KR100977278B1 - The bottom segment and shield tunnel process thereof - Google Patents

The bottom segment and shield tunnel process thereof Download PDF

Info

Publication number
KR100977278B1
KR100977278B1 KR1020090059196A KR20090059196A KR100977278B1 KR 100977278 B1 KR100977278 B1 KR 100977278B1 KR 1020090059196 A KR1020090059196 A KR 1020090059196A KR 20090059196 A KR20090059196 A KR 20090059196A KR 100977278 B1 KR100977278 B1 KR 100977278B1
Authority
KR
South Korea
Prior art keywords
bottom plate
segment
ground
plate segment
installation
Prior art date
Application number
KR1020090059196A
Other languages
Korean (ko)
Inventor
정성남
정병철
Original Assignee
강릉건설 주식회사
주식회사경도
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 강릉건설 주식회사, 주식회사경도 filed Critical 강릉건설 주식회사
Priority to KR1020090059196A priority Critical patent/KR100977278B1/en
Application granted granted Critical
Publication of KR100977278B1 publication Critical patent/KR100977278B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F13/00Transport specially adapted to underground conditions
    • E21F13/006Equipment transport systems

Abstract

PURPOSE: A bottom plate segment and a shield method using the same are provided to reduce working time by reducing working processes and to improve work efficiency by reducing costs. CONSTITUTION: A shield method using a bottom plate segment is as follows. A segment ring(10) is installed inside a cave using multiple segments(20) and bottom plate segments. Excavated materials and the segments are transferred to the outside or inside the cave. A ground wire(122) is installed in a mounting groove(120) of the segment ring.

Description

저판 세그먼트 및 이를 이용한 쉴드공법{The bottom segment and shield tunnel process thereof}Base plate segment and shield method using the same

본 발명은 저판 세그먼트 및 쉴드공법에 관한 것으로, 더욱 상세하게는 상면이 평평한 저판 세그먼트를 구비하여 종래 이동면 설치를 위한 공정을 생략하고, 세그먼트링 설치 후, 작업자의 이동은 물론, 침목 및 레일을 용이하게 설치할 수 있어 전체적인 작업기간과 비용을 감소시킬 수 있어 작업 효율을 향상시킬 수 있는 저판 세그먼트 및 이를 이용한 쉴드공법에 관한 것이다.The present invention relates to a bottom plate segment and a shielding method, and more particularly to a bottom plate segment having a flat top surface, thus omitting a process for installing a conventional moving surface, and easily moving a sleeper and a rail after the segmenting installation. The present invention relates to a bottom plate segment and a shield method using the same, which can be installed in such a way that the overall work period and cost can be reduced, thereby improving work efficiency.

일반적으로, 쉴드공법은 거대한 초대형 굴착기라고 할 수 있는 쉴드 굴착기를 이용한 최첨단 공법으로 기존의 NATM공법보다 진보된 공법이다.In general, the shield method is a state-of-the-art method using a shield excavator, which can be called a huge super excavator, is an advanced method than the conventional NATM method.

이러한 쉴드공법은 선단에 커터휠을 가진 쉴드 굴착기를 지중에서 굴착하면서 전진하고, 굴착된 굴에는 다수의 세그먼트(Segment)가 결합된 하나의 세그먼트링을 설치하여 터널의 외벽을 구성하게 된다.Such a shielding technique moves forward while digging a shield excavator having a cutter wheel at its tip in the ground, and installs one segment ring in which a plurality of segments are coupled to the excavated cave to form an outer wall of the tunnel.

그리고 다시 쉴드 굴착기에 의해 일정길이 굴착 된 후, 기 설치된 세그먼트링의 단에 새로운 세그먼트링을 설치하는 과정을 반복하여 터널 및 지하구조체를 시공하는 공법이다.After a certain length of excavation by the shield excavator, the tunnel and the underground structure are constructed by repeating the process of installing a new segment ring at the end of the segment ring.

도 1은 종래 쉴드공법을 도시한 도면이고, 도 2는 종래 쉴드공법의 계략적인 순서도를 도시한 도면이며, 도 3은 세그먼트 설치 및 접지지선 설치를 도시한 도면이다.1 is a view showing a conventional shield method, Figure 2 is a view showing a schematic flow chart of the conventional shield method, Figure 3 is a view showing the installation of the segment and ground line installation.

도면에서 도시한 바와 같이, 터널을 형성하고자 하는 위치까지 지면을 수직방향으로 굴착하고, 터널 형성위치에서 수평방향으로 쉴드 굴착기(미 도시)를 이용하여 굴착을 시작하게 된다.As shown in the figure, the ground is excavated in the vertical direction to the position where the tunnel is to be formed, and the excavation is started using a shield excavator (not shown) in the horizontal direction at the tunnel formation position.

쉴드 굴착기가 일정거리를 굴착하게 되면, 기 제조된 다수의 세그먼트(2)를 운반하여 굴착된 부위의 외벽을 형성하도록 관 형상의 세그먼트링(1)으로 조립된다.When the shield excavator excavates a predetermined distance, it is assembled into a tubular segment ring 1 to carry a plurality of prefabricated segments 2 to form an outer wall of the excavated portion.

이 세그먼트링(1)은 터널의 외벽을 형성하는 것으로, 굴착된 부위를 지지함에 따라 지반침하를 방지하는 역할도 하게 된다.The segment ring 1 forms the outer wall of the tunnel, and serves to prevent ground subsidence by supporting the excavated portion.

세그먼트링(1)이 설치되면, 쉴드 굴착기는 다시 일정거리를 굴착하며 전진하고, 굴착된 부위에 새로운 세그먼트링(1)을 설치하는 과정을 반복하게 된다.When the segment ring (1) is installed, the shield excavator moves forward again by digging a predetermined distance, and repeats the process of installing a new segment ring (1) in the excavated portion.

이때, 굴착물과 자재들의 운반 및 작업자의 이동을 위해 보조블럭(3)과 침목(4) 및 레일(5)을 세그먼트링(1)의 내부에 설치하게 된다.At this time, the auxiliary block 3, the sleeper 4 and the rail 5 is installed in the segment ring 1 for the transport of the excavation and materials and the movement of the worker.

이러한 레일(5) 설치, 제거 및 접지지선(6) 설치를 살펴보면, 도 2 내지 도 3에서 도시한 바와 같이, 굴착하면서 세그먼트링(1)을 설치하되, 세그먼트링(1)을 구성하는 각 세그먼트와 자제 및 굴착물을 운반할 수 있는 운반로를 확보해야된다.Looking at the installation and removal of the rail (5) and installation of the grounding ground (6), as shown in Figures 2 to 3, while installing the segment ring (1) while excavating, each segment constituting the segment ring (1) You must ensure that there is a transport route for transporting restraints and excavations.

이 운반로를 확보하기 위해 세그먼트링(1)의 하부에 위치된 세그먼트(2) 상 측에 상면이 평평한 보조블럭(3)을 설치하게 된다.In order to secure this transport path, an auxiliary block 3 having a flat top surface is installed on the segment 2 located below the segment ring 1.

이 보조블럭(3)은 하면이 저면 세그먼트(2)의 상면에 대응되도록 호로 형성되며, 상면에는 침목(4)과 레일(5)을 설치하여 운반로를 확보하게 된다.The auxiliary block 3 is formed in an arc such that the lower surface thereof corresponds to the upper surface of the bottom segment 2, and the sleeper 4 and the rail 5 are installed on the upper surface to secure the transport path.

이와 같은 과정을 반복하여 굴착 및 세그먼트링(1) 설치가 완료되면, 침목(4)과 레일(5) 및 보조블럭(3)을 제거하여 접지지선(6)을 설치하게 된다.When the excavation and segment ring (1) installation is completed by repeating this process, the grounding wire (6) is installed by removing the sleepers (4), the rails (5) and the auxiliary block (3).

이 접지지선(6)은 유공배수관(7)과 함께 거치된 후, 자갈 등으로 채운 잡석층(8)을 형성하게 되고, 잡석층(8)의 상측에는 평평한 콘크리트층(9)을 타설하여 접지지선(6)의 설치를 마무리하게 된다.After the ground wire 6 is mounted together with the perforated drain pipe 7, the rubble layer 8 filled with gravel or the like is formed, and the flat concrete layer 9 is placed on the upper side of the rubble layer 8 to ground. The installation of the branch line 6 is completed.

이때, 지층에 흐르는 물은 유공배수관을 따라 배출되는 것으로, 잡석층(8) 상부에 포함된 물을 용이하게 배출시켜 콘크리트층(9) 타설을 용이하게 할 수 있게 한다.At this time, the water flowing in the ground layer is discharged along the pore drain pipe, it is easy to discharge the water contained in the rubble layer (8) to facilitate the concrete layer (9) pouring.

그리고 콘크리트층(9)의 상면에는 별도의 배수홈이 형성되어 가수의 세그먼트링(1) 사이로 유입되는 물을 용이하게 배출시키게 된다.And a separate drain groove is formed on the upper surface of the concrete layer (9) to easily discharge the water flowing between the segment ring (1) of the mantissa.

타설된 콘크리트층(9)은 이후 터널 추가설치 및 관리 등을 위한 작업자의 이동 및 자재 등의 운반을 위해 사용된다.The poured concrete layer 9 is then used for transport of workers and transportation of materials for further installation and management of the tunnel.

그러나 굴착 및 세그먼트링(1) 설치 시, 별도의 보조블럭(3)을 설치하여 침목(4)과 레일(5)을 설치함은 당연하지만, 접지저선(6) 및 유공배수관(7)을 설치하기 위해 보조블럭(3)을 제거해야되는 공정 및 비용의 손실이 발생되고 있다.However, when installing the excavation and segment ring (1), it is natural to install the sleeper (4) and the rail (5) by installing a separate auxiliary block (3), but the ground bottom (6) and perforated drain pipe (7) In order to eliminate the auxiliary block (3) in order to lose the process and costs are generated.

이러한 과정은 전체 공기를 증가시키는 원인이 되고 있으며, 그에 따른 비용이 더욱 증가하여 작업 효율성을 저하시키는 문제점이 있다.This process is the cause of increasing the total air, the resulting cost is further increased, there is a problem that lowers the work efficiency.

이에 본 발명은 상기와 같은 문제점들을 해소하기 위해 안출된 것으로써, 저판 세그먼트의 하면은 호를 형성하고, 상면은 평평하게 형성하여 터널 외벽을 형성함에 따라 종래 이동면을 형성하는 공정을 생략할 수 있다.Accordingly, the present invention has been made to solve the above problems, the lower surface of the bottom plate segment to form an arc, the upper surface is formed to form a tunnel outer wall can be omitted the process of forming a conventional moving surface. .

그리고 저판 세그먼트의 상면에 배수로를 형성하여 배수 기능을 원활히 할 수 있음은 물론, 침목을 용이하게 설치 및 제거할 수 있고, 내부에 접지지선 설치구를 형성하여 접지지선을 용이하게 설치할 수 있다.In addition, the drainage path may be formed on the upper surface of the bottom plate segment to facilitate the drainage function, as well as to easily install and remove the sleepers, and to form the grounding wire installation hole therein, so that the grounding wire can be easily installed.

이와 같은, 작업 공정의 감소에 따라 전체적인 공정이 감소되어 작업 기간을 단축시킬 수 있고, 비용이 감소시킬 수 있기 때문에 작업 효율성을 향상시킬 수 있는 저판 세그먼트 및 이를 이용한 쉴드공법을 제공하는 것이 목적이다.As a result of the reduction of the work process, the overall process can be reduced to shorten the working period and the cost can be reduced, and therefore, an object of the present invention is to provide a bottom plate segment and a shield method using the same that can improve work efficiency.

상기 목적을 이루기 위한 본 발명은, 다수의 세그먼트를 조립하여 터널 외벽을 형성시키고, 침목과 레일을 설치하여 자재 및 굴착물을 운반하여 터널을 형성시키는 쉴드공법에 있어서, 상기 조립되는 세그먼트링의 저면부를 형성하며, 하면은 다른 세그먼트와 원을 이루도록 호를 형성하고, 상면은 평평하게 형성되되, 일정간격을 갖는 한 쌍의 배수로가 터널 길이방향으로 형성되며, 내부에 접지지선 설치구와 그라우팅공이 형성되고, 상기 상면은 상기 침목과 레일을 설치하여 자재와 굴착물을 운반 및 작업자가 이동할 수 있으며, 상기 터널 외벽 완성 후, 침목과 레일 만을 제거하고, 접지지선을 설치하여 터널을 완공할 수 있다.In order to achieve the above object, the present invention provides a shielding method for assembling a plurality of segments to form a tunnel outer wall, and installing a sleeper and a rail to transport materials and excavations to form a tunnel, the bottom of the assembled segment ring The lower surface is formed to form an arc to form a circle with the other segment, the upper surface is formed flat, a pair of drainage passages having a predetermined interval is formed in the longitudinal direction of the tunnel, and the ground wire installation hole and grouting hole is formed inside The upper surface may be provided with the sleepers and rails to transport materials and excavations, and the worker may move. After completion of the outer wall of the tunnel, only the sleepers and rails may be removed, and a ground ground wire may be installed to complete the tunnel.

바람직하게, 상기 저판 세그먼트는, 상기 배수로가 상면 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 각각 이격되고, 상기 배수로 중 선택된 어느 하나 이상의 저면에 상기 접지지선 설치구가 구비되며, 상기 그라우팅공은 상면과 하면을 관통하도록 통공되되 상기 중심선 상에 위치된다.Preferably, the bottom plate segment is spaced apart at equal intervals based on a center line through which the drainage channel passes through the upper surface center portion, and the grounding wire installation hole is provided on at least one selected bottom surface of the drainage passage, and the grouting hole has a top surface. It penetrates through the lower surface and is located on the center line.

그리고 상기 접지지선 설치구에는 자갈과 접지지선을 설치 후, 밀폐시켜 상기 배수로와 구획시킨다.In addition, after the gravel and the ground wire is installed in the ground wire installation port, it is sealed and partitioned from the drainage path.

또한, 상기 저판 세그먼트는, 상기 배수로가 상면 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 각각 이격되고, 상기 그라우팅공은 상면과 하면을 관통하도록 통공되되 상기 중심선 상에 위치되며, 상기 접지지선 설치구는 상기 그라우팅공과 연통되도록 상기 중심선과 평행하게 통공된다.In addition, the bottom plate segment is spaced apart at equal intervals, respectively, with respect to the center line passing through the center of the upper surface, the grouting hole is perforated to pass through the upper surface and the lower surface is located on the center line, the earthing ground installation device It is perforated in parallel with the center line to communicate with the grouting hole.

그리고 상기 침목의 저면 양단부에는 설치턱이 각각 형성되고, 상기 각 설치턱은 저판 세그먼트의 각 배수로 측면 중 외측에 위치된 측면에 닿아 끼워진다.In addition, mounting jaws are formed at both ends of the bottom surface of the sleeper, and each of the mounting jaws touches a side located on the outer side of each side of the drainage segment of the bottom plate segment.

또한, 상기 저판 세그먼트는 프리캐스트 방식으로 제작되며, 형성하고자 하는 터널의 크기에 따라 사전에 제작된다.In addition, the bottom plate segment is manufactured in a precast manner, and is manufactured in advance according to the size of the tunnel to be formed.

그리고 다수의 세그먼트를 조립하여 터널 외벽을 형성시키고, 침목과 레일을 설치하여 자재 및 굴착물을 운반하여 터널을 형성시키는 쉴드공법에 있어서, 하면은 다른 세그먼트와 원을 이루도록 호를 형성하고, 상면은 평평하게 형성되며, 상기 상면에 일정간격을 갖는 한 쌍의 배수로가 터널 길이방향으로 형성되고, 내부에 접지지선 설치구와 그라우팅공이 통공된 저판 세그먼트가 상기 조립되는 세그먼트링의 저면을 형성하는 세그먼트 설치단계, 상기 저판 세그먼트의 상면에 침목과 레일을 설치하며, 상기 설치된 레일을 이용하여 굴착물과 각 세그먼트 및 자재를 굴 외부 또는 내부로 운반하고, 설치하는 굴착물과 자재 운반 및 설치단계, 및 상기 굴착물과 자재의 운반과 설치가 끝난 후, 상기 저판 세그먼트에 설치된 레일 및 침목을 제거하고, 상기 접지지선 설치구에 접지지선을 설치하는 접지지선 설치단계를 포함하여 이루어진다.In the shield method of assembling a plurality of segments to form a tunnel outer wall, and installing sleepers and rails to transport materials and excavations to form a tunnel, the lower surface forms an arc to form a circle with another segment, and the upper surface is Segment installation step of forming a flat bottom, a pair of drainage passages having a predetermined interval on the upper surface in the longitudinal direction of the tunnel, and the bottom plate segment through which the grounding wire installation hole and the grouting hole are formed to form the bottom surface of the segmenting to be assembled And installing a sleeper and a rail on an upper surface of the bottom plate segment, and carrying and installing the excavated material and the respective segments and materials to the outside or the inside of the oyster using the installed rail, and installing and transporting the material and the excavated material. After the transportation and installation of water and materials, the rails and sleepers installed on the bottom plate segment are removed. It includes the grounding ground installation step of installing the grounding ground wire in the existing ground ground installation hole.

또한, 상기 저판 세그먼트의 배수로가 상면 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 이격되고, 상기 배수로 중 선택된 어느 하나 이상의 저면 하측에 상기 접지지선 설치구가 구비되며, 상기 그라우팅공은 상면과 하면을 관통하도록 통공되되 상기 중심선 상에 위치되고, 상기 접지선 설치단계는, 상기 침목 및 레일을 제거 후, 접지지선 설치구에 접지지선을 거치시키는 접지지선 거치단계, 상기 접지지선이 외측에서 보이지 않도록 상기 접지지선 설치구에 자갈을 채워 자갈층을 형성하는 충진단계, 및 상기 자갈층 상측을 콘크리트 타설하여 상기 배수로와 구획은 물론, 배수로의 저면을 형성시키는 밀폐단계를 포함하여 이루어진다.Further, the drainage passages of the bottom plate segment are spaced at equal intervals based on the centerline passing through the upper center portion, and the grounding wire installation hole is provided below the bottom of any one or more selected ones of the drainage passages, and the grouting hole has an upper surface and a lower surface. Perforated to penetrate through and positioned on the center line, the ground line installation step, after removing the sleeper and the rails, the ground line mounting step for mounting the ground line to the ground line installation port, the ground so that the ground line is not visible from the outside Filling step to form a gravel layer by filling the gravel layer in the branch line installation, and a concrete sealing the step of forming the bottom surface of the drainage passages, as well as the drainage passages by the concrete pouring the upper side of the gravel layer.

그리고 상기 저판 세그먼트의 배수로가 상면 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 이격되고, 상기 그라우팅공은 상면과 하면을 관통하도록 통공되되 상기 중심선 상에 위치되며, 상기 접지지선 설치구는 상기 그라우팅공과 연통되도록 상기 중심선과 평행하게 통공되고, 상기 접지선 설치단계는, 상기 접지지선의 일단에 리드선을 연결하고, 리드선을 상기 접지지선 설치구로 삽입하는 리드선 삽입단계, 상기 리드선을 통과시켜 상기 접지지선 설치구에 접지지선을 거치시 키는 접지지선 거치단계, 및 상기 접지지선이 거치된 접지지선 설치구와 그라우팅공을 밀폐시키는 밀폐단계를 포함하여 이루어진다.And the drainage passage of the bottom plate segment is spaced at equal intervals, based on the center line passing through the upper surface center portion, the grouting hole is penetrated through the upper surface and the lower surface is located on the center line, the ground wire installation port is in communication with the grouting hole Perforated parallel to the center line so as to, the ground wire installation step, the lead wire insertion step of connecting a lead wire to one end of the ground ground wire, and inserting the lead wire into the ground ground wire installation port, through the lead wire through the ground wire installation hole It includes a grounding wire mounting step for passing through the grounding ground, and a sealing step for sealing the grounding ground installation hole and the grouting hole is mounted on the grounding ground.

또한, 상기 저판 세그먼트는 프리캐스트 방식으로 제작되며, 형성하고자 하는 터널의 크기에 따라 사전에 제작된다.In addition, the bottom plate segment is manufactured in a precast manner, and is manufactured in advance according to the size of the tunnel to be formed.

그리고 상기 굴착물과 자재 운반 및 설치단계에서, 상기 침목의 저면 양단부에는 설치턱이 각각 형성되고, 상기 각 설치턱은 저판 세그먼트의 각 배수로 측면 중 외측에 위치된 측면에 닿아 끼워진다.And in the excavation and material transport and installation step, the mounting jaw is formed on both ends of the bottom surface of the sleeper, each mounting jaw is fitted in contact with the side located on the outer side of each side of the bottom plate segment.

상기한 바와 같이, 본 발명에 의한 저판 세그먼트 및 이를 이용한 쉴드공법에 의하면, 상면이 평평하게 형성되어 설치 후, 작업자가 이동하거나 자재 등을 용이하게 운반시키도록 침목과 레일을 용이하게 설치 및 제거할 수 있다.As described above, according to the bottom plate segment and the shield method using the same according to the present invention, the upper surface is formed to be flat, after installation, to easily install and remove the sleepers and rails so that the operator can move or easily transport the material, etc. Can be.

특히, 종래 하부 세그먼트의 상측을 쇄석으로 채우고 콘크리트로 이동면을 형성시키는 공정이 생략되어 작업 공정을 단축시킬 수 있다.In particular, the process of filling the upper side of the conventional lower segment with crushed stone and forming a moving surface with concrete can be omitted, thereby reducing the work process.

그리고 각 저판 세그먼트에 형성된 접지지선 설치구를 통해 접지지선을 용이하게 설치할 수 있고, 배수로에 침목을 용이하게 설치 및 해체할 수 있어 작업 시간을 단축시킬 수 있다.In addition, through the grounding wire installation hole formed in each bottom plate segment, the grounding ground wire can be easily installed, and the sleeper can be easily installed and dismantled in the drainage path, thereby reducing the work time.

이에 따라, 전체적인 작업 공기를 단축시킬 수 있고, 공기 단축에 의한 비용을 감소시킬 수 있어 작업 효율성을 향상시킬 수 있게 하는 매우 유용하고 효과적인 발명이다.Accordingly, it is a very useful and effective invention that can shorten the overall working air, and can reduce the cost by shortening the air, thereby improving the working efficiency.

이하, 본 발명의 바람직한 실시 예를 첨부된 도면을 참조하여 설명한다.Hereinafter, preferred embodiments of the present invention will be described with reference to the accompanying drawings.

또한, 본 실시 예는 본 발명의 권리범위를 한정하는 것은 아니고 단지 예시로 제시된 것이며, 그 기술적 요지를 이탈하지 않는 범위 내에서 다양한 변경이 가능하다.In addition, the present embodiment is not intended to limit the scope of the present invention, but is presented by way of example only, and various modifications may be made without departing from the technical gist of the present invention.

도 4는 본 발명에 따른 저판 세그먼트의 설치상태를 도시한 도면이고, 도 5는 본 발명에 따른 저판 세그먼트를 이용한 쉴드공법의 계략적 순서도를 도시한 도면이며, 도 6은 도 5의 순서도에 따른 작업공정을 도시한 도면이고, 도 7은 본 발명에 따른 저판 세그먼트를 도시한 도면이며, 도 8은 본 발명에 따른 저판 세그먼트에 접지지선 설치방법을 계략적으로 도시한 순서도이고, 도 9는 도 8의 순서도에 따른 접지지선 설치를 도시한 도면이며, 도 10은 본 발명에 따른 저판 세그먼트의 다른 실시 예를 도시한 도면이고, 도 11은 도 10의 저판 세그먼트에 접지지선 설치방법을 계략적으로 도시한 순서도이며, 도 12는 도 11의 순서에 따라 저판 세그먼트에 접지지선 설치 상태를 도시한 도면이고, 도 13은 본 발명에 따른 저판 세그먼트에 침목 및 레일의 설치를 도시한 도면이다.4 is a view showing the installation state of the bottom plate segment according to the present invention, Figure 5 is a view showing a schematic flow chart of the shield method using the bottom plate segment according to the present invention, Figure 6 according to the flow chart of FIG. 7 is a view showing a working process, Figure 7 is a view showing a bottom plate segment according to the present invention, Figure 8 is a flow chart schematically showing a method of installing a ground wire to the bottom plate segment according to the present invention, Figure 9 is a view 8 is a view showing the grounding ground installation according to the flow chart of Figure 8, Figure 10 is a view showing another embodiment of the bottom plate segment in accordance with the present invention, Figure 11 FIG. 12 is a view illustrating a grounding ground installation state in the bottom plate segment in the order of FIG. 11, and FIG. 13 illustrates the installation of sleepers and rails in the bottom plate segment according to the present invention. It is time limit drawing.

도면에서 도시한 바와 같이, 저판 세그먼트(100)는 하면(102)이 다른 세그먼트(20)와 원을 이루도록 호를 형성하고, 상면(104)은 평평하게 형성되되, 일정간격을 갖는 한 쌍의 배수로(110)가 터널 길이방향으로 형성된다.As shown in the figure, the bottom plate segment 100 forms an arc such that the lower surface 102 forms a circle with the other segment 20, and the upper surface 104 is formed flat, with a pair of drainages having a predetermined interval. 110 is formed in the tunnel longitudinal direction.

그리고 저판 세그먼트(100)의 내부에 접지지선 설치구(120)와 그라우트 공(130)이 형성되어 조립되는 세그먼트링(10)의 저면부를 형성하며, 상면은 침목(200)과 레일(210)을 선택적으로 설치하여 자재와 굴착물을 운반 및 작업자가 이동할 수 있게 된다.In addition, the ground branch installation unit 120 and the grout ball 130 are formed inside the bottom plate segment 100 to form a bottom portion of the segment ring 10 to be assembled, and the upper surface of the sleeper 200 and the rail 210. Optionally installed, the material and excavation can be transported and moved by workers.

이러한 저판 세그먼트(100)를 이용한 쉴드공법을 살펴보면, 도 5 내지 도 6에서 도시한 바와 같이, 세그먼트 설치단계(S10)와 굴착물과 자재 운반 및 설치단계(S20) 및 접지지선 설치단계(S30)로 구성된다.Looking at the shield method using the bottom plate segment 100, as shown in Figure 5 to Figure 6, the segment installation step (S10) and the excavation and material transport and installation step (S20) and ground wire installation step (S30) It consists of.

먼저, 수직방향으로 지면을 굴착하거나 수평방향으로 굴착하는 단계는 종래의 방법과 동일하며, 세그먼트 설치단계(S10) 전에 이루어진다.First, the step of excavating the ground in the vertical direction or the excavation in the horizontal direction is the same as the conventional method, it is made before the segment installation step (S10).

세그먼트 설치단계(S10)에서는 다수의 세그먼트(20)와 저판 세그먼트(100)를 이용하여 굴 내부에 세그먼트링(10)을 설치하게 된다.In the segment installation step (S10), the segment ring 10 is installed inside the oyster using the plurality of segments 20 and the bottom plate segment 100.

이때, 저판 세그먼트(100)는 하면(102)이 다른 세그먼트(20)와 원을 이루도록 호를 형성하고, 상면(104)은 평평하게 형성되되, 일정간격을 갖는 한 쌍의 배수로(110)가 터널 길이방향으로 형성되며, 그 내부에 접지지선 설치구(120)와 그라우트공(130)이 형성된다.In this case, the bottom plate segment 100 forms an arc so that the lower surface 102 forms a circle with the other segment 20, and the upper surface 104 is formed flat, and a pair of drainage paths 110 having a predetermined interval are tunneled. It is formed in the longitudinal direction, the ground wire installation hole 120 and the grout hole 130 is formed therein.

그리고 굴착물과 자재 운반 및 설치단계(S20)는 굴착물과 각 세그먼트(20, 100) 및 자재를 굴 외부 또는 내부로 운반 및 설치하는 것으로, 저판 세그먼트(100)의 상면(104)에 침목(200)과 레일(210)을 설치하고, 이 레일(210)을 이용하여 굴착물과 자재 등을 운반 및 설치하게 된다.And the excavation and material transport and installation step (S20) is to transport and install the excavation and each segment (20, 100) and material to the outside or inside of the oyster, the sleeper (top) on the top surface 104 of the bottom plate segment (100) 200 and the rail 210 are installed, and the rail 210 is used to transport and install the excavated material and the like.

접지지선 설치단계(S30)는 각 세그먼트링(10)의 접지지선 설치구(120)에 접지지선(122)을 설치하는 것으로, 저판 세그먼트(100)에 설치된 레일(210) 및 침 목(200)을 제거하고, 접지지선 설치구(120)에 접지지선(122)을 설치하게 된다.Grounding ground installation step (S30) is to install the grounding ground wire 122 in the grounding ground installation hole 120 of each segment ring 10, the rail 210 and sleeper 200 installed in the bottom plate segment 100 Then, the ground ground wire 122 is installed in the ground ground installation hole 120.

상기와 같은, 접지지선 설치단계(S30)를 저 자세히 살펴보면, 도 7 내지 도 9에 도시한 바와 같다.Looking at the ground line installation step (S30) as described above in detail, as shown in Figs.

먼저, 도 7에 도시된 바와 같이, 저판 세그먼트(100)는 하면(102)이 다른 세그먼트(20)와 원을 이루도록 호를 형성하고, 상면(104)은 평평하게 형성되되, 일정간격을 갖는 한 쌍의 배수로(110)가 터널 길이방향으로 형성된다.First, as shown in FIG. 7, the bottom plate segment 100 forms an arc such that the bottom surface 102 forms a circle with another segment 20, and the top surface 104 is formed flat, but has a predetermined interval. A pair of drainage paths 110 are formed in the tunnel longitudinal direction.

그리고 저판 세그먼트(100)의 내부에 접지지선 설치구(120)와 그라우트공(130)이 형성되어 조립되는 세그먼트링(10)의 저면부를 형성하며, 상면은 침목(200)과 레일(210)을 설치하여 자재와 굴착물을 운반 및 작업자가 이동할 수 있게 된다.In addition, the grounding wire installation hole 120 and the grout hole 130 are formed inside the bottom plate segment 100 to form a bottom portion of the segment ring 10 to be assembled, and the upper surface of the sleeper 200 and the rail 210. The installation allows materials and excavations to be transported and moved by workers.

이때, 배수로(110)는 저판 세그먼트(100) 상면(104) 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 각각 이격되고, 배수로(110) 중 선택된 어느 하나 이상의 저면에 접지지선 설치구(120)가 구비되며, 그라우팅공(130)은 상면(104)과 하면(102)을 관통하도록 통공되되 중심선 상에 위치된다.At this time, the drainage path 110 is spaced apart at equal intervals with respect to the center line passing through the central portion of the upper surface 104 of the bottom plate segment 100, and the grounding wire installation hole 120 is formed on any one or more selected bottoms of the drainage path 110. The grouting hole 130 is provided to be penetrated through the upper surface 104 and the lower surface 102 and is positioned on the center line.

이러한 저판 세그먼트(100)에 접지지선 설치단계(S30)는 도 8 내지 도 9에 도시한 바와 같이, 접지지선 거치단계(S31)와 충진단계(S32) 및 밀폐단계(S33)로 구성된다.As shown in FIGS. 8 to 9, the ground branch installation step S30 in the bottom plate segment 100 includes a ground branch mounting step S31, a filling step S32, and a sealing step S33.

접지지선 거치단계(S31)는 저판 세그먼트(100)의 접지지선 설치구(120)에 접지지선(122)을 거치시키는 것으로, 저판 세그먼트(100)의 상면(104)에서 침목(200) 및 레일(210)을 제거한 상태에서 접지지선(122)을 거치시키게 된다.Grounding ground mounting step (S31) is to mount the grounding ground 122 to the grounding ground installation hole 120 of the bottom plate segment 100, the sleeper 200 and the rail (200) on the upper surface 104 of the bottom plate segment 100 The ground branch 122 is mounted in a state in which 210 is removed.

그리고 충전단계(S32)는 거치된 접지지선(122)이 배수로(110)를 통해 외측에서 보이지 않도록 접지지선 설치구(120)에 자갈을 채워 자갈층(124)을 형성하게 된다.And filling step (S32) fills the gravel layer 124 by filling the gravel in the ground line installation port 120 so that the mounted ground line 122 is not visible from the outside through the drainage path (110).

밀폐단계(S33)는 자갈층(124)의 상측을 콘크리트 타설하여 콘크리트층(126)을 형성시키는 것으로, 접지지선 설치구(120)를 배수로(110)와 구획은 물론, 배수로의 저면을 형성시키게 된다.The sealing step (S33) is to form the concrete layer 126 by placing the upper side of the gravel layer 124 to form a concrete ground duct 120, as well as the drainage passage 110 and the partition, and to form the bottom surface of the drainage passage. .

이와 같은 접지지선 설치단계(S30)를 거친 상태는 도 4에서 도시한 바와 같다.The state passed through such a ground wire installation step (S30) is as shown in FIG.

한편, 도 10 내지 도 12에서 도시한 바와 같이, 다른 실시 예의 저판 세그먼트(100')와 이를 이용한 쉴드공법을 도시하였다.Meanwhile, as shown in FIGS. 10 to 12, the bottom plate segment 100 ′ of another embodiment and a shield method using the same are illustrated.

다른 실시 예의 저판 세그먼트(100')는 도 10에 도시한 바와 같이, 하면(102')이 다른 세그먼트(20)와 원을 이루도록 호를 형성하고, 상면(104')은 평평하게 형성되되, 일정간격을 갖는 한 쌍의 배수로(110')가 터널 길이방향으로 형성된다.As shown in FIG. 10, the bottom plate segment 100 ′ may form an arc such that the bottom surface 102 ′ forms a circle with another segment 20, and the top surface 104 ′ may be formed flat. A pair of drainage paths 110 'with a spacing is formed in the tunnel longitudinal direction.

그리고 저판 세그먼트(100')의 내부에 접지지선 설치구(120')와 그라우트공(130')이 형성되어 조립되는 세그먼트링(10)의 저면부를 형성하며, 상면은 침목(200)과 레일(210)을 설치하여 자재와 굴착물을 운반 및 작업자가 이동할 수 있게 된다.In addition, the grounding wire installation hole 120 'and the grout hole 130' are formed inside the bottom plate segment 100 'to form a bottom portion of the segment ring 10, and the upper surface of the sleeper 200 and the rail ( By installing 210, the material and the excavation can be transported and moved by the worker.

이때, 배수로(110')는 저판 세그먼트(100') 상면(104') 중앙부를 지나는 중 심선을 기준으로, 동일한 간격으로 각각 이격되고, 그라우팅공(130')은 상면(104')과 하면(102')을 관통하도록 통공되되 상기 중심선 상에 위치된다.At this time, the drainage path 110 'is spaced apart at equal intervals from the center line passing through the center portion of the upper surface 104' of the bottom plate segment 100 ', and the grouting holes 130' are spaced apart from the upper surface 104 '( 102 ') and is located on the centerline.

그리고 접지지선 설치구(120')는 그라우팅공(130')과 연통되도록 저판 세그먼트(100') 내부에 중심선과 평행하게 통공된다.In addition, the grounding wire installation hole 120 ′ is formed to communicate with the grouting hole 130 ′ in parallel with the center line in the bottom plate segment 100 ′.

이러한 저판 세그먼트(100')에 접지지선 설치단계(S30')는 도 11에 도시한 바와 같이, 리더선 삽입단계(S31')와 접지지선 거치단계(S32') 및 밀폐단계(S33')로 구성된다.As shown in FIG. 11, the ground lead installation step S30 'is installed in the bottom plate segment 100' as the leader line insertion step S31 ', the ground lead mounting step S32', and the sealing step S33 '. It is composed.

리더선 삽입단계(S31')는 접지지선 설치구(120')에 리드선(124')을 거치 및 통과시키는 것으로, 접지지선(122')의 일단에 리드선(124')을 연결하고, 리드선(124')을 접지지선 설치구(120')로 삽입하게 된다.The leader line inserting step (S31 ') allows the lead wire 124' to pass through and pass through the ground lead wire installation hole 120 '. The lead wire 124' is connected to one end of the ground lead wire 122 ', and the lead wire ( 124 'is inserted into the ground wire installation hole 120'.

그리고 접지지선 거치단계(S32')는 접지지선(122')을 접지지선 설치구(120')에 거치시키는 것으로, 접지지선 설치구(120')에 거치된 리드선(124')을 통과시켜 접지지선 설치구(120')에 접지지선(122')을 거치시킨 후, 리드선(124')을 제거하게 된다.In addition, the ground lead mounting step (S32 ') is to mount the ground lead 122' to the ground lead installation 120 ', and passes through the lead wire 124' mounted on the ground lead installation 120 ' The ground wire 122 'is mounted on the branch wire installation hole 120', and then the lead wire 124 'is removed.

밀폐단계(S33')는 접지지선(122')이 거치된 접지지선 설치구(120') 및 그라우팅공(130')을 밀폐시키는 것으로, 접지지선 설치구(120') 및 그라우팅공(130')에 밀폐층(126')을 형성하여 물이 유입되는 것을 방지하게 된다.Sealing step (S33 ') is to seal the grounding ground installation hole 120' and the grouting hole 130 'is mounted, the grounding ground installation hole 120' and grouting hole 130 ' ) To form a sealing layer 126 ′ to prevent water from entering.

이러한 접지지선 설치단계(S30')에 의한 접지지선(122') 설치 상태는 도 12에서 도시한 바와 같다.The ground ground 122 'installation state by the ground ground installation step S30' is as shown in FIG.

한편, 도 13에서 도시한 바와 같이, 저판 세그먼트(100)에 침목(200)과 레일(210)을 설치를 살펴보면, 침목(200)의 저면 양단부에는 설치턱(202)이 각각 형성된다.On the other hand, as shown in Figure 13, look at the installation of the sleeper 200 and the rail 210 to the bottom plate segment 100, the mounting jaw 202 is formed on both ends of the bottom surface of the sleeper 200, respectively.

이 침목(200)의 각 설치턱(202)은 저판 세그먼트(100)의 각 배수로(110)에 끼워지는 것으로, 각 배수로(110)의 측면 중 외측에 위치된 측면에 닿아 끼워짐에 따라 침목(200)이 저판 세그먼트(100)에 고정된다.Each mounting jaw 202 of the sleeper 200 is fitted to each of the drainage passages 110 of the bottom plate segment 100, the sleeper ( 200 is fixed to the bottom plate segment 100.

이는, 침목을 고정시키기 위한 종래 별도의 고정부재 사용을 생략함에 따라 공정을 생략할 수 있어 작업시간과 비용을 감소시킬 수 있는 것이다.This can omit a process by omitting the use of a separate fixing member for fixing the sleeper, thereby reducing work time and cost.

또한, 침목(200)을 저판 세그먼트(100)에 용이하게 탈부착시킬 수 있어 쉴드 터널 형성 후, 침목(200)과 레일(210)을 간편하게 설치 및 제거는 물론, 작업 시간 및 비용을 감소시킬 수 있다.In addition, the sleeper 200 can be easily attached and detached to the bottom plate segment 100, so that after the shield tunnel is formed, the sleeper 200 and the rail 210 can be easily installed and removed, as well as reducing work time and cost. .

이와 같은 침목(200)은 다른 실시 예의 저판 세그먼트(100')에서도 적용됨이 당연하다.Naturally, the sleeper 200 is also applicable to the bottom plate segment 100 ′ of another embodiment.

또한, 저판 세그먼트(100, 100')는 프리캐스트 방식으로 형성하고자 하는 터널의 크기에 따라 사전에 제작되어 현장으로 운반되는 것으로, 작업 공정을 단축시키게 된다.In addition, the bottom plate segments 100 and 100 ′ are prefabricated and transported to the site according to the size of the tunnel to be formed by the precast method, thereby shortening the work process.

도 1은 종래 쉴드공법을 도시한 도면이고,1 is a view showing a conventional shield method,

도 2는 종래 쉴드공법의 계략적인 순서도를 도시한 도면이며,2 is a view showing a schematic flowchart of a conventional shield method,

도 3은 세그먼트 설치 및 접지지선 설치를 도시한 도면이고,3 is a diagram showing the installation of the segment and ground wire installation,

도 4는 본 발명에 따른 저판 세그먼트의 설치상태를 도시한 도면이며,4 is a view showing an installation state of the bottom plate segment according to the present invention,

도 5는 본 발명에 따른 저판 세그먼트를 이용한 쉴드공법의 계략적 순서도를 도시한 도면이고,5 is a schematic flowchart of a shield method using a bottom plate segment according to the present invention;

도 6은 도 5의 순서도에 따른 작업공정을 도시한 도면이며,6 is a view showing a work process according to the flow chart of FIG.

도 7은 본 발명에 따른 저판 세그먼트를 도시한 도면이고,7 is a view showing a bottom plate segment according to the present invention,

도 8은 본 발명에 따른 저판 세그먼트에 접지지선 설치방법을 계략적으로 도시한 순서도이며,8 is a flowchart schematically showing a method for installing grounding conductors in a bottom plate segment according to the present invention.

도 9는 도 8의 순서도에 따른 접지지선 설치를 도시한 도면이고,9 is a view showing the grounding ground installation according to the flow chart of FIG.

도 10은 본 발명에 따른 저판 세그먼트의 다른 실시 예를 도시한 도면이며,10 is a view showing another embodiment of a bottom plate segment according to the present invention,

도 11은 도 10의 저판 세그먼트에 접지지선 설치방법을 계략적으로 도시한 순서도이고,FIG. 11 is a flowchart schematically illustrating a method for installing grounding lines in a bottom plate segment of FIG. 10.

도 12는 도 11의 순서에 따라 저판 세그먼트에 접지지선 설치 상태를 도시한 도면이며,FIG. 12 is a view illustrating a ground line installation state in a bottom plate segment in the order of FIG. 11;

도 13은 본 발명에 따른 저판 세그먼트에 침목 및 레일의 설치를 도시한 도면이다.13 is a view showing the installation of sleepers and rails in the bottom plate segment according to the present invention.

< 도면의 주요 부분에 대한 부호의 설명 ><Description of Symbols for Main Parts of Drawings>

10 : 세그먼트 100, 100' : 저판 세그먼트10: segment 100, 100 ': bottom plate segment

102, 102' : 하면 104, 104' : 상면102, 102 ': Bottom surface 104, 104': Top surface

110, 110' : 배수로 120, 120' : 접지지선 설치구110, 110 ': Drainage 120, 120': Grounding earth installation

122, 122' : 접지지선 124 : 자갈층122, 122 ': ground wire 124: gravel layer

126 : 콘크리트층 124' : 리더선126: concrete layer 124 ': leader line

126' : 밀폐층 130, 130' : 그라우팅공126 ': sealing layer 130, 130': grouting ball

Claims (11)

터널을 형성시키기 위한 쉴드공법에 사용되며, 자재 및 굴착물을 운반할 수 있도록 침목과 레일을 설치하기 위해 구비되는 다수의 세그먼트를 갖는 세그먼트링에 있어서,In the shielding method for forming a tunnel, in the segmenting having a plurality of segments provided for installing sleepers and rails to transport materials and excavations, 다수의 세그먼트가 조립된 세그먼트링의 저면부를 형성하며, 하면은 다른 세그먼트와 원을 이루도록 호를 형성하고, 상면은 평평하게 형성되되, 일정간격을 갖는 한 쌍의 배수로가 터널 길이방향으로 형성되며, 내부에 접지지선 설치구와 그라우팅공이 형성되고,A plurality of segments form a bottom portion of the assembled segment ring, the lower surface is formed arc to form a circle with the other segment, the upper surface is formed flat, a pair of drainage channels having a predetermined interval is formed in the tunnel longitudinal direction, Grounding wire installation hole and grouting hole is formed inside, 상기 상면은 상기 침목과 레일을 설치하여 자재와 굴착물을 운반 및 작업자가 이동할 수 있으며, 상기 터널 외벽 완성 후, 침목과 레일 만을 제거하고, 접지지선을 설치하여 터널을 완공할 수 있으며,The upper surface is to install the sleepers and rails to transport materials and excavations and workers can move, and after completion of the tunnel outer wall, only the sleepers and rails can be removed, and the ground ground wire can be installed to complete the tunnel, 상기 세그먼트의 저면부에 형성되는 저판 세그먼트는,The bottom plate segment formed in the bottom portion of the segment, 상기 배수로가 상면 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 각각 이격되고, 상기 배수로 중 선택된 어느 하나 이상의 저면에 상기 접지지선 설치구가 구비되며, 상기 그라우팅공은 상면과 하면을 관통하도록 통공되되 상기 중심선 상에 위치되고, 상기 접지지선 설치구에는 자갈과 접지지선을 설치 후, 밀폐시켜 상기 배수로와 구획시키는 것을 특징으로 하는 저판 세그먼트.The drainage passages are spaced apart at equal intervals, respectively, based on the centerline passing through the upper surface center portion, and the grounding branch installation hole is provided on at least one selected bottom surface of the drainage passage, and the grouting hole is perforated to penetrate the upper and lower surfaces of the drainage passage. Located on the center line, after installing the gravel and ground line in the ground line installation port, the bottom plate segment characterized in that it is partitioned from the drainage. 삭제delete 삭제delete 터널을 형성시키기 위한 쉴드공법에 사용되며, 자재 및 굴착물을 운반할 수 있도록 침목과 레일을 설치하기 위해 구비되는 다수의 세그먼트를 갖는 세그먼트링에 있어서,In the shielding method for forming a tunnel, in the segmenting having a plurality of segments provided for installing sleepers and rails to transport materials and excavations, 다수의 세그먼트가 조립된 세그먼트링의 저면부를 형성하며, 하면은 다른 세그먼트와 원을 이루도록 호를 형성하고, 상면은 평평하게 형성되되, 일정간격을 갖는 한 쌍의 배수로가 터널 길이방향으로 형성되며, 내부에 접지지선 설치구와 그라우팅공이 형성되고,A plurality of segments form a bottom portion of the assembled segment ring, the lower surface is formed arc to form a circle with the other segment, the upper surface is formed flat, a pair of drainage channels having a predetermined interval is formed in the tunnel longitudinal direction, Grounding wire installation hole and grouting hole is formed inside, 상기 상면은 상기 침목과 레일을 설치하여 자재와 굴착물을 운반 및 작업자가 이동할 수 있으며, 상기 터널 외벽 완성 후, 침목과 레일 만을 제거하고, 접지지선을 설치하여 터널을 완공할 수 있으며,The upper surface is to install the sleepers and rails to transport materials and excavations and workers can move, and after completion of the tunnel outer wall, only the sleepers and rails can be removed, and the ground ground wire can be installed to complete the tunnel, 상기 세그먼트의 저면부에 형성되는 저판 세그먼트는,The bottom plate segment formed in the bottom portion of the segment, 상기 배수로가 상면 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 각각 이격되고, 상기 그라우팅공은 상면과 하면을 관통하도록 통공되되 상기 중심선 상에 위치되며, 상기 접지지선 설치구는 상기 그라우팅공과 연통되도록 상기 중심선과 평행하게 통공되는 것을 특징으로 하는 저판 세그먼트.The drainage passages are spaced apart at equal intervals, respectively, based on the center line passing through the upper surface center portion, and the grouting holes are penetrated through the upper surface and the lower surface, and are positioned on the center line, and the ground line installation tool is in communication with the grouting hole. A bottom plate segment characterized in that it is perforated in parallel with the. 제1항 또는 제4항에 있어서,The method according to claim 1 or 4, 상기 침목의 저면 양단부에는 설치턱이 각각 형성되고, 상기 각 설치턱은 저판 세그먼트의 각 배수로 측면 중 외측에 위치된 측면에 닿아 끼워지는 것을 특징으로 하는 저판 세그먼트.Mounting jaw is formed on both ends of the bottom surface of the sleeper, each mounting jaw is characterized in that the bottom plate segment is inserted in contact with the side located on the outer side of each side of the drainage segment of the bottom plate segment. 제1항 또는 제4항에 있어서,The method according to claim 1 or 4, 상기 저판 세그먼트는 프리캐스트 방식으로 제작되며, 형성하고자 하는 터널의 크기에 따라 사전에 제작되는 것을 특징으로 하는 저판 세그먼트.The bottom plate segment is manufactured in a precast manner, the bottom plate segment characterized in that it is manufactured in advance according to the size of the tunnel to be formed. 다수의 세그먼트를 조립하여 터널 외벽을 형성시키고, 침목과 레일을 설치하여 자재 및 굴착물을 운반하여 터널을 형성시키는 쉴드공법에 있어서,In the shield method of assembling a plurality of segments to form a tunnel outer wall, and install a sleeper and a rail to transport materials and excavation to form a tunnel, 하면은 다른 세그먼트와 원을 이루도록 호를 형성하고, 상면은 평평하게 형성되며, 상기 상면에 일정간격을 갖는 한 쌍의 배수로가 터널 길이방향으로 형성되고, 내부에 접지지선 설치구와 그라우팅공이 통공된 저판 세그먼트가 상기 조립되는 세그먼트링의 저면을 형성하는 세그먼트 설치단계;The lower surface forms an arc to form a circle with another segment, the upper surface is formed flat, a pair of drainage channels having a predetermined interval on the upper surface is formed in the longitudinal direction of the tunnel, the ground plate installation hole and the grouting hole through the bottom plate A segment installation step of forming segments at the bottom of the assembled segment ring; 상기 저판 세그먼트의 상면에 침목과 레일을 설치하며, 상기 설치된 레일을 이용하여 굴착물과 각 세그먼트 및 자재를 굴 외부 또는 내부로 운반하고, 설치하는 굴착물과 자재 운반 및 설치단계; 및Installing a sleeper and a rail on an upper surface of the bottom plate segment, and carrying and installing the excavated material and each segment and material to the outside or the inside of the oyster using the installed rail, and installing and transporting the material; And 상기 굴착물과 자재의 운반과 설치가 끝난 후, 상기 저판 세그먼트에 설치된 레일 및 침목을 제거하고, 상기 접지지선 설치구에 접지지선을 설치하는 접지지선 설치단계를 포함하여 이루어지는 저판 세그먼트를 이용한 쉴드공법.After the transport and installation of the excavation and the material is finished, the shield method using a bottom plate segment comprising a ground line installation step of removing the rails and sleepers provided in the bottom plate segment, and install a ground line in the ground line installation port . 제7항에 있어서,The method of claim 7, wherein 상기 저판 세그먼트의 배수로가 상면 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 이격되고, 상기 배수로 중 선택된 어느 하나 이상의 저면 하측에 상기 접지지선 설치구가 구비되며, 상기 그라우팅공은 상면과 하면을 관통하도록 통공되되 상기 중심선 상에 위치되고,The drainage passages of the bottom plate segment are spaced at equal intervals with respect to the centerline passing through the center of the upper surface, and the grounding wire installation hole is provided below the bottom of any one or more selected ones of the drainage passages, and the grouting hole penetrates the upper and lower surfaces. Perforated but located on the centerline, 상기 접지선 설치단계는,The ground wire installation step, 상기 침목 및 레일을 제거 후, 접지지선 설치구에 접지지선을 거치시키는 접지지선 거치단계;After removing the sleeper and the rail, the ground wire mounting step of mounting the ground wire to the ground wire installation port; 상기 접지지선이 외측에서 보이지 않도록 상기 접지지선 설치구에 자갈을 채워 자갈층을 형성하는 충진단계; 및A filling step of forming a gravel layer by filling gravel in the grounding wire installation port so that the grounding wire is not visible from the outside; And 상기 자갈층 상측을 콘크리트 타설하여 상기 배수로와 구획은 물론, 배수로의 저면을 형성시키는 밀폐단계를 포함하여 이루어지는 저판 세그먼트를 이용한 쉴드공법.Shielding method using the bottom plate segment comprising a sealing step of forming the bottom surface of the drainage passage as well as the drainage passages and partitions by placing concrete on the gravel layer. 제7항에 있어서,The method of claim 7, wherein 상기 저판 세그먼트의 배수로가 상면 중앙부를 지나는 중심선을 기준으로, 동일한 간격으로 이격되고, 상기 그라우팅공은 상면과 하면을 관통하도록 통공되되 상기 중심선 상에 위치되며, 상기 접지지선 설치구는 상기 그라우팅공과 연통되도록 상기 중심선과 평행하게 통공되고,The drainage passages of the bottom plate segment are spaced at equal intervals with respect to the center line passing through the center of the upper surface, and the grouting hole is penetrated to penetrate the upper and lower surfaces, and is located on the center line, so that the ground branch installation hole is in communication with the grouting hole. Perforated parallel to the centerline, 상기 접지선 설치단계는,The ground wire installation step, 상기 접지지선의 일단에 리드선을 연결하고, 리드선을 상기 접지지선 설치구로 삽입하는 리드선 삽입단계;A lead wire insertion step of connecting a lead wire to one end of the ground lead wire and inserting a lead wire into the ground lead installation hole; 상기 리드선을 통과시켜 상기 접지지선 설치구에 접지지선을 거치시키는 접지지선 거치단계; 및A ground wire holding step of passing a ground wire to the ground wire installation hole through the lead wire; And 상기 접지지선이 거치된 접지지선 설치구와 그라우팅공을 밀폐시키는 밀폐단계를 포함하여 이루어지는 저판 세그먼트를 이용한 쉴드공법.A shield method using a bottom plate segment comprising a sealing step of sealing the ground ground wire installation hole and the grouting hole is mounted. 제7항에 있어서,The method of claim 7, wherein 상기 저판 세그먼트는 프리캐스트 방식으로 제작되며, 형성하고자 하는 터널의 크기에 따라 사전에 제작되는 것을 특징으로 하는 저판 세그먼트를 이용한 쉴드공법.The bottom plate segment is manufactured by a precast method, the shield method using a bottom plate segment, characterized in that the pre-fabrication according to the size of the tunnel to be formed. 제7항에 있어서, 상기 굴착물과 자재 운반 및 설치단계에서,8. The method of claim 7, wherein in the excavation and material transport and installation step, 상기 침목의 저면 양단부에는 설치턱이 각각 형성되고, 상기 각 설치턱은 저판 세그먼트의 각 배수로 측면 중 외측에 위치된 측면에 닿아 끼워지는 것을 특징으로 하는 저판 세그먼트를 이용한 쉴드공법.Shielding method using a bottom plate segment, characterized in that the mounting jaw is formed on both ends of the bottom surface of the sleeper, each of the mounting jaw is in contact with the side located on the outside of the side of each drainage channel of the bottom plate segment.
KR1020090059196A 2009-06-30 2009-06-30 The bottom segment and shield tunnel process thereof KR100977278B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090059196A KR100977278B1 (en) 2009-06-30 2009-06-30 The bottom segment and shield tunnel process thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090059196A KR100977278B1 (en) 2009-06-30 2009-06-30 The bottom segment and shield tunnel process thereof

Publications (1)

Publication Number Publication Date
KR100977278B1 true KR100977278B1 (en) 2010-08-23

Family

ID=42759886

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090059196A KR100977278B1 (en) 2009-06-30 2009-06-30 The bottom segment and shield tunnel process thereof

Country Status (1)

Country Link
KR (1) KR100977278B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101144900B1 (en) 2009-10-14 2012-05-14 강릉건설 주식회사 The bottom segment and shield tunnel process thereof
KR101596802B1 (en) 2014-11-14 2016-02-24 강릉건설(주) Double pressure pipe of reverse propelling type and exposing method for enlarging diameter span and semi shield excavating method by the same
CN106150518A (en) * 2016-07-29 2016-11-23 浙江广天构件股份有限公司 A kind of simulation assembling method of duct pieces of shield tunnel
CN108361045A (en) * 2018-04-23 2018-08-03 同济大学 A kind of duct pieces of shield tunnel being adapted to soft soil layer
CN110374677A (en) * 2019-08-02 2019-10-25 中铁九局集团第六工程有限公司 Plateau rich water soft rock tunnel control drainage construction engineering method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001288992A (en) * 2000-01-31 2001-10-19 Geostr Corp Segment ring for shield construction work, segment and inter-ring joint
JP3413114B2 (en) * 1998-10-14 2003-06-03 株式会社奥村組 Tunnel bottom lining
JP2006233538A (en) * 2005-02-24 2006-09-07 Setsuo Takaku Invert for tunnel, invert block, and invert construction method using invert block

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3413114B2 (en) * 1998-10-14 2003-06-03 株式会社奥村組 Tunnel bottom lining
JP2001288992A (en) * 2000-01-31 2001-10-19 Geostr Corp Segment ring for shield construction work, segment and inter-ring joint
JP3735532B2 (en) * 2000-01-31 2006-01-18 ジオスター株式会社 Segment ring for shield construction
JP2006233538A (en) * 2005-02-24 2006-09-07 Setsuo Takaku Invert for tunnel, invert block, and invert construction method using invert block

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101144900B1 (en) 2009-10-14 2012-05-14 강릉건설 주식회사 The bottom segment and shield tunnel process thereof
KR101596802B1 (en) 2014-11-14 2016-02-24 강릉건설(주) Double pressure pipe of reverse propelling type and exposing method for enlarging diameter span and semi shield excavating method by the same
CN106150518A (en) * 2016-07-29 2016-11-23 浙江广天构件股份有限公司 A kind of simulation assembling method of duct pieces of shield tunnel
CN108361045A (en) * 2018-04-23 2018-08-03 同济大学 A kind of duct pieces of shield tunnel being adapted to soft soil layer
CN110374677A (en) * 2019-08-02 2019-10-25 中铁九局集团第六工程有限公司 Plateau rich water soft rock tunnel control drainage construction engineering method

Similar Documents

Publication Publication Date Title
CN104612698B (en) A kind of shallow-depth-excavation tunnel top bar interval wall construction method
WO2015196872A1 (en) Method for removing hydraulic support for solid filling coal mining
KR100977278B1 (en) The bottom segment and shield tunnel process thereof
JP2010101062A (en) Drainage structure of underground water, and construction method for tunnel equipped with the drainage structure
KR20060049741A (en) Construction method of three arch excavation tunnel
CN102748040A (en) Main structure for metro long-span station and pillar arching construction method thereof
CN102758442A (en) Earth excavation method and open-cut tunnel construction method
CN107514262A (en) The construction method of shield piping lane
KR100877452B1 (en) Construction method of middle wall of three arch excavation tunnel
CN107575237A (en) A kind of subsurface excavation method is combined the construction method of construction subway station with shield method
KR20080082892A (en) A circular structure supported by the segment with a drainage structure and method constructing the shield tunnel
KR101144900B1 (en) The bottom segment and shield tunnel process thereof
CN112983461B (en) Construction method for biasing tunnel portal in slope integrated
CN104184097A (en) Non-migration suspension protection system and method for communication pipes and cables
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
JP2019124019A (en) Invert construction method to existing tunnel
CN107642101A (en) A kind of rocky bed steel cofferdam back cover leak stopping and guarded drainage construction method
KR101427812B1 (en) Open cut method for constructing an underground structure
KR20050020451A (en) Shield tunneling construction method and tunnel structure
JP2001220988A (en) Method for constructing underwater tunnel and working method for construction
KR20200133548A (en) Underaround continued wall structure using casing and pile continuous connection and method therefor
CN109630194A (en) A kind of karst region fault belt Tunnel Gushing administration structure and its construction method
KR101612522B1 (en) Construction method for tunneling
KR101399787B1 (en) Bottom segment
KR102243586B1 (en) Two-side semicircle arch type leading pipe and structure of non-excavation type tunnel using thereof and method of constructing thereof

Legal Events

Date Code Title Description
A201 Request for examination
A302 Request for accelerated examination
E902 Notification of reason for refusal
E90F Notification of reason for final refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee