KR0179708B1 - Working method for underground structure of a building - Google Patents
Working method for underground structure of a building Download PDFInfo
- Publication number
- KR0179708B1 KR0179708B1 KR1019950003376A KR19950003376A KR0179708B1 KR 0179708 B1 KR0179708 B1 KR 0179708B1 KR 1019950003376 A KR1019950003376 A KR 1019950003376A KR 19950003376 A KR19950003376 A KR 19950003376A KR 0179708 B1 KR0179708 B1 KR 0179708B1
- Authority
- KR
- South Korea
- Prior art keywords
- underground
- stratified
- slabs
- slab
- core
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
- E02D29/05—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
- E02D29/055—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
본 발명은 중앙부에 코아개구부를 두고 각 지층슬라브를 역타설하여서 굴토작업을 용이하게 수행할 수 있도록 하면서도, 그 지층슬라브들의 코아개구부를 통하여 코아구조부를 시공할 수 있도록 하여 주는 건축물의 지하구조부 시공방법에 관한 것으로, 본 발명의 기술적 구성은 해당 지하층 축조 구역의 외주변 둘레에 지중연속벽(10)을 설치한 후에 지지기둥(20)들을 세워서 설치하고, 지중 굴토작업을 수행하여서 노출된 지중연속벽(10) 및 지지기둥(20)들이 일체로 연결되도록 지층슬라브(30)들을 설치하여서 지하구조부(100)를 축조하는 것에 있어서, 상기 지층슬라브(30)들을 지표면에 가까운 최상부로부터 지하 기초 바닥에 이르기까지 역타설하여서 설치할 때에, 타설되는 각 지층슬라브(30)들의 중앙부에 상하로 관통되게 뚫어지는 코아개구부(40)가 확보되도록 설치하여서, 해당 지층슬라브(30) 하부에서 굴토작업시 굴토되는 토사를 반출하는 통로로 사용하고, 상기 지층슬라브(30)들을 설치한 후에는 각 지층슬라브들의 코아개구부(40)를 코아구조부(200) 시공을 위한 공간으로 활용할 수 있도록 한 것이다.The present invention allows the construction of core structures through the core openings of the stratum slabs, while easily laying out the stratum slabs with core openings in the center to facilitate the gulting work. Regarding the technical configuration of the present invention, the underground continuous wall 10 is installed around the outer periphery of the underground construction area, and the supporting pillars 20 are installed upright, and the underground continuous wall exposed by performing underground burial work. In constructing the underground structure part 100 by installing the stratified slabs 30 so that the 10 and the support pillars 20 are integrally connected, the stratified slabs 30 extend from the top close to the ground to the basement ground. When installed by reverse casting until, the core opening portion 40 which is drilled to penetrate vertically through the central portion of each stratum slab 30 to be poured is Installed to be seen, used as a passage for carrying out the soil excavated during the excavation work in the bottom of the stratified slab 30, and after installing the stratified slabs 30, the core openings 40 of each stratified slab core structure (200) It is to be used as a space for construction.
Description
제1도는 종래의 지하구조부를 시공한 상태를 예시한 것임1 is a view illustrating a state of construction of a conventional underground structure
제2도는 본 발명의 지하구조부를 예시한 평면도.2 is a plan view illustrating an underground structure of the present invention.
제3도는 본 발명의 지하구조부를 예시한 일측단면도.Figure 3 is a cross-sectional side view illustrating the underground structure of the present invention.
제4도의 (a)(b)(c)(d)는 본 발명의 지하구조부 시공에 따른 단계별 공정을 나타낸 것임.Figure 4 (a) (b) (c) (d) shows the step-by-step process according to the construction of the underground structure of the present invention.
제5도는 본 발명 지층슬라브를 설치하는 일실시예를 나타낸 것임.Figure 5 shows an embodiment of installing the present invention ground slab.
* 도면의 주요부분에 대한 부호의 설명* Explanation of symbols for main parts of the drawings
10 : 지중연속벽 20 : 지지기둥10: underground continuous wall 20: support pillar
20a : 기둥기초 30 : 지층슬라브20a: pillar foundation 30: stratified slab
40 : 코아개구부 59 : 버림콘크리트40: core opening 59: discarded concrete
(산업상 이용분야)(Industrial use)
본 발명은 건축물공사에 수반되는 지하구조부를 시공하기 위한 것으로, 특히 중앙부에 코아개구부를 두고 각 지층슬라브를 역타설하여서 굴토작업을 용이하게 수행할 수 있도록 하면서도, 그 지층슬라브들의 코아개구부를 통하여 코아구조부를 시공할 수 있도록 하여 주는 건축물의 지하구조부 시공방법에 관한 것이다.The present invention is for constructing the underground structure accompanying the building construction, and in particular, the core through the core opening in the center of each slab slabs to facilitate the excavation work, while the core through the core openings of the slabs It relates to the construction method of the underground structure of the building that allows the construction of the structure.
이전에는 건축물의 지하구조부 공사시 개착식 가설토류공법이 주로 채택되어 왔으며, 이와 같은 가설 토류 공법에 의한 지하구조부 구축공사는, 지층의 변형 및 침하로 인한 주변 건축물의 위해가 발생되고, 가설토류벽 설치작업이 완료된 이후에 비로소 본 구조체 공사를 수행하게 되어 공사기간이 연장되는 등의 문제점이 제기되어 왔다.Previously, the installation temporary construction earthwork method has been mainly adopted for the construction of underground structures of buildings, and the construction of underground construction parts by such constructional earthwork methods causes damage to surrounding buildings due to deformation and settlement of the ground layers, and installation of temporary earth walls. After the work was completed, the construction of the structure was carried out until the construction period was extended.
상기한 바와 같은 문제점을 해결하기 위하여 최근에 개발되어 건축물의 지하구조부 공사에 활용되고 있는 탑다운공법은, 토공작업을 수행하기 전에 지하 연속벽과 지지기둥들을 설치하고, 단계별로 굴토작업과 지층슬라브의 설치작업을 반복하면서 역타설하여 지하구조부를 구축하는 한편, 지상에서는 지상구조부를 구축하는 작업을 병행하여서 시공할 수 있기 때문에, 지하층과 지상층 공사가 동시에 진행되어 공기 단축의 효과가 크며, 부지활용의 극대화로 지하층 최대면적의 시공이 가능하며, 지하층 굴착시 발생하는 붕괴사고 등을 방지할 수 있는 등의 장점을 가지는 것으로 알려져 있다.The top-down method, which has been recently developed to solve the problems described above and is used in the construction of underground structures of buildings, installs underground continuous walls and supporting columns before carrying out earthworks, It is possible to construct the underground structure part by repeating the installation work while repeating the installation work, and the construction of the ground structure part on the ground can be performed in parallel. It is known to have the advantage of being able to construct the maximum area of the basement floor by maximization of and to prevent collapse accidents that occur when excavation of the basement floor.
이와 같이 탑다운공법으로서 건축물의 지하구조부를 구축함에 있어서는 제1도에 도시되는 바와 같이, 건축물에 필수적으로 수반되는 엘리베이터 승강통로, 계단실, 화장실 등의 공간을 확보하기 위한 코아구조부(2)를 시공하게 되는 바, 단계별로 역타설되는 각 지층슬라브(1)와 일체로서 연결되도록 수직 코아벽체(2a)를 설치하여서, 그 지층슬라브(1)들의 중앙을 관통하여서 최상부의 지상층까지 코아구조부(2)를 시공할 수 있도록 하였다.As shown in FIG. 1, in constructing the underground structure part of the building as a top-down method, a core structure part 2 for securing a space such as an elevator lift passage, a staircase room, a restroom, which is essential to the building, is constructed. Bar cores 2a are installed so as to be integrally connected with each stratified slab 1, which is back-cast in stages, and the core structure 2 passes through the center of the stratified slabs 1 to the top ground layer. It was possible to construct.
이때, 각 지층슬라브(1)와 일체로서 세워지는 코아벽체(2a)는 상하로 관통되고 좌우로는 막혀져 있어, 지하구조부를 시공하는 동안에 각종의 장비나 물자를 반입하기 위한 공간으로서 활용되기 곤란하기 때문에, 단계별로 역타설되는 지층슬라브(1) 하부에서 진행되는 굴토작업을 수행하기 위한 장비의 반입이나 굴토된 토사를 반출하기 위해서는 각 지층슬라브(1)에 개구부(3)를 별도로 확보하여야 할 필요성이 있었다.At this time, the core wall 2a, which is erected with each stratified slab 1, penetrates up and down and is blocked from side to side, and is difficult to be used as a space for carrying various equipment or materials during construction of the underground structure. Therefore, in order to carry out the excavation of the equipment or carry out the excavated soil to be carried out in the lower part of the stratified slab (1) which is back-poured step by step, it is necessary to secure an opening 3 separately in each stratified slab (1). There was a need.
따라서, 각 지층슬라브(1)를 설치할 때에 개구부(3)를 별도로 형성하여야 하는 번거로움은 물론이고, 지하구조부를 완전히 시공한 후에는 각 지층슬라브(1)에 형성되어 있는 개구부(3)를 봉입하는 작업을 추가적으로 수행하게 되는 부담을 감수하게 되었다.Therefore, as well as the hassle of separately forming the openings 3 when installing each stratified slab 1, the opening 3 formed in each stratified slab is enclosed after the underground structure is completely constructed. It was a burden to carry out additional work.
더욱이, 각 지층슬라브(1)에 형성되는 개구부(3)는 이후의 봉입작업을 감안하여서 가급적 작은 크기로 형성하게 되고, 공간 배치상 각 지층슬라브(1)상의 일측방으로 치우쳐진 위치에 설치되기 때문에, 굴토작업을 위한 장비나 굴토된 토사를 반출하는 작업을 원할하게 수행할 수 없는 등의 문제점을 수반하게 되었다.In addition, the openings 3 formed in each stratified slab 1 are formed to be as small as possible in consideration of the subsequent encapsulation work, and are installed at positions deviated to one side on each stratified slab 1 due to the spatial arrangement. Therefore, it has been accompanied by problems such as the equipment for the excavation work or the work to take out the excavated earth and sand can not be performed smoothly.
한편, 일본국 특개소63-312438호(1988.12.20)에는, 지하구조물의 외주에 지지말뚝겸용의 지중연속벽을 시공함과 더불어 지지기둥을 세운 후에, 제1차 절토작업을 행하여서 절토된 바닥에서 기둥 사이 및 지중연속벽 사이로 승강될 수 있도록 슬라브 및 보거푸집을 조립하고, 지지기둥 상에 거푸집을 PC스트랜드로서 매달은 가대를 설치하며, 거푸집을 지상1층부까지 끌어올려서 기둥 및 기둥과 연속벽과의 사이에 설치하고, 거푸집 상에 1층 바닥 및 보 구조체 콘크리트를 타설한 후, 제2차 굴토작업을 행하여 거푸집들을 가대의 PC스트랜드로서 지하1층의 바닥까지 내려서 설치하고, 그 거푸집상에 콘크리트를 타설하는 작업을 반복하여서 되는 지하구조물의 구축공법이 제안되어 있다.On the other hand, Japanese Patent Laid-Open No. 63-312438 (December 20, 1988) installed a underground continuous wall for supporting piles on the outer periphery of an underground structure, built a supporting column, and then cut it by performing the first cutting work. Assemble slabs and formwork so that they can be elevated from floor to floor and between underground continuous walls, install the mounts as PC strands on formwork columns, and pull the formwork up to the ground level to connect it with the columns and columns. It is installed between the wall, the first floor and the concrete is laid on the formwork, and then the second excavation work is carried out, and the formwork is installed as the PC strand of the mount down to the ground floor of the first floor. A construction method for underground structures, which is to repeat the work of pouring concrete in the roof, has been proposed.
이러한 지하구조물의 구축공법은, 지중에 구축된 지하연속벽 및 지지기둥간에, 바닥 굴토작업 후에 설치되는 슬라브 및 보 거푸집을 가대의 PC스트랜드로서 자유로이 승강시켜서 해당 슬라브 및 보를 타설하게 됨으로써, 각 슬라브 및 보를 타설할 때마다 거푸집을 지지하기 위한 현장지보공을 가설하여야 하는 번잡한 작업공정을 배제시켜서, 슬라브 및 보 설치작업을 능률적으로 수행하여서 공사기간을 단축시켜 주는 장점을 가지는 것이 사실이다.The construction method of such an underground structure is to freely elevate slabs and formwork installed after the bottom excavation work as a PC strand between the underground continuous walls and supporting pillars constructed in the ground, and to cast the slabs and beams, respectively. It is true that it has the advantage of shortening the construction period by efficiently performing the slab and beam installation work by excluding the complicated work process that requires the installation of site support for supporting the formwork whenever the beam is placed.
그러나, 이와 같은 종래의 지하구조물의 구축공법을 수행함에 있어, 단계별로 역타설되는 슬라브 하부에서 굴토작업을 위한 장비의 반입이나 굴토된 토사의 반출을 위한 대책이 구체적으로 제시되어 있지 않은 관계로, 지하구조물 시공에 따른 굴토작업을 원할하게 수행할 수 있는 지의 여부가 불투명한 결과를 초래하게 되었다.However, in carrying out the construction method of the conventional underground structure, the measures for bringing in equipment for excavation or excavation of excavated soil from the slab lowered in stages are not presented in detail. Whether the excavation work can be performed smoothly according to the construction of underground structures has resulted in opaque results.
혹시 굴토작업을 위해서 각 슬라브 상에 별도의 개구부를 형성하는 경우에는, 슬라브 상에 별도의 개구부를 마련하고 이후에 봉입하는 데에 따른 문제점과, 각 층간슬라브에 별도로 형성된 개구부는 장비나 굴토된 토사를 원할하게 반출입시키기 위한 통로로서의 기능이 역부족해서, 지하구조부 시공에 따른 굴토작업 능률이 저하되는 문제점을 감수할 수밖에 없었다.In the case of forming a separate opening on each slab for gulting work, the problem of providing a separate opening on the slab and enclosing it later, and the opening formed separately in each interlayer slab is equipment or excavated earth and sand Due to the insufficient function as a passageway for smoothly carrying in and out of the building, there was no choice but to suffer from the problem that the efficiency of the excavation work due to the construction of the underground structure was reduced.
또한, 일본 특개소63-312439호(1988.12.20)에는, 지하구조물을 건설하려고 하는 위치의 외주에 가설용 지중연속벽을 구축함과 아울러 기둥기초를 설치하여서 그 상부에 철골구조의 기둥을 건설하며, 다음에 지중벽으로 감싼 위치의 굴토작업을 행하고, 철골구조보를 수평방향 종횡으로 기둥에 걸치도록 가설하고, 보와 기둥을 볼트로서 연결한다. 그리고 연속벽의 내측에 연속벽에 연속되게 SRC구조의 내벽을 구축하고, 또한 보 상측에 텍크플레이트를 부설하고, 그 위에 콘크리트를 타설하여 바닥판을 형성하여서 되는 지반구축공법이 제안되어 있다.In addition, Japanese Patent Laid-Open No. 63-312439 (December 20, 1988) constructs a temporary underground continuous wall on the outer periphery of the location where the underground structure is to be constructed, and installs a pillar foundation to construct a steel column on the upper part. Next, the excavation work is carried out at the location of the underground wall, and the steel frame beams are laid horizontally and horizontally across the columns, and the beams and the columns are connected by bolts. Then, a ground construction method has been proposed in which an inner wall of an SRC structure is continuously formed inside a continuous wall, a text plate is laid on the complementary side, and concrete is placed thereon to form a bottom plate.
이러한 지반구축공법에 의하면, 지하에 구축된 지중연속벽 내에 굴토작업을 수행한 후에 기둥에 걸쳐지도록 철골구조보를 연결시켜서 가설하고, 그 철골구조보 상에 부설되는 텍크플레이트를 위에 콘크리트를 타설하여서 바닥판을 형성함으로써, 현장지보공을 조립하여서 설치하는 번잡한 작업공정을 배제하여서 바닥판 설치작업을 능률적으로 수행할 수 있도록 하여서 본체 구조물을 구축하는 데에 따른 공사기간을 단축시켜 주는 장점을 가지는 것이 사실이다.According to the ground construction method, after the excavation work is carried out in the underground continuous wall constructed underground, the steel structure beams are connected to the pillars, and the concrete plates are placed on the steel structure beams. By forming the plate, it is possible to efficiently perform the floor plate installation work by eliminating the complicated work process of assembling and installing the site support, thereby reducing the construction period for constructing the main structure. to be.
그러나, 이와 같은 지반구축공법 역시, 단계별로 역타설되는 슬라브 하부에서 굴토작업을 위한 장비의 반입이나 굴토된 토사의 반출을 위한 대책이 구체적으로 제시되어 있지 않은 관계로, 지하구조물 시공에 따른 굴토작업을 원할하게 수행할 수 있는 지의 여부가 불투명한 결과를 초래하게 되었다.However, such ground structuring method also does not provide specific measures for carrying out equipment for excavation or excavation of excavated soil from the lower slabs that are backcast in stages. Whether it can be done smoothly has opaque results.
혹시 굴토 작업을 위해서 각 슬라브 상에 별도의 개구부를 형성하는 경우에는, 슬라브 상에 별도의 개구부를 마련하고 이후에 봉입하는 데에 따른 문제점과, 각 층간슬라브에 별도로 형성된 개구부는 장비나 굴토된 토사를 원할하게 반출입시키기 위한 통로로서의 기능이 역부족하여서, 지하구조부 시공에 따른 굴토작업 능률이 저하되는 문제점을 감수할 수밖에 없었다.In case of forming a separate opening on each slab for gulting work, the problem of providing a separate opening on the slab and enclosing it later, and the opening formed separately in each interlayer slab is equipment or excavated earth and sand Due to the lack of function as a passage for smoothly carrying in and out, there was no choice but to suffer from the problem that the efficiency of the excavation work due to the construction of the underground structure was reduced.
[발명의 목적][Purpose of invention]
본 발명은 지하연속벽 내에 단계별로 역타설되는 각 지층슬라브 상의 중앙부에 코아개구부가 확보되도록 하여서, 첫째 지하구조부를 시공하는 중에는 코아개구부를 통하여 굴토작업을 능률적으로 수행할 수 있도록 하여 지하구조부 시공에 따른 굴토작업의 여건을 개선시켜 주며, 둘째 지하구조부를 시공한 후에 각 지층슬라브에 확보된 코아개구부를 통하여 코아구조물 공사를 효율적으로 시공할 수 있도록 하여 주는 건축물의 지하구조부 시공방법을 제공하는 데에 있다.The present invention is to ensure the core openings in the central portion on each stratified slab that is back-cast in stages in the underground continuous wall, so that during the construction of the first underground structure, it is possible to efficiently perform the excavation work through the core opening in the underground structure construction To improve the conditions of the excavation work and to provide the construction method of the underground structure of the building that allows the core structure construction to be efficiently carried out through the core opening secured to each stratified slab after the construction of the underground structure. have.
[발명의 기술적 구성][Technical composition of the invention]
본 발명도, 해당 지하층 축조 구역의 외주변 둘레에 지중연속벽(10)을 설치한 후에 지지기둥(20)들을 세워서 설치하고, 지중 굴토작업을 수행하여서 노출된 지중연속벽(10) 및 지지기둥(20)들이 일체로 연결되도록 지층슬라브(30)들을 설치하여서 지하구조부(100)를 축조하는 점에 있어서는 종래의 것과 기술적 개념을 같이 한다.In the present invention, the underground continuous wall 10 is installed around the outer periphery of the basement construction area, and then the supporting pillars 20 are erected and installed, and the underground continuous wall 10 and the supporting pillars are exposed by performing underground excavation. The construction of the underground structure unit 100 by installing the stratified slabs 30 so that the 20 is integrally connected is the same as the conventional concept.
단, 본 발명의 건축물의 지하구조부 시공방법은 제2도 및 제4도에 도시되는 바와 같이, 상기 지층슬라브(30)들을 지표면에 가까운 최상부로부터 지하 기초 바닥에 이르기까지 역타설하여서 설치할 때에, 타설되는 각 지층슬라브(30)들의 중앙부에 상하로 관통되게 뚫어지는 코아개구부(40)가 확보되도록 설치하여서, 해당 지층슬라브(30) 하부에서 굴토작업시 굴토되는 토사를 반출하는 통로로 사용하고, 상기 지층슬라브(30)들을 설치한 후에는 각 지층슬라브들의 코아개구부(40)를 코아구조부(200) 시공을 위한 공간으로 활용할 수 있도록 함을 기술적 구성상의 특징으로 한다.However, in the construction method of the underground structure of the building of the present invention, as shown in FIG. 2 and FIG. 4, when placing the ground slabs 30 from the top close to the ground surface to the basement base floor, Installed to secure the core opening 40 to be penetrated vertically through the central portion of each of the stratum slabs 30 to be used, and used as a passage for carrying out the soil excavated when the excavation work in the bottom stratum slab 30, After installing the stratum slabs 30 is characterized by the technical configuration that can be used as a space for the core structure portion 200 construction of the core opening portion 40 of each stratum slab.
이하, 본 발명의 구체적인 실시예를 각 공정별로 상세히 설명하면 다음과 같다.Hereinafter, specific embodiments of the present invention will be described in detail for each process.
지중연속벽(10)은 제4도의 (a)에 도시되는 바와 같이, 먼저 지하 구조부가 시공될 둘레를 따라 벤토나이트와 시멘트등의 혼합물을 크라우팅하여 지층을 안정화시킨 후에, 그 지층을 일정한 폭으로서 수직으로 지반층까지 굴착하고, 굴착된 지중에 철근 구조체를 삽입하고 미경화콘크리트를 타설하여서 된다.As shown in (a) of FIG. 4, the underground continuous wall 10 first stabilizes the strata by crawling a mixture of bentonite and cement along the perimeter of the underground structure, and then sets the strata as a constant width. It is to excavate to the ground layer vertically, insert the reinforcing structure into the excavated ground and pour the unhardened concrete.
지지기둥(20)들은 제4도의 (b)에 도시되는 바와 같이, 지반층에 설치된 각각의 기둥기초(20a)들의 사이에 말단부가 위치되도록 지지기둥(20)을 강제 삽입시켜서 지중에 수직으로 매설하여서 된다.As shown in (b) of FIG. 4, the support pillars 20 are embedded vertically in the ground by forcibly inserting the support pillars 20 so that the distal ends are positioned between the respective pillar foundations 20a installed in the ground layer. It is done.
상기 기둥기초(20a)들은, 지중연속벽(10)의 내측 주변을 따라 지지기둥(20)들이 설치될 위치에 우물통 작업으로 지반층까지 굴착하여서 철근 구조체를 삽입한 후에 미경화콘크리트를 타설하여서 된다. 이때 상기 기둥기초(20a)들은 복수개를 한조로 하여 설치하되 그 간격은 대략 1m 정도로서 설치되도록 한다.The pillar foundations 20a are excavated to the ground layer by a well operation at the position where the support pillars 20 are to be installed along the inner periphery of the underground continuous wall 10, and then, after the reinforcing structure is inserted, the unreinforced concrete is poured. do. At this time, the pillar foundations 20a are installed in a set of a plurality, so that the interval is installed as about 1m.
지층슬라브(30)는 제4도의 (c),(d)에 도시되는 바와 같이, 선시공된 지중연속벽(10) 내측 주변의 지층을 굴삭장비등으로 굴토작업과 정지작업을 수행하여서 된 평편한 굴토 바닥면에서 거푸집을 가설하고, 그 거푸집 상에 지중연속벽(10)과 지지기둥(20)들을 연결시켜 슬라브 철근을 배근한 후에 상기 지중연속벽(10)과 지지기둥(20)들이 일체가 되도록 설치하여서 된다.As shown in (c) and (d) of FIG. 4, the stratified slab 30 is flat by performing excavation and stop work with the excavating equipment on the inner periphery of the inner continuous underground wall 10. After laying the formwork at the bottom of the pit, and connecting the underground continuous wall 10 and the support pillars 20 on the form of the slab reinforcement, the underground continuous wall 10 and the support pillars 20 are integrated It should be installed as much as possible.
이와 같은 지층슬라브(30)의 설치작업을 반복적으로 수행하면서 지표면에 가까운 지하1층으로부터 단계별로 굴토작업 후에 각 지층슬라브(30)들을 설치하면서 역타설하여서 지하 기초 바닥까지 설치하게 된다.While repeatedly performing the installation work of the ground slab 30 as described above, after the excavation step by step from the basement 1 floor close to the ground surface by installing each stratified slab 30 and installed to the basement basement floor.
그리고, 상기 각 지층슬라브(30)를 설치할 때에, 그 지층슬라브(30) 중앙부에 엘리베이터 승강통로, 계단실, 화장실 등을 위한 전용공간인 코아구조부(200)을 설치할 수 있도록 코아개구부(40)를 남겨두고 미경화콘크리트를 타설하여서 된다.And, when installing each of the stratified slabs 30, the core opening portion 40 is left so that the core structure 200, which is a dedicated space for elevator lift passages, stairs, toilets, etc. can be installed in the center of the stratified slabs 30. Leave unhardened concrete.
이와 같이 각 지층슬라브(30) 중앙부에 상대적으로 넓게 확보된 코아개구부(40)를 통하여 그 지층슬라브(30) 하부의 굴토작업을 수행할 때에 필요한 장비를 반입하게 됨은 물론이고, 반입된 장비로서 굴토된 토사는 다시 지층슬라브(30)의 코아개구부(40)를 통하여 원할하게 반출시킬 수 있게 된다.Thus, through the core opening 40 secured to the central portion of each stratified slab 30, the necessary equipment is required to carry out the excavation work of the lower portion of the stratified slab 30, as well as as the imported equipment. The earth and sand can be smoothly carried out through the core opening 40 of the stratum slab 30 again.
또, 각 지층슬라브(30)들은 일시에 타설되도록 하는 것이 구조적인 강도를 가지도록 하는 데에 바람직하나, 필요에 따라서는 부분적으로 조인트를 두고 블럭화하여서 시공될 수 있음을 밝혀둔다.In addition, each stratified slab 30 is preferable to have a structural strength to be cast at a time, but it can be found that it can be constructed by partially blocking the joint if necessary.
여기에서 제5도에서와 같이, 상기 지층슬라브(30)의 굴토작업시에 약5Cm 정도의 여유 높이 폭을 두고 굴토된 지층 상부면에 버림콘크리트(50)를 타설하여, 상기 버림콘크리트(50)의 상부면에 각각의 지층슬라브(30)가 타설되도록 함이 바람직하다. 그 이유는, 단계별로 역타설되는 지층슬라브(30)를 시공할 때에 굴토된 바닥면을 지지체로 하여 지보공을 가설함이 없이 거푸집을 설치할 수 있도록 하기 위함이다.Here, as shown in FIG. 5, when the ground slab 30 is excavated, the discarded concrete 50 is cast on the upper surface of the ground layer which is excavated with a clearance height of about 5 cm. It is preferable to allow each stratified slab 30 to be poured on its upper surface. The reason for this is to allow the formwork to be installed without placing the groundwork as a support when constructing the ground slab 30 which is backcast in stages.
이와 같이 지층슬라브(30) 설치를 완료하여서 지하구조부(100)를 축조한 후에는 제3도에서와 같이, 지하 기초 바닥으로부터 각 지층슬라브(30)의 코아개구부(40)를 통하여 코아벽체(200a)를 순차적으로 연결 설치하여서 건축물의 최상부까지 코아구조부(200)를 시공하게 된다.In this way, after the installation of the ground slab 30 is completed and the underground structure 100 is constructed, the core wall 200a is opened through the core openings 40 of the respective ground slabs 30 from the basement ground as shown in FIG. ) Will be installed to connect the core structure 200 to the top of the building sequentially.
[발명의 작용 및 효과][Operation and Effects of the Invention]
이와 같은 본 발명의 작용 및 효과를 종합하여 보면, 지하연속벽 내에 단계별로 각 지층슬라브를 역타설할 때에 그 지층슬라브 중앙부에 코아개구부가 확보되도록 설치함으로써, 첫째 각 지층슬라브 중앙부에 상대적으로 넓게 확보된 코아개구부를 통하여 그 지층슬라브 하부의 굴토작업을 수행할 때에 필요한 장비를 원할하게 반입할 수 있는 동시에, 반입된 장비로서 굴토된 토사는 다시 지층슬라브의 코아개구부를 통하여 효율적으로 반출시킬 수 있어, 지하구조부를 시공할 때에 반복적인 굴토작업을 능률적으로 수행할 수 있는 효과를 가지며, 둘째, 지하구조부를 시공한 후에는 각 지층슬라브에 확보된 코아개구부를 통하여 코아부벽체를 연결 설치하는 작업을 통하여 코아구조물을 효율적으로 시공할 수 있는 등의 효과를 가지게 되는 것이다.In view of the above effects and effects of the present invention, the core openings are secured in the middle of the stratified slabs at the time of reverse placing each stratified slab in the underground continuous wall. It is possible to smoothly bring in the equipment necessary for carrying out the excavation work of the lower part of the stratified slab through the core opening, and at the same time, the earth and sand excavated as imported equipment can be efficiently taken out through the core opening of the stratified slab. When constructing underground structures, it has the effect of efficiently performing repetitive excavation work. Second, after constructing underground structures, through the core openings secured in each stratified slab, The core structure can be effectively constructed, and so on.
Claims (1)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019950003376A KR0179708B1 (en) | 1995-02-21 | 1995-02-21 | Working method for underground structure of a building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1019950003376A KR0179708B1 (en) | 1995-02-21 | 1995-02-21 | Working method for underground structure of a building |
Publications (2)
Publication Number | Publication Date |
---|---|
KR960031718A KR960031718A (en) | 1996-09-17 |
KR0179708B1 true KR0179708B1 (en) | 1999-04-01 |
Family
ID=19408548
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1019950003376A KR0179708B1 (en) | 1995-02-21 | 1995-02-21 | Working method for underground structure of a building |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR0179708B1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100376590B1 (en) * | 1999-10-30 | 2003-03-17 | 삼성중공업 주식회사 | Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts |
KR100376589B1 (en) * | 1999-10-30 | 2003-03-26 | 삼성중공업 주식회사 | Underground construction method using permanent reinforced concrete girders as temporary struts |
KR20160023062A (en) * | 2014-08-21 | 2016-03-03 | (주)바로건설기술 | Method and structure to build underground structures using the border structure |
KR101687495B1 (en) * | 2015-10-01 | 2016-12-16 | 박광호 | Partial top-down construction method for building underground structures |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6536181B1 (en) | 1999-01-13 | 2003-03-25 | Won Kee Hong | Composite retaining wall and construction method for underground structure |
KR100313720B1 (en) * | 1999-01-13 | 2001-11-15 | 김징완 | Composite Underground Structure Construction Method |
KR100767952B1 (en) * | 2005-08-26 | 2007-10-17 | 이창남 | Pass way construction method below the existing foundation |
-
1995
- 1995-02-21 KR KR1019950003376A patent/KR0179708B1/en not_active IP Right Cessation
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100376590B1 (en) * | 1999-10-30 | 2003-03-17 | 삼성중공업 주식회사 | Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts |
KR100376589B1 (en) * | 1999-10-30 | 2003-03-26 | 삼성중공업 주식회사 | Underground construction method using permanent reinforced concrete girders as temporary struts |
KR20160023062A (en) * | 2014-08-21 | 2016-03-03 | (주)바로건설기술 | Method and structure to build underground structures using the border structure |
KR101687495B1 (en) * | 2015-10-01 | 2016-12-16 | 박광호 | Partial top-down construction method for building underground structures |
Also Published As
Publication number | Publication date |
---|---|
KR960031718A (en) | 1996-09-17 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JPH08253946A (en) | Reverse placing method for concrete of underground structure under road | |
RU2414563C1 (en) | Method to erect multistory subsurface structure | |
JP3556559B2 (en) | Underground structure construction method | |
KR100767952B1 (en) | Pass way construction method below the existing foundation | |
KR100313720B1 (en) | Composite Underground Structure Construction Method | |
KR0179708B1 (en) | Working method for underground structure of a building | |
RU2220258C1 (en) | Process of erection of multilevel underground structure ( variants ) | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
KR100673475B1 (en) | A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof | |
JP3390081B2 (en) | How to build an underground parking | |
JPH0684690B2 (en) | Building basement extension method | |
KR100615149B1 (en) | A method of construction top-down for the ground fabric construction | |
KR100663109B1 (en) | Method for Constructing an Underground Structure Using Up-down Method | |
JP3057466B2 (en) | How to build underground structures | |
KR100722198B1 (en) | Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same | |
JPH11152762A (en) | Structure and its construction method | |
JP4267175B2 (en) | Construction method of underground structure | |
JPH10299003A (en) | Foundation work using precast concrete member | |
KR20040012290A (en) | shoring structure using prestressed retaining wall and building construction method using the same | |
KR100663108B1 (en) | Method for Constructing an Underground Structure Using Up-down Method | |
KR101026112B1 (en) | The construction method of underground structure using mega-structure | |
JPH08291526A (en) | Construction method for underground structure | |
Marchand | A DEEP BASEMENT IN ALDERSGATE STREET, LONDON. PART 2: CONSTRUCTION. | |
JP2838019B2 (en) | Caisson blade framing method | |
KR100623005B1 (en) | Underground outer wall construction method using temporary retaining wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20081103 Year of fee payment: 11 |
|
LAPS | Lapse due to unpaid annual fee |