WO2020224233A1 - Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner - Google Patents

Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner Download PDF

Info

Publication number
WO2020224233A1
WO2020224233A1 PCT/CN2019/120380 CN2019120380W WO2020224233A1 WO 2020224233 A1 WO2020224233 A1 WO 2020224233A1 CN 2019120380 W CN2019120380 W CN 2019120380W WO 2020224233 A1 WO2020224233 A1 WO 2020224233A1
Authority
WO
WIPO (PCT)
Prior art keywords
shield
construction
tunnel
viaduct
grouting
Prior art date
Application number
PCT/CN2019/120380
Other languages
French (fr)
Chinese (zh)
Inventor
孙捷城
路林海
刘瑞琪
胡永利
韩帅
Original Assignee
济南轨道交通集团有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 济南轨道交通集团有限公司 filed Critical 济南轨道交通集团有限公司
Priority to AU2019444087A priority Critical patent/AU2019444087B2/en
Publication of WO2020224233A1 publication Critical patent/WO2020224233A1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members
    • E21D11/386Sealing means positioned between adjacent lining members inflatable sealing means
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining
    • E21D9/0607Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining the shield being provided with devices for lining the tunnel, e.g. shuttering

Definitions

  • the invention relates to the technical field of subway shield tunnel construction, in particular to a construction method for shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts.
  • the existing technology is mainly aimed at the isolation and reinforcement control of shield tunnels passing through viaducts orthogonally.
  • the isolation and reinforcement usually use bored piles, mixing piles, jet-grouted piles, and even underground continuous walls to block shield tunnels and elevated bridges.
  • the continuous deformation of the pile foundation has limited deformation control effects. It is difficult to meet the construction safety control requirements under multiple complex conditions such as water-bearing strata, multi-interval shield tunnels, and small-clear overlap crossing construction, and there is no combination of multiple control technologies.
  • Comprehensive control system and construction methods are aimed at the isolation and reinforcement control of shield tunnels passing through viaducts orthogonally.
  • the present invention provides a construction method for shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts.
  • Step 1 According to the principle of the least impact on the deformation of the viaduct pile foundation and the surrounding environment, formulate the optimal construction sequence for the construction of the shield tunnel with multiple sections and stacked under the viaduct;
  • Step 2 Before the tunnel underpasses the viaduct, conduct active isolation and reinforcement of the short-distance underpass construction of the shield;
  • Step 3 Carry out the construction of the shield tunnel under the viaduct
  • Step 4 Reinforce the segment structure of the shield tunnel in the area where the multi-shield tunnel overlaps and pass through the viaduct, and strengthen the tunnel cavity;
  • Step 5 The track vibration reduction and isolation control is carried out in the section of the shield tunnel passing through the viaduct.
  • the specific working method of step one is to establish a high-precision three-dimensional numerical model, simulate and analyze the deformation of the viaduct structure and surrounding stratum caused by the construction of multiple shield tunnels in different sequences, and determine the correctness of the viaduct pile foundation and surrounding environment
  • the underpass construction sequence with the least deformation effect is the optimal construction sequence.
  • the formation parameters, tunnel direction and size, viaduct load and pile foundation parameters, shield tunneling process and other information in the high-precision three-dimensional numerical model must be consistent with the actual construction situation to improve the accuracy of the numerical simulation.
  • the specific working method of the second step is:
  • Step 2.1 Construct bored piles as isolation piles
  • the isolation pile construction is completed some time before the shield passes through the viaduct, and bored piles are built between the shield tunnel and the viaduct pile foundation.
  • the protection range of the cast-in-place pile extends beyond the pier cap, and the bottom of the cast-in-place pile reaches the shield segment. Below the structure bottom, in order to limit the horizontal deformation of bridge piles caused by shield tunneling, and try to block the stress transmission and deformation expansion of shield construction;
  • Step 2.2 Carry out sleeve valve pipe grouting to stop water between piles;
  • Sleeve valve tube grouting is adopted for the middle, fine sand layer and pebble layer between the isolated piles.
  • the bored pile is formed by a positive circulation drilling machine with a grinding disc.
  • a positive circulation drilling machine with a grinding disc.
  • the rotation speed and the drilling speed are gradually increased; the drilling parameters and drilling speed are controlled throughout the process.
  • Speed when changing layers, appropriately slow down the speed and reduce the weight on bit to prevent the borehole from tilting.
  • bored piles adopts steel casing and mud water wall protection.
  • the mud wall protection effect is good and it is suitable for the construction of pebble stratum. If there is a hole collapse, the surrounding drilling should be stopped immediately, the cause of the hole collapse should be found out, and the monitoring of the bridge structure should be strengthened; when the pile is repaired, the original pile should be drilled and poured.
  • bored piles adopts jumping pile construction, and guarantees "drill one hole, inject one hole” and guarantee symmetrical drilling to reduce the impact of isolation pile construction on viaduct piles.
  • the steel cage is made in sections, and the hoisting equipment of the millstone drill is used for hoisting the steel cage to meet the construction space under the viaduct.
  • the sleeve valve tube is drilled with a pilot hole drill, and the hole depth needs to meet the design requirements.
  • the area where the working space of grouting is restricted can be adjusted by adjusting the angle of the grouting pipe and the arrangement of dense grouting holes.
  • the sleeve valve pipe construction adopts the grouting construction method of interval skipping holes, gradual restraint, and first down and then up.
  • Drilling sequence drill the peripheral holes first, and gradually drill from the outside to the inside.
  • Grouting sequence from the outside to the inside, first grouting the holes on the reinforcement range line, blocking the slurry leakage channel, and then gradually densifying the grouting holes to perform grouting and compaction in the middle of the area.
  • the shield tunnel segment structure strengthening is performed in the step 4, which mainly includes:
  • a porous EPDM elastic gasket is set at the joints of the tube sections, a nitrile cork rubber pad is set at the circumferential and longitudinal seams of the tube sections, and the full loops of the tube sections are caulked with flexible polyurethane sealant;
  • Water-wet stains in the invert range are made of polymer waterproof mortar, all bolt holes are sealed with water-swellable rubber rings, and the lifting holes are sealed with plastic protective covers.
  • the reinforcement in the tunnel in the overlap zone is carried out in the fourth step, which mainly includes:
  • a support trolley is erected in the descending tunnel to support and strengthen the overall longitudinal rigidity of the previously formed tunnel to prevent longitudinal uneven settlement of the tunnel segments.
  • each ring tunnel segment is generally divided into 6 blocks, which are 3 standard blocks, 2 adjacent blocks, and 1 capping block.
  • the additional reserved grouting holes for the segment are added to each standard block and adjacent blocks. 2 reserved grouting holes, so that after the segment is assembled and stabilized, the interlayer soil in the overlapping area is reinforced by grouting twice or more through the reserved grouting holes.
  • the track vibration reduction and isolation control is performed in the subway tunnel underpassing the viaduct section, which mainly includes:
  • Vibration reduction and isolation measures are adopted for the subway track within the 50m tunnel range on both sides of the pier cap of the subway tunnel under the viaduct section to reduce the impact of rail transit operations on the vibration of the elevated bridge.
  • the subway track uses an improved rubber (polyurethane) floating slab damping track (the first-order natural vibration frequency is 10-20 Hz) to avoid resonance with the railway train running on the viaduct and reduce the vibration energy of the subway train itself.
  • the first-order natural vibration frequency is 10-20 Hz
  • the present invention forms an active control system of shield tunnel underpassing viaduct through a combination of control technologies in five aspects: construction sequence optimization, active isolation and reinforcement, segment structure reinforcement, tunnel grouting reinforcement, and track vibration reduction and isolation, and the construction stability and deformation
  • the control effect is excellent. It overcomes the disadvantages of single control method of traditional isolation piles, limited control effect, and failure to actively prevent risks. It can meet the safety control of water-bearing strata, multiple intervals, small clear distance, and overlapping shield tunnels under the viaduct construction Claim.
  • the present invention formulates the optimal construction sequence for the multi-section and stacked-down underpass construction of the shield tunnel, and determines the sequence of the multi-section underpass construction according to scientific and informatized means, avoiding the subjectivity and blindness of empirical decision-making, and effectively reducing Crossing construction risks.
  • the invention actively changes the stress field state of the stratum surrounding the viaduct by pre-implementing measures such as isolation and reinforcement of bored piles and sleeve valve pipe grouting piles before the underpass construction, thereby improving the mechanical properties of the soil and blocking the original
  • the continuous deformation and stress development trend of the stratum play a role in active isolation and risk control.
  • grouting reinforcement is carried out in the overlapping area of multiple sections, and the weak disturbing soil between the overlapping tunnels is cemented into a whole, which improves the rigidity, strength and self-control of the ground. Stability, so as to reduce the impact of additional stress and superimposed deformation on the structure of the first formed tunnel.
  • the present invention has successfully realized the construction safety of shield tunnels with multiple intervals, small clear distances, and overlapping underpasses in water-bearing soft formations, effectively controlling the structural damage and settlement deformation of the viaducts and subway tunnels, and can be widely used. It is suitable for shield crossing construction projects under the conditions of water-bearing and weak geology, shield tunneling with small clear spacing, multiple interval tunnels under the same bridge span, and under the conditions of strict control of the deformation of the viaduct.
  • Fig. 1 is a cross-section view of the reinforcement control of the shield tunnel of the present invention with multiple sections, small clear distances, and overlapping underpass viaducts;
  • Figure 2 is a plan view of the reinforcement control of the shield tunnel with multiple sections, small clear distances, and overlapping underpass viaducts;
  • Figure 3 is a schematic diagram of the section of the shield tunnel segment with additional reserved grouting holes
  • Figure 4 is a schematic diagram showing the structure of additional reserved grouting holes for shield tunnel segments
  • Figure 5 is a schematic diagram of grouting pre-reinforcement in shield tunnels with small clearance and overlapping areas
  • Figure 6 is a schematic diagram of the layout of the supporting trolley in the shield tunnel
  • Figure 7 is a flow chart of the construction process of bored piles.
  • 1-down section of shield tunnel 2-up section of shield tunnel; 3-high-speed railway bridge; 4-pile foundation; 5-isolated pile; 6-pier cap; 7-sleeve valve tube; 8-segment Structure; 9-hoisting hole; 10-prepared grouting hole; 11-connecting bolt; 12-grouting pipe; 13-grouting area; 14-support trolley; 15-wheeled support arm.
  • the existing technology is mainly aimed at the isolation and reinforcement control of shield tunnels crossing the viaduct orthogonally.
  • the isolation and reinforcement mostly use bored piles, mixing piles, jet grouting piles, and even underground continuous walls and other retaining structures , Blocking the continuous deformation of the shield tunnel and the elevated pile foundation, its deformation control effect is limited. It is difficult to meet the construction safety control requirements under multiple complex conditions such as water-bearing strata, multi-interval shield tunnels, and small-clear overlap crossing construction.
  • a comprehensive control system and construction method that does not form a combination of multiple control technologies; the present invention provides a construction method for shield tunnels with multiple sections, small clear distances, and overlapped underpass viaducts, in order to enable the objectives, technical solutions and The effect is clearer and clearer, and the present invention will be described in further detail below. It should be understood that the specific embodiments described here are only used to explain the present invention, but not to limit the present invention.
  • the shield tunnel multi-interval, small clear distance, and overlapped underpass construction method proposed by the present invention mainly includes shield tunnel multi-interval, overlapped underpass construction sequence determination technology; shield tunnel close underpass construction active isolation control technology; shield Tunnel segment structure strengthening technology; tunnel reinforcement control technology in the overlap zone; vibration reduction and isolation control technology for subway tunnels under the viaduct; the combination of the above 5 technologies forms a shield tunnel with multiple sections, small clear distances, and overlap Actively control construction methods across viaducts.
  • the invention provides a construction method for shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts, which specifically includes the following steps:
  • Step 1 Before multiple shield tunnels, small clear distances, and overlapping underpass viaducts, first formulate the optimal construction sequence for multi-section underpass viaduct construction. Through the establishment of a high-precision three-dimensional numerical model, simulation and analysis of the viaduct structural deformation and surrounding ground deformation caused by the construction of multiple shield tunnels in different sequences, the optimal construction sequence is determined by the construction sequence that has the least impact on the viaduct pile foundation and surrounding environment deformation.
  • the formation parameters, tunnel direction and size, viaduct load and pile foundation parameters, shield tunneling process and other information in the high-precision three-dimensional numerical model must be consistent with the actual construction situation to improve the accuracy of the numerical simulation.
  • Step 2 Complete the isolation pile construction one month before the shield tunnel goes under the viaduct, and drill cast-in-place piles between the shield tunnel and the viaduct pile foundation as isolation piles to limit the horizontal deformation of the viaduct pile foundation caused by shield tunneling , Try to block the stress transmission and deformation expansion of shield construction.
  • the size of the isolation pile is selected as ⁇ 800@1000; and it is generally required that the protection range is 15m beyond the pier cap, and the bottom of the isolation pile reaches 4.0m below the bottom of the shield segment; but the specific size is not limited to this size, and can be based on specific The construction environment shall be adjusted accordingly.
  • bored piles are formed by a positive circulation drilling machine with a grinding disc.
  • they are drilled with light pressure, low rotation speed and slow drilling. After entering the normal state, the rotation speed and the drilling speed are gradually increased, and the drilling parameters are controlled throughout the process.
  • Drilling speed when changing layers of drilling, appropriately slow down the speed and reduce the drilling pressure to prevent the borehole from tilting; the time interval from the completion of the hole to the start of the concrete pouring is generally controlled within 16 hours, and the pouring time of each pile is generally controlled Within 4-6 hours; of course it is not difficult to understand that the time interval from the completion of the hole formation to the start of the concrete pouring is generally controlled and the pouring time of each pile can also be set to another time, depending on the actual construction needs.
  • the construction of bored piles adopts steel casing and mud water protection.
  • the construction adopts jumping pile construction, jumping 2 holes and drilling 1 hole, and ensuring "drill one hole, inject one hole", symmetrical drilling, adjacent piles should not be poured in less than time 24 hours to avoid the impact of isolation pile collapse on the horizontal deformation of the viaduct pile foundation.
  • the drill rig Due to the height restriction of the viaduct on the construction site, the drill rig is 6m high, and the steel cage is made in 8 sections, and the length of a single section is about 5m.
  • the hoisting equipment of the millstone drill rig is used to hoist the steel cage to meet the construction space under the viaduct.
  • Step 3 Consider the influence of groundwater on the settlement of the viaduct pile foundation and reduce the difficulty of shield construction, and adopt sleeve valve tube grouting treatment for the isolation between the piles, the fine sand layer and the pebble layer to stop the water between the piles.
  • a 40mm diameter rigid sleeve valve tube retreat type segmented grouting can be used, the outlet hole diameter is about 6mm, the quincunx pattern hole, the hole spacing is 20cm, and the outer tube is sealed with rubber.
  • the pipe diameter grouting spacing is 1.2m, and the filling influence radius is 0.8m.
  • the sleeve valve pipe construction adopts the grouting construction method of interval skipping holes, gradual restraint, and first down and then up. Drilling sequence: drill the peripheral holes first, and gradually drill from the outside to the inside. Grouting sequence: from the outside to the inside, first grouting the holes on the reinforcement range line, blocking the slurry leakage channel, and then gradually densifying the grouting holes to grouting and compacting in the middle of the area; the grouting local reinforcement work space is affected The limit can be adjusted by adjusting the angle of the grouting pipe and the arrangement of dense grouting holes.
  • the grouting reinforcement of the sleeve valve tube in the pebble layer with high water-rich and strong permeability should be conducted on-site special experiments, and the solution should be solved by strengthening the grouting port plugging, injecting cement-water glass double-liquid slurry, adding AB chemical slurry, and adding polyurethane slurry.
  • Traditional sleeve valve pipe grouting is easy to collapse, easy to lose grout, and insufficient grouting compactness in such formations.
  • the grouting material can be cement and water glass two-liquid grout, the volume ratio can be 1:1, the water glass concentration can be 35Be, and the grouting pressure can be controlled at 0.5 to 1.0 MPa; but the specific ratio and final grouting The pressure shall be determined by field test.
  • Step 4 Carry out the excavation construction of the downward section of the shield tunnel.
  • the downward section of the shield tunnel underpasses the first 100m of the viaduct as the shield tunneling test section, and optimizes, adjusts, and determines the reasonable control range of the tunneling parameters according to the measured data.
  • the downward sections of the shield tunnel go under the viaduct in the order of left and right, and the distance between the two sections is at least 100m.
  • the shield tunnel traversal and excavation construction in the upward section of the shield tunnel shall be carried out.
  • the upward section of the shield tunnel goes under the viaduct in the order from right to left, and the distance between the two sections is at least 100m.
  • Step 5 Cross the viaduct area under the overlap of multi-shield tunnels, and adopt strengthening measures for the segment structure of the shield tunnel to meet the requirements of strength, durability and waterproofing.
  • the specific measures are as follows:
  • the reinforced segment with HRB400 steel bar diameter of 25mm is generally used.
  • the connecting bolts generally adopt B grade M27 and performance 8.8 bolts to increase the longitudinal rigidity of the tunnel.
  • the impermeability grade is P12 concrete
  • the pipe segment joints are equipped with a porous EPDM elastic gasket
  • the pipe segment circumferential and longitudinal joints are equipped with nitrile cork rubber pads
  • the pipe segments are full of flexible rings.
  • Polyurethane sealant is used for caulking, water stains appearing in the invert range are made of polymer waterproof mortar, all bolt holes are sealed with water-swellable rubber rings, and the lifting holes are sealed with plastic protective covers.
  • Step 6 In the overlap area of multiple shield tunnels, add reserved grouting holes in the segment structure, and carry out secondary or multiple grouting reinforcements for the interlayer soil in the overlap area through lifting holes and grouting holes. In order to reduce the deteriorating effects of additional stress and superimposed deformation on the structure of the first formed tunnel after construction of the tunnel in the overlapping area.
  • the above-mentioned shield tunnel segments are generally divided into 6 blocks, which are 3 standard blocks, 2 adjacent blocks, and 1 capping block.
  • the additional reserved grouting holes for the segments are in each standard block and adjacent block. Two additional reserved grouting holes are added so that after the segment is assembled and stabilized, the interlayer soil in the overlapping area is reinforced by grouting twice or more through the reserved grouting holes.
  • the grouting liquid adopts cement slurry with a water-cement ratio of 1:1, and grouting is drilled at intervals.
  • the grouting pressure is controlled at 0.5 ⁇ 1.0MPa, and it is optimized according to the grouting test on site. After reinforcement, the soil shall have good self-support, sealing and strength, and the unconfined compressive strength shall be greater than 0.8MPa.
  • Step 7 During the shield tunneling of the upward tunnel, a support trolley is erected in the downward tunnel to support and strengthen the overall longitudinal rigidity of the previously constructed tunnel to prevent longitudinal uneven settlement of the tunnel segments.
  • the length of the support section of the support trolley should be selected according to the length of the shield machine.
  • the support trolley can travel on the steel rail.
  • Each support consists of 5 wheeled support arms at 9 o'clock, 11 o'clock, 12 o'clock, 1 o'clock, and 3 o'clock. , Under the thrust of external force, the supporting trolley can move forward in the longitudinal direction without releasing the force.
  • the minimum stiffness of the steel support should be estimated in advance according to the maximum internal force that the support may bear and the allowable value of uneven deformation of the tunnel.
  • the support should have the function of prestress adjustment.
  • the supporting trolley in the downward tunnel must keep in touch with the upward shield tunneling machine at any time, and keep the two moving synchronously.
  • Step 8 Use vibration reduction and isolation measures on the subway track within 50m of the tunnel on both sides of the pier cap of the multi-section tunnel under the viaduct section to reduce the vibration impact of rail transit operations on the viaduct.
  • the subway track adopts an improved rubber (polyurethane) floating slab damping track (the first-order natural vibration frequency is 10-20Hz) to avoid resonance with the railway train running on the viaduct and reduce the vibration energy of the subway train itself.
  • the project described in this embodiment is the project of 4 shield tunnels, small clear distance, and overlapped under-crossing high-speed railway bridge 3.
  • 4 shield tunnels correspond to the two shield tunnels 1 and 2 in the figure.
  • the upper section 2 of the shield tunnels are all driven by an active articulated earth pressure balance shield machine.
  • the outer diameter of the cutter head is 6.68m.
  • the shield segment 8 adopts a single-layer reinforced concrete assembly structure with an outer diameter of 6.4m and an inner diameter of 5.8. m, the thickness is 0.3m, the ring width is 1.2m, the segment ring is divided into six pieces, consisting of a capping block K, two adjacent blocks B, and three standard blocks A, assembled in staggered seams.
  • High-speed rail bridge 3 is a 64m-span pre-stressed continuous beam bridge.
  • the current high-speed rail operating speed is 300km/h.
  • the low-cap pile foundation is adopted under the bridge.
  • the size of the pier cap 6 is 11m ⁇ 26.6m, and 21 diameters are arranged under the cap 6.
  • the 1.5m round piles constitute the pile group foundation, and the lengths of the pile foundations 4 on the left and right sides are 45m and 42m respectively.
  • the minimum distance between the left and right sections of the shield down tunnel is 4.33m, and the buried depths are 28.35m and 19.22m respectively; the shield up tunnel is 5.25m above the shield down tunnel, the left and right sections have a clear distance of 5.6m, and the buried depth is 7.57m. .
  • the minimum clear distances between the 4 shield tunnels and the pile foundations 4 of the high-speed railway bridge on both sides are 10.45m and 10.84m, respectively, as shown in Figure 1.
  • the geology of the four shield tunnels with small clear distances and overlapping high-speed railway bridges is mainly loess, silty clay, fine sand and pebble layers.
  • the water content in the fine sand and pebble layers is relatively rich.
  • this implementation is proposed.
  • the technical solutions are mainly as follows:
  • the isolation pile 5 construction was completed one month before the 4 shield tunnels under the high-speed railway bridge 3, actively changing the original stress field state of the formation and blocking the continuous deformation and stress development trend of the formation.
  • the protection range is 15m beyond the pier cap 6 and the bottom of the isolation pile 5 reaches 4.0m below the bottom of the shield segment 8 Limit the horizontal deformation of the pile foundation 4 of the high-speed railway bridge caused by shield tunneling, and try to block the stress transfer and deformation expansion of shield construction.
  • the isolation pile 5 is arranged in a broken line shape, as shown in FIG. 2.
  • the bored pile is formed by a positive circulation drilling machine with a grinding disc.
  • drilling the drilling is carried out with light pressure, low speed and slow drilling. After entering the normal state, the speed and drilling speed are gradually increased, and the drilling parameters and drilling speed are controlled throughout the process;
  • changing layers and drilling appropriately slow down the speed and reduce the weight on bit to prevent the borehole from tilting; the time interval from the completion of the hole formation to the start of the concrete pouring is controlled within 16 hours, and the pouring time of each pile is controlled within 4-6 hours Inside.
  • the construction of the bored pile adopts steel casing and mud water wall protection.
  • the mud wall protection effect is good, and it is suitable for the construction of the pebble stratum;
  • Immediately stop the surrounding drilling construction find out the cause of the hole collapse, and strengthen the monitoring of the bridge structure.
  • the original pile should be drilled and poured.
  • the drill rig is 6m high, and the steel cage is made in 8 sections, and the length of a single section is about 5m.
  • the hoisting equipment of the grinding disc drill rig is used for the steel cage hoisting work to meet the construction space under the high-speed railway bridge. The location is 3.4m away from the bottom of the high-speed rail bridge.
  • the sleeve valve tube 7 grouting treatment is adopted for the middle and fine sand layer and the pebble layer between the 5 isolation piles.
  • a 40mm diameter rigid sleeve valve tube 7 is used for stepwise grouting.
  • the outlet hole diameter is about 6mm, and the plum blossom-shaped hole is 20cm apart.
  • the outer tube is sealed with rubber.
  • the pipe diameter grouting spacing is 1.2m, and the filling influence radius is 0.8m.
  • the main points of grouting construction for sleeve valve pipe 7 are as follows:
  • 1Sleeve valve tube 7 is drilled by a pilot hole drill with a hole diameter of 90mm, and the hole depth must meet the design requirements.
  • the area where the working space of grouting is restricted can be adjusted by adjusting the angle of the grouting pipe and the arrangement of dense grouting holes.
  • the sleeve valve pipe 7 construction adopts the grouting construction method of interval skipping holes, gradual restraint, and first down and then up.
  • Drilling sequence drill the peripheral holes first, and gradually drill from the outside to the inside.
  • Grouting sequence from the outside to the inside, first grouting the holes on the reinforcement range line, blocking the slurry leakage channel, and then gradually densifying the grouting holes to grouting and compacting in the middle of the area;
  • the grouting material is cement and water glass two-liquid grout, the volume ratio is 1:1, the water glass concentration is 35Be, the grouting pressure is controlled at 0.5 to 1.0 MPa, and the ratio and final grouting pressure need to be determined by field tests.
  • the grouting reinforcement of the sleeve valve tube 7 in the pebble layer with high water content and strong permeability should be carried out on-site special experiments, by strengthening the grouting port plugging, injecting cement-water glass double-liquid slurry, adding AB chemical slurry, adding polyurethane slurry, etc. Measures to solve the problems of traditional sleeve valve pipe grouting in such formations as easy collapse, easy loss of grout, and insufficient grouting compactness.
  • the shield tunnel boring construction of the shield tunnel section will be carried out.
  • the sections of the shield-bored up tunnel go under the high-speed rail bridge 3 in the order from right to left, and the distance between the two sections is at least 100m.
  • the shield tunnel segment structure 8 shall be strengthened to meet the requirements of strength, durability and waterproofing.
  • the main measures are as follows:
  • the reinforced segment with HRB400 steel bar diameter of 25mm is adopted.
  • the connecting bolts 11 of the tube segments adopt B grade M27 and performance 8.8 bolts to increase the longitudinal stiffness of the tunnel.
  • 3Improve the waterproof of the segment structure 8 adopt P12 concrete with impermeability grade, set a porous EPDM elastic gasket at the joints of the pipe segments, and set up nitrile cork rubber pads at the circumferential and longitudinal joints of the pipe segments, and the pipe segments are fully ringed.
  • Use flexible polyurethane sealant for caulking use polymer waterproof mortar for water stains in the invert range, all bolt holes are sealed with water-expandable rubber rings, and lifting holes 9 are sealed with plastic protective covers.
  • a reserved grouting hole 10 is added to the segment structure 8, as shown in Figures 3 and 4.
  • the segment 8 reserved grouting hole 10 and the original hoisting hole 9 are used for secondary or multiple grouting reinforcement in the interlayer soil in the overlapping area; after the construction of the right line, the grouting hole 10 and the original The lifting hole 9 and compensation grouting to the interlayer soil, as shown in Figure 5.
  • the additional stress and superimposed deformation of the first formed tunnel structure 8 are degraded by reducing the overlap area and then constructing the tunnel.
  • control points for adding reserved grouting holes 10 to segments are as follows:
  • the shield tunnel segment 8 is divided into 3 standard blocks, 2 adjacent blocks, and 1 capping block.
  • Two reserved grouting holes 10 are added to each standard block and adjacent block, so that the segments can be assembled and stabilized. , Through the reserved grouting hole 10, the interlayer soil in the overlapping area is reinforced by grouting twice or more times.
  • the installation angles are along the radial direction of the tunnel.
  • the longitudinal spacing is 2.4m.
  • the reinforcement range is 120° at the bottom of the ascending tunnel.
  • the reinforcement thickness is 3m.
  • 3Cement slurry is used for grouting liquid, water cement ratio is 1:1, and grouting is drilled at intervals.
  • the grouting pressure is controlled at 0.5-1.0MPa, and the site is optimized according to the grouting test. After reinforcement, the soil shall have good self-support, sealing and strength, and the unconfined compressive strength shall be greater than 0.8MPa.
  • the length of the support section of the support trolley 14 needs to be selected according to the length of the shield machine.
  • the support trolley 14 can travel on the rails.
  • Each support consists of 9 o'clock, 11 o'clock, 12 o'clock, 1 o'clock and 3 o'clock.
  • a total of 5 wheeled support arms 15 are composed, and the support trolley 14 can move forward in the longitudinal direction without releasing the force under the thrust of external force.
  • the minimum rigidity of the wheel support arm 15 should be estimated in advance according to the maximum internal force that the wheel support arm 15 may bear and the allowable value of uneven deformation of the tunnel.
  • the wheel support arm 15 should have the function of pre-stress adjustment .
  • the shield machine on the right line of the shield down tunnel section must keep in touch with the supporting trolley 14 at any time to keep the two moving in sync.
  • the track adopts vibration reduction and isolation measures.
  • the subway track adopts an improved rubber (polyurethane) floating plate damping track (the first-order natural vibration frequency is 10-20Hz) to avoid resonance with the railway train running on the high-speed railway bridge 3, and to reduce the vibration energy of the subway train itself.

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Civil Engineering (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Paleontology (AREA)
  • Soil Sciences (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

Disclosed is a construction method for shield tunnels passing underneath a viaduct in a multi-interval, small-clear-distance and overlapping manner. The construction method comprises the following steps: according to a principle of having the minimal deformation effect on pile foundations of a viaduct and the surrounding environment, formulating an optimal construction sequence for constructing shield tunnels passing underneath the viaduct in a multi-interval and overlapping manner; before a tunnel passes underneath the viaduct, carrying out active isolation reinforcement for construction in which a shield passes underneath for a short distance; constructing the shield tunnel passing underneath the viaduct; in an area where a plurality of shield tunnel sections pass underneath the viaduct in an overlapping manner, reinforcing a segment structure of the shield tunnel and reinforcing the interior of a tunnel hole; and carrying out track vibration reduction and isolation control in a section where the shield tunnel passes underneath the viaduct.

Description

一种盾构隧道多区间、小净距、交叠下穿高架桥施工方法Construction method for shield tunnels with multiple intervals, small clear distances, and overlapping underpass viaducts 技术领域Technical field
本发明涉及地铁盾构隧道施工技术领域,尤其涉及一种盾构隧道多区间、小净距、交叠下穿高架桥施工方法。The invention relates to the technical field of subway shield tunnel construction, in particular to a construction method for shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts.
背景技术Background technique
这里的陈述仅提供与本发明相关的背景技术,而不必然地构成现有技术。The statements here only provide background art related to the present invention, and do not necessarily constitute prior art.
随着我国城市规模的不断扩张,城市三维立体交通建设成为新时代乘运发展的主趋势,城市地铁与高架路桥是实现三维立体交通的主要渠道,两者的并行发展,势必导致地铁隧道多区间、小净距、交叠下穿高架桥的情况越来越多。尤其是两者对各自运行环境与变形控制均具有较为严苛的要求,受高架桥行车动载、盾构掘进施工地层损失、多区间叠落地铁运营叠加地层扰动等因素影响,容易引起临近高架桥桩不均匀沉降、地表沉陷变形、地铁轨道不平顺等安全风险。因此,制定相应的施工方法与防控措施,保障盾构隧道小净距、叠落下穿高架桥施工安全,避免高架桥桩与盾构隧道不均匀沉陷变形,已成为设计与施工中亟待解决的关键难题。With the continuous expansion of the scale of cities in my country, the construction of urban three-dimensional transportation has become the main trend in the development of transportation in the new era. Urban subways and viaducts are the main channels to achieve three-dimensional transportation. The parallel development of the two will inevitably lead to multiple sections of subway tunnels. There are more and more cases of small clear distances and overlapping underpasses. In particular, the two have relatively strict requirements for their respective operating environment and deformation control. They are affected by factors such as the dynamic load of the viaduct, the ground loss during the shield tunneling construction, and the superimposed ground disturbance of the multi-section subway operation. It is easy to cause adjacent viaduct piles. Safety risks such as uneven settlement, surface subsidence and deformation, and irregular subway tracks. Therefore, formulating corresponding construction methods and prevention and control measures to ensure the safety of shield tunnels with small clear distances, stacking and falling through viaducts, and avoiding uneven settlement and deformation of viaduct piles and shield tunnels, has become a key problem to be solved in design and construction. .
现有技术主要是针对盾构隧道正交下穿高架桥隔离加固控制,隔离加固多采用钻孔灌注桩、搅拌桩、旋喷桩、甚至地下连续墙等围护结构,阻断盾构隧道与高架桩基的连续变形,其变形控制效果有限,对于含水地层、多区间盾构隧道、小净距交叠穿越施工等多重复杂工况下,难以满足施工安全控制要求,未形成多控制技术联合的综合控制体系及施工方法。The existing technology is mainly aimed at the isolation and reinforcement control of shield tunnels passing through viaducts orthogonally. The isolation and reinforcement usually use bored piles, mixing piles, jet-grouted piles, and even underground continuous walls to block shield tunnels and elevated bridges. The continuous deformation of the pile foundation has limited deformation control effects. It is difficult to meet the construction safety control requirements under multiple complex conditions such as water-bearing strata, multi-interval shield tunnels, and small-clear overlap crossing construction, and there is no combination of multiple control technologies. Comprehensive control system and construction methods.
发明内容Summary of the invention
为了解决现有技术的不足,本发明提供了一种盾构隧道多区间、小净距、交叠下穿高架桥施工方法。In order to solve the shortcomings of the prior art, the present invention provides a construction method for shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts.
为了达成上述目的,本发明采用如下技术方案:In order to achieve the above objective, the present invention adopts the following technical solutions:
一种盾构隧道多区间、小净距、交叠下穿高架桥施工方法,具体步骤如下:A construction method for shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts. The specific steps are as follows:
步骤一:按照对高架桥桩基及周边环境变形影响最小的原则,制定盾构隧道多区间、叠落下穿高架桥施工的最优施工顺序;Step 1: According to the principle of the least impact on the deformation of the viaduct pile foundation and the surrounding environment, formulate the optimal construction sequence for the construction of the shield tunnel with multiple sections and stacked under the viaduct;
步骤二:在隧道下穿高架桥之前,进行盾构近距离下穿施工的主动隔离加固;Step 2: Before the tunnel underpasses the viaduct, conduct active isolation and reinforcement of the short-distance underpass construction of the shield;
步骤三:进行盾构隧道下穿高架桥的施工;Step 3: Carry out the construction of the shield tunnel under the viaduct;
步骤四:在多盾构隧道区间交叠下穿高架桥的区域,对盾构隧道的管片结构进行加强,对隧道洞内进行加固;Step 4: Reinforce the segment structure of the shield tunnel in the area where the multi-shield tunnel overlaps and pass through the viaduct, and strengthen the tunnel cavity;
步骤五:在盾构隧道下穿高架桥区段进行轨道减隔振控制。Step 5: The track vibration reduction and isolation control is carried out in the section of the shield tunnel passing through the viaduct.
作为进一步的技术方案,步骤一的具体工作方法是:建立高精度三维数值模型,模拟分析多条盾构隧道不同顺序施工引起的高架桥结构变形与周边地层变形情况,确定对高架桥桩基及周边环境变形影响最小的下穿施工顺序即为最优施工顺序。As a further technical solution, the specific working method of step one is to establish a high-precision three-dimensional numerical model, simulate and analyze the deformation of the viaduct structure and surrounding stratum caused by the construction of multiple shield tunnels in different sequences, and determine the correctness of the viaduct pile foundation and surrounding environment The underpass construction sequence with the least deformation effect is the optimal construction sequence.
更进一步地,高精度三维数值模型中地层参数、隧道走向及尺寸、高架桥荷载与桩基参数、盾构掘进过程等信息要与实际施工情况一致,以提高数值模拟准确性。Furthermore, the formation parameters, tunnel direction and size, viaduct load and pile foundation parameters, shield tunneling process and other information in the high-precision three-dimensional numerical model must be consistent with the actual construction situation to improve the accuracy of the numerical simulation.
作为进一步的技术方案,所述的步骤二的具体工作方法是:As a further technical solution, the specific working method of the second step is:
步骤2.1施做钻孔灌注桩作隔离桩;Step 2.1 Construct bored piles as isolation piles;
在盾构下穿高架桥前一段时间完成隔离桩施工,在盾构隧道与高架桥桩基间 打设钻孔灌注桩,灌注桩的防护范围长出桥墩承台外,灌注桩底部达到盾构管片结构底以下,以限制盾构掘进引起的桥桩水平变形,尽量阻断盾构施工的应力传递及变形扩展;The isolation pile construction is completed some time before the shield passes through the viaduct, and bored piles are built between the shield tunnel and the viaduct pile foundation. The protection range of the cast-in-place pile extends beyond the pier cap, and the bottom of the cast-in-place pile reaches the shield segment. Below the structure bottom, in order to limit the horizontal deformation of bridge piles caused by shield tunneling, and try to block the stress transmission and deformation expansion of shield construction;
步骤2.2进行袖阀管注浆作桩间止水;Step 2.2 Carry out sleeve valve pipe grouting to stop water between piles;
对隔离桩间中、细砂层及卵石层采取袖阀管注浆处理。Sleeve valve tube grouting is adopted for the middle, fine sand layer and pebble layer between the isolated piles.
进一步地,钻孔灌注桩采用磨盘正循环钻机成孔,钻进时先轻压、低转速、慢钻进,进入正常状态后,逐渐加大转速和钻进速度;全程控制钻进参数、钻速;在换层钻进时,适当地减慢转速和减轻钻压,防止造成钻孔倾斜。Further, the bored pile is formed by a positive circulation drilling machine with a grinding disc. When drilling, it is drilled with light pressure, low rotation speed and slow drilling. After entering the normal state, the rotation speed and the drilling speed are gradually increased; the drilling parameters and drilling speed are controlled throughout the process. Speed; when changing layers, appropriately slow down the speed and reduce the weight on bit to prevent the borehole from tilting.
进一步地,钻孔灌注桩施工采用钢护筒跟进与泥水护壁,泥浆护壁效果好,适用于卵石地层施工。若出现塌孔,应立即停止周围钻孔施工,查明塌孔原因,并加强对桥梁结构监测;补桩时,应在原桩位进行钻孔灌注。Furthermore, the construction of bored piles adopts steel casing and mud water wall protection. The mud wall protection effect is good and it is suitable for the construction of pebble stratum. If there is a hole collapse, the surrounding drilling should be stopped immediately, the cause of the hole collapse should be found out, and the monitoring of the bridge structure should be strengthened; when the pile is repaired, the original pile should be drilled and poured.
进一步地,钻孔灌注桩施工采用跳桩施工,且保证“钻一孔,注一孔”,并保证对称钻孔,以减小隔离桩施工对高架桥桩的影响。Furthermore, the construction of bored piles adopts jumping pile construction, and guarantees "drill one hole, inject one hole" and guarantee symmetrical drilling to reduce the impact of isolation pile construction on viaduct piles.
进一步地,由于施工场地高架桥高度限制,钢筋笼分节制作,采用磨盘钻机的卷扬设备进行钢筋笼吊装工作,以满足高架桥下施工空间。Furthermore, due to the height restriction of the viaduct in the construction site, the steel cage is made in sections, and the hoisting equipment of the millstone drill is used for hoisting the steel cage to meet the construction space under the viaduct.
进一步地,袖阀管钻孔采用引孔钻机,孔深需达设计要求。注浆局部加固作业空间受限处,可通过调整注浆管角度、加密注浆孔布置等措施调整。Further, the sleeve valve tube is drilled with a pilot hole drill, and the hole depth needs to meet the design requirements. The area where the working space of grouting is restricted can be adjusted by adjusting the angle of the grouting pipe and the arrangement of dense grouting holes.
进一步地,袖阀管施工采用间隔跳孔、逐步约束、先下后上的注浆施工方法。钻孔顺序:先钻周边孔,由外向内逐步钻孔。注浆顺序:由外向内进行,先对加固范围线上钻孔进行注浆,阻断浆液漏失通道后,再逐步加密注浆孔,进行区域中部注浆压密。Furthermore, the sleeve valve pipe construction adopts the grouting construction method of interval skipping holes, gradual restraint, and first down and then up. Drilling sequence: drill the peripheral holes first, and gradually drill from the outside to the inside. Grouting sequence: from the outside to the inside, first grouting the holes on the reinforcement range line, blocking the slurry leakage channel, and then gradually densifying the grouting holes to perform grouting and compaction in the middle of the area.
进一步地,对高富水强渗透的卵石层袖阀管注浆加固应做现场专项实验,通 过多种措施解决传统袖阀管注浆在此类地层中易塌孔、浆液易流失、注浆致密性不足等问题;措施包括:加强注浆口封堵、注入水泥~水玻璃双液浆、加注AB化学浆液、加注聚氨酯浆液等Further, special field experiments should be done for the grouting reinforcement of sleeve valve tube in the pebble layer with high water richness and strong permeability. Various measures should be taken to solve the problem that traditional sleeve valve tube grouting is easy to collapse in such formations, the slurry is easy to lose, and the grouting is dense. Insufficient performance and other issues; measures include: strengthening the plugging of the grouting port, injecting cement-water glass double-liquid slurry, adding AB chemical slurry, adding polyurethane slurry, etc.
作为进一步的技术方案,所述的步骤四中进行盾构隧道管片结构加强,其主要包括:As a further technical solution, the shield tunnel segment structure strengthening is performed in the step 4, which mainly includes:
1、进行隧道管片主筋和分布筋加强;1. Reinforce the main reinforcement and distribution reinforcement of the tunnel segment;
2、提高管片纵向螺栓等级,增加隧道纵向刚度。2. Improve the longitudinal bolt grade of the segment and increase the longitudinal rigidity of the tunnel.
3、提高管片结构防水;管片接缝设置一道多孔型三元乙丙弹性密封垫,管片环缝及纵缝设置丁腈软木橡胶垫,管片满环采用柔性聚氨酯密封胶嵌缝;仰拱范围出现水湿渍采用聚合物防水砂浆,所有螺栓孔均采用遇水膨胀橡胶圈进行密封处理,吊装孔采用塑料保护罩封堵。3. Improve the waterproofness of the tube structure; a porous EPDM elastic gasket is set at the joints of the tube sections, a nitrile cork rubber pad is set at the circumferential and longitudinal seams of the tube sections, and the full loops of the tube sections are caulked with flexible polyurethane sealant; Water-wet stains in the invert range are made of polymer waterproof mortar, all bolt holes are sealed with water-swellable rubber rings, and the lifting holes are sealed with plastic protective covers.
作为进一步的技术方案,所述的步骤四中进行交叠区隧道洞内加固,其主要包括:As a further technical solution, the reinforcement in the tunnel in the overlap zone is carried out in the fourth step, which mainly includes:
1、在管片结构增设预留注浆孔,通过注浆孔对交叠区域土体进行洞内注浆加固,以减小多区间交叠区域后施工隧道对先成型隧道结构的附加应力和叠加变形等劣化影响;1. Add a reserved grouting hole in the segment structure, and use the grouting hole to reinforce the soil in the overlapping area to reduce the additional stress and stress on the first formed tunnel structure after the construction of the multi-section overlapping area. Degradation effects such as superimposed deformation;
2、在上行盾构掘进期间,对下行隧道内架设支撑台车以支撑加强先成型隧道的整体纵向刚度,防止对隧道管片产生纵向不均匀沉降。2. During the ascending shield tunneling, a support trolley is erected in the descending tunnel to support and strengthen the overall longitudinal rigidity of the previously formed tunnel to prevent longitudinal uneven settlement of the tunnel segments.
进一步地,每环隧道管片一般分为6块,为3块标准块、2块邻接块、1块封顶块,管片增设预留注浆孔是在每块标准块与邻接块中各增设2个预留注浆孔,以便管片拼装稳定后,通过预留注浆孔对交叠区域夹层土体进行洞内二次或多次注浆加固。Furthermore, each ring tunnel segment is generally divided into 6 blocks, which are 3 standard blocks, 2 adjacent blocks, and 1 capping block. The additional reserved grouting holes for the segment are added to each standard block and adjacent blocks. 2 reserved grouting holes, so that after the segment is assembled and stabilized, the interlayer soil in the overlapping area is reinforced by grouting twice or more through the reserved grouting holes.
作为进一步的技术方案,所述的步骤五中在地铁隧道下穿高架桥区段进行轨道减隔振控制,其主要包括:As a further technical solution, in the fifth step, the track vibration reduction and isolation control is performed in the subway tunnel underpassing the viaduct section, which mainly includes:
在地铁隧道下穿高架桥区段的桥墩承台两侧各50m隧道范围内,对地铁轨道采用减隔振措施,以减小轨道交通运营对高架桥梁的振动影响。Vibration reduction and isolation measures are adopted for the subway track within the 50m tunnel range on both sides of the pier cap of the subway tunnel under the viaduct section to reduce the impact of rail transit operations on the vibration of the elevated bridge.
进一步地,地铁轨道采用改良橡胶(聚氨酯)浮置板减震轨道(一阶自振频率为10~20Hz),以避免与高架桥运行铁路列车发生共振,又能降低地铁列车自身振动能量。Furthermore, the subway track uses an improved rubber (polyurethane) floating slab damping track (the first-order natural vibration frequency is 10-20 Hz) to avoid resonance with the railway train running on the viaduct and reduce the vibration energy of the subway train itself.
本发明积极效果体现为:The positive effects of the present invention are embodied as:
1、本发明通过施工顺序优化、主动隔离加固、管片结构加强、洞内注浆加固、轨道减隔振5方面控制技术组合形成了盾构隧道下穿高架桥主动控制体系,施工稳定性与变形控制效果极佳,克服了传统隔离桩控制方式单一、控制效果有限、未能主动预防风险等弊端,能够满足含水地层、多区间、小净距、交叠盾构隧道下穿高架桥施工的安全控制要求。1. The present invention forms an active control system of shield tunnel underpassing viaduct through a combination of control technologies in five aspects: construction sequence optimization, active isolation and reinforcement, segment structure reinforcement, tunnel grouting reinforcement, and track vibration reduction and isolation, and the construction stability and deformation The control effect is excellent. It overcomes the disadvantages of single control method of traditional isolation piles, limited control effect, and failure to actively prevent risks. It can meet the safety control of water-bearing strata, multiple intervals, small clear distance, and overlapping shield tunnels under the viaduct construction Claim.
2、本发明通过制定盾构隧道多区间、叠落下穿施工最优施工顺序,依据科学化、信息化手段判定多区间的先后下穿施工顺序,避免经验决策的主观性与盲目性,有效降低穿越施工风险。2. The present invention formulates the optimal construction sequence for the multi-section and stacked-down underpass construction of the shield tunnel, and determines the sequence of the multi-section underpass construction according to scientific and informatized means, avoiding the subjectivity and blindness of empirical decision-making, and effectively reducing Crossing construction risks.
3、本发明通过下穿施工前预先施做钻孔灌注桩隔离加固、袖阀管注浆桩间止水等措施,主动改变高架桥周围地层的应力场状态,改善土体力学性能,阻断原始地层的连续变形与应力发展趋势,起到主动隔离、预控风险的作用。3. The invention actively changes the stress field state of the stratum surrounding the viaduct by pre-implementing measures such as isolation and reinforcement of bored piles and sleeve valve pipe grouting piles before the underpass construction, thereby improving the mechanical properties of the soil and blocking the original The continuous deformation and stress development trend of the stratum play a role in active isolation and risk control.
4、本发明通过隧道管片增设预留注浆孔对多区间交叠区域进行洞内注浆加固,将交叠隧道间的软弱扰动土体胶结形成整体,提高了地层的刚度、强度和自稳性,从而降低后施工隧道对先成型隧道结构的附加应力和叠加变形等劣化影 响。4. In the present invention, by adding reserved grouting holes to the tunnel segments, grouting reinforcement is carried out in the overlapping area of multiple sections, and the weak disturbing soil between the overlapping tunnels is cemented into a whole, which improves the rigidity, strength and self-control of the ground. Stability, so as to reduce the impact of additional stress and superimposed deformation on the structure of the first formed tunnel.
综上所述,本发明成功实现了含水软弱地层中盾构隧道多区间、小净距、交叠下穿高架桥的施工安全,有效控制了高架桥梁与地铁隧道的结构损伤与沉降变形,可广泛适用于含水软弱地质、盾构小净距交叠掘进、多条区间隧道同一桥跨下穿高架桥、高架桥变形控制严格等条件下的盾构穿越施工工程。In summary, the present invention has successfully realized the construction safety of shield tunnels with multiple intervals, small clear distances, and overlapping underpasses in water-bearing soft formations, effectively controlling the structural damage and settlement deformation of the viaducts and subway tunnels, and can be widely used. It is suitable for shield crossing construction projects under the conditions of water-bearing and weak geology, shield tunneling with small clear spacing, multiple interval tunnels under the same bridge span, and under the conditions of strict control of the deformation of the viaduct.
附图说明Description of the drawings
构成本申请的一部分的说明书附图用来提供对本申请的进一步理解,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的不当限定。The drawings of the specification forming a part of the application are used to provide a further understanding of the application, and the exemplary embodiments and descriptions of the application are used to explain the application, and do not constitute an improper limitation of the application.
图1为本发明盾构隧道多区间、小净距、交叠下穿高架桥加固控制剖面图;Fig. 1 is a cross-section view of the reinforcement control of the shield tunnel of the present invention with multiple sections, small clear distances, and overlapping underpass viaducts;
图2为盾构隧道多区间、小净距、交叠下穿高架桥加固控制平面图;Figure 2 is a plan view of the reinforcement control of the shield tunnel with multiple sections, small clear distances, and overlapping underpass viaducts;
图3为盾构隧道管片增设预留注浆孔剖面示意图;Figure 3 is a schematic diagram of the section of the shield tunnel segment with additional reserved grouting holes;
图4为盾构隧道管片增设预留注浆孔结构示意图;Figure 4 is a schematic diagram showing the structure of additional reserved grouting holes for shield tunnel segments;
图5为盾构隧道小净距、交叠区域注浆预加固示意图;Figure 5 is a schematic diagram of grouting pre-reinforcement in shield tunnels with small clearance and overlapping areas;
图6为盾构隧道洞内支撑台车布置示意图;Figure 6 is a schematic diagram of the layout of the supporting trolley in the shield tunnel;
图7为钻孔灌注桩施工工艺流程图。Figure 7 is a flow chart of the construction process of bored piles.
图例说明:1-盾构隧道下行区间;2-盾构隧道上行区间;3-高铁桥;4-桩基;5-隔离桩;6-桥墩承台;7-袖阀管;8-管片结构;9-吊装孔;10-预留注浆孔;11-连接螺栓;12-注浆管;13-注浆区;14-支撑台车;15-轮式支撑臂。Legend: 1-down section of shield tunnel; 2-up section of shield tunnel; 3-high-speed railway bridge; 4-pile foundation; 5-isolated pile; 6-pier cap; 7-sleeve valve tube; 8-segment Structure; 9-hoisting hole; 10-prepared grouting hole; 11-connecting bolt; 12-grouting pipe; 13-grouting area; 14-support trolley; 15-wheeled support arm.
具体实施方式Detailed ways
应该指出,以下详细说明都是例示性的,旨在对本申请提供进一步的说明。除非另有指明,本发明使用的所有技术和科学术语具有与本申请所属技术领域的普通技术人员通常理解的相同含义。It should be pointed out that the following detailed descriptions are all illustrative and are intended to provide further explanations for the application. Unless otherwise specified, all technical and scientific terms used in the present invention have the same meaning as commonly understood by those of ordinary skill in the technical field to which this application belongs.
需要注意的是,这里所使用的术语仅是为了描述具体实施方式,而非意图限制根据本申请的示例性实施方式。如在这里所使用的,除非上下文另外明确指出,否则单数形式也意图包括复数形式,此外,还应当理解的是,当在本说明书中使用术语“包含”和/或“包括”时,其指明存在特征、步骤、操作、器件、组件和/或它们的组合;It should be noted that the terms used here are only for describing specific embodiments, and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should also be understood that when the terms "comprising" and/or "including" are used in this specification, they indicate There are features, steps, operations, devices, components, and/or combinations thereof;
正如背景技术部分所描述的,现有技术主要是针对盾构隧道正交下穿高架桥隔离加固控制,隔离加固多采用钻孔灌注桩、搅拌桩、旋喷桩、甚至地下连续墙等围护结构,阻断盾构隧道与高架桩基的连续变形,其变形控制效果有限,对于含水地层、多区间盾构隧道、小净距交叠穿越施工等多重复杂工况下,难以满足施工安全控制要求,未形成多控制技术联合的综合控制体系及施工方法;本发明提供了一种盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,为使本发明的目的、技术方案及效果更加清楚、明确,以下对本发明进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。As described in the background technology section, the existing technology is mainly aimed at the isolation and reinforcement control of shield tunnels crossing the viaduct orthogonally. The isolation and reinforcement mostly use bored piles, mixing piles, jet grouting piles, and even underground continuous walls and other retaining structures , Blocking the continuous deformation of the shield tunnel and the elevated pile foundation, its deformation control effect is limited. It is difficult to meet the construction safety control requirements under multiple complex conditions such as water-bearing strata, multi-interval shield tunnels, and small-clear overlap crossing construction. , A comprehensive control system and construction method that does not form a combination of multiple control technologies; the present invention provides a construction method for shield tunnels with multiple sections, small clear distances, and overlapped underpass viaducts, in order to enable the objectives, technical solutions and The effect is clearer and clearer, and the present invention will be described in further detail below. It should be understood that the specific embodiments described here are only used to explain the present invention, but not to limit the present invention.
本发明提出的盾构隧道多区间、小净距、交叠下穿高架桥施工方法主要包括盾构隧道多区间、叠落下穿施工顺序判定技术;盾构近距离下穿施工主动隔离控制技术;盾构隧道管片结构加强技术;交叠区隧道洞内加固控制技术;地铁隧道下穿高架桥减隔振控制技术;上述5项技术组合即形成了盾构隧道多区间、小净距、交叠下穿高架桥主动控制施工方法。The shield tunnel multi-interval, small clear distance, and overlapped underpass construction method proposed by the present invention mainly includes shield tunnel multi-interval, overlapped underpass construction sequence determination technology; shield tunnel close underpass construction active isolation control technology; shield Tunnel segment structure strengthening technology; tunnel reinforcement control technology in the overlap zone; vibration reduction and isolation control technology for subway tunnels under the viaduct; the combination of the above 5 technologies forms a shield tunnel with multiple sections, small clear distances, and overlap Actively control construction methods across viaducts.
本发明提供了一种盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其具体包括以下步骤:The invention provides a construction method for shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts, which specifically includes the following steps:
步骤一:在多条盾构区间隧道、小净距、交叠下穿高架桥前,首先制定多区间下穿高架桥施工最优施工顺序。通过建立高精度三维数值模型,模拟分析多条 盾构隧道不同顺序施工引起的高架桥结构变形与周边地层变形情况,确定对高架桥桩基及周边环境变形影响最小的施工顺序即为最优施工顺序。Step 1: Before multiple shield tunnels, small clear distances, and overlapping underpass viaducts, first formulate the optimal construction sequence for multi-section underpass viaduct construction. Through the establishment of a high-precision three-dimensional numerical model, simulation and analysis of the viaduct structural deformation and surrounding ground deformation caused by the construction of multiple shield tunnels in different sequences, the optimal construction sequence is determined by the construction sequence that has the least impact on the viaduct pile foundation and surrounding environment deformation.
进一步地,高精度三维数值模型中地层参数、隧道走向及尺寸、高架桥荷载与桩基参数、盾构掘进过程等信息要与实际施工情况一致,以提高数值模拟准确性。Furthermore, the formation parameters, tunnel direction and size, viaduct load and pile foundation parameters, shield tunneling process and other information in the high-precision three-dimensional numerical model must be consistent with the actual construction situation to improve the accuracy of the numerical simulation.
步骤二:在盾构隧道下穿高架桥前1个月完成隔离桩施工,在盾构隧道与高架桥桩基间打设钻孔灌注桩作隔离桩,以限制盾构掘进引起高架桥桩基的水平变形,尽量阻断盾构施工的应力传递及变形扩展。Step 2: Complete the isolation pile construction one month before the shield tunnel goes under the viaduct, and drill cast-in-place piles between the shield tunnel and the viaduct pile foundation as isolation piles to limit the horizontal deformation of the viaduct pile foundation caused by shield tunneling , Try to block the stress transmission and deformation expansion of shield construction.
优选的,隔离桩的尺寸选择Φ800@1000;且一般要求防护范围长出桥墩承台外15m,隔离桩底部达到盾构管片结构底以下4.0m;但是具体尺寸不限于此尺寸,可以根据具体施工环境进行相应的调整。Preferably, the size of the isolation pile is selected as Φ800@1000; and it is generally required that the protection range is 15m beyond the pier cap, and the bottom of the isolation pile reaches 4.0m below the bottom of the shield segment; but the specific size is not limited to this size, and can be based on specific The construction environment shall be adjusted accordingly.
进一步地,上述钻孔灌注桩采用磨盘正循环钻机成孔,钻进时先轻压、低转速、慢钻进,进入正常状态后,逐渐加大转速和钻进速度,全程控制钻进参数、钻速;在换层钻进时,适当地减慢转速和减轻钻压,防止造成钻孔倾斜;成孔完毕至开始灌注混凝土的时间间隔一般控制在16小时内,每根桩灌注时间一般控制在4~6小时内;当然不难理解的,成孔完毕至开始灌注混凝土的时间间隔一般控制和每根桩灌注时间也可以设置为别的时间,具体的根据实际施工需要进行施工。Further, the above-mentioned bored piles are formed by a positive circulation drilling machine with a grinding disc. When drilling, they are drilled with light pressure, low rotation speed and slow drilling. After entering the normal state, the rotation speed and the drilling speed are gradually increased, and the drilling parameters are controlled throughout the process. Drilling speed; when changing layers of drilling, appropriately slow down the speed and reduce the drilling pressure to prevent the borehole from tilting; the time interval from the completion of the hole to the start of the concrete pouring is generally controlled within 16 hours, and the pouring time of each pile is generally controlled Within 4-6 hours; of course it is not difficult to understand that the time interval from the completion of the hole formation to the start of the concrete pouring is generally controlled and the pouring time of each pile can also be set to another time, depending on the actual construction needs.
钻孔灌注桩施工采用钢护筒跟进与泥水护壁,施工采用跳桩施工,跳2孔钻1孔,且保证“钻一孔,注一孔”,对称钻孔,邻近桩灌注时间不宜小于24小时,以避免隔离桩塌孔对高架桥桩基的水平变形影响。The construction of bored piles adopts steel casing and mud water protection. The construction adopts jumping pile construction, jumping 2 holes and drilling 1 hole, and ensuring "drill one hole, inject one hole", symmetrical drilling, adjacent piles should not be poured in less than time 24 hours to avoid the impact of isolation pile collapse on the horizontal deformation of the viaduct pile foundation.
由于施工场地高架桥高度限制,钻机高6m,钢筋笼分8节制作,单节长度5m 左右,采用磨盘钻机的卷扬设备进行钢筋笼吊装工作,以满足高架桥下施工空间。Due to the height restriction of the viaduct on the construction site, the drill rig is 6m high, and the steel cage is made in 8 sections, and the length of a single section is about 5m. The hoisting equipment of the millstone drill rig is used to hoist the steel cage to meet the construction space under the viaduct.
步骤三:考虑地下水对高架桥桩基沉降的影响及降低盾构施工难度,对隔离桩间中、细砂层及卵石层采取袖阀管注浆处理作桩间止水。Step 3: Consider the influence of groundwater on the settlement of the viaduct pile foundation and reduce the difficulty of shield construction, and adopt sleeve valve tube grouting treatment for the isolation between the piles, the fine sand layer and the pebble layer to stop the water between the piles.
优选的,可以采用直径40mm刚性袖阀管后退式分段注浆,出浆孔眼直径约6mm,梅花型布孔,孔眼间距20cm,并用橡胶皮封住外管。管径注浆间距1.2m,充填影响半径0.8m。Preferably, a 40mm diameter rigid sleeve valve tube retreat type segmented grouting can be used, the outlet hole diameter is about 6mm, the quincunx pattern hole, the hole spacing is 20cm, and the outer tube is sealed with rubber. The pipe diameter grouting spacing is 1.2m, and the filling influence radius is 0.8m.
进一步的,上述袖阀管钻孔采用引孔钻机,钻孔直径大概为90mm,孔深需达设计要求。袖阀管施工采用间隔跳孔、逐步约束、先下后上的注浆施工方法。钻孔顺序:先钻周边孔,由外向内逐步钻孔。注浆顺序:由外向内进行,先对加固范围线上钻孔进行注浆,阻断浆液漏失通道后,再逐步加密注浆孔,进行区域中部注浆压密;注浆局部加固作业空间受限处,可通过调整注浆管角度、加密注浆孔布置等措施调整。Further, the above-mentioned sleeve valve tube is drilled by a pilot hole drill, the diameter of the hole is about 90mm, and the hole depth needs to meet the design requirements. The sleeve valve pipe construction adopts the grouting construction method of interval skipping holes, gradual restraint, and first down and then up. Drilling sequence: drill the peripheral holes first, and gradually drill from the outside to the inside. Grouting sequence: from the outside to the inside, first grouting the holes on the reinforcement range line, blocking the slurry leakage channel, and then gradually densifying the grouting holes to grouting and compacting in the middle of the area; the grouting local reinforcement work space is affected The limit can be adjusted by adjusting the angle of the grouting pipe and the arrangement of dense grouting holes.
对高富水强渗透的卵石层袖阀管注浆加固应做现场专项实验,通过加强注浆口封堵、注入水泥~水玻璃双液浆、加注AB化学浆液、加注聚氨酯浆液等措施解决传统袖阀管注浆在此类地层中易塌孔、浆液易流失、注浆致密性不足等问题。例如:注浆材料可以为水泥、水玻璃双液浆,体积比可以为1:1,水玻璃浓度可以为35Be,注浆压力可以控制在0.5~1.0MPa;但是具体的配比及注浆终压需经现场试验确定。The grouting reinforcement of the sleeve valve tube in the pebble layer with high water-rich and strong permeability should be conducted on-site special experiments, and the solution should be solved by strengthening the grouting port plugging, injecting cement-water glass double-liquid slurry, adding AB chemical slurry, and adding polyurethane slurry. Traditional sleeve valve pipe grouting is easy to collapse, easy to lose grout, and insufficient grouting compactness in such formations. For example: the grouting material can be cement and water glass two-liquid grout, the volume ratio can be 1:1, the water glass concentration can be 35Be, and the grouting pressure can be controlled at 0.5 to 1.0 MPa; but the specific ratio and final grouting The pressure shall be determined by field test.
步骤四:进行盾构隧道下行区间掘进施工,盾构隧道下行区间下穿高架桥前100m作为盾构掘进试验段,根据实测数据优化、调整、确定合理的掘进参数控制范围。盾构隧道下行区间以先左后右的顺序分别下穿高架桥,两区间间隔距离至少100m。盾构隧道下行区间穿越完成后,间隔至少个月后,进行盾构隧道上行区 间的盾构穿越掘进施工。盾构隧道上行区间以先右后左的顺序分别下穿高架桥,两区间间隔距离至少100m。Step 4: Carry out the excavation construction of the downward section of the shield tunnel. The downward section of the shield tunnel underpasses the first 100m of the viaduct as the shield tunneling test section, and optimizes, adjusts, and determines the reasonable control range of the tunneling parameters according to the measured data. The downward sections of the shield tunnel go under the viaduct in the order of left and right, and the distance between the two sections is at least 100m. After the downward section of the shield tunnel is traversed, at least a month later, the shield tunnel traversal and excavation construction in the upward section of the shield tunnel shall be carried out. The upward section of the shield tunnel goes under the viaduct in the order from right to left, and the distance between the two sections is at least 100m.
步骤五:在多盾构区间交叠下穿高架桥区域,对盾构隧道管片结构采取加强措施,以满足强度、耐久性及防水等要求,具体手段如下:Step 5: Cross the viaduct area under the overlap of multi-shield tunnels, and adopt strengthening measures for the segment structure of the shield tunnel to meet the requirements of strength, durability and waterproofing. The specific measures are as follows:
加强隧道管片主筋和分布筋,一般采用HRB400钢筋直径为25mm的加强型管片。To strengthen the main reinforcement and distribution reinforcement of the tunnel segment, the reinforced segment with HRB400 steel bar diameter of 25mm is generally used.
提高管片纵向螺栓等级,连接螺栓一般采用B级M27,性能8.8级螺栓,增加隧道纵向刚度。To improve the longitudinal bolt grade of the segment, the connecting bolts generally adopt B grade M27 and performance 8.8 bolts to increase the longitudinal rigidity of the tunnel.
提高管片结构防水,采用抗渗等级为P12混凝土,管片接缝设置一道多孔型三元乙丙弹性密封垫,管片环缝及纵缝设置丁腈软木橡胶垫,管片满环采用柔性聚氨酯密封胶嵌缝,仰拱范围出现水湿渍采用聚合物防水砂浆,所有螺栓孔均采用遇水膨胀橡胶圈进行密封处理,吊装孔采用塑料保护罩封堵。To improve the waterproof of the pipe segment structure, the impermeability grade is P12 concrete, the pipe segment joints are equipped with a porous EPDM elastic gasket, the pipe segment circumferential and longitudinal joints are equipped with nitrile cork rubber pads, and the pipe segments are full of flexible rings. Polyurethane sealant is used for caulking, water stains appearing in the invert range are made of polymer waterproof mortar, all bolt holes are sealed with water-swellable rubber rings, and the lifting holes are sealed with plastic protective covers.
步骤六:在多条盾构区间交叠区域,在管片结构增设预留注浆孔,通过吊装孔和注浆孔对交叠区域夹层土体进行洞内二次或多次注浆加固,以减小交叠区域后施工隧道对先成型隧道结构的附加应力和叠加变形等劣化影响。Step 6: In the overlap area of multiple shield tunnels, add reserved grouting holes in the segment structure, and carry out secondary or multiple grouting reinforcements for the interlayer soil in the overlap area through lifting holes and grouting holes. In order to reduce the deteriorating effects of additional stress and superimposed deformation on the structure of the first formed tunnel after construction of the tunnel in the overlapping area.
进一步地,上述盾构隧道管片一般分为6块,为3块标准块、2块邻接块、1块封顶块,管片增设预留注浆孔是在每块标准块与邻接块中各增设2个预留注浆孔,以便管片拼装稳定后,通过预留注浆孔对交叠区域夹层土体进行洞内二次或多次注浆加固。Furthermore, the above-mentioned shield tunnel segments are generally divided into 6 blocks, which are 3 standard blocks, 2 adjacent blocks, and 1 capping block. The additional reserved grouting holes for the segments are in each standard block and adjacent block. Two additional reserved grouting holes are added so that after the segment is assembled and stabilized, the interlayer soil in the overlapping area is reinforced by grouting twice or more through the reserved grouting holes.
注浆管可以采用直径42mm,t=3.5mm钢化管,打设角度均沿隧道径向,纵向间距为2.4m,注浆管长度L=3.0m,加固范围为上行隧道底部120°,加固厚度3m。注浆液采用水泥浆,水灰比1:1,间隔钻孔注浆。注浆压力控制在0.5~1.0MPa, 现场根据注浆试验进行优化。加固后土体需具有良好的自立性、密封性及强度,无侧限抗压强度大于0.8MPa。The grouting pipe can be a steel pipe with a diameter of 42mm, t=3.5mm, and the setting angles are along the radial direction of the tunnel, the longitudinal spacing is 2.4m, the length of the grouting pipe is L=3.0m, and the reinforcement range is 120° at the bottom of the ascending tunnel, and the reinforcement thickness 3m. The grouting liquid adopts cement slurry with a water-cement ratio of 1:1, and grouting is drilled at intervals. The grouting pressure is controlled at 0.5~1.0MPa, and it is optimized according to the grouting test on site. After reinforcement, the soil shall have good self-support, sealing and strength, and the unconfined compressive strength shall be greater than 0.8MPa.
步骤七:在上行隧道盾构掘进期间,对下行隧道内架设支撑台车以支撑加强先建隧道的整体纵向刚度,防止对隧道管片产生纵向不均匀沉降。Step 7: During the shield tunneling of the upward tunnel, a support trolley is erected in the downward tunnel to support and strengthen the overall longitudinal rigidity of the previously constructed tunnel to prevent longitudinal uneven settlement of the tunnel segments.
支撑台车支撑段长度需根据盾构机长度选择,支撑台车可在钢轨上行进,每道支撑由9点、11点、12点、1点和3点位共计5个轮式支撑臂组成,支撑台车在外力的推力下,可不卸力实现沿纵向向前移动。The length of the support section of the support trolley should be selected according to the length of the shield machine. The support trolley can travel on the steel rail. Each support consists of 5 wheeled support arms at 9 o'clock, 11 o'clock, 12 o'clock, 1 o'clock, and 3 o'clock. , Under the thrust of external force, the supporting trolley can move forward in the longitudinal direction without releasing the force.
台车设计时应根据支撑可能承受的最大内力,及隧道不均匀变形允许值,事先估算钢支撑的最小刚度,支撑应具备预应力调节的功能。下行隧道内的支撑台车必须与上行盾构机掘进随时保持联系,保持两者同步行进。In the design of the trolley, the minimum stiffness of the steel support should be estimated in advance according to the maximum internal force that the support may bear and the allowable value of uneven deformation of the tunnel. The support should have the function of prestress adjustment. The supporting trolley in the downward tunnel must keep in touch with the upward shield tunneling machine at any time, and keep the two moving synchronously.
步骤八:在多区间隧道下穿高架桥区段的桥墩承台两侧各50m隧道范围内,对地铁轨道采用减隔振措施,以减小轨道交通运营对高架桥梁的振动影响。地铁轨道采用改良橡胶(聚氨酯)浮置板减震轨道(一阶自振频率为10~20Hz),以避免与高架桥运行铁路列车发生共振,又能降低地铁列车自身振动能量。Step 8: Use vibration reduction and isolation measures on the subway track within 50m of the tunnel on both sides of the pier cap of the multi-section tunnel under the viaduct section to reduce the vibration impact of rail transit operations on the viaduct. The subway track adopts an improved rubber (polyurethane) floating slab damping track (the first-order natural vibration frequency is 10-20Hz) to avoid resonance with the railway train running on the viaduct and reduce the vibration energy of the subway train itself.
实施例Example
为了更进一步描述本发明的技术方案,下面结合具体实施例,以及附图1-图7,进行更为详尽的描述。In order to further describe the technical solution of the present invention, a more detailed description will be given below in conjunction with specific embodiments and accompanying drawings 1 to 7.
本实施例所述工程为4条盾构区间隧道、小净距、交叠下穿高速铁路桥3工程,其中4条盾构区间隧道,对应图中的两个盾构下行隧道区间1和两个盾构隧道上行区间2,均采用主动铰接土压平衡盾构机掘进,刀盘外径为6.68m,盾构管片8采用单层钢筋混凝土装配式结构,外径为6.4m,内径5.8m,厚度0.3m,环宽1.2m,管片环分为六块,由一块封顶块K、两块邻接块B、三块标准块A构 成,错缝拼装。高铁桥3为64m桥跨预应力连续梁桥,当前高铁运营速度为300km/h,桥下采用低承台群桩基础,桥墩承台6尺寸11m×26.6m,承台6下方布置21根直径为1.5m的圆桩构成群桩基础,左、右两侧桥墩桩基4长度分别为45m、42m。盾构下行隧道的左右区间最小间距为4.33m,埋深分别为28.35m、19.22m;盾构上行隧道在盾构下行隧道的上方5.25m,左右区间净距5.6m,埋深均为7.57m。The project described in this embodiment is the project of 4 shield tunnels, small clear distance, and overlapped under-crossing high-speed railway bridge 3. Among them, 4 shield tunnels correspond to the two shield tunnels 1 and 2 in the figure. The upper section 2 of the shield tunnels are all driven by an active articulated earth pressure balance shield machine. The outer diameter of the cutter head is 6.68m. The shield segment 8 adopts a single-layer reinforced concrete assembly structure with an outer diameter of 6.4m and an inner diameter of 5.8. m, the thickness is 0.3m, the ring width is 1.2m, the segment ring is divided into six pieces, consisting of a capping block K, two adjacent blocks B, and three standard blocks A, assembled in staggered seams. High-speed rail bridge 3 is a 64m-span pre-stressed continuous beam bridge. The current high-speed rail operating speed is 300km/h. The low-cap pile foundation is adopted under the bridge. The size of the pier cap 6 is 11m×26.6m, and 21 diameters are arranged under the cap 6. The 1.5m round piles constitute the pile group foundation, and the lengths of the pile foundations 4 on the left and right sides are 45m and 42m respectively. The minimum distance between the left and right sections of the shield down tunnel is 4.33m, and the buried depths are 28.35m and 19.22m respectively; the shield up tunnel is 5.25m above the shield down tunnel, the left and right sections have a clear distance of 5.6m, and the buried depth is 7.57m. .
4条盾构隧道与两侧的高铁桥桩基4的最小净距分别为10.45m与10.84m,如图1所示。4条盾构区间隧道小净距、交叠下穿高速铁路桥区域的地质主要为黄土、粉质黏土、细砂土及卵石层,细砂土及卵石层中的含水量较为丰富。为了有效控制含水软弱地层中盾构隧道多区间、小净距、交叠下穿高铁桥3的施工安全,避免高铁桥桩基4的不均匀沉降与地铁隧道结构的损伤劣化,提出了本实施的技术方案,主要如下:The minimum clear distances between the 4 shield tunnels and the pile foundations 4 of the high-speed railway bridge on both sides are 10.45m and 10.84m, respectively, as shown in Figure 1. The geology of the four shield tunnels with small clear distances and overlapping high-speed railway bridges is mainly loess, silty clay, fine sand and pebble layers. The water content in the fine sand and pebble layers is relatively rich. In order to effectively control the construction safety of shield tunnels in multi-sections, small clear distances, and overlapping under-crossing high-speed railway bridges 3 in water-bearing soft formations, and to avoid uneven settlement of pile foundations 4 of high-speed railway bridges and damage and deterioration of subway tunnel structures, this implementation is proposed. The technical solutions are mainly as follows:
(1)在4条盾构隧道小净距、交叠下穿高铁桥3前,首先制定两个盾构下行隧道区间1和两个盾构隧道上行区间2下穿高铁桥3施工最优施工顺序。通过建立高精度三维数值模型,模拟分析4条盾构隧道不同顺序施工引起的高铁桥3结构变形与周边地层变形情况,得到对高铁桥桩基4与周围地层变形最小的下穿施工顺序为:盾构隧道下行区间左线→盾构隧道下行区间右线→盾构隧道上行区间右线→盾构隧道上行区间左线。依据科学化、信息化手段判定多盾构区间下穿施工顺序,避免经验决策的主观性与盲目性,有效降低了穿越施工风险。(1) Before the four shield tunnels with small clear distances and overlap and underpass the high-speed rail bridge 3, firstly formulate two shield-driven down tunnel sections 1 and two shield-machined tunnel up sections 2 under the high-speed rail bridge 3 construction optimal construction order. By establishing a high-precision three-dimensional numerical model, and simulating and analyzing the structural deformation of the high-speed railway bridge 3 and the surrounding ground deformation caused by the construction of 4 shield tunnels in different sequences, the construction sequence of the underpassing construction with the smallest deformation of the high-speed railway bridge pile foundation 4 and the surrounding ground is obtained: Shield tunnel down section left line → shield tunnel down section right line → shield tunnel up section right line → shield tunnel up section left line. According to scientific and information methods, the construction sequence of multi-shield section is determined to avoid the subjectivity and blindness of empirical decision-making, and the risk of crossing construction is effectively reduced.
(2)在4条盾构隧道下穿高铁桥3前1个月完成隔离桩5施工,主动改变地层原始应力场状态,阻断地层连续变形与应力发展趋势。在盾构隧道与高铁桥桩基4间打设Φ800@1000的钻孔灌注桩,防护范围长出桥墩承台6外15m,隔离桩 5底部达到盾构管片结构8底以下4.0m,以限制盾构掘进引起高铁桥桩基4的水平变形,尽量阻断盾构施工的应力传递及变形扩展。隔离桩5采用折线形布设,如图2所示。(2) The isolation pile 5 construction was completed one month before the 4 shield tunnels under the high-speed railway bridge 3, actively changing the original stress field state of the formation and blocking the continuous deformation and stress development trend of the formation. Set up Φ800@1000 bored piles between the shield tunnel and the 4 pile foundations of the high-speed railway bridge. The protection range is 15m beyond the pier cap 6 and the bottom of the isolation pile 5 reaches 4.0m below the bottom of the shield segment 8 Limit the horizontal deformation of the pile foundation 4 of the high-speed railway bridge caused by shield tunneling, and try to block the stress transfer and deformation expansion of shield construction. The isolation pile 5 is arranged in a broken line shape, as shown in FIG. 2.
钻孔灌注桩施工流程如图7所示,其施工要点如下:The construction process of bored piles is shown in Figure 7. The main points of the construction are as follows:
①钻孔灌注桩采用磨盘正循环钻机成孔,钻进时先轻压、低转速、慢钻进,进入正常状态后,逐渐加大转速和钻进速度,全程控制钻进参数、钻速;在换层钻进时,适当地减慢转速和减轻钻压,防止造成钻孔倾斜;成孔完毕至开始灌注混凝土的时间间隔控制在16小时内,每根桩灌注时间控制在4~6小时内。①The bored pile is formed by a positive circulation drilling machine with a grinding disc. When drilling, the drilling is carried out with light pressure, low speed and slow drilling. After entering the normal state, the speed and drilling speed are gradually increased, and the drilling parameters and drilling speed are controlled throughout the process; When changing layers and drilling, appropriately slow down the speed and reduce the weight on bit to prevent the borehole from tilting; the time interval from the completion of the hole formation to the start of the concrete pouring is controlled within 16 hours, and the pouring time of each pile is controlled within 4-6 hours Inside.
②为避免隔离桩5塌孔对高架桥桩基4的水平变形影响,钻孔灌注桩施工采用钢护筒跟进与泥水护壁,泥浆护壁效果好,适用于卵石地层施工;若出现塌孔,应立即停止周围钻孔施工,查明塌孔原因,并加强对桥梁结构监测。补桩时,应在原桩位进行钻孔灌注。②In order to avoid the impact of the collapse of the isolation pile 5 on the horizontal deformation of the viaduct pile foundation 4, the construction of the bored pile adopts steel casing and mud water wall protection. The mud wall protection effect is good, and it is suitable for the construction of the pebble stratum; Immediately stop the surrounding drilling construction, find out the cause of the hole collapse, and strengthen the monitoring of the bridge structure. When refilling piles, the original pile should be drilled and poured.
③钻孔灌注桩施工采用跳桩施工,跳2孔钻1孔,保证“钻一孔,注一孔”,并保证对称钻孔。邻近桩灌注时间不宜小于24小时。③The construction of bored piles adopts jumping pile construction, jumping 2 holes and drilling 1 hole to ensure "drill one hole, pour one hole" and ensure symmetrical drilling. The pouring time of adjacent piles should not be less than 24 hours.
④由于施工场地高铁桥3高度限制,钻机高6m,钢筋笼分8节制作,单节长度5m左右,采用磨盘钻机的卷扬设备进行钢筋笼吊装工作,以满足高铁桥下施工空间,最不利位置距离高铁桥梁底3.4m。④Due to the height limit of the high-speed railway bridge 3 in the construction site, the drill rig is 6m high, and the steel cage is made in 8 sections, and the length of a single section is about 5m. The hoisting equipment of the grinding disc drill rig is used for the steel cage hoisting work to meet the construction space under the high-speed railway bridge. The location is 3.4m away from the bottom of the high-speed rail bridge.
(3)考虑地下水对高铁桥桩基4沉降的影响及降低盾构施工难度,对隔离桩5间中、细砂层及卵石层采取袖阀管7注浆处理。采用直径40mm刚性袖阀管7后退式分段注浆,出浆孔眼直径约6mm,梅花型布孔,孔眼间距20cm,并用橡胶皮封住外管。管径注浆间距1.2m,充填影响半径0.8m。(3) Considering the influence of groundwater on the settlement of the pile foundation 4 of the high-speed railway bridge and reducing the difficulty of shield construction, the sleeve valve tube 7 grouting treatment is adopted for the middle and fine sand layer and the pebble layer between the 5 isolation piles. A 40mm diameter rigid sleeve valve tube 7 is used for stepwise grouting. The outlet hole diameter is about 6mm, and the plum blossom-shaped hole is 20cm apart. The outer tube is sealed with rubber. The pipe diameter grouting spacing is 1.2m, and the filling influence radius is 0.8m.
袖阀管7注浆施工要点如下:The main points of grouting construction for sleeve valve pipe 7 are as follows:
①袖阀管7钻孔采用引孔钻机,钻孔直径为90mm,孔深需达设计要求。注浆局部加固作业空间受限处,可通过调整注浆管角度、加密注浆孔布置等措施调整。①Sleeve valve tube 7 is drilled by a pilot hole drill with a hole diameter of 90mm, and the hole depth must meet the design requirements. The area where the working space of grouting is restricted can be adjusted by adjusting the angle of the grouting pipe and the arrangement of dense grouting holes.
②袖阀管7施工采用间隔跳孔、逐步约束、先下后上的注浆施工方法。钻孔顺序:先钻周边孔,由外向内逐步钻孔。注浆顺序:由外向内进行,先对加固范围线上钻孔进行注浆,阻断浆液漏失通道后,再逐步加密注浆孔,进行区域中部注浆压密;②The sleeve valve pipe 7 construction adopts the grouting construction method of interval skipping holes, gradual restraint, and first down and then up. Drilling sequence: drill the peripheral holes first, and gradually drill from the outside to the inside. Grouting sequence: from the outside to the inside, first grouting the holes on the reinforcement range line, blocking the slurry leakage channel, and then gradually densifying the grouting holes to grouting and compacting in the middle of the area;
③注浆材料为水泥、水玻璃双液浆,体积比为1:1,水玻璃浓度为35Be,注浆压力控制在0.5~1.0MPa,配比及注浆终压需经现场试验确定。③The grouting material is cement and water glass two-liquid grout, the volume ratio is 1:1, the water glass concentration is 35Be, the grouting pressure is controlled at 0.5 to 1.0 MPa, and the ratio and final grouting pressure need to be determined by field tests.
④对高富水强渗透的卵石层袖阀管7注浆加固应做现场专项实验,通过加强注浆口封堵、注入水泥~水玻璃双液浆、加注AB化学浆液、加注聚氨酯浆液等措施解决传统袖阀管注浆在此类地层中易塌孔、浆液易流失、注浆致密性不足等问题。④The grouting reinforcement of the sleeve valve tube 7 in the pebble layer with high water content and strong permeability should be carried out on-site special experiments, by strengthening the grouting port plugging, injecting cement-water glass double-liquid slurry, adding AB chemical slurry, adding polyurethane slurry, etc. Measures to solve the problems of traditional sleeve valve pipe grouting in such formations as easy collapse, easy loss of grout, and insufficient grouting compactness.
(4)进行4条盾构隧道依次下穿高铁桥3施工,每条盾构区间下穿高铁桥3前100m作为盾构掘进试验段,根据实测数据优化、调整、确定合理的掘进参数控制范围;在盾构隧道距离高铁桥桩基4的30m界限前,检查刀具磨损情况,若有磨损应立即更换滚刀,确保管片防水和拼装质量,选用质量优良盾尾油脂。盾构下行隧道区间以先左后右的顺序分别下穿高铁桥3,两区间间隔距离至少100m。盾构下行隧道区间穿越完成后,间隔至少3个月后,进行盾构上行隧道区间的盾构穿越掘进施工。盾构上行隧道区间以先右后左的顺序分别下穿高铁桥3,两区间间隔距离至少100m。(4) Carry out the construction of 4 shield tunnels under the high-speed railway bridge 3 in turn, and each shield section goes under the high-speed railway bridge 3 before 100m as the shield tunneling test section. According to the measured data, optimize, adjust and determine the reasonable tunneling parameter control range ; Before the shield tunnel is 30m away from the high-speed rail bridge pile foundation 4, check the wear of the cutter. If there is wear, the hob should be replaced immediately to ensure the waterproof and assembly quality of the pipe segments. Use high-quality shield tail grease. The sections of the shield down tunnel go through the high-speed rail bridge 3 in the order of left and right, and the distance between the two sections is at least 100m. After the traversal of the shield tunnel section is completed, at least 3 months later, the shield tunnel boring construction of the shield tunnel section will be carried out. The sections of the shield-bored up tunnel go under the high-speed rail bridge 3 in the order from right to left, and the distance between the two sections is at least 100m.
(5)在4条盾构区间交叠下穿高铁桥3区域,对盾构隧道管片结构8采取加强措施,以满足强度、耐久性及防水等要求,主要措施如下:(5) When the 4 shield tunnels overlap and pass through the high-speed railway bridge 3 area, the shield tunnel segment structure 8 shall be strengthened to meet the requirements of strength, durability and waterproofing. The main measures are as follows:
①加强隧道管片主筋和分布筋,采用HRB400钢筋直径为25mm的加强型管片。① To strengthen the main reinforcement and distribution reinforcement of the tunnel segment, the reinforced segment with HRB400 steel bar diameter of 25mm is adopted.
②提高管片纵向连接螺栓11等级,管片连接螺栓11采用B级M27,性能8.8级螺栓,增加隧道纵向刚度。②Improve the 11 grade of the longitudinal connecting bolts of the tube segments. The connecting bolts 11 of the tube segments adopt B grade M27 and performance 8.8 bolts to increase the longitudinal stiffness of the tunnel.
③提高管片结构8防水,采用抗渗等级为P12混凝土,管片接缝设置一道多孔型三元乙丙弹性密封垫,管片环缝及纵缝设置丁腈软木橡胶垫,管片满环采用柔性聚氨酯密封胶嵌缝,仰拱范围出现水湿渍采用聚合物防水砂浆,所有螺栓孔均采用遇水膨胀橡胶圈进行密封处理,吊装孔9采用塑料保护罩封堵。③Improve the waterproof of the segment structure 8, adopt P12 concrete with impermeability grade, set a porous EPDM elastic gasket at the joints of the pipe segments, and set up nitrile cork rubber pads at the circumferential and longitudinal joints of the pipe segments, and the pipe segments are fully ringed. Use flexible polyurethane sealant for caulking, use polymer waterproof mortar for water stains in the invert range, all bolt holes are sealed with water-expandable rubber rings, and lifting holes 9 are sealed with plastic protective covers.
(6)在4条盾构区间交叠区域,在管片结构8增设预留注浆孔10,如图3、4所示,在盾构下行隧道区间1右线施工前,利用左线隧道管片8预留注浆孔10和原先的吊装孔9向交叠区域夹层土体进行洞内二次或多次注浆加固;右线施工后,通过右线预留注浆孔10和原先的吊装孔9和向夹层土体进行补偿注浆,如图5所示。减小交叠区域后施工隧道对先成型隧道结构8的附加应力和叠加变形等劣化影响。(6) In the overlap area of the 4 shield tunnels, a reserved grouting hole 10 is added to the segment structure 8, as shown in Figures 3 and 4. Before the construction of the right line of the shield tunnel section 1, use the left tunnel The segment 8 reserved grouting hole 10 and the original hoisting hole 9 are used for secondary or multiple grouting reinforcement in the interlayer soil in the overlapping area; after the construction of the right line, the grouting hole 10 and the original The lifting hole 9 and compensation grouting to the interlayer soil, as shown in Figure 5. The additional stress and superimposed deformation of the first formed tunnel structure 8 are degraded by reducing the overlap area and then constructing the tunnel.
管片增设预留注浆孔10控制要点如下:The control points for adding reserved grouting holes 10 to segments are as follows:
①盾构隧道管片8分为3块标准块、2块邻接块、1块封顶块,在每块标准块与邻接块中各增设2个预留注浆孔10,以便管片拼装稳定后,通过预留注浆孔10对交叠区域夹层土体进行洞内二次或多次注浆加固。①The shield tunnel segment 8 is divided into 3 standard blocks, 2 adjacent blocks, and 1 capping block. Two reserved grouting holes 10 are added to each standard block and adjacent block, so that the segments can be assembled and stabilized. , Through the reserved grouting hole 10, the interlayer soil in the overlapping area is reinforced by grouting twice or more times.
②注浆管12采用直径42mm,t=3.5mm钢化管,打设角度均沿隧道径向,纵向间距为2.4m,注浆管12长度L=3.0m,加固范围为上行隧道底部120°,加固厚度3m。 ②The grouting pipe 12 adopts a steel pipe with a diameter of 42mm and t=3.5mm. The installation angles are along the radial direction of the tunnel. The longitudinal spacing is 2.4m. The length of the grouting pipe 12 is L=3.0m. The reinforcement range is 120° at the bottom of the ascending tunnel. The reinforcement thickness is 3m.
③注浆液采用水泥浆,水灰比1:1,间隔钻孔注浆。注浆压力控制在0.5~1.0MPa,现场根据注浆试验进行优化。加固后土体需具有良好的自立性、密 封性及强度,无侧限抗压强度大于0.8MPa。③Cement slurry is used for grouting liquid, water cement ratio is 1:1, and grouting is drilled at intervals. The grouting pressure is controlled at 0.5-1.0MPa, and the site is optimized according to the grouting test. After reinforcement, the soil shall have good self-support, sealing and strength, and the unconfined compressive strength shall be greater than 0.8MPa.
(7)由于盾构下行隧道区间左、右线施工仅间隔100m,且两区间小净距叠落,右线施工时,下方左线隧道周围土体未完全固结,会对隧道管片结构8产生纵向不均匀沉降。因此,在盾构下行隧道区间右线盾构掘进期间,对左线内架设支撑台车14以支撑加强既有隧道的整体纵向刚度,防止对隧道管片8产生纵向不均匀沉降。(7) Since the construction of the left and right lines of the shield tunnel section is only 100m apart, and the two sections overlap with a small clear distance, during the construction of the right line, the soil around the lower left line tunnel is not fully consolidated, which will affect the tunnel segment structure 8 Produce longitudinal uneven settlement. Therefore, during the excavation of the right line of the shield tunnel section, a support trolley 14 is erected in the left line to support and strengthen the overall longitudinal rigidity of the existing tunnel, and prevent longitudinal uneven settlement of the tunnel segments 8.
如图6所示,支撑台车14支撑段长度需根据盾构机长度选择,支撑台车14可在钢轨上行进,每道支撑由9点、11点、12点、1点和3点位共计5个轮式支撑臂15组成,支撑台车14在外力的推力下,可不卸力实现沿纵向向前移动。支撑台车14设计时应根据轮式支撑臂15可能承受的最大内力,及隧道不均匀变形允许值,提前估算轮式支撑臂15的最小刚度,轮式支撑臂15应具备预应力调节的功能。盾构下行隧道区间右线盾构机必须与支撑台车14随时保持联系,保持两者同步行进。As shown in Figure 6, the length of the support section of the support trolley 14 needs to be selected according to the length of the shield machine. The support trolley 14 can travel on the rails. Each support consists of 9 o'clock, 11 o'clock, 12 o'clock, 1 o'clock and 3 o'clock. A total of 5 wheeled support arms 15 are composed, and the support trolley 14 can move forward in the longitudinal direction without releasing the force under the thrust of external force. When designing the support trolley 14, the minimum rigidity of the wheel support arm 15 should be estimated in advance according to the maximum internal force that the wheel support arm 15 may bear and the allowable value of uneven deformation of the tunnel. The wheel support arm 15 should have the function of pre-stress adjustment . The shield machine on the right line of the shield down tunnel section must keep in touch with the supporting trolley 14 at any time to keep the two moving in sync.
(8)为减小地铁运营对高铁桥梁3的振动影响,保证高铁列车的安全运营,在4条地铁隧道下穿高铁桥3区段的桥墩承台6两侧各50m隧道范围内,对地铁轨道采用减隔振措施。地铁轨道采用改良橡胶(聚氨酯)浮置板减震轨道(一阶自振频率为10~20Hz),以避免与高铁桥3运行铁路列车发生共振,又能降低地铁列车自身振动能量。(8) In order to reduce the impact of subway operation on the vibration of the high-speed rail bridge 3 and ensure the safe operation of high-speed rail trains, 4 subway tunnels pass through the pier caps of section 3 of the high-speed rail bridge within 50m on both sides of the tunnel. The track adopts vibration reduction and isolation measures. The subway track adopts an improved rubber (polyurethane) floating plate damping track (the first-order natural vibration frequency is 10-20Hz) to avoid resonance with the railway train running on the high-speed railway bridge 3, and to reduce the vibration energy of the subway train itself.
以上所述仅为本发明的较佳实施例,本发明并不限于列举上述实施例,应当说明的是,任何熟悉本领域的技术人员在本说明书的教导下,所做出的所有等同替代、明显变形形式,均落在本说明书的实质范围之内,理应受到本发明的保护。The above are only preferred embodiments of the present invention. The present invention is not limited to the above embodiments. It should be noted that any person skilled in the art can make all equivalent substitutions, Obviously deformed forms fall within the essential scope of this specification and should be protected by the present invention.

Claims (15)

  1. 一种盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,包括步骤如下:A construction method for shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts is characterized in that it comprises the following steps:
    步骤一:按照对高架桥桩基及周边环境变形影响最小的原则,制定盾构隧道多区间、叠落下穿高架桥施工的最优施工顺序;Step 1: According to the principle of the least impact on the deformation of the viaduct pile foundation and the surrounding environment, formulate the optimal construction sequence for the construction of the shield tunnel with multiple sections and stacked under the viaduct;
    步骤二:在隧道下穿高架桥之前,进行盾构近距离下穿施工的主动隔离加固;Step 2: Before the tunnel underpasses the viaduct, conduct active isolation and reinforcement of the short-distance underpass construction of the shield;
    步骤三:进行盾构隧道下穿高架桥的施工;Step 3: Carry out the construction of the shield tunnel under the viaduct;
    步骤四:在多盾构隧道区间交叠下穿高架桥的区域,对盾构隧道的管片结构进行加强,对隧道洞内进行加固;Step 4: Reinforce the segment structure of the shield tunnel in the area where the multi-shield tunnel overlaps and pass through the viaduct, and strengthen the tunnel cavity;
    步骤五:在盾构隧道下穿高架桥区段进行轨道减隔振控制。Step 5: The track vibration reduction and isolation control is carried out in the section of the shield tunnel passing through the viaduct.
  2. 如权利要求1所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,步骤一的具体工作方法是:建立与实际施工情况一致的三维数值模型,模拟分析多条盾构隧道不同顺序施工引起的高架桥结构变形与周边地层变形情况,确定对高架桥桩基及周边环境变形影响最小的下穿施工顺序即为最优施工顺序。The construction method of shield tunnels with multiple intervals, small clear distances, and overlapping underpass viaducts according to claim 1, wherein the specific working method of step one is: establishing a three-dimensional numerical model consistent with the actual construction situation, and simulating Analyze the structural deformation of the viaduct and the surrounding ground deformation caused by the construction of multiple shield tunnels in different sequences, and determine the optimal construction sequence that has the least impact on the deformation of the viaduct pile foundation and the surrounding environment.
  3. 如权利要求1所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,步骤二的具体工作方法是:The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts according to claim 1, characterized in that the specific working method of step two is:
    步骤2.1施做钻孔灌注桩作隔离桩;Step 2.1 Construct bored piles as isolation piles;
    在盾构下穿高架桥前一段时间完成隔离桩施工,在盾构隧道与高架桥桩基间打设钻孔灌注桩,灌注桩的防护范围长出桥墩承台外,灌注桩底部达到盾构管片结构底以下;The isolation pile construction is completed some time before the shield passes through the viaduct, and bored piles are built between the shield tunnel and the viaduct pile foundation. The protection range of the cast-in-place pile extends beyond the pier cap, and the bottom of the cast-in-place pile reaches the shield segment. Below the structure bottom;
    步骤2.2进行袖阀管注浆作桩间止水;Step 2.2 Carry out sleeve valve pipe grouting to stop water between piles;
    对隔离桩间中、细砂层及卵石层采取袖阀管注浆处理。Sleeve valve tube grouting is adopted for the middle, fine sand layer and pebble layer between the isolated piles.
  4. 如权利要求3所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,所述的钻孔灌注桩采用磨盘正循环钻机成孔,钻进时先轻压、低转速、慢钻进,进入正常状态后,逐渐加大转速和钻进速度;全程控制钻进参数、钻速;在换层钻进时,适当地减慢转速和减轻钻压,防止造成钻孔倾斜。The construction method of shield tunnels with multiple intervals, small clear distances, and overlapping underpass viaducts according to claim 3, characterized in that the bored piles are formed by grinding disc positive circulation drills, which are lighter when drilling. After entering the normal state, gradually increase the rotation speed and the drilling speed; control the drilling parameters and drilling speed throughout the whole process; when changing the drilling, appropriately slow down the speed and reduce the drilling pressure to prevent Cause the borehole to tilt.
  5. 如权利要求3所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,所述的钻孔灌注桩施工采用钢护筒跟进与泥水护壁,若出现塌孔,应立即停止周围钻孔施工,查明塌孔原因,并加强对桥梁结构监测;补桩时,应在原桩位进行钻孔灌注;The construction method of shield tunnels with multiple sections, small clear distances, and overlapped underpass viaducts according to claim 3, characterized in that the construction of the bored piles adopts steel casing and mud water protection. If the hole collapses, the surrounding drilling should be stopped immediately, the cause of the hole collapse should be found, and the monitoring of the bridge structure should be strengthened; when the pile is repaired, the original pile should be drilled and poured;
    进一步的,钻孔灌注桩施工采用跳桩施工,且保证“钻一孔,注一孔”,并保证对称钻孔。Further, the construction of bored piles adopts jumping pile construction, and it is ensured that “one hole is drilled and one hole is injected” and symmetrical drilling is ensured.
  6. 如权利要求3所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,灌注桩的钢筋笼分节制作,采用磨盘钻机的卷扬设备进行钢筋笼吊装工作,以满足高架桥下施工空间。The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts according to claim 3, characterized in that the steel cages of the cast-in-place piles are made in sections, and the steel cages are hoisted by the hoisting equipment of the millstone drill Work to meet the construction space under the viaduct.
  7. 如权利要求3所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,袖阀管施工采用间隔跳孔、逐步约束、先下后上的注浆施工方法;The construction method of shield tunnels with multiple intervals, small clear distances, and overlapping underpass viaducts according to claim 3, characterized in that the sleeve valve tube construction adopts interval skipping, gradual restraint, and grouting construction. method;
    进一步的,钻孔顺序:先钻周边孔,由外向内逐步钻孔;注浆顺序:由外向内进行,先对加固范围线上钻孔进行注浆,阻断浆液漏失通道后,再逐步加密注浆孔,进行区域中部注浆压密。Further, the drilling sequence: drill the peripheral holes first, and gradually drill holes from the outside to the inside; the grouting sequence: proceed from the outside to the inside, first grouting the holes on the reinforcement range line, blocking the slurry leakage channel, and then gradually densifying Grouting hole, grouting and compaction in the middle of the area.
  8. 如权利要求3所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,对高富水强渗透的卵石层袖阀管注浆加固应做现场专项实验,通过多种不同的措施解决传统袖阀管注浆在此类地层中出现的问题。The construction method of shield tunnels with multiple sections, small clear distances, and overlapped underpass viaducts according to claim 3, characterized in that the grouting reinforcement of the sleeve valve tube in the pebble layer with high water content and strong permeability shall be subject to on-site special experiments. A variety of different measures are adopted to solve the problems of traditional sleeve valve pipe grouting in such formations.
  9. 如权利要求1所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,所述的步骤四主要包括:The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts according to claim 1, wherein said step four mainly includes:
    进行隧道管片主筋和分布筋加强;Reinforce the main reinforcement and distribution reinforcement of the tunnel segment;
    提高管片纵向螺栓等级,增加隧道纵向刚度;Improve the grade of longitudinal bolts of the segment and increase the longitudinal rigidity of the tunnel;
    提高管片结构防水。Improve the waterproof of the tube structure.
  10. 如权利要求9所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts according to claim 9, characterized in that:
    所述管片结构采用抗渗等级为P12混凝土;The segment structure adopts concrete with an impermeability grade of P12;
    所述的管片接缝设置一道多孔型三元乙丙弹性密封垫,A porous EPDM elastic sealing gasket is provided at the joint of the tube piece,
    管片环缝及纵缝设置丁腈软木橡胶垫,管片满环采用柔性聚氨酯密封胶嵌缝;仰拱范围出现水湿渍采用聚合物防水砂浆,所有螺栓孔均采用遇水膨胀橡胶圈进行密封处理,吊装孔采用塑料保护罩封堵。Nitrile cork rubber pads are provided for the circumferential and longitudinal joints of the segments, and the full loops of the segments are caulked with flexible polyurethane sealant; water stains appearing in the invert range are made of polymer waterproof mortar, and all bolt holes are made of water-swellable rubber rings. Sealed, the lifting hole is blocked with a plastic protective cover.
  11. 如权利要求1所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,步骤四主要包括:The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts according to claim 1, characterized in that step four mainly includes:
    在管片结构增设预留注浆孔,通过注浆孔和吊装孔对交叠区域土体进行洞内注浆加固;且在上行盾构掘进期间,对下行隧道内架设支撑台车以支撑加强先成型隧道的整体纵向刚度。Additional grouting holes are reserved in the segment structure, and the soil in the overlapping area is reinforced by grouting holes and lifting holes; and during the upward shield tunneling, a support trolley is erected in the downward tunnel to support and strengthen First shape the overall longitudinal stiffness of the tunnel.
  12. 如权利要求11所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts as claimed in claim 11, characterized in that:
    所述的支撑台车的支撑段长度需根据盾构机长度选择,支撑台车可在钢轨上行进,每道支撑由9点、11点、12点、1点和3点位共计5个轮式支撑臂组成,台车在外力的推力下,可不卸力实现沿纵向向前移动。The length of the supporting section of the supporting trolley needs to be selected according to the length of the shield machine. The supporting trolley can travel on the rails. Each support consists of 5 wheels at 9 o'clock, 11 o'clock, 12 o'clock, 1 o'clock, and 3 o'clock. The trolley can move forward in the longitudinal direction without releasing the force under the thrust of external force.
  13. 如权利要求11所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,每环隧道管片分为6块,为3块标准块、2块邻接块、1块封顶块,管片增设预留注浆孔是在每块标准块与邻接块中各增设2个预留注浆孔。The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts according to claim 11, characterized in that each ring tunnel segment is divided into 6 blocks, which are 3 standard blocks and 2 adjacent blocks , 1 capping block, additional reserved grouting holes for the segment is to add 2 reserved grouting holes in each standard block and adjacent blocks.
  14. 如权利要求11所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,步骤五主要包括:The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts according to claim 11, characterized in that step five mainly includes:
    在地铁隧道下穿高架桥区段的桥墩承台两侧各50m的隧道范围内,对地铁轨道采用减隔振措施。Within the tunnel area of 50m on each side of the pier cap of the subway tunnel under the viaduct section, vibration reduction and isolation measures are adopted for the subway track.
  15. 如权利要求14所述的盾构隧道多区间、小净距、交叠下穿高架桥的施工方法,其特征在于,所述的地铁轨道采用自振频率为10~20Hz的橡胶浮置板减震轨道。The construction method of shield tunnels with multiple sections, small clear distances, and overlapping underpass viaducts according to claim 14, characterized in that the subway track adopts rubber floating slabs with a natural vibration frequency of 10-20Hz to absorb vibration track.
PCT/CN2019/120380 2019-05-05 2019-11-22 Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner WO2020224233A1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
AU2019444087A AU2019444087B2 (en) 2019-05-05 2019-11-22 Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN201910368188.8A CN110080781B (en) 2019-05-05 2019-05-05 Construction method for shield tunnel multi-section, small-clear-distance and overlapped underpass viaduct
CN201910368188.8 2019-05-05

Publications (1)

Publication Number Publication Date
WO2020224233A1 true WO2020224233A1 (en) 2020-11-12

Family

ID=67418609

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2019/120380 WO2020224233A1 (en) 2019-05-05 2019-11-22 Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner

Country Status (3)

Country Link
CN (1) CN110080781B (en)
AU (1) AU2019444087B2 (en)
WO (1) WO2020224233A1 (en)

Cited By (74)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112589993A (en) * 2020-11-19 2021-04-02 绍兴中亚工贸园有限公司 Segment embedded part fixing base and segment forming method thereof
CN112627848A (en) * 2020-12-07 2021-04-09 中国电建集团华东勘测设计研究院有限公司 Segment typesetting method for intermediate ring with given point position
CN112796771A (en) * 2021-01-28 2021-05-14 中铁第一勘察设计院集团有限公司 Construction structure and method of shield tunnel head start under the condition of limited space
CN112948931A (en) * 2021-03-03 2021-06-11 河南大学 Method for determining reasonable included angle and clear distance of shield construction under double-line overlapping working condition of new construction and existing subway tunnel
CN113006832A (en) * 2021-05-11 2021-06-22 西京学院 Small-excavation segment welded type underground vacuum pipeline and construction method thereof
CN113047859A (en) * 2021-04-12 2021-06-29 上海应用技术大学 Shield tunneling parameter control method based on local Fisher soil layer identification
CN113049775A (en) * 2021-03-09 2021-06-29 天津大学 Double-freedom-degree existing tunnel simulation test device and method
CN113137239A (en) * 2021-05-15 2021-07-20 中铁十一局武汉重型装备有限公司 Shield cutter head face reinforcing method and grouting reinforcing device used for method
CN113177245A (en) * 2021-04-19 2021-07-27 浙大城市学院 Calculation method for longitudinal deformation of adjacent subway tunnel caused by steel sleeve construction
CN113177246A (en) * 2021-04-19 2021-07-27 浙大城市学院 Method for calculating additional confining pressure of adjacent subway tunnel caused by steel sleeve construction
CN113217037A (en) * 2021-06-25 2021-08-06 中铁二局集团有限公司 Backfill system and backfill method for single shield TBM or behind shield segment wall
CN113266376A (en) * 2021-05-12 2021-08-17 济南轨道交通集团有限公司 Model test device for simulating shield approaching underground structure micro-disturbance construction
CN113309536A (en) * 2021-04-26 2021-08-27 上海市政工程设计研究总院(集团)有限公司 Method for tunneling from separated type to laminated type mine method
CN113322937A (en) * 2021-05-18 2021-08-31 中建交通建设集团有限公司 Openable assembly type steel underground diaphragm wall and application method thereof
CN113356881A (en) * 2021-07-15 2021-09-07 上海地铁维护保障有限公司工务分公司 Segment deep grouting method for treating tunnel leakage diseases
CN113374496A (en) * 2021-06-23 2021-09-10 上海隧道工程有限公司 Upper-crossing tunnel structure and construction method
CN113373901A (en) * 2021-05-27 2021-09-10 中建一局集团建设发展有限公司 Overlapping shield tunnel house foundation reinforcing structure next to house and construction method
CN113389557A (en) * 2021-06-25 2021-09-14 中铁第五勘察设计院集团有限公司 Isolation structure of side-passing bridge pile of shield tunnel and shield tunnel structure assembly
CN113431085A (en) * 2021-05-26 2021-09-24 中铁第一勘察设计院集团有限公司 Reserved underpass structure system of subway station and construction method thereof
CN113486435A (en) * 2021-07-22 2021-10-08 华侨大学 Shield underground butt joint and abandoned shell disassembly construction method based on BIM and numerical simulation
CN113605931A (en) * 2021-09-07 2021-11-05 浙江大学 Soil layer interface urban tunnel crossing reinforcement structure and construction method thereof
CN113653508A (en) * 2021-09-01 2021-11-16 中机中联工程有限公司 Bridge-lining combined structure with tunnel inner crossing function and construction method thereof
CN113685192A (en) * 2021-08-20 2021-11-23 上海市城市建设设计研究总院(集团)有限公司 Connecting node of main line shield tunnel in and out of ramp and construction method
CN113685186A (en) * 2021-08-09 2021-11-23 北京城建轨道交通建设工程有限公司 Tunneling method for geological drilling in shield underpass water area
CN113685201A (en) * 2021-09-30 2021-11-23 济南大学 Construction method for replacing inverted arch of highway tunnel
CN113700437A (en) * 2021-09-01 2021-11-26 中交第二航务工程局有限公司 Tube-following drilling device for soft rock tunnel tube shed and construction method
CN113774908A (en) * 2021-09-24 2021-12-10 浙江交工集团股份有限公司 Construction method of multiple-stirring pile machine capable of breaking hardness and preventing cracking
CN113832947A (en) * 2021-11-05 2021-12-24 中铁第六勘察设计院集团有限公司 Device and method for reinforcing multiple-track railway with small space passing under shield tunnel
CN113863380A (en) * 2021-09-14 2021-12-31 中铁十九局集团广州工程有限公司 Construction method for large-diameter pipe jacking to penetrate through seawall
CN113863953A (en) * 2021-10-08 2021-12-31 陕西同人应用材料有限公司 Subway tunnel segment reinforcing structure and rapid construction process
CN113863280A (en) * 2021-10-25 2021-12-31 中交隧道工程局有限公司 Reinforced pipe shed structure suitable for karst or fault open caisson foundation grouting
CN113863273A (en) * 2021-09-28 2021-12-31 中铁第四勘察设计院集团有限公司 Construction method of bored pile adjacent to operation railway
CN113958343A (en) * 2021-05-10 2022-01-21 南昌轨道交通集团有限公司 Structure and method for restraining upward floating of duct piece in full-section rock stratum shield tunnel
CN114046151A (en) * 2021-10-25 2022-02-15 中交隧道工程局有限公司 The reinforcement method of caisson suitable for shield construction
CN114135311A (en) * 2021-12-23 2022-03-04 甘肃省交通规划勘察设计院股份有限公司 Tunnel advanced horizontal reinforcement jet grouting pile supporting structure and construction method
CN114232491A (en) * 2021-12-29 2022-03-25 广西路建工程集团有限公司 Construction method of multi-span simply supported prestressed bridge span in tunnel
CN114260847A (en) * 2021-12-16 2022-04-01 中铁隧道局集团有限公司 Assembling system and assembling method of horizontal vacuum tunnel detection model
CN114352315A (en) * 2021-11-29 2022-04-15 北京恒祥宏业基础加固技术有限公司 Grouting method suitable for inhibiting shield segment from floating in water-rich area
CN114412484A (en) * 2022-01-20 2022-04-29 北京住总集团有限责任公司 A kind of construction method of stacking tunnel
CN114444189A (en) * 2022-02-08 2022-05-06 同济大学 A method for inversion analysis of longitudinal joint opening angle of shield tunnel
CN114483091A (en) * 2021-12-02 2022-05-13 中南大学 A method for segmented grouting of large tube sheds in tunnels
CN114592892A (en) * 2022-04-02 2022-06-07 中铁第六勘察设计院集团有限公司 Implementation method for pulling out anchor cable of shield tunnel in steel sleeve in soft soil area
CN114592875A (en) * 2022-01-26 2022-06-07 浙江大通建设科技有限公司 Multi-angle reinforcement construction method in subway tunnel
CN114607390A (en) * 2022-03-28 2022-06-10 中铁二十局集团第五工程有限公司 Concrete pouring method for communication channel based on freezing method of soft soil water-rich stratum
CN114646411A (en) * 2022-03-14 2022-06-21 西安科技大学 Intelligent wireless multidirectional continuous drilling stress monitoring device
CN114687760A (en) * 2022-03-24 2022-07-01 中铁九局集团第四工程有限公司 Anti-displacement subway tunnel structure based on soft foundation
CN114775673A (en) * 2022-05-30 2022-07-22 杭州萧山交通建设管理有限公司 Pile foundation reserved filling enlarged bearing platform system construction method
CN114776309A (en) * 2021-11-15 2022-07-22 中铁二院华东勘察设计有限责任公司 Method for improving transverse stress of deep-buried shield tunnel in soft soil body area
CN114856616A (en) * 2022-05-13 2022-08-05 中铁第五勘察设计院集团有限公司 A kind of tunnel construction method and reinforcement protection structure
CN114859017A (en) * 2022-07-06 2022-08-05 湖南大学 Stratum stress field and displacement field control test device and method
CN114881440A (en) * 2022-04-26 2022-08-09 济南交通发展投资有限公司 Risk control method and system for shield tunnel crossing high-speed railway bridge
CN114964091A (en) * 2022-02-23 2022-08-30 上海建工集团股份有限公司 Rapid detection device and method for slab staggering amount between shield section tunnel segments
CN114991830A (en) * 2022-07-18 2022-09-02 中铁电气化局集团有限公司 Subway construction mobile tunnel segment supporting trolley
CN115012966A (en) * 2022-06-09 2022-09-06 宁波地铁产业工程有限公司 Rapid reinforcing system and method for deformation of shield tunnel
CN115075827A (en) * 2022-07-06 2022-09-20 中铁工程装备集团有限公司 Method and structure for advanced processing of main line tunnel influence area based on small-section tunnel
CN115132048A (en) * 2022-06-28 2022-09-30 中铁四院集团西南勘察设计有限公司 Simulation test device and test method for proximity construction in built tunnel area
CN115492071A (en) * 2022-09-21 2022-12-20 甘肃省交通科学研究院集团有限公司 Reaction platform for static load test of foundation in highway tunnel and construction method thereof
CN115492592A (en) * 2022-08-16 2022-12-20 中铁十四局集团有限公司 The construction method of starting and building warehouses for large-section shield tunnels jointly built by highways and railways
CN115506824A (en) * 2022-08-31 2022-12-23 中铁十九局集团第三工程有限公司 Rock Wall Reinforcement Structure and Reinforcement Method in Small Clear Distance Tunnel
CN115949091A (en) * 2022-11-21 2023-04-11 山东大学 A pile foundation structure and method suitable for pile foundation underpinning of stacked tunnels
CN115928798B (en) * 2023-03-13 2023-05-23 北京城建设计发展集团股份有限公司 Method for passing through existing underground structure of rail transit through ultra-small clear distance long-distance oblique crossing
CN116241260A (en) * 2022-12-14 2023-06-09 杭州临平交通建设有限公司 Construction method of temporary slab support assisted shield tunneling through ultra-deep foundation pit
CN116607574A (en) * 2023-03-09 2023-08-18 中铁二院工程集团有限责任公司 Protection structure suitable for crossing existing shallow underground tunnel on road and construction method
CN116451310B (en) * 2023-03-17 2023-10-27 北京城建设计发展集团股份有限公司 Method for ultra-small clear distance long-distance oblique crossing of existing U-shaped groove structure of rail transit
CN117128008A (en) * 2023-10-26 2023-11-28 江苏快鹿地铁钢结构制造有限公司 Quick assembly type steel pipe sheet for tunnel connecting channel
CN112879025B (en) * 2021-02-04 2023-12-22 中铁十六局集团北京轨道交通工程建设有限公司 Intelligent regulation and control method for earth pressure balance shield earth pressure based on GRU deep learning
CN117780387A (en) * 2023-12-27 2024-03-29 北京城建道桥建设集团有限公司 An underground cavern lining construction method that passes through existing waste piles
CN117905484A (en) * 2024-01-29 2024-04-19 深圳大学 E-shaped plate joint for assembled inverted arch, design method and construction method thereof
CN118208259A (en) * 2024-05-22 2024-06-18 中铁十一局集团城市轨道工程有限公司 Negative ring pipe piece of embedded sleeve and construction method thereof
CN118686216A (en) * 2024-08-27 2024-09-24 浙江道其乐科技有限公司 A pile foundation reinforcement structure for increasing load amplitude and implementation method thereof
CN119145883A (en) * 2024-11-11 2024-12-17 中国建筑第六工程局有限公司 Shield construction grouting method for water-rich sandy pebble stratum
CN119249582A (en) * 2024-12-04 2025-01-03 中铁七局集团第三工程有限公司 A construction method and device for shield tunneling through existing structures
CN119849268A (en) * 2025-03-19 2025-04-18 中铁十四局集团有限公司 Segment bearing safety early warning method, system and storage medium in large-diameter shield synchronous pushing and splicing mode
CN120105559A (en) * 2025-05-08 2025-06-06 中国地质大学(武汉) A method for predicting ground deformation caused by a shield tunnel passing through an existing ground-connected wall

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110080781B (en) * 2019-05-05 2021-05-07 济南轨道交通集团有限公司 Construction method for shield tunnel multi-section, small-clear-distance and overlapped underpass viaduct
CN110939127A (en) * 2019-11-28 2020-03-31 中建四局土木工程有限公司 Steel pipe pile construction method for protecting subway pier
CN110952987A (en) * 2019-12-03 2020-04-03 济南轨道交通集团有限公司 Construction method for side-through bridge pile of stacked porous subway tunnel
CN111982559B (en) * 2020-09-11 2025-01-07 浙大城市学院 A simplified device and experimental method for simulating the influence of supporting trolleys in overlapping tunnels
CN114704265A (en) * 2020-11-17 2022-07-05 中铁六局集团有限公司交通工程分公司 Construction method for subway shield tunnel to pass through viaduct tunnel downwards
CN112538870B (en) * 2020-11-30 2022-08-16 中铁二十局集团第五工程有限公司 Isolation and reinforcement structure and method for water-rich sand layer shield tunnel to pass through viaduct
CN112664203B (en) * 2020-12-25 2023-06-27 北京市政路桥股份有限公司 Reinforcing system for controlling shield tunnel deformation by river dredging above shield tunnel and construction method
CN112682055B (en) * 2021-03-22 2021-07-09 中铁九局集团第四工程有限公司 Small-clear-distance parallel tunnel shield tunneling construction method
CN113062742B (en) * 2021-03-23 2022-10-14 济南轨道交通集团有限公司 Deformation control construction method for shield tunnel lower-passing high-speed railway bridge
CN113338948A (en) * 2021-05-27 2021-09-03 中建一局集团建设发展有限公司 Overlapping shield tunnel foundation treatment structure next to old house and construction method
CN113898385A (en) * 2021-09-30 2022-01-07 上海盾构设计试验研究中心有限公司 Deformation control device for tunnel segment and construction method thereof
CN114017037A (en) * 2021-11-01 2022-02-08 中铁一局集团第二工程有限公司 A construction method of shield tunnel crossing municipal bridge area at close range
CN114278319B (en) * 2021-12-27 2023-09-26 中交第三航务工程局有限公司 Shield construction method for small-clear-distance tunnel
CN114673199A (en) * 2022-03-15 2022-06-28 广州市第二市政工程有限公司 Tunnel construction close high-voltage electric tower matching protection method
CN114778799B (en) * 2022-04-22 2023-04-28 福建船政交通职业学院 Test bed for tunnel shield soil body performance detection and test method thereof
CN115095336B (en) * 2022-05-20 2023-05-05 中铁四局集团第四工程有限公司 Shield construction method for underground railway and bridge pile of subway line

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003213708A (en) * 2001-11-13 2003-07-30 Taisei Corp Underground structure construction method and elevated traffic path
JP2004124548A (en) * 2002-10-03 2004-04-22 Kensetsu Kikaku Consultant:Kk Pile foundation, underground wall structure, and construction method
JP2005002671A (en) * 2003-06-12 2005-01-06 Kajima Corp Underpinning method and viaduct
CN103114611A (en) * 2013-03-01 2013-05-22 同济大学 Multistage cut-off method for underpass high-speed rail bridge opening deformation
CN103882854A (en) * 2014-04-08 2014-06-25 中铁二十五局集团轨道交通工程有限公司 Shield construction method for continuously passing through earth under railways and overpasses
CN204591302U (en) * 2015-02-12 2015-08-26 中国水利水电第十四工程局有限公司 A kind of support chassis for overlapping shield tunnel construction and brace table truck system
CN204984441U (en) * 2015-09-08 2016-01-20 中铁隧道股份有限公司 It backfills novel section of jurisdiction of quality behind one's back to change single shield TBM section of jurisdiction
CN107386274A (en) * 2017-08-14 2017-11-24 中铁第勘察设计院集团有限公司 Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side
CN110080781A (en) * 2019-05-05 2019-08-02 济南轨道交通集团有限公司 Between a kind of shield tunnel multi-region, small interval, it is overlapping under wear high-level bridge construction method

Family Cites Families (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE4401403C2 (en) * 1994-01-19 2003-03-06 Willich F Berg Bautechnik Process for consolidating and / or sealing floors and device for carrying out the process
DE19859276B4 (en) * 1998-12-22 2004-04-08 Rag Ag Device for discharging iso foam in underground mining and tunnel construction
CN103510959B (en) * 2013-09-13 2015-12-02 北京交通大学 A kind of Shallow-buried Large-span small interval loess tunnel excavation technology
CN103775091B (en) * 2014-01-06 2015-12-09 中国建筑第五工程局有限公司 Partition detection method and device for construction of three-dimensional intersection tunnel
CN207453984U (en) * 2017-11-06 2018-06-05 中铁第一勘察设计院集团有限公司 The constructing structure of existing buildings is worn under a kind of weak soil rich water tunnel
CN108376205B (en) * 2018-03-14 2020-03-24 中国铁路设计集团有限公司 Systematic design method for long-distance up-down overlapping shield tunnel in soft soil area

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003213708A (en) * 2001-11-13 2003-07-30 Taisei Corp Underground structure construction method and elevated traffic path
JP2004124548A (en) * 2002-10-03 2004-04-22 Kensetsu Kikaku Consultant:Kk Pile foundation, underground wall structure, and construction method
JP2005002671A (en) * 2003-06-12 2005-01-06 Kajima Corp Underpinning method and viaduct
CN103114611A (en) * 2013-03-01 2013-05-22 同济大学 Multistage cut-off method for underpass high-speed rail bridge opening deformation
CN103882854A (en) * 2014-04-08 2014-06-25 中铁二十五局集团轨道交通工程有限公司 Shield construction method for continuously passing through earth under railways and overpasses
CN204591302U (en) * 2015-02-12 2015-08-26 中国水利水电第十四工程局有限公司 A kind of support chassis for overlapping shield tunnel construction and brace table truck system
CN204984441U (en) * 2015-09-08 2016-01-20 中铁隧道股份有限公司 It backfills novel section of jurisdiction of quality behind one's back to change single shield TBM section of jurisdiction
CN107386274A (en) * 2017-08-14 2017-11-24 中铁第勘察设计院集团有限公司 Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side
CN110080781A (en) * 2019-05-05 2019-08-02 济南轨道交通集团有限公司 Between a kind of shield tunnel multi-region, small interval, it is overlapping under wear high-level bridge construction method

Cited By (94)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112589993A (en) * 2020-11-19 2021-04-02 绍兴中亚工贸园有限公司 Segment embedded part fixing base and segment forming method thereof
CN112627848B (en) * 2020-12-07 2023-02-28 中国电建集团华东勘测设计研究院有限公司 Segment typesetting method for intermediate ring with given point position
CN112627848A (en) * 2020-12-07 2021-04-09 中国电建集团华东勘测设计研究院有限公司 Segment typesetting method for intermediate ring with given point position
CN112796771A (en) * 2021-01-28 2021-05-14 中铁第一勘察设计院集团有限公司 Construction structure and method of shield tunnel head start under the condition of limited space
CN112879025B (en) * 2021-02-04 2023-12-22 中铁十六局集团北京轨道交通工程建设有限公司 Intelligent regulation and control method for earth pressure balance shield earth pressure based on GRU deep learning
CN112948931A (en) * 2021-03-03 2021-06-11 河南大学 Method for determining reasonable included angle and clear distance of shield construction under double-line overlapping working condition of new construction and existing subway tunnel
CN112948931B (en) * 2021-03-03 2023-04-07 河南大学 Method for determining reasonable included angle and clear distance of shield construction under double-line overlapping working condition of new construction and existing subway tunnel
CN113049775B (en) * 2021-03-09 2022-12-30 天津大学 Double-freedom-degree existing tunnel simulation test device and method
CN113049775A (en) * 2021-03-09 2021-06-29 天津大学 Double-freedom-degree existing tunnel simulation test device and method
CN113047859A (en) * 2021-04-12 2021-06-29 上海应用技术大学 Shield tunneling parameter control method based on local Fisher soil layer identification
CN113177246A (en) * 2021-04-19 2021-07-27 浙大城市学院 Method for calculating additional confining pressure of adjacent subway tunnel caused by steel sleeve construction
CN113177245A (en) * 2021-04-19 2021-07-27 浙大城市学院 Calculation method for longitudinal deformation of adjacent subway tunnel caused by steel sleeve construction
CN113309536A (en) * 2021-04-26 2021-08-27 上海市政工程设计研究总院(集团)有限公司 Method for tunneling from separated type to laminated type mine method
CN113958343B (en) * 2021-05-10 2024-04-02 南昌轨道交通集团有限公司 Structure and method for restraining floating of segment of full-section stratum shield tunnel
CN113958343A (en) * 2021-05-10 2022-01-21 南昌轨道交通集团有限公司 Structure and method for restraining upward floating of duct piece in full-section rock stratum shield tunnel
CN113006832A (en) * 2021-05-11 2021-06-22 西京学院 Small-excavation segment welded type underground vacuum pipeline and construction method thereof
CN113266376A (en) * 2021-05-12 2021-08-17 济南轨道交通集团有限公司 Model test device for simulating shield approaching underground structure micro-disturbance construction
CN113266376B (en) * 2021-05-12 2024-06-07 济南轨道交通集团有限公司 Model test device for simulating shield near-grounding underground structure micro-disturbance construction
CN113137239B (en) * 2021-05-15 2023-08-22 中铁十一局武汉重型装备有限公司 Method for reinforcing tunnel face of shield cutter head and grouting reinforcing device for method
CN113137239A (en) * 2021-05-15 2021-07-20 中铁十一局武汉重型装备有限公司 Shield cutter head face reinforcing method and grouting reinforcing device used for method
CN113322937A (en) * 2021-05-18 2021-08-31 中建交通建设集团有限公司 Openable assembly type steel underground diaphragm wall and application method thereof
CN113431085A (en) * 2021-05-26 2021-09-24 中铁第一勘察设计院集团有限公司 Reserved underpass structure system of subway station and construction method thereof
CN113373901A (en) * 2021-05-27 2021-09-10 中建一局集团建设发展有限公司 Overlapping shield tunnel house foundation reinforcing structure next to house and construction method
CN113374496A (en) * 2021-06-23 2021-09-10 上海隧道工程有限公司 Upper-crossing tunnel structure and construction method
CN113217037A (en) * 2021-06-25 2021-08-06 中铁二局集团有限公司 Backfill system and backfill method for single shield TBM or behind shield segment wall
CN113389557A (en) * 2021-06-25 2021-09-14 中铁第五勘察设计院集团有限公司 Isolation structure of side-passing bridge pile of shield tunnel and shield tunnel structure assembly
CN113356881A (en) * 2021-07-15 2021-09-07 上海地铁维护保障有限公司工务分公司 Segment deep grouting method for treating tunnel leakage diseases
CN113486435A (en) * 2021-07-22 2021-10-08 华侨大学 Shield underground butt joint and abandoned shell disassembly construction method based on BIM and numerical simulation
CN113486435B (en) * 2021-07-22 2023-07-28 华侨大学 Construction method of shield underground docking and abandoned shell dismantling based on BIM and numerical simulation
CN113685186A (en) * 2021-08-09 2021-11-23 北京城建轨道交通建设工程有限公司 Tunneling method for geological drilling in shield underpass water area
CN113685192A (en) * 2021-08-20 2021-11-23 上海市城市建设设计研究总院(集团)有限公司 Connecting node of main line shield tunnel in and out of ramp and construction method
CN113700437B (en) * 2021-09-01 2023-12-08 中交第二航务工程局有限公司 Soft rock tunnel pipe shed and pipe following drilling device and construction method
CN113700437A (en) * 2021-09-01 2021-11-26 中交第二航务工程局有限公司 Tube-following drilling device for soft rock tunnel tube shed and construction method
CN113653508A (en) * 2021-09-01 2021-11-16 中机中联工程有限公司 Bridge-lining combined structure with tunnel inner crossing function and construction method thereof
CN113605931A (en) * 2021-09-07 2021-11-05 浙江大学 Soil layer interface urban tunnel crossing reinforcement structure and construction method thereof
CN113605931B (en) * 2021-09-07 2022-05-03 浙江大学 Soil layer interface urban tunnel crossing reinforcement structure and construction method thereof
CN113863380A (en) * 2021-09-14 2021-12-31 中铁十九局集团广州工程有限公司 Construction method for large-diameter pipe jacking to penetrate through seawall
CN113774908A (en) * 2021-09-24 2021-12-10 浙江交工集团股份有限公司 Construction method of multiple-stirring pile machine capable of breaking hardness and preventing cracking
CN113863273A (en) * 2021-09-28 2021-12-31 中铁第四勘察设计院集团有限公司 Construction method of bored pile adjacent to operation railway
CN113685201A (en) * 2021-09-30 2021-11-23 济南大学 Construction method for replacing inverted arch of highway tunnel
CN113863953A (en) * 2021-10-08 2021-12-31 陕西同人应用材料有限公司 Subway tunnel segment reinforcing structure and rapid construction process
CN114046151A (en) * 2021-10-25 2022-02-15 中交隧道工程局有限公司 The reinforcement method of caisson suitable for shield construction
CN113863280A (en) * 2021-10-25 2021-12-31 中交隧道工程局有限公司 Reinforced pipe shed structure suitable for karst or fault open caisson foundation grouting
CN114046151B (en) * 2021-10-25 2024-04-05 中交隧道工程局有限公司 Caisson reinforcement method suitable for shield construction
CN113832947A (en) * 2021-11-05 2021-12-24 中铁第六勘察设计院集团有限公司 Device and method for reinforcing multiple-track railway with small space passing under shield tunnel
CN114776309A (en) * 2021-11-15 2022-07-22 中铁二院华东勘察设计有限责任公司 Method for improving transverse stress of deep-buried shield tunnel in soft soil body area
CN114352315A (en) * 2021-11-29 2022-04-15 北京恒祥宏业基础加固技术有限公司 Grouting method suitable for inhibiting shield segment from floating in water-rich area
CN114352315B (en) * 2021-11-29 2023-11-28 北京恒祥宏业基础加固技术有限公司 Grouting method suitable for restraining shield segment from floating upwards in water-rich area
CN114483091A (en) * 2021-12-02 2022-05-13 中南大学 A method for segmented grouting of large tube sheds in tunnels
CN114260847A (en) * 2021-12-16 2022-04-01 中铁隧道局集团有限公司 Assembling system and assembling method of horizontal vacuum tunnel detection model
CN114135311A (en) * 2021-12-23 2022-03-04 甘肃省交通规划勘察设计院股份有限公司 Tunnel advanced horizontal reinforcement jet grouting pile supporting structure and construction method
CN114232491B (en) * 2021-12-29 2024-01-30 广西路建工程集团有限公司 Construction method of multi-span simply supported prestressed bridge span in tunnel
CN114232491A (en) * 2021-12-29 2022-03-25 广西路建工程集团有限公司 Construction method of multi-span simply supported prestressed bridge span in tunnel
CN114412484A (en) * 2022-01-20 2022-04-29 北京住总集团有限责任公司 A kind of construction method of stacking tunnel
CN114592875B (en) * 2022-01-26 2024-06-04 浙江大通建设科技有限公司 Multi-angle reinforcement construction method in subway tunnel
CN114592875A (en) * 2022-01-26 2022-06-07 浙江大通建设科技有限公司 Multi-angle reinforcement construction method in subway tunnel
CN114444189B (en) * 2022-02-08 2024-09-10 同济大学 A method for inverse analysis of the longitudinal joint angle of shield tunnel
CN114444189A (en) * 2022-02-08 2022-05-06 同济大学 A method for inversion analysis of longitudinal joint opening angle of shield tunnel
CN114964091A (en) * 2022-02-23 2022-08-30 上海建工集团股份有限公司 Rapid detection device and method for slab staggering amount between shield section tunnel segments
CN114646411A (en) * 2022-03-14 2022-06-21 西安科技大学 Intelligent wireless multidirectional continuous drilling stress monitoring device
CN114646411B (en) * 2022-03-14 2024-05-31 西安科技大学 An intelligent wireless multi-directional continuous drilling stress monitoring device
CN114687760A (en) * 2022-03-24 2022-07-01 中铁九局集团第四工程有限公司 Anti-displacement subway tunnel structure based on soft foundation
CN114607390A (en) * 2022-03-28 2022-06-10 中铁二十局集团第五工程有限公司 Concrete pouring method for communication channel based on freezing method of soft soil water-rich stratum
CN114592892A (en) * 2022-04-02 2022-06-07 中铁第六勘察设计院集团有限公司 Implementation method for pulling out anchor cable of shield tunnel in steel sleeve in soft soil area
CN114881440A (en) * 2022-04-26 2022-08-09 济南交通发展投资有限公司 Risk control method and system for shield tunnel crossing high-speed railway bridge
CN114856616A (en) * 2022-05-13 2022-08-05 中铁第五勘察设计院集团有限公司 A kind of tunnel construction method and reinforcement protection structure
CN114775673A (en) * 2022-05-30 2022-07-22 杭州萧山交通建设管理有限公司 Pile foundation reserved filling enlarged bearing platform system construction method
CN114775673B (en) * 2022-05-30 2023-08-08 杭州萧山交通建设管理有限公司 Construction method for pile foundation reserved pile supplementing and pile cap enlarging system
CN115012966A (en) * 2022-06-09 2022-09-06 宁波地铁产业工程有限公司 Rapid reinforcing system and method for deformation of shield tunnel
CN115132048B (en) * 2022-06-28 2023-11-28 中铁四院集团西南勘察设计有限公司 Simulation test device and test method for proximity construction in established tunnel area
CN115132048A (en) * 2022-06-28 2022-09-30 中铁四院集团西南勘察设计有限公司 Simulation test device and test method for proximity construction in built tunnel area
CN114859017A (en) * 2022-07-06 2022-08-05 湖南大学 Stratum stress field and displacement field control test device and method
CN115075827A (en) * 2022-07-06 2022-09-20 中铁工程装备集团有限公司 Method and structure for advanced processing of main line tunnel influence area based on small-section tunnel
CN114991830B (en) * 2022-07-18 2022-10-21 中铁电气化局集团有限公司 Subway construction mobile tunnel segment supporting trolley
CN114991830A (en) * 2022-07-18 2022-09-02 中铁电气化局集团有限公司 Subway construction mobile tunnel segment supporting trolley
CN115492592A (en) * 2022-08-16 2022-12-20 中铁十四局集团有限公司 The construction method of starting and building warehouses for large-section shield tunnels jointly built by highways and railways
CN115506824A (en) * 2022-08-31 2022-12-23 中铁十九局集团第三工程有限公司 Rock Wall Reinforcement Structure and Reinforcement Method in Small Clear Distance Tunnel
CN115492071B (en) * 2022-09-21 2024-01-26 甘肃省交通科学研究院集团有限公司 Counterforce platform for static load test of foundation in highway tunnel and construction method thereof
CN115492071A (en) * 2022-09-21 2022-12-20 甘肃省交通科学研究院集团有限公司 Reaction platform for static load test of foundation in highway tunnel and construction method thereof
CN115949091A (en) * 2022-11-21 2023-04-11 山东大学 A pile foundation structure and method suitable for pile foundation underpinning of stacked tunnels
CN116241260A (en) * 2022-12-14 2023-06-09 杭州临平交通建设有限公司 Construction method of temporary slab support assisted shield tunneling through ultra-deep foundation pit
CN116607574A (en) * 2023-03-09 2023-08-18 中铁二院工程集团有限责任公司 Protection structure suitable for crossing existing shallow underground tunnel on road and construction method
CN115928798B (en) * 2023-03-13 2023-05-23 北京城建设计发展集团股份有限公司 Method for passing through existing underground structure of rail transit through ultra-small clear distance long-distance oblique crossing
CN116451310B (en) * 2023-03-17 2023-10-27 北京城建设计发展集团股份有限公司 Method for ultra-small clear distance long-distance oblique crossing of existing U-shaped groove structure of rail transit
CN117128008B (en) * 2023-10-26 2024-02-23 江苏快鹿地铁钢结构制造有限公司 Quick assembly type steel pipe sheet for tunnel connecting channel
CN117128008A (en) * 2023-10-26 2023-11-28 江苏快鹿地铁钢结构制造有限公司 Quick assembly type steel pipe sheet for tunnel connecting channel
CN117780387A (en) * 2023-12-27 2024-03-29 北京城建道桥建设集团有限公司 An underground cavern lining construction method that passes through existing waste piles
CN117905484A (en) * 2024-01-29 2024-04-19 深圳大学 E-shaped plate joint for assembled inverted arch, design method and construction method thereof
CN118208259A (en) * 2024-05-22 2024-06-18 中铁十一局集团城市轨道工程有限公司 Negative ring pipe piece of embedded sleeve and construction method thereof
CN118686216A (en) * 2024-08-27 2024-09-24 浙江道其乐科技有限公司 A pile foundation reinforcement structure for increasing load amplitude and implementation method thereof
CN119145883A (en) * 2024-11-11 2024-12-17 中国建筑第六工程局有限公司 Shield construction grouting method for water-rich sandy pebble stratum
CN119249582A (en) * 2024-12-04 2025-01-03 中铁七局集团第三工程有限公司 A construction method and device for shield tunneling through existing structures
CN119849268A (en) * 2025-03-19 2025-04-18 中铁十四局集团有限公司 Segment bearing safety early warning method, system and storage medium in large-diameter shield synchronous pushing and splicing mode
CN120105559A (en) * 2025-05-08 2025-06-06 中国地质大学(武汉) A method for predicting ground deformation caused by a shield tunnel passing through an existing ground-connected wall

Also Published As

Publication number Publication date
CN110080781A (en) 2019-08-02
AU2019444087B2 (en) 2023-11-23
AU2019444087A1 (en) 2022-01-06
CN110080781B (en) 2021-05-07

Similar Documents

Publication Publication Date Title
WO2020224233A1 (en) Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner
Hong Typical underwater tunnels in the mainland of China and related tunneling technologies
CN101761346B (en) Method for constructing metamorphic rock confined water tunnel
CN101440708B (en) PBA shallow buried underground excavating close range large section three-hole separated island type structure construction method
CN101139838B (en) Construction method for high artesian area ultra-deep foundation pit
CN109914456B (en) A design and construction method when a bridge and a subway tunnel are built adjacent to each other
CN103835723B (en) Pit shaft passes through the comprehensive pre-administering method on stratum, goaf
CN111206944B (en) Construction method for differential settlement control of pre-supporting excavation of deformation joint of underpass subway station
CN108868814B (en) Air shaft of underground excavation air duct shield tunnel of collapsible loess combined pebble soil stratum
CN105525619B (en) A kind of water rich strata bored tunnel occlusion pipe curtain
Yang et al. A new construction method for metro stations in dense urban areas in Shanghai soft ground: Open-cut shafts combined with quasi-rectangular jacking boxes
CN110700853A (en) Shallow soil covering shield tunnel reinforcing method based on weak stratum
CN109386293A (en) The sealed reception construction method of large section rectangular top pipe
CN112145203A (en) Full-face advancing type sectional grouting construction method and overlapped tunnel construction method
CN106758759A (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN111350106A (en) A kind of railway track temporary support structure and construction method thereof
CN108952728B (en) A kind of headframe main body construction and self well digging freeze parallel construction system and method
CN211202006U (en) A tunnel arch structure with advanced locking feet to reinforce weak soil layers
CN112922646A (en) Building method of underground excavation station excavated by large-section single-span support through superposed arch-wall integrated type
CN205576990U (en) Cross section and wear bridge pier tunnel slip casting supporting construction
CN219909058U (en) Separated island type subway station structure
CN206477240U (en) A kind of trestle pile foundation for deep water drift net riverbed
Lunardi et al. Brenner base tunnel & Isarco River underpass section: Several technical and operational solutions
CN114704265A (en) Construction method for subway shield tunnel to pass through viaduct tunnel downwards
Tan et al. Deep intervention shaft excavation in Kuala Lumpur limestone formation with pre-tunnelling construction method

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 19928092

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

ENP Entry into the national phase

Ref document number: 2019444087

Country of ref document: AU

Date of ref document: 20191122

Kind code of ref document: A

122 Ep: pct application non-entry in european phase

Ref document number: 19928092

Country of ref document: EP

Kind code of ref document: A1

122 Ep: pct application non-entry in european phase

Ref document number: 19928092

Country of ref document: EP

Kind code of ref document: A1

32PN Ep: public notification in the ep bulletin as address of the adressee cannot be established

Free format text: NOTING OF LOSS OF RIGHTS PURSUANT TO RULE 112(1) EPC (EPO FORM 1205A DATED 15/05/2023)

122 Ep: pct application non-entry in european phase

Ref document number: 19928092

Country of ref document: EP

Kind code of ref document: A1