KR20100094140A - Wall structure capable of earth retaining and the building method of the same - Google Patents

Wall structure capable of earth retaining and the building method of the same Download PDF

Info

Publication number
KR20100094140A
KR20100094140A KR1020090013428A KR20090013428A KR20100094140A KR 20100094140 A KR20100094140 A KR 20100094140A KR 1020090013428 A KR1020090013428 A KR 1020090013428A KR 20090013428 A KR20090013428 A KR 20090013428A KR 20100094140 A KR20100094140 A KR 20100094140A
Authority
KR
South Korea
Prior art keywords
building
building wall
ground
support
wall structure
Prior art date
Application number
KR1020090013428A
Other languages
Korean (ko)
Inventor
조용량
Original Assignee
케이앤씨컨설턴트 주식회사
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 케이앤씨컨설턴트 주식회사 filed Critical 케이앤씨컨설턴트 주식회사
Priority to KR1020090013428A priority Critical patent/KR20100094140A/en
Publication of KR20100094140A publication Critical patent/KR20100094140A/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2220/00Temporary installations or constructions
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0076Drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0075Textiles
    • E02D2300/0076Textiles non-woven

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

PURPOSE: A building wall structure and a construction method thereof are provided to increase the rigidity of a building wall structure and stability of a building and to reduce construction costs and times by simultaneously installing a sheathing structure and constructing the building wall structure. CONSTITUTION: A building wall structure comprises multiple support columns(40), a building wall(100), building beams(200,200',200"), and building slabs(300,300',300"). The support column is installed in the hole of a site boundary at fixed intervals and supports rear soil. The building wall is installed in the support column. The building wall forms the wall with the support column. The building beam and the building slab are integrated with the building wall.

Description

건물벽 구조체 및 그 시공 방법{WALL STRUCTURE CAPABLE OF EARTH RETAINING AND THE BUILDING METHOD OF THE SAME}WALL STRUCTURE CAPABLE OF EARTH RETAINING AND THE BUILDING METHOD OF THE SAME}

본 발명은 건물벽 구조체 및 그 시공 방법에 관한 것으로서, 건물 시공시 흙막이 공사와 더불어 건물벽을 동시에 시공할 수 있는 획기적인 흙막이 겸용 건물벽 구조체 및 그 시공 방법에 관한 것이다.The present invention relates to a building wall structure and a construction method thereof, and to a groundbreaking building wall structure and a construction method capable of constructing a building wall simultaneously with a construction of a wall at the time of building construction.

종래의 흙막이 공사에서는 인접대지를 침범하여 앵커나 스트러트로 흙막이 구조물을 지지하게 되고, 특히 경사가 급하고 부지 여유가 없는 절개지에 부지를 조성하고 흙막이 구조물을 시공하고자 할 때에는 흙막이용 가시설물이 필요하게 된다.In the conventional earthen construction, it is necessary to support the earthen structure with anchors or struts by invading adjacent lands, and in particular, when constructing a site at an incline where there is a steep slope and lacking a lot of space, and constructing the earthen structure, a temporary earthenware is required. do.

이때, 상기와 같은 가시설물을 설치하여 토사를 굴착한 후 영구 건물벽을 설치하고, 비로소 흙막이용 가시설물을 해체하게 되는데, 가시설물의 설치와 해체로 인해 공사기간이 증가되고, 인접 대지로 인해 시공성이 저하되며, 영구 건물벽 공사비와는 별도로 가시설물의 공사비가 소요되는 문제점이 있었다.At this time, the excavation of the earth and sand after installing the temporary equipment, and then install the permanent building wall, and finally to dismantle the temporary equipment for the earthquake, construction period is increased due to the installation and dismantling of the temporary equipment, construction properties due to the adjacent land This deterioration, there was a problem in that the construction cost of the temporary building wall separately from the construction cost of the permanent building.

또한, 흙막이용 영구 건물벽을 설치 완료하면 흙막이용 가시설물을 해체하는 것은 물론, 건물 축조시 상기 영구 건물벽과 별도로 건물벽 구조체를 축조하게 되므로 이중 삼중의 공사비와 공사 기간이 소요되는 문제점이 있었다.In addition, when the installation of the permanent wall for the earthquake is completed, as well as dismantling the temporary wall for the earthquake, as well as building the building wall structure separately from the permanent building wall when building the building, there was a problem of double triple construction cost and construction period. .

건설 자재비의 상승으로 건설 공사비의 부담이 커지는 현실을 감안하면 건설 공사비의 절감과 공사 효율을 안정적으로 높일 수 있는 획기적으로 간소화된 흙막이 겸용 건물벽 구조체 및 그 시공 방법의 개발이 절실한 실정이다.Considering the fact that the burden of construction cost increases due to the increase of construction materials cost, it is urgently needed to develop a dramatically simplified building wall structure and construction method that can reduce construction cost and stably increase construction efficiency.

본 발명의 목적은 상술한 문제점을 개선하기 위한 것으로서 종래의 흙막이용 가시설물 및 흙막이용 건물벽 구조체를 별도로 설치할 필요없이 지반에 삽입되는 지지 기둥 그 자체로서 건물벽 구조체의 기본 골조가 되게 함으로써 건물벽 구조체의 강도가 지지 기둥에 의하여 보강됨은 물론 건물벽 구조체의 타설 두께를 줄일 수 있고, 흙막이 구조물의 설치와 동시에 건물벽 구조체의 형성이 가능하므로 공사비 및 공사 기간이 획기적으로 절감되며, 지지 기둥으로서 기성품 말뚝을 사용하므로 지지 기둥의 강도를 일정하게 규격화할 수 있어 건물벽 구조체의 강성 증가는 물론 건물의 안정성 증가에 크게 이바지할 수 있는 흙막이 겸용 건물벽 구조체 및 그 시공 방법을 제공하는 것이다.It is an object of the present invention to improve the above-mentioned problems, the building wall by making the basic frame of the building wall structure itself as a support column inserted into the ground without the need to separately install the conventional walling fixture and the building wall structure for the wall The strength of the structure is not only reinforced by the supporting column, but also the thickness of the building wall structure can be reduced, and the building wall structure can be formed at the same time as the installation of the retaining structure, thereby significantly reducing the construction cost and construction period, and making the ready-made product as the supporting column. The use of piles allows constant standardization of the strength of the support columns to provide an earthquake combined building wall structure and construction method which can contribute to the increase of the rigidity of the building wall structure as well as the stability of the building.

본 발명이 이루고자 하는 기술적 과제는 이상에서 언급한 기술적 과제로 제한되지 않으며 언급되지 않은 또 다른 기술적 과제들은 아래의 기재로부터 본 발명이 속하는 기술분야에서 통상의 지식을 가진 자에게 명확하게 이해될 수 있을 것이다.The technical problem to be achieved by the present invention is not limited to the technical problem mentioned above, and other technical problems not mentioned above may be clearly understood by those skilled in the art from the following description. will be.

상술한 목적을 달성하기 위하여 본 발명의 건물벽 구조체는, 건물이 신축될 건물 지반과 상기 건물 지반에 인접한 주변 지반의 부지 경계에 구멍을 천공한 다음 상기 구멍에 삽입 고정됨으로써 외주의 일측이 상기 주변 지반을 지지하는 복수 의 지지 기둥; 상기 지지 기둥에 연결되어 상기 주변 지반의 흙막이 및 상기 건물의 측벽을 겸하는 건물벽; 상기 건물벽과 일체로 연결되는 건물보 및 건물슬래브; 를 포함하는 것을 특징으로 한다.In order to achieve the above object, the building wall structure of the present invention is formed by drilling a hole in the site boundary of the building ground on which the building is to be constructed and the surrounding ground adjacent to the building ground, and then inserting the hole into one side of the outer circumference. A plurality of support columns supporting the ground; A building wall connected to the support column to serve as a soil barrier of the surrounding ground and a side wall of the building; A building beam and a building slab integrally connected with the building wall; Characterized in that it comprises a.

일 실시예로서, 상기 건물벽은, 상기 지지 기둥이 삽입 고정된 다음 상기 건물 지반을 굴착하여 상기 지지 기둥의 외주의 타측을 노출시키고 상기 지지 기둥들 사이에 철근 및 콘크리트를 타설함으로써 축조된다.In one embodiment, the building wall is constructed by inserting and fixing the support pillar to excavate the building ground to expose the other side of the outer circumference of the support pillar and to cast rebar and concrete between the support pillars.

일 실시예로서, 상기 건물벽, 상기 건물보 및 상기 건물슬래브는 상기 건물 지반의 굴착 깊이가 증가됨에 따라 상기 지지 기둥의 상측부터 하측의 순서로 축조되면서 다층 구조를 이룬다. In one embodiment, the building wall, the building beam and the building slab is built in a multi-layered structure in the order from the upper side to the lower side of the support column as the excavation depth of the building ground increases.

일 실시예로서, 상기 건물벽 구조체는, 상기 지지 기둥과 수직으로 연장되어 상기 지지 기둥들의 상단부를 서로 연결하는 캡 빔; 을 더 포함한다.In one embodiment, the building wall structure, the cap beam extending perpendicular to the support pillar to connect the upper ends of the support pillars to each other; It includes more.

일 실시예로서, 상기 건물벽 구조체는, 상기 건물벽에 매설되는 앵커 빔; 일단부는 상기 앵커 빔에 고정되고 타단부는 상기 주변 지반에 묻힘으로써 상기 건물벽을 인장하여 지지하는 앵커; 를 더 포함한다.In one embodiment, the building wall structure, the anchor beam embedded in the building wall; An anchor fixed at one end to the anchor beam and at the other end to be buried in the surrounding ground to tension and support the building wall; It further includes.

일 실시예로서, 상기 건물벽 구조체는, 상기 지지 기둥들 사이의 이격 공간에 설치되는 배수관; 상기 배수관을 감싸는 부직포; 를 더 포함한다.In one embodiment, the building wall structure, the drain pipe is installed in the spaced space between the support pillars; Non-woven fabric surrounding the drain pipe; It further includes.

한편, 본 발명의 건물벽 구조체의 시공 방법은, 건물이 신축될 건물 지반과 상기 건물 지반에 인접한 주변 지반의 부지 경계에 구멍을 천공하는 단계; 미리 준비된 지지 기둥을 상기 구멍에 삽입 고정하는 단계; 삽입 고정된 상기 지지 기둥의 외주의 일측이 상기 주변 지반을 지지할 때, 상기 건물 지반을 굴착하여 상기 지지 기둥의 외주의 타측을 노출시키는 단계; 상기 지지 기둥과 일체로 연결되도록 상기 건물의 건물벽, 건물보 및 건물슬래브를 축조하는 단계; 를 포함하는 것을 특징으로 한다.On the other hand, the construction method of the building wall structure of the present invention comprises the steps of: drilling a hole in the site boundary of the building ground on which the building is to be built and the surrounding ground adjacent to the building ground; Inserting and fixing a supporting pillar prepared in advance into the hole; When one side of the outer circumference of the support pillar which is inserted and fixed supports the surrounding ground, excavating the building ground to expose the other side of the outer circumference of the support pillar; Constructing a building wall, a building beam, and a building slab of the building to be integrally connected with the support pillar; Characterized in that it comprises a.

일 실시예로서, 상기 건물벽, 건물보 및 건물슬래브는, 상기 건물 지반을 굴착하여 상기 지지 기둥의 외주의 타측을 노출시킨 다음 상기 지지 기둥들 사이에 철근 및 콘크리트를 타설함으로써 축조되고, 상기 건물 지반의 굴착 깊이가 증가됨에 따라 상기 지지 기둥의 상측부터 하측의 순서로 축조되면서 다층 구조를 이룬다.In one embodiment, the building wall, building beam and building slab is constructed by excavating the building ground to expose the other side of the outer circumference of the support column and then placing reinforcing steel and concrete between the support columns, and building As the excavation depth of the ground increases, it is constructed in the order from the upper side to the lower side of the support column to form a multilayer structure.

일 실시예로서, 상기 건물벽 구조체의 시공 방법은, 상기 지지 기둥을 상기 구멍에 삽입 고정한 후, 상기 지지 기둥과 수직으로 연장되어 상기 지지 기둥들의 상단부를 서로 연결하는 캡 빔을 설치하는 단계; 를 더 포함한다.In one embodiment, the construction method of the building wall structure, after inserting and fixing the support pillar in the hole, and extending perpendicular to the support pillar to install a cap beam connecting the upper ends of the support pillars to each other; It further includes.

일 실시예로서, 상기 건물벽 구조체의 시공 방법은, 상기 건물벽, 건물보 및 건물슬래브를 축조한 후, 상기 건물벽에 앵커 빔을 매설하고, 상기 건물벽을 인장 지지하는 앵커의 양단부를 상기 앵커 빔 및 상기 주변 지반에 각각 고정하는 단계; 를 더 포함한다. In one embodiment, the construction method of the building wall structure, after building the building wall, building beams and building slab, the anchor beam is embedded in the building wall, and both ends of the anchor for tension-supporting the building wall Fixing to anchor beams and the surrounding ground respectively; It further includes.

본 발명에 따르면, 종래의 흙막이용 가시설물 및 흙막이용 건물벽 구조체를 별도로 설치할 필요없이 흙막이 구조물인 지지 기둥 및 그 사이에 타설된 콘크리트 그 자체가 건물벽 구조체로 형성되므로 공사비 및 공사 기간이 획기적으로 절감되 고, 지반에 삽입되는 지지 기둥 그 자체가 건물벽 구조체의 기본 골조가 되므로 지지 기둥의에 의하여 건물벽 구조체의 강도가 보강됨은 물론 건물벽 구조체의 타설 두께를 줄일 수 있고, 지지 기둥으로서 기성품 말뚝을 사용하므로 지지 기둥의 강도를 일정하게 규격화할 수 있어 건물의 품질 수준 및 안정성 증가에 크게 이바지할 수 있는 장점이 있다. According to the present invention, the construction cost and construction period is remarkably innovative because the support pillars and the concrete cast between them are formed as the building wall structures without the need for installing the conventional temporary wall fixtures and the building wall structures for the wall blocks separately. Since the supporting pillar itself inserted into the ground becomes the basic frame of the building wall structure, the strength of the building wall structure is reinforced by the supporting pillar, and the thickness of the building wall structure can be reduced, and the ready-made product as the supporting column Since the pile is used, the strength of the support columns can be regularly standardized, which greatly contributes to increasing the quality level and stability of the building.

이하, 첨부된 도면들을 참조하여 본 발명에 따른 실시예를 상세히 설명한다. 이 과정에서 도면에 도시된 구성요소의 크기나 형상 등은 설명의 명료성과 편의상 과장되게 도시될 수 있다. 또한, 본 발명의 구성 및 작용을 고려하여 특별히 정의된 용어들은 사용자, 운용자의 의도 또는 관례에 따라 달라질 수 있다. 이러한 용어들에 대한 정의는 본 명세서 전반에 걸친 내용을 토대로 내려져야 한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings. In this process, the size or shape of the components shown in the drawings may be exaggerated for clarity and convenience of description. In addition, terms that are specifically defined in consideration of the configuration and operation of the present invention may vary depending on the intention or custom of the user or operator. Definitions of these terms should be made based on the contents throughout the specification.

도 1 내지 도 10은 본 발명의 흙막이 겸용 건물벽 구조체의 시공 방법을 순차적으로 도시한 측단면도이다. 도 1 내지 도 10을 함께 참조하며 본 발명의 흙막이 겸용 건물벽 구조체의 구성 및 작용을 설명하고 그 시공 방법을 순차적으로 설명한다.1 to 10 is a side cross-sectional view sequentially showing a construction method of a building wall structure combined with a wall of the present invention. With reference to Figures 1 to 10 will be described the structure and operation of the combined-use building wall structure of the present invention and the construction method will be described sequentially.

본 발명의 건물벽 구조체는 복수의 지지 기둥(40)과, 건물벽(100), 건물보(200, 200´, 200˝), 건물슬래브(300, 300´, 300˝)를 포함한다. 이때, 건물벽 구조체는 캡 빔(50), 앵커 빔(91), 앵커(63), 배수관(미도시), 부직포(미도시)를 더 포함할 수 있다.The building wall structure of the present invention includes a plurality of support pillars 40, building walls 100, building beams 200, 200 ', 200', and building slabs 300, 300 ', 300'. In this case, the building wall structure may further include a cap beam 50, an anchor beam 91, an anchor 63, a drain pipe (not shown), and a nonwoven fabric (not shown).

건물의 신축이 예정된 지반은 건물이 신축될 건물 지반(10)과 기존 건물이나 도로가 이미 축조되어 있는 주변 지반(10´)으로 구획된다. 이러한 건물 지반(10)과 주변 지반(10´)은 부지 경계를 기준으로 구획된다. 일반적으로 건물의 신축시 공사에 따른 분진이나 소음을 차단하기 위하여 부지 경계에 인접하여 부지 경계벽(1)이 마련된다.The ground on which the new construction is scheduled is divided into the building ground 10 on which the building is to be constructed and the surrounding ground 10 'on which an existing building or road is already constructed. The building ground 10 and the surrounding ground 10 'are partitioned based on the site boundary. In general, the site boundary wall (1) is provided adjacent to the site boundary in order to block dust or noise due to the construction of the building.

건물 지반(10)과 주변 지반(10´)의 부지 경계에 굴착/삽입 장비(31)가 안착될 수 있도록 지반을 정리한 후 굴착/삽입 장비(31)를 이용하여 구멍(30)을 천공하고, 이 구멍(30)에 지지 기둥(40)을 삽입 고정한다. 구멍(30)의 천공 깊이는 건물의 축조 높이 및 지하 시설이 될 본 발명의 건물벽 구조체의 축조 높이에 비례하여 결정된다.After arranging the ground so that the excavation / insertion equipment 31 can be seated at the site boundary between the building ground 10 and the surrounding ground 10 ', and then drill the holes 30 using the excavation / insertion equipment 31. The support column 40 is inserted into this hole 30 and fixed. The perforation depth of the hole 30 is determined in proportion to the building height of the building and the building height of the building wall structure of the present invention to be the underground facility.

지지 기둥(40)은 중공의 원기둥 형상으로서 콘크리트를 이용하여 미리 완제품으로 제조된다. 이러한 지지 기둥(40)은 작업 현장에 원하는 개수만큼 공급되어 사용된다. 지지 기둥(40)은 부지 경계의 구멍(30)에 소정 간격으로 이격 설치되며 원기둥의 외주의 배면은 배면 토사를 지지하여 흙막이용 지주로서 역할을 하게 되고, 원기둥의 외주의 정면은 건물벽(100)의 형성 공간이 된다.The support column 40 is manufactured in advance as a finished product using concrete as a hollow cylindrical shape. The support pillar 40 is used to supply the desired number to the work site. The support column 40 is spaced apart at predetermined intervals in the hole 30 of the site boundary, and the back of the outer circumference of the cylinder supports the earth and sand, and serves as a retaining pillar, and the front of the column is the building wall 100. ) To form a space.

종래에는 건물 지반을 굴착한 다음 흙막이용 가시설물 공사 후 건물의 본 구조물을 축조하였으므로 공사비 및 공사 기간이 낭비되는 단점이 있었지만, 본 발명에서는 흙막이 구조물의 설치가 지지 기둥(40)과 같은 영구 시설물에 의하므로 공사비 및 공사 기간의 절감에 매우 유리하다. Conventionally, after excavating the ground of the building and constructing the main structure of the building after the construction of the temporary wall equipment, there was a disadvantage in that the construction cost and construction period was wasted, but in the present invention, the installation of the wall structure to the permanent facility such as the support column 40 Therefore, it is very advantageous to reduce construction cost and construction period.

또한, 지지 기둥(40)은 건물의 시공 시점과 상관없이 미리 제작된 기성 말뚝 이므로 시공 과정이 복잡하지 않고 자재 조달 시간, 시공 기간 및 시공비 단축에 매우 효과적이다. In addition, since the support pillar 40 is a ready-made pile regardless of the construction time of the building, the construction process is not complicated and is very effective in shortening the material procurement time, construction period and construction cost.

도 1 내지 도 4와 같이 지지 기둥(40)의 삽입 고정이 완료되면, 지지 기둥(40)들의 상단부에 캡 빔(50)을 설치함으로써 지지 기둥(40)의 하중 지지력을 보강한다. 도 5 및 도 6 을 참조하면, 캡 빔(50), 건물벽(100), 건물보(200), 건물슬래브(300)의 설치 상태가 도시된다.When the insertion fixing of the support pillar 40 is completed as shown in FIGS. 1 to 4, the cap beam 50 is installed on the upper ends of the support pillars 40 to reinforce the load bearing force of the support pillar 40. 5 and 6, the installation state of the cap beam 50, the building wall 100, the building beam 200, the building slab 300 is shown.

지지 기둥(40)의 삽입 고정이 완료된 후, 캡 빔(50), 건물벽(100), 건물보(200), 건물슬래브(300)를 설치한다. 지지 기둥(40)은 구멍(30)에 삽입됨으로써 단단히 고정되지만 그 상측 선단부가 자유단이면 하중 지지력이 떨어질 수 있다. 따라서, 이를 보강하기 위한 보강 부재가 지지 기둥(40)의 선단부에 마련되는 것이 바람직하다. After the insertion fixing of the support column 40 is completed, the cap beam 50, the building wall 100, the building beam 200, the building slab 300 is installed. The support pillar 40 is firmly fixed by being inserted into the hole 30, but if the upper end thereof is a free end, the load bearing force may be reduced. Therefore, it is preferable that a reinforcing member for reinforcing them is provided at the tip portion of the support pillar 40.

예를 들어 'H' 형상의 빔 또는 'ㄷ' 형상의 빔으로 된 캡 빔(50)을 보강 부재로서 설치한다. 캡 빔(50)은 지지 기둥(40)과 수직으로 연장되어 지지 기둥(40)들의 상단부를 서로 연결함으로써 지지 기둥(40)의 하중 지지력을 보강한다.For example, the cap beam 50 which consists of a beam of "H" shape or a beam of "c" shape is installed as a reinforcement member. The cap beam 50 extends perpendicular to the support pillar 40 to reinforce the load bearing force of the support pillar 40 by connecting the upper ends of the support pillars 40 to each other.

건물벽(100)은 지지 기둥(40)에 설치된 벽체를 일컫는다. 즉, 지지 기둥(40)들 사이의 이격 구간 및 지지 기둥(40)의 노출면에 철근(93)을 배열하고 여기에 콘크리트를 타설함으로써 지지 기둥(40)과 함께 벽체를 형성한 것이 건물벽(100)이다. 건물벽(100)의 강성 보강을 위하여 스터드 볼트(92) 및 철근(93)이 콘크리트와 함께 시공되는 것이 바람직하다. The building wall 100 refers to a wall installed in the support column 40. That is, by arranging the reinforcement 93 on the spaced intervals between the support columns 40 and the exposed surface of the support columns 40 and placing concrete thereon, the walls are formed together with the support columns 40 by building walls ( 100). In order to reinforce the rigidity of the building wall 100, it is preferable that the stud bolt 92 and the reinforcement 93 are constructed together with the concrete.

건물벽(100)은 주변 지반(10´) 측의 배면 토사가 지지 기둥(40)들 사이로 누설되는 것을 방지하는 한편 지지 기둥(40)들을 서로 결합시킴으로써 배면 토사의 하중 지지력을 보강하는 흙막이로서의 기능과, 건물의 측벽으로서의 기능을 동시에 하게 되므로 공사비 및 공사 기간 절감에 대단히 효과적이다. The building wall 100 functions as an earth barrier to reinforce the load bearing capacity of the rear soil by preventing the back soil from the surrounding ground 10 ′ from leaking between the support pillars 40, while joining the support pillars 40 with each other. And at the same time function as a side wall of the building is very effective in reducing construction costs and construction period.

건물벽(100), 건물보(200), 건물슬래브(300) 중 적어도 하나는, 지지 기둥(40)이 삽입 고정된 다음 건물 지반(10)을 굴착하여 지지 기둥(40)의 외주의 타측을 노출시키고 지지 기둥(40)들 사이에 철근(93) 및 콘크리트를 타설함으로써 축조된다. At least one of the building wall 100, the building beam 200, and the building slab 300 is inserted into and fixed to the support pillar 40, and then excavates the ground of the building 10 so that the other side of the support pillar 40 is formed. It is constructed by exposing and placing reinforcement 93 and concrete between the support pillars 40.

한편, 도 5 및 도 6에는 건물보(200)와 건물슬래브(300)를 먼저 형성한 다음, 도 6과 같이 건물 지반(10)을 더욱 굴착하고 건물벽(100)을 이미 형성된 건물보(200)와 건물슬래브(300)에 연결하여 축조하는 실시예가 도시된다. Meanwhile, in FIGS. 5 and 6, the building beam 200 and the building slab 300 are first formed, and then, as shown in FIG. 6, the building ground 10 is further excavated, and the building beam 200 has already formed the building wall 100. And building slab 300 is shown.

그러나 도시되지 않은 실시예로서, 도 6에 도시된 정도의 깊이로 건물 지반(10)을 먼저 굴착하고, 건물벽(100), 건물보(200), 건물슬래브(300)를 함께 시공하면서 단계적으로 시공 깊이를 늘려가거나, 건물벽(100)을 먼저 시공하고 건물보(200) 및 건물슬래브(300)는 이어서 시공하면서 시공 깊이를 늘려가는 실시예도 가능하다.However, as an embodiment not shown, the ground of the building 10 is first excavated to a depth as shown in FIG. 6, and the building walls 100, the building beams 200, and the building slabs 300 are constructed step by step. It is also possible to increase the construction depth or to increase the construction depth while constructing the building wall 100 first and the building beam 200 and the building slab 300 subsequently.

도 7 내지 도 10을 참조하면, 본 발명은 건물벽(100), 건물보(200, 200´, 200˝) 및 건물슬래브(300, 300´, 300˝)의 축조시, 건물 지반(10)의 굴착 깊이가 증가됨에 따라 지지 기둥(40)의 상측부터 하측의 순서로 축조되면서 다층 구조를 이룬다. 이를 '톱 다운 공법(top down method)'으로 부르기로 한다. 7 to 10, the present invention is the building wall 100, building beams (200, 200 ', 200´) and building slab (300, 300', 300˝) when building, building ground (10) As the excavation depth of the increase in the order from the upper side to the lower side of the support pillar 40 to form a multi-layer structure. This is called the 'top down method'.

톱 다운 공법에 따르면 공사 방법이 간단하고 흙막이용 가시설물 또는 흙막 이용 영구 시설물을 별도로 설치할 필요없이 건물 측벽과 흙막이용 시설물을 겸하는 건물벽 구조체를 일시에 시공하게 되므로 공법이 대폭 간소화된다.According to the top-down method, the construction method is simple, and the construction method is greatly simplified because the building wall structure, which combines the building sidewall and the mudstone facility, is temporarily constructed without the need for installing a temporary wall fixture or a permanent facility using the mud wall.

한편, 지지 기둥(40)을 포함한 건물벽 구조체는 자립식 구조물이므로 설치 높이가 제한될 수 있다. 이러한 문제점은 영구 지지 수단을 설치하여 건물벽(100)의 휨(bending) 하중 지지력, 좌굴(toggle) 하중 지지력, 인장 하중 지지력을 증강시킴으로써 해결될 수 있는 바, 본 발명에서는 영구 지지 수단으로서 소일 네일(미도시) 또는 앵커(63)를 설치한다. On the other hand, the building wall structure including the support column 40 is a self-supporting structure, the installation height may be limited. This problem can be solved by installing a permanent support means to increase the bending load bearing capacity, buckling load bearing capacity, tensile load bearing capacity of the building wall 100, in the present invention, nail nail as a permanent support means (Not shown) or anchor 63 is provided.

이러한 영구 지지 수단의 일 실시예로서, 건물벽(100)에 매설되는 앵커 빔(91)과, 앵커 빔(91)에 고정되는 앵커(63)가 있다. 앵커 빔(91)은 'H' 형상의 빔 또는 'ㄷ' 형상의 빔으로서 건물벽(100)을 형성하는 콘크리트에 매설된다. 앵커(63)는 그 일단부가 앵커 빔(91)에 고정되고 그 타단부는 주변 지반(10´)에 묻혀 고정됨으로써 건물벽(100)을 주변 지반(10´) 방향으로 끌어당겨 지지하며, 이에 따라 지지 기둥(40) 및 건물벽(100)의 붕괴가 방지된다. 앵커(63)와 더불어 소일 네일(미도시)이 설치될 수도 있다. One embodiment of such a permanent support means is an anchor beam 91 embedded in the building wall 100 and an anchor 63 fixed to the anchor beam 91. The anchor beam 91 is embedded in the concrete forming the building wall 100 as a 'H' shaped beam or a 'c' shaped beam. One end of the anchor 63 is fixed to the anchor beam 91 and the other end is buried and fixed to the surrounding ground 10 ', thereby attracting and supporting the building wall 100 toward the surrounding ground 10'. Accordingly, the collapse of the support column 40 and the building wall 100 is prevented. Soil nail (not shown) may be installed together with the anchor 63.

이러한 영구 지지 수단에 의하여 하중 지지력이 더욱 보강되면, 건물의 지하 시설물이 될 건물벽(100), 건물보(200, 200´, 200˝), 건물슬래브(300, 300´, 300˝)를 원하는 깊이로 설치하더라도 하중 지지력에 관한 염려를 더 이상 하지 않아도 되므로 건물벽(100), 건물보(200, 200´, 200˝), 건물슬래브(300, 300´, 300˝)를 예를 들어 지하 1층 및 지하 2층을 포함한 다층 구조로 매우 간편하게 형성할 수 있다.If the load bearing capacity is further reinforced by such a permanent support means, the building walls 100, the beams 200, 200 ', 200˝, and the building slabs 300, 300', 300 될, which will be the underground facilities of the building, are desired. Even if the depth of installation is no longer concerned about the load bearing capacity, the building wall 100, building beams (200, 200 ', 200˝), building slabs (300, 300', 300˝), for example, underground 1 It can be formed very simply in a multi-layer structure including a layer and two underground levels.

이와 같이 구멍(30)에 삽입되는 구조로 인한 강력한 하중 지지 구조를 갖는 지지 기둥(40) 및 이를 보충하는 영구 지지 수단이 마련됨으로써, 건물벽(100)의 축조 두께를 줄일 수 있는 장점도 있다. 즉, 지지 기둥(40)에 연결되지 않는 일반 적인 단순 구조의 건물벽에 비하여 지반에 고정 설치되는 지지 기둥(40) 또는 영구 지지 수단에 연결되어 하중 지지력이 한층 보강된 본 발명의 건물벽(100)은 훨씬 얇은 두께로 축조되더라도 건물의 안정성을 동일하게 유지할 수 있고 이에 따라 공사비 및 공사 기간을 크게 절감할 수 있는 장점이 있다. As such, the support pillar 40 having the strong load supporting structure and the permanent supporting means supplementing the same are provided by the structure inserted into the hole 30, thereby reducing the construction thickness of the building wall 100. That is, the building wall 100 of the present invention is connected to the support pillar 40 fixed to the ground or permanent support means is further reinforced with a load bearing force than the building wall of the general simple structure that is not connected to the support pillar 40 ) Can maintain the stability of the building even if it is constructed to a much thinner thickness, which has the advantage of greatly reducing the construction cost and construction period.

특히 경사가 급하고 부지 여유가 없는 절개지에 콤팩트한 공간에 충분한 강도로 건물을 축조할 수 있게 된다. In particular, it is possible to build a building with sufficient strength in a compact space in an incline with a steep slope and lack of site space.

또한, 도시되지 않은 실시예로서, 건물벽(100)의 시공시 배면 토사의 물빠짐을 좋게 하기 위하여 배수관이 설치되는 것이 바람직하다. 배수관은 지지 기둥(40)의 이격 구간에 소정 간격으로 배치되며, 토사는 유출되지 않고 물 빠짐만 이루어질 수 있도록 부직포와 함께 시공되는 것이 바람직하다. 즉, 부직포는 배수관을 감싸서 물만 배출되도록 하고 토사의 누설은 억제한다. In addition, as an embodiment not shown, it is preferable that a drain pipe is installed in order to improve the drainage of the back earth and sand during construction of the building wall 100. The drain pipe is disposed at a predetermined interval in the interval of the support pillar 40, it is preferable that the earth and sand is constructed with a non-woven fabric so that only water is drained out. In other words, the non-woven fabric wraps the drain pipe so that only water is discharged and the leakage of soil is suppressed.

한편, 본 발명의 건물벽 구조체의 시공 방법을 정리하면 다음과 같다. On the other hand, the construction method of the building wall structure of the present invention is summarized as follows.

먼저, 건물이 신축될 건물 지반(10)과 상기 건물 지반(10)에 인접한 주변 지반(10´)의 부지 경계에 구멍(30)을 천공한다. 미리 준비된 지지 기둥(40)을 구멍(30)에 삽입 고정한다. 삽입 고정된 지지 기둥(40)의 외주의 일측이 주변 지반(10´)의 토사를 지지하는 흙막이 기능을 할 수 있게 되었으므로, 건물 지반(10)을 굴착하여 지지 기둥(40)의 외주의 타측을 노출시킨다. 다음으로, 지지 기둥(40) 과 일체로 연결되도록 건물벽(100), 건물보(200, 200´, 200˝) 및 건물슬래브(300, 300´, 300˝)를 축조하여 건물을 완성한다.First, the hole 30 is drilled in the site boundary of the building ground 10 to which the building is to be constructed and the surrounding ground 10 'adjacent to the building ground 10. The support pillar 40 prepared in advance is fixed to the hole 30. Since one side of the outer circumference of the inserted and fixed support column 40 can function as a soil support for supporting the soil of the surrounding ground 10 ', the ground of the building 10 is excavated and the other side of the outer circumference of the support column 40 is fixed. Expose Next, the building walls 100, building beams 200, 200 ', 200' and building slabs 300, 300 ', 300' are constructed so as to be integrally connected with the support column 40 to complete the building.

여기서, 건물벽(100), 건물보(200, 200´, 200˝) 및 건물슬래브(300, 300´, 300˝)는, 건물 지반(10)을 굴착하여 지지 기둥(40)의 외주의 타측을 노출시킨 후 지지 기둥(40)들 사이에 철근(93) 및 콘크리트를 타설함으로써 축조되고, 건물 지반(10)의 굴착 깊이가 증가됨에 따라 지지 기둥(40)의 상측부터 하측의 순서로 축조되면서 다층 구조를 이루게 할 수 있다.Here, the building wall 100, the building beams 200, 200 ′, 200 및 and the building slabs 300, 300 ′, 300 ˝ excavate the building ground 10 to the other side of the outer circumference of the support column 40. After exposing the reinforcement 93 and concrete between the support pillars 40 is constructed, and as the excavation depth of the building ground 10 is increased in order from the upper side to the lower side of the support column 40 It can make a multilayered structure.

또한, 지지 기둥(40)을 구멍(30)에 삽입 고정한 후, 지지 기둥(40)의 하중 지지력을 보강하는 캡 빔(50)이 설치되는 것이 바람직하다. 이와 마찬가지로 건물벽(100), 건물보(200, 200´, 200˝) 및 건물슬래브(300, 300´, 300˝)를 축조한 후, 건물벽(100)에 앵커 빔(91)을 매설하고, 건물벽(100)을 인장 지지하는 앵커(63)의 양단부를 앵커 빔(91) 및 주변 지반(10´)에 각각 고정하여 건물벽 구조체의 하중 지지력을 보강하는 것이 바람직하다.Moreover, it is preferable that the cap beam 50 which reinforces the load bearing force of the support pillar 40 after the support pillar 40 is inserted and fixed to the hole 30 is provided. Similarly, after constructing the building wall 100, the building beams 200, 200 ′, 200 ˝ and the building slabs 300, 300 ′, 300 ˝, the anchor beam 91 is embedded in the building wall 100. Both ends of the anchor 63 for tension-supporting the building wall 100 are preferably fixed to the anchor beam 91 and the surrounding ground 10 'to reinforce the load bearing force of the building wall structure.

이상에서 본 발명에 따른 실시예들이 설명되었으나, 이는 예시적인 것에 불과하며, 당해 분야에서 통상적 지식을 가진 자라면 이로부터 다양한 변형 및 균등한 범위의 실시예가 가능하다는 점을 이해할 것이다. 따라서, 본 발명의 진정한 기술적 보호 범위는 다음의 특허청구범위에 의해서 정해져야 할 것이다.Although embodiments according to the present invention have been described above, these are merely exemplary, and it will be understood by those skilled in the art that various modifications and equivalent embodiments of the present invention are possible therefrom. Therefore, the true technical protection scope of the present invention will be defined by the following claims.

도 1 내지 도 10은 본 발명의 흙막이 겸용 건물벽 구조체의 시공 방법을 순차적으로 도시한 측단면도이다.1 to 10 is a side cross-sectional view sequentially showing a construction method of a building wall structure combined with a wall of the present invention.

<도면의 주요 부분에 대한 부호의 설명><Explanation of symbols for the main parts of the drawings>

1...부지 경계벽 10...건물 지반1 ... site boundary wall 10 ... building ground

10´...주변 지반 30...구멍10´ ... Ground 30 ... hole

31...굴착/삽입 장비 40...지지 기둥31 Excavation / insertion equipment 40 Support columns

50...캡 빔(cap beam) 63...앵커(anchor)50 ... cap beam 63 ... anchor

91...앵커 빔(anchor beam) 92...스터드 볼트(stud bolt)91 Anchor beam 92 Stud bolt

93...철근 100...건물벽93 Reinforced 100 Building Wall

200, 200´, 200˝...건물보200, 200´, 200˝ ... building

300, 300´, 300˝...건물슬래브(slab)300, 300´, 300˝ ... building slab

Claims (10)

건물이 신축될 건물 지반과 상기 건물 지반에 인접한 주변 지반의 부지 경계에 구멍을 천공한 다음 상기 구멍에 삽입 고정됨으로써, 외주의 일측이 상기 주변 지반을 지지하는 복수의 지지 기둥;A plurality of support pillars on which one side of the outer circumference supports the peripheral ground by drilling a hole in the site boundary of the building ground on which the building is to be built and the surrounding ground adjacent to the building ground and then inserting and fixing the hole in the hole; 상기 지지 기둥에 연결되어 상기 주변 지반의 흙막이 및 상기 건물의 측벽을 겸하는 건물벽;A building wall connected to the support column to serve as a soil barrier of the surrounding ground and a side wall of the building; 상기 건물벽과 일체로 연결되는 건물보 및 건물슬래브; 를 포함하는 것을 특징으로 하는 건물벽 구조체.A building beam and a building slab integrally connected with the building wall; Building wall structure comprising a. 제1항에 있어서,The method of claim 1, 상기 건물벽은, 상기 지지 기둥이 삽입 고정된 다음 상기 건물 지반을 굴착하여 상기 지지 기둥의 외주의 타측을 노출시키고 상기 지지 기둥들 사이에 철근 및 콘크리트를 타설함으로써 축조되는 것을 특징으로 하는 건물벽 구조체.The building wall is constructed by inserting and fixing the support pillar, excavating the building ground to expose the other side of the outer circumference of the support pillar, and building by building reinforcing steel and concrete between the support pillars. . 제2항에 있어서,The method of claim 2, 상기 건물벽, 상기 건물보 및 상기 건물슬래브는 상기 건물 지반의 굴착 깊이가 증가됨에 따라 상기 지지 기둥의 상측부터 하측의 순서로 축조되면서 다층 구 조를 이루는 것을 특징으로 하는 건물벽 구조체.The building wall, the building beam and the building slab is a building wall structure, characterized in that the building structure in the order from the upper side to the lower side of the support pillar as the excavation depth of the building ground increases. 제3항에 있어서,The method of claim 3, 상기 지지 기둥과 수직으로 연장되어 상기 지지 기둥들의 상단부를 서로 연결하는 캡 빔; 을 더 포함하는 것을 특징으로 하는 건물벽 구조체.A cap beam extending perpendicular to the support pillar to connect upper ends of the support pillars to each other; Building wall structure, characterized in that it further comprises. 제4항에 있어서,The method of claim 4, wherein 상기 건물벽에 매설되는 앵커 빔; An anchor beam embedded in the building wall; 일단부는 상기 앵커 빔에 고정되고 타단부는 상기 주변 지반에 묻힘으로써 상기 건물벽을 인장하여 지지하는 앵커; 를 더 포함하는 것을 특징으로 하는 건물벽 구조체.An anchor fixed at one end to the anchor beam and at the other end to be buried in the surrounding ground to tension and support the building wall; Building wall structure, characterized in that it further comprises. 제5항에 있어서,The method of claim 5, 상기 지지 기둥들 사이의 이격 공간에 설치되는 배수관;A drain pipe installed in the spaced space between the support pillars; 상기 배수관을 감싸는 부직포; 를 더 포함하는 것을 특징으로 하는 건물벽 구조체.Non-woven fabric surrounding the drain pipe; Building wall structure, characterized in that it further comprises. 건물이 신축될 건물 지반과 상기 건물 지반에 인접한 주변 지반의 부지 경계에 구멍을 천공하는 단계;Drilling holes in the site boundary of the building ground on which the building is to be constructed and the surrounding ground adjacent to the building ground; 미리 준비된 지지 기둥을 상기 구멍에 삽입 고정하는 단계;Inserting and fixing a supporting pillar prepared in advance into the hole; 삽입 고정된 상기 지지 기둥의 외주의 일측이 상기 주변 지반을 지지할 때, 상기 건물 지반을 굴착하여 상기 지지 기둥의 외주의 타측을 노출시키는 단계;When one side of the outer circumference of the support pillar which is inserted and fixed supports the surrounding ground, excavating the building ground to expose the other side of the outer circumference of the support pillar; 상기 지지 기둥과 일체로 연결되도록 상기 건물의 건물벽, 건물보 및 건물슬래브를 축조하는 단계; 를 포함하는 것을 특징으로 하는 건물벽 구조체의 시공 방법.Constructing a building wall, a building beam, and a building slab of the building to be integrally connected with the support pillar; Construction method of a building wall structure comprising a. 제7항에 있어서,The method of claim 7, wherein 상기 건물벽, 건물보 및 건물슬래브는, The building wall, building beams and building slabs, 상기 건물 지반을 굴착하여 상기 지지 기둥의 외주의 타측을 노출시킨 다음 상기 지지 기둥들 사이에 철근 및 콘크리트를 타설함으로써 축조되고,It is constructed by excavating the ground of the building to expose the other side of the outer circumference of the support pillar and then placing reinforcing steel and concrete between the support pillars, 상기 건물 지반의 굴착 깊이가 증가됨에 따라 상기 지지 기둥의 상측부터 하측의 순서로 축조되면서 다층 구조를 이루는 것을 특징으로 하는 건물벽 구조체의 시공 방법.The construction method of the building wall structure, characterized in that as the excavation depth of the building ground increases in order from the upper side to the lower side of the support pillar to form a multi-layer structure. 제8항에 있어서,The method of claim 8, 상기 지지 기둥을 상기 구멍에 삽입 고정한 후, 상기 지지 기둥과 수직으로 연장되어 상기 지지 기둥들의 상단부를 서로 연결하는 캡 빔을 설치하는 단계; 를 더 포함하는 것을 특징으로 하는 건물벽 구조체의 시공 방법.Inserting and fixing the support pillar into the hole, and installing a cap beam extending perpendicular to the support pillar and connecting upper ends of the support pillars to each other; Construction method of a building wall structure further comprises a. 제9항에 있어서,10. The method of claim 9, 상기 건물벽, 건물보 및 건물슬래브를 축조한 후, 상기 건물벽에 앵커 빔을 매설하고, 상기 건물벽을 인장 지지하는 앵커의 양단부를 상기 앵커 빔 및 상기 주변 지반에 각각 고정하는 단계; 를 더 포함하는 것을 특징으로 하는 건물벽 구조체의 시공 방법.After constructing the building wall, the building beam, and the building slab, embedding an anchor beam in the building wall, and fixing both ends of the anchor for tension-supporting the building wall to the anchor beam and the surrounding ground, respectively; Construction method of a building wall structure further comprises a.
KR1020090013428A 2009-02-18 2009-02-18 Wall structure capable of earth retaining and the building method of the same KR20100094140A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090013428A KR20100094140A (en) 2009-02-18 2009-02-18 Wall structure capable of earth retaining and the building method of the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090013428A KR20100094140A (en) 2009-02-18 2009-02-18 Wall structure capable of earth retaining and the building method of the same

Publications (1)

Publication Number Publication Date
KR20100094140A true KR20100094140A (en) 2010-08-26

Family

ID=42758357

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090013428A KR20100094140A (en) 2009-02-18 2009-02-18 Wall structure capable of earth retaining and the building method of the same

Country Status (1)

Country Link
KR (1) KR20100094140A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110878631A (en) * 2019-12-02 2020-03-13 中国水利水电第八工程局有限公司 Template system for construction of side wall on side of opening and construction method
CN112695763A (en) * 2020-12-28 2021-04-23 中国水利水电第七工程局有限公司 Deep sludge stratum foundation pit excavation method
KR102312882B1 (en) 2020-12-08 2021-10-13 김재봉 Waterproof Concrete structure for ground penetration and penetration method
KR102312847B1 (en) 2020-12-08 2021-10-13 김재봉 Ground penetration spraying device for concrete buildings
KR102322702B1 (en) 2020-12-08 2021-11-04 김재봉 Construction method of ground-penetrating concrete building
KR102322689B1 (en) 2020-12-08 2021-11-08 김재봉 Ground penetration device and penetration method of concrete buildings

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110878631A (en) * 2019-12-02 2020-03-13 中国水利水电第八工程局有限公司 Template system for construction of side wall on side of opening and construction method
KR102312882B1 (en) 2020-12-08 2021-10-13 김재봉 Waterproof Concrete structure for ground penetration and penetration method
KR102312847B1 (en) 2020-12-08 2021-10-13 김재봉 Ground penetration spraying device for concrete buildings
KR102322702B1 (en) 2020-12-08 2021-11-04 김재봉 Construction method of ground-penetrating concrete building
KR102322689B1 (en) 2020-12-08 2021-11-08 김재봉 Ground penetration device and penetration method of concrete buildings
CN112695763A (en) * 2020-12-28 2021-04-23 中国水利水电第七工程局有限公司 Deep sludge stratum foundation pit excavation method

Similar Documents

Publication Publication Date Title
KR101014796B1 (en) Top-down underground construction method using prefabricated concrete column member as temporary bridge column
KR20060092552A (en) The non-strut down framework construction method of having used cast in place concrete pile
KR20140055639A (en) A execution method of architecture beam
JP2009097176A (en) Banking structure and its construction method
KR20100094140A (en) Wall structure capable of earth retaining and the building method of the same
KR101149895B1 (en) Reinforcement block for pillar of tunnel
KR101096664B1 (en) Construction method of approaching duel tunnel and pressing unit of pillar using the same
KR101182704B1 (en) Construction method of undergroud structure using PHC pile
KR101296857B1 (en) Underground structure having slab beam with enhanced bearing power against earth pressure and construction methods of the same
KR20070052109A (en) Down-ward construction method of the underground slabs and retaining walls by the slim-type composit floor system consisted of the architectural conposit deep deck and unsymmetric h-beam without preliminary wall-attached support beams and sub-beams of the floor
KR100849226B1 (en) C.i.p temporary wall and method for constructing thereof
JP2000265484A (en) CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL
KR100673475B1 (en) A pc girder member for frame of underground layer and assembling structure of frame of underground by using of it and the method therof
JP2000352296A (en) Method o constructing passage just under underground structure
KR20110136258A (en) Method of constructing underground composite outer wall structure and underground composite outer wall structure constructed by the same
KR20100115919A (en) Retaining wall and construction method thereof
KR100625115B1 (en) downward reinforced-concrete underground structure using temporary assistant columns
JP4228308B2 (en) Reinforcement method for existing floors and seismic isolation method for existing buildings
JP7275844B2 (en) WALL-LIKE STRUCTURE AND METHOD OF CONSTRUCTING WALL-LIKE STRUCTURE
KR100926323B1 (en) Constructing method for extension of underground
JPH11141140A (en) Rebuilding method of building
KR20190012368A (en) Smallcaliber composite pile wall using small drilling rig at adjacent building proximity section and construction method of the same
KR101257905B1 (en) Method for constructing foundation work
KR20210098162A (en) Under ground structure using column steel pipe wall and construction method thereof
KR100544012B1 (en) A construction method of a wall for supporting a soil

Legal Events

Date Code Title Description
A201 Request for examination
E902 Notification of reason for refusal
E601 Decision to refuse application