CN205557573U - Underground structure - Google Patents

Underground structure Download PDF

Info

Publication number
CN205557573U
CN205557573U CN201620201483.6U CN201620201483U CN205557573U CN 205557573 U CN205557573 U CN 205557573U CN 201620201483 U CN201620201483 U CN 201620201483U CN 205557573 U CN205557573 U CN 205557573U
Authority
CN
China
Prior art keywords
guard
along
underground structure
center pillar
corner post
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201620201483.6U
Other languages
Chinese (zh)
Inventor
华若延
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201620201483.6U priority Critical patent/CN205557573U/en
Application granted granted Critical
Publication of CN205557573U publication Critical patent/CN205557573U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The utility model provides an underground structure, in the construction, the outside and the envelope's of the soil body side is direct contact on every side, envelope is including going along with sb. To guard him the corner post, going along with sb. To guard him center pillar and containment sheet, its characterized in that: including following step: with claw fill or underground continuous wall excavator, along the inside slot that excavates out desired depth in the outside of the soil body around the underground structure will with the static pressure mode go along with sb. To guard him the corner post, go along with sb. To guard him the center pillar in the vertical soil body of impressing of containment sheet extremely design depth, excavate the soil body in the envelope, the clearance the surface that envelope exposes, go along with sb. To guard him the corner post and/or go along with sb. To guard him the center pillar with pour into waterproof mortar in the clearance between the containment sheet into, will underground structure's outer wall, bottom plate, floor and envelope pours as an organic wholely, forms underground structure's major structure.

