CN107386274A - Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side - Google Patents

Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side Download PDF

Info

Publication number
CN107386274A
CN107386274A CN201710691818.6A CN201710691818A CN107386274A CN 107386274 A CN107386274 A CN 107386274A CN 201710691818 A CN201710691818 A CN 201710691818A CN 107386274 A CN107386274 A CN 107386274A
Authority
CN
China
Prior art keywords
isolation pile
pile
slip casting
reinforcing bar
isolation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710691818.6A
Other languages
Chinese (zh)
Inventor
贾少春
王立新
王天明
王俊
戴志仁
段亚刚
王海祥
翁木生
王博
倪飞
王春希
高志宏
张海
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Survey and Design Institute Group Ltd
Original Assignee
China Railway First Survey and Design Institute Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Survey and Design Institute Group Ltd filed Critical China Railway First Survey and Design Institute Group Ltd
Priority to CN201710691818.6A priority Critical patent/CN107386274A/en
Publication of CN107386274A publication Critical patent/CN107386274A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material

Abstract

The present invention relates to the compound isolation pile and its reinforced construction method that bridge pier is worn in tunnel side.Traditional isolation pile typically uses cast-in-situ bored pile, and it is difficult to be applicable that the placement of its construction machinery and steel reinforcement cage splicing are limited by under-clearance.Compound isolation pile of the present invention is set in a row between existing bridge pile foundation and bridge bearing platform and newly built tunnels, is stretched into below newly built tunnels bottom, forms isolation wall construction;The steel reinforcement cage and injecting cement paste that compound isolation pile is made up of isolation pile longitudinal reinforcement, shading ring reinforcing bar, positioning spacer bar form;Shading ring reinforcing bar is located at axis, and isolation pile longitudinal reinforcement is arranged in shading ring reinforcing bar periphery, positioning spacer bar is disposed between the interval of isolation pile longitudinal reinforcement.The present invention reduces the laxity of stake surrounding soil, the frictional resistance loss of bridge pier is controlled, has the characteristics that easy for construction, short construction period, noise be small, environment keeps good, is adapted to pass through various build in the boring construction of city(Structure)Build and popularization and application are carried out in thing reinforcing engineering.

