CN106677339A - Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method - Google Patents

Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method Download PDF

Info

Publication number
CN106677339A
CN106677339A CN201710139858.XA CN201710139858A CN106677339A CN 106677339 A CN106677339 A CN 106677339A CN 201710139858 A CN201710139858 A CN 201710139858A CN 106677339 A CN106677339 A CN 106677339A
Authority
CN
China
Prior art keywords
concrete
column
precast
frame structure
node
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710139858.XA
Other languages
Chinese (zh)
Inventor
郭正兴
杨辉
杨森
管东芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southeast University
Original Assignee
Southeast University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southeast University filed Critical Southeast University
Priority to CN201710139858.XA priority Critical patent/CN106677339A/en
Publication of CN106677339A publication Critical patent/CN106677339A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/19Three-dimensional framework structures
    • E04B1/1903Connecting nodes specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Rod-Shaped Construction Members (AREA)

Abstract

The invention discloses an assembly integral type concrete frame structure of dry-wet mixed connection of nodes and a construction method. The assembly integral type concrete frame structure comprises pre-fabricated concrete pillars, pre-fabricated concrete beams, node local pre-stressed tendons, pre-fabricated concrete plates and rear-poured concrete combined interface layers; in an installation construction stage of a structural system, pre-fabricated components of the beams and the pillars adopt local pre-stress exerting and are connected in a dry mode, step-shaped rabbets at the ends of the pre-fabricated concrete beams are stored on side brackets of the pre-fabricated concrete pillars, and the pre-stressed tendons are inserted into vertical cross arc-shaped porous channels reserved in the beam ends and the node pillar sections of the pre-fabricated concrete pillars and are stretched; after dry-type connection between the pre-fabricated concrete beams and the pre-fabricated concrete pillars is completed, and the structural bearing capacity is achieved; in a using stage, after the pre-fabricated concrete plates or steel bearing plates, the pre-fabricated beams and steel rebars on the upper portions of the pre-fabricated plates are installed, the concrete combined interface layers are poured, and wet-type connection among the pre-fabricated concrete pillars, the pre-fabricated concrete beams and the pre-fabricated concrete plates is completed; and through dry-and-wet-type mixed connection of the nodes, the assembly integral type concrete frame structure is formed.

Description

Node dry and wet Hybrid connections assembled integral concrete frame structure and construction method
Technical field
The present invention relates to architectural engineering assembling field, and in particular to a kind of assembled integral concrete frame structure.
Background technology
Assembling concrete frame structure can greatly improve construction ability and construction speed, save a large amount of labour forces, ensure Build guality, and be conducive to reaching the requirement of " four sections one are environmentally friendly ", in national increased force propulsion assembly concrete building, push away There is good development prospect under the background of wide green building and green construction.
At present, known domestic and international prefabrication and assembly construction frame structure mainly has conventional prefabricated bean column node wet type to be linked and packed Frame structure and node dry type connection prestress assembly frame structure.The prefabricated post of wet type connection framework is highly located at bean column node Lower section, is combined between prefabricated post node section and prefabricated beam-ends by cast-in-place concrete, and good integrity, energy consumption ability is excellent, Structural behaviour is equal to cast-in-place structural, and the prefabricated integral frame structure Typical Representative has French generation structure system, the safe body of Taiwan profit System.But cast-in-place concrete wet type connecting node, in-site installation efficiency is low, high cost, falsework consumption is big, and reinforcement installation is complicated Have high demands, be unfavorable for large scale integration production and construction.Additionally, wet type assembling framework structural system must treat cast-in-place node shell of column Concrete is reached after some strength, could carry out the assembling construction of a upper floor, and installation effectiveness is not high enough, is unfavorable for shortening high The layer assembled architecture index bed installation time.
The prestressing force assembling framework of node dry type connection, can preferably play precast concrete factorial praluction and scene Installation effectiveness, and post-tensioned prestressing connection can provide good structure restorability, be easy to the reparation after earthquake disaster.It is existing Prefabricated post-tensioned prestressing frame structure mainly has the subassemblage concrete frame of the PRESSS systems of the U.S.-Japan and Japan System.Subassemblage concrete frame structure is that prefabricated post and precast beam is straight by penetrating posttension, multistage, soap-free emulsion polymeization in beam The prestressing force assembly concrete frame structure of line prestressing force and Tension Forming.The precast beam intercolumniation of PRESSS systems adopts posttension Unbonded prestressing tendon and regular reinforcement carry out Hybrid connections, and presstressed reinforcing steel is passed through and reserved in whole beam longitudinal central axis line position Presstressed reinforcing steel duct the both sides crossbeam of post is linked together, beam column seam filling mortar.Regular reinforcement is indulged up and down by beam The reserved duct in muscle position passes through pillar, and carries out duct grouting in scene.Two kinds of structures are using the related post section of whole beam Point applies prestressing force, and the safety of structure excessively relies on presstressed reinforcing steel, it is impossible to which the beam plasticity of post side certain distance is left in realization Hinge transfer.In addition the presstressed reinforcing steel of subassemblage xoncrete structure needs lashing, tensioning etc. in the reserving hole channel of whole precast beam Complicated construction technique, Structural Energy Dissipation is relatively weak;PRESSSS is difficult to give full play to tribute of its presstressed reinforcing steel for structural bearing capacity Offer, its design theory is also mismatched with China specification current design methods.The prestressed assembling framework structure in also a kind of local Dry type connecting node, the step ends rest of its precast beam on the side bracket of prefabricated post, and in the prefabricated beam column of node district Between arrange that horizontal arc intersects presstressed reinforcing steel and carries out local prestressing force crimping, tension of prestressed tendon end is located at the side of beam and keeps away Open the abdominal part that upper and lower longitudinal reinforcement encrypts scope.The joint form belongs to the dress of the pure dry type connection without overlapping cast-in-place concrete surface layer With concrete frame structure, and match with precast floor slab dry type splicing process, though its structural behaviour connects better than external similar bolt Mode is connect, but structural integrity is weaker than cast-in-place concrete frame structure, therefore the joint form is mainly used in multilamellar assembled Concrete frame structure house.
The content of the invention
Technical problem:In order to overcome the deficiencies in the prior art, the present invention to provide a kind of node dry and wet Hybrid connections Assembled integral concrete frame structure and its construction method, the system is connected using " dry-wet mixing type ", gives full play to assembling Quick and " wet type " attachment structure globality that concrete frame structure post-tensioned prestressing " dry type " attachment structure makes and installs Good advantage, had both been easy to precast construction to construct with upper and lower floor crossings on different level assembling by cross, improve again structure globality and Anti-seismic performance.
Technical scheme:The invention provides a kind of node dry and wet Hybrid connections assembled integral concrete frame structure, bag The precast concrete column with node shell of column, precast concrete beam, precast slab and rear pouring concrete coincidence surface plate are included, is constructed Precast concrete beam described in stage forms grillage, and the beam-ends of the precast concrete beam is provided with tongue and groove, the concrete The node shell of column side of earth pillar is provided with the described prefabricated mixed of the bracket being adapted with tongue and groove, the precast concrete column and its both sides Solidifying Tu Liang, with merging by presstressed reinforcing steel through tensioning is carried out, forms the non-floor framework knot of dry type connection by tongue and groove and bracket Structure;Precast slab described in operational phase is laid on each Vierendeel girder of grillage, in precast slab and prefabricated mixed Pouring concrete coincidence surface plate formation wet type connection has floor assembled integral after in the reserved height of solidifying 60~200mm of Tu Liang tops Frame structure.
Further, the dry type connection of construction stage, is located at prefabricated beam section height middle part and wears with known presstressed reinforcing steel Cross whole beam and assembling or the local crimping of presstressed reinforcing steel horizontal cross arrangement beam-ends depth of section middle part and shell of column are crimped with shell of column Entirely different, node district is applied crossed arc arrangement in the perpendicular plane of the prestressed presstressed reinforcing steel in local, tensioning by the present invention End is arranged on top surface of the beam and bottom surface, and the intersection post side of presstressed reinforcing steel is in the range of 0.05~0.2 times of beam span L, in advance Stress rib afterbody is staggered between the levels longitudinal reinforcement of precast beam and forms closely overlap joint connection, reaches and obtains maximum beam-ends Section resistance moment and the optimal effectiveness consistent with bean column node bending moment envelope diagram, and help realize that bean column node plastic hinge is shifted, Strengthen overall structure anti-seismic performance, and form the non-floor frame structure with bearing capacity.Presstressed reinforcing steel can be wanted according to design Ask and be processed into bonding and/or soap-free emulsion polymeization;It is different according to the application of prefabricated integral frame, post-tensioned prestressing muscle can be changed Quantity and length, degree of prestressing and concrete binding mode and scope.
Further, wet type connection, it is entirely different with known assembling concrete frame bean column node concrete cast-in-situ, this It is bright on the basis of node shell of column is prefabricated, the longitudinal main stress reinforcing bar in the coincidence surface plate of precast beam top is by precast concrete Reserving hole channel or reinforcing bar connector realize continuous arrangement, floor surface layer reinforced bar in the coincidence surface plate of precoated plate in the node shell of column of post In the cut-out of prefabricated shell of column periphery, discontinuously by node shell of column section, the way is obtained having the beneficial effect that and ensure that holding for girder Loading capability, releases stress concentration of the floor in bearing load lower corner area, reduces the crack of comer area plate face, and with it is prefabricated Concrete slab or steel board overlap together after pouring concrete surface layer, complete precast concrete beam, precast concrete column and prefabricated mixed The wet type connection of concrete board;Precast concrete beam top longitudinal reinforcement may pass through the elongated arrangement of bean column node multispan, or many Across carrying out overlap joint connection, it is welded to connect or is mechanically connected.
Further, the precast concrete column according to lifting crane gear ability, using single story height or multiple buildings The precast concrete column of layer height, is connected between precast concrete column and with basis using grout sleeve;The precast concrete Post also can be further prefabricated using segmentation, described including prefabricated concrete column reinforcing joint area and concrete column hypomere is segmented up and down Concrete column reinforcing joint area it is reserved longitudinally through and vertical precompressed splicing in the middle part of being distributed in the reinforcing bar duct of cross-sectional perimeter and section Bolt duct, the longitudinal reinforcement correspondence that the concrete column hypomere top surface stretches out extends to node through reserved steel bar duct On area, the tensioning screw rod correspondence that the concrete column hypomere top surface stretches out splices duct, concrete column section through vertical precompressed By concrete epoxy piece glue bond, piece is crimped and extrudes closely connected the piece of point area and concrete column hypomere by tensioning bolt, It is in the milk in the reinforcing bar duct and vertical precompressed splicing duct.
A kind of construction method of node dry and wet Hybrid connections assembled integral concrete frame structure, comprises the following steps:
(1) after this layer of precast concrete column is in place, some precast concrete columns of adjacent pillars net are installed;
(2) precast concrete beam is shelved on the bracket of precast concrete Column border node shell of column side by the tongue and groove of beam-ends, will be pre- Beams of concrete processed is aligned to designed elevation, the reserved left and right vertical arc prestressing force of prefabricated solidifying earth pillar and precast concrete beam-ends The mutual para-position in muscle duct position, forms complete arc and intersects presstressed reinforcing steel duct;Arc presstressed reinforcing steel penetrates prestressed pore passage And stretch-draw anchor, beam-ends stretching notch sealing off and covering anchorage, the local for completing non-floor frame structure applies the connection of prestressing force dry type;
(3) this layer of precast slab is shelved on the precast concrete beam of frame structure, installs precast beam coincidence surface plate Interior longitudinal reinforcement is fixed with sealing stirrup, and colligation;
(4) repeat (2), (3), using line production install by cross prefabricated frame set a roof beam in place, prefabricated frame frame plate, colligation precoated plate fold Close surfacing steel bar and built-in electric wire pipe;
(5) precast concrete column of upper layer frame structure, the installation synchronization of upper layer precast concrete beam are installed Suddenly (2);
(6) pouring concrete coincidence surface plate after one-piece casting This floor, completes the wet type connection of precast beam, post and plate, this step Suddenly with step (5) using line production synchronous construction;
(7) repeating (1), (2), (3), (4), (5), (6) can complete whole assembled integral concrete frame by that analogy The construction of frame structure.
Beneficial effect:The dry type attachment structure of construction stage of the invention by beam column node area apply local it is prestressed it is pre- should Crossed arc arrangement in the perpendicular plane of power muscle, stretching end is arranged on top surface of the beam and bottom surface, and presstressed reinforcing steel afterbody is staggered in prefabricated Closely overlap joint connection, the change of the arrangement are formed between the levels longitudinal reinforcement of beam, has obtained obtaining maximum beam-ends Section resistance moment and the optimal effectiveness consistent with bean column node bending moment envelope diagram, and help realize that bean column node plastic hinge is shifted, Non-floor frame structure of the formation with bearing capacity under conditions of not installing precoated plate and pouring coincidence surface plate concrete, directly Subsequent installation precoated plate is connected in there is provided condition, the skyscraper index bed cross construction time is effectively shortened;
Additionally, in operational phase, the node shell of column of prefabricated post is also together prefabricated, the longitudinal direction in the coincidence surface plate of precast beam top Main stress reinforcing bar realizes continuous arrangement by the reserving hole channel in the node shell of column of precast concrete column or reinforcing bar connector, prefabricated Floor surface layer reinforced bar cuts off in prefabricated shell of column periphery in the coincidence surface plate of plate, discontinuously by node shell of column section, the way Advantage is the bearing capacity that both ensure that girder, and stress concentration of the floor in bearing load lower corner area is released again, is reduced The crack of comer area plate face, and pouring concrete surface layer after overlapping together with precast slab or steel board, form node dry and wet Hybrid connections assembled integral concrete frame structure.
Description of the drawings
Fig. 1 is node dry and wet Hybrid connections assembled integral concrete frame structure system schematic diagram;
Fig. 2 is that precast concrete column sectional is prefabricated, combination face high-strength bolt crimping structure schematic diagram;Wherein (a) is Precast concrete Column border node shell of column 16, is (b) concrete column hypomere 15, (c) is the fractional one layer prefabricated post being assembled into;
Fig. 3 is the vertical crossed arc prestressing force arranged in prefabricated and the connection of precast beam dry type the vertical plane of node shell of column Muscle and stretching end are arranged at the schematic diagram of top surface of the beam and bottom surface;
Fig. 4 is prefabricated post, the precast beam upper longitudinal bar that precast beam and precoated plate wet type connect passes through prefabricated shell of column and prefabricated The discontinuous schematic diagram in plate plate face steel bar column side;
Fig. 5 construction procedure schematic diagrams.
Specific embodiment
Technical solution of the present invention is described in detail below, but protection scope of the present invention is not limited to the enforcement Example.
Embodiment:Two Pin two-layers three are illustrated in figure 1 across Precast Concrete Frame, the structure includes fractional one layer Prefabricated post 1, precast concrete beam 4, precast slab 14 and rear pouring concrete coincidence surface plate 10, wherein fractional one layer prefabricated post 1 is made up of precast concrete Column border node shell of column 16 and concrete column hypomere 15.
Construction stage precast concrete beam 4 forms grillage, and the beam-ends of precast concrete beam 4 is provided with tongue and groove, prefabricated mixed The node shell of column side of solidifying earth pillar 1 is provided with the bracket 2 being adapted with tongue and groove, as shown in Figure 3.Precast concrete column 1 and its both sides Precast concrete beam 4 by tongue and groove and bracket 2 with merging by presstressed reinforcing steel 7 through tensioning is carried out, form the nothing of dry type connection Floor frame structure.Crossed arc arrangement in the perpendicular plane of presstressed reinforcing steel 7 of beam column node area, presstressed reinforcing steel 7 is in the top surface of beam 4 Bonding is processed as with bottom surface tensioning post-grouting, the side of intersection post 1 of presstressed reinforcing steel 7 is 0.05 times of beam span L.As schemed Shown in 4, the longitudinal main stress reinforcing bar 9 in the top coincidence surface plate 10 of precast beam 4 is by the node shell of column of precast concrete column Continuous arrangement is realized in reserved wavy metal duct 13, is welded to connect between multispan.In precast slab 14 and concrete The formation of pouring concrete coincidence surface plate 10 wet type connection has floor assembling overall after in the reserved altitude ranges of the top 130mm of native beam 4 Formula frame structure.
With reference to the embodiment of fractional one layer post 1, as shown in Fig. 2 the manufacturing process of the present invention is as follows:In precast concrete structure Part factory completes fractional one layer prefabricated post 1 including precast concrete Column border node shell of column 16 and concrete column hypomere 15, concrete The making of native beam 4, precast slab 14, and each component is numbered, transported to job site.Precast concrete column 1 is in beam column Node district 16 reserve left and right vertical arc beams of concrete presstressed reinforcing steel duct 3, regular reinforcement duct 13, longitudinally through and be distributed Vertical precompressed splice bolt duct 20 and post side bracket 2 in the middle part of the reinforcing bar duct 19 and section of cross-sectional perimeter;Concrete Tu Liang adopts U-stirrups 12, beam-ends bottom to be provided with stepped tongue and groove, and beam-ends also leaves left and right vertical arc and intersects beams of concrete Presstressed reinforcing steel duct 5.
Above-mentioned node dry and wet Hybrid connections assembled integral concrete frame structure, as shown in figure 5, site operation process is such as Under:
1) Assembling fractional one layer prefabricated post 1, the longitudinal reinforcement 17, tensioning screw rod that the top surface of concrete column hypomere 15 stretches out 18 correspond to through the reserving hole channel 19,20 of concrete column reinforcing joint area 16 respectively, and piece is by concrete epoxy piece glue bond, tensioning spiral shell Bolt 18 is crimped and extrudes closely connected, grouting in reinforcing bar duct 19 and vertical precompressed splicing duct 20.
2) it is first that this layer of precast concrete column 1 is in place, some precast concrete columns 1 of adjacent pillars net are installed, it is prefabricated mixed Connected using grout sleeve between solidifying earth pillar 1 and basis.
3) this layer of precast concrete beam 4 is installed, precast concrete beam 4 is shelved on post side bracket by the tongue and groove of beam-ends bottom On 2;Precast concrete beam 4 is aligned to into designed elevation, the reserved left and right vertical arc of prefabricated post node district and prefabricated beam-ends is pre- Stress rib duct position 3,5 mutual para-positions, form complete arc and intersect presstressed reinforcing steel duct;Arc presstressed reinforcing steel 7 penetrates pre- Stress duct 3,5 and stretch-draw anchor, arc duct grouting, beam-ends stretching notch 6,8 sealing off and covering anchorages complete " dry type " of frame structure even Connect.
4) this layer of precast slab 14 is installed, the precast concrete beam 4 with bearing capacity frame structure is shelved on On;Longitudinal reinforcement 9 in the coincidence surface plate of mounting rail top is fixed with sealing stirrup 12, and colligation;Longitudinal reinforcement 9 is mixed through prefabricated The duct 13 of the back reinforcing bar of solidifying earth pillar 1, longitudinal reinforcement 9 is welded to connect, and two-way concrete slab needs consideration to be arranged symmetrically with duct And mutual dislocation;Preheating embedding line, reinforcing bar 14,15 are synchronous in pouring concrete coincidence surface plate after This floor installs.
5) repeat 3), 4), using line production install by cross prefabricated frame set a roof beam in place, prefabricated frame frame plate, colligation coincidence surface plate steel Muscle and built-in electric wire pipe etc..
6) precast concrete column 1 of a floor, a upper floor precast concrete beam 4, specific embodiment are installed With the 2) step.
7) pouring concrete coincidence surface plate 10 after one-piece casting This floor;Complete " wet type " connection of bean column node;
This stage precast concrete column 1 of a floor frame structure, the installation of precast concrete beam 4 and this layer upwards The construction of pouring concrete coincidence surface plate 10 afterwards, can adopt line production synchronous construction according to engineering practice.
8) repeat that 1), 2), 3), 4), 5), 6), 7) applying for whole prefabricated integral frame structure can be completed by that analogy Work.
The above is only the preferred embodiment of the present invention, it should be pointed out that:For the ordinary skill people of the art For member, under the premise without departing from the principles of the invention, some improvements and modifications can also be made, these improvements and modifications also should It is considered as protection scope of the present invention.

