CN107100653A - A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station - Google Patents
A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station Download PDFInfo
- Publication number
- CN107100653A CN107100653A CN201710370641.XA CN201710370641A CN107100653A CN 107100653 A CN107100653 A CN 107100653A CN 201710370641 A CN201710370641 A CN 201710370641A CN 107100653 A CN107100653 A CN 107100653A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- construction
- pilot tunnel
- plate
- excavation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 44
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 112
- 239000010959 steel Substances 0.000 claims abstract description 112
- 238000009412 basement excavation Methods 0.000 claims abstract description 37
- 238000000034 method Methods 0.000 claims abstract description 33
- 239000004567 concrete Substances 0.000 claims abstract description 17
- 239000002689 soil Substances 0.000 claims description 28
- 238000013461 design Methods 0.000 claims description 13
- 238000004078 waterproofing Methods 0.000 claims description 4
- 238000012545 processing Methods 0.000 claims description 2
- 230000010412 perfusion Effects 0.000 claims 2
- 239000003795 chemical substances by application Substances 0.000 claims 1
- 238000003780 insertion Methods 0.000 claims 1
- 230000037431 insertion Effects 0.000 claims 1
- 230000003014 reinforcing effect Effects 0.000 claims 1
- 238000007569 slipcasting Methods 0.000 claims 1
- 238000005728 strengthening Methods 0.000 claims 1
- 230000005641 tunneling Effects 0.000 claims 1
- 238000003466 welding Methods 0.000 claims 1
- 239000011150 reinforced concrete Substances 0.000 abstract description 10
- 238000010586 diagram Methods 0.000 description 15
- 238000007789 sealing Methods 0.000 description 6
- 230000002787 reinforcement Effects 0.000 description 3
- 239000000243 solution Substances 0.000 description 3
- 238000009434 installation Methods 0.000 description 2
- 241001270131 Agaricus moelleri Species 0.000 description 1
- 238000004873 anchoring Methods 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000002347 injection Methods 0.000 description 1
- 239000007924 injection Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 235000019353 potassium silicate Nutrition 0.000 description 1
- 238000011160 research Methods 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- NTHWMYGWWRZVTN-UHFFFAOYSA-N sodium silicate Chemical compound [Na+].[Na+].[O-][Si]([O-])=O NTHWMYGWWRZVTN-UHFFFAOYSA-N 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D13/00—Large underground chambers; Methods or apparatus for making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明提供一种新的城市超浅埋暗挖地铁车站修建的施工方法,水平和竖向位置分别密集顶进大直径钢管,相邻钢管间采用高强度螺栓和翼缘板进行连接,接着在钢管内部和刚管间浇筑混凝土,然后在侧边钢管下方的下边导洞内,把预先浇筑钢筋混凝土墙与侧边钢管进行连接,使钢筋混凝土墙作为整体管幕结构的基座。在未进行车站主体施工时,已形成刚度很大的支护体系,相比传统的管幕工法,由于增加整体管幕结构的横向承载力和刚度,能实现大断面开挖,并且在开挖过程中无需架设过多的临时支撑体系,缩短工期、节约成本;本发明提出的支护体系为平顶直墙结构,增大了空间利用率。
The invention provides a new construction method for construction of urban ultra-shallow underground excavation subway stations. Large-diameter steel pipes are densely jacked into the horizontal and vertical positions respectively, and high-strength bolts and flange plates are used to connect adjacent steel pipes. Concrete is poured inside the steel pipe and between the rigid pipes, and then in the lower pilot hole under the side steel pipe, the pre-cast reinforced concrete wall is connected with the side steel pipe, so that the reinforced concrete wall serves as the base of the overall pipe curtain structure. Before the construction of the main body of the station, a support system with high rigidity has been formed. Compared with the traditional pipe curtain construction method, due to the increase in the lateral bearing capacity and rigidity of the overall pipe curtain structure, large-section excavation can be realized, and the excavation There is no need to erect too many temporary support systems during the process, which shortens the construction period and saves costs; the support system proposed by the present invention has a flat roof and straight wall structure, which increases the space utilization rate.
Description
技术领域technical field
本发明涉及大直径密集钢管浇筑混凝土后形成的平顶直墙管幕支护体系,在新型管幕支护体系下进行城市超浅埋暗挖地铁车站修建的施工方法,属于隧道和地下工程领域。The invention relates to a flat-roofed straight-wall pipe-curtain support system formed after pouring concrete with large-diameter dense steel pipes, and a construction method for constructing urban ultra-shallow underground excavation subway stations under the new pipe-curtain support system, belonging to the field of tunnels and underground engineering .
背景技术Background technique
管幕工法最早在日本被用于修建穿越铁路的通道工程,国内首次使用管幕工法是在香港某城市地下通道的修建中。管幕工法经过国内学多年的研究和在工程中的成功实施,其已发展成熟。但由于传统的管幕结构相邻钢管间仅用锁口连接,致使整体管幕的横向刚度和承载力较弱,故开挖管幕内部土体时,需要架设大量临时支撑以确保整体结构的稳定性,造成施工进度较慢。加之横向断面多为拱形结构,空间利用率低。The pipe curtain construction method was first used in Japan to build a passageway project across the railway. The first use of the pipe curtain construction method in China was in the construction of an underground passage in a city in Hong Kong. After many years of domestic research and successful implementation in engineering, the pipe curtain construction method has matured. However, since the adjacent steel pipes in the traditional pipe curtain structure are only connected by locks, the lateral stiffness and bearing capacity of the overall pipe curtain are relatively weak. Stability, resulting in slower construction progress. In addition, most of the transverse sections are arch structures, and the space utilization rate is low.
发明内容Contents of the invention
本发明提供一种平顶直墙管幕结构修建超浅埋暗挖地铁车站的施工方法,在未进行车站主体施工时,即可形成刚度很大的支护体系,提高施工效率。The invention provides a construction method for building an ultra-shallow underground excavation subway station with a flat roof and straight wall tube curtain structure. When the main body of the station is not under construction, a support system with high rigidity can be formed to improve construction efficiency.
为解决上述技术问题,本发明采用如下技术方案:In order to solve the problems of the technologies described above, the present invention adopts the following technical solutions:
一种平顶直墙管幕结构修建超浅埋暗挖地铁车站的施工方法,包括如下步骤:A construction method for constructing an ultra-shallow underground excavation subway station with a flat-top and straight-wall tube-curtain structure, comprising the following steps:
1)在工作井四周施工围护桩,待围护桩达到强度后,进行工作井的开挖,搭建顶管施工平台;1) Construct enclosure piles around the working well. After the enclosure piles reach strength, excavate the working well and build a pipe jacking construction platform;
2)在施工用钢管的两侧焊接翼缘板,并在两侧开设预留螺栓孔和预留槽;2) Weld the flange plates on both sides of the steel pipe for construction, and set up reserved bolt holes and reserved grooves on both sides;
3)采用顶进法施工暗挖段的全部顶部钢管及两侧最上端的侧边钢管,边开挖边清除钢管内部的土体,并通过钢管侧面的预留槽清除各钢管间土体;顶进及挖土工作完成后,在相邻钢管内通过预留螺栓孔安装连接螺栓,待相邻钢管横向连接安装完毕后,在钢管两端焊接封堵板,向钢管内部和相邻钢管间灌注混凝土;3) Use the jacking method to construct all the top steel pipes and the uppermost side steel pipes on both sides of the underground excavation section, remove the soil inside the steel pipes while excavating, and remove the soil between the steel pipes through the reserved grooves on the side of the steel pipes; After the entry and excavation work is completed, the connecting bolts are installed in the adjacent steel pipes through the reserved bolt holes. After the installation of the horizontal connection of the adjacent steel pipes is completed, the sealing plates are welded at both ends of the steel pipes and poured into the interior of the steel pipes and between adjacent steel pipes. concrete;
4)在两侧最上端的侧边钢管与顶部钢管连接牢固后,由上向下依次进行其余侧边钢管的顶进、钢管之间的连接,以及钢管内及钢管间的注浆作业;4) After the uppermost side steel pipes on both sides are firmly connected to the top steel pipes, the jacking of the remaining side steel pipes, the connection between the steel pipes, and the grouting operations in and between the steel pipes are performed sequentially from top to bottom;
5)采用超前预注浆加固地层,台阶法开挖两侧下边导洞并施作初期支护,在下边导洞内施作钢筋混凝土边墙及墙下条基,用于连接两侧最下端的侧边钢管;5) Advanced pre-grouting is used to strengthen the ground, and the lower pilot tunnels on both sides are excavated by step method and the initial support is applied. Reinforced concrete side walls and lower wall strip foundations are built in the lower pilot tunnels to connect the lowermost ends of both sides. side steel pipes;
6)采用边导洞的开挖方法进行第一底部导洞开挖,并施作初期支护;6) Use the excavation method of side pilot tunnels to excavate the first bottom pilot tunnel, and implement initial support;
7)第一底部导洞贯通后,采用台阶法再进行第一上部导洞的开挖,第一上部导洞采用格栅支护;7) After the first bottom pilot tunnel is penetrated, the step method is used to excavate the first upper pilot tunnel, and the first upper pilot tunnel is supported by grids;
8)分别施作第一上部导洞、第一底部导洞内的防水,以及底纵梁和部分底板,采用人工挖孔桩修建钢管柱,然后浇筑顶纵梁及部分顶板;8) Waterproofing of the first upper pilot tunnel and the first bottom pilot tunnel, as well as the bottom longitudinal beam and part of the bottom plate shall be applied respectively, and the steel pipe column shall be built with manual excavation piles, and then the top longitudinal beam and part of the roof shall be poured;
9)采用步骤6)到步骤8)的方法纵向分步开挖第二底部导洞和第二上部导洞,导洞开挖过程中对与其相邻的导洞之间土体进行注浆加固处理,并分别施工导洞内防水板、底纵梁、部分底板及顶纵梁、部分顶板、钢管柱;9) Use the method from step 6) to step 8) to excavate the second bottom pilot tunnel and the second upper pilot tunnel vertically and step by step, and perform grouting reinforcement on the soil between the adjacent pilot tunnels during the excavation of the pilot tunnels , and construct waterproof boards, bottom longitudinal beams, part of the bottom plate and top longitudinal beams, part of the roof, and steel pipe columns in the pilot tunnel respectively;
10)破除上部导洞间格栅支护,铺设防水层,施做中跨顶板;10) Remove the grid support between the upper pilot tunnels, lay a waterproof layer, and construct the mid-span roof;
11)待中跨顶板达到设计强度80%后,纵向分段开挖站厅层中板的底部以上土体,水平钢管和竖向钢管连接处采用型钢支撑,施做车站结构边跨处站厅层侧墙防水层,中板端头处焊接牛腿支撑与竖向钢管连接,分别施工中纵梁和站厅层中板;11) After the mid-span roof reaches 80% of the design strength, excavate the soil above the bottom of the mid-slab in the station hall layer longitudinally and segmentally, and use section steel support at the connection between the horizontal steel pipe and the vertical steel pipe to make the side span of the station structure at the station hall The waterproof layer of the side wall of the first floor, the welded corbel support at the end of the middle plate is connected with the vertical steel pipe, and the middle longitudinal beam and the middle plate of the station hall floor are respectively constructed;
12)待站厅层中板达到设计强度80%后,分别开挖中跨土体和边跨土体至底板位置,施做底板;12) After the middle slab of the station hall floor reaches 80% of the design strength, excavate the mid-span soil and side-span soil to the bottom slab respectively, and construct the bottom slab;
13)破除剩余格栅支护,施做剩余防水设施,浇筑剩余主体结构,完成施工。13) Remove the remaining grid support, implement the remaining waterproof facilities, pour the remaining main structure, and complete the construction.
步骤4)中,侧边钢管施工过程中,需待上一根侧边钢管与已施工钢管连接牢固并已挖除钢管内及钢管间土体和灌注混凝土后,再顶进下一根侧边钢管。在最下层的侧边钢管内预留与下边导洞内部钢筋混凝土边墙相连接的钢筋支架。In step 4), during the construction of the side steel pipe, it is necessary to wait until the previous side steel pipe is firmly connected to the constructed steel pipe and the soil inside and between the steel pipes and the concrete have been excavated before jacking the next side steel pipe. Steel Pipe. A steel bar bracket connected to the reinforced concrete side wall inside the lower pilot tunnel is reserved in the lowermost side steel pipe.
步骤11)中,所述站厅层中板端头处的上、下层侧墙设置接头结构。In step 11), the upper and lower side walls at the end of the middle plate of the station hall layer are provided with a joint structure.
步骤12)中,施做底板的具体方法如下:In step 12), the specific method of applying the bottom plate is as follows:
开挖中跨土体至底板位置的底部,施作封底结构并拆除部分导洞结构,施做中跨底板防水层并浇筑中跨底板;Excavate the mid-span soil to the bottom of the bottom slab, apply the back-sealing structure and remove part of the pilot tunnel structure, apply the mid-span bottom slab waterproof layer and pour the mid-span bottom slab;
待中跨底板混凝土达到设计强度80%后,开挖边跨土体至底板位置的底部,施作封底结构并拆除部分导洞结构,施做底板防水层并浇筑底板剩余结构。After the mid-span bottom slab concrete reaches 80% of the design strength, excavate the side-span soil to the bottom of the bottom slab, construct the back-sealing structure and remove part of the pilot tunnel structure, apply the waterproof layer of the bottom slab and pour the remaining structure of the bottom slab.
由以上技术方案可知,本发明提出一种新的施工形式,水平和竖向位置分别密集顶进大直径钢管,相邻钢管间采用高强度螺栓和翼缘板进行连接,接着在钢管内部和刚管间浇筑混凝土,然后在侧边钢管下方的下边导洞内,把预先浇筑钢筋混凝土墙与侧边钢管进行连接,使钢筋混凝土墙作为整体管幕结构的基座。在未进行车站主体施工时,已形成刚度很大的支护体系,相比传统的管幕工法,由于增加整体管幕结构的横向承载力和刚度,能实现大断面开挖,并且在开挖过程中无需架设过多的临时支撑体系,缩短工期、节约成本;本发明提出的支护体系为平顶直墙结构,增大了空间利用率。It can be seen from the above technical solutions that the present invention proposes a new construction form, in which large-diameter steel pipes are intensively jacked in the horizontal and vertical positions respectively, and high-strength bolts and flange plates are used to connect adjacent steel pipes, and then inside the steel pipes and rigid Concrete is poured between the pipes, and then in the lower pilot hole under the side steel pipes, the pre-cast reinforced concrete wall is connected with the side steel pipes, so that the reinforced concrete wall serves as the base of the overall pipe curtain structure. When the main body of the station is not under construction, a support system with high rigidity has been formed. Compared with the traditional pipe curtain construction method, due to the increase in the lateral bearing capacity and rigidity of the overall pipe curtain structure, large-section excavation can be realized, and in the excavation There is no need to erect too many temporary support systems during the process, which shortens the construction period and saves costs; the support system proposed by the present invention has a flat roof and straight wall structure, which increases the space utilization rate.
附图说明Description of drawings
图1是顶管施工平台示意图;Figure 1 is a schematic diagram of a pipe jacking construction platform;
图2是带翼缘板钢管的结构示意图;Fig. 2 is a structural schematic diagram of a steel pipe with a flange plate;
图3是相邻钢管的连接状态示意图;Fig. 3 is a schematic diagram of the connection state of adjacent steel pipes;
图4是车站开挖工序一示意图;Fig. 4 is a schematic diagram of station excavation process;
图5是车站开挖工序二示意图;Fig. 5 is a schematic diagram of station excavation process two;
图6是车站开挖工序二示意图;Fig. 6 is a schematic diagram of station excavation process two;
图7是车站开挖工序三示意图;Fig. 7 is a schematic diagram of station excavation process three;
图8是车站开挖工序四示意图;Fig. 8 is a schematic diagram of station excavation process four;
图9是车站开挖工序五示意图;Fig. 9 is a schematic diagram of station excavation process five;
图10是车站开挖工序六示意图;Fig. 10 is a schematic diagram of station excavation process six;
图11是车站开挖工序七示意图;Fig. 11 is a schematic diagram of station excavation process seven;
图12是车站开挖工序八示意图;Fig. 12 is a schematic diagram of station excavation process eight;
图13是车站开挖工序九示意图;Fig. 13 is a nine schematic diagram of station excavation process;
图14是车站开挖工序十示意图;Fig. 14 is a ten schematic diagram of station excavation process;
图15是车站开挖工序十一示意图。Fig. 15 is a schematic diagram of the station excavation process eleven.
图中:1、工作井,2、围护桩,3、钢管,4、翼缘板,6、预留槽,7、连接螺栓,8、螺帽,9、混凝土,11、钢筋支架,12、钢筋混凝土边墙,13、初期支护,131、格栅支护,14、墙下条基,15、底纵梁,16、底板,17、人工挖孔桩,18、钢管柱,19、顶纵梁,20、顶纵梁上方顶板,21、土体加固,22、中跨顶板,23、站厅层中板,24、斜撑,25、牛腿支撑,26、中纵梁,27、侧墙接头,28、底板,29、坡度。In the figure: 1. Working well, 2. Surrounding pile, 3. Steel pipe, 4. Flange plate, 6. Reserved groove, 7. Connecting bolt, 8. Nut, 9. Concrete, 11. Steel support, 12 . Reinforced concrete side wall, 13. Initial support, 131. Grid support, 14. Strip foundation under the wall, 15. Bottom longitudinal beam, 16. Bottom plate, 17. Artificial hole-digging pile, 18. Steel pipe column, 19, Top longitudinal beam, 20. Roof above the top longitudinal beam, 21. Soil reinforcement, 22. Mid-span roof, 23. Middle plate of station hall floor, 24. Diagonal bracing, 25. Corbel support, 26. Middle longitudinal beam, 27 , side wall joint, 28, bottom plate, 29, slope.
具体实施方式detailed description
下面结合附图对本发明的一种优选实施方式作详细的说明。A preferred embodiment of the present invention will be described in detail below with reference to the accompanying drawings.
本发明提供一种用于修建超浅埋暗挖地铁车站的施工方法,采用平顶直墙管幕结构,具体包括如下施工步骤:The invention provides a construction method for constructing an ultra-shallow underground excavation subway station, which adopts a flat roof and straight wall pipe curtain structure, and specifically includes the following construction steps:
步骤1:在工作井1四周施工围护桩2,待围护桩达到强度后,进行工作井的开挖,搭建顶管施工平台,参见图1。Step 1: Construct enclosure piles 2 around the working well 1. After the enclosure piles reach strength, excavate the working well and build a pipe jacking construction platform, see Figure 1.
步骤2:在加工厂对施工钢管3进行加工,钢管两侧在设计位置焊接翼缘板4,并在设计位置开设有预留螺栓孔和预留槽6,参见图2。Step 2: Process the construction steel pipe 3 in the processing plant, weld the flange plate 4 at the design position on both sides of the steel pipe, and open reserved bolt holes and reserved grooves 6 at the design position, see FIG. 2 .
步骤3:采用顶进法施工暗挖段的编号1~24号顶部钢管及编号25、34号侧边钢管,边开挖边清除钢管内部的土体,并通过钢管侧面的预留槽清除钢管间土体,参见图4。钢管顶进施工时要控制好方向,不得偏转,顶进及挖土工作完成后,在相邻钢管3内安装连接螺栓7,并在螺栓的两端安置螺帽8,以增加螺栓与混凝土9的锚固力。待相邻钢管3横向连接安装完毕后,在钢管两端焊接封堵板,通过封堵板预留灌浆孔,向钢管内灌注混凝土,同时在钢管之间灌注混凝土,参见图2和3。Step 3: Use the jacking method to construct the No. 1 to No. 24 top steel pipes and No. 25 and No. 34 side steel pipes in the underground excavation section. Remove the soil inside the steel pipes while excavating, and remove the steel pipes through the reserved grooves on the side of the steel pipes. For soil, see Figure 4. When the steel pipe jacking construction, the direction should be controlled well, and the deflection should not be allowed. After the jacking and excavation work is completed, the connecting bolt 7 is installed in the adjacent steel pipe 3, and the nuts 8 are placed at both ends of the bolt to increase the distance between the bolt and the concrete 9. anchoring force. After the installation of the horizontal connection of the adjacent steel pipes 3 is completed, weld the sealing plates at both ends of the steel pipes, reserve grouting holes through the sealing plates, pour concrete into the steel pipes, and pour concrete between the steel pipes at the same time, see Figures 2 and 3.
步骤4:在两侧最上端的侧边钢管与顶部钢管连接牢固后,由上向下进行26~32号侧边钢管、35~41号侧边钢管的顶进、钢管之间的连接以及钢管内及钢管间的注浆作业。侧边钢管施工过程中,需待上一根钢管与已施工钢管连接牢固并已挖除钢管内及钢管间土体、灌注混凝土后,再顶进下一根钢管。在最下段的侧边钢管33号和42号内预留与导洞内部钢筋混凝土边墙12相连接的钢筋支架11,参见图5。Step 4: After the uppermost side steel pipes on both sides are firmly connected to the top steel pipes, carry out the jacking of No. 26-32 side steel pipes, No. 35-41 side steel pipes, the connection between the steel pipes and the inside of the steel pipes from top to bottom. And grouting between steel pipes. During the construction of the side steel pipe, the next steel pipe needs to be pushed in after the previous steel pipe is firmly connected to the constructed steel pipe, the soil inside and between the steel pipes has been excavated, and concrete has been poured. In No. 33 and No. 42 of the side steel pipes of the lowest section, a steel bar bracket 11 connected with the reinforced concrete side wall 12 inside the pilot tunnel is reserved, as shown in FIG. 5 .
步骤5:采用超前预注浆加固地层,台阶法开挖下边导洞Z5、Z6,并施作初期支护13。在下边导洞内施作钢筋混凝土边墙12及墙下条基14,并使侧边钢管最下部33、42号与导洞内钢筋混凝土边墙连接牢靠,参见图6和7。Step 5: Use advanced pre-grouting to strengthen the ground, excavate the lower pilot tunnels Z5 and Z6 by step method, and implement initial support 13 . Build the reinforced concrete side wall 12 and the lower strip foundation 14 in the lower pilot tunnel, and make the lowermost part 33, 42 of the side steel pipes firmly connected with the reinforced concrete side wall in the pilot tunnel, see Fig. 6 and 7 .
步骤6:采用下边导洞的开挖方法进行第一底部导洞Z2的开挖,并施作初期支护13,参见图8。Step 6: Use the excavation method of the lower pilot tunnel to excavate the first bottom pilot tunnel Z2, and implement initial support 13, see FIG. 8 .
步骤7:第一底部导洞Z2贯通后,采用台阶法再进行第一上部导洞Z1的开挖,导洞采用格栅支护131,参见图9。Step 7: After the first bottom pilot tunnel Z2 is penetrated, the first upper pilot tunnel Z1 is excavated using the step method, and the pilot tunnel is supported by a grid 131 , see FIG. 9 .
步骤8:分别施作第一上部导洞Z1和第一底部导洞Z2内的防水和底纵梁15及部分底板16,采用人工挖孔桩17修建钢管柱18,然后浇筑顶纵梁19及部分顶板20,参见图10。Step 8: Waterproofing and bottom longitudinal beams 15 and part of the bottom plate 16 in the first upper pilot tunnel Z1 and the first bottom pilot tunnel Z2 are constructed respectively, and steel pipe columns 18 are built with manual excavation piles 17, and then the top longitudinal beams 19 and Part of the top plate 20, see FIG. 10 .
步骤9:采用上述方法和步骤纵向分步开挖第二底部导洞Z4和第二上部导洞Z3,导洞开挖过程中对与其相邻的导洞之间土体进行注浆加固处理,形成土体加固21,注水泥水玻璃双液浆,并分别施工导洞内防水板、底纵梁、部分底板及顶纵梁、部分顶板、钢管柱,参见图11。Step 9: Excavate the second bottom pilot tunnel Z4 and the second upper pilot tunnel Z3 vertically and step-by-step using the above method and steps. During the excavation of the pilot tunnel, the soil between the adjacent pilot tunnels is grouted and reinforced to form Soil reinforcement 21, injection of cement and water glass double slurry, and construction of waterproof boards, bottom longitudinal beams, part of the bottom plate and top longitudinal beams, part of the roof, and steel pipe columns in the pilot tunnel, see Figure 11.