Description

Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side
Technical field
The present invention relates to Tunnel Engineering technical field, and in particular to wears the compound isolation pile of bridge pier and its adds in a kind of tunnel side Gu construction method.
Background technology
With the Large scale construction of urban rail transit in China, urban underground space utilization rate is being stepped up, city Iron is inevitably under existing building or municipal bridge foundation or nearby by that will bring these existing basic protections With reinforcing problem.When subway work is built apart from ground(Structure)When building that thing is very near or the stratum passed through is poor, to ensure that engineering is applied Work safety, it is necessary to building(Structure)Build thing and treatment measures are taken on stratum.Compared with safeguard measure being taken during with from underground construction, from Ground is in face of building(Structure)It is more advantageous but traditional to build operability, controllability and economy that thing takes measures etc. The problems such as there is working space and be limited in ground reinforcement measure, environmental pollution and construction disturb residents.
The content of the invention
It is an object of the invention to provide the compound isolation pile and its reinforced construction method that bridge pier is worn in a kind of tunnel side, by Isolation pile is set around bridge foundation, the stratum under the bridge foundation that isolation pile is enclosed and the stratum beyond enclosing(Newly-built tunnel Road structure)Isolated, cutting off the soil body plane of fracture caused by excavation will not invade below bridge foundation.
The technical solution adopted in the present invention is:
Wear the compound isolation pile of bridge pier in tunnel side, it is characterised in that:
The compound isolation pile is set in a row between existing bridge pile foundation and bridge bearing platform and newly built tunnels, stretches into newly-built tunnel Below road bottom, isolation wall construction is formed;
The steel reinforcement cage and injecting cement paste group that compound isolation pile is made up of isolation pile longitudinal reinforcement, shading ring reinforcing bar, positioning spacer bar Into;Shading ring reinforcing bar is located at axis, and isolation pile longitudinal reinforcement is arranged in shading ring reinforcing bar periphery, the interval of isolation pile longitudinal reinforcement Between be disposed with positioning spacer bar.
The compound isolation pile is arranged in double blossom type, and 0.6m is spaced between adjacent compound isolation pile, isolates wall thickness Not less than 1.6m.
The compound isolation pile is in the linear type of existing bridge pile foundation and bridge bearing platform side, L-type, U-shaped or square Arrangement.
Shading ring reinforcing bar longitudinally arranges a ring for every meter, is welded to connect with isolation pile longitudinal reinforcement and positioning spacer bar.
It is in long annular to position spacer bar, and the straightway of side is connected with shading ring reinforcement welding.
Include more piece in compound isolation pile from top to bottom by isolation pile longitudinal reinforcement, shading ring reinforcing bar, positioning spacer bar The steel reinforcement cage of composition, respectively connected between section steel reinforcement cage with reinforcing bar connector.
Wear the reinforced construction method of the compound isolation pile of bridge pier in tunnel side, it is characterised in that:
Comprise the following steps:
Step 1:Surveying and locating:
Setting-out is measured between existing bridge pile foundation and bridge bearing platform and newly built tunnels, is sat according to design isolation pile parameter Mark, mark the earth's surface correspondence position of isolation pile;
Isolation pile is arranged using double quincunx mode, adjacent isolation pile interval 0.6m, is formed isolation wall thickness and is not less than 1.6m;
Step 2:Drilling:
Mounting and positioning device, isolation pile pore-forming equipment use small-sized geological drilling rig, and drilling diameter is slightly larger than isolation pile diameter, use Pipe-following drilling technique;
Step 3:Isolation pile makes, connects and installed:
The steel reinforcement cage of isolation pile is made up of isolation pile longitudinal reinforcement, shading ring reinforcing bar, positioning spacer bar, and shading ring reinforcing bar is located at Axis, isolation pile longitudinal reinforcement are arranged in shading ring reinforcing bar periphery, and positioning branch is disposed between the interval of isolation pile longitudinal reinforcement Support reinforcing bar;Longitudinally every meter of ring and isolation pile longitudinal reinforcement and the positioning spacer bar welding of shading ring reinforcing bar, positions spacer bar Curve wide 40mm, high 200mm annular;
The steel reinforcement cage of isolation pile often saves long 2m, is connected with reinforcing bar connector, and scene is hung using Simple support frame, and hand fit is just Position;Often section is slowly fallen into stake holes after slinging, and is ensured that the elevation of support system and perpendicularity are correct by deadweight, is plugged into reinforcing bar Device is connected firmly;Prevent from reversing during handling, bend, be directed at hole position during installation, hang it is straight help steady, slowly decentralization, collision free hole wall, Fixed immediately after in place;
Step 4:Slip casting:
After the steel reinforcement cage of isolation pile is in place, prepare slip casting;Slip casting is made up of 3 Grouting Pipes and 1 escape pipe, and every Grouting Pipe goes out Mouth scope is away from bottom 4m;When Grouting Pipe is vertically installed, the 1st, 3 Grouting Pipe stretches into a bottom, and the 2nd Grouting Pipe is than the 1st, the 3rd Short 4m;1st Grouting Pipe does not close pipe end, no slurry outlet, other 2 tube ends closings, and when giving the 1st pipe slip casting, the 2nd, the slurry outlet plastic adhesive tape of the 3rd pipe is pasted to isolate slurries, prevents that envelope gambles slurry outlet during slip casting;
Step 5:After slip casting terminates, cut isolation pile and go out above ground portion, construction is completed.
In step 4, slip casting uses compaction grouting, slip casting point 3 times:1st slip casting uses common pressure grouting, grouting pressure 0.4-0.6 MPa, terminate this slip casting, the cement mortar ratio of mud 0.5 when overflowing slurry to aperture:1;2nd slip casting is noted using mesohigh Slurry, grouting pressure 1.0-1.5MPa, 10-15h is carried out after the completion of the 1st slip casting, the cement mortar ratio of mud 0.75:1;3rd note Pressure 1.5-2.0 MPa are starched, 5-10h is carried out after the completion of the 2nd slip casting, the cement mortar ratio of mud 0.75:1;All injecting paste materials Use the general class g cement of silicon 42.5.
The present invention has advantages below:
1st, by setting multiple rows of compound isolation pile around bridge foundation, certain thickness isolation wall construction is formed, is not only reduced The laxity of pile peripheral earth, controls the frictional resistance of bridge pier to lose, also enters the stratum under bridge foundation and newly built tunnels structure Row isolation, the soil body plane of fracture is excavated so as to separate.Compound isolation pile rigidity can be according to internal tendon rigidity and injecting paste material etc. Information summary determines.
2nd, compound isolation pile can also serve as deep hole grouting, by the multiple slip casting in formation of pile, not only form more original The big many minor diameter pile bodies of ground stiffness layer, while slip casting liquid penetrates into stratum, significantly improves ground after being combined with former foundation soil The geotechnological index of layer, particularly with the strong stratum of the property noted, after slip casting liquid penetrates into solidification, stratum has the change of matter.When When slip casting formation at target locations is located at Bridge Pile bottom, stake bottom bearing capacity can be greatly improved.
3rd, the deformation of the minor diameter pile body that compound isolation pile is formed layer over the ground is more sensitive, when stratum produces less change After shape, you can with stratum cooperation, can tension, resistance to compression, shearing resistance, antitorque, bending resistance simultaneously, the material property of pile body is more easy to send out Wave.
4th, the spacing of compound isolation pile, quantity and arrangement form can be according to tunnels with building(Structure)Build the relative pass between thing System, underground utilities situation and ground surrounding enviroment situation are adjusted, while have isolation pile and sleeve valve barrel grouting double action concurrently, Slip casting tube opening depth in compound isolation pile is controllable, slip casting can be oriented to the soil layer of certain depth scope, after slip casting Stratum improves clearly, reliably, it can be ensured that tunnel safety, which passes through, to be built(Structure)Build thing.
Brief description of the drawings
Fig. 1 is that isolation pile reinforces schematic diagram.
Fig. 2 is isolation pile drawing.
Fig. 3 is positioning spacer bar drawing.
In figure, 1- bridge bearing platforms, 2- bridge pile foundations, 3- newly built tunnels, 4- isolation piles, 5- isolation pile longitudinal reinforcements, 6- every From ring reinforcing bar, 7- positioning spacer bars, 8- Grouting Pipes, 9- escape pipes.
Embodiment
With reference to embodiment, the present invention will be described in detail.
It is that double isolation is set between existing bridge pier and tunnel the present invention relates to the compound isolation pile that bridge pier is worn in tunnel side The technical scheme of stake, stake bottom gos deep into tunnel bottom certain distance, by the Grouting Pipe that is set in isolation pile to soil body certain depth Scope interior orientation slip casting, thicker divider wall building enclosure is formed, so as to reduce the laxity of a surrounding soil, controls bridge The frictional resistance loss of stake.
The compound isolation pile is set in a row between existing bridge pile foundation 2 and bridge bearing platform 1 and newly built tunnels 3, is stretched Enter below the bottom of newly built tunnels 3, form isolation wall construction.Bridge pile foundation 2 and bridge bearing platform 1 can represent other various foundation class Type, structural shape.Newly built tunnels 3 can be shape of a hoof Tunneling by mining method, circular shield tunnel or rectangle open trench tunnel.
The steel reinforcement cage and note that compound isolation pile is made up of isolation pile longitudinal reinforcement 5, shading ring reinforcing bar 6, positioning spacer bar 7 Slurry forms;Shading ring reinforcing bar 6 is located at axis, and isolation pile longitudinal reinforcement 5 is arranged in the periphery of shading ring reinforcing bar 6, isolation pile longitudinal direction Positioning spacer bar 7 is disposed between the interval of reinforcing bar 5.
The compound isolation pile is arranged in double blossom type, and 0.6m is spaced between adjacent compound isolation pile, isolates wall thickness Not less than 1.6m.The compound isolation pile is in the linear type of existing bridge pile foundation 2 and the side of bridge bearing platform 1, L-type, U-shaped or four Square is arranged.Compound isolation pile bottom gos deep into the bottom of newly built tunnels 3 and is generally higher than 2m to ensure isolation effect.
Every meter of the longitudinal direction of shading ring reinforcing bar 6 one ring of arrangement, is welded to connect with isolation pile longitudinal reinforcement 5 and positioning spacer bar 7. It is in long annular to position spacer bar 7, and straightway and the shading ring reinforcing bar 6 of side are welded to connect.In compound isolation pile from upper and Include the steel reinforcement cage that more piece is made up of isolation pile longitudinal reinforcement 5, shading ring reinforcing bar 6, positioning spacer bar 7 down, respectively save steel reinforcement cage Between with reinforcing bar connector connect.
The reinforced construction method of the compound isolation pile of bridge pier is worn in above-mentioned tunnel side, comprises the following steps:
Step 1:Surveying and locating:
In existing bridge pile foundation 2 and bridge bearing platform 1(Or other existing constructions of structures)Measure and put between newly built tunnels 3 Sample, according to isolation pile parameter coordinate is designed, mark the earth's surface correspondence position of isolation pile 4;
Isolation pile 4 arranges that adjacent isolation pile 4 is spaced 0.6m using double quincunx mode, forms isolation wall thickness and is not less than 1.6m;
Step 2:Drilling:
Mounting and positioning device, isolation pile pore-forming equipment use small-sized geological drilling rig, and drilling diameter is slightly larger than the diameter of isolation pile 4, adopted With pipe-following drilling technique;
Step 3:Isolation pile 4 makes, connects and installed:
The steel reinforcement cage of isolation pile 4 is made up of isolation pile longitudinal reinforcement 5, shading ring reinforcing bar 6, positioning spacer bar 7, shading ring reinforcing bar 6 are located at axis, and isolation pile longitudinal reinforcement 5 is arranged in the periphery of shading ring reinforcing bar 6, arranged between the interval of isolation pile longitudinal reinforcement 5 There is positioning spacer bar 7;The every meter of ring in longitudinal direction of shading ring reinforcing bar 6 welds with isolation pile longitudinal reinforcement 5 and positioning spacer bar 7, Positioning spacer bar 7 curves wide 40mm, high 200mm annular;
The steel reinforcement cage of isolation pile 4 often saves long 2m, is connected with reinforcing bar connector, and scene is hung using Simple support frame, hand fit In place;Often section is slowly fallen into stake holes after slinging, and is ensured that the elevation of support system and perpendicularity are correct by deadweight, is connect with reinforcing bar Device is refuted to be connected firmly;Prevent from reversing during handling, bend, be directed at hole position during installation, hang and straight help steady, slowly decentralization, collision free hole Wall, fixed immediately after in place;
Step 4:Slip casting:
After the steel reinforcement cage of isolation pile 4 is in place, prepare slip casting;Slip casting is made up of 3 Grouting Pipes 8 and 1 escape pipe 9, every slip casting Pipe output range is away from bottom 4m;When Grouting Pipe is vertically installed, the 1st, 3 Grouting Pipe 8 stretches into a bottom, the 2nd Grouting Pipe 8 to the 1, 3rd short 4m;1st Grouting Pipe 8 does not close pipe end, no slurry outlet, other 2 tube end closings, and gives the 1st pipe slip casting When, the slurry outlet plastic adhesive tape of the 2nd, the 3rd pipe is pasted to isolate slurries, prevents that envelope gambles slurry outlet during slip casting;
Slip casting uses compaction grouting, slip casting point 3 times:1st slip casting uses common pressure grouting, grouting pressure 0.4-0.6 MPa, to hole Mouth overflows terminates this slip casting, the cement mortar ratio of mud 0.5 when starching:1;2nd slip casting uses middle-high pressure grouting, grouting pressure 1.0- 1.5MPa, 10-15h is carried out after the completion of the 1st slip casting, the cement mortar ratio of mud 0.75:1;3rd grouting pressure 1.5-2.0 MPa, 5-10h is carried out after the completion of the 2nd slip casting, the cement mortar ratio of mud 0.75:1;All injecting paste materials use general silicon 42.5 Class g cement;
Step 5:After slip casting terminates, cut isolation pile 8 and go out above ground portion, construction is completed.
Present disclosure is not limited to cited by embodiment, and those of ordinary skill in the art are by reading description of the invention And any equivalent conversion taken technical solution of the present invention, it is that claim of the invention is covered.

Claims (8)

1. the compound isolation pile of bridge pier is worn in tunnel side, it is characterised in that:
The compound isolation pile is set in a row in existing bridge pile foundation(2)And bridge bearing platform(1)With newly built tunnels(3)Between, Stretch into newly built tunnels(3)Below bottom, isolation wall construction is formed;
Compound isolation pile is by isolation pile longitudinal reinforcement(5), shading ring reinforcing bar(6), positioning spacer bar(7)The steel reinforcement cage of composition and Injecting cement paste forms;Shading ring reinforcing bar(6)Positioned at axis, isolation pile longitudinal reinforcement(5)It is arranged in shading ring reinforcing bar(6)Periphery, every From stake longitudinal reinforcement(5)Interval between be disposed with positioning spacer bar(7).
2. the compound isolation pile of bridge pier is worn in tunnel side according to claim 1, it is characterised in that:
The compound isolation pile is arranged in double blossom type, and 0.6m is spaced between adjacent compound isolation pile, and isolation wall thickness is not small In 1.6m.
3. the compound isolation pile of bridge pier is worn in tunnel side according to claim 1, it is characterised in that:
The compound isolation pile is in existing bridge pile foundation(2)And bridge bearing platform(1)It is the linear type in side, L-type, U-shaped or cubic Type is arranged.
4. the compound isolation pile of bridge pier is worn in tunnel side according to claim 1, it is characterised in that:
Shading ring reinforcing bar(6)Every meter of longitudinal direction one ring of arrangement, with isolation pile longitudinal reinforcement(5)With positioning spacer bar(7)Welding connects Connect.
5. the compound isolation pile of bridge pier is worn in tunnel side according to claim 4, it is characterised in that:
Position spacer bar(7)In long annular, straightway and the shading ring reinforcing bar of side(6)It is welded to connect.
6. the compound isolation pile of bridge pier is worn in tunnel side according to claim 1, it is characterised in that:
Include more piece in compound isolation pile from top to bottom by isolation pile longitudinal reinforcement(5), shading ring reinforcing bar(6), positioning supporting steel Muscle(7)The steel reinforcement cage of composition, respectively connected between section steel reinforcement cage with reinforcing bar connector.
7. the reinforced construction method of the compound isolation pile of bridge pier is worn in tunnel side, it is characterised in that:
Comprise the following steps:
Step 1:Surveying and locating:
In existing bridge pile foundation(2)And bridge bearing platform(1)With newly built tunnels(3)Between measure setting-out, according to design every From stake parameter coordinate, isolation pile is marked(4)Earth's surface correspondence position;
Isolation pile(4)Arranged using double quincunx mode, adjacent isolation pile(4)0.6m is spaced, it is not small to form isolation wall thickness In 1.6m;
Step 2:Drilling:
Mounting and positioning device, isolation pile pore-forming equipment use small-sized geological drilling rig, and drilling diameter is slightly larger than isolation pile(4)Diameter, Using pipe-following drilling technique;
Step 3:Isolation pile(4)Make, connect and install:
Isolation pile(4)Steel reinforcement cage by isolation pile longitudinal reinforcement(5), shading ring reinforcing bar(6), positioning spacer bar(7)Composition, every From ring reinforcing bar(6)Positioned at axis, isolation pile longitudinal reinforcement(5)It is arranged in shading ring reinforcing bar(6)Periphery, isolation pile longitudinal reinforcement (5)Interval between be disposed with positioning spacer bar(7);Shading ring reinforcing bar(6)Every meter of a longitudinal direction ring and isolation pile longitudinal reinforcement (5)And positioning spacer bar(7)Welding, position spacer bar(7)Curve wide 40mm, high 200mm annular;
Isolation pile(4)Steel reinforcement cage often save long 2m, with reinforcing bar connector connect, scene hung using Simple support frame, manually match somebody with somebody Close in place;Often section is slowly fallen into stake holes after slinging, and is ensured that the elevation of support system and perpendicularity are correct by deadweight, is used reinforcing bar Connector is connected firmly;Prevent from reversing during handling, bend, be directed at hole position during installation, hang and straight help steady, slowly decentralization, collision free Hole wall, fixed immediately after in place;
Step 4:Slip casting:
Isolation pile(4)Steel reinforcement cage it is in place after, prepare slip casting;Slip casting is by 3 Grouting Pipes(8)And 1 escape pipe(9)Composition, often Root Grouting Pipe output range is away from bottom 4m;When Grouting Pipe is vertically installed, the 1st, 3 Grouting Pipe(8)Stretch into a bottom, the 2nd slip casting Pipe(8)Than the 1st, the 3rd short 4m;1st Grouting Pipe(8)Pipe end, no slurry outlet are not closed, other 2 tube ends are closed, and During to the 1st pipe slip casting, the slurry outlet plastic adhesive tape of the 2nd, the 3rd pipe is pasted to isolate slurries, prevents that envelope is gambled out during slip casting Starch hole;
Step 5:After slip casting terminates, isolation pile is cut(8)Go out above ground portion, construction is completed.
8. the reinforced construction method of the compound isolation pile of bridge pier is worn in tunnel side according to claim 7, it is characterised in that:
In step 4, slip casting uses compaction grouting, slip casting point 3 times:1st slip casting uses common pressure grouting, grouting pressure 0.4-0.6 MPa, terminate this slip casting, the cement mortar ratio of mud 0.5 when overflowing slurry to aperture:1;2nd slip casting uses middle-high pressure grouting, slip casting Pressure 1.0-1.5MPa, 10-15h is carried out after the completion of the 1st slip casting, the cement mortar ratio of mud 0.75:1;3rd grouting pressure 1.5-2.0 MPa, 5-10h is carried out after the completion of the 2nd slip casting, the cement mortar ratio of mud 0.75:1;All injecting paste materials use The general class g cement of silicon 42.5.
CN201710691818.6A 2017-08-14 2017-08-14 Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side Pending CN107386274A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710691818.6A CN107386274A (en) 2017-08-14 2017-08-14 Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710691818.6A CN107386274A (en) 2017-08-14 2017-08-14 Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side

Publications (1)

Publication Number Publication Date
CN107386274A true CN107386274A (en) 2017-11-24

Family

ID=60355648

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710691818.6A Pending CN107386274A (en) 2017-08-14 2017-08-14 Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side

Country Status (1)

Country Link
CN (1) CN107386274A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108049888A (en) * 2018-01-16 2018-05-18 西南交通大学 It is a kind of for the tunnel structure in metro shield section and stratum consolidation method
CN109083132A (en) * 2018-07-24 2018-12-25 北京隧盾市政建设有限公司 A kind of Composite Bolt stake and its construction technology
CN109898539A (en) * 2019-04-15 2019-06-18 中恒工程设计院有限公司 A kind of positional structure of bridge pile foundation and subway tunnel
CN110939127A (en) * 2019-11-28 2020-03-31 中建四局土木工程有限公司 Steel pipe pile construction method for protecting subway pier
WO2020224233A1 (en) * 2019-05-05 2020-11-12 济南轨道交通集团有限公司 Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner
CN111997097A (en) * 2020-09-03 2020-11-27 西南交通大学 Composite isolation pile for tunnel side-through house and reinforcing construction method thereof
CN112228081A (en) * 2020-10-24 2021-01-15 中铁一局集团有限公司 Method for reinforcing pile foundation of shield tunnel side-through high-speed rail viaduct
CN113309108A (en) * 2021-04-14 2021-08-27 武汉市市政建设集团有限公司 Isolation pile with servo grouting function and construction method thereof
CN113338274A (en) * 2021-06-01 2021-09-03 中铁十八局集团有限公司 Anchor rod pile locator is built to underground space

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565955A (en) * 2009-06-01 2009-10-28 北京科技大学 Micro-stress shelter pile foundation strengthening method
CN102031795A (en) * 2010-06-12 2011-04-27 中铁十六局集团有限公司 Short pile reinforcing technology in narrow space
CN103114611A (en) * 2013-03-01 2013-05-22 同济大学 Multistage cut-off method for underpass high-speed rail bridge opening deformation
CN203891008U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Miniature isolation pile
CN207109805U (en) * 2017-08-14 2018-03-16 中铁第一勘察设计院集团有限公司 Wear the compound isolation pile of bridge pier in a kind of tunnel side

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101565955A (en) * 2009-06-01 2009-10-28 北京科技大学 Micro-stress shelter pile foundation strengthening method
CN102031795A (en) * 2010-06-12 2011-04-27 中铁十六局集团有限公司 Short pile reinforcing technology in narrow space
CN103114611A (en) * 2013-03-01 2013-05-22 同济大学 Multistage cut-off method for underpass high-speed rail bridge opening deformation
CN203891008U (en) * 2014-05-27 2014-10-22 中铁十九局集团轨道交通工程有限公司 Miniature isolation pile
CN207109805U (en) * 2017-08-14 2018-03-16 中铁第一勘察设计院集团有限公司 Wear the compound isolation pile of bridge pier in a kind of tunnel side

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108049888A (en) * 2018-01-16 2018-05-18 西南交通大学 It is a kind of for the tunnel structure in metro shield section and stratum consolidation method
CN109083132A (en) * 2018-07-24 2018-12-25 北京隧盾市政建设有限公司 A kind of Composite Bolt stake and its construction technology
CN109898539A (en) * 2019-04-15 2019-06-18 中恒工程设计院有限公司 A kind of positional structure of bridge pile foundation and subway tunnel
WO2020224233A1 (en) * 2019-05-05 2020-11-12 济南轨道交通集团有限公司 Construction method for shield tunnels passing underneath viaduct in multi-interval, small-clear-distance and overlapping manner
CN110939127A (en) * 2019-11-28 2020-03-31 中建四局土木工程有限公司 Steel pipe pile construction method for protecting subway pier
CN111997097A (en) * 2020-09-03 2020-11-27 西南交通大学 Composite isolation pile for tunnel side-through house and reinforcing construction method thereof
CN112228081A (en) * 2020-10-24 2021-01-15 中铁一局集团有限公司 Method for reinforcing pile foundation of shield tunnel side-through high-speed rail viaduct
CN113309108A (en) * 2021-04-14 2021-08-27 武汉市市政建设集团有限公司 Isolation pile with servo grouting function and construction method thereof
CN113338274A (en) * 2021-06-01 2021-09-03 中铁十八局集团有限公司 Anchor rod pile locator is built to underground space

Similar Documents

Publication Publication Date Title
CN107386274A (en) Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN105840207B (en) Construction method for comprehensive tunnel entering structure of large-span tunnel penetrating shallow-buried bias-pressure loose accumulation body
CN106402490B (en) Silt stratum push pipe jacking construction method based on steel bushing head tool pipe
CN103206219A (en) Holed excavation supporting structure for light and dark junction section of tunnel in bias pressure state and construction method
CN204199335U (en) A kind of pressure release well reducing PHC tube pile construction soil compaction effect
CN101343868B (en) Underground continuous wall construction method of city-across pipeline
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN101343869A (en) Underground continuous wall construction method of city-across pipeline
CN110107310A (en) A kind of construction method at tunnel slope hole
CN102505704A (en) Large open caisson construction method in soft geological shaft
CN101225664A (en) Caisson dock structure and construction method therefor
CN208965598U (en) The Anti-seeping technology structure of grout curtain and underground chamber intersection area
CN104863183B (en) Damping pilework and construction method is isolated in large cross-section tunnel proximity architecture construction
CN112482364A (en) Construction process of rotary digging cast-in-place pile under strong corrosive soft geological conditions in coastal region
CN110374677A (en) Plateau rich water soft rock tunnel control drainage construction engineering method
CN102296621A (en) Construction method of ground sectional water-stop curtain
CN103485347A (en) Batter pile used for building foundation pit support and construction method thereof
CN209429153U (en) It is a kind of to hammer the steel cylinder caisset constructed into shape suitable for hydraulic resonance of exempting from
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN207109805U (en) Wear the compound isolation pile of bridge pier in a kind of tunnel side
CN107514266A (en) Shield export & import bolt anchorage soil body construction method
CN102031795A (en) Short pile reinforcing technology in narrow space
CN110762286B (en) Drainage pipe network artificial pipe jacking construction process
CN111560959A (en) Excavation and supporting method for shield starting well foundation pit adjacent to subway

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination