CN107060140B - Prefabricated double-steel-tube concrete shear wall and assembling method thereof - Google Patents

Prefabricated double-steel-tube concrete shear wall and assembling method thereof Download PDF

Info

Publication number
CN107060140B
CN107060140B CN201710373977.1A CN201710373977A CN107060140B CN 107060140 B CN107060140 B CN 107060140B CN 201710373977 A CN201710373977 A CN 201710373977A CN 107060140 B CN107060140 B CN 107060140B
Authority
CN
China
Prior art keywords
concrete
steel
tube
wall
concrete wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710373977.1A
Other languages
Chinese (zh)
Other versions
CN107060140A (en
Inventor
周靖
方小丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
South China University of Technology SCUT
Original Assignee
South China University of Technology SCUT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by South China University of Technology SCUT filed Critical South China University of Technology SCUT
Priority to CN201710373977.1A priority Critical patent/CN107060140B/en
Publication of CN107060140A publication Critical patent/CN107060140A/en
Priority to PCT/CN2017/115600 priority patent/WO2018214477A1/en
Priority to AU2017415961A priority patent/AU2017415961B2/en
Application granted granted Critical
Publication of CN107060140B publication Critical patent/CN107060140B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/562Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with fillings between the load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/58Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of metal
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements

Abstract

The invention discloses a prefabricated double-steel-tube concrete shear wall and an assembly method thereof; comprises an outer steel pipe buried in a concrete wall; the steel bar net is embedded in the concrete wall and is formed by interweaving tie steel bars, vertically distributed steel bars and horizontally distributed steel bars; the upper end and the lower end of the outer steel pipe partially extend out of the upper part and the lower part of the concrete wall; an inner steel pipe is sleeved inside the outer steel pipe; the inner steel tube is internally filled with a high-strength concrete column; the parts of the outer steel tube and the inner steel tube, which extend out of the concrete wall, are radially penetrated and fixed through transverse bolts and are used for preventing relative movement between the outer steel tube and the inner steel tube in the axial direction and the circumferential direction. The double-steel-tube concrete shear wall has the advantages of quick and reliable vertical connection, simple construction process, high horizontal shear bearing capacity, good integrity, high out-of-plane stability, good earthquake resistance, short construction period and standardized production of most components.

Description

Prefabricated double-steel-tube concrete shear wall and assembling method thereof
Technical Field
The invention relates to the technical field of prefabricated concrete structures in structural engineering, in particular to a prefabricated double-steel-tube concrete shear wall and an assembly method thereof.
Background
The joint connection technology is a key technology for guaranteeing the integrity and the earthquake resistance of the prefabricated concrete structure. The traditional prefabricated assembled shear wall or the prefabricated assembled steel tube concrete shear wall horizontal joint is mainly connected by sleeve grouting or slurry anchor lap joint of vertical steel bars, the vertical steel bar connection structure is complex, the construction process requirement is high, the assembly quality control difficulty is high, the construction period is long, the cost is high, the advantages of an assembled shear wall structure can not be fully exerted, and the building height is greatly limited; the steel pipe concrete column is adopted as a connection design, but the steel pipes are in non-through continuous rigid connection, so that the bending resistance of the steel pipe concrete embedded column is difficult to volatilize, the structural integrity is not strong, the out-of-plane eccentric stability is not high, and the anti-seismic performance of the assembled steel pipe concrete shear wall is seriously reduced.
At present, related researches are carried out on the prefabricated steel tube concrete frame shear wall and the vertical reinforcement connection method thereof in China, but a technical method capable of fundamentally and obviously changing the integrity and the out-of-plane stability of the prefabricated steel tube concrete frame shear wall structure is not provided, and the anti-seismic performance of the prefabricated steel tube concrete frame shear wall structure is limited by a horizontal joint connection technology. The prefabricated assembly rate of the high-rise structure is an important index for measuring the industrial development level of buildings in China in the future, and the development and the proposal of the prefabricated assembly type shear wall which can be suitable for the high-rise structure and even the super high-rise structure become urgent demands.
Disclosure of Invention
The invention aims to overcome the defects and the shortcomings of the prior art and provide a prefabricated double-steel-tube concrete shear wall and an assembly method thereof. The vertical connection is quick and reliable, the construction process is simple, the horizontal shear bearing capacity is high, the integrity is good, the out-of-plane stability is high, the anti-seismic performance is good, the construction period is short, and most of components can be produced in a standardized way.
The invention is realized by the following technical scheme:
a prefabricated double-steel-tube concrete shear wall comprises the following components:
an outer steel pipe 3 embedded in the concrete wall 4;
the steel bar net is embedded in the concrete wall 4 and is formed by interweaving tie steel bars 9, vertically distributed steel bars 7 and horizontally distributed steel bars 8;
the upper and lower ends of the outer steel pipe 3 partially extend out of the upper and lower parts of the concrete wall 4;
an inner steel pipe 1 is sleeved in the outer steel pipe 3; the inner steel tube 1 is internally filled with a high-strength concrete column 2;
the parts of the outer steel tube 3 and the inner steel tube 1 extending out of the concrete wall 4 are radially penetrated and fixed through the transverse bolts 11 and used for preventing relative movement between the two in the axial direction and the circumferential direction.
The outer steel pipes 3 are arranged in a row and are buried in the concrete wall 4 at intervals.
The outer wall of the outer steel pipe 3 is provided with a plurality of shearing ring ribs 10 along the axial direction of the outer steel pipe 3.
The lower part interval of the concrete wall 4 is buried with a plurality of vertical steel bar sleeves 6, and the upper part interval is buried with a plurality of vertical connecting steel bars 5.
The lengths of the parts of the outer steel pipe 3 and the inner steel pipe 1 extending out of the concrete wall 4 are 80 mm-120 mm.
The spacing distance between the shearing ring ribs 10 is 500 mm-1000 mm.
The assembly method of the prefabricated double-steel-tube concrete shear wall during construction is as follows:
mounting of the concrete wall 4 of the first layer:
fixedly mounting a concrete wall 4 on a reinforced concrete foundation cast in situ on a foundation;
