CN107795749A - A kind of precast spliced pipe fitting jacking system and its construction method - Google Patents

A kind of precast spliced pipe fitting jacking system and its construction method Download PDF

Info

Publication number
CN107795749A
CN107795749A CN201711330797.1A CN201711330797A CN107795749A CN 107795749 A CN107795749 A CN 107795749A CN 201711330797 A CN201711330797 A CN 201711330797A CN 107795749 A CN107795749 A CN 107795749A
Authority
CN
China
Prior art keywords
pipeline
jacking
design
splicing
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711330797.1A
Other languages
Chinese (zh)
Inventor
张智宏
肖宗莉
林自明
刘小勇
王福至
曹承伟
杨启升
张红革
马悦
孙秀云
蒋丽平
郭楠
耿卫红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING ZHUZONG GROUP Co Ltd
Original Assignee
BEIJING ZHUZONG GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING ZHUZONG GROUP Co Ltd filed Critical BEIJING ZHUZONG GROUP Co Ltd
Priority to CN201711330797.1A priority Critical patent/CN107795749A/en
Publication of CN107795749A publication Critical patent/CN107795749A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Abstract

A kind of precast spliced pipe fitting jacking system and its construction method, jacking system include Zhu Ding mechanisms and the splicing pipeline set along in the design path of design pipeline, and splicing internal diameter of the pipeline is more than the external diameter of design pipeline, and splicing pipeline is spliced by splicing pipe fitting;Splicing pipe fitting is stripe board, and its former and later two side corresponds to the axial overlap edge of outstanding formation respectively, two sides in left and right correspond to the outstanding circumferentially overlapping side of formation respectively;Axle of the coaxial splicing pipe fitting along splicing pipeline splices successively upwardly through axial overlap edge, splicing successively upwardly through circumferentially overlapping side along the ring for splicing pipeline with all splicing pipe fittings, is fastened by connector.The construction method of the present invention provides strong support with jack-in process to excavate, by the way of artificial cooperation jacking construction of cutting the earth, can meet execution conditions requirement common in jacking construction by the interim splicing pipeline of the assembly in the design path of design pipeline.It can be widely applied to jacking construction.

Description

A kind of precast spliced pipe fitting jacking system and its construction method
Technical field
The present invention relates to underground engineering field, particularly a kind of jacking construction system and construction method.
Background technology
With the rapid development of science and technology, technical innovation plays important role in all trades and professions.For For building enterprise, undoubtedly a kind of opportunities and challenges.Wherein, jacking construction is as relatively common non-excavating construction method, It is a kind of piping laying construction technology do not excavated or excavated less, when open-cut is more difficult and cutting depth is more than under 5 meters When waterline is higher, suitable for non-excavating construction, i.e. pipe jacking construction technique, it is mainly used in and excavates the larger pipeline work of difficulty Journey, such as sewer line engineering, water supply and sewerage pipeline, natural gas petroleum pipeline, communication cable, it being capable of river crossing, tunnel, public affairs Any building such as road, railway, high mountain.Using pipe jacking construction technique, first, manpower can be saved by not excavating or excavating less, reduce The expense of earth clearance;Second, not excavating or excavating less the disturbance reduced to greatest extent to soil, atmosphere pollution can be reduced, Protect periphery natural ecological environment.
At present, the jacking of jacking construction generally use one side or both sides jacking, the control of generally use computer, laser guide control Preparation method control pipeline elevation and position of center line.For jacking construction as a kind of non-excavating construction method, it is by jacking device Caused top power, overcome the frictional force of pipeline and surrounding soil, the gradient of pipe design is headed into soil, popular says, is exactly After one section pipe jacking, next section pipe continues jacking.Its principle is pushed away by means of main top oil cylinder and pipeline enclosure, relay well etc. Power, tool pipe or development machine are advanced in received well always out of active well through soil layer and sling.Pipeline follow closely tool pipe or After development machine, it is embedded between two wells.Wherein, four kinds of pipe jacking construction techniques are relatively conventional, i.e., cutting edge propulsion working method, mud water type push away Enter engineering method, soil pressure formula propulsion working method, the dense formula propulsion working method of mud.Cutting edge propulsion working method is opening medium-large caliber pipe propulsion working method, Other three kinds are hermetic type medium-large caliber pipe propulsion working method, and mud water type propulsion working method is by cutterhead and top speed balance front soil Pressure, regulation circulating water pressure are handled to balance groundwater pressure without ground improvement or precipitation, after construction ground settlement compared with It is small;Soil pressure formula propulsion working method into cutting storehouse by injecting a certain proportion of mixing material so that the soil mixing full of hopper dredger Body balances earth balance pressure and groundwater pressure, and without the rear portion such as slush pump corollary apparatus, complete machine is cheap, and without mud Processing, construction cost are low;The dense formula propulsion working method of mud uses secondary grouting method, greatly reduces mill resistance, is adapted to push up over long distances Enter.
Although above-mentioned traditional pipe jacking construction method automaticity is high, constructed in the case of single geological conditions straight line jacking Speed is fast, pipeline elevation and position of center line precision are high.But this method needs pipe ends to have active well or a received well, and Pipeline elevation and position of center line precision control when running into barrier during complex geological condition or sweep jacking and jacking Deviation processed is larger, or even can not continue jacking;Especially pipe with small pipe diameter deviation be it is very big, it is necessary to it is continuous adjustment jacking side To and elevation, fine setting number it is frequent, speed of application is slower;And in the initial propulsion stage, direction is mainly main top oil cylinder control, because This, on the one hand will slow down main top fltting speed, on the other hand constantly adjust oil cylinder marshalling and the correction of push pipe head.Sometimes it is mechanical In jack-in process push pipe head damage can not work, and push pipe push pipe head be embedded in soil can not take out push pipe head, it is necessary to Push pipe Handpiece Location takes out push pipe head after excavating shaft again.The A patent disclosures of CN 103090107 rectangle big cross section steel knot The assembled support tube coupling jacking mechanism of structure, advantage are that support tube coupling instead of the prefabricated tube coupling of traditional push pipe, reduce push pipe deadweight, The drawbacks of can effectively avoiding that push pipe driving can not be utilized, but buried depth is restricted, and only applies constructed in shallow embedding at this stage In.
The content of the invention
It is an object of the invention to provide a kind of precast spliced pipe fitting jacking system and its construction method, to solve complex conditions The technical problem that lower jacking construction efficiency is low, precision is low.
To achieve the above object, the present invention adopts the following technical scheme that:
A kind of precast spliced pipe fitting jacking system, including Zhu Ding mechanisms, in addition to set along in the design path of design pipeline Splice pipeline, the splicing internal diameter of the pipeline is more than the external diameter of design pipeline, and splicing pipeline is spliced by splicing pipe fitting;Institute It is stripe board to state splicing pipe fitting, and its former and later two side corresponds to two the axial overlap edge of outstanding formation, left and right sides respectively The outstanding circumferentially overlapping side of formation is corresponded to respectively;Axle of the coaxial splicing pipe fitting along splicing pipeline is upwardly through axial overlap joint Side is spliced and fastened by connector successively, and the ring along splicing pipeline for splicing pipe fitting with week is upwardly through circumferentially overlapping Splice successively and fastened by connector in side.
The Zhu Ding mechanisms are arranged on work bottom, including the postnotum being connected in active well side wall and vertical apical grafting Main top jack on postnotum, the front end of the Zhu Ding mechanisms are also associated with push pipe head.
The cross section of the splicing pipeline is the either more curve abnormity of circular, polygon.
The material of the splicing pipe fitting is fiberglass or metal alloy.
The size for splicing the external diameter that internal diameter of the pipeline is more than design pipeline described in jacking construction is 10~20cm.
A kind of construction method of precast spliced pipe fitting jacking system described in application, is comprised the following steps that
Step 1, construction working well and received well.
Step 2, excavated forward along design path in the design attitude of design pipeline.
Step 3, with the assembled splicing pipeline of excavation construction.
Step 4, repeat step two and step 3 are to splicing pipeline along design path assembly to received well.
Step 5, connection installation Zhu Ding mechanisms and push pipe head in the bottom of active well.
Step 6, adjust the jacking of Zhu Ding mechanisms and highly and behind jacking direction start jacking.
Step 7, design pipeline stop jacking along design path jacking received well.
Step 8, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms and push pipe head.
Step 9, to the surrounding cement injection of design pipeline, complete whole construction.
In the step 2, unidirectionally excavated from active well to received well or from active well and received well simultaneously to middle double To excavation;In the step 7, with design pipeline jacking, the splicing pipeline before push pipe head is removed.
A kind of precast spliced pipe fitting jacking system described in application without received well construction method, for by place or its from Right condition limitation, the situation that can not set received well, are comprised the following steps that:
Step 1, construction working well.
Step 2, excavated forward along design path in the design attitude of design pipeline.
Step 3, with the assembled splicing pipeline of excavation construction.
Step 4, repeat step two and step 3 extremely splice pipeline to design path terminal.
Step 5, in the bottom of active well connection installation Zhu Ding mechanisms.
Step 6, adjust the jacking of Zhu Ding mechanisms and highly and behind jacking direction start jacking.
Step 7, design pipeline to terminal, stop jacking along design path jacking.
Step 8, remove and take out Zhu Ding mechanisms.
Step 9, to the surrounding cement injection of design pipeline, complete whole construction.
Construction method when having a barrier of precast spliced pipe fitting jacking system described in a kind of application, in design pipeline When to have barrier or design path in design path be curve, comprise the following steps that:
Step 1, construction working well and received well.
Step 2, excavated forward along design path in the design attitude of design pipeline.
Step 3, with the assembled splicing pipeline of excavation construction.
Step 4, repeat step two and step 3 are to splicing pipeline along design path assembly to received well.
Step 5, connection installation Zhu Ding mechanisms and push pipe head in the bottom of active well.
Step 6, adjust the jacking of Zhu Ding mechanisms and highly and behind jacking direction start jacking.
Step 7, with design pipeline jacking, remove the splicing pipeline before push pipe head.
Step 8, design pipeline stop jacking along design path jacking received well.
Step 9, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms and push pipe head.
Step 10, to the surrounding cement injection of design pipeline, complete whole construction.
Construction method during a kind of push pipe head damage of the precast spliced pipe fitting jacking system described in application, for setting Count in pipeline jack-in process, the situation of push pipe head damage, comprise the following steps that:
Step 1, excavated from received well along design path to push pipe heading.
Step 2, with the assembled splicing pipeline of excavation construction.
Step 3, repeat step one and step 2 are to splicing pipeline along design path assembly to push pipe Handpiece Location.
Step 4, push pipe head is removed, and received well taking-up is transported to by splicing pipeline.
Step 5, new push pipe head is transported by splicing pipeline, starts jacking after replacing.
Step 6, with design pipeline jacking, remove the splicing pipeline before push pipe head.
Step 7, design pipeline stop jacking along design path jacking received well.
Step 8, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms and push pipe head.
Step 9, to the surrounding cement injection of design pipeline, complete whole construction.
Compared with prior art the invention has the characteristics that and beneficial effect:
The present invention devises a set of jacking system for jacking construction, the assembled interim splicing in the design path of design pipeline Pipeline, strong support is provided with jack-in process to excavate, by the way of artificial cooperation jacking construction of cutting the earth, can meet to push up Common execution conditions requirement in pipe construction:
The first, under normal condition, while is provided with active well and received well, when natural conditions are preferable, can use two-way excavation, Efficiency of construction is improved, splicing tube material is fiberglass, and its processing performance is excellent, has the characteristics of simple technique, one-shot forming, And glass-reinforced plastic material high-strength light, good corrosion resistance, prefabrication is high in machining efficiency, while as design pipeline jacking can be torn open Except splicing pipeline, assembled pipe fitting can continue cycling through utilization, and cost is relatively low.
Second, solves the construction problem in the case of without received well, this method can be not provided with received well, now uneasy Push pipe head is filled, due to splicing the special construction and material of pipeline, advance resistance, speed of application can be reduced when the inorganic crown is entered It hurry up, securely and reliably, suitable wide popularization and application.
The third, splicing pipeline be whole jack-in process provides be oriented to and support effect, guarantee complex geologic conditions or Jacking construction pipeline elevation and position of center line have higher precision in the case of curved jacking, solve and are running into barrier The problem of Shi Dingjin difficulties, the advantages of speed of application is fast, cost is low.
4th kind, when can solve to design middle push pipe head damage in pipeline jack-in process, do not increasing the situation of vertical shaft Under, the problem of push pipe head is taken out, excavate simultaneously assembled interim splicing pipeline in addition by received well, damage push-bench Head can be transported to received well along splicing pipeline and take out, and do not influence normal work, the soil body will not be damaged, securely and reliably Efficiency high.
It the composite can be widely applied to jacking construction.
Brief description of the drawings
The present invention will be further described in detail below in conjunction with the accompanying drawings.
Fig. 1 is the constructing structure schematic diagram of the embodiment of the present invention one.
Fig. 2 is the constructing structure schematic diagram of the embodiment of the present invention two.
Fig. 3 is the constructing structure schematic diagram of the embodiment of the present invention three.
Fig. 4 is the splicing structure schematic diagram of present invention splicing section of jurisdiction.
Fig. 5 is the single chip architecture schematic diagram of present invention splicing section of jurisdiction.
Reference:1- active wells, 2- received wells, 3- Zhu Ding mechanisms, 4- splicings pipe fitting, 5- push pipes head, 6- design pipes Road, 7- connectors, 8- barriers.
Embodiment
Embodiment is shown in Figure 1, this precast spliced pipe fitting jacking system, including Zhu Ding mechanisms 3, in addition to edge design The splicing pipeline set in the design path of pipeline 6, the splicing internal diameter of the pipeline are more than the external diameter of design pipeline 6, splice pipeline It is spliced by splicing pipe fitting 4.
Referring to described in Fig. 5, the splicing pipe fitting 4 is stripe board, and its former and later two side corresponds to outstanding formation respectively Two axial overlap edge, left and right sides correspond to the outstanding circumferentially overlapping side of formation respectively;Splicing shown in Figure 4, coaxial Axle of the pipe fitting 4 along splicing pipeline splices and fastened by connector 7 successively upwardly through axial overlap edge, with the splicing in week The ring along splicing pipeline of pipe fitting 4 splices and fastened by connector successively upwardly through circumferentially overlapping side.
Referring to shown in Fig. 2, Fig. 3, the Zhu Ding mechanisms 3 are arranged on the bottom of active well 1, including are connected in active well side wall Postnotum and vertical top be connected on main top jack on postnotum;The front end of the Zhu Ding mechanisms 3 is also associated with push pipe head.
The cross section of the splicing pipeline is special-shaped for the either more curves of circular, polygon, the material of the splicing pipe fitting 4 For fiberglass or steel, aluminium alloy, hardness can meet surrounding soil pressure, and splicing internal diameter of the pipeline is more than described in jacking construction The size for designing the external diameter of pipeline 6 is 10~20cm.
A kind of construction method of precast spliced pipe fitting jacking system described in application, is comprised the following steps that:
Step 1, construction working well 1 and received well 2.
During construction working well, well head earth excavation is by the way of mechanical equivalent of light excavation, crane lifting;Digging process is according to a Pin The cycle installation of grid steel frame one, the cyclic spray concrete of two Pin grid steel frames one are carried out;Should be along vertical shaft long axis direction point in excavation Duan Jinhang, a soil bucket lay down area is first excavated out at one end, the earthwork at excavation is temporarily placed at the other end;Lifting soil bucket is adopted With diameter 1m, high 1.2m steel cylinder;Crane lifting is commanded by special messenger, while personnel answer extraction shaft in hoisting process Bottom.Fore shaft collar tie beam construction is carried out after to be done, survey crew first is carried out to the plan-position walling crib excavating sideline of fore shaft collar tie beam Positioning, because fore shaft collar tie beam construction stratum is not directed to underground water, so collar tie beam construction is can be carried out in non-Dewatering well, Walling crib earth excavation mainly by the way of the construction of hand excavation's cooperative mechanical, treats that machinery is excavated to apart from fore shaft circle projected depth Manual cleaning surplus earth, smooth compacting are used during 0.5m, and clears up leveling side wall, avoids invading structure, treats manual cleaning base After the completion of face, reinforcing bar is processed and colligation, the hook length of stirrup and reinforcement is 10d, and the connection between cage bar uses The mode of colligation is overlapped, the lap of splice is not less than 35d.In corresponding absolute altitude colligation fore shaft ring beam reinforcing steel bar, in order to ensure that reinforcing bar is taken The requirement connect, after the completion of fore shaft ring beam reinforcing steel bar colligation, vertically inserted in soil and be no less than through fore shaft collar tie beam using spiral 10d, arranged using blossom type, during in order to shaft excavation, the needs of Pin framves construction.Fore shaft circle is propped up after reinforcing bar colligation Mould, fore shaft circle template use glued board, bolt connection, and back up selects the 10 × 10cm lumps of wood and shelf pipe from back up.It is vertical Concrete pad, then formwork erection are first added during mould, carrying out concrete to fore shaft collar tie beam to ensure thickness of protection tier, after formwork erection pours Build, before pouring, check whether template contral line position is accurate, horizontal, cross dimensions and headroom size meet design and wanted Ask;Construction in layer is wanted during placing concrete, setting chute in construction stretches into template;Per one layer of placing, made firm by ramming with poker vibrator it is closely knit, Principle according to " fast insert is pulled out slowly " is vibrated;When concrete is poured into a mould, arrange to stand by Quality Inspector, builder and security official.Treat concrete Intensity reaches form removal after requirement, and watering maintenance immediately, pays attention to being incubated during winter construction after form removal, while in construction of working shaft It is preceding also to take effective Groundwater Control measure, to prevent from locally lying in the possibility of upper strata sealing.Fore shaft collar tie beam has been constructed Finish after concrete strength reaches requirement, that is, start the earthwork in excavation pit, the one side in collar tie beam bottom first digs 1.0m depths, installation Steel grating, vertical reinforcement make an entirety with Guan Liang.Then along crater wall in framework of steel reinforcement medial and lateral welding hanging double steel bar Mesh sheet.Mesh sheet joint is all not less than a grid using colligation, length.Steel grating sets spacing, generally, is set per 0.5m One of steel grating.Punched in vertical shaft and locate the Pin grid solid matters of upper and lower three.Borehole wall integral sinking is prevented, is excavated using diagonal, other Triangle is supported, and this angle is cut the earth, after installation steel grating, gunite concrete, then digs corresponding one jiao.Jetting cement thickness is 300mm, grade C25;Accelerator volume is the 3%~5% of cement weight;Compound is stirred using mixer, with mixing with not mixing Its resting period of the siccative of accelerator is not to be exceeded 1 hour.Spray shield operation should be layered, be segmented, Divisional is carried out, and injection order should Bottom-up, spiral mobile in the horizontal direction, tactical diameter should be 300mm or so, and the circle of a circle pressure one, each jetting height is not It should not be accumulated more than 0.5m, during injection at one, it is desirable to spray closely knit, muscle must not be leaked, it is desirable to which the concrete surface after injection is put down It is whole, straight suitable.Whether checking tool, equipment are complete good before injection, and pipeline must not have dog leg during injection, and spray gun is under any circumstance Forbid to people.Injection worker must accomplish start when first blow, start shooting again, being fed again, at the end of after material sprayed after close wind again.To Jet pump is fed continuous uniform, and when machine runs well, enough material stocks are maintained in hopper.The operating pressure of spraying machine meets Pressure at shower nozzle is in 0.1Mpa.Shower nozzle is vertical with by spray plane holding, preferably keeps 0.6~1.0m distance, controls during injection The ratio of mud.Batch position that connects of previous jetting cement is cleared up before injection every time, the soil on surface is removed, to ensure the close of joint part It is real.Working pit should successively construct downwards successively when constructing, and soil excavation, install external net slice, interior dowel, install steel grating, be interior Dowel, interior mesh sheet, anchor spraying concrete.To ensure the stabilization of vertical shaft, in working shaft, corner is vertically every twice steel grating One of angle brace is placed, to improve the resistance to capsizing of vertical shaft and stability, is supported with digging with setting until vertical shaft bottom surface.For convenience of people Member's vertical shaft up and down, sets in every vertical shaft and is required for the upper and lower safety climbing ladder of personnel, access ladder construction according to atlas, height and For specification according to atlas drawing requirement installation, cat ladder width is 90cm, and cat ladder vertically every 3m designer's half spaces, is climbed Handrail is installed in terraced both sides, and handrail installation must firmly facilitate.Cat ladder material selection steel plate and angle steel are built, need during construction shaft by Cat ladder built-in fitting is pre-buried in place.Shaft bottom uses 300 thick C25 concrete ejections+steel gratings, the 500 thick cast-in-place steel of C40 water-tight concretes Tendon concrete structure, shaft bottom arrangement shaft bottom grid, after shotcrete is constructed, reaches designed elevation, 1.3 × 1.3m is in working pit Catch pit, catch pit use reinforced concrete structure, collect current in working pit.Double-layer threaded reinforced mesh is laid, pours into a mould C40 Concrete 500mm is thick, ensures the hole smooth drying in bottom.Working shaft is set to form an entirety.At the same time, apply being operated well Man-hour is it is noted that safety problem.
After the completion of construction of working shaft, Zhu Ding mechanisms are arranged in well, mainly postnotum, guide rail, main top oil cylinder, oil pump moves Power station, steel staircase etc..Push pipe pedestal is steel construction prefabricated components, and push pipe base position is accurately put by pipe design axis Sample, according to the baseline of surveying and locating during installation, hang in underground and fixation is installed in place.Guide rail on pedestal designs axis according to push pipe And be placed centrally by actual measurement portal center, and bracing reinforcement is set, it is indeformable to ensure that pedestal is stablized.Shaft excavation is to structural outer rim After substrate, back cover should be carried out in time.Vertical shaft shaft bottom is using the structure of " back cover grid+transverse and longitudinal dowel+casting concrete ", work Vertical shaft back cover bar-mat reinforcement is arranged using the double-deck 150mm crosses of φ 22, pours C30 concrete.Casting concrete and installation vertical shaft bottom Elevation must be checked before slab grid, welding, the casting concrete of steel grating could be carried out after accurate, silo bottom is applied Make heatable adobe sleeping platform and catch pit, treat to abolish interim back cover after the completion of jacking.To ensure, entering the stabilization of openings position supporting construction Property, going out, entering the side step of hole two to set the 100mm of 3 Ф of stiffener 22, stretching out hole length up and down and be not less than 1m.On vertical shaft hole Under the support of each increase by one of HW300 × 300 × 10 × 145mm disks, connection upper lower burrs support to form gate frame, to ensure that vertical shaft punches Place is stable, and ensures that disk support is reliably welded with just lining grid.One layer of 20cm basis is spread with C20 concrete in bottom land, width is relatively rested the head on The long 50cm of wood, 20cm × 20cm sleepers, buried depth 13cm are buried in inside concrete.Sleeper length should be each longer than guide rail outer rim both sides Go out 30cm, spacing 40cm.The face of sleeper Transducers Embedded in Concrete needs bag malthoid.Guide rail selects No. 24 rail, two guide rail parallels, contour, The gradient and center line meet the requirements.Elevation is consistent with design conduit slope, is weldingly fixed on steel plate.(This part-structure is existing Have)
Step 2, excavated forward along design path in the design attitude of design pipeline 6:In design pipeline after the completion of active well Design attitude determines a ttom of pipe elevation and position of center line using manually being excavated along duct orientation, per 50cm is excavated forward, opens Mouth size determines according to splicing outer diameter tube.
Step 3, with the assembled splicing pipeline of excavation construction:Splice internal diameter of the pipeline slightly larger than design outer diameter tube, splicing tubes Part uses glass steel material or other rigid materials, and splicing pipe fitting block number can determine according to field condition, this example exemplified by three pieces, Fixation is bolted before contiguous concatenation pipe fitting.
Step 4, repeat step two and step 3 are to splicing pipeline along design path assembly to received well:Assembly completes one The section splicing follow-up continuous excavation of pipeline, assembled splicing pipeline forward is then proceeded to, equally spiral shell is used before two adjacent sections splicing pipeline Bolt is connected, until pipe design terminal.
Step 5, connection installation Zhu Ding mechanisms 3 and push pipe head 5 in the bottom of active well 1.
Splice pipe fitting after the completion of in active well pipe laying jacking device, back is installed first, the size of back passes through Calculating and setting, vertical iron is set before the lumps of wood, piles up horizontal iron before vertical iron, horizontal iron requirement is piled up smooth, and top pick back seat is combined sternly with horizontal iron It is close, top power equably can be passed into back;Jacking hole back will have enough intensity and firmness, can be born in jack-in process The maximum force of jack;Parados surface will smooth out afterwards, and perpendicular to the axis of jacking pipeline, avoid producing it is eccentric by Pressure.Tool back plane will install main top equipment again perpendicular to pipe centerline afterwards after installing, and main top jack is symmetrically arranged as into 2, It is fixed on combination jack stand and makees integral hoisting.Every jack specification is consistent, travel synchronization, and oil circuit is in parallel, collective effect, Independent control valve is had, the range of stretching is less than oil cylinder stroke 10cm or so.Oil pump device is located at apart from main top thousand Jin top nearby, and sets rain-proof shelter, and oil circuit installation is straight, reduces corner, joint is oil-proof, and the maximum working pressure (MWP) of oil pump is not More than 32kpa, equipped with the index protection device such as pressure limiting valve, overflow valve and pressure gauge, test run must be carried out after installing, is being pushed up Enter middle timing repair and maintenance, fix a breakdown in time.The size and structure of push pipe head will meet the requirements, will before jacking hole is hung in Make detailed inspection.When crane unloads head, steady, slow, avoid impacting, collide, and commanded by special messenger, it is ensured that safety can Lean on.After head is placed on guide rail, determine the deviation of directivity and relative relief at the center of front and back end, and make a record, head with The contact surface of guide rail must be steady, identical.Tool pipe and development machine will be accurately positioned, both sides are symmetrical by design requirement.Head must The equipment such as circuit, oil circuit, water route, mud channel and steerable system must be connected one by one, each part is connected firmly, and must not ooze Leakage, installation is correct, and conscientiously inspection and trial operation are carried out to each subsystem.When disposing earthwork transportation equipment, put down using muddy water Weighed push-bench, and mud is passed through into the dredge pump that is connected with pipeline output and directly defeated with spoil disposal by-pass collar in a manner of hydraulic It is sent to surface mud sedimentation basin.During push pipe, either pipe enters hole from working pit, still appears, between pipe and hole all Gap must be left, but gap must carry out closing, such as bad sealing, and underground water, thixotropic slurry and silt particle will be from the gaps In flow in hole, influence to cheat interior operation, the slump at hole can be caused when serious, is caused the accident, therefore hole must do sealing, sealing Method is to pour 300mm thickness concrete seepproof screens entering openings position, watertight rubber circle is installed on the outside of wall.δ is used among rubber ring =10mm steel plates are used as barrier and fixed rubber ring.In order to prevent push pipe head disengaging working pit hole from flowing into muddy water, and ensure The thixotropic slurry of pressure injection will not be lost in jack-in process, it is necessary to install front wall sealing collar in advance, its part is pre-buried Flange chassis, rubber slab, keeper plate of steel, packing ring and bolt.Flange chassis is preliminarily embedded in concrete vertical shaft, and center is correct, and end face is put down It is whole, firmly install, the silk mouth safekeeping of bolt, cement mortar is preliminarily removed.First fill rubber slab during installation, rear steel loading pressing plate, then Upper gasket is simultaneously fastened with nut, it is prevented current.Step 6, the jacking of Zhu Ding mechanisms 3 is adjusted highly and behind jacking direction Start jacking:Top power size is controlled during jacking, top power crosses conference and destroys pipeline.
Step 7, design pipeline 6 stop jacking along design path jacking received well.
Step 8, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms 3 and push pipe head 5.
Step 9, to the surrounding cement injection of design pipeline 6, complete whole construction:The caliber of splicing pipeline is that basis is set The choice of diameter of pipeline is counted, grouting amount will not also be impacted even if assembled pipeline is not removed.
In the step 2, unidirectionally excavated from active well to received well or from active well and received well simultaneously to middle double To excavation;In the step 7, with design pipeline jacking, the splicing pipeline before push pipe head is removed.
It is shown in Figure 1, a kind of precast spliced pipe fitting jacking system described in application without received well construction method, it is and upper State unlike construction method, be the situation for limit, can not being set received well by place or its natural conditions in this example, have Body step is as follows:
Step 1, construction working well 1.
Step 2, excavated forward along design path in the design attitude of design pipeline 6.
Step 3, with the assembled splicing pipeline of excavation construction.
Step 4, repeat step two and step 3 extremely splice pipeline to design path terminal.
Step 5, the connection installation Zhu Ding mechanisms 3 in the bottom of active well 1.
Step 6, adjust the jacking of Zhu Ding mechanisms 3 and highly and behind jacking direction start jacking.
Step 7, design pipeline 6 to terminal, stop jacking along design path jacking.
Step 8, remove and take out Zhu Ding mechanisms 3.
Step 9, to the surrounding cement injection of design pipeline 6, complete whole construction.
It is shown in Figure 2, a kind of construction method when having a barrier of precast spliced pipe fitting jacking system described in application, Unlike embodiment one, this example be when to have barrier 8 or design path be curve in the design path for designing pipeline, Comprise the following steps that:
Step 1, construction working well 1 and received well 2.
Step 2, excavated forward along design path in the design attitude of design pipeline 6.
Step 3, with the assembled splicing pipeline of excavation construction.
Step 4, repeat step two and step 3 are to splicing pipeline along design path assembly to received well.
Step 5, connection installation Zhu Ding mechanisms 3 and push pipe head 5 in the bottom of active well 1.
Step 6, adjust the jacking of Zhu Ding mechanisms 3 and highly and behind jacking direction start jacking.
Step 7, with design pipeline jacking, remove the splicing pipeline before push pipe head.
Step 8, design pipeline 6 stop jacking along design path jacking received well.
Step 9, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms 3 and push pipe head 5.
Step 10, to the surrounding cement injection of design pipeline 6, complete whole construction.
It is shown in Figure 3, construction when a kind of push pipe head of the precast spliced pipe fitting jacking system described in application damages Method, unlike embodiment one, in this example be in pipeline jack-in process design, the situation that push pipe head damages, When mechanical breakdown or damage occur in jack-in process for head, conventional construction method can only increase a vertical shaft in Handpiece Location, Successively excavation supporting takes out head afterwards on earth, maintenance or changes the follow-up continuous jacking of head, and due to head during precession with The soil body is in close contact, and head of being changed planes after active well taking-up needs the time, and can destroy original soil structures during taking out, specifically Step is as follows:
Step 1, excavated from received well 2 along design path to push pipe heading.
Step 2, with the assembled splicing pipeline of excavation construction.
Step 3, repeat step one and step 2 are to splicing pipeline along design path assembly to push pipe Handpiece Location.
Step 4, push pipe head is removed, and received well taking-up is transported to by splicing pipeline.
Step 5, new push pipe head is transported by splicing pipeline, starts jacking after replacing.
Step 6, with design pipeline jacking, remove the splicing pipeline before push pipe head.
Step 7, design pipeline 6 stop jacking along design path jacking received well.
Step 8, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms 3 and push pipe head 5.
Step 9, to the surrounding cement injection of design pipeline 6, complete whole construction.
The time that head takes out head of changing planes from active well is so not only saved, improves operating efficiency, and avoid The possibility of the head destruction soil body is taken out from active well, greatly reduces workload.
The present invention can realize no received well jacking, at the same in complex geological condition and curved jacking pipeline elevation and in Heart line position precision is high, and speed of application is fast, and the processing in jack-in process during head failure is had a clear superiority, and splices pipe fitting Repeatable to utilize, cost is relatively low.

Claims (10)

1. a kind of precast spliced pipe fitting jacking system, including Zhu Ding mechanisms(3), it is characterised in that:Also include along design pipeline(6) Design path on the splicing pipeline that sets, the splicing internal diameter of the pipeline is more than design pipeline(6)External diameter, splicing pipeline be by Splice pipe fitting(4)It is spliced;
The splicing pipe fitting(4)For stripe board, its former and later two side corresponds to the axial overlap edge of outstanding formation, left and right respectively Two sides correspond to the outstanding circumferentially overlapping side of formation respectively;
Coaxial splicing pipe fitting(4)Splice successively upwardly through axial overlap edge along the axle of splicing pipeline and pass through connector Fastening, with the splicing pipe fitting in week(4)The ring along splicing pipeline splice successively upwardly through circumferentially overlapping side and pass through connection Part fastens.
2. precast spliced pipe fitting jacking system according to claim 1, it is characterised in that:The Zhu Ding mechanisms(3)Set In active well(1)Bottom, including the main top that the postnotum and vertical top being connected in active well side wall are connected on postnotum are very heavy Top;
The Zhu Ding mechanisms(3)Front end be also associated with push pipe head(5).
3. precast spliced pipe fitting jacking system according to claim 1, it is characterised in that:The cross section of the splicing pipeline For circular or polygon.
4. precast spliced pipe fitting jacking system according to claim 1, it is characterised in that:The splicing pipe fitting(4)Material Expect for fiberglass or metal alloy.
5. precast spliced pipe fitting jacking system according to claim 1, it is characterised in that:The splicing internal diameter of the pipeline is more than Design pipeline(6)The size of external diameter be 10~20cm.
6. a kind of construction method of precast spliced pipe fitting jacking system using described in claim 2 to 5 any one, its feature It is, comprises the following steps that:
Step 1, construction working well(1)And received well(2);
Step 2, in design pipeline(6)Design attitude excavated forward along design path;
Step 3, with the assembled splicing pipeline of excavation construction;
Step 4, repeat step two and step 3 are to splicing pipeline along design path assembly to received well;
Step 5, in active well(1)Bottom connection installation Zhu Ding mechanisms(3)With push pipe head(5);
Step 6, adjust Zhu Ding mechanisms(3)Jacking height and jacking direction after start jacking;
Step 7, design pipeline(6)Along along design path jacking received well, stop jacking;
Step 8, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms(3)With push pipe head(5);
Step 9, to design pipeline(6)Surrounding cement injection, complete whole construction.
7. construction method according to claim 6, it is characterised in that:
In the step 2, unidirectionally excavated from active well to received well or from active well and received well simultaneously to middle two-way opened Dig;
In the step 7, with design pipeline jacking, the splicing pipeline before push pipe head is removed.
8. a kind of precast spliced pipe fitting jacking system using described in claim 1 to 5 any one without received well construction party Method, the situation for received well is limited, can not set by place or its natural conditions, it is characterised in that comprise the following steps that:
Step 1, construction working well(1);
Step 2, in design pipeline(6)Design attitude excavated forward along design path;
Step 3, with the assembled splicing pipeline of excavation construction;
Step 4, repeat step two and step 3 extremely splice pipeline to design path terminal;
Step 5, in active well(1)Bottom connection installation Zhu Ding mechanisms(3);
Step 6, adjust Zhu Ding mechanisms(3)Jacking height and jacking direction after start jacking;
Step 7, design pipeline(6)Along design path jacking to terminal, jacking is stopped;
Step 8, remove and take out Zhu Ding mechanisms(3);
Step 9, to design pipeline(6)Surrounding cement injection, complete whole construction.
9. a kind of precast spliced pipe fitting jacking system using described in claim 2 to 5 any one has applying during barrier Work method, there is barrier in the design path of design pipeline(8)Or design path is when being curve, it is characterised in that specific Step is as follows:
Step 1, construction working well(1)And received well(2);
Step 2, in design pipeline(6)Design attitude excavated forward along design path;
Step 3, with the assembled splicing pipeline of excavation construction;
Step 4, repeat step two and step 3 are to splicing pipeline along design path assembly to received well;
Step 5, in active well(1)Bottom connection installation Zhu Ding mechanisms(3)With push pipe head(5);
Step 6, adjust Zhu Ding mechanisms(3)Jacking height and jacking direction after start jacking;
Step 7, with design pipeline jacking, remove the splicing pipeline before push pipe head;
Step 8, design pipeline(6)Along along design path jacking received well, stop jacking;
Step 9, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms(3)With push pipe head(5);
Step 10, to design pipeline(6)Surrounding cement injection, complete whole construction.
10. during a kind of push pipe head damage of precast spliced pipe fitting jacking system using described in claim 2 to 5 any one Construction method, in pipeline jack-in process is designed, push pipe head damage situation, it is characterised in that specific steps are such as Under:
Step 1, by received well(2)Excavated along design path to push pipe heading;
Step 2, with the assembled splicing pipeline of excavation construction;
Step 3, repeat step one and step 2 are to splicing pipeline along design path assembly to push pipe Handpiece Location;
Step 4, push pipe head is removed, and received well taking-up is transported to by splicing pipeline;
Step 5, new push pipe head is transported by splicing pipeline, starts jacking after replacing;
Step 6, with design pipeline jacking, remove the splicing pipeline before push pipe head;
Step 7, design pipeline(6)Along along design path jacking received well, stop jacking;
Step 8, respectively by being removed in active well and received well and taking out Zhu Ding mechanisms(3)With push pipe head(5);
Step 9, to design pipeline(6)Surrounding cement injection, complete whole construction.
CN201711330797.1A 2017-12-13 2017-12-13 A kind of precast spliced pipe fitting jacking system and its construction method Pending CN107795749A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711330797.1A CN107795749A (en) 2017-12-13 2017-12-13 A kind of precast spliced pipe fitting jacking system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711330797.1A CN107795749A (en) 2017-12-13 2017-12-13 A kind of precast spliced pipe fitting jacking system and its construction method

Publications (1)

Publication Number Publication Date
CN107795749A true CN107795749A (en) 2018-03-13

Family

ID=61536755

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711330797.1A Pending CN107795749A (en) 2017-12-13 2017-12-13 A kind of precast spliced pipe fitting jacking system and its construction method

Country Status (1)

Country Link
CN (1) CN107795749A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108386608A (en) * 2018-05-02 2018-08-10 广东中科华冉智网科技有限公司 Pipe with small pipe diameter plastic drain-pipe push pipe equipment and plastic drain-pipe pipe jacking construction method
CN108547619A (en) * 2018-05-16 2018-09-18 北京中地盾构工程技术研究院有限公司 Underground shaft assembles recovery type prestressing force support equipment
CN108824449A (en) * 2018-07-26 2018-11-16 中国建筑第八工程局有限公司 Support system and its construction method with underground horizontal support
CN110541966A (en) * 2019-08-27 2019-12-06 北京住总集团有限责任公司 pipe joint jacking auxiliary equipment in narrow space and using method thereof
CN110565779A (en) * 2019-09-03 2019-12-13 苏州市平海排水服务有限公司 method for trenchless replacement and repair of sewage pipeline
CN111810715A (en) * 2020-06-18 2020-10-23 中铁工程装备集团有限公司 Trenchless pipeline updating method and construction system
CN114319433A (en) * 2021-12-22 2022-04-12 深圳市市政工程总公司 Assembly type construction method for working well reverse construction method
CN114321495A (en) * 2021-12-31 2022-04-12 北京易成市政工程有限责任公司 Natural gas pipeline jacking pipe construction method
CN114319443A (en) * 2021-12-22 2022-04-12 深圳市市政工程总公司 Assembled working well
CN114857353A (en) * 2022-04-21 2022-08-05 中铁一局集团有限公司 Construction method of jacking pipe internally-penetrated steel sleeve steel steam pipeline

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2344630Y (en) * 1997-12-12 1999-10-20 马寿 Wide-bore pipe and elbow pipe internal die support device
JP2005155147A (en) * 2003-11-25 2005-06-16 Kidoh Construction Co Ltd Penetration type pipe-jacking method
JP2007139156A (en) * 2005-11-22 2007-06-07 Kurimoto Ltd Pipe travel guide tool for sleeve jacking method
CN101457648A (en) * 2008-12-30 2009-06-17 中铁隧道勘测设计院有限公司 Full-ring steel tunnel segment structure with seal protection door
CN105201517A (en) * 2015-11-11 2015-12-30 中铁二十局集团有限公司 Advance support construction method for high-strength pipe shed of tunnel
CN105863646A (en) * 2016-03-30 2016-08-17 中煤特殊凿井有限责任公司 Freezing construction method in steel pipe curtain of large-section subsurface tunnel
CN106451271A (en) * 2016-12-28 2017-02-22 国网冀北电力有限公司迁西县供电分公司 Cable aisle bridge structure and installment method thereof
CN106437738A (en) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 Pipe roof construction thruster and using method thereof
CN207777770U (en) * 2017-12-13 2018-08-28 北京住总集团有限责任公司 A kind of precast spliced pipe fitting jacking system

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2344630Y (en) * 1997-12-12 1999-10-20 马寿 Wide-bore pipe and elbow pipe internal die support device
JP2005155147A (en) * 2003-11-25 2005-06-16 Kidoh Construction Co Ltd Penetration type pipe-jacking method
JP2007139156A (en) * 2005-11-22 2007-06-07 Kurimoto Ltd Pipe travel guide tool for sleeve jacking method
CN101457648A (en) * 2008-12-30 2009-06-17 中铁隧道勘测设计院有限公司 Full-ring steel tunnel segment structure with seal protection door
CN105201517A (en) * 2015-11-11 2015-12-30 中铁二十局集团有限公司 Advance support construction method for high-strength pipe shed of tunnel
CN105863646A (en) * 2016-03-30 2016-08-17 中煤特殊凿井有限责任公司 Freezing construction method in steel pipe curtain of large-section subsurface tunnel
CN106437738A (en) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 Pipe roof construction thruster and using method thereof
CN106451271A (en) * 2016-12-28 2017-02-22 国网冀北电力有限公司迁西县供电分公司 Cable aisle bridge structure and installment method thereof
CN207777770U (en) * 2017-12-13 2018-08-28 北京住总集团有限责任公司 A kind of precast spliced pipe fitting jacking system

Cited By (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108386608B (en) * 2018-05-02 2023-06-16 中国瑞林工程技术股份有限公司东莞分公司 Small-pipe-diameter plastic drain pipe jacking machine tool and plastic drain pipe jacking construction method
CN108386608A (en) * 2018-05-02 2018-08-10 广东中科华冉智网科技有限公司 Pipe with small pipe diameter plastic drain-pipe push pipe equipment and plastic drain-pipe pipe jacking construction method
CN108547619A (en) * 2018-05-16 2018-09-18 北京中地盾构工程技术研究院有限公司 Underground shaft assembles recovery type prestressing force support equipment
CN108547619B (en) * 2018-05-16 2024-04-19 北京中地盾构工程技术研究院有限公司 Underground shaft assembly recovery type prestress supporting equipment
CN108824449A (en) * 2018-07-26 2018-11-16 中国建筑第八工程局有限公司 Support system and its construction method with underground horizontal support
CN110541966A (en) * 2019-08-27 2019-12-06 北京住总集团有限责任公司 pipe joint jacking auxiliary equipment in narrow space and using method thereof
CN110541966B (en) * 2019-08-27 2024-03-26 北京住总集团有限责任公司 Auxiliary equipment for jacking pipe joint in narrow space and application method thereof
CN110565779A (en) * 2019-09-03 2019-12-13 苏州市平海排水服务有限公司 method for trenchless replacement and repair of sewage pipeline
CN110565779B (en) * 2019-09-03 2021-07-30 苏州市平海排水服务有限公司 Method for trenchless replacement and repair of sewage pipeline
CN111810715B (en) * 2020-06-18 2021-09-24 中铁工程装备集团有限公司 Trenchless pipeline updating method and construction system
CN111810715A (en) * 2020-06-18 2020-10-23 中铁工程装备集团有限公司 Trenchless pipeline updating method and construction system
CN114319433A (en) * 2021-12-22 2022-04-12 深圳市市政工程总公司 Assembly type construction method for working well reverse construction method
CN114319443A (en) * 2021-12-22 2022-04-12 深圳市市政工程总公司 Assembled working well
CN114319443B (en) * 2021-12-22 2023-09-26 深圳市市政工程总公司 Assembled working well
CN114321495A (en) * 2021-12-31 2022-04-12 北京易成市政工程有限责任公司 Natural gas pipeline jacking pipe construction method
CN114857353A (en) * 2022-04-21 2022-08-05 中铁一局集团有限公司 Construction method of jacking pipe internally-penetrated steel sleeve steel steam pipeline
CN114857353B (en) * 2022-04-21 2024-04-05 中铁一局集团有限公司 Construction method for penetrating steel sleeve steel steam pipeline in jacking pipe

Similar Documents

Publication Publication Date Title
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
CN107795749A (en) A kind of precast spliced pipe fitting jacking system and its construction method
CN106641440B (en) A kind of transverse crossing railway line underground piping jacking construction method
CN104612162B (en) A kind of Deep Foundation Pit of Metro Stations excavation construction method
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN111236957B (en) Mechanical pipe jacking construction process
CN102720140B (en) Large-span prestress concrete continuous beam deepwater pier construction process
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN105804089B (en) Locally increase deep support system and its construction method after a kind of former deep foundation pit construction
CN113833480A (en) Shield initial tunneling and arrival construction method
CN109778869A (en) Foundation ditch construction method
CN109723443A (en) Method for tunnel construction
CN113266392B (en) Pipe jacking construction method for penetrating through existing anchor cable group
CN110439590A (en) Method for tunnel construction
CN109488347B (en) Excavation construction method for special stratum chamber
CN109882182A (en) A kind of extra small clear distance construction method in tunnel
US11959243B2 (en) Method for constructing large-span station with two-wing open type half-cover excavation and half-reverse construction
CN109706945A (en) Come down fracture belt tunnel construction method
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN104164881A (en) Piling wall overlapping cantilever foundation pit support construction method and structure
CN204040021U (en) Large diameter pile construction equipment system in city underground engineering tunneling pilot tunnel
CN106284410B (en) The complete rapid constructing method of covered back-digging subway transfer station
CN113898007B (en) Semi-inverse construction method for long-span corridor structure along street
CN110258600A (en) A kind of vertical cofferdam construction engineering method suitable for deep water waters
CN113266362B (en) Top pipe cover excavation construction method for penetrating through existing dense anchor cable area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination