CN105735469A - Partially-bonded precast prestressed concrete frame structure - Google Patents

Partially-bonded precast prestressed concrete frame structure Download PDF

Info

Publication number
CN105735469A
CN105735469A CN201610096784.1A CN201610096784A CN105735469A CN 105735469 A CN105735469 A CN 105735469A CN 201610096784 A CN201610096784 A CN 201610096784A CN 105735469 A CN105735469 A CN 105735469A
Authority
CN
China
Prior art keywords
concrete
prestressed
precast
post
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610096784.1A
Other languages
Chinese (zh)
Other versions
CN105735469B (en
Inventor
薛伟辰
胡翔
孙哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tongji University
Original Assignee
Tongji University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tongji University filed Critical Tongji University
Priority to CN201610096784.1A priority Critical patent/CN105735469B/en
Publication of CN105735469A publication Critical patent/CN105735469A/en
Application granted granted Critical
Publication of CN105735469B publication Critical patent/CN105735469B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • E—FIXED CONSTRUCTIONS
    • E04—BUILDING
    • E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/22—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material with parts being prestressed

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The invention relates to a partially-bonded precast prestressed concrete frame structure. The partially-bonded precast prestressed concrete frame structure is composed of prestressed tendons, precast concrete columns, precast concrete beams, precast concrete boards, post-poured concrete composite layers and post-poured concrete joint core areas. Carbon fiber reinforced plastic (CFRP) prestressed tendons are adopted as the prestressed tendons, and the prestressed tendons are distributed in a curve-shaped mode and constructed in a partially-bonded mode. The prestressed tendons are constructed through a post tension process and penetrate through the joint core areas. Lower longitudinal bars of every two adjacent precast concrete beams are connected through welding or a sleeve. Upper longitudinal bars of the precast concrete beams are arranged on the composite layers and bound on the site. A plurality of layers of precast columns are adopted for constructing the precast concrete columns. The precast concrete beams and the precast concrete columns are connected with the post-poured concrete joint core areas through the post-poured concrete composite layers. All the precast concrete columns, the precast concrete beams and the precast concrete boards in the partially-bonded precast prestressed concrete frame structure can be obtained through standardized production in a factory so that the effect that the partially-bonded precast prestressed concrete frame structure has good stress performance can be ensured, the partially-bonded precast prestressed concrete frame structure has the advantages of being simple in construction, high in construction speed and the like and has wide application prospects in the architectural engineering field.

Description

一种部分粘结预制预应力混凝土框架结构A Partially Bonded Prefabricated Prestressed Concrete Frame Structure

技术领域technical field

本发明属于土木工程技术领域,具体涉及一种部分粘结预制预应力混凝土框架结构。The invention belongs to the technical field of civil engineering, and in particular relates to a partially bonded prefabricated prestressed concrete frame structure.

背景技术Background technique

预制预应力框架结构体系指在预制混凝土框架结构的基础上,对节点和框架梁施加预应力所形成的结构体系。该框架结构体系能够实现大跨度,且施工速度快、质量好、可大量节省模板和支撑。是一种符合产业化发展需要、可实现节能与结构一体化的结构体系。The prefabricated prestressed frame structure system refers to the structural system formed by applying prestress to the nodes and frame beams on the basis of the prefabricated concrete frame structure. The frame structure system can achieve a large span, and the construction speed is fast, the quality is good, and a large amount of templates and supports can be saved. It is a structural system that meets the needs of industrialization development and can realize energy saving and structural integration.

现有的预制预应力框架结构体系有世构体系、PRESSS体系和预压装配式混凝土框架结构体系。世构体系由预制混凝土柱、先张法预应力叠合梁、预制混凝土板通过现浇混凝土连接而成,该体系中预应力筋未穿过节点核心区、为形成整体预应力体系。PRESSS体系采用后张无粘结预应力筋和普通钢筋进行连接,预应力筋穿过在梁纵向中轴线位置预留好的预应力筋孔道将柱的两侧横梁连接在一起,梁柱接缝填充砂浆。普通钢筋通过梁上下纵筋位置预留的孔道穿过柱子,并于现场灌浆。该体系预应力筋在梁截面中间布置,难以充分发挥其对于结构承载力的贡献。此外,无粘结预应力筋易发生因锚具破坏而导致的结构连续倒塌。预压装配式混凝土框架结构体系是通过后张、多段、无粘结直线预应力张拉成型的预制预应力混凝土框架结构。该体系预应力张拉施工复杂,无粘结预应力筋易发生因锚具破坏而导致的结构连续倒塌。The existing prefabricated prestressed frame structure systems include the world structure system, the PRESSS system and the preloaded prefabricated concrete frame structure system. The world structure system is composed of precast concrete columns, pretensioned prestressed composite beams, and precast concrete slabs connected by cast-in-place concrete. In this system, the prestressed tendons do not pass through the core area of the joints, forming an overall prestressed system. The PRESSS system uses post-tensioned unbonded prestressed tendons and ordinary steel bars for connection. The prestressed tendons pass through the prestressed tendon channel reserved at the longitudinal axis of the beam to connect the beams on both sides of the column together. The beam-column joint Fill with mortar. Ordinary steel bars pass through the columns through the holes reserved at the positions of the upper and lower longitudinal bars of the beams, and are grouted on site. The prestressed tendons of this system are arranged in the middle of the beam section, and it is difficult to give full play to their contribution to the structural bearing capacity. In addition, unbonded prestressed tendons are prone to progressive collapse of the structure due to anchor failure. The prestressed prefabricated concrete frame structure system is a prefabricated prestressed concrete frame structure formed by post-tensioning, multi-segment, unbonded linear prestressing tension. The prestressed tensioning construction of this system is complex, and the unbonded prestressed tendons are prone to continuous collapse of the structure caused by anchorage damage.

