KR101612522B1 - Construction method for tunneling - Google Patents
Construction method for tunneling Download PDFInfo
- Publication number
- KR101612522B1 KR101612522B1 KR1020150138367A KR20150138367A KR101612522B1 KR 101612522 B1 KR101612522 B1 KR 101612522B1 KR 1020150138367 A KR1020150138367 A KR 1020150138367A KR 20150138367 A KR20150138367 A KR 20150138367A KR 101612522 B1 KR101612522 B1 KR 101612522B1
- Authority
- KR
- South Korea
- Prior art keywords
- tunnel
- wall
- excavation
- pillar
- trailing
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/14—Lining predominantly with metal
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/38—Waterproofing; Heat insulating; Soundproofing; Electric insulating
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/14—Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
Abstract
Description
The present invention relates to a tunnel construction method.
In general, the road tunnel is divided into an up-line and a down-line, and takes the form of a double tunnel with an interval of 1.5 times the maximum width of the tunnel. However, due to the surrounding conditions and ground characteristics of the planned tunnel, There is an increasing tendency to install parallel tunnels with very narrow intervals between tunnels.
In this case, two arch tunnel can be used as an excellent alternative structure in linear planning. However, due to the structural characteristics of the two arch tunnel, constructional, economic, and maintenance aspects are more disadvantageous than general tunnel construction.
As a prior art document, Korean Patent Laid-Open Publication No. 10-2010-0128521 discloses a method of "construction method of two arch tunnel".
In the conventional two-arch tunnel construction method, the pilot tunnel is first excavated at the center of the two-arch tunnel, the concrete wall is constructed, and the left and right main tunnel are constructed.
However, the conventional two-arch tunnel construction method has a problem that the construction period is excessive due to the inability to excavate left and right tunnels until the completion of the center wall construction, and the construction cost is increased.
In addition, according to the existing two-arch tunnel construction method, there is a problem that groundwater is concentrated at the central part of the public middle tunnel.
SUMMARY OF THE INVENTION An object of the present invention is to provide a tunnel construction method in which a pilot tunnel excavation process can be omitted and a center wall can be constructed.
According to one aspect of the present invention, there is provided a tunnel construction method comprising the steps of: (a) drilling a pillar extending to a side of a preceding tunnel and a preceding tunnel; (b) installing a support material for reinforcing the excavation surface of the preceding tunnel and the excavation surface of the pillar portion; (c) installing a stiffener for supporting the upper excavation surface of the pillar portion from below; (d) constructing a first wall formed along the longitudinal direction of the pillar using the reinforcing member as a support; (e) excavating a trailing tunnel disposed in parallel with the preceding tunnel and communicating with the pillar portion; (f) installing a backing material on the excavation surface of the trailing tunnel; (g) constructing a second wall formed along the longitudinal direction of the pillar portion; And (h) placing a waterproofing membrane and a lining in the preceding tunnel and the trailing tunnel.
According to another aspect of the present invention, there is provided a tunnel construction method comprising the steps of: (a) excavating an upper part of a preceding tunnel; (b) installing a support material on the excavation surface of the upper half of the preceding tunnel; (c) digging a pillar portion extending to the lower half of the preceding tunnel and the side of the preceding tunnel; (d) installing a backing material on the lower half of the preceding tunnel and on the excavation surface of the pillar portion; (e) constructing a first wall for supporting the upper excavation surface of the pillar portion from below; (f) excavating an upper portion of a trailing tunnel disposed in parallel with the preceding tunnel and communicating with the pillar portion; (g) installing a support material on the upper excavation surface of the trailing tunnel; (h) excavating the lower half of the trailing tunnel; (i) installing a support material on an excavation surface in a lower part of the trailing tunnel; (j) installing a second wall formed along a longitudinal direction of the pillar portion; And (k) placing a waterproofing membrane and a lining in the preceding tunnel and the trailing tunnel.
According to the embodiment of the present invention, since the center wall can be formed simultaneously with the excavation of the left and right tunnels, the pilot tunnel excavation process can be omitted, and the disadvantage of the existing two-arch tunnel can be solved.
That is, according to the tunnel construction method proposed in the present invention, the construction period is shortened compared with the existing two-arch tunnel construction method, and the construction cost is relatively simple, so that the construction cost can be reduced.
In addition, since the excavation process of the pilot tunnel is omitted, it is possible to solve the problem that the groundwater is concentrated in the central part of the public tunnel.
1 is a view showing a tunnel constructed according to a tunnel construction method according to an embodiment of the present invention.
2 to 5 are views showing a tunnel construction method according to an embodiment of the present invention in the order of construction.
6 to 14 are views showing a tunnel construction method according to another embodiment of the present invention in the order of construction.
Hereinafter, some embodiments of the present invention will be described in detail with reference to exemplary drawings. It should be noted that, in adding reference numerals to the constituent elements of the drawings, the same constituent elements are denoted by the same reference numerals even though they are shown in different drawings. In the following description of the embodiments of the present invention, a detailed description of known functions and configurations incorporated herein will be omitted when it may make the difference that the embodiments of the present invention are not conclusive.
In describing the components of the embodiment of the present invention, terms such as first, second, A, B, (a), and (b) may be used. These terms are intended to distinguish the constituent elements from other constituent elements, and the terms do not limit the nature, order or order of the constituent elements. When a component is described as being "connected", "coupled", or "connected" to another component, the component may be directly connected or connected to the other component, Quot; may be "connected," "coupled," or "connected. &Quot;
1 is a view showing a tunnel constructed according to a tunnel construction method according to an embodiment of the present invention.
Referring to FIG. 1, a tunnel constructed according to a tunnel construction method according to an embodiment of the present invention includes a preceding
The preceding tunnel (100) and the trailing tunnel (200) are opened front and rear.
The preceding tunnel (100) and the trailing tunnel (200) may be partitioned by the partition wall (400).
Hereinafter, a tunnel construction method according to an embodiment of the present invention will be described in the order of construction. The tunnel construction method of the present embodiment corresponds to front end section excavation.
2 to 5 are views showing a tunnel construction method according to an embodiment of the present invention in the order of construction.
FIG. 2 is a view showing a state where a preceding tunnel is excavated. FIG. Referring to FIG. 2, as a first step of the tunnel construction process, excavation of the preceding
The excavation of the preceding tunnel (100) and the pillar (300) may be directed forward. Forward excavation can be done by depth of 1 ~ 5m depending on the surrounding rock condition.
The
After the excavation is performed by the depth, the preceding
The excavation depth in the forward direction of the preceding
3 is a view showing a state in which a support material for reinforcing a preceding tunnel is installed.
Referring to FIG. 3, the
The
A step of installing a steel beam on the
The
A
If the
Since the point at which the
The
Next, a
The reinforcing
The lower end of the reinforcing
However, it is also possible to perform the excavation without installing the
A separate blocking wall may be provided to prevent the
By repeating the first to second steps, the preceding
4 is a view showing a state where a rear tunnel is excavated.
Referring to FIG. 4, the first wall 304 (see FIG. 5) can be constructed by installing the concrete 303a using the reinforcing
The concrete or the like 303a may include shotcrete, spotted concrete, precast concrete, or the like. The reinforcing
The gaps that can be formed in the ceiling portion of the
A separate blocking wall may be provided to prevent the
The
Next, the trailing
The trailing
The construction of the trailing
Mechanical excavation may be performed at a portion adjacent to the
In addition, in order to minimize the damage of the
A base (not shown) for supporting the
5 is a view showing a state in which a backing material for reinforcing a rearward tunnel is installed.
Referring to FIG. 5, a
A step of installing a steel beam on the
The
Also, a
Since the stability of the
Steel pipe reinforcement grouting may be performed on the
Next, a
When the
The
Next, a step of installing a nonwoven fabric and a waterproof film on the shotcrete placement surfaces of the preceding
Next, a lining can be applied to the preceding
Hereinafter, a tunnel construction method according to another embodiment of the present invention will be described in the order of construction.
6 to 14 are views showing a tunnel construction method according to another embodiment of the present invention in the order of construction.
The tunnel construction method of this embodiment corresponds to upper and lower half-section excavation. Upper and lower half-sided excavation is generally an excavation method where the ground is weak.
6 is a view showing a state where primary excavation of a preceding tunnel is performed. Referring to FIG. 6, the
After the
The
7 is a view showing a state in which a support material is installed on the upper half of the preceding tunnel.
Referring to FIG. 7, a support material is installed on the
A step of installing a steel girder (not shown) on the
The steel girder (not shown) may be fixed to the
A
If the
In the meantime, considering the portion to be widened in the future, the steel girder (not shown) may be fixed to the start point of the section to be widened, and may be fixed with a
Up to a certain depth of the tunnel, the first step and the second step may be alternately performed. Next, lower tunnel excavation of the preceding tunnel is performed.
8 is a view showing a state in which a lower tunnel has been installed in a preceding tunnel.
8, excavation of the
Fig. 9 is a view showing a state in which a support material is installed in the lower half of the preceding tunnel, and a girder beam and a support material are installed in the pillar portion.
Referring to FIG. 9, a
Specifically, after the
(Not shown) provided in the
The strong jig (not shown) may be supported by the
Also, a
A plurality of steel pipe reinforcing grouting may be installed at the point where the preceding
A
A reinforcing
The lower end of the reinforcing
The reinforcing
A blocking wall (not shown) may be provided at one side of the reinforcing
10 is a view showing a state where the upper half of the trailing tunnel is excavated.
Referring to FIG. 10, the first wall 304 (see FIG. 11) can be constructed by installing the concrete 303a using the reinforcing
The concrete or the like 303a may include shotcrete, spotted concrete, precast concrete, or the like. The reinforcing
The gaps formed in the ceiling portion of the
A separate blocking wall may be provided to prevent the
A gap is formed between the
Next, excavation of the
The
Mechanical excavation may be performed at a portion adjacent to the
In addition, in order to minimize the damage of the
11 is a view showing a state in which a support material for reinforcing the upper half of the rear tunnel is installed.
Referring to FIG. 11, a
(Not shown) may be added to the
In the meantime, considering the portion to be widened in the future, the steel girder (not shown) may be fixed to the start point of the section to be widened, and may be fixed with a
Also, a
The
12 is a view showing a state in which a lower half of a trailing tunnel is excavated.
A portion of the pillar portion adjacent to the
Next, a
13 is a view showing a state in which the
When the
The
14 is a view showing a state in which a support material is installed in a lower half of a rear tunnel and a wall is installed in a pillar portion.
Referring to FIG. 14, a
Specifically, after the
The steel girders (not shown) provided in the
The strong jig (not shown) may be supported by the
A plurality of steel pipe reinforcing grouting may be installed at a point where the trailing
A
Next, a member for preventing damage, which is provided on the
Next, a step of installing a nonwoven fabric and a waterproofing membrane on the preceding
On the other hand, a waterproof shotcrete can be installed in place of the waterproof film.
Next, a lining can be applied to the preceding
According to the embodiment of the present invention, the center wall can be formed only by tunnel excavation of the left and right without excavation of the pilot tunnel, and the disadvantage of the existing two-arch tunnel construction method can be solved.
Although the tunnel has been described herein with reference to an arch-shaped tunnel, the tunnel construction method of the present invention is applicable to a rectangular or circular tunnel instead of an arch shape. In other words, the shape of the tunnel is not limited.
The foregoing description is merely illustrative of the technical idea of the present invention, and various changes and modifications may be made by those skilled in the art without departing from the essential characteristics of the present invention. Therefore, the embodiments disclosed in the present invention are intended to illustrate rather than limit the scope of the present invention, and the scope of the technical idea of the present invention is not limited by these embodiments. The scope of protection of the present invention should be construed according to the following claims, and all technical ideas within the scope of equivalents should be construed as falling within the scope of the present invention.
100: preceding tunnel 200: trailing tunnel
300: Pillar portion 400: Compartment wall
Claims (12)
(b) installing a support material for reinforcing the excavation surface of the preceding tunnel and the excavation surface of the pillar portion;
(c) installing a stiffener for supporting the upper excavation surface of the pillar portion from below;
(d) repeating the steps (a), (b), and (c)
(e) constructing a first wall formed along the longitudinal direction of the pillar using the reinforcing member as a support;
(f) excavating a trailing tunnel disposed in parallel with the preceding tunnel and communicating with the pillar portion;
(g) installing a backing material on the excavation surface of the trailing tunnel;
(h) repeating the steps (f) and (g) by a plurality of circuits;
(i) constructing a second wall formed along a longitudinal direction of the pillar portion; And
(j) placing a waterproofing membrane and a lining in the preceding tunnel and the trailing tunnel,
The first wall is constructed by shotcrete, concrete or precast concrete,
Wherein the second wall is integrally formed with the first wall by using a reinforcing member as a support.
The step (b) and the step (g)
Placing a shotcrete on the excavation surface and installing a rock bolt,
And a reinforcing grout having a length greater than that of the other point is installed at a point where the preceding tunnel and the pillar meet and a point where the trailing tunnel meets the pillar.
In the step (c), in order to prevent the first wall from being damaged by the excavation of the trailing tunnel, the first wall is spaced apart from the side wall of the pillar by a predetermined distance.
In the step (c), in order to prevent the first wall from being damaged by the excavation of the trailing tunnel, a cushioning material is installed in the space between the side walls of the first wall and the pillar portion.
In the step (f), in order to minimize the damage of the first wall when the trailing tunnel is excavated, a portion adjacent to the first wall proceeds by a mechanical excavation or a vibration control blasting method.
(b) installing a support material on the excavation surface of the upper half of the preceding tunnel;
(c) repeating the steps (a) and (b) by a plurality of circuits;
(d) digging a pillar portion extending to a lower half of the preceding tunnel and a side of the preceding tunnel;
(e) installing a support material on the lower half of the preceding tunnel and the excavation surface of the pillar portion;
(f) constructing a first wall for supporting the upper excavation surface of the pillar portion from below;
(g) excavating an upper portion of a trailing tunnel disposed in parallel with the preceding tunnel and communicating with the pillar portion;
(h) installing a support material on the upper excavation surface of the trailing tunnel;
(i) repeating the steps (g) and (h) by a plurality of circuits;
(j) excavating the lower half of the trailing tunnel;
(k) installing a support material on an excavation surface in a lower part of the trailing tunnel;
(1) installing a second wall formed along the longitudinal direction of the pillar portion; And
(m) placing a waterproof membrane and a lining in the preceding tunnel and the trailing tunnel,
The first wall is constructed by shotcrete, concrete or precast concrete,
Wherein the second wall is integrally formed with the first wall by using a reinforcing member as a support.
In the step (f), in order to prevent the first wall from being damaged by the excavation of the trailing tunnel, the first wall is spaced apart from the side wall of the pillar by a predetermined distance,
And a cushioning material is provided in the space between the first wall and the side wall of the pillar portion.
In the step (g) and the step (j)
Wherein a portion adjacent to the first wall is performed by a mechanical excavation method or a vibration-controlled blasting method in order to minimize damage to the first wall when the trailing tunnel is excavated.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150138367A KR101612522B1 (en) | 2015-10-01 | 2015-10-01 | Construction method for tunneling |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020150138367A KR101612522B1 (en) | 2015-10-01 | 2015-10-01 | Construction method for tunneling |
Publications (1)
Publication Number | Publication Date |
---|---|
KR101612522B1 true KR101612522B1 (en) | 2016-04-14 |
Family
ID=55801587
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020150138367A KR101612522B1 (en) | 2015-10-01 | 2015-10-01 | Construction method for tunneling |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR101612522B1 (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108487911A (en) * | 2018-03-28 | 2018-09-04 | 中铁二院工程集团有限责任公司 | The compound crossing method construction method of longspan tunnel bilateral wall under complex geological condition |
KR20220084693A (en) * | 2020-12-14 | 2022-06-21 | 전영권 | Construction method of an ultra-close parallel tunnel using steel beams and shotcrete reinforcement pillars |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100701633B1 (en) * | 2005-06-01 | 2007-03-30 | 윤석렬 | Load dispersing plate for supporting central part of a twin tunnel and a construction method of a twin tunnel using the load dispersing plate |
KR101283663B1 (en) * | 2013-02-13 | 2013-07-08 | 주식회사 성우사면 | Method for digging two arch type tunnel |
KR101391218B1 (en) * | 2013-04-19 | 2014-05-28 | 주식회사 하이콘엔지니어링 | Construction methods of close-twin tunnel by blast shock-controlling and rebar reinforced shotcrete |
-
2015
- 2015-10-01 KR KR1020150138367A patent/KR101612522B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100701633B1 (en) * | 2005-06-01 | 2007-03-30 | 윤석렬 | Load dispersing plate for supporting central part of a twin tunnel and a construction method of a twin tunnel using the load dispersing plate |
KR101283663B1 (en) * | 2013-02-13 | 2013-07-08 | 주식회사 성우사면 | Method for digging two arch type tunnel |
KR101391218B1 (en) * | 2013-04-19 | 2014-05-28 | 주식회사 하이콘엔지니어링 | Construction methods of close-twin tunnel by blast shock-controlling and rebar reinforced shotcrete |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108487911A (en) * | 2018-03-28 | 2018-09-04 | 中铁二院工程集团有限责任公司 | The compound crossing method construction method of longspan tunnel bilateral wall under complex geological condition |
KR20220084693A (en) * | 2020-12-14 | 2022-06-21 | 전영권 | Construction method of an ultra-close parallel tunnel using steel beams and shotcrete reinforcement pillars |
KR102593945B1 (en) * | 2020-12-14 | 2023-10-24 | 전영권 | Construction method of an ultra-close parallel tunnel using steel beams and shotcrete reinforcement pillars |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
JP7125550B2 (en) | SUPPORT STRUCTURE AND CONSTRUCTION METHOD FOR TWO-STAGE HIGH-SPEED CLOSING TUNNEL WITH INVERTED ARCH | |
KR101834847B1 (en) | Echo-environmental construction method of tunnel portal area using mini pipe-roof | |
KR101028535B1 (en) | Construction method of double tunnel | |
KR101244257B1 (en) | Method for digging tunnel | |
JP2007217911A (en) | Construction method of underground cavity and tunnel construction method | |
JP2015098676A (en) | Construction method of shield tunnel | |
JP6186267B2 (en) | How to build an underground tunnel | |
KR101536209B1 (en) | Steel Pipe Multi Step Grouting device Open and cut and NATM complex excavation tunnel construction method | |
KR20170016897A (en) | Tunnel construction method with support walls | |
KR102215505B1 (en) | Construction method of internal pre-support tunnel for complete blocking water of all directions of the tunnel | |
KR101612522B1 (en) | Construction method for tunneling | |
JP6460712B2 (en) | Construction method of underground continuous wall | |
KR101974183B1 (en) | Construction methods of approaching dual tunnel | |
KR100562121B1 (en) | Shield tunneling construction method and tunnel structure | |
KR100898969B1 (en) | Tunnel Boring Method Using Sheet Pile and Tunnel Structure therof | |
KR101612527B1 (en) | Construction method for tunneling | |
KR101283663B1 (en) | Method for digging two arch type tunnel | |
KR101427812B1 (en) | Open cut method for constructing an underground structure | |
KR20190072213A (en) | Method Of Ground Half-Openning For Tunnel Excavation | |
JP5012149B2 (en) | Ground support structure and ground support method | |
KR101669669B1 (en) | Construction methods of approaching dual tunnel | |
JP4303512B2 (en) | Construction method of large section tunnel | |
KR101091081B1 (en) | Excavation method and construction of dual tunnel | |
CN108843339B (en) | The auxiliary slip casting platform and construction method of large-scale solution cavity are passed through when existing tunnel digs | |
KR20170000008A (en) | Tunnel construction method with support walls |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20190404 Year of fee payment: 4 |