KR101077242B1 - Construction method of basement structure using retaining wall and steel column - Google Patents

Construction method of basement structure using retaining wall and steel column Download PDF

Info

Publication number
KR101077242B1
KR101077242B1 KR1020090035968A KR20090035968A KR101077242B1 KR 101077242 B1 KR101077242 B1 KR 101077242B1 KR 1020090035968 A KR1020090035968 A KR 1020090035968A KR 20090035968 A KR20090035968 A KR 20090035968A KR 101077242 B1 KR101077242 B1 KR 101077242B1
Authority
KR
South Korea
Prior art keywords
steel
pillars
wall
outer steel
column
Prior art date
Application number
KR1020090035968A
Other languages
Korean (ko)
Other versions
KR20100117300A (en
Inventor
김점한
Original Assignee
(주)네오크로스구조엔지니어링
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)네오크로스구조엔지니어링 filed Critical (주)네오크로스구조엔지니어링
Priority to KR1020090035968A priority Critical patent/KR101077242B1/en
Publication of KR20100117300A publication Critical patent/KR20100117300A/en
Application granted granted Critical
Publication of KR101077242B1 publication Critical patent/KR101077242B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench
    • E02D29/055Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench further excavation of the cross-section proceeding underneath an already installed part of the structure, e.g. the roof of a tunnel
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/02Sheet piles or sheet pile bulkheads
    • E02D5/03Prefabricated parts, e.g. composite sheet piles
    • E02D5/04Prefabricated parts, e.g. composite sheet piles made of steel
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/61Connections for building structures in general of slab-shaped building elements with each other
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork

Abstract

본 발명은 지하 구조물의 경계선을 따라서 흙막이 벽체(100)를 구축하는 단계; 기둥이 설치되어야 할 위치에 내부 철골 기둥(110)을 설치하는 단계; 상기 흙막이 벽체(100)의 내측에 외곽 철골 기둥(120)을 소정 간격으로 설치하는 단계; 1차 터파기를 수행하여 상기 흙막이 벽체(100)와 내부 철골 기둥(110) 및 외곽 철골 기둥(120)의 일부가 노출되도록 하는 단계; 상기 외곽 철골 기둥(120)들 사이에는 외곽 철골보(130)를 연결하는 단계; 상기 내부 철골 기둥(110)과 외곽 철골 기둥(120) 사이 및 상기 내부 철골 기둥(110) 상호간의 사이에 내부 철골보(140)를 연결하는 단계; 상기 외곽 철골 기둥(120)과 외곽 철골보(130)가 위치하는 부분을 제외한 나머지 부분의 철골보 위에 콘크리트를 타설하여 슬래브를 축조하는 단계; 상기 단계들을 반복하여 지하 구조물의 시공 깊이까지 슬래브(S1)(S2)(S3)와 바닥층(B)을 축조하는 단계; 및 상기 바닥층(B)에서 지상까지 상방향으로 지하 외벽(150)을 연속적으로 시공하는 단계;를 포함하는 지하 구조물 시공 방법이 제공된다.The present invention comprises the steps of constructing the retaining wall (100) along the boundary line of the underground structure; Installing the internal steel column 110 at a location where the column should be installed; Installing the outer steel frame pillars 120 at predetermined intervals inside the earth wall 100; Performing a first digging to expose a portion of the retaining wall (100), the inner steel column (110), and the outer steel column (120); Connecting the outer cheolgolbo 130 between the outer steel pillars 120; Connecting the inner steel beams 140 between the inner steel pillars 110 and the outer steel pillars 120 and between the inner steel pillars 110; Constructing a slab by placing concrete on the steel gimbal of the remaining portion except for the portion where the outer steel pillar 120 and the outer steel gimbal 130 are located; Repeating the above steps to build the slab (S1) (S2) (S3) and the bottom layer (B) to the construction depth of the underground structure; And continuously constructing the basement outer wall 150 upwards from the bottom layer (B) to the ground.

지하 구조물, 흙막이 벽체 Underground structures, retaining walls

Description

흙막이 벽체와 철골 기둥을 이용한 지하 구조물 시공 방법 {Construction method of basement structure using retaining wall and steel column}Construction method of basement structure using retaining wall and steel column {Construction method of basement structure using retaining wall and steel column}

본 발명은 지하 구조물 시공 방법에 관한 것으로서, 보다 상세하게는 터파기를 하면서 지하 구조물을 하향 시공하는 탑-다운(Top-Down) 공법에 있어서 흙막이벽체 내부에 철골기둥을 설치하지 않을뿐더러 흙막이 벽체 내부의 철골기둥에 연결할 철골 띠장을 지지하는 철골 좌대와 같은 가설 지지수단을 별도로 설치할 필요없이 흙막이 벽체 및 상기 흙막이 벽체와 근접하여 설치된 최소한의 개수를 가진 철골 기둥을 이용하여 간단하고 용이하게 건축물을 축조할 수 있는 지하 구조물 시공 방법에 관한 것이다. The present invention relates to a method for constructing an underground structure, and more particularly, in the top-down method of digging down an underground structure while digging, it does not need to install a steel pillar in the retaining wall, and also in the retaining wall. It is possible to construct the structure simply and easily by using the earth wall and the minimum number of steel poles installed in close proximity to the earth wall without the need to install a temporary support means such as a steel frame for supporting the steel frame to be connected to the steel column. It is about a method of constructing underground structures.

지하 구조물을 시공하는 방법은 크게 순타공법과 역타공법으로 분류될 수 있는데, 순타공법은 스트러트와 같은 가설 지지수단에 의해 지하 구조물의 외곽에 형성된 흙막이 벽체를 지지하면서 지하 시공 깊이까지 굴토를 한 다음, 바닥에서부터 지상까지 구조물을 순차적으로 시공하면서 가설 지지수단을 해체해 나가는 방식이 다.The method of constructing underground structures can be largely divided into net and reverse methods, which can be excavated to the depth of underground construction while supporting the wall of walls formed on the outside of the underground structure by means of temporary support such as struts. Dismantling the temporary support means by constructing the structure sequentially from the floor to the ground.

