JP2005002671A - Underpinning method and viaduct - Google Patents
Underpinning method and viaduct Download PDFInfo
- Publication number
- JP2005002671A JP2005002671A JP2003167483A JP2003167483A JP2005002671A JP 2005002671 A JP2005002671 A JP 2005002671A JP 2003167483 A JP2003167483 A JP 2003167483A JP 2003167483 A JP2003167483 A JP 2003167483A JP 2005002671 A JP2005002671 A JP 2005002671A
- Authority
- JP
- Japan
- Prior art keywords
- viaduct
- reinforcing wall
- pile
- underpinning
- underpinning method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000009424 underpinning Methods 0.000 title claims abstract description 52
- 238000000034 method Methods 0.000 title claims abstract description 31
- 230000003014 reinforcing effect Effects 0.000 claims abstract description 67
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 19
- 239000010959 steel Substances 0.000 claims abstract description 19
- 239000004567 concrete Substances 0.000 claims abstract description 12
- 239000002689 soil Substances 0.000 claims abstract description 4
- 239000004568 cement Substances 0.000 claims description 4
- 230000002787 reinforcement Effects 0.000 description 11
- 238000010276 construction Methods 0.000 description 10
- 239000002344 surface layer Substances 0.000 description 9
- 230000015572 biosynthetic process Effects 0.000 description 4
- 238000009412 basement excavation Methods 0.000 description 3
- 238000009434 installation Methods 0.000 description 3
- 239000011150 reinforced concrete Substances 0.000 description 3
- 238000013019 agitation Methods 0.000 description 2
- 229910000278 bentonite Inorganic materials 0.000 description 1
- 239000000440 bentonite Substances 0.000 description 1
- SVPXDRXYRYOSEX-UHFFFAOYSA-N bentoquatam Chemical compound O.O=[Si]=O.O=[Al]O[Al]=O SVPXDRXYRYOSEX-UHFFFAOYSA-N 0.000 description 1
- 238000004132 cross linking Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000009751 slip forming Methods 0.000 description 1
- 238000004804 winding Methods 0.000 description 1
Images
Landscapes
- Bridges Or Land Bridges (AREA)
- Excavating Of Shafts Or Tunnels (AREA)
Abstract
【課題】高架橋直下部において、地中部に仮スラブや仮杭を新設する必要がなく、土被りの浅い部分にもシールドトンネルを通過させることができるアンダーピニング方法および高架橋を提供すること。
【解決手段】高架橋1の柱部5の周囲の地盤7上に、耐圧版13を設置する。また、耐圧版13に連続して、柱部5の間に補強壁23、補強壁17を設置する。さらに、補強壁23、補強壁17に連続して、床版3の下側に補強スラブ15を設置する。そして、耐圧版13の上に、柱部5に巻立てた根巻きコンクリート25を形成し、PC鋼棒27を根巻きコンクリート25と補強壁23に貫通させて、柱部5と補強壁23を一体化する。次に、高架橋1直下の地盤7にシールド機を通過させて、既設杭9の一部を切断・撤去しつつ、トンネル29を形成する。
【選択図】 図7To provide an underpinning method and a viaduct capable of passing a shield tunnel through a shallow portion of a soil cover without newly installing a temporary slab or a temporary pile in the underground portion immediately below the viaduct.
A pressure plate 13 is installed on a ground 7 around a pillar portion 5 of a viaduct 1. In addition, a reinforcing wall 23 and a reinforcing wall 17 are installed between the column portions 5 continuously to the pressure plate 13. Further, the reinforcing slab 15 is installed on the lower side of the floor slab 3 continuously to the reinforcing wall 23 and the reinforcing wall 17. Then, on the pressure plate 13, a root-wrapped concrete 25 wound around the column portion 5 is formed, and the PC steel rod 27 is passed through the root-wrap concrete 25 and the reinforcing wall 23, so that the column portion 5 and the reinforcing wall 23 are connected. Integrate. Next, the tunnel 29 is formed while passing a shield machine through the ground 7 immediately below the viaduct 1 and cutting and removing a part of the existing pile 9.
[Selection] Figure 7
Description
【0001】
【発明の属する技術分野】
本発明は、アンダーピニング方法および高架橋に関するものである。
【0002】
【従来の技術】
従来、構造物の直下を通過するトンネルの施工を行う際には、構造物に影響を及ぼさないようにアンダーピニング(受け替え工法)と呼ばれる仮受防護を行っている。その多くは、地中部にアンダーピニングのための新たな仮受桁やスラブと杭を設け、既設杭から荷重を受け替えるというものである。陸上部の高架橋においては、旅客や列車の安全、近隣や周囲の構造物への影響を配慮しながら、高架橋を仮受杭および仮受梁で仮受けする工事がいくつか行われている(非特許文献1参照)。
【0003】
【非特許文献1】
土木学会編「土木施工技術便覧」オーム社、p.384〜391
【0004】
【発明が解決しようとする課題】
しかしながら、営業中の高架橋で、土被りが浅い条件下で高架橋直下を縦断するトンネルを施工する際には、一般的なアンダーピニング方法の適用は困難である。
【0005】
本発明は、このような問題に鑑みてなされたもので、その目的とするところは、高架橋直下部において、地中部に仮スラブや仮杭を新設する必要がなく、土被りの浅い部分にもシールドトンネルを通過させることができるアンダーピニング方法および高架橋を提供することにある。
【0006】
【課題を解決するための手段】
前述した目的を達成するための第1の発明は、対向する柱部が連続して設けられ、前記柱部で床版を支持する既存構造物のアンダーピニング方法であって、前記柱部の周囲の地盤上に耐圧版を設置する工程(a)と、前記対向する柱部の間に補強壁を、前記床版の下側に補強スラブを設置する工程(b)と、前記柱部と前記補強壁とを一体化する工程(c)とを具備することを特徴とするアンダーピニング方法である。
【0007】
既存構造物とは、例えば、柱部である橋脚と、橋脚に支持された床版からなる高架橋である。工程(b)では、柱部の内側に沿って補強壁を設置する。既存構造物が高架橋である場合、例えば、縦断方向の補強壁と横断方向の補強壁が設置される。工程(c)では、柱部の外周に沿って巻立てたコンクリートと補強壁とにPC鋼棒を貫通させて、柱部と補強壁とを一体化する。アンダーピニングを行う区間の端部では、耐圧版の下部に支持杭が設置される。
【0008】
第1の発明では、柱部の周囲の地盤上に耐圧版を、隣接する2本の柱部の間に補強壁を、床版の下側に補強スラブを設置する。そして、柱部の外周に沿ってコンクリートを巻立て、このコンクリート補強壁とを一体化することにより、杭基礎構造である既存構造物を耐圧版による直接基礎構造に変換する。
【0009】
第2の発明は、対向する柱部が連続して設けられ、前記柱部で床版を支持する既存構造物のアンダーピニング方法であって、前記柱部の間の地盤を改良して杭状体を形成し、前記杭状体の上部を帯状に表層改良する工程(a)と、前記工程(a)で表層改良した地盤上に第1の耐圧版を設置する工程(b)と、前記対向する柱部の間に補強壁を、前記床版の下側に補強スラブを設置する工程(c)と、前記柱部のフーチング部の周囲を掘削してフーチングおよび既設杭を撤去する工程(d)と、前記工程(d)で掘削した部分を埋め戻す工程(e)と、前記工程(e)で埋め戻した部分の上に第2の耐圧版を設置する工程(f)とを具備することを特徴とするアンダーピニング方法である。
【0010】
既存構造物とは、例えば、柱部である橋脚と、橋脚に支持された床版からなる高架橋である。工程(a)では、高圧噴射撹拌工により杭状体を形成する。工程(c)では、柱部の内側に沿って補強壁を設置する。既存構造物が高架橋である場合、例えば、補強壁は、縦断方向に設置される。工程(d)では、工程(d)の前にフーチングの周囲に設置された鋼矢板の内部を掘削する。使用した鋼矢板は、工程(e)の後で引き抜く。工程(e)では、ソイルセメントを用いて埋め戻しを行う。
【0011】
第2の発明では、柱部の間の地盤を改良して杭状体を形成し、杭状体の上部を帯状に表層改良し、表層改良した地盤上に第1の耐圧版を設置する。次に、柱部の間に補強壁を、床版の下側に補強スラブを設置する。そして、柱部のフーチング部の周囲を掘削してフーチングおよび既設杭を撤去し、掘削した部分を埋め戻した後、埋め戻した部分の上に第2の耐圧版を設置する。これにより、杭基礎構造である既存構造物を耐圧版による直接基礎構造に変換する。
【0012】
【発明の実施の形態】
以下、図面に基づいて、本発明の第1の実施の形態について詳細に説明する。図1は、高架橋1の縦断方向の断面図、図2は、アンダーピニングを行った後の高架橋1の斜視図である。
【0013】
図1に示すように、アンダーピニングを行う高架橋1は、橋脚である柱部5、既設杭9、床版3等で構成される。柱部5は、高架橋1の縦断方向に2列に並置される。床版3は、柱部5上に設置される。既設杭9は、柱部5の下部の地盤7内に設置される。高架橋1は、柱部5、床版3等を、既設杭9で支持する杭基礎構造である。
【0014】
第1の実施の形態では、トンネル計画位置11が地盤7の比較的深い位置にあり、既設杭9に重なる場合のアンダーピニング方法について述べる。
【0015】
図2に示すように、高架橋1のアンダーピニングは、耐圧版13、補強スラブ15、補強壁17、補強壁23、根巻きコンクリート25、PC鋼棒27、耐圧版端部支持杭21(図3)等を設置して行われる。
【0016】
図3、図4はアンダーピニングを行った高架橋1の縦断方向の断面図を、図5は高架橋1の横断方向の断面図を、図6は柱部5付近の断面図を示す。図3は高架橋1を側方から見た図であり、図4のB−Bによる断面図である。図4は高架橋1を上方から見た図であり、図3のA−Aによる断面図である。図5は、図4のC−Cによる断面図である。図6は、図4のEに示す部分の拡大図である。図4のD−Dによる断面は、図2の端面と同様である。
【0017】
高架橋1のアンダーピニングを行うには、まず、柱部5の周囲の地盤7、すなわち、2列に設置された柱部5の間の地盤7と、柱部5の外側の地盤7とを覆うように、耐圧版13を設置する(図2、図3、図5)。そして、高架橋1の縦断方向に隣合う柱部5の間を補強する補強壁23を、柱部5の内側に沿って設置する(図2、図4、図5)。また、横断方向に隣合う柱部5の間を補強する補強壁17を設置する(図2から図5)。さらに、床版3の下側に補強スラブ15を設置する(図2、図3、図5)。
【0018】
図2に示すように、耐圧版13、補強スラブ15、補強壁17、補強壁23は連続しており、柱部5および床版3の内側に沿って荷重が伝達される。耐圧版13、補強スラブ15、補強壁17、補強壁23は、鉄筋コンクリート等とする。
【0019】
次に、柱部5の4面のうち、補強壁23、補強壁17が設置されない3面の周囲に、根巻きコンクリート25を設置する(図4、図5、図6)。根巻きコンクリート25は、耐圧版13の上面に設置される。そして、根巻きコンクリート25と補強壁23を貫通するように複数のPC鋼棒27を設置する(図2、図6)。PC鋼棒27は、柱部5と補強壁23を一体化するための部材である。
【0020】
補強壁23の施工区間の端部19付近では、耐圧版13の下部に、耐圧版端部支持杭21が設置される(図3)。耐圧版端部支持杭21は、施工区間の端部において、高架橋1の変形量を抑える。
【0021】
耐圧版13等の設置からPC鋼棒27の設置までの工程を各柱部35間について繰り返し、図2から図6に示すように、高架橋1のアンダーピニングを完成する。アンダーピニングを行うことにより、既設杭9で支持される杭基礎構造であった高架橋1は、耐圧版13で支持される直接基礎構造に変換される。
【0022】
図7は、トンネル29形成後の高架橋1の縦断方向の断面図を示す。図7は、柱部5を含む位置での断面を、高架橋1の側方から見た図である。図2から図6に示すようにアンダーピニングを行った後、高架橋1の下方のトンネル計画位置11(図1)にシールド機を通過させ、トンネル29(図7)を形成する。
【0023】
上述したように、アンダーピニングが行われた高架橋1は耐圧版13による直接基礎構造に変換されており、既存の躯体および連続する耐圧版13、補強壁17、補強壁23、補強スラブ15の剛性によって安定が確保されている。そのため、トンネル29の形成時には、図7に示すように、既設杭9の一部をシールドマシンにより切断、撤去することができる。必要に応じて、新設された耐圧版端部支持杭21の一部も切断、撤去される。
【0024】
第1の実施の形態では、高架橋1に耐圧版13、補強スラブ15、補強壁17、補強壁23を設置して、杭基礎構造から直接基礎構造に転換する工法を用いるため、トンネル29の形成に先行して既設躯体を撤去する必要がない。また、トンネル29の形成時には、シールドマシンにより既設杭9を切断・撤去することができる。
【0025】
第1の実施の形態のアンダーピニング工法は、掘削を行わず、土留め壁、支保工が不要であるため、周辺環境への影響が小さく施工性に優れる。また、軌道への影響なく施工可能である。さらに、従来の開削によるアンダーピニング方法と比較して、狭い作業ヤードで施工できるうえ、夜間作業時間を短縮でき、工事の安全性が向上し、全体としての工期の縮減を図ることができる。
【0026】
次に、第2の実施の形態について詳細に説明する。図8は、高架橋31の縦断方向の断面図、図9は、アンダーピニングを行った後の高架橋31の斜視図である。
【0027】
図8に示すように、アンダーピニングを行う高架橋31は、橋脚である柱部35、既設杭39、床版33等で構成される。柱部35は、高架橋31の縦断方向に2列に並置される。床版33は、柱部35上に設置される。既設杭39は、柱部35の下部の地盤37内に設置される。高架橋31は、柱部35、床版33等を、既設杭39で支持する杭基礎構造である。
【0028】
第2の実施の形態では、トンネル計画位置41が地盤37の浅い位置にあり、既設杭39と柱部35のフーチング59に重なる場合のアンダーピニング方法について述べる。
【0029】
図9に示すように、高架橋31のアンダーピニングは、耐圧版43、補強スラブ45、補強壁53、表層改良49、杭状体47等を設置して行われる。耐圧版43は、耐圧版43aと耐圧版43bからなる。
【0030】
図10は、杭状体47を形成し、表層改良49を行い、耐圧版43a、補強スラブ45、補強壁53を設置した高架橋31の縦断方向の断面図を示す。図10は、柱部35を含む位置での断面を、高架橋1の側方から見た図である。図10のF−Fによる断面は、図2の端面と同様である。
【0031】
高架橋1のアンダーピニングを行うには、図9、図10に示すように、まず、高架橋1の縦断方向に隣合う柱部35の間に杭状体47を設置する。杭状体47は、例えば、高圧噴射撹拌工(コラムジェットグラウト工)によって形成される。次に、横断方向に隣合う2本の杭状体47の上部を連結するように、地盤37の表層改良49を行う。図9に示すように、表層改良49の両端部は、杭状体47の外側に達する。
【0032】
表層改良49を行った後、表層改良49の上部に耐圧版43aを設置する(図9、図10)。そして、高架橋31の縦断方向に隣合う柱部35の間を補強する補強壁53を、柱部35の内側に沿って設置する(図9、図10)。さらに、床版33の下側に補強スラブ45を設置する(図9)。
【0033】
図9に示すように、耐圧版43a、補強スラブ45、補強壁53は連続しており、柱部35および床版33の内側に沿って荷重が伝達される。耐圧版43a、補強スラブ45、補強壁53は、鉄筋コンクリート等とする。
【0034】
図11は、柱部35のフーチング59を撤去しつつある高架橋31の縦断方向の断面図である。耐圧版43a、補強スラブ45、補強壁53を設置した後、図11の(a)に示すように、地盤37に鋼矢板51を打設する。鋼矢板51は、高架橋31の横断方向に隣合う2本の柱部35のフーチング59を囲むように設置される。
【0035】
図12は、フーチング59を撤去した高架橋31の横断方向の断面図である。図12は、図11のG−Gによる断面図である。図11の(a)に示すように鋼矢板51を打設した後、図11の(b)、図12に示すように、鋼矢板51で囲まれた部分の地盤37を、フーチング59の下面まで掘削する。そして、フーチング59と柱部35の地下部分を撤去する。
【0036】
次に、図11の(c)に示すように、掘削部55の下部に埋設された既設杭39を撤去する。既設杭39を撤去した後、緩んだ地盤にセメントベントナイトを注入する。そして、地盤37の掘削とフーチング59等の撤去により生じた空間55に、図11の(d)に示すように、埋戻し57を行う。埋戻し57には、例えば、ソイルセメントなどを用いる。埋戻し57を行った後、図11の(e)に示すように、鋼矢板51を撤去する。
【0037】
図13は、耐圧版43bを設置した高架橋31の横断方向の断面図である。図13は、図11のH−Hによる断面図である。図11の(e)に示すように鋼矢板51を撤去した後、図11の(f)、図13に示すように、埋戻し57を行った部分の上に耐圧版43bを設置する。
【0038】
図9、図11の(f)、図13に示すように、耐圧版43bは、耐圧版43a、補強壁53に連続して形成される。耐圧版43bは、耐圧版43aと同様に、鉄筋コンクリート等とする。耐圧版43は、耐圧版43aと耐圧版43bを一体化したものである。耐圧版43には、柱部35および床版33の内側に沿って荷重が伝達される。
【0039】
図10、図11に示すように、杭状体47の形成から耐圧版43bの設置までの工程を各柱部35間で繰り返し、図9に示すように、高架橋31のアンダーピニングを完成する。アンダーピニングを行うことにより、既設杭39で支持される杭基礎構造であった高架橋31は、耐圧版43で支持される直接基礎構造に変換される。
【0040】
図14は、トンネル61形成後の高架橋31の縦断方向の断面図、図15は、トンネル61形成後の高架橋31の横断方向の断面図を示す。図14は、柱部35を含む位置での断面を、高架橋1の側方から見た図である。図15は、図14のI−Iによる断面図である。
【0041】
図9に示すようにアンダーピニングを行った後、高架橋31の下方のトンネル計画位置41(図10)にシールド機を通過させ、トンネル61(図14)を形成する。
【0042】
上述したように、アンダーピニングが行われた高架橋31は耐圧版43による直接基礎構造に変換されており、既存の躯体および連続する耐圧版43、補強壁53、補強スラブ45の剛性によって安定が確保されている。そのため、トンネル61の形成時には、図14、図15に示すように、杭状体47、表層改良49、埋め戻し57の一部を、シールドマシンにより切断、撤去することができる。
【0043】
第2の実施の形態では、高架橋31に耐圧版43、補強スラブ45、補強壁53を設置し、フーチング59等を撤去して、杭基礎構造から直接基礎構造に転換する工法を用いる。このとき、トンネル61の形成に先行して行う地盤37の掘削作業や既設躯体の撤去作業は小規模ですむため、周辺環境への影響が小さく施工性に優れる。また、軌道への影響なく施工可能である。
【0044】
第2の実施の形態のアンダーピニング工法では、地盤37内に仮杭や仮受桁を設置せず、高圧噴射撹拌工による杭状体47の形成や表層改良49を行うため、地盤37の浅い部分までシールド機を通過させることができ、シールド機の到達坑が不要となる。また、従来の開削によるアンダーピニング方法と比較して、狭い作業ヤードで施工できるうえ、夜間作業時間を短縮でき、工事の安全性が向上し、全体としての工期の縮減を図ることができる。
【0045】
【発明の効果】
以上、詳細に説明したように、本発明によれば、高架橋直下部において、地中部に仮スラブや仮杭を新設する必要がなく、土被りの浅い部分にもシールドトンネルを通過させることができるアンダーピニング方法および高架橋を提供できる。
【図面の簡単な説明】
【図1】高架橋1の縦断方向の断面図
【図2】アンダーピニングを行った後の高架橋1の斜視図
【図3】アンダーピニングを行った高架橋1の縦断方向の断面図
【図4】アンダーピニングを行った高架橋1の縦断方向の断面図
【図5】高架橋1の横断方向の断面図
【図6】柱部5付近の断面図
【図7】トンネル29形成後の高架橋1の縦断方向の断面図
【図8】高架橋31の縦断方向の断面図
【図9】アンダーピニングを行った後の高架橋31の斜視図
【図10】杭状体47を形成し、表層改良49を行い、耐圧版43a、補強スラブ45、補強壁53を設置した高架橋31の縦断方向の断面図
【図11】柱部35のフーチング59を撤去しつつある高架橋31の縦断方向の断面図
【図12】フーチング59を撤去した高架橋31の横断方向の断面図
【図13】耐圧版43bを設置した高架橋31の横断方向の断面図
【図14】トンネル61形成後の高架橋31の縦断方向の断面図
【図15】トンネル61形成後の高架橋31の横断方向の断面図
【符号の説明】
1、31………高架橋
3、33………床版
5、35………柱部
7、37………地盤
9、39………既設杭
11、41………トンネル計画位置
13、43、43a、43b………耐圧版
15、45………補強スラブ
17、23、53………補強壁
21………耐圧版端部支持杭
25………根巻きコンクリート
27………PC鋼棒
47………杭状体
49………表層改良
51………鋼矢板
57………埋戻し[0001]
BACKGROUND OF THE INVENTION
The present invention relates to an underpinning method and high crosslinking.
[0002]
[Prior art]
