KR20130021952A - Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same - Google Patents

Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same Download PDF

Info

Publication number
KR20130021952A
KR20130021952A KR1020110084545A KR20110084545A KR20130021952A KR 20130021952 A KR20130021952 A KR 20130021952A KR 1020110084545 A KR1020110084545 A KR 1020110084545A KR 20110084545 A KR20110084545 A KR 20110084545A KR 20130021952 A KR20130021952 A KR 20130021952A
Authority
KR
South Korea
Prior art keywords
underground structure
wall
steel pipe
concrete
horizontal reinforcement
Prior art date
Application number
KR1020110084545A
Other languages
Korean (ko)
Other versions
KR101296857B1 (en
Inventor
채흥석
문영민
박찬면
Original Assignee
주식회사 세진에스씨엠
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 주식회사 세진에스씨엠 filed Critical 주식회사 세진에스씨엠
Priority to KR1020110084545A priority Critical patent/KR101296857B1/en
Publication of KR20130021952A publication Critical patent/KR20130021952A/en
Application granted granted Critical
Publication of KR101296857B1 publication Critical patent/KR101296857B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/01Flat foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/28Prefabricated piles made of steel or other metals
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1607Shapes round, e.g. circle

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE: An underground structure including a floor beam in which supporting force of the earth pressure is reinforced and a construction method thereof are provided to easily construct an underground structure and to reduce the time for construction. CONSTITUTION: An underground structure including a floor beam in which supporting force of the earth pressure is reinforced comprises a stiffener, a connection member(110), a horizontal stiffener, and a floor beam. The stiffener is embedded in an earth retaining wall(1) in regular intervals. The connection member is installed at the stiffener. The horizontal stiffener is installed in order to connect the connect members to each other and is embedded with the connection member in the concrete of a wall. The floor beam is installed at the horizontal stiffener or the connection member and supports a concrete slab.

Description

토압 지지력이 강화된 바닥보를 구비하는 지하 구조물 및 그 시공방법{Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same}Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same

본 발명은 지하 구조물 및 그 시공방법에 관한 것으로서, 더욱 상세하게는 바닥보의 토압 지지력이 크기 때문에 한꺼번에 두 개 이상의 지하층을 굴토할 수 있고 건물의 지하 최하층까지 바닥보를 먼저 설치한 후 콘크리트 슬래브를 형성할 수 있기 때문에 시공이 편리하고 공사 기간을 단축할 수 있으며, 지하 구조물의 벽체 두께를 감소시키더라도 토압 지지구조를 강화할 수 있고 이에 따라 지하 구조물의 구축에 필요한 콘크리트를 줄일 수 있고 지하 구조물의 공간 활용도를 향상시킬 수 있는, 지하 구조물 및 그 시공방법에 관한 것이다.The present invention relates to an underground structure and its construction method, and more particularly, because the earth pressure bearing capacity of the floor beams is large, it is possible to excavate two or more basement layers at once and to form a concrete slab after installing the floor beams to the basement floor of the building first. The construction can be convenient and shorten the construction period, and the earth pressure supporting structure can be strengthened even if the wall thickness of the underground structure is reduced, thus reducing the concrete required for the construction of the underground structure and the space utilization of the underground structure. To improve, it relates to an underground structure and its construction method.

일반적으로, 건물을 시공할 경우 지하층을 구축하게 되는데, 이와 같은 지하층을 구축하기 위해 지반의 붕괴를 막는 흙막이벽을 설치하고 탑다운(Top-Down) 방식으로 지하층을 구축한다. In general, when the building construction is to build a basement, such a basement to build a basement wall to prevent the collapse of the ground and to build a basement floor in a top-down (Top-Down) method.

상기 탑다운 방식은 굴착공사 이전에 흙막이벽과 지하층 기둥을 미리 시공한 다음, 단계별로 지하층 슬래브와 토공사를 반복해 가면서 위에서 아래로 지하 구조물을 형성하는 공법으로서, 도심지의 대규모 구조물을 위한 굴착공사에도 안정적이며, 구조물의 1층 바닥 선시공으로 인한 작업장의 조기확보 및 지상과 지하의 동시 시공으로 인한 공기단축 등의 효과를 기대할 수 있는 공법이다.The top-down method is a method of forming the basement walls and basement pillars in advance before the excavation, and then forming the underground structure from the top to the bottom while repeating the basement slab and earthwork step by step, and also for excavation for large structures in downtown It is stable and the construction method can expect the effect of early securing of the work place by the first floor construction of the structure and the reduction of air due to the simultaneous construction of the ground and the underground.

한편, 상기 흙막이벽 시공의 예로서, 축조 현장에서 콘크리트로 흙막이벽을 타설하는 CIP 공법(Cast In Place Pile)과, 빔 형태의 파일(PILE)을 일정 간격으로 항타하고 터파기 굴착을 진행하면서 토류판을 파일 사이에 끼우는 파일 토류판 흙막이벽, 소일시멘트 월(SCW : Soil Cement Wall), 다이아프램 월(Diaphragm wall) 등이 있다. 이 중에서 CIP 공법은 파일 토류판 흙막이벽과 소일시멘트 윌 등에 비해 흙막이벽의 강성이 우수하여 지하층을 구축하기 위한 공법으로 주로 사용되고 있다.On the other hand, as an example of the construction of the clam wall, the earth plate while driving the excavation and excavating the excavation excavation at a predetermined interval between the CIP method (Cast In Place Pile) and the beam-shaped pile (PILE) for placing the clam wall in concrete at the construction site Pile soil plate wall between the piles, Soil Cement Wall (SCW), diaphragm wall (Diaphragm wall). Among them, the CIP method is mainly used as a method for constructing the basement layer because of the superior rigidity of the retaining wall as compared to the pile earth retaining wall and the soil cement wheel.

상기 CIP 공법은 주열식으로 철근 콘크리트 기둥을 현장에서 타설하는 것으로서, 천공장비로 지반을 수직으로 천공하여 케이싱을 설치하고 케이싱 내부에 철근을 설치하고, H 형강을 소정간격으로 케이싱 내부에 삽입시킨 후 콘크리트를 충진시켜 기둥으로 고형화한 다음 케이싱을 제거하는 일련의 과정을 반복함으로써 흙막이벽을 형성하는 공법이다.The CIP method is to cast reinforced concrete columns in the field by casting heat, install a casing by drilling the ground vertically with a drilling equipment, install reinforcing bars in the casing, and insert H-beams into the casing at predetermined intervals. It is a method of forming the retaining wall by repeating a series of processes of filling concrete to solidify the column and then removing the casing.

건축물의 경계선을 따라 상기 흙막이벽이 설치되면 1차 터파기 후, 흙막이벽을 지지하도록 띠장과 테두리보를 설치한 다음, 철골보를 기둥과 테두리보에 연결하고 그 위에 슬래브를 타설하는 방법을 반복함으로써 지하 구조물을 구축한다. 이때, 건물의 각 층고는 대략 3.6m 내지 4.5m이며, 이러한 슬래브의 하중 및 건축물의 하중을 지지하기 위하여 흙막이벽에 벽체가 시공된다. When the retaining wall is installed along the boundary of the building, after the first dig, after installing the strip and the rim beam to support the retaining wall, the method of connecting the cheolgolbo to the column and the rim beam and placing the slab on it is repeated. Build the structure. At this time, the height of each floor of the building is approximately 3.6m to 4.5m, and the wall is constructed on the retaining wall to support the load of the slab and the load of the building.

한편, 하나의 층고 깊이만큼 지반을 터파기하고 철골보를 설치한 후 슬래브를 타설하는데, 이것은 상기 철골보가 토압 지지력이 약하기 때문에 슬래브가 토압을 지지하도록 하기 위해서이다. 즉, 상기 철골보가 토압 지지력이 약하기 때문에 하나의 층고 깊이만큼 터파기, 철골보 설치, 슬래브 타설이 반복적으로 이루어져야 하고, 이에 따라 시공이 어려워지고 공사기간이 많이 소요되는 문제점이 있다. On the other hand, the ground is excavated by one layer height, and after installing the cheolgolbo is installed slab, this is to allow the slab to support the earth pressure because the cheolgolbo is weak earth pressure bearing capacity. That is, since the cheolgolbo has a weak earth pressure bearing force, it is necessary to repeatedly excavate, install the cheolgolbo, and slab as much as one floor height, thereby making construction difficult and requiring a lot of construction period.

도 1은 지하 구조물을 시공한 단면을 보여준다. 전술한 CIP 공법을 이용하여 흙막이벽(w)을 시공 후, 탑다운 방식에 의해 지하 구조물의 외벽 즉, 흙막이벽의 내측으로 벽체(5)가 시공된다. 여기서, 각 층간 설치되는 철골보 및 철골보의 위에 타설된 슬래브는 도시되지 않았다.Figure 1 shows a cross section of the construction of the underground structure. After constructing the retaining wall w using the above-described CIP method, the wall 5 is constructed inside the outer wall of the underground structure, that is, inside the retaining wall by the top-down method. Here, the cheolgolbo and the slab placed on the cheolgolbo installed between each layer is not shown.

상기 벽체(5)는 슬래브의 하중 및 건축물의 하중을 지지함과 더불어 토압에 의해 지반이 붕괴는 것을 방지하도록 이루어져야 한다. 따라서, 벽체(5)는 토압에 저항하며 슬래브의 하중 및 건축물의 하중을 지지하기 위하여 두께가 두꺼워져야 한다는 문제점이 있다.The wall 5 should be made to support the load of the slab and the load of the building and to prevent the ground from collapse by earth pressure. Therefore, the wall 5 is resistant to earth pressure and has a problem that the thickness must be thick to support the load of the slab and the load of the building.

또한, 벽체(5)가 두꺼워짐에 따라 벽체(5)를 형성하는 콘크리트 및 보강철근 등의 재료가 많이 소요됨은 물론, 지하 구조물 내부의 공간 활용도도 감소되는 문제점이 있다.In addition, as the wall 5 becomes thicker, a lot of materials such as concrete and reinforcing bars forming the wall 5 are required, as well as the space utilization inside the underground structure is also reduced.

본 발명은 상기와 같은 문제점을 해결하기 위해 창안된 것으로서, 바닥보의 토압 지지력이 커서 한꺼번에 두 개 층 이상의 지반을 굴토할 수 있기 때문에 시공이 편리하고 공사 기간을 단축할 수 있는 지하 구조물 및 그 시공방법을 제공하는데 그 목적이 있다. The present invention was devised to solve the above problems, the basement structure and its construction can be convenient and shorten the construction period because it can excavate more than two floors at a time due to the large earth pressure bearing capacity of the floor beam The purpose is to provide a method.

본 발명의 또 다른 목적은 건물의 지하 최하층까지 바닥보를 먼저 설치한 후 슬래브를 형성할 수 있기 때문에 시공이 편리하고 공사 기간을 단축할 수 있는 지하 구조물 및 그 시공방법을 제공하는데 있다. Still another object of the present invention is to provide an underground structure and a construction method thereof, which is convenient for construction and can shorten the construction period, since it is possible to form a slab after first installing a floor beam to the basement floor of a building.

본 발명의 또 다른 목적은 지하 구조물의 벽체의 두께를 감소시키더라도 토압에 대한 지지구조를 강화함과 더불어 슬래브의 하중에 견딜 수 있는 지하 구조물 및 그 시공방법을 제공하는데 있다.Still another object of the present invention is to provide an underground structure and a construction method thereof capable of withstanding the load of the slab as well as strengthening the supporting structure against earth pressure even if the thickness of the wall of the underground structure is reduced.

본 발명의 또 다른 목적은 지하 구조물의 벽체의 두께를 감소시켜 벽체를 형성하는 재료의 비용을 감소시킬 수 있는 지하 구조물 및 그 시공방법을 제공하는데 있다.It is still another object of the present invention to provide an underground structure and a method for constructing the same, which can reduce the thickness of the wall of the underground structure, thereby reducing the cost of the material forming the wall.

상기 목적을 달성하기 위하여, 본 발명에 따른 지하 구조물은, 흙막이벽에 소정 간격으로 매립된 보강재; 보강재에 결합되는 연결부재; 연결부재를 서로 연결하도록 설치된 수평 보강재; 및, 수평 보강재와 연결부재 중 적어도 어느 하나에 설치된 바닥보;를 포함한다. 바닥보는 강관(170)을 포함하는데, 강관(170)은 각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성되며 상기 중공에는 콘크리트(C3)가 채워진다. 연결부재와 수평 보강재는 지하 구조물의 벽체(160)에 매립되고, 이에 따라 벽체(160)의 강성이 커진다. 한편, 강관(170)의 중공에는 콘크리트(C3)가 없고 강관(170)만으로도 토압 지지력을 제공하도록 할 수도 있다.In order to achieve the above object, the underground structure according to the present invention, the reinforcement buried at a predetermined interval on the earth wall; A connection member coupled to the reinforcement; Horizontal reinforcement provided to connect the connecting members to each other; And a floor beam installed on at least one of the horizontal reinforcement and the connection member. The bottom beam includes a steel pipe 170, the steel pipe 170 has a rectangular or circular cross-sectional shape and a hollow is formed along the longitudinal direction therein, the hollow is filled with concrete (C3). The connecting member and the horizontal reinforcement are embedded in the wall 160 of the underground structure, thereby increasing the rigidity of the wall 160. On the other hand, there is no concrete (C3) in the hollow of the steel pipe 170 may be to provide a earth pressure bearing force only by the steel pipe 170.

상기 강관(170)에는 콘크리트(C3)를 주입하기 위한 주입홀(171)이 형성될 수 있다.An injection hole 171 for injecting concrete C3 may be formed in the steel pipe 170.

상기 보강재는 강관(4)을 포함할 수 있는데, 강관(4)은 각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성되며 상기 중공에는 콘크리트(C1)가 채워진다.The reinforcing material may comprise a steel pipe (4), the steel pipe (4) has a square or circular cross-sectional shape and a hollow is formed along the longitudinal direction therein, the hollow is filled with concrete (C1).

상기 수평 보강재는 강관(120)을 포함할 수 있는데, 강관(120)은 각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성되며 상기 중공에는 콘크리트(C2)가 채워진다.The horizontal reinforcing material may include a steel pipe 120, the steel pipe 120 has a rectangular or circular cross-sectional shape and a hollow is formed along the longitudinal direction therein, the hollow is filled with concrete (C2).

상기 강관(120)에는 콘크리트를 주입하기 위한 주입공(123)이 형성될 수 있다. The steel pipe 120 may be formed with an injection hole 123 for injecting concrete.

상기 수평 보강재와 흙막이벽 사이에는 이격부재(128)가 설치될 수 있다. 이격부재에 의해서 수평 보강재와 흙막이 벽 사이에 확보되는 공간에는 수평철근(130)이 설치되는 것이 바람직하다. 수평철근(130)은 벽체(160)에 매립되고, 이에 따라 벽체(160)의 토압 지지력이 증가될 수 있다. A spacer 128 may be installed between the horizontal reinforcement and the retaining wall. It is preferable that horizontal reinforcement 130 is installed in the space secured between the horizontal reinforcement and the wall of the earth by the spacer member. The horizontal reinforcement 130 is embedded in the wall 160, thereby increasing the earth pressure bearing force of the wall 160.

본 발명의 다른 측면인 지하 구조물의 시공방법은, (a) 시공되는 구조물의 경계선을 따라 흙막이벽(1)을 구축하는 단계; (b) 흙막이벽(1)의 안쪽으로 지반을 소정 깊이로 굴토하여 터파기 작업을 수행하고, 흙막이벽(1)에 소정 간격으로 매립된 보강재에 연결부재(110)를 설치하는 단계; (c) 연결부재를 서로 연결하도록 수평 보강재를 설치하는 단계; (d) 수평 보강재와 연결부재(110) 중 적어도 어느 하나에 바닥보를 설치하는 단계; (e) 바닥보의 상부에 슬래브(150)를 형성하는 단계; 및 (f) 흙막이벽의 내측으로 벽체(160)를 시공하는 단계;를 포함한다. 연결부재(110) 및 수평 보강재는 벽체(160)에 매립된다. 그리고, 바닥보는 강관(170)을 포함하는데, 강관(170)은 각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성되며 상기 중공에는 콘크리트(C3)가 채워진다. 한편, 강관(170)의 중공에는 콘크리트(C3)가 없고 강관(170)만으로도 토압 지지력을 제공하도록 할 수도 있다.According to another aspect of the present invention, a method of constructing an underground structure includes: (a) constructing a barrier wall 1 along a boundary line of a structure to be constructed; (b) excavating the ground to the inside of the retaining wall (1) to a predetermined depth to perform the digging operation, and installing the connecting member (110) in the reinforcing material embedded in the retaining wall (1) at predetermined intervals; (c) installing horizontal reinforcement to connect the connecting members to each other; (d) installing a floor beam on at least one of the horizontal reinforcement and the connecting member 110; (e) forming a slab 150 on top of the floor beam; And (f) constructing the wall body 160 to the inside of the retaining wall. The connecting member 110 and the horizontal reinforcement are embedded in the wall 160. In addition, the bottom beam includes a steel pipe 170, the steel pipe 170 has a rectangular or circular cross-sectional shape and a hollow is formed along the longitudinal direction therein, the hollow is filled with concrete (C3). On the other hand, there is no concrete (C3) in the hollow of the steel pipe 170 may be to provide a earth pressure bearing force only by the steel pipe 170.

상기 보강재는 강관(4)을 포함하는데, 강관(4)은 각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성되며 상기 중공에는 콘크리트(C1)가 채워진다.The reinforcing material comprises a steel pipe (4), the steel pipe (4) has a square or circular cross-sectional shape therein is formed hollow in the longitudinal direction therein, the hollow is filled with concrete (C1).

상기 수평 보강재는 강관(120)을 포함하는데, 강관(120)은 각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성되며 상기 중공에는 콘크리트(C2)가 채워진다.The horizontal reinforcing material includes a steel pipe 120, the steel pipe 120 has a rectangular or circular cross-sectional shape and a hollow is formed along the longitudinal direction therein, the hollow is filled with concrete (C2).

상기 연결부재에는 수평철근(130)이 삽입되어 연결되도록 관통공(113)이 형성되고, 수평철근(130)은 벽체(160)에 매립되는 것이 바람직하다.Through-holes 113 are formed in the connection member so that the horizontal reinforcement 130 is inserted and connected, and the horizontal reinforcement 130 is embedded in the wall 160.

상기 시공방법은 (d) 단계에서 바닥보를 설치한 후, 흙막이벽의 안쪽 지반을 굴토하는 단계;를 포함하는데, 상기 굴토는 한꺼번에 두 개 지하층 또는 그 이상의 깊이를 굴토할 수 있다. 상기 굴토는 (d) 단계에서 설치된 바닥보에 슬래브(150)를 형성하기 전에 이루어질 수 있다.The construction method includes installing a floor beam in step (d), and then excavating the inner ground of the retaining wall; the excavation may excavate two basement layers or more depths at a time. The gulch may be made before forming the slab 150 in the bottom beam installed in step (d).

상기 (e) 단계는 지하 최하층까지 바닥보를 먼저 설치한 후에 이루어질 수 있다. The step (e) may be performed after installing the floor beams to the basement floor first.

본 발명에 따른 지하 구조물 및 그 시공방법은 다음과 같은 효과를 가진다. Underground structure and construction method according to the invention has the following effects.

첫째, 바닥보의 토압 지지력이 커서 한꺼번에 두 개 층 이상의 지반을 굴토할 수 있기 때문에 시공이 편리하고 공사 기간을 단축할 수 있다. First, because the earth pressure bearing capacity of the floor beam is large, it is possible to excavate more than two floors at once, which makes the construction easier and shorten the construction period.

둘째, 지하 최하층까지 바닥보를 먼저 설치한 후 슬래브를 형성할 수 있기 때문에 시공이 편리하고 공사 기간을 단축할 수 있다. Second, since the floor beams can be installed first to the bottom of the basement and then slab can be formed, the construction is convenient and the construction period can be shortened.

셋째, 지하 구조물의 벽체의 두께를 감소시키더라도 토압에 대한 지지구조를 강화함과 더불어 슬래브의 하중에 견딜 수 있다.Third, even if the thickness of the wall of the underground structure is reduced, the support structure for earth pressure can be strengthened, and the slab can withstand the load.

넷째, 지하 구조물의 벽체의 두께를 감소시켜 벽체를 형성하는 재료의 비용을 감소시킬 수 있고, 지하 구조물의 공간 활용도를 향상시킬 수 있다. Fourth, it is possible to reduce the thickness of the wall of the underground structure to reduce the cost of the material forming the wall, it is possible to improve the space utilization of the underground structure.

본 발명은 아래 도면들에 의해 구체적으로 설명될 것이지만, 이러한 도면은 본 발명의 바람직한 실시예를 나타낸 것이므로 본 발명의 기술사상이 그 도면에만 한정되어 해석되어서는 아니된다.
도 1은 종래의 흙막이벽에 벽체가 시공된 지하 구조물을 개략적으로 나타낸 단면도.
도 2는 본 발명의 바람직한 실시예에 따른 지하 구조물을 나타낸 사시도.
도 3은 도 2의 지하 구조물을 나타낸 평면도.
도 4는 도 2의 지하 구조물에 구비된 보강재 및 연결부재를 나타낸 사시도.
도 5a는 도 3의 A 부분 확대도.
도 5b는 도 5a의 B-B선에 따른 단면도.
도 6은 도 3의 C-C'선에 따른 단면도.
도 7a 내지 7h는 본 발명의 바람직한 실시예에 따른 지하 구조물을 시공하는 각 단계를 나타내는 도면.
BRIEF DESCRIPTION OF THE DRAWINGS The present invention will be described in detail with reference to the following drawings, which illustrate preferred embodiments of the present invention, and thus the technical idea of the present invention should not be construed as being limited thereto.
1 is a cross-sectional view schematically showing an underground structure in which a wall is constructed on a conventional retaining wall.
2 is a perspective view showing an underground structure according to a preferred embodiment of the present invention.
3 is a plan view showing the underground structure of FIG.
4 is a perspective view showing a reinforcing member and a connection member provided in the underground structure of FIG.
5A is an enlarged view of a portion A of FIG. 3;
FIG. 5B is a cross sectional view along line BB of FIG. 5A;
6 is a cross-sectional view taken along the line CC ′ of FIG. 3.
7a to 7h are diagrams illustrating each step of constructing an underground structure according to a preferred embodiment of the present invention.

이하 첨부된 도면을 참조로 본 발명의 바람직한 실시예를 상세히 설명한다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일 실시예에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. Prior to this, terms or words used in the specification and claims should not be construed as having a conventional or dictionary meaning, and the inventors should properly explain the concept of terms in order to best explain their own invention. Based on the principle that can be defined, it should be interpreted as meaning and concept corresponding to the technical idea of the present invention. Therefore, the embodiments described in this specification and the configurations shown in the drawings are merely the most preferred embodiments of the present invention and do not represent all the technical ideas of the present invention. Therefore, It is to be understood that equivalents and modifications are possible.

한편, 본 발명은 콘크리트 슬래브를 지지하기 위한 바닥보가 각형 또는 원형의 강관으로 이루어지고 상기 강관의 내부에 콘크리트가 채워진 것을 특징으로 한다. 이러한 바닥보는 수평 보강재와 연결부재 중의 적어도 어느 하나에 설치될 수 있는데, 아래에서는 설명의 편의를 위해 바닥보가 연결부재에 설치된 것만을 설명하기로 한다. 바닥보가 수평 보강재에 설치된 것 또는 바닥보가 연결부재와 수평 보강재에 모두 설치된 것은 아래의 설명을 참조한 당업자가 쉽게 알 수 있을 것이므로 그 설명을 생략하기로 한다. On the other hand, the present invention is characterized in that the floor beam for supporting the concrete slab made of a square or circular steel pipe and the concrete is filled in the interior of the steel pipe. Such a bottom beam may be installed on at least one of the horizontal reinforcement and the connecting member. Hereinafter, only the bottom beam is installed on the connecting member for convenience of description. Since the floor beam is installed in the horizontal reinforcement or the floor beam is installed in both the connecting member and the horizontal reinforcing material will be easily understood by those skilled in the art with reference to the following description, the description thereof will be omitted.

도 2는 본 발명의 바람직한 실시예에 따른 지하 구조물을 나타낸 사시도이고, 도 3은 상기 지하 구조물을 나타낸 평면도이다.2 is a perspective view showing an underground structure according to a preferred embodiment of the present invention, Figure 3 is a plan view showing the underground structure.

도면을 참조하면, 지하 구조물은 흙막이벽(1)에 소정간격으로 매립된 보강재와, 보강재에 설치된 연결부재(110)와, 연결부재(110)를 연결하도록 설치된 수평 보강재 및, 수평 보강재와 연결부재(110) 중 적어도 어느 하나에 설치된 바닥보를 구비한다. Referring to the drawings, the underground structure is a reinforcement embedded in the retaining wall (1) at a predetermined interval, the horizontal reinforcement and the horizontal reinforcement and the connecting member 110 installed to connect the connecting member 110 and the connecting member 110 installed in the reinforcing material The floor beam provided in at least one of the 110 is provided.

상기 흙막이벽(1)은 지반이 붕괴되는 것을 방지하기 위하여 건축물이 세워지는 경계선을 따라 설치되는 것으로서, 본 명세서에서는 이러한 흙막이벽(1)이 CIP 공법에 의하여 형성된 것으로 설명하기로 한다. 그러나, 흙막이벽(1)이 종래의 파일 토류판, 소일시멘트 월(SCW), 다이아프램 월(Diaphragm wall) 등에 의해서도 형성될 수 있는 것으로 이해되어야 한다. 상기 CIP 공법에 대해서는 전술한 바 있으므로 상세한 설명을 생략하기로 한다.The barrier wall (1) is to be installed along the boundary line on which the building is erected to prevent the ground from collapsing, in the present specification will be described as such a barrier wall (1) formed by the CIP method. However, it should be understood that the retaining wall 1 may also be formed by conventional pile earth plate, small cement wall (SCW), diaphragm wall, or the like. Since the CIP method has been described above, a detailed description thereof will be omitted.

상기 보강재는 흙막이벽(1)에 소정 간격으로 매립된다. 이하에서는 흙막이벽(1)을 이루는 기둥 중 보강재가 매립된 기둥을 철골기둥(2)이라 한다. The reinforcing material is embedded in the retaining wall 1 at predetermined intervals. Hereinafter, a column in which the reinforcing material is embedded among the pillars constituting the retaining wall 1 is called a steel column 2.

보강재는 흙막이벽(1)의 토압 지지력을 강화하는데, 본 발명에서는 그 내부에 콘크리트(C1)가 채워진 각형 또는 원형의 강관(4)이 보강재로서 사용되는 것이 바람직하다. 강관(4)의 내부에는 그 길이방향으로 중공이 형성되어 있는데, 상기 중공에는 콘크리트(C1)가 채워진다. 그 내부에 콘크리트(C1)가 채워진 강관(4)은 H 형강 등에 비하여 토압에 대한 지지력이 크다는 장점이 있다. The reinforcing material reinforces the earth pressure bearing force of the retaining wall 1, and in the present invention, it is preferable that a rectangular or circular steel pipe 4 filled with concrete C1 is used as the reinforcing material. A hollow is formed in the longitudinal direction of the steel pipe 4, and the hollow is filled with concrete (C1). Steel pipe 4 filled with concrete (C1) therein has the advantage that the bearing capacity for earth pressure is greater than H-shaped steel.

상기 '각형 강관'은 삼각형, 사각형, 오각형, 육각형 등의 단면을 가진 강관을 의미하고, '원형 강관'은 수학적인 의미의 원형 단면을 가진 강관 뿐만 아니라 원형에 근접한 단면 형상을 가진 강관도 의미한다. The 'square steel pipe' means a steel pipe having a cross section of a triangle, a square, a pentagon, a hexagon, and the like, and the 'round steel pipe' refers to a steel pipe having a cross-sectional shape close to a circle as well as a steel pipe having a circular cross section of a mathematical meaning. .

상기 콘크리트(C1)는 지반 천공 후 케이싱을 설치하고 강관을 케이싱의 내부에 설치한 후 케이싱 내부에 콘크리트를 타설할 때 한꺼번에 타설될 수도 있고, 공장에서 강관(4) 내부에 미리 타설되어 양생될 수도 있다. The concrete (C1) may be installed at the same time when installing the casing after the drilling of the ground and installing the steel pipe inside the casing at the same time, when the concrete is placed inside the casing, may be pre-poured inside the steel pipe (4) in the factory have.

상기 연결부재(110)는 흙막이벽(1)에 소정 간격으로 설치되는데, 도 4에 나타난 바와 같이 소정 길이를 갖는 T 형강인 것이 바람직하다. 구체적으로, 연결부재(110)는 강관(4)에 결합된다. 이 때, 연결부재(110)를 설치시 강관(4)을 둘러싼 철골기둥(2)의 콘크리트를 일부 파취(破取)하여 강관(4)을 부분 노출시킨 후, 이 노출된 부분에 연결부재(110)를 결합한다. 상기 연결부재(110)는 용접 또는 볼트 및 너트에 의하여 강관(4)에 고정된다. 한편, 연결부재(110)로는 T 형강 이외에 H 형강도 사용될 수 있다. The connecting member 110 is installed at a predetermined interval on the retaining wall 1, it is preferable that the T-shaped steel having a predetermined length as shown in FIG. Specifically, the connection member 110 is coupled to the steel pipe (4). At this time, when the connecting member 110 is installed, the concrete of the steel pillars 2 surrounding the steel pipe 4 is partially trapped to partially expose the steel pipe 4, and then the connecting member ( 110). The connecting member 110 is fixed to the steel pipe (4) by welding or bolts and nuts. On the other hand, the connection member 110 may be used in addition to the H-shaped steel H-shaped steel.

연결부재(110)는 지하 구조물의 지하층 전체 구간의 길이와 동일한 길이를 갖도록 제작되어 설치될 수 있지만, 선택적으로 필요한 구간에만 설치될 수도 있다. 상기 필요한 구간은 슬래브를 타설하기 위하여 설치되는 바닥보(140)의 설치 구간 및 벽체(도 7h의 '160'참조)의 강성을 증가시킬 수 있는 최소의 구간을 의미하는 것으로 이해될 수 있다.The connection member 110 may be manufactured and installed to have the same length as the length of the entire basement section of the underground structure, but may be selectively installed only in the required section. The necessary section may be understood to mean a minimum section that can increase the stiffness of the installation section and the wall (see '160' in FIG. 7H) of the floor beam 140 installed for placing the slab.

이러한 연결부재(110)는 벽체(160)를 타설시 벽체 콘크리트에 매립되어 벽체(160)의 강성을 증대시키는 역할을 한다.The connecting member 110 is embedded in the wall concrete when placing the wall 160 serves to increase the rigidity of the wall 160.

한편, 연결부재(110)에는 연결부재(110)의 길이방향을 따라 복수의 관통공(113)이 형성된다. 관통공(113)은 후술할 수평 보강재(120)의 아래에 위치하도록 형성된다. On the other hand, the connection member 110 is formed with a plurality of through-holes 113 along the longitudinal direction of the connection member 110. The through hole 113 is formed to be located below the horizontal reinforcement member 120 to be described later.

관통공(113)에는 수평철근(130)이 삽입되어 설치된다. 도 5a 및 도 5b에 나타난 바와 같이, 수평철근(130)은 이웃하는 수평철근(130)과 결합되어 연결된다. 수평철근(130)이 삽입되어 설치됨에 따라 벽체(160)의 강성을 증가시킴은 물론, 횡토압에 대한 저항력을 향상시키게 된다. 아울러, 연결부재(110)에 형성된 관통공(113) 사이로 벽체 콘크리트가 타설됨으로써 연결부재(110)와 벽체 콘크리트와의 결합력이 높아진다. 한편, 수평철근(130)은 수학적인 의미의 수평으로 설치될 수도 있지만, 수직보다는 수평에 상대적으로 가깝게 기울어지도록 설치될 수도 있다.The horizontal reinforcing bars 130 are inserted into the through holes 113. As shown in Figure 5a and 5b, the horizontal reinforcement 130 is coupled to the neighboring horizontal reinforcement 130. As the horizontal reinforcement 130 is inserted and installed, the rigidity of the wall 160 is increased, as well as the resistance to transverse earth pressure is improved. In addition, the wall concrete is poured between the through-holes 113 formed in the connecting member 110, the coupling force between the connecting member 110 and the wall concrete is increased. On the other hand, the horizontal reinforcement 130 may be installed horizontally in a mathematical sense, but may be installed to be inclined relatively close to the horizontal rather than vertical.

본 발명에 따르면, 수평 보강재는 연결부재(110)를 서로 연결하도록 설치된다. 수평 보강재는 흙막이벽(1)을 지지하는 역할을 한다.According to the invention, the horizontal reinforcement is installed to connect the connecting members 110 to each other. The horizontal reinforcement serves to support the retaining wall 1.

이러한 수평 보강재는 각형 또는 원형의 강관(120)으로 이루어질 수 있다. 강관(120)의 내부에는 그 길이방향을 따라 중공이 형성되어 있는데, 상기 중공에는 콘크리트(C2)가 타설되어 채워진다. 상기 콘크리트(C2)의 타설은 강관(120)에 형성된 주입공(123)을 통해 이루어진다. 콘크리트(C2)가 채워진 강관(120)은 H 형강 등에 비하여 토압에 대한 지지력이 크다는 장점이 있다.This horizontal reinforcement may be made of a steel pipe 120 of the square or circular. Inside the steel pipe 120, a hollow is formed along its longitudinal direction, and the hollow is filled with concrete C2. The casting of the concrete (C2) is made through the injection hole 123 formed in the steel pipe (120). Steel pipe 120 filled with concrete (C2) has an advantage that the bearing capacity for earth pressure is greater than H-shaped steel.

강관(120)은 연결부재(110)와 용접 등에 의해 연결된다. 즉, 도시된 바와 같이 강관(120)을 연결부재(110)의 플랜지(111) 및 웨브(112)에 각각 용접하여 결합시킬 수 있다. 또한, 비록 도면에는 나타나지 않았지만, 강관(120)을 플랜지(111) 및/또는 웨브(112)에 볼트 및 너트를 이용하여 결합시킬 수도 있다.Steel pipe 120 is connected to the connecting member 110 by welding or the like. That is, as shown, the steel pipe 120 may be welded to the flange 111 and the web 112 of the connection member 110 to be coupled to each other. In addition, although not shown in the drawings, the steel pipe 120 may be coupled to the flange 111 and / or web 112 using bolts and nuts.