Description

A kind of underground structure
Technical field
This utility model relates to a kind of building underground structure, especially relates to build and has basement or similar underground structure.
Background technology
Build underground structure time, prior art generally uses sheet pile, diaphram wall etc. formed retaining wall, then with Building template in being spaced a less space between retaining wall, in the template completed, casting concrete forms underground structure Wall.
This traditional construction method, when excavating ground, needs to dig out additional space to guarantee to build the sky required for template Between, the answer simultaneously also resulting in earth excavation amount increases, particularly during construction in the case of urban renewal, and newly-built underground Building usually and needs only have the most limited slight distance between the inhering architecture retained, and this exists for needing to improve effectively utilizing The demand of rate.Additionally, this traditional construction method there is also, above-mentioned extra excavation space requirement is backfilled, before backfill Need to carry out the soil excavated concentrating to stack, and the surface collapse after backfill settles the various problems such as uneven.
Chinese patent CN1155606A discloses a kind of by foundation side wall as basement wall and construction method thereof, this side wall by Foundation ditch retaining wall, filling waterproof layer and interior wall composition.Retaining wall includes cantilever pile, freely-supported stake etc..Its mentality of designing is main It is the ingredient saying retaining wall as basement guard wall, the retaining wall of gib is become permanent structure, replace reinforcing bar Cast-in-place concrete pile.But this patent has a drawback in that, the DESIGN OF RETAINING WALLS of gib originally needs according to permanent knot Structure is designed, and improves the cost of supporting construction, and retaining wall structure is not suitable as permanent load-carrying members, such use The change on way may bring unpredictable hidden danger.
It is structure-integrated that Chinese patent CN103669402A discloses the piling wall that a kind of main body outer wall of basement combines with fender post Structure, between outer wall of basement and fender post formed narrow space in, arrange along outer wall of basement side safeguard structure, Power transmission strip etc. so that fender post acts in permanent use jointly with outer wall of basement, it is considered to subtract after the stiffness contribution of fender post The thickness of few outer wall of underground structure, saves construction investment.But this patent still can not additionally excavate space in work progress, And in limited narrow space, carry out building the defect of template.
Defect in view of above-mentioned conventional construction method, it is necessary to further improve the construction method of underground structure, to solve Certainly the problems referred to above.
Utility model content
Thus setting out, one of the present utility model to solve the technical problem that and is, it is not necessary to arrange the then supporting such as retaining wall after excavation The construction method of structure, to realize without excavating additional space for building template.
Of the present utility model another to solve the technical problem that and to be, supporting construction uses the hidden danger brought as permanent structure, with And the impact for agent structure.
This utility model provides a kind of underground structure, and the exterior wall of described underground structure, base plate, floor go along with sb. to guard him knot with described Structure pours and is integrated, and in construction, the outermost of surrounding soil is directly to contact with the side of described building enclosure, described in go along with sb. to guard him Structure includes going along with sb. to guard him corner post, going along with sb. to guard him center pillar and wall interior panel, it is characterised in that described underground structure is built by following methods: with pawl Bucket or diaphram wall excavator, the outermost inner excavation along described underground structure surrounding soil goes out the groove of desired depth, Described desired depth less than the projected depth of described building enclosure, the cross-sectional width phase of the width of described groove and described building enclosure When or be slightly less than the cross-sectional width of described building enclosure;In the corner of underground structure, in static pressure mode, to go along with sb. to guard him corner post vertical by described To described projected depth in the press-in soil body;In static pressure mode, described center pillar of going along with sb. to guard him vertically is pressed between the corner of underground structure To described projected depth in the soil body;Go along with sb. to guard him described in adjacent corner post and/or described in go along with sb. to guard him and enclose described in static pressure mode between center pillar To described projected depth in the backplate press-in soil body;Excavate the soil body in described building enclosure, clear up the table that described building enclosure is exposed Face;Described go along with sb. to guard him corner post and/or described in go along with sb. to guard him and inject waterproof mortar in the gap between center pillar and described wall interior panel;Enclose described The exposing surface dabbing of protection structure, using the surface of described building enclosure as the formwork for placing of described underground structure exterior wall, then Build the inner side template of described underground structure exterior wall, by underground structure exterior wall, base plate, concrete floor slab placement in building enclosure, Form the agent structure of underground structure.
Preferably, described building enclosure uses directly as the template of underground structure exterior wall.
This utility model additionally provides the construction method of a kind of underground structure, in construction, the outermost of surrounding soil with go along with sb. to guard him The side of structure is directly contact, and described building enclosure includes going along with sb. to guard him corner post, going along with sb. to guard him center pillar and wall interior panel, it is characterised in that: Comprise the steps: step 1: with pawl bucket or diaphram wall excavator, along the outermost of described underground structure surrounding soil Side inner excavation goes out the groove of desired depth, and described desired depth is less than the projected depth of described building enclosure, the width of described groove Degree and the cross-sectional width of described building enclosure quite or are slightly less than the cross-sectional width of described building enclosure;Step 2: in hypogee Described corner post of going along with sb. to guard him vertically is pressed in the soil body to described projected depth by the corner of thing in static pressure mode;Step 3: in hypogee In static pressure mode, described center pillar of going along with sb. to guard him vertically is pressed in the soil body to described projected depth between the corner of thing;Step 4: adjacent Described in go along with sb. to guard him corner post and/or described in go along with sb. to guard him between center pillar with static pressure mode by described wall interior panel press-in the soil body in described design deep Degree;Step 5: excavate the soil body in described building enclosure, clears up the surface that described building enclosure is exposed;Step 6: enclose described Corner protector post and/or described in go along with sb. to guard him and inject waterproof mortar in the gap between center pillar and described wall interior panel;Step 7: described underground is built Build the exterior wall of thing, base plate, floor to pour with described building enclosure and be integrated, form the agent structure of underground structure.
Preferably, go along with sb. to guard him described in corner post, described in go along with sb. to guard him center pillar and described wall interior panel is prefabricated components.
Preferably, the end of described wall interior panel has protuberance, is suitable to engage with the described recess going along with sb. to guard him center pillar side, or described The junction surface going along with sb. to guard him corner post engages.
Preferably, described in go along with sb. to guard him the cross sectional shape of center pillar be I-shaped, described in go along with sb. to guard him the cross sectional shape of corner post be that circle cuts out The shape corresponding with described protuberance.
Preferably, described wall interior panel is internally provided with vertical and horizontal steel bar layer, at the peripheral end parts of described wall interior panel, be provided with The built-in fitting that steel bar layer connects, first by described go along with sb. to guard him corner post and/or described in the built-in fitting gone along with sb. to guard him between center pillar with described wall interior panel be connected Good, then carry out waterproof mortar process.
The beneficial effects of the utility model are:
1. the building enclosure that the groove excavating out desired depth makes static pressure enter in the soil body is fitted for the squeezing effect of surrounding soil When alleviation.
2. pillar and the wall interior panel of building enclosure is precast construction, suitableeer than the retaining wall of the gib of conventional art use Cooperate to use for permanent structure.
3. although building enclosure is as a part for permanent structure, but to remain integral type cast-in-place for the agent structure of underground structure , its bulk strength is not affected by building enclosure, and building enclosure is intended only as the outboard template of the agent structure of underground structure Use.
4 work progress are avoided additionally excavate space, and the various problems such as the backfill process brought, also solve is narrow simultaneously In space, template is difficult to the defect built.
Accompanying drawing explanation
Fig. 1 is the part construction floor map of underground structure of the present utility model.
Fig. 2 is the wall interior panel schematic cross-section of use of the present utility model.
Detailed description of the invention
Below in conjunction with specific embodiment, this utility model is further described, but this utility model is not confined to these Detailed description of the invention.One skilled in the art would recognize that this utility model covers the possible bag of institute in Claims scope All alternatives, improvement project and the equivalents included.
As Fig. 1 illustrates, the part construction plan of underground structure, the soil body 1 of the surrounding of underground structure to be built is Outside is expressed as 2, for clarity sake, in the accompanying drawings by the outermost 2 of surrounding soil 1 spaced apart with the side of building enclosure one Individual small distance.But in Shi Gong, the outermost 2 of surrounding soil 1 can directly contact with the side of building enclosure.
According to design, on construction ground in bury underground along the outermost of the soil body 1 of the surrounding of the underground structure built and to go along with sb. to guard him corner post 11 and go along with sb. to guard him center pillar 12.Go along with sb. to guard him corner post 11, to go along with sb. to guard him center pillar 12 can be prefabrication, or water at the construction field (site) and build up Type.Preferably go along with sb. to guard him corner post 11, to go along with sb. to guard him center pillar 12 be mill work.Go along with sb. to guard him corner post 11, go along with sb. to guard him center pillar 12 and preferably adopt It is pressed in the soil body 1 to projected depth by static pressure mode.
Then go along with sb. to guard him corner post 11 adjacent and go along with sb. to guard him center pillar between 12 or adjacent go along with sb. to guard him between center pillar 12, by wall interior panel 13 are pressed into projected depth in the soil body.As the figures show, the end of wall interior panel 13 has protuberance 131, is suitable to and goes along with sb. to guard him The recess 121 of center pillar 12 side engages, or the junction surface 111 going along with sb. to guard him corner post 111 engages.The most as shown in drawings, The cross section going along with sb. to guard him center pillar 12 is I-shaped, and the cross section going along with sb. to guard him corner post 11 is that circle cuts out the shape corresponding with protuberance 131.
But optional, the cross section going along with sb. to guard him center pillar can also be other shapes, the most T-shaped, circular with recess etc., go along with sb. to guard him angle The cross section of post can also be other shapes, and such as square is with recess etc..
Consider easily for Prefabrication, it is possible to use the prefabricated pile of other standards shape, however it is necessary that in stake surface configuration Can be with wall interior panel 13 to the built-in fitting being connected.
As in figure 2 it is shown, wall interior panel 13 is internal can be provided with vertical and horizontal steel bar layer.At the peripheral end parts of wall interior panel 13, arrange There is the built-in fitting being connected with steel bar layer.Preferably built-in fitting is the steel plate in strap bolt hole.So wall interior panel 13 can with go along with sb. to guard him corner post 11 and go along with sb. to guard him completed by bolt between center pillar 12 preliminary fixing.
Wall interior panel 13 preferably has the size of Modular building modulus, in order to be suitable in combination underground structure chi Very little.
Building enclosure can use directly as the template of underground structure exterior wall, property illustrated below a kind of concrete execute is depicted Work method, but the mode of this utility model enforcement is not limited to this and schematically describes, and skilled person will appreciate that dawn uses other Known non-dismantling formwork or after the mode of watering implement.As after to carrying out waterproof mortar process at the gap between building enclosure, can By the exposing surface dabbing of building enclosure, using building enclosure surface as the formwork for placing of underground structure exterior wall, then to build The inner side template of underground structure exterior wall, by underground structure exterior wall 10, base plate and concrete floor slab placement in building enclosure, forms ground The agent structure of lower building.
The construction method of underground structure of the present utility model is below described in different embodiments:
Embodiment 1
The construction method of a kind of underground structure, comprises the steps:
Step 1: with engineering machinery such as pawl bucket or diaphram wall excavators, along the outermost of the soil body 1 around underground structure Side 2 inner excavation goes out the groove of desired depth, the projected depth that this desired depth is less than and goes along with sb. to guard him corner post 11, goes along with sb. to guard him center pillar 12, The width of groove and the cross-sectional width of building enclosure quite or are slightly less than the cross-sectional width of building enclosure;
Step 2: corner post 11 will be gone along with sb. to guard him in the corner of underground structure in static pressure mode and be pressed into projected depth;
Step 3: center pillar 12 will be gone along with sb. to guard him in static pressure mode between the corner of underground structure and be pressed into projected depth;
Step 4: in static pressure mode, wall interior panel 13 is pressed into design between center pillar 12 at the adjacent corner post 11 and/or go along with sb. to guard him of going along with sb. to guard him The degree of depth;
Step 5: excavate the soil body 10 in building enclosure, the surface that cleaning building enclosure is exposed;
Step 6: connect and go along with sb. to guard him corner post 11 and/or the built-in fitting (if having built-in fitting) going along with sb. to guard him between center pillar 12 and wall interior panel 13, Waterproof mortar is injected in going along with sb. to guard him corner post 11 and/or going along with sb. to guard him the gap between center pillar 12 and wall interior panel 13;
Step 7: the exterior wall 10 of underground structure and base plate, floor are poured with building enclosure and is integrated, form underground structure Agent structure.
Embodiment 2
The construction method of a kind of multi-layer underground building, comprises the steps:
Step 1: with engineering machinery such as pawl bucket or diaphram wall excavators, along the outermost of the soil body 1 around underground structure Side 2 inner excavation goes out the groove of desired depth, the projected depth that this desired depth is less than and goes along with sb. to guard him corner post 11, goes along with sb. to guard him center pillar 12, The width of groove and the cross-sectional width of building enclosure quite or are slightly less than the cross-sectional width of building enclosure;
Step 2: corner post 11 will be gone along with sb. to guard him in the corner of underground structure in static pressure mode and be pressed into projected depth;
Step 3: center pillar 12 will be gone along with sb. to guard him in static pressure mode between the corner of underground structure and be pressed into projected depth;
Step 4: in static pressure mode, wall interior panel 13 is pressed into design between center pillar 12 at the adjacent corner post 11 and/or go along with sb. to guard him of going along with sb. to guard him The degree of depth;
Step 5: excavate the soil body 10 in building enclosure, the surface that cleaning building enclosure is exposed;
Step 6: connect and go along with sb. to guard him corner post 11 and/or the built-in fitting (if having built-in fitting) going along with sb. to guard him between center pillar 12 and wall interior panel 13, Waterproof mortar is injected in going along with sb. to guard him corner post 11 and/or going along with sb. to guard him the gap between center pillar 12 and wall interior panel 13;
Step 7: the exterior wall 10 of underground structure and orlop base plate are poured with building enclosure and is integrated, then by last layer ground The exterior wall 10 of lower building and floor pour with building enclosure and are integrated, and are repeatedly formed multiple structure as required.
Having the beneficial effects that of this utility model embodiment:
1. the building enclosure that the groove excavating out desired depth makes static pressure enter in the soil body is fitted for the squeezing effect of surrounding soil When alleviation.
2. pillar and the wall interior panel of building enclosure is precast construction, suitableeer than the retaining wall of the gib of conventional art use Cooperate to use for permanent structure.
3. although building enclosure is as a part for permanent structure, but to remain integral type cast-in-place for the agent structure of underground structure , its bulk strength is not affected by building enclosure, and building enclosure is intended only as the outboard template of the agent structure of underground structure Use.
4 work progress are avoided additionally excavate space, and the various problems such as the backfill process brought, also solve is narrow simultaneously In space, template is difficult to the defect built.
This utility model content is simply schematically illustrated by above-mentioned specific embodiment, does not represent the restriction to this utility model content. It may occur to persons skilled in the art that, in this utility model, concrete structure can have a lot of versions, but it uses skill The technical characteristics of art scheme is same or similar with this utility model, all should be covered by this utility model protection domain.

Claims (6)

1. a underground structure, the exterior wall of described underground structure, base plate, floor pour with building enclosure and are integrated, in construction, the outermost of surrounding soil is directly to contact with the side of described building enclosure, and described building enclosure includes going along with sb. to guard him corner post, going along with sb. to guard him center pillar and wall interior panel.
Underground structure the most according to claim 1, it is characterised in that go along with sb. to guard him described in: corner post, described in go along with sb. to guard him center pillar and described wall interior panel is prefabricated components.
Underground structure the most according to claim 1, it is characterised in that: the end of described wall interior panel has protuberance, is suitable to engage with the described recess going along with sb. to guard him center pillar side, or described in go along with sb. to guard him the junction surface of corner post and engage.
Underground structure the most according to claim 3, it is characterised in that the cross sectional shape going along with sb. to guard him center pillar described in: is I-shaped, described in go along with sb. to guard him the cross sectional shape of corner post be that circle cuts out the shape corresponding with described protuberance.
Underground structure the most according to claim 1, it is characterised in that: described wall interior panel is internally provided with vertical and horizontal steel bar layer, at the peripheral end parts of described wall interior panel, is provided with the built-in fitting being connected with steel bar layer.
Underground structure the most according to claim 1, it is characterised in that: described building enclosure uses directly as the template of underground structure exterior wall.
CN201620201483.6U 2016-03-15 2016-03-15 Underground structure Expired - Fee Related CN205557573U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620201483.6U CN205557573U (en) 2016-03-15 2016-03-15 Underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620201483.6U CN205557573U (en) 2016-03-15 2016-03-15 Underground structure

Publications (1)

Publication Number Publication Date
CN205557573U true CN205557573U (en) 2016-09-07

Family

ID=56817791

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620201483.6U Expired - Fee Related CN205557573U (en) 2016-03-15 2016-03-15 Underground structure

Country Status (1)

Country Link
CN (1) CN205557573U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625468A (en) * 2016-03-15 2016-06-01 华若延 Underground building

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105625468A (en) * 2016-03-15 2016-06-01 华若延 Underground building

Similar Documents

Publication Publication Date Title
KR100722665B1 (en) Steel guide wall for underground continuous wall construction and underground continuous wall construction method
CN105239578B (en) Water-rich sand layer deep foundation pit underwater construction method
CN1958966A (en) Underground consecutive sinking well type openweb wall body, and construction method
CN109183848A (en) A kind of Tunnel Design and building method
KR100376590B1 (en) Multi-phased underground construction method for wide excavation using permanent structural members as temporary struts
CN206157594U (en) Campshed box culvert structure
CN205557573U (en) Underground structure
CN105155421B (en) Complete embedding circular construction method in a kind of single pile Single column pier river course shallow water
CN107165170A (en) A kind of foundation ditch construction method
CN215441921U (en) Novel support shear structure
CN214738333U (en) Permanent-faced combined box culvert foundation reinforcing structure
CN106120853B (en) A kind of inverted construction method of frame bridge
CN105625468B (en) A kind of method of construction of multi-layer underground building
CN210459300U (en) An envelope structure covering an excavation station
JP3234820B2 (en) Retaining wall construction method and construction of retaining wall for building residential land
KR20180040095A (en) Construction method for soil retaining wall using cap slab
JPS5936058B2 (en) How to construct a structure using underground continuous walls
CN105604180B (en) A kind of construction method of underground structure
JP3728659B2 (en) Basement extension method
JP7480069B2 (en) How to reinforce existing revetments
CN219261048U (en) Working well
CN210562118U (en) Novel combined steel sheet pile
CN216428327U (en) Slope protection reinforced concrete structure
JP4031284B2 (en) Construction method for underground structures
JP2764482B2 (en) Construction method of large depth human hole

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160907

Termination date: 20190315

CF01 Termination of patent right due to non-payment of annual fee