CN107795749A - A prefabricated splicing pipe fitting jacking system and its construction method - Google Patents

A prefabricated splicing pipe fitting jacking system and its construction method Download PDF

Info

Publication number
CN107795749A
CN107795749A CN201711330797.1A CN201711330797A CN107795749A CN 107795749 A CN107795749 A CN 107795749A CN 201711330797 A CN201711330797 A CN 201711330797A CN 107795749 A CN107795749 A CN 107795749A
Authority
CN
China
Prior art keywords
jacking
pipe
spliced
pipeline
design
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711330797.1A
Other languages
Chinese (zh)
Inventor
张智宏
肖宗莉
林自明
刘小勇
王福至
曹承伟
杨启升
张红革
马悦
孙秀云
蒋丽平
郭楠
耿卫红
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BEIJING ZHUZONG GROUP Co Ltd
Original Assignee
BEIJING ZHUZONG GROUP Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BEIJING ZHUZONG GROUP Co Ltd filed Critical BEIJING ZHUZONG GROUP Co Ltd
Priority to CN201711330797.1A priority Critical patent/CN107795749A/en
Publication of CN107795749A publication Critical patent/CN107795749A/en
Pending legal-status Critical Current

Links

Classifications

    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F16ENGINEERING ELEMENTS AND UNITS; GENERAL MEASURES FOR PRODUCING AND MAINTAINING EFFECTIVE FUNCTIONING OF MACHINES OR INSTALLATIONS; THERMAL INSULATION IN GENERAL
    • F16LPIPES; JOINTS OR FITTINGS FOR PIPES; SUPPORTS FOR PIPES, CABLES OR PROTECTIVE TUBING; MEANS FOR THERMAL INSULATION IN GENERAL
    • F16L1/00Laying or reclaiming pipes; Repairing or joining pipes on or under water
    • F16L1/024Laying or reclaiming pipes on land, e.g. above the ground
    • F16L1/06Accessories therefor, e.g. anchors

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

一种预制拼接管件顶进系统及其施工方法,顶进系统包括主顶机构和沿设计管道的设计路径上设置的拼接管道,拼接管道内径大于设计管道的外径,拼接管道是由拼接管件拼接而成的;拼接管件为条形板,其前后两个侧边分别对应向外突出形成轴向搭接边、左右两个侧边分别对应向外突出形成周向搭接边;同轴的拼接管件沿着拼接管道的轴向上通过轴向搭接边依次拼接、同周的拼接管件的沿着拼接管道的环向上通过周向搭接边依次拼接,均通过连接件紧固。本发明的施工方法通过在设计管道的设计路径上拼装临时的拼接管道,为开挖和顶进过程提供有力的支撑,采用人工挖土配合顶管施工的方式,可以满足顶管施工中常见的施工条件要求。可广泛应用于顶管施工。

A prefabricated splicing pipe fitting jacking system and its construction method. The jacking system includes a main jacking mechanism and a splicing pipe arranged along the design path of the designed pipe. The inner diameter of the spliced pipe is larger than the outer diameter of the designed pipe. The spliced pipe is spliced by spliced pipe fittings. The spliced pipe fittings are strip-shaped plates, and the front and rear sides respectively protrude outward to form an axial lap, and the left and right sides respectively protrude outward to form a circumferential lap; coaxial splicing The pipe fittings are sequentially spliced along the axial direction of the spliced pipe through the axial overlapping edges, and the spliced pipe fittings on the same circumference are sequentially spliced along the circumferential direction of the spliced pipe through the circumferential overlapping edges, all of which are fastened by the connectors. The construction method of the present invention provides strong support for the excavation and jacking process by assembling temporary spliced pipelines on the design path of the designed pipeline, and adopts the method of manual excavation and pipe jacking construction, which can meet the common requirements in pipe jacking construction. construction requirements. It can be widely used in pipe jacking construction.

Description

一种预制拼接管件顶进系统及其施工方法A prefabricated splicing pipe fitting jacking system and its construction method

技术领域technical field

本发明涉及地下工程领域,特别是一种顶管施工系统以及施工方法。The invention relates to the field of underground engineering, in particular to a pipe jacking construction system and a construction method.

背景技术Background technique

随着科学技术的飞速发展,技术上的革新在各行各业中扮演着重要的角色。对于建筑企业来说,无疑是一种机遇与挑战。其中,顶管施工作为相对常见的非开挖施工方法,是一种不开挖或少开挖的管道埋设施工技术,当明挖施工较困难且开挖深度大于5米地下水位线较高时,适用于非开挖施工,即顶管施工技术,主要应用于开挖难度较大的管线工程,如污水管线工程、给排水管道、天然气石油管道、通讯电缆等,它能够穿越河流、隧道、公路、铁路、高山等任何建筑物。采用顶管施工技术,一是不开挖或少开挖能够节省人力,减少征地拆迁的费用;二是不开挖或少开挖最大限度地减少对土地的扰动,能够减少大气污染,保护周边自然生态环境。With the rapid development of science and technology, technological innovation plays an important role in all walks of life. For construction enterprises, it is undoubtedly an opportunity and a challenge. Among them, pipe jacking construction, as a relatively common non-excavation construction method, is a pipeline burying construction technology with no or less excavation. When open-cut construction is difficult and the excavation depth is greater than 5 meters, the groundwater level is high , suitable for non-excavation construction, that is, pipe jacking construction technology, mainly used in pipeline projects that are difficult to excavate, such as sewage pipeline projects, water supply and drainage pipelines, natural gas and oil pipelines, communication cables, etc. It can cross rivers, tunnels, Roads, railways, mountains and any other buildings. The use of pipe jacking construction technology, firstly, no excavation or less excavation can save manpower and reduce the cost of land acquisition and demolition; second, no excavation or less excavation can minimize the disturbance to the land, reduce air pollution, and protect the surrounding area natural ecological environment.

目前,顶管施工通常采用单侧顶进或两侧顶进,通常采用计算机控制,激光导向控制法控制管道高程及中心线位置。顶管施工作为一种非开挖施工方法,它是借助顶进设备产生的顶力,克服管道与周围土体的摩擦力,将管道设计的坡度顶入土中,通俗的说,就是一节管子顶进后,下一节管子继续顶进。其原理是借助于主顶油缸及管道间、中继间等推力,把工具管或掘进机从工作井内穿过土层一直推进到接收井内吊起。管道紧随工具管或掘进机后,埋设在两井之间。其中,四种顶管施工技术较为常见,即刃口推进工法、泥水式推进工法、土压式推进工法、泥浓式推进工法。刃口推进工法为开放型大中口径管推进工法,其他三种为密闭型大中口径管推进工法,泥水式推进工法是通过刀盘以及顶速平衡正面土压力,调节循环水压力用以平衡地下水压力,无需地盘改良或降水处理,施工后地表沉降较小;土压式推进工法通过向切削仓内注入一定比例的混合材料,使得充满泥仓的泥土混合体平衡正面土压以及地下水压力,无需泥浆泵等后部配套装置,整机造价低廉,且无需泥浆处理,施工成本低;泥浓式推进工法采用二次注浆方法,大大减少了磨阻力,适合长距离顶进。At present, the pipe jacking construction usually adopts one-side jacking or two-side jacking, and computer control is usually used, and the laser guide control method is used to control the elevation and centerline position of the pipe. As a non-excavation construction method, pipe jacking construction uses the jacking force generated by the jacking equipment to overcome the friction between the pipe and the surrounding soil, and push the designed slope of the pipe into the soil. In layman's terms, it is a section of pipe After jacking, the next section of pipe continues to jacking. Its principle is to push the tool pipe or roadheader from the working well through the soil layer to the receiving well and hoist by means of the thrust of the main top oil cylinder, the pipeline room and the relay room. The pipeline is buried between the two wells immediately after the tool pipe or roadheader. Among them, four kinds of pipe jacking construction techniques are more common, namely, the cutting-edge propulsion method, the mud-water propulsion method, the earth pressure propulsion method, and the mud-thick propulsion method. The cutting edge propulsion method is an open type large and medium-diameter pipe propulsion method, and the other three are closed large and medium-diameter pipe propulsion methods. The muddy water propulsion method is to balance the frontal soil pressure through the cutter head and top speed, and adjust the circulating water pressure to balance Underground water pressure, without site improvement or precipitation treatment, the surface subsidence after construction is small; the earth pressure propulsion method injects a certain proportion of mixed materials into the cutting chamber, so that the soil mixture filled with the mud chamber balances the frontal soil pressure and groundwater pressure, There is no need for rear supporting devices such as mud pumps, and the cost of the whole machine is low, and no mud treatment is required, so the construction cost is low; the mud-thick propulsion method adopts the secondary grouting method, which greatly reduces friction resistance and is suitable for long-distance jacking.

虽然上述传统顶管施工方法自动化程度高,在单一地质条件直线顶进情况下施工速度快、管道高程及中心线位置精度高。但该方法需要管道两端都有工作井或接收井,且在复杂地质条件或弯曲线顶进及顶进的过程中遇到障碍物时管道高程及中心线位置精度控制偏差较大,甚至无法继续顶进;尤其在小管径的偏差是非常大的,需要不断的调整顶进方向和高程,微调次数频繁,施工速度较慢;且在初始推进阶段,方向主要是主顶油缸控制,因此,一方面要减慢主顶推进速度,另一方面要不断调整油缸编组和顶管机头纠偏。有时机械顶进过程中顶管机头损坏不能工作,而顶管顶管机头埋在土中无法取出顶管机头,需要在顶管机头位置重新开挖竖井后取出顶管机头。CN 103090107 A专利公布了矩形大断面钢结构拼装支撑管节顶进机构,优点是支撑管节代替了传统的顶管预制管节,减少了顶管自重,能够有效避免不能利用顶管掘进的弊端,但埋置深度受到限制,现阶段只应用在浅埋施工中。Although the above-mentioned traditional pipe jacking construction method has a high degree of automation, the construction speed is fast, and the pipe elevation and centerline position accuracy is high under the condition of straight jacking under a single geological condition. However, this method requires working wells or receiving wells at both ends of the pipeline, and when obstacles are encountered during jacking and jacking of curved lines under complex geological conditions, the control deviation of pipeline elevation and centerline position accuracy is relatively large, and even cannot be achieved. Continue jacking; especially in small pipe diameters, the deviation is very large, it is necessary to continuously adjust the jacking direction and elevation, the frequency of fine-tuning is frequent, and the construction speed is slow; and in the initial stage of propulsion, the direction is mainly controlled by the main jacking cylinder, so On the one hand, it is necessary to slow down the propulsion speed of the main jack, on the other hand, it is necessary to continuously adjust the oil cylinder grouping and the deviation correction of the pipe jacking head. Sometimes the pipe jacking head is damaged and cannot work during the mechanical jacking process, and the pipe jacking head is buried in the soil and cannot be taken out. It is necessary to re-excavate the shaft at the position of the pipe jacking head and then take out the pipe jacking head. CN 103090107 A patent discloses a rectangular large-section steel structure assembled support pipe joint jacking mechanism. The advantage is that the support pipe joint replaces the traditional pipe jacking prefabricated pipe joint, reduces the dead weight of the pipe jacking, and can effectively avoid the disadvantages of not being able to use the pipe jacking for excavation , but the burial depth is limited, and it is only used in shallow burial construction at this stage.

发明内容Contents of the invention

本发明的目的是提供一种预制拼接管件顶进系统及其施工方法,要解决复杂条件下顶管施工效率低、精度低的技术问题。The purpose of the present invention is to provide a jacking system for prefabricated spliced pipe fittings and its construction method, to solve the technical problems of low construction efficiency and low precision of pipe jacking under complex conditions.

为实现上述目的,本发明采用如下技术方案:To achieve the above object, the present invention adopts the following technical solutions:

一种预制拼接管件顶进系统,包括主顶机构,还包括沿设计管道的设计路径上设置的拼接管道,所述拼接管道内径大于设计管道的外径,拼接管道是由拼接管件拼接而成的;所述拼接管件为条形板,其前后两个侧边分别对应向外突出形成轴向搭接边、左右两个侧边分别对应向外突出形成周向搭接边;同轴的拼接管件沿着拼接管道的轴向上通过轴向搭接边依次拼接、并通过连接件紧固,同周的拼接管件的沿着拼接管道的环向上通过周向搭接边依次拼接、并通过连接件紧固。A jacking system for prefabricated spliced pipe fittings, including a main jacking mechanism, and a spliced pipe arranged along the design path of the designed pipe, the inner diameter of the spliced pipe is larger than the outer diameter of the designed pipe, and the spliced pipe is spliced by spliced pipe fittings The splicing pipe fitting is a strip plate, and its front and rear sides protrude outward respectively to form an axial lap, and the left and right sides respectively protrude outward to form a circumferential lap; the coaxial splicing pipe Along the axial direction of the spliced pipe, it is sequentially spliced through the axial overlapping edge and fastened by the connecting piece. fasten.

所述主顶机构设置在工作井底部,包括连接在工作井侧壁上的后背板和垂直顶接在后背板上的主顶千斤顶,所述主顶机构的前端还连接有顶管机头。The main jacking mechanism is arranged at the bottom of the working well, including the back plate connected to the side wall of the working well and the main jacking jack vertically connected to the back plate, and the front end of the main jacking mechanism is also connected with a pipe jacking machine head.

所述拼接管道的横截面为圆形、多边形或者是多曲线异形。The cross-section of the spliced pipe is circular, polygonal or multi-curved.

所述拼接管件的材料为玻璃钢或者金属合金。The material of the spliced pipe fittings is glass fiber reinforced plastic or metal alloy.

顶进施工所述拼接管道内径大于设计管道的外径的尺寸为10~20cm。In jacking construction, the inner diameter of the spliced pipeline is 10-20cm larger than the outer diameter of the designed pipeline.

一种应用所述的预制拼接管件顶进系统的施工方法,具体步骤如下A construction method using the prefabricated splicing pipe fitting jacking system, the specific steps are as follows

步骤一,施工工作井和接收井。Step 1: Construction of working wells and receiving wells.

步骤二,在设计管道的设计位置沿着设计路径向前开挖。Step 2: Excavate forward along the design path at the design position of the design pipeline.

步骤三,随着开挖施工拼装拼接管道。Step 3, assembling and splicing pipelines along with the excavation construction.

步骤四,重复步骤二和步骤三至拼接管道沿设计路径拼装至接收井。Step 4, repeat steps 2 and 3 until the spliced pipeline is assembled to the receiving well along the design path.

步骤五,在工作井的底部连接安装主顶机构和顶管机头。Step five, connect and install the main jacking mechanism and the pipe jacking head at the bottom of the working shaft.

步骤六,调整好主顶机构的顶进高度和顶进方向后开始顶进。Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism.

步骤七,设计管道沿设计路径顶进接收井内,停止顶进。Step seven, the designed pipeline is jacked into the receiving well along the designed path, and the jacking is stopped.

步骤八,分别由工作井和接收井中拆除并取出主顶机构和顶管机头。Step 8: Remove and take out the main jacking mechanism and the pipe jacking head from the working well and the receiving well respectively.

步骤九,向设计管道的四周注水泥浆,完成整个施工。Step 9: inject grout around the designed pipeline to complete the whole construction.

所述步骤二中,由工作井向接收井单向开挖或者由工作井和接收井同时向中间双向开挖;所述步骤七中,随着设计管道顶进,拆除顶管机头前的拼接管道。In the second step, one-way excavation is carried out from the working well to the receiving well, or the two-way excavation is carried out from the working well and the receiving well to the middle at the same time; Splicing pipes.

一种应用所述的预制拼接管件顶进系统的无接收井施工方法,针对受场地或其自然条件限制、无法设置接收井的情况,具体步骤如下:A construction method without a receiving well using the prefabricated splicing pipe fitting jacking system, for the situation where the receiving well cannot be set due to the limitation of the site or its natural conditions, the specific steps are as follows:

步骤一,施工工作井。Step one, construction work well.

步骤二,在设计管道的设计位置沿着设计路径向前开挖。Step 2: Excavate forward along the design path at the design position of the design pipeline.

步骤三,随着开挖施工拼装拼接管道。Step 3, assembling and splicing pipelines along with the excavation construction.

步骤四,重复步骤二和步骤三至拼接管道至设计路径终点。Step 4, repeat steps 2 and 3 to splice the pipes to the end of the design path.

步骤五,在工作井的底部连接安装主顶机构。Step five, connect and install the main top mechanism at the bottom of the working well.

步骤六,调整好主顶机构的顶进高度和顶进方向后开始顶进。Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism.

步骤七,设计管道沿设计路径顶进至终点,停止顶进。Step 7, the designed pipeline is jacked to the end point along the design path, and the jacking is stopped.

步骤八,拆除并取出主顶机构。Step eight, remove and take out the main top mechanism.

步骤九,向设计管道的四周注水泥浆,完成整个施工。Step 9: inject grout around the designed pipeline to complete the whole construction.

一种应用所述的预制拼接管件顶进系统的有障碍物时的施工方法,在设计管道的设计路径上有障碍物或者设计路径为曲线时,具体步骤如下:A construction method when there are obstacles using the prefabricated splicing pipe fitting jacking system, when there are obstacles on the design path of the design pipeline or the design path is a curve, the specific steps are as follows:

步骤一,施工工作井和接收井。Step 1: Construction of working wells and receiving wells.

步骤二,在设计管道的设计位置沿着设计路径向前开挖。Step 2: Excavate forward along the design path at the design position of the design pipeline.

步骤三,随着开挖施工拼装拼接管道。Step 3, assembling and splicing pipelines along with the excavation construction.

步骤四,重复步骤二和步骤三至拼接管道沿设计路径拼装至接收井。Step 4, repeat steps 2 and 3 until the spliced pipeline is assembled to the receiving well along the design path.

步骤五,在工作井的底部连接安装主顶机构和顶管机头。Step five, connect and install the main jacking mechanism and the pipe jacking head at the bottom of the working shaft.

步骤六,调整好主顶机构的顶进高度和顶进方向后开始顶进。Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism.

步骤七,随着设计管道顶进,拆除顶管机头前的拼接管道。Step 7: With the jacking of the designed pipeline, remove the spliced pipeline in front of the pipe jacking head.

步骤八,设计管道沿设计路径顶进接收井内,停止顶进。Step 8, the designed pipeline is jacked into the receiving well along the designed path, and the jacking is stopped.

步骤九,分别由工作井和接收井中拆除并取出主顶机构和顶管机头。Step 9: Remove and take out the main jacking mechanism and the pipe jacking head from the working well and the receiving well respectively.

步骤十,向设计管道的四周注水泥浆,完成整个施工。Step ten, inject grout around the designed pipeline to complete the whole construction.

一种应用所述的预制拼接管件顶进系统的顶管机头损坏时的施工方法,针对在设计管道顶进过程中、顶管机头损坏的情况,具体步骤如下:A construction method when the pipe jacking head of the prefabricated splicing pipe fitting jacking system is damaged, the specific steps are as follows for the damage of the pipe jacking head during the design pipeline jacking process:

步骤一,由接收井沿着设计路径向顶管机头方向开挖。Step 1: Excavate from the receiving well to the direction of the pipe jacking head along the designed path.

步骤二,随着开挖施工拼装拼接管道。Step 2, assembling and splicing pipelines along with the excavation construction.

步骤三,重复步骤一和步骤二至拼接管道沿设计路径拼装至顶管机头位置。Step 3, repeat step 1 and step 2 until the spliced pipe is assembled to the position of the pipe jacking head along the design path.

步骤四,拆除顶管机头,并通过拼接管道运送至接收井取出。Step 4, dismantle the pipe jacking head, and transport it to the receiving well through the spliced pipeline to take it out.

步骤五,通过拼接管道运送新的顶管机头,更换后开始顶进。Step 5: Transport the new pipe jacking head through spliced pipes, and start jacking after replacement.

步骤六,随着设计管道顶进,拆除顶管机头前的拼接管道。Step 6: With the jacking of the designed pipeline, the spliced pipeline in front of the pipe jacking head is removed.

步骤七,设计管道沿设计路径顶进接收井内,停止顶进。Step seven, the designed pipeline is jacked into the receiving well along the designed path, and the jacking is stopped.

步骤八,分别由工作井和接收井中拆除并取出主顶机构和顶管机头。Step 8: Remove and take out the main jacking mechanism and the pipe jacking head from the working well and the receiving well respectively.

步骤九,向设计管道的四周注水泥浆,完成整个施工。Step 9: inject grout around the designed pipeline to complete the whole construction.

与现有技术相比本发明具有以下特点和有益效果:Compared with the prior art, the present invention has the following characteristics and beneficial effects:

本发明针对顶管施工设计了一套顶进系统,在设计管道的设计路径上拼装临时的拼接管道,为开挖和顶进过程提供有力的支撑,采用人工挖土配合顶管施工的方式,可以满足顶管施工中常见的施工条件要求:The present invention designs a set of jacking system for pipe jacking construction, assembles temporary spliced pipes on the design path of the designed pipes, provides strong support for the excavation and jacking process, and adopts the method of manual excavation and pipe jacking construction, It can meet the common construction conditions in pipe jacking construction:

第一种,常规条件下,同时设有工作井和接收井,自然条件较好时,可以采用双向开挖,提高施工效率,拼接管件材料为玻璃钢,其工艺性能优良,具有工艺简单、一次成型的特点,且玻璃钢材料轻质高强,耐腐蚀性好,工厂预制加工效率高,同时随着设计管道顶进可以拆除拼接管道,拼装管件可以继续循环利用,造价较低。The first one, under normal conditions, there are working wells and receiving wells at the same time. When the natural conditions are good, two-way excavation can be used to improve construction efficiency. The material of the splicing pipe fittings is glass fiber reinforced plastic, which has excellent process performance, simple process, and one-time molding. The characteristics of FRP are light, high strength, good corrosion resistance, high efficiency of factory prefabrication and processing, and at the same time, the spliced pipe can be dismantled along with the jacking of the designed pipe, and the assembled pipe fittings can continue to be recycled, and the cost is low.

第二种,解决了在无接收井情况下的施工问题,该方法可不设置接收井,此时不安装顶管机头,由于拼接管道的特殊结构和材料,无机头顶进时能够减少前进阻力,施工速度快,安全可靠,适宜广泛推广应用。The second method solves the construction problem without a receiving well. This method does not need to set a receiving well. At this time, the pipe jacking head is not installed. Due to the special structure and material of the spliced pipes, the forward resistance can be reduced when the head is jacked. The construction speed is fast, safe and reliable, and suitable for wide application.

第三种,拼接管道为整个顶进过程提供导向和支撑的作用,保证地质条件复杂或曲线顶进的情况下顶管施工管道高程及中心线位置具有较高的精度,解决了在遇到障碍物时顶进困难的问题,施工速度快、成本低的优点。The third type, spliced pipes provide guidance and support for the entire jacking process, ensuring that the pipe jacking construction has high accuracy in the elevation and center line position of the pipe jacking construction in the case of complex geological conditions or curved jacking, and solves the problem when encountering obstacles It has the advantages of fast construction speed and low cost.

第四种,可以解决设计管道顶进过程中中顶管机头损坏时,在不增加竖井的情况下,将顶管机头取出的问题,通过接收井另外开挖并拼装临时的拼接管道即可,损坏顶管机头即可沿着拼接管道运送至接收井取出,不影响正常工作,不会对土体造成破坏,安全可靠效率高。The fourth type can solve the problem of taking out the pipe jacking head without increasing the vertical shaft when the pipe jacking head is damaged during the design pipeline jacking process, and then excavate and assemble the temporary spliced pipe through the receiving shaft. Yes, if the pipe jacking head is damaged, it can be transported to the receiving well along the spliced pipeline and taken out without affecting the normal work or causing damage to the soil, which is safe, reliable and efficient.

本发明可广泛应用于顶管施工。The invention can be widely used in pipe jacking construction.

附图说明Description of drawings

下面结合附图对本发明做进一步详细的说明。The present invention will be described in further detail below in conjunction with the accompanying drawings.

图1是本发明实施例一的施工结构示意图。Fig. 1 is a schematic diagram of the construction structure of Embodiment 1 of the present invention.

图2是本发明实施例二的施工结构示意图。Fig. 2 is a schematic diagram of the construction structure of Embodiment 2 of the present invention.

图3是本发明实施例三的施工结构示意图。Fig. 3 is a schematic diagram of the construction structure of Embodiment 3 of the present invention.

图4是本发明拼接管片的拼装结构示意图。Fig. 4 is a schematic diagram of the assembled structure of the spliced segments of the present invention.

图5是本发明拼接管片的单片结构示意图。Fig. 5 is a schematic diagram of the single-piece structure of the spliced segment of the present invention.

附图标记:1-工作井、2-接收井、3-主顶机构、4-拼接管件、5-顶管机头、6-设计管道、7-连接件、8-障碍物。Reference signs: 1 - working well, 2 - receiving well, 3 - main jacking mechanism, 4 - splicing pipe fittings, 5 - pipe jacking head, 6 - design pipeline, 7 - connecting piece, 8 - obstacle.

具体实施方式Detailed ways

实施例参见图1所示,这种预制拼接管件顶进系统,包括主顶机构3,还包括沿设计管道6的设计路径上设置的拼接管道,所述拼接管道内径大于设计管道6的外径,拼接管道是由拼接管件4拼接而成的。Referring to the embodiment shown in Figure 1, this prefabricated splicing pipe fitting jacking system includes a main jacking mechanism 3, and also includes splicing pipes arranged along the design path of the design pipe 6, and the inner diameter of the splicing pipe is larger than the outer diameter of the design pipe 6 , the spliced pipeline is formed by splicing the spliced pipe fittings 4 .

参见图5所述,所述拼接管件4为条形板,其前后两个侧边分别对应向外突出形成轴向搭接边、左右两个侧边分别对应向外突出形成周向搭接边;参见图4所示,同轴的拼接管件4沿着拼接管道的轴向上通过轴向搭接边依次拼接、并通过连接件7紧固,同周的拼接管件4的沿着拼接管道的环向上通过周向搭接边依次拼接、并通过连接件紧固。Referring to FIG. 5 , the spliced pipe fitting 4 is a strip plate, and its front and rear sides respectively protrude outwards to form an axial overlapping edge, and the left and right sides respectively protrude outwards to form a circumferential overlapping edge. ; Referring to Figure 4, the coaxial spliced pipe fittings 4 are sequentially spliced along the axial direction of the spliced pipe through the axial overlapping edges and fastened by the connecting piece 7, and the spliced pipe fittings 4 of the same circumference are spliced along the spliced pipe. The rings are sequentially spliced upward through the circumferential overlapping edges and fastened through the connecting pieces.

参见图2、图3所示,所述主顶机构3设置在工作井1底部,包括连接在工作井侧壁上的后背板和垂直顶接在后背板上的主顶千斤顶;所述主顶机构3的前端还连接有顶管机头。Referring to Fig. 2 and shown in Fig. 3, the main jacking mechanism 3 is arranged at the bottom of the working well 1, including the backboard connected to the side wall of the working well and the main jacking jack vertically connected to the backboard; The front end of the main jacking mechanism 3 is also connected with a pipe jacking head.

所述拼接管道的横截面为圆形、多边形或者是多曲线异形,所述拼接管件4的材料为玻璃钢或者钢、铝合金,硬度能满足周围土体压力即可,顶进施工所述拼接管道内径大于设计管道6的外径的尺寸为10~20cm。The cross-section of the spliced pipeline is circular, polygonal or multi-curved. The material of the spliced pipe fitting 4 is glass fiber reinforced plastic, steel, or aluminum alloy, and the hardness can meet the pressure of the surrounding soil. The dimension whose inner diameter is larger than the outer diameter of the designed pipeline 6 is 10-20 cm.

一种应用所述的预制拼接管件顶进系统的施工方法,具体步骤如下:A construction method using the prefabricated splicing pipe fitting jacking system, the specific steps are as follows:

步骤一,施工工作井1和接收井2。Step 1, construction of working well 1 and receiving well 2.

施工工作井时,井口土方开挖采用机械开挖的方式,吊车提升;开挖过程按照一榀格栅钢架一循环安装,两榀格栅钢架一循环喷射混凝土进行;开挖中应沿竖井长轴方向分段进行,先在一端开挖出一个土斗搁置区,将开挖处的土方临时放置在另一端;提升土斗采用直径1m,高1.2m的钢制圆筒;吊车提升由专人进行指挥,同时在吊装过程中人员应撤出井底。待完成后进行锁口圈梁施工,首先测量人员对锁口圈梁的平面位置井圈开挖边线进行定位,因锁口圈梁施工地层未涉及到地下水,所以在未施工降水井时就可以进行圈梁施工,井圈土方开挖主要采用人工开挖配合机械施工的方式,待机械开挖至距离锁口圈设计深度0.5m时采用人工清理剩余土方,平整夯实,并清理整平侧壁,避免侵入结构,待人工清理基面完成后,对钢筋进行加工和绑扎,箍筋及加强筋的弯钩长度为10d,主筋之间的连接采用搭接绑扎的方式,搭接长度不小于35d。在对应的标高绑扎锁口圈梁钢筋,为了保证钢筋搭接的要求,在锁口圈梁钢筋绑扎完成后,使用螺纹钢筋穿过锁口圈梁竖向插入土中不少于10d,采用梅花型布置,以便于竖井开挖时,榀架施工的需要。钢筋绑扎后对锁口圈进行支模,锁口圈模板采用胶合板,螺栓连接,背撑选用背撑选用10×10cm的方木以及架子管。立模时先加设混凝土垫块,再立模,以保证钢筋保护层厚度,立模后对锁口圈梁进行混凝土浇筑,浇筑之前,检查模板控制线位置是否准确无误,水平、断面尺寸和净空大小符合设计要求;灌筑砼时要分层施工,施工中设滑槽伸入模板;每灌筑一层,用插入式振捣器捣固密实,按照“快插慢拔”的原则进行振捣;砼浇注时,安排质检员、施工员和安全员旁站。待混凝土强度达到要求后拆除模板,拆模后立即洒水养护,冬季施工时注意保温,同时在工作井施工前还应采取有效的地下水控制措施,以防止局部存在上层止水的可能性。锁口圈梁施工完毕待混凝土强度达到要求后,即开始开挖基坑内土方,在圈梁下部的一面先挖1.0m深,安装钢格栅,竖向钢筋与冠梁使之成为一个整体。然后沿坑壁在钢筋骨架内、外侧焊挂双层钢筋网片。网片接头全部采用绑扎,长度不小于一网格。钢格栅设置间距,一般情况下,每0.5m设一道钢格栅。在竖井开洞处上、下方三榀格栅密排。防止井壁整体下沉,采用对角开挖,其他三角做支撑,此角挖土、安装钢格栅、喷射混凝土后,再挖相对应的一角。喷射砼厚度为300mm,等级C25;速凝剂掺量为水泥重量的3%~5%;混合料采用搅拌机搅拌,随拌随用,不掺速凝剂的干料其存放时间不应超过1小时。喷护作业应分层、分段、分部位进行,喷射顺序应自下向上,沿水平方向螺旋式移动,回旋直径应为300mm左右,一圈压一圈,每次喷射高度不大于0.5m,喷射时不应在一处堆积,要求喷射密实,不得漏筋,要求喷射后的混凝土表面平整、直顺。喷射前检查工具、设备是否齐全良好,喷射时管道不得有死弯,喷枪在任何情况下严禁对人。喷射工人必须做到开始时先送风、再开机、再给料,结束时待料喷完后再关风。向喷射泵供料连续均匀,机器正常运转时,料斗内保持有足够的存料。喷射机的工作压力满足喷头处的压力在0.1Mpa。喷头与受喷面保持垂直,宜保持0.6~1.0m的距离,喷射时控制好水灰比。每次喷射前将前次喷射砼的接茬部位清理,清除表面的泥土,以保障接茬处的密实。工作坑施工时应依次向下逐层施工,土体开挖、安装外网片、内连接筋、安装钢格栅、内连接筋、内网片、锚喷混凝土。为确保竖井的稳定,在工作竖井内,四角竖向每隔两道钢格栅放置一道角撑,以提高竖井的抗倾覆能力及稳定性,支撑随挖随设直至竖井底面。为方便人员上下竖井,在每座竖井内设置供人员上、下的安全爬梯,爬梯施工按照图集要求,高度及规格按照图集图纸要求安装施工,爬梯宽度为90cm,爬梯竖向每隔3m设置人员休息平台,爬梯两侧安装扶手,扶手安装必须牢固方便。爬梯材料选用钢板及角钢搭建,施工竖井时需将爬梯预埋件预埋到位。井底采用300厚C25混凝土喷射+钢格栅,500厚C40抗渗混凝土现浇钢筋混凝土结构,井底布置井底格栅,锚喷施工完毕后,达到设计标高,在工作坑做1.3×1.3m集水坑,集水坑采用钢筋混凝土结构,汇集工作坑内水流。铺设双层螺纹钢筋网片,浇注C40混凝土500mm厚,保证坑底平整干燥。使工作竖井形成一个整体。与此同时,在进行工作井施工时要注意安全问题。During the construction of the working well, the excavation of the earthwork at the wellhead adopts the method of mechanical excavation, and the crane is lifted; the excavation process is installed according to one grid steel frame and one cycle, and the two grid steel frames are sprayed concrete in one cycle; the excavation should be carried out along the The long axis of the shaft is carried out in sections. First, a soil bucket rest area is excavated at one end, and the earthwork at the excavation site is temporarily placed at the other end; the lifting soil bucket adopts a steel cylinder with a diameter of 1m and a height of 1.2m; Commanded by a special person, at the same time, the personnel should withdraw from the bottom of the well during the hoisting process. After the construction of the lock ring beam is completed, the surveyors first locate the plane position of the lock ring beam and the excavation line of the well circle. Because the construction stratum of the lock ring beam does not involve groundwater, it can be done when the dewatering well is not constructed. For ring beam construction, the excavation of the well ring earthwork mainly adopts the method of manual excavation combined with mechanical construction. When the mechanical excavation reaches the design depth of 0.5m from the locking ring, the remaining earthwork is manually cleaned, leveled and compacted, and the side wall is cleaned and leveled , to avoid intrusion into the structure, after the manual cleaning of the base surface is completed, the steel bars are processed and bound, the hook length of the stirrups and reinforcing bars is 10d, the connection between the main bars is lapped and tied, and the lapped length is not less than 35d . Bind the steel bars of the lock ring beam at the corresponding elevation. In order to ensure the requirements of the overlapping of the steel bars, after the binding of the lock ring beam reinforcement is completed, use the threaded steel bar to pass through the lock ring beam and insert vertically into the soil for no less than 10 days. Type layout, in order to meet the needs of the frame construction when the shaft is excavated. After the steel bars are bound, the lock ring is molded. The lock ring template is made of plywood, connected by bolts, and the back support is made of 10×10cm square wood and shelf pipes. When setting up the formwork, add concrete pads first, and then set up the formwork to ensure the thickness of the steel bar protection layer. After the formwork is set up, concrete is poured on the lock ring beam. Before pouring, check whether the position of the formwork control line is correct, the level, the size of the section and The size of the headroom meets the design requirements; when pouring concrete, it should be constructed in layers, and a chute should be provided to extend into the formwork during construction; each layer of pouring should be compacted with a plug-in vibrator according to the principle of "quick insertion and slow extraction" Vibration; when pouring concrete, arrange quality inspectors, construction workers and safety officers to stand by. Remove the formwork after the concrete strength reaches the requirement, sprinkle water immediately after the removal of the formwork, pay attention to heat preservation during construction in winter, and take effective groundwater control measures before the construction of the working well to prevent the possibility of local water stop on the upper layer. After the construction of the lock ring beam is completed and the concrete strength meets the requirements, the earthwork in the foundation pit will be excavated, and the lower side of the ring beam will be dug 1.0m deep first, and the steel grid will be installed, and the vertical steel bar and the crown beam will be integrated. Then weld and hang double-layer steel mesh sheets on the inside and outside of the steel skeleton along the pit wall. The mesh joints are all bound, and the length is not less than one mesh. The spacing of the steel grid is set. Generally, a steel grid is set every 0.5m. The upper and lower three grilles are closely arranged at the opening of the shaft. To prevent the overall sinking of the shaft wall, excavate diagonally, and other triangles are used as supports. After excavating soil at this corner, installing steel grids and spraying concrete, dig the corresponding corner. The thickness of sprayed concrete is 300mm, grade C25; the amount of accelerator is 3% to 5% of the weight of cement; the mixture is stirred by a mixer, and it can be used as it is mixed. The storage time of dry materials without accelerator should not exceed 1 Hour. The spray protection operation should be carried out in layers, sections, and parts. The spraying sequence should be from bottom to top, moving spirally along the horizontal direction. The diameter of the circle should be about 300mm, one circle at a time, and the height of each spraying should not exceed 0.5m. When spraying, it should not accumulate in one place. It is required that the spraying should be dense without leaking reinforcement, and that the surface of the sprayed concrete should be flat and straight. Before spraying, check whether the tools and equipment are complete and in good condition. There must be no dead bends in the pipeline during spraying. The spray gun is strictly forbidden to touch people under any circumstances. Spray workers must first supply air at the beginning, then turn on the machine, and then feed materials, and then turn off the air after the materials are sprayed at the end. The material is continuously and evenly supplied to the jet pump, and there is sufficient stock in the hopper when the machine is in normal operation. The working pressure of the jet machine meets the pressure at the nozzle at 0.1Mpa. The nozzle should be kept vertical to the surface to be sprayed, and a distance of 0.6-1.0m should be kept, and the water-cement ratio should be well controlled when spraying. Before each spraying, clean the part where the stubble was sprayed last time, and remove the soil on the surface to ensure the compactness of the stubble. During the construction of the working pit, it should be constructed layer by layer downwards, excavating the soil, installing the outer mesh, the inner connecting bars, installing the steel grid, the inner connecting bars, the inner mesh, and the anchor shotcrete. In order to ensure the stability of the shaft, in the working shaft, a corner brace is placed vertically every two steel grids at the four corners to improve the anti-overturning ability and stability of the shaft. In order to make it easier for people to go up and down the shaft, a safety ladder is installed in each shaft for people to go up and down. The construction of the ladder is in accordance with the requirements of the atlas, and the height and specifications are installed and constructed according to the requirements of the drawings of the atlas. The width of the ladder is 90cm, and the vertical interval of the ladder is 3m Set up a rest platform for personnel, install handrails on both sides of the ladder, and the installation of the handrails must be firm and convenient. The material of the ladder is constructed of steel plate and angle steel, and the embedded parts of the ladder must be pre-embedded in place when constructing the shaft. The bottom of the well adopts 300 thick C25 concrete spraying + steel grid, 500 thick C40 impermeable concrete cast-in-place reinforced concrete structure, and the bottom of the well is arranged with bottom grid. m sump, the sump adopts reinforced concrete structure to collect the water flow in the working pit. Lay double-layer threaded steel mesh, and pour C40 concrete 500mm thick to ensure that the bottom of the pit is flat and dry. Make the working shaft form a whole. At the same time, safety issues should be paid attention to during the construction of working wells.

工作井施工完成后,在井内布置主顶机构,主要是后背板、导轨、主顶油缸、油泵动力站、钢制扶梯等。顶管基座为钢结构预制构件,顶管基座位置按管道设计轴线准确进行放样,安装时按照测量放样的基线,吊入井下就位安装固定。基座上的导轨按照顶管设计轴线并按实测洞门中心居中放置,并设置支撑加固,保证基座稳定不变形。竖井开挖至结构外缘基底后,应及时进行封底。竖井井底采用“封底格栅+横纵连接筋+浇筑混凝土”的结构,工作竖井封底钢筋网采用双层φ22@150mm十字布置,浇筑C30混凝土。浇筑混凝土和安装竖井底板钢格栅前一定要复核高程,准确无误后才能进行钢格栅的焊接、浇筑混凝土,竖井底部施作土坑和集水坑,待顶进完成后将临时封底破除。为确保出、入洞口位置支撑结构的稳定性,在出、入洞口两侧步设加强钢筋3Ф22@100mm,上下伸出洞口长度不小于1m。竖井洞口上下各增加一道HW300×300×10×145mm盘撑,连接上下盘撑形成门型框架,以保证竖井开洞处稳定,且保证盘撑与初衬格栅可靠焊接。在槽底用C20混凝土铺一层20cm基础,宽度较枕木长50cm,在混凝土内部埋设20cm×20cm枕木,埋深13cm。枕木长度应比导轨外缘两边各长出30cm,间距40cm。枕木埋入混凝土的面需包油毡。导轨选用24号钢轨,两导轨平行、等高,坡度及中心线符合要求。高程与设计管道坡度一致,焊接固定在钢板上。(这部分结构是现有的吧)After the construction of the working well is completed, the main roof mechanism is arranged in the well, mainly including the back plate, guide rail, main roof cylinder, oil pump power station, steel escalator, etc. The pipe jacking base is a prefabricated steel structure. The position of the pipe jacking base is accurately set out according to the design axis of the pipeline. The guide rail on the base is placed in the center according to the design axis of the pipe jacking and the center of the measured hole, and support reinforcement is provided to ensure the stability of the base without deformation. After the shaft is excavated to the base of the outer edge of the structure, it shall be sealed in time. The bottom of the shaft shaft adopts the structure of "bottom sealing grid + horizontal and vertical connecting bars + pouring concrete". The bottom sealing reinforcement mesh of the working shaft adopts double-layer φ22@150mm cross arrangement and pours C30 concrete. Before pouring concrete and installing the steel grid on the bottom plate of the shaft, the elevation must be checked. Only after the steel grid is correct can the steel grid be welded and concrete poured. The bottom of the shaft is constructed with an earth pit and a sump. After the jacking is completed, the temporary bottom cover will be removed. In order to ensure the stability of the supporting structure at the exit and entrance positions, reinforcing steel bars 3Ф22@100mm are installed on both sides of the exit and entrance openings, and the length of the upper and lower extensions of the openings is not less than 1m. A HW300×300×10×145mm disc support is added at the top and bottom of the shaft opening, and the upper and lower disc supports are connected to form a door frame to ensure the stability of the shaft opening and the reliable welding of the disc support and the primary lining grid. Lay a layer of 20cm foundation with C20 concrete at the bottom of the tank, the width is 50cm longer than the sleepers, and 20cm×20cm sleepers are buried inside the concrete with a depth of 13cm. The length of the sleeper should be 30cm longer than both sides of the outer edge of the guide rail, and the distance between them should be 40cm. The surface of sleepers embedded in concrete needs to be covered with linoleum. The guide rail is made of No. 24 steel rail. The two guide rails are parallel and equal in height, and the slope and center line meet the requirements. The elevation is consistent with the slope of the designed pipeline, and it is welded and fixed on the steel plate. (This part of the structure is existing)

步骤二,在设计管道6的设计位置沿着设计路径向前开挖:工作井完成后在设计管道的设计位置采用人工沿管道方向开挖,每向前开挖50cm确定一次管底高程及中心线位置,开口大小根据拼接管道外径确定。Step 2: Excavate forward along the design path at the design position of the design pipeline 6: after the completion of the working well, manually excavate along the direction of the pipeline at the design position of the design pipeline, and determine the elevation and center of the pipe bottom every 50cm forward excavation The position of the line and the size of the opening are determined according to the outer diameter of the spliced pipe.

步骤三,随着开挖施工拼装拼接管道:拼接管道内径稍大于设计管道外径,拼接管件采用玻璃钢材质或其它刚性材料,拼接管件块数可根据现场情况确定,本例以三块为例,相邻拼接管件之前通过螺栓连接固定。Step 3: Assembling and splicing pipelines along with the excavation construction: the inner diameter of the splicing pipeline is slightly larger than the outer diameter of the designed pipeline, and the splicing pipe fittings are made of glass fiber reinforced plastic or other rigid materials. The number of splicing pipe fittings can be determined according to the site conditions. Adjacent spliced pipes are previously secured by bolted connections.

步骤四,重复步骤二和步骤三至拼接管道沿设计路径拼装至接收井:拼装完成一节拼接管道后继续开挖,然后继续向前拼装拼接管道,相邻两节拼接管道之前同样采用螺栓连接固定,直至管道设计终点。Step 4, repeat step 2 and step 3 until the spliced pipeline is assembled to the receiving well along the design path: after assembling a section of spliced pipeline, continue to excavate, and then continue to assemble the spliced pipeline forward, and the adjacent two sections of spliced pipeline are also connected by bolts Fixed until the end of the piping design.

步骤五,在工作井1的底部连接安装主顶机构3和顶管机头5。Step five, connect and install the main jacking mechanism 3 and the pipe jacking head 5 at the bottom of the working well 1 .

拼接管件完成后在工作井内安装管道顶进设备,首先安装后背,后背的尺寸通过计算设置,方木前设置立铁,立铁前码放横铁,横铁要求码放平整,顶镐后座与横铁结合严密,可均匀地将顶力传到后背;顶进坑后背要有足够的强度及牢固度,在顶进过程中能承受千斤顶的最大作用力;后背墙表面要平顺,并且垂直于顶进管道的轴线,避免产生偏心受压。后背平面要垂直于管道中心线,装完后再安装主顶设备,将主顶千斤顶对称布置为2只,固定在组合千斤顶架上作整体吊装。每台千斤顶规格一致,行程同步,油路并联,共同作用,均备有独立的控制阀,伸出的最大行程小于油缸行程10cm左右。油泵设备设在距离主顶千斤顶的近处,并设置防雨棚,油路安装顺直,减小转角,接头不漏油,油泵的最大工作压力不大于32kpa,装有限压阀、溢流阀和压力表等指标保护装置,安装完毕后必须进行试车,在顶进中定时检修维护,及时排除故障。顶管机头的尺寸和结构要符合要求,在吊入顶进坑前要作详细检查。起重机卸机头时,要平稳、缓慢、避免冲击、碰撞,并由专人指挥,确保安全可靠。机头安放在导轨上后,测定前后端的中心的方向偏差和相对高差,并做好记录,机头与导轨的接触面必须平稳、吻合。工具管和掘进机要按设计要求,准确定位,两边对称。机头必须对电路、油路、水路、泥浆管路和操纵系统等设备进行逐一连接,各部件连接牢固,不得渗漏,安装正确,并对各分系统进行认真检查和试运行。在安置土方运输设备时,采用泥水平衡顶管机,以水力机械方式将泥浆通过与管路连接的吸泥泵输出并与排泥旁通装置直接输送到地面泥浆沉淀池。顶管过程中,无论是管从工作坑进洞,还是出洞,管子与洞口之间都必须留有间隙,但间隙必须做好封闭,如封闭不严,地下水、触变泥浆和泥砂就会从该间隙中流到坑中,影响坑内作业,严重时会造成洞口的坍落,造成事故,故洞口必须做止水,止水方法为,在入洞口位置浇筑300mm厚混凝土止水墙,墙外侧安装止水橡胶圈。橡胶圈中间用δ=10mm钢板作为隔挡和固定橡胶圈用。为了防止顶管机头进出工作坑洞口流入泥水,并确保在顶进过程中压注的触变泥浆不致流失,必须事先安装好前墙止水圈,其组成部分为预埋法兰底盘、橡胶板、钢压板、垫圈与螺栓。法兰底盘予先埋设在砼竖井内,中心正确,端面平整,安装牢固,螺栓的丝口妥善保护,水泥浆予先清除。安装时先装橡胶板,后装钢压板,再上垫圈并用螺帽紧固,使其阻止水流。步骤六,调整好主顶机构3的顶进高度和顶进方向后开始顶进:顶进时要控制顶力大小,顶力过大会破坏管道。After splicing the pipe fittings, install the pipe jacking equipment in the working well. First, install the back. The size of the back is set by calculation. The vertical iron is set in front of the square log, and the horizontal iron is placed in front of the vertical iron. It is closely combined with the horizontal iron, and can evenly transmit the jacking force to the back; the back of the jacking pit must have sufficient strength and firmness, and can withstand the maximum force of the jack during the jacking process; the surface of the back wall must be smooth , and perpendicular to the axis of the jacking pipe to avoid eccentric compression. The plane of the back should be perpendicular to the center line of the pipeline. After the installation, install the main jacking equipment, arrange the main jacking jacks symmetrically into 2 pieces, and fix them on the combined jack frame for overall hoisting. The specifications of each jack are the same, the strokes are synchronized, the oil circuits are connected in parallel, and they work together. They are all equipped with independent control valves. The maximum stroke that extends is about 10cm less than the cylinder stroke. The oil pump equipment is located near the main jack, and a rainproof shed is installed. The oil circuit is installed straight, the corner is reduced, the joint does not leak oil, the maximum working pressure of the oil pump is not greater than 32kpa, and a pressure limiting valve and a relief valve are installed. Indicator protection devices such as pressure gauges and pressure gauges must be tested after installation, and regularly inspected and maintained during jacking to eliminate faults in time. The size and structure of the pipe jacking head must meet the requirements, and a detailed inspection must be carried out before hoisting into the pit. When the crane unloads the head, it must be stable and slow, avoid impact and collision, and be directed by a special person to ensure safety and reliability. After the machine head is placed on the guide rail, measure the directional deviation and relative height difference between the front and rear ends, and make a record. The contact surface between the machine head and the guide rail must be stable and consistent. The tool tube and the boring machine should be positioned accurately and symmetrically on both sides according to the design requirements. The machine head must connect the circuit, oil circuit, water circuit, mud pipeline and control system one by one. The components are firmly connected without leakage, installed correctly, and carefully inspected and tested for each subsystem. When installing the earthwork transportation equipment, the mud-water balance pipe jacking machine is used to output the mud through the suction dredge pump connected to the pipeline in a hydraulic mechanical way and directly transport it to the ground mud sedimentation tank with the mud discharge bypass device. During the pipe jacking process, whether the pipe enters the hole from the working pit or exits the hole, there must be a gap between the pipe and the hole, but the gap must be sealed well. If the seal is not tight, groundwater, thixotropic mud and mud sand will It flows from the gap into the pit, affecting the operation in the pit. In severe cases, it will cause the collapse of the hole and cause accidents. Therefore, the hole must be sealed. Install the water-stop rubber ring. A δ=10mm steel plate is used in the middle of the rubber ring as a barrier and to fix the rubber ring. In order to prevent the pipe jacking head from entering and exiting the working pit from flowing into muddy water, and to ensure that the thixotropic mud injected during the jacking process will not be lost, the water stop ring on the front wall must be installed in advance, and its components are embedded flange chassis, rubber plates, steel platens, washers and bolts. The flange chassis is buried in the concrete shaft in advance, the center is correct, the end surface is flat, the installation is firm, the thread opening of the bolt is properly protected, and the cement slurry is removed in advance. When installing, install the rubber plate first, then install the steel pressure plate, and then install the gasket and fasten it with a nut to prevent water flow. Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism 3: When jacking, control the jacking force, if the jacking force is too high, the pipeline will be damaged.

步骤七,设计管道6沿设计路径顶进接收井内,停止顶进。Step seven, the designed pipeline 6 is jacked into the receiving well along the designed path, and the jacking is stopped.

步骤八,分别由工作井和接收井中拆除并取出主顶机构3和顶管机头5。Step eight, remove and take out the main jacking mechanism 3 and the pipe jacking head 5 from the working well and the receiving well respectively.

步骤九,向设计管道6的四周注水泥浆,完成整个施工:拼接管道的管径是根据设计管道的管径选择的,即使不拆除拼装管道也不会对注浆量造成影响。Step 9, pouring grout around the designed pipeline 6 to complete the entire construction: the diameter of the spliced pipeline is selected according to the diameter of the designed pipeline, even if the assembled pipeline is not removed, the amount of grouting will not be affected.

所述步骤二中,由工作井向接收井单向开挖或者由工作井和接收井同时向中间双向开挖;所述步骤七中,随着设计管道顶进,拆除顶管机头前的拼接管道。In the second step, one-way excavation is carried out from the working well to the receiving well, or the two-way excavation is carried out from the working well and the receiving well to the middle at the same time; Splicing pipes.

参见图1所示,一种应用所述的预制拼接管件顶进系统的无接收井施工方法,与上述施工方法不同的是,本例中是针对受场地或其自然条件限制、无法设置接收井的情况,具体步骤如下:As shown in Figure 1, a construction method without a receiving well using the prefabricated splicing pipe fitting jacking system described above is different from the above-mentioned construction method in that, in this example, it is limited by the site or its natural conditions, and it is impossible to set up a receiving well case, the specific steps are as follows:

步骤一,施工工作井1。Step 1, construction work well 1.

步骤二,在设计管道6的设计位置沿着设计路径向前开挖。Step 2: Excavate forward along the design path at the design position of the design pipeline 6 .

步骤三,随着开挖施工拼装拼接管道。Step 3, assembling and splicing pipelines along with the excavation construction.

步骤四,重复步骤二和步骤三至拼接管道至设计路径终点。Step 4, repeat steps 2 and 3 to splice the pipes to the end of the design path.

步骤五,在工作井1的底部连接安装主顶机构3。Step five, connect and install the main top mechanism 3 at the bottom of the working well 1 .

步骤六,调整好主顶机构3的顶进高度和顶进方向后开始顶进。Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism 3 .

步骤七,设计管道6沿设计路径顶进至终点,停止顶进。Step 7, the design pipeline 6 is jacked along the design path to the end point, and the jacking is stopped.

步骤八,拆除并取出主顶机构3。Step 8, dismantle and take out the main top mechanism 3.

步骤九,向设计管道6的四周注水泥浆,完成整个施工。In step nine, grout is poured around the designed pipeline 6 to complete the entire construction.

参见图2所示,一种应用所述的预制拼接管件顶进系统的有障碍物时的施工方法,与实施例一不同的是,本例是在设计管道的设计路径上有障碍物8或者设计路径为曲线时,具体步骤如下:Referring to Fig. 2, a construction method using the prefabricated splicing pipe fitting jacking system when there are obstacles is different from the first embodiment in that there are obstacles 8 or 8 on the design path of the design pipeline in this example When the design path is a curve, the specific steps are as follows:

步骤一,施工工作井1和接收井2。Step 1, construction of working well 1 and receiving well 2.

步骤二,在设计管道6的设计位置沿着设计路径向前开挖。Step 2: Excavate forward along the design path at the design position of the design pipeline 6 .

步骤三,随着开挖施工拼装拼接管道。Step 3, assembling and splicing pipelines along with the excavation construction.

步骤四,重复步骤二和步骤三至拼接管道沿设计路径拼装至接收井。Step 4, repeat steps 2 and 3 until the spliced pipeline is assembled to the receiving well along the design path.

步骤五,在工作井1的底部连接安装主顶机构3和顶管机头5。Step five, connect and install the main jacking mechanism 3 and the pipe jacking head 5 at the bottom of the working well 1 .

步骤六,调整好主顶机构3的顶进高度和顶进方向后开始顶进。Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism 3 .

步骤七,随着设计管道顶进,拆除顶管机头前的拼接管道。Step 7: With the jacking of the designed pipeline, remove the spliced pipeline in front of the pipe jacking head.

步骤八,设计管道6沿设计路径顶进接收井内,停止顶进。Step 8, the designed pipeline 6 is jacked into the receiving well along the designed path, and the jacking is stopped.

步骤九,分别由工作井和接收井中拆除并取出主顶机构3和顶管机头5。Step 9: Remove and take out the main jacking mechanism 3 and the pipe jacking head 5 from the working well and the receiving well respectively.

步骤十,向设计管道6的四周注水泥浆,完成整个施工。In step ten, inject grout around the designed pipeline 6 to complete the entire construction.

参见图3所示,一种应用所述的预制拼接管件顶进系统的顶管机头损坏时的施工方法,与实施例一不同的是,本例中是针对在设计管道顶进过程中、顶管机头损坏的情况,机头在顶进过程中发生机械故障或损坏时,常规施工方法只能在机头位置增加一座竖井,逐层开挖支护到底后取出机头,维修或更换机头后继续顶进,而由于机头在旋进过程中与土体紧密接触,从工作井取出后换机头需要时间,且取出过程中会破坏原有土体结构,具体步骤如下:Referring to Fig. 3, a construction method when the pipe jacking head of the prefabricated splicing pipe fitting jacking system is damaged, the difference from the first embodiment is that in this example, it is aimed at the design of the pipe jacking process, In the case of damage to the pipe jacking head, when the machine head has a mechanical failure or damage during the jacking process, the conventional construction method can only add a shaft at the head position, excavate and support it layer by layer, take out the machine head, repair or replace it Continue jacking after the machine head, and because the machine head is in close contact with the soil during the precession process, it takes time to replace the machine head after it is taken out from the working well, and the original soil structure will be destroyed during the removal process. The specific steps are as follows:

步骤一,由接收井2沿着设计路径向顶管机头方向开挖。Step 1: Excavate from the receiving shaft 2 along the designed path to the direction of the pipe jacking head.

步骤二,随着开挖施工拼装拼接管道。Step 2, assembling and splicing pipelines along with the excavation construction.

步骤三,重复步骤一和步骤二至拼接管道沿设计路径拼装至顶管机头位置。Step 3, repeat step 1 and step 2 until the spliced pipe is assembled to the position of the pipe jacking head along the design path.

步骤四,拆除顶管机头,并通过拼接管道运送至接收井取出。Step 4, dismantle the pipe jacking head, and transport it to the receiving well through the spliced pipeline to take it out.

步骤五,通过拼接管道运送新的顶管机头,更换后开始顶进。Step 5: Transport the new pipe jacking head through spliced pipes, and start jacking after replacement.

步骤六,随着设计管道顶进,拆除顶管机头前的拼接管道。Step 6: With the jacking of the designed pipeline, the spliced pipeline in front of the pipe jacking head is removed.

步骤七,设计管道6沿设计路径顶进接收井内,停止顶进。Step seven, the designed pipeline 6 is jacked into the receiving well along the designed path, and the jacking is stopped.

步骤八,分别由工作井和接收井中拆除并取出主顶机构3和顶管机头5。Step eight, remove and take out the main jacking mechanism 3 and the pipe jacking head 5 from the working well and the receiving well respectively.

步骤九,向设计管道6的四周注水泥浆,完成整个施工。In step nine, grout is poured around the designed pipeline 6 to complete the entire construction.

这样不仅节省了机头从工作井取出换机头的时间,提高了工作效率,而且避免了从工作井取出机头破坏土体的可能性,大大减少了工作量。This not only saves the time for taking out the machine head from the working well to change the machine head, improves the work efficiency, but also avoids the possibility of taking out the machine head from the working well to damage the soil, and greatly reduces the workload.

本发明可以实现无接收井顶进,同时在复杂地质条件及曲线顶进时管道高程及中心线位置精度高,施工速度快,对顶进过程中机头故障时的处理具有明显优势,且拼接管件可重复利用,成本较低。The invention can realize jacking without receiving well, and at the same time, it has high accuracy of pipeline elevation and center line position under complex geological conditions and curved jacking, and fast construction speed. The pipe fittings can be reused and the cost is low.

Claims (10)

1.一种预制拼接管件顶进系统,包括主顶机构(3),其特征在于:还包括沿设计管道(6)的设计路径上设置的拼接管道,所述拼接管道内径大于设计管道(6)的外径,拼接管道是由拼接管件(4)拼接而成的;1. A jacking system for prefabricated spliced pipe fittings, comprising a main jacking mechanism (3), characterized in that it also includes a spliced pipe arranged along the design path of the designed pipe (6), and the inner diameter of the spliced pipe is larger than the designed pipe (6) ), the spliced pipe is spliced by spliced pipe fittings (4); 所述拼接管件(4)为条形板,其前后两个侧边分别对应向外突出形成轴向搭接边、左右两个侧边分别对应向外突出形成周向搭接边;The spliced pipe fitting (4) is a strip plate, the front and rear sides protrude outward respectively to form an axial lap, and the left and right sides respectively protrude outward to form a circumferential lap; 同轴的拼接管件(4)沿着拼接管道的轴向上通过轴向搭接边依次拼接、并通过连接件紧固,同周的拼接管件(4)的沿着拼接管道的环向上通过周向搭接边依次拼接、并通过连接件紧固。The coaxial spliced pipe fittings (4) are sequentially spliced along the axial direction of the spliced pipe through the axial overlapping edges and fastened by the connecting piece, and the spliced pipe fittings (4) of the same circumference pass through the circumferential Splice to the overlapping edge in turn and fasten through the connecting piece. 2.根据权利要求1所述的预制拼接管件顶进系统,其特征在于:所述主顶机构(3)设置在工作井(1)底部,包括连接在工作井侧壁上的后背板和垂直顶接在后背板上的主顶千斤顶;2. The jacking system for prefabricated spliced pipe fittings according to claim 1, characterized in that: the main jacking mechanism (3) is set at the bottom of the working well (1), including a back plate connected to the side wall of the working well and The main jacking jack vertically connected to the back panel; 所述主顶机构(3)的前端还连接有顶管机头(5)。The front end of the main jacking mechanism (3) is also connected with a pipe jacking head (5). 3.根据权利要求1所述的预制拼接管件顶进系统,其特征在于:所述拼接管道的横截面为圆形或者多边形。3. The jacking system for prefabricated spliced pipe fittings according to claim 1, characterized in that: the cross section of the spliced pipe is circular or polygonal. 4.根据权利要求1所述的预制拼接管件顶进系统,其特征在于:所述拼接管件(4)的材料为玻璃钢或者金属合金。4. The jacking system for prefabricated spliced pipe fittings according to claim 1, characterized in that: the material of the spliced pipe fittings (4) is glass fiber reinforced plastic or metal alloy. 5.根据权利要求1所述的预制拼接管件顶进系统,其特征在于:所述拼接管道内径大于设计管道(6)的外径的尺寸为10~20cm。5. The jacking system for prefabricated spliced pipe fittings according to claim 1, characterized in that: the inner diameter of the spliced pipe is 10-20 cm larger than the outer diameter of the designed pipe (6). 6.一种应用权利要求2至5任意一项所述的预制拼接管件顶进系统的施工方法,其特征在于,具体步骤如下:6. A construction method for applying the prefabricated splicing pipe fitting jacking system described in any one of claims 2 to 5, characterized in that, the specific steps are as follows: 步骤一,施工工作井(1)和接收井(2);Step 1, constructing the working well (1) and the receiving well (2); 步骤二,在设计管道(6)的设计位置沿着设计路径向前开挖;Step 2, digging forward along the design path at the design position of the design pipeline (6); 步骤三,随着开挖施工拼装拼接管道;Step 3, assembling and splicing pipelines along with the excavation construction; 步骤四,重复步骤二和步骤三至拼接管道沿设计路径拼装至接收井;Step 4, repeat steps 2 and 3 until the spliced pipeline is assembled to the receiving well along the design path; 步骤五,在工作井(1)的底部连接安装主顶机构(3)和顶管机头(5);Step five, connect and install the main jacking mechanism (3) and the pipe jacking head (5) at the bottom of the working well (1); 步骤六,调整好主顶机构(3)的顶进高度和顶进方向后开始顶进;Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism (3); 步骤七,设计管道(6)沿设计路径顶进接收井内,停止顶进;Step 7, the design pipeline (6) is jacked into the receiving well along the design path, and the jacking is stopped; 步骤八,分别由工作井和接收井中拆除并取出主顶机构(3)和顶管机头(5);Step eight, remove and take out the main jacking mechanism (3) and pipe jacking head (5) from the working well and the receiving well respectively; 步骤九,向设计管道(6)的四周注水泥浆,完成整个施工。In step 9, inject grout around the designed pipeline (6) to complete the whole construction. 7.根据权利要求6所述的施工方法,其特征在于:7. The construction method according to claim 6, characterized in that: 所述步骤二中,由工作井向接收井单向开挖或者由工作井和接收井同时向中间双向开挖;In said step 2, one-way excavation from the working well to the receiving well or two-way excavation from the working well and the receiving well to the middle at the same time; 所述步骤七中,随着设计管道顶进,拆除顶管机头前的拼接管道。In the seventh step, along with the jacking of the designed pipeline, the spliced pipeline in front of the pipe jacking head is removed. 8.一种应用权利要求1至5任意一项所述的预制拼接管件顶进系统的无接收井施工方法,针对受场地或其自然条件限制、无法设置接收井的情况,其特征在于,具体步骤如下:8. A construction method without a receiving well applying the jacking system of prefabricated splicing pipe fittings according to any one of claims 1 to 5, aimed at the situation where the receiving well cannot be set due to the limitation of the site or its natural conditions, it is characterized in that, Proceed as follows: 步骤一,施工工作井(1);Step one, construction work well (1); 步骤二,在设计管道(6)的设计位置沿着设计路径向前开挖;Step 2, digging forward along the design path at the design position of the design pipeline (6); 步骤三,随着开挖施工拼装拼接管道;Step 3, assembling and splicing pipelines along with the excavation construction; 步骤四,重复步骤二和步骤三至拼接管道至设计路径终点;Step 4, repeat steps 2 and 3 to splice the pipeline to the end of the design path; 步骤五,在工作井(1)的底部连接安装主顶机构(3);Step five, connect and install the main top mechanism (3) at the bottom of the working well (1); 步骤六,调整好主顶机构(3)的顶进高度和顶进方向后开始顶进;Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism (3); 步骤七,设计管道(6)沿设计路径顶进至终点,停止顶进;Step 7, the design pipeline (6) is jacked along the design path to the end point, and the jacking is stopped; 步骤八,拆除并取出主顶机构(3);Step eight, remove and take out the main top mechanism (3); 步骤九,向设计管道(6)的四周注水泥浆,完成整个施工。In step 9, inject grout around the designed pipeline (6) to complete the whole construction. 9.一种应用权利要求2至5任意一项所述的预制拼接管件顶进系统的有障碍物时的施工方法,在设计管道的设计路径上有障碍物(8)或者设计路径为曲线时,其特征在于,具体步骤如下:9. A construction method when there are obstacles applying the prefabricated splicing pipe fitting jacking system described in any one of claims 2 to 5, when there are obstacles (8) on the design path of the design pipeline or the design path is a curve , characterized in that the specific steps are as follows: 步骤一,施工工作井(1)和接收井(2);Step 1, constructing the working well (1) and the receiving well (2); 步骤二,在设计管道(6)的设计位置沿着设计路径向前开挖;Step 2, digging forward along the design path at the design position of the design pipeline (6); 步骤三,随着开挖施工拼装拼接管道;Step 3, assembling and splicing pipelines along with the excavation construction; 步骤四,重复步骤二和步骤三至拼接管道沿设计路径拼装至接收井;Step 4, repeat steps 2 and 3 until the spliced pipeline is assembled to the receiving well along the design path; 步骤五,在工作井(1)的底部连接安装主顶机构(3)和顶管机头(5);Step five, connect and install the main jacking mechanism (3) and the pipe jacking head (5) at the bottom of the working well (1); 步骤六,调整好主顶机构(3)的顶进高度和顶进方向后开始顶进;Step 6, start jacking after adjusting the jacking height and jacking direction of the main jacking mechanism (3); 步骤七,随着设计管道顶进,拆除顶管机头前的拼接管道;Step 7, along with the jacking of the designed pipeline, remove the spliced pipeline in front of the pipe jacking head; 步骤八,设计管道(6)沿设计路径顶进接收井内,停止顶进;Step 8, the design pipeline (6) is jacked into the receiving well along the design path, and the jacking is stopped; 步骤九,分别由工作井和接收井中拆除并取出主顶机构(3)和顶管机头(5);Step 9, remove and take out the main jacking mechanism (3) and the pipe jacking head (5) from the working well and the receiving well respectively; 步骤十,向设计管道(6)的四周注水泥浆,完成整个施工。In step ten, inject grout around the designed pipeline (6) to complete the whole construction. 10.一种应用权利要求2至5任意一项所述的预制拼接管件顶进系统的顶管机头损坏时的施工方法,针对在设计管道顶进过程中、顶管机头损坏的情况,其特征在于,具体步骤如下:10. A construction method when the pipe jacking head of the prefabricated splicing pipe fitting jacking system described in any one of claims 2 to 5 is damaged, for the situation that the pipe jacking head is damaged during the design pipeline jacking process, It is characterized in that the specific steps are as follows: 步骤一,由接收井(2)沿着设计路径向顶管机头方向开挖;Step 1: Excavate from the receiving well (2) along the design path to the direction of the pipe jacking head; 步骤二,随着开挖施工拼装拼接管道;Step 2, assembling and splicing pipelines along with the excavation construction; 步骤三,重复步骤一和步骤二至拼接管道沿设计路径拼装至顶管机头位置;Step 3, repeat step 1 and step 2 until the spliced pipe is assembled to the position of the pipe jacking head along the design path; 步骤四,拆除顶管机头,并通过拼接管道运送至接收井取出;Step 4, remove the pipe jacking head, and transport it to the receiving well through spliced pipes; 步骤五,通过拼接管道运送新的顶管机头,更换后开始顶进;Step 5, transport the new pipe jacking head through the spliced pipeline, and start jacking after replacement; 步骤六,随着设计管道顶进,拆除顶管机头前的拼接管道;Step 6, along with the jacking of the designed pipeline, remove the spliced pipeline in front of the pipe jacking head; 步骤七,设计管道(6)沿设计路径顶进接收井内,停止顶进;Step 7, the design pipeline (6) is jacked into the receiving well along the design path, and the jacking is stopped; 步骤八,分别由工作井和接收井中拆除并取出主顶机构(3)和顶管机头(5);Step eight, remove and take out the main jacking mechanism (3) and pipe jacking head (5) from the working well and the receiving well respectively; 步骤九,向设计管道(6)的四周注水泥浆,完成整个施工。In step 9, inject grout around the designed pipeline (6) to complete the whole construction.
CN201711330797.1A 2017-12-13 2017-12-13 A prefabricated splicing pipe fitting jacking system and its construction method Pending CN107795749A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711330797.1A CN107795749A (en) 2017-12-13 2017-12-13 A prefabricated splicing pipe fitting jacking system and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711330797.1A CN107795749A (en) 2017-12-13 2017-12-13 A prefabricated splicing pipe fitting jacking system and its construction method

Publications (1)

Publication Number Publication Date
CN107795749A true CN107795749A (en) 2018-03-13

Family

ID=61536755

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711330797.1A Pending CN107795749A (en) 2017-12-13 2017-12-13 A prefabricated splicing pipe fitting jacking system and its construction method

Country Status (1)

Country Link
CN (1) CN107795749A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108386608A (en) * 2018-05-02 2018-08-10 广东中科华冉智网科技有限公司 Pipe with small pipe diameter plastic drain-pipe push pipe equipment and plastic drain-pipe pipe jacking construction method
CN108547619A (en) * 2018-05-16 2018-09-18 北京中地盾构工程技术研究院有限公司 Underground shaft assembles recovery type prestressing force support equipment
CN108824449A (en) * 2018-07-26 2018-11-16 中国建筑第八工程局有限公司 Support system and its construction method with underground horizontal support
CN110541966A (en) * 2019-08-27 2019-12-06 北京住总集团有限责任公司 pipe joint jacking auxiliary equipment in narrow space and using method thereof
CN110565779A (en) * 2019-09-03 2019-12-13 苏州市平海排水服务有限公司 method for trenchless replacement and repair of sewage pipeline
CN111810715A (en) * 2020-06-18 2020-10-23 中铁工程装备集团有限公司 Trenchless pipeline renewal method and construction system
CN114319433A (en) * 2021-12-22 2022-04-12 深圳市市政工程总公司 Assembly type construction method for working well reverse construction method
CN114321495A (en) * 2021-12-31 2022-04-12 北京易成市政工程有限责任公司 Natural gas pipeline jacking pipe construction method
CN114319443A (en) * 2021-12-22 2022-04-12 深圳市市政工程总公司 Assembled working well
CN114542087A (en) * 2022-02-15 2022-05-27 北京绿佳杰园林工程有限公司 Garden tunnel construction structure and tunnel construction method
CN114857353A (en) * 2022-04-21 2022-08-05 中铁一局集团有限公司 Construction method of jacking pipe internally-penetrated steel sleeve steel steam pipeline
CN115614544A (en) * 2022-09-19 2023-01-17 北京金河水务建设集团有限公司 A pipe jacking shaft construction method and auxiliary device for pipeline laying

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2344630Y (en) * 1997-12-12 1999-10-20 马寿 Wide-bore pipe and elbow pipe internal die support device
JP2001323779A (en) * 2000-05-17 2001-11-22 Kajima Corp Pipe burial method
JP2005155147A (en) * 2003-11-25 2005-06-16 Kidoh Construction Co Ltd Insertion-type propulsion method
JP2007139156A (en) * 2005-11-22 2007-06-07 Kurimoto Ltd Pipe travel guide tool for sleeve jacking method
CN101457648A (en) * 2008-12-30 2009-06-17 中铁隧道勘测设计院有限公司 Full-ring steel tunnel segment structure with seal protection door
CN105201517A (en) * 2015-11-11 2015-12-30 中铁二十局集团有限公司 Advance support construction method for high-strength pipe shed of tunnel
CN105863646A (en) * 2016-03-30 2016-08-17 中煤特殊凿井有限责任公司 Freezing construction method in steel pipe curtain of large-section subsurface tunnel
CN106451271A (en) * 2016-12-28 2017-02-22 国网冀北电力有限公司迁西县供电分公司 Cable aisle bridge structure and installment method thereof
CN106437738A (en) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 Pipe roof construction thruster and using method thereof
CN207777770U (en) * 2017-12-13 2018-08-28 北京住总集团有限责任公司 A kind of precast spliced pipe fitting jacking system

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2344630Y (en) * 1997-12-12 1999-10-20 马寿 Wide-bore pipe and elbow pipe internal die support device
JP2001323779A (en) * 2000-05-17 2001-11-22 Kajima Corp Pipe burial method
JP2005155147A (en) * 2003-11-25 2005-06-16 Kidoh Construction Co Ltd Insertion-type propulsion method
JP2007139156A (en) * 2005-11-22 2007-06-07 Kurimoto Ltd Pipe travel guide tool for sleeve jacking method
CN101457648A (en) * 2008-12-30 2009-06-17 中铁隧道勘测设计院有限公司 Full-ring steel tunnel segment structure with seal protection door
CN105201517A (en) * 2015-11-11 2015-12-30 中铁二十局集团有限公司 Advance support construction method for high-strength pipe shed of tunnel
CN105863646A (en) * 2016-03-30 2016-08-17 中煤特殊凿井有限责任公司 Freezing construction method in steel pipe curtain of large-section subsurface tunnel
CN106437738A (en) * 2016-08-26 2017-02-22 中铁十局集团第四工程有限公司 Pipe roof construction thruster and using method thereof
CN106451271A (en) * 2016-12-28 2017-02-22 国网冀北电力有限公司迁西县供电分公司 Cable aisle bridge structure and installment method thereof
CN207777770U (en) * 2017-12-13 2018-08-28 北京住总集团有限责任公司 A kind of precast spliced pipe fitting jacking system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
上海市城乡建设和交通委员会科学技术委员会 上海市苏州河环境综合整治领导小组办公室编: "《苏州河环境综合整治二期、三期工程》", vol. 1, 31 May 2012, 上海:上海科学技术出版社, pages: 92 *

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108386608B (en) * 2018-05-02 2023-06-16 中国瑞林工程技术股份有限公司东莞分公司 Small-pipe-diameter plastic drain pipe jacking machine tool and plastic drain pipe jacking construction method
CN108386608A (en) * 2018-05-02 2018-08-10 广东中科华冉智网科技有限公司 Pipe with small pipe diameter plastic drain-pipe push pipe equipment and plastic drain-pipe pipe jacking construction method
CN108547619A (en) * 2018-05-16 2018-09-18 北京中地盾构工程技术研究院有限公司 Underground shaft assembles recovery type prestressing force support equipment
CN108547619B (en) * 2018-05-16 2024-04-19 北京中地盾构工程技术研究院有限公司 Underground shaft assembly recovery type prestress supporting equipment
CN108824449A (en) * 2018-07-26 2018-11-16 中国建筑第八工程局有限公司 Support system and its construction method with underground horizontal support
CN110541966A (en) * 2019-08-27 2019-12-06 北京住总集团有限责任公司 pipe joint jacking auxiliary equipment in narrow space and using method thereof
CN110541966B (en) * 2019-08-27 2024-03-26 北京住总集团有限责任公司 Auxiliary equipment for jacking pipe joint in narrow space and application method thereof
CN110565779A (en) * 2019-09-03 2019-12-13 苏州市平海排水服务有限公司 method for trenchless replacement and repair of sewage pipeline
CN110565779B (en) * 2019-09-03 2021-07-30 苏州市平海排水服务有限公司 Method for trenchless replacement and repair of sewage pipeline
CN111810715A (en) * 2020-06-18 2020-10-23 中铁工程装备集团有限公司 Trenchless pipeline renewal method and construction system
CN111810715B (en) * 2020-06-18 2021-09-24 中铁工程装备集团有限公司 Trenchless pipeline renewal method and construction system
CN114319443A (en) * 2021-12-22 2022-04-12 深圳市市政工程总公司 Assembled working well
CN114319443B (en) * 2021-12-22 2023-09-26 深圳市市政工程总公司 Assembled working well
CN114319433A (en) * 2021-12-22 2022-04-12 深圳市市政工程总公司 Assembly type construction method for working well reverse construction method
CN114321495A (en) * 2021-12-31 2022-04-12 北京易成市政工程有限责任公司 Natural gas pipeline jacking pipe construction method
CN114542087A (en) * 2022-02-15 2022-05-27 北京绿佳杰园林工程有限公司 Garden tunnel construction structure and tunnel construction method
CN114542087B (en) * 2022-02-15 2025-08-01 北京绿佳杰园林工程有限公司 Garden tunnel construction structure and tunnel construction method
CN114857353A (en) * 2022-04-21 2022-08-05 中铁一局集团有限公司 Construction method of jacking pipe internally-penetrated steel sleeve steel steam pipeline
CN114857353B (en) * 2022-04-21 2024-04-05 中铁一局集团有限公司 Construction method for penetrating steel sleeve steel steam pipeline in jacking pipe
CN115614544A (en) * 2022-09-19 2023-01-17 北京金河水务建设集团有限公司 A pipe jacking shaft construction method and auxiliary device for pipeline laying

Similar Documents

Publication Publication Date Title
CN107795749A (en) A prefabricated splicing pipe fitting jacking system and its construction method
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN103343544B (en) Construction method for large-scale open caisson
CN113833480A (en) Shield initial tunneling and arrival construction method
CN207777770U (en) A kind of precast spliced pipe fitting jacking system
CN107542108B (en) A reverse construction method of a building basement structure
CN111810180B (en) A construction method for super-large diameter earth pressure balance pipe jacking across expressway
CN104631470A (en) Deep foundation pit combination retaining and protecting construction method for geology with high water level and large particle size sand gravel
CN113338983B (en) Large-pipe-diameter mud-water balance jacking pipe construction method suitable for high-water-level rock geology
CN112576812A (en) Large-diameter long-distance linear jacking pipe jacking method
CN111503368B (en) Pipe jacking construction method under sandy gravel geological condition
CN112727466A (en) Construction method for support-free prefabricated assembled type shield tunnel air shaft structure
CN110439590A (en) tunnel construction method
CN115539056A (en) Methods including shield construction, waterproofing and monitoring methods for shield construction
CN115897600A (en) A construction method for a new foundation pit adjacent to the deep foundation pit adjacent area of an existing subway station
CN114622572A (en) Large-scale round foundation pit triaxial mixing pile supporting structure and construction method thereof
CN104762982A (en) Construction method of watery red sandstone geological underground water level control
CN113756314B (en) Construction method suitable for excavation of deep large subway foundation pit of soft soil foundation in long triangular area
CN113266392B (en) A construction method of pipe jacking through existing anchor cable groups
CN113338950A (en) Shield closed arrival construction method of freezing method and cement system combined steel sleeve
CN113846695B (en) Reverse construction method basement construction method
CN111379273A (en) Construction method of corrugated steel comprehensive pipe gallery
CN110552702B (en) Underground excavation construction method for assembled corrugated steel plate underground comprehensive pipe gallery
CN209586373U (en) The support system of the lower rock compound cross-section stratum jacking construction inlet and outlet cave of upper soil
CN113266019B (en) A construction method of steel pipe support system for foundation pit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20180313

RJ01 Rejection of invention patent application after publication