KR20100115919A - Retaining wall and construction method thereof - Google Patents

Retaining wall and construction method thereof Download PDF

Info

Publication number
KR20100115919A
KR20100115919A KR1020090034569A KR20090034569A KR20100115919A KR 20100115919 A KR20100115919 A KR 20100115919A KR 1020090034569 A KR1020090034569 A KR 1020090034569A KR 20090034569 A KR20090034569 A KR 20090034569A KR 20100115919 A KR20100115919 A KR 20100115919A
Authority
KR
South Korea
Prior art keywords
wall
shelf
retaining wall
lower wall
nail
Prior art date
Application number
KR1020090034569A
Other languages
Korean (ko)
Other versions
KR101077348B1 (en
Inventor
김중희
김동준
백충현
Original Assignee
(주)이랜드건설
주식회사 지오그룹이엔지
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by (주)이랜드건설, 주식회사 지오그룹이엔지 filed Critical (주)이랜드건설
Priority to KR1020090034569A priority Critical patent/KR101077348B1/en
Publication of KR20100115919A publication Critical patent/KR20100115919A/en
Application granted granted Critical
Publication of KR101077348B1 publication Critical patent/KR101077348B1/en

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls
    • E02D29/0225Retaining or protecting walls comprising retention means in the backfill
    • E02D29/0233Retaining or protecting walls comprising retention means in the backfill the retention means being anchors
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/20Securing of slopes or inclines
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D3/00Improving or preserving soil or rock, e.g. preserving permafrost soil
    • E02D3/12Consolidating by placing solidifying or pore-filling substances in the soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/20Bulkheads or similar walls made of prefabricated parts and concrete, including reinforced concrete, in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • E02D2300/0034Steel; Iron in wire form

Abstract

PURPOSE: A retaining wall and a construction method thereof are provided to prevent the activity or the conduction of a retaining wall and to prevent interference with a surrounding construction structure. CONSTITUTION: A retaining wall comprises a wall body(10), a shelf(20), and a soil nail(30). The wall stands up on the side of a cut ground(1). The shelf is installed on the rear side of the wall and is buried under the ground. The soil nail connects the wall to the ground. The wall and the shelf are composed of a reinforcing bar concrete structure. The soil nails are installed on the lower wall based on the shelf.

Description

옹벽과 그 시공방법{retaining wall and construction method thereof}Retaining wall and construction method

본 발명은 옹벽과 그 시공방법에 관한 것으로, 소일네일과 선반이 설치되어 안정성 및 시공성이 크게 향상된 옹벽과 그 시공방법에 관한 것이다.The present invention relates to a retaining wall and a construction method thereof, and to a retaining wall and a construction method of which a nail and a shelf are installed to greatly improve stability and workability.

옹벽은 토압에 저항하여 성토 또는 절토 사면을 지지함으로써 토사의 붕괴를 방지하는 벽체 구조물로서, 산지나 도로의 양 측벽 등에 많이 사용되고 있다.Retaining wall is a wall structure that prevents the collapse of soil by supporting the fill or cut slope by resisting soil pressure. It is widely used in mountain areas and both side walls of roads.

개발의 진행으로 인해 도시 건축물의 밀도가 증가되고, 부지활용의 극대화를 꾀하는 경향에 따라 건축구조물과 옹벽 사이의 거리 및 옹벽과 부지경계 사이의 거리가 점차 감소하는 추세이다.As the development progresses, the density of urban buildings increases, and the distance between the building structures and the retaining walls and the distance between the retaining walls and the site boundary gradually decrease according to the tendency to maximize the land utilization.

따라서, 종래의 일반적인 철근콘크리트옹벽(RC옹벽; reforced concrete retaining wall)이나 앵커(anchor)옹벽은 옹벽의 저판이나 앵커가 인접 건축구조물에 간섭되고 부지경계를 넘어서기 때문에 시공하기 곤란한 경우가 증가하였다.Therefore, a conventional reinforced concrete retaining wall (RC retaining wall) or anchor retaining wall has been more difficult to install because the bottom plate or anchor of the retaining wall interferes with adjacent building structures and crosses the site boundary.

또한, 일반적인 캔틸레버 양식의 옹벽에서는 저판 시공을 위해 충분한 터파기 면적이 필요하므로 굴착 토량이 크게 증가되는 단점이 있었으며, 이러한 문제점은 옹벽 설치 위치의 고저차가 클수록 심화되었다.In addition, the general cantilever style retaining wall has a disadvantage in that the excavated soil is greatly increased because a sufficient trench area is required for the bottom plate construction, and this problem is aggravated as the height difference of the retaining wall installation position increases.

또한, 옹벽의 높이가 높을 경우 토압이 크므로 토압에 저항하기 위해서는 저 판의 길이가 길어져야 하며, 영구 앵커를 설치할 경우 옹벽의 두께가 증가하는 단점이 있다.In addition, when the height of the retaining wall is high, the earth pressure is large, so the length of the bottom plate must be long in order to resist the earth pressure, and when the permanent anchor is installed, the thickness of the retaining wall is increased.

따라서, 건축구조물이나 부지경계와의 이격거리가 좁고, 고저차가 크며, 굴착 토량이 과도하여 기존의 옹벽 시공이 곤란한 곳에 보다 용이하게 시공할 수 있고, 경제적이면서 안정성이 우수한 옹벽 및 그 옹벽의 시공방법이 필요하였다.Therefore, the distance between the building structure and the site boundary is small, the height difference is big, the excavation volume is excessive, so that the existing retaining wall construction is difficult to be installed more easily, and the economic and stability retaining wall and its construction method are excellent. Was needed.

이에 본 발명은 상기와 같은 요구에 부응하여 안출된 것으로, 주변 건축구조물과 간섭되거나 이웃 부지경계를 침범할 우려가 적고, 굴착 토량이 감소되며, 시공이 용이하고, 공기 및 소요 비용이 감소되며, 옹벽의 활동이나 전도가 보다 확실하게 방지될 수 있도록 된 옹벽과 그 시공방법을 제공함에 그 목적이 있다.Accordingly, the present invention has been devised in response to the above-described demands, and less likely to interfere with neighboring building structures or invade neighboring site boundaries, reduce excavation soil, facilitate construction, and reduce air and required costs. The purpose is to provide a retaining wall and its construction method that can be more reliably prevented in the activity or fall of the retaining wall.

상기와 같은 목적을 달성하기 위한 본 발명에 따른 옹벽은,Retaining wall according to the present invention for achieving the above object,

절취된 지반의 측면에 세워진 벽체와;A wall erected on the side of the cut ground;

상기 벽체의 배면에 설치되어 상기 지반에 매립되는 선반과;A shelf installed on the rear surface of the wall and embedded in the ground;

상기 벽체를 상기 지반과 연결하는 소일네일;A nail nail connecting the wall with the ground;

을 포함한다..

