CN105714856A - Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up - Google Patents

Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up Download PDF

Info

Publication number
CN105714856A
CN105714856A CN201610277119.2A CN201610277119A CN105714856A CN 105714856 A CN105714856 A CN 105714856A CN 201610277119 A CN201610277119 A CN 201610277119A CN 105714856 A CN105714856 A CN 105714856A
Authority
CN
China
Prior art keywords
layer
arch
negative
pilot tunnel
carried out
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610277119.2A
Other languages
Chinese (zh)
Inventor
胡少斌
张立平
马海燕
张元春
赵富壮
李晓文
马宁
马乐
边宁宁
崔红波
陈伟
谢校亭
张文慧
宋少奇
刘辉
刘雪峰
孟海港
杨帆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Urban and Rural Construction Group Co Ltd
Original Assignee
Beijing Urban and Rural Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Urban and Rural Construction Group Co Ltd filed Critical Beijing Urban and Rural Construction Group Co Ltd
Priority to CN201610277119.2A priority Critical patent/CN105714856A/en
Publication of CN105714856A publication Critical patent/CN105714856A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water

Abstract

The invention relates to an underground air duct construction method with a first negative structural layer and a second negative structural layer in bottom-up. According to the technique, the underground air duct construction method comprises the steps that firstly, pilot tunnels in the two sides of an air duct are constructed, drilling and cast-in-place pile construction are carried out on the interiors of the pilot tunnels, earth excavation is carried out on the arch portion of a middle pilot tunnel, after the arch portion of the middle pilot tunnel is preliminarily supported, earth excavation to a middle layer plate is carried out, and the middle layer plate, a side wall of the first negative layer, and a top arch (buckling arch) are constructed. Layered earth excavation is carried out on the middle plate position to the downward position, erecting and supporting are carried out, and after earth excavation to the bottom of a foundation pit is carried out, a bottom plate and the side wall of the second negative layer are constructed from bottom to top. The construction sequence that a whole body is inversely carried out, and the first negative structural layer and the second negative structural layer are arranged in bottom-up is adopted, defects of complete bottom-up operation and complete inverse operation can be overcome, and meanwhile, beneficial effects of complete bottom-up operation and complete inverse operation are kept.

Description

A kind of structure is born one layer and bears two layers respectively along the ventilation passage of metro methods of construction made
[technical field]
The present invention relates to a kind of ventilation passage of metro method of construction, be specifically related to a kind of structure and bear one layer and bear two layers respectively along the ventilation passage of metro methods of construction made, belong to city track traffic engineering technical field.
[background technology]
Ventilation passage of metro structure generally all adopts double-decker pattern, when adopting cavern-pile method to build ventilation passage of metro structure, conventional sequence of construction has two kinds, one, adopt completely along the practice, that is: first completing excavation and the preliminary bracing of Zhong Dong arch, then earth excavation is to structure base slab from top to bottom, then the structure completing base plate, negative two layers of side wall, middle plate and negative one layer of side wall from bottom to top is built;They are two years old, complete contrary sequence method, that is: excavation and the preliminary bracing of Zhong Dong arch are first completed, then arch two lining structure is built, the negative one layer of earthwork of excavation from top to bottom again, build negative one layer of side wall and middle plate, then support from the downward stage excavation earthwork of middle Board position, erection, earth excavation is to after bottom foundation ditch, building negative two layers of side wall and base plate.
The advantage of the completely suitable practice of employing is: easy construction, structurally waterproof is continuous, shortcoming is: in the construction stage, preliminary bracing structural requirement in Zhong Dong arch undertakes whole external load, is unfavorable for stablizing of preliminary bracing;The advantage adopting complete contrary sequence method is: arch preliminary bracing and the common bearing load of secondary lining, is conducive to stablizing of arch preliminary bracing.Shortcoming is: along with the excavation of the earthwork, the load that arch two lining structure bears is in and constantly adjusts and in change, may result in two lining structure crackings, being unfavorable for waterproof and the durability of structure, another drawback is: during two lining arch springing constructions, the reinforcing bar that arch springing reinforcing bar throws away with limit pilot tunnel fender post to be connected, cause going out at arch springing, splash guard can not continuous laying, arch springing waterproof is discontinuous, is unfavorable for the waterproof of structure.
Therefore, for solving above-mentioned technical problem, the structure of a kind of innovation of necessary offer is born one layer and bears two layers respectively along the ventilation passage of metro methods of construction made, to overcome described defect of the prior art.
[summary of the invention]
For solving the problems referred to above, it is an object of the invention to provide a kind of structure bear one layer and bear two layers respectively along the ventilation passage of metro methods of construction made, it adopts the sequence of construction of " entirety is inverse to be made; bears a layer and bears two layers respectively along making ", the shortcoming that can avoid all-cis work and full-reverse, meanwhile, its advantage is remained again.
For achieving the above object, the technical scheme that the present invention takes is: a kind of structure is born one layer and bears two layers respectively along the ventilation passage of metro methods of construction made, and it includes following construction procedure:
1), per-fore pouring liquid with small pipe strengthening stratum;Joint reserved by pilot tunnel steelframe;
2), after having propped up at the beginning of little pilot tunnel, fall back drilling stake from inside to outside, applies an apical cap beam;
3), in pilot tunnel, apply main body arch grid steel frame arch springing, longitudinal pitch 0.5m, be connected with the reserved joint of pilot tunnel steelframe.
4), arch springing and space, behind thereof in formwork erection backfill pilot tunnel;
5), section arch, air channel per-fore pouring liquid with small pipe strengthening stratum, the excavation arch soil body, erection arch grid steel frame, apply preliminary bracing;
6), after at the beginning of arch springing fill concrete and main arch reaches design strength, removing interim perpendicular support, the excavation soil body is to middle plate downwards, removes pilot tunnel grid steel frame within the scope of permanent structure section;
7), lay abutment wall, arch waterproof layer, apply two linings in time, close cyclization, reserved abutment wall reinforcing bar for negative one layer.
8), the excavation soil body is to the lower 0.5m absolute altitude of steel pipe support downwards, sprays 50mm thickness C20 concrete leveling between stake;
9), the excavation soil body is continued to substrate absolute altitude, pneumatically placed concrete between stake, apply bottom cushion;
10), lay air channel base plate waterproofing and pea gravel concreten protective layer, build base plate and part abutment wall;
11), treat that base plate reaches some strength, jump and tear steel pipe support open, lay negative two layers of side wall waterproof layer, build side wall concrete and connect with upper strata abutment wall;
12), performing air channel internal structure, air channel civil engineering completes.
Negative one layer and negative two layers of the structure of the present invention along the ventilation passage of metro method of construction made is respectively further: in step 1), spacing out before and after two little pilot tunnel constructions, spacing is not less than 10m, and little pilot tunnel adopts benching tunnelling method construction, step pitch 0.5m, C20 gunite concrete.
Negative one layer and negative two layers of the structure of the present invention along the ventilation passage of metro method of construction made is respectively further: step 2) in, drilled pile is jumped and is done, and in stake, reinforcing bar throws away reserved.
Negative one layer and negative two layers of the structure of the present invention along the ventilation passage of metro method of construction made is respectively further: in step 5), arrange interim perpendicular support if desired.
Negative one layer of the structure of the present invention with negative two layers along the ventilation passage of metro method of construction made is respectively further: in step 8), stake back-grouting is reinforced if desired, sets up waist rail and steel pipe support.
Compared with prior art, there is advantages that
(1) negative one layer and negative two layers all adopts along practice construction, can ensure that structurally waterproof is continuous, and structurally waterproof is effective;
(2) after the arch preliminary bracing structure of negative a layer is formed, the space of negative one layer of remainder is less, digs the level of disruption to arch preliminary bracing structure less;And when excavation is to after middle Board position, beginning to apply two lining structures of negative a layer, it is possible to by the tau-effect reduction to the degree that has the greatest impact of arch preliminary bracing.
(3) owing to, before negative two layers of earth excavation, negative one layer has formed closure frame structure, and stress performance is good, negative two layers of disturbance brought of constructing can be born preferably.
[accompanying drawing explanation]
Fig. 1 is the construction procedure 1 of the present invention) schematic diagram.
Fig. 2 is the construction procedure 2 of the present invention) schematic diagram.
Fig. 3 is the construction procedure 3 of the present invention) schematic diagram.
Fig. 4 is the construction procedure 4 of the present invention) schematic diagram.
Fig. 5 is the construction procedure 5 of the present invention) schematic diagram.
Fig. 6 is the construction procedure 6 of the present invention) schematic diagram.
Fig. 7 is the construction procedure 7 of the present invention) schematic diagram.
Fig. 8 is the construction procedure 8 of the present invention) schematic diagram.
Fig. 9 is the construction procedure 9 of the present invention) schematic diagram.
Figure 10 is the construction procedure 10 of the present invention) schematic diagram.
Figure 11 is the construction procedure 11 of the present invention) schematic diagram.
Figure 12 is the construction procedure 12 of the present invention) schematic diagram.
[detailed description of the invention]
Referring to shown in Figure of description 1 to accompanying drawing 12, the present invention is that a kind of structure is born one layer and bears two layers respectively along the ventilation passage of metro methods of construction made, and it includes following construction procedure:
1), as it is shown in figure 1, advanced tubule 1 Grouting Consolidation, spacing out before and after two little pilot tunnel 2 constructions, spacing is not less than 10m, and little pilot tunnel adopts benching tunnelling method construction, and step pitch 0.5m, C20 gunite concrete, joint 3 reserved by pilot tunnel steelframe.
2), as in figure 2 it is shown, after having propped up at the beginning of little pilot tunnel 2, fall back drilling stake 4 from inside to outside, applies an apical cap beam 5, and (stake footpath φ 800, φ 1000, spacing 1.2m, 1.5m), drilled pile should be jumped and be done.In stake, reinforcing bar throws away reserved.
3), as it is shown on figure 3, apply main body arch grid steel frame arch springing 6 in pilot tunnel, longitudinal pitch 0.5m, it is connected with the reserved joint 3 of pilot tunnel steelframe.
4), as shown in Figure 4, formwork erection backfills arch springing and space, behind thereof in 7 pilot tunnels.
5), as it is shown in figure 5, section arch, air channel per-fore pouring liquid with small pipe strengthening stratum 8, the excavation arch soil body, erection arch grid steel frame, apply preliminary bracing 9, interim perpendicular support 10 is set if desired.
6), as shown in Figure 6, after at the beginning of arch springing fill concrete and main arch 9 reaches design strength, remove interim perpendicular support 10, the excavation soil body is to certain distance under middle plate downwards, removes pilot tunnel grid steel frame within the scope of permanent structure section, and pilot tunnel grid is longitudinally removed length and strictly should be controlled according to monitoring measurement.
7), as it is shown in fig. 7, lay abutment wall, arch waterproof layer, apply two linings 11 in time, close cyclization, reserved abutment wall reinforcing bar 12 for negative one layer.
8), as shown in Figure 8, excavating downwards the soil body and support 13 times 0.5m absolute altitudes to steel pipe, spray 50mm thickness C20 concrete leveling between stake, stake back-grouting is reinforced if desired, and erection waist rail and steel pipe support.
9), as it is shown in figure 9, continue the excavation soil body to substrate absolute altitude, pneumatically placed concrete between stake, apply bottom cushion 14.
10), as shown in Figure 10, lay air channel base plate waterproofing and pea gravel concreten protective layer, build base plate 15 and part abutment wall 16.
11), as shown in figure 11, treat that base plate 15 reaches some strength, jump and tear steel pipe support open, lay negative two layers of side wall waterproof layer, build side wall concrete 17 and connect with upper strata abutment wall.
12), as shown in figure 12, performing air channel internal structure 18, air channel civil engineering completes.
Above detailed description of the invention is only the preferred embodiment of this creation, not in order to limit this creation, and any amendment of making within all spirit in this creation and principle, equivalent replacement, improvement etc., should be included within the protection domain of this creation.

Claims (5)

1. a structure is born one layer and bears two layers respectively along the ventilation passage of metro methods of construction made, it is characterised in that: include following construction procedure:
1), per-fore pouring liquid with small pipe strengthening stratum;Joint reserved by pilot tunnel steelframe;
2), after having propped up at the beginning of little pilot tunnel, fall back drilling stake from inside to outside, applies an apical cap beam;
3), in pilot tunnel, apply main body arch grid steel frame arch springing, longitudinal pitch 0.5m, be connected with the reserved joint of pilot tunnel steelframe;
4), arch springing and space, behind thereof in formwork erection backfill pilot tunnel;
5), section arch, air channel per-fore pouring liquid with small pipe strengthening stratum, the excavation arch soil body, erection arch grid steel frame, apply preliminary bracing;
6), after at the beginning of arch springing fill concrete and main arch reaches design strength, removing interim perpendicular support, the excavation soil body is to middle plate downwards, removes pilot tunnel grid steel frame within the scope of permanent structure section;
7), lay abutment wall, arch waterproof layer, apply two linings in time, close cyclization, reserved abutment wall reinforcing bar for negative one layer;
8), the excavation soil body is to the lower 0.5m absolute altitude of steel pipe support downwards, sprays 50mm thickness C20 concrete leveling between stake;
9), the excavation soil body is continued to substrate absolute altitude, pneumatically placed concrete between stake, apply bottom cushion;
10), lay air channel base plate waterproofing and pea gravel concreten protective layer, build base plate and part abutment wall;
11), treat that base plate reaches some strength, jump and tear steel pipe support open, lay negative two layers of side wall waterproof layer, build side wall concrete and connect with upper strata abutment wall;
12), performing air channel internal structure, air channel civil engineering completes.
2. structure as claimed in claim 1 negative one layer and negative two layers respectively along the ventilation passage of metro methods of construction made, it is characterised in that: in step 1), space out before and after two little pilot tunnels constructions, spacing is not less than 10m, little pilot tunnel adopts benching tunnelling method construction, step pitch 0.5m, C20 gunite concrete.
3. structure as claimed in claim 1 is born one layer and bears two layers respectively along the ventilation passage of metro methods of construction made, it is characterised in that: step 2) in, drilled pile jumping is done, and in stake, reinforcing bar throws away reserved.
4. structure as claimed in claim 1 is born one layer and bears two layers respectively along the ventilation passage of metro methods of construction made, it is characterised in that: in step 5), temporarily perpendicular support is set if desired.
5. structure as claimed in claim 1 is born one layer and bears two layers respectively along the ventilation passage of metro methods of construction made, it is characterised in that: in step 8), stake back-grouting reinforcing if desired, erection waist rail and steel pipe support.
CN201610277119.2A 2016-04-30 2016-04-30 Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up Pending CN105714856A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610277119.2A CN105714856A (en) 2016-04-30 2016-04-30 Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610277119.2A CN105714856A (en) 2016-04-30 2016-04-30 Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up

Publications (1)

Publication Number Publication Date
CN105714856A true CN105714856A (en) 2016-06-29

Family

ID=56161867

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610277119.2A Pending CN105714856A (en) 2016-04-30 2016-04-30 Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up

Country Status (1)

Country Link
CN (1) CN105714856A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110005420A (en) * 2019-05-21 2019-07-12 成都市建筑设计研究院 A kind of ledge tunneling is inverse to build underground structure and construction method
CN110017149A (en) * 2019-05-21 2019-07-16 成都市建筑设计研究院 A kind of ledge tunneling is suitable to build underground structure and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03279600A (en) * 1990-03-29 1991-12-10 Hazama Gumi Ltd Construction method of large cavity
CN103821167A (en) * 2014-03-17 2014-05-28 北京市政建设集团有限责任公司 Construction method for subway station body
CN204457786U (en) * 2015-02-04 2015-07-08 北京市政建设集团有限责任公司 The large diameter shield tunnel that digs after the dismounting of a kind of B section of jurisdiction builds subway station

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH03279600A (en) * 1990-03-29 1991-12-10 Hazama Gumi Ltd Construction method of large cavity
CN103821167A (en) * 2014-03-17 2014-05-28 北京市政建设集团有限责任公司 Construction method for subway station body
CN204457786U (en) * 2015-02-04 2015-07-08 北京市政建设集团有限责任公司 The large diameter shield tunnel that digs after the dismounting of a kind of B section of jurisdiction builds subway station

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110005420A (en) * 2019-05-21 2019-07-12 成都市建筑设计研究院 A kind of ledge tunneling is inverse to build underground structure and construction method
CN110017149A (en) * 2019-05-21 2019-07-16 成都市建筑设计研究院 A kind of ledge tunneling is suitable to build underground structure and construction method

Similar Documents

Publication Publication Date Title
CN106337686A (en) Rock stratum underground excavation three-story subway station umbrella cover structure and construction method thereof
CN106703814A (en) Mined metro station hole pile construction method
CN204729099U (en) Rock quality layer tunneling three layers of subway station canopy structure
CN106567718A (en) Construction method for composite stratum single-arch super long-span subway station through groove broaching and support substitution
CN108589771A (en) One kind having runed underground station increasing layer transfer node construction method
Paul et al. Comparative study of construction technologies for underground metro stations in India
CN112575670B (en) T-shaped rigid frame bridge suitable for tunnel to pass through giant karst cave and construction technology thereof
CN204457792U (en) A kind ofly dig large diameter shield tunnel with many pilot tunnel methods and the subway station of building
CN107288642A (en) PBA construction technologies
CN107795749A (en) A kind of precast spliced pipe fitting jacking system and its construction method
CN105736001A (en) Construction method for building subway station through precast parts
CN110486036B (en) Construction method for expanding arch foot primary support arch cover method
CN105201516A (en) Subway station body structure and four-joint-arch PBA underground excavation construction method thereof
CN102410031B (en) Underground space structure constructed by pile wall construction method
JP7394252B1 (en) Protruding type wind duct structure perpendicular to the vertical direction and construction method at deep subway station
CN104632245A (en) Method using multi-pilot-tunnel expanding excavation large-diameter shield tunnel for building subway station
CN109958445A (en) The frame construction method in Large Underground space is buried for an ultra shallow
CN110847915A (en) Construction process for jumping-cutting demolishing and subsection back-jacking of double-side-wall temporary support of shallow-buried fine sand layer
CN205036380U (en) Block of four encircles PBA and secretly digs subway station major structure
CN101153494A (en) Underground beam-pile frame construction for reinforcing side slope
CN108978673A (en) A kind of foundation pit supporting construction and construction method of viaduct pile foundation underpinning
CN105714856A (en) Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up
CN105386779A (en) Arch column method for building large-scale underground structure in shallow buried rock stratums
CN110486062B (en) Method for mechanically underground excavating multi-layer multi-span underground engineering in soft soil
CN112627002B (en) Continuous beam bridge suitable for tunnel to pass through giant karst cave and construction technical method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20160629

WD01 Invention patent application deemed withdrawn after publication