Claims (6)

1. a kind of node dry and wet Hybrid connections assembled integral concrete frame structure, it is characterised in that:Including band node shell of column Precast concrete column, precast concrete beam, precast slab and rear pouring concrete coincidence surface plate, it is prefabricated described in the construction stage Beams of concrete forms grillage, and the beam-ends of the precast concrete beam is provided with tongue and groove, the node post of the precast concrete column Section side is provided with the precast concrete beam of the bracket being adapted with tongue and groove, the precast concrete column and its both sides by enterprise Mouth and bracket are passed through by presstressed reinforcing steel with merging and carry out tensioning, the non-floor frame structure of formation dry type connection;Operational phase institute State precast slab to be laid on each Vierendeel girder of grillage, precast slab and precast concrete beam top 60 ~ Pouring concrete coincidence surface plate formation wet type connection has floor prefabricated integral frame structure after in the reserved height of 200mm.
2. node dry and wet Hybrid connections assembled integral concrete frame structure according to claim 1, it is characterised in that: Crossed arc arrangement in the perpendicular plane of the presstressed reinforcing steel, tension of prestressed tendon end is located at the top surface of precast concrete beam and bottom Face, the intersection post side of presstressed reinforcing steel is in the range of 0.05 ~ 0.2 times of beam span, presstressed reinforcing steel afterbody is staggered in prefabricated Overlap joint connection is formed between the levels longitudinal reinforcement of beams of concrete, presstressed reinforcing steel has been processed into bonding and/or soap-free emulsion polymeization.
3. node dry and wet Hybrid connections assembled integral concrete frame structure according to claim 1, it is characterised in that: Longitudinal main stress reinforcing bar in the concrete folding surface layer is by the reserving hole channel in the node shell of column of precast concrete column Or reinforcing bar connector realizes continuous arrangement;Floor surface layer reinforced bar cuts off in prefabricated shell of column periphery in the concrete folding surface layer, The discontinuous coincidence surface plate concrete by node shell of column section, integral cast-in-situ precast beam and precoated plate.
4. node dry and wet Hybrid connections assembled integral concrete frame structure according to claim 3, it is characterised in that: Precast concrete beam top longitudinal reinforcement passes through the elongated arrangement of bean column node multispan, or overlap joint connection, weldering are carried out between multispan Connect in succession or be mechanically connected.
5. node dry and wet Hybrid connections assembled integral concrete frame structure according to claim 1, it is characterised in that: The precast concrete column is divided into single story height or multiple story heights and carries out prefabricated or prefabricated using segmentation, bag Include and be segmented prefabricated concrete column reinforcing joint shell of column and concrete column hypomere up and down:The reserved longitudinal direction of the concrete column reinforcing joint shell of column is passed through Wear and be distributed in the vertical precompressed splice bolt duct in the middle part of the reinforcing bar duct and section of cross-sectional perimeter;The concrete column hypomere The longitudinal reinforcement correspondence that top surface stretches out is extended on node district, the concrete column hypomere top through reserved steel bar duct The tensioning screw rod correspondence that face is stretched out splices reserving hole channel, concrete column reinforcing joint shell of column and concrete column hypomere through vertical precompressed By concrete epoxy piece glue bond, piece is crimped and extrudes closely connected piece by tensioning bolt, and the reinforcing bar duct is pre- with vertical Pressure splicing is in the milk in duct.
6. the construction method of node dry and wet Hybrid connections assembled integral concrete frame structure according to claim 1, It is characterized in that:Comprise the following steps:
(1)After this layer of precast concrete column is in place, some precast concrete columns of adjacent pillars net are installed;
(2)Precast concrete beam is shelved on the bracket of precast concrete Column border node shell of column side by the tongue and groove of beam-ends, will be prefabricated mixed Solidifying Tu Liang is aligned to designed elevation, the reserved left and right vertical arc presstressed reinforcing steel hole of prefabricated solidifying earth pillar and precast concrete beam-ends The mutual para-position in road position, forms complete arc and intersects presstressed reinforcing steel duct;Arc presstressed reinforcing steel penetrates prestressed pore passage and opens Anchoring, beam-ends stretching notch sealing off and covering anchorage, the local for completing non-floor frame structure is drawn to apply the connection of prestressing force dry type;
(3)This layer of precast slab is shelved on the precast concrete beam of frame structure, is installed in precast beam coincidence surface plate and is indulged Fix with sealing stirrup, and colligation to reinforcing bar;
(4)Repeat(2)、(3), using line production install by cross prefabricated frame set a roof beam in place, prefabricated frame frame plate, colligation precoated plate superposed surfaces Layer reinforcing bar and built-in electric wire pipe;
(5)The precast concrete column of upper layer frame structure, the same step of installation of upper layer precast concrete beam are installed (2);
(6)Pouring concrete coincidence surface plate after one-piece casting This floor, complete precast beam, post and plate wet type connection, this step with Step(5)Using line production synchronous construction;
(7)Repeat(1)、(2)、(3)、(4)、(5)、(6)Whole assembled integral concrete frame knot can be completed by that analogy The construction of structure.
CN201710139858.XA 2017-03-10 2017-03-10 Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method Pending CN106677339A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710139858.XA CN106677339A (en) 2017-03-10 2017-03-10 Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710139858.XA CN106677339A (en) 2017-03-10 2017-03-10 Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method

Publications (1)

Publication Number Publication Date
CN106677339A true CN106677339A (en) 2017-05-17

Family

ID=58828707

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710139858.XA Pending CN106677339A (en) 2017-03-10 2017-03-10 Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method

Country Status (1)

Country Link
CN (1) CN106677339A (en)

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107165271A (en) * 2017-07-07 2017-09-15 浙江工业大学工程设计集团有限公司 A kind of assembled Special-Shaped Column concrete frame structure
CN107578691A (en) * 2017-10-16 2018-01-12 哈尔滨建筑云网络科技有限公司 Frame structure construction training model is used in a kind of assembled architecture teaching
CN107938845A (en) * 2017-12-23 2018-04-20 中冶建筑研究总院有限公司 A kind of concrete prefabricated assembling combining structures of FRP
CN108149785A (en) * 2017-12-29 2018-06-12 湖南标迪夫节能科技有限公司 A kind of prefabricated post frame for assembled architecture
CN108179806A (en) * 2018-02-01 2018-06-19 胡习兵 A kind of complete assembled steel reinforced concrete frame structure system
CN108457422A (en) * 2018-02-01 2018-08-28 东南大学 Precast prestressed beam, assembled composite frame structure and its installation method
CN108755941A (en) * 2018-08-10 2018-11-06 大连理工大学 Assembly concrete frame Mixed Architecture
CN109469202A (en) * 2018-12-12 2019-03-15 中国建筑技术集团有限公司 Prestressed assembly integral concrete frame structure system and construction method thereof
CN109469326A (en) * 2017-09-07 2019-03-15 润弘精密工程事业股份有限公司 Special-shaped grid board construction method
CN109695345A (en) * 2017-10-20 2019-04-30 润弘精密工程事业股份有限公司 A kind of structure construction method of building
CN110206347A (en) * 2019-05-18 2019-09-06 陕西建工第五建设集团有限公司 A kind of assembled electronic workshop end bay structure and its construction method
CN110258783A (en) * 2019-07-02 2019-09-20 广东工业大学 A kind of assembly concrete frame joint
CN110284520A (en) * 2019-06-25 2019-09-27 北京工业大学 A kind of Long span closure frame plate of dry and wet Hybrid connections-column assembly system
CN110439116A (en) * 2019-08-09 2019-11-12 昌大建筑科技有限公司 Concrete assembles dry construction linked system entirely
CN110485570A (en) * 2019-08-07 2019-11-22 杨秀敏 The support top circulatory system and three-dimensional prefabricated full prefabricated concrete structure method
CN110670721A (en) * 2019-10-15 2020-01-10 广州瀚阳工程咨询有限公司 Implementation method of large-span prestressed concrete assembly type building frame structure
CN110670722A (en) * 2019-10-15 2020-01-10 广州瀚阳工程咨询有限公司 Implementation method of beam-column connecting node of fabricated building
CN110670723A (en) * 2019-10-15 2020-01-10 广州瀚阳工程咨询有限公司 Large-span prestressed concrete assembled building frame system
CN111576619A (en) * 2020-05-29 2020-08-25 三一筑工科技有限公司 Production method of high-strength concrete post-cast assembled frame system
CN112593632A (en) * 2020-12-04 2021-04-02 中天建设集团有限公司 Fabricated beam-slab structure suitable for large-span high-clearance building and construction method thereof
CN112900235A (en) * 2021-03-25 2021-06-04 王冰璇 Assembled supporting trestle and filling core concrete supporting beam
CN113103429A (en) * 2021-04-15 2021-07-13 中国建筑第八工程局有限公司 Prefabricated node mould of assembled steel-concrete mixed frame structure and production method
CN113123462A (en) * 2021-05-25 2021-07-16 重庆大学 Large-span prestressed concrete assembled frame connecting joint and construction method
CN113356349A (en) * 2021-06-24 2021-09-07 昌大建筑科技有限公司 Assembled frame structure system
CN113605771A (en) * 2021-07-27 2021-11-05 中铁十六局集团城市建设发展有限公司 Prestress assembly type frame structure system
CN114164938A (en) * 2021-09-23 2022-03-11 郑州辉昂装饰设计工程有限公司 Self-balancing assembly type frame thin-shell structure system and construction method thereof
CN114396118A (en) * 2021-12-21 2022-04-26 中国建筑技术集团有限公司 Fabricated concrete frame structure connected through prestress compression joint and construction method
CN114508175A (en) * 2022-02-23 2022-05-17 浙江大学建筑设计研究院有限公司 Connecting joint and connecting method for assembled reinforced concrete prefabricated column and beam
CN114892799A (en) * 2022-06-29 2022-08-12 四川宏基原创建筑设计有限公司 Construction method and building of prefabricated reinforced concrete frame structure
CN115198966A (en) * 2021-04-09 2022-10-18 上海砼邦建设工程有限公司 Construction method of prestressed prefabricated laminated frame beam

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1821501A (en) * 2005-02-15 2006-08-23 三井住友建设株式会社 Column-beam attaching tectosome of architecture and method of attaching the same
CN104612246A (en) * 2015-01-30 2015-05-13 柳忠东 Assembled monolithic concrete large-span frame structure system and assembling method thereof
CN105735469A (en) * 2016-02-23 2016-07-06 同济大学 Partially-bonded precast prestressed concrete frame structure
CN105839775A (en) * 2016-05-24 2016-08-10 东南大学 Beam end crossed arc-shaped post-tensioned pre-stressed reinforcing steel dry-type assembling beam-column node
CN205617561U (en) * 2016-04-26 2016-10-05 福州大学 Concrete assembly type structure's beam column node connects
CN205875395U (en) * 2016-08-02 2017-01-11 北京市建筑工程研究院有限责任公司 Prestressing force is from restoring to throne assembled concrete frame beam column node
CN206737116U (en) * 2017-03-10 2017-12-12 东南大学 Node dry and wet Hybrid connections assembled integral concrete frame structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1821501A (en) * 2005-02-15 2006-08-23 三井住友建设株式会社 Column-beam attaching tectosome of architecture and method of attaching the same
CN104612246A (en) * 2015-01-30 2015-05-13 柳忠东 Assembled monolithic concrete large-span frame structure system and assembling method thereof
CN105735469A (en) * 2016-02-23 2016-07-06 同济大学 Partially-bonded precast prestressed concrete frame structure
CN205617561U (en) * 2016-04-26 2016-10-05 福州大学 Concrete assembly type structure's beam column node connects
CN105839775A (en) * 2016-05-24 2016-08-10 东南大学 Beam end crossed arc-shaped post-tensioned pre-stressed reinforcing steel dry-type assembling beam-column node
CN205875395U (en) * 2016-08-02 2017-01-11 北京市建筑工程研究院有限责任公司 Prestressing force is from restoring to throne assembled concrete frame beam column node
CN206737116U (en) * 2017-03-10 2017-12-12 东南大学 Node dry and wet Hybrid connections assembled integral concrete frame structure

Cited By (39)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107165271A (en) * 2017-07-07 2017-09-15 浙江工业大学工程设计集团有限公司 A kind of assembled Special-Shaped Column concrete frame structure
CN109469326A (en) * 2017-09-07 2019-03-15 润弘精密工程事业股份有限公司 Special-shaped grid board construction method
CN109469326B (en) * 2017-09-07 2021-03-30 润弘精密工程事业股份有限公司 Construction method of special-shaped grid plate
CN107578691A (en) * 2017-10-16 2018-01-12 哈尔滨建筑云网络科技有限公司 Frame structure construction training model is used in a kind of assembled architecture teaching
CN109695345B (en) * 2017-10-20 2021-08-06 润弘精密工程事业股份有限公司 Structure construction method of building
CN109695345A (en) * 2017-10-20 2019-04-30 润弘精密工程事业股份有限公司 A kind of structure construction method of building
CN107938845A (en) * 2017-12-23 2018-04-20 中冶建筑研究总院有限公司 A kind of concrete prefabricated assembling combining structures of FRP
CN108149785A (en) * 2017-12-29 2018-06-12 湖南标迪夫节能科技有限公司 A kind of prefabricated post frame for assembled architecture
CN108457422A (en) * 2018-02-01 2018-08-28 东南大学 Precast prestressed beam, assembled composite frame structure and its installation method
CN108179806B (en) * 2018-02-01 2023-10-20 胡习兵 Fully assembled reinforced concrete frame structure system
CN108179806A (en) * 2018-02-01 2018-06-19 胡习兵 A kind of complete assembled steel reinforced concrete frame structure system
CN108755941A (en) * 2018-08-10 2018-11-06 大连理工大学 Assembly concrete frame Mixed Architecture
CN108755941B (en) * 2018-08-10 2023-06-13 大连理工大学 Assembled concrete frame mixed structure system
CN109469202A (en) * 2018-12-12 2019-03-15 中国建筑技术集团有限公司 Prestressed assembly integral concrete frame structure system and construction method thereof
CN110206347A (en) * 2019-05-18 2019-09-06 陕西建工第五建设集团有限公司 A kind of assembled electronic workshop end bay structure and its construction method
CN110284520A (en) * 2019-06-25 2019-09-27 北京工业大学 A kind of Long span closure frame plate of dry and wet Hybrid connections-column assembly system
CN110258783B (en) * 2019-07-02 2024-06-11 广东工业大学 Assembled concrete frame node
CN110258783A (en) * 2019-07-02 2019-09-20 广东工业大学 A kind of assembly concrete frame joint
CN110485570A (en) * 2019-08-07 2019-11-22 杨秀敏 The support top circulatory system and three-dimensional prefabricated full prefabricated concrete structure method
CN110439116A (en) * 2019-08-09 2019-11-12 昌大建筑科技有限公司 Concrete assembles dry construction linked system entirely
CN110670721A (en) * 2019-10-15 2020-01-10 广州瀚阳工程咨询有限公司 Implementation method of large-span prestressed concrete assembly type building frame structure
CN110670722A (en) * 2019-10-15 2020-01-10 广州瀚阳工程咨询有限公司 Implementation method of beam-column connecting node of fabricated building
CN110670723A (en) * 2019-10-15 2020-01-10 广州瀚阳工程咨询有限公司 Large-span prestressed concrete assembled building frame system
CN111576619A (en) * 2020-05-29 2020-08-25 三一筑工科技有限公司 Production method of high-strength concrete post-cast assembled frame system
CN111576619B (en) * 2020-05-29 2023-01-24 三一筑工科技股份有限公司 Production method of high-strength concrete post-cast assembled frame system
CN112593632A (en) * 2020-12-04 2021-04-02 中天建设集团有限公司 Fabricated beam-slab structure suitable for large-span high-clearance building and construction method thereof
CN112900235B (en) * 2021-03-25 2024-02-13 王冰璇 Assembled support trestle and filling core bar concrete bracing beam
CN112900235A (en) * 2021-03-25 2021-06-04 王冰璇 Assembled supporting trestle and filling core concrete supporting beam
CN115198966A (en) * 2021-04-09 2022-10-18 上海砼邦建设工程有限公司 Construction method of prestressed prefabricated laminated frame beam
CN113103429A (en) * 2021-04-15 2021-07-13 中国建筑第八工程局有限公司 Prefabricated node mould of assembled steel-concrete mixed frame structure and production method
CN113123462A (en) * 2021-05-25 2021-07-16 重庆大学 Large-span prestressed concrete assembled frame connecting joint and construction method
CN113356349A (en) * 2021-06-24 2021-09-07 昌大建筑科技有限公司 Assembled frame structure system
CN113605771A (en) * 2021-07-27 2021-11-05 中铁十六局集团城市建设发展有限公司 Prestress assembly type frame structure system
CN113605771B (en) * 2021-07-27 2023-08-29 中铁十六局集团城市建设发展有限公司 Prestress assembly type frame structure system
CN114164938A (en) * 2021-09-23 2022-03-11 郑州辉昂装饰设计工程有限公司 Self-balancing assembly type frame thin-shell structure system and construction method thereof
CN114396118A (en) * 2021-12-21 2022-04-26 中国建筑技术集团有限公司 Fabricated concrete frame structure connected through prestress compression joint and construction method
CN114508175A (en) * 2022-02-23 2022-05-17 浙江大学建筑设计研究院有限公司 Connecting joint and connecting method for assembled reinforced concrete prefabricated column and beam
CN114892799B (en) * 2022-06-29 2022-12-02 四川宏基原创建筑设计有限公司 Construction method and building of prefabricated reinforced concrete frame structure
CN114892799A (en) * 2022-06-29 2022-08-12 四川宏基原创建筑设计有限公司 Construction method and building of prefabricated reinforced concrete frame structure

Similar Documents

Publication Publication Date Title
CN106677339A (en) Assembly integral type concrete frame structure of dry-wet mixed connection of nodes and construction method
CN206737116U (en) Node dry and wet Hybrid connections assembled integral concrete frame structure
CN107165272B (en) Prestressed assembled concrete frame node connecting structure and construction method thereof
CN107700653B (en) Mixed connection post-tensioned prestressing assembled concrete frame system and construction method thereof
CN108060746B (en) Assembled prestressed concrete large-span frame system and construction method thereof
CN106499051B (en) A kind of column perforation prefabricated PC concrete frame frame system and its construction method
CN107460954A (en) A kind of post-tensioned prestressing assembling concrete frame energy dissipation component system and construction method
CN107476476B (en) One kind is greatly across steel bar truss floor support plate and reinforced beam combination constructing method thereof
CN105735469B (en) A kind of part adhesive precast prestressed concrete frame structure
CN107503553A (en) Full prefabricated PC concrete frame energy dissipation component system and construction method
CN109469202A (en) Prestressed assembly integral concrete frame structure system and construction method thereof
CN108005304B (en) Assembled prestressed concrete frame system and construction method thereof
CN206308796U (en) A kind of post insertion prefabricated PC concrete frame frame system
CN207194146U (en) Prestressing force assembly concrete frame joint attachment structure
CN207538322U (en) A kind of prefabricated PC concrete frame frame system
CN109653350B (en) Mixed reinforcement embedded low-prestress dry beam column node and method
CN111424850A (en) Prefabricated reinforced concrete shear wall and construction method
CN208267234U (en) A kind of prefabricated PC concrete large-span frame system
CN212534652U (en) Steel-concrete composite structure frame-cast-in-place concrete shear wall structure system
CN110258788B (en) Semi-dry type connection node of frame beam and frame column and construction method thereof
CN207538201U (en) A kind of post-tensioned prestressing assembles concrete frame energy dissipation component system
CN207538558U (en) Full prefabricated PC concrete frame energy dissipation component system
CN109113171A (en) A kind of Novel bolt connection Precast Concrete Frame
CN115434425A (en) Lattice type steel reinforced concrete prefabricated beam column joint and method
CN207348216U (en) A kind of Hybrid connections post-tensioned prestressing assembles concrete frame system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170517