KR101257905B1 - Method for constructing foundation work - Google Patents

Method for constructing foundation work Download PDF

Info

Publication number
KR101257905B1
KR101257905B1 KR1020120049277A KR20120049277A KR101257905B1 KR 101257905 B1 KR101257905 B1 KR 101257905B1 KR 1020120049277 A KR1020120049277 A KR 1020120049277A KR 20120049277 A KR20120049277 A KR 20120049277A KR 101257905 B1 KR101257905 B1 KR 101257905B1
Authority
KR
South Korea
Prior art keywords
pile
embedded
excavation
embedded pile
foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
KR1020120049277A
Other languages
Korean (ko)
Inventor
정재홍
최진석
Original Assignee
주식회사 삼호에스텍
민병찬
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 삼호에스텍, 민병찬 filed Critical 주식회사 삼호에스텍
Priority to KR1020120049277A priority Critical patent/KR101257905B1/en
Application granted granted Critical
Publication of KR101257905B1 publication Critical patent/KR101257905B1/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/62Compacting the soil at the footing or in or along a casing by forcing cement or like material through tubes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/005Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof removing the top of placed piles of sheet piles
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • E04B2001/389Brackets

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Civil Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • General Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Environmental & Geological Engineering (AREA)
  • Foundations (AREA)

Abstract

PURPOSE: A foundation construction method using a bored pile is provided to reduce the construction period and costs by performing only excavation work for installing the bored pile. CONSTITUTION: A foundation construction method using a bored pile(100) comprises a step of installing an earth retaining wall(210) in the ground; a step of forming a plurality of excavation holes in a site in which a main column(250) is arranged using an excavating device; a step of embedding the bored pile in the excavation holes and of grouting through the bored pile; a step of performing initial ground excavating work; a step of performing arrange work of a first floor frame including a girder(240); a step of performing additional excavating work and the arrange work of an underground frame until excavation work reaches a basic level(L); a step of installing the main column between the bored piles; and a step of cutting and removing an upper part of the bored pile.

Description

매입말뚝을 이용한 기초 공법{METHOD FOR CONSTRUCTING FOUNDATION WORK}Foundation method using embedded pile {METHOD FOR CONSTRUCTING FOUNDATION WORK}

본 발명은 건축물의 지하층 구조물을 시공하는 방법으로서, 더욱 상세하게는 지하 구조물을 구축함에 있어서 상층에서 하층으로 하향 시공해 나가면서 구조물을 형성하는 탑다운(Top-down) 공법(역타 공법) 중 매입말뚝을 이용한 기초 공법에 관한 것으로서, 본기둥 설치 전에 매입말뚝을 설치하여, 가설기둥으로 사용하고 시공이 완료된 후 최종적으로 본기둥을 설치함으로써 시공 효율성, 경제성 및 안전성이 향상된 매입말뚝을 이용한 기초 공법에 관한 것이다.The present invention is a method for constructing a basement structure of a building, and more specifically, in the construction of an underground structure, the construction of the top-down method (reverse construction method) for forming a structure while constructing the structure from the upper floor to the lower floor. It is a basic construction method using piles, and it is necessary to install the pile before installing the main pillar, use it as a temporary pillar, and finally install the main pillar after the construction is completed to improve the construction efficiency, economy and safety. It is about.

일반적으로 건물의 지하층 구조물을 구축하는 방식을 분류하면, 지하구조물을 구축 시공하는 방향에 따라 크게 순타 공법과 역타 공법으로 분류된다.In general, when the basement structure of a building is classified, it is classified into a forward and a reverse method according to the direction in which the underground structure is constructed.

이중, 역타 공법은 소위 탑다운(Top-down) 공법이라고도 하는데, 이는 건축물의 지상고가 높아지고 이에 필요한 지하구조물이 깊어짐에 따라 지상층과 지하층을 동시에 완성할 수 있는 공법이다. 이러한 탑다운 공법은 지하 터파기에 앞서 지하 외벽과 지하 기둥을 시공한 후 층별 터파기 작업과 함께 지하구조물을 병행하여 시공함으로써 스트러트나 어스앵커와 같은 별도의 지보공 없이 위에서 아래로, 즉 전통적인 순타 공법과는 반대 방향으로 지하층을 완성해 나가는 공법에 해당한다.In particular, the reverse stroke method is also called a top-down method, which is a method that can simultaneously complete the ground floor and the underground floor as the ground height of the building increases and the underground structures necessary for this deepen. This top-down method is to install underground outer walls and pillars before underground trenches, and then construct underground structures in parallel with floor trenches, so that the top-down method can be used from top to bottom without struts or earth anchors. Corresponds to the construction method to complete the basement in the opposite direction.

상기와 같은 탑다운 공법을 적용하게 되면, 지하층과 지상층 공사가 동시에 진행될 수 있기 때문에, 공사 기간 단축의 효과가 클 뿐 아니라, 1 층 바닥에 직접 공사 차량이나 장비를 진입시켜 작업 공간으로 사용할 수 있으므로, 부지가 협소한 공사에서도 원활한 시공이 가능하다는 장점이 있다. 아울러 상기와 같은 탑다운 공법의 경우, 건물 본 구조체를 횡토압에 대한 버팀대로 이용하면서 상층에서 하층으로 굴착과 구체 구축을 반복하여 시공하는 공법이므로 일반적인 개착식 공법에 비해 토류벽의 안정성이 높으며 주변 건물의 침하로 인한 민원 발생의 우려가 낮다는 장점을 가지고 있는바, 상기와 같은 탑다운 공법은 전술한 여러가지 장점으로 인해 최근 들어 활용도가 점차 높아지는 추세이다.When applying the above-mentioned top-down method, since the basement and ground floor construction can be carried out at the same time, the effect of shortening the construction period is large, and the construction vehicle or equipment can be directly used on the ground floor to be used as a work space. In addition, the construction has a merit of being able to be constructed smoothly even in a narrow site. In addition, in the case of the top-down method as described above, excavation and concrete construction are repeated from the upper floor to the lower floor while using the main structure of the building as a support for transverse earth pressure. There is a low concern about the occurrence of civil complaints due to the settlement of the bar, the top-down method as described above is due to the various advantages described above, the utilization is gradually increasing in recent years.

한편, 상기와 같은 탑다운 공법에 따르면, 지하 터파기를 하지 않은 상태에서 기둥 부재를 지중에 설치하여 지하 기둥을 선 시공한 다음, 1 층 바닥 구조체를 완성한 후 그 하부 지반을 굴착해 나가는 방식에 따라 시공이 이루어지게 되는데, 이때 상기와 같이 설치되는 기둥 부재의 경우 기존의 탑다운 공법에 의하면 주로 철골 형강 부재를 사용하는 것이 일반적이었다.On the other hand, according to the top-down method as described above, after installing the pillar member in the ground without the underground trench, and pre-installed the underground pillar, after completing the ground structure of the first floor, according to the way to excavate the lower ground The construction is made, where the pillar member is installed as described above according to the conventional top-down method was generally used steel frame member.

그런데, 일반적으로 지하층에 설치되는 기둥의 경우 지상 구조물을 포함한 건물 구조체의 전체 자중과 완공 후 사용 하중을 모두 지지하므로 상당히 큰 단면 및 규모를 가져야 한다. 따라서, 탑다운 공법에 있어 상기와 같이 대규모의 기둥 부재를 설치하기 위해 대구경의 삽입공을 천공해야 하며, 이와 같은 대구경의 지반 천공이 가능한 공법으로 RCD(Riverse Circulation Drill) 공법 또는 PRD(Percussion Rotary Drill) 공법이 사용된다.However, in general, the pillars installed in the basement floor must have a fairly large cross section and scale because they support both the total weight of the building structure including the ground structure and the working load after completion. Therefore, in the top-down method, in order to install a large-scale pillar member as described above, a large diameter insertion hole must be drilled, and such a large diameter ground drilling method is available such as a reverse circulation drill (RCD) method or a percussion rotary drill (PRD). ) Method is used.

그러나, 상기와 같은 RCD 또는 PRD 공법의 경우 그 시공 속도가 매우 느리므로 시공 효율성이 저하될 뿐 아니라 높은 작업 비용으로 인해 전체 공사 비용이 증가하여 탑다운 공법 전체의 경제성을 떨어트리는 요인으로 작용한다.However, in the case of the RCD or PRD method as described above, since the construction speed is very slow, not only the construction efficiency is lowered, but also the overall construction cost is increased due to the high work cost, which acts as a factor that lowers the overall economic efficiency of the top-down method.

또한, 일반적인 탑다운 공법의 경우 지반의 상태가 좋지 않은 연약 지반에 적용되는 경우가 많은데, 이와 같이 연약지반에 설치되는 기둥 부재는 지하 기초만으로는 지지력이 부족한 경우 지지력 확보를 위해 기초 레벨 하부로 소정 깊이 이상 관입됨으로써 연약 지반에 대한 지지력 파일의 역할을 겸할 수 있도록 하고 있다. 그러나, 기존 탑다운 공법에 있어 기둥 부재로서 일반적으로 사용되는 철골 'H' 형상의 경우 그 단면 형태상 전방위 지지력을 확보하기 어려운 점이 문제가 될 수 있다.In addition, in general, the top-down method is often applied to the soft ground of poor ground condition, the column member installed in the soft ground in this way, if the base is not enough support capacity only in the basement base to a certain depth below the foundation level to secure the support capacity By invading the above, it is possible to serve as a support pile for the soft ground. However, in the case of steel 'H' shape which is generally used as a pillar member in the existing top-down method, it may be a problem that it is difficult to secure an omnidirectional bearing force in the cross-sectional shape.

공개특허 10-2007-0108741Patent Publication 10-2007-0108741

본 발명은 전술한 문제점을 해결하기 위해 안출된 것으로서, 탑다운 공법중 매입말뚝을 이용한 기초 공법으로서 우선 원형 단면을 갖는 소구경의 매입말뚝을 이용하여 가설기둥을 설치한 후 지하층 시공이 완료된 다음 본기둥을 설치한 후, 상기 매입말뚝의 일부분을 제외한 나머지 부분을 제거함으로써, 공사 기간 및 공사 비용을 대폭적으로 절감할 수 있는 매입말뚝을 이용한 기초 공법을 제공하는 데 그 목적이 있다.The present invention has been made to solve the above problems, as a basic method using the embedded pile in the top-down method, first install the temporary column using a small diameter buried pile having a circular cross section and then the basement construction is completed After installing the column, by removing the remaining portion except for a portion of the purchase pile, the purpose is to provide a basic construction method using the purchase pile that can significantly reduce the construction period and construction cost.

상술한 목적을 달성하기 위하여, 본 발명에 따른 매입말뚝을 이용한 기초 공법은, 지중에 흙막이 벽을 구축하는 단계; 본기둥이 배치되는 부위에 굴착 장치를 이용하여 복수의 굴착공을 형성하는 단계; 상기 굴착공에 매입말뚝을 매설하고 상기 매입말뚝을 통해 그라우팅하는 단계; 초기 터파기 공사를 수행하는 단계; 거더를 포함한 지상 1층 골조 배치 공사를 수행하는 단계; 기초 레벨에 이르기까지 추가 터파기 및 지하층 골조 배치 공사를 수행하는 단계; 상기 복수의 매입말뚝 사이에 본기둥을 설치하는 단계; 및 기초 레벨보다 상부로 연장된 상기 매입말뚝의 상단부를 절단하여 제거하는 단계;를 포함하는 것을 특징으로 한다.In order to achieve the above object, the foundation method using the embedded pile according to the present invention comprises the steps of: constructing a wall of mud; Forming a plurality of excavation holes using an excavation device at a portion where the main pillar is disposed; Embedding the embedded pile in the excavation hole and grouting through the embedded pile; Performing an initial excavation work; Performing a ground-floor framing arrangement including a girder; Performing additional digging and basement frame placement work down to the foundation level; Installing a main pillar between the plurality of embedded piles; And cutting and removing an upper end of the embedded pile extending above the foundation level.

바람직하게는, 본 발명의 일 실시예에 따른 매입말뚝을 이용한 기초 공법은 상기 본기둥은 상기 복수의 매입말뚝 사이에 배치된다.Preferably, in the foundation method using the embedded pile according to an embodiment of the present invention, the main pillar is disposed between the plurality of embedded piles.

바람직하게는, 본 발명의 일 실시예에 따른 매입말뚝을 이용한 기초 공법은 각 지하층 높이마다 상기 매입말뚝에 고정되는 브라켓이 마련되고, 상기 지하층 골조는 상기 브라켓에 의해서 지지된다.Preferably, the foundation method using the embedded pile according to an embodiment of the present invention is provided with a bracket fixed to the embedded pile for each basement height, the basement frame is supported by the bracket.

바람직하게는, 본 발명의 일 실시예에 따른 매입말뚝을 이용한 기초 공법에 사용되는 상기 매입말뚝은, 그라우팅액이 통과하도록 하단부의 내외주면을 관통하여 그라우팅액홀이 형성되며 저면이 개방된 중공형의 파일; 상기 파일의 하단부가 안착되는 안착부와, 상기 안착부의 가장자리로부터 상측으로 연장되는 연장부를 갖는 선단보강판;을 포함하되, 상기 연장부는 상측으로 갈수록 상기 안착부의 중심으로부터 이격되도록 경사지게 형성된다.Preferably, the buried pile used in the foundation method using the buried pile according to an embodiment of the present invention, the grouting liquid hole is formed through the inner and outer peripheral surface of the lower end so that the grouting liquid passes through the hollow of the bottom file; And a front end reinforcing plate having a seating portion on which the lower end of the pile is seated, and an extension part extending upward from an edge of the seating portion, wherein the extension portion is inclined to be spaced apart from the center of the seating portion toward the upper side.

바람직하게는, 본 발명의 일 실시예에 따른 매입말뚝을 이용한 기초 공법에 사용되는 상기 매입말뚝은, 상기 안착부의 저면으로부터 하측방향으로 돌출되는 굴착용 보강판을 더 포함한다.Preferably, the embedding pile used in the foundation method using the embedded pile according to an embodiment of the present invention further includes an excavation reinforcement plate protruding downward from the bottom of the seating portion.

바람직하게는, 본 발명의 일 실시예에 따른 매입말뚝을 이용한 기초 공법에 사용되는 매입말뚝은, 상기 선단보강판이 상기 연장부의 둘레에 걸쳐 형성된 제1 관통공, 및 상기 안착부에 형성된 제2 관통공 중 적어도 하나를 포함한다.Preferably, the embedding pile used in the foundation method using the embedded pile according to an embodiment of the present invention, the first through-hole the front end reinforcing plate is formed over the periphery of the extension, and the second through-hole formed in the seating portion At least one of the balls.

본 발명에 따른 매입말뚝을 이용한 기초 공법에 의하면, 구조물의 구축 단계에서 본기둥이 전체 설계하중을 받기 전에 일단 소구경의 매입말뚝을 설치하여 거더, 슬래브 등 지하 바닥 구조체 구축을 위한 가설용 임시 기둥으로 이용한 다음, 지하 구조체가 완성된 이후 영구 구조물로서 본기둥을 설치할 수 있다.According to the foundation method using the embedded pile according to the present invention, before receiving the full design load of the main pillar at the construction stage of the structure, temporary pillars for temporary construction for the construction of underground floor structures such as girders and slabs After use, the pillar can be installed as a permanent structure after the underground structure is completed.

이에 따라서, 처음 지반을 굴착하고 가설 기둥을 설치할 때 비교적 소구경의 가설 기둥인 매입말뚝의 설치를 위한 굴착만이 필요하므로, 지중에 본기둥 설치를 위한 굴착공의 형성을 위한 공사가 생략되고 아울러 비교적 소규모의 저가 장비만을 사용하면 되므로 공사 기간 및 공사 비용을 절감할 수 있다. 예컨대, 대구경의 지반 천공을 위한 RCD(Riverse Circulation Drill) 공법 또는 PRD(Percussion Rotary Drill) 공법 등의 사용이 필요하지 아니하고 일반적인 DRA(Double Rod Auger) 장비와 같은 소규모 장비를 사용하여 시공할 수 있기 때문에 공사 기간 및 공사 비용의 절감이 달성될 수 있다.Accordingly, when excavating the ground for the first time and installing the temporary pillars, only excavation for the installation of the embedded pile, which is a relatively small diameter temporary pillar, is required, so that construction for the formation of the excavation hole for the installation of the main pillar in the ground is omitted. Only a relatively low cost of equipment can be used to reduce construction period and construction costs. For example, since it does not require the use of a reverse circulation drill (RCD) method or a percussion rotary drill (PRD) method for drilling a large diameter ground, it can be constructed using small equipment such as general double rod auger (DRA) equipment. Reduction of construction period and construction cost can be achieved.

또한, 상기 가설 기둥으로서 매입말뚝을 사용하기 때문에, 매입말뚝 외에 별도의 가설 기둥의 설치가 필요하지 아니하여 공사가 더욱 간편히 진행될 수 있다. 또한, 상기 매입말뚝은 공사 완료 단계에서 제거되기 때문에, 본기둥과 달리 필요에 따라서 하나만이 아니라 수개 설치될 수 있으므로, 본기둥의 수에 구애받지 아니하고 상황에 따라서 임의의 수의 가설 기둥이 마련될 수 있다. 즉, 지반의 상태, 지하층 규모, 상층의 높이 등 여러 요인에 따라 가설 기둥으로서 임의의 수의 매입말뚝이 설치될 수 있다. 예컨대, 지반의 상태에 따라서 견고한 지반의 경우 적은 수의 매입말뚝만 설치함도 가능하며, 또는 연약한 지반의 경우에는 다수의 매입말뚝이 설치될 수 있다. 따라서, 상황에 따라 가설 기둥의 수를 조절함으로써 유연한 공사 운영이 가능하며, 신뢰성있고 비용이 절감된 기초 공사를 진행할 수 있다. In addition, since the use of the embedded pile as the temporary pillar, the construction can be carried out more simply because it is not necessary to install a separate temporary pillar in addition to the embedded pile. In addition, since the purchase pile is removed at the completion stage of construction, unlike the main column, only one may be installed as needed, so that any number of temporary columns may be provided depending on the situation regardless of the number of the main pillar. Can be. In other words, any number of embedded piles may be installed as temporary columns depending on various factors such as the condition of the ground, the basement level, and the height of the upper floor. For example, depending on the condition of the ground, it is possible to install only a small number of embedded piles in the case of solid ground, or in the case of soft ground, a plurality of embedded piles may be installed. Therefore, flexible construction operation is possible by adjusting the number of temporary columns according to the situation, and reliable and cost-saving foundation construction can be carried out.

또한, 바람직하게는, 상술한 바와 같이 가설 기둥으로 사용되는 매입말뚝은 단순 콘크리트 말뚝이 아닌 그라우팅 강관 파일로 구성되므로, 일반적인 콘크리트 기둥과 달리 별도의 철근 배근과 같은 작업이 필요없이 그라우팅만으로 형성되어 형성이 용이하며 신뢰성이 더욱 향상될 수 있다. 또한, 매입말뚝은 원형 단면을 가짐에 따라서 전방위 지지력을 용이하게 확보할 수 있으며, 하단부에 선단보강판, 굴착용 보강판, 및 위치결정편을 포함하여 구성됨에 따라서 매입말뚝 및 그를 이용한 가설 기둥의 설치가 더욱 용이해질 수 있다. 또한, 매입말뚝의 하단부에 마련된 선단보강판이 매입말뚝의 기저부에 구비됨에 따라서, 가설 기둥의 설치 및 지지가 더욱 신뢰성있게 이루어질 수 있다.In addition, the buried pile used as a temporary pillar as described above is composed of a grouting steel pipe pile, not a simple concrete pile, unlike the general concrete pillars are formed by forming only grouting without the need for a separate reinforcement such as reinforcement It is easy and the reliability can be further improved. In addition, the embedded pile has a circular cross-section can easily secure the omni-directional support force, and the lower end portion includes a tip reinforcement plate, excavation reinforcement plate, and positioning pieces in the lower end of the embedded pile and the temporary column using the same Installation can be easier. In addition, since the tip reinforcing plate provided on the lower end of the embedded pile is provided at the base of the embedded pile, the installation and support of the temporary pillar can be made more reliable.

또한, 매입말뚝에 고정되는 브라켓이 마련됨에 따라서, 매입말뚝의 좌굴을 방지하고, 거더, 및 본기둥과 같은 골조의 타설을 보조하여 공사의 신뢰성 및 안정성이 더욱 개선될 수 있다.In addition, as the bracket fixed to the embedding pile is provided, it is possible to prevent the buckling of the embedding pile and assist in placing the frame such as the girder and the main pillar to further improve the reliability and stability of the construction.

도 1 은 본 발명의 매입말뚝을 이용한 기초 공법에 사용되는 매입말뚝을 나타낸 도면이다.
도 2 는 본 발명의 매입말뚝을 이용한 기초 공법에 사용되는 매입말뚝을 나타낸 도면이다.
도 3 은 본 발명의 매입말뚝을 이용한 기초 공법에 사용되는 매입말뚝을 나타낸 도면이다.
도 4 는 본 발명의 매입말뚝을 이용한 기초 공법에 사용되는 매입말뚝을 나타낸 도면이다.
도 5 는 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
도 6 은 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
도 7 은 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
도 8 은 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
도 9 는 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
도 10 은 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
도 11 은 본 발명에 따른 매입말뚝을 이용한 기초 공법에 사용되는 브라켓을 나타낸 도면이다.
도 12 는 본 발명에 따른 매입말뚝을 이용한 기초 공법에 사용되는 브라켓을 나타낸 도면이다.
도 13 은 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
도 14 는 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
도 15 는 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이다.
1 is a view showing a buried pile used in the foundation method using the buried pile of the present invention.
Figure 2 is a view showing the embedded pile used in the foundation method using the embedded pile of the present invention.
3 is a view showing the embedded pile used in the foundation method using the embedded pile of the present invention.
Figure 4 is a view showing the embedded pile used in the foundation method using the embedded pile of the present invention.
5 is a view showing a basic construction method using the embedded pile according to the present invention.
6 is a view showing a basic construction method using the embedded pile according to the present invention.
7 is a view showing a basic construction method using the embedded pile according to the present invention.
8 is a view showing a basic construction method using the embedded pile according to the present invention.
9 is a view showing the basic construction method using the embedded pile according to the present invention.
10 is a view showing a basic construction method using the embedded pile according to the present invention.
11 is a view showing a bracket used in the foundation method using the embedded pile according to the present invention.
12 is a view showing a bracket used in the foundation method using the embedded pile according to the present invention.
13 is a view showing a basic construction method using the embedded pile according to the present invention.
14 is a view showing a basic construction method using the embedded pile according to the present invention.
15 is a view showing a basic construction method using the embedded pile according to the present invention.

본 발명의 이점 및 특징, 그리고 그것들을 달성하는 방법은 첨부되는 도면과 함께 상세하게 후술되어 있는 실시예들을 참조하면 명확해질 것이다. 그러나 본 발명은 이하에서 개시되는 실시예들에 한정되는 것이 아니라 서로 다른 다양한 형태로 구현될 수 있으며, 단지 본 실시예들은 본 발명의 개시가 완전하도록 하고, 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 발명의 범주를 완전하게 알려주기 위해 제공되는 것이며, 본 발명은 청구항의 범주에 의해 정의될 뿐이다. 명세서 전체에 걸쳐 동일 참조 부호는 동일 구성 요소를 지칭한다.Advantages and features of the present invention, and methods of achieving the same will become apparent with reference to the embodiments described below in detail in conjunction with the accompanying drawings. The present invention may, however, be embodied in many different forms and should not be construed as limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the invention to those skilled in the art. To fully disclose the scope of the invention to those skilled in the art, and the invention is only defined by the scope of the claims. Like reference numerals refer to like elements throughout.

공간적으로 상대적인 용어인 "아래(below)", "아래(beneath)", "하부(lower)", "위(above)", "상부(upper)" 등은 도면에 도시되어 있는 바와 같이 하나의 부재 또는 구성 요소들과 다른 소자 또는 구성 요소들과의 상관관계를 용이하게 기술하기 위해 사용될 수 있다. 공간적으로 상대적인 용어는 도면에 도시되어 있는 방향에 더하여 사용시 또는 동작 시 부재의 서로 다른 방향을 포함하는 용어로 이해되어야 한다. 예를 들면, 도면에 도시되어 있는 방향은 기준에 따라서 "상방향" 및 "하방향" 으로 해석될 수 있다. 따라서, 예시적인 용어인 "상하"는 좌우 방향을 모두 포함할 수 있다. 부재는 다른 방향으로도 배향될 수 있고, 이에 따라 공간적으로 상대적인 용어들은 배향에 따라 해석될 수 있다.The spatially relative terms " below ", " beneath ", " lower ", " above ", " upper " It can be used to easily describe the correlation of a member or component with other elements or components. Spatially relative terms should be understood to include, in addition to the orientation shown in the drawings, terms that include different orientations of members during use or operation. For example, the direction shown in the figures can be interpreted as "upward" and "downward" according to a reference. Thus, the exemplary terms "up" and " up & down " The member can also be oriented in other directions, so that spatially relative terms can be interpreted according to the orientation.

본 명세서에서 사용된 용어는 실시예들을 설명하기 위한 것이며 본 발명을 제한하고자 하는 것은 아니다. 본 명세서에서, 단수형은 문구에서 특별히 언급하지 않는 한 복수형도 포함한다. 명세서에서 사용되는 "포함한다(comprises)" 및/또는 "포함하는(comprising)"은 언급된 구성요소, 단계, 동작 및/또는 부재는 하나 이상의 다른 구성요소, 단계, 동작 및/또는 부재의 존재 또는 추가를 배제하지 않는다.The terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of the invention. In the present specification, the singular form includes plural forms unless otherwise specified in the specification. &Quot; comprises, "and / or" comprising ", as used herein, unless the recited element, step, operation and / Or additions.

다른 정의가 없다면, 본 명세서에서 사용되는 모든 용어(기술 및 과학적 용어를 포함)는 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 공통적으로 이해될 수 있는 의미로 사용될 수 있을 것이다. 또 일반적으로 사용되는 사전에 정의되어 있는 용어들은 명백하게 특별히 정의되어 있지 않은 한 이상적으로 또는 과도하게 해석되지 않는다.Unless otherwise defined, all terms (including technical and scientific terms) used in the present specification may be used in a sense that can be commonly understood by those skilled in the art. Also, commonly used predefined terms are not ideally or excessively interpreted unless explicitly defined otherwise.

