KR100767952B1 - Pass way construction method below the existing foundation - Google Patents
Pass way construction method below the existing foundation Download PDFInfo
- Publication number
- KR100767952B1 KR100767952B1 KR1020050078780A KR20050078780A KR100767952B1 KR 100767952 B1 KR100767952 B1 KR 100767952B1 KR 1020050078780 A KR1020050078780 A KR 1020050078780A KR 20050078780 A KR20050078780 A KR 20050078780A KR 100767952 B1 KR100767952 B1 KR 100767952B1
- Authority
- KR
- South Korea
- Prior art keywords
- existing
- foundation
- pile
- piles
- underground
- Prior art date
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
- E02D2300/0034—Steel; Iron in wire form
Landscapes
- Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Foundations (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
노후 아파트를 리모델링 할 경우 기존 아파트의 계단이나 승강기를 신설 지하 주차장 바닥까지 내리고 주차장과 연결하는 통로를 조성하는 것이 본 발명의 목적이다. 신설 지하 주차장의 위치가 기존 아파트 승강기의 반대편에 있을 때도 기존 기초 밑에 연결통로를 추가할 수 있다.In the case of remodeling an old apartment, it is an object of the present invention to create a passage connecting the parking lot and lowering the stairs or the lift of the existing apartment to the floor of the new underground parking lot. Connection passages can be added under existing foundations when the location of the new underground car park is on the opposite side of an existing apartment lift.
10층 이상의 기존 아파트 건물 하부를 본격 굴토하여 통로, 계단실 또는 승강기를 설치하는 예는 드문 일이며 대부분의 아파트는 벽과 벽 사이가 좁아 기초가 차지하는 범위를 피하여 지하 통로를 배치하는 것은 어려운 일이다. 따라서 기존 기초 밑에 승강기, 계단, 통로 등 공간을 조성할 때 기초 손상 범위를 최소한으로 줄이고 공사 기간과 공사비를 줄이는 공법을 찾는 것이 기술적 과제이다.It is rare to install an aisle, staircase or elevator by digging down the bottom of an existing apartment building with more than 10 stories, and most apartments have a narrow space between walls, so it is difficult to place underground passageways away from the foundation. Therefore, when creating spaces such as elevators, stairs, and passages under existing foundations, it is a technical challenge to find a construction method that minimizes damage to foundations and reduces construction period and cost.
도 1과 6에서 좌우 기둥 또는 벽체 사이에 승강기, 계단 또는 지하통로를 조성할 때 공사 중 일시적으로만 굴토하는 부분의 지내력 또는 말뚝 지지력이 소멸되도록 한다. 아래는 단계별 시공 순서이다.In Figures 1 and 6 when creating a lift, stairway or underground passage between the left and right pillars or walls to ensure that the endurance or pile bearing capacity of the part that only temporarily excavates during construction. Below is the order of construction step by step.
1. 굴토로 인하여 저감되는 내력만큼 추가말뚝(마이크로파일)을 박아 공사 중 기둥 축력을 지지시킨다.1.Put additional piles (micro piles) as much as the reduced strength due to excavation to support column axial force during construction.
2. 도 3, 4 및 도 7, 8은 굴토로 인하여 야기되는 편심 불균형 응력에 대비한 연결보이고 도 8은 구멍을 뚫어 언본디드 강선을 배열하고 유압잭으로 긴장 정착하여 벽체로 분리된 연결보를 일체화시키는 그림이다. 도 9는 기존기초 사이에 콘크리트를 채워 연결보로 삼고 기존기초 외곽면에 ㄷ형강을 세워서 그 사이에 배열한 언본디드 강선을 유압잭으로 긴장 정착하며 기존 기초 상단에 여유 공간이 없을 때 사용한다.2. FIGS. 3, 4 and 7 and 8 are connection beams prepared for eccentric unbalanced stress caused by gulting, and FIG. 8 is a hole for arranging unbonded steel wires and tension-fixing with a hydraulic jack to integrate the connection beams separated by a wall. Picture. 9 is used to fill the concrete between the existing foundation as a connecting beam and to establish a c-beam on the outer surface of the existing foundation to tension the unbonded steel wires arranged therebetween with a hydraulic jack and there is no free space on the top of the existing foundation.
3. 추가말뚝과 지하통로벽 주변에 시멘트 물을 주입하여 굴착작업 시 말뚝의 횡좌굴을 방지하며 직접기초일 때는 지내력 감소를 방지하거나 강화시킨다.3. Cement water is injected around additional piles and underground passage walls to prevent lateral buckling of piles during excavation work and to prevent or reinforce bearing capacity in direct foundations.
4. 지하통로 굴토공사를 진행하는 과정에서 추가말뚝이 횡좌굴에 안전한 깊이마다 수평말뚝을 박고 수평띠(강판)로 추가말뚝을 구속한다. 수평말뚝은 최소경 32mm의 고강도 전산볼트 또는 유공강관에 시멘트물을 주입하는 것이며 반대 측 벽을 반력판으로 삼아 유압잭으로 박는다. 말뚝기초일 경우는 굴토 시 말뚝을 자르며 내림기초 하단에서 말뚝 두부를 정리한다.4. In the course of underground tunnel excavation, additional piles shall be put in horizontal piles at safe depths for transverse buckling, and restrained additional piles with horizontal bands (steel plates). Horizontal pile is to inject cement into high-strength computer bolt or perforated steel pipe with a minimum diameter of 32mm. The opposite side wall is used as a reaction plate and driven by hydraulic jack. In the case of pile foundations, the piles are cut at the time of gulting and the pile heads are arranged at the bottom of the foundation.
5. 내림기초와 지하통로벽을 시공한다. 벽두께와 철근 배근량은 구조계산으로 정한다.5. Construct descending foundations and underground passage walls. Wall thickness and reinforcement are determined by structural calculation.
6. 도 10, 11은 기존 아파트 외벽에 인접하여 굴토할 때 기존 기초 일부가 손상되는 것을 보완하는 것이고 공사 절차는 도 1과 6에서 설명한 방법에 준한다.6. Figures 10 and 11 are to compensate for damage to a part of the existing foundation when excavating adjacent to the exterior wall of the existing apartment and the construction procedure is in accordance with the method described in Figures 1 and 6.
위와 같이 기존기초 하부 통로조성 공법을 적용하면 리모델링 아파트도 신축 아파트와 동등한 가치를 갖게 되는 효과가 있다.Applying the existing base lower aisle construction method as described above has the effect that the remodeled apartment has the same value as the new apartment.
Description
기존 건물 기초 밑을 굴착하여 통로를 조성하는 것은 지하철 등 기존 기초보다 깊이가 많이 깊고 암반 등 토질이 양호한 경우에 시도하는 방법이다. 또한 간혹 기존 건물에 근접하여 다른 건물을 신축할 때 기존 건물 기초가 신축하고자 하는 건물 대지를 침범한 것이 확인되어 이를 보강하는 일도 있다. 그러나 2-3층 건물도 아닌 10층 이상의 기존 아파트 건물 하부를 본격 굴토하여 통로, 계단실 또는 승강기를 설치하는 것은 어려운 일이다.Excavation under the existing building foundation is a way to try when the depth is much deeper than the existing foundation such as subway and the soil is good. In addition, when building another building in close proximity to an existing building, it is sometimes confirmed that the foundation of the existing building has invaded the building site to be built. However, it is difficult to install an aisle, staircase, or elevator by digging into the lower part of an existing apartment building of 10 or more floors rather than a 2-3 floor building.
기존 건물의 기둥 간격이 멀어서 기초를 피하면서도 지하 통로를 조성할 수 있다면 별 문제가 되지 않으나, 대부분의 아파트는 벽과 벽 사이가 좁아 기초가 차지하는 면적을 피하여 지하 통로를 배치하는 것은 어려운 일이다.It is not a problem if the existing building has a long distance between the pillars and can create an underground passage while avoiding the foundation. However, most apartments have a narrow space between the walls, so it is difficult to arrange the underground passage to avoid the area occupied by the foundation.
기존 기초 밑에 승강기, 계단 또는 통로를 조성하기 위해서 필수적인 기초 손상 범위를 최소한으로 줄이고 공사 기간과 공사비도 큰 부담이 되지 않는 공법을 찾는 것이 기술적 과제이다.It is a technical challenge to find a construction method that minimizes the extent of foundation damage necessary to create an elevator, stairway or passageway under an existing foundation, and does not burden the construction period and cost.
도 1과 6에서 좌우에 위치한 기둥(2)이나 기존벽체(13)가 마주보는 면 이내가 조성하고자 하는 지하통로 폭일 경우 그 내부의 기초 부분을 지지하는 지지력 또는 말뚝은 그 부분을 파서 제거하는 굴토공사 중에는 일시적으로 지지력이 소멸된다. 그러나 굴토 공사가 완료되어 내림기초와 지하통로벽을 시공하여 양생이 끝나면 내림기초 하부의 지반 또는 기존말뚝이 원 상태의 지지력으로 복원된다. 이를 위해 시공 단계별로 설명한다.In Figures 1 and 6, if the column 2 or the existing walls 13 located on the left and right sides are within the width of the underground passage to be constructed, the supporting force or pile supporting the foundation part of the interior is dug to remove the part. During earthwork, bearing capacity is temporarily lost. However, after the completion of the excavation work, the foundation and the underground passage wall are constructed. After curing, the ground or existing pile under the foundation is restored to its original bearing capacity. For this purpose, the construction step will be explained.
1. 기초 하부에 지하 통로를 조성하면 원래의 기초 내력이 대폭 저감된다. 위 저감된 값이 리모델링을 위하여 칸막이 벽이나 마감재 등을 제거한 상태의 기둥 또는 기존벽체의 축하중에 미치지 못하는 것이 구조계산으로 확인되면 그 모자라는 값만큼의 추가말뚝(6)을 기존기초에 보강한다. 추가말뚝은 소규모 장비로 천공하여 기초 신설이 가능한 마이크로파일이 적합하다. 마이크로 파일을 이용한 기초 보강공사는 기존 리모델링 과정에서도 폭넓게 적용되고 있다.위 추가말뚝은 지하통로를 조성하는 공사 과정에서 기능이 일시 소멸되는 기초 지반이나 기존말뚝(3)을 제외한 나머지와 더불어 공사 중 기둥 축력을 능히 지지할 수 있어야 한다.1. If the underground passage is formed under the foundation, the original foundation strength is greatly reduced. If the reduced value falls short of the celebration of the column or existing wall with the partition wall or the finishing material removed for remodeling, it is confirmed by the structural calculation that the additional pile 6 that is less than that value is reinforced to the existing foundation. Additional piles are suitable for micro piles, which can be drilled into small-scale equipment and newly constructed as foundations. The foundation reinforcement work using micro piles is widely applied in the existing remodeling process.The additional pile is the pillar under construction, with the exception of the foundation ground or the existing pile (3), which temporarily disappears during the construction of the underground passage. It must be able to support axial force.
2. 기존말뚝과 추가말뚝이 지하통로(9) 외부에 편재함으로 인하여 기존 기초에 큰 불균형모멘트가 유발되므로 이를 소멸시킬만한 조치가 필요하다. 도 3, 4 및 도 7, 8은 각각 기둥 기초와 기존벽체의 편심 재하로 인한 불균형 응력에 대비한 연결보이다. 연결보는 기존 구조가 라멘골조일 경우 도 3, 4와 같이 기존 기둥 주변을 연결보(5)로 감싸는데 그 규격과 배근은 불균형 응력에 대응하도록 구조계산으로 정한다. 연결보의 높이가 높지 않을 때는 기둥 표면에 세트앵커를 박아 부착력을 증진시킨다. 기존 구조가 벽식구조의 경우 도 7, 8과 같이 연결보를 기존벽체(13)길이에 따라 연속으로 같은 두께로 조성하는 것인데 위 연결보가 기존벽체(13)로 인하여 완전 분리되므로 기존벽체 표면에 세트앵커를 박는 것만으로는 연결보와 일체화되는 것을 기대하기는 어렵다. 따라서 기존벽체 하단에 도 8과 같이 횡방향으로 구멍을 뚫어 언본디드 강선(12)을 배열하고 연결보 콘크리트가 양생된 후 유압잭으로 긴장 정착하는 방법으로 보강한다.2. As the existing pile and the additional pile are ubiquitous outside the underground passage (9), a large unbalanced moment is caused in the existing foundation, so it is necessary to take measures to extinguish them. 3, 4 and 7, 8 are connection beams for the unbalanced stress caused by the eccentric load of the column foundation and the existing wall, respectively. If the existing beam is a ramen frame, as shown in Figs. 3 and 4, the surrounding beam is wrapped around the existing column with the connecting beam (5). When the height of the connecting beam is not high, the set anchor is fixed on the column surface to increase the adhesion. If the existing structure is a wall structure, as shown in Figure 7, 8 to form a connecting beam in the same thickness continuously according to the length of the existing wall (13), because the connecting beam is completely separated by the existing wall (13) set anchor on the surface of the existing wall It is difficult to expect to be integrated with the connecting beams just by driving them. Therefore, the unbonded steel wire 12 is arranged by drilling a hole in the transverse direction at the bottom of the existing wall as shown in FIG. 8 and reinforcing by a method of tension fixing with a hydraulic jack after the connecting beam concrete is cured.
또한 기존기초 상단에 여유 공간이 없을 경우 연결보는 도 9와 같이 기존기초 외곽면에 ㄷ형강(14)을 언본디드 강선이 배치되도록 기존기초 보다 크게 설치하고 기존기초에 세트앵커 등으로 고정시키며, ㄷ형강 사이 상하에 수평하게 언본디드 강선을 배열한다. 그러므로 언본디드 강선은 기존기초 상부와 하부에 수평으로 배치된 상태이며, 배치된 언본디드 강선을 유압잭으로 긴장한 후 거푸집을 설치하고 콘크리트를 채워 보강한다. 이 경우 기존기초 하부에 횡방향으로 구멍을 뚫어 언본디드 강선을 배열하여야 하므로 말뚝기초에서만 가능하다.In addition, when there is no free space at the top of the existing foundation, the connecting beam is installed larger than the existing foundation so that the unbonded steel wire is placed on the outer surface of the existing foundation as shown in FIG. 9 and fixed with a set anchor in the existing foundation. Arrange unbonded steel wires horizontally above and below the steel sections. Therefore, the unbonded steel wires are horizontally arranged on the upper and lower parts of the existing foundation, and the unbonded steel wires are tensioned with hydraulic jacks, and then formwork is formed and reinforced with concrete. In this case, it is possible only in pile foundations because the unbonded steel wire should be arranged by drilling holes in the transverse direction under the existing foundation.
3. 새로 박은 추가말뚝(6)과 지하통로벽(10)을 시공할 주변에는 땅을 수직으로 파 내려가도 무너지지 않도록 시멘트물(8)을 주입한다. 이는 지하통로를 위한 굴착작업 시에도 말뚝의 횡좌굴을 방지하며 직접기초일 때는 지내력 감소를 방지하거나 강화시키는 역할을 한다.3. Inject the cement (8) so that the new pile (6) and the underground passage wall (10) will be built so that it will not fall even if the ground is vertically dug. This prevents the lateral buckling of piles in the excavation work for underground passages and prevents or strengthens the reduction of bearing capacity in the case of direct foundation.
4. 지하통로 굴토공사를 진행하는 과정에서 추가말뚝이 횡좌굴을 일으키지 않을만한 깊이마다 수평말뚝(7)을 박고 수평띠(11, 강판)로 추가말뚝을 구속한다.4. In the course of the underground passage gulting construction, put the horizontal piles (7) at depths where the additional piles do not cause lateral buckling, and restrain the additional piles with horizontal bands (11, steel plates).
수평말뚝은 위 시멘트물(8) 주입의 정도에 따라 지반이 밀실해진 경우는 마이크로파일에 사용하는 전산볼트(최소경이 32mm)를 사용하고 그렇지 못할 경우는 주변에 구멍을 뚫은 강관 수평말뚝을 박고 강관 내부 공간에 시멘트물을 주입한다. 수평말뚝은 유압잭(별도 특허출원)으로 박으며 반대 측 벽을 반력판으로 활용한다. 기존 기초 지정이 말뚝일 경우는 지하통로 내부의 말뚝을 자르면서 굴토하며 내림기초 하단에서 말뚝 두부정리를 한다.If the ground is tight depending on the level of cement (8) injection, the horizontal pile shall use a computer bolt (minimum diameter of 32mm) used for the micro pile. Cement is injected into the interior space. Horizontal piles are driven by hydraulic jacks (patented separately), and the opposite wall is used as a reaction plate. If the existing foundation designation is a pile, the pile is piled up while cutting the pile inside the underground passage, and the pile tofu is arranged at the bottom of the lower foundation.
5. 내림기초(4)와 지하통로벽(10)을 시공한다. 벽두께와 배근량은 구조계산으로 정한다.5. Construct the down foundation (4) and the underground passage wall (10). The wall thickness and the amount of back muscle are determined by structural calculation.
6. 도 10, 11은 기존 아파트 외벽에 인접하여 굴토할 때 기존 기초 일부가 손상되는 것을 보완하는 것이고 공사 절차는 도 1과 6에서 설명한 방법에 준한다.6. Figures 10 and 11 are to compensate for damage to a part of the existing foundation when excavating adjacent to the exterior wall of the existing apartment and the construction procedure is in accordance with the method described in Figures 1 and 6.
기존 아파트를 철거하지 않고 리모델링 할 경우 가장 큰 장애 요인이 증설하는 지하 주차장과 기존 아파트와의 통로가 계단 또는 경사로로 구성되어야 하는데 본 발명의 기존기초 하부 통로조성 공법을 적용하면 계단과 경사로가 없이 수평 이동이 가능하므로 리모델링 아파트도 신축 아파트와 동등한 가치를 갖게 되는 효과가 있다.When remodeling an existing apartment, the passageway between the underground parking lot and the existing apartment, which is the biggest obstacle factor, should be composed of stairs or ramps. The remodeled apartments have the same value as new apartments because they can be moved.
도 1은 기존기초의 평면도,1 is a plan view of an existing foundation,
도 2는 기존기초의 단면도,2 is a cross-sectional view of an existing foundation,
도 3은 연결보의 평면도,3 is a plan view of the connecting beam,
도 4는 지하통로의 단면도,4 is a cross-sectional view of the underground passage,
도 5는 추가말뚝과 수평말뚝의 배열도,5 is an arrangement of the additional pile and the horizontal pile,
도 6은 기존 연속기초의 평면도,6 is a plan view of a conventional continuous foundation,
도 7은 기존 연속기초 보강 평면도,7 is a conventional continuous foundation reinforcement plan,
도 8과 9는 기존 연속기초 하부 지하통로 단면도.8 and 9 is a cross-sectional view of the existing continuous basement lower underground passage.
도 10과 11은 외벽에 면한 기초 하부 지하통로 단면도이다.10 and 11 are cross-sectional views of the basement underground passage facing the outer wall.
〈도면의 부호에 대한 간단한 설명〉<Brief description of the symbols in the drawings>
1 : 기존기초 2 : 기둥1: Existing Foundation 2: Column
3 : 기존말뚝 4 : 내림기초3: Existing Pile 4: Descending Foundation
5 : 연결보 6 : 추가말뚝5: connection beam 6: additional pile
7 : 수평말뚝 8 : 시멘트물7: horizontal pile 8: cement water
9 : 지하통로 10 : 지하통로벽9: underground passage 10: underground passage wall
11 : 수평띠 12 : 언본디드 강선11: horizontal band 12: unbonded steel wire
13 : 기존벽체 14 : ㄷ형강13: Existing wall 14: C-beam
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020050078780A KR100767952B1 (en) | 2005-08-26 | 2005-08-26 | Pass way construction method below the existing foundation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020050078780A KR100767952B1 (en) | 2005-08-26 | 2005-08-26 | Pass way construction method below the existing foundation |
Publications (2)
Publication Number | Publication Date |
---|---|
KR20070024148A KR20070024148A (en) | 2007-03-02 |
KR100767952B1 true KR100767952B1 (en) | 2007-10-17 |
Family
ID=38098910
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020050078780A KR100767952B1 (en) | 2005-08-26 | 2005-08-26 | Pass way construction method below the existing foundation |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100767952B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101016405B1 (en) | 2010-11-03 | 2011-02-18 | (주)다음기술단 | Structure earthquake-proof reinforcing method |
CN106759473A (en) * | 2016-11-11 | 2017-05-31 | 中国建筑第八工程局有限公司 | The constructing structure and its construction method of underground pipe gallery and road |
Families Citing this family (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100803921B1 (en) * | 2007-11-08 | 2008-02-15 | 쌍용건설 주식회사 | Pit working method forr undergrund floor railroad operation of elevator |
KR100976621B1 (en) * | 2008-06-03 | 2010-08-17 | 주식회사 가인이앤피 | Construction method for basement extention |
KR100976620B1 (en) * | 2008-06-03 | 2010-08-17 | 주식회사 가인이앤피 | Construction method for basement extention |
CN106193104A (en) * | 2016-08-30 | 2016-12-07 | 温州大学 | The underground pipe gallery of soft soil foundation and construction method thereof |
CN107313453A (en) * | 2017-08-09 | 2017-11-03 | 中冶京诚工程技术有限公司 | Comprehensive pipe gallery of soft soil foundation and construction method thereof |
CN112942441B (en) * | 2021-04-28 | 2024-07-09 | 中铁十八局集团有限公司 | Pre-grouting water-stopping construction method for water-rich powder sand stratum |
Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR960031718A (en) * | 1995-02-21 | 1996-09-17 | 최훈 | Underground structure and construction method for top down construction |
-
2005
- 2005-08-26 KR KR1020050078780A patent/KR100767952B1/en not_active IP Right Cessation
Patent Citations (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR960031718A (en) * | 1995-02-21 | 1996-09-17 | 최훈 | Underground structure and construction method for top down construction |
Non-Patent Citations (1)
Title |
---|
공개특허공보 특1996-0031718호 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101016405B1 (en) | 2010-11-03 | 2011-02-18 | (주)다음기술단 | Structure earthquake-proof reinforcing method |
CN106759473A (en) * | 2016-11-11 | 2017-05-31 | 中国建筑第八工程局有限公司 | The constructing structure and its construction method of underground pipe gallery and road |
Also Published As
Publication number | Publication date |
---|---|
KR20070024148A (en) | 2007-03-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100767952B1 (en) | Pass way construction method below the existing foundation | |
KR101014796B1 (en) | Top-down underground construction method using prefabricated concrete column member as temporary bridge column | |
KR101960413B1 (en) | Structure construction method | |
RU2414563C1 (en) | Method to erect multistory subsurface structure | |
JP2012107479A (en) | Method for constructing underground and aboveground structure | |
US7025537B2 (en) | Subterranean structures and methods for constructing subterranean structures | |
KR100313720B1 (en) | Composite Underground Structure Construction Method | |
JP3761323B2 (en) | How to rebuild a building | |
KR101262357B1 (en) | Inclined Earth Retaining Structure Method | |
CN201077988Y (en) | Hidden beam-column type prestressing force earth nail wall | |
KR100698912B1 (en) | Applying method of the PHC pile as the footing with the column of building | |
CN111218938A (en) | Excavation construction method for foundation pit above existing tunnel | |
KR0179708B1 (en) | Working method for underground structure of a building | |
KR100615149B1 (en) | A method of construction top-down for the ground fabric construction | |
CN214143788U (en) | Tower crane foundation on foundation pit slope | |
KR100967496B1 (en) | Device for constructing an underground structure | |
JP4833949B2 (en) | Concrete integrated structure pillar | |
AU2020100004A4 (en) | A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method | |
KR200263526Y1 (en) | Hanging semi down up system | |
KR102181416B1 (en) | method of constructing earthquake-proof ALC house | |
CN112227405A (en) | Tower crane foundation located on foundation pit slope and construction method thereof | |
JP2022060628A (en) | Base-enlarged foundation structure, composite foundation structure of reinforced soil and construction method thereof | |
KR960016755B1 (en) | Working method and working apparatus of underground structure | |
RU2633619C1 (en) | Method of strengthening foundation at reconstruction | |
JP2571426B2 (en) | Construction method of retaining wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
E902 | Notification of reason for refusal | ||
E902 | Notification of reason for refusal | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20121004 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20131001 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20141006 Year of fee payment: 8 |
|
LAPS | Lapse due to unpaid annual fee |