CN113202508A - Construction method for providing shear-resistant bearing capacity for gapped discrete steel structure pipe row - Google Patents
Construction method for providing shear-resistant bearing capacity for gapped discrete steel structure pipe row Download PDFInfo
- Publication number
- CN113202508A CN113202508A CN202110493423.1A CN202110493423A CN113202508A CN 113202508 A CN113202508 A CN 113202508A CN 202110493423 A CN202110493423 A CN 202110493423A CN 113202508 A CN113202508 A CN 113202508A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- clamping piece
- steel
- pipe joint
- joint
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 95
- 239000010959 steel Substances 0.000 title claims abstract description 95
- 238000010276 construction Methods 0.000 title claims abstract description 20
- 238000004519 manufacturing process Methods 0.000 claims abstract description 16
- 238000000034 method Methods 0.000 claims description 8
- 239000002689 soil Substances 0.000 claims description 7
- 239000011440 grout Substances 0.000 claims description 3
- 230000035515 penetration Effects 0.000 claims description 3
- 230000008901 benefit Effects 0.000 abstract description 5
- 238000010008 shearing Methods 0.000 abstract description 3
- 238000009412 basement excavation Methods 0.000 description 4
- 230000000694 effects Effects 0.000 description 3
- 238000003466 welding Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000008878 coupling Effects 0.000 description 1
- 238000010168 coupling process Methods 0.000 description 1
- 238000005859 coupling reaction Methods 0.000 description 1
- 238000002474 experimental method Methods 0.000 description 1
- 230000006872 improvement Effects 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 230000002035 prolonged effect Effects 0.000 description 1
- 229920006395 saturated elastomer Polymers 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
- E21D11/15—Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21F—SAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
- E21F17/00—Methods or devices for use in mines or tunnels, not covered elsewhere
Abstract
The invention discloses a construction method for providing shear-resistant bearing capacity for a gapped discrete steel structure tube row, which comprises the following steps of manufacturing an outer flange of a steel tube section, an inner flange of the steel tube section and a web plate of the steel tube section, and arranging a corrugated tube perforation on the web plate of the steel tube section; step two, manufacturing a first clamping piece and a second clamping piece, and fixing the first clamping piece and the second clamping piece on the outer flange of the steel pipe section and the inner flange of the steel pipe section respectively, wherein the first clamping piece and the second clamping piece are arranged in the full length direction along the jacking direction; and step three, respectively fixing the steel pipe joint web plates to the outer flange of the steel pipe joint and the inner flange of the steel pipe joint, and finishing the whole manufacturing of the steel pipe joint. The invention not only solves the shearing resistance problem of the transverse stress steel pipe row, but also enables the pipe curtain structure without filling concrete to become possible, expands the construction means of underground engineering, promotes the technical progress of industry, and has good economic and social benefits.
Description
Technical Field
The invention relates to the technical field of pipe curtain structures, in particular to a construction method for providing shear-resistant bearing capacity for a gapped discrete steel structure pipe row.
Background
With the rapid development of economy and the increasing population density of China, the ground developable resources are less and less, and the land utilization rate tends to be saturated. Therefore, the development of cities to underground spaces is a necessary trend for the development of the international metropolis. However, when underground structures are built in urban core areas and old urban areas, the problems of insufficient underground space, incapability of touching adjacent facilities and the like exist.
The existing underground excavation method in the field is gradually the preferred method for building underground structures in complex environments by virtue of the advantage that the underground excavation method has less interference to the ground environment. The pipe curtain method is used as an underground excavation method, and has the advantages of low noise during construction, small ground surface settlement, low construction space requirement, no need of road reconstruction and pipeline adjustment, suitability for underground construction of various soil bodies and the like.
However, in the existing pipe curtain structure, steel pipes are arranged in the longitudinal direction and connected with each other in the transverse direction through lock catches, and concrete is poured inside the steel pipes. Because the restraint effect of the transverse lock catch is weaker, a pipe shed supporting system is formed mainly by the longitudinal strength of a pipe curtain structure and the temporary steel arch frame in the earth excavation process. On the basis of the above, new Tube curtain structures, such as ntr (new Tube Roof) Tube curtain structure, sts (Steel Tube slab) Tube curtain structure, FCSR (Flange-Channel Steel Roof) Tube curtain structure, pcr (stressed Concrete Roof) Tube curtain structure, and bundle Tube curtain structure, have been developed in recent decades. However, considering the factors of overall rigidity, improvement of structural bearing capacity, isolation of underground water and the like, concrete needs to be filled in the steel pipe joints. But not only can the construction period be prolonged and the construction cost be increased, but also the construction difficulty and risk are increased; meanwhile, most pipe curtain structures are stressed longitudinally, so that the shearing-resistant bearing capacity of the transverse pipe joints and the lock catches among the pipe joints is small.
Therefore, how to ensure the shear-resistant bearing capacity of the steel-structured tube bank without filling concrete in the tube bank is a new technical problem to be solved urgently by technical personnel in the technical field.
Disclosure of Invention
In view of the above-mentioned drawbacks of the prior art, a technical object of the present invention is to solve the technical problems mentioned in the above-mentioned background art.
In order to achieve the technical purpose, the invention provides a construction method for providing shear-resistant bearing capacity for a gapped discrete steel structure pipe row, which comprises the following steps:
the manufacturing method comprises the following steps of firstly, manufacturing an outer flange of a steel pipe joint, an inner flange of the steel pipe joint and a web plate of the steel pipe joint, and forming a corrugated pipe perforation on the web plate of the steel pipe joint;
step two, manufacturing a first clamping piece and a second clamping piece, and fixing the first clamping piece and the second clamping piece on the outer flange of the steel pipe section and the inner flange of the steel pipe section respectively, wherein the first clamping piece and the second clamping piece are arranged in the full length direction along the jacking direction;
step three, respectively fixing the steel pipe joint web plates to the outer flange of the steel pipe joint and the inner flange of the steel pipe joint, and finishing the whole manufacturing of the steel pipe joint;
jacking one steel pipe joint into the soil layer, and jacking the first clamping piece in the adjacent steel pipe joint along the second clamping piece in the steel pipe joint jacked into the soil layer;
step five, construction is carried out in sequence, and the subsequent jacking of the steel pipe joints is completed;
sixthly, completing the penetration of the prestressed steel strands through the corrugated pipe perforations arranged on the steel pipe joint web plates;
and seventhly, grouting among the steel pipe joints, and stretching the prestressed steel strands to enable the plurality of steel pipe joints to form a structural whole after the grout is gradually solidified.
Preferably, in the second step, the first clamping piece and the second clamping piece are respectively welded and fixed on the outer flange of the steel pipe joint and the inner flange of the steel pipe joint through fillet welds.
Preferably, in the third step, the steel pipe joint web is welded and fixed to the steel pipe joint outer flange and the steel pipe joint inner flange respectively.
Preferably, the first clamping piece and the second clamping piece are arranged in a full-length mode along the jacking direction.
Preferably, the first clip member is a male clip member, and the second clip member is a female clip member.
The invention has the beneficial effects that:
due to the innovation of the construction method, compared with the prior art, the invention has the following advantages:
first, the integrity of the tube rows is improved, and the lateral stiffness and load bearing capacity are increased.
Secondly, the propulsion precision that novel female, male lock joint can guide follow-up tube coupling is higher, reduces vertical and horizontal deviation.
And the related structure is simple, the material can be processed in a factory or manufactured on site, and blanking, manufacturing and installation can be arranged more flexibly.
And thirdly, the lock catch joint clearance can ensure the propelling precision of the pipe joint and can avoid the friction and collision of the joint during propelling operation caused by too small clearance.
In conclusion, the invention not only solves the shearing resistance problem of the transverse stress steel pipe row, but also enables the pipe curtain structure without filling concrete to become possible, expands the construction means of underground engineering, promotes the technical progress of industry, and has good economic and social benefits.
Drawings
FIG. 1 is a schematic structural view of the present invention after completion of construction;
fig. 2 is an enlarged schematic structural view of a portion a in fig. 1.
In the figure: the steel pipe joint comprises a steel pipe joint outer flange 1, a steel pipe joint inner flange 2, a steel pipe joint web 3, a corrugated pipe perforation 4, a prestressed steel strand 5, a first clamping piece 6, a second clamping piece 7, an angle welding seam 8 and a steel pipe joint 9.
Detailed Description
The conception, the specific structure and the technical effects of the present invention will be further described with reference to the accompanying drawings to fully understand the objects, the features and the effects of the present invention.
Example (b):
as shown in fig. 1-2, a specific embodiment of the present invention provides a construction method for providing shear-resisting bearing capacity for a gapped discrete steel-structured tube array, which includes the following steps:
the manufacturing method comprises the following steps of firstly, manufacturing an outer flange 1 of the steel pipe joint, an inner flange 2 of the steel pipe joint and a web 3 of the steel pipe joint, and forming a corrugated pipe perforation 4 on the web 3 of the steel pipe joint.
And step two, manufacturing the male clamping piece 6 and the female clamping piece 7, and welding and fixing the male clamping piece 6 and the female clamping piece 7 on the outer flange 1 and the inner flange 2 of the steel pipe section through fillet welds 9, wherein the male clamping piece 6 and the female clamping piece 7 are arranged in the full length direction along the jacking direction.
And step three, welding the steel pipe joint web 3 to the outer flange 1 and the inner flange 2 of the steel pipe joint to complete the whole manufacture of the steel pipe joint 9.
And step four, a pipe jacking machine is adopted to jack the steel pipe sections 9 into the soil layer, and when the later adjacent steel pipe sections 9 are jacked in, the male clamping pieces 6 in the later adjacent steel pipe sections 9 are jacked in along the grooves in the female clamping pieces 7 in the steel pipe sections 9 which are jacked into the soil layer.
And fifthly, sequentially constructing to finish the jacking work of the steel pipe section 9.
And step six, completing the penetration of the prestressed steel strands 5 through corrugated pipe through holes 4 formed in the steel pipe joint web 3.
And step seven, grouting between the steel pipe joints 9 is completed, and after the grout is gradually solidified, tensioning work of the prestressed steel strands 5 is completed, so that the single steel pipe joint 9 forms a structural whole.
The foregoing detailed description of the preferred embodiments of the invention has been presented. It should be understood that numerous modifications and variations could be devised by those skilled in the art in light of the present teachings without departing from the inventive concepts. Therefore, the technical solutions available to those skilled in the art through logic analysis, reasoning and limited experiments based on the prior art according to the concept of the present invention should be within the scope of protection defined by the claims.
Claims (4)
1. A construction method for providing shear-resistant bearing capacity for a gapped discrete steel structure tube row is characterized by comprising the following steps:
the manufacturing method comprises the following steps of firstly, manufacturing an outer flange of a steel pipe joint, an inner flange of the steel pipe joint and a web plate of the steel pipe joint, and forming a corrugated pipe perforation on the web plate of the steel pipe joint;
step two, manufacturing a first clamping piece and a second clamping piece, and fixing the first clamping piece and the second clamping piece on the outer flange of the steel pipe section and the inner flange of the steel pipe section respectively, wherein the first clamping piece and the second clamping piece are arranged in the full length direction along the jacking direction;
step three, respectively fixing the steel pipe joint web plates to the outer flange of the steel pipe joint and the inner flange of the steel pipe joint to complete the whole manufacturing of the steel pipe joint;
jacking one steel pipe joint into the soil layer, and jacking the first clamping piece in the adjacent steel pipe joint along the second clamping piece in the steel pipe joint jacked into the soil layer;
step five, construction is carried out in sequence, and the subsequent jacking of the steel pipe joints is completed;
sixthly, completing the penetration of the prestressed steel strands through the corrugated pipe perforations arranged on the steel pipe joint web plates;
and seventhly, grouting among the steel pipe joints, and stretching the prestressed steel strands to enable the plurality of steel pipe joints to form a structural whole after the grout is gradually solidified.
2. The construction method for providing shear-resisting bearing capacity for the gapped discrete steel structure tube rows according to claim 1, wherein in the second step, the first clamping piece and the second clamping piece are respectively welded and fixed on the outer flange and the inner flange of the steel tube joint through fillet welds.
3. The method of claim 1, wherein the steel tube joint webs are welded and fixed to the steel tube joint outer flanges and the steel tube joint inner flanges in the third step.
4. The method of claim 1, wherein the first and second clips are disposed along a length of the tube row in the pushing direction, the first clip is a male clip, and the second clip is a female clip.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110493423.1A CN113202508A (en) | 2021-05-07 | 2021-05-07 | Construction method for providing shear-resistant bearing capacity for gapped discrete steel structure pipe row |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110493423.1A CN113202508A (en) | 2021-05-07 | 2021-05-07 | Construction method for providing shear-resistant bearing capacity for gapped discrete steel structure pipe row |
Publications (1)
Publication Number | Publication Date |
---|---|
CN113202508A true CN113202508A (en) | 2021-08-03 |
Family
ID=77030268
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110493423.1A Pending CN113202508A (en) | 2021-05-07 | 2021-05-07 | Construction method for providing shear-resistant bearing capacity for gapped discrete steel structure pipe row |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113202508A (en) |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20040027252A (en) * | 2002-11-22 | 2004-04-01 | (주)현이앤씨 | Construction and design method about center wall of three arch tunnel excavation method |
CN203222896U (en) * | 2013-04-24 | 2013-10-02 | 中国建筑东北设计研究院有限公司 | Plane outer joint of steel girder and thin concrete sheer wall |
CN104806274A (en) * | 2015-04-20 | 2015-07-29 | 中建南方投资有限公司 | Large-span long-distance underground space main body supporting integrated structure and construction method |
CN107100653A (en) * | 2017-05-23 | 2017-08-29 | 中铁四局集团第五工程有限公司 | A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station |
CN206607710U (en) * | 2017-03-10 | 2017-11-03 | 西安建筑科技大学 | Steel plate wall construction built in a kind of assembled Self-resetting Concrete Filled Square Steel Tubular Frame |
CN208309831U (en) * | 2018-05-14 | 2019-01-01 | 常州工程职业技术学院 | A kind of prefabricated steel tube shear rotary plug-in type connection structure |
CN110410091A (en) * | 2019-07-29 | 2019-11-05 | 东北大学 | A kind of New pipe curtain structure being laid with underground utilities and its construction method |
CN111305422A (en) * | 2020-05-11 | 2020-06-19 | 中国船舶重工集团国际工程有限公司 | Assembled prestress buckling-restrained short-leg box-shaped thin steel plate shear wall structure and construction method |
KR102219072B1 (en) * | 2020-07-21 | 2021-02-23 | (유)미래건설 | Construction Method of Bridge Structures Using Segmented Preflex Girders and Segmented Preflex Girder |
-
2021
- 2021-05-07 CN CN202110493423.1A patent/CN113202508A/en active Pending
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20040027252A (en) * | 2002-11-22 | 2004-04-01 | (주)현이앤씨 | Construction and design method about center wall of three arch tunnel excavation method |
CN203222896U (en) * | 2013-04-24 | 2013-10-02 | 中国建筑东北设计研究院有限公司 | Plane outer joint of steel girder and thin concrete sheer wall |
CN104806274A (en) * | 2015-04-20 | 2015-07-29 | 中建南方投资有限公司 | Large-span long-distance underground space main body supporting integrated structure and construction method |
CN206607710U (en) * | 2017-03-10 | 2017-11-03 | 西安建筑科技大学 | Steel plate wall construction built in a kind of assembled Self-resetting Concrete Filled Square Steel Tubular Frame |
CN107100653A (en) * | 2017-05-23 | 2017-08-29 | 中铁四局集团第五工程有限公司 | A kind of flat top wall pipe curtain structure builds the construction method of super Shallow Covered Metro Station |
CN208309831U (en) * | 2018-05-14 | 2019-01-01 | 常州工程职业技术学院 | A kind of prefabricated steel tube shear rotary plug-in type connection structure |
CN110410091A (en) * | 2019-07-29 | 2019-11-05 | 东北大学 | A kind of New pipe curtain structure being laid with underground utilities and its construction method |
CN111305422A (en) * | 2020-05-11 | 2020-06-19 | 中国船舶重工集团国际工程有限公司 | Assembled prestress buckling-restrained short-leg box-shaped thin steel plate shear wall structure and construction method |
KR102219072B1 (en) * | 2020-07-21 | 2021-02-23 | (유)미래건설 | Construction Method of Bridge Structures Using Segmented Preflex Girders and Segmented Preflex Girder |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107060140B (en) | Prefabricated double-steel-tube concrete shear wall and assembling method thereof | |
WO2017045425A1 (en) | Steel-concrete composite tunnel lining support structure and manufacturing and construction method thereof | |
CN109958445B (en) | Scaffold construction method for ultra-shallow large underground space | |
CN112780304B (en) | Strong-rigidity low-reinforcement prestress shield tunnel structure and construction method thereof | |
CN110284723B (en) | Composite structure for sleeving hollow pile on periphery of existing pile and construction method thereof | |
CN113417300B (en) | Slope support system and construction method thereof | |
CN113502835A (en) | Wet cellular assembled gridwork roof beam slope protection structure of connecting | |
CN113202518A (en) | Assembled corrugated steel-filling layer composite tunnel supporting system and construction method thereof | |
CN113202508A (en) | Construction method for providing shear-resistant bearing capacity for gapped discrete steel structure pipe row | |
CN108915768B (en) | Fixing force transmission support system for thermodynamic pipeline in thermodynamic shield tunnel | |
CN210529747U (en) | Composite assembly type integral prefabricated middle longitudinal beam of subway station and node of longitudinal beam and steel upright post | |
KR101684389B1 (en) | PHC Pile having Steel Bands, Retaining Wall using such PHC Piles, and Constructing Method of such Retaining Wall | |
CN116497856A (en) | Construction method of prefabricated assembly shaft | |
CN114197511B (en) | Assembly type steel reinforced concrete light foundation and assembly method thereof | |
CN214657227U (en) | Top-down shaft channel for constructing ultra-deep shaft by reverse construction method | |
CN213476893U (en) | Supporting structure for spanning large underground pipeline foundation pit | |
CN211547686U (en) | Prestressed concrete-filled steel tube pipe curtain structure based on prefabricated concrete-filled steel tube connection | |
CN211816415U (en) | Subway station side wall construction crack control prestressing force structure | |
CN211285686U (en) | Underpinning structure for pile foundation in hole | |
CN114086983A (en) | Combined reinforcing system for weak medium rock wall of extra-large-section branch tunnel | |
CN113090277A (en) | Batch jacking discrete pipe row uninterrupted tensioning forming integral frame and construction method | |
CN111485560A (en) | Deep foundation pit supporting structure under ultra-wide pipeline and deep foundation pit construction method under ultra-wide pipeline | |
CN214145512U (en) | Subway tunnel concrete member | |
CN113339004B (en) | Construction method of prestressed steel structure advanced support | |
CN219772980U (en) | Underground combined supporting structure of deep foundation pit adjacent building |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20210803 |