도면에서 각 부재의 두께나 크기는 설명의 편의 및 명확성을 위하여 과장되거나 생략되거나 또는 개략적으로 도시되었다. 또한 각 구성요소의 크기와 면적은 실제크기나 면적을 전적으로 반영하는 것은 아니다. In the drawings, the thickness or size of each member is exaggerated, omitted, or schematically illustrated for convenience and clarity of description. Also, the size and area of each component do not entirely reflect actual size or area.

또한, 실시예에서 본 발명의 구조를 설명하는 과정에서 언급하는 각도와 방향은 도면에 기재된 것을 기준으로 한다. 명세서에서 본 발명을 이루는 구조에 대한 설명에서, 각도에 대한 기준점과 위치관계를 명확히 언급하지 않은 경우, 관련 도면을 참조하도록 한다.In addition, the angle and direction mentioned in the process of demonstrating the structure of this invention in the Example are based on what was described in drawing. In the description of the structure constituting the present invention in the specification, reference points and positional relationship with respect to angles are not explicitly referred to, reference is made to the relevant drawings.

도 1 내지 도 4 는 본 발명에 따른 매입말뚝을 이용한 기초 공법에 사용되는 매입말뚝(100)을 나타낸 도면이다.1 to 4 is a view showing the embedded pile 100 used in the foundation method using the embedded pile according to the present invention.

도 1 내지 도 4 를 참조하면 본 발명에 따른 매입말뚝을 이용한 기초 공법에 사용되는 매입말뚝(100)은, 매입말뚝공법에 사용되는 매입말뚝으로서, 그라우팅액이 통과하도록 하단부의 내외주면을 관통하여 그라우팅액홀(11)이 형성되며 저면이 개방된 중공형의 파일(10)과, 상기 파일(10)의 하단부가 안착되는 안착부(21)와 상기 안착부(21)의 가장자리로부터 상측으로 연장되는 연장부(22)를 갖는 선단보강판(20)을 포함한다. 1 to 4, the embedded pile 100 used in the foundation method using the embedded pile according to the present invention, the embedded pile used in the embedded pile method, penetrating through the inner and outer peripheral surface of the lower end to allow the grouting liquid to pass through Grouting liquid hole 11 is formed and the bottom of the hollow pile (10), the lower end of the pile 10 is seated portion 21 and extending from the edge of the seating portion 21 A tip reinforcing plate 20 having an extension portion 22 is included.

상기 파일(10)은 중공(12)을 갖는 원통형으로 형성되며, 상단부는 개방되고 하단부 저면은 개방되어 있다. 파일(10)의 하단부에는 내외주면을 관통하여 형성된 그라우팅액홀(11)이 형성된다.The pile 10 is formed in a cylindrical shape having a hollow 12, and the upper end is open and the lower end is open. The grouting liquid hole 11 formed through the inner and outer peripheral surfaces is formed at the lower end of the pile 10.

상기 그라우팅액홀(11)은 상기 파일(10)의 중공(12)을 통하여 그라우팅액이 주입되어 그라우팅될 때, 그 하단부에서 굴착공 측으로 그라우팅액을 배출시키기 위해서 마련된다. The grouting liquid hole 11 is provided to discharge the grouting liquid from the lower end portion to the excavation hole side when the grouting liquid is injected and grouted through the hollow 12 of the pile 10.

상기 선단보강판(20)은 철재와 같은 강성을 갖는 재질로 이루어지는 것으로, 파일(10)의 하단부의 강성을 증가시켜 파일(10)이 굴착공에 삽입되어 경타될 때 관입성을 향상시키고, 그라우팅시 그라우팅을 용이하게 하고 양질의 그라우팅을 수행하며, 그라우팅된 파일(10)의 지지력을 향상시키기 위해서 마련된 것이다. The tip reinforcing plate 20 is made of a material having the same rigidity as the steel, to increase the stiffness of the lower end of the pile 10 to improve the penetration when the pile 10 is inserted into the excavation hole, and grouting, grouting In order to facilitate grouting, to perform good grouting, and to improve the bearing capacity of the grouted pile 10.

도 1 에 도시된 바와 같이, 본 발명의 일 실시예에 따른 선단보강판(20)은 파일(10)의 하단부가 안착되는 안착부(21)와, 상기 안착부(21)로부터 상측으로 연장되는 연장부(22)를 포함한다. As shown in FIG. 1, the tip reinforcing plate 20 according to the exemplary embodiment of the present invention extends upwardly from the seating portion 21 on which the lower end of the pile 10 is seated, and the seating portion 21. And an extension 22.

본 실시예에서 상기 연장부(22)에는 그 둘레방향을 따라 복수의 제1 관통공(23)이 형성된다. 상기 제1 관통공(23)은 파일(10)의 중공(12)을 통하여 주입된 그라우팅액이 파일(10)의 하단부에서 흘러나갈 때 굴착공의 내주면을 향하여 고르게 그라우팅액이 분산되도록 하며, 그라우팅액의 주입압력을 증가시켜 그라우팅액의 확산속도를 향상시킨다. 한편, 도 2 에 따른 선단보강판(20)은 안착부(21)에 제2 관통공(24)이 형성될 수 있다. 파일(10)의 저면으로 확산된 그라우팅액은, 상기 제2 관통공(24)에 의해 노출되는 파일(10)의 저면과 굴착공의 저면 사이에도 채워져 파일(10)의 지지력을 향상시킨다.In the present embodiment, the plurality of first through holes 23 are formed in the extension part 22 along the circumferential direction thereof. The first through hole 23 allows the grouting liquid to be evenly distributed toward the inner circumferential surface of the excavation hole when the grouting liquid injected through the hollow 12 of the pile 10 flows out from the lower end of the pile 10. Increase the injection pressure of the liquid to improve the diffusion speed of the grouting liquid. Meanwhile, the front reinforcement plate 20 according to FIG. 2 may have a second through hole 24 formed in the seating part 21. The grouting liquid diffused to the bottom of the pile 10 is also filled between the bottom of the pile 10 exposed by the second through hole 24 and the bottom of the drilling hole to improve the bearing force of the pile 10.

도 1 및 도 2 에 도시된 바와 같이, 상기 연장부(22)는 파일(10)의 하단부 외주면과 이격되어 있다. 이에 따라, 연장부(22)의 내주면과 파일(10)의 하단부 외주면 사이에도 그라우팅액이 채워져 파일(10)의 강성을 증가시키게 된다.As shown in FIGS. 1 and 2, the extension part 22 is spaced apart from the outer peripheral surface of the lower end of the pile 10. Accordingly, the grouting liquid is also filled between the inner circumferential surface of the extension portion 22 and the lower circumferential surface of the lower portion of the pile 10 to increase the rigidity of the pile 10.

또한, 상기 연장부(22)는 상측으로 갈수록 상기 안착부(21)의 중심으로부터 멀어지도록 경사지게 형성된다. 상기 연장부(22)가 상측으로 갈수록 굴착공의 내주면에 근접하도록 경사지게 형성됨으로써, 그라우팅시 굴착공의 저면에 위치한 흙 입자 등이 그라우팅액에 의해 굴착공의 상부 측으로 이동되는 것을 방지하게 되어, 그라우팅시 불필요한 흙 입자 등의 혼입을 방지하여 양질의 그라우팅을 가능케 한다. In addition, the extension portion 22 is formed to be inclined away from the center of the seating portion 21 toward the upper side. As the extension part 22 is formed to be inclined closer to the inner circumferential surface of the excavation hole toward the upper side, grouting prevents dirt particles, etc. located at the bottom of the excavation hole from being moved to the upper side of the excavation hole by the grouting liquid. It prevents the incorporation of unnecessary soil particles and enables high quality grouting.

한편, 본 발명에 따른 매입말뚝(100)은 굴착용 보강판(30)를 더 구비할 수 있다. 상기 굴착용 보강판(30)은 파일(10)의 경타시 관입성을 향상시키기 위해서 마련된 것으로, 안착부(21)의 저면으로부터 하측방향으로 돌출 형성된다.On the other hand, the embedded pile 100 according to the present invention may further include an excavation reinforcement plate (30). The excavation reinforcing plate 30 is provided to improve the penetration of the pile 10, the protrusion 10 is formed to protrude downward from the bottom of the seating portion (21).

한편, 상기 굴착용 보강판(30)은 도 3 및 도 4 에 도시된 바에 한정하지 아니하며, 하측으로 갈수록 뾰족하게 경사지게 형성되거나 또는 임의의 형상을 가질 수 있으며, 파일(10)의 관입성을 향상시키도록 구성되고 구체적으로 제1 보강판(32)과, 제2 보강판(34)으로 구성될 수 있다.On the other hand, the excavation reinforcing plate 30 is not limited to the bar shown in Figures 3 and 4, it may be formed to be inclined sharply toward the lower side or have an arbitrary shape, improve the penetration of the pile 10 It may be configured to specifically be composed of a first reinforcing plate 32, and a second reinforcing plate (34).

상기 제1 보강판(32)은 안착부(21)의 중심을 가로지르도록 결합되고, 제2 보강판(34) 또한 상기 제1 보강판(32)과 마찬가지로, 상기 안착부(21)의 중심을 가로지르도록 결합된다. 상기 제1 보강판(32)과 제2 보강판(34)은 안착부(21)의 중심에서 교차한다. 도 4 는, 안착부(21)의 중심에 제2 관통공(24)이 형성된 상태에서, 상기 굴착용 보강판(30)이 결합된 상태의 저면을 도시한 것이다. 물론, 안착부(21)에 제2 관통공(24)이 형성되지 않은 상태로, 상기 굴착용 보강판(30)을 결합시키는 것 또한 가능하다. The first reinforcement plate 32 is coupled to cross the center of the seating portion 21, and the second reinforcement plate 34 is also the center of the seating portion 21, similarly to the first reinforcement plate 32. Are combined to cross. The first reinforcement plate 32 and the second reinforcement plate 34 intersect at the center of the seating portion 21. FIG. 4 illustrates a bottom of the excavation reinforcement plate 30 in a state in which the second through hole 24 is formed at the center of the seating portion 21. Of course, it is also possible to combine the excavation reinforcement plate 30 in a state in which the second through hole 24 is not formed in the seating part 21.

파일(10)의 하단부를 선단보강판(20)의 안착부(21)에 용이하게 안착시키기 위해서 위치결정편(40)이 마련될 수 있다. 상기 위치결정편(40)은 파일(10)의 하단부가 정위치되도록 선단보강판(20)의 연장부(22)의 내주면 둘레를 따라 이격되어 결합된다. 본 실시예에서 상기 위치결정편(40)은 연장부(22)의 둘레방향을 따라서 일정간격 이격되어 4개가 배치되어 있다. 물론 그 갯수 및 이격거리를 다양하게 변경 가능하다.The positioning piece 40 may be provided to easily seat the lower end of the pile 10 on the seating portion 21 of the tip reinforcing plate 20. The positioning pieces 40 are spaced apart and coupled along the circumference of the inner circumferential surface of the extension portion 22 of the tip reinforcing plate 20 so that the lower end portion of the pile 10 is fixed. In the present embodiment, four positioning pieces 40 are arranged at regular intervals along the circumferential direction of the extension part 22. Of course, the number and separation distance can be variously changed.

상기 위치결정편(40)들 사이에 정위치된 파일(10)은 굴착공 내에 삽입되어 굴착공의 내주면과 일정거리 이격된 상태로 배치되게 되며, 이후 그라우팅시 그라우팅액이 파일(10)의 외주면과 굴착공의 내주면에 정량적으로 채워져 양질의 그라우팅을 가능케 한다.The pile 10 positioned between the positioning pieces 40 is inserted into the excavation hole so that the pile 10 is spaced apart from the inner circumferential surface of the excavation hole by a predetermined distance. Then, when grouting, the grouting liquid is the outer circumferential surface of the pile 10. And quantitatively filled in the inner circumferential surface of the excavation hole to enable high quality grouting.

이하, 상기와 같은 구성에 따른 매입말뚝을 이용한 매입말뚝을 이용한 기초 공법에 관해 도면을 참조하여 상세히 설명한다.Hereinafter, with reference to the drawings with respect to the foundation method using the embedded pile using the embedded pile according to the above configuration will be described in detail.

도 5 내지 도 13 은 본 발명에 따른 매입말뚝을 이용한 기초 공법 순서를 나타낸 도면이며, 이중 도 11 및 도 12 는 본 발명에 따른 매입말뚝을 이용한 기초 공법에 사용되는 브라켓을 나타낸 도면이다.5 to 13 is a view showing the basic construction method using the embedded pile according to the present invention, Figure 11 and Figure 12 is a view showing the bracket used in the basic method using the embedded pile according to the present invention.

먼저, 도 5 를 참조하면, 지면에 대해 흙막이 공사를 진행한다. 흙막이 공사는 지하 터파기 시 주위 토사가 붕괴하는 것을 방지하기 위하여 지하층의 외부 경계측에 소정의 흙막이 벽(210)과 같은 구조물을 설치함으로써 이루어진다. 이와 같은 흙막이 공사는 CIP, SCW, 슬러리 월, 토류판 등과 같은 부재를 사용하여 일반적인 가설 흙막이 공법 중에서 현장 상황에 맞추어 적절한 공법을 선정하여 실시할 수 있다. First, referring to Figure 5, the earthwork construction proceeds to the ground. The clogging construction is performed by installing a structure such as a predetermined barrier wall 210 on the outer boundary side of the basement layer to prevent the surrounding soil from collapsing during the underground trench. Such a clogging construction can be carried out by selecting a suitable construction method according to the site situation from the general temporary clogging construction method using members such as CIP, SCW, slurry wall, earth plate.

다음으로, 도 6 에 따라서 지반에 매입말뚝(100)을 설치하기 위한 굴착공을 형성하기 위해 지반을 굴착한다. 이때, 굴착공의 형성은 오거(auger)와 같은 소정의 굴착 장치(220)를 이용해 이루어질 수 있다. 이때 굴착공의 형성은 도 6 에 도시된 바와 같이 복수일 수 있으며, 이에 한정하지 않는다.Next, the ground is excavated to form an excavation hole for installing the embedded pile 100 in accordance with FIG. At this time, the formation of the excavation hole may be made using a predetermined excavation device 220 such as an auger. In this case, the formation of the excavation hole may be plural as shown in FIG. 6, but is not limited thereto.

다음으로, 도 7 에 도시된 바와 같이 상기 굴착공에 매입말뚝(100)을 설치하며 그라우팅 공정을 진행한다.Next, as shown in Figure 7, install the pile 100 in the excavation hole and proceeds the grouting process.

오거와 같은 굴착 장치(220)를 통한 굴착 후 상기 굴착 장치(220)를 굴착공에서 빼낸 다음 매입말뚝(100)을 삽입하며, 매입말뚝(100)의 하단부가 굴착공의 저면에 밀착되도록 소정의 경타기를 이용하여 매입말뚝(100)의 상단부를 경타할 수 있다.After excavation through an excavation device 220 such as an auger, the excavation device 220 is removed from the excavation hole, and then the insertion pile 100 is inserted, and the lower end of the embedment pile 100 is in close contact with the bottom surface of the excavation hole. Using the putter can be swung the upper end of the embedded pile 100.

이때, 매입말뚝(100)은 상술한 바와 같은 파일(10)의 하단부에 선단보강판(20)이 마련된 매입말뚝(100)을 사용할 수 있다. 파일(10)의 하단부에 결합된 선단보강판(20)에 의해 파일(10)의 관입성이 증대되고, 선단보강판(20)의 연장부(22)에 의해 굴착공 내부의 흙 입자가 상기 연장부(22)의 상측으로 과도하게 혼입되는 것이 방지된다.In this case, the embedded pile 100 may use the embedded pile 100 provided with the tip reinforcing plate 20 at the lower end of the pile 10 as described above. Penetration of the pile 10 is increased by the tip reinforcing plate 20 coupled to the lower end of the pile 10, and the soil particles inside the excavation hole are extended by the extension part 22 of the tip reinforcing plate 20. Excessive mixing into the upper side of the extension part 22 is prevented.

이어서, 파일(10)의 중공(12)을 통하여 그라우팅액을 주입한다. 상기 그라우팅액은 파일(10)의 중공(12)에 채워지면서 하단부에 형성된 그라우팅액홀(11)을 통하여 파일(10) 외부로 흘러나간다. 이와 같은 과정을 통해, 그라우팅액은 굴착공의 하부로부터 상부로 상승하면서 채워지게 된다. Then, the grouting liquid is injected through the hollow 12 of the pile 10. The grouting liquid flows out of the pile 10 through the grouting liquid hole 11 formed at the lower end while being filled in the hollow 12 of the pile 10. Through this process, the grouting liquid is filled while rising from the bottom of the drilling hole to the top.

이때, 그라우팅액은 연장부(22)의 제1 관통공(23)을 통하여 굴착공 의 내주면 측으로 고르게 분산된다. 따라서, 연장부(22)의 경사면 하측에도 그라우팅액이 채워지게 된다. At this time, the grouting liquid is evenly distributed to the inner peripheral surface side of the excavation hole through the first through hole 23 of the extension portion 22. Therefore, the grouting liquid is also filled below the inclined surface of the extension part 22.

이어서, 도 8 에 도시된 바와 같이 초기 터파기 공정을 수행한다. 이때, 초기 터파기 공사는 필요 이상 깊이 굴착함이 없이, 지상 1 층 바닥 철골 거더 및 슬래브 구조체와 같은 골조를 설치할 수 있을 정도의 깊이만큼 굴착하는 것도 가능하다.Subsequently, as shown in FIG. 8, an initial destruction process is performed. At this time, the initial excavation work can be excavated to the depth enough to install a framework such as ground floor steel frame girders and slab structures without deep excavation more than necessary.

