KR100912574B1 - Retaining wall system using strut assembly and excavating method using the same - Google Patents
Retaining wall system using strut assembly and excavating method using the same Download PDFInfo
- Publication number
- KR100912574B1 KR100912574B1 KR1020080038519A KR20080038519A KR100912574B1 KR 100912574 B1 KR100912574 B1 KR 100912574B1 KR 1020080038519 A KR1020080038519 A KR 1020080038519A KR 20080038519 A KR20080038519 A KR 20080038519A KR 100912574 B1 KR100912574 B1 KR 100912574B1
- Authority
- KR
- South Korea
- Prior art keywords
- double
- braces
- brace
- bracket
- longitudinal
- Prior art date
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/20—Miscellaneous comprising details of connection between elements
Abstract
Description
본 발명은 흙막이 시스템에 관한 것으로, 보다 상세하게는 분해 조립이 용이하고 구조적인 측면뿐만 아니라 시공의 측면에서도 공기단축, 공사비 절감 등과 같은 합리화를 유도할 수 있는 흙막이 시스템 및 그를 이용한 터파기 방법에 관한 것이다.The present invention relates to an earthquake system, and more particularly, to an earthquake system that can easily disassemble and assemble, as well as structural aspects, such as an air shortening, construction cost reduction, etc. in terms of construction, and a method of digging using the same. will be.
흙막이 공사는 터파기 공사 중의 토압과 수압 등의 측압에 대해 저항하고 주변지반의 침하와 인접구조물의 보호를 목적으로 시공되는데 직접 흙에 접하는 흙막이 벽과 이를 지지하는 지보공으로 구성된다. 흙막이 벽으로는 엄지말뚝(H-말뚝)+토류판, C.I.P.(Cast-in Pile), S.C.W.(Soil Cement Wall) 및 지하연속벽이 많이 사용되고 있으며, 지보공은 그 지지구조에 따라 자립식, 버팀대(Strut), 그라운드 앵커, 역타지지구조(Top-down)로 분류할 수 있다.The earthquake construction is constructed for the purpose of resisting the side pressure such as earth pressure and water pressure during the digging work and for the purpose of settlement of the surrounding ground and the protection of adjacent structures. It consists of a wall of mud walls directly contacting the soil and supporting ground. Thumb wall (H-pile) + earth plate, CIP (Cast-in Pile), SCW (Soil Cement Wall), and underground continuous wall are used for the wall, and Jibo is a self-supporting, strut according to its supporting structure. ), Ground anchors, and top-down structures.
토압저항을 위한 버팀대 역할을 담당하는 스트러트 가시설은 지하구조체 시공시 철거되어야 하며 해체과정에서 흙막이 벽에 갑작스런 응력불균형 현상을 유발 하며 설치, 해체시 발생하는 위험성뿐 아니라 골조공사 기간단축 저해 및 이로 인한 원가절감 기회상실 등 여러 가지 측면에서 개선할 필요가 있다. 역타공법(Top-down 공법)은 구조물 본체의 슬래브 및 보를 시공하여 지보공으로 이용하면서 굴착을 진행해 가는 방법으로 흙막이 벽에 걸리는 토압과 수압 등의 측압을 슬래브 및 보가 직접 부담하는 공법으로 지하연속벽공법의 장점을 이용하여 영구적인 철근콘크리트 벽체를 시공하고 현장타설 말뚝으로 영구기둥 및 기초를 조성한 다음에 1층 슬래브를 시공하여 벽체를 지지하는 버팀역할을 하게 한 후 굴착을 한 다음에 지하 1층 슬래브를 시공하고 굴착하는 순서로 지상에서부터 지하로 내려가며 구조물을 시공하여 완성하는 것이다. 역타공법은 굴착 깊이가 깊고 구조물의 형태가 불규칙하고 굴착면적이 큰 경우 부지면적이 좁아서 작업공간이 요구되는 경우에 적합하다. 그러나 지하공사시의 작업환경이 열악하며 슬래브의 단면이 증대할 가능성이 높은 단점이 있다.The strut temporary facility, which serves as a support for earth pressure resistance, should be demolished when constructing underground structures, causing sudden stress imbalances on the wall of the earth during dismantling, as well as the risks that occur during installation and dismantling, as well as shortening the construction period and cost Improvements are needed in many ways, including the loss of savings opportunities. Top-down method is the method of constructing slab and beam of the main body of the structure and using excavation to proceed with excavation.The underground continuous wall method is a method in which the slab and beam directly bear the side pressure such as earth pressure and water pressure applied to the wall of the earth. Construct the permanent reinforced concrete wall by using the advantages of the building, construct the permanent column and foundation with the cast-in-placement pile, construct the ground floor slab to support the wall, and then excavate the ground floor slab. Construction is completed by going down from the ground to the basement in the order of construction and excavation. The reverse drilling method is suitable for the case where the working space is required due to the narrow ground area in case of deep excavation depth, irregular structure and large excavation area. However, there is a disadvantage that the working environment at the time of underground construction is poor and the cross section of the slab is likely to increase.
이러한 측면에서 재래의 흙막이 공법을 개선하여 구조적인 측면뿐만 아니라 시공의 측면에서도 공기단축, 공사비 절감 등과 같은 합리화를 유도할 수 있도록 여러 가지 공법이 개발되고 있으며 그 중 SPS 공법과 BRD 공법을 살펴보면 아래와 같다.In this respect, various construction methods have been developed to improve the conventional soil barrier construction method to induce rationalization such as reduction of construction cost and construction cost in terms of construction as well as structural aspects. Among them, the SPS and BRD methods are as follows. .
SPS(Strut as Permanent System) 공법은 지하 토공사 가설 버팀대 공법을 대체한 공법으로 지하 영구 구조물용 철골기둥과 보를 굴토공사 진행에 따라 선 시공하여 굴토공사 중 흙막이 지보공 버팀대로 사용하고 굴토공사 완료 후에는 본 구조물로 사용하는 공법이다. 이 공법의 경우 지하공사 시공 중의 영구 보 부재는 토압 에 의한 횡력에 저항해야만 하므로 경우에 따라서 H-형강 보 부재의 단면 크기를 증가시켜야 할 경우가 발생하며 이는 지하층 철골 부재의 물량을 증가시키는 원인이 되고 영구 보 부재만으로는 각 층부의 평면적인 강성 확보 및 변형 제어 효과가 충분하지 않아 별도의 수평 브레이싱 등의 가설부재가 추가되는 경우가 발생하여 이 또한 철골 물량 증가의 원인이 되는 단점이 있다. 또한 지상층 철골 보(버팀보) 설치 및 슬래브 콘크리트 타설이 끝난 후에 터파기가 진행되고 지하 1층 레벨이 나오면 실측을 해서 철골 보를 제작하므로 공기가 상당히 소요된다.The SPS (Strut as Permanent System) method is an alternative to the underground earthen construction support method. The steel pillars and beams for underground permanent structures are pre-installed according to the progress of the excavation work, and used as the earthwork supporters during the excavation work. It is a construction method used as a structure. In this method, the permanent beam member during underground construction must resist the lateral force due to earth pressure, so in some cases, it is necessary to increase the cross-sectional size of the H-shaped steel beam member. In addition, the permanent beam member alone is not enough to secure the planar stiffness and deformation control effect of each layer portion, additional temporary bracing members, such as horizontal bracing occurs, which also has the disadvantage that causes the increase in steel stocks. In addition, after the installation of the ground floor steel beams (brass beams) and slab concrete casting, the dig proceeds, and when the ground level of the first floor comes out, the steel beams are made by actual measurement.
BRD(Bracket R/C Downward) 공법은 와이드 거더 및 데크 슬래브를 사용하여 거푸집을 최소화시키고 브라켓 및 거더 거푸집 지지틀을 설치하여 동바리 없이 무지보 시공이 가능한 공법으로 콘크리트 양생 후 거푸집 지지틀을 현수 하강시켜 재사용함에 따라 시공성 및 경제성을 향상시킨 공법이다. 이 공법에서 거더 거푸집 지지 거더는 단순히 거더 거푸집을 지지하는 기능만 하는 것으로 토압은 와이드 거더가 지지하여야 하므로 와이드 거더 콘크리트가 양생되기 전까지는 터파기를 진행할 수 없어 공기가 지연되는 단점이 있다. BRD (Bracket R / C Downward) method minimizes formwork by using wide girder and deck slab and installs bracket and girder formwork support frame so that construction can be carried out without drift. It is a construction method that improves workability and economic efficiency by reusing. The girder formwork girder in this construction simply supports the girder formwork, and the earth pressure must be supported by the wide girder, so that the dig cannot proceed until the wide girder concrete is cured.
본 발명은 종래의 흙막이 공법을 개선하여 구조적인 측면뿐만 아니라 시공의 측면에서도 공기단축, 공사비 절감 등과 같은 합리화를 유도할 수 있는 흙막이 시스템 및 그를 이용한 터파기 방법을 제공하는데 그 목적이 있다.An object of the present invention is to provide an earthquake system that can induce rationalization such as air shortening, construction cost reduction, etc. in terms of construction as well as structural aspects by improving the conventional earthquake construction method, and an explosive method using the same.
본 발명의 적절한 실시형태에 따르면 흙막이 벽과, 흙막이 벽을 지지하기 위한 H형 버팀보들과, 흙막이 벽으로 구획된 터파기 부지에 설치되고 각 버팀보가 연결되는 H형 기둥들을 포함하는 흙막이 시스템에 있어서, 상기 H형 기둥들의 각 플랜지에는 브라켓이 고정되고, 상기 H형 버팀보들은, 상기 브라켓들에 의해 각각 지지되며 상기 기둥을 사이에 두고 서로 이격되어 설치되고 상기 브라켓 상에 이음부가 위치하는 더블 종방향 버팀보들과, 상기 더블 종방향 버팀보들과 각각 직교하도록 각 더블 종방향 버팀보의 외측에 접합되고 상기 기둥을 사이에 두고 서로 이격되어 설치되는 더블 횡방향 외측 보팀보들와, 상기 더블 횡방향 외측 보팀보들과 각각 동일선상에 위치하도록 상기 더블 종방향 버팀보 사이의 내측에 접합되는 더블 횡방향 내측 보팀보를 포함하고, 서로 이격되어 설치된 상기 더블 종방향 버팀보 및 더블 횡방향 외측 보팀보는 횡좌굴을 방지하기 각각 연결보로 연결된 것을 특징으로 하는 흙막이 시스템이 제공된다.According to a preferred embodiment of the present invention, in a retaining system comprising a retaining wall, an H-shaped support for supporting the retaining wall, and an H-shaped column installed at a trench site partitioned by the retaining wall and to which each support is connected. Brackets are fixed to the flanges of the H-shaped pillars, and the H-shaped braces are respectively supported by the brackets, and are spaced apart from each other with the pillars interposed therebetween, and a double longitudinal direction in which a joint is located on the bracket. And a double transverse outer reinforcement beam which is joined to the outside of each double longitudinal reinforcement so as to be orthogonal to the double longitudinal reinforcements, and spaced apart from each other with the pillar interposed therebetween, and the double transverse outer reinforcement beams. Double transverse medial splices joined to the inner side between the double longitudinal braces so that they are on the same line each To include, and is the double longitudinal and double beotimbo prevent lateral outer botim viewing lateral buckling are spaced apart from each other is installed provided with a retaining system, it characterized in that each connection is connected to the beam.
이때, 상기 더블 종방향 버팀보들과 상기 더블 횡방향 외측 버팀보들 및 상기 더블 횡방향 내측 버팀보들의 접합은, 상기 각 더블 종방향 버팀보의 플랜지 사 이에 'ㄷ'형강을 삽입하고 상기 'ㄷ'형강에 접하는 상기 각 더블 횡방향 외측 버팀보 및 상기 각 더블 횡방향 내측 버팀보의 단부에 단부판을 접합하며 상기 더블 종방향 버팀보와 더블 횡방향 외측 버팀보 및 더블 횡방향 내측 버팀보의 접합부 상면에 덮개판을 댄 후 이들을 서로 볼트 접합한 것을 특징으로 한다.At this time, the joining of the double longitudinal braces, the double transverse outer braces and the double lateral inner braces, insert the 'c' section between the flange of each of the double longitudinal bracing and the 'c' section steel Bond an end plate to the ends of each of the double transverse outer braces and the double transverse inner braces, and cover the upper surface of the joint of the double longitudinal braces and the double transverse outer braces and the double transverse inner braces. They are bolted together, It is characterized by the above-mentioned.
또한, 상기 기둥과 브라켓의 접합은, 상기 브라켓을 H형강으로 구성하고 상기 기둥의 플랜지에 접하는 단부에는 단부판을 접합하고 상기 단부판을 상기 기둥의 플랜지에 서로 볼트 접합한 것이고, 이때, 상기 브라켓이 접합되는 기둥의 플랜지 사이 및 상기 더블 종방향 버팀보가 얹혀지는 상기 브라켓의 플랜지 사이에는 스티프너가 접합된 것을 특징으로 한다.In addition, joining of the pillar and the bracket is made by joining an end plate to an end of the bracket formed of H-shaped steel and contacting the flange of the pillar and bolting the end plate to the flange of the pillar. A stiffener is connected between the flange of the pillar to be joined and the flange of the bracket on which the double longitudinal support is mounted.
또한, 상기 브라켓 상에 위치하는 더블 종방향 버팀보의 이음은, 서로 접합되는 상기 더블 종방향 버팀보의 단부에 각각 단부판을 접합하고 상면에 덮개판을 위치시킨 다음 이들을 서로 볼트 접합한 것을 특징으로 한다.In addition, the joint of the double longitudinal brace is located on the bracket, characterized in that the end plate is bonded to each end of the double longitudinal brace to be bonded to each other and the cover plate on the upper surface and then bolted to each other .
본 발명의 다른 적절한 실시형태에 따르면, 대지경계면에 흙막이 벽을 시공하는 제1단계와, 흙막이 벽으로 구획된 터파기 부지에 H형 기둥들을 관입하는 제2단계와, 지상층 슬래브를 구축하기 위한 굴토를 진행하고 노출된 흙막이 벽에 띠장을 대고 H형 기둥들의 각 플랜지에 브라켓을 설치하는 제3단계와, 각 기둥을 사이에 두고 브라켓에 의해 지지되도록 더블 종방향 버팀보들을 설치하고, 상기 더블 종방향 버팀보들과 직교하도록 각 기둥을 사이에 두고 서로 이격하여 상기 더블 종방향 버팀보들 사이에 더블 횡방향 외측 버팀보들을 설치하며, 각 더블 종방향 버팀보들 사이에 더블 횡방향 내측 버팀보를 설치하는 제4단계와, 지상층 슬래브를 시공하는 제5단계와, 지하층 슬래브를 구축하기 위한 굴토를 진행하고 상기 제3단계 및 제4단계를 진행한 후 지하층 슬래브를 시공하는 단계를 설계 지하층까지 반복하는 것을 특징으로 하는 터파기 방법이 제공된다.According to another suitable embodiment of the present invention, the first step of constructing the earth wall on the ground boundary, the second step of injecting the H-shaped columns into the trench site partitioned by the earth wall, and the excavation for constructing the ground layer slab The third step is to install a bracket on each flange of the H-shaped pillars to the exposed earth wall and to install a double longitudinal braces so that each pillar is supported by the bracket, the double longitudinal direction A fourth step of installing double lateral outer braces between the double longitudinal braces and spaced apart from each other with the columns intersected so as to be perpendicular to the braces, and installing a double lateral inner brace between each double longitudinal braces And the fifth step of constructing the ground floor slab, and the excavation for constructing the basement slab, and proceeding with the third and fourth steps. Dig the method comprising repeating the steps for construction of the basement slab to design the basement is provided.