步骤10:破除上部导洞间格栅支护,铺设防水层,施做中跨顶板22,参见图12。Step 10: Remove the grid support between the upper pilot tunnels, lay a waterproof layer, and make the mid-span roof 22, see Figure 12.
步骤11:待中跨顶板达到设计强度80%后,纵向分段开挖站厅层中板23底以上土体,顶部钢管和侧边钢管连接处采用型钢支撑24,施做车站结构边跨处站厅层侧墙防水层,站厅层中板端头处焊接牛腿支撑25与侧边钢管连接,依次施工中纵梁26、站厅层中板23及中板端头处的上、下层的侧墙接头27,参见图13。Step 11: After the mid-span roof reaches 80% of the design strength, excavate the soil above the bottom of the mid-slab 23 of the station hall layer in longitudinal sections, and use section steel supports 24 at the connection between the top steel pipe and the side steel pipes to be used as the side span of the station structure The waterproof layer of the side wall of the station hall floor, the welded corbel support 25 at the end of the middle plate of the station hall floor is connected with the side steel pipes, and the middle longitudinal beam 26, the middle plate 23 of the station hall floor, and the upper and lower floors at the end of the middle plate are constructed sequentially side wall joint 27, see Figure 13.
步骤12:待站厅层中板23达到设计强度80%后,开挖中跨土体至底板位置,施做底板28并拆除格栅支护,土体预留一定坡度29,参见图4-11。待中跨底板混凝土达到设计强度80%后,开挖边跨土体至底板位置的底部,施作封底结构并拆除部分导洞结构,施做底板防水层并浇筑底板剩余结构,参见图14。Step 12: After the mid-slab 23 of the station hall floor reaches 80% of the design strength, excavate the mid-span soil to the bottom slab, construct the bottom slab 28 and remove the grid support, reserve a certain slope 29 for the soil, see Figure 4- 11. After the mid-span bottom slab concrete reaches 80% of the design strength, excavate the side-span soil to the bottom of the bottom slab, construct the back-sealing structure and remove part of the pilot tunnel structure, apply the waterproof layer of the bottom slab and pour the remaining structure of the bottom slab, see Figure 14.
步骤13:破除剩余格栅支护13,施做剩余防水设施,浇筑剩余主体结构,完成施工,参见图15。Step 13: Remove the remaining grid support 13, implement the remaining waterproof facilities, pour the remaining main structure, and complete the construction, see Figure 15.
以上所述实施方式仅仅是对本发明的优选实施方式进行描述,并非对本发明的范围进行限定,在不脱离本发明设计精神的前提下,本领域普通技术人员对本发明的技术方案作出的各种变形和改进,均应落入本发明的权利要求书确定的保护范围内。The above-mentioned embodiments are only descriptions of the preferred embodiments of the present invention, and are not intended to limit the scope of the present invention. Without departing from the design spirit of the present invention, those skilled in the art may make various modifications to the technical solutions of the present invention. and improvements, all should fall within the scope of protection determined by the claims of the present invention.
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710370641.XA CN107100653A (en) | 2017-05-23 | 2017-05-23 | A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710370641.XA CN107100653A (en) | 2017-05-23 | 2017-05-23 | A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107100653A true CN107100653A (en) | 2017-08-29 |
Family
ID=59669275
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710370641.XA Pending CN107100653A (en) | 2017-05-23 | 2017-05-23 | A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107100653A (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108343450A (en) * | 2018-04-18 | 2018-07-31 | 中铁十四局集团有限公司 | A kind of new pipe-roof method active well ruggedized construction and reinforcement means |
CN108868778A (en) * | 2018-07-02 | 2018-11-23 | 中国铁路设计集团有限公司 | A kind of Large Underground Structure no-dig technique construction method |
CN109024668A (en) * | 2018-06-07 | 2018-12-18 | 北京市轨道交通设计研究院有限公司 | A kind of construction method of multilayer subway station |
CN109488314A (en) * | 2018-12-30 | 2019-03-19 | 中铁十四局集团有限公司 | Pipe curtain construction method |
CN109653772A (en) * | 2019-02-03 | 2019-04-19 | 东北大学 | A kind of shallow buried tube curtain support system and its construction method |
CN109736813A (en) * | 2018-12-30 | 2019-05-10 | 中铁十四局集团有限公司 | Engineering construction method |
CN110486062A (en) * | 2019-08-15 | 2019-11-22 | 中交铁道设计研究总院有限公司 | A kind of method of mechanical tunneling multilayer multispan underground engineering in weak soil |
CN110528575A (en) * | 2019-07-10 | 2019-12-03 | 中铁上海工程局集团华海工程有限公司 | Subway solid concrete roabed concrete reserved opening device and its construction method |
CN110593881A (en) * | 2019-09-17 | 2019-12-20 | 中铁第六勘察设计院集团有限公司 | Method for realizing large-section underground space excavation by using small-section combined jacking pipe |
CN111677515A (en) * | 2020-05-20 | 2020-09-18 | 中铁二院工程集团有限责任公司 | Construction method for breaking open cut foundation pit wall into hole from pile support supporting system by adopting shallow-buried underground excavation method |
CN111677520A (en) * | 2020-06-17 | 2020-09-18 | 海南大学 | Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method |
CN111911168A (en) * | 2020-09-04 | 2020-11-10 | 石家庄铁道大学 | Construction Method and Permanent Support System of Shallow Buried Long-Span Tunnel |
CN112901213A (en) * | 2021-03-04 | 2021-06-04 | 中铁七局集团有限公司 | Underground roof construction method based on pipe curtain support |
CN113153355A (en) * | 2021-04-26 | 2021-07-23 | 中铁建大桥工程局集团第五工程有限公司 | Construction method for down-penetrating tunnel forepoling curtain |
CN113202508A (en) * | 2021-05-07 | 2021-08-03 | 上海市城市建设设计研究总院(集团)有限公司 | Construction method for providing shear-resistant bearing capacity for gapped discrete steel structure pipe row |
CN114198116A (en) * | 2021-11-10 | 2022-03-18 | 同济大学 | An integrated tunnel structure with pipe curtain and box culvert with joint reinforcement |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08184289A (en) * | 1994-12-28 | 1996-07-16 | Kajima Corp | Subway station structure and construction method |
CN103244143A (en) * | 2013-05-27 | 2013-08-14 | 中铁工程设计咨询集团有限公司 | Underground engineering tunneling construction method and underground station |
CN103321659A (en) * | 2013-07-22 | 2013-09-25 | 中铁隧道集团有限公司 | Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method |
CN103821167A (en) * | 2014-03-17 | 2014-05-28 | 北京市政建设集团有限责任公司 | Construction method for subway station body |
CN105781595A (en) * | 2016-04-01 | 2016-07-20 | 中铁工程装备集团有限公司 | Method for mechanical branch underground excavation construction of rectangular and quasi-rectangular cross-section underground engineering |
CN106089243A (en) * | 2016-06-12 | 2016-11-09 | 东北大学 | A kind of pipe curtain supporting construction connected based on concrete filled steel tube |
-
2017
- 2017-05-23 CN CN201710370641.XA patent/CN107100653A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH08184289A (en) * | 1994-12-28 | 1996-07-16 | Kajima Corp | Subway station structure and construction method |
CN103244143A (en) * | 2013-05-27 | 2013-08-14 | 中铁工程设计咨询集团有限公司 | Underground engineering tunneling construction method and underground station |
CN103321659A (en) * | 2013-07-22 | 2013-09-25 | 中铁隧道集团有限公司 | Large-diameter tube curtain support underground excavation construction super-shallow burying large-section subway station structure and construction method |
CN103821167A (en) * | 2014-03-17 | 2014-05-28 | 北京市政建设集团有限责任公司 | Construction method for subway station body |
CN105781595A (en) * | 2016-04-01 | 2016-07-20 | 中铁工程装备集团有限公司 | Method for mechanical branch underground excavation construction of rectangular and quasi-rectangular cross-section underground engineering |
CN106089243A (en) * | 2016-06-12 | 2016-11-09 | 东北大学 | A kind of pipe curtain supporting construction connected based on concrete filled steel tube |
Non-Patent Citations (1)
Title |
---|
谢欣: "沈阳地铁STS工法钢管混凝土横向连接正截面杭弯性能研究", 《中国优秀硕士学位论文全文数据库工程科技Ⅱ辑》 * |
Cited By (21)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108343450B (en) * | 2018-04-18 | 2023-11-03 | 中铁十四局集团有限公司 | Novel pipe curtain method working well reinforcing structure and reinforcing method |
CN108343450A (en) * | 2018-04-18 | 2018-07-31 | 中铁十四局集团有限公司 | A kind of new pipe-roof method active well ruggedized construction and reinforcement means |
CN109024668A (en) * | 2018-06-07 | 2018-12-18 | 北京市轨道交通设计研究院有限公司 | A kind of construction method of multilayer subway station |
CN108868778B (en) * | 2018-07-02 | 2020-06-19 | 中国铁路设计集团有限公司 | Non-excavation construction method for large underground structure |
CN108868778A (en) * | 2018-07-02 | 2018-11-23 | 中国铁路设计集团有限公司 | A kind of Large Underground Structure no-dig technique construction method |
CN109488314A (en) * | 2018-12-30 | 2019-03-19 | 中铁十四局集团有限公司 | Pipe curtain construction method |
CN109736813A (en) * | 2018-12-30 | 2019-05-10 | 中铁十四局集团有限公司 | Engineering construction method |
CN109653772B (en) * | 2019-02-03 | 2020-07-21 | 东北大学 | Shallow buried pipe curtain supporting system and construction method thereof |
CN109653772A (en) * | 2019-02-03 | 2019-04-19 | 东北大学 | A kind of shallow buried tube curtain support system and its construction method |
CN110528575A (en) * | 2019-07-10 | 2019-12-03 | 中铁上海工程局集团华海工程有限公司 | Subway solid concrete roabed concrete reserved opening device and its construction method |
CN110486062A (en) * | 2019-08-15 | 2019-11-22 | 中交铁道设计研究总院有限公司 | A kind of method of mechanical tunneling multilayer multispan underground engineering in weak soil |
CN110593881A (en) * | 2019-09-17 | 2019-12-20 | 中铁第六勘察设计院集团有限公司 | Method for realizing large-section underground space excavation by using small-section combined jacking pipe |
CN111677515A (en) * | 2020-05-20 | 2020-09-18 | 中铁二院工程集团有限责任公司 | Construction method for breaking open cut foundation pit wall into hole from pile support supporting system by adopting shallow-buried underground excavation method |
CN111677520B (en) * | 2020-06-17 | 2022-03-01 | 海南大学 | Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method |
CN111677520A (en) * | 2020-06-17 | 2020-09-18 | 海南大学 | Construction method of excavating station structure by tunnel first and then station pipe curtain hole pile method |
CN111911168A (en) * | 2020-09-04 | 2020-11-10 | 石家庄铁道大学 | Construction Method and Permanent Support System of Shallow Buried Long-Span Tunnel |
CN112901213A (en) * | 2021-03-04 | 2021-06-04 | 中铁七局集团有限公司 | Underground roof construction method based on pipe curtain support |
CN113153355A (en) * | 2021-04-26 | 2021-07-23 | 中铁建大桥工程局集团第五工程有限公司 | Construction method for down-penetrating tunnel forepoling curtain |
CN113153355B (en) * | 2021-04-26 | 2023-09-08 | 中铁建大桥工程局集团第五工程有限公司 | Construction method for advanced pipe curtain of underpass tunnel |
CN113202508A (en) * | 2021-05-07 | 2021-08-03 | 上海市城市建设设计研究总院(集团)有限公司 | Construction method for providing shear-resistant bearing capacity for gapped discrete steel structure pipe row |
CN114198116A (en) * | 2021-11-10 | 2022-03-18 | 同济大学 | An integrated tunnel structure with pipe curtain and box culvert with joint reinforcement |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107100653A (en) | A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station | |
CN102587922B (en) | A construction method for arc-guided roof lifting in oblique inclined shafts in soft and broken rock formations | |
CN106761778B (en) | A kind of underground digging in subway station construction technology suitable for upper-soft lower-hard ground | |
CN105064397B (en) | Open excavation construction method for expanding excavation of station on metro interzone shield tunnel foundation | |
CN205742213U (en) | Foundation pit supporting construction | |
CN107905814B (en) | Large span loess tunnel top bar CD construction method | |
CN108589771B (en) | Construction method for layer-adding transfer node of operated underground station | |
CN105756091B (en) | A Construction Method of Subway Station Foundation Pit Controlling the Deformation of Adjacent Buildings | |
CN110541721A (en) | Support system and construction method for fully weathered surrounding rock tunnel in water-rich quicksand stratum | |
CN105003272A (en) | Reversed construction method for expanding and excavating stations on sectional shield tunnel foundations of subways | |
CN105089670B (en) | Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel | |
CN106930321A (en) | Underground structure novel construction method is built in a kind of pipe-jacking with large diameter combination hole stake | |
CN113266017B (en) | Regulation and storage tank construction method based on 'permanent-face integrated' inner support structure of deep foundation pit | |
CN111396060A (en) | An anti-uplift reinforcement method for a new tunnel that penetrates an existing shield tunnel at a super close distance | |
CN104632227B (en) | Subway station excavation technology of single-layer beam arch structure | |
CN105201516A (en) | Subway station body structure and four-joint-arch PBA underground excavation construction method thereof | |
CN112302686A (en) | Vertical jacking construction method for entering tunnel inclined shaft into main tunnel | |
CN105386779B (en) | The counterfort method of large underground structure is built in shallow embedding rock stratum | |
CN114412509A (en) | A support method suitable for large deformation of mudstone tunnel | |
CN210141142U (en) | Underground structure is built in same direction as digging in hole stake secret | |
CN115467690B (en) | New structure system of shallow-buried large-span underground excavation subway station and construction method thereof | |
CN208763446U (en) | A support structure for adding underground space under existing buildings | |
CN115324104B (en) | Permanent-face combined assembled station and construction method thereof | |
CN110952563A (en) | Temporary anti-floating structure for excavation of foundation pit above existing subway tunnel | |
CN105804086A (en) | Construction method for support change joints in foundation trench reverse building method construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170829 |