이어서, 도 9 에 도시된 바와 같이 지상 1 층 골조 공사를 진행한다.Subsequently, as shown in FIG. 9, a ground-floor framework construction is performed.

흙막이 벽(210)과 매입말뚝(100) 사이 및 매입말뚝(100)과 매입말뚝(100) 사이에 거더(240)와 같은 부재들을 설치함으로써 골조 공사가 진행된다. 여기서, 상기 거더(240)는 지하층의 시공 중 흙막이 벽(210)으로부터 가해지는 토압을 지지하는 스트러트(strut)와 같은 역할을 하며, 지하 공사의 완료 후에는 해체되지 않고 영구 구조물로서 상부로부터 가해지는 연직하중을 지지하여 기둥으로 전달하는 역할을 할 수 있다. Frame construction is performed by installing members such as girder 240 between the retaining wall 210 and the embedded pile 100 and between the embedded pile 100 and the embedded pile 100. Here, the girder 240 serves as a strut supporting the earth pressure applied from the earth wall 210 during the construction of the basement layer, and is applied from the top as a permanent structure without being dismantled after completion of the underground construction. It can support the vertical load and transfer it to the column.

한편, 도 9 에 도시된 바와 같이, 복수의 매입말뚝(100) 사이에 좌굴을 방지하고 거더(240)를 지지하며 거더(240) 및 본기둥과 같은 골조 설치를 보조하기 위해서 소정의 브라켓(230)이 설치될 수 있다. Meanwhile, as shown in FIG. 9, a predetermined bracket 230 is provided to prevent buckling between the plurality of embedded piles 100, to support the girder 240, and to assist the frame installation such as the girder 240 and the main pillar. ) Can be installed.

한편, 도 10 에 도시된 바와 같이, 지상 1 층 골조 공사가 이루어진 후에 상기 브라켓(230)은 지하 1층 골조를 형성하는 거더(미도시)를 지지하도록 지하 1 층 높이로 하강할 수 있다.On the other hand, as shown in Figure 10, after the ground-floor frame construction is completed, the bracket 230 may be lowered to the height of the basement 1 floor to support the girder (not shown) forming the basement 1 floor frame.

예컨대, 도 11 및 도 12 에 도시된 바와 같이, 브라켓(230)은 매입말뚝(100)에 단단히 고정될 수 있으며, 상기 브라켓 상에 상기 거더(240)가 배치될 수 있다. 이때, 브라켓(230)은 지하 각 층의 높이마다 배치될 수 있고, 브라켓(230)의 설치 높이를 조절함에 따라서 각 층의 거더(240)의 높이가 결정될 수 있으며, 복수의 지하층 공사가 진행됨에 따라서 하나의 매입말뚝(100)에 수개의 층을 형성하는 복수의 브라켓(230)이 설치될 수 있다.For example, as shown in FIGS. 11 and 12, the bracket 230 may be firmly fixed to the embedded pile 100, and the girder 240 may be disposed on the bracket. At this time, the bracket 230 may be arranged for each height of each basement floor, the height of the girder 240 of each floor may be determined by adjusting the installation height of the bracket 230, a plurality of basement construction is in progress Therefore, a plurality of brackets 230 forming several layers may be installed in one embedment pile 100.

즉, 각 층의 거더(240)는 상기 브라켓(230)에 의해서 지지되고 연결될 수 있으며, 또한 후술하는 본기둥(250)은 상기 매입말뚝(100)과 매입말뚝(100) 사이에 배치되거나 또는 상기 매입말뚝(100) 주위에 본기둥(250)이 배치됨에 따라서 상기 브라켓(230)은 골조의 타설을 보조할 수 있다.That is, the girder 240 of each layer may be supported and connected by the bracket 230, and the main pillar 250 to be described later is disposed between the embedded pile 100 and the embedded pile 100 or the As the main pillar 250 is disposed around the embedded pile 100, the bracket 230 may assist in placing the frame.

아울러, 브라켓(230)은 매입말뚝(100)에 고정되고 매입말뚝(100)이 서로 소정의 간격을 유지하게 지지함에 따라서 매입말뚝(100)의 좌굴을 방지할 수 있다. 이에 따라서, 브라켓(230)은 좌굴 방지 및 골조타설을 보조하는 기능을 가질 수 있다.In addition, the bracket 230 is fixed to the embedded pile 100 and the support pile 100 to prevent the buckling of the embedded pile 100 to support to maintain a predetermined distance from each other. Accordingly, the bracket 230 may have a function of assisting buckling prevention and framing.

다음으로, 도 13 및 도 14 에 도시된 바와 같이 기초 레벨(L)에 이르기까지 추가적인 터파기 및 지하층의 거더(240)와 같은 골조 배치 공사를 완료한다. 이때, 각 층의 골조 공사가 완료되며, 복수의 매입말뚝(100) 사이에 본기둥(250)이 배치될 수 있다. 본기둥(250)은 예컨대 도 13 에 도시된 바와 같이 상기 매입말뚝(100)에 인접한 부분에 기둥 철근(P)을 배근하고, 이어서 도 14 에 도시된 바와 같이 상기 배근된 철근(P)에 콘크리트를 타설하여 형성될 수 있으며, 이에 한정하지 않는다. 한편, 상술한 바와 같이 매입말뚝(100) 사이에 브라켓(230)이 설치되며 상기 브라켓(230)은 거더(240) 및 본기둥(250)과 같은 골조의 타설을 보조할 수 있다.Next, as shown in FIG. 13 and FIG. 14, the frame arrangement work such as additional trenches and basement girder 240 up to the foundation level L is completed. At this time, frame construction of each floor is completed, the main column 250 may be disposed between the plurality of embedded pile 100. Main pillar 250 is for example to reinforce the column reinforcement (P) to the portion adjacent to the buried pile 100 as shown in Figure 13, and then to the reinforced reinforcement (P) as shown in Figure 14 It can be formed by pouring, but is not limited thereto. On the other hand, as described above, the bracket 230 is installed between the embedded pile 100, the bracket 230 may assist in placing the frame such as the girder 240 and the main column 250.

바람직하게는, 도 13 및 도 14 에 도시된 바와 같이, 본기둥(250)은 매입말뚝(100) 사이에 배치될 수 있으며, 따라서 본기둥 설치 공사 과정에서 공사 안전성 및 신뢰성이 더욱 향상될 수 있다.Preferably, as shown in FIGS. 13 and 14, the main pillar 250 may be disposed between the embedded pile 100, and thus, construction safety and reliability may be further improved during the main pillar installation construction process. .

이때, 매입말뚝(100)은 기초 레벨(L)보다 깊이 매설됨으로써, 최저층 바닥면까지 터파기를 진행하고 본기둥(250)이 아직 배치되지 않은 상태에서도 매입말뚝(100)은 가설기둥으로서 지하층 골조를 지지하고 유지할 수 있다. 한편, 슬라브 배치 전에 무근 콘크리트로 형성된 기초 파일 캡(pile cap)(260)이 마련될 수 있다.At this time, the embedding pile 100 is embedded deeper than the foundation level (L), so that the burrow to the bottom of the bottom floor, and even when the main pillar 250 is not yet placed, the embedding pile 100 is a temporary pillar to build the basement frame. Support and maintain. Meanwhile, a foundation pile cap 260 formed of plain concrete before slab arrangement may be provided.

이어서, 도 15 에 도시된 바와 같이, 기초 레벨(L)보다 하부에 매설된 매입말뚝(100)의 기초 레벨(L)보다 상부로 연장된 상단부를 절단하여 제거하고, 마무리 공사를 진행한다. Subsequently, as shown in FIG. 15, the upper end portion extending upward from the foundation level L of the embedded pile 100 embedded below the foundation level L is cut and removed, and the finishing work is performed.

이때, 매입말뚝(100)은 최저층 바닥면인 기초 레벨(L)보다 깊이 매설됨으로써, 기초 레벨 상에서 매입말뚝(100)을 절단하여도 매입말뚝(100)의 하단부가 매설된 상태로 유지될 수 있다. 즉, 매입말뚝(100)은 기초 레벨(L) 하부에 매설된 부분의 상부 부분을 절단하여 제거할 수 있다. In this case, the embedded pile 100 is embedded deeper than the foundation level (L), which is the bottom floor, so that the lower end portion of the embedded pile 100 may be maintained even when the embedded pile 100 is cut on the foundation level. . That is, the embedding pile 100 may be removed by cutting the upper portion of the portion buried below the foundation level (L).

기존의 탑다운 공법에서는 지하 구조체 형성 전에 본기둥(250)을 설치하는 반면에, 본 발명에서는 구조물의 구축 단계에서 본기둥(250)이 전체 설계하중을 받기 전에 일단 소구경의 매입말뚝(100)을 설치하여 거더(240), 슬래브 등 지하 바닥 구조체 구축을 위한 가설용 임시 기둥으로 이용한 다음, 지하 구조체가 완성된 이후 상기와 같이 영구 구조물로서 본기둥(250)을 설치한다.In the existing top-down method, the main pillar 250 is installed before the underground structure is formed, whereas in the present invention, the main pillar 250 is once embedded in the small diameter before receiving the total design load in the construction stage of the structure. After installing the girder 240, used as a temporary pillar for the construction of a basement floor structure, such as slabs, and then the base structure 250 is installed as a permanent structure as described above after the underground structure is completed.

이에 따라서, 처음 지반을 굴착하고 가설 기둥을 설치할 때 비교적 소구경의 가설 기둥인 매입말뚝(100)의 설치를 위한 굴착만이 필요하므로, 지중에 본기둥(250) 설치를 위한 굴착공의 형성을 위한 공사 규모가 작아지고 아울러 비교적 소규모의 저가 장비만을 사용하면 되므로 공사 기간 및 공사 비용을 절감할 수 있다. 예컨대, 본기둥(250) 설치를 위해서 대구경의 지반 천공을 위한 RCD(Riverse Circulation Drill) 공법 또는 PRD(Percussion Rotary Drill) 공법 등의 사용이 필요하지 아니하고 일반적인 DRA(Double Rod Auger) 장비와 같은 소규모 장비를 사용하여 시공할 수 있기 때문에 공시 기간 및 공사 비용의 절감이 달성될 수 있다.Accordingly, when excavating the ground for the first time and install the temporary pillar, only excavation for the installation of the embedded pile 100, which is a relatively small diameter temporary pillar, is necessary, thus forming the excavation hole for installing the main pillar 250 in the ground. In addition, the construction time for the construction is reduced, and the use of relatively small, low-cost equipment can reduce construction period and construction costs. For example, the installation of the main column 250 does not require the use of a reverse circulation drill (RCD) method or a percussion rotary drill (PRD) method for drilling a large diameter ground, and a small equipment such as a general double rod auger (DRA) device. Since construction can be carried out using the construction, the reduction of the disclosure period and the construction cost can be achieved.

또한, 상기 가설 기둥으로서 매입말뚝(100)을 사용하기 때문에, 매입말뚝(100) 외에 별도의 가설 기둥의 설치가 필요하지 아니하여 공사가 더욱 간편히 진행될 수 있다. 또한, 상기 매입말뚝(100)은 공사 완료 단계에서 제거되기 때문에, 본기둥(250)과 달리 필요에 따라서 하나만이 아니라 수개 설치될 수 있으므로, 본기둥의 수에 구애받지 아니하고 상황에 따라서 임의의 수의 가설 기둥이 마련될 수 있다. 즉, 지반의 상태, 지하층 규모, 상층의 높이 등 여러 요인에 따라 가설 기둥으로서 임의의 수의 매입말뚝(100)이 설치될 수 있다. 예컨대, 지반의 상태에 따라서 견고한 지반의 경우 적은 수의 매입말뚝(100)만 설치할 수 있으며, 또는 연약한 지반의 경우에는 다수의 매입말뚝(100)이 설치될 수 있다. 따라서, 상황에 따라 가설 기둥의 수를 조절함으로써 유연한 공사 운영이 가능하며, 신뢰성있고 비용이 절감된 기초 공사를 진행할 수 있다. In addition, since the use of the embedded pile 100 as the temporary pillar, the construction can be carried out more simply because it is not necessary to install a separate temporary pillar in addition to the embedded pile 100. In addition, since the purchase pile 100 is removed at the completion stage of construction, unlike the main column 250, since only one can be installed as needed, depending on the situation, any number depending on the situation regardless of the number of pillars The hypothesis pillar can be provided. That is, any number of embedded piles 100 may be installed as temporary columns according to various factors such as ground conditions, basement floor scales, and heights of upper floors. For example, depending on the state of the ground can be installed only a small number of embedded piles 100 in the case of solid ground, or in the case of soft ground a plurality of embedded piles 100 may be installed. Therefore, flexible construction operation is possible by adjusting the number of temporary columns according to the situation, and reliable and cost-saving foundation construction can be carried out.

또한, 바람직하게는, 상술한 바와 같이 가설 기둥으로 사용되는 매입말뚝(100)은 단순 콘크리트 말뚝이 아닌 그라우팅 강관 파일로 구성되므로, 일반적인 콘크리트 기둥과 달리 별도의 철근 배근과 같은 작업이 필요없이 그라우팅만으로 형성되어 형성이 용이하며 신뢰성이 더욱 향상될 수 있다. 또한, 매입말뚝(100)은 원형 단면을 가짐에 따라서 전방위 지지력을 용이하게 확보할 수 있으며, 하단부에 선단보강판(20), 굴착용 보강판(30), 및 위치결정편(40)을 포함하여 구성됨에 따라서 매입말뚝(100) 및 그를 이용한 가설 기둥의 설치가 더욱 용이해질 수 있다. 또한, 매입말뚝(100)의 하단부에 마련된 선단보강판(20)이 매입말뚝(100)의 기저부에 구비됨에 따라서, 가설 기둥의 설치 및 지지가 더욱 신뢰성있게 이루어질 수 있다.Also, preferably, the embedded pile 100 used as a temporary pillar as described above is composed of grouting steel pipe piles, not simple concrete piles, and thus is formed by grouting without the need for a separate reinforcement, unlike a general concrete pillar. Can be easily formed and the reliability can be further improved. In addition, the embedded pile 100 can easily secure an omnidirectional bearing force as it has a circular cross section, and includes a front end reinforcing plate 20, an excavation reinforcing plate 30, and a positioning piece 40 at the lower end. As it is configured so that the mounting pile 100 and the installation of temporary columns using the same can be more easily. In addition, since the tip reinforcing plate 20 provided at the lower end of the embedded pile 100 is provided at the base of the embedded pile 100, the installation and support of the temporary pillar can be made more reliable.

또한, 매입말뚝(100)에 고정되는 브라켓(230)이 마련됨에 따라서, 매입말뚝(100)의 좌굴을 방지하고, 거더(240), 및 본기둥(250)과 같은 골조의 타설을 보조하여 공사의 신뢰성 및 안정성이 더욱 개선될 수 있다.In addition, as the bracket 230 fixed to the embedding pile 100 is provided, the buckling of the embedding pile 100 is prevented, and the construction is performed by assisting the casting of the frame such as the girder 240 and the main pillar 250. The reliability and stability of the can be further improved.

이상에서는 바람직한 실시예에 대하여 도시하고 설명하였지만, 본 발명은 상술한 특정의 실시예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술분야에서 통상의 지식을 가진자에 의해 다양한 변형실시가 가능한 것은 물론이고, 이러한 변형실시들은 본 발명의 기술적 사상이나 전망으로부터 개별적으로 이해되어져서는 안될 것이다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed exemplary embodiments, but, on the contrary, It should be understood that various modifications may be made by those skilled in the art without departing from the spirit and scope of the present invention.

10: 파일 11: 그라우팅액홀
12: 중공 20: 선단보강판
21: 안착부 22: 연장부
23: 제1 관통공 24: 제2 관통공
30: 굴착용 보강판 32: 제1 보강판
34: 제2 보강판 40: 위치결정편
100: 매입말뚝 210: 흙막이 벽
220: 굴착 장치 230: 브라켓
240: 거더 250: 본기둥
260: 파일 캡
10: File 11: Grouting Hole
12: hollow 20: tip reinforcing plate
21: seating part 22: extension part
23: first through hole 24: second through hole
30: excavation reinforcement plate 32: first reinforcement plate
34: second reinforcing plate 40: positioning piece
100: embedded pile 210: earth wall
220: drilling device 230: bracket
240: girder 250: the pillar
260: file cap

Claims (6)

매입말뚝을 이용한 기초 공법에 있어서,
지중에 흙막이 벽(210)을 설치하는 단계;
본기둥(250)이 배치되는 부위에 굴착 장치(220)를 이용하여 복수의 굴착공을 형성하는 단계;
상기 굴착공에 매입말뚝(100)을 매설하고 상기 매입말뚝(100)을 통해 그라우팅하는 단계;
초기 터파기 공사를 수행하는 단계;
거더(240)를 포함한 지상 1층 골조 배치 공사를 수행하는 단계;
기초 레벨(L)에 이르기까지 추가 터파기 및 지하층 골조 배치 공사를 수행하는 단계;
상기 복수의 매입말뚝(100) 사이에 본기둥(250)을 설치하는 단계; 및
기초 레벨(L)보다 상부로 연장된 상기 매입말뚝(100)의 상단부를 절단하여 제거하는 단계;를 포함하며,
상기 매입말뚝(100)은,
그라우팅액이 통과하도록 하단부의 내외주면을 관통하여 그라우팅액홀(11)이 형성되며, 저면이 개방된 중공형의 파일(10); 및
상기 파일(10)의 하단부가 안착되는 안착부(21)와, 상기 안착부(21)의 가장자리로부터 상측으로 연장되는 연장부(22)를 갖는 선단보강판(20); 을 포함하되,
상기 연장부(22)는 상측으로 갈수록 상기 안착부(21)의 중심으로부터 이격되도록 경사지게 형성된 것을 특징으로 하는 매입말뚝을 이용한 기초 공법.
In the foundation method using the embedded pile,
Installing a retaining wall 210 in the ground;
Forming a plurality of excavation holes by using the excavation device 220 at a portion where the main pillar 250 is disposed;
Embedding the embedded pile 100 in the excavation hole and grouting through the embedded pile 100;
Performing an initial excavation work;
Performing a ground-floor framing arrangement including a girder 240;
Performing further digging and basement framework placement work down to foundation level (L);
Installing a main pillar (250) between the plurality of embedded piles (100); And
And cutting off and removing an upper end of the embedded pile 100 extending above the foundation level (L).
The embedding pile 100,
A grouting liquid hole 11 is formed through the inner and outer circumferential surfaces of the lower end to allow the grouting liquid to pass therethrough, and a hollow pile 10 having an open bottom surface; And
A tip reinforcing plate having a seating portion 21 on which the lower end of the pile 10 is seated, and an extension portion 22 extending upward from an edge of the seating portion 21; Including,
The extension part 22 is a foundation method using the embedded pile, characterized in that inclined so as to be spaced apart from the center of the seating portion 21 toward the upper side.
제1항에 있어서,
상기 본기둥(250)은 상기 복수의 매입말뚝(100) 사이에 배치되는 것을 특징으로 하는 매입말뚝을 이용한 기초 공법.
The method of claim 1,
The main pillar 250 is a foundation method using the embedded pile, characterized in that disposed between the plurality of embedded pile (100).
제1항 또는 제2항에 있어서,
각 지하층 높이마다 상기 매입말뚝(100)에 고정되는 브라켓(230)이 마련되고,
상기 지하층 골조는 상기 브라켓(230)에 의해서 지지되는 것을 특징으로 하는 매입말뚝을 이용한 기초 공법.
The method according to claim 1 or 2,
For each basement height is provided with a bracket 230 fixed to the embedded pile 100,
The basement framework is a foundation method using the embedded pile, characterized in that supported by the bracket (230).
삭제delete 제1항에 있어서,
상기 매입말뚝(100)은, 상기 안착부(21)의 저면으로부터 하측방향으로 돌출되는 굴착용 보강판(30)을 더 포함하는 것을 특징으로 하는 매입말뚝을 이용한 기초 공법.
The method of claim 1,
The embedding pile 100, the foundation method using the embedded pile, characterized in that it further comprises an excavation reinforcement plate (30) protruding downward from the bottom of the seating portion (21).
제1항 또는 제5항에 있어서,
상기 선단보강판(20)은,
상기 연장부(22)의 둘레에 걸쳐 형성된 제1 관통공(23), 및 상기 안착부(21)에 형성된 제2 관통공(24) 중 적어도 하나를 포함한 것을 특징으로 하는 매입말뚝을 이용한 기초 공법.
6. The method according to claim 1 or 5,
The tip reinforcing plate 20,
Basic construction method using the embedded pile, characterized in that it comprises at least one of the first through hole 23 formed over the circumference of the extension portion 22, and the second through hole 24 formed in the seating portion 21 .
KR1020120049277A 2012-05-09 2012-05-09 Method for constructing foundation work Active KR101257905B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020120049277A KR101257905B1 (en) 2012-05-09 2012-05-09 Method for constructing foundation work

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020120049277A KR101257905B1 (en) 2012-05-09 2012-05-09 Method for constructing foundation work

Publications (1)

Publication Number Publication Date
KR101257905B1 true KR101257905B1 (en) 2013-04-26

Family

ID=48443751

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020120049277A Active KR101257905B1 (en) 2012-05-09 2012-05-09 Method for constructing foundation work

Country Status (1)

Country Link
KR (1) KR101257905B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101600845B1 (en) * 2013-09-09 2016-03-21 주식회사 씨엠파트너스건축사사무소 The horizontal structural frame and the underground construction methods using it
CN115288286A (en) * 2022-08-17 2022-11-04 北京市市政一建设工程有限责任公司 Big specification stone material masonry construction structure

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100923107B1 (en) 2009-05-27 2009-10-22 롯데건설 주식회사 Centrifugal force concrete pile assembly for building and construction method using same
KR100967497B1 (en) 2010-02-19 2010-07-07 (주)바로건설기술 Method for constructing an underground structure
KR101014796B1 (en) * 2008-03-03 2011-02-15 주식회사 한빛구조엔지니어링 Top-down construction method using ready-made concrete pillar member
KR20110043976A (en) * 2009-10-22 2011-04-28 주식회사 포스코건설 Inverse perforation using prefabricated columns and building structures thereby

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101014796B1 (en) * 2008-03-03 2011-02-15 주식회사 한빛구조엔지니어링 Top-down construction method using ready-made concrete pillar member
KR100923107B1 (en) 2009-05-27 2009-10-22 롯데건설 주식회사 Centrifugal force concrete pile assembly for building and construction method using same
KR20110043976A (en) * 2009-10-22 2011-04-28 주식회사 포스코건설 Inverse perforation using prefabricated columns and building structures thereby
KR100967497B1 (en) 2010-02-19 2010-07-07 (주)바로건설기술 Method for constructing an underground structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101600845B1 (en) * 2013-09-09 2016-03-21 주식회사 씨엠파트너스건축사사무소 The horizontal structural frame and the underground construction methods using it
CN115288286A (en) * 2022-08-17 2022-11-04 北京市市政一建设工程有限责任公司 Big specification stone material masonry construction structure
CN115288286B (en) * 2022-08-17 2023-06-30 北京市市政一建设工程有限责任公司 Large-specification stone masonry construction structure

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down construction method using ready-made concrete pillar member
KR101341679B1 (en) Device for constructing an underground structure and method thereof
KR101070426B1 (en) Improved Underpinning Method Using the micro pile
US20220098817A1 (en) Method for constructing structure
KR100967497B1 (en) Method for constructing an underground structure
KR20140055639A (en) A execution method of architecture beam
KR100926323B1 (en) Underground extension method using small diameter steel pipe
US20120301227A1 (en) Foundation pile and installing method thereof
KR20100094140A (en) Wall structure capable of earth retaining and the building method of the same
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
KR20090090742A (en) Bottom-up Underground Structure Construction Using Permanent Struts
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
JP2012112121A (en) Excavation method of ground under spread foundation and base-isolating method of existing building
JP5228862B2 (en) Underground structure, construction method of underground structure
KR101257905B1 (en) Method for constructing foundation work
KR102223856B1 (en) Foundation structure of waste landfill site and construction method thereof
KR20110043976A (en) Inverse perforation using prefabricated columns and building structures thereby
KR20050113450A (en) Downward reinforced-concrete underground structure using temporary assistant columns
KR100967496B1 (en) Device for constructing an underground structure
JP2020125630A (en) Building construction method
KR20100136900A (en) Foundation reinforcement method of structure
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
KR20110095538A (en) Tofu fixing method of micro pile and its device
JP6534026B2 (en) Seismic isolation building and its construction method
Dellaria et al. Combining multiple techniques to complete an urban deep excavation

Legal Events

Date Code Title Description
A201 Request for examination
PA0109 Patent application

Patent event code: PA01091R01D

Comment text: Patent Application

Patent event date: 20120509

PA0201 Request for examination
A302 Request for accelerated examination
PA0302 Request for accelerated examination

Patent event date: 20120629

Patent event code: PA03022R01D

Comment text: Request for Accelerated Examination

Patent event date: 20120509

Patent event code: PA03021R01I

Comment text: Patent Application

E902 Notification of reason for refusal
PE0902 Notice of grounds for rejection

Comment text: Notification of reason for refusal

Patent event date: 20121030

Patent event code: PE09021S01D

E701 Decision to grant or registration of patent right
PE0701 Decision of registration

Patent event code: PE07011S01D

Comment text: Decision to Grant Registration

Patent event date: 20130123

N231 Notification of change of applicant
PN2301 Change of applicant

Patent event date: 20130416

Comment text: Notification of Change of Applicant

Patent event code: PN23011R01D

GRNT Written decision to grant
PR0701 Registration of establishment

Comment text: Registration of Establishment

Patent event date: 20130418

Patent event code: PR07011E01D

PR1002 Payment of registration fee

Payment date: 20130419

End annual number: 3

Start annual number: 1

PG1601 Publication of registration
FPAY Annual fee payment

Payment date: 20190314

Year of fee payment: 7

PR1001 Payment of annual fee

Payment date: 20190314

Start annual number: 7

End annual number: 7

PR1001 Payment of annual fee

Payment date: 20230227

Start annual number: 11

End annual number: 11

PR1001 Payment of annual fee

Payment date: 20250326

Start annual number: 13

End annual number: 13