KR100663108B1 - Method for Constructing an Underground Structure Using Up-down Method - Google Patents

Method for Constructing an Underground Structure Using Up-down Method Download PDF

Info

Publication number
KR100663108B1
KR100663108B1 KR1020050014572A KR20050014572A KR100663108B1 KR 100663108 B1 KR100663108 B1 KR 100663108B1 KR 1020050014572 A KR1020050014572 A KR 1020050014572A KR 20050014572 A KR20050014572 A KR 20050014572A KR 100663108 B1 KR100663108 B1 KR 100663108B1
Authority
KR
South Korea
Prior art keywords
constructing
underground
excavation
wall
central
Prior art date
Application number
KR1020050014572A
Other languages
Korean (ko)
Other versions
KR20060093815A (en
Inventor
홍성영
오성남
Original Assignee
주식회사 스마텍엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 스마텍엔지니어링 filed Critical 주식회사 스마텍엔지니어링
Priority to KR1020050014572A priority Critical patent/KR100663108B1/en
Publication of KR20060093815A publication Critical patent/KR20060093815A/en
Application granted granted Critical
Publication of KR100663108B1 publication Critical patent/KR100663108B1/en

Links

Images

Classifications

    • AHUMAN NECESSITIES
    • A47FURNITURE; DOMESTIC ARTICLES OR APPLIANCES; COFFEE MILLS; SPICE MILLS; SUCTION CLEANERS IN GENERAL
    • A47LDOMESTIC WASHING OR CLEANING; SUCTION CLEANERS IN GENERAL
    • A47L15/00Washing or rinsing machines for crockery or tableware
    • A47L15/42Details
    • A47L15/4293Arrangements for programme selection, e.g. control panels; Indication of the selected programme, programme progress or other parameters of the programme, e.g. by using display panels

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

본 발명은 지하 구조물의 상향 축조되는 기둥과 하향 축조되는 슬래브 등의 지하층 구조물을 이용하여 지하 터파기 후 흙막이 공사와 구조물의 축조를 동시에 시행함으로써 공사의 효율성을 향상시키며, 공기 단축 및 공사비 절감의 효과를 발휘할 수 있는 새로운 구성의 무지보 업-다운(up-down) 방식의 흙막이 지보공을 이용한 지하 구조물 시공방법에 관한 것이다.The present invention improves the efficiency of construction work by constructing the earthquake construction and the structure at the same time after the excavation of the underground by using the basement structure such as the column to be built up and the slab to be built down the underground structure, the effect of shortening the air and reducing the construction cost The present invention relates to a method for constructing underground structures using an up-down earth retaining jib hole of a new configuration capable of exerting a high performance.

본 발명에서는, 지반을 터파기하여 지하 구조물을 시공하는 방법으로서, 굴착 경계면을 따라 흙막이 벽체를 시공하는 단계; 흙막이 벽체로부터 소정 거리 떨어진 위치까지 안식각을 유지한 상태로 사면을 이루도록 중앙을 터파기하여 중앙 굴착부를 형성하는 단계; 상기 중앙 굴착부의 바닥면에 기초구조물 및 기둥을 시공하는 단계; 구조물의 지상 1층에 해당하며, 횡방향으로는 흙막이 벽체를 지지하는 지상층 구조물을 상기 기둥의 상부에 시공하는 단계; 상기 중앙 굴착부의 기초구조물과 기둥 주변에 사면 형태로 남아 있던 사면토사를 지하 한 층 구조물 높이 이상으로 굴착하는 단계; 상기 굴착 지반 상부로 지하 1층에 해당하며 횡방향으로는 흙막이 벽체를 지지하는 지하 1층 구조물을 시공하는 단계; 상기 중앙 굴착부 주위의 잔류 토사를 굴착하는 단계; 및 굴착된 바닥면에 콘크리트를 타설하여 바닥 슬래브를 완성하여 지하 2층 구조물을 시공하는 단계를 포함하여 구성되는 것을 특징으로 하는 지하 구조물 시공방법이 제공된다. In the present invention, a method for constructing an underground structure by digging the ground, comprising the steps of: constructing a wall along the excavation interface; Forming a central excavation by digging a center to form a slope while maintaining an angle of repose to a position away from the wall of the earth wall; Constructing a foundation and a pillar on the bottom surface of the central excavation portion; A ground floor structure corresponding to the ground floor of the structure, and transversely supporting the ground wall structure on the top of the pillar; Excavating the sloped soil remaining in the form of a slope around the base structure and the pillar of the central drilling portion above the height of the underground one-story structure; Constructing an underground first floor structure corresponding to an underground first floor above the excavation ground and supporting an earth wall in a transverse direction; Excavating residual soil around the central excavation; And laying the concrete on the excavated bottom surface to complete the floor slab is provided an underground structure construction method comprising a step of constructing a two-story underground structure.

터파기, 흙막이 벽체, 지하 구조물, 지보공 Dig, Climbing Wall, Underground Structure, Jibo

Description

무지보 업-다운 방식의 흙막이 지보공을 이용한 지하 구조물 시공방법{Method for Constructing an Underground Structure Using Up-down Method} Method for constructing an underground structure using up-down method

도 1 내지 도 7은 본 발명의 흙막이 시공방법을 구성하는 각 단계를 보여주는 개략적인 굴착 단면도이다.  1 to 7 is a schematic excavation cross-sectional view showing each step constituting the earthquake construction method of the present invention.

도 8a 내지 도 8c는 본 발명의 흙막이 시공방법의 변형 실시예에 포함된 시공 단계를 보여주는 개략적인 굴착 단면도이다.  8a to 8c is a schematic excavation cross-sectional view showing a construction step included in a modified embodiment of the earthquake construction method of the present invention.

<도면의 주요 부분에 대한 부호의 설명> <Explanation of symbols for the main parts of the drawings>

1 : 흙막이 벽체 2 : 중앙 굴착부1: earth wall 2: central excavation

3 : 기초구조물 4 : 기둥 3: foundation structure 4: column

10 : 지상층 구조물 11 : 지하 1층 구조물10: ground floor structure 11: underground basement structure

12 : 바닥 슬래브12: floor slab

본 발명은 지하 구조물의 시공방법에 관한 것으로서, 구체적으로는 지하 구조물의 상향 축조되는 기둥과 하향 축조되는 슬래브 등의 지하층 구조물을 이용하여 지하 터파기 후 흙막이 공사와 구조물의 축조를 동시에 시행함으로써 공사의 효율성을 향상시키며, 공기 단축 및 공사비 절감의 효과를 발휘할 수 있는 새로운 구성의 무지보 업-다운(up-down) 방식의 흙막이 지보공을 이용한 지하 구조물 시공방법에 관한 것이다. The present invention relates to a method of constructing an underground structure, specifically, by using a basement structure, such as a column to be built up and a down-constructed slab of the underground structure, the earthquake construction and the construction of the structure at the same time after the excavation of the underground construction. The present invention relates to a method for constructing an underground structure using an up-down mud supporter of a new configuration that can improve efficiency and reduce air and reduce construction costs.

일반적으로 지하 구조물 시공을 위한 흙막이 공사는 흙과 접하여 흙의 유동을 막는 흙막이 벽체의 설치와 흙막이 벽체를 지지하는 지보공이 그 중요한 부분을 차지한다. 구체적인 시공방법과 사용 재료에 따라 다양한 흙막이 공사방법이 존재하는데, 흙막이 벽체를 설치하는 방식에 따라 쉬트파일공법, 엄지말뚝-토류판 공법, 지중연속벽 공법, 주열식 벽체공법 등의 대표적인 공법이 존재하며, 지보공의 형식에 따라서는 스트러트 공법, 어스앵커공법, 네일링 공법 등이 대표적인 공법으로 꼽히고 있다. In general, the earthquake construction for the construction of underground structures occupies an important part of the installation of the earthquake wall to prevent the flow of soil in contact with the soil and the jibogong which supports the earthquake wall. According to the concrete construction method and the material used, there are various construction methods for earthquake. There are representative construction methods such as sheet pile method, thumb pile-earth plate method, underground continuous wall method, and columnar wall method depending on the method of installing the wall. Depending on the type of jibo ball, strut method, earth anchor method, and nailing method are considered as typical methods.

최근에는 도심지의 재개발, 재건축 등이 활발하게 진행되면서 지하 굴착 심도는 약 10m 내외로 그다지 깊지 않으나, 폭이 50m 이상이 되는 저심도 광폭 굴착 공사 현장이 늘어나고 있는 추세이다. 특히, 도심지에서는 일반적으로 대지 활용도를 높이기 위하여 인접 대지 경계선 가까이 굴착 공사기 진행되는 경우가 많다. 흙막이 벽체를 지지하기 위한 지보공으로 어스앵커 공법이 효율적임에도 불구하고, 이러한 도심지의 저심도 광폭 굴착 공사에 있어서는, 인접 대지 지하를 관통하여야만 하는 어스앵커 공법을 적용할 수가 없다. 따라서, H형강을 사용하는 버팀대 공 법을 지보공으로 적용하게 되는데, 이러한 H형강을 사용한 버팀대 공법의 경우에는 강재 소모량이 막대하여 공사비가 많이 소요되는 단점이 있으며, 공사 기간도 길기 때문에 공사 효율 및 경제성이 낮다는 문제점이 있다. 이러한 버팀대 공법을 변형하여 버팀대를 경사지게 설치한 소위 레이커(raker)공법의 경우에는 강재 소모량을 줄일 수 있으나, 역학적 안정성이 낮기 때문에 주변 지반의 침하를 유발하여 붕괴사고의 위험이 매우 높다는 문제점이 있다. Recently, with the redevelopment and reconstruction of the downtown area, the depth of underground excavation is not very deep, about 10m, but the low-depth wide-area excavation construction sites that are more than 50m in width are increasing. In particular, in urban areas, excavation work is often performed near the adjacent land boundary to increase land utilization. Although the earth anchor method is effective for supporting the earth wall, the earth anchor method, which must penetrate the adjacent ground, cannot be applied to the low-depth wide-area excavation work in the downtown area. Therefore, the brace method using the H-beam is applied as the support, but in the case of the brace method using the H-beam, the steel consumption is enormous, which requires a lot of construction costs. There is a problem that this is low. In the case of a so-called raker method in which the prop is inclined to be modified by the prop method, the steel consumption can be reduced, but there is a problem that the risk of collapse is very high due to low mechanical stability, causing settlement of the surrounding ground.

따라서, 도심지의 저심도 광폭 굴착 공사에 적합하면서도 공사의 용이성, 공사 기간 단축 및 공사비 절감의 효과를 발휘할 수 있는 새로운 방식으로 흙막이 벽체를 지지할 수 있는 지하 구조물 시공방법의 개발이 절실히 요구되고 있는 실정이다. Therefore, there is an urgent need for the development of a method for constructing underground structures that can support mud walls in a new way that is suitable for low-depth wide-area excavation works in urban areas, but also to facilitate the ease of construction, shorten the construction period and reduce construction costs. to be.

본 발명은 업계의 요구에 부응하기 위하여 개발된 것으로서, 지하층을 시공함에 있어서 공사의 용이성, 공사 기간 단축 및 공사비 절감의 효과를 발휘할 수 있으며, 도심지의 저심도 광폭 굴착 형태의 흙막이 공사에 적합한 새로운 시공방법을 제공하는 것을 목적으로 한다. The present invention was developed to meet the demands of the industry, and can exhibit the effect of ease of construction, shortening the construction period and reducing the construction cost in the construction of the basement, new construction suitable for low-depth wide-scale excavation construction in the downtown area It is an object to provide a method.

상술한 본 발명의 목적은, 지반을 터파기하여 지하 구조물을 시공하는 방법으로서, 굴착 경계면을 따라 흙막이 벽체를 시공하는 단계; 흙막이 벽체로부터 소 정 거리 떨어진 위치까지 안식각을 유지한 상태로 사면을 이루도록 중앙을 터파기하여 중앙 굴착부를 형성하는 단계; 상기 중앙 굴착부의 바닥면에 기초구조물 및 기둥을 시공하는 단계; 구조물의 지상 1층에 해당하며, 횡방향으로는 흙막이 벽체를 지지하는 지상층 구조물을 상기 기둥의 상부에 시공하는 단계; 상기 중앙 굴착부의 최외측 기초구조물과 기둥 주변에 사면 형태로 남아 있던 사면토사를 지하 한 층 구조물 높이 이상으로 굴착하는 단계; 상기 굴착 지반 상부로 지하 1층에 해당하며 횡방향으로는 흙막이 벽체를 지지하는 지하 1층 구조물을 시공하는 단계; 상기 중앙 굴착부 주위의 잔류 토사를 굴착하는 단계; 및 굴착된 바닥면에 콘크리트를 타설하여 바닥 슬래브를 완성하여 지하 2층 구조물을 시공하는 단계를 포함하여 구성되는 것을 특징으로 하는 지하 구조물 시공방법에 의하여 달성된다. An object of the present invention described above is a method of constructing an underground structure by breaking the ground, comprising the steps of: constructing a wall along the excavation interface; Forming a central excavation by digging a center to form a slope while maintaining an angle of repose to a position away from the wall of the earth wall; Constructing a foundation and a pillar on the bottom surface of the central excavation portion; A ground floor structure corresponding to the ground floor of the structure, and transversely supporting the ground wall structure on the top of the pillar; Excavating the sloped soil remaining in the form of a slope around the outermost base structure and the pillar of the central excavation portion more than the height of one underground structure; Constructing an underground first floor structure corresponding to an underground first floor above the excavation ground and supporting an earth wall in a transverse direction; Excavating residual soil around the central excavation; And by placing concrete on the excavated floor surface is completed by the underground structure construction method comprising the step of completing the floor slab to construct a two-story underground structure.

본 발명에서는 상기한 시공방법의 구체적인 일 실시예로서, 바닥 슬래브를 완성하기에 앞서, 중앙 굴착부 주위의 잔류 토사의 굴착 단계 및 지하층 구조물 시공단계를 반복하여 추가적인 지하층을 더 시공하는 단계를 더 포함함으로써 지하로 2층 이상의 층을 갖는 지하 구조물을 시공하게 되는 것을 특징으로 하는 지하 구조물 시공방법이 제공된다. In the present invention, as a specific embodiment of the above construction method, prior to completing the floor slab, further comprises the step of further construction of the additional underground layer by repeating the excavation step of the residual soil around the central excavation and the construction of the basement layer structure Thereby, there is provided an underground structure construction method comprising constructing an underground structure having two or more layers underground.

또한 본 발명에서는 상기한 시공방법에서, 상기 지상층 구조물 및 지하층 구조물을 시공함에 있어서, 상기 지상층 구조물 및 상기 지하층 구조물은 그 주변이 흙막이 벽체까지 연장되어 상기 흙막이 벽체와 평면상으로 폐합된다. In the present invention, in the above-described construction method, in constructing the ground layer structure and the basement layer structure, the ground layer structure and the basement layer structure have their periphery extending to the wall of the earth wall so as to be closed in plane with the earth wall.

본 발명에서는 상기한 시공방법의 구체적인 일 실시예로서, 바닥 슬래브를 완성하기에 앞서, 중앙 굴착부 주위의 잔류 토사의 굴착 단계 및 지하층 구조물 시 공단계를 반복하여 추가적인 지하층을 더 시공하는 단계를 더 포함함으로써 지하로 2층 이상의 층을 갖는 지하 구조물을 시공하게 되는 것을 특징으로 하는 지하 구조물 시공방법이 제공된다. In the present invention, as a specific embodiment of the above-described construction method, prior to completing the floor slab, by repeating the excavation step of the remaining soil around the central excavation and the construction step of the basement layer structure, further construction of the additional basement layer By providing an underground structure construction method comprising the construction of an underground structure having two or more floors underground.

한편, 중앙 굴착부를 형성함에 있어서, 흙막이 벽체의 일측에만 사면이 유지되고 반대편 흙막이 벽체에는 사면 없이 흙막이 벽체가 노출되도록 굴착한 후, 후속 시공단계를 시행함으로써, 상기한 본 발명의 시공방법이 흙막이 벽체의 일측에 대해서만 적용되도록 할 수 있다. On the other hand, in forming the central excavation, the slope is maintained only on one side of the retaining wall and the excavating wall is exposed to the opposite retaining wall without the slope, and then the subsequent construction step is carried out, the construction method of the present invention described above is the retaining wall Only one side of can be applied.

이하, 첨부된 예시도면을 참조하여 본 발명의 지하 구조물 시공방법을 각 단계별로 설명한다. 도 1 내지 도 7에는 본 발명의 시공방법을 구성하는 각 단계를 설명하기 위한 개략적인 굴착 단면도가 도시되어 있다. Hereinafter, with reference to the accompanying drawings will be described in each step the construction method of the underground structure of the present invention. 1 to 7 are schematic excavation cross-sectional views for explaining each step constituting the construction method of the present invention.

우선 흙막이 벽체용 파일을 관입하거나 또는 현장타설 콘크리트 벽체 또는 말뚝 벽체 등을 이용하여 도 1에 도시된 것처럼 굴착 경계면을 따라 흙막이 벽체(1)를 시공한다. 본 발명에 있어서, 흙막이 벽체(1)를 시공하는 방법이나 흙막이 벽체(1)의 형식에는 제한이 없다. First, the piling wall 1 is constructed along the excavation interface as shown in FIG. 1 by injecting the piling wall pile or by using a cast-in-place concrete wall or a pile wall. In this invention, there is no restriction | limiting in the method of constructing the retaining wall 1 and the form of the retaining wall 1.

후속하여 중앙부를 굴착하게 되는데, 도 2에 도시된 것처럼, 흙막이 벽체(1)로부터 소정 거리 떨어진 위치까지 즉, 후술하는 바와 같이 기초구조물과 기둥이 설치되는 위치 부근까지 안식각을 유지한 상태로 사면을 이루도록 중앙을 터파기하여 중앙 굴착부(2)를 형성한다. 중앙 굴착부(2)의 굴착이 완료되면, 슬래브 기초 또는 독립 기초 등의 기초구조물(3)을 시공하고, 지하 구조물을 지지하는 기둥(4) 을 상기 기초구조물(3) 위로 시공한다(도 3). 상기 기초구조물(3)은 도면의 실시예에 도시된 것처럼 독립기초 형식의 것일 수도 있지만, 경우에 따라서는 연속기초 형식의 것일 수도 있다. 요컨대, 본 발명에 있어서 상기 기초구조물(3)의 형식에는 제한이 없다. Subsequently, the center portion is excavated, and as shown in FIG. 2, the slope is maintained to a position away from the earth wall 1 by a predetermined distance, that is, near the position where the foundation structure and the pillar are installed as described below. The center is excavated to form a central excavation 2. When the excavation of the central excavation 2 is completed, the foundation 3 is constructed such as a slab foundation or an independent foundation, and the pillar 4 supporting the underground structure is constructed on the foundation 3 (FIG. 3). ). The foundation 3 may be in the form of an independent basis, as shown in the embodiment of the figure, but in some cases may also be of the form of a continuous basis. In short, in the present invention, the type of the foundation structure 3 is not limited.

기초구조물(3) 및 기둥(4)의 시공이 완료되면, 그 상부에 지상 1층을 형성하는 지상층 슬래브 또는 지상층 거더 등으로 이루어진 지상층 구조물(10)을 시공한다. 이 때, 지상층 구조물(10)의 주변을 흙막이 벽체(1)의 상부까지 연장하여 지상층 구조물(10)과 흙막이 벽체(1)가 평면상으로 완전히 폐합시킴으로써 지상층 구조물(10)이 흙막이 벽체(1)를 지지되도록 한다. When the construction of the basic structure (3) and the column (4) is completed, the ground layer structure 10 consisting of a ground layer slab or ground layer girder, etc. to form a ground layer on top thereof is constructed. At this time, the periphery of the ground layer structure 10 extends to the upper part of the retaining wall 1 so that the ground layer structure 10 and the retaining wall 1 are completely closed in a plane, and thus the ground layer structure 10 becomes the retaining wall 1. To be supported.

다음으로, 사면 형태로 남아 있던 중앙 굴착부(2) 주위의 토사를 굴착한다. 즉, 도 4에 도시된 것처럼, 최외측 기초구조물(3)과 기둥(4) 주변의 사면토사를 지하 구조물의 한 층간 높이 정도로 굴착한다. Next, the earth and sand around the central excavation part 2 which remained in the form of a slope is excavated. That is, as shown in FIG. 4, the sloped soil around the outermost foundation 3 and the pillar 4 is excavated to a height between one floor of the underground structure.

후속하여, 지하 1층에 해당하는 지하 1층 슬래브 또는 지하 1층 거더 등의 지하 1층 구조물(11)을 시공한다(도 5). 상기 지상층 구조물(10)과 마찬가지로, 상기 지하 1층 구조물(11)은 그 주변이 흙막이 벽체(1)까지 연장되어 흙막이 벽체(1)와 평면상으로 완전히 폐합된 형태를 이루게 된다. 이와 같이, 본 발명에서는 지하 1층 구조물(11)이 흙막이 벽체(1)의 지보공 기능을 하게 되므로, 종래의 경우처럼 흙막이 벽체(1)를 지지하기 위한 버팀대를 별도로 설치할 필요가 없으며, 그에 따라 지보공에 사용되는 강재 소모량을 감소시킬 수 있다. 특히, 슬래브 또는 거더로 이루어진 층 구조물은 강성이 매우 큰 구조물로서, 이러한 높은 강성의 지 하층 구조물을 흙막이 벽체(1) 지지를 위한 지보공에 사용하게 되므로 흙막이 벽체(1)의 안정성을 현저하게 향상시킬 수 있게 된다. 즉, 굴착 공사 주변의 지반의 변위와 침하를 적극적으로 억제할 수 있어 굴착 공사의 안정성을 현저하게 향상시킬 수 있는 것이다. 그 뿐만 아니라, 흙막이 벽체(1)의 지보공과 함께 지하 구조물의 축조를 동시에 진행할 수 있으므로, 상당한 공사 기간의 감축 효과를 얻을 수 있게 된다. Subsequently, an underground one-story structure 11, such as an underground one-story slab or an underground one-layer girder, corresponding to the underground one, is constructed (FIG. 5). Like the ground layer structure 10, the basement 1 layer structure 11 is extended to the earth wall 1 to form a form in which the earth wall 1 is completely closed with the earth wall 1. As described above, in the present invention, since the first basement structure 11 functions as a supporting function of the retaining wall 1, there is no need to separately install a brace for supporting the retaining wall 1 as in the conventional case. Can reduce the steel consumption. In particular, the layer structure consisting of slabs or girders is a very rigid structure, and this high rigidity underground structure is used to support the retaining walls 1, thereby significantly improving the stability of the retaining walls 1. It becomes possible. That is, the displacement and settlement of the ground around the excavation work can be actively suppressed, and the stability of the excavation work can be significantly improved. In addition, since the construction of the underground structure can proceed simultaneously with the support work of the retaining wall 1, a significant reduction in the construction period can be obtained.

후속하여, 중앙 굴착부(2) 주위의 잔류 토사를 굴착하고(도 6), 바닥면에 콘크리트를 타설하여 바닥 슬래브(12)를 완성한다(도 7). 앞서 설명한 것처럼, 기초구조물(3)은 도면에 도시된 것과 같은 독립기초 이외에 연속기초 형식으로 설치될 수 있는데, 이와 같이 연속기초 형식으로 기초구조물(3)이 시공된 경우, 굴착부의 토사가 노출된 바닥면에만 콘크리트를 타설하여 간단하게 바닥 슬래브(12)를 완성할 수 있다. Subsequently, the residual soil around the central excavation 2 is excavated (FIG. 6), and concrete is poured into the bottom to complete the bottom slab 12 (FIG. 7). As described above, the foundation structure 3 may be installed in the form of a continuous foundation in addition to the independent foundation as shown in the drawing. When the foundation structure 3 is constructed in the form of the continuous foundation, the soil of the excavation part is exposed. By placing concrete only on the bottom surface, it is possible to simply complete the floor slab (12).

이와 같이 바닥 슬래브(12)가 완성된 후에는 흙막이 벽체(1)의 내측면으로는 구조물의 외벽을 시공하고, 기타 마감처리를 하여 전체 지하 구조물을 완성하게 된다. After the bottom slab 12 is completed as described above, the outer wall of the structure is constructed on the inner surface of the retaining wall 1, and other finishes are completed to complete the entire underground structure.

도면에 도시된 실시예에서는 지하 2층까지만 구조물을 시공하는 사례를 예시하였는데, 필요한 경우, 더 많은 지하층을 시공할 수도 있다. 즉, 중앙 굴착부(2) 주위의 잔류 토사를 지하 2층 구조물 축조 높이 정도로 굴착한 후 지하 1층 구조물(11)과 마찬가지로 지하 2층에 해당하는 지하 2층 슬래브 또는 지하 2층 거더 등의 지하 2층 구조물 시공하고, 또다시 중앙 굴착부(2) 주위의 잔류 토사를 굴착하는 작업을 반복하여, 추가적인 지하층을 더 시공할 수도 있는 것이다. In the embodiment shown in the drawings exemplified a case of constructing a structure only up to the basement 2, if necessary, more basement may be constructed. That is, the excavated soil around the central excavation part 2 is excavated at the height of the construction of the underground two-story structure, and then underground, such as the underground two-story slab or the underground two-story girder, which corresponds to the two-story underground, like the underground one-story structure 11. The construction of the two-layer structure, and again repeating the excavation of the remaining soil around the central excavation (2), it is also possible to further build an additional underground layer.

한편, 위와 같은 본 발명의 시공방법은 현장 여건에 따라서, 다음과 같이 변형 실시할 수 있다. 도 8a 내지 도 8c에는 본 발명의 변형 실시예에 포함된 각각의 시공단계가 개략적으로 도시되어 있는데, 도 8a 내지 도 8c에 도시된 시공단계는 도 2에 도시된 중앙 굴착부(2) 굴착 단계 이후의 단계를 변형한 것이다. On the other hand, the construction method of the present invention as described above can be modified as follows, depending on the site conditions. 8A to 8C schematically show each construction step included in the modified embodiment of the present invention. The construction steps shown in FIGS. 8A to 8C are excavation steps of the central excavation unit 2 shown in FIG. 2. The later steps are modified.

지하 구조물의 지하층이 비교적 깊은 경우, 도 3의 단계에서 기초구조물(3) 및 기둥(4)을 시공한 후 지상층 구조물(10)을 시공하는데 애로사항이 있을 수 있다. 즉, 기둥(4)의 높이가 높기 때문에, 지상층 구조물(10)의 시공을 위하여 슬래브 타설용 거푸집 설치 등이 어려울 수 있다. 이러한 경우에는 도 8a 내지 도 8c에 도시된 바와 같은 시공단계를 이용할 수 있다. 즉, 도 8a에 도시된 것처럼, 중앙 굴착부(2)에 기초구조물(3) 및 기둥(4)을 시공한 후, 지하 1층 구조물(11)의 일부를 미리 시공하는 것이다. 이 때, 중앙 굴착부(2) 주변에는 잔류 사면이 존재하므로, 지하 1층 구조물(11)의 주변은 아직 흙막이 벽체(1)와 폐합될 수 없다. If the basement of the underground structure is relatively deep, there may be difficulties in constructing the ground layer structure 10 after the foundation structure 3 and the pillars 4 in the step of FIG. That is, since the height of the column 4 is high, it may be difficult to install the slab casting formwork for the construction of the ground layer structure (10). In this case, a construction step as shown in FIGS. 8A to 8C may be used. That is, as shown in Figure 8a, after the foundation structure (3) and pillars (4) to the central excavation (2), a part of the underground one-story structure 11 is to be constructed in advance. At this time, since there is a residual slope around the central excavation portion 2, the periphery of the basement 1 story structure 11 can not yet be closed with the retaining wall (1).

후속하여, 도 8b에 도시된 것처럼, 지상층 구조물(10)을 시공한다. 상기 일부가 시공된 지하 1층 구조물(11)을 이용하여 지상층 구조물(10) 시공용 동바리, 거푸집 등을 용이하게 설치할 수 있으므로, 기둥(4)의 높이가 높더라도 지상층 구조물(10)을 쉽게 설치할 수 있게 된다. 지상층 구조물(10)이 완성되면 도 8c에 도시된 것처럼 중앙 굴착부(2) 주위의 토사 즉, 최외측 기초구조물(3)과 기둥 주변의 사면토사를 지하 1층 구조물(11)의 시공 가능할 정도로 굴착하고, 일부가 이미 설치되어 있던 지하 1층 구조물(11)의 주변(도 8c에서 점선으로 도시된 부분)을 연속 시공하여 지하 1층 구조물(11)의 주변이 흙막이 벽체(1)와 폐합되도록 함으로써, 지하 1층 구조물(11)이 흙막이 벽체(1)에 작용하는 토압을 지지할 수 있도록 한다. 이후의 시공단계는 앞서 도 5에 도시된 단계 이후의 것과 동일하므로 반복 설명은 생략한다.Subsequently, the ground layer structure 10 is constructed, as shown in FIG. 8B. The ground floor structure 10 can be easily installed by using a part of the construction of the basement 1 floor structure 11, so that the ground layer structure 10 can be easily installed even if the height of the column 4 is high. It becomes possible. When the ground layer structure 10 is completed, the earth and sand around the central excavation 2, that is, the outermost base structure 3 and the sloped soil around the column, can be constructed as shown in FIG. 8C. Excavation and continuous construction of the periphery of the basement 1st floor structure 11 (part shown by dashed line in FIG. 8C), which has already been installed, so that the periphery of the basement 1st floor structure 11 is closed with the retaining wall 1. By doing so, the basement 1 story structure 11 can support the earth pressure acting on the retaining wall 1. Since the subsequent construction steps are the same as those after the steps shown in FIG. 5, repeated descriptions thereof will be omitted.

위와 같은 본 발명의 실시예에 있어서, 지상층 구조물(10)의 시공 이전에 부분적으로 설치되는 지하층 구조물의 예로서 지하 1층 구조물(11)을 예시하였으나, 경우에 따라서는 지하 2층 구조물 또는 그보다 더 지하에 있는 지하층 구조물의 일부를 미리 시공하고 이를 지상층 구조물(10) 시공에 이용하는 것도 가능하다. 즉, 예를 들면, 기둥(4) 설치후 지하 2층 구조물의 일부를 설치한 후, 지상층 구조물(10) 및 지하 1층 구조물(11) 앞서 설명한 방법으로 차례로 시공한 후, 지하 2층 구조물을 완성하는 것도 가능한 것이다. In the embodiment of the present invention as described above, as an example of the basement layer structure that is partially installed before the construction of the ground layer structure 10, the basement 1 layer structure 11 is illustrated, but in some cases, the basement 2 layer structure or more It is also possible to construct a part of the basement structure in the basement in advance and use it for the construction of the ground layer structure (10). That is, for example, after installing a part of the basement 2 stories after the installation of the column 4, the ground floor structure 10 and the basement 1 floor structure (11) after the construction by the method described above in turn, the basement 2 floor structure It is also possible to complete.

한편, 상기한 실시예에서는 굴착부의 양측을 모두 지상층 구조물(10)과 지하층 구조물로 지지하는 것으로 설명하였으나, 굴착부 일측에 대해서만 적용할 수도 있다. 즉, 굴착부 일측의 흙막이 벽체는 앵커 등을 이용하여 지지할 수 있는 경우, 앵커 등으로 지지할 수 없는 굴착부 일측에 대해서만 상기한 본 발명의 시공방법을 적용할 수 있는 것이다. Meanwhile, in the above embodiment, both sides of the excavation portion are described as supporting the ground layer structure 10 and the basement layer structure, but it may be applied only to one side of the excavation portion. That is, when the retaining wall on one side of the excavation part can be supported using an anchor or the like, the above-described construction method of the present invention can be applied only to one side of the excavation part which cannot be supported by the anchor or the like.

구체적으로, 상기한 본 발명의 시공방법에 따라 중앙 굴착부(2)를 형성함에 있어서, 흙막이 벽체(1)의 일측에만 사면이 유지되고 반대편 흙막이 벽체(1)에는 사면 없이 흙막이 벽체(1)가 노출되도록 굴착한다. 이 후, 앞서 설명한 것과 같이 기초구조물(3), 기둥(4) 및 지상층 구조물(10)을 시공한다. 후속하여 흙막이 벽체 (1)의 일측에만 잔류하여 있던 사면토사를 지하층 한 층의 높이 이상으로 굴착하고, 지하층 구조물을 시공한다. 이 후, 흙막이 벽체(1)의 일측에만 남아 있던 나머지 사면토사를 굴착하고 바닥 슬래브를 시공하게 된다. Specifically, in forming the central excavation portion 2 according to the construction method of the present invention, the slope is maintained only on one side of the retaining wall (1) and the retaining wall (1) without the slope on the opposite retaining wall (1) Excavate to expose. Thereafter, as described above, the foundation structure 3, the pillar 4 and the ground layer structure 10 are constructed. Subsequently, the sloped soil remaining only on one side of the retaining wall 1 is excavated above the height of one basement layer, and a basement structure is constructed. Thereafter, the remaining slopes left on only one side of the retaining wall 1 are excavated and the floor slab is constructed.

이와 같이, 본 발명에서는, 일측의 흙막이 벽체를 앵커 등에 의하여 지지하는 경우, 흙막이 벽체의 일측에 대해서만 지하층 시공 순서에 따른 단계적인 사면 굴착이 이루어지도록 할 수 있는 것이다. As described above, in the present invention, when one side of the wall is supported by an anchor or the like, step slope excavation according to the construction procedure of the basement layer can be performed only on one side of the wall.

이상 살펴본 바와 같이, 본 발명의 시공방법에서는 강성이 큰 슬래브 또는 거더로 이루어진 층 구조물을 흙막이 벽체(1) 지지를 위한 지보공에 사용하게 되므로 흙막이 벽체(1)의 안정성을 현저하게 향상시킬 수 있게 되며, 흙막이 벽체(1) 지지용 버팀대 등 별도의 지보공이 필요하지 아니하므로, 지보공 설치에 수반되는 재료비, 설치 및 해체 비용 등의 공사비를 절감할 수 있을 뿐만 아니라 시공기간도 줄일 수 있게 된다. 특히, 흙막이 벽체(1)의 지보공과 함께 지하 구조물의 축조를 동시에 진행할 수 있으므로, 상당한 시공기간의 감축 효과를 얻을 수 있게 된다. As described above, in the construction method of the present invention, since the layer structure made of slab or girder having a large rigidity is used for support for supporting the retaining wall 1, the stability of the retaining wall 1 can be remarkably improved. Since there is no need for a separate support work, such as a support wall for supporting the retaining wall (1), the construction cost such as material costs, installation and dismantling costs associated with installing the support work can be reduced, as well as the construction period. In particular, since the construction of the underground structure can be carried out simultaneously with the support of the retaining wall 1, it is possible to obtain a significant reduction in the construction period.

또한 기초구조물과 기둥 주변의 토사 제거를 위한 굴착 공사를 수행할 때, 작업 공간이 넓고 굴착 토사의 반출을 위한 동선 확보가 용이하므로, 공사의 진행이 빠르고 경제적으로 이루어질 수 있게 된다. In addition, when carrying out excavation work for removing the earth and sand around the foundation structures and pillars, the work space is large and it is easy to secure copper wire for the excavation of excavated earth and sand, and thus the construction can be carried out quickly and economically.

일반적으로 기초 지반이 약한 경우에는, 말뚝 기초를 시공하여야 하는데, 종래의 기술처럼 버팀대를 이용하여 흙막이 벽체의 지보공을 시공하는 경우에는 버팀 대로 인하여 지하 작업 공간에 상당한 제약이 있게 되므로, 말뚝 기초를 선시공하여야 한다. 따라서, 말뚝 기초의 선시공으로 인한 추가적인 비용이 발생하게 되고, 시공 기간도 길어지는 문제가 있다. In general, when the foundation ground is weak, the pile foundation should be constructed. However, when constructing the support wall of the retaining wall using the prop as in the conventional technique, the pile foundation is pre-installed because there is considerable limitation in the underground work space. shall. Therefore, additional cost is generated due to the pre-installation of the pile foundation, there is a problem that the construction period is also long.

그러나, 본 발명에서는, 종래 기술과는 달리 중앙부를 선굴착하기 때문에, 말뚝 기초를 굴착 후 시공할 수 있게 된다. 따라서, 말뚝 기초의 선시공에 따른 추가 비용을 절감할 수 있으며, 시공 기간의 감축은 물론 작업도 용이하게 할 수 있는 장점이 있다. However, in the present invention, unlike the prior art, since the central portion is pre-excavated, the pile foundation can be constructed after excavation. Therefore, it is possible to reduce the additional cost according to the pre-installation of the pile foundation, there is an advantage that can ease the work as well as the reduction of construction period.

또한 본 발명에서는 지하 구조물이 하향으로 축조되고, 이러한 지하 구조물의 각 층의 하중을 이미 축조된 기둥과 기초 구조물에 의하여 지지할 수 있으므로, 종래 기술에서 필요하였던 지반 굴착전 현장타설 말뚝의 선시공이 필요하지 않게 된다. 따라서, 본 발명에서는 종래 기술에 비하여 시공기간을 줄일 수 있으며, 시공비도 현저하게 절감할 수 있게 된다. In addition, in the present invention, the underground structure is constructed downward, and the load of each layer of the underground structure can be supported by the already constructed pillars and the foundation structure, so the construction of the site-placement pile before the ground excavation required in the prior art is necessary. You will not. Therefore, in the present invention, the construction period can be reduced as compared with the prior art, and construction costs can be significantly reduced.

따라서 본 발명에 따른 시공방법은 도심지의 저심도 광폭 굴착 공사 후 지하 구조물을 시공하는 공사에 매우 적합하다. Therefore, the construction method according to the present invention is very suitable for the construction of the underground structure after the low depth wide excavation construction in downtown.

Claims (4)

지반을 터파기하여 지하 구조물을 시공하는 방법으로서, As a method of constructing underground structures by breaking the ground, 굴착 경계면을 따라 흙막이 벽체(1)를 시공하는 단계; Constructing the retaining wall 1 along the excavation interface; 흙막이 벽체(1)로부터 소정 거리 떨어진 위치까지 안식각을 유지한 상태로 사면을 이루도록 중앙을 터파기하여 중앙 굴착부(2)를 형성하는 단계; Forming a central excavation part 2 by digging a center to form a slope while maintaining an angle of repose to a position away from the earth wall 1; 상기 중앙 굴착부(2)의 바닥면에 기초구조물(3) 및 기둥(4)을 시공하는 단계; Constructing the foundation structure (3) and the pillar (4) on the bottom surface of the central excavation (2); 구조물의 지상층에 해당하며 횡방향으로는 그 주변이 흙막이 벽체(1)와 폐합되어 흙막이 벽체(1)를 지지하는 지상층 구조물(10)을 상기 기둥(4)의 상부에 시공하는 단계; Constructing a ground layer structure (10) corresponding to the ground layer of the structure and having a periphery close to the earth wall (1) to support the earth wall (1) at the top of the column (4); 상기 중앙 굴착부(2)의 기초구조물(3)과 기둥(4) 주변에 사면 형태로 남아 있던 사면토사를 지하 1층의 구조물 높이 이상으로 굴착하는 단계; Digging the slopes remaining in the form of slopes around the foundation structure (3) and the pillar (4) of the central drilling portion (2) above the height of the structure of the first basement; 상기 굴착 지반 상부로 지하층에 해당하며 횡방향으로는 그 주변이 흙막이 벽체(1)와 폐합되어 흙막이 벽체(1)를 지지하는 지하층 구조물(11)을, 상기 굴착된 사면토사의 표면 위쪽의 공간에 시공하는 단계;The basement layer 11, which corresponds to the basement layer above the excavated ground and is laterally merged with the retaining wall 1 and supports the retaining wall 1, in the space above the surface of the excavated sloped soil. Construction step; 상기 중앙 굴착부(2) 주위의 잔류 토사를 굴착하는 단계; 및 Excavating residual soil around the central excavation (2); And 굴착된 바닥면에 콘크리트를 타설하여 바닥 슬래브(12)를 시공하는 단계를 포함하여 구성되는 것을 특징으로 하는 지하 구조물 시공방법. Underground construction method comprising the step of constructing the floor slab 12 by pouring concrete to the excavated floor surface. 제1항에 있어서, 중앙 굴착부(2) 주위의 잔류 토사를 굴착하는 단계에 앞서, 중앙 굴착부(2) 주위의 사면토사를 지하 1층 구조물 높이 이상으로 굴착하는 단계와, 그 굴착된 사면토사 표면 위쪽의 공간에 지하층 구조물(11)을 시공하는 단계를 반복하여 추가적인 지하층을 더 시공한 후, 상기 중앙 굴착부(2) 주위의 잔류 토사 굴착 단계 및 바닥 슬래브(12)를 시공하는 단계를 수행하는 것을 특징으로 하는 지하 구조물 시공방법. The method according to claim 1, wherein before the step of digging out the residual soil around the central excavation portion 2, excavating the sloped soil around the central excavation portion 2 above the height of the underground one-story structure, and the excavated slope Repeating the step of constructing the basement layer structure 11 in the space above the surface of the earth and sand to further construct the basement layer, and then the step of constructing the residual soil excavation step and the bottom slab 12 around the central excavation 2 Underground structure construction method characterized in that performed. 지반을 터파기하여 지하 구조물을 시공하는 방법으로서, As a method of constructing underground structures by breaking the ground, 굴착 경계면을 따라 흙막이 벽체(1)를 시공하는 단계; Constructing the retaining wall 1 along the excavation interface; 흙막이 벽체(1)로부터 소정 거리 떨어진 위치까지 안식각을 유지한 상태로 사면을 이루도록 중앙을 터파기하여 중앙 굴착부(2)를 형성하는 단계; Forming a central excavation part 2 by digging a center to form a slope while maintaining an angle of repose to a position away from the earth wall 1; 상기 중앙 굴착부(2)의 바닥면에 기초구조물(3) 및 기둥(4)을 시공하는 단계; Constructing the foundation structure (3) and the pillar (4) on the bottom surface of the central excavation (2); 상기 중앙 굴착부(2) 내의 공간에 지하 1층에 해당하는 지하층 구조물(11)의 일부를 시공하는 단계; Constructing a part of the basement structure 11 corresponding to the basement 1 in the space in the central drilling part 2; 구조물의 지상층에 해당하며 횡방향으로는 그 주변이 흙막이 벽체(1)와 폐합되어 흙막이 벽체(1)를 지지하는 지상층 구조물(10)을 상기 기둥(4)의 상부에 시공하는 단계; Constructing a ground layer structure (10) corresponding to the ground layer of the structure and having a periphery close to the earth wall (1) to support the earth wall (1) at the top of the column (4); 상기 중앙 굴착부(2)의 기초구조물(3)과 기둥(4) 주변에 사면 형태로 남아 있던 사면토사를 지하 1층의 구조물 높이 이상으로 굴착하는 단계; Digging the slopes remaining in the form of slopes around the foundation structure (3) and the pillar (4) of the central drilling portion (2) above the height of the structure of the first basement; 상기 일부만 시공되어 있던 지하층 구조물(11)의 주변이 흙막이 벽체(1)와 폐합되어 흙막이 벽체(1)를 지지하도록 상기 지하층 구조물(11)의 나머지 부분을 시공하는 단계; Constructing the remaining part of the basement layer structure 11 so that the periphery of the basement layer structure 11, which was only partially constructed, is closed with the retaining wall 1 to support the retaining wall 1; 상기 중앙 굴착부(2) 주위의 잔류 토사를 굴착하는 단계; 및 Excavating residual soil around the central excavation (2); And 굴착된 바닥면에 콘크리트를 타설하여 바닥 슬래브(12)를 시공하는 단계를 포함하여 구성되는 것을 특징으로 하는 지하 구조물 시공방법.Underground construction method comprising the step of constructing the floor slab 12 by pouring concrete to the excavated floor surface. 제1항에 있어서, The method of claim 1, 중앙 굴착부(2)를 형성하는 단계에서, 일측의 흙막이 벽체(1) 방향으로만 사면이 유지되도록 하고 반대측 흙막이 벽체(1) 방향으로는 사면을 제거하여 흙막이 벽체(1)가 노출되도록 굴착하여 중앙 굴착부(2)를 형성하는 것을 특징으로 하는 지하 구조물 시공방법. In the step of forming the central excavation part 2, the slope is maintained only in the direction of one side wall (1) and the slope is removed in the direction of the opposite side wall (1) to excavate so that the wall (1) is exposed Underground structure construction method characterized in that to form a central excavation (2).
KR1020050014572A 2005-02-22 2005-02-22 Method for Constructing an Underground Structure Using Up-down Method KR100663108B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020050014572A KR100663108B1 (en) 2005-02-22 2005-02-22 Method for Constructing an Underground Structure Using Up-down Method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020050014572A KR100663108B1 (en) 2005-02-22 2005-02-22 Method for Constructing an Underground Structure Using Up-down Method

Publications (2)

Publication Number Publication Date
KR20060093815A KR20060093815A (en) 2006-08-28
KR100663108B1 true KR100663108B1 (en) 2007-01-02

Family

ID=37601797

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020050014572A KR100663108B1 (en) 2005-02-22 2005-02-22 Method for Constructing an Underground Structure Using Up-down Method

Country Status (1)

Country Link
KR (1) KR100663108B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101025399B1 (en) 2009-01-28 2011-03-30 진성토건 주식회사 Underground Structure and Method for Constructing thereof

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04319121A (en) * 1991-04-16 1992-11-10 Fujita Corp Construction of underground base of building

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH04319121A (en) * 1991-04-16 1992-11-10 Fujita Corp Construction of underground base of building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101025399B1 (en) 2009-01-28 2011-03-30 진성토건 주식회사 Underground Structure and Method for Constructing thereof

Also Published As

Publication number Publication date
KR20060093815A (en) 2006-08-28

Similar Documents

Publication Publication Date Title
KR101960413B1 (en) Structure construction method
KR102522619B1 (en) Upward basement structure demolition method
KR100313720B1 (en) Composite Underground Structure Construction Method
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR101187170B1 (en) Application of under pinning method in remodeling
KR100663109B1 (en) Method for Constructing an Underground Structure Using Up-down Method
KR100376590B1 (en) Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts
CN106988337A (en) Reinforcing method for reducing uneven settlement of strip-shaped shallow foundation house
KR100625115B1 (en) downward reinforced-concrete underground structure using temporary assistant columns
KR100663108B1 (en) Method for Constructing an Underground Structure Using Up-down Method
KR0179708B1 (en) Working method for underground structure of a building
KR20130021949A (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
CN214832749U (en) Novel inner supporting structure for foundation pit
KR100615149B1 (en) A method of construction top-down for the ground fabric construction
JPS62288269A (en) Method for extending underground stair of building
JP2005002671A (en) Underpinning method and viaduct
KR101257905B1 (en) Method for constructing foundation work
KR200219236Y1 (en) A mold assembly for reinforced concrete girders execution
JPH11152762A (en) Structure and its construction method
KR100722198B1 (en) Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same
KR200428941Y1 (en) Strut system of temporary retaining wall
KR100593203B1 (en) a deck supportframe and a construction methed
KR102500013B1 (en) Method for constructing underground structure
KR102113117B1 (en) Structure construction method using guide wall

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee