JP6710999B2 - Temporary receiving method for existing structures - Google Patents

Temporary receiving method for existing structures Download PDF

Info

Publication number
JP6710999B2
JP6710999B2 JP2016024633A JP2016024633A JP6710999B2 JP 6710999 B2 JP6710999 B2 JP 6710999B2 JP 2016024633 A JP2016024633 A JP 2016024633A JP 2016024633 A JP2016024633 A JP 2016024633A JP 6710999 B2 JP6710999 B2 JP 6710999B2
Authority
JP
Japan
Prior art keywords
foundation
footing
reinforcing
existing structure
ground
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
JP2016024633A
Other languages
Japanese (ja)
Other versions
JP2017141626A (en
Inventor
眞弘 佐藤
眞弘 佐藤
実 水本
実 水本
利光 坂井
利光 坂井
真 荒川
真 荒川
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Obayashi Corp
Original Assignee
Obayashi Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Obayashi Corp filed Critical Obayashi Corp
Priority to JP2016024633A priority Critical patent/JP6710999B2/en
Publication of JP2017141626A publication Critical patent/JP2017141626A/en
Application granted granted Critical
Publication of JP6710999B2 publication Critical patent/JP6710999B2/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Description

本発明は、フーチング基礎で支持された既設構造物の仮受け工法に関する。 The present invention relates to a method for temporarily receiving an existing structure supported by a footing foundation.

従来より、既設構造物の基礎下または中間層に免震装置を組み込むことにより、既設構造物を大幅に改修することなく免震構造物にする免震レトロフィットが知られている。なかでも、既設構造物の基礎下に免震装置を介装する際には、既設構造物の鉛直荷重を既設基礎から仮受け部材に盛り替える作業を行ったうえで、基礎下に免震装置を介装するための空間を設ける必要が生じる。 BACKGROUND ART Conventionally, a seismic isolation retrofit has been known in which a seismic isolation device is incorporated into a foundation or an intermediate layer of an existing structure to make the existing structure a seismic isolated structure without being significantly modified. Above all, when installing a seismic isolation device under the foundation of an existing structure, the vertical load of the existing structure is transferred from the existing foundation to a temporary receiving member, and then the seismic isolation device is installed under the foundation. It becomes necessary to provide a space for interposing.

例えば、特許文献1では、まず、フーチング基礎間を繋ぐ基礎梁下を一次掘削して基礎梁を補強した後、補強した基礎梁下を二次掘削したうえで、基礎梁下と掘削底面との間に仮受け部材を設置する。次に、当該仮受け部材にて既存建物の全鉛直荷重を仮受けした状態でフーチング基礎下を掘削し、フーチング基礎の下方に耐圧版を構築する。そして、耐圧版とフーチング基礎との間に仮受け部材を設置し、既存建物の全鉛直荷重を基礎梁下の仮受け部材からフーチング基礎下の仮受け部材に盛り替える。 For example, in Patent Document 1, first, the bottom of a foundation beam that connects footing foundations is first excavated to reinforce the foundation beam, then the bottom of the reinforced foundation beam is secondarily excavated, and then the bottom of the foundation beam and the excavated bottom surface are A temporary receiving member is installed between them. Next, the footing foundation is excavated with the temporary receiving member temporarily receiving the total vertical load of the existing building, and a pressure plate is constructed below the footing foundation. Then, a temporary receiving member is installed between the pressure plate and the footing foundation, and the total vertical load of the existing building is changed from the temporary receiving member under the foundation beam to the temporary receiving member under the footing foundation.

この後、基礎梁下の仮受け部材を撤去して基礎梁の下方に耐圧版を構築した後、耐圧版と基礎梁との間に仮受け部材を設置し、既存建物の全鉛直荷重をフーチング基礎下の仮受け部材から基礎梁下の仮受け部材に盛り替え、フーチング基礎下の仮受け部材を撤去する。こうして形成された耐圧版とフーチング基礎との間の空間に、免震装置を介装する。 After this, after removing the temporary receiving member under the foundation beam and constructing a pressure resistant plate below the foundation beam, a temporary receiving member is installed between the pressure resistant plate and the foundation beam to foot the entire vertical load of the existing building. Replace the temporary receiving member under the foundation with the temporary receiving member under the foundation beam, and remove the temporary receiving member under the footing foundation. A seismic isolation device is installed in the space between the pressure plate and the footing foundation thus formed.

特開2011−7008号公報JP, 2011-7008, A

上記の方法において、補強した基礎梁下を二次掘削する場合、床スラブの撤去が可能であれば、基礎梁で囲まれ上方が開放された領域から基礎梁下の掘削作業や仮受け部材の設置を、効率よく行うことが可能である。 In the above method, in the case of secondary excavation under the reinforced foundation beam, if the floor slab can be removed, the excavation work under the foundation beam and the temporary receiving member of the area surrounded by the foundation beam and open above Installation can be performed efficiently.

しかし、床スラブを撤去できない条件下では、既設構造物の基礎梁下を通り抜け可能な作業坑を隣り合うフーチング基礎の間に、基礎梁下に仮受け部材が設置できる深さまで掘削して構築し、基礎梁を補強したうえで、当該作業坑からフーチング基礎に向かって基礎梁下を作業坑の底面深さまで二次掘削した後、仮受け部材を設置することとなる。この場合において、例えば掘削のり面が内部摩擦角より急峻になると、のり面の崩落が生じやすく作業者の安全を確保できない。また、フーチング基礎に近づくにつれて応力の影響範囲を掘削することとなり、地盤が十分な地耐力を有していない場合には、フーチング基礎下において地盤が緩み、不等沈下を生じかねない。 However, under the condition that the floor slab cannot be removed, a work pit that can pass under the foundation beam of the existing structure is constructed by excavating between adjacent footing foundations to a depth where temporary support members can be installed under the foundation beam. After reinforcing the foundation beam, after the secondary excavation from the work pit toward the footing foundation under the foundation beam to the bottom depth of the work pit, the temporary receiving member is installed. In this case, for example, when the excavated slope becomes steeper than the internal friction angle, the slope is likely to collapse and the safety of the operator cannot be ensured. Further, as the footing foundation is approached, the area affected by the stress is excavated, and if the ground does not have sufficient bearing capacity, the ground may loosen under the footing foundation and uneven settlement may occur.

一方で、床スラブを撤去できない条件下における一般的な従来工法としては、隣り合うフーチング基礎の間に作業坑を構築し、フーチング基礎の底面レベルまで1次掘削を行った後、フーチング基礎および基礎梁を補強したうえで、作業坑内にて仮受け杭を打設しつつ、基礎梁下を二次掘削する方法が知られている。 On the other hand, as a general conventional method under the condition that the floor slab cannot be removed, a work pit is constructed between adjacent footing foundations, and after performing primary excavation to the bottom level of the footing foundations, the footing foundations and foundations are A method is known in which the beam is reinforced and then a secondary pile is excavated under the foundation beam while placing a temporary receiving pile in the work pit.

特許文献1に記載の方法および一般的な従来工法のいずれの場合にも、基礎梁下を二次掘削する場合には土留めを設けるだけでなく、掘削を進めるごとに基礎梁下の空間に仮受け部材もしくは仮受け杭を逐次設置し、フーチング基礎が支持する既存建物の鉛直荷重を段階的に盛り替える作業を実施しなければならず、作業が煩雑であるとともに施工が長期化しやすい。 In both cases of the method described in Patent Document 1 and the general conventional construction method, when secondary excavation under the foundation beam is performed, not only is earth retaining provided, but also a space under the foundation beam is provided each time the excavation proceeds. Temporary receiving members or temporary receiving piles must be installed one by one and the vertical load of the existing building supported by the footing foundation must be changed stepwise, which is complicated and the construction is likely to take a long time.

本発明は、かかる課題に鑑みなされたものであって、その主な目的は、床スラブを撤去できない環境下においても、フーチング基礎で直接支持された既設構造物の鉛直荷重を、効率よく仮受けすることの可能な、既設構造物の仮受け工法を提供することである。 The present invention has been made in view of such problems, and its main purpose is to efficiently temporarily receive a vertical load of an existing structure directly supported by a footing foundation even in an environment in which a floor slab cannot be removed. It is to provide a temporary receiving method for existing structures that can be done.

かかる目的を達成するため、本発明の既設構造物の仮受け工法は、フーチング基礎で直接支持された既設構造物の鉛直荷重を仮受けするための既設構造物の仮受け工法であって、一次掘削として、隣り合う前記フーチング基礎の中間位置をフーチング基礎の底面より下方の深さまで掘削し溝状の作業坑を構築するとともに、基礎梁の周囲を前記フーチング基礎の底面の深さまで掘削し補強空間を構築する第1の工程と、前記補強空間を利用して、前記基礎梁およびフーチング基礎を補強する第2の工程と、前記フーチング基礎下およびその周囲を地盤改良する第3の工程と、二次掘削として、前記フーチング基礎下の地盤を残して前記基礎梁下の地盤を、前記作業坑から前記フーチング基礎に向かって前記作業坑の掘削底に至る深さまで掘削する第4の工程と、前記基礎梁下と前記フーチング基礎下のうち、少なくともいずれか一方に仮受け杭を打設する第5の工程と、を備えることを特徴とする。 To achieve the above object, temporary supporting method of the existing structure of the present invention is a temporary supporting method of existing structures for receiving temporary vertical load directly supported existing structures in footing foundation, primary As excavation, the intermediate position of the adjacent footing foundations is excavated to a depth below the bottom surface of the footing foundation to construct a groove-like working pit, and the periphery of the foundation beam is excavated to the depth of the bottom surface of the footing foundation to provide a reinforcement space. a first step of constructing a, by using the reinforcing space, a second step of reinforcing the foundation beam and footing foundation, and a third step of ground improvement the footing foundation and under its periphery two As the next excavation, a fourth step of excavating the ground under the foundation beam leaving the ground under the footing foundation to a depth from the work pit toward the footing foundation to the bottom of the work pit , A fifth step of placing a temporary support pile under at least one of the foundation beam and the footing foundation.

上述する本発明の既設構造物の仮受け工法によれば、地盤改良を実施したうえで基礎梁下を二次掘削することにより、掘削のり面の崩落が生じにくくなるため、床スラブを撤去できず、床スラブ下に作業坑を構築して当該作業坑からフーチング基礎に向けて二次掘削を進める場合にも、安全に二次掘削を実施することが可能となる。また、二次掘削の後に、基礎梁下のフーチング基礎近傍に仮受杭を打設することも可能となるため、基礎梁の曲げ耐力向上のための補強も低減できる。 According to the method for temporarily receiving the existing structure of the present invention described above, the ground slab can be removed because the excavation slope is less likely to collapse by performing the secondary excavation under the foundation beam after performing the ground improvement. Instead, it is possible to safely perform the secondary excavation even when a working pit is constructed under the floor slab and the secondary digging is advanced from the working pit toward the footing foundation. Further, after the secondary excavation, it is possible to drive a temporary support pile near the footing foundation under the foundation beam, so that the reinforcement for improving the bending resistance of the foundation beam can be reduced.

また、フーチング基礎下の地盤改良を行うことによりフーチング基礎下の地耐力が向上することから、既設構造物の荷重によっては基礎梁下に仮受け杭を打設しなくても、二次掘削を行うことができる。この場合は、基礎梁下を二次掘削するにあたり、基礎梁下に多数の仮受け部材を設置して、当該仮受け部材に既設構造物の鉛直荷重を段階的に盛り替える作業を省略でき、二次掘削の作業性を大幅に向上することが可能となる。 In addition, since the ground strength under the footing foundation is improved by improving the ground under the footing foundation, depending on the load of the existing structure, secondary excavation may be performed without placing temporary support piles under the foundation beam. It can be carried out. In this case, when performing secondary excavation under the foundation beam, it is possible to install a large number of temporary receiving members under the foundation beam and omit the work of stepwise reassembling the vertical load of the existing structure on the temporary receiving member. It is possible to significantly improve the workability of secondary excavation.

また、本発明の既設構造物の仮受け工法は、前記第4の工程では、前記基礎梁下を二次掘削するとともに、前記フーチング基礎下に残置された地盤を拘束部材にて拘束することを特徴とする。 Further, in the temporary receiving method for the existing structure of the present invention, in the fourth step, secondary excavation under the foundation beam is performed, and the ground remaining under the footing foundation is constrained by a constraining member. Characterize.

上述する本発明の既設構造物の仮受け工法によれば、フーチング基礎下の地盤は、地盤改良と拘束部材の両者により地耐力が大幅に向上する。このため、フーチング基礎一体あたりが負担する鉛直荷重が大きい場合にも、支持することが可能となる。 According to the above-described method for temporarily receiving an existing structure according to the present invention, the ground strength under the footing foundation is significantly improved by both the ground improvement and the restraining member. Therefore, it is possible to support even when the vertical load applied to the footing foundation is large.

本発明によれば、フーチング基礎下およびその周囲を地盤改良した後に基礎梁下の二次掘削を行うことにより、床スラブを撤去できない環境下においても、床スラブ下に構築した作業坑を利用して効率よく安全に、既設構造物の仮受け工に係る作業を実施することが可能となる。 According to the present invention, by performing the secondary excavation under the foundation beam after improving the ground under the footing foundation and its surroundings, even in an environment where the floor slab cannot be removed, the work pit constructed under the floor slab is used. Therefore, it becomes possible to efficiently and safely carry out the work related to the temporary receiving work of the existing structure.

本発明における既設構造物の仮受け工法の第1の実施の形態の手順を示す図である(その1)。It is a figure which shows the procedure of 1st Embodiment of the temporary receiving method of the existing structure in this invention (the 1). 本発明における既設構造物の仮受け工法の第1の実施の形態の手順を示す図である(その2)。It is a figure which shows the procedure of 1st Embodiment of the temporary receiving method of the existing structure in this invention (the 2). 本発明における既設構造物の仮受け工法の第1の実施の形態の手順を示す図である(その3)。It is a figure which shows the procedure of 1st Embodiment of the temporary receiving construction method of the existing structure in this invention (the 3). 本発明における既設構造物の仮受け工法の第1の実施の形態の手順を示す図である(その4)。It is a figure which shows the procedure of 1st Embodiment of the temporary receiving construction method of the existing structure in this invention (the 4). 本発明における既設構造物の仮受け工法の第1の実施の形態の手順を示す図である(その5)。It is a figure which shows the procedure of 1st Embodiment of the temporary receiving construction method of the existing structure in this invention (the 5). 本発明における既設構造物の仮受け工法の第1の実施の形態の手順を示す図である(その6)。It is a figure which shows the procedure of 1st Embodiment of the temporary receiving construction method of the existing structure in this invention (the 6). 本発明における既設構造物の仮受け工法の第2の実施の形態の手順を示す図である(その1)。It is a figure which shows the procedure of 2nd Embodiment of the temporary receiving construction method of the existing structure in this invention (the 1). 本発明における既設構造物の仮受け工法の第2の実施の形態の手順を示す図である(その2)。It is a figure which shows the procedure of 2nd Embodiment of the temporary receiving construction method of the existing structure in this invention (the 2). 本発明における既設構造物の仮受け工法の第2の実施の形態の手順を示す図である(その3)。It is a figure which shows the procedure of 2nd Embodiment of the temporary receiving construction method of the existing structure in this invention (the 3). 本発明における既設構造物の仮受け工法の第3の実施の形態の手順を示す図である(その1)。It is a figure which shows the procedure of 3rd Embodiment of the temporary receiving construction method of the existing structure in this invention (the 1). 本発明における既設構造物の仮受け工法の第3の実施の形態の手順を示す図である(その2)。It is a figure which shows the procedure of 3rd Embodiment of the temporary receiving construction method of the existing structure in this invention (the 2). 本発明における既設構造物の仮受け工法の第4の実施の形態の手順を示す図である(その1)。It is a figure which shows the procedure of 4th Embodiment of the temporary receiving construction method of the existing structure in this invention (the 1). 本発明における既設構造物の仮受け工法の第4の実施の形態の手順を示す図である(その2)。It is a figure which shows the procedure of 4th Embodiment of the temporary receiving construction method of the existing structure in this invention (the 2). 本発明における既設構造物の仮受け工法の第4の実施の形態の手順を示す図である(その3)。It is a figure which shows the procedure of 4th Embodiment of the temporary receiving construction method of the existing structure in this invention (the 3).

本発明は、例えばフーチング基礎下に空間を設けて免震装置を介装する免震レトロフィットを実施する場合等に採用するものであり、既設構造物の鉛直荷重の一部を仮受け杭に仮受する方法に関する発明である。以下に、図1〜図14を参照して既設構造物の仮受け工法を詳述する。 INDUSTRIAL APPLICABILITY The present invention is adopted, for example, when performing a seismic isolation retrofit in which a space is provided under a footing foundation to interpose a seismic isolation device, and a part of the vertical load of an existing structure is temporarily used as a temporary support pile. It is an invention relating to a method of temporarily receiving. Hereinafter, the method for temporarily receiving the existing structure will be described in detail with reference to FIGS. 1 to 14.

図1(a)で示すように、既設構造物1はフーチング基礎21にて支持される構造物であり、フーチング基礎21間は基礎梁22を介して連結されている。そして、基礎梁22の上方には床スラブ3が設置されているが、本実施の形態では、床スラブ3を撤去することなくフーチング基礎21または基礎梁22下に仮受け杭を設置し、既設構造物1の鉛直荷重を仮受けする方法を、順を追って説明する。 As shown in FIG. 1A, the existing structure 1 is a structure supported by a footing foundation 21, and the footing foundations 21 are connected to each other via foundation beams 22. Then, the floor slab 3 is installed above the foundation beam 22, but in the present embodiment, a temporary receiving pile is installed under the footing foundation 21 or the foundation beam 22 without removing the floor slab 3, and the existing slab is installed. A method of temporarily receiving the vertical load of the structure 1 will be described step by step.

<第1の実施の形態>
まず、第1の工程では図1(b)で示すように、作業坑4を構築し、既設構造物1の床スラブ3の下方にて一次掘削を行い、フーチング基礎21および基礎梁22を補強するための補強空間5を構築する。作業坑4は、図6(a)の平面図で示すように、基礎梁22と直交するように構築される溝であり、基礎梁22の下方を通り抜けるようにして隣り合うフーチング基礎21の中間位置それぞれに配置され、フーチング基礎21の底面より下方の深さまで掘削されている。また、補強空間5は、フーチング基礎21および基礎梁22の補強後の形状に応じて適宜必要な空間を設ければよく、本実施の形態では、フーチング基礎21の平面方向と、基礎梁22の梁幅方向および梁成方向に補強空間5を設けている。
<First embodiment>
First, in the first step, as shown in FIG. 1( b ), a work pit 4 is constructed, primary excavation is performed below the floor slab 3 of the existing structure 1, and the footing foundation 21 and foundation beam 22 are reinforced. The reinforcement space 5 for constructing is constructed. As shown in the plan view of FIG. 6A, the work shaft 4 is a groove constructed so as to be orthogonal to the foundation beam 22, and is an intermediate portion of the footing foundations 21 adjacent to each other so as to pass below the foundation beam 22. It is arranged at each position and excavated to a depth below the bottom surface of the footing foundation 21. In addition, the reinforcing space 5 may be provided with an appropriate space depending on the shapes of the footing foundation 21 and the foundation beam 22 after reinforcement, and in the present embodiment, the plane direction of the footing foundation 21 and the foundation beam 22. The reinforcing space 5 is provided in the beam width direction and the beam formation direction.

次に、第2の工程では図2(a)で示すように、補強空間5を利用してフーチング基礎21および基礎梁22を補強する。これらの補強方法は、炭素繊維シートの貼り付けや鋼板の設置等いずれでもよいが、本実施の形態では増し打ちコンクリートを打設することにより、基礎梁22の断面を大きくするとともに、補強基礎梁62の断面に応じてフーチング基礎21を補強している。 Next, in the second step, as shown in FIG. 2A, the footing foundation 21 and the foundation beam 22 are reinforced by utilizing the reinforcing space 5. These reinforcing methods may be performed by pasting a carbon fiber sheet, installing a steel plate, or the like, but in the present embodiment, the cross-section of the foundation beam 22 is increased by placing additional concrete, and the reinforcement foundation beam is The footing foundation 21 is reinforced according to the cross section of 62.

基礎2の補強が終了したところで、第3の工程では図2(b)で示すように、補強基礎梁62の下方に位置する作業坑4に第1の仮受け杭7を打設する。なお、第1の仮受け杭7の打設方法はいずれでもよいが、本実施の形態では、アンダーピニング工法を採用している。 When the reinforcement of the foundation 2 is completed, in the third step, as shown in FIG. 2B, the first temporary receiving pile 7 is driven in the work pit 4 located below the reinforcing foundation beam 62. Any method may be used to drive the first temporary receiving pile 7, but in the present embodiment, the underpinning method is used.

アンダーピニング工法は、不等沈下した直接基礎の沈下修正を行う場合等に一般に広く採用される工法であり、具体的には、補強基礎梁62の下面にてジャッキ(図示しない)の反力をとりつつ第1の仮受け杭7を地中に圧入して打設する。第1の仮受け杭7の打設後にはジャッキを撤去し、第1の仮受け杭7の杭頭と補強基礎梁62との間にピース部材71を設置する。これにより、補強基礎梁62から伝達される既設構造物1の鉛直荷重の一部を、ピース部材71を介して第1の仮受け杭7に効率よく伝達させることが可能となる。 The underpinning method is a method that is generally widely used when correcting the subsidence of an unevenly set direct foundation, and specifically, the reaction force of a jack (not shown) is applied to the lower surface of the reinforcing foundation beam 62. While taking it, the first temporary receiving pile 7 is pressed into the ground and placed. After driving the first temporary receiving pile 7, the jack is removed, and the piece member 71 is installed between the pile head of the first temporary receiving pile 7 and the reinforcing foundation beam 62. Thereby, a part of the vertical load of the existing structure 1 transmitted from the reinforcing foundation beam 62 can be efficiently transmitted to the first temporary receiving pile 7 via the piece member 71.

この作業と併せて図3(a)および図6(b)の平面図で示すように、補強フーチング基礎61の下方およびその周囲の地盤Gを改良し、補強フーチング基礎61の下方を含む周辺地盤Gの地耐力を向上させる。地盤改良方法はいずれを採用してもよいが、本実施の形態では薬液注入工法を採用している。具体的には、作業坑4から補強フーチング基礎61の下方領域に向けて、図示しない削孔ドリルにて側方から注入孔を構築する。そして、注入孔を介して薬液注入機Mにより薬液10を地盤Gに圧入し、補強フーチング基礎61の下方およびその周囲の地盤Gを浸透固結する。 As shown in the plan views of FIGS. 3(a) and 6(b) in conjunction with this work, the ground G below and around the reinforcing footing foundation 61 is improved to include the surrounding ground including the lower portion of the reinforcing footing foundation 61. Improve the G bearing capacity. Although any ground improvement method may be adopted, the chemical solution injection method is adopted in the present embodiment. Specifically, an injection hole is constructed from the side from the work pit 4 toward the lower region of the reinforcing footing foundation 61 by a boring drill (not shown). Then, the chemical liquid 10 is press-fitted into the ground G by the chemical liquid injector M through the injection hole, and the ground G below and around the reinforcing footing foundation 61 is solidified by penetration.

第4の工程では、図3(b)で示すように、補強フーチング基礎61の下方の地盤Gを残置するようにして、作業坑4から補強フーチング基礎61に向かって補強基礎梁62の下方を、作業坑4の掘削底に至る深さまで二次掘削する。このとき、補強フーチング基礎61の下方およびその周囲の地盤Gは地盤改良がなされているため、掘削のり面を急峻にしてものり面の崩落を生じることはない。したがって、補強フーチング基礎61の底面より下方まで構築した作業坑4から二次掘削を進める場合にも、既設構造物1の鉛直荷重が比較的軽量であれば土留めを行うことなく、安全に効率よく掘削作業を実施することが可能である。 In the fourth step, as shown in FIG. 3( b ), the ground G below the reinforcing footing foundation 61 is left and the lower part of the reinforcing foundation beam 62 is moved toward the reinforcing footing foundation 61 from the work pit 4. Secondly excavate to the depth of the excavation bottom of the work pit 4. At this time, since the ground G below and around the reinforcing footing foundation 61 has been improved, the slope of the excavation slope does not collapse even if the excavation slope is steep. Therefore, even when secondary excavation is carried out from the work pit 4 constructed below the bottom surface of the reinforcing footing foundation 61, if the vertical load of the existing structure 1 is relatively light, earth retaining is not performed and the efficiency is safe. It is possible to carry out excavation work well.

この後、第5の工程では図4(a)および図6(c)の平面図で示すように、補強基礎梁62の下方であって、補強フーチング基礎61との接合部の近接位置に第2の仮受け杭8を設置する。これにより、既設構造物1の鉛直荷重は、補強基礎梁62に設置された第1の仮受け杭7および第2の仮受け杭8と補強フーチング基礎61との3者により分担して仮受け支持されることとなる。 After that, in the fifth step, as shown in the plan views of FIGS. 4A and 6C, the first position is located below the reinforcing foundation beam 62 and at a position close to the joint with the reinforcing footing foundation 61. 2 temporary support pile 8 is installed. As a result, the vertical load of the existing structure 1 is shared by the three members of the first and second temporary receiving piles 7 and 8 and the reinforcing footing foundation 61, which are installed on the reinforcing foundation beam 62, to temporarily receive the temporary load. Will be supported.

なお、補強フーチング基礎61の下方およびその周囲の地盤Gは、補強フーチング基礎61の周囲の地盤Gを容易に掘削でき、かつ、周囲の地盤Gの掘削後において、既設構造物1の鉛直荷重の一部を補強フーチング基礎61にて分担可能な程度の強度を発現できるように改良するとよい。 The ground G below and around the reinforcing footing foundation 61 can easily excavate the ground G around the reinforcing footing foundation 61, and after excavating the surrounding ground G, the vertical load of the existing structure 1 It is advisable to improve a part of the reinforcing footing foundation 61 so that the reinforcing footing foundation 61 can exhibit sufficient strength.

これにより、既設構造物1の鉛直荷重の一部を補強フーチング基礎61に負担させながら二次掘削を実施できるため、安全に二次掘削を実施することが可能となるとともに、補強フーチング基礎61との接合部の近接位置に第2の仮受け杭8が打設できるので、基礎梁22の曲げ耐力向上のための補強も低減できる。 As a result, the secondary excavation can be performed while part of the vertical load of the existing structure 1 is being borne by the reinforcing footing foundation 61, so that it is possible to safely perform the secondary excavation and the reinforcing footing foundation 61 and Since the second temporary receiving pile 8 can be driven at a position close to the joint portion, the reinforcement for improving the bending resistance of the foundation beam 22 can be reduced.

上記のように、既設構造物1の鉛直荷重を、第1の仮受け杭7および第2の仮受け杭8と補強フーチング基礎61との3者により分担して仮受け支持した後、図4(b)で示すように補強フーチング基礎61下の残置した地盤Gを撤去しつつ、前記フーチング基礎下の周縁に近接した位置に第3の仮受け杭9を打設し、補強フーチング基礎61の下方および基礎梁22の下方に、作業空間12を形成する。 As described above, after the vertical load of the existing structure 1 is temporarily supported by the three members, that is, the first temporary receiving pile 7 and the second temporary receiving pile 8 and the reinforcing footing foundation 61, the vertical load of FIG. As shown in (b), while the remaining ground G under the reinforcing footing foundation 61 is removed, the third temporary support pile 9 is driven at a position close to the peripheral edge under the footing foundation, and the reinforcement footing foundation 61 The working space 12 is formed below and below the foundation beam 22.

図5(a)で示すように、免震ピット14を構築するための空間13を確保するべく三次掘削を行う。そして、図5(b)で示すように、三次掘削の掘削底に底盤コンクリート141を打設したうえで、底盤コンクリート141と補強フーチング基礎61との間に免震基礎151および免震装置152を設置する。最後に、第1の仮設杭7、第2の仮設杭8および第3の仮設杭9のうち底盤コンクリート141から上方に突出する部分を切断撤去し、既設構造物1の全鉛直荷重を補強フーチング基礎61に盛り替えて作業を終了する。 As shown in FIG. 5A, tertiary excavation is performed to secure the space 13 for constructing the seismic isolation pit 14. Then, as shown in FIG. 5(b), after placing the bottom concrete 141 on the excavation bottom of the tertiary drilling, the seismic isolation foundation 151 and the seismic isolation device 152 are provided between the bottom concrete 141 and the reinforced footing foundation 61. Install. Finally, the parts of the first temporary pile 7, the second temporary pile 8 and the third temporary pile 9 that project upward from the bottom concrete 141 are cut and removed to reinforce all vertical loads of the existing structure 1. The work is finished by exchanging it with the foundation 61.

なお、第2の仮設杭8および第3の仮設杭9はいずれも第1の仮設杭7と同様に、アンダーピニング工法により打設すればよく、図示しないが、第1の仮設杭7、第2の仮設杭8および第3の仮設杭9の切断後の杭頭には、水密性のキャップを設置するとよい。 It should be noted that both the second temporary pile 8 and the third temporary pile 9 may be driven by the underpinning method like the first temporary pile 7, and although not shown, the first temporary pile 7, A watertight cap may be installed on the pile heads of the second temporary pile 8 and the third temporary pile 9 after cutting.

<第2の実施の形態>
ところで、フーチング基礎21一体あたりの負担鉛直荷重が大きい場合や地盤改良のみでは地盤Gに必要な地耐力が得られない場合には、既設構造物の仮受け工法を実施するにあたって、補強フーチング基礎61の下方に残置する地盤Gを拘束部材11にて拘束し補強するとよい。そこで、第2の実施の形態では、拘束部材11を用いて既設構造物1を仮受する方法を説明する。
<Second Embodiment>
By the way, when the vertical load borne by the footing foundation 21 is large, or when the ground strength required for the ground G cannot be obtained only by the ground improvement, the reinforcement footing foundation 61 is used to carry out the temporary receiving method for the existing structure. It is advisable to restrain and reinforce the ground G, which is left below, with the restraining member 11. Therefore, in the second embodiment, a method of temporarily receiving the existing structure 1 using the restraint member 11 will be described.

既設構造物1のフーチング基礎21および基礎梁22の下方まで一次掘削を行う第1の工程から、フーチング基礎21および基礎梁22を補強し、第1の仮受け杭7を打設するとともに、補強フーチング基礎61の下方およびその周囲の地盤Gを地盤改良する第3の工程までは、第1の実施の形態と同様である。この後、第4の工程で、図8(b)で示すように、二次掘削を上方から下方に向けて複数段に分割して行ない、一段掘削するごとに補強フーチング基礎61の下方に残置された地盤Gを拘束部材11にて拘束する。 From the first step of performing the primary excavation down to the footing foundation 21 and the foundation beam 22 of the existing structure 1, the footing foundation 21 and the foundation beam 22 are reinforced, and the first temporary receiving pile 7 is driven and reinforced. Up to the third step of ground improvement of the ground G below and around the footing foundation 61, it is the same as in the first embodiment. Thereafter, in the fourth step, as shown in FIG. 8B, the secondary excavation is divided into a plurality of stages from the upper side to the lower side, and the secondary excavation is left below the reinforcing footing foundation 61 for each stage of excavation. The restrained member 11 restrains the ground G thus made.

具体的には、補強フーチング基礎61直下の部分を除いた周囲の地盤Gを図7(a)で示すように、補強基礎梁62の直下から一定の深さだけ削り取り、この後に残された補強フーチング基礎61下の地盤Gを、図7(b)の平面図で示すように、拘束部材11にて拘束する。拘束部材11は、コンクリート部材を補強する際に一般に用いられるメタルバンドや炭素繊維シート等いずれを用いてもよいが、本実施の形態では、鋼材を組み合わせた平面視矩形状の枠材を採用している。 Specifically, as shown in FIG. 7A, the surrounding ground G excluding the portion immediately below the reinforcing footing foundation 61 is scraped off from just below the reinforcing foundation beam 62 to a certain depth, and the reinforcement remaining after this is removed. The ground G under the footing foundation 61 is constrained by the constraining member 11 as shown in the plan view of FIG. The restraint member 11 may be any metal band, carbon fiber sheet, or the like that is commonly used when reinforcing a concrete member, but in the present embodiment, a frame member having a rectangular shape in plan view which is a combination of steel materials is adopted. ing.

ここで、拘束部材11に枠材を採用すると、補強フーチング基礎61の下方に残置された地盤Gと拘束部材11との間に隙間が生じて拘束部材11による拘束効果を十分に得られない場合が生じる。そこで、図8(a)の平面図で示すように、拘束部材11をなす枠材にグラウト注入口111を設けておき、地盤Gと拘束部材11との隙間にグラウト等の硬化材Cを注入充填するとよい。 Here, if a frame member is adopted as the restraint member 11, a gap is created between the restraint member 11 and the ground G left below the reinforcing footing foundation 61, and the restraint effect by the restraint member 11 cannot be sufficiently obtained. Occurs. Therefore, as shown in the plan view of FIG. 8A, a grout injection port 111 is provided in a frame material forming the restraint member 11, and a hardening material C such as grout is injected into a gap between the ground G and the restraint member 11. Good to fill.

上記の作業を図8(b)で示すように、上方から下方に向けて一段ごとに繰り返して行ことにより、二次掘削の終了後における補強フーチング基礎61の下方には、図9(a)で示すような、地盤Gとこれを拘束する複数層の拘束部材11が配置された状態となる。そして、第5の工程で、補強基礎梁62の下方であって補強フーチング基礎61との接合部の近接位置に、図9(b)で示すような第2の仮受け杭8を設置する。これにより、既設構造物1の鉛直荷重は、補強基礎梁62に設置された第1の仮受け杭7および第2の仮受け杭8と補強フーチング基礎61との3者により分担して仮受け支持されることとなる。 As shown in FIG. 8(b), the above work is repeated step by step from the upper side to the lower side, so that FIG. 9(a) is provided below the reinforcing footing foundation 61 after the completion of the secondary excavation. The ground G and a plurality of constraining members 11 for constraining the ground G are arranged as shown in FIG. Then, in a fifth step, a second temporary receiving pile 8 as shown in FIG. 9B is installed below the reinforcing foundation beam 62 and in the vicinity of the joint with the reinforcing footing foundation 61. As a result, the vertical load of the existing structure 1 is shared by the three members of the first and second temporary receiving piles 7 and 8 and the reinforcing footing foundation 61, which are installed on the reinforcing foundation beam 62, to temporarily receive the temporary load. Will be supported.

この後、拘束部材11を取り外して図4(a)のように補強フーチング基礎61の下方に残置した地盤Gを露出させ、これを撤去しつつ図4(b)で示すように、補強フーチング基礎61の下方に第3の仮受け杭9を打設し、第1の実施の形態と同様に、補強フーチング基礎61の下方および基礎梁22の下方に、作業空間12を形成すればよい。 Thereafter, the restraining member 11 is removed to expose the ground G left below the reinforcing footing foundation 61 as shown in FIG. 4A, and while removing the ground G, as shown in FIG. It suffices to drive the third temporary receiving piles 9 below 61 and form the working space 12 below the reinforcing footing foundation 61 and below the foundation beam 22 as in the first embodiment.

上記のように、第4の工程では、補強フーチング基礎61の下方に残置され拘束部材11にて拘束された地盤Gと第1の仮受け杭7により既設構造物1の鉛直荷重が分担される状態にある。このため、フーチング基礎21一体あたりの負担鉛直荷重が大きい場合や地盤改良のみでは地盤Gに必要な地耐力が得られない場合にも、第5の工程にて第2の仮受け杭を打つまでの間、安全に作業をすすめることが可能となる。 As described above, in the fourth step, the vertical load of the existing structure 1 is shared by the ground G that is left below the reinforcing footing foundation 61 and is restrained by the restraining member 11 and the first temporary receiving pile 7. Is in a state. Therefore, even if the vertical load borne by the footing foundation 21 is large or if the ground strength required for the ground G cannot be obtained only by ground improvement, until the second temporary bearing pile is driven in the fifth step. During this time, it is possible to proceed with work safely.

なお、本実施の形態では、補強フーチング基礎61の下方に第3の仮受け杭9を打設したが、必ずしもこれに限定されるものではない。例えば、既設構造物1の鉛直荷重を補強基礎梁62の下面に設置された第1の仮設杭7と第2の仮設杭8で支持できる程度に既設構造物1の荷重が小さい場合、あるいは、既設構造物1の荷重に対して補強フーチング基礎61および補強基礎梁62の耐力が十分な場合には、補強フーチング基礎61に対して第3の仮受け杭9の設置する工程を省略してもよい。 In addition, in this Embodiment, although the 3rd temporary receiving pile 9 was drive|operated below the reinforcement footing foundation 61, it is not necessarily limited to this. For example, when the load of the existing structure 1 is small enough to support the vertical load of the existing structure 1 by the first temporary pile 7 and the second temporary pile 8 installed on the lower surface of the reinforcing foundation beam 62, or When the proof footing foundation 61 and the reinforced foundation beam 62 have sufficient proof stress against the load of the existing structure 1, even if the step of installing the third temporary receiving pile 9 on the reinforced footing foundation 61 is omitted. Good.

<第3の実施の形態>
第3の実施の形態では、図4(a)で示すように、基礎梁62の下方に第2の仮受け杭を打設した後、図4(b)で示すように、補強フーチング基礎61の下方に第3の仮受け杭を打設する際の、打設手順の事例を示す。
<Third Embodiment>
In the third embodiment, as shown in FIG. 4( a ), after the second temporary receiving pile is placed below the foundation beam 62, as shown in FIG. 4( b ), the reinforcing footing foundation 61 is provided. An example of a placing procedure when placing the third temporary receiving pile below the is shown.

まず、補強フーチング基礎61の下方に残置した地盤Gの一部を、図11の平面図で示すように、区画A、B、C、D各々が1つの隅部を含むように区分けする。次に、補強フーチング基礎61の区画Aに該当する領域の地盤Gを切削し、この跡地に図10(a)で示すような第3の仮受け杭9を打設する。このような作業を、区画A、B、C、Dの全てに対して順次実施する。 First, a part of the ground G left below the reinforcing footing foundation 61 is divided so that each of the sections A, B, C, and D includes one corner, as shown in the plan view of FIG. 11. Next, the ground G in the area corresponding to the section A of the reinforcing footing foundation 61 is cut, and the third temporary receiving pile 9 as shown in FIG. Such work is sequentially performed on all the sections A, B, C, and D.

すると、図11の平面図で示すように、補強フーチング基礎61の四隅各々に第3の仮受け杭9が打設される。こうして、既設構造物1の鉛直荷重は、図10(b)で示すように、補強基礎梁62に設置された第1の仮受け杭7および第2の仮受け杭8と、補強フーチング基礎61の下方に打設された第3の仮受け杭9により分担して仮受け支持されることとなる。これにより補強フーチング基礎61にかかる鉛直荷重を基礎梁22だけで支持するという場面がなく、補強フーチング基礎61の下の地盤または第1〜第3の仮受け杭7、8、9で常に分担するので、基礎梁21の補強を小さくすることが可能となる。 Then, as shown in the plan view of FIG. 11, the third temporary receiving piles 9 are driven at each of the four corners of the reinforcing footing foundation 61. Thus, the vertical load of the existing structure 1 is, as shown in FIG. 10B, the first temporary receiving pile 7 and the second temporary receiving pile 8 installed on the reinforcing foundation beam 62, and the reinforcing footing foundation 61. The third temporary receiving pile 9 that is placed below the first temporary receiving pile 9 shares and temporarily supports the third temporary receiving pile 9. As a result, there is no situation in which the vertical load applied to the reinforcing footing foundation 61 is supported only by the foundation beams 22, and the ground under the reinforcing footing foundation 61 or the first to third temporary receiving piles 7, 8, and 9 are always shared. Therefore, the reinforcement of the foundation beam 21 can be reduced.

〈第4の実施の形態〉
一方で、第4の工程および第5の工程を実施するにあたって、第1の仮設杭7と第2の仮設杭8が不要な程度に、既設構造物1の荷重が小さい場合もしくは地盤改良により地盤Gに必要な地耐力を確保可能な場合には、第1の仮設杭7と第2の仮設杭8の打設工程を省略できる。そこで、第4の実施の形態では、第3の仮受け杭9のみで既設構造物1を仮受する方法を説明する。
<Fourth Embodiment>
On the other hand, in carrying out the fourth step and the fifth step, when the load of the existing structure 1 is small or the ground is improved by the ground improvement so that the first temporary pile 7 and the second temporary pile 8 are unnecessary. When it is possible to secure the required earth bearing strength for G, the step of placing the first temporary pile 7 and the second temporary pile 8 can be omitted. Therefore, in the fourth embodiment, a method of temporarily receiving the existing structure 1 only by the third temporary receiving pile 9 will be described.

既設構造物1のフーチング基礎21および基礎梁22の下方まで一次掘削を行う第1の工程から、フーチング基礎21および基礎梁22を補強する第2の工程までは、第1の実施の形態と同様である。この後、第3の工程において図12(a)で示すように、補強基礎梁62の下方に位置する作業坑4を利用して補強フーチング基礎61の下方およびその周囲の地盤Gを改良し、補強フーチング基礎61の下方を含む周辺地盤Gの地耐力を向上させる。 From the first step of performing the primary excavation down to the footing foundation 21 and the foundation beam 22 of the existing structure 1 to the second step of reinforcing the footing foundation 21 and the foundation beam 22, the same as in the first embodiment. Is. Thereafter, in the third step, as shown in FIG. 12A, the work pit 4 located below the reinforcing foundation beam 62 is utilized to improve the ground G below the reinforcing footing foundation 61 and the surrounding area thereof, The bearing capacity of the surrounding ground G including the lower portion of the reinforcing footing foundation 61 is improved.

次に、第4の工程では図12(b)で示すように、補強フーチング基礎61の下方の地盤Gを残置するようにして、作業坑4から補強フーチング基礎61に向かって補強基礎梁62の下方を、作業坑4の掘削底に至る深さまで二次掘削する。この後、第5の工程では、上記の第3の実施の形態で示した方法で、図13(b)で示すように、補強フーチング基礎61の下方に第3の仮受け杭9の打設する。 Next, in the fourth step, as shown in FIG. 12B, the ground G below the reinforcing footing foundation 61 is left, and the reinforcing foundation beam 62 is moved from the work pit 4 toward the reinforcing footing foundation 61. Secondary drilling is performed below to a depth reaching the drilling bottom of the work pit 4. After that, in the fifth step, as shown in FIG. 13(b), the third temporary receiving pile 9 is driven under the reinforcing footing foundation 61 by the method shown in the third embodiment. To do.

つまり、補強フーチング基礎61の下方に残置した地盤Gの一部を、図14の平面図で示すように、区画A、B、C、D各々が1つの隅部を含むように区分けする。次に、補強フーチング基礎61の区画Aに該当する領域の地盤Gを切削し、この跡地に図13(a)で示すような第3の仮受け杭9を打設する。このような作業を、区画A、B、C、Dの全てに対して順次実施する。 That is, a part of the ground G left below the reinforcing footing foundation 61 is divided so that each of the sections A, B, C, and D includes one corner, as shown in the plan view of FIG. Next, the ground G in the area corresponding to the section A of the reinforcing footing foundation 61 is cut, and the third temporary receiving pile 9 as shown in FIG. Such work is sequentially performed on all the sections A, B, C, and D.

上述した既設構造物の仮受け工法によれば、地盤改良を行うことにより補強フーチング基礎61下の地耐力が向上することから、補強基礎梁62下に第1の仮受け杭7および第2の仮受け杭8を打設することなく、二次掘削を行うことができるため、作業性を大幅に向上することが可能となる According to the above-mentioned method for temporarily receiving the existing structure, since the ground proof strength under the reinforcing footing foundation 61 is improved by performing the ground improvement, the first temporary receiving pile 7 and the second temporary receiving pile 7 are provided under the reinforcing foundation beam 62. Since the secondary excavation can be performed without placing the temporary receiving piles 8, the workability can be significantly improved.

なお、本発明の既設構造物の仮受け工法は、上記実施形態に限定されるものではなく、本発明の趣旨を逸脱しない範囲で、種々の変更が可能であることはいうまでもない。 Needless to say, the method for temporarily receiving the existing structure of the present invention is not limited to the above-described embodiment, and various modifications can be made without departing from the spirit of the present invention.

例えば、補強フーチング基礎61下に残置する地盤Gや拘束部材11の形状は必ずしも平面視角型に限定されるものではない。たとえば、拘束部材11を平面視円形に形成すると、応力が分配されその平面視形状を小さくすることが可能となる。 For example, the shapes of the ground G and the restraint member 11 left under the reinforcing footing foundation 61 are not necessarily limited to the rectangular shape in plan view. For example, when the restraint member 11 is formed in a circular shape in plan view, stress is distributed and the shape in plan view can be reduced.

また、作業坑4は、作業者が地盤Gの掘削や第1から第3の仮受け杭7、8、9の打設作業可能で、かつ薬液注入機Mの搬出入および設置が可能であれば、いずれの断面形状でもよいが、例えば幅2000〜2500mm程度、高さ1200〜1500mm程度を確保するとよい。また、補強空間5についても、補強方法に応じて適宜必要な空間を確保すればよく、例えば増打ちコンクリートの打設により補強する場合には、増打ち寸法(例えば、300mm程度)に作業空間に必要な寸法(例えば、型枠設置等200〜300mm程度)を足し合わせる程度を確保するとよい。 Further, in the work pit 4, an operator can excavate the ground G and place the first to third temporary receiving piles 7, 8 and 9 and can carry in/out and install the chemical liquid injector M. For example, the cross-sectional shape may be any, but it is preferable to secure a width of about 2000 to 2500 mm and a height of about 1200 to 1500 mm. Also, as for the reinforcing space 5, it is only necessary to secure a necessary space according to the reinforcing method. For example, when reinforcement is performed by placing additional concrete, the additional space (for example, about 300 mm) is added to the working space. It is advisable to secure a degree to which necessary dimensions (for example, about 200 to 300 mm for installing a mold, etc.) are added.

1 既設構造物
21 フーチング基礎
22 基礎梁
3 床スラブ
4 作業坑
5 補強空間
61 補強フーチング基礎
62 補強基礎梁
7 第1の仮受け杭
71 ピース部材
8 第2の仮受け杭
9 第3の仮受け杭
10 薬液
11 拘束部材
111 薬液注入口
12 作業空間
13 免震ピット用の空間
14 免震ピット
141 底盤コンクリート
151 免震基礎
152 免震装置
G 地盤
M 薬液注入機
1 Existing structure 21 Footing foundation 22 Foundation beam 3 Floor slab 4 Work mine 5 Reinforcement space 61 Reinforcement footing foundation 62 Reinforcement foundation beam 7 First temporary receiving pile 71 Piece member 8 Second temporary receiving pile 9 Third temporary receiving Pile 10 Chemical solution 11 Restraint member 111 Chemical solution inlet 12 Working space 13 Space for seismic isolation pit 14 Seismic isolation pit 141 Bottom concrete 151 Seismic isolation foundation 152 Seismic isolation device G Ground M Chemical fluid injection machine

Claims (2)

フーチング基礎で直接支持された既設構造物の鉛直荷重を仮受けするための既設構造物の仮受け工法であって、
一次掘削として、隣り合う前記フーチング基礎の中間位置をフーチング基礎の底面より下方の深さまで掘削し溝状の作業坑を構築するとともに、基礎梁の周囲を前記フーチング基礎の底面の深さまで掘削し補強空間を構築する第1の工程と、
前記補強空間を利用して、前記基礎梁およびフーチング基礎を補強する第2の工程と、
前記フーチング基礎下およびその周囲を地盤改良する第3の工程と、
二次掘削として、前記フーチング基礎下の地盤を残して前記基礎梁下の地盤を、前記作業坑から前記フーチング基礎に向かって前記作業坑の掘削底に至る深さまで掘削する第4の工程と、
前記基礎梁下と前記フーチング基礎下のうち、少なくともいずれか一方に仮受け杭を打設する第5の工程と、
を備えることを特徴とする既設構造物の仮受け工法。
A method of temporarily receiving an existing structure for temporarily receiving the vertical load of an existing structure directly supported by a footing foundation,
As a primary excavation, the intermediate position of the adjacent footing foundations is excavated to a depth below the bottom surface of the footing foundation to construct a groove-like working pit, and the periphery of the foundation beam is excavated to the depth of the bottom surface of the footing foundation for reinforcement. The first step of building a space,
A second step of reinforcing the foundation beam and footing foundation using the reinforcement space;
A third step of improving the ground under and around the footing foundation,
As a secondary excavation, a fourth step of excavating the ground under the foundation beam leaving the ground under the footing foundation to a depth reaching the excavation bottom of the work well from the work well toward the footing foundation, and
A fifth step of placing a temporary support pile on at least one of the bottom of the foundation beam and the bottom of the footing foundation;
A method for temporarily receiving an existing structure, which comprises:
請求項1に記載の既設構造物の仮受け工法において、
前記第4の工程では、前記基礎梁下を二次掘削するとともに、前記フーチング基礎下に残置された地盤を拘束部材にて拘束することを特徴とする既設構造物の仮受け工法。
In the method for temporarily receiving the existing structure according to claim 1,
In the fourth step, a method for temporarily receiving an existing structure is characterized in that secondary excavation is performed under the foundation beam and the ground remaining under the footing foundation is constrained by a constraining member.
JP2016024633A 2016-02-12 2016-02-12 Temporary receiving method for existing structures Active JP6710999B2 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
JP2016024633A JP6710999B2 (en) 2016-02-12 2016-02-12 Temporary receiving method for existing structures

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
JP2016024633A JP6710999B2 (en) 2016-02-12 2016-02-12 Temporary receiving method for existing structures

Publications (2)

Publication Number Publication Date
JP2017141626A JP2017141626A (en) 2017-08-17
JP6710999B2 true JP6710999B2 (en) 2020-06-17

Family

ID=59627201

Family Applications (1)

Application Number Title Priority Date Filing Date
JP2016024633A Active JP6710999B2 (en) 2016-02-12 2016-02-12 Temporary receiving method for existing structures

Country Status (1)

Country Link
JP (1) JP6710999B2 (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2019073885A (en) * 2017-10-16 2019-05-16 東日本旅客鉄道株式会社 Vibration displacement suppressing structure of structure group

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001271497A (en) * 2000-03-24 2001-10-05 Kajima Corp Temporary bearing construction method for existing building
JP2001271499A (en) * 2000-03-24 2001-10-05 Kajima Corp Temporary bearing construction method for existing building by steel batter brace member
JP2012136841A (en) * 2010-12-24 2012-07-19 Takenaka Komuten Co Ltd Method for excavating ground under spread foundation of existing building, and base-isolating method for existing building
JP5937488B2 (en) * 2012-10-30 2016-06-22 大成建設株式会社 Temporary support method for foundation

Also Published As

Publication number Publication date
JP2017141626A (en) 2017-08-17

Similar Documents

Publication Publication Date Title
KR100884289B1 (en) Composite type steel temporary construction and construction method thereof
JP5811389B2 (en) Construction method for underground structures
JP5038170B2 (en) How to rebuild a structure
JP6543176B2 (en) Building method
JP2012026211A (en) Ground deformation preventing method and underground structure construction method using the same
JP2014088714A (en) Temporary supporting method for foundation
JP6710999B2 (en) Temporary receiving method for existing structures
JP2000352296A (en) Method o constructing passage just under underground structure
JP4069509B2 (en) Construction method of reverse struts in the outer periphery of underground excavation space
KR20120126573A (en) Soil cement wall structure and method for constructing thereof
JP5465086B2 (en) Construction method of underground structure
JP4226954B2 (en) Underpinning method and viaduct
CN111827265A (en) Construction method of steel reinforced concrete underground continuous wall
JP7173459B2 (en) Construction method of structures
JP6918480B2 (en) Prop reinforcement method
JP4993132B2 (en) Foundation reinforcement method for existing structures
JP6422084B2 (en) Underground space construction method
JP2003268770A (en) Earth retaining construction method and reinforcing structure of sheet pile used for this construction method
JP2019157508A (en) Under-ground piled column and seismic base-isolated buildings
JP6534026B2 (en) Seismic isolation building and its construction method
JP2019173453A (en) Construction method of building
JP2019127746A (en) Flotation inhibition structure and inverted construction method
CN111827266B (en) Method for constructing underground continuous wall by using steel caisson technology
JP6851180B2 (en) How to rebuild the building
JP5480745B2 (en) Reinforcement method for existing foundations for structures

Legal Events

Date Code Title Description
A621 Written request for application examination

Free format text: JAPANESE INTERMEDIATE CODE: A621

Effective date: 20190118

A977 Report on retrieval

Free format text: JAPANESE INTERMEDIATE CODE: A971007

Effective date: 20191111

A131 Notification of reasons for refusal

Free format text: JAPANESE INTERMEDIATE CODE: A131

Effective date: 20191119

A521 Written amendment

Free format text: JAPANESE INTERMEDIATE CODE: A523

Effective date: 20200108

TRDD Decision of grant or rejection written
A01 Written decision to grant a patent or to grant a registration (utility model)

Free format text: JAPANESE INTERMEDIATE CODE: A01

Effective date: 20200428

A61 First payment of annual fees (during grant procedure)

Free format text: JAPANESE INTERMEDIATE CODE: A61

Effective date: 20200511

R150 Certificate of patent or registration of utility model

Ref document number: 6710999

Country of ref document: JP

Free format text: JAPANESE INTERMEDIATE CODE: R150