CN114856616A - A kind of tunnel construction method and reinforcement protection structure - Google Patents
A kind of tunnel construction method and reinforcement protection structure Download PDFInfo
- Publication number
- CN114856616A CN114856616A CN202210521374.2A CN202210521374A CN114856616A CN 114856616 A CN114856616 A CN 114856616A CN 202210521374 A CN202210521374 A CN 202210521374A CN 114856616 A CN114856616 A CN 114856616A
- Authority
- CN
- China
- Prior art keywords
- construction
- tunnel
- concrete
- existing railway
- reinforcement
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000010276 construction Methods 0.000 title claims abstract description 144
- 230000002787 reinforcement Effects 0.000 title claims abstract description 46
- 238000002955 isolation Methods 0.000 claims abstract description 37
- 238000000034 method Methods 0.000 claims abstract description 29
- 239000002689 soil Substances 0.000 claims abstract description 29
- 239000004567 concrete Substances 0.000 claims description 34
- 238000009412 basement excavation Methods 0.000 claims description 31
- 229910000831 Steel Inorganic materials 0.000 claims description 30
- 239000010959 steel Substances 0.000 claims description 30
- 238000013461 design Methods 0.000 claims description 15
- 239000011378 shotcrete Substances 0.000 claims description 12
- 238000009415 formwork Methods 0.000 claims description 10
- 238000004140 cleaning Methods 0.000 claims description 9
- 238000002360 preparation method Methods 0.000 claims description 5
- 238000005507 spraying Methods 0.000 claims description 5
- 239000011083 cement mortar Substances 0.000 claims description 4
- 239000011150 reinforced concrete Substances 0.000 claims description 4
- 238000005728 strengthening Methods 0.000 claims description 3
- 239000004568 cement Substances 0.000 claims description 2
- 239000004746 geotextile Substances 0.000 claims description 2
- 239000012528 membrane Substances 0.000 claims description 2
- 238000005192 partition Methods 0.000 claims description 2
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 239000002002 slurry Substances 0.000 claims 1
- 239000007921 spray Substances 0.000 claims 1
- 238000003466 welding Methods 0.000 claims 1
- 230000001681 protective effect Effects 0.000 description 7
- 241001669679 Eleotris Species 0.000 description 6
- 238000012986 modification Methods 0.000 description 6
- 230000004048 modification Effects 0.000 description 6
- 230000000694 effects Effects 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 239000011435 rock Substances 0.000 description 4
- 239000000243 solution Substances 0.000 description 3
- 238000010586 diagram Methods 0.000 description 2
- 238000006073 displacement reaction Methods 0.000 description 2
- 238000009933 burial Methods 0.000 description 1
- 238000004891 communication Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 239000011440 grout Substances 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 230000035515 penetration Effects 0.000 description 1
- 238000009417 prefabrication Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/003—Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
- E21D11/107—Reinforcing elements therefor; Holders for the reinforcing elements
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
- E21D11/383—Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D5/00—Lining shafts; Linings therefor
- E21D5/11—Lining shafts; Linings therefor with combinations of different materials, e.g. wood, metal, concrete
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Wood Science & Technology (AREA)
- Mechanical Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
本申请实施例提供一种隧道加固防护结构及应用这种防护结构的施工方法,这种隧道的加固防护结构包括防护结构及加固结构,防护结构包括隔离防护桩、水平隔离管棚、隧道顶插大管棚,隔离防护桩及水平隔离管棚用于阻断隧道施工引起的通行道路的水平及竖向变形。隧道顶插大管棚用于保证隧道顶既有铁路设施的安全,防止坍塌,加固结构包括支撑桩及D型便梁,用于在施工过程中对待开挖隧道上方的既有铁路设施进行支撑加固。经验证,采用上述加固防护结构及施工方法,可以保证隧道上方土体的稳定性,可以满足既有市政道路及铁路运营安全。
Embodiments of the present application provide a tunnel reinforcement protection structure and a construction method using the protection structure. The reinforcement protection structure of the tunnel includes a protection structure and a reinforcement structure, and the protection structure includes an isolation protection pile, a horizontal isolation pipe shed, a tunnel top insert Large pipe sheds, isolation protection piles and horizontal isolation pipe sheds are used to block the horizontal and vertical deformation of the passageway caused by tunnel construction. The large pipe shed inserted on the top of the tunnel is used to ensure the safety of the existing railway facilities on the top of the tunnel and prevent collapse. The reinforcement structure includes supporting piles and D-shaped beams, which are used to support the existing railway facilities above the tunnel to be excavated during the construction process. reinforcement. It has been verified that the above reinforcement and protection structure and construction method can ensure the stability of the soil above the tunnel, and can meet the operational safety of existing municipal roads and railways.
Description
技术领域technical field
本申请涉及路桥施工技术领域,更具体地说,涉及一种隧道施工方法及加固防护结构。The present application relates to the technical field of road and bridge construction, and more particularly, to a tunnel construction method and a reinforcement protection structure.
背景技术Background technique
随着现代经济的快速发展,几乎所有的大型城市都存在着交通拥堵,城市配套管线等设施落后的情况,其市政与公路工程及配套管线等已不能满足日益增长的当地交通及配套设施的要求,地铁、轻轨、市政公路等公共交通设施的新增建设需求十分迫切。With the rapid development of modern economy, almost all large cities have traffic congestion and backward facilities such as urban supporting pipelines. Their municipal and highway projects and supporting pipelines can no longer meet the growing requirements of local traffic and supporting facilities. , the need for new construction of public transport facilities such as subways, light rails, and municipal highways is very urgent.
而城市市区已经现存大量的既有铁路设施如市内铁路线路及铁路相关建筑等等,新增市政铁路或公路工程及管线等下穿既有铁路设施往往是不可避免的,通常,下穿位置应选择在对既有铁路设施运行及干扰较小的位置,并且,为保证隧道暗挖施工过程中,既有铁路及市政道路运营安全,因此,必须采取可靠措施,使施工引起的变形指标满足规范和设计要求。当地下隧道下穿既有铁路设施时,当埋深较深时,可以在隧道洞内采取注浆等加固措施结合地表纵横梁及3-5-3扣轨加固措施(以重型钢轨加钢扣件、螺栓连接形成为纵、横梁。)可以保证既有铁路设施变形要求。However, there are already a large number of existing railway facilities in urban areas, such as urban railway lines and railway-related buildings, etc. It is often inevitable for new municipal railways or highway projects and pipelines to penetrate existing railway facilities. The location should be selected in a location with less interference to the operation of the existing railway facilities, and in order to ensure the safe operation of the existing railway and municipal roads during the tunnel excavation construction process, reliable measures must be taken to make the deformation index caused by the construction. Meet specification and design requirements. When the underground tunnel passes through the existing railway facilities, when the burial depth is relatively deep, reinforcement measures such as grouting can be taken in the tunnel hole, combined with the surface longitudinal beams and 3-5-3 rail reinforcement measures (heavy steel rails plus steel buckles). The parts and bolts are connected to form longitudinal and transverse beams.) It can ensure the deformation requirements of existing railway facilities.
但是地下隧道的建设有时受道路及管线规划及地形等限制,从既有铁路设施运行繁忙的位置,例如既有铁路的平交道口位置下穿也是难以避免的。这种平交道口的位置,通常采用整体钢筋混凝土板结构,由于隧道覆土很浅,无法形成拱效应,既有铁路及市政道路变形指标无法满足运营安全要求。现有的在隧道洞内采取注浆等加固措施结合地表纵横梁及3-5-3扣轨加固措施,无法保证隧道上方土体的稳定性,无法满足既有市政道路及铁路运营安全。However, the construction of underground tunnels is sometimes limited by road and pipeline planning and terrain, and it is unavoidable to pass under the location where the existing railway facilities are busy, such as the level crossing of the existing railway. The location of this level crossing usually adopts an integral reinforced concrete slab structure. Due to the shallow soil covering of the tunnel, the arch effect cannot be formed, and the deformation indicators of the existing railways and municipal roads cannot meet the operational safety requirements. The existing reinforcement measures such as grouting in the tunnel cavity combined with the surface longitudinal beams and the 3-5-3 rail buckle reinforcement measures cannot ensure the stability of the soil above the tunnel, and cannot meet the operational safety of existing municipal roads and railways.
发明内容SUMMARY OF THE INVENTION
为了解决上述技术缺陷之一,本申请实施例中提供了一种隧道的加固防护结构及应用这种结构的施工方法。In order to solve one of the above technical defects, embodiments of the present application provide a tunnel reinforcement protection structure and a construction method using the structure.
根据本申请实施例的第一个方面,提供了一种隧道的加固防护结构,其包括防护结构及加固结构,防护结构包括隔离防护桩、水平隔离管棚、隧道顶插大管棚,所述隔离防护桩设置在待开挖隧道的一侧或两侧,所述水平隔离管棚设置在隔离防护桩的外侧,所述隧道顶插大管棚设置在待开挖隧道的顶部;加固结构包括支撑桩及便梁,便梁包括纵梁及横梁,便梁架设在支撑桩上,便梁设置在待开挖隧道上方的既有铁路设施下。根据本申请实施例的第二个方面,提供了一种隧道的施工方法,这种施工方法采用如上所述的隧道的加固防护结构,其具体施工步骤包括:According to a first aspect of the embodiments of the present application, a reinforcement protection structure for a tunnel is provided, which includes a protection structure and a reinforcement structure. The isolation protection pile is arranged on one side or both sides of the tunnel to be excavated, the horizontal isolation pipe shed is arranged on the outer side of the isolation protection pile, and the large pipe shed inserted at the top of the tunnel is arranged on the top of the tunnel to be excavated; the reinforcement structure includes: Support piles and beams, the beams include longitudinal beams and transverse beams, the beams are erected on the support piles, and the beams are set under the existing railway facilities above the tunnel to be excavated. According to a second aspect of the embodiments of the present application, a construction method of a tunnel is provided, and the construction method adopts the reinforcement protection structure of the tunnel as described above, and the specific construction steps include:
设立施工竖井,于隧道设计起点处设立施工竖井,进行竖井高压旋喷桩及圈梁施工;Set up a construction shaft, set up a construction shaft at the starting point of the tunnel design, and carry out the construction of high-pressure rotary jet piles and ring beams in the shaft;
防护结构施工,所述加固防护结构施工的步骤包括按照权利要求1所述的架设位置进行所述水平隔离管棚施工、隧道顶插大管棚施工以及隔离防护桩施工,以及所述既有铁路设施需要架空的位置的下方,进行所述加固结构中的支撑桩施工;The protection structure construction, the step of strengthening the protection structure construction includes carrying out the horizontal isolation pipe shed construction, the tunnel roof inserting the large pipe shed construction and the isolation protection pile construction according to the erection position of
加固结构施工,在所述支撑桩上架设D型便梁,对所述既有铁路设施进行支撑加固;Construction of the reinforcement structure, erecting D-shaped beams on the supporting piles to support and reinforce the existing railway facilities;
隧道暗挖施工,执行加固结构施工步骤后开挖隧道,所述隧道暗挖施工采用分段开挖的方式,先对所述既有铁路设施的一侧进行开挖施工,再对待开挖隧道上方既有铁路设施的另一侧进行开挖施工。For tunnel undercover construction, the tunnel is excavated after the reinforcement structure construction steps are performed. The tunnel undercover construction adopts the method of subsection excavation. First, one side of the existing railway facility is excavated, and then the tunnel is to be excavated. Excavation is carried out on the other side of the existing railway facilities above.
采用本申请实施例中提供的隧道的加固防护结构及应用这种结构的施工方法,对既有市政道路进行临时导改,分幅通行,保证既有铁路设施的运营;施工中在隧道旁同时采取隔离防护桩+水平隔离管棚的措施,来阻断隧道施工引起的土体的水平及竖向变形,保证既有铁路设施的稳固与安全;采取隧道顶插大管棚措施来保证隧道顶既有铁路设施的安全,防止坍塌;另对既有铁路设施采取便梁架空的加固方法,以满足既有铁路设施的变形和受力要求。经验证,采用这种加固防护结构及施工方法,可以保证隧道上方土体的稳定性,可以满足既有市政道路及铁路运营安全。The reinforcement and protection structure of the tunnel provided in the embodiment of the present application and the construction method using this structure are used to temporarily guide and reform the existing municipal roads, and pass through in sections, so as to ensure the operation of the existing railway facilities; The measures of isolation protection piles and horizontal isolation pipe sheds are adopted to block the horizontal and vertical deformation of the soil caused by the tunnel construction, so as to ensure the stability and safety of the existing railway facilities. Safety of existing railway facilities to prevent collapse; in addition, the existing railway facilities are strengthened with overhead beams to meet the deformation and stress requirements of existing railway facilities. It has been verified that the use of this reinforced protective structure and construction method can ensure the stability of the soil above the tunnel, and can meet the operational safety of existing municipal roads and railways.
附图说明Description of drawings
此处所说明的附图用来提供对本申请的进一步理解,构成本申请的一部分,本申请的示意性实施例及其说明用于解释本申请,并不构成对本申请的不当限定。在附图中:The drawings described herein are used to provide further understanding of the present application and constitute a part of the present application. The schematic embodiments and descriptions of the present application are used to explain the present application and do not constitute an improper limitation of the present application. In the attached image:
图1为本申请实施例提供的隧道的加固防护结构的平面结构示意图;1 is a schematic plan view of the reinforcement and protection structure of a tunnel provided by an embodiment of the present application;
图2为本申请实施例提供的隧道的加固防护结构的立面结构示意图;FIG. 2 is a schematic elevational structure diagram of a tunnel reinforcement protection structure provided by an embodiment of the present application;
图3为本申请实施例提供的隧道的施工方法的流程示意图;3 is a schematic flowchart of a tunnel construction method provided by an embodiment of the present application;
图4为本申请实施例提供的隧道的加固结构施工步骤流程示意图;FIG. 4 is a schematic flowchart of the construction steps of the reinforcement structure of the tunnel provided by the embodiment of the present application;
图5为本申请实施例提供的隧道的隧道暗挖施工步骤流程示意图;FIG. 5 is a schematic flowchart of the construction steps of the tunnel undercover construction of the tunnel provided by the embodiment of the present application;
图6为本申请实施例提供的隧道的清理以及验收步骤流程示意图。FIG. 6 is a schematic flowchart of a tunnel cleaning and acceptance step according to an embodiment of the present application.
附图标记:Reference number:
1-施工竖井;2-待挖隧道;3-隔离防护桩;4-水平隔离管棚;5-D型便梁;6-支撑桩;7-临时支墩;8-道口板;9-大管棚。1-construction shaft; 2-tunnel to be dug; 3-isolation protection pile; 4-horizontal isolation pipe shed; 5-D-type beam; 6-support pile; 7-temporary pier; Tube Shed.
具体实施方式Detailed ways
为了使本申请实施例中的技术方案及优点更加清楚明白,以下结合附图对本申请的示例性实施例进行进一步详细的说明,显然,所描述的实施例仅是本申请的一部分实施例,而不是所有实施例的穷举。需要说明的是,在不冲突的情况下,本申请中的实施例及实施例中的特征可以相互组合。In order to make the technical solutions and advantages of the embodiments of the present application more clear, the exemplary embodiments of the present application will be described in further detail below with reference to the accompanying drawings. Obviously, the described embodiments are only a part of the embodiments of the present application, and Not all embodiments are exhaustive. It should be noted that the embodiments in the present application and the features of the embodiments may be combined with each other in the case of no conflict.
在实现本申请的过程中,发明人发现在隧道覆土很浅的位置进行浅埋暗挖隧道施工,由于覆土很浅,无法形成拱效应,既有铁路及市政道路变形指标无法满足运营安全要求,而现有的在隧道洞内采取注浆等加固措施结合地表纵横梁及3-5-3扣轨加固措施,无法保证隧道上方土体的稳定性,无法满足既有市政道路及铁路运营安全。In the process of realizing the present application, the inventor found that the shallow buried tunnel construction was carried out at the position where the tunnel covering soil was very shallow. Due to the shallow covering soil, the arch effect could not be formed, and the deformation indicators of the existing railways and municipal roads could not meet the operational safety requirements. However, the existing reinforcement measures such as grouting in the tunnel cavity combined with the surface longitudinal beams and the 3-5-3 rail buckle reinforcement measures cannot ensure the stability of the soil above the tunnel, and cannot meet the operational safety of existing municipal roads and railways.
针对上述问题,本申请实施例中提供了一种隧道的加固防护结构以及应用这种防护结构的隧道的施工方法,以期在隧道覆土很浅的位置进行隧道施工时,既可以保证隧道上方土体的稳定性,又可以满足既有市政道路及铁路运营安全。In view of the above problems, the embodiments of the present application provide a tunnel reinforcement protection structure and a tunnel construction method using the protection structure, so as to ensure that the soil body above the tunnel can be ensured when the tunnel is constructed at a position where the tunnel is covered with shallow soil. It can also meet the operational safety of existing municipal roads and railways.
为了清楚明白地说明本申请的技术方案,本申请实施例采用浅埋暗挖隧道下穿既有铁路平交道口的具体应用场景进行说明,但是值得注意的是,本申请的技术方案不止应用于这一类应用场景,而是可以应用在所有覆土过浅的浅埋暗挖隧道施工场景中。In order to clearly and clearly illustrate the technical solution of the present application, the embodiment of the present application adopts the specific application scenario of a shallow buried tunnel underpassing an existing railway level crossing for illustration, but it is worth noting that the technical solution of the present application is not only applied to This type of application scenario can be applied to all shallow buried tunnel construction scenarios where the overburden is too shallow.
图1为本申请实施例提供的隧道的加固防护结构的平面结构示意图;图2为本申请实施例提供的隧道的加固防护结构的立面结构示意图,如图1及图2所示,本申请实施例隧道的加固防护结构包括防护结构及加固结构,其中防护结构在隧道施工前进行架设,防护结构包括隔离防护桩3、水平隔离管棚4、隧道顶插大管棚9,隔离防护桩3设置在待开挖隧道2的一侧或两侧,水平隔离管棚4设置在隔离防护桩3的外侧(隔离防护桩3靠近待开挖隧道2的一侧为内侧),隧道顶插大管棚9设置在待开挖隧道2的顶部,其断面形状依地质结构需要而定,通常为与隧道拱顶同心的弧形;加固结构在施工前及施工中架设,可以对待开挖隧道上方的既有铁路设施进行支撑加固,加固结构包括支撑桩6及便梁5,便梁包括纵梁及横梁,纵梁架设在支撑桩6和/或临时支墩7上,待开挖隧道上方的既有铁路设施架设在纵梁及横梁组成的构架上。FIG. 1 is a schematic plan view of a reinforced protective structure of a tunnel provided by an embodiment of the application; FIG. 2 is a schematic diagram of an elevation structure of a reinforced protective structure of a tunnel provided by an embodiment of the application. As shown in FIGS. 1 and 2 , the present application The reinforcement protection structure of the embodiment tunnel includes a protection structure and a reinforcement structure, wherein the protection structure is erected before the tunnel construction, and the protection structure includes an
隧道开挖卸荷之后围岩应力状态重新改变,隧道底部压力减小导致底部发生变形而隆起:同时隧道支护结构变形导致隧道围岩向隧道内滑移,在隧道支护结构与被保护建筑物之间设置隔离防护桩,利用桩身插入到滑动面下部的稳固土层中,通过对桩的抗力来平衡滑动体的推力,从而达到平衡稳定。当隧道围岩向隧道内滑动时受到桩体的阻抗,使桩前滑体达到稳定状态,控制了桩后土体的位移变形,从而减小了隧道周边设施或建筑物的变形,起到保护既有铁路设施和/或建筑物的作用。After the tunnel excavation and unloading, the stress state of the surrounding rock changes again, and the pressure at the bottom of the tunnel decreases, causing the bottom to deform and uplift. At the same time, the deformation of the tunnel support structure causes the tunnel surrounding rock to slide into the tunnel, and the tunnel support structure and the protected building An isolation protection pile is set between the objects, and the pile body is inserted into the stable soil layer at the lower part of the sliding surface, and the thrust of the sliding body is balanced by the resistance of the pile, so as to achieve balance and stability. When the surrounding rock of the tunnel slides into the tunnel, it is resisted by the pile body, so that the sliding body in front of the pile reaches a stable state, which controls the displacement and deformation of the soil body behind the pile, thereby reducing the deformation of the facilities or buildings around the tunnel and protecting it. The role of existing railway facilities and/or buildings.
管棚结构是一种超前支护结构,水平隔离管棚是在隔离防护桩的外侧(隔离防护桩靠近隧道主体的一侧为内侧),平行于隔离防护桩的位于预先钻孔并安设惯性力矩较大的厚壁钢管,进一步起到超前支护的作用。一方面,水平隔离管棚在隔离防护桩的基础上进一步从整体上提高了土体刚度,可阻止土体水平变形。另一方面,当隧道施工扰动土体时,防护隔离桩及水平隔离管棚周围的土体产生不均匀变形,使土颗粒互相“楔紧”,在一定区域的土层中出现土拱效应,有效阻止桩后土体水平变形,由于水平隔离管棚排列密集,土拱效应明显,配合防护隔离桩,可以有效隔离隧道周围土体在施工过程中的水平位移。The pipe shed structure is a kind of advanced support structure. The horizontal isolation pipe shed is on the outer side of the isolation protection pile (the side of the isolation protection pile close to the tunnel main body is the inner side), parallel to the isolation protection pile is located in pre-drilled holes and installed inertial. The thick-walled steel pipe with larger moment further plays the role of advanced support. On the one hand, the horizontal isolation tube shed further improves the overall stiffness of the soil mass on the basis of the isolation protection pile, which can prevent the horizontal deformation of the soil mass. On the other hand, when the tunnel construction disturbs the soil, the soil around the protective isolation pile and the horizontal isolation pipe shed will deform unevenly, causing the soil particles to "wedge" each other, and the soil arching effect will appear in the soil layer in a certain area. It can effectively prevent the horizontal deformation of the soil after the piles. Due to the dense arrangement of the horizontal isolation pipe sheds, the soil arch effect is obvious. With the protective isolation piles, the horizontal displacement of the soil around the tunnel during the construction process can be effectively isolated.
隧道顶插大管棚9是在开挖的地下隧道或结构工程的衬砌拱圈隐埋弧线上,预先钻孔并安设惯性力矩较大的厚壁钢管,起临时超前支护作用,防止土层坍塌和地表下沉,以保证掘进与后续支护工艺安全运作。The large pipe shed 9 is inserted at the top of the tunnel is to drill holes in advance and install a thick-walled steel pipe with a large moment of inertia on the buried arc of the lining arch ring of the excavated underground tunnel or structural engineering, which plays the role of temporary advanced support and prevents the Soil collapse and surface subsidence to ensure safe operation of excavation and subsequent support processes.
D型便梁适用于既有线路或站场的桥涵及隧道施工,它的最大优点是可以在施工过程中保证既有铁路设施的运行,例如,使用D型便梁支撑既有铁路或市政公路,可以在在不中断行车的情况下,利用它进行隧道的开挖和施工。由于这些特性,D型便梁已经得到了广泛的应用,为了节省设计及生产成本,本申请实施例中优选D型便梁。D-type beam is suitable for the construction of bridges, culverts and tunnels of existing lines or stations. Its biggest advantage is that it can ensure the operation of existing railway facilities during the construction process. For example, use D-type beam to support existing railways or municipal roads. , it can be used for tunnel excavation and construction without interrupting traffic. Due to these characteristics, D-type stool beams have been widely used. In order to save design and production costs, D-type stool beams are preferred in the embodiments of the present application.
采用上述结构,可以在隧道覆土很浅的位置进行浅埋暗挖隧道施工时,既可以保证隧道上方土体的稳定性,又可以满足既有市政道路及铁路运营安全。The above structure can ensure the stability of the soil above the tunnel and meet the operational safety of the existing municipal roads and railways when the tunnel is shallowly buried and excavated at the position where the tunnel covering soil is very shallow.
本申请实施例还提供了应用上述加固防护结构的隧道的施工方法,图3为本申请实施例提供的隧道的施工方法的流程示意图,如图3所示,其具体施工步骤包括:The embodiment of the present application also provides a construction method of the tunnel applying the above-mentioned reinforcement and protection structure. FIG. 3 is a schematic flowchart of the construction method of the tunnel provided by the embodiment of the present application. As shown in FIG. 3, the specific construction steps include:
步骤200:设立施工竖井1,于隧道设计起点处设立施工竖井,进行竖井高压旋喷桩及圈梁施工;Step 200: Set up the
步骤300:防护结构施工,加固防护结构施工的步骤包括按照上述隧道的加固支护结构的架设位置进行水平隔离管棚施工、隧道顶插大管棚施工以及隔离防护桩施工,以及既有铁路设施(如既有铁路)需要架空的位置的下方,进行加固结构中的支撑桩施工;Step 300: Construction of the protective structure. The steps of strengthening the protective structure include the construction of horizontal isolation pipe sheds, the construction of large pipe sheds inserted into the top of the tunnel, the construction of isolation protection piles, and the construction of existing railway facilities according to the erection positions of the above-mentioned tunnel reinforcement and support structures. (such as existing railways) below the position that needs to be overhead, carry out the construction of supporting piles in the reinforcement structure;
步骤400:加固结构施工,在支撑桩上架设D型便梁,对既有铁路设施(如既有铁路)进行支撑加固;Step 400: Constructing the reinforcement structure, erecting D-shaped beams on the support piles to support and reinforce existing railway facilities (such as existing railways);
步骤500:执行加固结构施工步骤后,进行隧道暗挖施工,隧道施工采用分段开挖的方式,先对既有铁路设施(如既有铁路)的一侧进行开挖施工,再对待开挖隧道上方既有铁路设施的另一侧进行开挖施工。Step 500: After the reinforcement structure construction step is performed, the tunnel excavation construction is carried out. The tunnel construction adopts the method of subsection excavation. First, excavate one side of the existing railway facilities (such as the existing railway), and then perform the excavation construction. Excavation will be carried out on the other side of the existing railway facilities above the tunnel.
其中,在进行步骤200前可以进行步骤100:施工前准备,施工前准备的步骤包括交通临时导改、分幅通行;以在既有铁路平交道口处下穿暗挖隧道为例,施工前根据计划进行临时导流,必要时改道,引导列车在不同时间通行;Wherein, before proceeding to step 200, step 100 can be performed: preparation before construction. The steps of preparation before construction include temporary traffic guidance and modification, and divided traffic; Temporary diversion according to the plan, diversion if necessary, and guide trains to pass at different times;
在步骤500之后,可以进行步骤600:清理及验收,即在施工完成后对施工现场进行清理、恢复并验收。After
如果施工场景是既有铁路平交道口处下穿隧道,在隧道开挖以及进行架设D型便梁前需要拆除道口板8,并铺设道砟、轨枕、钢轨等,为了保障通车,道口板8的拆除需要在天窗点内进行。If the construction scene is to pass through the tunnel at the existing railway level crossing, the crossing
图4为本申请实施例提供的隧道的加固结构施工步骤流程示意图,如图4所示,进一步的,加固结构施工步骤包括:FIG. 4 is a schematic flowchart of the construction steps of the reinforcement structure of the tunnel provided by the embodiment of the application. As shown in FIG. 4 , further, the construction steps of the reinforcement structure include:
步骤401:组装便梁,即采用吊车将纵梁吊装到位后,与横梁进行连接,组装D型便梁5;Step 401: Assembling the facilitation beam, that is, after the longitudinal beam is hoisted in place by a crane, it is connected with the transverse beam to assemble the D-shaped
步骤402:架设便梁,在D型便梁5组装完毕后,逐渐抬高纵梁,使D型便梁5及支撑桩承重;Step 402: erecting the facilitation beam, after the D-
步骤403:隧道施工过程中对D型便梁进行检查和养护。Step 403: Inspect and maintain the D-type facilitation beam during the tunnel construction process.
以既有铁路平交道口处下穿浅埋暗挖隧道为例,组装便梁的具体方式为:Taking an existing railway level crossing under a shallow buried tunnel as an example, the specific method of assembling the beam is as follows:
1)用吊车把钢枕吊运至线路两侧。根据钢枕间距在线路上标出的钢枕位置(标在轨腰上)。封锁点前利用列车慢行间隔先要调整轨枕间距,调整好轨枕间距,并将多余的轨枕抽出,按空隙插入D型便梁钢枕。钢枕的穿入要垂直于线路,先中间后两侧。1) Use a crane to lift the steel sleeper to both sides of the line. The position of the steel sleeper marked on the line according to the spacing of the steel sleeper (marked on the rail waist). Before the blockade point, the distance between the sleepers should be adjusted by using the interval of the slow running of the train, and the distance between the sleepers should be adjusted properly. The penetration of the steel sleeper should be perpendicular to the line, first in the middle and then on both sides.
2)吊装纵梁,在线路一侧停放大吨位吊车,吊装完一侧的纵梁,再吊装另外一侧纵梁,纵梁吊装到位,先把每孔便梁的两头的钢枕与纵梁连接好,再进行其它钢枕连接、拼装。2) Hoist the longitudinal beam, park the large-tonnage crane on one side of the line, hoist the longitudinal beam on one side, and then hoist the longitudinal beam on the other side, and the longitudinal beam is hoisted in place. After the connection is completed, other steel sleepers are connected and assembled.
3)将钢枕与D型便梁的纵梁连接成整体架设完毕后,逐渐抬高纵梁,让纵梁缓慢受力,使铁路线路承重于纵梁上。在抬高纵梁时,现场技术人员进行抄平控制,控制纵梁四角高程一致性及施工地段轨道线路的平顺性。3) After connecting the steel sleeper and the longitudinal beam of the D-type facilitation beam as a whole, gradually raise the longitudinal beam, so that the longitudinal beam is slowly stressed, so that the railway line can bear the load on the longitudinal beam. When the longitudinal beam is raised, the on-site technicians perform leveling control to control the elevation consistency of the four corners of the longitudinal beam and the smoothness of the track line in the construction site.
本申请实施例提供了隧道暗挖施工的具体操作步骤,图5为本申请实施例提供的隧道的隧道暗挖施工步骤流程示意图。如图5所示,本申请实施例提供了隧道暗挖施工步骤包括:The embodiment of the present application provides specific operation steps of tunnel undercut construction, and FIG. 5 is a schematic flowchart of the tunnel undercover construction step of the tunnel provided by the embodiment of the present application. As shown in FIG. 5 , the embodiment of the present application provides tunnel excavation construction steps including:
步骤501:开挖准备,结合现场地质因素确定隧道开挖方式。Step 501: Prepare for excavation, and determine the tunnel excavation method in combination with the on-site geological factors.
采用全断面法、台阶法、中隔壁法、双侧壁导坑法的其中一种或几种组合;One or several combinations of the full-section method, the step method, the middle partition method, and the double-side wall guide pit method are adopted;
步骤502:路基、地基注浆,待路基、地基的注浆固化后,预留路基注浆小导管;Step 502 : grouting the roadbed and the foundation. After the grouting of the roadbed and the foundation is solidified, reserve a small conduit for grouting of the roadbed;
步骤503:隧道开挖,由施工竖井处开挖隧道,直至设计里程。Step 503: Tunnel excavation, excavating the tunnel from the construction shaft until the design mileage.
隧道开挖步骤包括隧道纵向施工及隧道横向施工,若采用台阶法施工,隧道纵向施工的掌子面需错开不小于3m的距离。而隧道横向施工步骤包括:The tunnel excavation steps include the longitudinal construction of the tunnel and the horizontal construction of the tunnel. If the step method is used for construction, the tunnel face in the longitudinal construction of the tunnel shall be staggered by a distance of not less than 3m. The horizontal construction steps of the tunnel include:
步骤504:初期支护施工,土体开挖完成后,进行初期支撑保护结构的施工及架设;Step 504: the initial support construction, after the soil excavation is completed, the construction and erection of the initial support and protection structure are carried out;
步骤505:防水层施工,在初期支护施工完成后进行防水层的敷设。Step 505 : waterproof layer construction, after the initial support construction is completed, the waterproof layer is laid.
防水层施工采用土工布做为缓冲层,防水卷材作为防水板,使用双焊缝铺设的方式进行铺设;The construction of the waterproof layer uses geotextile as the buffer layer, and the waterproof membrane is used as the waterproof board, which is laid by the method of double-weld laying;
步骤506:二次衬砌施工,防水层施工完成后进行二次衬砌施作。Step 506 : secondary lining construction, after the waterproof layer construction is completed, the secondary lining construction is carried out.
若采用台阶法施工,上台阶部分和下台阶部分需先后开挖,每部分开挖完成后即进行该部分的初期支护施工,防水层施工需从下而上,具体步骤为路基、地基注浆,待地基固化后,预留铁路路基注浆小导管→开挖上台阶部土体→进行上台阶部分的初期支护施工→开挖下台阶部土体,并施作下部初期支护封闭成环→敷设下部防水层→对下台阶部分施作二次衬砌→敷设上部防水层并施作上台阶部分二次衬砌→二次衬砌封闭成环,回填注浆。If the step method is used for construction, the upper step part and the lower step part need to be excavated successively. After the excavation of each part is completed, the initial support construction of this part will be carried out. The waterproof layer construction should be carried out from the bottom to the top. After the foundation is solidified, reserve a small grouting conduit for railway subgrade → excavate the soil at the upper step → carry out the initial support construction of the upper step → excavate the soil at the lower step, and apply the lower initial support to seal Forming a ring → laying the lower waterproof layer → applying secondary lining to the lower step portion → laying the upper waterproof layer and applying the secondary lining to the upper step portion → closing the secondary lining into a ring, backfilling and grouting.
进一步的,初期支护施工的步骤包括:Further, the steps of the initial support construction include:
初喷砼,隧道开挖完成后进行初喷混凝土;初喷砼需要在开挖完成后立即进行,以及时封闭、找平开挖面,防止围岩表面风化剥离脱落。The initial shotcrete, after the tunnel excavation is completed, the preliminary shotcrete; the preliminary shotcrete needs to be carried out immediately after the excavation is completed, and the excavation surface should be closed and leveled in time to prevent the surrounding rock surface from weathering and peeling off.
格栅钢架架设,初喷砼完成后紧贴初喷砼面架设格栅钢架;The grille steel frame is erected, and the grille steel frame is erected close to the initial sprayed concrete surface after the completion of the initial spraying concrete;
复喷砼,格栅钢架架设完成后复喷混凝土。复喷砼需要在型钢钢架施工完毕检验合格后进行,一次喷射砼厚度6~8cm,分3次喷至设计厚度。Re-sprayed concrete and re-sprayed concrete after the grid steel frame is erected. The re-sprayed concrete needs to be carried out after the construction of the section steel frame has passed the inspection. The thickness of the concrete is 6-8cm in one injection, and it is sprayed in 3 times to the design thickness.
进一步的,格栅钢架采用标准成品单元现场组装的方式进行架设,各成品单元之间采用连接筋焊接在一起,格栅钢架采用锁脚锚管定位并进行锚固,格栅钢架与初喷砼后形成的混凝土面的间隙使用混凝土块填充。Further, the grid steel frame is erected by on-site assembly of standard finished units. The finished units are welded together by connecting ribs. The grid steel frame is positioned and anchored by locking foot anchors. The gaps in the concrete surface formed after spraying concrete are filled with concrete blocks.
更进一步的,二次衬砌施工的步骤包括:底板钢筋绑扎、支底部模板、底板混凝土浇筑、侧墙及拱顶钢筋绑扎、支侧墙及拱顶模板、侧墙及拱顶混凝土浇筑、二衬背后回填注浆。各子步骤属于现有成熟技术,不再赘述。Further, the steps of the secondary lining construction include: binding of steel reinforcement for the bottom plate, formwork for the bottom support, concrete pouring for the bottom plate, binding of steel reinforcement for the side wall and the vault, formwork for the side wall and the vault, concrete pouring for the side wall and the vault, and secondary lining. Backfill grouting. Each sub-step belongs to the existing mature technology and will not be repeated here.
上述底部模板、侧墙及拱顶模板采用组合模板,二衬背后回填注浆步骤在底板混凝土、侧墙及拱顶混凝土达到设计强度后进行,二衬背后回填注浆步骤采用水泥浆进行注浆。The above-mentioned bottom formwork, side wall and vault formwork use combined formwork, the backfill grouting step of the secondary lining is carried out after the bottom concrete, side wall and vault concrete reach the design strength, and the backfill grouting step of the secondary lining is carried out with cement grout. .
图6为本申请实施例提供的隧道的清理以及验收步骤流程示意图,如图6所示,清理及验收步骤包括既有铁路设施恢复步骤,既有铁路设施恢复步骤包括:FIG. 6 is a schematic flowchart of the cleaning and acceptance steps of the tunnel provided by the embodiment of the present application. As shown in FIG. 6 , the cleaning and acceptance steps include the steps of restoring existing railway facilities, and the steps of restoring existing railway facilities include:
步骤601:既有铁路设施底部基础处理;Step 601: Treatment of the bottom of the existing railway facilities;
步骤602:D型便梁拆除;Step 602: Remove the D-shaped toilet beam;
步骤603:恢复既有铁路设施;Step 603: Restoring the existing railway facilities;
步骤604:清理现场、工程验收。Step 604: Clean up the site and check the project.
进一步的,既有铁路设施底部基础处理包括按照设计标高将既有铁路设施下方掏空;既有铁路设施下方浇筑混凝土,混凝土上方用水泥砂浆进行标高找平和/或既有铁路设施下方先浇筑混凝土垫层,混凝土垫层上方再浇筑钢筋混凝土基层,混凝土垫层及混凝土基层的宽度均大于既有铁路设施的宽度。Further, the foundation treatment for the bottom of the existing railway facilities includes hollowing out the bottom of the existing railway facilities according to the design elevation; pouring concrete under the existing railway facilities, using cement mortar for leveling above the concrete and/or pouring concrete under the existing railway facilities first Cushion, reinforced concrete base is poured above the concrete cushion, and the width of the concrete cushion and the concrete base is larger than the width of the existing railway facilities.
以既有铁路平交道口处下穿浅埋暗挖隧道为例,在清理以及验收步骤中需要重新安装道口板及道口板平台,具体操作流程为:道口板及道口平台底基础处理→D型便梁5下方线路拆除→拆除D型便梁5→安装道口板→铁路轨道铺设复原→铺设道口平台。Taking the existing railway level crossing under the shallow buried tunnel as an example, the crossing slab and the crossing slab platform need to be re-installed in the cleaning and acceptance steps. The specific operation process is: foundation treatment of the crossing slab and the crossing platform → D type Demolition of the line under the
在进行道口板及道口平台底基础处理时,需按照设计标高将道口板及道口平台下方掏空,期间完全由D型便梁5对地面铁路线路(即既有铁路设施)进行支撑,待安装道口板的下方掏空后浇筑C15混凝土,上方用水泥砂浆进行标高找平;道口平台下方浇筑C15垫层,垫层上方浇筑C35钢筋混凝土基层,垫层及基层均比道口平台宽出10cm。During the foundation treatment of the crossing slab and the bottom of the crossing platform, it is necessary to hollow out the crossing slab and the bottom of the crossing platform according to the design elevation. During this period, the ground railway line (that is, the existing railway facilities) is completely supported by the D-shaped
道口板及道口平台底基础处理完成,待混凝土达到一定强度后进行地面铁路线路拆除。先将原有钢轨锯断并抬出,然后将轨枕抬出。The crossing slab and the bottom of the crossing platform have been processed, and the ground railway line will be removed after the concrete reaches a certain strength. First cut off the original rail and lift it out, then lift out the sleeper.
原有钢轨拆除后进一步拆除D型便梁,D型便梁拆除按照钢便梁安装的相反顺序进行。After the original steel rail is removed, the D-type facilitation beam shall be further removed, and the removal of the D-type facilitation beam shall be carried out in the reverse order of the installation of the steel facilitation beam.
待安装的道口板由预制场提前1天运至现场,用吊车配合人工将道口板按设计位置及标高安装在水泥砂浆垫层上,安装时应保证道口板的平整,不出现翘角及悬空现象。The crossing slab to be installed shall be transported to the site from the
道口板安装完成后,进行铁路轨道铺设复原,将25m/根的50钢轨安装在道口板凹槽内并固定。After the installation of the crossing slab is completed, the railway track is laid and restored, and the 25m/piece 50 steel rail is installed in the groove of the crossing slab and fixed.
铁路轨道铺设复原完成后,将道口平台铺装在混凝土基层上,道口平台与道口板之间留3cm缝隙。安装时注意标高控制,保证道口板、道口平台及李天路的衔接处车辆能够平稳通过。After the railway track laying and restoration is completed, the crossing platform is paved on the concrete base, leaving a 3cm gap between the crossing platform and the crossing slab. During installation, pay attention to elevation control to ensure that vehicles can pass smoothly at the junction between the crossing board, the crossing platform and Litian Road.
全部恢复原状后进行最后验收。The final acceptance will be carried out after everything is restored to its original state.
在本申请的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本申请和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本申请的限制。In the description of this application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", " The orientation or positional relationship indicated by "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc. is based on the orientation shown in the drawings or The positional relationship is only for the convenience of describing the present application and simplifying the description, rather than indicating or implying that the indicated device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be construed as a limitation on the present application.
此外,术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征。在本申请的描述中,“多个”的含义是至少两个,例如两个,三个等,除非另有明确具体的限定。In addition, the terms "first" and "second" are only used for descriptive purposes, and should not be construed as indicating or implying relative importance or implying the number of indicated technical features. Thus, a feature defined as "first" or "second" may expressly or implicitly include one or more of that feature. In the description of the present application, "plurality" means at least two, such as two, three, etc., unless expressly and specifically defined otherwise.
在本申请中,除非另有明确的规定和限定,术语“安装”、“相连”、“连接”、“固定”等术语应做广义理解,例如,可以是固定连接,也可以是可拆卸连接,或成一体;可以是机械连接,也可以是电连接或可以互相通讯;可以是直接相连,也可以通过中间媒介间接相连,可以是两个元件内部的连通或两个元件的相互作用关系。对于本领域的普通技术人员而言,可以根据具体情况理解上述术语在本申请中的具体含义。In this application, unless otherwise expressly specified and limited, the terms "installed", "connected", "connected", "fixed" and other terms should be understood in a broad sense, for example, it may be a fixed connection or a detachable connection It can be a mechanical connection, an electrical connection or can communicate with each other; it can be directly connected, or it can be indirectly connected through an intermediate medium, it can be the internal communication between two elements or the interaction relationship between the two elements. For those of ordinary skill in the art, the specific meanings of the above terms in this application can be understood according to specific situations.
尽管已描述了本申请的优选实施例,但本领域内的技术人员一旦得知了基本创造性概念,则可对这些实施例作出另外的变更和修改。所以,所附权利要求意欲解释为包括优选实施例以及落入本申请范围的所有变更和修改。Although the preferred embodiments of the present application have been described, additional changes and modifications to these embodiments may occur to those skilled in the art once the basic inventive concepts are known. Therefore, the appended claims are intended to be construed to include the preferred embodiment and all changes and modifications that fall within the scope of this application.
显然,本领域的技术人员可以对本申请进行各种改动和变型而不脱离本申请的精神和范围。这样,倘若本申请的这些修改和变型属于本申请权利要求及其等同技术的范围之内,则本申请也意图包含这些改动和变型在内。Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.
Claims (14)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210521374.2A CN114856616B (en) | 2022-05-13 | 2022-05-13 | A tunnel construction method and reinforced protective structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210521374.2A CN114856616B (en) | 2022-05-13 | 2022-05-13 | A tunnel construction method and reinforced protective structure |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114856616A true CN114856616A (en) | 2022-08-05 |
CN114856616B CN114856616B (en) | 2025-03-11 |
Family
ID=82636569
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210521374.2A Active CN114856616B (en) | 2022-05-13 | 2022-05-13 | A tunnel construction method and reinforced protective structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114856616B (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101244257B1 (en) * | 2012-11-14 | 2013-03-18 | 주식회사 성우사면 | Method for digging tunnel |
CN107542470A (en) * | 2017-08-30 | 2018-01-05 | 中铁三局集团有限公司 | Existing railway Business Line construction method is worn under the shallow tunnel of karst broken region |
CN109989767A (en) * | 2019-01-17 | 2019-07-09 | 中铁二院贵阳勘察设计研究院有限责任公司 | The ruggedized construction and construction method of existing railway are worn under Large span tunnel |
CN111139721A (en) * | 2020-01-16 | 2020-05-12 | 中铁第五勘察设计院集团有限公司 | Frame bridge penetrating existing railway bridge downwards and construction method thereof |
CN111749704A (en) * | 2019-03-29 | 2020-10-09 | 中铁第五勘察设计院集团有限公司 | Protective device for railway level crossing construction |
WO2020224233A1 (en) * | 2019-05-05 | 2020-11-12 | 济南轨道交通集团有限公司 | Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner |
CN113293665A (en) * | 2021-06-02 | 2021-08-24 | 新疆铁道勘察设计院有限公司 | Roadbed reinforcing method for long side of railway bridge and culvert connection |
CN114411761A (en) * | 2022-02-28 | 2022-04-29 | 甘肃第七建设集团股份有限公司 | Advanced pre-support system for planned subway tunnel during construction of newly-built building and pre-support construction method |
-
2022
- 2022-05-13 CN CN202210521374.2A patent/CN114856616B/en active Active
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR101244257B1 (en) * | 2012-11-14 | 2013-03-18 | 주식회사 성우사면 | Method for digging tunnel |
CN107542470A (en) * | 2017-08-30 | 2018-01-05 | 中铁三局集团有限公司 | Existing railway Business Line construction method is worn under the shallow tunnel of karst broken region |
CN109989767A (en) * | 2019-01-17 | 2019-07-09 | 中铁二院贵阳勘察设计研究院有限责任公司 | The ruggedized construction and construction method of existing railway are worn under Large span tunnel |
CN111749704A (en) * | 2019-03-29 | 2020-10-09 | 中铁第五勘察设计院集团有限公司 | Protective device for railway level crossing construction |
WO2020224233A1 (en) * | 2019-05-05 | 2020-11-12 | 济南轨道交通集团有限公司 | Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner |
CN111139721A (en) * | 2020-01-16 | 2020-05-12 | 中铁第五勘察设计院集团有限公司 | Frame bridge penetrating existing railway bridge downwards and construction method thereof |
CN113293665A (en) * | 2021-06-02 | 2021-08-24 | 新疆铁道勘察设计院有限公司 | Roadbed reinforcing method for long side of railway bridge and culvert connection |
CN114411761A (en) * | 2022-02-28 | 2022-04-29 | 甘肃第七建设集团股份有限公司 | Advanced pre-support system for planned subway tunnel during construction of newly-built building and pre-support construction method |
Non-Patent Citations (3)
Title |
---|
张彬;: "浅埋暗挖大跨隧道下穿既有铁路施工安全分析", 市政技术, no. 05, 10 September 2012 (2012-09-10) * |
田鹏;: "富水粉细砂地层下穿既有铁路顶管隧道设计与施工", 铁道建筑, no. 06, 20 June 2017 (2017-06-20) * |
郅建国;夏正茂;陈兵;: "不同防护措施下盾构下穿施工对既有桥梁结构物的影响研究", 交通节能与环保, no. 06, 15 December 2019 (2019-12-15) * |
Also Published As
Publication number | Publication date |
---|---|
CN114856616B (en) | 2025-03-11 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
WO2021223573A1 (en) | Construction structure for communication and connection between newly added mined channel and existing station hall layer | |
US9322137B2 (en) | Method for building structures, particularly passages under operating railways or the like | |
JP7394252B1 (en) | Protruding type wind duct structure perpendicular to the vertical direction and construction method at deep subway station | |
CN105201516B (en) | A kind of main structure of subway station and its tetrad arch PBA excavating construction methods | |
CN104018405A (en) | Pile-anchor-frame composite double-layer roadbed structure | |
CN211144503U (en) | High steep topography bridge tunnel meets section open cut tunnel and connects long structure | |
CN110486036B (en) | A kind of construction method of expanding arch foot initial support arch cover method | |
Paul et al. | Comparative study of construction technologies for underground metro stations in India | |
CN115450221B (en) | Construction method for subway crossing river channel | |
CN114922200B (en) | Existing-newly-built combined retaining structure of wide road embankment and construction method | |
CN110486062B (en) | Method for mechanically underground excavating multi-layer multi-span underground engineering in soft soil | |
US12123157B1 (en) | Delaminated subway station structure in sea-land connection region and construction method thereof | |
CN108708290A (en) | The case crane span structure hollow structure and cast-in-situ construction method of minor radius railway curve unit | |
CN108978673A (en) | A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning | |
CN113005918A (en) | Method for constructing large-span frame bridge by high filling of multi-strand railway in protective railway station | |
Hulme et al. | SINGAPORE MASS RAPID TRANSIT SYSTEM: CONSTRUCTION. | |
CN113898007B (en) | Semi-inverse construction method for long-span corridor structure along street | |
CN110700116A (en) | Overpass reverse construction method suitable for loess area | |
CN215906845U (en) | Large-span vestibule mounting structure in foundation pit | |
CN114856616B (en) | A tunnel construction method and reinforced protective structure | |
CN113389218A (en) | Retaining wall structure for entrance and exit of road bridge and construction method thereof | |
CN105714856A (en) | Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up | |
CN117189189B (en) | Dark-cover excavation half reverse construction method for cross transfer subway station | |
CN219343473U (en) | Cross-street corridor mounting structure | |
CN216043718U (en) | For power system interchange tunnel structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |