KR101025399B1 - Underground Structure and Method for Constructing thereof - Google Patents

Underground Structure and Method for Constructing thereof Download PDF

Info

Publication number
KR101025399B1
KR101025399B1 KR1020090006535A KR20090006535A KR101025399B1 KR 101025399 B1 KR101025399 B1 KR 101025399B1 KR 1020090006535 A KR1020090006535 A KR 1020090006535A KR 20090006535 A KR20090006535 A KR 20090006535A KR 101025399 B1 KR101025399 B1 KR 101025399B1
Authority
KR
South Korea
Prior art keywords
retaining member
excavation
slab
ground
inclined end
Prior art date
Application number
KR1020090006535A
Other languages
Korean (ko)
Other versions
KR20100087505A (en
Inventor
우혁근
이창훈
Original Assignee
진성토건 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 진성토건 주식회사 filed Critical 진성토건 주식회사
Priority to KR1020090006535A priority Critical patent/KR101025399B1/en
Publication of KR20100087505A publication Critical patent/KR20100087505A/en
Application granted granted Critical
Publication of KR101025399B1 publication Critical patent/KR101025399B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • E04B1/04Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for

Abstract

본 발명은 입체 교차로, 지하보도, 개착식 터널 등과 같이 지중에 설치되는 구조물을 시공함에 있어서, 흙막이 벽체 설치와 상부 슬래브 설치 즉시 슬래브 위쪽의 토사를 되메우기함으로써 차량 통행 등과 같은 지면의 활용을 보장할 수 있으면서도, 지중의 터파기 과정에서 흙막이 벽체 상부의 횡방향 지보공을 생략할 수 있도록 함으로써 시공의 간소화 및 터파기 작업 공간의 확보 용이성 등의 효과를 발휘할 수 있게 되는 새로운 구성의 지중 구조물 및 그 시공방법에 관한 것이다.

본 발명에서는 지반을 굴착하여 상부 굴착부(2)를 형성하는 단계; 상부 굴착부(2) 내에 지중 구조물이 구축될 지하 공간의 확보하도록 간격을 두고 흙막이 부재(10)를 지중에 설치하는 단계; 간격을 두고 설치된 양측 흙막이 부재(10)를 가로질러 배치되는 중앙부(31)와, 상기 중앙부(31)의 양측에 각각 연장되는 경사 단부(32)로 이루어진 상부 슬래브(3)를, 흙막이 부재(10)의 상단부에 경사 단부(32)가 놓이도록, 흙막이 부재(10) 사이에 설치하는 단계; 흙막이 부재(10) 사이에 설치된 상부 슬래브(3) 위로 상부 굴착부(2)를 토사로 되메우기 하는 단계; 상부 슬래브(3) 아래로 흙막이 부재(10) 사이의 지반을 굴착하는 단계; 및 지반 굴착 완료 후 하부 바닥판(4)을 시공하는 단계를 포함하며; 상부 슬래브(3)를 흙막이 부재(10)의 사이에 설치함에 있어서, 상부 슬래브(3)의 경사 단부(32)에 의해 가해지는 축력에 의해 흙막이 부재(10)의 상단부에 외측으로의 수평분력이 작용하도록, 경사 단부(32)의 중심축이 흙막이 부재(10)의 수직축에 대해 경사지게 만나는 형태 로 경사 단부(32)가 상부 굴착부(2)로 노출되어 있는 흙막이 부재(10)의 상부에 놓이도록 하는 것을 특징으로 하는 지중 구조물 시공방법 및 이에 의한 지중 구조물이 제공된다.

Figure R1020090006535

흙막이, 지중, 굴착, 절곡, 상부슬래브, 무지보

The present invention can ensure the utilization of the ground, such as vehicle traffic by refilling the soil on the top of the slab immediately upon installation of the wall and the upper slab in the construction of underground structures such as three-dimensional intersection, underground walkway, open-type tunnel, etc. In addition, it is possible to omit the lateral support hole in the upper part of the wall in the process of excavation of the underground, thereby simplifying the construction and making it easy to secure the excavation work space. It is about.

In the present invention, the step of excavating the ground to form an upper excavation (2); Installing the retaining member 10 in the ground at intervals to secure an underground space in which the underground structure is to be built in the upper excavation portion 2; The upper slab 3 which consists of the center part 31 arrange | positioned across the both retaining members 10 provided at intervals, and the inclined end 32 which respectively extends in the both sides of the said center part 31, the retaining member 10 Step between the earth member (10) so that the inclined end 32 is placed on the upper end of the; Backfilling the upper excavation portion 2 with earth and sand over the upper slab 3 provided between the earth member 10; Excavating the ground between the retaining member (10) below the upper slab (3); And constructing the lower bottom plate 4 after the completion of the ground excavation; In installing the upper slab 3 between the retaining members 10, the horizontal force to the outside of the upper retaining member 10 is increased by the axial force applied by the inclined end 32 of the upper slab 3. In order to act, the inclined end 32 is placed on the top of the retaining member 10 in which the inclined end 32 is exposed to the upper excavation portion 2 such that the central axis of the inclined end 32 meets the inclined angle with respect to the vertical axis of the retaining member 10. There is provided an underground structure construction method and an underground structure thereby.

Figure R1020090006535

Dirt, underground, excavation, bending, upper slab, plain beam

Description

선 되메우기를 이용한 무지보 지중 구조물 및 그 시공방법{Underground Structure and Method for Constructing thereof}Underground Structure and Method for Constructing Technical Information

본 발명은 선(先) 되메우기를 이용한 무지보 지중 구조물 및 그 시공방법에 관한 것으로서, 구체적으로는 입체 교차로, 지하보도, 개착식 터널 등과 같이 지중에 설치되는 구조물을 시공함에 있어서, 흙막이 벽체 설치와 상부 슬래브 설치 즉시 슬래브 위쪽의 토사를 되메우기함으로써 차량 통행 등과 같은 지면의 활용을 보장할 수 있으면서도, 지중의 터파기 과정에서 흙막이 벽체 상부의 횡방향 지보공을 생략할 수 있도록 함으로써 시공의 간소화 및 터파기 작업 공간의 확보 용이성 등의 효과를 발휘할 수 있게 되는 새로운 구성의 지중 구조물 및 그 시공방법에 관한 것이다. The present invention relates to an unsupported underground structure using pre-filling and a construction method thereof. Specifically, in constructing a structure installed in the ground such as a three-dimensional intersection, an underground walkway, an open tunnel, and the like, By refilling the soil of the upper part of the slab immediately after installation of the upper slab, it is possible to guarantee the utilization of the ground such as vehicle traffic, while also simplifying the construction and digging work by eliminating the transverse support of the upper wall of the earth wall during the excavation of the ground. The present invention relates to an underground structure having a new structure and an construction method thereof, which can exert an effect such as ease of securing space.

입체 교차로, 지하보도, 개착식 터널 등과 같은 지중 구조물을 시공함에 있어서, 종래에는 흙막이 부재를 설치한 후, 흙막이 부재 사이의 공간을 굴착해가면서 흙막이 부재 사이에 버팀보 등의 지보공을 수행하였다. 즉, 흙막이 부재 사이의 공간을 굴착하게 되면 흙막이 부재 배면의 토압이 작용하므로, 흙막이 부재 사 이의 간격을 유지하기 위해서는 흙막이 부재 상부에서부터 소정 간격으로 버팀보 등을 흙막이 부재 사이에 설치할 수밖에 없었던 것이다. In constructing underground structures such as a three-dimensional intersection, an underground walkway, an open-type tunnel, and the like, conventionally, after installing the earthquake member, excavation of the space between the earthquake members was carried out, such as a support beam between the earthquake members. In other words, when excavating the space between the retaining members, the earth pressure on the back of the retaining member acts, so in order to maintain the gap between the retaining member had to install a brace between the retaining member at a predetermined interval between the retaining member.

이와 같이 지보공을 수행하게 되면, 지보공 수행을 위한 비용과 시간이 더 소요되는 것은 물론이고 지보공에 의해 설치된 버팀보가 흙막이 부재 사이의 지반 굴착에 장애 요소가 되었다. 흙막이 부재 사이의 공간에 굴삭기 등의 굴착 장비를 투입하였을 때, 굴착 장비 위쪽으로 버팀보가 존재하게 되므로, 굴착 장비의 운용이나 작업자들의 작업에 큰 장애가 되었던 것이다. In this way, if the support is carried out, the cost and time for performing the support is also increased, as well as the support installed by the support has become an obstacle to the excavation of the ground between the earth members. When the excavation equipment such as an excavator is put in the space between the earthquake members, since there is a brace above the excavating equipment, the operation of the excavating equipment or the work of workers was a great obstacle.

또한 흙막이 부재사이의 굴착과 별도로 상부에는 임시적인 구조물인 복공판 등을 설치하였으나, 지중 구조물의 설치가 완료된 후에는 복공판을 제거한 후 다시 토사 되메움을 하여야 하므로 그만큼 시공이 번거롭고, 공기 증가 및 비용 소요의 원인이 되어 왔다. In addition to the excavation between the earthquake members, a temporary hollow plate, etc., was installed on the upper part, but after the installation of the underground structure was completed, it was necessary to remove the hollow plate and backfill the soil again. It has been the cause.

본 발명은 이와 같이 종래 기술이 가지는 한계 및 문제점을 극복하기 위하여 개발된 것으로서, 흙막이 부재 사이의 지반을 굴착함에 있어서, 흙막이 부재 상부에 버팀보 설치 등의 별도 지보공을 수행하지 아니하도록 함으로써, 시공의 간소화를 이룰 수 있도록 하는 것을 목적으로 한다. The present invention was developed in order to overcome the limitations and problems of the prior art as described above, in the excavation of the ground between the retaining member, by simplifying the construction by not performing a separate support, such as installing a support on the upper retaining member The aim is to be able to achieve.

또한 본 발명은 지하 굴착시에도 지반 상면에 차량 등의 통행이 가능하도록 함으로써, 시공에 따른 차량 통행금지 등의 불편함을 최소화하고, 공기 절감 및 공사비 절감 효과를 얻을 수 있도록 하는 것을 목적으로 한다. In addition, an object of the present invention is to enable the passage of vehicles, such as vehicles on the ground surface even when underground excavation, to minimize the inconvenience, such as prohibition of vehicle traffic due to construction, and to achieve the effect of saving air and reducing construction costs.

본 발명에서는 위와 같은 목적을 달성하기 위하여, 지반의 상부 굴착부 내에 지중 구조물이 구축될 지하 공간의 확보하도록 간격을 두고 지중에 설치된 흙막이 부재와; 간격을 두고 설치된 양측 흙막이 부재를 가로질러 배치되는 중앙부와, 상기 중앙부의 양측에 각각 연장되는 경사 단부로 이루어져, 흙막이 부재의 상단부에 경사 단부가 놓여, 흙막이 부재 사이에 설치되는 상부 슬래브로 이루어지되; 상부 슬래브의 경사 단부에 의해 가해지는 축력에 의해 흙막이 부재의 상단부에 외측으로의 수평분력이 작용하도록 경사 단부는, 그 중심축이 흙막이 부재의 수직축에 대해 경사지게 만나는 형태로, 상부 굴착부에 노출되어 있는 흙막이 부재의 상부에 놓이게 되며; 상부 슬래브가 흙막이 부재 사이에 설치된 상태에서 상부 슬래브 위로 상부 굴착부 내에 토사에 의한 되메우기가 이루어진 구조를 가지는 것을 특징으 로 하는 지중 구조물이 제공된다. In the present invention, in order to achieve the above object, the earth block member installed in the ground at intervals to secure the underground space in which the underground structure is to be built in the upper excavation of the ground; Comprising a center portion disposed across both of the earth retaining members provided at intervals, and inclined ends extending to both sides of the center portion, the inclined end is placed on the upper end of the earth retaining member, consisting of an upper slab installed between the earth retaining members; The inclined end is exposed to the upper rig in such a manner that its central axis meets inclined with respect to the vertical axis of the retaining member so that the horizontal force on the upper end of the retaining member is applied by the axial force applied by the inclined end of the upper slab. A retaining soil block is placed on top of the member; There is provided an underground structure, characterized in that the upper slab has a structure made of backfilling by soil in the upper excavation portion over the upper slab in the state installed between the earth member.

또한 본 발명에서는 위와 같은 목적을 달성하기 위하여, 지반을 굴착하여 상부 굴착부를 형성하는 단계; 상부 굴착부 내에 지중 구조물이 구축될 지하 공간의 확보하도록 간격을 두고 흙막이 부재를 지중에 설치하는 단계; 간격을 두고 설치된 양측 흙막이 부재를 가로질러 배치되는 중앙부와, 상기 중앙부의 양측에 각각 연장되는 경사 단부로 이루어진 상부 슬래브를, 흙막이 부재의 상단부에 경사 단부가 놓이도록, 흙막이 부재 사이에 설치하는 단계; 흙막이 부재 사이에 설치된 상부 슬래브 위로 상부 굴착부를 토사로 되메우기 하는 단계; 상부 슬래브 아래로 흙막이 부재 사이의 지반을 굴착하는 단계; 및 지반 굴착 완료 후 하부 바닥판을 시공하는 단계를 포함하며; 상부 슬래브를 흙막이 부재의 사이에 설치함에 있어서, 상부 슬래브의 경사 단부에 의해 가해지는 축력에 의해 흙막이 부재의 상단부에 외측으로의 수평분력이 작용하도록, 경사 단부의 중심축이 흙막이 부재의 수직축에 대해 경사지게 만나는 형태로 경사 단부가 상부 굴착부로 노출되어 있는 흙막이 부재의 상부에 놓이도록 하는 것을 특징으로 하는 지중 구조물 시공방법이 제공된다. In addition, the present invention to achieve the above object, the step of excavating the ground to form an upper excavation; Installing an earthquake member in the ground at intervals to secure an underground space in which the underground structure is to be built in the upper excavation portion; Installing an upper slab comprising a center portion disposed across both of the earth retaining members spaced apart from each other, and an inclined end extending on both sides of the center portion, such that the inclined end portion is placed on the upper end of the earth retaining member; Backfilling the upper excavation with earth and sand over the upper slab provided between the mud members; Excavating the ground between the retaining members below the upper slab; And constructing a bottom plate after completion of the ground excavation; In the installation of the upper slab between the retaining members, the central axis of the inclined end is directed to the vertical axis of the retaining member so that the horizontal component acts outwardly on the upper end of the retaining member by the axial force applied by the inclined end of the upper slab. There is provided a method for constructing underground structures, characterized in that the inclined end is placed on the upper portion of the earth film member exposed to the upper excavation in an oblique manner.

위와 같은 본 발명의 시공방법에서, 상부 슬래브는 프리캐스트 콘크리트 부재로 제작되고, 인양장치에 의해 인양되어 흙막이 부재 사이에 거치될 수도 있다. In the construction method of the present invention as described above, the upper slab is made of precast concrete member, may be lifted by the lifting device may be mounted between the earth member.

본 발명에 따르면, 되메우기 토사 하중이 상부 슬래브의 경사 단부를 거쳐 흙막이 부재의 상단부에 외측 수평방향으로의 능동적인 외력으로 작용하기 때문에, 별도의 버팀보 설치와 같은 지보공 없이도 흙막이 부재 사이의 간격을 유지할 수 있게 되며, 그에 따라 흙막이 부재 상부에 대한 별도의 지보공을 수행하지 않는 무지보공의 상태로도 흙막이 부재 사이의 간격을 유지한 채로 지반의 굴착을 수행할 수 있게 된다. According to the present invention, since the backfill soil load acts as an active external force in the outer horizontal direction at the upper end of the retaining member via the inclined end of the upper slab, it is possible to maintain the gap between the retaining members without the support such as installing a separate brace. As a result, the excavation of the ground can be performed while maintaining the gap between the retaining members even in the state of the non-supporting hole without performing a separate support for the upper part of the retaining member.

따라서 버팀보 설치와 같은 지보공 수행에 소요되는 비용 및 공기 등을 절감할 수 있게 된다. 또한 버팀보와 같은 장애물이 없으므로 지반 굴착을 위한 장비 운행이나 굴착 작업이 용이하게 이루어질 수 있게 된다. Therefore, it is possible to reduce the cost and air required to perform the geotechnical, such as the installation of the brace. In addition, since there are no obstacles such as braces, it is possible to easily operate equipment for excavation or excavation work.

특히, 지반의 굴착이 완료되지 않은 상태에서도 상부 슬래브를 설치한 후 그 상부 공간을 되메우기하게 되므로, 지반 굴착 작업과 무관하게 상부에서 차량 통행 등이 이루어질 수 있게 되어, 지반 굴착 공사로 인한 차량 통행 제한이나 기타 상부 공간의 통행 제한 등의 불편함을 최소화할 수 있게 되는 효과가 있다. 상부 슬래브 위의 되메우기 부분은 시공이 완료된 상태이므로, 되메우기 부분을 다시 굴착하는 등의 추가 작업이 필요 없게 되어 그만큼 시공이 간소화되는 효과도 발휘된다. Particularly, after the upper slab is installed even when the excavation of the ground is not completed, the upper space is refilled, so that vehicle traffic can be made from the upper portion regardless of the ground excavation work, and vehicle traffic restriction due to the ground excavation work is restricted. However, there is an effect to minimize the inconvenience, such as restriction of the passage of the upper space. Since the backfill portion on the upper slab is completed, no additional work such as digging the backfill portion is required and the construction is simplified accordingly.

이하, 첨부도면을 참조하면서 본 발명의 바람직한 실시예를 구체적으로 설명한다. Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1 내지 도 7에는 본 발명에 따른 지중 구조물을 시공하는 각 단계를 보여주는 개략적인 단면도가 도시되어 있다. 도면에서는 지중 구조물의 일예로서 지하 차량 통행로를 예시하였으나, 본 발명의 지중 구조물은 이에 한정되지 아니한다. 1 to 7 are schematic cross-sectional views showing each step of constructing the underground structure according to the present invention. Although the drawings illustrate an underground vehicle passage as an example of the underground structure, the underground structure of the present invention is not limited thereto.

우선 도 1에 도시된 것처럼, 지중 구조물을 시공할 지반의 상면을 소정 깊이로 굴착하고 지중 구조물이 구축될 지하 공간의 확보하도록 지중 구조물의 간격에 대응하여 흙막이 부재(10)를 지중에 설치한다. 상기 흙막이 부재(10)는 말뚝을 이용한 흙막이 벽체이거나 또는 강널말뚝 등일 수 있으며, 이에 대한 특별한 제한은 없다. 상기 흙막이 부재(10)를 지중에 설치함에 있어서, 도면에 도시된 것처럼, 상기 흙막이 부재(10)의 상단부는 상부 굴착부(2)에 노출되어 있도록 한다. 상기 흙막이 부재(10)의 상단부에는 도 2에 도시된 것처럼 상부 슬래브(3)의 설치를 위한 슬래브 설치부(11)가 일체로 형성된다. 상기 슬래브 설치부(11)는 콘크리트를 이용하여 제작될 수 있다. First, as shown in Figure 1, excavating the upper surface of the ground to be constructed underground structure to a predetermined depth and to install the earthquake member 10 in the ground corresponding to the interval of the underground structure to secure the underground space in which the underground structure will be built. The earth blocking member 10 may be an earth wall using a pile or a steel sheet pile, and the like, and there is no particular limitation thereto. In installing the retaining member 10 in the ground, as shown in the figure, the upper end of the retaining member 10 is to be exposed to the upper excavation (2). As shown in FIG. 2, the slab installation unit 11 for installing the upper slab 3 is integrally formed at the upper end of the earth blocking member 10. The slab installation unit 11 may be manufactured using concrete.

후속하여 상기 양측 흙막이 부재(10)의 상단부에 형성된 슬래브 설치부(11)에 걸쳐서 상부 슬래브(3)가 형성된다. 상기 상부 슬래브(3)는, 현장 타설 콘크리트에 의해 제작될 수도 있으나, 프리캐스트 콘크리트 부재로 제작되어 도 3에 도시된 것처럼 크레인 등의 인양장비(100)에 의해 상기 슬래브 설치부(11) 위에 상부 슬래브(3)의 양단부가 놓임으로써 상기 흙막이 부재(10) 사이의 공간을 덮도록 설치될 수도 있다. Subsequently, the upper slab 3 is formed over the slab installation portion 11 formed at the upper end portions of the both retaining members 10. The upper slab 3 may be manufactured by cast-in-place concrete, but is made of precast concrete member and upper part on the slab installation part 11 by lifting equipment 100 such as a crane as shown in FIG. 3. Both ends of the slab 3 may be placed so as to cover the space between the earth member 10.

여기서 본 발명에 따른 상부 슬래브(3)는 다음과 같은 구성을 갖는다. 구체적으로, 도 3에 도시된 것처럼 상부 슬래브(3)는 양쪽 경사 단부(32)의 중심축이 각각 상기 슬래브 설치부(11)의 수직축에 경사지게 만나게 된다. 구체적으로 상부 슬래브(3)는 간격을 두고 설치된 양측 흙막이 부재(10)를 가로질러 배치되는 중앙부(31)와, 상기 중앙부(31)의 양측에 각각 연장되는 경사 단부(32)로 이루어지는 데, 상기 경사 단부(32)의 중심축이 상기 흙막이 부재(10)의 수직축에 대해 경사지게 만나도록 상기 경사 단부(32)는 상기 흙막이 부재(10)의 상부에 놓이게 되는 것이다. 도면에 도시된 실시예에서는 상기 흙막이 부재(10)의 상부에 설치된 슬래브 설치부(11)와 상기 경사 단부(32)가 만나는 면은 경사지게 되어 있고 단턱이 형성되어 있다. 도면에 도시된 실시예에서는 상기 중앙부(31)와 상기 경사 단부(32)가 이어지는 부분이 각도를 가지고 절곡된 것으로 도시되어 있으나, 반드시 절곡될 필요는 없으며, 곡선 형태로 상기 중앙부(31)와 상기 경사 단부(32)가 완만하게 이어져도 무방하다. 또한 상부 슬래브(3) 단부의 부재 축이 흙막이 부재(10)의 상부의 부재 수직축과 경사지게 만날 수 있다면, 상기 상부 슬래브(3)의 상기 중앙부(31)는 직선 이외에도 곡선으로 형성되어도 무방하다. 따라서 본 명세서에 있어서 상기 경사 단부(32)는 이와 같이 중앙부(31)로부터 완만하게 경사지는 단부와 절곡 각을 가지고 절곡되는 단부를 모두 포함하는 의미로 해석되어야 한다. Here, the upper slab 3 according to the present invention has the following configuration. Specifically, as shown in Figure 3, the upper slab (3) so that the central axis of both inclined end 32 is inclined to the vertical axis of the slab installation portion 11, respectively. Specifically, the upper slab (3) is composed of a central portion 31 disposed across the two retaining members 10 provided at intervals, and inclined ends 32 respectively extending to both sides of the central portion 31, The inclined end 32 is placed on the top of the retaining member 10 so that the central axis of the inclined end 32 meets the inclined relative to the vertical axis of the retaining member 10. In the embodiment shown in the drawing, the surface where the slab installation portion 11 and the inclined end portion 32 installed on the top of the earth member 10 is inclined and the step is formed. In the embodiment shown in the figure is shown that the portion connecting the central portion 31 and the inclined end 32 is bent at an angle, but need not necessarily be bent, the center portion 31 and the The inclined end 32 may continue smoothly. In addition, as long as the member axis of the upper slab 3 end can incline with the member vertical axis of the upper part of the earth block member 10, the center part 31 of the upper slab 3 may be formed in a curve other than a straight line. Therefore, in the present specification, the inclined end 32 should be interpreted to include both the end that is gently inclined from the central portion 31 and the end that is bent at a bending angle.

후속해서 도 4에 도시된 것처럼, 상기 상부 슬래브(3) 위의 상부 굴착부(2)를 되메우기 한다. 즉, 흙막이 부재(10) 사이의 지반을 터파기에 앞서 상부 슬래브(3) 위의 공간을 선(先) 되메우기하는 것이다. 이와 같이 상부 슬래브(3) 위로 토사가 되메우기 되면, 토사에 의한 하중에 의해 상부 슬래브(3)의 경사 단부(32)에는 그 중심축 방향으로 압축력이 작용한다. 이 압축력은 결국 흙막이 부재(10)의 상단부(도면에 도시된 실시예에서는 슬래브 설치부)에 경사지게 가해진다. 도 5에는 되메우기가 이루어진 상태에서 흙막이 부재(10)의 상단부에 작용하는 힘의 상태를 보여주는 개략도가 도시되어 있는데, 도면에 도시된 것처럼 흙막이 부 재(10)의 상단부에는 상부 슬래브(3)의 경사 단부(32)로부터 경사진 방향의 축력(F)이 작용하고, 이 축력(F)은 결국 수직분력(Fv)과 수평분력(Fh)의 형태로 흙막이 부재(10) 상단부에 작용하게 된다. 즉, 위와 같은 구성에 의해 흙막이 부재(10)의 외측으로 능동적인 수평분력(Fh)이 작용하는 것이다. Subsequently, as shown in FIG. 4, the upper excavation 2 over the upper slab 3 is backfilled. In other words, the space above the upper slab 3 is prefilled before the ground between the soil member 10 is broken. When the soil is backfilled onto the upper slab 3 in this way, a compressive force acts on the inclined end 32 of the upper slab 3 by the load by the soil. This compressive force is eventually applied obliquely to the upper end of the retaining member 10 (slab installation in the embodiment shown in the figure). 5 is a schematic view showing a state of the force acting on the upper end of the retaining member 10 in the backfill state, as shown in the figure, the slope of the upper slab 3 on the upper end of the retaining member 10 The axial force F in the inclined direction from the end 32 acts, and this axial force F eventually acts on the upper end of the retaining member 10 in the form of the vertical component Fv and the horizontal component Fh. That is, the active horizontal component Fh acts on the outer side of the retaining member 10 by the above configuration.

이와 같이 흙막이 부재(10)의 위에 상부 슬래브(3)가 설치되고 선 되메우기가 이루어져 본 발명에 따른 지중 구조물이 형성되는 것이다. 즉, 상부 굴착부(2) 내에 흙막이 부재(10)가 간격을 두고 지중에 매립된 상태에서, 상부 슬래브(3)의 경사 단부(32)의 중심축이 흙막이 부재(10)의 수직축에 경사지게 만나도록 상기 상부 슬래브(3)가 흙막이 부재(10)의 상단부에 걸쳐져서 설치됨으로써 본 발명에 따른 지중 구조물이 형성되는 것이다. In this way, the upper slab 3 is installed on the earth member 10 and the backfill is made to form the underground structure according to the present invention. That is, in the state in which the earthing member 10 is buried in the ground at intervals in the upper excavation portion 2, the central axis of the inclined end 32 of the upper slab 3 meets inclined with the vertical axis of the earthing member 10. The upper slab 3 is installed so as to span the upper end of the earth member 10 so that the underground structure according to the present invention is formed.

상부 슬래브(3) 위의 공간을 되메우기한 후에는 흙막이 부재(10) 사이의 지반을 굴착하게 되는데, 흙막이 부재(10) 사이의 지반 굴착할 때, 종래에는 흙막이 부재(10) 사이에 버팀보를 설치하는 등의 지보공을 수행하여, 흙막이 부재(10) 사이의 간격을 유지하여야 했다. 그러나 본 발명에서는 위와 같이 되메우기 토사 하중이 상부 슬래브(3)의 경사 단부(32)를 거쳐 흙막이 부재(10)의 상단부에 외측 수평방향으로의 능동적인 수평분력(Fh)으로 작용하기 때문에, 별도의 버팀보 설치와 같은 지보공 없이도 흙막이 부재(10) 사이의 간격을 유지할 수 있게 된다. 따라서 흙막이 부재(10) 상부에 대한 별도의 지보공을 수행하지 않는 무지보공의 상태로도 흙막이 부재(10) 사이의 간격을 유지한 채로 지반의 굴착을 수행할 수 있게 된다. 이와 같이 흙막이 부재(10) 사이의 지반 굴착시에, 버팀보와 같은 지보공을 수행할 필요 없으므로, 그에 따른 비용 및 공기 절감 효과가 발휘된다. 또한 버팀보와 같은 장애물이 없으므로 지반 굴착을 위한 장비 운행이나 굴착 작업이 용이하게 이루어질 수 있게 되는 효과가 있다. 특히, 지반의 굴착이 완료되지 않은 상태에서도 상부 슬래브(3)를 설치한 후 그 상부 공간을 되메우기하게 되므로, 지반 굴착 작업과 무관하게 상부 슬래브(3) 위의 되메우기 부분에서 차량 통행 등이 이루어질 수 있게 되어, 지반 굴착 공사로 인한 차량 통행 제한이나 기타 상부 공간의 통행 제한 등의 불편함을 최소화할 수 있게 되는 효과가 있다. 상부 슬래브(3) 위의 되메우기 부분은 시공이 완료된 상태이므로, 되메우기 부분을 다시 굴착하는 등의 추가 작업이 필요 없게 되어 그만큼 시공이 간소화되는 효과도 발휘된다. After filling the space above the upper slab (3) to excavate the ground between the retaining member 10, when excavating the ground between the retaining member (10), conventionally installed a brace between the retaining member (10) To carry out the support, such as to maintain the gap between the retaining member (10). However, in the present invention, since the backfill soil load acts as an active horizontal component Fh in the outer horizontal direction at the upper end portion of the retaining member 10 via the inclined end 32 of the upper slab 3 as described above. It is possible to maintain the gap between the retaining member 10 even without the support such as the support. Therefore, it is possible to carry out excavation of the ground while maintaining the gap between the retaining member 10 even in the state of the non-supporting ball does not perform a separate support for the top of the retaining member (10). In this way, when the ground excavation between the retaining member 10, it is not necessary to perform a support ball, such as a brace, thereby resulting in a cost and air saving effect. In addition, since there is no obstacle, such as braces, there is an effect that the operation or excavation work for the ground excavation can be easily made. Particularly, since the upper slab 3 is installed even after the excavation of the ground is not completed, the upper space is refilled, so that vehicle traffic may be performed at the backfill portion on the upper slab 3 regardless of the ground excavation work. As a result, it is possible to minimize inconvenience such as vehicle traffic restriction or other traffic restrictions in the upper space due to the ground excavation work. Since the backfill portion on the upper slab 3 is in a completed state, no additional work such as digging the backfill portion is required, and the construction is simplified.

흙막이 벽체(10)의 상부에 상부 슬래브(3)를 설치하고 되메우기를 한 후에는 도 6에 도시된 것처럼, 상기 상부 슬래브(3) 아래의 흙막이 벽체(10) 사이의 지반을 하향 굴착한다. 설계 깊이까지 굴착한 후에는 도 7에 도시된 것처럼 하부 바닥판(4)을 시공하게 된다. 필요에 따라 상당한 깊이까지 굴착하는 경우, 중간 슬래브를 흙막이 벽체(10) 사이에 설치한 뒤 추가 지반 굴착을 수행한 다음에 하부 바닥판(4)을 시공할 수도 있으며, 굴착, 중간 슬래브 설치, 추가 굴착 등의 작업을 수회 반복하여 복층의 지하층을 형성한 후 하부 바닥판(4)을 시공할 수도 있다. After installing and backfilling the upper slab 3 on the top of the retaining wall 10, the ground between the retaining wall 10 below the upper slab 3 is excavated downward. After excavation to the design depth, the bottom plate 4 is constructed as shown in FIG. In case of excavation to a considerable depth, if necessary, the intermediate slab may be installed between the retaining walls 10, and then additional ground excavation may be performed, and then the lower bottom plate 4 may be constructed. The bottom floor plate 4 may be constructed after several operations such as excavation are repeated to form a basement layer of a double layer.

위의 설명에서는 상부 슬래브(3) 위쪽의 되메우기를 한 후에 상부 슬래브(3) 아래의 지반 하향 굴착이 이루어지는 것으로 설명하였으나, 이는 되메우기와 하향 굴착이 동시에 시행되는 것 및 하향 굴착이 이루어지면서 되메우기가 진행되는 것을 모두 포함하는 의미로 이해되어야 하며, 이는 특허청구범위의 기재에 있어서도 마찬가지이다. In the above description, the ground down excavation under the upper slab 3 is performed after backfilling the upper slab 3, but this is performed by the backfilling and the downward excavation at the same time and the downward excavation is performed. It is to be understood that the meaning includes all such things, and the same is true in the description of the claims.

도 8은 도 3에 도시된 상태에 대응되는 상태 즉, 상부 슬래브(3)를 설치하고 아직 그 상부를 되메우기하지 않은 상태를 보여주는 개략적인 단면도로서, 흙막이 벽체(10)를 복수개로 설치하고, 각각의 흙막이 벽체(10) 사이에 상부 슬래브(3)를 설치한 실시예를 보여준다. 도 8에 도시된 것처럼, 필요한 경우, 흙막이 벽체(10)를 복수개로 설치하고 각각의 흙막이 벽체(10) 사이에 상부 슬래브(3)를 설치할 수도 있다. 상기 흙막이 벽체(10)의 개수 및 상부 슬래브(3)의 개수는 더 증가될 수도 있다. 기타 사항은 앞서 설명한 내용과 동일하므로 반복 설명은 생략한다. FIG. 8 is a schematic cross-sectional view showing a state corresponding to the state shown in FIG. 3, that is, a state in which the upper slab 3 is installed and the upper portion thereof is not yet backfilled, and a plurality of retaining walls 10 are provided, respectively. Shows an embodiment in which the upper slab 3 is installed between the retaining wall (10). As shown in FIG. 8, if necessary, a plurality of retaining walls 10 may be provided, and an upper slab 3 may be provided between the respective retaining walls 10. The number of the retaining walls 10 and the number of the upper slabs 3 may be further increased. Other details are the same as the above description, so repeated description is omitted.

도 1 내지 도 7에는 본 발명에 따른 지중 구조물을 시공하는 각 단계를 보여주는 개략적인 단면도이다. 1 to 7 are schematic cross-sectional views showing each step of constructing the underground structure according to the present invention.

도 8은 도 3에 도시된 상태에 대응되는 상태를 보여주는 본 발명의 다른 실시예에 대한 개략적인 단면도이다. 8 is a schematic cross-sectional view of another embodiment of the present invention showing a state corresponding to the state shown in FIG. 3.

<도면의 주요 부분에 대한 부호의 설명> <Description of the symbols for the main parts of the drawings>

2 : 상부 굴착부2: upper excavation

3 : 상부 슬래브3: upper slab

10 : 흙막이 부재10: soil member

Claims (3)

지반의 상부 굴착부(2) 내에 지중 구조물이 구축될 지하 공간의 확보하도록 간격을 두고 지중에 설치된 흙막이 부재(10)와;  An earth retaining member 10 installed in the ground at intervals to secure an underground space in which the underground structure is to be built in the upper excavation portion 2 of the ground; 간격을 두고 설치된 양측 흙막이 부재(10)를 가로질러 배치되는 중앙부(31)와, 상기 중앙부(31)의 양측에 각각 연장되는 경사 단부(32)로 이루어져, 흙막이 부재(10)의 상단부에 경사 단부(32)가 놓여, 흙막이 부재(10) 사이에 설치되는 상부 슬래브(3)로 이루어지되; It is composed of a central portion 31 disposed across the both sides of the retaining member 10 provided at intervals and inclined ends 32 respectively extending on both sides of the central portion 31, the inclined end portion at the upper end of the retaining member 10 32 is placed, consisting of the upper slab (3) is installed between the retaining member (10); 상부 슬래브(3)의 경사 단부(32)에 의해 가해지는 축력에 의해 흙막이 부재(10)의 상단부에 외측으로의 수평분력이 작용하도록 경사 단부(32)가 상부 굴착부(2)에 노출되어 있는 흙막이 부재(10)의 상부에 놓이도록 상기 상부 슬래브(3)는 흙막이 부재(10)를 가로질러 배치되는데, 경사 단부(32)의 중심축은 흙막이 부재(10)의 수직축에 대해 경사지게 만나며; The inclined end 32 is exposed to the upper rig 2 so that the horizontal force acts on the upper end of the retaining member 10 by the axial force applied by the inclined end 32 of the upper slab 3. The upper slab 3 is disposed across the occlusion member 10 so as to lie on top of the occlusion member 10, wherein the central axis of the inclined end 32 meets inclined with respect to the vertical axis of the occlusion member 10; 상부 슬래브(3)가 흙막이 부재(10) 사이에 설치된 상태에서 상부 슬래브(3) 위로 상부 굴착부(2) 내에 토사에 의한 되메우기가 이루어진 구조를 가지는 것을 특징으로 하는 지중 구조물. Underground structure, characterized in that the upper slab (3) has a structure made of backfilling by the earth in the upper excavation (2) over the upper slab (3) in the state installed between the earth member (10). 지반을 굴착하여 상부 굴착부(2)를 형성하는 단계;  Excavating the ground to form an upper excavation portion 2; 상부 굴착부(2) 내에 지중 구조물이 구축될 지하 공간의 확보하도록 간격을 두고 흙막이 부재(10)를 지중에 설치하는 단계; Installing the retaining member 10 in the ground at intervals to secure an underground space in which the underground structure is to be built in the upper excavation portion 2; 간격을 두고 설치된 양측 흙막이 부재(10)를 가로질러 배치되는 중앙부(31)와, 상기 중앙부(31)의 양측에 각각 연장되는 경사 단부(32)로 이루어진 상부 슬래브(3)를, 흙막이 부재(10)의 상단부에 경사 단부(32)가 놓이도록, 흙막이 부재(10) 사이에 설치하는 단계; 및 The upper slab 3 which consists of the center part 31 arrange | positioned across the both retaining members 10 provided at intervals, and the inclined end 32 which respectively extends in the both sides of the said center part 31, the retaining member 10 Step between the earth member (10) so that the inclined end 32 is placed on the upper end of the; And 흙막이 부재(10) 사이에 설치된 상부 슬래브(3) 위로 상부 굴착부(2)를 토사로 되메우기 하며, 상부 슬래브(3) 아래로 흙막이 부재(10) 사이의 지반을 굴착하는 단계; 및Backfilling the upper excavation portion 2 with earth and sand over the upper slab 3 provided between the earthquake members 10, and excavating the ground between the earthquake members 10 under the upper slab 3; And 지반 굴착 완료 후 하부 바닥판(4)을 시공하는 단계를 포함하며; Constructing the bottom sole plate 4 after the ground excavation is completed; 상부 슬래브(3)를 흙막이 부재(10)의 사이에 설치함에 있어서, 상부 슬래브(3)의 경사 단부(32)에 의해 가해지는 축력에 의해 흙막이 부재(10)의 상단부에 외측으로의 수평분력이 작용하도록, 경사 단부(32)의 중심축이 흙막이 부재(10)의 수직축에 대해 경사지게 만나는 형태로 경사 단부(32)가 상부 굴착부(2)로 노출되어 있는 흙막이 부재(10)의 상부에 놓이도록 하는 것을 특징으로 하는 지중 구조물 시공방법. In installing the upper slab 3 between the retaining members 10, the horizontal force to the outside of the upper retaining member 10 is increased by the axial force applied by the inclined end 32 of the upper slab 3. To act, the inclined end 32 is placed on the top of the retaining member 10 in which the inclined end 32 is exposed to the upper excavation portion 2 in such a manner that the central axis of the inclined end 32 meets inclined with respect to the vertical axis of the retaining member 10. Underground structure construction method characterized in that. 제2항에 있어서, The method of claim 2, 상부 슬래브(3)는 프리캐스트 콘크리트 부재로 제작되고, 인양장치에 의해 인양되어 흙막이 부재(10) 사이에 거치되는 것을 특징으로 하는 지중 구조물 시공방법. The upper slab (3) is made of precast concrete member, is lifted by the lifting device is underground structure construction method, characterized in that mounted between the retaining member (10).
KR1020090006535A 2009-01-28 2009-01-28 Underground Structure and Method for Constructing thereof KR101025399B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090006535A KR101025399B1 (en) 2009-01-28 2009-01-28 Underground Structure and Method for Constructing thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090006535A KR101025399B1 (en) 2009-01-28 2009-01-28 Underground Structure and Method for Constructing thereof

Publications (2)

Publication Number Publication Date
KR20100087505A KR20100087505A (en) 2010-08-05
KR101025399B1 true KR101025399B1 (en) 2011-03-30

Family

ID=42754034

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090006535A KR101025399B1 (en) 2009-01-28 2009-01-28 Underground Structure and Method for Constructing thereof

Country Status (1)

Country Link
KR (1) KR101025399B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101937366B1 (en) * 2018-04-26 2019-01-15 정지용 A Precast structure for underground tunnel

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108643231B (en) * 2018-06-22 2020-10-16 中铁二局第一工程有限公司 Top plate cover excavation construction method for central urban subway station half-width structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100499338B1 (en) 2002-07-03 2005-07-04 (주)세일엔지니어링 Conduit using phc pile
KR100663109B1 (en) 2005-02-22 2007-01-02 주식회사 스마텍엔지니어링 Method for Constructing an Underground Structure Using Up-down Method
KR100663108B1 (en) 2005-02-22 2007-01-02 주식회사 스마텍엔지니어링 Method for Constructing an Underground Structure Using Up-down Method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100499338B1 (en) 2002-07-03 2005-07-04 (주)세일엔지니어링 Conduit using phc pile
KR100663109B1 (en) 2005-02-22 2007-01-02 주식회사 스마텍엔지니어링 Method for Constructing an Underground Structure Using Up-down Method
KR100663108B1 (en) 2005-02-22 2007-01-02 주식회사 스마텍엔지니어링 Method for Constructing an Underground Structure Using Up-down Method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101937366B1 (en) * 2018-04-26 2019-01-15 정지용 A Precast structure for underground tunnel

Also Published As

Publication number Publication date
KR20100087505A (en) 2010-08-05

Similar Documents

Publication Publication Date Title
US20220098817A1 (en) Method for constructing structure
JP5055249B2 (en) Multiple tunnel construction method and multiple tunnel structure
CN105839946A (en) Brick-concrete structure building lifting add-layer method
JP6543176B2 (en) Building method
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR101902791B1 (en) Under ground structure construction method using composite steel pile and under ground structure therewith
JP5204063B2 (en) Box foundation construction method in open shield method
KR101902786B1 (en) Under ground structure construction method using composite sheet pile and under ground structure therewith
KR101025399B1 (en) Underground Structure and Method for Constructing thereof
JP6194388B1 (en) Open shield method
JP4113187B2 (en) Construction method of underground structure
KR100468034B1 (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
JP4226954B2 (en) Underpinning method and viaduct
KR20130021949A (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
JP2005133408A (en) Method of correcting foundation settlement using sandbag
CN213476893U (en) Supporting structure for spanning large underground pipeline foundation pit
KR100663109B1 (en) Method for Constructing an Underground Structure Using Up-down Method
JP6860895B2 (en) Retaining wall and its construction method
JP5140515B2 (en) Installation method of underground floor pillar and construction method of underground structure
JP2008280738A (en) Retaining wall reinforcing structure and method of constructing the same
KR20100087506A (en) Underground structure and method for constructing thereof
CN205557573U (en) Underground structure
CN112012771A (en) Underground excavation and sequential construction underground structure of hole piles and construction method thereof
KR102420947B1 (en) Retaining wall construction method using gravity block
KR102149709B1 (en) Deformation prevention method of files for retaining wall of underground

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20140319

Year of fee payment: 4

LAPS Lapse due to unpaid annual fee