KR100967496B1 - Device for constructing an underground structure - Google Patents
Device for constructing an underground structure Download PDFInfo
- Publication number
- KR100967496B1 KR100967496B1 KR1020100015362A KR20100015362A KR100967496B1 KR 100967496 B1 KR100967496 B1 KR 100967496B1 KR 1020100015362 A KR1020100015362 A KR 1020100015362A KR 20100015362 A KR20100015362 A KR 20100015362A KR 100967496 B1 KR100967496 B1 KR 100967496B1
- Authority
- KR
- South Korea
- Prior art keywords
- horizontal structure
- layer
- horizontal
- interlayer
- underground
- Prior art date
Links
- 238000010276 construction Methods 0.000 claims abstract description 45
- 238000009412 basement excavation Methods 0.000 claims abstract description 31
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 28
- 239000010959 steel Substances 0.000 claims abstract description 28
- 239000011229 interlayer Substances 0.000 claims description 90
- 239000010410 layer Substances 0.000 claims description 75
- 239000011150 reinforced concrete Substances 0.000 claims description 48
- 230000003014 reinforcing effect Effects 0.000 claims description 32
- 238000000034 method Methods 0.000 claims description 23
- 238000009434 installation Methods 0.000 claims description 20
- 230000008878 coupling Effects 0.000 claims description 12
- 238000010168 coupling process Methods 0.000 claims description 12
- 238000005859 coupling reaction Methods 0.000 claims description 12
- 238000003466 welding Methods 0.000 claims description 4
- 238000003825 pressing Methods 0.000 abstract description 2
- 238000010586 diagram Methods 0.000 description 16
- 230000002787 reinforcement Effects 0.000 description 13
- 239000002689 soil Substances 0.000 description 3
- 239000000463 material Substances 0.000 description 2
- 238000005452 bending Methods 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 239000004567 concrete Substances 0.000 description 1
- 230000003111 delayed effect Effects 0.000 description 1
- 239000000428 dust Substances 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000007373 indentation Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000002250 progressing effect Effects 0.000 description 1
- 238000004904 shortening Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/045—Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/02—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
- E04B1/04—Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements the elements consisting of concrete, e.g. reinforced concrete, or other stone-like material
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D9/00—Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
- E21D9/04—Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0026—Metals
- E02D2300/0029—Steel; Iron
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- General Engineering & Computer Science (AREA)
- Environmental & Geological Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
Description
본 발명은 지하 구조물 구축장치에 관한 것으로서, 보다 상세하게는 층간기둥의 수직도를 향상시키기가 용이하고 공사비를 절감할 수 있도록 하는 지하 구조물 구축장치에 관한 것이다.The present invention relates to an underground structure construction apparatus, and more particularly, to an underground structure construction apparatus that makes it easy to improve the verticality of the interlayer pillar and to reduce the construction cost.
지하구조물을 축조하는데 있어 지금까지의 주요 지하 구조물 시공법은 굴토계획선을 따라 흙막이벽을 설치하고 가설형강지지체로서 토압이나 수압 등의 외력을 지탱하면서 지상에서 지하의 기초바닥까지 굴착 완료한 다음 각 층 구조물을 바닥에서 상부로 순차적으로 축조하면서 순차적으로 가설형강지지체를 해체하여 본 구조물을 시공하는 개착식공법과 흙막이 벽을 설치하고 현장 타설말뚝으로서 철골기둥과 이에 연장된 말뚝기초를 형성하여 지하 구조물의 축조와 동시에 지상구조물을 축조할 수 있는 탑 다운(TOP DOWN)공법과 동일한 방법으로서 지하구조물을 완료한 후 지상구조물을 시공하는 다운워드(DOWNWARD)공법이 있다.In the construction of underground structures, the main construction methods for underground structures have been excavated from the ground to the basement ground after installing the retaining wall along the pit soil plan line and supporting external forces such as earth pressure and water pressure as temporary steel supports. Construct the structure from the bottom to the top, and then install the installation method and soil wall to dismantle the temporary steel support in order to form the steel pillars and the pile foundations extended to the foundation structure. The same method as the TOP DOWN method, which allows the construction of ground structures at the same time as the construction, has a DOWNWARD method for constructing ground structures after completing underground structures.
개착식 공법에는 적용한계가 있는 바, 첫째 지하 구조물의 규모가 크고 굴착심도가 깊은 대형 현장에서는 흙막이벽체에 작용되는 토압과 수압 등의 외력을 지탱하여 주어야하나 가설형강지지체로는 변형이 크다는 취약한 문제점이 있으며, 둘째, 건축물이 밀집된 도심지에서는 이로 인해 흙막이 벽체의 큰 변형을 유발하고 지반침하로 인하여 주변 건축물에 위해가 발생될 수 있는 문제점이 있으며, 셋째로 외부에 노출된 상태에서 굴토작업과 구조물 공사를 수행함에 따라 소음과 진동 및 분진에 의한 환경 및 민원 발생의 문제점이 있으며, 넷째 가설형강지지체 공사가 완료된 후에 순차적으로 본 영구구조물 공사를 수행하는 관계로 공사기간이 길어지는 문제점이 있다.Applicable construction method has limitations. First, in large sites with large underground structures and deep excavation depths, it is necessary to support external forces such as earth pressure and hydraulic pressure acting on the wall, but the deformation is large as temporary steel support. Secondly, in the downtown area where buildings are densely located, this causes a large deformation of the retaining wall and damages to surrounding buildings due to the ground subsidence. Third, the excavation work and the construction work in the state exposed to the outside As a result, there is a problem of environment and civil complaints caused by noise, vibration, and dust, and fourth, there is a problem in that the construction period is lengthened since the permanent structure construction is sequentially performed after the construction of the temporary steel support.
이러한 개착식 공법의 문제점을 해결하기 위해 탑다운공법과 다운워드공법이 사용되고 있다.Top down method and down method are used to solve the problem of the sticking method.
그러나 이러한 탑다운공법과 다운워드공법은 굴착을 진행하기 전에 다수개의 철골기둥과 이에 연장된 말뚝기초를 설치한 후 굴착을 진행하면서 각 층 구조물을 철골기둥에 연결하여 설치하는 구조로 이루어져 철골기둥과 이에 연장된 말뚝기초에 모든 하중이 작용하므로 단면계수가 높고 강성이 큰 고가의 재질을 사용해야 하는 문제점이 있다. 그리고 철골기둥과 이에 연장된 말뚝기초의 최 하단에는 천공한 상태에서 콘크리트를 타설하여 지지력을 향상시켜야 하는 공정이 필요하다.However, the top-down method and the down-word method consist of a structure that installs a plurality of steel pillars and an extended pile foundation before the excavation, and connects each layer structure to the steel pillars while the excavation proceeds. Since all loads act on the extended pile foundation, there is a problem in that an expensive material having a high cross-sectional coefficient and a large rigidity is used. And at the bottom of the steel pillar and the pile foundation extending there is a process to improve the bearing capacity by placing concrete in the perforated state.
또한, 굴착 전에 굴착이 시작되는 상부에서부터 말뚝이 형성되는 최하부까지 하나의 자재로 철골기둥과 이에 연장된 말뚝기초가 설치된 후에 각 층 구조물을 설치하게 되는데 철골기둥에 편심이 생겼을 경우 각 층 구조물의 길이가 조금씩 맞지 않아 연결에 큰 어려움이 따른다.In addition, before the excavation, each layer structure is installed after the steel pillars and the pile foundations extending from the upper part to the bottom where the pile is formed. It doesn't fit a bit, so it's hard to connect.
