KR101401057B1 - Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed - Google Patents

Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed Download PDF

Info

Publication number
KR101401057B1
KR101401057B1 KR1020130021684A KR20130021684A KR101401057B1 KR 101401057 B1 KR101401057 B1 KR 101401057B1 KR 1020130021684 A KR1020130021684 A KR 1020130021684A KR 20130021684 A KR20130021684 A KR 20130021684A KR 101401057 B1 KR101401057 B1 KR 101401057B1
Authority
KR
South Korea
Prior art keywords
steel
slab
frame
column
ground
Prior art date
Application number
KR1020130021684A
Other languages
Korean (ko)
Inventor
김광만
Original Assignee
(주)바로건설기술
롯데건설 주식회사
주식회사 삼우종합건축사사무소
두산중공업 주식회사
두산건설 주식회사
주식회사 한화건설
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)바로건설기술, 롯데건설 주식회사, 주식회사 삼우종합건축사사무소, 두산중공업 주식회사, 두산건설 주식회사, 주식회사 한화건설 filed Critical (주)바로건설기술
Priority to KR1020130021684A priority Critical patent/KR101401057B1/en
Application granted granted Critical
Publication of KR101401057B1 publication Critical patent/KR101401057B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/02Structures consisting primarily of load-supporting, block-shaped, or slab-shaped elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04CSTRUCTURAL ELEMENTS; BUILDING MATERIALS
    • E04C3/00Structural elongated elements designed for load-supporting
    • E04C3/02Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/388Separate connecting elements
    • E04B2001/389Brackets

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to an underground structure construction method using a structure comprising columns, capitals, steel beams, and a slab, wherein the underground structure construction method is as follows: brackets are installed by measuring the accurate positions of temporary steel columns appearing after excavating the ground in which the temporary steel columns are buried at regular intervals to construct an underground structure; two of the steel beams, which are separated from each other at the regular interval at positions in which structural columns are to be positioned, are directly mounted on the brackets; and 雅�shaped connection beams are formed at the positions, in which the structural columns are to be positioned, by perpendicularly assembling another steel frame to the steel frames above. According to the present invention, the underground structure construction method for installing the steel frame of a horizontal structure as above makes installing the steel frame easy and reduces working hours for installing the steel frame so that economic feasibility can be improved.

Description

기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법{Method to build underground structures using the pillars and the stigma and Steel Beam and slab structures are formed}BACKGROUND OF THE INVENTION 1. Field of the Invention The present invention relates to a method of constructing an underground structure using pillars,

본 발명은 지하 구조물 구축공법에 관한 것으로, 보다 상세하게는, 지하 구조물을 구축하도록 지중에 일정간격으로 매설된 가설 철골기둥에 브라켓를 설치한 후, 철골보를 안착시키면서 향후 구조물기둥이 위치할 부분에 '井'자형의 연결보를 격자형으로 형성하는 철골 지하 구조물의 설치가 간편하여 작업시간의 단축으로 경제성을 확보할 수 있는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법에 관한 것이다.
The present invention relates to a method of constructing an underground structure, and more particularly, to a method of constructing an underground structure, in which a bracket is installed in a hypothetical steel column embedded at a predetermined interval in the ground to construct an underground structure, The present invention relates to a method for constructing an underground structure using a structure formed by a column, a column, a steel frame, and a slab, which can be easily installed by installing a steel underground structure having a lattice shape, .

일반적으로 주요 지하 구조물 축조하는 공법은, 굴토계획선을 따라 흙막이벽을 설치하고 가설형강지지체로서 토압이나 수압 등의 외력을 지탱하면서 지상에서 지하의 기초바닥까지 굴토 완료한 다음 각 층 구조물을 바닥에서 상부로 순차적으로 축조하면서 가설형강지지체를 해체하여 시공하는 개착식 공법이 있다.Generally, in the construction method of the main underground structure, the earth retaining wall is installed along the excavation planning line and the excavation is completed from the ground to the foundation floor of the underground while supporting the external force such as earth pressure and water pressure as the support of the hypothetical steel, There is an open type method in which the temporary support is dismantled and constructed by sequentially constructing the upper part.

상기 개착식 공법에는 적용에 한계가 있는 바, 이는 첫째 지하 구조물의 규모가 크고 굴토심도가 깊은 대형 현장에서는 흙막이벽에 작용하는 토압과 수압 등의 외력을 지탱하여 주어야 하나 가설형강지지체로는 변형이 크다는 취약한 문제점이 있으며, 둘째, 건축물이 밀집된 도심지에서는 이로 인해 흙막이벽의 큰 변형을 유발하고 지반침하로 인하여 주변 건축물에 위해가 발생될 수 있는 문제점이 있으며, 셋째, 외부에 노출된 상태에서 굴토작업과 구조물 공사를 수행함에 따라 소음과 진동 및 분진에 의한 환경 및 민원 발생의 문제점이 있으며, 넷째, 가설형강지지체 공사가 완료된 후에 순차적으로 영구구조물 공사를 수행해야 하는 관계로 공사기간이 늘어나는 문제점이 있었다.In the above-mentioned method, there is a limitation in application. First, it is necessary to support external force such as earth pressure and water pressure acting on the earth retaining wall in a large site where the underground structure is large and the depth of the excavation is deep, Second, there is a problem that in urban areas with dense buildings, it causes large deformation of the retaining wall and may cause damage to surrounding buildings due to subsidence of the ground. Third, There is a problem of environmental and civil complaints caused by noise, vibration and dust as a result of performing the construction of the structure. Fourth, since the construction of the permanent structure should be sequentially performed after completion of the construction of the support frame, .

이러한 개착식 공법의 문제점을 해결하기 위해 흙막이벽을 설치하고 현장 타설말뚝으로서 철골기둥과 이에 연장된 말뚝기초를 형성하여 지하 구조물을 축조하는 탑다운(TOP DOWN) 공법이 사용되고 있다.In order to solve the problems of the open type method, TOP DOWN method is used in which an earth retaining wall is installed and a steel pillar and an extended pile foundation are formed as a cast pile to construct an underground structure.

상기 탑다운 공법은 철근콘크리트 탑다운 공법과 철골조 탑다운 공법이 있는데, 상기 철근콘크리트 탑다운 공법은 철근콘크리트 구조를 형성하기 위해 거푸집과 동바리를 설치하거나 큰 가설철골보를 설치하여야 한다. 이는 철근콘크리트조이기 때문에 경제적인 장점이 있지만, 가설재를 설치하고 해체하여야 하는 공기적인 또는 시공적인 단점이 있다.The tower-down method includes a reinforced concrete tower-down method and a steel tower-down method. The reinforced concrete tower-down method requires a formwork and a steel bridge or a large steel bridge to form a reinforced concrete structure. This is economically advantageous because of the reinforcing concrete tightening, but there is a disadvantage in that the installation and dismantling of the installation material is an air or construction work.

상기 철골조 탑다운 공법은, 철골위에 철근트러스데크 또는 철선트러스데크를 깔고 콘크리트를 타설하기 때문에 공기가 빠르고 시공이 간편한 장점이 있으나, 철골조이기 때문에 공사비가 상승하는 비경제적인 단점이 있다.The above-mentioned steel tower top down method has advantages of quick air and easy construction because a reinforcing truss deck or a wire truss deck is laid on a steel frame and concrete is laid. However, there is an uneconomical disadvantage that a construction cost rises due to a steel frame.

또한, 상기 철근콘크리트 탑다운 공법과 철골조 탑다운 공법의 장점만을 취한 공법이 이중보(DOUBLE BEAM)로 형성된 철골조 탑다운 공법으로, 이는 이중보가 형성되면서 기둥 주위에 주두가 형성되고 주두의 효과로 철골보의 순경간이 줄어드는 효과가 생겨 작은 철골부재로 큰 효과를 실현할 수 있는 구조가 된다.In addition, a method of taking down only the merits of the above-mentioned reinforced concrete tower down method and steel tower down method is a steel tower down method in which a double beam is formed. This is because a double beam is formed and a circumference is formed around the column, So that a large effect can be realized with a small steel member.

상기 이중 철골보 탑다운 공법으로 본 건 출원인은 대한민국 등록특허 제10-0749855호(이하 '선행 특허 1'이라 함.)로 건축물의 수평 뼈대구조를 등록받은 바 있고, 대한민국 등록특허 제10-0967497호(이하 '선행 특허 2'라 함.)로 지하 구조물 구축공법을 등록받은 바 있고, 대한민국 공개특허 제10-2012-033683호(이하 '선행 특허 3'이라 함.)로 지하 구조물 구축장치 및 공법이 공개된 바 있는데, 이는 모두 기둥과 주두, 철골보, 슬래브로 구성된 이중보과 관련이 있으며, 주두의 영향으로 철골보의 순경간이 줄어드는 구조이다.The applicant of the present invention has registered the horizontal skeleton structure of the building with the Korean Patent No. 10-0749855 (hereinafter referred to as "Prior Patent 1"), and Korean Patent No. 10-0967497 (Hereinafter referred to as "Prior Patent 2"), and Korean Patent Laid-Open No. 10-2012-033683 (hereinafter referred to as "Prior Patent 3") was used to construct an underground structure, This is related to a double beam consisting of columns, columns, steel beams, and slabs, and the diameter of the steel beams is reduced due to the influence of the columns.

또한, 선행 특허 1은, 수평구조부재를 가설 철골기둥에 거치하여 기초 윗층까지 형성하였다가 수평구조부재와 그 하부의 수평구조부재 사이를 수직보강부재를 사용하여 연결하여 지탱한 후, 가설 철골기둥을 제거하고, 기둥을 형성하는 구성이고, 선행 특허 2는, 수평구조부재를 가설 철골기둥에 거치하면서 매 층마다 층간기둥을 설치하였다가 기초가 형성되면 층간기둥에서 하중을 지탱한 후, 가설 철골기둥을 제거하고 기둥을 형성하는 방법이며, 선행 특허 3은, 1층에서 형성된 수평구조물에 하부층 수평구조물을 연결재로 매어달아 높이를 조정하여 설치한 후, 브라켓에 지지하는 공법이다.In addition, in the prior patent 1, a horizontal structural member is mounted on a hypothetical steel column to form a foundation upstairs. Then, a horizontal structural member and a horizontal structural member below the horizontal structural member are connected and supported by using a vertical reinforcing member, In the prior art 2, a horizontal structure member is placed on a hypothetical steel column, and an interstory column is provided for each layer. When a foundation is formed, the load is supported by the interstice column, In the method of forming a column by removing a column, the prior art patent 3 is a method of attaching a lower level horizontal structure to a horizontal structure formed on a first floor by connecting the floor structure by adjusting the height, and then supporting the bracket.

그러나 선행 특허 1과 2는, 수직보강재를 위에서 아래로 연결한 후, 가설 철골기둥을 제거하는 방법으로 철골기둥이 필요하거나 철근콘크리트 기둥이 역타로 타설되어야 하므로 시공이 어려울 뿐만 아니라 공기가 늘어나 비경제적인 문제점이 있었고, 선행 특허 3은, 하부층의 수평구조물을 그 위층에서 메달이 두었다가 레벨 조정이 끝나고 설치가 마무리되면 브라켓에 연결하는 방법으로 달대를 설치하여 수평구조물을 메어다는 일정과 브라켓의 설치 일정이 중복되어 작업공정이 복잡해지는 번거로운 문제점이 있으며, 또한, 선행 특허의 3가지 방법에서 흙막이 구조로부터 전달되는 토압을 수평구조물이 받아야 하는 탑다운공사의 필수적인 힘의 흐름에서 수평구조물의 역할이 불분명하였다.
However, in the prior patents 1 and 2, since a vertical steel stiffener is connected from the top to the bottom and the steel column is removed, a steel column is required or a reinforced concrete column is to be installed in a reverse stator. In the prior patent 3, the horizontal structure of the lower layer is placed in the upper layer, and after the level adjustment is completed, when the installation is completed, the connection is made to the bracket, and the calendar for mounting the horizontal structure and the bracket installation schedule There is a problem that the work process becomes complicated and the role of the horizontal structure is unclear in the flow of the force necessary for the top down construction in which the horizontal structure receives the earth pressure transmitted from the retaining structure in the three methods of the prior patent.

이에 상술한 바와 같은 종래의 제반 문제점을 감안하여 이루어진 것으로, 본 발명의 목적은, 지하 구조물을 구축하도록 일정간격으로 가설 철골기둥이 매설된 지중을 터파기하여 나타난 가설 철골기둥의 정확한 위치를 측량하여 브라켓를 설치한 후, 향후, 구조물기둥이 위치할 부위에서 일정간격으로 이격된 평행한 두 철골보를 상기 브라켓에 직접안착시키고, 이와 직각으로 또 다른 철골보를 조립하면 구조물기둥이 위치할 부분에 '井'자 형태의 연결보가 형성되며, 이의 방법으로 수평구조물의 철골 프레임을 설치하는 작업이 간편함은 물론 작업시간의 단축으로 경제성을 향상시킬 수 있는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법을 제공함에 있다.SUMMARY OF THE INVENTION The present invention has been made in view of the above-mentioned problems, and it is an object of the present invention to provide a method and apparatus for measuring an exact position of a hypothetical steel column, which is formed by inserting a hypothetical steel column at predetermined intervals to construct an underground structure, In the future, when two parallel steel beams spaced apart from each other at a position where a structural column is to be placed are directly placed on the bracket and another steel beam is assembled at right angles to the bracket, a '井' And it is possible to construct an underground structure using a structure formed by a column, a pillar, a steel frame, and a slab, which can improve the economical efficiency by shortening the working time as well as the work of installing the steel frame of the horizontal structure To provide a method.

또한, 본 발명의 다른 목적은, 수평구조물의 철골 프레임과 흙막이벽이 만나는 부분에 철골 띠장보를 설치하여 흙막이 구조로부터 전달되는 토압을 수평구조물의 철골 프레임이 받을 수 있도록 상세를 구비하므로서 안전한 탑다운 공사를 수행하게 하고, 기초에서부터 지상층까지 구조물기둥과 지하외벽을 아래에서부터 위로 타설하여 구조적으로 틈이 없이 안정감있게 형성할 수 있는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법을 제공함에 있다.It is another object of the present invention to provide a detailed structure of a steel structure frame to receive the earth pressure transmitted from the earth retaining structure by installing a steel strip fastener at a portion where the steel frame of the horizontal structure meets the earth retaining wall, Construction of an underground structure using pillar, pillar, steel frame and slab, which can be constructed with stability and without structural gap by piling structure pillars and underground outer wall from bottom to ground layer from bottom to top. .

또한, 본 발명의 또 다른 목적은, 구조물기둥에 주두를 형성하여 철골보의 순경간이 줄어듦으로 구조적 안전성을 높일 수 있는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법을 제공함에 있다.
Another object of the present invention is to provide a method of constructing an underground structure using a structure formed by a column, a column, a steel frame, and a slab capable of increasing the structural safety by reducing the diameter of a steel beam by forming a circumference at a column of the structure .

본 발명 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법은,The present invention relates to a method of constructing an underground structure using a pillar, a pillar, a steel frame, and a slab,

철근콘크리트 기둥과 주두 그리고 상기 주두의 끝면에 배치되는 철골보, 철골보 위에 설치되는 슬래브로 구성되는 지하 구조물에 있어서 지하공사 중에는 가설 철골기둥 및 상기 가설 철골기둥에 고정된 브라켓으로 수직하중을 지지하고, 토압은 수평구조물의 철골 프레임과 슬래브로 버티면서 지하로 공사를 진행하는 공사방법에 있어서,In the underground construction comprising a reinforced concrete pillar and a pillar, a steel beam disposed on the end surface of the pillar, and a slab installed on the steel beam, a vertical load is supported by a bracket fixed to the pillar of the steel column and the pillar of the steel column, In a construction method of constructing a building underground while holding it with a steel frame and a slab of a horizontal structure,

상기 지하 구조물을 설치하고자 하는 지중에 흙막이벽을 형성하는 제1단계와;A first step of forming an earth retaining wall in the ground where the underground structure is to be installed;

상기 지하 구조물을 받쳐 지지하는 구조물기둥의 설치 위치가 아닌 지중에 일정간격으로 가설 철골기둥을 설치하는 제2단계와;A second step of installing a hypothetical steel column at a predetermined interval in the ground instead of the installation position of the column supporting the underground structure;

상기 가설 철골기둥이 설치된 지중을 굴토하는 제3단계와;A third step of excavating the ground in which the hypothetical steel column is installed;

상기 지중이 굴토되어 나타난 가설 철골기둥에 트러스 형태의 브라켓을 설치하는 제4단계와;A fourth step of installing a truss type bracket on the hypothetical steel column where the ground is excavated;

상기 브라켓 상면에 철골보를 안착 및 서로 연결하여 향후 구조물기둥이 위치할 부분에 '井'자 형태의 연결보를 형성하면서 상기 '井'자 형태의 연결보가 격자형으로 배열되도록 수평구조물의 철골 프레임을 형성하는 제5단계와;A steel frame frame is formed on the upper surface of the bracket so as to form a connection beam in the shape of a '井' ;

상기 '井'자 형태의 연결보의 폐쇄된 부분의 저면 플랜지에 드롭 데크플레이트를 설치하고, 상기 '井'자 형태의 연결보의 폐쇄된 부분 이외의 철골보 상면 플랜지에 슬래브 데크플레이트를 설치하는 제6단계와;A drop deck plate is installed on the bottom flange of the closed portion of the connection beam in the form of a "boss", and a slab deck plate is installed on the upper surface flange of the steel beam other than the closed portion of the " Step 6;

상기 드롭 데크플레이트에는 콘크리트를 타설하지 않고, 상기 슬래브 데크플레이트에 콘크리트를 타설 및 양생하여 지상슬래브를 형성하는 제7단계와;A seventh step of forming a ground slab by placing and curing concrete on the slab deck plate without pouring concrete into the drop deck plate;

상기 지상슬래브 하부의 지중을 굴토하는 제8단계와;An eighth step of excavating the ground below the ground slab;

상기 지중을 굴토하여 나타난 가설 철골기둥에 트러스 형태의 브라켓을 설치하는 제4단계 내지 제7단계를 반복한 후, 지하 구조물의 기초 하단까지 굴토하는 제9단계와;Repeating the fourth to seventh steps of installing a truss-type bracket on the hypothetical steel column that has been excavated from the ground, and then advancing to the bottom of the underground structure;

상기 지하 구조물의 기초에 철근을 배근한 후, 콘크리트를 타설 및 양생하여 기초슬래브를 형성하는 제10단계와;A tenth step of placing a reinforcing bar on the foundation of the underground structure, and then placing and curing the concrete to form a foundation slab;

상기 기초슬래브 상면에서 지상슬래브까지 구조물기둥 및 주두를 형성하는 제11단계와;An eleventh step of forming a column and a column of the structure from the upper surface of the foundation slab to the ground slab;

상기 각 슬래브 사이에 구조물기둥이 형성되면, 각 층의 가설 철골기둥에 설치된 브라켓을 제거한 후, 가설 철골기둥을 제거하는 제12단계와;A twelfth step of removing the brackets provided on the columns of the steel columns of each layer and removing the columns of the steel columns when the columns of the structure are formed between the slabs;

상기 가설 철골기둥이 제거되어 각 슬래브에 형성된 홀을 콘크리트로 메우기하는 제13단계를 포함하여 이루어지는 것을 특징으로 하는 것이다.And a thirteenth step of removing the pillar columns and filling holes formed in the slabs with concrete.

또한, 상기 흙막이벽은, 가설 또는 영구구조물인 것을 특징으로 하는 것이다.Further, the earth retaining wall is a permanent structure or a permanent structure.

또한, 상기 제5단계에서, 상기 수평구조물의 철골 프레임 철골보 단부에 형성된 안착홈에 철골띠장보를 안착 및 고정한 후, 철골띠장보와 흙막이벽을 토압전달부재로 일정간격 이격되게 고정시켜 흙막이벽으로부터 전달되는 토압이 수평구조물의 철골 프레임과 슬래브로 분산되어 전달되도록 하는 것을 특징으로 하는 것이다.In addition, in the fifth step, after the steel strips are fixed and fixed to the seating grooves formed at the ends of the steel frame steel frame of the horizontal structure, the steel strip strips and the earth retaining walls are fixed to the earth pressure- And the earth pressure to be delivered is dispersed and transmitted to the steel frame and the slab of the horizontal structure.

상기 안착홈은, 상기 철골띠장보가 철골보 상면으로 슬래브 두께의 1/2 이상 내지 슬래브 두께 이내로 돌출되도록 형성되는 것을 특징으로 하는 것이다.The seating groove is formed such that the steel strip can be protruded from the upper surface of the steel frame to at least 1/2 of the thickness of the slab or within the thickness of the slab.

또한, 상기 흙막이벽이 영구구조물일 경우, 상기 철골 프레임의 철골보는 흙막이벽에 맞닿지 않도록 배치하며 테두리보 하부 거푸집을 받쳐주기 위해 삼각 까치발을 고정하고 그 위에 철근배근을 하며, 철근배근과 철골보가 부딪히는 부분에는 철골보를 따내어 안착홈을 형성하는 것을 특징으로 하는 것이다.When the earth retaining wall is a permanent structure, the steel frame of the steel frame is disposed so as not to touch the earth retaining wall, and the triangular bracket is fixed to support the frame under the frame and the reinforcing steel is laid thereon. And the steel bridge is pulled out to form a seating groove.

또한, 상기 제5단계에서, 1층 부분에서 흙막이벽과 수평구조물의 철골 프레임이 연결되는 부위는 철골띠장보 대신에 철근콘크리트 테두리보를 설치하여 상기 흙막이벽의 상부와 철골보의 최외곽을 일체화하는 것을 특징으로 하는 것이다.
In addition, in the fifth step, in the first floor portion, a portion where the earth retaining wall and the steel frame of the horizontal structure are connected may be formed by installing a reinforcing concrete frame beam instead of the steel frame brace to integrate the upper portion of the earth retaining wall and the outermost portion of the steel frame It is characterized by.

본 발명에 의하면, 지하 구조물을 구축하도록 일정간격으로 가설 철골기둥이 매설된 지중을 터파기하여 나타난 가설 철골기둥의 정확한 위치를 측량하여 브라켓를 설치한 후, 향후, 구조물기둥이 위치할 부위에서 일정간격으로 이격된 평행한 두 철골보를 상기 브라켓에 직접안착시키고, 이와 직각으로 또 다른 철골보를 조립하면 구조물기둥이 위치할 부분에 '井'자 형태의 연결보가 형성되며, 이의 방법으로 수평구조물의 철골 프레임을 설치하는 작업이 간편함은 물론 작업시간의 단축으로 경제성을 향상시킬 수 있는 이점을 가질 수 있는 것이다.According to the present invention, after the bracket is installed by measuring the exact position of the hypothetical steel column that is formed by trenching the ground where the hypothetical steel column is embedded at regular intervals to construct the underground structure, When two spaced parallel steel rods are directly seated on the brackets and another steel rods are assembled at right angles to each other, a '' 'shaped connecting beam is formed at a position where the column is to be positioned. It is possible to have an advantage that the installation work is simple, and the economical efficiency can be improved by shortening the working time.

또한, 본 발명에 의하면, 수평구조물의 철골 프레임과 흙막이벽이 만나는 부분에 철골 띠장보를 설치하여 흙막이 구조로부터 전달되는 토압을 수평구조물의 철골 프레임이 받을 수 있도록 상세를 구비하므로서 안전한 탑다운 공사를 수행하게 하고, 기초에서부터 지상층까지 구조물기둥과 지하외벽을 아래에서부터 위로 타설하여 구조적으로 틈이 없이 안정감있게 형성할 수 있는 이점을 가질 수 있는 것이다.In addition, according to the present invention, since the steel frame belt of the horizontal structure meets the steel frame and the earth retaining wall, the steel frame frame of the horizontal structure can receive the earth pressure transmitted from the retaining structure, And the structure pillars and the underground outer wall can be pushed up from the foundation to the ground floor from above to form a stable structure without any gap.

또한, 본 발명에 의하면, 구조물기둥에 주두를 형성하여 철골보의 순경간이 줄어듦으로 구조적 안전성을 높일 수 있을 뿐만 아니라 '井'자 형태의 연결보를 현장에서 조립하여 형성할 수 있으므로 굳이 공장에서 제작하여 반입하는 운반의 어려움을 해소할 수 있어 작업공정이 단축되므로 작업시간의 단축으로 경제성을 향상시킬 수 있는 이점을 가질 수 있는 것이다.
In addition, according to the present invention, not only the structural safety can be improved by reducing the diameter of the steel frame by forming the circumference at the column of the structure, but also the umbrella-shaped connecting beam can be assembled in the field, It is possible to solve the difficulty of transportation and shorten the work process, so that it is possible to shorten the working time and to improve the economical efficiency.

도 1은 본 발명 흐름도
도 2 내지 도 25은 본 발명의 시공과정도
1 is a flow chart
2 to 25 show the construction process of the present invention

이하, 첨부된 도면에 의거하여 본 발명의 실시예를 상세히 설명한다. 도 1은 본 발명 흐름도이다.Hereinafter, embodiments of the present invention will be described in detail with reference to the accompanying drawings. 1 is a flow chart of the present invention.

먼저, 본 발명은, 도 2 내지 도 5에 도시된 바와 같이, 지하 구조물(100)을 설치하고자 하는 지중에 흙막이벽(110)을 형성하는데, 상기 흙막이벽(110)은 H-beam+토류판, CIP(Cast in-Place Pile), SCW(Soil Cement Wall), 지하연속벽(Slurry Wall) 등과 같이 주열식으로 시공된다.2 to 5, the earth retaining wall 110 is formed in the ground where the underground structure 100 is to be installed. The earth retaining wall 110 is formed of an H-beam + Cast in-place pile, SCW (Soil Cement Wall), and underground continuous wall (Slurry Wall).

상기 흙막이벽(110)은 가설 흙막이벽일 수도 있고, 지하연속벽처럼 영구구조물일 수도 있다. 상기 흙막이벽(110)의 시공이 완료되면, 지하 구조물(100)을 받쳐 지지하는 구조물기둥(200)의 설치 위치가 아닌 지중에 일정간격으로 가설 철골기둥(120)을 설치하는데, 상기 가설 철골기둥(120)의 위치는 구조물기둥(200)의 사이가 바람직하고, 경우에 따라서는 구조물기둥(200) 간격보다 더 좁게 또는 더 넓게 배치되면서 그 깊이는 구조물의 기초 하부로부터 3m~6m까지 형성한다. 만약 기반암의 깊이가 그보다 더 밑에 있는 경우라면 기반암까지 연장되어야 한다. 또한, 하부에는 콘크리트로 채워져 상부의 하중을 선단지지 및 콘크리트와 암반간의 마찰력으로 지지하게 된다.The earth retaining wall 110 may be a permanent earth retaining wall or a permanent structure such as an underground continuous wall. When the installation of the earth retaining wall 110 is completed, the steel column columns 120 are installed at predetermined intervals in the ground instead of the installation positions of the column 200 supporting the underground structure 100, The position of the structural columns 120 is preferably between the columns 200 of the structure and is sometimes narrower or wider than the spacing of the columns 200 of the structure and its depth is formed to 3 m to 6 m from the bottom of the foundation of the structure. If bedrock depth is lower than that, it should extend to bedrock. In addition, the lower part is filled with concrete, and the upper load is supported by the tip support and the friction between the concrete and the rock.

상기 가설 철골기둥(120)이 설치된 지중을 일정깊이 굴토하는데, 일반적으로 하부에서 브라켓(130)의 연결작업을 인력으로 가능한 깊이 정도로 굴토하고, 상기 지중을 굴토하여 나타난 가설 철골기둥(120)의 상단부에 트러스 형태의 브라켓(130)을 설치한다. 이때 브라켓의 설치 위치는 정확한 측량에 의해 이루어진다. 이 전의 방법은 개략 설치 후, 오차가 생기는 부분에 대해서는 철골보(141)와 브라켓(130) 사이에 고임재를 넣어 높이를 조정하였으나, 측량 방법으로 레이져 빔 등과 같은 장비를 이용하면 건물 전체의 높이가 같이 측정될 수 있게 된다. 브라켓(130)이 정확히 설치된다면 철골보(141)를 고임재 없이 브라켓(130)에 직접 얹을 수 있다는 의미이다. 브라켓(130)과 가설 철골기둥(120)과의 연결은 가설 철골기둥(120)에 볼트구멍을 정확한 측량 위치에 뚫고 브라켓(130)의 옆면을 맞대어 볼트에 의해 체결한다. Generally, the connecting operation of the bracket 130 is excavated to a depth as much as possible by the gravity of the lower part of the foundation, and the upper end of the hypothetical steel column 120, A truss-type bracket 130 is provided. At this time, the mounting position of the bracket is made by accurate measurement. In the previous method, the elevation was adjusted by placing a high-precision member between the steel bracket 141 and the bracket 130 for the portion where the error occurred. However, when the equipment such as a laser beam is used as a measurement method, And can be measured together. If the bracket 130 is correctly installed, it means that the steel bracket 141 can be placed directly on the bracket 130 without any high-level presence. The connection between the bracket 130 and the temporary steel column 120 is made by inserting a bolt hole in the temporary steel column 120 at an accurate measuring position and fixing the side surface of the bracket 130 by bolts.

여기서, 상기 구조물기둥(200)이 향후 설치되는 위치의 철골보(141)는 '井'자로 연결하여 '井'자 형태의 연결보(142)를 형성할 수 있으며, 상기 '井'자의 연결보(142)가 격자형으로 배열되도록 수평구조물의 철골 프레임(140)을 형성한다. '井'자 형태의 연결보(142)를 형성하는 이유는 향후 구조물기둥(200)이 설치되었을 때 '井'자 형태가 자연스럽게 구조물기둥(200)의 주두(190)를 형성하게 된다. 이 주두(190)로 인하여 주두(190)와 주두(190)가 연결된 철골보(141)의 경간이 짧아져 작은 철골부재로 사용될 수 있다. 이는 경제적이고 시공성이 좋아진다는 의미이다. 이런 '井'자가 기둥에만 배치되는 것은 아니다. 경우에 따라서는 수직하중을 많이 받는 코어벽체에도 형성될 수 있고, 지하외벽(210) 주위에도 형성될 수 있다. 또한, 기둥이 4m 이내로 인접한 경우라면 두 개의 기둥을 포함하는 긴 '井'자 형태의 연결보가 될 수 있다.Here, the steel beam 141 at a position where the structure column 200 is installed in the future may be connected with a "well" to form a connection beam 142 in the form of a " 142 are arranged in a lattice shape. The reason why the connection beam 142 in the form of a 'well' is formed is that when the structure column 200 is installed in the future, the 'well' shape naturally forms the top 190 of the column 200. The spindle 190 shortens the span of the steel beam 141 to which the spindle 190 and the spindle 190 are connected and can be used as a small steel frame member. This means that it is economical and improves workability. This "井" is not only placed on the column. In some cases, it may be formed on the core wall which receives a large amount of vertical load, and may also be formed around the underground outer wall 210. In addition, if the column is adjacent within 4 m, it can be a long '井' shaped connecting beam including two columns.

이때, 이렇게 형성된 수평구조물의 철골 프레임(140)과 이후, 콘크리트 타설에 의해 형성되는 슬래브(180)는 흙막이벽(110)으로부터 전달되는 토압을 받게 되는데, 토압을 적절히 수평구조물의 철골 프레임(140)과 슬래브(180)로 분산하기 위하여 철골띠장보(150)의 역할이 필요하다. 이전의 기술은 철근콘크리트 테두리보를 형성하여 철골 프레임(140)에 타설되는 슬래브 콘크리트와 함께 타설되면 토압의 전달이 이루어졌다. 그러나 이 경우 향후 본 구조인 지하외벽(210)을 형성할 때, 기 타설된 테두리보 위에서 구멍을 통해 콘크리트가 타설되어 지하외벽(210)이 형성되므로 테두리보와 지하외벽(210) 사이에 분리 현상이 발생하는 등 공사에 많은 불편을 주고 누수가 되는 하자를 유발하였다. 본 발명에서는 토압의 전달도 유효하게 하고 지하외벽(210)도 분리되지 않도록 발명된 것이다.At this time, the steel frame 140 of the horizontal structure thus formed and the slab 180 formed by pouring concrete receive the earth pressure transmitted from the earth retaining wall 110. The earth pressure is suitably applied to the steel frame 140 of the horizontal structure, And the slabs 180, the steel strips 150 need to play a role. The former technique forms a reinforced concrete frame beam, and when the concrete frame is installed together with the slab concrete placed in the steel frame 140, the earth pressure is transmitted. However, in this case, when forming the basement outer wall 210 in the present structure, since the concrete is poured through the hole on the pavement beam pavement to form the basement outer wall 210, separation phenomenon occurs between the pavement beam and the basement outer wall 210 Which caused many inconveniences such as the occurrence of the leak, and caused the defect to leak. In the present invention, the transmission of the earth pressure is also effective and the underground outer wall 210 is not separated.

상기 수평구조물의 철골 프레임(140)과 흙막이벽(110)의 연결방법으로는, 도 6에 도시된 바와 같이, 상기 수평구조물의 철골 프레임(140)의 철골보(141) 단부에 형성된 안착홈(141')에 수직으로 통공(151)이 관통된 철골띠장보(150)를 안착시켜 용접 및 볼팅으로 고정한 후, 상기 철골띠장보(150)와 흙막이벽(110)을 토압전달부재(160)로 일정간격 이격되게 고정시켜 흙막이벽(110)으로부터 전달되는 토압이 일정간격 이격된 다수의 토압전달부재(160)로 전달되도록 한다.As shown in FIG. 6, the connecting structure between the steel frame 140 and the earth retaining wall 110 of the horizontal structure includes a seating groove 141 formed at an end of the steel frame 141 of the steel frame 140 of the horizontal structure, And the earth retaining wall 110 and the earth retaining wall 110 are fixed to the earth pressure transmitting member 160 by a predetermined distance after the steel strip supporting member 150 having passed through the through hole 151 is fixed by welding and bolting, So that the earth pressure transmitted from the earth retaining wall 110 is transmitted to a plurality of earth pressure transmitting members 160 spaced apart by a predetermined distance.

상기 철골띠장보(150)가 안착되는 안착홈(141')은, 상기 철골띠장보(150)가 철골보(141) 상면으로 지상슬래브(180) 두께의 1/2 이상 내지 지상슬래브(180) 두께 이내로 돌출되도록 형성되며, 상기 철골띠장보(150)가 지상슬래브(180) 두께의 1/2 이하로 돌출될 경우는 지상슬래브(180)로 전달되는 토압의 분산이 작아지고, 지상슬래브(180) 두께보다 크게 돌출될 경우는 지상슬래브(180)에 배근된 철근이 지하외벽(210)으로 정착되기 어렵기 때문이다.The seating groove 141 'in which the steel strip supporting member 150 is seated is formed such that the steel strip supporting member 150 is supported on the upper surface of the steel beam 141 by a thickness of not less than 1/2 of the thickness of the grounding slab 180, And when the steel strip 150 protrudes less than 1/2 of the thickness of the ground slab 180, the dispersion of the earth pressure transmitted to the ground slab 180 becomes small, The reinforcing bars laid on the ground slab 180 are hardly fixed to the underground outer wall 210. In this case,

상기 수평구조물의 철골 프레임(140)과 흙막이벽(110)의 다른 연결방법으로는, 도 7에 도시된 바와 같이, 상기 수평구조물의 철골 프레임(140)의 철골보(141) 단부에 철근콘크리트 테두리보를 형성하는 방법으로 상기 철골보(141)는 흙막이벽(110)에 맞닿지 않도록 배치하며, 테두리보 하부 거푸집을 받쳐주기 위해 삼각 까치발(110')을 고정하고, 그 위에 철근배근을 한다. 철근배근과 철골보(141)가 부딪히는 부분에는 철골보(141)를 따네어 안착홈(141')을 형성한다. 여기에는 향후 흙막이벽(110)과 일체가 되어야 하기 때문에 연결철근(R)을 수직으로 배치하여야 하고 콘크리트 타설을 위해 콘크리트 타설용 가설 파이프(P)를 설치하여야 한다.7, the steel frame 140 of the horizontal structure and the earth retaining wall 110 may be connected to each other by a reinforcing concrete frame beam at the end of the steel frame 141 of the steel frame 140 of the horizontal structure The steel wire rods 141 are disposed so as not to touch the earth retaining wall 110 and the triangular bracket 110 'is fixed to support the rim lower beam form and the reinforcing steel rods are placed thereon. A seating groove 141 'is formed at a portion where the reinforcing steel foot and the steel frame 141 are collided with the steel frame 141. Here, the connection reinforcing bar (R) should be arranged vertically in order to be integral with the earth retaining wall 110 in the future, and a hypothetical pipe P for pouring concrete should be installed for concrete pouring.

상기 철골띠장보(150)는 1층에서는 도 8에 도시된 바와 같이, 철근콘크리트 캡빔(Cap Beam)과 일체가 된 테두리보로 대체할 수 있다. 1층에서는 흙막이벽(110)을 일체화하여 흙막이벽(110)의 변위를 일체로 거동할 수 있도록 해야하는 필요가 있기 때문이다. 따라서 1층의 경우 흙막이벽(110)의 두께와 본 구조의 지하외벽(210)과 두께가 합쳐진 두께로 철근콘크리트 테두리보가 철골보(141)를 포함한 상태로 형성되고 흙막이벽(110)과 '井'자 형태의 연결보(142)가 일체로 거동하도록 한다.As shown in FIG. 8, the steel strip supporting member 150 can be replaced with a frame beam integrated with a reinforced concrete cap beam. This is because it is necessary to integrate the earth retaining walls 110 in the first floor so that the displacement of the earth retaining walls 110 can be unified. Therefore, in the case of the first layer, the reinforced concrete frame beam is formed in a state including the steel frame beam 141 in a thickness that the thickness of the earth retaining wall 110 and the thickness of the underground outer wall 210 of the present structure are combined and the reinforcing concrete wall frame 110 and the ' Shaped connecting beam 142 to move integrally.

여기서 상기 흙막이벽(110)이 지하연속벽 등과 같이 영구구조물일 경우는, 상기 철골띠장보(150)가 필요 없을 뿐만 아니라 콘크리트 타설용 가설 파이프(P) 및 연결철근(R)이 없는 철근콘크리트 테두리보를 설치한다.When the earth retaining wall 110 is a permanent structure such as an underground continuous wall or the like, the steel strip supporting member 150 is not required and the reinforced concrete rim without the reinforced concrete pipe P and the connecting reinforcing bar R Install the beam.

또한, 도 9 내지 도 11에 도시된 바와 같이, 상기 '井'자 형태의 연결보(142)의 폐쇄된 부분의 저면 플랜지에 드롭 데크플레이트(170)를 설치하고, 상기 '井'자 형태의 연결보(142)의 폐쇄된 부분 이외의 철골보(141) 상면 플랜지에 슬래브 데크플레이트(170')를 설치하는데, 상기 데크플레이트(170)(170')는, 양단에 지지가 되면 타설되는 콘크리트 하중과 타설 시 작업하중을 동바리 없이 견딜 수 있는 철근트러스 데크플레이트 또는 철선트러스 데크플레이트 중 어느 하나인 것이 바람직하고, 상기 '井'자 형태의 연결보(142)의 폐쇄된 부분의 저면 플랜지에 설치된 드롭 데크플레이트(170)는 향후 주두(190)가 형성되는 부위이며, 그 이외의 수평구조물의 철골 프레임(140) 상면에 형성되는 슬래브 데크플레이트(170')에는 콘크리트가 타설되어 철골띠장보(150)로부터 전달되는 토압을 저항하게 된다. 이때 주두(190)와 슬래브 부분의 경계는 수평구조물의 철골 프레임 상부에서 이루어지며, 두 부재 사이에는 메탈라스 등의 시공이음 재료에 의해 분리된다.9 to 11, a drop deck plate 170 is installed on the bottom flange of the closed portion of the 'umbrella-shaped connecting beam 142', and the 'deck' shaped The deck plates 170 and 170 'are installed on the upper surface flange of the steel beam 141 other than the closed portion of the connecting beam 142. The deck plates 170 and 170' Is preferably one of a reinforcing truss deck plate or a wire truss deck plate capable of withstanding the working load at the time of pouring and a drop installed on the bottom flange of the closed part of the ' Concrete is placed on the slab deck plate 170 'formed on the upper surface of the steel frame 140 of the horizontal structures other than the deck plate 170 to form the vertical bar 190, From It is to resist the earth pressure. At this time, the boundary between the top 190 and the slab portion is formed on the upper part of the steel frame of the horizontal structure, and separated between the two members by a construction joining material such as a metal lath.

상기 철골 프레임(140)에 데크플레이트(170)(170')가 설치되면, 상기 '井'자 형태의 연결보(142) 이외의 수평구조물의 철골 프레임(140) 상면에 설치된 슬래브 데크플레이트(170')에 콘크리트를 타설 및 양생하여 지상슬래브(180)를 형성한다. 여기서 드롭 데크플레이트(170)에는 콘크리트를 타설하지 않는 것이 일반적이다. 향후 철근콘크리트 기둥이 형성될 때 같이 형성되어 일체화 되어야 하는 부분이기 때문이다. 그러나 지상 1층의 경우에는 차량이 운행해야 하는 경우도 발생할 수도 있고, 토압을 받는데 역할을 해야 하는 부분이 될 수도 있으므로 경우에 따라서는 부분적으로 기둥철근을 매립한 상태에서 드롭 데크플레이트(170) 부분에 콘크리트를 타설할 수도 있다.When the deck plates 170 and 170 'are installed on the steel frame 140, the slab deck plates 170 installed on the upper surface of the steel frame 140 of the horizontal structure other than the' ') To form a ground slab 180. [0041] Here, it is general that concrete is not laid on the drop deck plate 170. This is because the reinforced concrete columns should be formed and integrated when they are formed. However, in the case of the first ground floor, the vehicle may have to be operated or may have a role of receiving the earth pressure. Accordingly, in some cases, the column deck plate may be partially buried, It is possible to pour concrete into the concrete.

상기 콘크리트가 타설된 층에서의 콘크리트 양생이 끝나면 도 12 내지 도 16에 도시된 바와 같이, 상기 지상슬래브(180) 하부의 지중을 굴토한다.When the concrete is cured in the concrete poured layer, the ground below the ground slab 180 is squeezed as shown in FIGS.

상기 지상슬래브(180) 하부의 지중을 굴토하여 나타난 가설 철골기둥(120)에 그 하부 층의 수평구조물의 철골 프레임(140)이 설치될 위치에 트러스 형태의 브라켓(130)을 설치하는 과정부터 브라켓(130) 상면에 철골보(141)를 안착 및 연결하여 '井'자 형태의 연결보(142)가 격자형으로 배열되도록 수평구조물의 철골 프레임(140)을 형성하는 과정과, 상기 수평구조물의 철골 프레임(140) 철골보(141) 단부에 형성된 안착홈(141')에 철골띠장보(150)를 안착 및 고정시키고, 상기 철골띠장보(150)와 흙막이벽(110)을 토압전달부재(160)로 일정간격 이격되게 고정하는 과정과, 상기 '井'자 형태의 연결보(142)의 폐쇄된 부분의 저면 플랜지와 상기 '井'자 형태의 연결보(142)의 폐쇄된 부분 이외의 철골보(141)의 상면 플랜지에 드롭 데크플레이트(170)와 슬래브 데크플레이트(170')를 각각 설치한 후, 상기 슬래브 데크플레이트(170')에 콘크리트를 타설 및 양생하여 슬래브(180a)를 형성하는 과정 및 상기 슬래브(180a) 하부의 지중을 굴토하는 과정을 반복하면서 도 17에 도시된 바와 같이, 지하 구조물(100)의 기초 하단까지 굴토한다.A process of installing a truss-type bracket 130 at a position where a steel frame 140 of a horizontal structure of a lower layer is to be installed on a hypothetical steel column 120 formed by digging the ground below the ground slab 180, A step of forming a steel frame frame 140 of a horizontal structure so that the connection beams 142 in the form of a 'ight' are arranged in a lattice form by seating and connecting the steel frame beams 141 on the upper surface of the frame 130, The frame member 140 is mounted and fixed to the mounting groove 141 'formed at the end of the frame 140 and the frame member 150 and the earth retaining wall 110 are connected to the earth pressure transmitting member 160, And a step of fixing the bottom flange of the closed portion of the 'umbrella-shaped connecting beam 142 and the closed portion of the' umbrella-shaped connecting beam 142, The drop deck plate 170 and the slab deck plate 170 ' 17A and 17B, the process of forming the slab 180a by placing and curing concrete on the slab deck plate 170 'and the process of excavating the bottom of the slab 180a are repeated, Likewise, the bottom of the foundation of the underground structure 100 is excavated.

상기 지하 구조물(100)의 기초에 철근을 배근한 후, 콘크리트를 타설 및 양생하여 기초슬래브(180b)를 형성한 후, 도 18 내지 도 20에 도시된 바와 같이, 철근 콘크리트 기둥이 설치되는데 한개층 씩 형성한다. 우선 기둥의 위치인 '井'자 형태의 연결보(142) 중앙부에 기둥 철근을 배근하고, 거푸집은 '井'자 형태의 연결보(142)의 저면까지 설치하고, 콘크리트를 타설 및 양생하는데, 이때 기 설치된 드롭 데크플레이트(170)는 기둥의 크기만큼 절단하여 구조물기둥(200)과 주두(190)가 일체콘크리트가 될 수 있도록 한다.After a reinforcing bar is laid on the foundation of the underground structure 100, concrete is laid and cured to form a foundation slab 180b. Then, as shown in FIGS. 18 to 20, a reinforced concrete column is installed, Respectively. First, a pillar reinforcement is disposed at a central portion of a connection beam 142, which is a position of a pillar, and a pillar is installed up to the bottom of a connection beam 142 having a pillar shape, At this time, the installed drop deck plate 170 is cut by the size of the pillar so that the pillar 200 and the pillar 190 can be integrally concrete.

상기 콘크리트에 의해 기초슬래브(180b)와 기초슬래브(180b) 상부의 '井'자 형태의 연결보(142)까지 철근콘크리트 기둥 및 '井'자 형태의 연결보(142) 내부에 주두(190)가 형성되고 기 타설된 기초슬래브(180b)와 연결되는 구조물기둥(200)을 형성한다.A concrete column 190 is formed inside the reinforcing concrete column and the connection beam 142 of '井' shape from the concrete slab 180b to the connection beam 142 of '井' shape on the base slab 180b, And the foundation pillars 200 connected to the foundation slabs 180b are formed.

이때, 상기 기초슬래브(180b)와 기초슬래브(180b) 상부의 슬래브(180a) 사이의 흙막이벽(110) 내측으로 토압전달부재(160) 및 철골띠장보(150)를 수용하도록 거푸집을 설치한 후, 상기 거푸집에 콘크리트를 타설 및 양생하여 지하외벽(210)을 형성한다. 여기서 지하외벽(210)은 구조물기둥(200)과 같이 시공할 수도 있고 시점을 달리하여 시공할 수도 있다.At this time, a mold is installed to house the earth pressure transmitting member 160 and the steel band strip joist 150 inside the earth retaining wall 110 between the foundation slab 180b and the slab 180a above the foundation slab 180b And concrete is placed and cured in the mold to form an underground outer wall 210. Here, the underground outer wall 210 may be constructed as a structure column 200 or may be constructed at different times.

또한, 상기 구조물기둥(200)과 동일선상으로 기초슬래브(180b) 상부의 슬래브(180a)와 슬래브(180a) 상부의 윗층 슬래브까지 거푸집과 철근을 '井'자 형태의 연결보(142)의 중앙에 위치하도록 설치하고, 상기 기초슬래브(180b)와 기초슬래브(180b) 상부의 '井'자 형태의 연결보(142)까지 설치된 거푸집을 해체시킨 상태에서 상기 슬래브(180a)와 슬래브(180a) 상부의 윗층 슬래브까지 설치된 '井'자 형태의 연결보(142)와 거푸집에 콘크리트를 타설 및 양생하여 주두(190) 및 구조물기둥(200)을 형성하는 과정을 지상슬래브(180)까지 반복한다.The slabs 180a on the foundation slabs 180b and the upper slabs on the upper slabs 180a are arranged in line with the structural columns 200 to form the formwork and the reinforcing bars in the center of the ' And the upper part of the slab 180a and the upper part of the slab 180a are separated from each other in a state where the foundation slab 180b and the ' And the upper and lower slabs of the upper and lower slabs 180 and 180. The process of forming the tops 190 and the pillars 200 is repeated until the ground slab 180 is poured and cured.

이때, 상기 기초슬래브(180b) 상부의 슬래브(180a)와 슬래브(180a) 상부의 윗층 슬래브 사이의 흙막이벽(110) 내측으로 토압전달부재(160) 및 철골띠장보(150)를 수용하도록 거푸집을 설치한 후, 상기 거푸집에 콘크리트를 타설 및 양생하여 지하외벽(210)을 형성하는 과정을 지상슬래브(180)까지 반복한다.At this time, the dies are housed in the earth retaining wall 110 between the slabs 180a on the foundation slabs 180b and the upper slabs on the slabs 180a to receive the earth pressure transfer member 160 and the steel strip support members 150 After the installation, the process of forming the underground outer wall 210 by placing and curing concrete in the formwork is repeated up to the ground slab 180.

여기서, 상기 지하외벽(210)을 형성하기 위해 타설되는 콘크리트는 철골띠장보(150)의 통공(151)을 통해 철골띠장보(150) 하부의 흙막이벽(110)과 거푸집 사이의 공간으로 타설됨과 동시에 상기 통공(151)에 위치한 슬래브(180a)의 철근을 매설하게 된다.The concrete poured to form the underground outer wall 210 is poured into the space between the earth retaining wall 110 under the steel wire band saw 150 and the formwork through the through hole 151 of the steel wire band saw 150, At the same time, the reinforcing bars of the slabs 180a located in the through holes 151 are buried.

상기 구조물기둥(200)과 지하외벽(210)을 형성하는 시점은 동시에 이루어질 수도 있고, 지하외벽(210)이 구조물기둥(200)보다 후에 이루어질 수도 있다. 이는 구조물기둥(200)을 우선 구성하여 지상의 공사를 먼저 시행하고 지하외벽(210)은 지하에만 있는 구조물이므로 후 시공할 수 있다. 경우에 따라서는 도 21 내지 도 22에 도시된 바와 같이, 구조물기둥(200)을 지상슬래브(180)에서 하부로 기초슬래브(180b) 상면까지 순차적으로 형성할 수도 있으며, 상기 지상슬래브(180)와 기초슬래브(180b) 사이의 다수의 슬래브 중 어느 하나의 슬래브에서 지상슬래브(180)까지 위로 형성하여 지상층을 우선 시공하도록 하고, 상기 어느 하나의 슬래브 하부는 기초슬래브(180b)가 완성된 후에 지하 공정에 맞게 형성할 수도 있다. 본 발명에서는 수평구조물의 철골 프레임(140)으로 지지하면서 하부로 공사를 진행하는 것이 본 발명의 핵심이다. 따라서 전체 단계과정 중에서 구조물기둥(200)의 시공은 실정에 맞게 먼저할 수도 있고 뒤에 할 수도 있는 것이다.The building columns 200 and the basement outer walls 210 may be formed at the same time or the basement outer walls 210 may be formed later than the structure columns 200. This is because the structure column 200 is constructed first and the ground construction is first performed, and the underground outer wall 210 is a structure existing only in the underground. 21 to 22, the column 200 may be sequentially formed from the ground slab 180 to the upper surface of the foundation slab 180b, and the ground slab 180 and the foundation slab 180b may be sequentially formed. A ground layer is formed first from any one of the plurality of slabs between the foundation slabs 180b to the ground slab 180 so that the ground layer is first applied to the foundation slab 180b. After completion of the foundation slab 180b, As shown in FIG. In the present invention, it is the core of the present invention that the steel frame 140 of the horizontal structure is supported while the construction is performed downward. Therefore, the construction of the structure column 200 in the whole step process can be performed first or later according to the actual situation.

상기의 과정을 반복하여 지하 구조물(100)의 각 슬래브(180)(180a)(180b) 사이에 구조물기둥(200)이 형성되면, 도 23에 도시된 바와 같이, 각 층의 브라켓(130)과 가설 철골기둥(120)을 제거한 후, 상기 가설 철골기둥(120)이 제거되어 각 슬래브(180)(180a)(180b)에 형성된 홀(미도시)을 콘크리트로 메우고 양생하여 도 24 내지 도 25에 도시된 바와 같이, 지하 구조물(100)을 형성한다.When the structure pillars 200 are formed between the slabs 180, 180a and 180b of the underground structure 100 by repeating the above process, as shown in FIG. 23, the brackets 130, After the temporary steel column 120 is removed, the temporary steel column 120 is removed and holes (not shown) formed in the respective slabs 180, 180a and 180b are filled with concrete and cured, As shown, an underground structure 100 is formed.

이상과 같이 본 발명은, 비록 한정된 실시예와 도면에 의해 설명되었으나, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정되어 해석되어서는 아니되며, 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 일실시예에 불과할 뿐이고, 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 발명의 청구범위를 벗어나지 않는 한도 내에서 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다.
While the present invention has been described with reference to the particular embodiments and drawings, it is to be understood that the phraseology and terminology employed herein are for the purpose of description and should not be regarded as limiting in any ordinary or prejudicial sense. It must be interpreted in terms of meaning and concept. Therefore, the embodiments described in the present specification and the configurations shown in the drawings are only examples of the present invention, and not all of the technical ideas of the present invention are described. Therefore, It is to be understood that equivalents and modifications are possible.

100: 지하 구조물 110: 흙막이벽
120: 가설 철골기둥 130: 브라켓
140: 철골 프레임 150: 철골띠장보
160: 토압전달부재 170: 데크플레이트
180: 지상슬래브 190: 주두
200: 구조물기둥
100: underground structure 110: retaining wall
120: Hypothesis steel column 130: Bracket
140: Steel frame 150: Steel strip
160: earth pressure transmitting member 170: deck plate
180: ground slab 190:
200: Structure column

Claims (8)

철근콘크리트 기둥과 주두 그리고 상기 주두의 끝면에 배치되는 철골보, 철골보 위에 설치되는 슬래브로 구성되는 지하 구조물에 있어서 지하공사 중에는 가설 철골기둥 및 상기 가설 철골기둥에 고정된 브라켓으로 수직하중을 지지하고, 토압은 수평구조물의 철골 프레임과 슬래브로 버티면서 지하로 공사를 진행하는 공사방법에 있어서,
상기 지하 구조물을 설치하고자 하는 지중에 흙막이벽을 형성하는 제1단계와;
상기 지하 구조물을 받쳐 지지하는 구조물기둥의 설치 위치가 아닌 지중에 일정간격으로 가설 철골기둥을 설치하는 제2단계와;
상기 가설 철골기둥이 설치된 지중을 굴토하는 제3단계와;
상기 지중이 굴토되어 나타난 가설 철골기둥에 트러스 형태의 브라켓을 설치하는 제4단계와;
상기 브라켓 상면에 철골보를 안착 및 서로 연결하여 향후 구조물기둥이 위치할 부분에 '井'자 형태의 연결보를 형성하면서 상기 '井'자 형태의 연결보가 격자형으로 배열되도록 수평구조물의 철골 프레임을 형성하는 제5단계와;
상기 '井'자 형태의 연결보의 폐쇄된 부분의 저면 플랜지에 드롭 데크플레이트를 설치하고, 상기 '井'자 형태의 연결보의 폐쇄된 부분 이외의 철골보 상면 플랜지에 슬래브 데크플레이트를 설치하는 제6단계와;
상기 드롭 데크플레이트에는 콘크리트를 타설하지 않고, 상기 슬래브 데크플레이트에 콘크리트를 타설 및 양생하여 지상슬래브를 형성하는 제7단계와;
상기 지상슬래브 하부의 지중을 굴토하는 제8단계와;
상기 지중을 굴토하여 나타난 가설 철골기둥에 트러스 형태의 브라켓을 설치하는 제4단계 내지 제7단계를 반복한 후, 지하 구조물의 기초 하단까지 굴토하는 제9단계와;
상기 지하 구조물의 기초에 철근을 배근한 후, 콘크리트를 타설 및 양생하여 기초슬래브를 형성하는 제10단계와;
상기 기초슬래브 상면에서 지상슬래브까지 구조물기둥 및 주두를 형성하는 제11단계와;
상기 각 슬래브 사이에 구조물기둥이 형성되면, 각 층의 가설 철골기둥에 설치된 브라켓을 제거한 후, 가설 철골기둥을 제거하는 제12단계와;
상기 가설 철골기둥이 제거되어 각 슬래브에 형성된 홀을 콘크리트로 메우기하는 제13단계를 포함하여 이루어지는 것을 특징으로 하는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법.
In the underground construction comprising a reinforced concrete pillar and a pillar, a steel beam disposed on the end surface of the pillar, and a slab installed on the steel beam, a vertical load is supported by a bracket fixed to the pillar of the steel column and the pillar of the steel column, In a construction method of constructing a building underground while holding it with a steel frame and a slab of a horizontal structure,
A first step of forming an earth retaining wall in the ground where the underground structure is to be installed;
A second step of installing a hypothetical steel column at a predetermined interval in the ground instead of the installation position of the column supporting the underground structure;
A third step of excavating the ground in which the hypothetical steel column is installed;
A fourth step of installing a truss type bracket on the hypothetical steel column where the ground is excavated;
A steel frame frame is formed on the upper surface of the bracket so as to form a connection beam in the shape of a '井';
A drop deck plate is installed on the bottom flange of the closed portion of the connection beam in the form of a "boss", and a slab deck plate is installed on the upper surface flange of the steel beam other than the closed portion of the " Step 6;
A seventh step of forming a ground slab by placing and curing concrete on the slab deck plate without pouring concrete into the drop deck plate;
An eighth step of excavating the ground below the ground slab;
Repeating the fourth to seventh steps of installing a truss-type bracket on the hypothetical steel column that has been excavated from the ground, and then advancing to the bottom of the underground structure;
A tenth step of placing a reinforcing bar on the foundation of the underground structure, and then placing and curing the concrete to form a foundation slab;
An eleventh step of forming a column and a column of the structure from the upper surface of the foundation slab to the ground slab;
A twelfth step of removing the brackets provided on the columns of the steel columns of each layer and removing the columns of the steel columns when the columns of the structure are formed between the slabs;
And a step of filling the holes formed in the slabs with concrete by removing the pillar columns. The method for constructing an underground structure using a pillar, a pillar, a steel frame, and a slab.
청구항 1에 있어서, 상기 제1단계에서,
상기 흙막이벽은, 가설 또는 영구구조물인 것을 특징으로 하는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법.
The method according to claim 1, wherein, in the first step,
Wherein the earth retaining wall is a hypothetical or permanent structure, and a method of constructing an underground structure using a pillar, a pillar, a steel beam, and a slab.
청구항 1에 있어서, 상기 제5단계에서,
상기 수평구조물의 철골 프레임 철골보 단부에 형성된 안착홈에 철골띠장보를 안착 및 고정한 후, 철골띠장보와 흙막이벽을 토압전달부재로 일정간격 이격되게 고정시켜 흙막이벽으로부터 전달되는 토압이 수평구조물의 철골 프레임과 슬래브로 분산되어 전달되도록 하는 것을 특징으로 하는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법.
The method according to claim 1, wherein, in the fifth step,
The steel strip is fixed and fixed to the earth moving wall at a predetermined distance by the earth pressure transmitting member so that the earth pressure delivered from the earth retaining wall is transmitted to the steel frame of the horizontal structure And the slabs are distributed to be distributed in a frame and a slab. The method of constructing an underground structure using a pillar, a steel frame, and a slab-formed structure.
청구항 3에 있어서,
상기 안착홈은, 상기 철골띠장보가 철골보 상면으로 지상슬래브 두께의 1/2 이상 내지 지상슬래브 두께 이내로 돌출되도록 형성되는 것을 특징으로 하는 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법.
The method of claim 3,
Wherein the seating groove is formed so that the steel strip can protrude from the upper surface of the steel frame to a thickness of less than 1/2 of the thickness of the ground slab to less than the thickness of the ground slab.
청구항 2에 있어서,
상기 흙막이벽이 영구구조물일 경우, 상기 철골 프레임의 철골보는 흙막이벽에 맞닿지 않도록 배치하며 테두리보 하부 거푸집을 받쳐주기 위해 삼각 까치발을 고정하고 그 위에 철근배근을 하며, 철근배근과 철골보가 부딪히는 부분에는 철골보를 따내어 안착홈을 형성하는 것을 특징으로 하는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법.
The method of claim 2,
When the earth retaining wall is a permanent structure, the steel frame of the steel frame is disposed so as not to contact with the earth retaining wall, the triangular bracket is fixed to support the frame under the frame, the steel reinforcement is placed thereon, A method of constructing an underground structure using a pillar, a steel frame, and a structure formed of steel bars and slabs.
청구항 1에 있어서,
상기 제5단계에서, 1층 부분에서 흙막이벽과 수평구조물의 철골 프레임이 연결되는 부위는 철골띠장보 대신에 철근콘크리트 테두리보를 설치하여 상기 흙막이벽의 상부와 철골보의 최외곽을 일체화하는 것을 특징으로 하는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법.
The method according to claim 1,
In the fifth step, a reinforcing concrete frame beam is installed in place of the steel frame brace to connect the earth retaining wall to the steel frame frame of the horizontal structure in the first layer portion, and the upper part of the earth retaining wall and the outermost frame of the steel frame are integrated. Construction Method of Underground Structures Using Columns, Columns, Steel Beams and Slabs.
청구항 1에 있어서,
상기 구조물기둥은 상기 지상슬래브와 기초슬래브 사이의 다수의 슬래브 중 어느 하나의 슬래브에서 지상슬래브까지 위로 형성하고, 상기 어느 하나의 슬래브 하부는 기초슬래브가 완성된 후에 형성하는 것을 특징으로 하는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법.
The method according to claim 1,
Characterized in that the structure column is formed up to a ground slab from any one of the plurality of slabs between the ground slab and the foundation slab, and the lower one of the slabs is formed after the foundation slab is completed. Construction Method of Underground Structures Using Structures Consisting of Steel Beams and Slabs.
청구항 1에 있어서,
상기 구조물기둥은, 상기 지상슬래브에서 하부로 기초슬래브 상면까지 순차적으로 형성하는 것을 특징으로 하는 기둥과 주두와 철골보 및 슬래브로 형성되는 구조물을 이용한 지하 구조물 구축공법.
The method according to claim 1,
Wherein the column of the structure is sequentially formed from the ground slab to the upper surface of the foundation slab, wherein the column is formed of a pillar, a steel frame, and a slab.
KR1020130021684A 2013-02-28 2013-02-28 Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed KR101401057B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020130021684A KR101401057B1 (en) 2013-02-28 2013-02-28 Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020130021684A KR101401057B1 (en) 2013-02-28 2013-02-28 Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed

Publications (1)

Publication Number Publication Date
KR101401057B1 true KR101401057B1 (en) 2014-05-29

Family

ID=50895733

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020130021684A KR101401057B1 (en) 2013-02-28 2013-02-28 Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed

Country Status (1)

Country Link
KR (1) KR101401057B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101607433B1 (en) * 2015-05-11 2016-04-11 (주)바로건설기술 Structure Having Modularized Beam Unit and Its Construction Method
KR101687495B1 (en) * 2015-10-01 2016-12-16 박광호 Partial top-down construction method for building underground structures
CN110004993A (en) * 2019-04-22 2019-07-12 上海建工一建集团有限公司 A kind of super thick bottom plate surveying setting-out construction method and unwrapping wire platform
KR102184568B1 (en) 2019-06-10 2020-11-30 현대건설(주) Apparatus for intalling bracket for top-down construction method
KR102392517B1 (en) 2021-07-13 2022-04-29 주식회사 와이앤케이에코 Top-down method using by double beam system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100531385B1 (en) 2004-09-17 2005-11-29 주식회사 한빛구조엔지니어링 Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
KR100662524B1 (en) 2005-03-28 2006-12-28 (주)바로건설기술 Double pipe girder struts as permanent system
KR20080098262A (en) * 2007-05-04 2008-11-07 (주)씨.에스 구조 엔지니어링 Non-support construction method using the deckplate for wall girder
KR20120033683A (en) * 2010-09-30 2012-04-09 (주)바로건설기술 Device for constructing an underground structure and method thereof

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100531385B1 (en) 2004-09-17 2005-11-29 주식회사 한빛구조엔지니어링 Construction method of underground structure that enables continuous retaining wall using steel wale and diaphragm effect of concrete slab
KR100662524B1 (en) 2005-03-28 2006-12-28 (주)바로건설기술 Double pipe girder struts as permanent system
KR20080098262A (en) * 2007-05-04 2008-11-07 (주)씨.에스 구조 엔지니어링 Non-support construction method using the deckplate for wall girder
KR20120033683A (en) * 2010-09-30 2012-04-09 (주)바로건설기술 Device for constructing an underground structure and method thereof

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101607433B1 (en) * 2015-05-11 2016-04-11 (주)바로건설기술 Structure Having Modularized Beam Unit and Its Construction Method
KR101687495B1 (en) * 2015-10-01 2016-12-16 박광호 Partial top-down construction method for building underground structures
CN110004993A (en) * 2019-04-22 2019-07-12 上海建工一建集团有限公司 A kind of super thick bottom plate surveying setting-out construction method and unwrapping wire platform
CN110004993B (en) * 2019-04-22 2024-01-02 上海建工一建集团有限公司 Ultra-thick bottom plate measuring paying-off construction method and paying-off platform
KR102184568B1 (en) 2019-06-10 2020-11-30 현대건설(주) Apparatus for intalling bracket for top-down construction method
KR102392517B1 (en) 2021-07-13 2022-04-29 주식회사 와이앤케이에코 Top-down method using by double beam system

Similar Documents

Publication Publication Date Title
KR101687495B1 (en) Partial top-down construction method for building underground structures
KR102208793B1 (en) Under ground structure using column wall and construction method thereof
KR101401057B1 (en) Method to build underground structures using the pillars and the stigma and steel beam and slab structures are formed
KR101341679B1 (en) Device for constructing an underground structure and method thereof
KR101600845B1 (en) The horizontal structural frame and the underground construction methods using it
CN110499779B (en) Construction method of air duct structure sharing side wall with subway station
KR20120096605A (en) Bracket support type downward construction system and method
KR102084829B1 (en) Top-down method using precast-concrete colum
KR100629437B1 (en) Casing structure for constructing column and column construction method using the same
CN104532856A (en) Fabricated lattice unit for foundation pit supporting and installation method
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
KR20090090742A (en) Bottom-up construction method of underground structure using permanent strut
KR20140042132A (en) Construction method of the underground tunnel and, structure for the slab construction
KR101566528B1 (en) Basement extension construction method using underground structure
JP5865567B2 (en) Connecting slab and its construction method
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR100912574B1 (en) Retaining wall system using strut assembly and excavating method using the same
JP5749620B2 (en) Seismic isolation method for existing buildings
CN109235453B (en) Deep foundation pit PRC pipe pile assembled supporting method
KR20120099811A (en) Vertically Inserting Column into the Eccentrically Bored Hole the Method Thereof
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof
CN108457300B (en) Construction method for replacing support of underground large-span structure by cover-excavation method
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column

Legal Events

Date Code Title Description
A201 Request for examination
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20190430

Year of fee payment: 6