상기 벽체와 선반은 일체의 철근콘크리트 구조물로 이루어진다.The wall and the shelf are made of a single reinforced concrete structure.

상기 소일네일은 상기 선반을 기준으로 하부벽체에 다수 개 설치된다.The small nails are installed on the lower wall on the basis of the shelf.

상기 벽체에서 상기 선반을 기준으로 하부벽체는 내측의 숏크리트층과 그 외측의 콘크리트층으로 이루어지고, 상기 숏크리트층에 와이어메쉬와, 그 와이어메쉬에 고정되는 연결철근과, 상기 소일네일에 장착되는 지압판과, 그 지압판을 고정하는 너트가 매립된다.The lower wall of the wall based on the shelf is made of an inner shotcrete layer and an outer concrete layer, a wire mesh to the shotcrete layer, connecting reinforcing bars fixed to the wire mesh, and a pressure plate mounted on the small nail And the nut which fixes the pressure plate is buried.

또한, 상기 콘크리트층에 상기 소일네일의 단부가 매립된다.In addition, an end portion of the small nail is embedded in the concrete layer.

또한, 상기 지압판에 스터드가 장착되고, 상기 스터드는 상기 콘크리트층에 매립된다.In addition, a stud is mounted on the pressure plate, and the stud is embedded in the concrete layer.

상기 스터드의 단부에 몸체의 반경방향으로 확장된 헤드가 형성된다.At the end of the stud is formed a radially extending head of the body.

상기 스터드는 상기 콘크리트층의 보강철근에 고정된다.The stud is fixed to the rebar of the concrete layer.

한편, 상기 옹벽을 시공하기 위한 본 발명에 따른 옹벽 시공방법은,On the other hand, the retaining wall construction method according to the present invention for constructing the retaining wall,

절취된 지반에 소일네일을 삽입하고 숏크리트층을 타설하는 소일네일링단계와;A small nailing step of inserting a small nail into the cut ground and placing a shotcrete layer;

상기 숏크리트층의 외측에 콘크리트층을 타설하여 상기 소일네일과 연결된 하부벽체를 시공하는 하부벽체 시공단계와;A lower wall construction step of constructing a lower wall connected to the small nail by pouring a concrete layer on the outside of the shotcrete layer;

상기 하부벽체의 상단과 같은 높이에 선반설치면을 마련하는 선반설치면 형성단계와;A shelf mounting surface forming step of providing a shelf mounting surface at the same height as the upper end of the lower wall;

상기 선반설치면에 상기 하부벽체와 일체로 선반 및 상부벽체를 시공하는 선반 및 상부벽체 시공단계와;A shelf and an upper wall construction step of constructing a shelf and an upper wall integrally with the lower wall on the shelf mounting surface;

상기 선반의 상부 및 상부벽체의 배면 공간을 메우는 뒷채움단계;A back filling step of filling the rear spaces of the upper and upper walls of the shelf;

를 포함한다.It includes.

상기 소일네일링단계에서 소일네일에 장착된 지압판에 스터드를 더 장착한 후, 상기 하부벽체 시공단계를 실시한다.In the small nailing step, the stud is further mounted on the pressure plate mounted on the small nail, and then the lower wall construction step is performed.

또한, 상기 소일네일링단계는 다수 개의 소일네일을 상기 지반에 삽입하며, 상기 지반의 상부에서 하부로 순차적으로 삽입한다.The small nailing step may include inserting a plurality of small nails into the ground and sequentially inserting the upper and lower portions of the ground.

상기 하부벽체 시공단계에서 하부벽체 내부에 배근되는 보강철근을 하부벽체의 상단 외부로 연장 설치하고, 이후 상기 선반 및 상부벽체 시공단계에서 선반 및 상부벽체의 보강철근을 상기 하부벽체의 보강철근에 연결하여 배근한다.In the lower wall construction step, the reinforcing bar that is installed inside the lower wall is extended and installed outside the upper end of the lower wall, and then, in the shelf and upper wall construction step, the reinforcing bar of the shelf and the upper wall is connected to the reinforcing bar of the lower wall. I'm going to work out.

상기 선반 및 상부벽체 시공단계는 일체로 제작된 거푸집에 콘크리트를 타설한다.The shelf and the upper wall construction step is to cast concrete on the integrally formed formwork.

이상 설명한 바와 같은 본 발명은, The present invention as described above,

상기 선반과 소일네일의 상호 작용에 의해 옹벽의 절취된 지반 지지력과, 활동 및 전도에 대한 안정성이 배가되므로 옹벽의 두께를 감소시킬 수 있고, 저판을 시공할 필요가 없게 되는 효과가 있다.Due to the interaction between the shelf and the nail, the retaining ground support strength of the retaining wall and the stability of the activity and the conduction are doubled, thereby reducing the thickness of the retaining wall and eliminating the need to construct the bottom plate.

따라서, 상기 저판 시공을 위한 터파기 공정이 필요 없게 됨으로써 토공에 소요되는 시간과 비용이 크게 절감되고, 공사를 보다 용이하게 진행할 수 있으며, 이로써 고저차가 큰 사면에 적용하기 유리하다.Therefore, the time and cost required for earthworks are greatly reduced by eliminating the process of digging for the low plate construction, and the construction can be more easily performed.

또한, 저판이 존재하지 않고 소일네일을 사용하므로 인접한 건축구조물과의 간섭 및 이웃 부지경계 침범의 우려가 감소하여 건축구조물 밀도가 높은 지역에 보다 용이하게 시공할 수 있다.In addition, since there is no bottom plate and a small nail is used, there is less concern about interference with neighboring building structures and invasion of neighboring site boundaries, and thus construction can be easily performed in areas with high density of building structures.

또한, 초기 공정인 소일네일링 단계가 사면의 중간 부분에서 탑-다운 방식으로 진행되므로 옹벽 설치 위치가 하부는 절토하고 상부는 성토해야 하는 지역에 보다 용이하게 시공할 수 있다.In addition, since the initial nailing step is performed in a top-down manner in the middle portion of the slope, the retaining wall installation location can be easily installed in an area where the lower part is cut and the upper part needs to be filled.

이하, 본 발명의 바람직한 실시예를 첨부된 도면을 참조하여 상세히 설명한다.Hereinafter, exemplary embodiments of the present invention will be described in detail with reference to the accompanying drawings.

도 1의 (a)는 본 발명에 따른 옹벽의 설치 상태도이고, (b)는 상기 (a)의 비교예로서 저판을 구비한 옹벽의 설치 상태도이다.FIG. 1 (a) is an installation state diagram of a retaining wall according to the present invention, and (b) is an installation state diagram of a retaining wall provided with a bottom plate as a comparative example of the above (a).

또한, 도 2의 (a)는 본 발명에 따른 옹벽의 토압 작용 상태도이고, (b)는 상기 (a)의 비교예로서 저판을 구비한 옹벽의 토압 작용 상태도이다.2 (a) is a state of earth pressure action of the retaining wall according to the present invention, and (b) is a state of earth pressure action of the retaining wall provided with a bottom plate as a comparative example of (a).

도 1의 (a)와 같이, 본 발명에 따른 옹벽은 절취된 지반(1)의 측면에 세워진 벽체(10)와, 상기 벽체(10)의 배면(상기 지반(1)측 면)에 설치된 선반(20)과, 상기 벽체(10)의 선반(20) 하부 부분을 지반(1)과 연결하는 소일네일(30)을 포함한다.(이하, 상기 벽체(10) 중 선반(20)의 하부 부분을 하부벽체(10a), 선반(20)의 상부 부분을 상부벽체(10b)로 지칭한다.)As shown in Figure 1 (a), the retaining wall according to the present invention is a wall (10) erected on the side of the cut ground (1), and the shelf provided on the back surface (the ground (side side) side) of the wall (10) And a small nail 30 for connecting the lower portion of the shelf 20 of the wall 10 to the ground 1 (hereinafter, the lower portion of the shelf 20 of the wall 10). The lower wall 10a and the upper portion of the shelf 20 are referred to as the upper wall 10b.)

상기 벽체(10)는 지면(2)에 대해 수직인 상태 또는 상기 지반(1)쪽으로 소정 각도 기울어진 상태로 설치될 수 있으며, 상기 선반(20)은 지면(2)에 대해 수평으로 설치되어 상기 지반(1)에 매립된다.The wall 10 may be installed in a state perpendicular to the ground 2 or inclined at an angle toward the ground 1, and the shelf 20 may be installed horizontally with respect to the ground 2. It is embedded in the ground (1).

상기 선반(20)은 토하중을 안정적으로 지지할 있도록 상기 벽체(10)에 일체로 견고히 설치된다.The shelf 20 is integrally and firmly installed on the wall 10 so as to stably support the load.

이를 위해 상기 벽체(10)와 선반(20)은 철근콘크리트 구조물로서 일체화되는 것이 바람직하다.To this end, the wall 10 and the shelf 20 is preferably integrated as a reinforced concrete structure.

상기 소일네일(30)은 주로 이형철근(이형봉강)을 이용하며, 몸체의 대부분이 상기 지반(1)으로 삽입되어 토압을 받고, 일측 단부가 하부벽체(10a)의 내부에 매립되어 일체로 연결된다.The small nail 30 mainly uses a deformed reinforcing bar (release bar), the majority of the body is inserted into the ground (1) is subjected to earth pressure, one end is buried in the interior of the lower wall (10a) and connected integrally do.

또한, 상기 소일네일(30)은 하부벽체(10a) 전체에 걸쳐 상하방향 및 좌우방 향으로 상호 일정 간격 이격되어 다수 개 설치된다.In addition, the small nail 30 is installed in a plurality of spaced apart from each other at regular intervals in the vertical direction and the left and right directions throughout the lower wall (10a).

따라서, 본 발명에 따른 옹벽은 상기 선반(20)에 의해 상부 지반(1)의 하중이 하부로 전달되는 것이 차단되어 하부벽체(10a)에 작용하는 토압이 일차로 감소되고, 그에 더하여 상기 소일네일(30)에 의해 상기 지반(1) 즉, 원지반 자체의 전단강도가 증가되어 하부벽체(10a)에 작용하는 토압이 더욱 감소된다.(P3 〉P1+P2 ; P1=하부벽체(10a)에 작용하는 토압, P2=상부벽체(10b)에 작용하는 토압, P3= 선반(20)이 없는 상태에서 벽체(10) 전체에 작용하는 토압, 도 2참조)Therefore, in the retaining wall according to the present invention, the load of the upper ground 1 is prevented from being transmitted downward by the shelf 20 so that the earth pressure acting on the lower wall 10a is primarily reduced, and in addition, the thumbnail (30) increases the shear strength of the ground 1, that is, the ground itself, further reducing the earth pressure acting on the lower wall 10a. (P3 > P1 + P2; P1 = acting on the lower wall 10a) To earth pressure, P2 = earth pressure acting on the upper wall (10b), P3 = earth pressure acting on the entire wall (10) without the shelf (20), see Figure 2)

따라서, 본 발명에 따른 옹벽은 도 1(b)의 비교예와 같이 저판(5)을 시공하거나 벽체(10)의 두께를 두텁게 하여 자중을 증가시키지 않고도 충분한 정도의 지반(1) 지지력 및 옹벽의 활동 및 전도에 대한 안정성을 확보할 수 있게 된다.Therefore, the retaining wall according to the present invention has a sufficient degree of support force and retaining wall of the ground 1 without constructing the bottom plate 5 or increasing the thickness of the wall 10 as in the comparative example of FIG. You will be able to secure stability in activities and evangelism.

따라서, 본 발명에 따른 옹벽 시공시에는 상기 저판(5) 시공을 위한 터파기 공정이 필요 없어 굴착 토량이 크게 감소됨으로써 토공에 소요되는 시간과 비용이 크게 절감되고, 공사를 보다 용이하게 진행할 수 있다.Therefore, the construction of the retaining wall according to the present invention does not require the excavation process for the construction of the bottom plate 5, so the excavated soil is greatly reduced, thereby greatly reducing the time and cost required for earthwork, and facilitates the construction. .

또한, 본 발명에 따른 옹벽은 상기 저판(5)이 존재하지 않아 저판(5)과 인접한 지하 건축구조물의 간섭 문제를 고려할 필요가 없게 되므로 옹벽을 부지경계에 근접하여 설치할 수 있다. 따라서, 건축구조물과 부지경계와의 이격거리가 짧은 장소에 시공하기 유리하다.In addition, the retaining wall according to the present invention can be installed in close proximity to the site boundary because the bottom plate 5 does not exist so that it is not necessary to consider the interference problem of the underground building structure adjacent to the bottom plate 5. Therefore, it is advantageous to install in places where the distance between the building structure and the site boundary is short.

또한, 상기 소일네일(30)은 영구앵커에 비교할 때 그 길이가 짧아 부지경계를 넘어 이웃 부지로 침입될 우려가 적으므로 옹벽과 부지경계와의 이격거리가 짧은 장소에 시공하기 유리하다.In addition, the small nail 30 has a shorter length than that of the permanent anchor, so it is less likely to break into the neighboring site beyond the site boundary, and thus, the small nail 30 is advantageously installed in a place having a short separation distance between the retaining wall and the site boundary.

즉, 개발의 진행에 따라 건축구조물이 과밀해지고 있는 현재에 보다 활용성이 높다.In other words, it is more usable in the present time when the construction structure is becoming dense as development progresses.

또한, 상기 지반(1) 상부면과 사면 하부 지면(2)의 고저차가 큰 경우에도 본 발명에 따른 옹벽은 길이가 긴 저판(5)을 시공할 필요가 없으므로 토공량의 과도한 증가를 우려할 필요 없이 용이하게 시공할 수 있다.In addition, even if the height difference between the upper surface of the ground (1) and the lower surface of the lower surface (2) is large, the retaining wall according to the present invention does not need to construct a long bottom plate (5), so there is no need to worry about excessive increase in the earthwork volume. It can be easily constructed.

한편, 상기 하부벽체(10a)는 도 3에 도시된 바와 같이, 상기 지반(1)에 접하는 숏크리트층(11)과, 상기 숏크리트층(11)에 접하는 콘크리트층(12)으로 이루어진다.Meanwhile, as shown in FIG. 3, the lower wall 10a includes a shotcrete layer 11 in contact with the ground 1 and a concrete layer 12 in contact with the shotcrete layer 11.

상기 숏크리트층(11)의 내부에는 와이어메쉬(11a)와 이에 묶여지는 연결철근(11b)이 설치되어 강도를 보강한다.The inside of the shotcrete layer 11 is provided with a wire mesh 11a and a connecting reinforcing bar 11b tied thereto to reinforce the strength.

또한, 상기 콘크리트층(12)의 내부에는 가로 및 세로로 보강철근(12a)이 배근되어 이후 타설되는 콘크리트와 결합하여 철근콘크리트 구조물을 이룬다.In addition, the inside of the concrete layer 12 is reinforced horizontally and vertically reinforced reinforcement (12a) to form a reinforced concrete structure by combining with the concrete to be poured later.

상기 연결철근(11b)의 외측으로 직사각형 판재인 지압판(31)이 배치되고, 상기 지압판(31)을 관통한 소일네일(30)에 라이너스크류(32)를 매개로 반구형의 너트(33)가 체결되어 지압판(31)이 와이어메쉬(11a) 쪽으로 가압되는 상태로 소일네일(30)에 고정된다.A pressure plate 31, which is a rectangular plate, is disposed on the outside of the connecting reinforcing bar 11b, and the hemispherical nut 33 is fastened to the small nail 30 penetrating the pressure plate 31 through the liner screw 32. And the pressure plate 31 is fixed to the small nail 30 in a state where the pressure plate 31 is pressed toward the wire mesh 11a.

상기 지압판(31)과 너트(33)도 숏크리트층(11)에 매립된다.The pressure plate 31 and the nut 33 are also embedded in the shotcrete layer 11.

또한, 상기 너트(33) 외측으로 돌출된 소일네일(30)의 단부는 상기 콘크리트층(12)의 내부에 매립되어 소일네일(30)과 하부벽체(10a)의 결합력을 보강한다.In addition, an end portion of the nail nail 30 protruding to the outside of the nut 33 is embedded in the concrete layer 12 to reinforce the coupling force between the small nail 30 and the lower wall 10a.

또한, 상기 지압판(31)에는 스터드(stud;34)가 장착되는데, 상기 스터드(34) 는 일단부에 몸체의 반경방향으로 확장된 헤드(34a)가 형성되어 있다.In addition, a stud (34) is mounted to the pressure plate (31), the stud (34) has a head (34a) extending in the radial direction of the body at one end.

상기 스터드(34)의 타단부에는 수나사가 형성되어 상기 지압판(31)에 형성된 탭홀에 나사체결되거나 또는 수나사가 형성되지 않은 단순 원기둥 형상으로 이루어져 상기 지압판(31)에 용접 고정된다.A male screw is formed at the other end of the stud 34 so as to be screwed into a tap hole formed in the pressure plate 31 or have a simple cylindrical shape in which the male screw is not formed, and is welded to the pressure plate 31.

상기 스터드(34)는 상기 콘크리트층(12)에 매립되는데, 스터드(34)의 헤드(34a)가 보강철근(12a)의 외측에 위치되는 정도로 스터드(34)의 몸체 대부분이 상기 콘크리트층(12)에 매립되며(지압판(31)측 일부는 숏크리트층(11)내에 위치된다.), 상기 헤드(34a)가 스터드(34)의 길이방향에 대해 반경방향으로 돌출된 형상을 가지고 있어서 콘크리트층(12)과 보다 견고하게 결합된다.The stud 34 is embedded in the concrete layer 12, and the majority of the body of the stud 34 is located in the concrete layer 12 such that the head 34a of the stud 34 is located outside the reinforcing bar 12a. (Part of the pressure plate 31 side is located in the shotcrete layer 11), and the head 34a has a shape protruding radially with respect to the longitudinal direction of the stud 34 so that the concrete layer ( 12) more firmly combined.

또한, 상기 스터드(34)는 상기 보강철근(12a)에 철사 등으로 묶여져 고정될 수 있다. 따라서, 콘크리트층(12)과의 결합력을 더 보강할 수 있으며, 콘크리트 타설시 타설압에 대항하여 설치 위치를 견고히 유지할 수 있다.In addition, the stud 34 may be fixed to the reinforcing bar (12a) by binding to a wire or the like. Therefore, the bonding force with the concrete layer 12 can be further reinforced, and the installation position can be firmly maintained against the placing pressure when placing concrete.

한편, 상기 보강철근(12a)은 하부벽체(10a)의 상부로 연장 돌출되어 선반(20) 및 상부벽체(10b)의 내부로 삽입되어 연결된다.On the other hand, the reinforcing bar (12a) is extended and protruded to the upper portion of the lower wall (10a) is inserted into the shelf 20 and the upper wall (10b) is connected to.

즉, 상기 선반(20) 및 상부벽체(10b) 역시 철근 콘크리트 구조물로서 전술한 바와 같이 하부벽체(10a)와 일체로 시공하기 위하여 상기 하부벽체(10a)의 상부로 돌출된 보강철근(12a)은 선반(20) 및 상부벽체(10b)의 내부에 배근되는 보강철근과 연결되고, 선반(20) 및 상부벽체(10b)를 이루는 콘크리트의 내부에 매립된다.That is, the reinforcing bar 12a protruding to the upper part of the lower wall 10a in order to construct the shelf 20 and the upper wall 10b integrally with the lower wall 10a as described above is also a reinforced concrete structure. It is connected to the reinforcing steel bars that are placed in the interior of the shelf 20 and the upper wall 10b, and embedded in the concrete forming the shelf 20 and the upper wall 10b.

이제, 도 4 내지 도 17을 참조하여 상기 옹벽의 시공방법에 대해 설명한다.Now, the construction method of the retaining wall will be described with reference to FIGS. 4 to 17.

본 발명에 따른 옹벽 시공방법은 도 4의 블록도와 같이, 절취된 지반(1)에 다수의 소일네일(30)을 설치하고 그 사면을 덮는 숏크리트층(11)을 형성하는 소일네일링단계(S1)와, 상기 숏크리트층(11)의 외측에 콘크리트층(12)을 형성하여 상기 소일네일(30)과 연결된 하부벽체(10a)를 시공하는 하부벽체 시공단계(S2), 상기 하부벽체(10a)의 상단과 같은 높이에 선반설치면을 마련하는 선반설치면 형성단계(S3), 상기 선반설치면에 상기 하부벽체(10a)와 일체로 선반(20) 및 상부벽체(10b)를 시공하는 선반 및 상부벽체 시공단계(S4)와, 상기 선반(20)의 상부 및 상부벽체(10b)의 배면 공간을 메우는 뒷채움단계(S5)를 포함한다.In the retaining wall construction method according to the present invention, as shown in the block diagram of FIG. 4, a small nailing step of installing a plurality of small nails 30 on the cut ground 1 and forming the shotcrete layer 11 covering the slopes (S1) ) And a lower wall construction step (S2) of forming the concrete layer 12 on the outside of the shotcrete layer 11 to construct the lower wall 10a connected to the small nail 30, and the lower wall 10a. Shelf mounting surface forming step (S3) to provide a shelf mounting surface at the same height as the top of the shelf, the shelf 20 and the shelf to construct the upper wall (10b) integrally with the lower wall (10a) on the shelf mounting surface and The upper wall construction step (S4), and the back filling step (S5) of filling the rear space of the upper and upper wall (10b) of the shelf (20).

상기 소일네일링단계(S1)는 도 5 내지 도 11에서 알 수 있는 바와 같이, 탑-다운(TOP-DOWN) 방식으로 순차적으로 실시된다.As shown in FIGS. 5 to 11, the small nailing step S1 is sequentially performed in a TOP-DOWN manner.

도 5는 옹벽이 설치될 장소를 개략적으로 도시한 것으로, 1은 절취된 지반이고 2는 지면이다.Fig. 5 schematically shows the place where the retaining wall is to be installed, where 1 is cut ground and 2 is ground.

먼저, 도 6와 같이 상기 지반(1)의 사면 중간 부분, 즉, 선반(20)이 설치될 위치에 1단 소일네일(30a)을 설치한다. 이와 같이 최상단의 1단 소일네일(30a)을 설치한 후에는 도 7과 같이 하방으로 한 단계 더 굴착한 후, 2단 소일네일(30b)을 설치한다.First, as shown in FIG. 6, a one-stage small nail 30a is installed at a middle portion of the slope of the ground 1, that is, the position at which the shelf 20 is to be installed. In this way, after the uppermost single-stage short nail 30a is installed, it is further excavated downward as shown in FIG. 7, and then, the second-stage small nail 30b is installed.

이어, 도 8 내지 도 10과 같이 설치위치가 지면(2)에 인접할 때까지 동일한 방식으로 3단, 4단, 5단 소일네일(30c, 30d,30e)의 설치를 반복한다.(도면에는 5단 소일네일까지 설치되는 예를 도시하였으나 단수는 옹벽 설계에 따라 증감된다.)Subsequently, the three-stage, four-stage, and five-stage small nails 30c, 30d, and 30e are repeatedly installed in the same manner until the installation position is adjacent to the ground 2, as shown in FIGS. An example of installing up to five stages of nails is shown, but the number of stages is increased or decreased according to the retaining wall design.)

한편, 상기 소일네일링단계(S1)에서는 각 단의 소일네일 설치시마다 숏크리 트 타설이 이루어진다.On the other hand, in the small nailing step (S1), shotcrete pouring is performed every time the small nails of each stage are installed.

소일네일링 공정을 간단히 설명하면 다음과 같다.(상세 구성은 도 3 참조.) 먼저, 상기 지반(1)의 면 정리를 한 후에 수직면에 1차 숏크리트를 타설한다. 이후 천공작업을 실시하고, 그 구멍으로 소일네일(30)을 삽입하고 1차 그라우팅을 실시한다.The small nailing process will be briefly described as follows. (See FIG. 3 for a detailed configuration.) First, the surface of the ground 1 is arranged, and then primary shotcrete is placed on a vertical surface. Then, the drilling operation is carried out, the nail nail 30 is inserted into the hole and the first grouting is performed.

상기와 같이 형성된 1차 숏크리트층에 와이어메쉬(11a)와 연결철근(11b)을 설치하고, 상기 소일네일(30)의 단부측에 지압판(31)을 설치한다.The wire mesh 11a and the connecting reinforcing bar 11b are installed on the primary shotcrete layer formed as described above, and the pressure plate 31 is provided on the end side of the small nail 30.

이후, 2차 숏크리트를 타설하고, 미리 심어놓은 그라우팅관을 이용하여 2차 그라우팅을 실시하면 한 단의 소일네일링이 종료된다.Subsequently, when the second shotcrete is poured and the second grouting is performed using a pre-planted grouting tube, one stage of nailing is finished.

이후, 다음 단의 소일네일링을 위해 하방으로 굴착 및 면 정리 공정을 반복 시행한다.Thereafter, the excavation and surface finishing process is repeated for the next stage of nailing.

상기와 같이, 각 단의 소일네일을 설치할 때마다 1,2차 숏크리트 타설이 이루어짐으로써 상기 소일네일링단계(S1)이 모두 끝나면 도 10과 같이 상기 지반(1)에 숏크리트층(11)이 시공되어 있게 된다.As described above, the first and second shotcrete pouring is performed every time the nails of each stage are installed, so that the shotcrete layer 11 is constructed on the ground 1 as shown in FIG. It becomes.

한편, 소일네일(30)과 하부벽체(10a)의 결합상태를 보다 견고히 하기 위하여 상기 지압판(31)에 복수의 스터드(34)를 설치할 수 있다. 도 3을 참조로 설명한 바와 같이, 스터드(34)는 상기 지압판(31)에 나사 체결되거나 용접 고정될 수 있으며, 단부에 원판형의 헤드(34a)가 형성되어 있다.On the other hand, a plurality of studs 34 may be installed on the pressure plate 31 in order to further secure the coupling state between the small nail 30 and the lower wall 10a. As described with reference to FIG. 3, the stud 34 may be screwed or welded to the pressure plate 31, and a disk-shaped head 34a is formed at an end thereof.

따라서, 상기 소일네일링단계(S1)가 종료되었을 때 상기 와이어메쉬(11a)와 연결철근(11b), 지압판(31), 지압판(31)을 고정하는 너트(33)는 숏크리트층(11)의 내부에 매립되고, 소일네일(30)의 단부와 상기 스터드(34)는 숏크리트층(11)의 외부로 돌출되어 있게 된다.Therefore, the nut 33 for fixing the wire mesh 11a, the connecting reinforcing bar 11b, the pressure plate 31, and the pressure plate 31 when the small nailing step S1 is completed is made of the shotcrete layer 11. Buried in the interior, the end of the nail nail 30 and the stud 34 is protruded to the outside of the shotcrete layer (11).

상기 하부벽체시공단계(S2)에서는 도 12와 같이, 상기 숏크리트층(11)의 외측에 보강철근(12a)을 배근하고, 거푸집(13)을 설치한다. 이때 상기 보강철근(12a)은 거푸집(13)의 상부로 연장 돌출되어 하부벽체(10a)와 선반(20) 및 상부벽체(10b)를 연결할 수 있도록 되어 있다.In the lower wall construction step (S2), as shown in FIG. 12, the reinforcing bar 12a is disposed outside the shotcrete layer 11 and a formwork 13 is installed. At this time, the reinforcing bar (12a) is extended to the upper portion of the formwork 13 to connect the lower wall (10a) and the shelf 20 and the upper wall (10b).

이어 도 13과 같이 상기 거푸집(13)에 콘크리트를 타설, 양생하여 하부벽체(10a)를 시공한다. 이때, 상기 거푸집(13)으로서 내측면에 소정의 문양을 가진 문양 거푸집을 설치할 수 있으며, 이 경우 옹벽의 외관에 미감을 부여할 수 있다.Subsequently, as shown in FIG. 13, concrete is poured into the formwork 13 to construct the lower wall 10a. At this time, as the formwork 13 can be provided with a pattern formwork having a predetermined pattern on the inner surface, in this case it can give aesthetics to the appearance of the retaining wall.

상기와 같이 하부벽체(10a)의 시공이 끝난 후에는 도 14와 같이, 상기 선반설치면형성단계(S3)를 실시한다.After the construction of the lower wall (10a) as described above, as shown in Figure 14, the shelf mounting surface forming step (S3) is carried out.

상기 선반설치면형성단계(S3)에서는 상기 하부벽체(10a)의 상단과 동일한 높이에서 상기 지반(1)의 내측으로 굴착하고 정지(整地)하여 평평한 선반설치면(3)을 형성한다.In the shelving mounting surface forming step (S3) is excavated and stopped to the inside of the ground (1) at the same height as the upper end of the lower wall (10a) to form a flat shelving mounting surface (3).

이어, 도 15와 같이 상기 선반 및 상부벽체 시공단계(S4)를 실시한다.Subsequently, the shelf and the upper wall construction step S4 are performed as shown in FIG. 15.

상기 하부벽체(10a)의 상단면과 상기 선반설치면(3)에 선반(20) 및 상부벽체(10b)의 보강철근(20a, 12b)을 일체로 배근하고, 이들의 거푸집(21,14)도 일체로 설치한다.The reinforcing bars 20a and 12b of the shelf 20 and the upper wall 10b are integrally disposed on the upper end surface of the lower wall 10a and the shelving mounting surface 3, and the formwork 21 and 14 thereof. Also install integrally.

이때 상기 하부벽체(10a)의 상단면으로 돌출된 하부벽체(10a)의 보강철근(12a)은 상기 거푸집(21,14)의 내부로 유입되며, 상기 선반(20) 및 상부벽 체(10b)의 보강철근(20a, 12b)과 연결된다.At this time, the reinforcing bar 12a of the lower wall 10a protruding to the upper surface of the lower wall 10a is introduced into the molds 21 and 14, and the shelf 20 and the upper wall 10b. Is connected to the reinforcing bars 20a and 12b.

상기 거푸집(21,14) 설치 후에는 도 16과 같이 상기 거푸집(21,14)의 내부로 콘크리트를 동시에 타설, 양생하여 선반(20)과 상부벽체(10b)를 시공한다.After the molds 21 and 14 are installed, concrete is poured and cured into the molds 21 and 14 at the same time, thereby constructing the shelf 20 and the upper wall 10b.

상기 선반(20)과 상부벽체(10b)가 소정 강도 이상으로 굳어지면 거푸집(21,14)을 제거하고 마지막으로 도 17과 같이 상기 뒷채움단계(S5)를 실시한다.When the shelf 20 and the upper wall 10b is hardened to a predetermined strength or more, the molds 21 and 14 are removed, and finally, the back filling step S5 is performed as shown in FIG. 17.

즉, 상기 선반(20)의 상부 및 상부벽체(10b)의 배면 공간에 흙을 채우고 다진다.That is, the soil is filled and compacted in the rear space of the upper and upper walls 10b of the shelf 20.

이상과 같은 단계(S1 ~ S5)들을 실시함으로써 벽체(10)가 소일네일(30)에 연결되고 배면에 선반(20)을 갖춘 본 발명에 따른 옹벽을 시공할 수 있게 된다.By carrying out the above steps (S1 ~ S5) it is possible to construct the retaining wall according to the invention the wall 10 is connected to the small nail 30 and the shelf 20 on the back.

한편, 본 발명에 따른 옹벽 시공방법은 상기 소일네일링단계(S1)가 상부에서 하부로 진행되는 탑-다운 방식으로 실시되고, 선반(20) 상부 및 상부벽체(10b)의 배면 공간에 뒷채움을 실시해야 하므로 옹벽 설치 위치가 옹벽을 기준으로 상부는 성토하고 하부는 절토해야 하는 산지와 같은 경우에 매우 유리하게 적용될 수 있다.On the other hand, the retaining wall construction method according to the present invention is carried out in a top-down manner in which the small nailing step (S1) proceeds from the top to the bottom, and backfilling the rear space of the shelf 20 and the upper wall (10b) Since the retaining wall installation position is based on the retaining wall, it can be very advantageously applied to a mountainous area where the upper part is to be filled and the lower part is to be cut.

도 1의 (a)는 본 발명에 따른 옹벽의 설치 상태도이고, (b)는 상기 (a)의 비교예로서 저판을 구비한 옹벽의 설치 상태도,(A) is an installation state diagram of the retaining wall according to the present invention, (b) is an installation state diagram of the retaining wall provided with a bottom plate as a comparative example of (a),

도 2의 (a)는 본 발명에 따른 옹벽의 토압 작용 상태도이고, (b)는 상기 (a)의 비교예로서 저판을 구비한 옹벽의 토압 작용 상태도,(A) is a earth pressure action state diagram of the retaining wall according to the present invention, (b) is a earth pressure action state diagram of the retaining wall provided with a bottom plate as a comparative example of (a),

도 3은 본 발명에 따른 옹벽의 하부벽체 상세 단면도,3 is a detailed cross-sectional view of the lower wall of the retaining wall according to the present invention;

도 4는 본 발명에 따른 옹벽 시공방법의 블록도,4 is a block diagram of a retaining wall construction method according to the present invention;

도 5 내지 도 17은 본 발명에 따른 옹벽 시공 방법의 실시 과정을 도시한 도면이다.5 to 17 is a view showing the implementation of the retaining wall construction method according to the present invention.

*도면의 주요 부분에 대한 부호의 설명** Description of the symbols for the main parts of the drawings *

1 : 지반 2 : 지면1: Ground 2: Ground

3 : 선반설치면 10 : 벽체3: shelf mounting surface 10: wall

10a : 하부벽체 10b : 상부벽체10a: lower wall 10b: upper wall

11 : 숏크리트층 11a : 와이어메쉬11: shotcrete layer 11a: wire mesh

12 : 콘크리트층 12a : 보강철근12: concrete layer 12a: reinforcing bars

20 : 선반 30 : 소일네일20: shelf 30: thumbnail

31 : 지압판 34 : 스터드31: pressure plate 34: stud

Claims (13)

절취된 지반의 측면에 세워진 벽체와;A wall erected on the side of the cut ground; 상기 벽체의 배면에 설치되어 상기 지반에 매립되는 선반과;A shelf installed on the rear surface of the wall and embedded in the ground; 상기 벽체를 상기 지반과 연결하는 소일네일;A nail nail connecting the wall with the ground; 을 포함하는 옹벽.Retaining wall comprising a. 청구항 1에 있어서,The method according to claim 1, 상기 벽체와 선반은 일체의 철근콘크리트 구조물인 것을 특징으로 하는 옹벽.Retaining wall, characterized in that the wall and the shelf is an integral reinforced concrete structure. 청구항 1에 있어서,The method according to claim 1, 상기 소일네일은 상기 선반을 기준으로 하부벽체에 다수 개 설치된 것을 특징으로 하는 옹벽.Retaining wall, characterized in that the plurality of small nails are installed on the lower wall based on the shelf. 청구항 1에 있어서,The method according to claim 1, 상기 벽체에서 상기 선반을 기준으로 하부벽체는 내측의 숏크리트층과 그 외측의 콘크리트층으로 이루어지고, 상기 숏크리트층에 와이어메쉬와, 그 와이어메쉬에 고정되는 연결철근과, 상기 소일네일에 장착되는 지압판과, 그 지압판을 고정하는 너트가 매립된 것을 특징으로 하는 옹벽.The lower wall of the wall based on the shelf is made of an inner shotcrete layer and an outer concrete layer, a wire mesh to the shotcrete layer, connecting reinforcing bars fixed to the wire mesh, and a pressure plate mounted on the small nail And a nut for fixing the pressure plate is embedded. 청구항 1에 있어서,The method according to claim 1, 상기 벽체에서 상기 선반을 기준으로 하부벽체는 내측의 숏크리트층과 그 외측의 콘크리트층으로 이루어지고, 상기 콘크리트층에 상기 소일네일의 단부가 매립된 것을 특징으로 하는 옹벽.Retaining wall, characterized in that the lower wall on the basis of the shelf in the wall is composed of a shotcrete layer of the inside and the concrete layer of the outside, the end of the nail nail is embedded in the concrete layer. 청구항 1에 있어서,The method according to claim 1, 상기 벽체에서 상기 선반을 기준으로 하부벽체는 내측의 숏크리트층과 그 외측의 콘크리트층으로 이루어지고, 상기 소일네일의 단부측에 지압판이 고정되고, 상기 지압판에 스터드가 장착되며, 상기 스터드는 상기 콘크리트층에 매립된 것을 특징으로 하는 옹벽.In the wall, the lower wall is composed of an inner shotcrete layer and an outer concrete layer based on the shelf, and a pressure plate is fixed to an end side of the small nail, and a stud is mounted on the pressure plate, and the stud is mounted on the concrete. Retaining wall, characterized in that embedded in the floor. 청구항 6에 있어서,The method according to claim 6, 상기 스터드의 단부에 몸체의 반경방향으로 확장된 헤드가 형성된 것을 특징으로 하는 옹벽.Retaining wall, characterized in that the head extending in the radial direction of the body at the end of the stud. 청구항 6에 있어서,The method according to claim 6, 상기 스터드가 상기 콘크리트층의 보강철근에 고정된 것을 특징으로 하는 옹벽.Retaining wall, characterized in that the stud is fixed to the reinforcement of the concrete layer. 절취된 지반에 소일네일을 삽입하고 숏크리트층을 타설하는 소일네일링단계와;A small nailing step of inserting a small nail into the cut ground and placing a shotcrete layer; 상기 숏크리트층의 외측에 콘크리트층을 타설하여 상기 소일네일과 연결된 하부벽체를 시공하는 하부벽체 시공단계와;A lower wall construction step of constructing a lower wall connected to the small nail by pouring a concrete layer on the outside of the shotcrete layer; 상기 하부벽체의 상단과 같은 높이에 선반설치면을 마련하는 선반설치면 형성단계와;A shelf mounting surface forming step of providing a shelf mounting surface at the same height as the upper end of the lower wall; 상기 선반설치면에 상기 하부벽체와 일체로 선반 및 상부벽체를 시공하는 선반 및 상부벽체 시공단계와;A shelf and an upper wall construction step of constructing a shelf and an upper wall integrally with the lower wall on the shelf mounting surface; 상기 선반의 상부 및 상부벽체의 배면 공간을 메우는 뒷채움단계;A back filling step of filling the rear spaces of the upper and upper walls of the shelf; 를 포함하는 옹벽 시공방법.Retaining wall construction method comprising a. 청구항 9에 있어서,The method according to claim 9, 상기 소일네일링단계에서 소일네일에 장착된 지압판에 스터드를 더 장착한 후, 상기 하부벽체 시공단계를 실시하는 것을 특징으로 하는 옹벽 시공방법.Retaining wall construction method characterized in that for further mounting the stud on the pressure plate mounted on the small nail in the small nailing step, the lower wall construction step. 청구항 9에 있어서,The method according to claim 9, 상기 소일네일링단계에서는 다수 개의 소일네일을 상기 지반에 삽입하며, 상기 지반의 상부에서 하부로 순차적으로 삽입되는 것을 특징으로 하는 옹벽 시공방법.In the small nailing step, a plurality of small nails are inserted into the ground, retaining wall construction method, characterized in that inserted sequentially from the top to the bottom of the ground. 청구항 9에 있어서,The method according to claim 9, 상기 하부벽체 시공단계에서 하부벽체 내부에 배근되는 보강철근을 하부벽체의 상단 외부로 연장 설치하고, 이후 상기 선반 및 상부벽체 시공단계에서 선반 및 상부벽체의 보강철근을 상기 하부벽체의 보강철근에 연결하여 배근하는 것을 특징으로 하는 옹벽 시공방법.In the lower wall construction step, the reinforcing bar extending inside the lower wall is installed to extend outside the upper end of the lower wall, and then the reinforcing bar of the shelf and the upper wall is connected to the reinforcing bar of the lower wall in the shelf and upper wall construction step. Retaining wall construction method characterized in that the reinforcement. 청구항 9에 있어서,The method according to claim 9, 상기 선반 및 상부벽체 시공단계는 일체로 제작된 거푸집에 콘크리트를 타설하는 것을 특징으로 하는 옹벽 시공방법.Retaining wall construction method characterized in that the shelf and the upper wall construction step is to cast concrete into the integrally formed formwork.
KR1020090034569A 2009-04-21 2009-04-21 retaining wall and construction method thereof KR101077348B1 (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
KR1020090034569A KR101077348B1 (en) 2009-04-21 2009-04-21 retaining wall and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
KR1020090034569A KR101077348B1 (en) 2009-04-21 2009-04-21 retaining wall and construction method thereof

Publications (2)

Publication Number Publication Date
KR20100115919A true KR20100115919A (en) 2010-10-29
KR101077348B1 KR101077348B1 (en) 2011-10-26

Family

ID=43134630

Family Applications (1)

Application Number Title Priority Date Filing Date
KR1020090034569A KR101077348B1 (en) 2009-04-21 2009-04-21 retaining wall and construction method thereof

Country Status (1)

Country Link
KR (1) KR101077348B1 (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106480880A (en) * 2015-08-28 2017-03-08 上海勘测设计研究院有限公司 Recoverable soil nailing and the construction method using recoverable soil nail
KR20200040518A (en) * 2018-10-10 2020-04-20 주식회사 알지엘텍 Self-standing Form System for Constructing Anchored Retaining Walls and Anchored Retaining Walls Constructing Method Using the Same
US10676890B2 (en) 2016-03-30 2020-06-09 Robert Gordon McIntosh Retaining wall system, method of supporting same, and kit for use in constructing same
USD895153S1 (en) 2018-10-05 2020-09-01 Pacific Prebenched Ltd. Block for a retaining wall
KR102644475B1 (en) * 2022-09-26 2024-03-06 국립군산대학교산학협력단 Composite retaining wall construction method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100710850B1 (en) * 2006-04-13 2007-04-23 주식회사 우일엔지니어링 Cantilever retaining wall having ledge with prestressed tendon

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106480880A (en) * 2015-08-28 2017-03-08 上海勘测设计研究院有限公司 Recoverable soil nailing and the construction method using recoverable soil nail
US10676890B2 (en) 2016-03-30 2020-06-09 Robert Gordon McIntosh Retaining wall system, method of supporting same, and kit for use in constructing same
USD895153S1 (en) 2018-10-05 2020-09-01 Pacific Prebenched Ltd. Block for a retaining wall
KR20200040518A (en) * 2018-10-10 2020-04-20 주식회사 알지엘텍 Self-standing Form System for Constructing Anchored Retaining Walls and Anchored Retaining Walls Constructing Method Using the Same
KR102644475B1 (en) * 2022-09-26 2024-03-06 국립군산대학교산학협력단 Composite retaining wall construction method

Also Published As

Publication number Publication date
KR101077348B1 (en) 2011-10-26

Similar Documents

Publication Publication Date Title
US6280121B1 (en) Reinforced retaining wall
KR101652163B1 (en) Concrerte pannel for retaining wall and method for constructing retaining wall using the same
JP4599384B2 (en) Embankment structure and construction method thereof
KR101103142B1 (en) Retaining wall structure and construction method of the retaining wall structure
JP2016515173A (en) Precast concrete retaining wall
KR101077348B1 (en) retaining wall and construction method thereof
CN110924433A (en) Design method of subway foundation pit foot-hanging pile enclosure structure in upper-soft lower-hard rock stratum
KR20130006420A (en) Method of constructing underground structure to be newly built
KR20140013497A (en) Method for constructing block type reinforced retaining wall in cut site
KR101373674B1 (en) Precast self-supported retaining wall using pile and construction method therefor
KR101182704B1 (en) Construction method of undergroud structure using PHC pile
KR20100094140A (en) Wall structure capable of earth retaining and the building method of the same
KR101211469B1 (en) Retaining wall structure having prefabricated block and method for constructing retaining wall using the same
KR101190739B1 (en) Method of Constructing Underground Composite Outer Wall Structure and Underground Composite Outer Wall Structure Constructed by the Same
KR101005351B1 (en) Prefabricated retaining wall and construction method thereof
JP2000265484A (en) CONSTRUCTION METHOD FOR UNDERGROUND STRUCTURE BY PCa PILE UNDERGROUND WALL
KR101254145B1 (en) Gravity type concrete precast modular retaining wall utilizing shear key and connected steel bar and constructing method thereof
KR101331219B1 (en) Method for constructing micro pile using reinforcing end bearing capacity
KR100854551B1 (en) The Structure of Retaining Wall Adopting the Combination of Pressing Plate and Precast Concrete Panel, And The Construction Method Thereof.
JP2000352296A (en) Method o constructing passage just under underground structure
KR102490872B1 (en) Reinforced earth retaining wall and construction method using tensile force of steel rod piles
KR100468034B1 (en) Construction Method of Reinforced Earth Retaining-Wall for using Anchoring
KR101993609B1 (en) Earth retaining structure using concrete block for the anchorage of anchor pc-strands and construction method thereof
KR20130081849A (en) Tunnel supporting structure
JP6860895B2 (en) Retaining wall and its construction method

Legal Events

Date Code Title Description
A201 Request for examination
N231 Notification of change of applicant
E902 Notification of reason for refusal
E701 Decision to grant or registration of patent right
GRNT Written decision to grant
LAPS Lapse due to unpaid annual fee