针对目前预制预应力混凝土框架结构存在的问题,本发明提出了一种预制预应力框架体系。该体系采用后浇整体式连接,预制混凝土梁、柱、板构件通过现浇混凝土和预应力形成可靠连接。相邻预制混凝土梁的下部纵筋通过焊接或套筒连接,预制混凝土梁的上部纵筋设置于叠合层并现场绑扎。预制混凝土柱采用多层预制柱构造。预应力筋采用后张工艺施工,并穿过节点核心区。预应力筋采用碳纤维增强塑料(CFRP)预应力筋,并根据设计内力将预应力筋布置为曲线形,以提高预应力筋的应用效率。预应力采用部分粘结构造,即在靠近节点的区域内将预应力筋套上内嵌黄油的塑料套管,待预应力筋张拉完成后灌浆,即可形成在靠近节点区域为无粘结、其他区域为有粘结的部分粘结构造。发明人完成的一系列试验研究表明这一构造结合了无粘结和全粘结两种粘结形式的优点,具有较高承载力,同时又改善了结构的延性和变形能力。Aiming at the problems existing in the current prefabricated prestressed concrete frame structure, the present invention proposes a prefabricated prestressed frame system. The system adopts post-cast integral connection, and prefabricated concrete beams, columns, and slab components form reliable connections through cast-in-place concrete and prestress. The lower longitudinal reinforcements of adjacent precast concrete beams are connected by welding or sleeves, and the upper longitudinal reinforcements of precast concrete beams are arranged in the superimposed layer and bound on site. Precast concrete columns are constructed using multi-layer precast columns. The prestressed tendons are constructed by post-tensioning technology and pass through the core area of the joint. The prestressed tendons are made of carbon fiber reinforced plastic (CFRP) prestressed tendons, and the prestressed tendons are arranged in a curved shape according to the design internal force to improve the application efficiency of the prestressed tendons. The prestress adopts a partially bonded structure, that is, the prestressed tendon is covered with a plastic sleeve embedded with butter in the area close to the node, and after the prestressed tendon is stretched, it is grouted to form a non-bonded joint in the area near the node. , Other areas are partly bonded structure with bonding. A series of experimental studies done by the inventors have shown that this structure combines the advantages of both unbonded and fully bonded forms of bonding, has a higher bearing capacity, and at the same time improves the ductility and deformation capacity of the structure.

本发明提出的部分粘结预制预应力混凝土框架结构具有良好的抗震性能,符合我国绿色建筑和工业化建筑的发展战略,具有十分广阔的应用前景。The partially bonded prefabricated prestressed concrete frame structure proposed by the invention has good seismic performance, conforms to the development strategy of green buildings and industrialized buildings in my country, and has very broad application prospects.

发明内容Contents of the invention

本发明的目的是开发一种既满足整体性能要求,抗震性能好,同时满足室内大空间需求、节约材料、施工便捷的部分粘结预制预应力混凝土框架结构。The purpose of the present invention is to develop a partly bonded prefabricated prestressed concrete frame structure that not only meets the overall performance requirements, but also has good seismic performance, and at the same time meets the needs of large indoor space, saves materials, and is convenient for construction.

本发明提出的一种采用部分粘结的预制预应力混凝土框架结构,所述框架结构由若干个预制混凝土柱2和若干个预制混凝土梁3组合而成,还包括预应力筋1、后浇混凝土叠合层5和后浇混凝土节点核心区6,若干个预制混凝土柱2和若干个预制混凝土梁3通过后浇混凝土叠合层5和后浇混凝土节点核心区6相连接;预制混凝土梁3上设有预应力筋1,所述预应力筋1采用后张工艺施工,并穿过后浇混凝土节点核心区6;预应力筋采用曲线形结构,以提高预应力筋1的应用效率;预应力筋1采用部分粘结构造,即在靠近后浇混凝土节点核心区6的区域内将预应力筋1套上内嵌黄油的塑料套管,待预应力筋1张拉完成后灌浆,即形成在后浇混凝土节点核心区6的区域内为无粘结、其他区域为有粘结的部分粘结构造。The present invention proposes a partially bonded prefabricated prestressed concrete frame structure, the frame structure is composed of several prefabricated concrete columns 2 and several prefabricated concrete beams 3, and also includes prestressed tendons 1, post-cast concrete The laminated layer 5 and the post-cast concrete joint core area 6, several precast concrete columns 2 and several precast concrete beams 3 are connected through the post-cast concrete laminated layer 5 and the post-cast concrete joint core area 6; A prestressed tendon 1 is provided, and the prestressed tendon 1 is constructed by a post-tensioning process, and passes through the post-cast concrete joint core area 6; the prestressed tendon adopts a curved structure to improve the application efficiency of the prestressed tendon 1; the prestressed tendon 1 Partial bonded structure is adopted, that is, the prestressed tendon 1 is covered with a plastic sleeve embedded with butter in the area close to the core area 6 of the post-cast concrete joint, and after the prestressed tendon 1 is stretched, it is grouted, that is, the post-stressed tendon is formed. The area of the core area 6 of the poured concrete node is unbonded, and the other areas are partially bonded structures with bonding.

本发明中,预制混凝土柱2采用多层柱构造,在现场拼装过程中相邻的预制混凝土柱采用错层布置方式,从而可很好地实现预制梁吊装就位时预留的纵向钢筋与预制柱发生碰撞而无法就位的问题。In the present invention, the prefabricated concrete column 2 adopts a multi-layer column structure, and the adjacent precast concrete columns adopt a staggered arrangement during the on-site assembly process, so that the reserved longitudinal reinforcement and prefabricated beam can be well realized when the prefabricated beam is hoisted in place. A problem with columns colliding and not seating.

本发明中,所述多层柱构造中,位于上层的预制混凝土柱的底面设置灌浆导气槽,并在中心留设排气孔10,以便浇筑后浇混凝土叠合层5时,位于上层的预制混凝土柱底部的空气通过预埋在该预制混凝土柱内的PVC管排出,灌浆导气槽截面为三角形,底边长度为15mm~25mm,高为10mm~15mm,排气孔直径为10mm~15mm。In the present invention, in the multi-layer column structure, the bottom surface of the upper precast concrete column is provided with a grouting air guide groove, and an air vent 10 is left in the center, so that when the post-cast concrete laminated layer 5 is poured, the upper layer The air at the bottom of the precast concrete column is discharged through the PVC pipe embedded in the precast concrete column. The cross section of the grouting air guide groove is triangular, the length of the bottom side is 15mm~25mm, the height is 10mm~15mm, and the diameter of the air vent is 10mm~15mm .

本发明的有益效果在于:The beneficial effects of the present invention are:

1、本发明提出的预制预应力混凝土框架具有施工速度快,环境污染小,节约工期和模板等优点,符合住宅产业化的需求。1. The prefabricated prestressed concrete frame proposed by the present invention has the advantages of fast construction speed, low environmental pollution, saving construction period and formwork, and meets the needs of housing industrialization.

2、试验研究表明,本发明提出的预制预应力混凝土框架具有良好的整体性和抗震性能。2. Experimental research shows that the prefabricated prestressed concrete frame proposed by the present invention has good integrity and anti-seismic performance.

3、本发明中,预应力筋采用部分粘结,能够结合无粘结和全粘结两种粘结形式的优点,具有较高承载力,同时又改善了结构的延性和变形能力。3. In the present invention, the prestressed tendons are partially bonded, which can combine the advantages of both non-bonded and fully bonded bonding forms, have a higher bearing capacity, and improve the ductility and deformation capacity of the structure at the same time.

4、本发明中,预制柱采用多层柱构造,且采用两层预制方案。在现场拼装过程中,相邻的多层柱采用错层布置方式,从而可很好地实现预制梁吊装就位时预留出头钢筋与预制柱发生碰撞而无法就位的问题。4. In the present invention, the prefabricated column adopts a multi-layer column structure, and adopts a two-layer prefabricated scheme. During the on-site assembly process, the adjacent multi-storey columns are arranged in staggered layers, which can well solve the problem that the reserved steel bars collide with the precast columns when the prefabricated beams are hoisted in place and cannot be in place.

5、本发明中,在上层预制混凝土柱底面设置灌浆导气槽,并在中心留设排气孔。在套筒灌浆过程中,座浆层中空气经导气槽,由中心排气孔进入预埋的PVC管,最终排出柱外。试验研究表明,设置灌浆导气槽能有效疏导气体,保证座浆层灌浆密实程度。5. In the present invention, a grouting air guide groove is arranged on the bottom surface of the upper precast concrete column, and an air vent is left in the center. During the sleeve grouting process, the air in the seat slurry layer passes through the air guide groove, enters the pre-embedded PVC pipe through the central vent hole, and finally discharges out of the column. Experimental research shows that setting the grouting air guide groove can effectively dredge the gas and ensure the grouting density of the seat grout layer.

附图说明Description of drawings

图1为本发明一两层两跨结构示意图。Fig. 1 is a schematic diagram of a two-story two-span structure of the present invention.

图2为本发明部分粘结预制预应力混凝土框架中节点示意图。Fig. 2 is a schematic diagram of nodes in a partially bonded prefabricated prestressed concrete frame according to the present invention.

图3为本发明部分粘结预制预应力混凝土组合梁截面示意图。Fig. 3 is a schematic cross-sectional view of a partially bonded prefabricated prestressed concrete composite beam of the present invention.

图4为本发明部分粘结预制预应力混凝土柱截面示意图。Fig. 4 is a schematic cross-sectional view of a partially bonded prefabricated prestressed concrete column according to the present invention.

图5为本发明上层预制混凝土柱底面灌浆导气槽示意图。Fig. 5 is a schematic diagram of the grouting air guide groove on the bottom surface of the upper precast concrete column of the present invention.

图6为本发明部分粘结预制预应力混凝土框架拼装示意图。Fig. 6 is a schematic diagram of assembling a partially bonded prefabricated prestressed concrete frame according to the present invention.

图中标号:1为预应力筋,2为预制混凝土柱,3为预制混凝土梁,4为预制混凝土板,5为后浇混凝土叠合层,6为后浇混凝土节点核心区,7为灌浆导气槽,8为排气孔。Numbers in the figure: 1 is prestressed tendon, 2 is precast concrete column, 3 is precast concrete beam, 4 is precast concrete slab, 5 is post-cast concrete laminated layer, 6 is post-cast concrete node core area, 7 is grouting guide Air groove, 8 is air vent.

具体实施方式detailed description

下面结合附图和实施例对本发明进一步说明。The present invention will be further described below in conjunction with the accompanying drawings and embodiments.

实施例1:Example 1:

图1为一榀两层两跨预制预应力混凝土框架结构,该结构中预制混凝土柱2和预制混凝土梁3通过后浇混凝土叠合层5和后浇混凝土节点核心区6连接。预应力筋1采用部分粘结构造,在靠近节点区域采用无粘结的形式,其余部分与混凝土采用有粘结的形式。预应力筋1曲线布置,线形为多段抛物线,在控制截面处靠近受拉边缘布置。Fig. 1 is a two-story two-span prefabricated prestressed concrete frame structure, in which precast concrete columns 2 and precast concrete beams 3 are connected by post-cast concrete lamination layer 5 and post-cast concrete node core area 6. The prestressed tendon 1 adopts a partly bonded structure, adopts an unbonded form near the joint area, and adopts a bonded form with the rest of the concrete. The prestressed tendon 1 is arranged in a curved line, and the line shape is a multi-section parabola, and it is arranged near the tensile edge at the control section.

图2为预制预应力混凝土框架中节点构造详图,预制混凝土柱2和预制混凝土梁3通过后浇混凝土叠合层5和后浇混凝土节点核心区6连接。预应力筋1采用部分粘结,在靠近节点区域采用无粘结的形式,其余部分与混凝土采用有粘结的形式。预应力筋1曲线布置,线形为多段抛物线,在控制截面处靠近受拉边缘布置。相邻预制混凝土梁的下部纵筋通过焊接或套筒连接,预制混凝土梁的上部纵筋设置于后浇混凝土叠合层5,并现场绑扎;预制混凝土柱2采用多层柱构造。Fig. 2 is a detailed diagram of the joint structure in the prefabricated prestressed concrete frame. The precast concrete column 2 and the precast concrete beam 3 are connected through the post-cast concrete lamination layer 5 and the post-cast concrete node core area 6 . The prestressed tendons 1 are partly bonded, unbonded in the area near the node, and bonded to the rest of the concrete. The prestressed tendon 1 is arranged in a curved line, and the line shape is a multi-section parabola, and it is arranged near the tensile edge at the control section. The lower longitudinal reinforcements of adjacent precast concrete beams are connected by welding or sleeves, and the upper longitudinal reinforcements of precast concrete beams are arranged in the post-cast concrete lamination layer 5 and bound on site; the precast concrete columns 2 are constructed of multi-layer columns.

图3为预制预应力混凝土叠合梁的截面示意图,相邻预制混凝土梁3的下部纵筋通过焊接或套筒连接,预制混凝土梁3的上部纵筋设置于后浇混凝土叠合层5,并现场绑扎。Fig. 3 is a schematic cross-sectional view of a prefabricated prestressed concrete composite beam. The lower longitudinal reinforcements of adjacent precast concrete beams 3 are connected by welding or sleeves. Lashing on site.

图4为预制混凝土柱的截面示意图。Figure 4 is a schematic cross-sectional view of a prefabricated concrete column.

图5为上层预制混凝土柱2底面灌浆导气槽示意图。上层预制混凝土柱2底面设置灌浆导气槽7,并在中心留设排气孔8,以便预制混凝土柱2底空气通过预埋在预制混凝土柱2内的PVC管排出。灌浆导气槽7截面为三角形,底边长度为15mm~25mm,高为10mm~15mm,排气孔直径为10mm~15mm。Fig. 5 is a schematic diagram of the grouting air guide groove on the bottom surface of the precast concrete column 2 on the upper floor. The bottom surface of the upper precast concrete column 2 is provided with a grouting air guide groove 7, and an air vent 8 is left in the center so that the air at the bottom of the precast concrete column 2 can be discharged through the PVC pipe embedded in the precast concrete column 2. The cross-section of the grouting air guide groove 7 is triangular, the length of the base is 15mm-25mm, the height is 10mm-15mm, and the diameter of the vent hole is 10mm-15mm.

图6为部分粘结预制预应力混凝土框架结构拼装示意图。相邻的预制多层柱采用错层拼装方案,可避免预制梁中预留的纵向钢筋与预制柱发生碰撞而导致预制梁无法吊装就位的问题。Figure 6 is a schematic diagram of the assembly of a partially bonded prefabricated prestressed concrete frame structure. The adjacent prefabricated multi-storey columns adopt a staggered assembly scheme, which can avoid the collision between the longitudinal reinforcement reserved in the prefabricated beam and the prefabricated column, which will cause the problem that the prefabricated beam cannot be hoisted in place.

本发明的制作过程如下:The manufacture process of the present invention is as follows:

准备过程:在预制混凝土构件工厂完成预制混凝土柱、预制混凝土梁、预制混凝土板的制作,并将各构件编号、运输至施工现场。Preparation process: complete the production of precast concrete columns, precast concrete beams, and precast concrete slabs in the precast concrete component factory, and number and transport each component to the construction site.

施工过程:a.先将预制柱就位,安装相邻柱网的若干根预制混凝土柱,预制混凝土柱与基础采用套筒连接;b.在完成预制混凝土柱的安装部位安装预制混凝土梁,预制混凝土梁架设在预制混凝土柱和支撑上,并将预制混凝土梁调谁水平,与预制混凝土柱对中;c.放置预制混凝土板,将预制板搁置在预制梁和.支撑上,控制预制板与预制梁的搭接长度、预制板整体尺寸;d.对焊节点核心区梁底的竖向钢筋,然后绑扎节点核心区箍筋、在核心区预定位置放置金属波纹管,对无粘结区段的预应力钢绞线做无粘结处理,穿预应力钢绞线、绑扎梁顶纵向钢筋、绑扎叠合板内分布钢筋;e.安装节点核心区模板,现场浇筑节点核心区和叠合层;f.待节点核心区及叠合层后浇混凝土强度达到设计强度的75%时,进行钢绞线张拉,将钢绞线张拉至指定张拉力后,持荷并计算锚具回缩值,然后对钢绞线进行超张拉。张拉完毕后,用素混凝土浆进行锚具封浆,待素混凝土凝结硬化后,通过预留灌浆孔灌浆;g.以此类推即可完成预制预应力框架结构的施工。Construction process: a. First put the precast columns in place, install several precast concrete columns adjacent to the column network, and connect the precast concrete columns to the foundation with sleeves; b. Install precast concrete beams at the installation site of the precast concrete columns, Concrete beams are erected on the precast concrete columns and supports, and the precast concrete beams are adjusted horizontally to align with the precast concrete columns; c. Place the precast concrete slabs, place the precast slabs on the prefabricated beams and supports, and control the precast slabs and the precast concrete slabs. The lap length of prefabricated beams and the overall size of prefabricated slabs; d. The vertical steel bars at the bottom of the beams in the core area of the butt-welded joints, and then the stirrups in the core area of the joints are bound, and metal bellows are placed at the predetermined positions in the core area. For the unbonded section The prestressed steel strands are treated without bonding, and the prestressed steel strands are threaded, the longitudinal steel bars on the top of the beam are bound, and the steel bars distributed in the laminated slab are bound; e. Install the formwork for the core area of the node, and pour the core area of the node and the laminated layer on site; f. When the strength of the post-cast concrete in the core area of the node and the superimposed layer reaches 75% of the design strength, the steel strand is stretched. After the steel strand is stretched to the specified tension, hold the load and calculate the retraction value of the anchorage , and then hypertension the steel strand. After the tensioning is completed, use plain concrete grout to seal the anchorage. After the plain concrete hardens, grout through the reserved grouting holes; g. By analogy, the construction of the prefabricated prestressed frame structure can be completed.

Claims (3)

1.一种采用部分粘结的预制预应力混凝土框架结构,所述框架结构由若干个预制混凝土柱(2)和若干个预制混凝土梁(3)组合而成,还包括预应力筋(1)、后浇混凝土叠合层(5)和后浇混凝土节点核心区(6),其特征在于:若干个预制混凝土柱(2)和若干个预制混凝土梁(3)通过后浇混凝土叠合层(5)和后浇混凝土节点核心区(6)相连接;预制混凝土梁(3)上设有预应力筋(1),所述预应力筋(1)采用后张工艺施工,并穿过后浇混凝土节点核心区(6);预应力筋采用曲线形结构,以提高预应力筋(1)的应用效率;预应力筋(1)采用部分粘结构造,即在靠近后浇混凝土节点核心区(6)的区域内将预应力筋(1)套上内嵌黄油的塑料套管,待预应力筋(1)张拉完成后灌浆,即形成在后浇混凝土节点核心区(6)的区域内为无粘结、其他区域为有粘结的部分粘结构造。1. A partially bonded prefabricated prestressed concrete frame structure, the frame structure is composed of several prefabricated concrete columns (2) and several prefabricated concrete beams (3), and also includes prestressed tendons (1) , post-cast concrete laminated layer (5) and post-cast concrete joint core area (6), characterized in that: several precast concrete columns (2) and several precast concrete beams (3) pass through the post-cast concrete laminated layer ( 5) It is connected with the post-cast concrete node core area (6); precast concrete beams (3) are provided with prestressed tendons (1), and the prestressed tendons (1) are constructed by post-tensioning technology and pass through the post-cast concrete The core area of the joint (6); the prestressed tendon adopts a curved structure to improve the application efficiency of the prestressed tendon (1); ) in the area of the prestressed tendon (1) is covered with a plastic sleeve embedded with butter, and the prestressed tendon (1) is grouted after the stretching is completed, that is, it is formed in the area of the core area (6) of the post-cast concrete node. Partially bonded construction with no bonding and bonding in other areas. 2.根据权利要求1所述的预制预应力混凝土框架,其特征在于预制混凝土柱(2)采用多层柱构造,在现场拼装过程中相邻的预制混凝土柱采用错层布置方式,从而可很好地实现预制梁吊装就位时预留的纵向钢筋与预制柱发生碰撞而无法就位的问题。2. The prefabricated prestressed concrete frame according to claim 1, characterized in that the prefabricated concrete columns (2) adopt a multi-layer column structure, and the adjacent prefabricated concrete columns adopt a staggered arrangement during the on-site assembly process, so that it can be easily To better realize the problem that the reserved longitudinal reinforcement collides with the prefabricated column when the prefabricated beam is hoisted in place and cannot be put in place. 3.根据权利要求2所述的预制预应力混凝土框架,其特征在于所述多层柱构造中,位于上层的预制混凝土柱的底面设置灌浆导气槽,并在中心留设排气孔(10),以便浇筑后浇混凝土叠合层(5)时,位于上层的预制混凝土柱底部的空气通过预埋在该预制混凝土柱内的PVC管排出,灌浆导气槽截面为三角形,底边长度为15mm~25mm,高为10mm~15mm,排气孔直径为10mm~15mm。3. The prefabricated prestressed concrete frame according to claim 2, characterized in that in the multi-layer column structure, the bottom surface of the precast concrete column positioned at the upper floor is provided with a grouting air guide groove, and an air vent (10 ), so that when pouring the concrete composite layer (5), the air at the bottom of the precast concrete column on the upper floor is discharged through the PVC pipe embedded in the precast concrete column. 15mm~25mm, height 10mm~15mm, vent hole diameter 10mm~15mm.
CN201610096784.1A 2016-02-23 2016-02-23 A kind of part adhesive precast prestressed concrete frame structure Active CN105735469B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610096784.1A CN105735469B (en) 2016-02-23 2016-02-23 A kind of part adhesive precast prestressed concrete frame structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610096784.1A CN105735469B (en) 2016-02-23 2016-02-23 A kind of part adhesive precast prestressed concrete frame structure

Publications (2)

Publication Number Publication Date
CN105735469A true CN105735469A (en) 2016-07-06
CN105735469B CN105735469B (en) 2018-08-24

Family

ID=56246171

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610096784.1A Active CN105735469B (en) 2016-02-23 2016-02-23 A kind of part adhesive precast prestressed concrete frame structure

Country Status (1)

Country Link
CN (1) CN105735469B (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677339A (en) * 2017-03-10 2017-05-17 东南大学 Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method
CN106948481A (en) * 2017-05-02 2017-07-14 扬州大学 Prefabrication and assembly construction concrete frame beam-column connection based on the high strengthening tendons in part
CN107869116A (en) * 2017-10-19 2018-04-03 四川双铁科技有限公司 A kind of light-weight thermal-insulating and sound-insulating batten and preparation method thereof
CN108678165A (en) * 2018-07-06 2018-10-19 上海天华建筑设计有限公司 A kind of method of construction of cross-layer floor
WO2019056716A1 (en) * 2017-09-21 2019-03-28 中国建筑股份有限公司 Fully-assembled prestress concrete frame anti-seismic energy dissipation member system and construction method
CN109868940A (en) * 2017-12-05 2019-06-11 上海同吉建筑工程设计有限公司 Post-tensioning has the total tension prestress concrete composite beam and its design, construction method of bonding
CN109868935A (en) * 2017-12-05 2019-06-11 上海同吉建筑工程设计有限公司 Post-tensioning has the prestressed concrete superposed beam and its design, construction method of bonding
CN109868938A (en) * 2017-12-05 2019-06-11 上海同吉建筑工程设计有限公司 The total tension prestress concrete composite beam and its design, construction method of post-tensioning soap-free emulsion polymeization
CN109989478A (en) * 2019-02-22 2019-07-09 同济大学 A prefabricated prestressed concrete frame structure
CN110206143A (en) * 2019-05-10 2019-09-06 中建八局第二建设有限公司 A kind of construction method of post-stressed assembly concrete frame structure
CN111794279A (en) * 2020-07-24 2020-10-20 中国铁道科学研究院集团有限公司城市轨道交通中心 The structure and method of reducing the axial force of the floor slab on the support column under the action of earthquake
CN112900614A (en) * 2021-01-20 2021-06-04 同济大学 Anti-continuous collapse method suitable for steel-concrete combined structure
CN114396118A (en) * 2021-12-21 2022-04-26 中国建筑技术集团有限公司 Fabricated concrete frame structure connected through prestress compression joint and construction method
CN116005797A (en) * 2022-12-29 2023-04-25 同济大学 Semi-rigid connection precast concrete frame structure

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1116264A (en) * 1995-02-10 1996-02-07 中国建筑科学研究院建筑结构研究所 Large column net prestressed plate frame structure system
JP2011038364A (en) * 2009-08-18 2011-02-24 Kumagai Gumi Co Ltd Construction method for structure
CN204040202U (en) * 2013-11-01 2014-12-24 润弘精密工程事业股份有限公司 Precasting structure with air guiding function
CN104499568A (en) * 2014-12-19 2015-04-08 东南大学 Square steel pipe fabricated column-prefabricated superposed beam integrally-fabricated frame and construction method
CN204850044U (en) * 2015-07-23 2015-12-09 青岛一建集团有限公司 Prefabricated post and composite beam combination department node structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1116264A (en) * 1995-02-10 1996-02-07 中国建筑科学研究院建筑结构研究所 Large column net prestressed plate frame structure system
JP2011038364A (en) * 2009-08-18 2011-02-24 Kumagai Gumi Co Ltd Construction method for structure
CN204040202U (en) * 2013-11-01 2014-12-24 润弘精密工程事业股份有限公司 Precasting structure with air guiding function
CN104499568A (en) * 2014-12-19 2015-04-08 东南大学 Square steel pipe fabricated column-prefabricated superposed beam integrally-fabricated frame and construction method
CN204850044U (en) * 2015-07-23 2015-12-09 青岛一建集团有限公司 Prefabricated post and composite beam combination department node structure

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
熊学玉: "《预应力结构原理与设计》", 31 October 2014, 中国建筑工业出版社 *
种迅等: "部分无黏结预制预应力混凝土框架及其节点抗震能力研究", 《地震工程与工程振动》 *

Cited By (19)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106677339A (en) * 2017-03-10 2017-05-17 东南大学 Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method
CN106948481B (en) * 2017-05-02 2019-05-07 扬州大学 Beam-column connection joint of prefabricated concrete frame based on part of high-strength reinforcement
CN106948481A (en) * 2017-05-02 2017-07-14 扬州大学 Prefabrication and assembly construction concrete frame beam-column connection based on the high strengthening tendons in part
WO2019056716A1 (en) * 2017-09-21 2019-03-28 中国建筑股份有限公司 Fully-assembled prestress concrete frame anti-seismic energy dissipation member system and construction method
CN107869116A (en) * 2017-10-19 2018-04-03 四川双铁科技有限公司 A kind of light-weight thermal-insulating and sound-insulating batten and preparation method thereof
CN109868938A (en) * 2017-12-05 2019-06-11 上海同吉建筑工程设计有限公司 The total tension prestress concrete composite beam and its design, construction method of post-tensioning soap-free emulsion polymeization
CN109868935B (en) * 2017-12-05 2022-01-07 上海同吉建筑工程设计有限公司 Post-tensioned bonded prestressed concrete composite beam and design and construction method thereof
CN109868935A (en) * 2017-12-05 2019-06-11 上海同吉建筑工程设计有限公司 Post-tensioning has the prestressed concrete superposed beam and its design, construction method of bonding
CN109868940A (en) * 2017-12-05 2019-06-11 上海同吉建筑工程设计有限公司 Post-tensioning has the total tension prestress concrete composite beam and its design, construction method of bonding
CN109868938B (en) * 2017-12-05 2022-02-01 上海同吉建筑工程设计有限公司 Post-tensioned unbonded co-tensioned prestressed concrete composite beam and design and construction method thereof
CN109868940B (en) * 2017-12-05 2022-01-14 上海同吉建筑工程设计有限公司 Post-tensioned bonded co-tensioned prestressed concrete composite beam and design and construction method thereof
CN108678165A (en) * 2018-07-06 2018-10-19 上海天华建筑设计有限公司 A kind of method of construction of cross-layer floor
CN108678165B (en) * 2018-07-06 2024-05-28 上海天华建筑设计有限公司 Construction method of cross-layer floor
CN109989478A (en) * 2019-02-22 2019-07-09 同济大学 A prefabricated prestressed concrete frame structure
CN110206143A (en) * 2019-05-10 2019-09-06 中建八局第二建设有限公司 A kind of construction method of post-stressed assembly concrete frame structure
CN111794279A (en) * 2020-07-24 2020-10-20 中国铁道科学研究院集团有限公司城市轨道交通中心 The structure and method of reducing the axial force of the floor slab on the support column under the action of earthquake
CN112900614A (en) * 2021-01-20 2021-06-04 同济大学 Anti-continuous collapse method suitable for steel-concrete combined structure
CN114396118A (en) * 2021-12-21 2022-04-26 中国建筑技术集团有限公司 Fabricated concrete frame structure connected through prestress compression joint and construction method
CN116005797A (en) * 2022-12-29 2023-04-25 同济大学 Semi-rigid connection precast concrete frame structure

Also Published As

Publication number Publication date
CN105735469B (en) 2018-08-24

Similar Documents

Publication Publication Date Title
CN105735469B (en) A kind of part adhesive precast prestressed concrete frame structure
CN109469202B (en) Prestressed assembly integral concrete frame structure system and construction method thereof
CN106836479B (en) Assembled prestressed concrete frame structure
CN106677339A (en) Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method
CN106869316A (en) The beam column edge of a wing is the group frame system and construction method of concrete filled steel tube
CN206737116U (en) Node dry and wet Hybrid connections assembled integral concrete frame structure
CN102747781A (en) Fiber reinforce plastic (FRP) combination structure frame where integral type node is adopted and construction method thereof
CN103711330A (en) Method for using prefabricated reinforced concrete frame to reinforce existing structure through prestressing assembly
CN105839775A (en) Beam end crossed arc-shaped post-tensioned pre-stressed reinforcing steel dry-type assembling beam-column node
CN115680159A (en) A Prefabricated Assembly Lattice Steel Reinforced Concrete Composite Shear Wall Structural System
CN109989478A (en) A prefabricated prestressed concrete frame structure
CN104179249A (en) Assembled composite-structure earthquake-resistant wall and assembly method thereof
CN115262747A (en) Prefabricated lattice type steel reinforced concrete combined frame structure system
CN116290525A (en) A prestressed steel concrete composite beam composite floor and its construction method
CN106869317B (en) The beam column edge of a wing is the group frame system and construction method of concrete-filled rectangular steel tube
CN116220200B (en) Pre-tensioning method and post-tensioning method combined prefabricated prestressed frame structure and construction method thereof
CN209975734U (en) A high-performance large-span heavy-duty multi-storey industrial building prefabricated structure system
CN106948486A (en) Steel tubes Combined concrete frame system and construction method
CN115434425A (en) Lattice type steel reinforced concrete prefabricated beam column joint and method
CN105649259B (en) A kind of wallboard structural system of the dark framework of band of precast concrete wall panel and its structure
CN119531489A (en) Connection nodes and construction technology of precast reinforced concrete columns and prestressed steel concrete beams
CN219261339U (en) Lattice type steel reinforced concrete precast beam column node
CN115538583B (en) UHPC connected post-tensioned bonded precast prestressed concrete open-pore beam frame structure system and design and construction method thereof
CN115288328A (en) Prefabricated lattice type steel reinforced concrete combined shear wall
CN115538579A (en) A UHPC-connected post-tensioned slow-bonded co-tensioned precast prestressed concrete frame structure system and its design and construction methods

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant