CN110374677A - Plateau rich water soft rock tunnel control drainage construction engineering method - Google Patents

Plateau rich water soft rock tunnel control drainage construction engineering method Download PDF

Info

Publication number
CN110374677A
CN110374677A CN201910711033.XA CN201910711033A CN110374677A CN 110374677 A CN110374677 A CN 110374677A CN 201910711033 A CN201910711033 A CN 201910711033A CN 110374677 A CN110374677 A CN 110374677A
Authority
CN
China
Prior art keywords
slip casting
mini
hole
rich water
plateau
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910711033.XA
Other languages
Chinese (zh)
Inventor
许庆君
高岩
蔡书洪
舒承兴
贾进勇
刘国龙
范玲玲
刘洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 9 Group Co Ltd
Sixth Engineering Co Ltd of China Railway No 9 Group Co Ltd
Original Assignee
China Railway No 9 Group Co Ltd
Sixth Engineering Co Ltd of China Railway No 9 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 9 Group Co Ltd, Sixth Engineering Co Ltd of China Railway No 9 Group Co Ltd filed Critical China Railway No 9 Group Co Ltd
Priority to CN201910711033.XA priority Critical patent/CN110374677A/en
Publication of CN110374677A publication Critical patent/CN110374677A/en
Pending legal-status Critical Current

Links

Classifications

    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B28/00Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements
    • C04B28/02Compositions of mortars, concrete or artificial stone, containing inorganic binders or the reaction product of an inorganic and an organic binder, e.g. polycarboxylate cements containing hydraulic cements other than calcium sulfates
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/00724Uses not provided for elsewhere in C04B2111/00 in mining operations, e.g. for backfilling; in making tunnels or galleries
    • CCHEMISTRY; METALLURGY
    • C04CEMENTS; CONCRETE; ARTIFICIAL STONE; CERAMICS; REFRACTORIES
    • C04BLIME, MAGNESIA; SLAG; CEMENTS; COMPOSITIONS THEREOF, e.g. MORTARS, CONCRETE OR LIKE BUILDING MATERIALS; ARTIFICIAL STONE; CERAMICS; REFRACTORIES; TREATMENT OF NATURAL STONE
    • C04B2111/00Mortars, concrete or artificial stone or mixtures to prepare them, characterised by specific function, property or use
    • C04B2111/00474Uses not provided for elsewhere in C04B2111/00
    • C04B2111/00732Uses not provided for elsewhere in C04B2111/00 for soil stabilisation

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Geology (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Architecture (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Civil Engineering (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Inorganic Chemistry (AREA)
  • Materials Engineering (AREA)
  • Organic Chemistry (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The present invention relates to a kind of plateau rich water soft rock tunnel control drainage construction engineering method, steps are as follows: 1) surrounding rock advanced support;2) tunnel excavation;3) country rock circumferential direction supporting;4) mini-valve tube test pile is tested;5) mini-valve tube coring is examined;6) two linings are handled;7) sleeve valve barrel grouting.Country rock active strength and self-stable ability ensure that using sleeve valve barrel grouting.

Description

Plateau rich water soft rock tunnel control drainage construction engineering method
Technical field
The present invention relates to a kind of plateau rich water soft rock tunnel control drainage construction engineering methods.
Background technique
The unfavorable geologies such as tunnel bottom rich water fractured weak zone and Special Rock development, engineering geology and hydrogeologic condition Complexity, the development of ROCK MASS JOINT crack, Bedrock Crevice Water can seep under joint plane, when tunnel is that descending tunnels form, in rain It is seeped under season surface water, tunnel trunk range has a large amount of Bedrock Crevice Waters, this crevice water will cause fine grained and be lost to form gap, from And the problems such as causing foundation bearing capacity to decline, setting of ground occur, while lining crack can be caused.
Summary of the invention
The technical problem to be solved in the present invention is to provide a kind of plateau rich water soft rock tunnel control drainage construction engineering methods, using sleeve Valve pipe slip casting ensure that country rock active strength and self-stable ability.
A kind of plateau rich water soft rock tunnel control drainage construction engineering method, steps are as follows 1) surrounding rock advanced support: rich water crushed zone Using pipe canopy link, remaining crushed zone is connect using seamless advanced tubule ring;2) tunnel excavation: weak surrounding rock section uses three steps Seven step excavating loads;3) it country rock circumferential direction supporting: is just propped up using 18# I-steel 0.8m spacing closed-loop tunnel inverted arch, circumferential direction is reserved Settling amount 20cm;4) mini-valve tube test pile is tested;5) mini-valve tube coring is examined: after grouting and reinforcing 28 days, different location boring and coring Test, at least three groups of tests, and the 2-3% of no less than injected hole of each slip casting section, every group is no less than 3 boring and corings;6) two lining Processing: using the strengths such as armored concrete tunneling boring reason;7) sleeve valve barrel grouting: carrying out radial grouting reinforcing in 3m after step 6), 7.1) spacing setting-out: arranging Φ 90mmPVC pipe installation site according to test pile result, and when drilling avoids structure main reinforcement, steelframe, reduces Destruction to existing structure;7.2) it drills: pvc pipe being reserved according to step 7.1) and determines hole location, is drilled;7.3) system is mixed, is filled Infuse sleeve shell material: step 7.2) uses clear water hole flushing afterwards, then carries out sheath body perfusion, sleeve shell material is pressed into hole using drilling rod; 7.4) install mini-valve tube: basset 30cm for mini-valve tube upper surface, and Xiang Guanzhong fills clear water, mini-valve tube lower end surface during installing It is sealed;7.5) slurries make: cement: water=0.5:1-1:1, grouting pressure 1-3Mpa;7.6) slip casting: using double embolism cores Pipe carries out slip casting;7.7) it cleans: cleaning slip casting machine, blender and various pipelines in time, remove residual slurry in mini-valve tube, be convenient for Next time uses;7.8) seal: mini-valve tube end 25cm depth bounds use 108 drill bit reaming of φ, backfill compensation after hole wall dabbing It shrinks C35 crushed stone concrete and carries out sealing of hole.
Mini-valve tube structure in the step 7.4) are as follows: φ 50mmPVC plastic tube excircle is equipped with φ 6mm every 35cm Penetrate slurry hole, penetrate slurry hole and be annularly distributed in plastic tube excircle, plastic tube excircle is set with rubber sleeve, rubber sleeve position with penetrate It is corresponding to starch hole site, plastic tube excircle is bonded with guide ring, and guide ring is between two neighboring rubber sleeve.For convenience into Row grouting is drilled with penetrating for a circle Φ 6mm every 35cm on mini-valve tube and starches hole, and every circle penetrates the longitudinal length 6cm in slurry hole, every meter of sleeve 2-3 group is bored on valve pipe and penetrates slurry hole, is penetrated outside slurry hole for every group and is glued with soft rubber sleeve packet, every group of ratio of rubber sleeve length is penetrated slurry hole length It is slightly longer, slurry hole is penetrated as principle to wrap, and when mini-valve tube is put into drilling, the effect of rubber sleeve is to prevent drilling slurry or set Shell material enters in pipe;Rubber case is washed open by slurries under pressure when grouting, and slurries is made to enter stratum, and can guarantee by wanting It asks and distinguishes level, form splitting, and when stopping grouting, rubber sleeve rebounds again and wraps mini-valve tube, prevents extratubal fluid from entering In pipe, the operation of reverse stop valve is played, to prevent rubber sleeve from misplacing up and down, must be fixed in rubber sleeve two sides with fixed ring, valve of tucking inside the sleeve Guan Buying has biggish bending, and inner wall must be smooth.
The seamless lock foot anchor tube of slip casting φ 42mm is reinforced using double between the step 3) I-steel, locks foot anchor tube horizontal direction Lower 30 ° connect country rock with supporting.Avoiding circumferential direction from the circumferential stress of weak link influence occur leads to just branch deformed damaged, avoids just The non-slip casting backfill in branch behind gap, advanced tubule spacing be excessive or outer limb control is bad, grouting reinforcement country rock is not up to imitated Fruit, construction disturbance etc., surrouding rock deformation or collapsing when caused excavation will using double 30 ° of lock foot anchor tubes lower to φ 42mm horizontal direction Country rock is securely connect with supporting;And arch springing is placed in do not destroy or the protolith of etch on, and prevent water from impregnating;In special circumstances After arch bottom plank or concrete slab support pad are secured, arch springing position is expanded the mixed protection of spray by gunite concrete.
In the step 1), rich water crushed zone overlaps 2m using the seamless middle pipe canopy overlap joint setting of φ 89mm, every mono- ring of 6m, Remaining crushed zone is uniformly distributed using the seamless advanced tubule 0.3m circumferential direction of φ 42mm, and every mono- ring of 0.8m is overlapped to form with a thickness of 2m Polycyclic ductule protective layer.The deformation or collapsing for effectively inhibiting country rock in digging process, prevent wall rock loosening and reduce intensity And stability.
Foundation bearing capacity fspk is not less than 300Kpa in the step 5).
Sheath body material weight ratio is cement in the step 7.3): clay: water=1:1.5:2.
Step 7.6) the construction method are as follows:
7.6.1) open loop: it is prominent to there is pressure in pressure process using thin pulp or clear water pressurization open loop for the preliminary stage of slip casting Drop, grout absorption increase severely, and indicate " open loop ";
7.6.2) slip casting: slip casting is carried out using double embolism core pipes, carries out slip casting from bottom to top from bottom hole, every round eye is as one Slip casting section, segment length 35cm;
7.6.3) by the method slip casting for injecting underflow is first injected after thin pulp when slip casting, normal grouting pressure is 1~3Mpa, starting note Pressure control is starched within 1.0Mpa, is then pressurizeed step by step, and be from bottom to top gradually reduced;
7.6.4) slip casting order: each one hole of tripping carries out slip casting;
7.6.5) interval slip casting: after the completion of complete opening section slip casting, interval a period of time carries out second of slip casting, intermittent time control again Within 10~30min;
7.6.6) slip casting ending standard: under the conditions of pressure 1.5MPa can pressure stabilizing 10min can terminate slip casting;When midge amount is long Between < 2.5L/min, slip casting can be terminated;It alters slurry, slurries leakage seriously or slurries emits along slip casting tube wall, hits and split plugged zone When, stop slip casting.
Bring of the present invention has the beneficial effect that using tunnel upper, middle and lower step construction height difference advantage, water conservancy diversion face, in Lead, under lead, first branch water seepage flow to the position 2m dewatering well before inverted arch end, by self-draining arrangement in dewatering well utilize along tunnel The pipe of pumping drainage step by step laid drains into hole Nei Shui outside hole, and construction surface country rock can be effectively ensured and impregnate from underground water, retain Country rock active strength and self-stable ability.
It is vertically pre-buried between inverted arch lining cutting and first branch from filling surface using φ 90mmPVC pipe, it is independently present in inverted arch Between reinforcing bar and first branch arch, main body reinforcing bar and arch are not damaged conducive to next step mini-valve tube tunnel bottom mortar depositing construction, and guarantee to face upward Arch lining is built, filling applies closing cyclization in time, reduces the tunnel bottom country rock exposed water logging time, and crevice water branch exudation as at the beginning of inverted arch is laggard Enter pvc pipe, on entity structure without influence.
Sleeve valve barrel grouting construction uses down-the-hole drill bit, eliminates pvc pipe in preformed hole, is conducive to later period inverted arch globality, and Avoid that operation phase tunnel bottom rich water fractured weak zone is likely to occur because caused by draining fine grained be lost to form hole, cause substrate to be held Power decline is carried, substrate sinking and lining crack hidden danger are caused.
Detailed description of the invention
Fig. 1 is mini-valve tube structural schematic diagram.
Specific embodiment
As shown in Figure 1, a kind of plateau rich water soft rock tunnel control drainage construction engineering method, steps are as follows: 1) surrounding rock advanced support: Rich water crushed zone uses pipe canopy link, remaining crushed zone is connect using seamless advanced tubule ring;2) tunnel excavation: weak surrounding rock section Using three steps, seven step excavating load;3) it country rock circumferential direction supporting: is just propped up using 18# I-steel 0.8m spacing closed-loop tunnel inverted arch, ring To direction anticipated settlement 20cm;4) mini-valve tube test pile is tested;5) mini-valve tube coring is examined: after grouting and reinforcing 28 days, different positions Boring and coring test is set, at least three groups of tests, and the 2-3% of no less than injected hole of each slip casting section, every group is no less than 3 drillings Coring;6) two linings are handled: using the strengths such as armored concrete tunneling boring reason;7) diameter sleeve valve barrel grouting: is carried out after step 6) in 3m To grouting and reinforcing, 7.1) spacing setting-out: arranging Φ 90mmPVC pipe installation site according to test pile result, and when drilling can be avoided tying Structure main reinforcement, steelframe reduce the destruction to existing structure.7.2) it drills: pvc pipe being reserved according to step 7.1) and determines hole location, is carried out Drilling;7.3) system mixes, sleeve shell material is perfused: then step 7.2) carries out sheath body perfusion afterwards using clear water hole flushing, will be covered using drilling rod Shell material is pressed into hole;7.4) install mini-valve tube: basset 30cm for mini-valve tube upper surface, and Xiang Guanzhong is filled clearly during installing Water, mini-valve tube lower end surface are sealed;7.5) slurries make: cement: water=0.5:1-1:1, grouting pressure 1-3Mpa;7.6 note Slurry: slip casting is carried out using double embolism core pipes;7.7) it cleans: cleaning slip casting machine, blender and various pipelines in time, remove mini-valve tube Interior residual slurry uses convenient for next time;7.8) seal: mini-valve tube end 25cm depth bounds use 108 drill bit reaming of φ, hole wall C35 crushed stone concrete progress sealing of hole is shunk in backfill compensation after dabbing.
Mini-valve tube structure in the step 7.4) are as follows: 1 excircle of φ 50mmPVC plastic tube is equipped with φ every 35cm 6mm penetrates slurry hole 2, penetrates slurry hole 2 and is annularly distributed in 1 excircle of plastic tube, 1 excircle of plastic tube is set with rubber sleeve 3, rubber sleeve 3 positions are corresponding with slurry 2 position of hole is penetrated, and 1 excircle of plastic tube is bonded with guide ring 4, and guide ring 4 is located at two neighboring rubber sleeve 3 Between.Every circle on valve pipe penetrates slurry hole 2, as a grout compartment, and grouting head is made of double plug system stop grouting plugs and grouting core, often It only include a grout compartment when once grouting head moves up and down grouting in mini-valve tube, that is, be in the milk head moving distance and every group It is identical to penetrate slurry 2 spacing of hole, the connection of mini-valve tube has to guarantee quality, is completely embedded, there must not be disconnection phenomenon;Sleeve shell material is perfused The closed mini-valve tube in bottom is inserted to bottom hole immediately afterwards, and mini-valve tube is made to be located at hole center as far as possible, be such as hampered power during assigning, It cannot smoothly be inserted into, should ascertain the reason, forbid being pressed into excessive external force, fitting depth should be consistent with drilling depth, worst error No more than 20cm, the mini-valve tube about 30cm suitable for reading that bassets is installed and is filled clear water in Shi Xiangguan, and the weight effect of water makes mini-valve tube It will not float, close the lid on mini-valve tube top, prevent sundries from entering, influence slip casting operation quality, under normal circumstances, because there is sheath body Only slurry effect be not required to seal, if really need, aperture away from below ground 0.5m or so range use accelerator cement bonded sand Slurry blocks, and prevents grout during slip casting.
The seamless lock foot anchor tube of slip casting φ 42mm is reinforced using double between the step 3) I-steel, locks foot anchor tube horizontal direction Lower 30 ° connect country rock with supporting.
In the step 1), rich water crushed zone overlaps 2m using the seamless middle pipe canopy overlap joint setting of φ 89mm, every mono- ring of 6m, Remaining crushed zone is uniformly distributed using the seamless advanced tubule 0.3m circumferential direction of φ 42mm, and every mono- ring of 0.8m is overlapped to form with a thickness of 2m Polycyclic ductule protective layer.
Foundation bearing capacity fspk is not less than 300Kpa in the step 5).
Sheath body material weight ratio is cement in the step 7.3): clay: water=1:1.5:2.Sleeve shell material is for sealing The annular space between mini-valve tube and drilling is closed, prevents slurries when slip casting from flowing string everywhere;It tucks inside the sleeve under valve and stop grouting plug cooperation in rubber, It forces the slurries only open loop in a slip casting segment limit: racking sleeve shell material, and enter slip casting section stratum, sleeve shell material uses swelling Property clay and cement grout stir, 3 day age compression strength of sheath body is 0.3Mpa, to preventing slurries string from emitting favorably, but not Conducive to open loop: low-intensity sheath body is conducive to open loop, is also easy to slurries and up goes here and there emit, therefore covers shell intensity and must have both open loop and anti- Only grout leaking cooperates weight ratio: cement: clay: water=1:1.5:2, drills to projected depth and carries out sheath body after using clear water hole flushing The good sleeve shell material of mixing, is pressed into hole by perfusion using drilling rod, and drilling rod is placed in bottom hole when perfusion, and sheath body is perfused from bottom to top Material is until mud is replaced by sleeve shell material completely in hole, until the virgin pulp liquid for meeting concentration requirement is overflowed in aperture.
Step 7.6) the construction method are as follows: 7.6.1) open loop: the preliminary stage of slip casting is pressurizeed using thin pulp or clear water There is abrupt pressure reduction in pressure process in open loop, and grout absorption increases severely, and indicates " open loop ";
7.6.2) slip casting: slip casting is carried out using double embolism core pipes, carries out slip casting from bottom to top from bottom hole, every round eye is as one Slip casting section, segment length 35cm;
7.6.3) by the method slip casting for injecting underflow is first injected after thin pulp when slip casting, normal grouting pressure is 1~3Mpa, starting note Pressure control is starched within 1.0Mpa, is then pressurizeed step by step, and be from bottom to top gradually reduced;
7.6.4) slip casting order: each one hole of tripping carries out slip casting;
7.6.5) interval slip casting: after the completion of complete opening section slip casting, interval a period of time carries out second of slip casting, intermittent time control again Within 10~30min;
7.6.6) slip casting ending standard: under the conditions of pressure 1.5MPa can pressure stabilizing 10min can terminate slip casting;When midge amount is long Between < 2.5L/min, slip casting can be terminated;It alters slurry, slurries leakage seriously or slurries emits along slip casting tube wall, hits and split plugged zone When, stop slip casting.
Vault sinking measures
The installation of measuring point should ensure that after excavation in 12h and measure initial reading before subsequent cycle excavation, by each measuring point Vault sinking regression curve is drawn respectively, and information is timely feedbacked.
The measurement of perimeter convergence
The spacing of perimeter convergence measuring section according to Grades of Surrounding Rock, tunnel cross-section size, buried depth etc. determine, its spacing for This engineering tunnel is V grades of country rocks 5m, IV grade of country rock 10m, III grade of country rock 20m.
Horizontal convergence is measured to be measured on time using convergence instrument, and to understand Change in surrounding rocks situation in work progress, level is received It is identical with vault sinking to hold back measurement frequency, draws horizontal convergence time graph by every survey line, analysis preliminary bracing is stablized Situation calculates final displacement value, to determine that two linings carry out the time.
Deformation in surrounding rock measures
Measuring section should be located at representational geology location;Under general wall rock condition, a measurement is set every 200~500m Section is than conveniently, each measuring section should lay 3~11 measuring points;The measuring point to be measured as close as possible to anchor pole or periphery displacement Place, to calculate analysis.
The measurement frequency of country rock intrinsic displacement is identical as the other projects measurement frequencies of same section.
It is measured using multipoint displacement meter, generally behind arch or top pilot drive, the extensometer of drilling installation immediately, then It is digged, is surveyed every certain time and read each point shift value;It is corrected, finds out relative to most deeper shift value, when making M- displacement curve analyzes the rate of deformation and stability of each point.With the vernier depth gauge of 0~300mm, (precision is scholar 0. 2mm) survey read, every need to carry out 5 survey reading, take its 3 times similar in reading average value as herein survey reading result;When surveying reading interval Between by a few hours to a couple of days, it is general be spaced 1d survey read it is primary.
Generally according to measurement, displacement-depth curve and displacement versus time relation curve are first drawn, passes through displacement- Time graph has grasped the rule deformed at any time inside country rock, then can be preferably applied to guiding construction.
Anchor axial force measures
Anchor pole internal force and withdrawal resistance measuring point are laid near tunnel surrounding internal displacement monitoring section, point layout encircles in tunnel At top, left and right haunch position, each country rock sets 2 groups, after tunnel excavation explosion, carries out measuring point laying.
Anchor pole internal force, withdrawal resistance are measured using anchor ergometer and ZX-20 type anchor pole pull out force meter.
Controlling value: withdrawal resistance is not less than design value, and internal force is not more than the 80% of design value.
Pressure from surrounding rock measures
Measuring point is measured to subterranean body pressure, seepage pressure, specific location is separately depending on condition of construction, various point layout positions It sets, is intended to install soil pressure cell, osmometer between palisades and steel arch-shelf by design position when installing steel arch-shelf, Mei Gezhu Section installs soil pressure cell 4, osmometer 4.
Rock mass pressure is timed measurement using pre- inbuilt GDY-2 earth pressure gauge;Seepage pressure is seeped using DKY-51 type Pressure meter, frequency reception instrument are timed measurement, measure frequency, are controlled with the longitudinal separation of excavation face to measuring point, as distance < 2B When, 1 time a day;As distance < 5B, every 2 days 1 time;It as distance > 5B, 1 times a week, is monitored on time, draws soil in time Pressure curve and seepage pressure curve understand excavate periphery soil stone pressure and seepage pressure in time, are conducive to Construction Decision.
Supporting, lining cutting stress measure
It sprays concrete and forces in lining detection method is substantially identical as bracing members Internal Force Monitoring, effect is provided to determine country rock and tunnel Road stability.
Steelframe internal force and the load born measure
Steelframe after the installation is completed, by resistance-strain type reinforcing rib meter, be separately mounted to after damp-proof treatment steel arch-shelf tension, by Then spray concrete is applied in splenium position, be connected to instrument by lead, then the deformation for the steelframe that resistance strain gage is experienced is converted into electricity Signal output is pressed, passes through the curve demarcated in advance, so that it may converse measured stress value.
Tunnel steelframe load-bearing monitor is monitored using preassembled resistance-strain reinforcing rib meter and resistance strain gauge.
Steel frame construction is modified if measurement steelframe category unstable state, should use measure immediately according to measurement, it is ensured that Construction safety.
The test of country rock elastic wave velocity
The testing elastic wave velocity on the rock mass for have determined that surrounding rock category, the correlation for establishing surrounding rock category with elastic wave velocity are bent Line.
Metric data processing, regression analysis, information feedback and Corresponding Countermeasures
(1) data processing and regression analysis
Each reading of each point is drawn in scatter plot, draws horizontal convergence, vault sinking, surface subsidence, country rock further according to scatter plot Preliminary the tense curve and stress strain curve such as deep displacement, country rock and support earth pressure, draw displacement and excavation face away from The relation curve between.
A certain curvilinear function (such as exponential function, logarithmic function, hyperbolic functions are first selected according to the feature of preliminary tense curve Deng) returned.
Selected function is carried out transformation to replace, so that it becomes linear function form, then uses the public affairs of one-variable linear regression Formula and method acquire the relationship a and b of the transformed linear function, then the coefficient is substituted into and replaces formula, it obtains former selected Curvilinear function coefficient, i.e., the regression curve finally acquired.
In the description of the present invention, it is to be understood that, term " vertical ", "upper", "lower", " side ", " one end ", The orientation of the instructions such as " upper end ", "horizontal", " top ", " lower section ", "vertical", " middle part ", " lower end ", " other end ", " longitudinal direction " Or positional relationship describes merely to description is of the invention with simplified to be based on the orientation or positional relationship shown in the drawings, rather than The device or element of indication or suggestion meaning must have a particular orientation, and be constructed and operated in a specific orientation, it is thus impossible to It is interpreted as limitation of the present invention.
In the present invention, it unless otherwise expressly provided and limits, term " installation ", " connects, the arts such as " fixation " " connected " Language shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral;It can be mechanical connect It connects, is also possible to be electrically connected;It can be and be directly connected to, can be and be indirectly connected with by intermediary, can be in two elements The interaction relationship of the connection in portion or two elements for the ordinary skill in the art can be according to specific feelings Condition understands the concrete meaning of above-mentioned term in the present invention.
Above-described is only the preferred embodiment of the present invention.It should be pointed out that coming for those of ordinary skill in the art It says, without departing from the principle of the present invention, several variations and modifications can also be made, also should be regarded as belonging to guarantor of the invention Protect range.

Claims (7)

1. a kind of plateau rich water soft rock tunnel control drainage construction engineering method, it is characterised in that following steps: 1) surrounding rock advanced support: rich Water crushed zone uses pipe canopy link, remaining crushed zone is connect using seamless advanced tubule ring;2) tunnel excavation: weak surrounding rock section is adopted With three steps, seven step excavating load;3) country rock circumferential direction supporting: just being propped up using 18# I-steel 0.8m spacing closed-loop tunnel inverted arch, circumferential Direction anticipated settlement 20cm;4) mini-valve tube test pile is tested;5) mini-valve tube coring is examined: after grouting and reinforcing 28 days, different location Boring and coring test, at least three groups of tests, and the 2-3% of no less than injected hole of each slip casting section, every group is no less than 3 drillings and takes Core;6) two linings are handled: using the strengths such as armored concrete tunneling boring reason;7) it sleeve valve barrel grouting: is carried out in 3m after step 6) radial Grouting and reinforcing;7.1) spacing setting-out: Φ 90mmPVC pipe installation site is arranged according to test pile result, when drilling avoids structure main reinforcement And steelframe, reduce the destruction to existing structure;7.2) it drills: pvc pipe being reserved according to step 7.1) and determines hole location, is drilled; 7.3) system mixes, be perfused sleeve shell material: step 7.2) is afterwards using clear water hole flushing, then progress sheath body perfusion, using drilling rod by sleeve shell material It is pressed into hole;7.4) install mini-valve tube: basset 30cm for mini-valve tube upper surface, and Xiang Guanzhong fills clear water during installing, Mini-valve tube lower end surface is sealed;7.5) slurries make: cement: water=0.5:1-1:1, grouting pressure 1-3Mpa;7.6) slip casting: Slip casting is carried out using double embolism core pipes;7.7) it cleans: cleaning slip casting machine, blender and various pipelines in time, remove in mini-valve tube Residual slurry uses convenient for next time;7.8) seal: mini-valve tube end 25cm depth bounds use 108 drill bit reaming of φ, hole wall chisel C35 crushed stone concrete progress sealing of hole is shunk in backfill compensation after hair.
2. plateau rich water soft rock tunnel control drainage construction engineering method as described in claim 1, it is characterised in that: the step 7.4) the mini-valve tube structure in are as follows: φ 50mmPVC plastic tube excircle is equipped with φ 6mm every 35cm and penetrates slurry hole, penetrates slurry Kong Chenghuan Shape is distributed in plastic tube excircle, and plastic tube excircle is set with rubber sleeve, and rubber sleeve position is corresponding with slurry hole site is penetrated, plastics Pipe excircle is bonded with guide ring, and guide ring is between two neighboring rubber sleeve.
3. plateau rich water soft rock tunnel control drainage construction engineering method as described in claim 1, it is characterised in that: the step 3) The seamless lock foot anchor tube of slip casting φ 42mm is reinforced using double between I-steel, lower 30 ° of lock foot anchor tube horizontal direction connects country rock and supporting It connects.
4. plateau rich water soft rock tunnel control drainage construction engineering method as described in claim 1, it is characterised in that: the step 1) In, rich water crushed zone overlaps 2m using the seamless middle pipe canopy overlap joint setting of φ 89mm, every mono- ring of 6m, remaining crushed zone uses φ 42mm Seamless advanced tubule 0.3m circumferential direction is uniformly distributed, and every mono- ring of 0.8m is overlapped to form the polycyclic ductule protective layer with a thickness of 2m.
5. plateau rich water soft rock tunnel control drainage construction engineering method as described in claim 1, it is characterised in that: the step 5) Middle foundation bearing capacity fspk is not less than 300Kpa.
6. plateau rich water soft rock tunnel control drainage construction engineering method as described in claim 1, it is characterised in that: the step 7.3) sheath body material weight ratio is cement in: clay: water=1:1.5:2.
7. plateau rich water soft rock tunnel control drainage construction engineering method as described in claim 1, it is characterised in that: the step 7.6) construction method are as follows:
7.6.1) open loop: it is prominent to there is pressure in pressure process using thin pulp or clear water pressurization open loop for the preliminary stage of slip casting Drop, grout absorption increase severely, and indicate " open loop ";
7.6.2) slip casting: slip casting is carried out using double embolism core pipes, carries out slip casting from bottom to top from bottom hole, every round eye is as one Slip casting section, segment length 35cm;
7.6.3) by the method slip casting for injecting underflow is first injected after thin pulp when slip casting, normal grouting pressure is 1~3Mpa, starting note Pressure control is starched within 1.0Mpa, is then pressurizeed step by step, and be from bottom to top gradually reduced;
7.6.4) slip casting order: each one hole of tripping carries out slip casting;
7.6.5) interval slip casting: after the completion of complete opening section slip casting, interval a period of time carries out second of slip casting, intermittent time control again Within 10~30min;
7.6.6) slip casting ending standard: under the conditions of pressure 1.5MPa can pressure stabilizing 10min can terminate slip casting;When midge amount is long Between < 2.5L/min, slip casting can be terminated;It alters slurry, slurries leakage seriously or slurries emits along slip casting tube wall, hits and split plugged zone When, stop slip casting.
CN201910711033.XA 2019-08-02 2019-08-02 Plateau rich water soft rock tunnel control drainage construction engineering method Pending CN110374677A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910711033.XA CN110374677A (en) 2019-08-02 2019-08-02 Plateau rich water soft rock tunnel control drainage construction engineering method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910711033.XA CN110374677A (en) 2019-08-02 2019-08-02 Plateau rich water soft rock tunnel control drainage construction engineering method

Publications (1)

Publication Number Publication Date
CN110374677A true CN110374677A (en) 2019-10-25

Family

ID=68257917

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910711033.XA Pending CN110374677A (en) 2019-08-02 2019-08-02 Plateau rich water soft rock tunnel control drainage construction engineering method

Country Status (1)

Country Link
CN (1) CN110374677A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821503A (en) * 2019-11-27 2020-02-21 中铁九局集团第四工程有限公司 Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN110939467A (en) * 2019-12-31 2020-03-31 中铁大桥局集团有限公司 Novel tunnel advanced small conduit, advanced support system and construction method
CN111636436A (en) * 2020-05-25 2020-09-08 中国土木工程集团有限公司 Construction method of foundation pit support
CN114086995A (en) * 2021-11-18 2022-02-25 中铁建大桥工程局集团第六工程有限公司 Rapid water stopping method for grouting of half-sleeve valve pipe of water-rich tunnel
CN115962000A (en) * 2022-12-12 2023-04-14 中铁西北科学研究院有限公司 Sleeve valve type negative pressure moisture absorption system capable of controlling deformation of swelling rock tunnel bottom drum
CN117888956A (en) * 2024-03-15 2024-04-16 集美大学 Plugging device suitable for tunnel water gushing

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100977278B1 (en) * 2009-06-30 2010-08-23 강릉건설 주식회사 The bottom segment and shield tunnel process thereof
CN201908308U (en) * 2010-12-31 2011-07-27 中铁港航工程局有限公司 Grouting sleeve valve pipe
CN202644538U (en) * 2011-12-28 2013-01-02 中铁十九局集团轨道交通工程有限公司 A grouting device used for a water-rich quicksand stratum
CN108643935A (en) * 2018-04-27 2018-10-12 中铁六局集团天津铁路建设有限公司 The construction method in tunnel under rich water shallow embedding geology
CN109750668A (en) * 2017-11-04 2019-05-14 重庆第二师范学院 A kind of reinforcing of rich water boulder bed Deep Foundation Pit bottom mini-valve tube and construction technology

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100977278B1 (en) * 2009-06-30 2010-08-23 강릉건설 주식회사 The bottom segment and shield tunnel process thereof
CN201908308U (en) * 2010-12-31 2011-07-27 中铁港航工程局有限公司 Grouting sleeve valve pipe
CN202644538U (en) * 2011-12-28 2013-01-02 中铁十九局集团轨道交通工程有限公司 A grouting device used for a water-rich quicksand stratum
CN109750668A (en) * 2017-11-04 2019-05-14 重庆第二师范学院 A kind of reinforcing of rich water boulder bed Deep Foundation Pit bottom mini-valve tube and construction technology
CN108643935A (en) * 2018-04-27 2018-10-12 中铁六局集团天津铁路建设有限公司 The construction method in tunnel under rich water shallow embedding geology

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
李孝才: "隧道地表袖阀管注浆施工技术", 《质量探索》 *
梁金平: "富水软弱围岩浅埋隧道下穿建筑物施工关键技术", 《四川建材》 *
陈阳: "基于袖阀管地表注浆加固的超浅埋大断面隧道施工技术", 《建筑技术开发》 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110821503A (en) * 2019-11-27 2020-02-21 中铁九局集团第四工程有限公司 Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN110821503B (en) * 2019-11-27 2021-10-15 中铁九局集团第四工程有限公司 Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN110939467A (en) * 2019-12-31 2020-03-31 中铁大桥局集团有限公司 Novel tunnel advanced small conduit, advanced support system and construction method
CN111636436A (en) * 2020-05-25 2020-09-08 中国土木工程集团有限公司 Construction method of foundation pit support
CN114086995A (en) * 2021-11-18 2022-02-25 中铁建大桥工程局集团第六工程有限公司 Rapid water stopping method for grouting of half-sleeve valve pipe of water-rich tunnel
CN114086995B (en) * 2021-11-18 2023-07-04 中铁建大桥工程局集团第六工程有限公司 Rapid water stopping method for grouting of middle sleeve valve pipe of water-rich tunnel
CN115962000A (en) * 2022-12-12 2023-04-14 中铁西北科学研究院有限公司 Sleeve valve type negative pressure moisture absorption system capable of controlling deformation of swelling rock tunnel bottom drum
CN115962000B (en) * 2022-12-12 2023-09-19 中铁西北科学研究院有限公司 Sleeve valve type negative pressure moisture absorption system capable of controlling deformation of bottom drum of expanded rock tunnel
CN117888956A (en) * 2024-03-15 2024-04-16 集美大学 Plugging device suitable for tunnel water gushing
CN117888956B (en) * 2024-03-15 2024-06-04 集美大学 Plugging device suitable for tunnel water gushing

Similar Documents

Publication Publication Date Title
CN110374677A (en) Plateau rich water soft rock tunnel control drainage construction engineering method
CN101122131B (en) Foundation pit supporting pile using pipe casting pile embedding in rock
CN106837351A (en) Tunnel Karst water detects Treatment Methods
CN110685714B (en) Micro-step reserved core soil construction structure and method for shallow-buried bias tunnel under phyllite geology
CN107975375B (en) A kind of miniature steel pipe pile reinforced soft foundation construction method of city tunnel
CN104790978A (en) Small-clear-distance grade separation tunnel annular guide pit construction method
CN104818712A (en) Construction method of cast-in-situ bored pile suitable for karst cave geology
CN105715296A (en) Blowing sand backfill and grouting construction method of tunnel crossing coal mine goaf
CN112627832B (en) Method for integrating detection, treatment and monitoring operation and maintenance of water inrush and mud inrush of karst tunnel
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN106050277B (en) One kind is soft to mould the body Karst Tunnel reinforcement process that caves in
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN107386274A (en) Wear the compound isolation pile and its reinforced construction method of bridge pier in tunnel side
CN113605410A (en) Landslide reinforcement method
CN108797620A (en) A kind of OPT construction method of interlocking pile
CN103410522A (en) Continuous close-range underpass railway bridge construction method employing shallow tunneling method
CN108457658A (en) A kind of texture stratum tunnel list hole bidirectional construction crosses section constructing method
CN105673025A (en) Underground engineering loess tunnel ground surface settlement control construction process
CN111810198A (en) Tunnel earth surface directional large-caliber deep hole grouting device and grouting method
CN104929146A (en) Multilayer karst development zone pile foundation engineering construction method
CN109577991A (en) A kind of tunnel structure that more tunnels are parallel and its construction method
CN112227401A (en) Method for constructing bearing platform by filling stones in underwater stone abrupt slope area
CN107829747B (en) Construction method suitable for swelled ground area shallow-depth-excavation tunnel
CN111560964B (en) Construction method of rear anti-seepage system of foundation pit
CN107178088B (en) A kind of basement waterproofing foundation pit structure and its construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20191025

RJ01 Rejection of invention patent application after publication