CN103821167A - Construction method for subway station body - Google Patents
Construction method for subway station body Download PDFInfo
- Publication number
- CN103821167A CN103821167A CN201410095835.XA CN201410095835A CN103821167A CN 103821167 A CN103821167 A CN 103821167A CN 201410095835 A CN201410095835 A CN 201410095835A CN 103821167 A CN103821167 A CN 103821167A
- Authority
- CN
- China
- Prior art keywords
- pilot tunnel
- excavation
- construction
- station
- concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
The invention relates to a construction method for a subway station body. The construction method includes the following steps that pilot tunnels are excavated, and primary support is constructed; after cutthrough of each lower pilot tunnel, a strip-shaped foundation of each lower side pilot tunnel is constructed; pile top beams and large arch springings are constructed on the upper layer side pilot tunnels in a moulding mode; the inner side of the upper layer middle pilot tunnel is reinforced through a top longitudinal beam, a ground layer is reinforced through preliminary grouting in advance, and a soil body part I is excavated symmetrically left and right; a soil body part II is symmetrically excavated, and arch primary support is constructed; after cutthrough of the primary support, a medium partition, a waterproof plate and a protective layer are cut off in a segment mode through an inverted supporting method; excavation is downwards performed in a layered mode in the longitudinal direction of a subway station to the bottom elevation of a station hall plate; after medium plate concrete reaches design strength, excavation is downwards performed in a layered mode by 3.5 m along the longitudinal direction of the station; slope excavation is longitudinally performed downwards in a layered and segment mode to the position of 370 mm below the bottom elevation of the station hall plate according to the scale of 1:1, a thick section steel sprayed mixed cushion layer, a waterproof layer and a waterproof protective layer are constructed; a side wall waterproof layer is laid, and side wall concrete is poured; an inner structure is constructed to finish structure construction of the station. The construction method has the advantages of being high in efficiency, short in construction period, safe in construction and the like.
Description
[technical field]
The present invention relates to a kind of architecture construction method, be specifically related to the construction method of a kind of subway station main body, belong to technical field of civil engineering.
[background technology]
The subway station main body of prior art mainly adopts the construction of hole stake method, and its overall sequence of construction is as follows:
1. in transverse passage-way, complete preliminary bracing button arch and the strengthening measure of agent structure, make the Path of Force Transfer of transverse passage-way by top board-side wall-base plate-stratum, be converted to transverse passage-way top board-agent structure preliminary bracing top board-Guan Liang and top longeron-steel core concrete column and skirt piles-bottom girder and bar base-stratum.
2. encircle to start agent structure preliminary bracing button away from transverse passage-way direction from transverse passage-way, and pilot tunnel side wall must not cut; From termination, station or two transverse passage-way centre positions start agent structure two lining button arch to transverse passage-way direction, when button arch, the segmentation of pilot tunnel side wall is removed, section length be a post across.
3. just lining button arched girder across the construction simultaneously of should try one's best, if symmetrical construction at need excavation face stagger and should be less than 3~5m, just lining button carries out two lining buttons and encircles and construct after encircle; After two lining buttons have encircleed, can be from top to bottom earth excavation successively.
The construction method of above-mentioned subway station main body exists following defect: long construction period, and efficiency is low, and security risk control is poor.
Therefore,, for solving the problems of the technologies described above, the necessary construction method that a kind of subway station main body is provided, to overcome described defect of the prior art.
[summary of the invention]
For addressing the above problem, the object of the present invention is to provide a kind of efficiency high, the construction method of the subway station main body of short and construction safety of duration.
For achieving the above object, the technical scheme that the present invention takes is: the construction method of a kind of subway station main body, and it comprises following processing step:
1), pre-Grouting Consolidation, excavation pilot tunnel, and apply preliminary bracing; Excavation is when pilot tunnel, and the first upper pilot tunnel of excavation after the lower pilot tunnel of excavation first excavates after the pilot tunnel of limit pilot tunnel in excavation;
2),, after lower pilot tunnel connects, retreat and apply strip foundation in following pilot tunnel; On top in pilot tunnel, apply skirt piles, between skirt piles outside and pilot tunnel, adopt C20 concrete backfill; In middle pilot tunnel, construct steel core concrete column borehole retaining wall between upper and lower pilot tunnel and bottom girder under middle standing pillar;
3), limit, upper strata pilot tunnel mould is built an apical cap beam and large arch springing, itself and top pilot tunnel is just propped up and skirt piles formation overall structure; In middle pilot tunnel, apply steel pipe column, top longeron, reserved steel bar and water joint;
4), side direction is reinforced top longeron in the pilot tunnel of upper strata, leading pre-Grouting Consolidation, and the symmetrical excavation I portion soil body, applies arch preliminary bracing and median septum, inverted arch;
5), after the leading 15m of I portion soil excavation, the symmetrical II portion soil body that excavates, applies arch preliminary bracing;
6.), after first Zhi Guantong, median septum is removed in 4~6m segmentation, and one-time-concreting concrete roof, reaches after design strength until the preceding paragraph concrete, carries out that next section of median septum is blocked and top board is built;
7), reach after design strength until vault concrete, longitudinal layeredly along station be excavated to absolute altitude at the bottom of subway concourse plate downwards; Segmentation applies topotype, lays side wall waterproofing course, builds middle plated construction, station hall layer side wall;
8), middle board concrete reaches after design strength, the longitudinal layered downward excavation 3.5m along station;
9), segmentation is put under slope aspect and is excavated to 370mm under floor level for longitudinal 1: 1, executes in time the mixed bed course of the thick shaped steel spray of 300mm, and construction waterproof layer and fish tail and waterproof layer, build base plate two linings in time; Lay side wall waterproofing course, build side wall concrete;
10), concrete reaches after design strength, and construction internal construction completes station structure construction.
The construction method of subway station of the present invention main body is further: described step 1) in, benching tunnelling method excavation pilot tunnel adopted.
The construction method of subway station of the present invention main body is further: described step 2) in, skirt piles need excavated by manual work stake to jump hole construction, dig one every three.
The construction method of subway station of the present invention main body also can be: described step 4) in, adopt the symmetrical excavation of the CD method I portion soil body, in shoveling process, do not remove pilot tunnel abutment wall.
Compared with prior art, the present invention has following beneficial effect: it is high that the construction method of subway station of the present invention main body has efficiency, the plurality of advantages such as short and construction safety of duration.
[accompanying drawing explanation]
Fig. 1 is the construction method step 1 of subway station of the present invention main body) schematic diagram.
Fig. 2 is the construction method step 2 of subway station of the present invention main body) schematic diagram.
Fig. 3 is the construction method step 3 of subway station of the present invention main body) schematic diagram.
Fig. 4 is the construction method step 4 of subway station of the present invention main body) schematic diagram.
Fig. 5 is the construction method step 5 of subway station of the present invention main body) schematic diagram.
Fig. 6 is the construction method step 6 of subway station of the present invention main body) schematic diagram.
Fig. 7 is the construction method step 7 of subway station of the present invention main body) schematic diagram.
Fig. 8 is the construction method step 8 of subway station of the present invention main body) schematic diagram.
Fig. 9 is the construction method step 9 of subway station of the present invention main body) schematic diagram.
Figure 10 is the construction method step 10 of subway station of the present invention main body) schematic diagram.
[specific embodiment]
The present invention is the construction method of a kind of subway station main body, and it comprises following processing step:
1), by the pre-Grouting Consolidation of advanced tubule 1, excavation pilot tunnel 2, and apply preliminary bracing; Excavation is when pilot tunnel, and the first upper pilot tunnel of excavation after the lower pilot tunnel of excavation first excavates after the pilot tunnel of limit pilot tunnel in excavation; Wherein, adopt benching tunnelling method excavation pilot tunnel;
2),, after lower pilot tunnel connects, retreat and apply strip foundation 3 in following pilot tunnel; On top in pilot tunnel, apply skirt piles 4, between skirt piles outside and pilot tunnel, adopt 5 backfills of C20 concrete; In middle pilot tunnel, construct steel core concrete column borehole retaining wall between upper and lower pilot tunnel and bottom girder 6 under middle standing pillar; Wherein, skirt piles need excavated by manual work stake to jump hole construction, dig one every three;
3), limit, upper strata pilot tunnel mould is built an apical cap beam 7 and large arch springing 8, itself and top pilot tunnel is just propped up and skirt piles formation overall structure; In middle pilot tunnel, apply steel pipe column 9, top longeron 10, reserved steel bar and water joint;
4), side direction is reinforced top longeron in the pilot tunnel of upper strata, leading pre-Grouting Consolidation, and the symmetrical excavation I portion soil body, applies arch preliminary bracing and median septum, inverted arch; Wherein adopt the symmetrical excavation of the CD method I portion soil body, in shoveling process, do not remove pilot tunnel abutment wall;
5), after the leading 15m of I portion soil excavation, the symmetrical II portion soil body that excavates, applies arch preliminary bracing;
6.), after first Zhi Guantong, median septum is removed in 4~6m segmentation, and one-time-concreting concrete roof 11, reaches after design strength until the preceding paragraph concrete, carries out that next section of median septum is blocked and top board is built;
7), reach after design strength until vault concrete, longitudinal layeredly along station be excavated to absolute altitude at the bottom of subway concourse plate downwards; Segmentation applies topotype, lays side wall waterproofing course, builds middle plated construction 12, station hall layer side wall 13;
8), middle board concrete reaches after design strength, the longitudinal layered downward excavation 3.5m along station;
9), segmentation is put under slope aspect and is excavated to 370mm under floor level for longitudinal 1: 1, the mixed bed course of the thick shaped steel spray of the 300mm that constructs in time, and construction waterproof layer and fish tail and waterproof layer, build in time base plate two and serve as a contrast 14; Lay side wall waterproofing course, build side wall concrete 15;
10), concrete reaches after design strength, and construction internal construction 16 completes station structure construction.
The above specific embodiment is only the preferred embodiment of this creation, not in order to limit this creation, any modification of making, is equal to replacement, improvement etc., within all should being included in the protection domain of this creation within all spirit in this creation and principle.
Claims (4)
1. a construction method for subway station main body, is characterized in that: comprise following processing step:
1), pre-Grouting Consolidation, excavation pilot tunnel, and apply preliminary bracing; Excavation is when pilot tunnel, and the first upper pilot tunnel of excavation after the lower pilot tunnel of excavation first excavates after the pilot tunnel of limit pilot tunnel in excavation;
2),, after lower pilot tunnel connects, retreat and apply strip foundation in following pilot tunnel; On top in pilot tunnel, apply skirt piles, between skirt piles outside and pilot tunnel, adopt C20 concrete backfill; In middle pilot tunnel, construct steel core concrete column borehole retaining wall between upper and lower pilot tunnel and bottom girder under middle standing pillar;
3), limit, upper strata pilot tunnel mould is built an apical cap beam and large arch springing, itself and top pilot tunnel is just propped up and skirt piles formation overall structure; In middle pilot tunnel, apply steel pipe column, top longeron, reserved steel bar and water joint;
4), side direction is reinforced top longeron in the pilot tunnel of upper strata, leading pre-Grouting Consolidation, and the symmetrical excavation I portion soil body, applies arch preliminary bracing and median septum, inverted arch;
5), after the leading 15m of I portion soil excavation, the symmetrical II portion soil body that excavates, applies arch preliminary bracing;
6), after first Zhi Guantong, median septum is removed in 4~6m segmentation, and one-time-concreting concrete roof, reaches after design strength until the preceding paragraph concrete, carries out that next section of median septum is blocked and top board is built;
7), reach after design strength until vault concrete, longitudinal layeredly along station be excavated to absolute altitude at the bottom of subway concourse plate downwards; Segmentation applies topotype, lays side wall waterproofing course, builds middle plated construction, station hall layer side wall;
8), middle board concrete reaches after design strength, the longitudinal layered downward excavation 3.5m along station;
9), segmentation is put under slope aspect and is excavated to 370mm under floor level for longitudinal 1: 1, the mixed bed course of the thick shaped steel spray of the 300mm that constructs in time, and construction waterproof layer and fish tail and waterproof layer, build base plate two linings in time; Lay side wall waterproofing course, build side wall concrete;
10), concrete reaches after design strength, and construction internal construction completes station structure construction.
2. the construction method of subway station as claimed in claim 1 main body, is characterized in that: described step 1) in, benching tunnelling method excavation pilot tunnel adopted.
3. the construction method of subway station as claimed in claim 1 main body, is characterized in that: described step 2) in, skirt piles need excavated by manual work stake to jump hole construction, dig one every three.
4. the construction method of subway station as claimed in claim 1 main body, is characterized in that: described step 4) in, adopt the symmetrical excavation of the CD method I portion soil body, in shoveling process, do not remove pilot tunnel abutment wall.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410095835.XA CN103821167A (en) | 2014-03-17 | 2014-03-17 | Construction method for subway station body |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410095835.XA CN103821167A (en) | 2014-03-17 | 2014-03-17 | Construction method for subway station body |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103821167A true CN103821167A (en) | 2014-05-28 |
Family
ID=50756435
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410095835.XA Pending CN103821167A (en) | 2014-03-17 | 2014-03-17 | Construction method for subway station body |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103821167A (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104120739A (en) * | 2014-08-11 | 2014-10-29 | 北京市政建设集团有限责任公司 | Multi-pilot tunnel excavation one-off arching construction method |
CN104806251A (en) * | 2015-04-27 | 2015-07-29 | 北京市轨道交通建设管理有限公司 | Subsidiary inverted excavation construction method for urban subway station under complex environment |
CN105714856A (en) * | 2016-04-30 | 2016-06-29 | 北京城乡建设集团有限责任公司 | Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up |
CN106640121A (en) * | 2017-01-11 | 2017-05-10 | 中铁隧道勘测设计院有限公司 | Supporting structure for six-pilot-holes large-section metro station undercrossing existing line |
CN106703814A (en) * | 2015-07-30 | 2017-05-24 | 宏润建设集团股份有限公司 | Mined metro station hole pile construction method |
CN107100653A (en) * | 2017-05-23 | 2017-08-29 | 中铁四局集团第五工程有限公司 | A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station |
CN107120119A (en) * | 2017-05-04 | 2017-09-01 | 中交第二航务工程局有限公司 | The construction method of Underground Subway Station |
CN107574830A (en) * | 2017-09-08 | 2018-01-12 | 中铁十六局集团地铁工程有限公司 | A kind of subway station combines the precipitation method of piping lane construction |
CN108005664A (en) * | 2018-02-02 | 2018-05-08 | 北京市政建设集团有限责任公司 | A kind of hole pile construction method of platform structure |
CN108277823A (en) * | 2018-02-02 | 2018-07-13 | 北京市政建设集团有限责任公司 | A kind of construction method of subway platform layer totality |
CN109487798A (en) * | 2018-12-29 | 2019-03-19 | 中交(广州)建设有限公司 | Station asymmetry excavation supporting structure and construction technology |
CN110374643A (en) * | 2019-08-22 | 2019-10-25 | 中水电四局武汉轨道交通工程有限公司 | A kind for the treatment of water leakage method at Underground Subway Station arch structure dovetail |
CN111997625A (en) * | 2020-08-27 | 2020-11-27 | 合肥市轨道交通集团有限公司 | Underground excavation construction method for subway station in weak-expansibility clay stratum |
CN113738377A (en) * | 2021-09-06 | 2021-12-03 | 中铁二局第四工程有限公司 | Construction method of main structure of station by rock stratum hole-pile method |
CN114033390A (en) * | 2021-11-12 | 2022-02-11 | 中铁北京工程局集团(天津)工程有限公司 | PBA construction method construction process |
CN114457846A (en) * | 2021-11-17 | 2022-05-10 | 中国水利水电第六工程局有限公司 | Road station main body structure construction method |
-
2014
- 2014-03-17 CN CN201410095835.XA patent/CN103821167A/en active Pending
Cited By (20)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104120739A (en) * | 2014-08-11 | 2014-10-29 | 北京市政建设集团有限责任公司 | Multi-pilot tunnel excavation one-off arching construction method |
CN104806251A (en) * | 2015-04-27 | 2015-07-29 | 北京市轨道交通建设管理有限公司 | Subsidiary inverted excavation construction method for urban subway station under complex environment |
CN104806251B (en) * | 2015-04-27 | 2017-05-17 | 北京市轨道交通建设管理有限公司 | Subsidiary inverted excavation construction method for urban subway station under complex environment |
CN106703814B (en) * | 2015-07-30 | 2019-07-12 | 宏润建设集团股份有限公司 | Tunneling subway station hole pile construction method |
CN106703814A (en) * | 2015-07-30 | 2017-05-24 | 宏润建设集团股份有限公司 | Mined metro station hole pile construction method |
CN105714856A (en) * | 2016-04-30 | 2016-06-29 | 北京城乡建设集团有限责任公司 | Underground air duct construction method with first negative structural layer and second negative structural layer in bottom-up |
CN106640121A (en) * | 2017-01-11 | 2017-05-10 | 中铁隧道勘测设计院有限公司 | Supporting structure for six-pilot-holes large-section metro station undercrossing existing line |
CN106640121B (en) * | 2017-01-11 | 2023-06-27 | 中铁第六勘察设计院集团有限公司 | Supporting structure for six-pilot tunnel large-section subway station to pass through existing line |
CN107120119A (en) * | 2017-05-04 | 2017-09-01 | 中交第二航务工程局有限公司 | The construction method of Underground Subway Station |
CN107100653A (en) * | 2017-05-23 | 2017-08-29 | 中铁四局集团第五工程有限公司 | A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station |
CN107574830A (en) * | 2017-09-08 | 2018-01-12 | 中铁十六局集团地铁工程有限公司 | A kind of subway station combines the precipitation method of piping lane construction |
CN108277823A (en) * | 2018-02-02 | 2018-07-13 | 北京市政建设集团有限责任公司 | A kind of construction method of subway platform layer totality |
CN108005664A (en) * | 2018-02-02 | 2018-05-08 | 北京市政建设集团有限责任公司 | A kind of hole pile construction method of platform structure |
CN109487798A (en) * | 2018-12-29 | 2019-03-19 | 中交(广州)建设有限公司 | Station asymmetry excavation supporting structure and construction technology |
CN109487798B (en) * | 2018-12-29 | 2024-03-22 | 中交(广州)建设有限公司 | Asymmetric excavation construction process for station |
CN110374643A (en) * | 2019-08-22 | 2019-10-25 | 中水电四局武汉轨道交通工程有限公司 | A kind for the treatment of water leakage method at Underground Subway Station arch structure dovetail |
CN111997625A (en) * | 2020-08-27 | 2020-11-27 | 合肥市轨道交通集团有限公司 | Underground excavation construction method for subway station in weak-expansibility clay stratum |
CN113738377A (en) * | 2021-09-06 | 2021-12-03 | 中铁二局第四工程有限公司 | Construction method of main structure of station by rock stratum hole-pile method |
CN114033390A (en) * | 2021-11-12 | 2022-02-11 | 中铁北京工程局集团(天津)工程有限公司 | PBA construction method construction process |
CN114457846A (en) * | 2021-11-17 | 2022-05-10 | 中国水利水电第六工程局有限公司 | Road station main body structure construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103821167A (en) | Construction method for subway station body | |
CN102562075B (en) | Large cross-section weak surrounding rock tunnel three-step and six-part short-distance construction method | |
CN105041349B (en) | A kind of excavating construction method that station is digged on the basis of Subway Tunnel shield tunnel | |
CN100577986C (en) | Goaf surrounding rock around gob-side supporting method under three soft geological condition | |
CN106337686B (en) | Three layers of subway station canopy structure of rocky stratum tunneling and construction method | |
CN106761778B (en) | A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground | |
CN108005664A (en) | A kind of hole pile construction method of platform structure | |
CN105370304B (en) | High stress strong disturbance coal seam gob side entry retaining multistage reinforcement means | |
CN102226399A (en) | Soft rock four-line large-span tunnel three-bench cable-bracing excavation construction method | |
CN105781571A (en) | Construction method for soft rock deformation tunnel lining support dismantling-replacing arch | |
CN104533446A (en) | Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel | |
CN105201516B (en) | A kind of main structure of subway station and its tetrad arch PBA excavating construction methods | |
CN104405399A (en) | Construction method for excavating support body in tunnel by crossing quicksand stratum | |
CN106930321B (en) | The construction method of underground structure is built in a kind of stake of pipe-jacking with large diameter combination hole | |
CN101338678A (en) | Supporting arch hidden digging top-down construction method | |
CN104047623A (en) | Large-span grotto excavation construction method | |
CN205013013U (en) | Secretly dig station supporting construction suitable for last soft hard formation down | |
CN106869969A (en) | A kind of excavation supporting construction method of soft rock large section tunnel | |
CN107288642A (en) | PBA construction technologies | |
CN104632227B (en) | Subway station excavation technology of single-layer beam arch structure | |
CN102400694A (en) | Method for reinforcing joint of shield tunnel and mine tunnel | |
CN103670446B (en) | Circular diversion tunnel 2/3 circle concrete-liner construction method | |
CN105370289A (en) | Ultra-long shallow-buried excavation construction method for existing pipeline in complex environment | |
CN207033463U (en) | Mine shield handing-over tunnel folded type joint design in the middle part of marine site | |
CN103993885A (en) | Construction method for underground excavation tunnel side-direction hole opening supporting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20140528 |
|
WD01 | Invention patent application deemed withdrawn after publication |