전술한 바와 마찬가지로, 상기 '각형 강관'은 삼각형, 사각형, 오각형, 육각형 등의 단면을 가진 강관을 의미하고, '원형 강관'은 수학적인 의미의 원형 단면을 가진 강관 뿐만 아니라 원형에 근접한 형상의 단면을 가진 강관도 의미한다. 아울러, '수평 보강재'의 '수평'은 수학적 의미의 수평만을 의미하는 것이 아니라 수직에 비하여 수평에 상대적으로 가까운 것도 포함하는 의미로 사용된다. 따라서, 본 발명에서 수평 보강재가 반드시 수학적 의미의 수평을 이루도록 설치되어야 하는 것은 아니다.As described above, the 'square steel pipe' means a steel pipe having a cross section of a triangle, a square, a pentagon, a hexagon, and the like, and the 'circular steel pipe' refers to a cross section of a shape close to a circular shape as well as a steel pipe having a circular cross section of a mathematical meaning. It also means steel pipe with. In addition, the 'horizontal' of the 'horizontal reinforcement' is used not only to mean the horizontal in the mathematical sense but also to include a relatively close to the horizontal than the vertical. Therefore, in the present invention, the horizontal reinforcing material is not necessarily installed to be horizontal in the mathematical sense.

상기와 같은 수평 보강재는 벽체(160) 시공시 연결부재(110)와 함께 벽체 콘크리트에 매립되어 영구 구조체가 된다.The horizontal reinforcement as described above is embedded in the wall concrete together with the connection member 110 when the wall 160 is constructed to be a permanent structure.

강관(120)에는 길이방향을 따라 소정 간격으로 주입공(123)이 형성된다. 주입공(123)을 통해서 콘크리트(C2)가 주입된다. 또한, 주입공(123)은 강관(120) 내부의 콘크리트(C2)와 벽체 콘크리트 사이의 결합력을 높인다.The steel pipe 120 is formed with injection holes 123 at predetermined intervals along the longitudinal direction. Concrete C2 is injected through the injection hole 123. In addition, the injection hole 123 increases the bonding force between the concrete (C2) and the wall concrete in the steel pipe 120.

아울러, 수평 보강재와 흙막이벽(1) 사이에는 이격부재(128)가 설치될 수 있다. 이격부재(128)는 블록 형상 예를 들어, 직육면체 형상으로 형성될 수 있는데, 수평 보강재(120)와 흙막이벽(1) 사이에 공간을 형성함으로써 수평철근(130)이 지나갈 수 있는 공간을 형성한다. 수평철근(130)에 대해서는 전술한 바 있다.In addition, a spacer 128 may be installed between the horizontal reinforcement and the retaining wall 1. The spacer member 128 may be formed in a block shape, for example, in a rectangular parallelepiped shape, thereby forming a space between the horizontal reinforcement member 120 and the retaining wall 1 to form a space through which the horizontal rebar 130 may pass. . The horizontal rebar 130 has been described above.

이와 같이, 기존 흙막이벽(도 1의 w)의 외곽면으로부터 형성되는 벽체(도 1의 5)에 비하여, 본 발명에서는 연결부재(110)의 일부가 흙막이벽(1)에 매립되어 설치됨에 따라 효율적으로 벽체의 두께를 감소시킬 수 있고 연결부재(110) 및 수평 보강재가 벽체(160)에 매립됨에 따라 벽체(160)의 강성을 증가시켜 벽체(160)의 두께를 감소시킬 수 있다. Thus, as compared to the wall (5 of FIG. 1) formed from the outer surface of the existing retaining wall (w in Figure 1), in the present invention, as a portion of the connecting member 110 is embedded in the retaining wall (1) The thickness of the wall can be efficiently reduced, and as the connecting member 110 and the horizontal reinforcement are embedded in the wall 160, the rigidity of the wall 160 can be increased to reduce the thickness of the wall 160.

또한, 수평 보강재와 보강재로서 강관(4)(120)을 사용함으로써, 기존의 흙막이벽(w) 및 벽체(5)에 비하여, 흙막이벽(1) 및 벽체(160)의 강성을 증가시킬 수 있다. In addition, by using the steel pipes 4 and 120 as horizontal reinforcement and reinforcement, the stiffness of the retaining wall 1 and the wall 160 can be increased compared to the existing retaining wall w and the wall 5. .

한편, 바닥보는 연결부재(110)에 설치되어 콘크리트 슬래브(도면에 미도시)를 지지한다. 바닥보는 연결부재(110)를 서로 연결하도록 설치되거나 연결부재(110)와 지하구조물의 기둥(7)을 서로 연결하도록 설치된다. 한편, 도면은 바닥보가 연결부재(110)에 설치된 것을 도시하고 있지만, 바닥보는 수평 보강재에 설치되거나, 수평 보강재 및 연결부재(110) 모두에 설치될 수 있다. 즉, 바닥보는 연결부재(110)와 수평 보강재 중 적어도 어느 하나에 설치될 수 있다. 다만, 아래에서는 설명의 편의를 위해서 바닥보가 연결부재(110)에 설치된 것만을 설명하기로 한다. On the other hand, the bottom beam is installed on the connecting member 110 to support the concrete slab (not shown in the figure). The girder is installed to connect the connecting members 110 to each other or to connect the connecting members 110 and the pillars 7 of the underground structure to each other. On the other hand, although the drawing shows that the floor beam is installed in the connecting member 110, the floor beam may be installed in the horizontal reinforcement, or may be installed in both the horizontal reinforcement and the connecting member 110. That is, the bottom beam may be installed on at least one of the connecting member 110 and the horizontal reinforcement. However, below, only the bottom beam is installed in the connecting member 110 for the convenience of description.

도 5a 내지 도 6에 나타난 바와 같이, 바닥보는 각형 또는 원형의 단면 형상을 갖는 강관(170)으로 이루어질 수 있다. 강관(170)의 내부에는 그 길이방향을 따라 중공이 형성되어 있는데, 상기 중공에는 콘크리트(C3)가 타설되어 채워진다. 상기 콘크리트(C3)의 타설은 주입홀(171)을 통해서 이루어질 수 있다. 한편, 본 발명에 따른 바닥보는 상기 중공에 콘크리트(C3)가 타설되지 않고 강관(170)만으로 이루어질 수도 있다. As shown in Figures 5a to 6, the bottom beam may be made of a steel pipe 170 having a square or circular cross-sectional shape. Inside the steel pipe 170, a hollow is formed along its longitudinal direction, and the hollow is filled with concrete C3. The casting of the concrete C3 may be made through the injection hole 171. On the other hand, the floor beam according to the present invention may be made of only the steel pipe 170 without placing concrete (C3) in the hollow.

강관(170)은 연결부재(110)의 플랜지(111)에 용접되어 설치될 수 있다. 상기 용접에 대한 대안으로써, 강관(170)은 볼트와 너트에 의해 플랜지(111)에 결합될 수도 있다. 예를 들어, 강관(170)의 끝단에 소정 폭과 높이를 가진 평판(도면에 미도시)을 용접하여 결합시키고, 상기 평판과 플랜지(111)를 관통하는 볼트(도면에 미도시)와 너트를 이용하여 상기 평판과 플랜지(111)를 서로 결합시킬 수도 있다. 이러한 결합은 본 명세서를 참조한 당업자가 쉽게 알 수 있을 것이므로 더 이상의 자세한 설명은 생략하기로 한다. The steel pipe 170 may be welded to the flange 111 of the connection member 110 to be installed. As an alternative to the welding, steel pipe 170 may be coupled to flange 111 by bolts and nuts. For example, by welding a flat plate (not shown) having a predetermined width and height to the end of the steel pipe 170, and bolts (not shown) and nuts penetrating the flat plate and the flange 111 The flat plate and the flange 111 may be coupled to each other by using. Such combinations will be easily understood by those skilled in the art with reference to the present specification, and thus detailed descriptions thereof will be omitted.

콘크리트(C3)가 채워진 강관(170)은, H 형강 등에 비하여, 토압에 대한 지지력이 크다. 따라서, 본 발명에 따르면, 바닥보를 이용하여 토압을 지지함으로써 한꺼번에 두 층 이상의 지반을 굴토할 수 있다. 다시 말해서, 기존에는 바닥보를 설치한 후, 상기 바닥보에 콘크리트 슬래브를 형성함으로써 콘크리트 슬래브가 토압을 지지하도록 하였지만, 본 발명은 바닥보가 토압을 지지할 수 있기 때문에 바닥보를 설치한 후에 곧바로 콘크리트 슬래브를 반드시 형성할 필요가 없고 바닥보를 설치한 후에 두 층 이상의 지반을 한꺼번에 굴토할 수 있다. 또한, 지하 최하층까지 바닥보를 먼저 설치한 후 각 층의 바닥보에 콘크리트 슬래브를 형성할 수도 있기 때문에 공사가 편리해지고 신속해진다는 장점을 가진다. 이 점에 대해서는 아래에서 추가로 설명된다. The steel pipe 170 filled with concrete C3 has a larger bearing capacity against earth pressure than H-shaped steel or the like. Therefore, according to the present invention, by supporting the earth pressure using a floor beam, it is possible to excavate more than two layers of ground at once. In other words, conventionally, after installing the floor beam, the concrete slab to support the earth pressure by forming a concrete slab on the floor beam, but in the present invention, because the floor beam can support the earth pressure, the concrete slab immediately after installing the floor beam It is not necessary to form and it is possible to excavate more than one layer of ground at once after installing the beams. In addition, since the concrete beams may be formed on the floor beams of each floor after installing the floor beams to the basement floor first, the construction is convenient and speedy. This point is discussed further below.

이와 같이, 본 발명은 흙막이벽(1) 및 벽체(160)의 강성을 증가시킴으로써 종래의 흙막이벽(w) 및 벽체(5)에 비해 두께를 얇게 할 수 있고, 이에 따라 콘크리트, 철근 등의 재료 사용을 절감할 수 있어 경제적이고 벽체(160)의 두께를 얇게 할 수 있기 때문에 지하 구조물의 공간 활용성을 높일 수 있다.As described above, the present invention can increase the rigidity of the retaining wall 1 and the wall 160 to make the thickness thinner than the conventional retaining wall w and the wall 5, and accordingly, materials such as concrete and reinforcing bars Since the use can be reduced and economical and the thickness of the wall 160 can be reduced, space utilization of the underground structure can be increased.

그러면, 도 7a 내지 도 7h를 참조하여, 상기와 같은 지하 구조물의 시공방법을 설명하기로 한다.Then, the construction method of the underground structure as described above will be described with reference to Figure 7a to 7h.

먼저, 도 7a에 도시된 바와 같이, 지하 구조물이 건축될 외곽 경계선을 따라 흙막이벽(1)을 구축한다. 흙막이벽(1)은, 주지하는 바와 같이, 지하 터파기 시 주위 토사가 붕괴되는 것을 방지하기 위하여 지하 구조물의 외부 경계측에 설치되는 구조물을 말하는 것으로, 이와 같은 흙막이벽(1)은 예컨대 CIP 공법에 의하여 형성될 수 있다. 또한, 종래의 토류판 흙막이벽이나 소일시멘트 월(Soil Cement Wall), 다이아프램 월(Diaphragm wall) 등에 의하여 흙막이벽을 구축할 수도 있다.First, as shown in FIG. 7A, the retaining wall 1 is constructed along the outer boundary where the underground structure is to be built. As the barrier wall 1 is known, it refers to a structure which is installed on the outer boundary side of the underground structure to prevent the surrounding soil from collapsing during the excavation of the underground. Such a barrier wall 1 is, for example, a CIP method. It can be formed by. In addition, a barrier wall may be formed by a conventional earth plate barrier wall, a soil cement wall, a diaphragm wall, or the like.

흙막이벽(1)에는 소정 간격으로 보강재 즉 강관(4)이 매립된다. 보강재는 그 내부에 콘크리트(C1)가 채워진 강관(4)이므로 기존의 H 형강 등에 비해서 토압 지지력이 크다. Reinforcing material, that is, steel pipe (4) is embedded in the retaining wall (1) at predetermined intervals. Since the reinforcing material is a steel pipe 4 filled with concrete (C1) therein, the earth pressure bearing force is larger than that of the conventional H-shaped steel.

한편, 도 7a 내지 도 7h에 도시된 흙막이벽(1)은 설명의 편의상 강관(4)이 보여지도록 도시한 것이다. On the other hand, the retaining wall (1) shown in Figure 7a to 7h is shown to show the steel pipe (4) for convenience of description.

부가적으로, 흙막이벽(1)의 구축시, 건축물을 지지하는 기둥(도 3의 7, 도 7a 내지 도 7h에는 미도시)을 선택적으로 설치할 수 있다. In addition, when constructing the retaining wall 1, a pillar supporting the building (not shown in FIGS. 3 and 7A to 7H) may be selectively installed.

다음으로, 도 7b에 도시된 바와 같이, 흙막이벽(1)의 내측 토사에 대하여 1차 터파기를 수행한 후, 흙막이벽(1)에 연결부재(110)를 설치한다. 이때, 1차 터파기의 깊이는 지상 1층 바닥보 및 연결부재(110)를 설치하기에 적당한 깊이로 굴착한다.Next, as shown in FIG. 7B, after performing the first trench on the inner soil of the retaining wall 1, the connecting member 110 is installed on the retaining wall 1. At this time, the depth of the primary trench is excavated to a suitable depth to install the ground floor floor beam and the connecting member 110.

구체적으로, 연결부재(110)는 흙막이벽(1)에 매립된 강관(4)에 설치된다. 여기서, 연결부재(110)는 T 형강이 사용될 수 있지만, H 형강도 사용될 수 있다. 연결부재(110)는 강관(4)에 용접 또는 볼트 등에 의하여 고정된다. Specifically, the connection member 110 is installed in the steel pipe (4) embedded in the retaining wall (1). Here, the connecting member 110 may be used T-shaped steel, H-shaped steel may also be used. The connecting member 110 is fixed to the steel pipe 4 by welding or bolts.

한편, 흙막이벽(1)을 이루는 각각의 기둥은 그 단면이 원형으로 이루어지는데, 강관(4)의 일면이 노출되도록 강관(4)을 덮는 콘크리트의 일부를 제거한 후 연결부재(110)를 설치한다.On the other hand, each pillar constituting the retaining wall (1) is made of a circular cross-section, and removes a part of the concrete covering the steel pipe 4 so that one surface of the steel pipe 4 is installed after the connection member 110 is installed. .

연결부재(110)는 이후의 공정에서 연결부재(110) 사이에 설치되는 수평 보강재(120) 및 연결부재(110)에 설치되는 바닥보를 지지한다.The connection member 110 supports the horizontal reinforcement 120 is installed between the connection member 110 in the subsequent process and the bottom beam installed in the connection member 110.

이어서, 도 7c에 나타난 바와 같이, 이격부재(128) 및 수평 보강재를 연결부재(110) 사이에 설치한다. 전술한 바와 같이, 수평 보강재는 콘크리트(C2)가 내부에 채워진 강관(120)이기 때문에 기존의 H 형강 등에 비해서 토압에 대한 지지력이 크다. 강관(120)은 연결부재(110)의 웨브(111) 및/또는 플랜지(112)에 용접 등에 의해 결합될 수 있다. Subsequently, as shown in FIG. 7C, the spacer 128 and the horizontal reinforcement are installed between the connection members 110. As described above, since the horizontal reinforcing material is a steel pipe 120 filled with concrete (C2) therein, the bearing capacity for earth pressure is greater than that of the conventional H-shaped steel. Steel pipe 120 may be coupled to the web 111 and / or flange 112 of the connecting member 110 by welding or the like.

다음으로, 수평철근(130)을 관통공(113)에 삽입하여 설치한다. 이격부재(128)는 강관(120)과 흙막이벽(1) 사이에 공간을 형성한다. 수평철근(130)은 이러한 공간에 설치되되, 관통공(113)을 관통하도록 설치되어 이웃하는 수평철근(130)과 서로 연결된다. Next, the horizontal reinforcing bar 130 is inserted into the through hole 113 and installed. The spacer member 128 forms a space between the steel pipe 120 and the retaining wall 1. Horizontal reinforcement 130 is installed in such a space, it is installed to pass through the through hole 113 is connected to the neighboring horizontal reinforcement 130.

수평 보강재는 흙막이벽(1)을 지지하는 역할을 한다. 또한, 수평 보강재는 벽체(160)에 매립됨으로써 벽체(160)의 강성을 증대시키는 역할을 한다.The horizontal reinforcement serves to support the retaining wall 1. In addition, the horizontal reinforcing material is embedded in the wall 160 serves to increase the rigidity of the wall 160.

이어서, 도 7d에 나타난 바와 같이, 바닥보인 강관(170)을 연결부재(110)에 설치한다. 도 7d는 강관(170)의 양쪽 끝단이 연결부재(110)에 설치된 것을 도시하고 있으나, 강관(170)은 연결부재(110)와 기둥(7)을 연결하도록 설치될 수도 있다.Subsequently, as shown in FIG. 7D, the bottom bore steel pipe 170 is installed in the connection member 110. 7D illustrates that both ends of the steel pipe 170 are installed at the connecting member 110, but the steel pipe 170 may be installed to connect the connecting member 110 and the pillar 7.

바닥보는 흙막이벽(1)으로부터 가해지는 토압을 지지하는 스트러트(strut)와 같은 역할을 하며, 지하 공사의 완료 후에는 콘크리트 슬래브를 지지하는 영구 구조물로서 존치된다.The girder acts as a strut supporting the earth pressure applied from the retaining wall 1, and after completion of the underground construction, it is maintained as a permanent structure supporting the concrete slab.

지상 1층의 바닥보 설치가 완료되면, 지반을 추가적으로 굴토한다. 그런데, 본 발명에서는 강관(170)으로 이루어진 바닥보가 토압에 대한 지지력이 매우 크기 때문에 한꺼번에 두 개 층 이상의 지반을 굴토할 수 있다. 즉, 기존에는 바닥보를 설치하고 슬래브를 타설하여 토압에 대한 지지력을 확보한 다음에 1개 층의 깊이에 상응하는 지반을 굴토하였지만, 본 발명에서는 바닥보의 토압 지지력이 크기 때문에 바닥보를 설치한 후 콘크리트 슬래브를 타설할 필요성이 없고 한꺼번에 두 개 층 이상의 깊이를 굴토할 수 있다. 도 7e는 지상 1층의 바닥보를 설치한 후 바닥보에 슬래브를 형성하지 않은 상태에서 두 개 층의 깊이에 해당하는 지반을 한꺼번에 굴토한 것을 예시적으로 보여준다. 따라서, 본 발명은 공사가 편리해지고 공사기간을 단축시킬 수 있다는 효과를 가진다.After the installation of the floor beams on the ground floor is completed, additional soil is excavated. By the way, in the present invention, the floor beam made of steel pipe 170 can excavate more than two layers of ground at a time because the support force for earth pressure is very large. That is, in the past, after installing the floor beam and placing the slab to secure the bearing capacity for earth pressure, the ground corresponding to the depth of one layer was excavated, but in the present invention, after the floor beam is installed because the earth pressure bearing capacity of the floor beam is large. There is no need to cast concrete slabs and it is possible to excavate more than two layers at once. Figure 7e shows an example of excavating the ground corresponding to the depth of the two layers at once without installing a slab on the floor beam after installing the floor beam of the ground floor. Therefore, the present invention has the effect that the construction can be convenient and the construction period can be shortened.

이어서, 도 7f에 나타난 바와 같이, 지하 1층 및 지하 2층에 해당하는 높이에서 연결부재(110)를 보강재에 설치하고 연결부재(110)에 수평 보강재와 바닥보 및 수평철근(130)을 설치한다. 연결부재(110)에 수평 보강재와 바닥보 및 수평철근(130)을 설치하는 것은 전술한 방법과 동일하게 이루어질 수 있다. Subsequently, as shown in FIG. 7F, the connecting member 110 is installed in the reinforcing material at the height corresponding to the first and second basement floors, and the horizontal reinforcing material and the floor beam and the horizontal reinforcement 130 are installed in the connecting member 110. do. Installing the horizontal reinforcement and the floor beam and horizontal reinforcement 130 to the connecting member 110 can be made in the same manner as described above.

상기와 같은 공정을 거쳐 지하 최하층까지 바닥보를 설치하고, 이어서 기초바닥 콘크리트(도 7g의 190)를 타설한다. 한편, 벽체(160)를 시공하기 전에 철근망으로 형성된 보강철근(180)을 설치할 수도 있다. The floor beam is installed to the lowest basement floor through the above process, and then the foundation floor concrete (190 in FIG. 7g) is poured. On the other hand, reinforcing bars 180 formed of a reinforcing bar network may be installed before the wall 160 is constructed.

다음으로, 도 7h에 나타난 바와 같이, 콘크리트를 타설하여 슬래브(150)를 형성하고 벽체(160)를 형성한다. 본 발명에서는 각 층의 바닥보를 설치한 후 곧바로 해당 층의 슬래브(150)를 형성할 수도 있지만, 지하 최하층까지 바닥보를 설치한 후 각 층의 슬래브(150)를 형성할 수도 있는데, 이렇게 바닥보를 모두 설치한 후 한꺼번에 슬래브(150)를 형성하면 공사가 편리해지고 공사기간이 단축될 수 있다. Next, as shown in FIG. 7H, the concrete is poured to form the slab 150 and the wall 160. In the present invention, the floor slab 150 may be formed immediately after installing the floor beams of each layer, but after installing the floor beams to the basement floor, the floor slabs 150 may be formed on each floor. If the slab 150 is formed at the same time after installation, the construction is convenient and the construction period can be shortened.

한편, 슬라브(150)는 당해 층의 전체 면적에 대해 타설 시공되는 것이 아니라, 외곽 가장자리 부분은 남겨두고 타설하여 슬라브(150)의 외곽 경계선이 흙막이벽(1)으로부터 소정거리 이격된 상태로 형성되도록 한다. 예컨대, 슬라브(150)의 외곽 경계부가 이후 시공될 지하 벽체(160)의 내측 경계선과 일치하거나 더 안쪽으로 위치할 수 있도록 타설 시공되도록 한다. 이와 같이 구성한 이유는 이후의 지하 벽체(160) 시공시에 벽체(160)의 연속시공이 가능할 수 있도록 하기 위한 것이다. 즉, 슬래브(150)와 연결부재(110) 사이 및 슬래브(150)와 수평 보강재 사이에 일정한 이격 공간이 형성되어 있음으로써, 종래 공법에서와 같이 지하 외벽이 테두리보 등에 의해 단절됨이 없이, 순타공법에 의해 연속적으로 시공이 가능된다.On the other hand, the slab 150 is not placed over the entire area of the layer, but is poured with leaving the outer edge portion so that the outer boundary of the slab 150 is formed with a predetermined distance away from the retaining wall 1. do. For example, the outer boundary of the slab 150 is to be poured so that it can be located in line with the inner boundary of the underground wall 160 to be constructed later. The reason for this configuration is to enable continuous construction of the wall 160 during the construction of the underground wall 160 afterwards. That is, since a predetermined space is formed between the slab 150 and the connecting member 110 and between the slab 150 and the horizontal reinforcement, as in the conventional method, the underground outer wall is not cut off by the rim beam, etc. Construction can be performed continuously by

슬래브(150) 시공이 완료된 후, 벽체(160)가 아래에서부터 지상까지 상향 시공(순타시공)된다. 이 때, 슬래브(150)의 외곽 경계부가 벽체 예정면까지만 선시공된 상태이므로, 전술한 바와 같이 각 층 슬라브(150)에 의해 단절됨이 없이 벽체(160)를 한 번에 연속 시공할 수 있다.After the construction of the slab 150 is completed, the wall 160 is constructed upward from the bottom to the ground (pneumatic construction). At this time, since the outer boundary portion of the slab 150 is pre-installed only to the wall predetermined surface, as described above, the wall 160 can be continuously constructed at one time without being cut off by each layer slab 150.

이상과 같이, 본 발명은 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 발명은 이것에 의해 한정되지 않으며 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에 의해 본 발명의 기술사상과 아래에 기재될 특허청구범위의 균등범위 내에서 다양한 수정 및 변형이 가능함은 물론이다.While the present invention has been particularly shown and described with reference to exemplary embodiments thereof, it is to be understood that the invention is not limited to the disclosed exemplary embodiments. It will be understood that various modifications and changes may be made without departing from the scope of the appended claims.

C1, C2, C3 : 콘크리트 1: 흙막이벽
110 : 연결부재 113 : 관통공
4, 120, 170 : 강관 130 : 수평철근
150 : 슬래브 160 : 벽체
180 : 보강철근
C1, C2, C3: Concrete 1: retaining wall
110: connecting member 113: through hole
4, 120, 170: steel pipe 130: horizontal rebar
150: slab 160: wall
180: rebar

Claims (12)

흙막이벽에 소정 간격으로 매립된 보강재;
보강재에 결합되는 연결부재;
연결부재를 서로 연결하도록 설치된 수평 보강재; 및
수평 보강재와 연결부재 중 적어도 어느 하나에 설치된 바닥보;를 포함하고,
바닥보는,
각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성된 강관(170)을 포함하고,
연결부재와 수평 보강재는 지하 구조물의 벽체(160)에 매립되는 것을 특징으로 하는 지하 구조물.
Reinforcing material embedded in the earth wall at a predetermined interval;
A connection member coupled to the reinforcement;
Horizontal reinforcement provided to connect the connecting members to each other; And
It includes; the floor beam installed on at least one of the horizontal reinforcement and the connecting member,
Footpath,
It has a rectangular or circular cross-sectional shape and includes a steel pipe 170 formed therein along the longitudinal direction therein,
Underground structure, characterized in that the connection member and the horizontal reinforcement is embedded in the wall (160) of the underground structure.
제1항에 있어서,
강관(170)의 상기 중공에는 콘크리트(C3)가 채워진 것을 특징으로 하는 지하 구조물.
The method of claim 1,
Underground structure, characterized in that the hollow of the steel pipe (170) is filled with concrete (C3).
제2항에 있어서,
강관(170)에는 콘크리트(C3)를 주입하기 위한 주입홀(171)이 형성된 것을 특징으로 하는 지하 구조물.
The method of claim 2,
Steel pipe 170 is an underground structure, characterized in that the injection hole 171 for injecting concrete (C3) is formed.
제2항에 있어서,
수평 보강재는,
각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성되며 상기 중공에는 콘크리트(C2)가 채워진 강관(120)을 포함하는 것을 특징으로 하는 지하 구조물.
The method of claim 2,
Horizontal reinforcement,
Underground structure characterized in that it has a rectangular or circular cross-sectional shape therein is formed in the hollow along the longitudinal direction, the hollow includes a steel pipe (120) filled with concrete (C2).
제4항에 있어서,
강관(120)에는 콘크리트를 주입하기 위한 주입공(123)이 형성된 것을 특징으로 하는 지하 구조물.
5. The method of claim 4,
Steel pipe 120 is an underground structure, characterized in that the injection hole 123 for injecting concrete is formed.
(a) 시공되는 구조물의 경계선을 따라 흙막이벽(1)을 구축하는 단계;
(b) 흙막이벽(1)의 안쪽으로 지반을 소정 깊이로 굴토하여 터파기 작업을 수행하고, 흙막이벽(1)에 소정 간격으로 매립된 보강재에 연결부재(110)를 설치하는 단계;
(c) 연결부재를 서로 연결하도록 수평 보강재를 설치하는 단계;
(d) 수평 보강재와 연결부재(110) 중 적어도 어느 하나에 바닥보를 설치하는 단계;
(e) 바닥보의 상부에 슬래브(150)를 형성하는 단계; 및
(f) 흙막이벽의 내측으로 벽체(160)를 시공하는 단계;를 포함하고,
연결부재(110) 및 수평 보강재가 벽체(160)에 매립되며,
바닥보는,
각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성된 강관(170)을 포함하는 것을 특징으로 하는 지하 구조물의 시공방법.
(a) constructing a retaining wall 1 along a boundary line of the structure to be constructed;
(b) excavating the ground to the inside of the retaining wall (1) to a predetermined depth to perform the digging operation, and installing the connecting member (110) in the reinforcing material embedded in the retaining wall (1) at predetermined intervals;
(c) installing horizontal reinforcement to connect the connecting members to each other;
(d) installing a floor beam on at least one of the horizontal reinforcement and the connecting member 110;
(e) forming a slab 150 on top of the floor beam; And
(f) constructing the wall body 160 to the inside of the retaining wall; and
The connecting member 110 and the horizontal reinforcement is embedded in the wall 160,
Footpath,
Method of constructing an underground structure, characterized in that it comprises a steel pipe (170) having a rectangular or circular cross-sectional shape formed therein along the longitudinal direction therein.
제6항에 있어서,
강관(170)의 상기 중공에는 콘크리트(C3)가 채워진 것을 특징으로 하는 지하 구조물의 시공방법.
The method according to claim 6,
Construction method of an underground structure, characterized in that the hollow of the steel pipe (170) is filled with concrete (C3).
제7항에 있어서,
수평 보강재는,
각형 또는 원형의 단면형상을 갖고 그 내부에 길이방향을 따라 중공이 형성되며 상기 중공에는 콘크리트(C2)가 채워진 강관(120)을 포함하는 것을 특징으로 하는 지하 구조물의 시공방법.
The method of claim 7, wherein
Horizontal reinforcement,
Method of constructing an underground structure, characterized in that it has a rectangular or circular cross-sectional shape and a hollow is formed in the longitudinal direction therein, the hollow includes a steel pipe (120) filled with concrete (C2).
제7항에 있어서,
연결부재에는 수평철근(130)이 삽입되어 연결되도록 관통공(113)이 형성되고,
수평철근(130)은 벽체(160)에 매립되는 것을 특징으로 하는 지하 구조물의 시공방법.
The method of claim 7, wherein
Through-holes 113 are formed in the connecting member so that the horizontal reinforcement 130 is inserted and connected thereto.
Horizontal reinforcement 130 is a method of construction of underground structures, characterized in that embedded in the wall (160).
제7항 내지 제9항 중 어느 한 항에 있어서,
(d1) 상기 (d) 단계에서 바닥보를 설치한 후, 흙막이벽의 안쪽 지반을 굴토하는 단계;를 포함하고,
상기 굴토는 한꺼번에 두 개 지하층 또는 그 이상의 깊이를 굴토하는 것을 특징으로 하는 지하 구조물의 시공방법.
10. The method according to any one of claims 7 to 9,
(d1) after installing the floor beam in the step (d), the step of excavating the inner ground of the retaining wall; includes,
The construction method of the underground structure, characterized in that the excavation of two underground layers or more depth at one time.
제10항에 있어서,
상기 (d1) 단계의 굴토는 (d) 단계에서 설치된 바닥보에 슬래브(150)를 형성하기 전에 이루어지는 것을 특징으로 하는 지하 구조물의 시공방법.
The method of claim 10,
The method of constructing an underground structure, characterized in that the gulto of step (d1) is made before forming the slab (150) on the floor beam installed in step (d).
제11항에 있어서,
상기 (e) 단계는 지하 최하층까지 바닥보를 먼저 설치한 후에 이루어지는 것을 특징으로 하는 지하 구조물의 시공방법.
The method of claim 11,
The step (e) is the construction method of the underground structure, characterized in that after the first to install the bottom beam to the basement floor.
KR1020110084545A 2011-08-24 2011-08-24 Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same KR101296857B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020110084545A KR101296857B1 (en) 2011-08-24 2011-08-24 Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020110084545A KR101296857B1 (en) 2011-08-24 2011-08-24 Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same

Publications (2)

Publication Number Publication Date
KR20130021952A true KR20130021952A (en) 2013-03-06
KR101296857B1 KR101296857B1 (en) 2013-08-20

Family

ID=48174723

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020110084545A KR101296857B1 (en) 2011-08-24 2011-08-24 Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same

Country Status (1)

Country Link
KR (1) KR101296857B1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180007161A (en) * 2016-07-12 2018-01-22 주식회사 엘지씨엔에스 Safe
KR101967693B1 (en) * 2018-07-20 2019-08-19 강문기 CIP retaining wall with for easy construction

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101557038B1 (en) * 2014-01-13 2015-10-02 윤동현 Construction method for underground structure
KR101923973B1 (en) * 2018-03-05 2018-11-30 민병찬 Outer wall construction method of underground structure using the reverse t-type steel composite vertical member
KR101913630B1 (en) * 2018-03-05 2018-10-31 민병찬 Reverse t-type steel composite vertical member for outer wall of the underground structure and the construction method using the same

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100662524B1 (en) * 2005-03-28 2006-12-28 (주)바로건설기술 Double pipe girder struts as permanent system
KR100634726B1 (en) * 2005-04-19 2006-10-16 (주)한국건설공법 Form system for construction of underground slab and method for constructing underground slab and breast wall using the same
KR20100113957A (en) * 2009-04-14 2010-10-22 (주)씨엠파트너스건축사사무소 Joint structure and method for constructing slab of underground structures using the same
KR20110052360A (en) * 2009-11-12 2011-05-18 장성재 Downward construction method of underground structure that enables continuous basement wall using non-wale and diaphragm action of concrete slab

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20180007161A (en) * 2016-07-12 2018-01-22 주식회사 엘지씨엔에스 Safe
KR101967693B1 (en) * 2018-07-20 2019-08-19 강문기 CIP retaining wall with for easy construction

Also Published As

Publication number Publication date
KR101296857B1 (en) 2013-08-20

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR100967497B1 (en) Method for constructing an underground structure
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
KR20140055639A (en) A execution method of architecture beam
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
JP4881555B2 (en) Construction method of underground structure
KR20080007483A (en) Underground retaining wall for public works and method for constructing the same
KR101182704B1 (en) Construction method of undergroud structure using PHC pile
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR101051978B1 (en) Basement structure construction method using PC member
KR101187170B1 (en) Application of under pinning method in remodeling
KR20090090742A (en) Bottom-up construction method of underground structure using permanent strut
KR101169462B1 (en) Top-down construction method using post member
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR20100094140A (en) Wall structure capable of earth retaining and the building method of the same
KR102254227B1 (en) High-strength concrete pile structure with pc pile cap and construction method
KR102362257B1 (en) Top-down construction method
KR101054696B1 (en) Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR101358471B1 (en) architecture using a complex steel pile
KR20120126573A (en) Soil cement wall structure and method for constructing thereof
JP5480744B2 (en) Foundation for structure and its construction method
KR100912574B1 (en) Retaining wall system using strut assembly and excavating method using the same
KR100967496B1 (en) Device for constructing an underground structure
KR102021496B1 (en) Retaining wall construction method and retaining wall structure by the method

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20160804

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20170808

Year of fee payment: 5

FPAY Annual fee payment

Payment date: 20180802

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20190724

Year of fee payment: 7