상기와 같은 점을 감안하여 안출한 본 발명의 목적은 비용과 공사기간이 많이 소요되고 철골기둥과 이에 연장된 말뚝기초의 설치 대신에 형강으로 구성된 가설 센터파일을 설치하고 이에 연결되어 흙막이벽 버팀역할을 하면서 영구구조물이 되는 첫째단 수평구조물을 설치하고 이에서부터 하단방향의 각층 수평구조물을 연결할 수 있도록 층간기둥을 설치하고, 그 층간기둥이 굴착부분의 바닥면까지 설치되어 각층 수평구조물을 지지하면 상기 센터파일을 분리하고 상기 층간기둥이 상기 각층 수평구조물 및 상기 첫째단 수평구조물을 지지할 수 있도록 하는 지하 구조물 구축장치를 제공함에 있다.The object of the present invention devised in view of the above point is that it takes a lot of cost and construction period, and installs a temporary center pile composed of section steel instead of installing steel pillars and pile foundations connected thereto, and is connected to the earth wall support While installing the first level horizontal structure to be a permanent structure while installing the interlayer column to connect the horizontal structure of each layer from the bottom direction, and the interlayer column is installed to the bottom surface of the excavation part to support the horizontal structure of each layer The present invention provides an underground structure construction apparatus for separating a center pile and allowing the interlayer pillars to support the horizontal structures and the first stage horizontal structures.
본 발명의 또 다른 목적은 층간기둥을 상부부터 하부 방향으로 순차적으로 설치하면서 각층 수평구조물을 설치하는 구조로 이루어져 층간기둥과 각층 수평구조물 간의 수직상태를 유지시키기가 용이한 특징을 갖는 지하 구조물 구축장치를 제공함에 있다.Another object of the present invention consists of a structure for installing the horizontal structure of each floor while sequentially installing the interlayer pillar from the top to the bottom direction, the underground structure construction apparatus having an easy feature to maintain the vertical state between the interlayer pillar and each horizontal structure In providing.
상기와 같은 본 발명의 목적을 달성하기 위한 지하 구조물 구축장치는 지하 구조물을 설치할 수 있도록 굴착되는 굴착부분의 둘레면에 형성되는 흙막이벽; 상기 굴착부분에 제거 가능하도록 근입시키는 다수개의 센터파일; 상기 센터파일에 지지되도록 상기 센터파일의 상단부에 설치되는 첫째단 수평구조물; 및 일측은 상기 첫째단 수평구조물에 고정되고 타측은 굴착부분의 바닥면에 설치되는 철근 콘크리트 기초에 고정시키는 다수개의 층간기둥;을 포함하여, 상기 층간기둥이 바닥면에 설치되어 상기 첫째단 수평구조물을 지지하면, 상기 센터파일을 분리하고 상기 층간기둥이 상기 첫째단 수평구조물을 지지한다.Underground structure construction apparatus for achieving the object of the present invention as described above is the earth wall formed on the circumferential surface of the excavated portion to be excavated to install the underground structure; A plurality of center piles to be removable to the excavation portion; A first horizontal structure installed at an upper end of the center pile to be supported by the center pile; And one side is fixed to the first horizontal structure and the other side is a plurality of interlayer pillars to be fixed to the reinforced concrete foundation installed on the bottom surface of the excavated portion; including, the interlayer pillars are installed on the bottom surface of the first stage horizontal structure Supporting, the center pile is separated and the interlayer pillar supports the first horizontal structure.
상기와 같은 본 발명의 목적을 달성하기 위한 지하 구조물 구축장치는 지하 구조물을 설치할 수 있도록 굴착되는 굴착부분의 둘레면에 형성되는 흙막이벽; 상기 굴착부분에 제거 가능하도록 근입시키는 다수개의 센터파일; 상기 센터파일에 지지되도록 상기 센터파일의 상단부에 설치되는 첫째단 수평구조물; 상기 첫째단 수평구조물의 하단방향으로 상기 굴착부분의 바닥면까지 층을 이루도록 설치되어 상기 흙막이벽을 지지하는 각층 수평구조물; 및 상기 각층 수평구조물을 상기 첫째단 수평구조물에서부터 순차적으로 연결하여 설치할 수 있도록 일측은 상기 첫째단 수평구조물이나 상단의 각층 수평구조물에 고정되고 타측은 이웃하는 하단의 층간 수평구조물이 연결되는 다수개의 층간기둥;을 포함하여, 상기 층간기둥은 상기 첫째단 수평구조물에서부터 하단방향의 상기 각층 수평구조물을 연결하여 설치하고, 상기 층간기둥이 바닥면까지 설치되어 상기 각층 수평구조물을 지지하면, 상기 센터파일을 분리하고 상기 층간기둥이 상기 각층 수평구조물 및 첫째단 수평구조물을 지지한다.Underground structure construction apparatus for achieving the object of the present invention as described above is the earth wall formed on the circumferential surface of the excavated portion to be excavated to install the underground structure; A plurality of center piles to be removable to the excavation portion; A first horizontal structure installed at an upper end of the center pile to be supported by the center pile; Each layer horizontal structure is installed to form a layer to the bottom surface of the excavated portion in the bottom direction of the first horizontal structure to support the earth wall; And one side is fixed to the first level horizontal structure or each layer horizontal structure at the top, and the other side is connected to the interlevel horizontal structure at the bottom so that the horizontal structures can be connected sequentially from the first level horizontal structure. Including the pillar; The interlayer pillar is installed by connecting the horizontal structure of each layer in the bottom direction from the first horizontal structure, and the interlayer pillar is installed to the bottom surface to support the horizontal structure of each layer, the center pile The interlayer pillars support the respective horizontal structures and the first stage horizontal structures.
또한, 보다 바람직하게는, 상기 층간기둥은 상기 각층 수평구조물과 직각을 이루도록 일렬로 배열된다.Further, more preferably, the interlayer pillars are arranged in a line to be perpendicular to the horizontal structure of each layer.
또한, 보다 바람직하게는, 상기 첫째단 수평구조물, 상기 각층 수평구조물 및 상기 층간기둥은 영구구조물로 이루어진다.In addition, more preferably, the first stage horizontal structure, each layer horizontal structure and the interlayer column is made of a permanent structure.
또한, 보다 바람직하게는, 상기 첫째단 수평구조물, 상기 각층 수평구조물 및 상기 층간기둥은 형강으로 형성되고, 서로 볼트접합 또는 용접으로 결합된다.In addition, more preferably, the first stage horizontal structure, the horizontal structure of each layer and the interlayer column is formed of a section steel, and are bonded to each other by bolting or welding.
또한, 보다 바람직하게는, 상기 각층 수평구조물 사이에는 상기 흙막이벽의 토압을 지지하는 가설 수평구조물이 더 포함된다.Further, more preferably, a temporary horizontal structure for supporting the earth pressure of the retaining wall is further included between the horizontal structures of each layer.
또한, 보다 바람직하게는, 상기 각층 수평구조물은 상기 층간기둥의 타측 끝단부에 연결부재가 매달릴 수 있도록 걸림턱부재가 장착된다.In addition, more preferably, the horizontal structure of each layer is equipped with a locking jaw member so that the connection member can be suspended in the other end of the interlayer pillar.
또한, 보다 바람직하게는, 상기 연결부재는 4개의 단위로드가 격자 형상을 이루는 구조로 이루어지고, 상기 연결부재의 격자 내부에 상기 층간기둥이 위치한다.Further, more preferably, the connecting member has a structure in which four unit rods form a lattice shape, and the interlayer pillar is positioned inside the lattice of the connecting member.
또한, 보다 바람직하게는, 상기 각층 수평구조물은 상기 연결부재를 서로 연결하는 결합부재로 이루어진다.In addition, more preferably, the horizontal structure of each layer is composed of a coupling member for connecting the connecting member to each other.
또한, 보다 바람직하게는, 상기 각층 수평구조물에는 철근 콘크리트 슬래브가 더 포함된다.Further, more preferably, the reinforced concrete slab is further included in each horizontal structure.
또한, 보다 바람직하게는, 상기 흙막이벽에 접촉되는 첫째단 수평구조물과 상기 각층 수평구조물의 테두리부를 일정 폭만큼 철근 콘크리트로 보강하는 테두리 보강부재를 더 포함한다.In addition, more preferably, the first stage horizontal structure in contact with the retaining wall and the rim reinforcing member for reinforcing the edge portion of the horizontal structure of each layer by reinforced concrete by a certain width further.
또한, 보다 바람직하게는, 상기 첫째단 수평구조물과 상기 각층 수평구조물을 이루는 형강 사이에 철근 콘크리트가 채워지는 보강부재가 설치되고, 상기 보강부재는 상기 테두리 보강부재와 연결된다.Further, more preferably, a reinforcing member filled with reinforced concrete is installed between the first stage horizontal structure and the beam forming the horizontal structure of each layer, and the reinforcing member is connected to the edge reinforcing member.
또한, 보다 바람직하게는, 상기 연결부재는 2개의 단위로드가 서로 교차되는 구조로 이루어지고. 교차되는 교차부에 상기 층간기둥이 위치한다.In addition, more preferably, the connecting member has a structure in which two unit rods cross each other. The interstitial column is located at the intersection where they intersect.
또한, 보다 바람직하게는, 상기 층간기둥은 바닥면에 설치되는 철근 콘크리트 기초에 고정된다.Further, more preferably, the interlayer column is fixed to the reinforced concrete foundation installed on the bottom surface.
또한, 보다 바람직하게는, 상기 층간기둥에는 지지력이 보강될 수 있도록 철근 콘크리트가 더 포함된다.In addition, more preferably, the interlayer pillar further includes reinforced concrete so that bearing capacity can be reinforced.
또한, 보다 바람직하게는, 상기 각층 수평구조물에는 일측은 상기 흙막이벽에 고정되고 타측은 상기 각층 수평구조물에 고정되어 경사지게 설치되는 경사버팀부재가 더 포함된다.In addition, more preferably, the horizontal structure of each layer further includes an inclined brace member that is fixed to one side is fixed to the retaining wall and the other side is fixed to the each layer horizontal structure.
또한, 보다 바람직하게는, 상기 각층 수평구조물에는 복수개의 상기 경사버팀부재가 상기 흙막이벽을 향해 일정 각도로 벌어지게 설치된다.In addition, more preferably, a plurality of the inclined brace member is installed in the horizontal structure at each angle toward the retaining wall.
또한, 보다 바람직하게는, 상기 흙막이벽과 각 상기 경사버팀부재의 일측 끝단 사이에는 상기 경사버팀부재의 일측 끝단을 서로 연결하는 띠장이 더 포함된다.Further, more preferably, between the earth wall and one end of each of the inclined bracing member, a belt is further included to connect one end of the inclined bracing member to each other.
또한, 보다 바람직하게는, 상기 굴착부분의 바닥면부까지 상기 각층 수평구조물의 설치가 완료되고 상기 경사버팀부재를 분리시키는 경우에는, 상기 흙막이벽에 추가하여 영구벽체를 이루도록 철근 콘크리트가 보강된다.More preferably, when the installation of the horizontal structure of each layer is completed up to the bottom surface of the excavated portion and the inclined support member is separated, reinforced concrete is reinforced to form a permanent wall in addition to the retaining wall.
또한, 보다 바람직하게는, 상기 센터파일은 상기 센터파일을 제거 후에 상기 각층 수평구조물과 상기 첫째단 수평구조물을 지지하는 상기 층간기둥에 겹치지 않도록 상기 층간기둥의 위치에 근접하여 설치된다.More preferably, the center pile is installed close to the position of the interlayer pillar such that the center pile does not overlap the interlayer pillar supporting the respective horizontal structures and the first horizontal structure after removing the center pile.
또한, 보다 바람직하게는, 상기 센터파일에는 상기 첫째단 수평구조물과 상기 각층 수평구조물을 지지하도록 돌출되는 버팀부재가 더 포함된다.Further, more preferably, the center pile further includes a brace member protruding to support the first horizontal structure and the respective horizontal structure.
이와 같이 본 발명에 의한 지하 구조물 구축장치는 고가의 재료와 공사기간이 많이 소요되는 철골기둥과 이에 연장된 말뚝기초 대신에 제거하여 재사용이 가능한 센터파일을 사용하여 지하구조물을 구축함으로써, 공사기간 단축 및 공사비가 절감되는 효과가 있다.As described above, the underground structure building apparatus according to the present invention reduces the construction period by constructing an underground structure using a center pile that can be removed and reused instead of steel pillars and pile foundations that require a lot of expensive materials and construction period. And construction costs are reduced.
또한, 층간기둥을 순차적으로 설치하는 것이 가능하므로 층간기둥과 각층 수평구조물간의 수직상태를 유지시키기가 용이하고 작업성이 향상되는 효과가 있다.In addition, since it is possible to install the interlayer pillars sequentially, it is easy to maintain the vertical state between the interlayer pillars and the horizontal structure of each layer, and the workability is improved.
첫째단 수평구조물이나 각층 수평구조물에 테두리 보강부재와 보강부재가 설치되어 흙막이벽에 의해 가해지는 토압에 견디는 힘이 증가되므로 안전성이 향상되는 효과가 있다.The first stage horizontal structure or each layer horizontal structure is provided with a rim reinforcement member and a reinforcement member to increase the force to withstand the earth pressure applied by the retaining wall has the effect of improving safety.
또한, 경사버팀부재가 경사지게 장착되어 경사버팀부재의 설치 및 제거 시간이 단축되고 굴착작업중에 불필요한 간섭으로 인해 굴착작업이 지연되는 것을 방지하므로 작업성이 향상되고 공사기간이 단축되는 효과가 있다.In addition, since the inclined bracing member is mounted inclined, the installation and removal time of the inclined bracing member is reduced, and the excavation work is prevented from being delayed due to unnecessary interference during the excavation work, thereby improving workability and shortening the construction period.
도 1a는 본 발명의 바람직한 일 실시예인 지하 구조물 구축장치를 도시한 사시도,
도 1b는 지하 구조물 구축장치의 하부를 확대하여 도시한 사시도,
도 2는 지하 구조물 구축장치를 도시한 단면도,
도 3 내지 도 5는 테두리 보강부재 및 보강부재를 도시한 단면도,
도 6 내지 도 13은 지하 구조물 구축장치가 시공되는 과정을 도시한 상태도로서,
도 6은 센터파일이 설치된 상태를 도시한 상태도,
도 7은 첫째단 수평구조물이 설치된 상태를 도시한 상태도,
도 8은 층간기둥과 각층 수평구조물의 연결부재가 장착된 상태를 도시한 상태도,
도 9는 각층 수평구조물이 설치된 상태를 도시한 상태도,
도 10은 추가 굴착이 진행되고 바닥면에 층간기둥과 철근 콘크리트 기초가 설치된 상태를 도시한 상태도,
도 11은 센터파일이 제거되고 층간기둥의 철근 콘크리트 보강과 철근 콘크리트 슬래브가 진행된 상태를 도시한 상태도,
도 12는 지하 구조물이 완료된 상태를 도시한 상태도.Figure 1a is a perspective view showing an underground structure construction apparatus which is a preferred embodiment of the present invention,
Figure 1b is an enlarged perspective view of the lower portion of the underground structure building device,
2 is a cross-sectional view showing an underground structure construction apparatus,
3 to 5 is a cross-sectional view showing a rim reinforcing member and a reinforcing member,
6 to 13 is a state diagram showing the process of construction of the underground structure building apparatus,
6 is a state diagram showing a state in which the center file is installed,
7 is a state diagram showing a state in which the first stage horizontal structure is installed,
8 is a state diagram showing a state in which the connecting member of the interlayer pillar and the horizontal structure of each layer,
9 is a state diagram showing a state in which each floor horizontal structure is installed,
10 is a state diagram showing a state in which the additional excavation is progressing and the interlayer pillar and reinforced concrete foundation is installed on the bottom surface,
Figure 11 is a state diagram showing a state in which the center pile is removed and reinforced concrete reinforcement and reinforced concrete slab of the interlayer column progressed,
12 is a state diagram showing a state in which the underground structure is completed.
이하, 본 발명의 바람직한 일 실시예인 지하 구조물 구축장치를 첨부된 도면을 참조하여 보다 상세히 설명하면 다음과 같다.Hereinafter, with reference to the accompanying drawings, an underground structure construction apparatus which is a preferred embodiment of the present invention in more detail as follows.
도 1a는 본 발명의 바람직한 일 실시예인 지하 구조물 구축장치를 도시한 사시도이고, 도 1b는 지하 구조물 구축장치의 하부를 확대하여 도시한 사시도이고, 도 2는 지하 구조물 구축장치를 도시한 단면도이고, 도 3 내지 도 5는 테두리 보강부재 및 보강부재를 도시한 단면도이고, 도 6 내지 도 13은 지하 구조물 구축장치가 시공되는 과정을 도시한 상태도로서, 도 6은 센터파일이 설치된 상태를 도시한 상태도이고, 도 7은 첫째단 수평구조물이 설치된 상태를 도시한 상태도이고, 도 8은 층간기둥과 각층 수평구조물의 연결부재가 장착된 상태를 도시한 상태도이고, 도 9는 각층 수평구조물이 설치된 상태를 도시한 상태도이고, 도 10은 추가 굴착이 진행되고 바닥면에 층간기둥과 철근 콘크리트 기초가 설치된 상태를 도시한 상태도이고, 도 11은 센터파일이 제거되고 층간기둥의 철근 콘크리트 보강과 철근 콘크리트 슬래브가 진행된 상태를 도시한 상태도이고, 도 12는 지하 구조물이 완료된 상태를 도시한 상태도이다.Figure 1a is a perspective view showing an underground structure building apparatus according to an embodiment of the present invention, Figure 1b is a perspective view showing an enlarged lower portion of the underground structure building device, Figure 2 is a cross-sectional view showing an underground structure building device, 3 to 5 is a cross-sectional view showing a rim reinforcing member and a reinforcing member, Figures 6 to 13 is a state diagram showing the process of construction of the underground structure construction apparatus, Figure 6 is a state diagram showing a state in which the center pile is installed 7 is a state diagram showing a state in which the first stage horizontal structure is installed, and FIG. 8 is a state diagram showing a state in which the connecting member of the interlayer pillar and the horizontal structure of each layer is mounted, and FIG. 9 is a state in which the horizontal structure of each layer is installed. Figure 10 is a state diagram, Figure 10 is a state diagram showing a state in which additional excavation is carried out and the interlayer pillar and reinforced concrete foundation is installed on the bottom surface, Figure 11 is a center pile Giant and the reinforcement of reinforced concrete and reinforced concrete slab of the inter-pole showing the advanced state is a state diagram, Figure 12 is a state diagram showing a state in the underground structure is completed.
도시된 바와 같이 본 발명의 바람직한 일 실시예인 지하 구조물 구축장치는 굴착부분의 둘레면을 따라 압입되어 형성되는 흙막이벽(10)과, 굴착부분에 제거 가능하도록 근입시키는 다수개의 센터파일(20)과, 센터파일(20)의 상단부에 설치되며 흙막이벽(10)의 토압을 견딜 수 있도록 가로질러 지지하는 첫째단 수평구조물(30)과, 첫째단 수평구조물(30)에 고정되고 하단방향으로 연장되는 층간기둥(40)과, 층간기둥(40) 끝단에 지지되며 첫째단 수평구조물(30)과 함께 흙막이벽(10)을 지지하는 각층 수평구조물(50)로 이루어지고, 층간기둥(40)과 각층 수평구조물(50)을 굴착하고자 하는 깊이에 따라 순차적으로 설치하여 지하층을 이룬다.As shown, an underground structure construction apparatus according to an embodiment of the present invention is a
센터파일(20)은 굴착하고자 하는 깊이 이상으로 근입시키는 형강으로 이루어진다. 상기 형강 및 후술하는 형강은 H빔, 강관 및 각관 등 건축물 골조로 사용되는 일반 구조물을 모두 포함한다. 센터파일(20)은 센터파일(20)을 제거한 후에 각층 수평구조물(50)과 첫째단 수평구조물(30)을 안정되게 지지할 수 있는 위치에 설치되는 층간기둥(40)과 겹치지 않도록 층간기둥(40)과 근접한 위치에 설치된다. 또한, 센터파일(20)에는 첫째단 수평구조물(30)이나 각층 수평구조물(50)을 지지할 수 있도록 돌출된 버팀부재(21)가 장착된다.The
첫째단 수평구조물(30)과 각층 수평구조물(50)은 영구구조물로 이루어진다. 첫째단 수평구조물(30)과 각층 수평구조물(50)은 형강으로 이루어지고 서로 볼트접합 또는 용접으로 결합된다. The first stage
첫째단 수평구조물(30)은 연결부재(31)와 각 연결부재(31)를 연결하는 결합부재(32)로 이루어진다. 연결부재(31)는 4개의 단위로드(31a)가 격자 형상을 이루는 구조로 이루어지고, 층간기둥(40)은 연결부재(31)의 격자 내부에 위치한다. 층간기둥(40)은 연결부재(31)의 중심점에 설치되는 것이 가장 바람직하고, 걸림턱부재(33)에 의해 연결부재(31)와 연결된다. The first stage
상기 연결부재(31)는 도시된 바와 같이 격자 형상으로 배열되는 것이 가장 바람직하지만, 2 개의 단위 로드가 서로 교차되도록 이루어지고, 교차되는 교차부에 층간기둥(40)이 설치되는 구조로 구성될 수도 있다.The connecting
첫째단 수평구조물(30)과 마찬가지로 각층 수평구조물(50)은 연결부재(51)와 각 연결부재(51)를 연결하는 결합부재(52)로 이루어진다. 연결부재(51)는 4개의 단위로드(51a)가 격자 형상을 이루는 구조로 이루어지고, 층간기둥(40)은 연결부재(51)의 격자 내부에 위치한다. 층간기둥(40)은 연결부재(51)의 중심점에 설치되는 것이 가장 바람직하고, 걸림턱부재(53)에 의해 연결부재(51)와 연결된다. Like the first stage
상기 연결부재(51)는 도시된 바와 같이 격자 형상으로 배열되는 것이 가장 바람직하지만, 2 개의 단위 로드가 서로 교차되도록 이루어지고, 교차되는 교차부에 층간기둥(40)이 설치되는 구조로 구성될 수도 있다.The connecting
층간기둥(40)은 형강으로 이루어진 영구구조물로 이루어지고, 첫째단 수평구조물(30) 및 각층 수평구조물(50)과 볼트접합 및 용접으로 결합된다. The
층간기둥(40)의 일측 끝단은 첫째단 수평구조물(30)이나 각층 수평구조물(50)에 걸림턱 부재(33, 53)으로 연결되어 고정되고, 타측 끝단은 이웃하는 하단에 위치하는 각층 수평구조물(50)에 걸림턱 부재(53)로 연결되어 고정된다. 층간기둥(40)과 각층 수평구조물(50)을 차례로 설치하기 때문에 층간기둥(40)에 각층 수평구조물(50)을 설치할 때 직각을 이루도록 설치하기가 용이하고, 직하방향으로 일렬을 이루도록 배열하는 것이 바람직하다.One end of the
상기 첫째단 수평구조물(30) 및 각층 수평구조물(50)을 구성하는 연결부재(31, 51)와 결합부재(32, 52)는 층간기둥(40)에 연결되기 전에 센터파일(20)에 버팀부재(21)를 설치하고 그 위에 거치 될 수 있고, 첫째단 및 각층 수평구조물(30, 50)이 형성된 후에 층간기둥(40)에 연결될 수 있고 첫째단 및 각층 수평구조물(30, 50)이 형성되기 전 연결부재(31, 51) 또는 결합부재(32, 52)가 층간기둥(40)에 연결될 수도 있다.The connecting
굴착을 진행하면서 상기 각층 수평구조물(50) 사이 간격을 넓게 형성하는 경우에는 각층 수평구조물(50) 사이에 흙막이벽(10)의 토압을 견딜 수 있도록 가설 수평구조물이 형성될 수 있다. 가설 수평구조물은 각층 수평구조물(50)과 같이 굴착공을 가로질러 토압을 견딜 수 있도록 형강으로 상기 흙막이벽(10)을 지지하는 구조로 이루어진다. 가설 수평구조물은 영구구조물이 아니라 후에 해체되는 구조물이다.In the case of forming a wide interval between the
각층 수평구조물(50)과 첫째단 수평구조물(30)에는 철근 콘크리트 슬래브(11)가 설치된다 철근 콘크리트 슬래브(11)는 형강으로 이루어진 각층 수평구조물(50)이나 첫째단 수평구조물(30)의 상면 위에 형성된다. 또한, 각층 수평구조물(50)과 첫째단 수평구조물(30)의 테두리부를 일정 폭만큼 철근 콘크리트로 보강하는 테두리 보강부재(12)가 형성되고, 테두리 보강부재(12)는 결합부재(32, 52) 사이에 철근 콘크리트로 보강되는 보강부재(13)와 연결된다.Reinforced
테두리 보강부재(12)와 보강부재(13)는 도 3에 도시된 바와 같이 첫째단 수평구조물(30)이나 각층 수평구조물(50)을 이루는 형강의 상면 위에 형성되거나, 도 4에 도시된 바와 같이 첫째단 수평구조물(30)이나 각층 수평구조물(50) 사이에 채워지거나, 도 5에 도시된 바와 같이 첫째단 수평구조물(30)이나 각층 수평구조물(50)의 단면 위 및 사이에 채워지는 구조로 형성된다. 테두리 보강부재(12)와 보강부재(13)는 흙막이벽(10)에서 발생되는 토압을 고르게 지지할 수 있는 역할을 수행한다. 또한, 보강부재(13)는 결합부재(32, 52) 사이에 형성되는 경우 형강의 강도를 보강하여 형강의 처짐이 발생되는 것을 방지하는 역할을 수행한다. The
굴착이 완료된 굴착부분의 바닥면에는 철근 콘크리트 기초(14)가 형성되고, 최하단의 층간기둥(40)은 철근 콘크리트 기초(14)에 고정된다. 이때 층간기둥(40)은 지지력이 보강될 수 있도록 철근 콘크리트(41)가 추가 형성된다. Reinforced
그리고 흙막이벽(10)과 첫째단 및 각층 수평구조물(30, 50)이 접하는 지점에는 경사지게 설치되는 경사버팀부재(60)가 설치된다. 경사버팀부재(60)는 가설 수평구조물을 대신하여 흙막이벽(10)의 토압을 견디는 구조물로서, 일측은 흙막이벽(10)에 고정되고 타측은 첫째단 및 각층 수평구조물(30, 50)에 고정된다. 이때 경사버팀부재(60)는 다수개가 흙막이벽(10)을 향해 일정 각도로 벌어지게 설치되며 그 끝단에는 경사버팀부재(60)를 서로 연결하는 띠장(61)이 설치된다. 띠장(61)은 흙막이벽(10)을 가로방향으로 지지한다.And the inclined bracing
또한, 굴착부분의 바닥면부까지 각층 수평구조물(50)의 설치가 완료되면 상기 경사버팀부재(60)를 제거한 후 흙막이벽(10)이 가설구조물인 경우 철근 콘크리트(10a)를 보강하여 영구벽체를 이루도록 한다.In addition, when the installation of the
상기와 같이 구성된 본 발명의 바람직한 일 실시예인 지하 구조물 구축장치는 지하 2층 이상의 지하 구조물을 시공하는 경우에는 상기 층간기둥(40)과 각층 수평구조물(50)을 설치하는 과정을 반복적으로 실시하여 지하 2층 이상의 지하 구조물을 시공할 수 있다. 또한, 지하1층의 지하 구조물을 시공하는 경우에는 상기 층간 수평구조물(50)을 설치하지 않고 첫째단 수평구조물(30)과 연결되는 층간기둥(40)을 곧바로 철근 콘크리트 기초(14)에 고정시킨 후, 센터파일(20)을 제거한다.Underground structure construction apparatus is a preferred embodiment of the present invention configured as described above, when constructing the underground structure of two or more basement floors by repeatedly performing the process of installing the
이와 같이 본 발명에 의한 지하 구조물 구축장치는 굴착작업을 진행하면서 첫째단 수평구조물(30)에서부터 층간기둥(40)을 거꾸로 아랫방향으로 연장시키면서 각층 수평구조물(50)을 설치하고, 철근 콘크리트 기초(14)에 최하단의 층간기둥(40)을 고정시킨 후, 센터파일(20)을 제거한다. As described above, the underground structure building apparatus according to the present invention installs the
또한, 흙막이벽(10)도 경사버팀부재(60)가 제거되고 흙막이벽(10)에 철근콘크리트(10a)가 보강되어 영구벽체를 이룬다. 경사버팀부재(60)를 첫째단 수평구조물(30)이나 각층 수평구조물(50)의 테두리부에 경사지게 설치되므로 굴착작업을 진행하거나 각층 수평구조물(50)을 설치하는 시공을 진행하는 와중에 간섭으로 인한 작업의 어려움이 발생되지 않는 특징을 가지며, 흙막이벽(10)에서 작용하는 토압을 효과적으로 지지하는 역할을 수행한다.In addition, the retaining
도 6에 도시된 바와 같이 굴착부분을 둘레면에 흙막이벽(10)을 설치하는 흙막이벽 설치단계를 진행한 후, 굴착부분에 다수개의 센터파일(20)을 제거가능하도록 근입시키는 센터파일 근입단계를 실시한다. 이때 센터파일(20)은 추후 설치될 층간기둥(40)이 설치되는 지점과 접하지 않도록 그 주변에 근입시킨다.As shown in FIG. 6, after proceeding with the installation of the retaining wall for installing the retaining
도 7에 도시된 바와 같이 근입된 센터파일(20)의 상단부에 버팀부재(21)를 설치하고 그 위에 걸쳐지는 첫째단 수평구조물(30) 설치단계를 진행한다. 버팀부재(21)는 순차적으로 설치되는 각층 수평구조물(50)을 지지할 수 있도록 일정 간격을 두고 센터파일(20)에 형성시킨다. 그리고 첫째단 수평구조물(30)을 이루는 연결부재(31)에 또 다른 연결부재(51)를 층을 이루도록 결합하여 설치하고 굴착작업이 진행되면 필요한 위치까지 순차적으로 내리고 그 상태로 층간기둥(40)을 연결하는 작업실시한다. 이때 추가적으로 연결되는 연결부재(51)는 시공하고자 하는 지하층수에 대응되는 개수를 장착한다. 즉, 지하2층 구조물을 시공하고자 하는 경우에는 한 개의 연결부재(51)가 층을 이루도록 장착되고, 지하 3층 구조물을 시공하고자 하는 경우에는 2개의 연결부재(51)가 층을 이루도록 장착되는 것이다.As shown in FIG. 7, the
첫째단 수평구조물(30)의 설치가 완료되면 도 8에 도시된 바와 같이 첫 번째 층간기둥(40)을 첫째단 수평구조물(30)에 연결하는 층간기둥 설치단계를 실시한 후, 층간기둥(40)의 타측 끝단에 각층 수평구조물(50)의 연결부재(51) 설치단계를 실시한다. 이때 추가적으로 버팀부재(21)를 설치하여 연결부재(51)가 일부 센터파일(20)에 지지될 수 있도록 할 수도 있다.When the installation of the first stage
그리고 도 9에 도시된 바와 같이 연결부재(51)를 연결하는 결합부재(52)를 설치하는 결합부재 설치단계를 실시하여 각층 수평구조물(50) 설치단계를 완료한다.Then, as shown in FIG. 9, the coupling member installation step of installing the
각층 수평구조물(50)은 층간기둥(40)과 직각을 이루도록 설치하는 것이 용이한 특징을 가지며, 각층 수평구조물(50)의 설치가 완료되면 다음 층까지의 추가 굴착작업을 실시한다. 굴착하고자 하는 지하 깊이에 따라 상기 층간기둥 설치단계와 각층 수평구조물 설치단계를 반복적으로 실시한다.Each layer
도 10에 도시된 굴착부분의 바닥면까지 굴착이 완료되면 층간기둥(40)을 연결하고, 굴착부분의 바닥면 위에 층간기둥(40)을 견고하게 고정할 수 있도록 철근 콘크리트 기초(14)를 설치하는 기초 설치단계를 실시한다. 이때 철근 콘크리트 기초(14)는 도시된 바와 같이 층간기둥(40)을 설치한 후에 철근 콘크리트 기초(14)를 시공하는 순서로 진행될 수도 있고, 철근 콘크리트 기초(14)를 설치한 후, 그 위에 층간기둥(40)을 설치하는 순서로 진행될 수도 있다.When the excavation is completed to the bottom surface of the excavated portion shown in Figure 10 is connected to the
철근 콘크리트 기초(14)에 층간기둥(40)을 견고하게 고정시킨 후에는 도 11에 도시된 바와 같이 센터파일(20)을 제거한다. 센터파일(20)을 제거하기 전에 층간기둥(40)에 가해지는 하중을 분담하기 위해 각층 수평구조물(50) 또는 첫째단 수평구조물(30) 하부에 동바리(70)를 설치할 수 있다. 철근 콘크리트(41)를 보강하는 층간기둥 보강단계를 실시한다. 각층 수평구조물(50) 위에 철근 콘크리트 슬래브(11)를 형성하는 슬래브 형성단계를 실시한다. 이때 첫째단 및 각층 수평구조물(30, 50)의 하중을 철근 콘크리트로 보강되기 전 층간기둥(40)과 분담하기 위하여 각 층에 동바리를 설치할 수 있다. 상단부까지 층간기둥 보강단계와 슬래브 형성단계를 반복 실시한다. 철근 콘크리트 슬래브(11)는 굴토작업이 진행중일 때는 첫째단 수평구조물(30)이나 각층 수평구조물(50)의 일부면에만 형성하고, 굴토작업이 모두 끝난 후에는 각층 수평구조물(50)의 전면에 형성한다.After firmly fixing the
또한, 흙막이벽(10)에 접촉되는 첫째단 수평구조물(30) 및 각층 수평구조물(50)의 테두리부와 흙막이벽(10) 사이를 도 2에 도시된 바와 같이 일정 폭만큼 또 첫째단 및 각층 수평구조물(30, 50)의 형강두께와 철근 콘크리트 슬래브(11) 두께를 합친 두께로 테두리 보강부재(12)를 설치하는 테두리 보강부재 설치단계를 실시한다. 테두리 보강부재(12)는 흙막이벽(10)의 토압을 첫째단 및 각층 수평구조물(30, 50)에 분포될 수 있도록 강성을 갖는 철근 콘크리트로 형성할 수 있다. 그리고 연결부재(31, 51) 사이 및 결합부재(32, 52) 사이에 철근 콘크리트를 채우는 보강부재(13) 설치단계를 실시할 수 있다. 이는 첫째단 및 각층 수평구조물(30, 50)이 형강만으로 형성되어 있는 부분에서 토압을 저항하는 능력을 증가시키기 위해서 또는 장비 등이 작업을 위해 첫째단 및 각층 수평구조물(30, 50) 위에 얹어질 때 휨 강성을 증가시키는 등의 구조보강에 대비하기 위함이다. 테두리 보강부재(12) 및 보강부재(13)는 도 3에 도시된 바와 같이 연결부재(31, 51)와 결합부재(32, 52)의 상단면 위에 설치되거나, 도 4에 도시된 바와 같이 연결부재(31, 51)와 결합부재(32, 52)의 내측면 사이에 설치되거나, 도 5에 도시된 바와 같이 연결부재(31, 51)와 결합부재(32, 52)의 상단면 위 및 내측면 사이에 동시에 설치될 수 있다. 이때 연결부재(31, 51) 내측면의 층간기둥(40)이 위치하는 부분에는 철근 콘크리트를 비워두어 하부에서부터 층간기둥(40) 철근 콘크리트(41)가 타설될 때 일체가 될 수 있도록 할 수 있다. 그리고 테두리 보강부재(12)와 보강부재(13)가 서로 연결되는 구조로 형성되는 경우 흙막이벽(10)에서 발생되는 토압에 대한 저항력이 커지게 되지만, 테두리 보강부재(12)와 보강부재(13)는 서로 연결되지 않는 구조로 형성될 수도 있다.In addition, between the first
층별로 각층 수평구조물(50)을 설치하면서 경사버팀부재(60)를 설치하는 경사버팀부재 설치단계를 실시한다. 경사버팀부재 설치단계에서는 복수개의 경사버팀부재(60)가 흙막이벽(10)을 향해 일정 각도로 벌어지게 설치하고, 경사버팀부재(60)의 끝단을 연결하는 띠장(61)을 설치한다. 이 경사버팀부재(60)는 직하부의 각층 수평구조물(50)이 설치된 후 해체될 수도 있고, 굴착부분의 바닥면까지 시공이 완료되면 바닥면 측부터 차례로 분리할 수도 있으며, 흙막이벽(10)이 영구벽체가 아닐 경우에는 철근 콘크리트(10a) 토압벽체가 추가로 설치된 후에 해체할 수도 있다.While installing the
도 12에 도시된 바와 같이 첫째단 수평구조물(30) 까지 철근콘크리트 층간기둥의 보강단계, 슬래브 설치단계 및 흙막이벽 보강단계를 실시하면 지하 구조물의 설치가 완료된다.As shown in FIG. 12, when the reinforcement step of the reinforced concrete interlayer pillar, the slab installation step and the retaining wall reinforcement step are performed to the first
상기와 같이 굴착작업 기간에는 첫째단 수평구조물(30)이나 각층 수평구조물(50)의 하중이 주로 센터파일(20)에 지지되었다가, 층간기둥(40)이 철근콘크리트 기초(14)에 지지되는 이후에는 센터파일(20)을 제거하고 층간기둥(40)이 첫째단 수평구조물(30) 및 각층 수평구조물(50)을 지지하도록 하는 것이다.In the excavation work period as described above, the load of the first
본 발명은 상술한 특정의 바람직한 실시예에 한정되지 아니하며, 청구범위에서 청구하는 본 발명의 요지를 벗어남이 없이 당해 발명이 속하는 기술 분야에서 통상의 지식을 가진 자라면 누구든지 다양한 변형 실시가 가능한 것은 물론이고, 그와 같은 변경은 청구범위 기재의 범위내에 있게 된다.The present invention is not limited to the above-described specific preferred embodiments, and various modifications can be made by any person having ordinary skill in the art without departing from the gist of the present invention claimed in the claims. Of course, such changes will fall within the scope of the claims.
10 : 흙막이벽 20 : 센터파일
30 : 첫째단 수평구조물 40 : 층간기둥
50 : 각층 수평구조물 60 : 경사버팀부재 10: retaining wall 20: center pile
30: first horizontal structure 40: interlayer column
50: horizontal structure of each layer 60: inclined bracing member
Claims (21)
상기 굴착부분에 제거 가능하도록 근입시키는 다수개의 센터파일;
상기 센터파일에 지지되도록 상기 센터파일의 상단부에 설치되는 첫째단 수평구조물; 및
일측은 상기 첫째단 수평구조물에 고정되고 타측은 굴착부분의 바닥면에 설치되는 철근 콘크리트 기초에 고정시키는 다수개의 층간기둥;을 포함하여,
상기 층간기둥이 바닥면에 설치되어 상기 첫째단 수평구조물을 지지하면, 상기 센터파일을 분리하고 상기 층간기둥이 상기 첫째단 수평구조물을 지지하는 것을 특징으로 하는 지하 구조물 구축장치.An earth retaining wall formed on the circumferential surface of the excavated portion to be excavated to install the underground structure;
A plurality of center piles to be removable to the excavation portion;
A first horizontal structure installed at an upper end of the center pile to be supported by the center pile; And
One side is fixed to the first horizontal structure and the other side a plurality of interlayer pillars to be fixed to the reinforced concrete foundation is installed on the bottom surface of the excavation portion;
And the interlayer pillar is installed on the bottom surface to support the first horizontal structure, and the center pile is separated and the interlayer pillar supports the first horizontal structure.
상기 굴착부분에 제거 가능하도록 근입시키는 다수개의 센터파일;
상기 센터파일에 지지되도록 상기 센터파일의 상단부에 설치되는 첫째단 수평구조물;
상기 첫째단 수평구조물의 하단방향으로 상기 굴착부분의 바닥면까지 층을 이루도록 설치되어 상기 흙막이벽을 지지하는 각층 수평구조물; 및
상기 각층 수평구조물을 상기 첫째단 수평구조물에서부터 순차적으로 연결하여 설치할 수 있도록 일측은 상기 첫째단 수평구조물이나 상단의 각층 수평구조물에 고정되고 타측은 이웃하는 하단의 층간 수평구조물이 연결되는 다수개의 층간기둥;을 포함하여,
상기 층간기둥은 상기 첫째단 수평구조물에서부터 하단방향의 상기 각층 수평구조물을 연결하여 설치하고, 상기 층간기둥이 바닥면까지 설치되어 상기 각층 수평구조물을 지지하면, 상기 센터파일을 분리하고 상기 층간기둥이 상기 각층 수평구조물 및 첫째단 수평구조물을 지지하는 것을 특징으로 하는 지하 구조물 구축장치.An earth retaining wall formed on the circumferential surface of the excavated portion to be excavated to install the underground structure;
A plurality of center piles to be removable to the excavation portion;
A first horizontal structure installed at an upper end of the center pile to be supported by the center pile;
Each layer horizontal structure is installed to form a layer to the bottom surface of the excavated portion in the bottom direction of the first horizontal structure to support the earth wall; And
One side is fixed to the first level horizontal structure or each layer horizontal structure at the top so that the horizontal structure can be installed sequentially from the first level horizontal structure, the other side is a plurality of interlayer pillars are connected to the adjacent horizontal interlayer structure Including;
The interlayer column is installed by connecting the horizontal structure of each layer from the first horizontal structure to the bottom direction, and the interlayer pillar is installed to the bottom surface to support the horizontal structure of each layer, the center pile is separated and the interlayer pillar Underground structure building apparatus, characterized in that for supporting the horizontal structure and the first stage horizontal structure of each layer.
상기 각층 수평구조물과 직각을 이루도록 일렬로 배열되는 것을 특징으로 하는 지하 구조물 구축장치.The method of claim 2, wherein the interlayer pillar
Underground structure construction apparatus, characterized in that arranged in a line to form a right angle with the horizontal structure of each floor.
상기 흙막이벽의 토압을 지지하는 가설 수평구조물이 더 포함되는 것을 특징으로 하는 지하 구조물 구축장치.The method of claim 2, wherein the horizontal structure between each layer
Underground structure construction apparatus further comprises a temporary horizontal structure for supporting the earth pressure of the earth wall.
철근 콘크리트 슬래브가 더 포함되는 것을 특징으로 하는 지하 구조물 구축장치.The horizontal structure of claim 9, wherein
Underground structure building apparatus, characterized in that it further comprises a reinforced concrete slab.
상기 첫째단 수평구조물과 상기 각층 수평구조물을 이루는 형강 사이에 철근 콘크리트가 채워지는 보강부재가 설치되고, 상기 보강부재는 상기 테두리 보강부재와 연결되는 것을 특징으로 하는 지하 구조물 구축장치.12. The method of claim 11,
And a reinforcing member filled with reinforced concrete between the first stage horizontal structure and the section steel forming the horizontal structure of each layer, and the reinforcing member is connected to the edge reinforcing member.
지지력이 보강될 수 있도록 철근 콘크리트가 더 포함되는 것을 특징으로 하는 지하 구조물 구축장치.The method of claim 14, wherein the interlayer pillar
Underground structure construction apparatus characterized in that it further includes reinforced concrete so that the bearing capacity can be reinforced.
일측은 상기 흙막이벽에 고정되고 타측은 상기 각층 수평구조물에 고정되어 경사지게 설치되는 경사버팀부재가 더 포함되는 것을 특징으로 하는 지하 구조물 구축장치.The horizontal structure of any one of claims 2 to 10,
One side is fixed to the retaining wall and the other side is an underground structure construction apparatus further comprises an inclined bracing member is installed to be inclined fixed to the horizontal structure of each layer.
복수개의 상기 경사버팀부재가 상기 흙막이벽을 향해 일정 각도로 벌어지게 설치되는 것을 특징으로 하는 지하 구조물 구축장치.The method of claim 16, wherein the horizontal structure of each layer
Underground structure construction apparatus, characterized in that a plurality of the inclined brace member is installed to be opened at a predetermined angle toward the retaining wall.
상기 흙막이벽에 추가하여 영구벽체를 이루도록 철근 콘크리트가 보강되는 것을 특징으로 하는 지하 구조물 구축장치.19. The method of claim 18, wherein when the installation of the horizontal structure of each layer is completed up to the bottom surface of the excavated portion and the inclined support member is separated,
Underground structure construction apparatus, characterized in that reinforced concrete is reinforced to form a permanent wall in addition to the retaining wall.
상기 센터파일을 제거 후에 상기 각층 수평구조물과 상기 첫째단 수평구조물을 지지하는 상기 층간기둥에 겹치지 않도록 상기 층간기둥의 위치에 근접하여 설치되는 것을 특징으로 하는 지하 구조물 구축장치.The method according to any one of claims 2 to 10, wherein the center pile is
After the removal of the center pile, underground structure building apparatus, characterized in that installed close to the position of the inter-layer column so as not to overlap the inter-layer column for supporting the horizontal structure and the first-level horizontal structure.
21. The basement construction device according to claim 20, wherein the center pile further includes a brace member protruding to support the first horizontal structure and each horizontal structure.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100015362A KR100967496B1 (en) | 2010-02-19 | 2010-02-19 | Device for constructing an underground structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020100015362A KR100967496B1 (en) | 2010-02-19 | 2010-02-19 | Device for constructing an underground structure |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100967496B1 true KR100967496B1 (en) | 2010-07-07 |
Family
ID=42645120
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020100015362A KR100967496B1 (en) | 2010-02-19 | 2010-02-19 | Device for constructing an underground structure |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100967496B1 (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2012044091A2 (en) * | 2010-09-30 | 2012-04-05 | (주)바로건설기술 | Device and method for constructing underground structure |
KR101707376B1 (en) | 2016-05-20 | 2017-02-16 | (주)대우건설 | Structure for constructing underground structure using composite beams and the construction method thereof |
CN108222023A (en) * | 2018-03-12 | 2018-06-29 | 江苏东合南岩土科技股份有限公司 | Double-deck foundation pit combined steel support and method of construction |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR19990037110U (en) * | 1999-06-24 | 1999-10-05 | 박정진 | Hanging semi down up system |
KR20050113450A (en) * | 2004-05-29 | 2005-12-02 | (주)새길이엔시 | Downward reinforced-concrete underground structure using temporary assistant columns |
KR100855098B1 (en) | 2007-05-22 | 2008-08-29 | 정택동 | Strut structure as temporary system using a vertical truss at the end and the method thereof |
-
2010
- 2010-02-19 KR KR1020100015362A patent/KR100967496B1/en active IP Right Grant
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR19990037110U (en) * | 1999-06-24 | 1999-10-05 | 박정진 | Hanging semi down up system |
KR20050113450A (en) * | 2004-05-29 | 2005-12-02 | (주)새길이엔시 | Downward reinforced-concrete underground structure using temporary assistant columns |
KR100855098B1 (en) | 2007-05-22 | 2008-08-29 | 정택동 | Strut structure as temporary system using a vertical truss at the end and the method thereof |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
WO2012044091A2 (en) * | 2010-09-30 | 2012-04-05 | (주)바로건설기술 | Device and method for constructing underground structure |
WO2012044091A3 (en) * | 2010-09-30 | 2012-06-21 | (주)바로건설기술 | Device and method for constructing underground structure |
KR101341679B1 (en) * | 2010-09-30 | 2013-12-16 | (주)바로건설기술 | Device for constructing an underground structure and method thereof |
KR101707376B1 (en) | 2016-05-20 | 2017-02-16 | (주)대우건설 | Structure for constructing underground structure using composite beams and the construction method thereof |
CN108222023A (en) * | 2018-03-12 | 2018-06-29 | 江苏东合南岩土科技股份有限公司 | Double-deck foundation pit combined steel support and method of construction |
CN108222023B (en) * | 2018-03-12 | 2024-04-05 | 江苏东合南岩土科技股份有限公司 | Double-layer foundation pit combined steel support and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR100967497B1 (en) | Method for constructing an underground structure | |
KR101014796B1 (en) | Top-down underground construction method using prefabricated concrete column member as temporary bridge column | |
KR101034398B1 (en) | Land-side protection wall that use ground structure | |
KR101341679B1 (en) | Device for constructing an underground structure and method thereof | |
KR100957599B1 (en) | Basement-structure construction method to use temporary earth retaining structure | |
KR101205783B1 (en) | The complex execution method which dismantling work of existing underground structure and constructs of new building simultaneously | |
KR20140055639A (en) | A execution method of architecture beam | |
JP5937488B2 (en) | Temporary support method for foundation | |
KR101296857B1 (en) | Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same | |
KR20080007483A (en) | Underground retaining wall for public works and method for constructing the same | |
KR20090090742A (en) | Bottom-up construction method of underground structure using permanent strut | |
KR101262357B1 (en) | Inclined Earth Retaining Structure Method | |
KR101187170B1 (en) | Application of under pinning method in remodeling | |
KR100967496B1 (en) | Device for constructing an underground structure | |
KR101296856B1 (en) | Reinforcement structure for wall of underground structure and construction method of underground structure using the same | |
KR101054696B1 (en) | Top-down construction method for underground structure with slurry wall retained by slab diaphragm effect | |
KR101358471B1 (en) | architecture using a complex steel pile | |
KR20080025219A (en) | Underground outer wall construction method using deck-plate and deck-plate for constructing underground outer wall | |
KR101426511B1 (en) | A temporary skeleton system used in constructuring a underground structure of a building and a top down underground construction method using a temporary skeleton system | |
JP7338119B2 (en) | Floating control structure and reversed construction method | |
JP4228308B2 (en) | Reinforcement method for existing floors and seismic isolation method for existing buildings | |
AU2020100004A4 (en) | A Method Of Constructing A Column, A Subterranean Structure, And A Structure Made From The Method | |
KR100615149B1 (en) | A method of construction top-down for the ground fabric construction | |
KR101257905B1 (en) | Method for constructing foundation work | |
JP4529631B2 (en) | Underground structure and construction method of underground structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20130415 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20140408 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20160705 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20170327 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20180524 Year of fee payment: 9 |