JP2017206882A - Method of constructing underground structure - Google Patents

Method of constructing underground structure Download PDF

Info

Publication number
JP2017206882A
JP2017206882A JP2016100293A JP2016100293A JP2017206882A JP 2017206882 A JP2017206882 A JP 2017206882A JP 2016100293 A JP2016100293 A JP 2016100293A JP 2016100293 A JP2016100293 A JP 2016100293A JP 2017206882 A JP2017206882 A JP 2017206882A
Authority
JP
Japan
Prior art keywords
underground
top plate
ground
continuous
constructing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
JP2016100293A
Other languages
Japanese (ja)
Inventor
大久保 憲二
Kenji Okubo
憲二 大久保
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Kajima Corp
Original Assignee
Kajima Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Kajima Corp filed Critical Kajima Corp
Priority to JP2016100293A priority Critical patent/JP2017206882A/en
Publication of JP2017206882A publication Critical patent/JP2017206882A/en
Pending legal-status Critical Current

Links

Images

Abstract

PROBLEM TO BE SOLVED: To provide a method of constructing an underground structure that can largely shorten the construction period and reduces the construction cost without using a precast member.SOLUTION: A part of an upper ground 1 between continuous underground walls 11a and 11b is excavated and a short strut 17 is installed. Next, the upper ground 1 between the continuous underground walls 11a and 11b is excavated to a predetermined depth and is excavated, for example, to a depth permitting installation of a form of a pile cap. The short strut 17 may be one that can resist an earth pressure up to the depth. An upper surface of an excavated part is smoothly finished and is rolled so as not to settle, and crushed stones are laid and leveled. Next, sand is evenly laid on the surface and leveled, and a form 19 is installed. Next, a reinforcement 22 is assembled on the form 19. Concrete is also placed so as to fill up the reinforcement 22, and a pile cap 21 is formed on the ground between the pair of continuous underground walls 11a and 11b.SELECTED DRAWING: Figure 10

Description

本発明は、地下トンネルなどの地下構造体の構築方法に関する。   The present invention relates to a method for constructing an underground structure such as an underground tunnel.

近年、都市部の道路整備工事等において、既設道路直下に通過交通用の地下トンネルを構築する計画が増加している。通常、計画中の地下トンネルの土かぶりが浅い場合には、開削工法が用いられる。開削工法では、まず、地下トンネルの躯体の外側に土留壁を構築し、内部に中間杭を打設する。そして、路面覆工を設置し、必要に応じて止水や底盤改良を行い、切梁を設置しながらトンネル構築スペースを掘削する。その後、掘削したトンネル構築スペースに底から順に現場打ちコンクリートを打設して、トンネル躯体を構築する。   In recent years, there are increasing plans to construct underground tunnels for passing traffic directly under existing roads in urban road maintenance works and the like. Normally, the open-cut method is used when the ground cover of the planned underground tunnel is shallow. In the open-cut method, a retaining wall is first constructed outside the underground tunnel frame, and an intermediate pile is placed inside. Then, a road surface lining is installed, water is stopped and the bottom is improved as necessary, and the tunnel construction space is excavated while installing the beams. Afterwards, cast concrete is cast in the excavated tunnel construction space from the bottom in order to construct the tunnel frame.

また、一般的な開削工法と比較して工期を短縮するために、プレキャストコンクリートを用いて、地下トンネルを構築する方法もある(特許文献1)。   Moreover, in order to shorten a construction period compared with a general cutting method, there is also a method of constructing an underground tunnel using precast concrete (Patent Document 1).

特開2015−117545号公報JP2015-117545A

特許文献1のように、プレキャスト部材を用いることで、工期の短縮を図ることは可能であるが、施工現場によっては、大きなプレキャスト部材を運搬するのが困難である場合や、資材を置く場所を確保することが困難である場合がある。したがって、現場打ちコンクリートによって、より工期を短縮可能な工法も望まれている。   Although it is possible to shorten the construction period by using a precast member as in Patent Document 1, depending on the construction site, it may be difficult to transport a large precast member, or the place where the material is placed. It may be difficult to ensure. Therefore, a construction method that can shorten the construction period by using cast-in-place concrete is also desired.

本発明は、前述した問題点に鑑みてなされたもので、プレキャスト部材を用いることなく、大幅な工期短縮と工費削減を図れる地下構造体の構築方法を提供することを目的とする。   The present invention has been made in view of the above-described problems, and an object of the present invention is to provide a method for constructing an underground structure that can significantly reduce the work period and cost without using a precast member.

前述した目的を達成するための本発明は、地盤中に連続地中壁を構築する工程aと、一対の前記連続地中壁の間の地盤上に頂版を施工する工程bと、前記連続地中壁および前記頂版で囲まれた空間を地下構造体の長手方向に向かって掘削する工程cと、前記連続地中壁および前記頂版で囲まれた空間の底部に底版を施工する工程dと、を具備することを特徴とする地下構造体の構築方法である。   The present invention for achieving the above-described object includes a step a for constructing a continuous underground wall in the ground, a step b for constructing a top plate on the ground between a pair of the continuous underground walls, and the continuous A step c of excavating a space surrounded by the underground wall and the top plate in a longitudinal direction of an underground structure, and a step of constructing a bottom plate at the bottom of the space surrounded by the continuous underground wall and the top plate d), and a construction method of an underground structure.

前記工程aと前記工程bの間に、前記底版を施工する部位の下方に地中梁として地盤改良部を施工する工程eを具備することが望ましい。   It is desirable to provide a step e between the step a and the step b, in which a ground improvement portion is constructed as an underground beam below a portion where the bottom plate is constructed.

前記工程eは、高圧噴射撹拌によって行われ、前記工程bの後であって、前記工程cの前または前記工程cと同時に、高圧噴射撹拌によって生じたスライムを用いて、前記頂版の上部を埋め戻す工程fを具備してもよい。   The step e is performed by high-pressure jet agitation, and after the step b, before the step c or simultaneously with the step c, using the slime generated by the high-pressure jet agitation, A backfilling step f may be provided.

前記工程aは、上部に仮設芯材を有する鋼製連壁芯材を用いて行われ、前記工程bの後に、前記仮設芯材を撤去してもよい。   The step a may be performed using a steel continuous wall core member having a temporary core member at the top, and the temporary core member may be removed after the step b.

前記工程bは、一対の前記連続地中壁の間を所定深さまで掘削し、一対の前記連続地中壁の間の地盤上に型枠を配置して、前記型枠上に前記頂版を施工し、前記工程cの後に、前記型枠を地下構造体内から撤去してもよい。   The step b includes excavating a predetermined depth between the pair of continuous underground walls, placing a formwork on the ground between the pair of continuous underground walls, and placing the top plate on the formwork. After the step c, the formwork may be removed from the underground structure.

本発明によれば、最初に頂版を施工するため、従来のような、支保工や切梁が不要である。また、内部掘削および底版施工の工程が完了することを待たずに、地上を利用することができる。このため、地下構造物施工に伴う地上の交通規制等を行う期間を短縮することができる。   According to the present invention, since the top plate is first constructed, there is no need for a support work or a beam as in the prior art. In addition, the ground can be used without waiting for the completion of the internal excavation and bottom plate construction processes. For this reason, it is possible to shorten the period for carrying out ground traffic regulation associated with the construction of underground structures.

また、頂版を施工した後に内部掘削および底版施工等を行うため、地上における騒音を抑制することができる。また、頂版を先に施工することで、地下構造体の内部の掘削後に頂版施工を行う場合と比較して、高所作業を削減することができる。例えば、頂版のコンクリートを打設する際には、地盤によって頂版を支持することができため、型枠設置などの高所作業が不要となる。このため、安全性を高め、施工期間を短縮することができる。   Moreover, since internal excavation and bottom plate construction are performed after the top plate is constructed, noise on the ground can be suppressed. In addition, by installing the top plate first, it is possible to reduce work at high places as compared with the case where top plate construction is performed after excavation inside the underground structure. For example, when placing the concrete of the top plate, the top plate can be supported by the ground, so that high-level work such as installation of a mold is not necessary. For this reason, safety can be improved and a construction period can be shortened.

また、底版施工部の下部に地盤改良により地中梁を施工することで、軟弱地盤に対しても、連続地中壁を頂版と地中梁によって支持することができ、地下構造体の内部の掘削時に、従来のような支保工や切梁の設置を削減することができる。   In addition, by constructing underground beams by improving the ground at the bottom of the bottom plate construction part, the continuous underground wall can be supported by the top plate and underground beams even for soft ground, and the inside of the underground structure During excavation, it is possible to reduce the conventional support work and installation of beams.

また、地中梁を高圧噴射撹拌によって形成し、高圧噴射撹拌によって生じたスライムを用いて、頂版の上部を埋め戻すことで、スライムの処理を行う費用を削減することができる。   Further, by forming the underground beam by high-pressure jet stirring and using the slime generated by the high-pressure jet stirring to backfill the upper part of the top plate, it is possible to reduce the cost of processing the slime.

また、上部に仮設芯材を有する鋼製連壁芯材を用いて連続地中壁を形成し、頂版上部を埋め戻す際に仮設芯材を撤去することで、現場復旧が容易である。   Moreover, the continuous underground wall is formed using the steel continuous wall core material having the temporary core material at the upper part, and the temporary core material is removed when the upper part of the top plate is backfilled.

また、一対の連続地中壁の間の地盤上に型枠を配置して、型枠上に頂版を施工することで、頂版下面を精度よく施工することができる。この際、頂版の荷重は地盤が受けるため、型枠には強度が不要である。また、地下構造体の内部の掘削後、型枠をトンネル内から撤去することで、型枠の撤去が容易である。   Moreover, the bottom of the top plate can be constructed with high accuracy by arranging the mold on the ground between the pair of continuous underground walls and constructing the top on the mold. At this time, since the ground receives the load of the top plate, the formwork does not require strength. Moreover, after excavation inside the underground structure, the formwork can be easily removed by removing the formwork from the tunnel.

本発明によれば、プレキャスト部材を用いることなく、大幅な工期短縮と工費削減を図れる地下構造体の構築方法を提供することができる。   ADVANTAGE OF THE INVENTION According to this invention, the construction method of the underground structure which can aim at a significant shortening of a construction period and a construction cost reduction can be provided, without using a precast member.

鋼製連壁芯材7a、7bを建て込む工程を示す図。The figure which shows the process of incorporating steel continuous wall core material 7a, 7b. 連続地中壁11a、11bを施工する工程を示す図。The figure which shows the process of constructing the continuous underground wall 11a, 11b. 地盤改良部15を形成する工程を示す図。The figure which shows the process of forming the ground improvement part. 上部の切梁17を設置する工程を示す図。The figure which shows the process of installing the upper beam 17. FIG. 上部の一部を掘削する工程を示す図。The figure which shows the process of excavating a part of upper part. 頂版21を施工する工程を示す図。The figure which shows the process of constructing the top plate. 頂版21の上部を埋め戻す工程を示す図。The figure which shows the process of refilling the upper part of the top plate. 頂版21の下部を掘削し、底版25を施工する工程を示す図。The figure which shows the process of excavating the lower part of the top plate 21, and constructing the bottom plate 25. FIG. 地下構造体30を示す図。The figure which shows the underground structure 30. 地下構造体30を順に施工する工程を示す図。The figure which shows the process of constructing the underground structure 30 in order.

以下、図面に基づいて、本発明の実施形態について説明する。図1〜図10は、本実施の形態にかかる地下トンネルの構築方法を示す図である。なお、特に記載がない限り、各図の(a)は平面図、(b)は断面図を示す。   Hereinafter, embodiments of the present invention will be described with reference to the drawings. 1-10 is a figure which shows the construction method of the underground tunnel concerning this Embodiment. Unless otherwise specified, (a) in each drawing is a plan view and (b) is a cross-sectional view.

まず、用地境界A、Cの間を作業エリアD(AB間)と、切り回し道路E(BC間)とに区分し、作業エリアにガイドウォール3を設置する。なお、以下の作業は、作業エリアD内で行われ、切り回し道路Eは、車道として利用可能である。   First, the land boundaries A and C are divided into a work area D (between AB) and a cut-off road E (between BC), and a guide wall 3 is installed in the work area. The following work is performed in the work area D, and the cut-off road E can be used as a roadway.

ガイドウォール3の設置部においては、連続地中壁掘削機によって地盤1を掘削し、連続地中壁孔壁5を形成し、内部を安定液で安定させる。さらに、連続地中壁孔壁5には、クレーンによって鋼製連壁芯材7a、7bを建て込む(図中矢印F)。鋼製連壁芯材7a、7bの上部には、上部仮設芯材9が設けられる。上部仮設芯材9は、鋼製連壁芯材7a、7bに対して撤去可能である。   In the installation part of the guide wall 3, the ground 1 is excavated by a continuous underground wall excavator to form a continuous underground wall hole wall 5, and the inside is stabilized with a stabilizing liquid. Furthermore, steel continuous wall core materials 7a and 7b are built into the continuous underground wall hole wall 5 by a crane (arrow F in the figure). An upper temporary core material 9 is provided on the upper part of the steel continuous wall core materials 7a and 7b. The upper temporary core material 9 can be removed from the steel continuous wall core materials 7a and 7b.

次に、図2(a)、図2(b)に示すように、それぞれの連続地中壁孔壁5にコンクリートを打設して一対の連続地中壁11a、11b(側壁)を形成する。なお、まず、鋼製連壁芯材7aを建て込み、連続地中壁11aを構築した後、鋼製連壁芯材7bを建て込み、連続地中壁11bを構築してもよい。コンクリートは、上部仮設芯材9よりも下方の位置まで打設される。   Next, as shown in FIGS. 2 (a) and 2 (b), concrete is cast on each continuous underground wall hole wall 5 to form a pair of continuous underground walls 11a and 11b (side walls). . First, the steel continuous wall core 7a may be built to construct the continuous underground wall 11a, and then the steel continuous wall core 7b may be built to construct the continuous underground wall 11b. The concrete is cast to a position below the upper temporary core material 9.

次に、連続地中壁11a、11bの上部を砂等で埋め戻す。この際、用地境界ACの中央部の連続地中壁11bの上部には、上部仮設芯材9の外側(切り回し道路側)に土留め板10が設置される。   Next, the upper portions of the continuous underground walls 11a and 11b are backfilled with sand or the like. Under the present circumstances, the earth retaining plate 10 is installed in the upper part of the continuous underground wall 11b of the center part of the site boundary AC on the outer side (the cut road side) of the upper temporary core material 9.

次に、図3(a)、図3(b)に示すように、連続地中壁11a、11bの下部の間に、地盤改良部15を設ける。地盤改良部15は、後述する底版施工部の下部に形成され、先行地中梁として機能する。   Next, as shown in FIGS. 3A and 3B, a ground improvement portion 15 is provided between the lower portions of the continuous underground walls 11a and 11b. The ground improvement part 15 is formed in the lower part of the bottom plate construction part mentioned later, and functions as a preceding underground beam.

地盤改良部15は、例えば、高圧噴射撹拌によって形成される。この場合には、所定の間隔でスライムピット13を設け、スライムピット13において、地盤改良施工機を用いて地盤改良部15が形成される。この際、連続地中壁11a、11b間に隙間なく地盤改良部15が形成されることが望ましい。なお、地盤改良部15は、薬液注入等によって形成してもよい。また、地盤1に十分な強度がある場合には、地盤改良部15は必ずしも必要ではない。   The ground improvement part 15 is formed by high-pressure jet stirring, for example. In this case, slime pits 13 are provided at predetermined intervals, and the ground improvement portion 15 is formed in the slime pits 13 using a ground improvement construction machine. At this time, it is desirable that the ground improvement portion 15 is formed without a gap between the continuous underground walls 11a and 11b. The ground improvement part 15 may be formed by chemical injection or the like. Moreover, when the ground 1 has sufficient strength, the ground improvement unit 15 is not necessarily required.

次に、図4(a)、図4(b)に示すように、連続地中壁11a、11b間の上部(上部仮設芯材9同士の間)の地盤1の一部を掘削し、切梁17を設置する(図中矢印G)。切梁17は、上部仮設芯材9同士の間に設置される。なお、この際には、切り回し道路の一部が作業エリアとして使用される。   Next, as shown in FIGS. 4 (a) and 4 (b), a part of the ground 1 at the upper part (between the upper temporary core members 9) between the continuous underground walls 11a and 11b is excavated and cut. The beam 17 is installed (arrow G in the figure). The cut beam 17 is installed between the upper temporary core materials 9. In this case, a part of the cut road is used as a work area.

次に、図5(a)、図5(b)に示すように、連続地中壁11a、11b間の上部(上部仮設芯材9同士の間)の地盤1を、所定深さまで掘削する。例えば、頂版の型枠が設置可能な深さまで掘削する。なお、切梁17は、この深さまでの土圧に耐えられるものでよい。また、上部仮設芯材9等で土圧に耐えることができれば、切梁17は必ずしも必要ではない。   Next, as shown in FIGS. 5A and 5B, the ground 1 at the upper part (between the upper temporary core materials 9) between the continuous underground walls 11a and 11b is excavated to a predetermined depth. For example, excavation is performed to a depth where the formwork of the top plate can be installed. The cut beam 17 may be capable of withstanding earth pressure up to this depth. Moreover, if the upper temporary core material 9 etc. can withstand earth pressure, the cut beam 17 is not necessarily required.

掘削部の上面は平滑に仕上げられて沈下しないように転圧され、砕石が敷均される。次に、砂を表面に敷均して平滑にし、型枠19が設置される。   The upper surface of the excavation part is finished smoothly and pressed so as not to sink, and crushed stone is leveled. Next, sand is spread on the surface to make it smooth, and the mold 19 is installed.

次に、図6(a)、図6(b)に示すように、型枠19上に、鉄筋22を組み立てる。鉄筋22の端部は、溶接等によって鋼製連壁芯材7a、7bと一体化される。   Next, as shown in FIGS. 6A and 6B, the reinforcing bars 22 are assembled on the mold 19. The ends of the reinforcing bars 22 are integrated with the steel continuous wall cores 7a and 7b by welding or the like.

さらに、鉄筋22が埋まるようにコンクリートを打設し、一対の連続地中壁11a、11bの間の地盤上に頂版21を形成する。なお、頂版21の重量は、地盤によって支持されるため、前述した型枠19には強度は不要である。頂版21のコンクリートが硬化した後、必要に応じて防水処理が施される。また、連続地中壁11a上の上部仮設芯材9を固定するボルトを外し、上部仮設芯材9を撤去可能な状態とする。   Furthermore, concrete is cast so that the reinforcing bars 22 are buried, and the top plate 21 is formed on the ground between the pair of continuous underground walls 11a and 11b. In addition, since the weight of the top plate 21 is supported by the ground, the above-described mold frame 19 does not require strength. After the concrete of the top plate 21 is cured, waterproofing is performed as necessary. Moreover, the bolt which fixes the upper temporary core material 9 on the continuous underground wall 11a is removed, and it is set as the state which can remove the upper temporary core material 9. FIG.

次に、図7(a)、図7(b)に示すように、頂版21の上部を地表面まで埋め戻す。また、連続地中壁11a上の上部仮設芯材9を撤去する(図中矢印H)。なお、前述した地盤改良部15が高圧噴射撹拌によって行われる場合には、高圧噴射撹拌によって生じたスライムに発生土を混ぜて流動化処理土とし、これを用いて、頂版21の上部を埋め戻してもよい。   Next, as shown in FIGS. 7A and 7B, the upper part of the top plate 21 is backfilled to the ground surface. Moreover, the upper temporary core material 9 on the continuous underground wall 11a is removed (arrow H in the figure). In addition, when the ground improvement part 15 mentioned above is performed by high-pressure jet stirring, the generated soil is mixed with the slime generated by high-pressure jet stirring to make fluidized treated soil, and this is used to fill the upper part of the top plate 21. You may return.

頂版21の上部が埋め戻されると、用地境界AC間は、道路として使用することができる。   When the upper part of the top plate 21 is backfilled, the land boundary AC can be used as a road.

次に、図8(a)の断面図に示すように、連続地中壁11a、11bおよび頂版21で囲まれた空間を掘削する(図中矢印I)。掘削は、バックホウなどによって行われ、地下構造体の長手方向に向かって掘り進められる。この際、型枠19をトンネル内から撤去する。型枠19によって、頂版21の下面は平滑に施工される。   Next, as shown in the sectional view of FIG. 8A, a space surrounded by the continuous underground walls 11a and 11b and the top plate 21 is excavated (arrow I in the figure). The excavation is performed with a backhoe or the like, and is excavated in the longitudinal direction of the underground structure. At this time, the mold 19 is removed from the tunnel. By the mold 19, the lower surface of the top plate 21 is applied smoothly.

地盤改良部15まで掘削が完了すると、図8(b)に示すように、地盤改良部15上に均しコンクリート23を打設して平らにし、均しコンクリート23上に鉄筋を組み立て、コンクリートを打設し、底版25が施工される。すなわち、連続地中壁11a、11b、頂版21で囲まれた空間の底部に、底版25が施工される。   When excavation to the ground improvement part 15 is completed, as shown in FIG. 8 (b), the leveling concrete 23 is placed on the ground improvement part 15 to make it flat, and a reinforcing bar is assembled on the leveling concrete 23 to put the concrete. The bottom slab 25 is installed. That is, the bottom plate 25 is constructed at the bottom of the space surrounded by the continuous underground walls 11 a and 11 b and the top plate 21.

この状態から、用地境界ACの間を作業エリアD(BC間)と、切り回し道路E(AB間)とに区分する。作業エリアでは、前述した工程と同様の工程でさらにトンネルを施工する。   From this state, the land boundary AC is divided into a work area D (between BC) and a cut-off road E (between AB). In the work area, a tunnel is further constructed in the same process as described above.

図9は、この様にして形成された地下構造体30(地下トンネル)を示す断面図である。なお、連続地中壁11b、11c間に頂版21を形成した後には、連続地中壁11b、11cの上部仮設芯材9がそれぞれ撤去される。また、トンネル内部の舗装や内装工を行うことで、地下構造体30が施工される。   FIG. 9 is a cross-sectional view showing the underground structure 30 (underground tunnel) formed in this way. In addition, after forming the top plate 21 between the continuous underground walls 11b and 11c, the upper temporary core material 9 of the continuous underground walls 11b and 11c is each removed. Moreover, the underground structure 30 is constructed by pavement and interior work inside the tunnel.

図10は、以上の工程を同時進行で行う状態を示す図である。図10においては、右側から順に施工が行われ、地下トンネルが施工される。   FIG. 10 is a diagram showing a state in which the above steps are performed simultaneously. In FIG. 10, construction is performed in order from the right side, and an underground tunnel is constructed.

図10のJ位置の状態は、図1に対応する位置である。すなわち、連続地中壁孔壁5が施工された状態である。同様に、図10のK位置の状態は、図2に対応する位置である。すなわち、連続地中壁11a、11bが施工された状態である。   The state of the J position in FIG. 10 is a position corresponding to FIG. That is, it is the state where the continuous underground wall hole wall 5 was constructed. Similarly, the state of the K position in FIG. 10 is a position corresponding to FIG. That is, it is the state where the continuous underground walls 11a and 11b were constructed.

図10のL位置の状態は、図3に対応する位置である。すなわち、地盤改良部15が施工された状態である。図10のM位置の状態は、図4に対応する位置である。すなわち、切梁17が設置された状態である。   The state of the L position in FIG. 10 is a position corresponding to FIG. That is, it is the state where the ground improvement part 15 was constructed. The state of the M position in FIG. 10 is a position corresponding to FIG. That is, it is a state where the cutting beam 17 is installed.

図10のN位置の状態は、図5に対応する位置である。すなわち、連続地中壁11a、11bの上部まで掘削された状態である。図10のO位置の状態は、図6に対応する位置である。すなわち、頂版21が施工された状態である。   The state of the N position in FIG. 10 is a position corresponding to FIG. That is, it is the state excavated to the upper part of continuous underground wall 11a, 11b. The state at the O position in FIG. 10 is a position corresponding to FIG. That is, the top plate 21 is in a state of being constructed.

図10のP位置の状態は、図7に対応する位置である。すなわち、頂版21が埋め戻された状態である。図10のQ位置の状態は、図8(a)に対応する位置である。すなわち、頂版21の下部が掘削された状態である。なお、掘削された発生土は、図中右側の坑口より搬出される。   The state of the P position in FIG. 10 is a position corresponding to FIG. That is, the top plate 21 is backfilled. The state of the Q position in FIG. 10 is a position corresponding to FIG. That is, the lower part of the top plate 21 is excavated. In addition, the excavated generated soil is carried out from the right well entrance in the figure.

図10のR位置の状態は、図8(b)に対応する位置である。すなわち、地盤改良部15上に配置された均しコンクリート23上に鉄筋26が組み立てられて底版25が施工された状態である。   The state of the R position in FIG. 10 is a position corresponding to FIG. That is, the bottom slab 25 is constructed by assembling the reinforcing bars 26 on the leveling concrete 23 arranged on the ground improvement portion 15.

以上のように、各工程はトンネルの各部において同時進行で行うことができる。例えば、頂版21上を埋め戻す工程と、頂版21の下部を掘削する工程は同時に行ってもよい。   As described above, each process can be performed simultaneously in each part of the tunnel. For example, the step of backfilling the top plate 21 and the step of excavating the lower portion of the top plate 21 may be performed simultaneously.

以上、本実施の形態によれば、トンネル内部の掘削時には、地表部を道路としても使用できることから、効率よく地下構造体30を構築することができ、大幅な工期短縮・工費削減を図ることができる。また、地表部の使用期間が短いため、近隣に対する環境負荷を低減することができる。例えば、図10において、P状態以降の工程時には、地表部における作業領域をなくすことができる。特に、地表部の使用期間が短く、切り回し道路を利用することができるため、アンダーパスなどへの採用も有効である。   As described above, according to the present embodiment, when excavating inside the tunnel, the surface portion can be used as a road, so that the underground structure 30 can be efficiently constructed, and the construction period can be greatly reduced and the construction cost can be reduced. it can. Moreover, since the use period of the surface part is short, the environmental load on the neighborhood can be reduced. For example, in FIG. 10, the work area in the ground surface can be eliminated during the process after the P state. In particular, the use period for the underpass and the like is effective because the ground surface is used for a short period of time and can be turned around.

また、連続地中壁11a、11b、頂版21、地盤改良部15によって土圧が支持されるため、トンネル内部の掘削時に、支保工や切梁の設置を削減することができる。このため、工期を短縮することができる。   Moreover, since earth pressure is supported by the continuous underground walls 11a and 11b, the top plate 21, and the ground improvement part 15, the excavation inside a tunnel can reduce installation of a support work and a beam. For this reason, a construction period can be shortened.

また、頂版21を施工するために型枠支保工を使用せず、高所作業も少ないため安全に作業を行うことができる。また、頂版21用の型枠19は、頂版21の下面を平滑にする目的のみであるため、強度が不要である。   In addition, no formwork support is used to construct the top plate 21, and work can be performed safely because there is little work at high places. Moreover, since the formwork 19 for the top plate 21 is only for the purpose of smoothing the lower surface of the top plate 21, strength is not required.

地盤改良部15が高圧噴射撹拌によって形成される場合において、高圧噴射撹拌によって生じたスライムを利用して頂版21の上部を埋め戻すことで、スライムの廃棄処理量を削減することができる。   When the ground improvement part 15 is formed by high-pressure jet stirring, the amount of slime discarded can be reduced by backfilling the upper part of the top plate 21 using slime generated by high-pressure jet stirring.

また、上部仮設芯材を撤去可能とすることで、トンネル施工後に、不要な土留め壁が地中に残ることがない。   Moreover, by making it possible to remove the upper temporary core material, unnecessary earth retaining walls do not remain in the ground after tunnel construction.

以上、添付図を参照しながら、本発明の実施形態を説明したが、本発明の技術的範囲は、前述した実施形態に左右されない。当業者であれば、特許請求の範囲に記載された技術的思想の範疇内において各種の変更例または修正例に想到し得ることは明らかであり、それらについても当然に本発明の技術的範囲に属するものと了解される。   As mentioned above, although embodiment of this invention was described referring an accompanying drawing, the technical scope of this invention is not influenced by embodiment mentioned above. It is obvious for those skilled in the art that various modifications or modifications can be conceived within the scope of the technical idea described in the claims, and these are naturally within the technical scope of the present invention. It is understood that it belongs.

1………地盤
3………ガイドウォール
5………連続地中壁孔壁
7a、7b………鋼製連壁芯材
9………上部仮設芯材
10………土留め板
11a、11b、11c………連続地中壁
13………スライムピット
15………地盤改良部
17………切梁
19………型枠
21………頂版
22………鉄筋
23………均しコンクリート
25………底版
26………鉄筋
30………地下構造体
DESCRIPTION OF SYMBOLS 1 ......... Ground 3 ......... Guide wall 5 ......... Continuous underground wall hole wall 7a, 7b ......... Steel continuous wall core material 9 ......... Upper temporary core material 10 ......... Dust plate 11a, 11b, 11c …… Continuous underground wall 13 ……… Slime pit 15 ……… Ground improvement part 17 ……… Cut beam 19 ……… Formwork 21 ……… Top plate 22 ……… Rebar 23 ……… Leveling concrete 25 ………… Bottom plate 26 ………… Rebar 30 ……… Underground structure

Claims (5)

地盤中に連続地中壁を構築する工程aと、
一対の前記連続地中壁の間の地盤上に頂版を施工する工程bと、
前記連続地中壁および前記頂版で囲まれた空間を地下構造体の長手方向に向かって掘削する工程cと、
前記連続地中壁および前記頂版で囲まれた空間の底部に底版を施工する工程dと、
を具備することを特徴とする地下構造体の構築方法。
Constructing a continuous underground wall in the ground; and
A step b of installing a top plate on the ground between the pair of continuous underground walls;
A step c of excavating a space surrounded by the continuous underground wall and the top plate in a longitudinal direction of an underground structure;
A step d of constructing a bottom plate at the bottom of the space surrounded by the continuous underground wall and the top plate;
The construction method of the underground structure characterized by comprising.
前記工程aと前記工程bの間に、前記底版を施工する部位の下方に地中梁として地盤改良部を施工する工程eを具備することを特徴とする請求項1記載の地下構造体の構築方法。   The construction of an underground structure according to claim 1, further comprising a step (e) of constructing a ground improvement portion as an underground beam between the step (a) and the step (b). Method. 前記工程eは、高圧噴射撹拌によって行われ、前記工程bの後であって、前記工程cの前または前記工程cと同時に、高圧噴射撹拌によって生じたスライムを用いて、前記頂版の上部を埋め戻す工程fを具備することを特徴とする請求項2記載の地下構造体の構築方法。   The step e is performed by high-pressure jet agitation, and after the step b, before the step c or simultaneously with the step c, using the slime generated by the high-pressure jet agitation, The method for constructing an underground structure according to claim 2, further comprising a step (f) of backfilling. 前記工程aは、上部に仮設芯材を有する鋼製連壁芯材を用いて行われ、
前記工程bの後に、前記仮設芯材を撤去することを特徴とする請求項1から請求項3のいずれかに記載の地下構造体の構築方法。
The step a is performed using a steel continuous wall core material having a temporary core material at the top,
The method for constructing an underground structure according to any one of claims 1 to 3, wherein the temporary core material is removed after the step b.
前記工程bは、一対の前記連続地中壁の間を所定深さまで掘削し、一対の前記連続地中壁の間の地盤上に型枠を配置して、前記型枠上に前記頂版を施工し、
前記工程cの後に、前記型枠を地下構造体内から撤去することを特徴とする請求項1から請求項4のいずれかに記載の地下構造体の構築方法。
The step b includes excavating a predetermined depth between the pair of continuous underground walls, placing a formwork on the ground between the pair of continuous underground walls, and placing the top plate on the formwork. Construct,
The method for constructing an underground structure according to any one of claims 1 to 4, wherein the formwork is removed from the underground structure after the step c.
JP2016100293A 2016-05-19 2016-05-19 Method of constructing underground structure Pending JP2017206882A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016100293A JP2017206882A (en) 2016-05-19 2016-05-19 Method of constructing underground structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016100293A JP2017206882A (en) 2016-05-19 2016-05-19 Method of constructing underground structure

Publications (1)

Publication Number Publication Date
JP2017206882A true JP2017206882A (en) 2017-11-24

Family

ID=60416409

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016100293A Pending JP2017206882A (en) 2016-05-19 2016-05-19 Method of constructing underground structure

Country Status (1)

Country Link
JP (1) JP2017206882A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110017144A (en) * 2019-04-04 2019-07-16 甘肃省交通规划勘察设计院股份有限公司 A kind of three step construction method of loess tunnel considering bottom stab ilization processing

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579049A (en) * 1991-09-20 1993-03-30 Fujita Corp Constructing method for beam and slab in underground body construction work
JPH05331843A (en) * 1992-05-29 1993-12-14 Nippon Steel Corp Connecting method for underground continuous wall and floor slab
JPH09125427A (en) * 1995-11-07 1997-05-13 Taisei Corp Construction method of basement floor
JP2000265458A (en) * 1999-03-19 2000-09-26 Penta Ocean Constr Co Ltd Floor slab connecting structure for underground structure with precast pile underground wall
JP2000265484A (en) * 1999-03-19 2000-09-26 Penta Ocean Constr Co Ltd CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL
JP2001032428A (en) * 1999-07-22 2001-02-06 Taisei Corp Floorslab construction method
JP2010222944A (en) * 2009-03-25 2010-10-07 Tenox Corp Wall member for continuous underground wall, construction method for continuous underground wall, and continuous underground wall
JP2011122386A (en) * 2009-12-14 2011-06-23 Toda Constr Co Ltd Method of construction of underground structure, underground structure, and precast concrete side wall or intermediate wall/column for the same
JP2012122190A (en) * 2010-12-06 2012-06-28 Taisei Corp Underground structure and construction method for the same
KR101293550B1 (en) * 2012-05-24 2013-08-06 유제남 Construction method of underground structure
JP2015117545A (en) * 2013-12-19 2015-06-25 鹿島建設株式会社 Construction method for underground tunnel
KR20150143952A (en) * 2014-06-13 2015-12-24 한국철도기술연구원 Method for constructing underground structure having precast wall using h-pile, method for connecting precast wall and slab

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0579049A (en) * 1991-09-20 1993-03-30 Fujita Corp Constructing method for beam and slab in underground body construction work
JPH05331843A (en) * 1992-05-29 1993-12-14 Nippon Steel Corp Connecting method for underground continuous wall and floor slab
JPH09125427A (en) * 1995-11-07 1997-05-13 Taisei Corp Construction method of basement floor
JP2000265458A (en) * 1999-03-19 2000-09-26 Penta Ocean Constr Co Ltd Floor slab connecting structure for underground structure with precast pile underground wall
JP2000265484A (en) * 1999-03-19 2000-09-26 Penta Ocean Constr Co Ltd CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL
JP2001032428A (en) * 1999-07-22 2001-02-06 Taisei Corp Floorslab construction method
JP2010222944A (en) * 2009-03-25 2010-10-07 Tenox Corp Wall member for continuous underground wall, construction method for continuous underground wall, and continuous underground wall
JP2011122386A (en) * 2009-12-14 2011-06-23 Toda Constr Co Ltd Method of construction of underground structure, underground structure, and precast concrete side wall or intermediate wall/column for the same
JP2012122190A (en) * 2010-12-06 2012-06-28 Taisei Corp Underground structure and construction method for the same
KR101293550B1 (en) * 2012-05-24 2013-08-06 유제남 Construction method of underground structure
JP2015117545A (en) * 2013-12-19 2015-06-25 鹿島建設株式会社 Construction method for underground tunnel
KR20150143952A (en) * 2014-06-13 2015-12-24 한국철도기술연구원 Method for constructing underground structure having precast wall using h-pile, method for connecting precast wall and slab

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
君島喜一郎 外5名: "大深度地盤改良による遮水層の造成", 土木学会第59回年次学術講演会, vol. 第59巻、6−223, JPN6019050681, September 2004 (2004-09-01), JP, pages 445 - 446, ISSN: 0004328067 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110017144A (en) * 2019-04-04 2019-07-16 甘肃省交通规划勘察设计院股份有限公司 A kind of three step construction method of loess tunnel considering bottom stab ilization processing
CN110017144B (en) * 2019-04-04 2020-12-04 甘肃省交通规划勘察设计院股份有限公司 Loess tunnel three-step construction method considering substrate reinforcement treatment

Similar Documents

Publication Publication Date Title
KR101205783B1 (en) The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously
KR101388521B1 (en) Construction method of underground structure under the pier with supporting piles
JP6186267B2 (en) How to build an underground tunnel
JP6543176B2 (en) Building method
JP2009057680A (en) Structure and method for supporting covering plate
JP3586864B2 (en) Underground structure construction method and elevated traffic path
KR101324231B1 (en) Soil cement wall structure and method for constructing thereof
JP5843413B1 (en) Lowering method of existing tunnel
JP2017206882A (en) Method of constructing underground structure
JP2000352296A (en) Method o constructing passage just under underground structure
KR20160131410A (en) Temporary construction and originally construction the outer layer of a 2-layer wall type underground road building method
JP4226954B2 (en) Underpinning method and viaduct
JP7232714B2 (en) how to build a foundation
JP6543177B2 (en) Building method
CN104963348A (en) Soft soil area tower crane foundation construction supporting structure and construction method thereof
JP7204228B2 (en) Underground beam construction method
JP5073960B2 (en) Construction method of underground structure and underground structure
JP6378873B2 (en) Artificial ground and construction method of artificial ground
KR101971554B1 (en) Method constructuring an underground structure using a temporary structure
JP2011241608A (en) Construction method of basement in existing house
JP7193994B2 (en) Strut construction method
JP6718767B2 (en) Composite of soil structure and concrete structure and its construction method
JP2003278173A (en) Construction method of underground structure
KR200291370Y1 (en) Concrete caisson structure for earth and sand guard of pier's basis
JP2016204848A (en) Vertical shaft construction method and underground storage tank construction method

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190130

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20191216

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200107

A521 Request for written amendment filed

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200212

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20200825

A02 Decision of refusal

Free format text: JAPANESE INTERMEDIATE CODE: A02

Effective date: 20210302