본 발명에 따르면 버팀보가 바닥 슬래브 콘크리트 타설 하중을 지지하면서 토압을 지지하는 역할을 하므로 지상층 슬래브 콘크리트가 양생된 후에 버팀보가 하부로 내려가고 보팀보가 지하 1층 콘크리트 하중을 지지하면서 토압을 지지하도록 내려가면 터파기는 쉬지 않고 계속해서 빠르게 진행되므로 기존 버팀보 공법보다 훨씬 빠른 속도로 공사 진행이 가능하다.According to the present invention, since the reinforcement serves to support the earth pressure while supporting the floor slab concrete placing load, when the ground floor slab concrete is cured, the reinforcement descends to the bottom and the supporter descends to support the earth pressure while supporting the first-floor concrete load. The excavation is continuously carried out quickly and continuously, and thus the construction can be performed at a much faster speed than the existing support method.
또한, 본 발명의 경우 최외측 더블 종방향 버팀보 및 더블 횡방향 외측 버팀보, 즉 흙막이 벽과 접하는 최외측 더블 종방향 버팀보 및 더블 횡방향 외측 버팀보만 실측을 해서 제작하면 되므로 철골제작 시간이 단축되어 철골제작으로 인해 후속공정이 지연되는 문제를 최소화할 수 있다. In addition, in the present invention, since only the outermost double longitudinal brace and the double transverse outer brace, that is, the outermost double longitudinal brace and the double transverse outer brace in contact with the retaining wall, have to be measured and manufactured, the steel production time is shortened. The manufacturing process can minimize the problem of delaying the subsequent process.
이하 본 발명의 바람직한 실시 예를 첨부한 도면을 참조하여 상세히 설명한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.
도 1은 본 발명에 따른 흙막이 시스템을 전체적으로 간략히 도시한 평면도이고, 도 2는 도 1의 "A"부분의 확대도이다.FIG. 1 is a plan view briefly showing the earth screen system according to the present invention as a whole, and FIG. 2 is an enlarged view of portion “A” of FIG. 1.
도시된 바와 같이 본 발명에 따른 흙막이 시스템은 버팀보가 슬래브 콘크리트가 경화시까지 그 하중을 지지함과 동시에 토압을 지지하도록 함으로써 공사기간 단축시키고 시공성을 향상시킨 것으로 각 부재를 현장에 반입하여 현장에서는 볼트로만 조립 시공하는 공법이다. As shown in the figure, the retaining system according to the present invention shortens the construction period and improves workability by supporting the load until the slab concrete hardens the slab concrete, and at the same time, improves workability. It is a construction method of assembling Roman.
본 발명에 따른 흙막이 시스템은 흙막이 벽(10)과, 흙막이 벽(10)을 지지하기 위한 H형 버팀보(20)들과, 흙막이 벽(10)으로 구획된 터파기 부지에 설치되고 각 버팀보(20)가 연결되는 H형 기둥(30)들을 포함하는 흙막이 시스템에 있어서, 상기 H형 기둥(30)들의 각 플랜지에는 브라켓(40)이 고정된다.Soil system according to the present invention is installed on the digging site partitioned by the soil wall (10), the H-shaped braces (20) for supporting the soil wall (10), and the soil wall (10) and each braces (20) In the retaining system including the H-
브라켓(40)은 바람직하게는 H형 단면을 갖는 강재로 구성되고 분해 및 조립이 용이하도록 기둥(30)의 양측 플랜지(31)에 볼트 접합된다. The
그리고 H형 버팀보(20)들은 한 쌍으로 구성되는 즉, 2개가 1조로 구성되는 더블 종방향 버팀보(210a)(210b)들과, 이에 직교하도록 배치되며 각각 2개가 1조로 구성되는 더블 횡방향 외측 버팀보(220a)(220b)들과 더블 횡방향 내측 버팀보(230a)(230b)들로 구성된다.And the H-shaped braces 20 are composed of a pair, that is, two longitudinal longitudinal braces (210a) (210b) consisting of a pair of two, and are arranged to be orthogonal to this, each two two lateral outward consisting of a pair It consists of
이때, 더블 종방향 버팀보(210a)(210b)들은 상기 브라켓(30)들에 의해 각각 지지되며 상기 기둥(30)을 사이에 두고 서로 이격되어 설치되며 그 이음부는 상기 브라켓(30) 상에 위치하도록 이음되는 것이 바람직하다.In this case, the double
그리고 더블 횡방향 외측 버팀보(220a)(220b)들은 상기 더블 종방향 버팀보(210a)(210b)들과 각각 직교하도록 각 더블 종방향 버팀보(210a)(210b)의 외측에 접합되고 상기 기둥(30)을 사이에 두고 서로 이격되어 설치되며, 더블 횡방향 내측 보팀보(230a)(230b)들은 상기 더블 횡방향 외측 보팀보(220a)(220b)들과 각각 동일선상에 위치하도록 상기 더블 종방향 버팀보(210a)(210b) 사이의 내측에 접합된다.And double transverse outer braces (220a) (220b) are bonded to the outside of each double longitudinal braces (210a) (210b) to be orthogonal to the double longitudinal braces (210a) (210b), respectively, and the pillar (30) Spaced apart from each other, and the double transverse
한편, 서로 이격되어 설치된 상기 더블 종방향 버팀보(210a)(210b) 및 더블 횡방향 외측 보팀보(220a)(220b)는 횡좌굴을 방지하기 각각 연결보(240)로 연결된다. Meanwhile, the double
이상과 같이 구성되는 본 발명에 따른 흙막이 시스템을 적용하여 터파기를 할 경우 종래 버팀보 흙막이 공법에서 문제가 되었던 공기지연의 문제를 해결할 수 있다. 즉, 종래 버팀보 흙막이 공법의 경우 슬래브 콘크리트가 완전히 경화한 후 터파기를 진행하므로 공기가 지연이 된다. 그러나 본 발명의 경우 버팀보가 슬래브 콘크리트 타설 하중을 지지함과 동시에 토압을 지지하므로 지상층 슬래브 콘크리트가 양생된 후에 버팀보가 하부로 내려가고 버팀보가 지하 1층 콘크리트 하중을 지지하면서 토압을 지지하도록 내려가면 터파기는 계속해서 빠르게 진행되므로 종래 버팀대 흙막이 공법보다 훨씬 빠른 속도로 공사 진행이 가능하다. When the earthwork system according to the present invention constituted as described above is made to break, it is possible to solve the problem of air delay, which has been a problem in the conventional brace soil construction method. That is, in the case of the conventional reinforcement earth construction method, air is delayed because the slab concrete proceeds to dig after completely curing. However, in the case of the present invention, since the brace supports the slab concrete placing load and at the same time supports the earth pressure, after the ground layer slab concrete is cured, the brace is lowered and the brace is supported to support the earth pressure while supporting the ground concrete floor load. Since the machine continues to go fast, it is possible to proceed with construction much faster than the conventional prop retaining method.
또한, 종래 버팀보 흙막이 공법의 경우 지상층 철골설치 및 슬래브 타설이 끝난 후에 터파기가 진행되고 지하 1층 레벨이 나오면 실측을 해서 철골 제작을 하므로 공기가 지연이 되는데, 본 발명의 경우 최외측 더블 종방향 버팀보 및 더블 횡방향 외측 버팀보, 즉 흙막이 벽과 접하는 최외측 더블 종방향 버팀보 및 더블 횡방향 외측 버팀보만 실측을 해서 제작하면 되므로 철골제작 시간이 단축되어 철골제작으로 인해 후속공정이 지연되는 문제를 최소화할 수 있다.In addition, in the case of the conventional reinforcement earth retaining method, after the ground layer steel frame installation and slab casting is completed, the destruction proceeds, and when the ground level of the first floor comes out, the air is delayed because the steel frame is produced by actual measurement. And double transverse outer braces, that is, the outermost double longitudinal brace and the double lateral outer brace that are in contact with the wall of the earth just need to be manufactured and manufactured so that the steel manufacturing time is shortened and the subsequent process is delayed due to the steel production. Can be.
도 3은 본 발명에 따른 더블 종방향 버팀보들과 더블 횡방향 외측 버팀보들 및 더블 횡방향 내측 버팀보들의 접합부(도 2의 "B"부분)를 나타낸 평편도이다.Figure 3 is a plan view showing the junction ("B" portion of Figure 2) of the double longitudinal braces, the double transverse outer braces and the double transverse inner brace in accordance with the present invention.
도 3을 참조하면, 상기 더블 종방향 버팀보(210a)(210b)들과 상기 더블 횡방 향 외측 버팀보(220a)(220b)들 및 상기 더블 횡방향 내측 버팀보(230a)(230b)들의 접합은, 상기 각 더블 종방향 버팀보(210a)(210b)의 플랜지 사이에 'ㄷ'형강(250)을 삽입하고 상기 'ㄷ'형강(250)에 접하는 상기 각 더블 횡방향 외측 버팀보(220a)(220b) 및 상기 각 더블 횡방향 내측 버팀보(230a)(230b)의 단부에 단부판(260)을 접합한 다음 상기 더블 종방향 버팀보(210a)(210b)와 더블 횡방향 외측 버팀보(220a)(220b) 및 더블 횡방향 내측 버팀보(230a)(230b)의 접합부 상면에 덮개판(270)을 댄 후 이들을 서로 볼트 접합한다.Referring to FIG. 3, the joining of the double
도 4는 기둥과 브라켓의 접합부(도 2의 "C"부분)를 나타낸 단면도이다.4 is a cross-sectional view showing the joint portion ("C" portion of Figure 2) of the pillar and the bracket.
도 4를 참조하면, 상기 기둥(30)과 브라켓(40)의 접합은, 상기 브라켓(40)을 H형강으로 구성하고 상기 기둥(30)의 플랜지(31)에 접하는 단부에는 단부판(42)을 접합하고 단부판(42)을 기둥(30)의 플랜지(31)에 서로 볼트 접합한 것이고, 이때, 상기 브라켓(40)이 접합되는 기둥(30)의 플랜지(31) 사이 및 상기 더블 종방향 버팀보(210a)(210b)가 얹혀지는 상기 브라켓(40)의 플랜지(41) 사이에는 스티프너(280)가 접합된다.Referring to FIG. 4, the joint of the
도 5는 브라켓 상에 위치하는 더블 종방향 버팀보의 이음부(도 2의 "D"부분)를 나타낸 단면도이다. FIG. 5 is a cross-sectional view of a joint ("D" portion in FIG. 2) of a double longitudinal brace positioned on the bracket.
도 5를 참조하면, 상기 브라켓(40) 상에 위치하는 더블 종방향 버팀보(210a)(210b)의 이음은, 서로 접합되는 상기 더블 종방향 버팀보(210a)(210b)의 단부에 각각 단부판(211)을 접합하고 상면에 덮개판(212)을 위치시킨 다음 이들을 서로 볼트 접합한다.Referring to FIG. 5, the joints of the double
이상과 같이 접합 및 이음되는 본 발명에 따른 버팀보는 슬래브 콘크리트 타설 하중을 지지하면서 토압을 지지하게 되는데, 부재의 규격화가 가능하고 길이 조정으로 조립시간이 단축되며 용접 없이 볼트로 연결 조립하므로 시공 정밀성이 증대되고 작업성이 우수하다.The brace according to the present invention, which is joined and joined as described above, supports the earth pressure while supporting the slab concrete placing load, and the construction precision can be standardized and the assembly time is shortened by adjusting the length and connected by bolts without welding. It is increased and workability is excellent.
다음으로, 본 발명에 따른 흙막이 시스템을 이용하여 터파기 공사를 진행하는 방법을 도면을 참조하여 설명하기로 한다.Next, a method of proceeding the excavation construction using the earthquake system according to the present invention will be described with reference to the drawings.
도 6a 내지 도 6f는 본 발명에 따른 흙막이 시스템을 이용한 터파기 공사를 시공순서대로 개략적으로 도시한 것이다.6a to 6f schematically show the construction of the trench using a clogging system according to the present invention in the construction order.
먼저, 대지경계면에 흙막이 벽(10)을 시공한다(도 6a 참조). 흙막이 벽으로는 주열식 흙막이 벽체, 예컨데, 쏘일시멘트벽체(S.C.W.), 현장타설콘크리트 말뚝벽체(C.I.P.) 등이나 지하 연속벽으로 시공한다(제1단계).First, construct the earth wall (10) on the land boundary (see Figure 6a). As the wall of the wall, it is constructed with the main column wall, for example, the soil cement wall (S.C.W.), the cast-in-place concrete pile wall (C.I.P.), or the underground continuous wall (step 1).
다음으로 흙막이 벽(10)으로 구획된 터파기 부지에 H형 기둥(30)들을 관입한다(도 6b 참조). 이 기둥(30)은 흙막이를 지지하는 버팀보가 연결되는 부분일뿐만 아니라 지하공사 완료 후에는 상층부의 축력을 기초로 전단하는 건물 구조재인 기둥으로서의 역할을 하게 된다. 따라서 기둥 관입을 위한 천공 및 근입시 이동 또는 변형되지 않고 정확한 수직도를 확보할 수 있도록 한다(제2단계). Next, the H-
다음으로 지상층 슬래브를 구축하기 위한 굴토를 진행하고 노출된 흙막이 벽에 띠장(50)을 대고 H형 기둥(30)들의 각 플랜지에 브라켓(40)을 설치한다(도 6c 참조). 이때, 띠장 및 1층 바닥 철골 설치 후 굴토장비의 이동을 고려하여 터파기 레벨을 선정한 후 굴착을 한다. 그리고 브라켓은 H형 단면을 갖는 강재로 구성되며 기둥의 각 플랜지에 볼트 접합한다(제3단계).Next, proceed to the excavation to build a ground-layer slab, and the
다음으로 각 기둥(30)을 사이에 두고 브라켓(40)에 의해 지지되도록 더블 종방향 버팀보(210a)(210b)들을 설치하고, 상기 더블 종방향 버팀보(210a)(210b)들과 직교하도록 각 기둥(30)을 사이에 두고 서로 이격하여 상기 더블 종방향 버팀보(210a)(210b)들 사이에 더블 횡방향 외측 버팀보(220a)(220b)들 그리고 각 더블 종방향 버팀보(210a)(210b)들 사이에 더블 횡방향 내측 버팀보(230a)(230b)를 설치한다(도 6d 참조). 이때, 더블 종방향 버팀보(210a)(210b)들의 이음부는 브라켓(40) 상에 위치하도록 한다. 한편, 최외측 더블 종방향 버팀보들 및 더블 횡방향 외측 버팀보들의 단부에는 스크류 잭(미도시)을 연결하여 띠장과 밀착되도록 설치한다(제4단계).Next, double
다음으로 상기 버팀보(210a,210b)(220a,220b)(230a,230b)들의 상부에 합성 데크(미도시)를 설치하고 철근을 배근한 후 콘크리트를 타설하여 지상층 슬래브(60)를 시공한다(제5단계)(도 6e 참조).Next, a synthetic deck (not shown) is installed on top of the support beams 210a and 210b (220a and 220b) and 230a and 230b, and after reinforcing reinforcing bars, the concrete is poured to construct the ground layer slab 60 (see FIG. Step 5) (see FIG. 6E).
마지막으로 지상층 슬래브가 경화한 후 지하층 슬래브를 구축하기 위한 굴토를 진행하고 상기 제3단계 및 제4단계를 진행한 후 지하층 슬래브를 시공하는 단계를 설계 지하층까지 반복한다(도 6f 참조).Finally, after the ground layer slab is hardened, the process of constructing the basement slab is carried out, and after the third and fourth steps, the construction of the basement slab is repeated to the design basement layer (see FIG. 6F).
이와 같이 본 발명에서는 더블 종방향 버팀보들과, 더블 횡방향 외측 버팀보들 및 더블 횡방향 내측 버팀보들이 격자형으로 배치되어 슬래브 콘크리트 타설 하중을 지지함과 동시에 토압을 지지하므로 지상층 슬래브 콘크리트가 양생된 후에 버팀보가 하부로 내려가고 버팀보가 지하 1층 콘크리트 하중을 지지하면서 토압을 지지하도록 내려가면 터파기는 계속해서 빠르게 진행되므로 종래 버팀대 흙막이 공법보다 훨씬 빠른 속도로 공사 진행이 가능하다. As described above, in the present invention, the double longitudinal braces, the double transverse braces and the double lateral inner braces are arranged in a grid to support the slab concrete placing load and simultaneously support the earth pressure, so that after the ground layer slab concrete is cured, When the brace is lowered and the brace is lowered to support the earth pressure while supporting the concrete load on the ground floor, it is possible to proceed with the construction at a much faster speed than the conventional brace trowel method because the trench continues continuously.
위에서 본 발명은 실시 예를 이용하여 상세하게 설명이 되었다. 제시된 실시 예는 예시적인 것으로 이 분야에서 통상의 지식을 가진 자는 본 발명의 기술적 사상을 벗어나지 않는 제시된 실시 예에 대한 다양한 변형 및 수정 발명을 만들 수 있을 것이다. 본 발명의 범위는 이러한 변형 및 수정 발명에 의하여 제한되지 않고 다만 아래에 첨부된 청구범위에 의해서만 제한된다.The present invention has been described above in detail by using an embodiment. The presented embodiments are exemplary and can be made by those skilled in the art to various modifications and modifications to the disclosed embodiments without departing from the spirit of the present invention. The scope of the invention is not limited by these modifications and variations, but only by the claims appended below.
도 1은 본 발명에 따른 흙막이 시스템을 간략히 도시한 평면도이다. 1 is a plan view briefly showing an earth screen system according to the present invention.
도 2는 도 1의 "A"부분의 확대도이다.FIG. 2 is an enlarged view of portion “A” of FIG. 1.
도 3은 본 발명에 따른 더블 종방향 버팀보들과 더블 횡방향 외측 버팀보들 및 더블 횡방향 내측 버팀보들의 접합부(도 2의 "B"부분)를 나타낸 평편도이다.Figure 3 is a plan view showing the junction ("B" portion of Figure 2) of the double longitudinal braces, the double transverse outer braces and the double transverse inner brace in accordance with the present invention.
도 4는 기둥과 브라켓의 접합부(도 2의 "C"부분)를 나타낸 단면도이다.4 is a cross-sectional view showing the joint portion ("C" portion of Figure 2) of the pillar and the bracket.
도 5는 브라켓 상에 위치하는 더블 종방향 버팀보의 이음부(도 2의 "D"부분)를 나타낸 단면도이다.FIG. 5 is a cross-sectional view of a joint ("D" portion in FIG. 2) of a double longitudinal brace positioned on the bracket.
도 6a 내지 도 6f는 본 발명에 따른 흙막이 시스템을 이용한 터파기 공사를 시공순서대로 개략적으로 도시한 것이다.6a to 6f schematically show the construction of the trench using a clogging system according to the present invention in the construction order.
< 도면의 주요부분에 대한 부호의 설명 ><Description of Symbols for Major Parts of Drawings>
10 : 흙막이 벽10: retaining wall
20 : 버팀보20: brace
30 : 기둥30: pillar
40 : 브라켓40: bracket
210a, 210b : 더블 종방향 버팀보210a, 210b: Double longitudinal brace
220a, 220b : 더블 횡방향 외측 버팀보220a, 220b: Double transverse outer brace
230a, 230b : 더블 횡방향 내측 버팀보230a, 230b: Double transverse inner brace
Claims (5)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080038519A KR100912574B1 (en) | 2008-04-25 | 2008-04-25 | Retaining wall system using strut assembly and excavating method using the same |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
KR1020080038519A KR100912574B1 (en) | 2008-04-25 | 2008-04-25 | Retaining wall system using strut assembly and excavating method using the same |
Publications (1)
Publication Number | Publication Date |
---|---|
KR100912574B1 true KR100912574B1 (en) | 2009-08-19 |
Family
ID=41209889
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
KR1020080038519A KR100912574B1 (en) | 2008-04-25 | 2008-04-25 | Retaining wall system using strut assembly and excavating method using the same |
Country Status (1)
Country | Link |
---|---|
KR (1) | KR100912574B1 (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059880A (en) * | 2017-03-09 | 2017-08-18 | 中国建筑第八工程局有限公司 | The ruggedized construction and its construction method of the concrete assembled shaped steel mixing support system of super-sized foundation pit |
CN107964958A (en) * | 2017-11-27 | 2018-04-27 | 中铁二局集团有限公司 | A kind of deep foundation pit precast overlaps pile construction method |
KR20190116624A (en) * | 2018-04-05 | 2019-10-15 | (주)대우건설 | Support structure of temporary strut for construction period reduction |
KR102611456B1 (en) | 2022-07-08 | 2023-12-07 | 디엘이앤씨 주식회사 | Top-down method of horizontal part for remodeling construction |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100313720B1 (en) | 1999-01-13 | 2001-11-15 | 김징완 | Composite Underground Structure Construction Method |
JP2005273181A (en) | 2004-03-23 | 2005-10-06 | Shimizu Corp | Structure of building |
KR200398758Y1 (en) | 2005-07-12 | 2005-10-18 | 황문삼 | Wale having reinforcement structure for preventing from buckling and falling down |
KR100776373B1 (en) | 2004-10-13 | 2007-11-16 | 코오롱건설주식회사 | Soil retaining method using two rows pile |
-
2008
- 2008-04-25 KR KR1020080038519A patent/KR100912574B1/en active IP Right Grant
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100313720B1 (en) | 1999-01-13 | 2001-11-15 | 김징완 | Composite Underground Structure Construction Method |
JP2005273181A (en) | 2004-03-23 | 2005-10-06 | Shimizu Corp | Structure of building |
KR100776373B1 (en) | 2004-10-13 | 2007-11-16 | 코오롱건설주식회사 | Soil retaining method using two rows pile |
KR200398758Y1 (en) | 2005-07-12 | 2005-10-18 | 황문삼 | Wale having reinforcement structure for preventing from buckling and falling down |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107059880A (en) * | 2017-03-09 | 2017-08-18 | 中国建筑第八工程局有限公司 | The ruggedized construction and its construction method of the concrete assembled shaped steel mixing support system of super-sized foundation pit |
CN107059880B (en) * | 2017-03-09 | 2020-08-04 | 中国建筑第八工程局有限公司 | Reinforcing structure of concrete-fabricated section steel mixed support system of ultra-large deep foundation pit and construction method thereof |
CN107964958A (en) * | 2017-11-27 | 2018-04-27 | 中铁二局集团有限公司 | A kind of deep foundation pit precast overlaps pile construction method |
KR20190116624A (en) * | 2018-04-05 | 2019-10-15 | (주)대우건설 | Support structure of temporary strut for construction period reduction |
KR102108622B1 (en) * | 2018-04-05 | 2020-05-07 | (주)대우건설 | Support structure of temporary strut for construction period reduction |
KR102611456B1 (en) | 2022-07-08 | 2023-12-07 | 디엘이앤씨 주식회사 | Top-down method of horizontal part for remodeling construction |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
KR101014796B1 (en) | Top-down underground construction method using prefabricated concrete column member as temporary bridge column | |
KR101687495B1 (en) | Partial top-down construction method for building underground structures | |
KR20060092552A (en) | The non-strut down framework construction method of having used cast in place concrete pile | |
KR100982827B1 (en) | Construction method of basement exterior wall applying the floor slab as the strut against the earth pressure from the temporary earth wall = TSW(Thrusting slabbed wall) method | |
JP5619646B2 (en) | Construction method of underground structure and underground structure | |
KR20150029512A (en) | The horizontal structural frame and the underground construction methods using it | |
JP5579635B2 (en) | Underground structure and construction method of underground structure | |
KR102286225B1 (en) | Method for constructing underground structure busing PC integrating method without support | |
KR100912574B1 (en) | Retaining wall system using strut assembly and excavating method using the same | |
KR20190022132A (en) | Top-down method using precast-concrete colum | |
KR101401057B1 (en) | Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed | |
KR20090090742A (en) | Bottom-up construction method of underground structure using permanent strut | |
KR101296857B1 (en) | Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same | |
KR20070052109A (en) | Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor | |
KR100673475B1 (en) | A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof | |
JP5619647B2 (en) | Underground structure and construction method of underground structure | |
KR20110052360A (en) | Downward construction method of underground structure that enables continuous basement wall using non-wale and diaphragm action of concrete slab | |
KR20020007521A (en) | method for underground construction of building by using permanent structural member as strut for support retaining wall | |
JP5764245B2 (en) | Construction method of underground structure and underground structure | |
JP5875651B2 (en) | Underground structure and construction method of underground structure | |
KR20210098162A (en) | Under ground structure using column steel pipe wall and construction method thereof | |
KR102571246B1 (en) | Underground permanent wall using PC retaining pile and construction method thereof | |
KR101028695B1 (en) | A method of PC-girder jointing for top down-construction | |
KR102523155B1 (en) | Connecting structure of middle girder and construction method thereof | |
KR20120032368A (en) | Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
A201 | Request for examination | ||
A302 | Request for accelerated examination | ||
N231 | Notification of change of applicant | ||
E701 | Decision to grant or registration of patent right | ||
GRNT | Written decision to grant | ||
FPAY | Annual fee payment |
Payment date: 20120809 Year of fee payment: 4 |
|
FPAY | Annual fee payment |
Payment date: 20130808 Year of fee payment: 5 |
|
FPAY | Annual fee payment |
Payment date: 20140806 Year of fee payment: 6 |
|
FPAY | Annual fee payment |
Payment date: 20150728 Year of fee payment: 7 |
|
FPAY | Annual fee payment |
Payment date: 20160527 Year of fee payment: 8 |
|
FPAY | Annual fee payment |
Payment date: 20170612 Year of fee payment: 9 |
|
FPAY | Annual fee payment |
Payment date: 20180417 Year of fee payment: 10 |
|
FPAY | Annual fee payment |
Payment date: 20190429 Year of fee payment: 11 |