Conventionally, when constructing a tunnel that passes directly under a structure, provisional protection called underpinning (replacement method) is performed so as not to affect the structure. Many of them are to install new provisional girders, slabs and piles for underpinning in the underground, and to transfer loads from existing piles. On the viaducts on land, several works have been undertaken to temporarily receive the viaduct with temporary piles and temporary beams while taking into account the safety of passengers and trains and the impact on nearby and surrounding structures. Patent Document 1).
[0003]
[Non-Patent Document 1]
"Public Works Engineering Handbook" edited by Japan Society of Civil Engineers, Ohmsha, p. 384-391
[0004]
[Problems to be solved by the invention]
However, it is difficult to apply a general underpinning method when constructing a tunnel that runs through a viaduct directly under the viaduct under a condition where the earth covering is shallow.
[0005]
The present invention has been made in view of such problems, and the purpose of the present invention is that it is not necessary to newly install a temporary slab or a temporary pile in the underground part directly under the viaduct, and even in a shallow part of the earth covering. An object of the present invention is to provide an underpinning method and a viaduct capable of passing through a shield tunnel.
[0006]
[Means for Solving the Problems]
A first invention for achieving the above-described object is a method of underpinning an existing structure in which opposing pillar portions are continuously provided and a floor slab is supported by the pillar portions, and the surroundings of the pillar portions are provided. A step (a) of installing a pressure-resistant plate on the ground of the step, a step (b) of installing a reinforcing wall between the opposing pillars, and a reinforcing slab on the lower side of the floor slab, the pillars and the A step (c) of integrating the reinforcing wall with the reinforcing wall.
[0007]
The existing structure is, for example, a viaduct composed of a pier that is a pillar and a floor slab supported by the pier. In the step (b), a reinforcing wall is installed along the inside of the column portion. When the existing structure is a viaduct, for example, a longitudinal reinforcing wall and a transverse reinforcing wall are installed. In the step (c), the PC steel rod is passed through the concrete wound around the outer periphery of the column portion and the reinforcing wall, and the column portion and the reinforcing wall are integrated. At the end of the section where underpinning is performed, a support pile is installed below the pressure plate.
[0008]
In the first invention, a pressure-resistant plate is installed on the ground around the column portion, a reinforcement wall is installed between two adjacent column portions, and a reinforcement slab is installed below the floor slab. And concrete is wound up along the outer periphery of a pillar part, By integrating this concrete reinforcement wall, the existing structure which is a pile foundation structure is converted into a direct foundation structure by a pressure-resistant plate.
[0009]
2nd invention is an underpinning method of the existing structure in which the opposing pillar part is continuously provided, and supports a floor slab by the said pillar part, Comprising: The ground between the said pillar parts is improved, and it is a pile shape Forming a body, and improving the surface layer of the upper part of the pile-shaped body in a strip shape (a), installing the first pressure-resistant plate on the ground surface improved in the step (a) (b), A step (c) of installing a reinforcing wall between opposing column portions and a reinforcing slab on the lower side of the floor slab, and a step of excavating the periphery of the footing portion of the column portion to remove the footings and existing piles ( d), a step (e) of backfilling the portion excavated in the step (d), and a step (f) of installing a second pressure plate on the portion backfilled in the step (e). The underpinning method is characterized by:
[0010]
The existing structure is, for example, a viaduct composed of a pier that is a pillar and a floor slab supported by the pier. In the step (a), a pile-shaped body is formed by a high-pressure jet agitator. In the step (c), a reinforcing wall is installed along the inside of the column portion. When the existing structure is a viaduct, for example, the reinforcing wall is installed in the longitudinal direction. In the step (d), the inside of the steel sheet pile installed around the footing is excavated before the step (d). The used steel sheet pile is pulled out after the step (e). In step (e), backfilling is performed using soil cement.
[0011]
In 2nd invention, the ground between pillar parts is improved, a pile-shaped body is formed, the upper part of a pile-shaped body is surface-layer-modified in a strip | belt shape, and a 1st pressure-resistant plate is installed on the ground improved. Next, a reinforcing wall is installed between the pillars, and a reinforcing slab is installed below the floor slab. And after excavating the circumference | surroundings of the footing part of a pillar part and removing a footing and an existing pile, and refilling the excavated part, a 2nd pressure-resistant plate is installed on the refilled part. Thereby, the existing structure which is a pile foundation structure is converted into the direct foundation structure by a pressure-resistant plate.
[0012]
DETAILED DESCRIPTION OF THE INVENTION
Hereinafter, a first embodiment of the present invention will be described in detail with reference to the drawings. FIG. 1 is a cross-sectional view of the
[0013]
As shown in FIG. 1, the
[0014]
In the first embodiment, an underpinning method when the tunnel planned
[0015]
As shown in FIG. 2, the underpinning of the
[0016]
3 and 4 are cross-sectional views in the longitudinal direction of the
[0017]
To perform underpinning of the
[0018]
As shown in FIG. 2, the
[0019]
Next, the root-wrapped
[0020]
In the vicinity of the end 19 of the construction section of the reinforcing
[0021]
The steps from the installation of the
[0022]
FIG. 7 shows a cross-sectional view in the longitudinal direction of the
[0023]
As described above, the
[0024]
In the first embodiment, since the
[0025]
The underpinning method according to the first embodiment does not perform excavation and does not require a retaining wall or a supporting work. Therefore, the influence on the surrounding environment is small and the workability is excellent. In addition, construction is possible without affecting the track. Furthermore, compared with the conventional underpinning method by open-cutting, construction can be performed in a narrow work yard, night work hours can be shortened, construction safety can be improved, and the overall construction period can be reduced.
[0026]
Next, a second embodiment will be described in detail. FIG. 8 is a cross-sectional view of the
[0027]
As shown in FIG. 8, the
[0028]
In the second embodiment, an underpinning method when the tunnel planned
[0029]
As shown in FIG. 9, the underpinning of the
[0030]
10 shows a cross-sectional view in the longitudinal direction of the
[0031]
In order to perform underpinning of the
[0032]
After the
[0033]
As shown in FIG. 9, the
[0034]
FIG. 11 is a longitudinal sectional view of the
[0035]
FIG. 12 is a cross-sectional view in the transverse direction of the
[0036]
Next, as shown in FIG. 11C, the existing
[0037]
FIG. 13 is a cross-sectional view in the transverse direction of the
[0038]
As shown in FIGS. 9 and 11 (f) and FIG. 13, the
[0039]
As shown in FIGS. 10 and 11, the steps from the formation of the
[0040]
14 is a cross-sectional view in the longitudinal direction of the
[0041]
After underpinning as shown in FIG. 9, the shield machine is passed through the tunnel planned position 41 (FIG. 10) below the
[0042]
As described above, the
[0043]
In the second embodiment, a
[0044]
In the underpinning method according to the second embodiment, the
[0045]
【The invention's effect】
As described above in detail, according to the present invention, it is not necessary to newly install a temporary slab or a temporary pile in the underground part directly under the viaduct, and the shield tunnel can be passed through a shallow part of the earth covering. Underpinning methods and high crosslinks can be provided.
[Brief description of the drawings]
1 is a cross-sectional view of the
1, 31 …………
Claims (12)
前記柱部の周囲の地盤上に耐圧版を設置する工程(a)と、
前記対向する柱部の間に補強壁を、前記床版の下側に補強スラブを設置する工程(b)と、
前記柱部と前記補強壁とを一体化する工程(c)と、
を具備することを特徴とするアンダーピニング方法。Opposing column portions are continuously provided, and an underpinning method for an existing structure that supports a floor slab with the column portions,
A step (a) of installing a pressure-resistant plate on the ground around the pillar part;
A step (b) of installing a reinforcing wall between the opposing pillars and a reinforcing slab on the lower side of the floor slab;
A step (c) of integrating the column portion and the reinforcing wall;
An underpinning method comprising:
前記柱部の間の地盤を改良して杭状体を形成し、前記杭状体の上部を帯状に表層改良する工程(a)と、
前記工程(a)で表層改良した地盤上に第1の耐圧版を設置する工程(b)と、
前記対向する柱部の間に補強壁を、前記床版の下側に補強スラブを設置する工程(c)と、
前記柱部のフーチング部の周囲を掘削してフーチングおよび既設杭を撤去する工程(d)と、
前記工程(d)で掘削した部分を埋め戻す工程(e)と、
前記工程(e)で埋め戻した部分の上に第2の耐圧版を設置する工程(f)と、
を具備することを特徴とするアンダーピニング方法。Opposing column portions are continuously provided, and an underpinning method for an existing structure that supports a floor slab with the column portions,
Improving the ground between the pillars to form a pile-like body, and improving the surface of the upper part of the pile-like body in a strip shape (a);
A step (b) of installing a first pressure-resistant plate on the ground improved in the step (a);
A step (c) of installing a reinforcing wall between the opposing pillars and a reinforcing slab on the lower side of the floor slab;
A step (d) of excavating the periphery of the footing portion of the pillar portion and removing the footing and the existing pile;
A step (e) of refilling a portion excavated in the step (d);
A step (f) of installing a second pressure-resistant plate on the portion backfilled in the step (e);
An underpinning method comprising:
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003167483A JP4226954B2 (en) | 2003-06-12 | 2003-06-12 | Underpinning method and viaduct |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
JP2003167483A JP4226954B2 (en) | 2003-06-12 | 2003-06-12 | Underpinning method and viaduct |
Publications (2)
Publication Number | Publication Date |
---|---|
JP2005002671A true JP2005002671A (en) | 2005-01-06 |
JP4226954B2 JP4226954B2 (en) | 2009-02-18 |
Family
ID=34093276
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
JP2003167483A Expired - Fee Related JP4226954B2 (en) | 2003-06-12 | 2003-06-12 | Underpinning method and viaduct |
Country Status (1)
Country | Link |
---|---|
JP (1) | JP4226954B2 (en) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101511265B1 (en) | 2013-08-20 | 2015-04-10 | 서울특별시 | Construction method for supporting structure of temporary bridge tayp |
CN106759458A (en) * | 2017-02-13 | 2017-05-31 | 中铁十九局集团轨道交通工程有限公司 | The U-shape structure of bridge pile foundation underpins transfer system and its applies method |
CN108330845A (en) * | 2018-01-26 | 2018-07-27 | 中铁隧道集团二处有限公司 | A kind of reinforcement means of curve bridge underpinning |
CN108868780A (en) * | 2018-05-19 | 2018-11-23 | 中水电第十工程局(郑州)有限公司 | A kind of method of mud-rock flow stratum tunnel excavation |
CN109797665A (en) * | 2019-01-29 | 2019-05-24 | 北京城建设计发展集团股份有限公司 | Statically indeterminate structure bridge pile foundation actively underpins top lift determination and displacement control method |
WO2020224233A1 (en) * | 2019-05-05 | 2020-11-12 | 济南轨道交通集团有限公司 | Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner |
CN113389557A (en) * | 2021-06-25 | 2021-09-14 | 中铁第五勘察设计院集团有限公司 | Isolation structure of side-passing bridge pile of shield tunnel and shield tunnel structure assembly |
CN114837104A (en) * | 2022-04-29 | 2022-08-02 | 中交隧道工程局有限公司 | Bridge pile foundation underpinning method |
CN118774832A (en) * | 2024-06-18 | 2024-10-15 | 中交四航局第一工程有限公司 | A construction method for pile foundation replacement structure in a shallow buried tunnel |
-
2003
- 2003-06-12 JP JP2003167483A patent/JP4226954B2/en not_active Expired - Fee Related
Cited By (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101511265B1 (en) | 2013-08-20 | 2015-04-10 | 서울특별시 | Construction method for supporting structure of temporary bridge tayp |
CN106759458A (en) * | 2017-02-13 | 2017-05-31 | 中铁十九局集团轨道交通工程有限公司 | The U-shape structure of bridge pile foundation underpins transfer system and its applies method |
CN108330845A (en) * | 2018-01-26 | 2018-07-27 | 中铁隧道集团二处有限公司 | A kind of reinforcement means of curve bridge underpinning |
CN108868780A (en) * | 2018-05-19 | 2018-11-23 | 中水电第十工程局(郑州)有限公司 | A kind of method of mud-rock flow stratum tunnel excavation |
CN108868780B (en) * | 2018-05-19 | 2019-12-03 | 中电建十一局工程有限公司 | A kind of method of mud-rock flow stratum tunnel excavation |
CN109797665A (en) * | 2019-01-29 | 2019-05-24 | 北京城建设计发展集团股份有限公司 | Statically indeterminate structure bridge pile foundation actively underpins top lift determination and displacement control method |
WO2020224233A1 (en) * | 2019-05-05 | 2020-11-12 | 济南轨道交通集团有限公司 | Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner |
CN113389557A (en) * | 2021-06-25 | 2021-09-14 | 中铁第五勘察设计院集团有限公司 | Isolation structure of side-passing bridge pile of shield tunnel and shield tunnel structure assembly |
CN114837104A (en) * | 2022-04-29 | 2022-08-02 | 中交隧道工程局有限公司 | Bridge pile foundation underpinning method |
CN118774832A (en) * | 2024-06-18 | 2024-10-15 | 中交四航局第一工程有限公司 | A construction method for pile foundation replacement structure in a shallow buried tunnel |
Also Published As
Publication number | Publication date |
---|---|
JP4226954B2 (en) | 2009-02-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100656194B1 (en) | Open type method using tunnel method | |
CN102410031B (en) | Underground space structure constructed by pile wall construction method | |
JP6543176B2 (en) | Building method | |
JP4226954B2 (en) | Underpinning method and viaduct | |
JP2000352296A (en) | Method o constructing passage just under underground structure | |
KR102223856B1 (en) | Foundation structure of waste landfill site and construction method thereof | |
JP5480744B2 (en) | Foundation for structure and its construction method | |
JPH1136338A (en) | Construction method for underground structures | |
CN210141142U (en) | Underground structure is built in same direction as digging in hole stake secret | |
KR101587062B1 (en) | Steel composite underground earth retaining wall structure and it's construction method | |
JP3930954B2 (en) | Construction method of structure | |
JP7115923B2 (en) | Foundation structure reinforcement method and foundation structure reinforcement structure | |
CN216765941U (en) | Tunnel decompression load shedding structure under bias voltage state | |
CN106988337B (en) | It is a kind of for reducing the reinforcement means of bar shaped shallow foundation house differential settlement | |
JP2001329545A (en) | Bridge pier foundation construction method and floor slab for bridge pier | |
JPH07243269A (en) | Method of building underground parking lot | |
JP6710999B2 (en) | Temporary receiving method for existing structures | |
JP5480745B2 (en) | Reinforcement method for existing foundations for structures | |
JPH1077644A (en) | Earthquake resisting pile foundation construction method | |
JP2017206882A (en) | Method of constructing underground structure | |
JP2013160029A (en) | Tunnel structure and method for constructing the same | |
KR20070052109A (en) | Simultaneous construction of slab and exterior wall and underground reverse casting using slim composite floor structure | |
KR101077242B1 (en) | Construction method of basement structure using retaining wall and steel column | |
JP6543177B2 (en) | Building method | |
JP4319231B2 (en) | Approach caisson and method for constructing tunnel approach section composed of caisson |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A621 | Written request for application examination |
Free format text: JAPANESE INTERMEDIATE CODE: A621 Effective date: 20051219 |
|
A977 | Report on retrieval |
Free format text: JAPANESE INTERMEDIATE CODE: A971007 Effective date: 20081022 |
|
TRDD | Decision of grant or rejection written | ||
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 Effective date: 20081125 |
|
A01 | Written decision to grant a patent or to grant a registration (utility model) |
Free format text: JAPANESE INTERMEDIATE CODE: A01 |
|
A61 | First payment of annual fees (during grant procedure) |
Free format text: JAPANESE INTERMEDIATE CODE: A61 Effective date: 20081127 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20111205 Year of fee payment: 3 |
|
R150 | Certificate of patent or registration of utility model |
Free format text: JAPANESE INTERMEDIATE CODE: R150 |
|
FPAY | Renewal fee payment (event date is renewal date of database) |
Free format text: PAYMENT UNTIL: 20141205 Year of fee payment: 6 |
|
R250 | Receipt of annual fees |
Free format text: JAPANESE INTERMEDIATE CODE: R250 |
|
LAPS | Cancellation because of no payment of annual fees |