the exposed part of the outer steel tube 3 at the lower part of the concrete wall 4 is embedded into the reinforced concrete foundation;
installation of the concrete wall 4 of the second layer:
butting a vertical steel bar sleeve 6 at the lower part of the concrete wall 4 of the second layer with a vertical connecting steel bar 5 at the upper part of the concrete wall 4 of the first layer, namely inserting the vertical steel bar sleeve 6 into the vertical connecting steel bar 5, aligning the outer steel tube 3 with the inner steel tube 1 at the moment, welding the joint of the outer steel tube 3 and the inner steel tube 1, and radially penetrating and fixing the parts of the outer steel tube 3 and the inner steel tube 1 extending out of the concrete wall 4 through transverse bolts 11 to prevent relative axial and circumferential movement between the two parts;
and (3) floor slab installation:
installing a prefabricated part of the floor slab 12 on the upper edge surface of the first layer of concrete wall 4, namely between the first layer of concrete wall and the second layer of concrete wall, and connecting prefabricated reinforcing steel bars at the end parts of the floor slab 12 with the concrete wall 4; pouring concrete at the joint between the first layer and the second layer of concrete walls 4 and the floor slab 12 to finish the construction of the grout layer, and simultaneously finishing the cast-in-situ part of the floor slab 12 to form the whole of the upper layer and the lower layer of concrete walls 4 adjacent to the floor slab 12; and (5) sequentially circulating to finish the whole prefabricated double-steel-tube concrete shear wall.
After each 2 to 3 floors are assembled, concrete is poured into the inner steel pipe 1, and so on.
Compared with the prior art, the invention has the following advantages and effects:
the assembled double-steel-tube concrete shear wall with 'partial prefabrication and partial cast-in-situ' takes an inner steel tube 1 and a high-strength concrete column 2 in the inner steel tube 1 which are manufactured by 'partial cast-in-situ' as a component for connecting adjacent upper and lower 'partial prefabrication' concrete shear walls, so that a prefabricated concrete shear wall module is formed into a whole which is completely sleeved on the steel tube high-strength concrete column, and the integrity and out-of-plane compression stability of the prefabricated concrete shear wall structure are obviously improved; the continuous steel tube high-strength concrete column has higher compression resistance, shearing resistance and bending resistance, and can obviously improve the horizontal shearing resistance and the bending resistance of the horizontal connecting joint of the precast concrete shear wall; the integrity and the compression stability are improved, so that the precast concrete shear wall has good anti-seismic energy consumption performance and redundant elastoplastic deformation capacity, the advantages of the concrete shear wall in high-rise structural application are fully exerted, and the construction height of the precast assembled shear wall structure is improved; the through steel pipe high-strength concrete column is adopted, vertical connecting steel bars are reduced or even cancelled, the construction process is simplified, and the construction quality of the prefabricated concrete shear wall is ensured.
Drawings
FIG. 1 is a schematic cross-sectional view of a prefabricated double steel pipe concrete shear wall of the present invention.
Fig. 2 is a schematic cross-sectional view of the outer steel pipe 3 and the inner steel pipe 1.
FIG. 3 is a schematic view of the cross-sectional B-B structure of FIG. 1.
FIG. 4 is an enlarged schematic view of a portion of the connection of the inner and outer steel pipes between the upper and lower concrete walls 4; in the figure, F represents a weld.
Fig. 5 is a schematic view of the C-C cross-sectional structure of fig. 4.
Detailed Description
The present invention will be described in further detail with reference to specific examples.
Examples
As shown in fig. 1 to 5. The invention discloses a prefabricated double-steel-tube concrete shear wall, which comprises an outer steel tube 3 embedded in a concrete wall 4 (prefabricated concrete shear wall); the steel bar net is embedded in the concrete wall 4 and is formed by interweaving tie steel bars 9, vertically distributed steel bars 7 and horizontally distributed steel bars 8;
the upper and lower ends of the outer steel pipe 3 partially extend out of the upper and lower parts of the concrete wall 4;
an inner steel pipe 1 is sleeved in the outer steel pipe 3; the inner steel tube 1 is internally filled with a high-strength concrete column 2;
the parts of the outer steel tube 3 and the inner steel tube 1 extending out of the concrete wall 4 are radially penetrated and fixed through the transverse bolts 11 and used for preventing relative movement between the two in the axial direction and the circumferential direction.
The outer steel pipes 3 are arranged in a row and are buried in the concrete wall 4 at intervals.
The outer wall of the outer steel pipe 3 is provided with a plurality of shearing ring ribs 10 along the axial direction of the outer steel pipe 3.
The lower part interval of the concrete wall 4 is buried with a plurality of vertical steel bar sleeves 6, and the upper part interval is buried with a plurality of vertical connecting steel bars 5.
The lengths of the parts of the outer steel pipe 3 and the inner steel pipe 1 extending out of the concrete wall 4 are 80 mm-120 mm.
The spacing distance between the shearing ring ribs 10 is 500 mm-1000 mm.
The concrete column in the inner steel pipe 1 is poured on the construction site. The outer steel pipes 3 are arranged at a pitch of 2 to 6 times the diameter thereof.
The concrete shear wall with the outer steel pipes outside the periphery is prefabricated in a factory and transported to field splicing, two steel bar nets consisting of vertically distributed steel bars 7 and horizontally distributed steel bars 8 are arranged in the wall, the two steel bar nets are tied by tie bars 9, a small amount of vertical connecting steel bars 5 are pre-embedded in the upper part of the concrete wall 4, a small amount of vertical connecting steel bar sleeves 6 are reserved in the lower part of the concrete wall, grouting holes are reserved in the lower part of the concrete wall, shearing ring ribs 10 are welded on the circumference at intervals of 500 mm-1000 mm in an adhering mode on the outer steel pipes 3 embedded in the concrete wall 4, the outer steel pipes 3 embedded in the wall are prefabricated with the concrete wall 4 synchronously, the outer steel pipes 3 extend out of the upper edge surface and the lower edge surface of the wall by 80 mm-120 mm, fastening holes of transverse bolts 11 are reserved, and the outer steel pipes 3 facilitate the concrete columns of the inner steel pipes to penetrate and have enough sliding spaces.
The assembly method of the prefabricated double-steel-tube concrete shear wall in construction is as follows:
mounting of the concrete wall 4 of the first layer:
fixedly mounting a concrete wall 4 on a reinforced concrete foundation cast in situ on a foundation;
the exposed part of the outer steel tube 3 at the lower part of the concrete wall 4 is embedded into the reinforced concrete foundation;
installation of the concrete wall 4 of the second layer:
butting a vertical steel bar sleeve 6 at the lower part of the concrete wall 4 of the second layer with a vertical connecting steel bar 5 at the upper part of the concrete wall 4 of the first layer, namely inserting the vertical steel bar sleeve 6 into the vertical connecting steel bar 5, aligning the outer steel tube 3 with the inner steel tube 1 at the moment, welding the joint of the outer steel tube 3 and the inner steel tube 1, and radially penetrating and fixing the parts of the outer steel tube 3 and the inner steel tube 1 extending out of the concrete wall 4 through transverse bolts 11 to prevent relative axial and circumferential movement between the two parts;
floor (prefabricated composite floor) installation:
installing a prefabricated part of the floor slab 12 on the upper edge surface of the first layer of concrete wall 4, namely between the first layer of concrete wall and the second layer of concrete wall, and connecting prefabricated reinforcing steel bars at the end parts of the floor slab 12 with the concrete wall 4; pouring concrete at the joint between the first layer and the second layer of concrete walls 4 and the floor slab 12 to finish the construction of the grout layer, and simultaneously finishing the cast-in-situ part of the floor slab 12 to form the whole of the upper layer and the lower layer of concrete walls 4 adjacent to the floor slab 12; and (5) sequentially circulating to finish the whole prefabricated double-steel-tube concrete shear wall.
After each 2 to 3 floors are assembled, concrete is poured into the inner steel pipe 1, and so on.
As described above, the present invention can be preferably realized.
The embodiments of the present invention are not limited to the above examples, and any other changes, modifications, substitutions, combinations, and simplifications that do not depart from the spirit and principles of the invention should be made and equivalents should be construed as falling within the scope of the invention.

