ正確に
行うことができる。大きな躯体を構築する場合は、複数
のオープンケーソン1を同時に沈設し、相互に接合する
ことにより構築する。
Embodiments of the present invention will be described below with reference to the drawings. <B> Underground building When building a building under the ground, a water impermeable wall 2 such as an underground continuous wall is built around the planned construction site of the building. In order to lower the water level in the inner area of the impermeable wall 2, the deep well (pumping well) 3 is dug. While lowering the groundwater in the inner area of the impermeable wall 2, the ground excavation is carried out and the open caisson 1 is sunk to construct an underground skeleton. When the open caisson 1 sinks, a center hole jack 41 is arranged near the blade opening 11, and the pulling reaction force of the ground anchor 4 can be used to perform it safely and accurately. When constructing a large skeleton, a plurality of open caissons 1 are simultaneously sunk and joined to each other.

【0007】<ロ>遮水壁 遮水壁2は、公知の連続地中壁などで地中に壁を構築
し、地下水がオープンケーソン1の構築現場に流入する
ことを阻止する。遮水壁2の深さは、オープンケーソン
1が最終的に沈設される深さより深めにとることによ
り、沈設作業での地下水の影響を除去するとともに、遮
水壁2外部領域の地下水の水位変動を押さえることがで
きる。遮水壁2の内部の複数箇所にディープウェル(揚
水井)3を設ける。ディープウェル3により遮水壁2の
内部の地下水を汲み上げて、地下水を低下させることが
できる。
<B> Impermeable Wall The impermeable wall 2 is a well-known continuous underground wall, etc., which is constructed underground to prevent groundwater from flowing into the construction site of the open caisson 1. By making the depth of the impermeable wall 2 deeper than the depth at which the open caisson 1 is finally submerged, the influence of groundwater in the subsidence work is removed and the water level fluctuation of the groundwater outside the impermeable wall 2 is eliminated. Can be held down. Deep wells (pumping wells) 3 are provided at a plurality of locations inside the impermeable wall 2. The deep well 3 can pump up groundwater inside the impermeable wall 2 to lower the groundwater.

【0008】<ハ>オープンケーソン オープンケーソン1は、外の枠が矩形、円形の形状のも
の、内部に仕切のあるものなど、地下躯体に応じて決め
られる。オープンケーソン1の下部には刃口11を有
し、刃口11付近にセンターホールジャッキ41が載置
可能な水平部を設ける。オープンケーソン1は遮水壁2
の内部領域に気中掘削により沈設され、地下躯体として
築造される。大型の地下躯体を築造する場合には、複数
のオープンケーソン1を気中掘削により同時に沈設し、
沈設終了後、ケーソン間を接続し、一体の地下躯体を築
造する。オープンケーソン1の沈下の際には、ディープ
ウェル3により地下水を汲上げながら水位を低下調整す
る。
<C> Open caisson The open caisson 1 is determined according to the underground skeleton, such as one having an outer frame having a rectangular shape, a circular shape, or one having a partition inside. The open caisson 1 has a blade opening 11 at a lower portion thereof, and a horizontal portion on which the center hole jack 41 can be placed is provided near the blade opening 11. Open caisson 1 is impermeable wall 2
It is sunk by aerial excavation in the inner area of and is built as an underground structure. When constructing a large underground structure, multiple open caisson 1 are simultaneously sunk by aerial excavation,
After the completion of the construction, the caisson will be connected and an integrated underground structure will be built. When the open caisson 1 sinks, the deep well 3 draws underground water to adjust the water level.

【0009】<ニ>アースアンカー オープンケーソン1の沈設下方に伸びるアースアンカー
4を設ける。オープンケーソン1の刃口11付近にセン
ターホールジャッキ41を配置し、アースアンカー4を
上方に引張り、オープンケーソン1に反力を与えること
により、オープンケーソン1の沈下を制御することがで
きる。センターホールジャッキ41が、オープンケーソ
ン1の下部に配置されるため、沈下の制御を正確に行う
ことができる。
<D> Earth Anchor An earth anchor 4 extending below the open caisson 1 is provided. By arranging the center hole jack 41 near the blade opening 11 of the open caisson 1, pulling the ground anchor 4 upward, and applying a reaction force to the open caisson 1, it is possible to control the settlement of the open caisson 1. Since the center hole jack 41 is arranged below the open caisson 1, the settlement can be accurately controlled.

【0010】<ホ>地盤改良 オープンケーソン躯体を地上で構築する際、オープンケ
ーソン1の据付地盤が、オープンケーソン躯体の重量を
支持できない場合、地盤改良を行い、重量に耐える地盤
にする。
<E> Ground improvement When constructing an open caisson skeleton body on the ground, if the installation ground of the open caisson 1 cannot support the weight of the open caisson skeleton body, the ground is improved to make it a weight-bearing ground.

【0011】<ヘ>基礎杭 地下躯体下方の支持層が深い場合は、基礎杭6を打ち、
基礎杭6で地上躯体を支持する。
<F> Foundation pile If the support layer below the underground structure is deep, strike the foundation pile 6
The foundation pile 6 supports the ground structure.

【0012】<ト>底版コンクリート オープンケーソン1が支持層に到達する深度で沈設され
た場合は、オープンケーソン躯体を底版コンクリート7
により支持層に直接保持する。基礎杭6で支持する場合
は、底版コンクリート7は基礎杭6とオープンケーソン
1を剛結するコンクリート7となる。底版コンクリート
7はオープンケーソン1の下部に打設される。
<G> When the bottom slab concrete open caisson 1 is sunk at a depth reaching the support layer, the open caisson skeleton body is replaced with the bottom slab concrete 7
Hold it directly on the support layer. When supported by the foundation pile 6, the bottom slab concrete 7 is the concrete 7 that rigidly connects the foundation pile 6 and the open caisson 1. The slab concrete 7 is placed below the open caisson 1.

【0013】<チ>オープンケーソン間の接合部 複数のオープンケーソン1を同時に沈設し、沈設終了
後、オープンケーソン1間の地盤を除去し、接合部5を
形成して、大型の地下躯体を築造する。
<H> Joint between open caissons A plurality of open caissons 1 are simultaneously sunk, and after the completion of the digging, the ground between the open caisson 1 is removed and a joint 5 is formed to build a large underground structure. To do.

【0014】以下に、オープンケーソンの沈設工程を説
明する。 <イ>遮水壁の構築 地下躯体を築造する範囲の外周に地中連続壁により遮水
壁2を設ける。遮水壁2の深さは、地下躯体の深度以深
まで設け、地下水の遮断を行う。ディープウェル3を遮
水壁2の内部で、遮水壁2の下端付近まで設け、内部の
地下水を除去し、水位の調整を行う。地盤が悪く、オー
プンケーソン躯体を支持できない場合は、地盤改良を行
う。アースアンカー4はオープンケーソン1の沈設位置
よりも深く設ける。
The process of staking the open caisson will be described below. <A> Construction of impermeable wall An impermeable wall 2 is provided by a continuous underground wall on the outer periphery of the area where the underground structure is built. The depth of the impermeable wall 2 is set to a depth below the depth of the underground structure to shut off groundwater. The deep well 3 is provided inside the impermeable wall 2 up to near the lower end of the impermeable wall 2 to remove the groundwater inside and to adjust the water level. If the ground is poor and the open caisson structure cannot be supported, ground improvement will be performed. The earth anchor 4 is provided deeper than the sunk position of the open caisson 1.

【0015】<ロ>オープンケーソンの沈設 オープンケーソン1の刃口11付近にセンターホールジ
ャッキ41を固定し、アースアンカー4の緊張材を取付
ける。気中掘削を行い、センターホールジャッキ41を
作動し、その反力でオープンケーソン1を沈下させる。
この際、ディープウェル3を用いて、オープンケーソン
刃口11近傍の地下水位を低下調整する。大型の地下躯
体を築造する場合は、複数のオープンケーソン1を同時
に沈設する。
<B> Sinking of open caisson A center hole jack 41 is fixed near the blade opening 11 of the open caisson 1, and a tension member for the earth anchor 4 is attached. The air is excavated, the center hole jack 41 is operated, and the open caisson 1 is sunk by its reaction force.
At this time, the deep well 3 is used to lower and adjust the groundwater level near the open caisson blade 11. When constructing a large underground structure, multiple open caisson 1 are sunk at the same time.

【0016】<ハ>地下躯体の構築 オープンケーソン1が支持層に到達する深度で沈設する
場合、オープンケーソンの下部に底版コンクリート7を
打設し、オープンケーソン1を支持層に固定する。支持
層が深い場合、支持杭を打ち、支持杭とオープンケーソ
ン1を底版コンクリート7で剛結する。複数のオープン
ケーソン1を沈設した場合は、オープンケーソン間の地
盤を掘削し、オープンケーソン1間を接続する。
<C> Construction of underground skeleton When the open caisson 1 is sunk at a depth reaching the support layer, a bottom slab concrete 7 is placed below the open caisson to fix the open caisson 1 to the support layer. When the support layer is deep, the support pile is hit and the support pile and the open caisson 1 are rigidly connected with the bottom slab concrete 7. When a plurality of open caissons 1 are sunk, the ground between the open caissons is excavated and the open caisson 1 is connected.

【0017】[0017]

【発明の効果】本発明は、次のような効果を得ることが
できる。 <イ>気中で掘削が行われるので、掘削効率を向上でき
る。 <ロ>刃口下の掘削が自由に行えるため、躯体の傾斜修
正など、沈下制御が自由に行え、沈設精度が向上でき
る。 <ハ>同時沈設された躯体が気中で接合できるため、施
工効率、施工精度が高く、高品質、急速施工化、低コス
トが得られる。 <ニ>オープンケーソンの沈下に伴い、その刃口近傍で
徐々に地下水の水位を低下するため、遮水壁2の遮水性
が低い場合でも、周辺の地下水位の低下に与える影響は
少ない。
According to the present invention, the following effects can be obtained. <A> Since excavation is performed in the air, excavation efficiency can be improved. <B> Since the excavation under the blade can be freely performed, the sinking control such as the inclination correction of the skeleton can be freely performed, and the sinking accuracy can be improved. <C> Since the simultaneously-deposited skeletons can be joined in the air, the construction efficiency and construction accuracy are high, and high quality, rapid construction, and low cost can be obtained. <D> As the open caisson sinks, the water level of the groundwater gradually decreases in the vicinity of the cutting edge, so even if the water impermeability of the water-impervious wall 2 is low, it has little effect on the lowering of the groundwater level in the vicinity.

【図面の簡単な説明】[Brief description of drawings]

【図1】オープンケーソンの沈下を示す図FIG. 1 Diagram showing settlement of open caisson

【図2】オープンケーソンの沈下の平面図[Figure 2] Plan view of settlement of open caisson

【図3】オープンケーソンの沈設前の遮水壁の内部を示
す図
FIG. 3 is a view showing the inside of the impermeable wall before the open caisson is sunk.

【図4】オープンケーソンの沈下開始を示す図FIG. 4 is a diagram showing the start of settlement of an open caisson.

【図5】オープンケーソンの沈設図[Figure 5] Open caisson sinking diagram

【符号の説明】[Explanation of symbols]

1・・オープンケーソン 2・・遮水壁 3・・ディープウェル 4・・アースアンカー 1. Open caisson 2 ... Impermeable wall 3 ... Deepwell 4 ... Earth anchor

Claims (3)

(57)【特許請求の範囲】(57) [Claims] 【請求項1】オープンケーソンによる地下躯体の築造方
法において、 該地下躯体を築造する範囲の外周で、該地下躯体の築造
深度以深まで遮水壁を設け、 複数のオープンケーソンの下方にアースアンカーを設
け、 複数のオープンケーソンの刃口近傍にジャッキを載置
し、 気中掘削し、該アースアンカーを該ジャッキで引張り引張り 反力により複数のオープンケーソンを同時に沈設
し、 複数のオープンケーソン間を接続し、一体の地下躯体を
築造することを特徴とする、 地下躯体の築造方法。
1. A method of constructing an underground skeleton by an open caisson, wherein an impermeable wall is provided to the outer periphery of a range where the underground skeleton is built to a depth deeper than the construction depth of the underground skeleton, and earth anchors are provided below the plurality of open caisson. Install, place jacks near the blade openings of multiple open caissons, excavate in the air, pull the earth anchor with the jacks, and simultaneously sink multiple open caissons by pulling reaction force, A method of constructing an underground skeleton, which is characterized by connecting and building an integral underground skeleton.
【請求項2】オープンケーソンによる地下躯体の築造方
法において、 該地下躯体を築造する範囲の外周で、該地下躯体の築造
深度以深まで遮水壁を設け、 該遮水壁で包囲されている内部にディープウェルを設
け、 複数のオープンケーソンの下方にアースアンカーを設
け、 複数のオープンケーソンの刃口近傍にジャッキを載置
し、 該遮水壁の内部の地下水位を低下させながら、気中掘削
し、該アースアンカーを該ジャッキで引張り引張り
力により複数のオープンケーソンを同時に沈設し、 複数のオープンケーソン間を接続し、オープンケーソン
の下部を底版コンクリートで補強し、一体の地下躯体を
築造することを特徴とする、地下躯体の築造方法。
2. A method of constructing an underground skeleton by an open caisson, wherein an impermeable wall is provided to the outer periphery of the range where the underground skeleton is constructed to a depth below the construction depth of the underground skeleton, and the interior surrounded by the impermeable wall. A deep well is installed on the ground, ground anchors are installed below the open caissons, jacks are placed near the blades of the open caisson, and the groundwater level inside the impermeable wall is lowered while drilling in the air. Then, pull the earth anchor with the jack, sunk multiple open caisson at the same time by pulling reaction force, connect multiple open caissons, and reinforced the lower part of the open caisson with bottom slab concrete to build an integrated underground skeleton. A method of constructing an underground skeleton, characterized by:
【請求項3】オープンケーソンによる地下躯体の築造方
法において、 該地下躯体を築造する範囲の外周で、該地下躯体の築造
深度以深まで遮水壁を設け、 該遮水壁で包囲されている内部にディープウェルを設
け、 該遮水壁で包囲されている内部に地盤改良材を注入して
地盤を改良し、 複数のオープンケーソンの下方にアースアンカーを設
け、 複数のオープンケーソンの刃口近傍にジャッキを載置
し、 該遮水壁の内部の地下水位を低下させながら、気中掘削
し、該アースアンカーを該ジャッキで引張り引張り
力により複数のオープンケーソンを同時に沈設し、 複数のオープンケーソン間を接続し、オープンケーソン
の下部を底版コンクリートで補強し、一体の地下躯体を
築造することを特徴とする、 地下躯体の築造方法。
3. A method of constructing an underground skeleton by an open caisson, wherein an impermeable wall is provided at an outer periphery of a range where the underground skeleton is constructed to a depth deeper than a construction depth of the underground skeleton, and an interior surrounded by the impermeable wall. A deep well is installed in the ground, the ground improvement material is injected into the interior surrounded by the impermeable wall to improve the ground, and ground anchors are installed below the open caissons, near the cutting edges of the open caissons. Place a jack, excavate in the air while lowering the groundwater level inside the impermeable wall, pull the earth anchor with the jack, and simultaneously sunk multiple open caissons by pulling reaction force, and open multiple A method of constructing an underground skeleton, characterized by connecting the caisson, reinforcing the lower part of the open caisson with bottom slab concrete, and constructing an integrated underground skeleton.
JP34642193A 1993-12-22 1993-12-22 How to build an underground skeleton Expired - Fee Related JP3430376B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP34642193A JP3430376B2 (en) 1993-12-22 1993-12-22 How to build an underground skeleton

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP34642193A JP3430376B2 (en) 1993-12-22 1993-12-22 How to build an underground skeleton

Publications (2)

Publication Number Publication Date
JPH07180164A JPH07180164A (en) 1995-07-18
JP3430376B2 true JP3430376B2 (en) 2003-07-28

Family

ID=18383309

Family Applications (1)

Application Number Title Priority Date Filing Date
JP34642193A Expired - Fee Related JP3430376B2 (en) 1993-12-22 1993-12-22 How to build an underground skeleton

Country Status (1)

Country Link
JP (1) JP3430376B2 (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100984898B1 (en) * 2008-06-09 2010-10-01 위성배 The Construction Method of Descenting Underground Structure
KR101960413B1 (en) * 2019-01-07 2019-03-20 김준성 Structure construction method

Also Published As

Publication number Publication date
JPH07180164A (en) 1995-07-18

Similar Documents

Publication Publication Date Title
CN110359476B (en) Construction method of construction platform for mounting steel sheet pile cofferdam inner support and bored pile steel casing
JP4942230B1 (en) Submersible method and equipment for submerged method
JP2001032673A (en) Tunnel work execution method
JP3516391B2 (en) Ground excavation method
JP3430376B2 (en) How to build an underground skeleton
CN109989346A (en) Bridge major diameter precast concrete tubular column basis and its construction method
CN106545018B (en) Excavation slope excavation construction process and excavation slope
JPH07145616A (en) Cast-in-place concrete piling method
JP2868651B2 (en) Earth retaining method above existing underground structure
KR101052363B1 (en) Freestanding Digging Method for Deep Excavation
CN114411781A (en) Construction method of rock geological sheet pile cofferdam
JP2001271365A (en) Construction method for underground structure
JP4475116B2 (en) Vertical shaft structure and its construction method
JP2858997B2 (en) Temporary support column used for reverse driving method
KR200373276Y1 (en) Steel pipe pile of support structure
JP2000355941A (en) Building and its construction method
CN214245742U (en) Deep mixed reinforced cement soil anchoring pile
JP6586213B2 (en) Construction method of jacket structure
JP2013024005A (en) Support construction method of structure
JPH01226935A (en) Transmission line tower foundation and its construction
KR200373275Y1 (en) Steel pipe pile of support structure
CN107237331A (en) A kind of foundation ditch construction method of utilization water pressure supporting
JP3809340B2 (en) Reverse strike method
JP3537641B2 (en) Basement submersion method and its equipment
JPS5991228A (en) Pit excavation work using caisson

Legal Events

Date Code Title Description
R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

R250 Receipt of annual fees

Free format text: JAPANESE INTERMEDIATE CODE: R250

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090523

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20090523

Year of fee payment: 6

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20100523

Year of fee payment: 7

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20110523

Year of fee payment: 8

FPAY Renewal fee payment (event date is renewal date of database)

Free format text: PAYMENT UNTIL: 20120523

Year of fee payment: 9

LAPS Cancellation because of no payment of annual fees