한편, 탑-다운(Top-Down) 공법이라고 불리우는 역타공법은 지하 터파기를 수행하면서 동시에 슬래브를 타설하고, 축조된 슬래브 구조물이 횡토압에 대한 버팀목 역할을 하도록 하면서 지상에서 지하까지 순차적으로 시공해 나가는 방법이다.On the other hand, the reverse drilling method, called Top-Down method, performs the underground excavation and at the same time casts the slab and builds the slab structure sequentially from the ground to the ground while acting as a support for the transverse pressure. It is a way.

이러한 탑-다운 공법의 한 가지 예로서, 특허등록 제0531385에는 매립형 철골 띠장과 슬래브 강막 작용을 이용하여 지하 외벽의 연속시공이 가능하도록 한 지하 구조물 시공방법이 개시되어 있다.As an example of such a top-down method, Patent Registration No. 0531385 discloses a method for constructing an underground structure that enables continuous construction of an underground outer wall by using a buried steel band and slab film forming action.

상기 방법에 따르면, 통상적인 방법으로 흙막이 벽체(1)를 구축하고, 흙막이 벽체(1) 내부에는 통상적으로 1.6m내외로 철골 기둥(2)이 설치된다. 그런 다음, 도 1a 및 도 1b에 도시된 바와 같이, 터파기 작업 후 흙막이 벽체(1) 내부에 매입된 철골 기둥(2)에 연결하기 위해 콘크리트 벽체를 부수어 철골 기둥(2)을 노출 시킨 다음 철골 기둥(2)의 측면에 복수의 철골 좌대(3)를 부착한다.According to the above method, the retaining wall 1 is constructed in a conventional manner, and the steel frame 2 is usually installed in the retaining wall 1 to about 1.6 m. Then, as shown in Figures 1a and 1b, after the excavation work to break the concrete wall to connect to the steel column (2) embedded in the retaining wall (1) to expose the steel column (2) and then the steel frame The steel frame base 3 is attached to the side surface of the pillar 2.

이어서, 상기 철골 좌대(300)의 상부에 철골 띠장(4)을 수평으로 설치하고, 상기 철골 띠장(4)과 기둥 철골 사이에 내부 수평보(5)를 설치한다.Subsequently, the steel frame strip 4 is horizontally installed on the upper portion of the steel frame base 300, and an inner horizontal beam 5 is installed between the steel frame strip 4 and the column steel frame.

마지막으로, 상기 내부 수평보(5)의 상부에 콘크리트를 타설하여 콘크리트 슬래브를 형성하게 된다. 추가적인 터파기를 진행하면서 이상과 같은 공정을 반복하여 지하 구조물을 축조하게 된다.Finally, concrete is poured on top of the inner horizontal beam 5 to form a concrete slab. While further digging, the above process is repeated to build an underground structure.

그런데, 상기와 같은 공정에 있어서는 철골 띠장 지지를 위해 흙막이 벽체 내부에 매립된 철골 기둥의 측면에 철골 좌대를 필수적으로 설치하여야 하므로 시공 자재와 공정이 매우 복잡하고 번거로워 공기 연장이 불가피하다. 특히, 철골 좌대를 설치하기 위해서는 흙막이 벽체 내부에 매립된 철골을 노출시켜야 하므로 강제로 콘크리트 벽체를 제거하여야 하는 불편도 뒤따른다.However, in the above process, since the steel frame base must be installed on the side of the steel pillars embedded in the earthen wall to support the steel strips, construction materials and processes are very complicated and cumbersome, and thus, air extension is inevitable. In particular, in order to install the steel frame base to expose the steel frame embedded in the wall of the earthquake, the inconvenience of having to remove the concrete wall forcibly follows.

또한, 철골 좌대 설치를 위해 흙막이 벽체체에는 흙막이 벽체만으로도 안정이 확보되고 강성 또한 보장이 되더라도 소정 간격으로 철골을 매립하여야 하므로 소요되는 철골 자재가 많이 소요된다.In addition, in order to install the steel frame, the earthenware wall requires much earthen material, because the earthenware is secured only by the earthenware wall and the rigidity is guaranteed.

본 발명은 상기와 같은 문제점을 해결하기 위한 것으로서, 흙막이 벽체 내부에 별도의 철골 기둥을 설치하지 않고 별도의 가설부재 시공 및 설치 없이 철골 띠장과 같은 별도의 부재를 가설할 필요가 없으며 흙막이 벽체의 구조나 유형에 상관없이 지하 구조물을 비교적 간단하고 용이하게 탑-다운 공법으로 구축할 수 있는 지하 구조물 시공 방법을 제공하는 것을 목적으로 한다.
또한, 본 발명은 각 층의 슬래브(S1)(S2)(S3)가 지하 외벽의 경계선까지만 선시공된 상태이므로 지하 외벽(150)이 단절됨이 없이 바닥층(B)에서 지상까지 연속적으로 시공될 수 있고, 외곽 철골 기둥(120)과 외곽 철골보(130)가 지하 외벽(150) 내에 매립되는 지하 구조물 시공 방법을 제공하는 것을 목적으로 한다.
The present invention is to solve the above problems, there is no need to install a separate member, such as steel frame strip without installing a separate steel frame pillar and installation and installation of a separate steel pillar inside the earth wall wall structure of the earth wall It is an object of the present invention to provide a method of constructing an underground structure, which can be constructed by a simple and easy top-down method regardless of the type.
In addition, the present invention, since the slab (S1) (S2) (S3) of each layer is pre-installed only to the boundary line of the basement outer wall can be constructed continuously from the bottom layer (B) to the ground without breaking the basement outer wall 150 and It is an object of the present invention to provide a method for constructing an underground structure in which the outer steel column 120 and the outer steel frame 130 are embedded in the basement outer wall 150.

상기와 같은 목적을 달성하기 위해서 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법은, 지하 구조물의 경계선을 따라서 흙막이 벽체를 구축하는 단계; 기둥이 설치되어야 할 위치에 내부 철골 기둥을 설치하는 단계; 상기 흙막이 벽체의 내측에 외곽 철골 기둥을 소정 간격으로 설치하는 단계; 1차 터파기를 수행하여 상기 흙막이 벽체과 내부 철골 기둥 및 외곽 철골 기둥의 일부가 노출되도록 하는 단계; 상기 외곽 철골 기둥들 사이에는 외곽 철골보를 연결하는 단계; 상기 내부 철골 기둥과 외곽 철골 기둥 사이 및 상기 내부 철골 기둥 상호간의 사이에 내부 철골보를 연결하는 단계; 상기 외곽 철골 기둥과 외곽 철골보가 위치하는 부분을 제외한 나머지 부분의 철골보 위에 콘크리트를 타설하여 슬래브를 축조하는 단계; 상기 단계들을 반복하여 지하 구조물의 시공 깊이까지 슬래브와 바닥층을 축조하는 단계; 및 상기 바닥층에서 지상까지 상방향으로 지하 외벽을 연속적으로 시공하는 단계;를 포함한다.Underground structure construction method according to a preferred embodiment of the present invention in order to achieve the above object, the step of building a wall along the boundary of the underground structure; Installing an internal steel column at a location where the column is to be installed; Installing outer steel pillars at predetermined intervals inside the retaining wall; Performing a first trench to expose a portion of the retaining wall, the inner steel pillar, and the outer steel pillar; Connecting an outer cheolgolbo between the outer steel pillars; Connecting an inner steel beam between the inner steel pillars and the outer steel pillars and between the inner steel pillars; Constructing a slab by pouring concrete on the steel gimbal of the remaining portion except for the portion where the outer steel pillar and the outer steel gimbal are located; Repeating the above steps to build the slab and the bottom layer to the construction depth of the underground structure; And continuously constructing an underground outer wall upward from the bottom layer to the ground.

바람직하게, 본 발명의 지하 구조물 시공 방법은 외곽 철골 기둥이 설치될 간격으로 철제 케이싱을 박아서 설치하는 단계; 상기 철제 케이싱의 내부에 상기 외곽 철골 기둥을 삽입하여 설치하는 단계; 및 상기 철제 케이싱을 빼내어 제거함으로써 상기 외곽 철골 기둥의 일부가 노출되도록 하는 단계;를 포함한다.Preferably, the underground structure construction method of the present invention comprises the steps of installing the steel casing at intervals to be installed the outer steel pillars; Inserting and installing the outer steel column inside the steel casing; And removing and removing the steel casing to expose a portion of the outer steel pillar.

더욱 바람직하게, 상기 외곽 철골 기둥이 삽입된 철제 케이싱 내부의 빈공간에는 모래나 흙을 채우게 된다.More preferably, the empty space inside the steel casing in which the outer steel column is inserted is filled with sand or soil.

또한, 상기 외곽 철골 기둥의 하단에는 제자리 콘크리트 말뚝을 구축할 수도 있다.In addition, it is also possible to build a concrete stake in the lower end of the outer steel pillars.

바람직하게, 상기 흙막이 벽체와 외곽 철골보 사이의 이격 공간에는 채움재로 메워질 수 있다. Preferably, the space between the earth wall and the outer cheolgolbo may be filled with a filling material.

본 발명의 지하 구조물 시공방법에 따르면, 시공 단계 시 흙막이 벽체만으로 도 안전하고 강성확보가 가능하므로 흙막이 벽체 내부에 철골 기둥을 별도로 설치할 필요가 없고 또한 철골 띠장을 지지할 철골 좌대와 같은 가설부재를 설치할 필요가 없으므로 공사에 소요되는 자재가 줄어들 뿐만 아니라 시공이 상대적으로 간편하고 용이하여 공사 기간이 단축된다.According to the method of construction of underground structures of the present invention, it is possible to secure the safety and rigidity only by the wall of the earth during the construction stage, so there is no need to install a steel column separately inside the wall of the earth, and also install a temporary member such as a steel frame to support the steel band. Since there is no need, the material required for construction is not only reduced, but also the construction period is relatively simple and easy, which shortens the construction period.

또한, 본 발명의 지하 구조물 시공방법에 있어서는, 흙막이 벽체에 띠장이나 철골보가 부착되거나 설치되지 않고 구조적으로 독립적인 거동을 하게 되므로, 그 구조나 유형에 제한을 받지 않아서 토사 붕괴 방지라는 고유한 목적에 부합하는 다양한 유형의 흙막이 벽체가 채용될 수 있는 장점이 있다.In addition, in the method of constructing the underground structure of the present invention, since the structure of the earthquake wall is not attached or installed to the earthenware wall or structurally independent behavior, it is not limited to the structure or type, so it is possible to prevent the earth and earth collapse. There is an advantage that different types of retaining walls can be employed.

나아가, 본 발명에서는 철골 띠장이나 철골보를 부착하기 위해 흙막이 벽체의 콘크리트 일부를 강제로 제거하는 등의 불필요한 공정이 사라지게 되어 시공 효율성이 향상된다.
또한, 각 층의 슬래브(S1)(S2)(S3)가 지하 외벽의 경계선까지만 선시공된 상태이므로 지하 외벽(150)이 단절됨이 없이 바닥층(B)에서 지상까지 연속적으로 시공될 수 있고, 외곽 철골 기둥(120)과 외곽 철골보(130)가 지하 외벽(150) 내에 매립되는 지하 구조물 시공 방법을 제공한다.
Furthermore, in the present invention, unnecessary processes such as forcibly removing a part of the concrete of the retaining wall to attach the steel frame or the steel frame are eliminated, thereby improving construction efficiency.
In addition, since the slab (S1) (S2) (S3) of each layer is pre-installed only to the boundary line of the basement outer wall, the basement outer wall 150 can be continuously constructed from the bottom layer (B) to the ground without being cut off, the outer steel frame The pillar 120 and the outer cheolgolbo 130 provides a construction method for underground structures embedded in the basement outer wall 150.

이하, 첨부된 도면을 참조로 본 발명의 바람직한 실시예를 상세히 설명하기로 한다. 이에 앞서, 본 명세서 및 청구범위에 사용된 용어나 단어는 통상적이거나 사전적인 의미로 한정해서 해석되어서는 아니되며, 발명자는 그 자신의 발명을 가장 최선의 방법으로 설명하기 위해 용어의 개념을 적절하게 정의할 수 있다는 원칙에 입각하여 본 발명의 기술적 사상에 부합하는 의미와 개념으로 해석되어야만 한다. 따라서, 본 명세서에 기재된 실시예와 도면에 도시된 구성은 본 발명의 가장 바람직한 일 실시예에 불과할 뿐이고 본 발명의 기술적 사상을 모두 대변하는 것은 아니므로, 본 출원시점에 있어서 이들을 대체할 수 있는 다양한 균등물과 변형예들이 있을 수 있음을 이해하여야 한다. Hereinafter, preferred embodiments of the present invention will be described in detail with reference to the accompanying drawings. Prior to this, terms or words used in the specification and claims should not be construed as having a conventional or dictionary meaning, and the inventors should properly explain the concept of terms in order to best explain their own invention. Based on the principle that can be defined, it should be interpreted as meaning and concept corresponding to the technical idea of the present invention. Therefore, the embodiments described in the specification and the drawings shown in the drawings are only the most preferred embodiment of the present invention and do not represent all of the technical idea of the present invention, various modifications that can be replaced at the time of the present application It should be understood that there may be equivalents and variations.

본 발명에 따른 지하 구조물 시공 방법은 크게, 건물경계선을 따라 흙막이 벽체를 설치하고 건물의 기둥이 될 위치에 내부 철골 기둥을 박는 공정, 철제 케이싱을 박고 그 내부에 외곽 철골 기둥을 설치하는 공정, 1차 터파기후 철제 케이싱을 제거하고 외곽 철골 기둥과 내부 철골 기둥을 노출시키는 공정, 노출된 외곽 철골 기둥 사이에 외곽 철골보를 설치하는 동시에 외곽 철골 기둥과 내부 철골 기둥 사이에는 내부 철골보를 설치하는 공정, 및 상기 내부 철골보 위에 콘크리트를 타설하여 슬래브를 구축하는 공정 등을 포함한다.Underground structure construction method according to the present invention is largely, the process of installing the wall of the earth along the building boundary line and the inner steel pillars in the position to be the pillar of the building, the process of installing the steel steel casing and the outer steel pillars therein, 1 Removing the steel casing after exposing the car and exposing the outer steel pillars and the inner steel pillars, installing the outer steel beams between the exposed outer steel pillars, and installing the inner steel beams between the outer steel pillars and the inner steel pillars; and It includes a step of building a slab by pouring concrete on the inner cheolgolbo.

그러면, 상기 각 공정들에 대해서 보다 상세히 살펴보기로 한다.Then, the processes will be described in more detail.

흙막이 벽체 시공Construction of wall

본 발명의 지하 구조물 시공 방법에 따라서, 먼저 도 2에 도시된 바와 같이 축조될 지하 구조물의 경계선을 따라서 흙막이 벽체(100)를 구축한다. 본 발명의 특징에 따르면 흙막이 벽체(100)에 철골 좌대나 띠장을 설치하지 않기 때문에 시공되는 흙막이 벽체의 구조나 유형에 있어서 어떠한 제약도 받지 않는다. 따라서, 상기 흙막이 벽체(100)는 당업계에 이미 알려진 다양한 방식에 의해 축조될 수 있다.According to the method for constructing an underground structure of the present invention, first, as shown in FIG. 2, the wall wall 100 is constructed along the boundary line of the underground structure to be constructed. According to the characteristics of the present invention, since the steel frame base or the band is not installed on the wall 100, there is no restriction in the structure or type of the wall to be constructed. Thus, the retaining wall 100 may be constructed by various methods already known in the art.

이러한 흙막이 벽체 시공의 예로서, H형강과 같은 파일(PILE)을 일정 간격(1.6n 내외)으로 매입하고 터파기 굴착을 진행하면서 토류판을 파일 사이에 끼우 는 파일 토류판 흙막이 벽체와, 축조 현장에서 콘크리트로 흙막이 벽체를 타설하는 현장 타설 콘크리트 흙막이 벽체(Cast In Place Pile, CIP) 등이 대표적이며, 이외에도 소일시멘트월(Soil Cement Wall, SCW), 다이아프램월(Diaphragm wall) 등이 있다.As an example of such a wall construction, pile pile plate wall wall, which inserts piles such as H-beams at regular intervals (about 1.6n) and inserts soil plates between piles while carrying out excavation, and concrete at the construction site For example, cast-in-place piles (CIPs), which are used to cast soil walls, are also typical, including Soil Cement Wall (SCW) and Diaphragm Wall.

본 발명에 따른 흙막이 벽체(100)는 철골 좌대나 철골 띠장의 설치를 위한 철골 기둥을 구비할 필요가 없으며, 콘크리트와 철근으로만 구성되어도 무방하다. 또한 철골 기둥이 구비될 경우에도 12m 내외로 간격을 이격시킬 수 있다.The retaining wall 100 according to the present invention does not need to be provided with steel pillars for the installation of steel frame bases or steel strips, and may be composed of only concrete and steel bars. In addition, even when provided with steel pillars can be spaced apart in about 12m.

상기와 같은 공법에 의해 흙막이 벽체(100)가 구축됨으로써 후속 공정에서 지하 터파기를 진행하더라도 토사의 붕괴를 방지할 수 있다.By constructing the soil wall 100 by the above-described method, it is possible to prevent the collapse of the earth and sand even if the underground trench in the subsequent process.

내부 철골 기둥 설치Internal steel column installation

흙막이 벽체(100) 시공이 완료되면, 도 3에 도시된 것과 같이, 축조되는 건축물의 설계에 따라서 기둥이 설치되어야 할 위치에 내부 철골 기둥(110)을 설치한다.When the construction of the earth wall 100 is completed, as shown in Figure 3, according to the design of the building to be built in accordance with the design of the column to install the inner steel pillars 110 in the position to be installed.

상기 내부 철골 기둥(110)은 H형강으로서 기존의 항타 공법 또는 지면 천공 후 매립 공법 등을 사용하여 필요한 위치에 설치될 수 있다.The inner steel column 110 may be installed in a required position using an existing anti-punching method or a landfill method after drilling the ground as an H-beam.

바람직하게, 상기 내부 철골 기둥(110)의 하부에는 이미 알려진 RCD(Reverse Circulation Drill) 공법이나 PRD(Percusion Rotary Drill) 공법 등에 의해서 기초부(112)를 가설하여 상부 구조물로부터 전달되는 하중을 지반으로 적절히 분산 전달할 수 있도록 한다.Preferably, the lower portion of the internal steel pillar 110 is a foundation of the foundation 112 by a known reverse circulation drill (RCD) method or percussion rotary drill (PRD) method, etc. to properly load the load transmitted from the upper structure to the ground Allow for distributed delivery.

외곽 철골 기둥 설치Outer steel column installation

본 발명의 특징에 따르면, 상기 흙막이 벽체(100)와는 독립적으로 그 내측에 외곽 철골 기둥(120)을 소정 간격으로 설치하고 이것을 기초로 외곽 철골보(130)와 내부 철골보(140)를 설치하게 된다.According to a feature of the present invention, the outer steel wall pillars 120 are installed at predetermined intervals independently of the retaining wall 100, and the outer steel steel beams 130 and the inner steel steel beams 140 are installed on the basis thereof.

이를 위해, 도 4 내지 도 6에 도시된 바와 같이, 외곽 철골 기둥(120)이 설치될 적절한 간격으로 지중에 철제 케이싱(122)을 박아서 설치한다. 상기 철제 케이싱(122)은 중공이 형성된 원통형의 부재로서 내부의 토사는 제거되어 비워진 상태가 되는데, 여기에 외곽 철골 기둥(120)을 삽입하게 된다.(도 5 참조)For this purpose, as shown in Figures 4 to 6, the outer steel pillars 120 are installed by driving the steel casing 122 in the ground at appropriate intervals to be installed. The steel casing 122 is a cylindrical member with a hollow formed therein, the soil is removed to be empty, the outer steel column 120 is inserted therein (see FIG. 5).

상기 외곽 철골 기둥(120)의 하단에는 콘크리트를 공급하여 제자리 콘크리트 말뚝(124)을 구축함으로써 외곽 철골 기둥(120)을 고정시키는 동시에 구조물로부터 가해지는 하중을 지면으로 분산 전달하는 기능을 하게 된다. 바람직하게, 상기 제자리 콘크리트 말뚝(124)의 상면은 지하층의 최종 굴토 깊이까지 형성된다.By supplying concrete to the lower end of the outer steel pillars 120 to build the concrete pile 124 in place to fix the outer steel pillars 120 and at the same time to distribute the load applied from the structure to the ground function. Preferably, the upper surface of the in-situ concrete pile 124 is formed to the final depth of pit of the basement layer.

또한, 상기 외곽 철골 기둥(120)이 삽입된 철제 케이싱(122) 내부의 빈공간에는 모래나 흙(126)을 채우게 된다.In addition, the empty space inside the steel casing 122 in which the outer steel pillars 120 are inserted is filled with sand or soil 126.

1차 터파기 Primary Dig

이어서, 상기 내부 철골 기둥(110)과 철제 케이싱(122) 및 외곽 철골 기둥(120)의 설치가 완료되면, 도 7에 도시된 바와 같이, 소정 깊이로 1차 터파기를 수행한다. 여기서, 상기 1차 터파기의 깊이는 적어도 지하 1층 깊이에 해당하는 것 이 바람직하지만 반드시 이것에 한정되는 것은 아니다.Subsequently, when the installation of the inner steel pillars 110, the steel casing 122 and the outer steel pillars 120 is completed, as shown in FIG. Here, the depth of the primary trench is preferably at least corresponding to the depth of basement 1, but is not necessarily limited thereto.

상기와 같이 터파기가 진행됨에 따라 흙막이 벽체(100)와 내부 철골 기둥(110)의 상단 일부가 노출된다.As the trench proceeds as described above, a portion of the upper end of the retaining wall 100 and the inner steel pillar 110 is exposed.

그러면, 상기 철제 케이싱(122)을 빼내어 제거함으로써 외곽 철골 기둥(120)의 상단 일부도 노출되도록 한다. 전술한 바와 같이, 상기 철제 케이싱(122) 내부의 빈 공간에는 모래나 흙(126)이 채워져 있을 뿐이므로 철제 케이싱(122)은 비교적 쉽게 제거될 수 있다. 비록 본 실시예에서는, 상기 철제 케이싱(122)을 1차 터파기 후에 제거하는 것으로 설명하였으나 이러한 순서에 한정될 필요는 없으며, 1차 터파기를 진행하기에 앞서 상기 철제 케이싱(122)을 제거하는 것도 가능한 것으로 이해되어야 한다.Then, by removing the steel casing 122 to remove a portion of the upper end of the outer steel pillars 120. As described above, since the empty space inside the steel casing 122 is filled with sand or soil 126, the steel casing 122 may be relatively easily removed. Although the present embodiment has been described as removing the steel casing 122 after the first burst, it is not necessary to be limited to this order, and the steel casing 122 may be removed before proceeding with the primary trench. It should be understood as possible.

철골보 설치Cheolgolbo installation

상기와 같이 소정 깊이로 1차 터파기가 마무리되면, 상기 노출된 외곽 철골 기둥(120)과 내부 철골 기둥(110) 사이에는 철골보가 연결된다.When the primary demolition is finished to a predetermined depth as described above, the cheolgolbo is connected between the exposed outer steel pillars 120 and the inner steel pillars (110).

먼저, 도 8 및 도 9에서 보는 바와 같이, 외곽 철골 기둥(120)들 사이에는 외곽 철골보(130)가 연결된다. 상기 외곽 철골보(130)는 통상적인 H형강이거나 또는 H형강에 프리캐스팅된 콘크리트 부재가 부착되어 있는 철골-콘크리트 복합보가 될 수 있다. 본 실시예에서는 일반적인 H형강을 도시하였다.First, as shown in Figures 8 and 9, the outer steel cheolbo 130 is connected between the outer steel pillars 120. The outer cheolgolbo 130 may be a conventional H-beam or steel-concrete composite beam is attached to the precast concrete member to the H-beam. In this example, a typical H-beam is shown.

상기 외곽 철골보(130)는 단부를 상기 외곽 철골 기둥(120)에 고력볼트 또는 용접에 의해 고정함으로써 연결될 수 있다. 필요한 경우에는 상기 외곽 철골 기 둥(120)에 연결 브라켓(미도시)을 추가로 설치하고 이것에 의해 상호 체결할 수도 있다.The outer steel cheolgolbo 130 may be connected by fixing the end to the outer steel frame pillar 120 by high-strength bolt or welding. If necessary, the outer steel frame pillar 120 may be further provided with a connecting bracket (not shown) and thereby mutually fastened.

바람직하게, 토압의 연속적인 전달과 구조적 밸런스를 위해 상기 흙막이 벽체(100)와 외곽 철골보(130) 사이의 이격 공간에는 채움재(128)로 메워진다. 이러한 채움재(128)는 콘크리트 또는 금속 소재로 이루어질 수 있다.Preferably, the space 128 between the retaining wall 100 and the outer cheolgolbo 130 is filled with a filler material 128 for the continuous transmission of the earth pressure and structural balance. The filler 128 may be made of a concrete or metal material.

또한, 도 7에도 나타나 있는 바와 같이, 상기 내부 철골 기둥(110)과 외곽 철골 기둥(120) 사이에는 내부 철골보(140)가 연결된다. 이러한 내부 철골보(140)의 상부에는 슬래브가 타설되므로 지하층의 시공 중에 흙막이 벽체(100)로부터 가해지는 토압을 지지하는 스트러트와 같은 역할을 하며 시공 후에는 영구 구조물로서 기능하게 된다.In addition, as shown in FIG. 7, the inner steel beams 140 are connected between the inner steel frame pillars 110 and the outer steel frame pillars 120. Since the slab is poured on the upper part of the internal cheolgolbo 140 serves as a strut to support the earth pressure applied from the earth wall 100 during the construction of the basement layer and functions as a permanent structure after construction.

상기 내부 철골보(140) 역시 통상적인 H형강 또는 철골-콘크리트 복합보로 구성될 수 있다. 물론, 내부 철골 기둥(110)과 내부 철골 기둥(110) 사이에도 내부 철골보(140)가 연결될 것이다.The inner cheolgolbo 140 may also be composed of a conventional H-beam or steel-concrete composite beam. Of course, the inner steel frame 140 will also be connected between the inner steel column 110 and the inner steel column (110).

상기 내부 철골보(140)는 그 단부를 철골 기둥(110)(120)에 고력볼트로 체결하거나 또는 용접함으로써 고정될 수 있으며, 바람직하게, 상기 외곽 철골 기둥(120) 또는 내부 철골 기둥(110)의 측면 플렌지에는 연결 브라켓(도 8의 132)이 돌출되도록 설치되어 있어서, 상기 연결 브라켓(132)에 형성된 체결공(134)을 상기 내부 철골보(140)의 단부에 형성된 결합공(136)과 일치시킨 후 체결볼트 및 너트로 고정시킬 수 있다.The inner steel beams 140 may be fixed by fastening or welding the ends of the inner steel frame (110, 120) with high-strength bolt, preferably, the outer steel frame (120) or the inner steel column (110) The side flange is installed so that the connecting bracket (132 of FIG. 8) is protruded, the matching hole 134 formed in the connecting bracket 132 and the coupling hole 136 formed at the end of the inner cheolgolbo 140 After fastening bolts and nuts can be fixed.

비록 본 명세서의 실시예에서는 철골 기둥과 철골보의 연결 방식을 구체적으 로 설명하였으나 본 발명은 그러한 실시예에 의해 한정되지 않으며, 그 외에도 당업계에 알려져 있는 다양한 방식에 의해 상호 연결될 수 있는 것으로 이해되어야 한다.Although embodiments of the present specification have been described in detail with respect to the connection method of the steel column and cheolgolbo, the present invention is not limited to such embodiments, it should be understood that can be interconnected by a variety of methods known in the art in addition to that do.

슬래브 시공Slab construction

이상과 같이, 철골보(130)(140)의 연결이 완료되면, 상기 철골보(130)(140) 위에 콘크리트를 타설하여 도 10에 도시된 바와 같이 지하 1층 슬래브(S1)를 축조한다.As described above, when the connection of the cheolgolbo 130, 140 is completed, the concrete is poured on the cheolgolbo 130, 140 to build a basement 1 floor slab (S1) as shown in FIG.

구체적으로, 상기 철골보(130)(140) 위에 데크 플레이트(미도시)를 거치하거나 또는 거푸집 구조체를 설치한 후, 슬래브 보강 철근(미도시)을 배근하고 콘크리트를 타설함으로써 슬래브(S1)를 축조할 수 있다.Specifically, after mounting the deck plate (not shown) on the cheolgolbo (130, 140) or install the formwork, the slab reinforcement (not shown) to reinforce the slab (S1) by pouring concrete to build the slab (S1) Can be.

바람직하게, 상기 슬래브(S1)는 외곽 철골 기둥(120)과 외곽 철골보(130)가 위치하는 부분을 제외한 나머지 부분에 대해서만(즉, 후술하는 지하 외벽의 시공 예정선까지) 형성된다.Preferably, the slab (S1) is formed only for the remaining portion (that is, up to the construction scheduled line of the basement outer wall to be described later) except for the portion where the outer steel column 120 and the outer steel column 130 is located.

하부층 연속 시공Lower floor continuous construction

상기와 같은 과정에 따라 지하 1층 슬래브(S1)가 완성되면, 추가적인 지하층의 구조물을 구축하기 위해서 전술한 공정을 반복적으로 되풀이한다.When the first basement slab S1 is completed according to the above process, the above-described process is repeated repeatedly to build an additional basement structure.

즉, 소정 깊이로 2차 터파기를 수행하고 노출된 외곽 철골 기둥(120)과 내부 철골 기둥(110)에 외곽 철골보(130) 및 내부 철골보(140)를 연결한다. 그런 다음, 철골보(130)(140)의 상면에 콘크리트를 타설하여 지하 2층 슬래브(S2)를 구축하게 된다.That is, the secondary demolition is performed to a predetermined depth and connects the outer steel steel beams 130 and the inner steel steel beams 140 to the exposed outer steel pillars 120 and the inner steel pillars 110. Then, by placing concrete on the upper surface of the cheolgolbo 130, 140 to build a two-story underground slab (S2).

이상과 같은 공정을 반복하여 시공 깊이까지 슬래브(S1)(S2)(S3)가 축조된 지하 구조물의 단면이 도 10에 도시되어 있다.10 is a cross-sectional view of the underground structure in which the slabs S1, S2, and S3 are constructed to the construction depth by repeating the above process.

전술한 바와 같이 건축물의 시공 깊이까지 지하 구조물의 슬래브(S1)(S2)(S3)와 바닥층(B)에 대한 시공이 완료되면, 도 11에 도시된 지하 외벽(150)을 바닥층(B)에서부터 지상까지 상방향으로 순타시공하게 된다. 이러한 지하 외벽(150) 시공과 함께 코아 옹벽, 기둥부의 SRC 시공 등을 병행한다.As described above, when the construction of the slab (S1), S2 (S3) and the bottom layer (B) of the underground structure to the construction depth of the building is completed, the basement outer wall 150 shown in Figure 11 from the bottom layer (B) It will be constructed smoothly upwards to the ground. Along with the construction of the underground outer wall 150, the core retaining wall, the SRC construction of the pillar portion, etc. are performed in parallel.

상기 지하 외벽(150) 시공시 외곽 철골 기둥(120)과 외곽 철골보(130)는 지하 외벽(150) 내에 매립되며, 앞서 설명한 바와 같이 각 층의 슬래브(S1)(S2)(S3)는 지하 외벽의 경계선까지만 선시공된 상태이므로 상기 지하 외벽(150)은 단절됨이 없이 지상까지 연속적으로 시공될 수 있다.When the underground outer wall 150 is constructed, the outer steel column 120 and the outer steel column 130 are buried in the underground outer wall 150, and as described above, the slab S1, S2, and S3 of each floor are underground outer walls. Since only the boundary line of the pre-installed state, the basement outer wall 150 can be continuously installed to the ground without being cut off.

본 발명은 아래 도면들에 의해 구체적으로 설명되지만, 이러한 도면은 본 발명의 바람직한 실시예를 나타낸 것이므로 본 발명의 기술사상이 그 도면에만 한정되어 해석되어서는 아니된다.Although the present invention will be described in detail with reference to the following drawings, these drawings illustrate preferred embodiments of the present invention, and the technical concept of the present invention is not limited to the drawings and should not be interpreted.

도 1a 및 도 1b는 종래 기술에 따른 지하 구조물 시공 방법을 설명하기 위한 일부 사시도 및 평면도이다.1A and 1B are a partial perspective view and a plan view for explaining a method for constructing an underground structure according to the prior art.

도 2는 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 흙막이 벽체를 구축한 상태를 보여주는 단면도이다.Figure 2 is a cross-sectional view showing a state in which the construction of the retaining wall in accordance with the construction method of the underground structure according to an embodiment of the present invention.

도 3은 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 내부 철골 기둥을 설치한 상태를 보여주는 단면도이다.3 is a cross-sectional view showing a state in which the internal steel pillars are installed in accordance with the method for constructing an underground structure according to a preferred embodiment of the present invention.

도 4는 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 철제 케이싱을 박은 상태를 보여주는 단면도이다.Figure 4 is a cross-sectional view showing a state in which the steel casing in accordance with the construction method of the underground structure according to a preferred embodiment of the present invention.

도 5는 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 철제 케이싱 내부에 외곽 철골 기둥을 설치한 상태를 보여주는 단면도이다.5 is a cross-sectional view showing a state in which the outer steel pillars are installed inside the steel casing according to the method for constructing an underground structure according to a preferred embodiment of the present invention.

도 6은 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 철제 케이싱 내부에 외곽 철골 기둥을 설치한 상태를 보여주는 평면도이다.6 is a plan view showing a state in which the outer steel pillars are installed inside the steel casing according to the method for constructing an underground structure according to a preferred embodiment of the present invention.

도 7은 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 기둥에 철골보를 연결하는 상태를 보여주는 단면도이다.Figure 7 is a cross-sectional view showing a state connecting the cheolgolbo to the pillar in accordance with the construction method for underground structures according to an embodiment of the present invention.

도 8는 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 외곽 철골 기둥에 외곽 철골보와 내부 철골보를 연결한 상태를 보여주는 단면도이다.8 is a cross-sectional view showing a state in which the outer cheolgolbo and the inner cheolgolbo connected to the outer steel frame pillar according to the method of construction of underground structures according to the preferred embodiment of the present invention.

도 9는 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 외곽 철골 기둥에 외곽 철골보와 내부 철골보를 연결한 상태를 보여주는 평면도이다.FIG. 9 is a plan view illustrating a state in which an outer steel frame beam and an inner steel frame beam are connected to an outer steel frame column according to a method for constructing an underground structure according to a preferred embodiment of the present invention.

도 10은 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 순차적으로 슬래브를 축조한 상태를 보여주는 단면도이다.10 is a cross-sectional view illustrating a state in which a slab is sequentially constructed according to the method for constructing an underground structure according to a preferred embodiment of the present invention.

도 11은는 본 발명의 바람직한 실시예에 따른 지하 구조물 시공 방법에 따라 지하 외벽을 시공하는 상태를 보여주는 단면도이다.11 is a cross-sectional view showing a state of constructing the basement outer wall according to the method for constructing an underground structure according to a preferred embodiment of the present invention.

<도면의 주요 참조번호에 대한 설명><Description of Major Reference Numbers in Drawing>

100: 흙막이 벽체 110: 내부 철골 기둥100: retaining wall 110: internal steel pillars

120: 외곽 철골 기둥 122: 철제 케이싱120: outer steel pillars 122: steel casing

128: 채움재 130: 외곽 철골보 128: Filler 130: Outer Cheolgolbo

140: 내부 철골보 150: 지하 외벽140: inner steel frame 150: underground outer wall

S1,S2,S3: 슬래브 B: 바닥층S1, S2, S3: Slab B: Bottom Layer

Claims (5)

지하 구조물의 경계선을 따라서 흙막이 벽체(100)를 구축하는 단계;Constructing a retaining wall 100 along a boundary line of the underground structure; 기둥이 설치되어야 할 위치에 내부 철골 기둥(110)을 설치하는 단계;Installing the internal steel column 110 at a location where the column should be installed; 상기 흙막이 벽체(100)의 내측에 외곽 철골 기둥(120)을 소정 간격으로 설치하는 단계;Installing the outer steel frame pillars 120 at predetermined intervals inside the earth wall 100; 1차 터파기를 수행하여 상기 흙막이 벽체(100)와 내부 철골 기둥(110) 및 외곽 철골 기둥(120)의 일부가 노출되도록 하는 단계;Performing a first digging to expose a portion of the retaining wall (100), the inner steel column (110), and the outer steel column (120); 상기 외곽 철골 기둥(120)들 사이에는 외곽 철골보(130)를 연결하는 단계;Connecting the outer cheolgolbo 130 between the outer steel pillars 120; 상기 내부 철골 기둥(110)과 외곽 철골 기둥(120) 사이 및 상기 내부 철골 기둥(110) 상호간의 사이에 내부 철골보(140)를 연결하는 단계;Connecting the inner steel beams 140 between the inner steel pillars 110 and the outer steel pillars 120 and between the inner steel pillars 110; 상기 외곽 철골 기둥(120)과 외곽 철골보(130)가 위치하는 부분을 제외한 나머지 부분의 철골보 위에 콘크리트를 타설하여 슬래브를 축조하는 단계;Constructing a slab by placing concrete on the steel gimbal of the remaining portion except for the portion where the outer steel pillar 120 and the outer steel gimbal 130 are located; 상기 단계들을 반복하여 지하 구조물의 시공 깊이까지 슬래브(S1)(S2)(S3)와 바닥층(B)을 축조하는 단계; 및 Repeating the above steps to build the slab (S1) (S2) (S3) and the bottom layer (B) to the construction depth of the underground structure; And 상기 바닥층(B)에서 지상까지 상방향으로 지하 외벽(150)을 연속적으로 시공하는 단계;를 포함하는 것을 특징으로 하는 지하 구조물 시공 방법.And constructing the basement outer wall 150 continuously from the bottom layer (B) upwards to the ground. 제1항에 있어서,The method of claim 1, 외곽 철골 기둥(120)이 설치될 간격으로 철제 케이싱(122)을 박아서 설치하는 단계;Driving the steel casing 122 at intervals at which the outer steel pillars 120 are installed; 상기 철제 케이싱(122)의 내부에 상기 외곽 철골 기둥(120)을 삽입하여 설치하는 단계; 및Inserting and installing the outer steel column (120) inside the steel casing (122); And 상기 철제 케이싱(122)을 빼내어 제거함으로써 상기 외곽 철골 기둥(120)의 일부가 노출되도록 하는 단계;를 포함하는 것을 특징으로 하는 지하 구조물 시공 방법. And removing the steel casing (122) to expose a portion of the outer steel column (120). 제2항에 있어서,3. The method of claim 2, 상기 외곽 철골 기둥(120)이 삽입된 철제 케이싱(122) 내부의 빈공간에는 모래나 흙(126)을 채우는 것을 특징으로 하는 지하 구조물 시공 방법.The construction method of the underground structure, characterized in that the empty space inside the steel casing 122, the outer steel pillars 120 is inserted to fill the sand or soil (126). 제2항에 있어서,3. The method of claim 2, 상기 외곽 철골 기둥(120)의 하단에는 제자리 콘크리트 말뚝(124)을 구축하는 것을 특징으로 하는 지하 구조물 시공 방법.Underground structure construction method, characterized in that to build the concrete pile 124 in place on the bottom of the outer steel pillars (120). 제2항에 있어서,3. The method of claim 2, 상기 흙막이 벽체(100)와 외곽 철골보(130) 사이의 이격 공간에는 채움재(128)로 메우는 것을 특징으로 하는 지하 구조물 시공 방법. The underground structure construction method, characterized in that the filling space (128) to fill the space between the earth wall and the outer cheolgolbo 130.
KR1020090035968A 2009-04-24 2009-04-24 Construction method of basement structure using retaining wall and steel column KR101077242B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090035968A KR101077242B1 (en) 2009-04-24 2009-04-24 Construction method of basement structure using retaining wall and steel column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090035968A KR101077242B1 (en) 2009-04-24 2009-04-24 Construction method of basement structure using retaining wall and steel column

Publications (2)

Publication Number Publication Date
KR20100117300A KR20100117300A (en) 2010-11-03
KR101077242B1 true KR101077242B1 (en) 2011-10-27

Family

ID=43403946

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090035968A KR101077242B1 (en) 2009-04-24 2009-04-24 Construction method of basement structure using retaining wall and steel column

Country Status (1)

Country Link
KR (1) KR101077242B1 (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102080221B1 (en) 2019-07-30 2020-02-21 (주)화성기초기술 Retaining structure for civil works and method of constructing it

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101296856B1 (en) * 2011-08-24 2013-08-14 주식회사 세진에스씨엠 Reinforcement structure for wall of underground structure and construction method of underground structure using the same

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR102080221B1 (en) 2019-07-30 2020-02-21 (주)화성기초기술 Retaining structure for civil works and method of constructing it

Also Published As

Publication number Publication date
KR20100117300A (en) 2010-11-03

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
JP2837128B2 (en) Construction method of cast-in-place concrete pile
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
KR100982827B1 (en) Construction method of basement exterior wall applying the floor slab as the strut against the earth pressure from the temporary earth wall = TSW(Thrusting slabbed wall) method
KR102286225B1 (en) Method for constructing underground structure busing PC integrating method without support
JP6543176B2 (en) Building method
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR20160000702A (en) Fastening member used in concrete filled steel tube and its using concrete filled steel tube mounting structure and method and its includes build underground structure and method
KR101296856B1 (en) Reinforcement structure for wall of underground structure and construction method of underground structure using the same
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
KR101077242B1 (en) Construction method of basement structure using retaining wall and steel column
JP5480744B2 (en) Foundation for structure and its construction method
KR20090043625A (en) Method for constructing underground slabs using asymmetric girder
KR20100118482A (en) To use reclamation steel perimeter beam and slab diaphragm effect in order for one side of the basement outer wall continuous construct was possible ,which the basement infrastructure construction method
JP2001329545A (en) Bridge pier foundation construction method and floor slab for bridge pier
JP7386095B2 (en) Underground structure construction method
KR20050113450A (en) Downward reinforced-concrete underground structure using temporary assistant columns
JP6938198B2 (en) Construction method
KR100722198B1 (en) Strut system of temporary retaining wall and subgrade external wall construction method utilizing the same
JP6534026B2 (en) Seismic isolation building and its construction method
KR102583537B1 (en) Top-down construction method for uneven-slope site
KR102426192B1 (en) File fof retaining wall and construction method using file
KR101971554B1 (en) Method constructuring an underground structure using a temporary structure
JP2012136841A (en) Method for excavating ground under spread foundation of existing building, and base-isolating method for existing building
KR20120032368A (en) Concrete structure and construction method for the same, constructing method of underground wall as a retaining structural wall used in the same

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
FPAY Annual fee payment

Payment date: 20141020

Year of fee payment: 4

FPAY Annual fee payment

Payment date: 20161018

Year of fee payment: 6

FPAY Annual fee payment

Payment date: 20171020

Year of fee payment: 7