Claims (3)

1. The assembly method of the prefabricated double-steel-tube concrete shear wall during construction is characterized by being realized based on the prefabricated double-steel-tube concrete shear wall, and the prefabricated double-steel-tube concrete shear wall comprises the following components:
an outer steel pipe (3) embedded in the concrete wall (4);
the steel bar net is embedded in the concrete wall (4) and is formed by interweaving tie steel bars (9), vertically distributed steel bars (7) and horizontally distributed steel bars (8);
the upper end and the lower end of the outer steel pipe (3) partially extend out of the upper part and the lower part of the concrete wall (4);
an inner steel pipe (1) is sleeved in the outer steel pipe (3); the inner steel tube (1) is internally filled with a high-strength concrete column (2);
the parts of the outer steel tube (3) and the inner steel tube (1) extending out of the concrete wall (4) are radially penetrated and fixed through transverse bolts (11) and used for preventing relative axial and circumferential movement between the two parts;
the outer steel pipes (3) are arranged in rows and are buried in the concrete wall (4) at intervals; the outer wall of the outer steel pipe (3) is provided with a plurality of shearing ring ribs (10) along the axial direction of the outer steel pipe (3);
a plurality of vertical steel bar sleeves (6) are buried at intervals at the lower part of the concrete wall (4), and a plurality of vertical connecting steel bars (5) are buried at intervals at the upper part of the concrete wall;
the assembly steps are as follows:
mounting of the concrete wall (4) of the first layer:
fixedly mounting a concrete wall (4) on a reinforced concrete foundation cast in situ on a foundation;
the exposed part of the outer steel pipe (3) at the lower part of the concrete wall (4) is embedded into the reinforced concrete foundation;
mounting of the concrete wall (4) of the second layer:
butting a vertical steel bar sleeve (6) at the lower part of the concrete wall (4) of the second layer with a vertical connecting steel bar (5) at the upper part of the concrete wall (4) of the first layer, namely inserting the vertical steel bar sleeve (6) into the vertical connecting steel bar (5), aligning the outer steel tube (3) with the inner steel tube (1) at the moment, welding the joint of the outer steel tube (3) and the inner steel tube (1), and radially penetrating and fixing the parts, extending out of the concrete wall (4), of the outer steel tube (3) and the inner steel tube (1) through transverse bolts (11) to prevent relative axial and circumferential movement between the two parts;
and (3) floor slab installation:
installing a prefabricated part of a floor slab (12) on the upper edge surface of the first layer of concrete wall (4), namely between the first layer of concrete wall and the second layer of concrete wall, and connecting prefabricated reinforced bars at the end part of the floor slab (12) with the concrete wall (4); pouring concrete at the joint between the first layer and the second layer of concrete walls (4) and the floor (12) to finish the construction of the grout layer, and simultaneously finishing the cast-in-situ part of the floor (12) to ensure that the upper layer and the lower layer of concrete walls (4) adjacent to the floor (12) form a whole;
sequentially circulating to complete the assembly of each layer of whole prefabricated double-steel-tube concrete shear wall;
after the assembly of 2 to 3 floors is completed, concrete is poured into the inner steel pipe (1), and so on.
2. The method for assembling the prefabricated double-steel-tube concrete shear wall in construction according to claim 1, which is characterized in that: the lengths of the parts of the outer steel pipe (3) and the inner steel pipe (1) extending out of the concrete wall (4) are 80-120 mm.
3. The method for assembling the prefabricated double-steel-tube concrete shear wall in construction according to claim 1, which is characterized in that: the spacing distance between the shearing ring ribs (10) is 500 mm-1000 mm.
CN201710373977.1A 2017-05-24 2017-05-24 Prefabricated double-steel-tube concrete shear wall and assembling method thereof Active CN107060140B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201710373977.1A CN107060140B (en) 2017-05-24 2017-05-24 Prefabricated double-steel-tube concrete shear wall and assembling method thereof
PCT/CN2017/115600 WO2018214477A1 (en) 2017-05-24 2017-12-12 Prefabricated dual-steel-tube concrete shear wall, and assembly method therefor
AU2017415961A AU2017415961B2 (en) 2017-05-24 2017-12-12 Prefabricated dual-steel-tube concrete shear wall, and assembly method therefor

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710373977.1A CN107060140B (en) 2017-05-24 2017-05-24 Prefabricated double-steel-tube concrete shear wall and assembling method thereof

Publications (2)

Publication Number Publication Date
CN107060140A CN107060140A (en) 2017-08-18
CN107060140B true CN107060140B (en) 2023-09-26

Family

ID=59610525

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710373977.1A Active CN107060140B (en) 2017-05-24 2017-05-24 Prefabricated double-steel-tube concrete shear wall and assembling method thereof

Country Status (3)

Country Link
CN (1) CN107060140B (en)
AU (1) AU2017415961B2 (en)
WO (1) WO2018214477A1 (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107060140B (en) * 2017-05-24 2023-09-26 华南理工大学 Prefabricated double-steel-tube concrete shear wall and assembling method thereof
CN108005309B (en) * 2017-12-06 2023-10-20 华南理工大学 Prefabricated assembled embedded steel sleeve connecting concrete column and assembling method thereof
CN108316514B (en) * 2018-03-12 2023-07-18 华南理工大学 Self-resetting prefabricated concrete swinging wall and assembling method thereof
CN109555112A (en) * 2018-12-04 2019-04-02 中国建筑股份有限公司 A kind of structure superposition formula diaphram wall and construction method
CN109898651A (en) * 2018-12-12 2019-06-18 中建四局第六建筑工程有限公司 The connection structure and construction method of antidetonation steel pipe in a kind of shear wall
CN109577176B (en) * 2019-01-30 2024-04-23 深圳市市政设计研究院有限公司福建分公司 Composite connection type concrete filled steel tube pier and construction method thereof
CN110029749A (en) * 2019-04-08 2019-07-19 中建科技有限公司深圳分公司 Overlapped shear wall
CN110439119A (en) * 2019-07-18 2019-11-12 南京长江都市建筑设计股份有限公司 A kind of outer filling wall construction with lateral connection node
CN110468966B (en) * 2019-08-29 2021-08-24 内蒙古科技大学 Steel plate concrete wall and steel beam joint based on assembled type crossed U-shaped connecting piece
CN112302165A (en) * 2020-10-16 2021-02-02 上海市建筑科学研究院有限公司 Box-shaped sleeve type connecting structure of assembled concrete member, construction method and application
CN112681568B (en) * 2020-12-25 2022-04-05 重庆涛扬绿建科技有限公司 Full-prefabricated steel tube concrete shear wall and building structure system
CN112942639A (en) * 2021-04-07 2021-06-11 碧源建工有限公司 Construction method for embedding temporary water supply pipe and temporary power main cable shear wall
CN113958038A (en) * 2021-09-26 2022-01-21 中国三冶集团有限公司 L-shaped steel pipe concrete short-limb shear wall
CN113914350B (en) * 2021-10-26 2023-02-10 中交第四航务工程勘察设计院有限公司 Prefabricated concrete foundation structure and installation method thereof
CN115419177B (en) * 2022-10-13 2024-03-19 吴承辉 Precast concrete shear wall building structure and construction method thereof
CN115434451B (en) * 2022-10-19 2023-08-18 华北理工大学 Assembled concrete connection structure and construction method
CN115492249A (en) * 2022-10-29 2022-12-20 安徽建工集团股份有限公司 Dry-type connection structure of prefabricated post of modularization box-type building and foundation slab

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07139057A (en) * 1993-11-15 1995-05-30 Tokyu Koken Kk Jointing method for precast concrete wall construction
CN202073208U (en) * 2011-04-28 2011-12-14 华南理工大学建筑设计研究院 Concrete-filled steel tube shear wall
CN102409782A (en) * 2011-11-28 2012-04-11 北京工业大学 Steel tube concrete frame inbuilt steel plate shear wall with soft steel sleeves at bottom and producing method of steel tube concrete frame inbuilt steel plate shear wall
CN102409783A (en) * 2011-11-28 2012-04-11 北京工业大学 Bottom double composite section steel shear wall with reinforced concrete frame and inside-hidden steel plate as well as manufacturing method
CN106639052A (en) * 2017-01-18 2017-05-10 陕西省建筑设计研究院有限责任公司 Fabricated structural system of steel plate reinforced concrete shear walls and construction method of fabricated structural system
CN206829416U (en) * 2017-05-24 2018-01-02 华南理工大学 A kind of prefabricated assembled double steel pipe concrete shear force wall

Family Cites Families (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2836005B2 (en) * 1994-02-17 1998-12-14 株式会社シェルター Building
JPH1025840A (en) * 1996-07-11 1998-01-27 Fujita Corp Constructing method for building frame with precast anti-seismic wall
KR20050009086A (en) * 2003-07-15 2005-01-24 유승룡 Constructing method of prefabricated bearing wall and wall member therefor
CN101881056B (en) * 2010-06-11 2011-12-07 北京工业大学 Internal division type laminated column frame-bilayer steel plate concrete combined shear wall and manufacturing method thereof
CN102127941B (en) * 2010-12-10 2012-11-14 清华大学 Steel tube concrete column-double-layer steel plate combined shear wall and construction method thereof
CN102561553B (en) * 2012-03-05 2013-12-25 河北联合大学 Prefabricated concrete-filled steel tube frame-shear wall and construction method thereof
CN103790265B (en) * 2014-01-28 2016-02-17 江苏建筑职业技术学院 A kind of prefabricated assembled steel tube concrete core pillar is put more energy into the making assembly method of shear wall
CN204418422U (en) * 2015-01-06 2015-06-24 深圳大学 A kind of combined concrete shear wall
CN106639040B (en) * 2016-10-13 2019-02-19 哈尔滨工业大学 Elongated hole precast shear wall and its construction method is perfused after vertical muscle boundling
CN106284844A (en) * 2016-10-13 2017-01-04 沈阳建筑大学 A kind of concrete-filled double skin steel tube superposed column and preparation method thereof
CN107060140B (en) * 2017-05-24 2023-09-26 华南理工大学 Prefabricated double-steel-tube concrete shear wall and assembling method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07139057A (en) * 1993-11-15 1995-05-30 Tokyu Koken Kk Jointing method for precast concrete wall construction
CN202073208U (en) * 2011-04-28 2011-12-14 华南理工大学建筑设计研究院 Concrete-filled steel tube shear wall
CN102409782A (en) * 2011-11-28 2012-04-11 北京工业大学 Steel tube concrete frame inbuilt steel plate shear wall with soft steel sleeves at bottom and producing method of steel tube concrete frame inbuilt steel plate shear wall
CN102409783A (en) * 2011-11-28 2012-04-11 北京工业大学 Bottom double composite section steel shear wall with reinforced concrete frame and inside-hidden steel plate as well as manufacturing method
CN106639052A (en) * 2017-01-18 2017-05-10 陕西省建筑设计研究院有限责任公司 Fabricated structural system of steel plate reinforced concrete shear walls and construction method of fabricated structural system
CN206829416U (en) * 2017-05-24 2018-01-02 华南理工大学 A kind of prefabricated assembled double steel pipe concrete shear force wall

Also Published As

Publication number Publication date
WO2018214477A1 (en) 2018-11-29
AU2017415961B2 (en) 2020-09-03
AU2017415961A1 (en) 2019-07-18
CN107060140A (en) 2017-08-18

Similar Documents

Publication Publication Date Title
CN107060140B (en) Prefabricated double-steel-tube concrete shear wall and assembling method thereof
CN106836479B (en) Assembled prestressed concrete frame structure
CN108005309B (en) Prefabricated assembled embedded steel sleeve connecting concrete column and assembling method thereof
CN108252424B (en) Connecting structure and method between prefabricated steel reinforced concrete columns
CN105544801A (en) Bolted connection technique for prefabricated large plate shear wall provided with concealed bracing and construction method
CN109252727B (en) Shock insulation layer rubber support, column, beam and plate system integrated assembly node and method
CN105735469A (en) Partially-bonded precast prestressed concrete frame structure
CN108678218B (en) Assembly type concrete shear wall based on multipurpose thin-wall steel pipe and construction method thereof
CN108775084B (en) Steel-concrete combined precast beam and precast column connecting structure and construction method
CN107355008B (en) Prefabricated connection structure and method for newly added concrete filled steel tubular column and existing structure
CN114319977B (en) Steel pipe concrete row column type connection precast shear wall structure and construction method
CN208105477U (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam L shape connecting node
CN206769200U (en) First wear formula post stretching vertical prestressing cast-in-place concrete rod structure
CN206829416U (en) A kind of prefabricated assembled double steel pipe concrete shear force wall
CN108265823A (en) Assembly concrete-filled steel tube column-isolated footing-concrete collar tie beam L-shaped connecting node
CN112942632A (en) Easy-to-process, assemble and decorate steel beam shear wall system with good stress
CN109267489B (en) Construction method for cable-stayed bridge cable tower anchoring area
CN204781443U (en) Device for connecting precast shear wall concatenation about being used for
CN115928882A (en) Assembled composite structure hybrid connection node suitable for coastal region
CN115045181A (en) Socket joint type node connection method and structure for prefabricated pier column and bearing platform in middle and high intensity region
CN113775050A (en) Assembly type flange steel-concrete combined beam-column joint, structure system and installation method
CN210713925U (en) Reinforced structure based on frame core section of thick bamboo rearmounted steel construction
CN108755939B (en) Composite connection assembling type building structure
CN107542185B (en) Bending shear type combined key slot connecting structure of assembly frame shear structure and assembly method
CN111962953A (en) Steel tube concrete column-H-shaped steel beam-steel support-pi-shaped connecting piece combined side column middle node and manufacturing method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant