KR20050113450A - Downward reinforced-concrete underground structure using temporary assistant columns - Google Patents

Downward reinforced-concrete underground structure using temporary assistant columns Download PDF

Info

Publication number
KR20050113450A
KR20050113450A KR1020040038635A KR20040038635A KR20050113450A KR 20050113450 A KR20050113450 A KR 20050113450A KR 1020040038635 A KR1020040038635 A KR 1020040038635A KR 20040038635 A KR20040038635 A KR 20040038635A KR 20050113450 A KR20050113450 A KR 20050113450A
Authority
KR
South Korea
Prior art keywords
temporary
pillar
support
reinforced concrete
underground
Prior art date
Application number
KR1020040038635A
Other languages
Korean (ko)
Other versions
KR100625115B1 (en
Inventor
최정범
유영록
신승목
홍찬유
Original Assignee
(주)새길이엔시
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)새길이엔시 filed Critical (주)새길이엔시
Priority to KR1020040038635A priority Critical patent/KR100625115B1/en
Publication of KR20050113450A publication Critical patent/KR20050113450A/en
Application granted granted Critical
Publication of KR100625115B1 publication Critical patent/KR100625115B1/en

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

본 발명은, 시공시 상부에 재하되는 하중을 가설보조기둥(5)을 설치하여 지지기둥(4)과 분배시키므로써, 지지기둥(4)의 규모를 축소시킬 수 있고, 철골의 소형화, 천공의 소구경화를 도모할 수 있는 철근콘크리트 역타설 지하구조물 축조 공법을 제공한다.According to the present invention, by installing a temporary auxiliary pillar (5) to distribute the load to the support pillar (4), the scale of the support pillar (4) can be reduced, and the size of the steel frame can be reduced. To provide reinforced concrete reinforcement underground structure construction method for small diameter hardening.

지하 구조물이 축조되는 구역에 H형강을 이용한 일반 가설흙막이벽(15)이나 지하연속벽(2)을 이용한 영구벽체를 설치하여 토압이나 수압 등 외력에 대응하고, 지지기둥(4)과 가설보조기둥(5)이 설치될 곳에 천공 후 표준화된 소형H형강이나 표준화된 소형 강관을 근입시킨 후, 하중전달을 위한 전단 연결재(7)를 설치한 다음, 굴착 작업을 실시하고 가설보조기둥(5)의 기둥머리(6)를 포함한 철근 콘크리트를 타설하는 작업을 지하층 상부에서부터 구조물의 최하단까지 역타설로 완료한 후에 외벽체(11)와 지지기둥(4)을 순타설하여 지하 구조물을 축조한 다음 가설보조기둥(5)을 절단, 제거하여 지하구조물을 완료하는 공법이다.In the area where underground structures are constructed, permanent temporary walls using H-beams or permanent walls using underground continuous walls (2) are installed to cope with external forces such as earth pressure and water pressure, and support columns (4) and temporary support columns. After drilling (5) where the standard small H-shaped steel or standardized small steel pipes are to be installed, install the shear connector (7) for load transfer, and then carry out excavation work and install the temporary auxiliary pillar (5). After finishing the reinforcement of reinforced concrete including the column head (6) from the top of the basement floor to the bottom of the structure by reverse casting, the outer wall body (11) and the support column (4) are cast in place to construct the underground structure, and then the temporary auxiliary pillar This method is to complete underground structure by cutting and removing (5).

지상에서 지하로 역타설로 시공되는 공법의 특성상 지지기둥(4)은 1,2차로 구분하여 시공하고 있으며 1차는 시공시 작용하는 상부 연직력을 말뚝 개념의 철골로서 지지하고 지하 전층의 보, 슬래브 타설이 완료된 후에는 2차로 철골의 외곽을 철근 콘크리트 기둥으로 설치한다. 따라서 1차 지지기둥(4)으로서 시공되는 철골은 가설의 의미가 있으므로 최소화할 필요가 있으며, 이에 따라 가설보조기둥(4)을 추가 설치하여, 지지기둥의 하중 분담을 최소화한 것이 본 발명의 특징이다.Due to the nature of the construction method, which is constructed from the ground to the underground, the support pillars (4) are divided into 1st and 2nd stages, and the 1st supports the upper vertical force acting during construction as steel frame of pile concept, and the beams and slabs of the basement floor After the casting is completed, the outside of the steel frame is installed with reinforced concrete columns. Therefore, the steel frame constructed as the primary support pillar (4) needs to be minimized because there is a meaning of the hypothesis, according to the additional installation of the temporary support pillar (4), to minimize the load sharing of the support pillar to be.

Description

가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물 축조 공법{downward reinforced-concrete underground structure using temporary assistant columns}Downward reinforced-concrete underground structure using temporary assistant columns

본 발명은 구조물 시공시 지하구조부를 철근콘크리트 역타설로 시공하는 공법(DOWNWARD)에 관한 것으로, 굴착 전 설치하는 지지기둥의 철골 크기를 줄이기 위하여 기둥머리를 이용한 가설보조기둥을 설치하여 상부하중을 지지기둥과 분배하고, 철근 콘크리트조로서 지지기둥을 마감한 후 가설보조기둥을 철거하여 지하구조물을 완성하는 공법에 관한 것이다.The present invention relates to a construction method (DOWNWARD) for the construction of underground structures to be reinforced concrete reinforcement during construction of the structure, to support the upper load by installing a temporary auxiliary column using the column head to reduce the size of the steel frame of the support pillar to be installed before excavation The present invention relates to a construction method for distributing pillars, finishing supporting columns as reinforced concrete, and then removing temporary auxiliary columns to complete underground structures.

지하 구조물을 축조하는데 있어 지금까지의 주요 지하 구조물 시공법은, 굴토계획선을 따라 가설흙막이벽(15)을 설치하고 지지체로서 토압이나 수압 등의 외력을 지탱하면서 지상(13)에서 지하(14)의 기초바닥까지 굴착 완료한 다음 각 층 구조물을 바닥에서 상부로 순차적으로 축조 하면서 본 구조물을 시공하는 개착식 공법과 가설흙막이 벽(15)을 설치하지 않고 철근 콘크리트를 지중에 영구벽체(지하연속벽,2)로서 설치하고 현장 타설말뚝으로서 합성지지기둥을 형성하여 지하 구조물과 동시에 지상구조물을 수행할 수 있는 탑다운(TOP DOWN) 공법과 동일한 방법으로서 지하구조물을 완료한 후 지상구조물을 시공하는 다운워드(DOWNWARD) 공법이 있다.In the construction of underground structures, the main underground structure construction method has been to install temporary temporary wall 15 along the excavation plan line and to support the external force such as earth pressure and water pressure as a support. After the excavation is completed to the foundation floor, each floor structure is constructed sequentially from the bottom to the top, and the permanent construction (underground continuous wall, underground continuous wall) 2) Downward construction of ground structures after completion of underground structures in the same way as the TOP DOWN method, which can be installed on the ground and form composite support pillars as site-pouring piles to perform ground structures simultaneously with underground structures. (DOWNWARD) There is a method.

그러나 개착식 공법에는 적용 한계가 있는 바, 첫째 지하 구조물의 규모가 크고 굴착심도가 깊은 대형 현장에서는 흙막이 벽체(15)에 작용되는 토압과 수압 등의 외력을 지탱하여 주어야하나 일반 흙막이 벽체로서는 취약한 문제점이 있으며, 둘째 건축물이 밀집된 도심지에서는 흙막이 벽체의 변형이나 지하수 유출에 의한 지반침하로 인하여 주변 건축물에 위해가 발생 될 수 있는 문제점이 있으며, 셋째 외부에 노출된 상태에서 굴토작업과 구조물 공사를 수행함에 따라 소음 과 진동 및 분진에 의한 환경 및 민원 발생의 문제점이 있으며, 넷째 흙막이 공사가 완료된 후에 순차적으로 공사를 수행하는 관계로 공사기간이 길어지는 문제점이 있다.However, there is a limit to the application of the detachable method. First, in a large site with a large underground structure and a deep excavation depth, it is necessary to support external forces such as earth pressure and water pressure acting on the retaining wall 15, but it is a weak problem for a general retaining wall. Second, there is a problem that the surrounding buildings may be damaged due to the deformation of the retaining wall or ground subsidence due to the outflow of groundwater in the downtown area where the buildings are concentrated. Third, to perform the excavation work and the construction work in the exposed state. Therefore, there are problems of environment and civil complaints caused by noise, vibration, and dust, and the fourth construction period is long because construction works are sequentially performed after the completion of the construction of the earthenware.

또한, 개착식 공법의 문제점을 많이 해소 할 수 있는 탑다운(TOP DOWN)공법과 다운워드(DOWNWARD)공법에서도 문제점이 있다. 첫째 지중에 설치하는 지하연속벽(2)은 장비에 의한 수직 굴착 후 철근을 근입한 다음 콘크리트를 타설하므로 단면을 변화 시킬 수가 없어 벽체 두께를 일정하게 할 수밖에 없으나, 외력이 적게 작용하는 지하층에서는 동일한 벽체 두께로 인하여 내부면적이 감소하고 굴착 및 콘크리트 타설량의 경제적인 문제가 있으며, 둘째 대형장비를 사용하여 지중에 철근 콘크리트 영구 벽체를 설치하므로 암반굴착 등으로 많은 공사 기간 및 비용이 소요 되고 있으며, 셋째 철근 콘크리트 구조의 지하층을 먼저 축조하는 다운워드공법에서, 상부하중을 지지하기 위한 지지기둥(4)은 대형 철골을 제작하여 사용하고 있으며 이를 설치하기 위하여 Φ800~Φ1200의 대구경 천공을 하여야 하지만 이는 많은 시간과 비용을 요구한다.In addition, there is a problem in the TOP DOWN method and DOWNWARD method that can solve a lot of problems of the sticking method. First, the underground continuous wall (2) to be installed in the underground will be forced to rebar after vertical excavation by equipment, and then concrete will be changed so that the cross section cannot be changed, but the wall thickness must be constant. Due to the thickness of the wall, the internal area is reduced and there are economic problems of excavation and concrete placing. Second, since the reinforced concrete permanent walls are installed in the ground using large equipment, many construction periods and costs are required due to rock excavation. Third, in the downward method of constructing the basement layer of reinforced concrete structure first, the support column (4) for supporting the upper load is made by using large steel frame, and to install it, large diameter drilling of Φ800 ~ Φ1200 should be performed. It requires time and money.

상기 문제점중의 첫째와 둘째는, 발명자가 엄지말뚝(1)을 사용한 일반 흙막이벽(15)을 이용한 개량형 탑다운 공법(특허번호 제0273864호)을 발명하여 현장적용함에 따라 이러한 문제점을 해소할 수 있었다.The first and second of the problems, the inventors can solve this problem by inventing the improved top-down method (Patent No. 0273864) using the general mud wall 15 using the thumb pile (1). there was.

그러나, 여전히 셋째의 문제점, 즉, 도4a 의 R.C.D 현장타설말뚝 천공경은 Φ1,500∼Φ3,000이며, 도4b의 P.R.D 현장타설말뚝의 천공경은 Φ800∼Φ1,200으로서 사용철골은 H형이나 상자형으로 제작되어 사용하기 때문에 이러한 대구경 천공에 의한 철골 근입과 제작은 정밀한 작업이 요구되며 많은 비용과 공기가 소요된다는 등의 문제가 있다.However, there is still a third problem, that is, the drill hole diameter of the RCD cast hole in FIG. 4A is Φ1,500 to Φ3,000, and the drill hole diameter of the PRD cast iron pile in FIG. 4B is Φ800 to Φ1,200. Since it is manufactured in a mold and used, the steel indentation and fabrication by the large-diameter drilling requires precise work and requires a lot of cost and air.

본 발명의 목적은, 철근 콘크리트 구조의 특히 다운워드공법을 적용하는 현장에서, 시공시 지하층에 재하되는 하중(사하중이 주된 것임)을 지지하는 기둥은 표준화된 소형 H형강이나 표준화된 소형 강관을 사용하고, 구조물 완성후에 재하되는 모든 하중은 콘크리트 타설에 의한 R.C 지지기둥으로 확대하여 지지되는 것이고, 역타설시 사용하는 지지철골은 가설개념이므로, 철골의 소형화, 천공의 소구경화를 도모할 수 있어 공사비용과 공기를 크게 저감시킬 수 있는 공법을 제공하는 것이다.The object of the present invention is to use a standard small H-shaped steel or a standardized small steel pipe for supporting the load (mainly dead load) loaded on the basement floor during construction, especially in the site of the down concrete method of reinforced concrete structure All the loads after the completion of the structure are expanded and supported by RC support pillars by concrete placing. Since the supporting steel used for reverse casting is a temporary concept, it is possible to miniaturize the steel frame and reduce the size of the drilling. It is to provide a method that can greatly reduce costs and air.

상술한 본 발명의 목적을 달성하기 위한 가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물 축조 공법의 일실시예는, 지하구조물이 축조되는 구역에 엄지말뚝을 이용한 가설흙막이벽 또는 지하연속벽을 이용한 영구 벽체를 설치하고 지지기둥을 지중에 근입시킨 다음 각 층별로 굴토하면서 철근 콘크리트 구조물을 역타설하여 축조하는 공법에 있어서, 상기 지지기둥의 철골 크기를 소형화 내지 소규모화하기 위해 지지기둥사이에 가설보조기둥을 설치하여 지지기둥에 작용하는 상부 하중을 서로 분담시키면서, 각 층별로 굴토와 콘크리트를 역타설로 바닥까지 시공한 후, 외벽체와 지지기둥의 콘크리트를 순타설함으로써 철근콘크리트조 지하 구조물을 완성하며, 그 뒤, 가설 보조 기둥은 절단하여 철거하는 것을 특징으로 한다.One embodiment of the reinforced concrete reinforcement underground structure construction method using a temporary auxiliary pillar to achieve the above object of the present invention, the permanent construction using a temporary soil wall or underground continuous wall using a thumb pile in the area where the underground structure is built In the method of installing walls and entering the support pillar into the ground, and then reinforcing the reinforced concrete structure while excavating for each floor, a temporary auxiliary pillar is placed between the support pillars to reduce or reduce the size of the steel frame of the support pillar. By installing the pit soil and concrete to the floor with each other floor while sharing the upper loads acting on the supporting pillars by each other, and then netting the concrete of the outer wall and the supporting pillar to complete the reinforced concrete basement structure. The temporary auxiliary column is then cut and demolished.

이하, 첨부된 도면을 참조하여 본 발명의 바람직한 실시예들을 상세히 설명하면 다음과 같다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

본 발명도, 구조물의 지하층을 역타설로 완료한 다음 상부 구조물을 시공하는 다운워드(DAWNWARD) 공법에 있어서 흙막이 버팀기둥으로서 작용하는 엄지말뚝(1)을 주로 하는 흙막이 벽체와 지지체로서 슬래브와 지지기둥(4)을 설치하고 하부로 굴착하면서 구조물을 축조하는 점에 있어서는 종래의 것과 기술적인 개념을 같이한다.In the present invention, the slab and the support pillar are mainly used as the wall and the support body, which mainly consists of the thumb pile (1) acting as the support pillar in the DAWNWARD method after completing the basement of the structure by reverse casting. When constructing the structure while installing (4) and excavating downward, the technical concept is the same as the conventional one.

다만, 본 발명의 가설보조기둥을 이용한 역타설 지하구조물 축조공법은 도 5a, 5b, 6a, 6b에 도시된 바와 같이 엄지 말뚝(1)이나 지하연속벽(2)으로서 흙막이 벽체를 형성하고 지지기둥(4)을 지중에 설치 한 다음, 상부에서부터 단계별로 굴토작업을 하면서 철근 콘크리트 지하 구조물을 축조하는데 있어서, 상부하중을 지지하기 위한 지지기둥(4)은 철골을 제작하여 사용하고 있으나 대구경 천공에 따른 대형 천공장비가 사용되어야 하므로 경제성이 저하되고 많은 공사기간이 소요되는바 소요의 가설보조기둥을 설치하여 지지기둥의 하중을 효율적으로 분배함을 기술적 구성상의 특징으로 한다.However, the reverse casting underground structure construction method using the hypothesis secondary pillar of the present invention forms a retaining wall as a thumb pile 1 or a continuous underground wall 2 as shown in FIGS. 5A, 5B, 6A, and 6B, and supports pillars. After installing (4) in the ground, and constructing the reinforced concrete underground structure by gulting work from the top step by step, the supporting column (4) for supporting the upper load is made of steel frame, but according to the large diameter drilling Because large drilling equipment should be used, it is economical and requires a lot of construction periods. It is characterized by the technical construction that it distributes the load of supporting pillar efficiently by installing temporary supporting pillars.

본 발명의 일실시예에 따라 기둥머리를 포함한 가설보조기둥(5)을 이용한 역타설 철근콘크리트조 지하구조물 축조 공법의 실시예를 더욱 구체적으로 설명하면 다음과 같다.According to an embodiment of the present invention will be described in more detail an embodiment of the reinforcement reinforced concrete tank underground structure construction method using a temporary auxiliary pillar (5) including a column head.

먼저 도 6b에서와 같이 지지기둥(4)의 하중을 경감 분담할 수 있도록 가설보조기둥(5)을 설치하는데 가설보조기둥의 설치 개수는 엄지말뚝(1) 설치시 천공하였던 장비를 그대로 사용 할 수 있고 표준화된 소형 H형강이나 표준화된 소형 강관을 사용할 수 있으며, 지하층의 규모에 따른 작용하는 상부하중을 고려하여 산정하고, 가설보조기둥(5)의 설치 위치는 지지기둥(4)과 상부하중을 균등분배 할 수 있고 시공시 작업에 지장을 주지 않는 곳을 선정하며, 지지기둥과 가설보조기둥이 좌굴되지 않도록 허용 편심을 고려하여 수직도를 유지하면서 천공하여 시공한다.First, as shown in Figure 6b to install the temporary auxiliary pillar (5) to share the load of the support pillar (4) to reduce the number of installation of the temporary auxiliary pillar can be used as the equipment was drilled when installing the thumb pile (1) The standardized small H-beam or standardized small steel pipe can be used, and it is calculated by considering the upper load acting according to the size of the basement. The installation position of the temporary auxiliary pillar (5) is determined by the supporting column (4) and the upper load. Select the place where it can be distributed evenly and do not interfere with the construction work, and make the perforation while maintaining the verticality in consideration of the allowable eccentricity so that the supporting pillar and the temporary supporting pillar are not buckled.

기둥의 수직도를 정밀하게 설치하기 위하여 1차 가이드케이싱(GUIDE CASING)을 설치하고 콘크리트 등으로 고정시킨 다음 2차 가이드케이싱을 설치하여, 토사는 오거로 암반은 에어함머나 비트를 사용하여 천공하고 수직도는 현장에서 점검장비로서 확인한다.In order to install the verticality of the column precisely, install the first guide casing, fix it with concrete, and then install the second guide casing. Verticalness is checked on site as inspection equipment.

도7의 가설보조기둥(5)은 상부 하중을 지지기둥(4)과 분배하여 전달하기 위하여 설치되며 기둥과 슬래브의 가설보조 연결 구조는 전단연결재(STUD,7)를 사용하지만 슬래브에 그대로 연결하다면 구조물의 슬래브 두께가 얕은 관계로 하중 전달에 무리가 있으며 펀칭(PUNCHING) 될 수가 있으므로, 구조물 슬래브에 기둥머리(DROP PANEL,6)를 설치하여 전단연결재(7)로서 하중을 원활히 전달 할 수 있도록 하며, 분담하중에 따라 전단연결재의 수와 기둥머리의 폭과 두께를 결정한다. 전단연결재는 스터드(STUD)를 사용으로 함을 기본으로 하지만, 필요에 따라 링형상이나 H형강 등의 다양한 구조나 형상이 사용될 수 있다.The temporary auxiliary column 5 of FIG. 7 is installed to distribute the upper load with the supporting column 4, and the temporary auxiliary connecting structure of the column and the slab uses the shear connector (STUD, 7), but is connected to the slab as it is. As the slab thickness of the structure is shallow, it is difficult to transfer the load and can be punched. Therefore, the DROP PANEL 6 is installed on the structure slab to smoothly transfer the load as the shear connector 7. The number of shear connectors and the width and thickness of the column heads are determined by the sharing load. Shear connector is based on the use of a stud (STUD), but various structures or shapes, such as ring-shaped or H-shaped steel can be used if necessary.

종래의 기술에서 설명한 바와 같이, 도4a와 같은 종래의 R.C.D 현장타설말뚝 천공경은 Φ1,500∼Φ3,000이며 도4b의 P.R.D 현장타설말뚝의 천공경은 Φ800∼Φ1,200으로서 사용철골은 H형이나 상자형으로 제작되어 사용된다. 이러한 대구경 천공에 의한 철골 근입과 제작은 정밀한 작업이 요구되며 많은 비용과 공기가 소요된다.As described in the prior art, the conventional RCD cast-in-place pile boring diameter as shown in FIG. 4A is Φ1,500 to Φ3,000, and the drill diameter of the PRD cast-in-place pile in FIG. 4B is Φ800 to Φ1,200. It is manufactured and used in a box shape. Steel intrusion and production by such a large diameter drilling requires precise work, high cost and air.

도8a 및 도8b는 가설보조기둥(5)과 지지기둥(4)의 단면과 상세도로서, R.C.D 나 P.R.D 보다 훨씬 적은 Φ500 이하의 천공경(16)으로서 흙막이 벽체의 엄지말뚝(1) 천공장비로서도 가능하며 표준화된 소형 H형강이나 표준화된 소형 강관을 사용할 수 있다.8A and 8B are cross-sectional and detailed views of the hypothetical support pillar 5 and the support pillar 4, with the drill pile 16 of the perforated wall 1 having a hole diameter 16 of Φ 500 or less, much smaller than that of the RCD or PRD. It is also possible to use standardized small H-beams or standardized small steel pipes.

도9a 내지 도9h는 본 발명의 일 실시예의 시공순서도이다. 먼저 도 9a는 일반 흙막이 벽체 설치도로서, H형강을 엄지말뚝(1)으로서 지중(14)에 근입하고 토사구간에는 차수와 지반 강화를 위하여 주열식 말뚝 및 그라우팅을 실시한다. 9A to 9H are construction flowcharts of one embodiment of the present invention. First, Figure 9a is a general earth wall installation diagram, H-shaped steel into the ground (14) as the thumb pile (1), and the sediment section is subjected to the heat-stacked pile and grouting for order and ground reinforcement.

도9b는 지하연속벽체 설치도로서, 지중(14)에 트랜치 컷(TRENCH CUT) 하여 안정액 으로서 굴착 공벽을 유지하고 철근을 조립 및 근입한 다음 콘크리트를 타설하여 지하연속벽(2)으로 영구 벽체를 형성한다.FIG. 9B is a drawing of the installation of the underground continuous wall, the trench cut in the ground (14) to maintain the excavated hollow wall as a stabilizer, assemble and reinforce the reinforcing bars, and then cast concrete to install the permanent wall into the underground continuous wall (2) Form.

그 뒤, 도9c에서는 가설보조기둥(5)과 지지기둥(4)의 위치에 일반 천공한 후, 표준화된 소형 H형강을 근입하고 전단연결재(7)를 설치한 다음 굴착 저면은 콘크리트를 타설하여 말뚝 기초로서 기둥을 고정시킨다.Then, in Fig. 9c, after general drilling at the position of the temporary support pillar (5) and the support pillar (4), the standardized small H-shaped steel is introduced and the shear connector 7 is installed, and then the excavation bottom is poured concrete. Secure the column as a pile foundation.

도9d에서는 가설보조기둥(5)과 지지기둥(4)의 위치에 표준화된 소형유공강관을 근입하고 주면 및 선단 지지로서 소요의 지반지지력을 얻을 수 있도록 그라우팅을 실시 한 다음 콘크리트를 타설하여 말뚝기초로서 기둥을 고정시킨다.In Fig. 9d, a small perforated steel pipe standardized at the positions of the temporary supporting column 5 and the supporting column 4 is inserted, and grouting is carried out to obtain the required ground supporting force as the main surface and the end support. To fix the column.

도9e에 도시된 바와 같이 그 가설보조기둥(5)이나 지지기둥(4)에는 하중 전달을 원활히 하기 위하여 전단연결재(7)를 설치하며, 기둥머리(6)에 설치하는 전단연결재(7)는 하중전달을 목적으로 설치되고, 선단에 미리 설치하는 전단연결재는 말뚝으로서 지반에 하중을 지지시키는 목적을 지닌다.As shown in FIG. 9E, the temporary auxiliary pillar 5 and the support pillar 4 are provided with a shear connecting member 7 to facilitate load transfer, and the shear connecting member 7 installed at the column head 6 is provided. The shear connector, which is installed for the purpose of load transfer and is installed in advance at the tip, has the purpose of supporting the load on the ground as a pile.

그 다음, 도9f에서와 같이 상부에서 하부 지하층별로 굴착과 기둥머리(6)를 포함한 철근콘크리트 타설을 반복 작업하며 기초로서 마감한다.Then, as shown in Fig. 9f, excavation and reinforcement of the reinforced concrete including the column head 6 at the upper basement floors are repeated and finished as a foundation.

이와 같이 기초를 마감한 후, 외벽체와 지지기둥(4)은 상부하중을 줄이기 위하여 소형 철골 상태로서 시공하였으나, 굴착과 기초시공이 완료한 후에는 도 9g에서와 같이 최저층부터 상부층으로 순차적으로 외벽체와 지지기둥의 콘크리트를 타설하여 철근 콘크리트 지하 구조물을 완료한다.After finishing the foundation in this way, the outer wall and the support column 4 was constructed as a small steel frame in order to reduce the upper load, but after the completion of excavation and foundation construction, as shown in Figure 9g sequentially from the lowest layer to the upper layer and the outer wall and The concrete of the supporting column is poured to complete the reinforced concrete underground structure.

상부하중을 줄이기 위하여 보조적으로 사용하였던 가설보조기둥의 기능이 완료하였으므로 도9h에서와 같이 가설보조기둥(5)을 철거하고 지상(13)의 구조부를 시공한다.Since the function of the temporary auxiliary pillar used to assist in reducing the upper load is completed, the temporary auxiliary pillar 5 is removed as shown in FIG. 9H and the structural part of the ground 13 is constructed.

이상에서 살펴본 바와 같이 본 발명의 가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물 축조 공법의 구성과 작용에 의하면, 지하구조물 공사에서 지지기둥(5)과 함께 기둥머리를 이용한 가설보조기둥(5)을 설치하여 시공하므로, 굴착 시공시 지지기둥(5)의 철골의 소형화, 천공경의 소구경화를 도모할 수 있어, 공사비용을 크게 저감시킬 수 있을 뿐만 아니라, 이에 따라 공기단축 등 공사의 원활은 물론 안정적이고 경제적으로 유리하게 되는 등의 효과를 가지게 된다. 더욱, 엄지말뚝(1)을 이용한 경우, 그 엄지말뚝(1) 설치시 천공하였던 장비를 그대로 사용할 수 있고 표준화된 소형 H형강이나 표준화된 소형 강관을 사용할 수 있어 더욱 효과적이다.As described above, according to the construction and operation of the reinforced concrete reverse casting underground structure construction method using the temporary auxiliary pillar of the present invention, the temporary auxiliary pillar (5) using the column head together with the supporting column (5) in the underground structure construction By installing and constructing, it is possible to miniaturize the steel frame of the support pillar (5) and to reduce the diameter of the hole diameter during the excavation construction, so that the construction cost can be greatly reduced, and accordingly, the construction of the construction such as air shortening is smooth and stable. And economically advantageous. In addition, in the case of using the thumb pile (1), it is possible to use the equipment drilled when the thumb pile (1) is installed as it is, it is more effective to use a standardized small H-shaped steel or a standardized small steel pipe.

도1a 및 도1b는 종래 실시예의 일부 개략평면도이다.1A and 1B are some schematic top views of a prior art embodiment.

도2a 및 도2b는 종래 실시예의 일부 개략단면도이다.2A and 2B are some schematic cross-sectional views of a prior art embodiment.

도3a 및 도3b는 종래 실시예의 현장타설말뚝의 횡단면도이다.3A and 3B are cross-sectional views of the cast-in-place pile of the prior art embodiment.

도4a 및 도4b는 종래 실시예의 현장타설말뚝의 길이방향 부분단면도이다.4A and 4B are longitudinal partial cross-sectional views of the cast-in-place pile of the prior art embodiment.

도5a 및 도5b는 본 발명 실시예의 일부평면도이다.5A and 5B are partial plan views of embodiments of the present invention.

도6a는 표준화된 소형 H형강을 사용한 지지기둥과 가설 보조 기둥의 개략 부분 단면도이고, 도6b는 표준화된 소형 강관을 사용한 지지기둥과 가설 보조 기둥의 개략 부분 단면도이다.FIG. 6A is a schematic partial cross-sectional view of a support pillar and a temporary auxiliary column using small H-shaped standardized steel, and FIG. 6B is a schematic partial cross-sectional view of a support pillar and a temporary auxiliary column using a small standardized steel pipe.

도7은 도6a 또는 도6b의 가설보조기둥의 기둥머리 부분의 단면도이다.7 is a cross-sectional view of the pillar head portion of the temporary support pillar of FIG. 6A or 6B.

도8a는 지지기둥과 가설보조기둥 표준화된 소형 H형강의 횡단면도이고, 도8b는 지지기둥과 가설보조기둥의 표준화된 소형 강관의 횡단면도이다.Fig. 8A is a cross sectional view of a standardized small H-beam of a support column and a temporary support pillar, and FIG. 8B is a cross-sectional view of a standardized small steel pipe of a support column and a temporary support pillar.

도9a 내지 도9h는 본 발명에 따른 일 실시예의 시공 순서를 도시한 개략도이다.9A to 9H are schematic diagrams showing the construction sequence of an embodiment according to the present invention.

<도면의 주요 부분에 대한 부호 설명><Description of the symbols for the main parts of the drawings>

1: 엄지말뚝 2: 지하 연속벽1: thumb pile 2: underground continuous wall

3: 주열식 말뚝 4: 지지기둥 3: columnar pile 4: support column

5: 가설보조기둥 6: 기둥머리(DROP PANEL)5: Temporary Auxiliary Column 6: DROP PANEL

7: 전단 연결재(STUD) 8: 유공 강관7: Shear connector (STUD) 8: Perforated steel pipe

9: R.C 지지기둥 10: 각층 슬래브9: R.C support pillar 10: each layer slab

11: 외벽 12: 기초 콘크리트11: outer wall 12: foundation concrete

13: 지상 14: 지하(지중)13: Ground 14: Underground (Underground)

15: 가설 흙막이벽 16: 천공경15: Hypothesis wall 16: Perforation

Claims (5)

지하구조물이 축조되는 구역에 엄지말뚝(1)을 이용한 가설흙막이벽(15) 또는 지하연속벽(2)을 이용한 영구 벽체를 설치하고 지지기둥을 지중에 근입시킨 다음 각 층별로 굴토하면서 철근 콘크리트 구조물을 역타설하여 축조하는 공법에 있어서,Reinforced concrete structures are installed in the area where the underground structures are constructed by installing temporary walls (15) using permanent piles (1) or permanent walls using underground continuous walls (2). In the construction method of inverse pouring the construction, 상기 지지기둥(4)의 철골 크기를 소형화 내지 소규모화하기 위해 지지기둥(4)사이에 가설보조기둥(5)을 설치하여 지지기둥(4)에 작용하는 상부 하중을 서로 분담시키면서, 각 층별로 굴토와 콘크리트를 역타설로 바닥까지 시공한 후, 외벽체와 지지기둥(4)의 콘크리트를 순타설함으로써 철근콘크리트조 지하 구조물을 완료하며, 그 뒤, 가설 보조 기둥(5)은 절단하여 철거하는 것을 특징으로 하는, 가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물 축조 공법.In order to reduce or reduce the size of the steel frame of the support pillar 4, a temporary auxiliary pillar 5 is installed between the support pillars 4, thereby sharing the upper loads acting on the support pillars 4 with each other. After constructing the concrete to the floor by back-pouring, the concrete of the outer wall body and the support pillar 4 is completed, and the reinforced concrete-based underground structure is completed, and then the temporary auxiliary column 5 is cut and demolished. Reinforced concrete reinforcement underground structure construction method using temporary support pillar. 제1항에 있어서, 지지기둥(4)과 가설보조기둥(5)은 소형강재 사용으로 소구경화하여 천공할 수 있으며, 그 소형강재로서 표준화된 소형 H형강 및/또는 강관을 사용할 수 있는 것을 특징으로 하는, 가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물 축조 공법.The support pillar (4) and the temporary support pillar (5) can be drilled by small diameter by using small steel, and can be used as a small steel standardized small H-shaped steel and / or steel pipes Reinforced concrete reinforcement underground structure construction method using temporary support pillar. 제2항에 있어서, 가설보조기둥(5) 및/또는 지지기둥(4)은, 엄지말뚝(1)을 이용한 가설흙막이벽(15)의 경우, 엄지말뚝(1) 설치시 천공하였던 장비를 그대로 사용할 수 있고 소형강재로서 표준화된 소형 H형강 및/또는 표준화된 소형 강관을 사용할 수 있으며 지하층의 규모에 따라 작용하는 상부하중을 지지기둥(4)과 균등분배할 수 있고 시공시 작업에 지장을 주지 않도록 그 설치 수량 및/또는 설치 위치를 설정하는 것을 특징으로 하는, 가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물 축조 공법.The temporary support pillar (5) and / or support pillar (4) according to claim 2, in the case of the temporary soil wall (15) using the thumb pile (1), the equipment that was drilled at the time of installing the thumb pile (1) as it is It can be used as a small steel standardized small H-shaped steel and / or standardized small steel pipe, and it is possible to equally distribute the upper load acting according to the size of the basement layer with the supporting pillar (4) and do not interfere with the construction work. Reinforced concrete reinforcement underground structure construction method using a temporary auxiliary pillar, characterized in that to set the installation quantity and / or installation position so as not to. 제1항에 있어서, 각층의 구조물 슬래브에 그 가설보조기둥(5)의 주위로 기둥머리(6)를 보의 높이 이내로 설치하고, 그 기둥머리(6)와 결합되는 전단연결재(7)를 가설보조기둥(5)에 설치하여 하중을 원활히 전달하고 지지하는 것을 특징으로 하는, 가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물 축조 공법.2. The shear connecting material (7) according to claim 1, wherein the column head (6) is installed in the structural slab of each layer around the temporary supporting column (5) within the height of the beam, and is coupled with the column head (6). Reinforced concrete reinforcement underground structure construction method using a temporary auxiliary pillar, characterized in that installed on the auxiliary pillar (5) to smoothly transmit and support the load. 제1항에 있어서, 지지기둥(4)과 가설보조기둥(5)의 지반지지력을 얻기 위하여 H형강의 경우, 그 선단에는 전단연결재를 사전 설치한 후에 콘크리트를 타설하고, 강관의 경우, 그 선단에는 강관을 유공관화시키고, 천공시킨 후 슬라임을 제거하고 강관을 근입시킨 다음, 그라우팅을 실시하여, 외주면 마찰력에 의한 지지력과 선단지지력을 확보하고 콘크리트로서 내부를 충진시키는 것을 특징으로 하는, 가설보조기둥을 이용한 철근콘크리트 역타설 지하구조물 축조 공법.The method according to claim 1, wherein in order to obtain the ground bearing force of the supporting column (4) and the temporary supporting column (5), concrete is cast after the shear connector is pre-installed at the end of the H-shaped steel. Temporary auxiliary pillar, characterized in that the steel pipe is perforated, perforated to remove slime and infiltrate the steel pipe, and then grouting to secure the support force and tip support force by the outer circumferential surface friction and to fill the interior with concrete. Construction of Reinforced Concrete Underground Structures Using Reinforced Concrete Structures.
KR1020040038635A 2004-05-29 2004-05-29 downward reinforced-concrete underground structure using temporary assistant columns KR100625115B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020040038635A KR100625115B1 (en) 2004-05-29 2004-05-29 downward reinforced-concrete underground structure using temporary assistant columns

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020040038635A KR100625115B1 (en) 2004-05-29 2004-05-29 downward reinforced-concrete underground structure using temporary assistant columns

Publications (2)

Publication Number Publication Date
KR20050113450A true KR20050113450A (en) 2005-12-02
KR100625115B1 KR100625115B1 (en) 2006-09-20

Family

ID=37288063

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020040038635A KR100625115B1 (en) 2004-05-29 2004-05-29 downward reinforced-concrete underground structure using temporary assistant columns

Country Status (1)

Country Link
KR (1) KR100625115B1 (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100817685B1 (en) * 2006-05-30 2008-03-27 연세대학교 산학협력단 New RC Plate Slab - to - CFT Column Connection, and Top-down Method for Constructing Underground Floors of Building
KR100967497B1 (en) * 2010-02-19 2010-07-07 (주)바로건설기술 Method for constructing an underground structure
KR100967496B1 (en) * 2010-02-19 2010-07-07 (주)바로건설기술 Device for constructing an underground structure
CN114197533A (en) * 2021-12-29 2022-03-18 中建四局第一建设有限公司 Method for constructing vertical shaft of ultra-high-rise deep foundation pit along straight edge in reverse direction
CN114635580A (en) * 2022-03-09 2022-06-17 上海勘察设计研究院(集团)有限公司 Underground storey-adding underpinning structure utilizing existing building foundation structure and construction method thereof
CN115354739A (en) * 2022-08-05 2022-11-18 中冶集团武汉勘察研究院有限公司 Permanent and temporary combined basement structure and construction method thereof

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102383433A (en) * 2011-08-22 2012-03-21 同济大学建筑设计研究院(集团)有限公司 Design method for large deep foundation pit of super high-rise building
KR101356724B1 (en) * 2013-07-26 2014-02-03 김규철 Retaining walls and construction method thereof

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2772397B2 (en) * 1988-04-21 1998-07-02 清水建設株式会社 Underground building construction method
KR100273864B1 (en) * 1998-04-08 2000-12-15 유영록 An improved top-down method using the retaining wall

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100817685B1 (en) * 2006-05-30 2008-03-27 연세대학교 산학협력단 New RC Plate Slab - to - CFT Column Connection, and Top-down Method for Constructing Underground Floors of Building
KR100967497B1 (en) * 2010-02-19 2010-07-07 (주)바로건설기술 Method for constructing an underground structure
KR100967496B1 (en) * 2010-02-19 2010-07-07 (주)바로건설기술 Device for constructing an underground structure
CN114197533A (en) * 2021-12-29 2022-03-18 中建四局第一建设有限公司 Method for constructing vertical shaft of ultra-high-rise deep foundation pit along straight edge in reverse direction
CN114635580A (en) * 2022-03-09 2022-06-17 上海勘察设计研究院(集团)有限公司 Underground storey-adding underpinning structure utilizing existing building foundation structure and construction method thereof
CN115354739A (en) * 2022-08-05 2022-11-18 中冶集团武汉勘察研究院有限公司 Permanent and temporary combined basement structure and construction method thereof

Also Published As

Publication number Publication date
KR100625115B1 (en) 2006-09-20

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
KR102301605B1 (en) A Method of Bottom-up Removal of Underground Structures
KR20140055639A (en) A execution method of architecture beam
KR20190022132A (en) Top-down method using precast-concrete colum
KR101187170B1 (en) Application of under pinning method in remodeling
KR100625115B1 (en) downward reinforced-concrete underground structure using temporary assistant columns
KR102396786B1 (en) Underground expansion and top-down method of new building using reinforcement of existing underground outer wall
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
JP2000352296A (en) Method o constructing passage just under underground structure
KR20200029080A (en) Construction method for earth self-retaining wall using reinforcing member and PHC pile
KR20130021952A (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR100926323B1 (en) Constructing method for extension of underground
KR20130100878A (en) Architecture using a complex steel pile and a constructing method thereof
JP2020125630A (en) Building construction method
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof
KR20110043976A (en) Top-down method using precast column and building structure thereof
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
KR20100136900A (en) Reinforcing method for structure base
JP6534026B2 (en) Seismic isolation building and its construction method
KR100327547B1 (en) Composite retaining wall construction method
KR102583537B1 (en) Top-down construction method for uneven-slope site
KR102644085B1 (en) Steel outer casing molding jig coated with lining for drilling clearance
KR102571246B1 (en) Underground permanent wall using PC retaining pile and construction method thereof

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20120907

Year of fee payment: 7

FPAY Annual fee payment

Payment date: 20130829

Year of fee payment: 8

FPAY Annual fee payment

Payment date: 20140829

Year of fee payment: 9

FPAY Annual fee payment

Payment date: 20150828

Year of fee payment: 10

FPAY Annual fee payment

Payment date: 20170817

Year of fee payment: 12

FPAY Annual fee payment

Payment date: 20180906

Year of fee payment: 13

FPAY Annual fee payment

Payment date: 20190828

Year of fee payment: 14